JOB CARD PACKAGE TITLE: AIC -
Fdmiu Tail Number - MSN -
FSN
VT-RTW - 11933 - 955
Fdmiu
MPD Reference Title DocType
31-36-00-710-013- FDIMU AIDS Software Load Procedure with
NONE AMM
A01 the MDDU
Job Cards Package is made of: 1 job cards.
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 1 of 2
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD PACKAGE TITLE: AIC -
Fdmiu Tail Number - MSN -
FSN
VT-RTW - 11933 - 955
Fdmiu
INTENTIONALLY LEFT BLANK
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 2 of 2
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Dec
JOB CARD
15/2024
AMM - AIC - A318/A319/A320/A321 TASK:
31-36-00-710-013-A01
31-36-00-02 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 31-36-00-710-013-A01 - FDIMU AIDS Software Load NONE
VT-RTW - 11933 - 955 Procedure with the MDDU
Fdmiu
MECH. INSP.
** ON A/C FSN 252-500, 508-850, 906-907, 910-910, 915-916, 919-999
TASK 31-36-00-710-013-A01
FDIMU AIDS Software Load Procedure with the MDDU
FIN: 10TV
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
ZONE/ACCESS ZONE DESCRIPTION
120 AVIONICS COMPARTMENT
210 CKPT,FWD COMPT BHD TO FLT COMPT
BULKHEAD
B. Referenced Information
REFERENCE DESIGNATION
Ref. Energize the Aircraft Electrical Circuits from
24-41-00-861-002-A the External Power
Ref. Energize the Aircraft Electrical Circuits from
24-41-00-861-002- the APU
A01
Ref. Energize the Aircraft Electrical Circuits from
24-41-00-861-002- Engine 1(2)
A02
** ON A/C FSN 252-500, 508-850, 906-907, 910-910, 915-916, 919-999
Ref. Test of the Flight Data Interface and
31-36-00-740-012-A Management Unit (FDIMU)
** ON A/C FSN 252-500, 508-850, 906-907, 910-910, 915-916, 919-999
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 1 of 7
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Dec
JOB CARD
15/2024
AMM - AIC - A318/A319/A320/A321 TASK:
31-36-00-710-013-A01
31-36-00-02 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 31-36-00-710-013-A01 - FDIMU AIDS Software Load NONE
VT-RTW - 11933 - 955 Procedure with the MDDU
Fdmiu
MECH. INSP.
REFERENCE DESIGNATION
Ref. Printout of the Engine/APU Hours and
31-36-00-740-015-A Cycles Stored in the Flight Data Interface
and Management Unit (FDIMU)
3. Job Set-up
** ON A/C FSN 252-400, 451-500, 551-850, 906-907, 910-910, 915-916,
919-999
PRE SB 31-1522 for A/C 252-255
SUBTASK 31-36-00-860-126-D
A. Aircraft Maintenance Configuration
(1) Energize the aircraft electrical circuits
Ref. AMM TASK 24-41-00-861-002.
(2) Do the print out of the engine and APU hours and cycles Ref.
AMM TASK 31-36-00-740-015.
NOTE: The printout gives a hard copy of this data.
NOTE: Upload of the software can erase the below data
and also set the report counters to initial condition:
- The data of the engine and APU hours and
cycles in the FDIMU
- The modifications that are done with the
MCDU menu programming.
(3) Make sure that the aircraft is in ground configuration (landing
gear compressed and all engines stopped).
(4) Make sure that 10TVMD2with 10TVSW2 are in the
writeprotected status (writeprotection ON).
NOTE: The number of disks can be different, related to the
software version.
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 2 of 7
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Dec
JOB CARD
15/2024
AMM - AIC - A318/A319/A320/A321 TASK:
31-36-00-710-013-A01
31-36-00-02 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 31-36-00-710-013-A01 - FDIMU AIDS Software Load NONE
VT-RTW - 11933 - 955 Procedure with the MDDU
Fdmiu
MECH. INSP.
** ON A/C FSN 252-500, 508-850, 906-907, 910-910, 915-916, 919-999
SUBTASK 31-36-00-865-158-A
B. Make sure that this (these) circuit breaker(s) is (are) closed:
PANEL DESIGNATION FIN LOCATION
** ON A/C FSN 252-300, 401-500, 508-750, 801-850, 906-907, 910-910,
915-916, 919-999
121VU CFDS/CFDIU/SPLY 2TW J18
121VU CFDS/CFDIU/BACK/UP 8TW J17
** ON A/C FSN 252-300, 401-500, 551-750, 801-850, 906-907, 910-910,
915-916, 919-999
121VU AIDS & RCDR/FDIMU 5TV K15
** ON A/C FSN 451-500, 951-999
121VU ADLU/SPLY 3TD J16
121VU DLRB/SPLY 5TD J15
** ON A/C FSN 252-500, 508-850, 906-907, 910-910, 915-916, 919-999
4. Procedure
** ON A/C FSN 252-400, 451-500, 551-850, 906-907, 910-910, 915-916,
919-999
PRE SB 31-1522 for A/C 252-255
SUBTASK 31-36-00-710-124-D
B. System Software Load-Procedure
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 3 of 7
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Dec
JOB CARD
15/2024
AMM - AIC - A318/A319/A320/A321 TASK:
31-36-00-710-013-A01
31-36-00-02 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 31-36-00-710-013-A01 - FDIMU AIDS Software Load NONE
VT-RTW - 11933 - 955 Procedure with the MDDU
Fdmiu
MECH. INSP.
NOTE: The standard system software package has two system
media disks. System software updates in the future can
have more than two disks in the package.
(1) It is necessary to load all disks until the loading process is
completed.
ACTION RESULT
On the overhead panel, on On the DLS display:
the Data Loading Selector
(DLS):
- Put the ON/OFF - The DB/N:XXXXXXXX
switch to the ON and PUSH NEXT/
position. PREV indications show.
- Push the NEXT or - The AIDS NOT
PREV key until the SELECTED indication
AIDS NOT shows.
SELECTED indication
shows on the display.
NOTE: The display shows
AIDS or ACMS.
- Push the SEL CTL - The AIDS SELECTED
key. indication shows.
NOTE: The display shows
AIDS or ACMS.
On the center pedestal, on On the MDDU display:
the MDDU:
- Open the floppy disk - The MDDU READY
access door. indication shows.
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 4 of 7
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Dec
JOB CARD
15/2024
AMM - AIC - A318/A319/A320/A321 TASK:
31-36-00-710-013-A01
31-36-00-02 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 31-36-00-710-013-A01 - FDIMU AIDS Software Load NONE
VT-RTW - 11933 - 955 Procedure with the MDDU
Fdmiu
MECH. INSP.
ACTION RESULT
- Put 10TVMD2 with - These indications show
10TVSW2 into the in a short time:
MDDU. It is necessary READY
to load all disks until WAIT RESPONSE
the loading process is TRANSF IN PROG.
completed.
NOTE: Each software
version has a
specified number
of disks.
NOTE: On some MDDUs,
the display shows
the BUS number
and the file sizes
between the
messages
TRANSF IN PROG
and TRANSF
COMPLETE. The
file sizes decrease
to zero during the
data loading. This
shows the
progress of the
data loading.
- Wait until the TRANSF - The TRANSF
COMPLETE indication COMPLETE indication
comes on. shows after the load
procedure is completed
correctly.
- Push the EJECT - The MDDU READY
button and remove indication shows.
10TVMD2 with
10TVSW2.
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 5 of 7
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Dec
JOB CARD
15/2024
AMM - AIC - A318/A319/A320/A321 TASK:
31-36-00-710-013-A01
31-36-00-02 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 31-36-00-710-013-A01 - FDIMU AIDS Software Load NONE
VT-RTW - 11933 - 955 Procedure with the MDDU
Fdmiu
MECH. INSP.
ACTION RESULT
- Close the floppy-disk
access door.
On the DLS panel: On the DLS display:
- Push the SEL CTL - The AIDS NOT
key. SELECTED indication
shows.
NOTE: The display shows
AIDS or ACMS.
- Set the ON/OFF
switch to the OFF
position.
On the MCDU: On the MCDU display:
- Push the MCDU - The AIDS prompt show.
MENU mode key.
** ON A/C FSN 252-400, 451-500, 551-652, 906-907, 910-910, 915-916,
919-999
PRE SB 31-1460 for A/C 252-255, 906-907, 910-910, 915-916, 919-919
PRE SB 31-1522 for A/C 252-255
SUBTASK 31-36-00-970-051-B
D. Check of the Part Number of the FDIMU Software
ACTION RESULT
On the MCDU: On the MCDU display:
- Push the line key adjacent - The AIDS page comes into
to the AIDS indication. view.
- Push the line key adjacent - The AIDS:SPECIAL FUNC/
to the REPROG page comes into
REPROGRAMMING view.
indication.
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 6 of 7
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Dec
JOB CARD
15/2024
AMM - AIC - A318/A319/A320/A321 TASK:
31-36-00-710-013-A01
31-36-00-02 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 31-36-00-710-013-A01 - FDIMU AIDS Software Load NONE
VT-RTW - 11933 - 955 Procedure with the MDDU
Fdmiu
MECH. INSP.
ACTION RESULT
- Push the line key adjacent - The AIDS:DOCUMENTARY
to the DOC DATA DATA page comes into
indication. view.
- Make sure that the FDIMU
software part-number and
FDIMU hardware part-
number are correct.
- Push the line key adjacent - The AIDS:SPECIAL FUNC/
to the RETURN indication. REPROG page comes into
view.
- Push the line key adjacent - The AIDS page comes into
to the RETURN indication. view.
** ON A/C FSN 252-500, 508-850, 906-907, 910-910, 915-916, 919-999
5. Close-up
** ON A/C FSN 252-500, 508-850, 906-907, 910-910, 915-916, 919-999
EMB SB 31-1306 for A/C 508-515
EMB SB 31-1522 for A/C 401-427
SUBTASK 31-36-00-710-126-A
A. Test(s)
(1) Do the test of the FDIMU Ref. AMM TASK 31-36-00-740-012.
© *** END OF CARD ***
JCP Title: Fdmiu CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 7 of 7
PRINT DATE: Jan 26/2025
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE