The document outlines various network topologies including ring, bus, hybrid, star, and mesh. It details a disaster recovery plan addressing hardware failures, cybersecurity threats, and power outages, along with a project plan for network setup phases from planning to documentation. Additionally, it lists hardware and software requirements along with manpower needs for the project.

Uploaded by

esubeesubalew2
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views6 pages

Esubalew

The document outlines various network topologies including ring, bus, hybrid, star, and mesh. It details a disaster recovery plan addressing hardware failures, cybersecurity threats, and power outages, along with a project plan for network setup phases from planning to documentation. Additionally, it lists hardware and software requirements along with manpower needs for the project.

Uploaded by

esubeesubalew2
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Types Network Topologies

• Ring Topology: In the upper left, PCs are connected in a ring, where each
PC is connected to exactly two other PCs, forming a circular pathway for
data.
• Bus Topology: In the upper right, PCs are connected to a single cable or
"bus" with terminators at each end.
• Hybrid Topology: A central "Hybrid" bus seems to act as a backbone,
connecting the other topologies.
• Star Topology: In the lower left, PCs are connected to a central hub.
• Mesh Topology: In the lower right, PCs are interconnected with multiple
redundant connections, providing high reliability.

Disaster Recovery Plan (Tabled and Bordered)


R.N Expected Types/Categor Recovery Plan/Action
. Disaster y of Disaster
1 Hardware Technical/Equi 1. Redundant Hardware: Utilize backup
failure Switch) pment Failure switches (diagram). Automated failover.
2. Spare Equipment: Keep spare
modems/switches on hand.
3. Monitoring Tools: Use network monitoring
software.
2 Cybersecurity Security 1. Antivirus: Endpoint protection.
Threat Breach 2. Regular Updates: Patch software.
(Malware, 3. Backup Data: Daily offsite backups.
Ransomware) 4. Incident Response: Documented plan.
3 Power Utility Failure 1. UPS: Install UPS for servers, switches, and
Outage/Electri routers.
cal Surge 2. Backup Generators: Deploy generator for
extended outages.
3. Surge Protectors: Use surge protectors.
4. Scheduled Maintenance: Inspect power
equipment.

Task 2: Project Phase and Activities


Phases Activities to be Performed Durati Responsible Body
on
Phase 1: - Assess network requirements. 1 IT Manager/Network
Planning - Identify hardware and software needs. Week Architect
- Design network topology.
Phase 2: - Purchase required hardware (switches, 2 Procurement Team
Procurement workstations, etc.). Weeks
- Procure software licenses.
Phase 3: - Install cabling and networking devices 1 IT Technicians
Installation ( switches). Weeks
- Set up DMZ and VLAN configurations.
Phase 4: - Configure switches. 1 Network Engineers
Configuration - Set up access points. Week
- Configure workstations.
Phase 5: - Test network connectivity and device 1 IT Support Team
Testing functionality. Week
- Test failover mechanisms (disaster
recovery).
Phase 6: - Train employees on using 1 IT Trainers
Training workstations, telephony systems, and Week
software tools.
Phase 7: - Document network configuration, 3 Days IT
Documentation disaster recovery procedures, and Manager/Document
maintenance schedules. ation Specialist

Task 1: Hardware Requirements


Task 1: Hardware Requirements
No Item Specification Qua Unit Total
ntity Price Price
(ETB) (ETB)

telephon Wire phone 2 1500 3000


e
wifi Tele wifi routers 2 3000 6000
1 Core Layer-3 Managed Switch 1 20,00 20,00
Switch,h (24-Port Gigabit) 0 0
ub

2 Workstati Desktop, PCs (Intel 15+1 25,00 400,0


ons i3/Ryzen 3, 8GB RAM, 0 00
SSD)

3 Network Cat6 Ethernet Cable ~200 50 ~10,0


Cables (per meter) mete 00
rs
4 Patch Patch Panel for 2 3,500 7,000
Panel organizing cables
5 RJ45 RJ45 Connectors for ~50 ~20 ~1,00
Keystone patch panel and cable 0
Jack ends
6 Rack Network Rack Cabinet 1 30,00 30,00
Cabinet for housing switches 0 0
and servers
7 UPS Uninterruptible
Power Supply (UPS) 2
15.00-20+*

Total 477;0
00
Share

Export

Rewrite

Task 4: Software Requirements


No Item Specification Qua Unit Total
ntity Price Price
(ETB) (ETB)
1 Operating Windows 10/11 Pro (Workstations) 15 10,000 90,000
Systems

2 Antivirus Endpoint Protection (e.g., 8+1 1,000 9,000


Software Bitdefender, Kaspersky)
3 Office Microsoft Office 365 Business 8 5,000 40,000
Productivity Standard OR LibreOffice (Free) (yearly) (yearly)
Suite
4
5
6 Network Open Source (e.g., Zabbix, Nagios) 1 Free/Vari Free/Vari
Monitoring OR Paid Solution able able
Tool
7 Backup Backup and Recovery Software 1 Variable Variable
Software (e.g., Veeam, Acronis) OR Cloud
Backup Service
9 POS (Point of Restaurant POS System (e.g., local 1 Variable Variable
Sale) Ethiopian POS)
Total Manpower Requirements
R.N. Manpower/Role Quanti Estimated Salary (ETB per Month)
ty
1 IT Manager 1 20,000 - 30,000
2 Network Engineer 1 15,000 - 25,000
3 IT Support Technician/Help Desk 1 8,000 - 15,000
Total (Monthly): 43,000 - 70,000 Birr