Mesurement 2

The document provides a detailed measurement sheet for L Drain and U Drain along the Poya Muhury Border Road, covering chainage from 85+00 to 85+500 on the right bank. It includes specific quantities for earth cutting, sand filling, brick work, concrete, plastering, and back filling for both L Drain and two U Drain sections. The total measurements for each category are summarized at the end, along with contact information for the proprietor.

Uploaded by

mushfiqzmn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views1 page

Mesurement 2

The document provides a detailed measurement sheet for L Drain and U Drain along the Poya Muhury Border Road, covering chainage from 85+00 to 85+500 on the right bank. It includes specific quantities for earth cutting, sand filling, brick work, concrete, plastering, and back filling for both L Drain and two U Drain sections. The total measurements for each category are summarized at the end, along with contact information for the proprietor.

Uploaded by

mushfiqzmn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Mesurement Sheet of L drain & U Drain in Poya muhury Border Road

Chainege No: 85+00 to 85+500 ( Right Bank)


Mesurement of L Drain
SL No. Description Nos Length (M) Height (M) Width (M) Unit Sub QTY
1 Earth Cutting 1 199.2 0.075 1.1 CUM 16.434
2 Sand Filling 1 199.2 0.075 0.7 CUM 10.458
3 Single Layer Brick Flat soling 1 199.2 1 0.7 SQM 139.44
4 Concrete Class 10 1 199.2 0.075 0.7 CUM 10.458
5 Brick Work 1 199.2 0.3 0.25 CUM 14.94
6 Plaster With net finishing 1 199.2 1 1 SQM 199.2
7 Back Filling 1 199.2 0.3 0.2 CUM 11.952
Mesurement of U Drain 1
SL No. Description Nos Length (M) Height (M) Width (M) Unit Sub QTY
1 Earth Cutting 1 41.2 0.45 1.1 CUM 20.394
2 Sand Filling 1 41.2 0.075 1.1 CUM 3.399
3 Single Layer Brick Flat soling 1 41.2 1 1.1 SQM 45.32
4 Concrete Class 10 1 41.2 0.075 1.1 CUM 3.399
5 Brick Work 1 41.2 1.322 0.25 CUM 13.6166
6 Plaster With net finishing 1 41.2 2.422 1 SQM 99.7864
7 Back Filling 1 41.2 0.6 0.2 CUM 4.944
Mesurement of U Drain 2
SL No. Description Nos Length (M) Height (M) Width (M) Unit Sub QTY
1 Earth Cutting 1 180.3 0.3 1.155 CUM 62.474
2 Sand Filling 1 180.3 0.075 1.1 CUM 14.8748
3 Single Layer Brick Flat soling 1 180.3 1 1.155 SQM 208.247
4 Concrete Class 10 1 180.3 0.075 1.155 CUM 15.6185
5 Brick Work 1 180.3 0.554 0.25 CUM 24.9716
6 Plaster With net finishing 1 180.3 1.709 1 SQM 308.133
7 Back Filling 1 180.3 0.3 0.2 CUM 10.818
Total Mesurement
SL No. Description Unit Sub QTY
1 Earth Cutting CUM 99.302
2 Sand Filling CUM 28.7318
3 Single Layer Brick Flat soling SQM 393.007
4 Concrete Class 10 CUM 29.4755
5 Brick Work CUM 53.5282
6 Plaster With net finishing SQM 607.119
7 Back Filling CUM 27.714

P/Engr……………………………. P/NCO…………………...….. P/JCO………………...………… P/Officer…………………..………

Thanks