0% found this document useful (0 votes)
43 views7 pages

Cost Estimate

The document outlines the electrical load schedule and cost estimate for a project at the Avesco Motorpol office in Balanga City. It details the specifications for lighting fixtures, switches, outlets, wires, conduits, circuit breakers, panel boards, and other materials, along with their quantities and costs. The total project cost is estimated at PHP 621,126.07, including materials, labor, equipment, and contingencies.

Uploaded by

Angelo Gonzales
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views7 pages

Cost Estimate

The document outlines the electrical load schedule and cost estimate for a project at the Avesco Motorpol office in Balanga City. It details the specifications for lighting fixtures, switches, outlets, wires, conduits, circuit breakers, panel boards, and other materials, along with their quantities and costs. The total project cost is estimated at PHP 621,126.07, including materials, labor, equipment, and contingencies.

Uploaded by

Angelo Gonzales
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 7

SCHEDULE OF LOADS

Motorpol
Brach No. of Total
LOAD Rating Voltage Ampere Conductor Conduit ACB
Ckt No. outlet Wattage
1 Lighting 10 100 1000 230 4.35 2 # 2.0 mm2 THHN Cu 15 mm ø 15 AT
2 Lighting 10 100 1000 230 4.35 2 # 3.5 mm2 THHN Cu 15 mm ø 15 AT
3 Heavy Duty Lamp 6 600 3600 230 15.65 2 # 3.5 mm2 THHN Cu 15 mm ø 20 AT
4 Heavy Duty Lamp 6 600 3600 230 15.65 2 # 3.5 mm2 THHN Cu 15 mm ø 20 AT
5 Convenience Outlet 10 360 3600 230 15.65 2 # 3.5 mm2 THHN Cu 15 mm ø 20 AT
6 Convenience Outlet 10 360 3600 230 15.65 2 # 3.5 mm2 THHN Cu 15 mm ø 20 AT
7 Machinery 1 1 5000 5000 230 21.74 2 # 14 mm2 THHN Cu 20 mm ø 60 AT
8 Machinery 2 1 5000 5000 230 21.74 2 # 14 mm2 THHN Cu 20 mm ø 60 AT
9 Machniery 3 1 5000 5000 230 21.74 2 # 14 mm2 THHN Cu 20 mm ø 60 AT
10 ACU 1 2 HP 230 12.00 2 # 5.5 mm2 THHN Cu 20 mm ø 30 AT
11 ACU 1 2 HP 230 12.00 2 # 5.5 mm2 THHN Cu 20 mm ø 30 AT
160.52 2 # 50 mm2 THHN Cu 50 mm ø 150 AT

Proposed Warehouse
Brach No. of Total
LOAD Rating Voltage Ampere Conductor Conduit ACB
Ckt No. outlet Wattage
1 Lighting 15 100 1500 230 6.52 2 # 2.0 mm2 THHN Cu 15 mm ø 15 AT
2 Lighting 15 100 1500 230 6.52 2 # 3.5 mm2 THHN Cu 15 mm ø 15 AT
3 Convenience Outlet 10 360 3600 230 15.65 2 # 3.5 mm2 THHN Cu 15 mm ø 20 AT
4 Convenience Outlet 10 360 3600 230 15.65 2 # 3.5 mm2 THHN Cu 15 mm ø 20 AT
44.35 2 # 14 mm2 THHN Cu 20 mm ø 60 AT

I base = 204.87 A I base = 204.87 A


ISEC = 204.87 (80%DF) + 25% HRM IACB = 204.87 (80%DF) + 100% HRM
ISEC = 166.90 A IACB = 175.89 A
Use 2 # 80 mm THHN Cu @ 50 mm diameter RMC
2

200 AT/AF
Avesco Motorpol
COST ESTIMATE

PROJECT : ABESCO OFFICE


ADDRESS: CATANING, BALANGA CITY

Particular Specification Unit Quantity Unit Cost Amount


I. Lighting Fixtures
Fumaco Brand, 2-
1 Flourescent luminaire pc 40 960.00 38,400.00
20W, with Ballast
Mercury vapor lamp
2 Heavy Duty luminaire pc 12 1,500.00 18,000.00
with casing
II. Switches
Panasonic wide series,
1 One gang, single pole with cover pc 6 120.00 720.00
20A, universal
Panasonic wide series,
2 Two gang, single pole with cover pc 10 140.00 1,400.00
20A, universal
Panasonic wide series,
3 Three gang, single pole with cover pc 4 180.00 720.00
20A, universal
III. Outlet
Panasonic wide series,
1 Duplex convenience outlet pc 40 280.00 11,200.00
20A, universal
Panasonic wide series,
2 ACU Outlet pc 2 300.00 600.00
30A, universal
V. Wires and Cables
THHN or THWN 600 V,
1 2.0 mm2 THHN Cu box 4 3,200.00 12,800.00
Color code
THHN or THWN 600 V,
2 3.5 mm2 THHN Cu box 12 4,500.00 54,000.00
Color code
THHN or THWN 600 V,
3 5.5 mm2 THHN Cu box 3 4,850.00 14,550.00
Color code
THHN or THWN 600 V,
4 14 mm2 THHN Cu m 150 200.00 30,000.00
Color code
THHN or THWN 600 V,
5 50 mm2 THHN Cu m 20 700.00 14,000.00
Color code
VI. Conduit
1 15 mm ø Flexible Moldex, ordinary Roll 20 900.00 18,000.00
2 20 mm ø PVC Moldex Gauge 40 pc 15 400.00 6,000.00
Panasonic with
3 50 mm ø RMC pc 6 2,400.00 14,400.00
interior coating
VII. Circuit Breakers
GE Brand, 18 KAIC, 2-
1 15 AT, single phase pc 4 250.00 1,000.00
pole, bolt-on
GE Brand, 18 KAIC, 2-
2 20 AT, single phase pc 8 250.00 2,000.00
pole, bolt-on
GE Brand, 18 KAIC, 2-
3 30 AT, single phase pc 22 300.00 6,600.00
pole, bolt-on
GE Brand, 18 KAIC, 2-
4 60 AT, single phase pc 4 400.00 1,600.00
pole, bolt-on
GE Brand, 25 KAIC, 2-
5 150 AT, Single Phase pc 1 1,200.00 1,200.00
pole, bolt-on
GE Brand, 25KAIC, 2-
6 200 AT, single phase, Main Breaker pc 1 6,000.00 6,000.00
pole, bolt-on
VIII. Panel Boards
1 2 x 4, 8 holes Single phase, top main pc 1 1,700.00 1,700.00

2 2 x 6, 12 holes Single phase, top main pc 1 2,200.00 2,200.00

single phase, heavy


3 Heavy Duty Enclosure for 350 AT pc 1 7,500.00 7,500.00
duty
single phase, heavy
4 MCCB (4 holes) pc 1 25,000.00 25,000.00
duty
XI. Boxes and Fittings
1 Junction Box Moldex, Gauge 40 pc 50 50.00 2,500.00
2 Utility Box Moldex, Gauge 41 pc 20 30.00 600.00
3 Service Entrance Cap 50 mm dia RMC set 1 380.00 380.00
4 Adaptor 50 mm dia adaptor pc 1 150.00 150.00
3-wire with ball
5 Secondary rack set 4 500.00 2,000.00
insulator, heavy duty
X. Others
1 Electrical tape Croco brand pc 15 300.00 4,500.00
2 Rubber Tape Croco brand pc 5 350.00 1,750.00
3 Tox and screws any lot 1 300.00 300.00
4 Expansion Bolt any pc 12 250.00 3,000.00
5 GI Wire, G-16 any kg 2 85.00 170.00
6 Solderless Connector any pc 6 500.00 3,000.00
Total Material Cost PHP 307,940.00
Labor Cost (35% of Material Cost) 107,779.00
Total Material & Labor Cost 415,719.00
Equipment/Boom Truuck 10,000.00
Contractor's Profit & Contingency (15%) 62,357.85
PPE 23,000.00
Permits 3,500.00
Mobilization/Demobilization 40,000.00
Total Project Cost (VAT exclusive) PHP 554,576.85
Total Project Cost (VAT inclusive) PHP 621,126.07
Prepared by:

Engr. Nelson S. Andres


Registered Electrical Engineer
Proprietor
ESTIMATE FORMAT FOR CONDUCTOR & CONDUIT

2.0mm2 3.5 mm2 60 mm2 For Switch Allowance Conduit (Total


Branch 5.5mm2 8.0 mm2
LOAD in in in for Length Length)/3meters
Ckt in meters in meters
meters meters in meters meters termination (in piece)

1 General Lighting 450 95 5 550 183


2 Convenience Outlet 350 5
3 Convenience Outlet 120 5
4 Refrigerator 30 5
5 Range 50 5 55 18
6 ACU 2 HP 60 5 65 22
7 ACU 1 HP 38 5
8 Washing Machine 60 5
9 Water Pump 80 5
10 Clothes Dryer 85 5
11 Service Entrance 10 10 3
No . Of Box
Total Length = (per 150 m)
Length x 2 Total
Length/150
550 4

55 0
65 0

10 0
SWITCHES & UTILITIES
Branch Utility Junction
LOAD SW1 SW2 SW3 15AT 20AT 30AT Outlet
Ckt Box Box
1 General Lighting
2 Convenience Outlet
3 Convenience Outlet
4 Refrigerator
5 Range
6 ACU 2 HP
7 ACU 1 HP
8 Washing Machine
9 Water Pump
10 Clothes Dryer
11 Service Entrance