Lkjhgfdaa

The document outlines a detailed construction estimate including various items such as earthwork excavation, filling, lime concrete in foundation, brickwork, and concrete work. It provides measurements, quantities, and calculations for each item, along with deductions for openings. The total quantities for different categories of work are summarized at the end.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views2 pages

Lkjhgfdaa

The document outlines a detailed construction estimate including various items such as earthwork excavation, filling, lime concrete in foundation, brickwork, and concrete work. It provides measurements, quantities, and calculations for each item, along with deductions for openings. The total quantities for different categories of work are summarized at the end.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

S.No. Description of Items No.

Length, Breadth, Height or Depth, Quantity Unit Remarks


m m m
1.0 Earthwork in excavation
a Rooms 1 29.00 0.90 0.90 23.49 L=29.90 - 0.9/2 - 0.9/2 = 29.00 m
b Verandah walls 1 12.00 0.70 0.90 7.56 L=12.90 - 0.9/2 - 0.9/2 = 12.00 m
c Steps 1 2.60 0.80 0.15 0.31 L=2.40+0.1+0.1 = 2.60 m, B=1.00+0.3/2-0.7/2
Total 31.36 m3
2 Earthwork in filling
a Earthwork in filling in trenches @ 20% of 1/5th of the excavation
20% 6.27
volume E/W excavation (approximate) m3
b L=4.5-2*0.05 = 4.10 m, B=3.6-2*0.05-=3.50, H= 0.60-
Room 1 1 4.40 3.50 0.430 6.62 0.1-0.075=0.43
c L=4.0-2*0.05 = 3.90 m, B=3.6-2*0.05-=3.50, H= 0.60-
Room 2 1 3.90 3.50 0.43 5.87 0.1-0.075=0.43
L=9.20 - 2*0.3/2 = 8.90 m, B=1.85-0.30/2 -0.40/2=1.50
d Verandah 1 8.90 1.50 0.43 5.74 m
Total 24.50 m3
3 Lime Concrete in Foundation
a Rooms 1 29.00 0.90 0.30 7.83 L=29.90 - 0.9/2 - 0.9/2 = 29.00 m
b Verandah walls 1 12.00 0.70 0.30 2.52 L=12.90 - 0.9/2 - 0.9/2 = 12.00 m
c Steps 1 2.60 1.00 0.15 0.39 L=2.4+0.1+0.1=2.60 m, B=1.00
Total 10.74 m3
4 1st class brick work in foundation &plinth in
cement mortar
Main Wall
a 1st footing 1 29.30 0.60 0.20 3.52 L=29.90 - 0.60/2 - 0.60/2 = 29.30 m
b 2nd footing 1 29.40 0.50 0.20 2.94 L=29.90 - 0.50/2 - 0.50/2 = 29.40 m
c 3rd footing 1 29.50 0.40 0.80 9.44 L=29.90 - 0.40/2 - 0.40/2 = 29.50 m
Verandah Walls
a 1st footing 1 12.30 0.40 0.20 0.98 L=12.90 - 0.60/2 - 0.60/2 = 12.30 m
b Plinth Wall lower footing 1 12.40 0.30 0.20 0.75 L=12.90 - 0.50/2 - 0.50/2 = 12.40 m
c Plinth Wall upper footing 1 12.50 0.30 0.80 3.00 L=12.90 - 0.40/2 - 0.40/2 = 12.50 m
H=0.6+0.2
d Steps B=(3*30+30)/2 1 2.40 0.60 0.45 0.65
Total 21.28 m3
5.0 5cm thickness
a Main wall 1 29.60 0.30 8.88 L=29.9-2*0.3/2
b Verandah Wall 5 0.2 0.2 0.04
c Deduction for door 3 1.20 0.30 0.36 Ld=1.2
Total 8.56 m3
6.0 1st class brick work in cement mortar in
superstructure
a Rooms 1 29.60 0.30 3.60 31.97 L=29.90 - 0.30/2 - 0.30/2 = 29.60 m
b Above pillars 1 12.60 0.20 0.90 2.27 L=12.90 - 0.30/2 - 0.30/2 = 12.60 m
c Pillars 5 0.20 0.20 2.70 0.54
Total 34.78 m3
Page 2

Deductions for openings


a Door 3 1.20 0.30 2.10 2.27
b Window 8 1.10 0.30 1.50 3.96
c Band lintel in main wall 1 29.60 0.30 0.15 1.33
d Band lintel in verandah wall 1 12.60 0.20 0.15 0.38 width = 20 cm given in dimension
e Band lintel in Shelves opening 1 1.10 0.20 1.50 0.33
Total 8.27 m3
Total Brickwork in cement mortar in superstructure after deductions 26.51 m3

7 10cm thick brickwork in parpet 1 30.4 0.1 0.7 L=(9.4-2*0.1/2)*2+(6-2*0.1/2)*2=30.4


Cement Concrete excluding reinforcement
8 &shuttering
a For Lintel
i Main walls 1 29.6 0.3 0.15 1.332
ii Verandah 1 12.60 0.10 0.15 0.189

b For Chajjas
i Window 6 1.30 0.45 0.07 0.2457 (9cm+5cm)/2=0.07m
ii Verandah front 1 10.30 0.45 0.07 0.32445 L=9.4+0.45+0.45
iii Verandah sides 2 1.80 0.45 0.07 0.1134 L=1.6+0.2
c Roofing Slabs 1 9.40 6.00 0.10 5.64
d Web of Beams 2 4.2 0.15 0.2 0.252 L=3.6+0.3+0.3
Total 8.09655 m3
Hire&Labour charges for centering
9 &shuttering
a For Lintel
i Main Wall outside 1 27.2 0.15 4.08 L=9.4+4.2+4.2+9.4
ii Main Wall inside 1 31.40 0.15 4.71 L=4.5*2+4*2+3.6*2+3.6*2
iii Verandah outside 1 13.30 0.15 1.995 L=9.4+2*1.95
iv Verandah inside 1 12.20 0.15 1.83 L=9+1.6*2
Total 12.615 m3
b Chajjas bottom 1 21.7 0.45 9.765 L=6*1.3+(9.4+2*0.45)+2*1.8
i Edge Front 1 22.60 0.05 1.13
ii Edge window sides 2*6 0.45 0.07 0.38
iii Edge verandah sides 2 0.45 0.07 0.063
Total 11.34 m3
c Roofing Slab
i Bigger Room 1 4.50 3.60 16.20
ii Samller Room 1 4.00 3.60 14.40
iii Sides of beam 2*2 3.6 0.2 2.88
Total 33.48 m2