Out
Out
Two hundred sixty-nine regulated pipeline system accidents caused fatalities and/or
injuries in the United States between 2010 and 2018, resulting in 106 fatalities and
599 injuries requiring hospitalization. About 84% of these serious accidents occurred
on gas distribution systems, which primarily transport natural gas. This study adapts
probabilistic risk assessment (PRA) methods which are used predominantly in the
space and nuclear industries to gas distribution systems in the U.S. Nationwide
system and accident data are used to evaluate natural gas distribution system risks,
estimate how many additional resources the public would be willing to dedicate to
reduce or eliminate these risks, and determine which improvement areas warrant
as well as the scope, quality, and level of detail of the underlying data, are provided.
     A PROBABILISTIC RISK ASSESSMENT BASED APPROACH TO
   UNDERSTANDING AND MANAGING THE RISKS OF NATURAL GAS
          DISTRIBUTION PIPING IN THE UNITED STATES
by
Sara Lyons
Advisory Committee:
 Professor Mohammad Modarres, Chair
 Professor Katrina Groth
 Professor Jeffrey Herrmann
                             ProQuest Number: 27997719
         In the unlikely event that the author did not send a complete manuscript
  and there are missing pages, these will be noted. Also, if material had to be removed,
                              a note will indicate the deletion.
ProQuest 27997719
Published by ProQuest LLC ( 2020 ). Copyright of the Dissertation is held by the Author.
                                   ProQuest LLC
                            789 East Eisenhower Parkway
                                   P.O. Box 1346
                             Ann Arbor, MI 48106 - 1346
        This work is
not under copyright protection
Preface
I began my career shortly after the Space Shuttle Columbia accident took the
South Florida to work at the Michoud Assembly Facility in New Orleans, Louisiana.
For the next five years, I learned from some of the country’s most talented engineers,
as we collectively worked toward reducing the risks of space flight for future
gained some exposure to the world of risk management that stayed with me in the
years to come.
Colorado, and I found a great position with the Pipeline and Hazardous Materials
Safety Administration (PHMSA). While there, I studied their pipeline accident data
and learned from their pipeline accident investigators in support of various data-
driven initiatives the agency was pursuing at the time. I was convinced that further
analysis of available accident data could help drive significant safety improvements,
A few years later, a position with the Nuclear Regulatory Commission (NRC)
motivated me and my family to move to the D.C. area. The NRC provided many
probabilistic risk assessment, public perception of risk, and a seemingly endless list of
                                           ii
related intricacies and nuance in application. I learned a great deal about these topics
from the staff at the NRC, especially while supporting response efforts following the
tragic events that occurred at the Fukushima Daiichi nuclear power plant in 2011.
the University of Maryland with the goal of building the skills needed to inspire
I have decided to take another look at the work I attempted while studying accident
data for PHMSA. Now, with an additional decade of experience, related graduate-
level coursework, and the advisement of Dr. Modarres, I hope that I have laid out a
framework that can be built upon and improved by others. As I have recently joined
                                           iii
Table of Contents
Preface........................................................................................................................... ii
Table of Contents ......................................................................................................... iv
List of Tables ................................................................................................................ v
List of Figures .............................................................................................................. vi
List of Abbreviations .................................................................................................. vii
Chapter 1: Introduction ................................................................................................. 1
  Section 1.1: Background .......................................................................................... 2
  Section 1.2: Safety ................................................................................................... 3
Chapter 2: PRA Methodology ...................................................................................... 5
  Section 2.1: Gas Distribution System Characterization........................................... 6
  Section 2.2: Threat Identification ............................................................................ 9
  Section 2.3: Likelihood Determination .................................................................. 10
  Section 2.4: Consequence Analysis ....................................................................... 13
  Section 2.5: Risk Quantification ............................................................................ 15
  Section 2.6: Uncertainty Evaluation ...................................................................... 16
  Section 2.7: Sensitivity and Importance Analysis ................................................. 16
  Section 2.8: Risk Acceptance ................................................................................ 17
  Section 2.9: Risk Reduction................................................................................... 17
Chapter 3: Results ....................................................................................................... 18
  Section 3.1: Gas Distribution System Characterization ......................................... 18
  Section 3.2: Threat Identification .......................................................................... 21
  Section 3.3: Likelihood Determination .................................................................. 23
  Section 3.4: Consequence Analysis ....................................................................... 30
  Section 3.5: Risk Quantification ............................................................................ 36
  Section 3.6: Uncertainty Evaluation ...................................................................... 38
  Section 3.7: Sensitivity and Importance Analysis ................................................. 40
  Section 3.8: Risk Acceptance ................................................................................ 42
  Section 3.9: Risk Reduction................................................................................... 43
Chapter 4: Recommendations for Future Work .......................................................... 47
Chapter 5: Conclusion................................................................................................ 49
Bibliography ............................................................................................................... 53
                                                                 iv
List of Tables
                                                                  v
List of Figures
                                                                 vi
List of Abbreviations
PE polyethylene
PVC polyvinylchloride
evaluations
                                    viii
Chapter 1: Introduction
customers. However, there are accidents and incidents 1 associated with these pipelines
each year, some of which impact public safety and result in significant unexpected
costs. About 84% of serious pipeline accidents – accidents which involve fatalities
(PHMSA) since 2010 have occurred on gas distribution systems (Table 1). The costs
associated with these accidents can be substantial, exceeding a billion dollars in some
cases [1]. This thesis will focus on adapting the probabilistic risk assessment (PRA)
approach practiced mostly by the nuclear and space industries to the assessment of gas
distribution systems risks. It will provide a method for evaluating these risks, estimate
how many additional resources the public would be willing to dedicate to reduce or
     1
       There are various definitions of the terms “accident” and “incident” associated with the
transportation of hazardous materials by pipeline. The term “accident” will be used throughout this paper
to indicate an unplanned event which occurred on a hazardous material pipeline system.
                                                    1
Section 1.1: Background
Natural gas pipeline technology has evolved since the Chinese introduced it in
900 BC. At that time, the Chinese used bamboo tubes to transport natural gas over short
distances to supply heat and light [3]. The first commercial use of natural gas occurred in
1802 when the Scottish engineer William Murdoch transported gas to the James Watt
factory for lighting. Four years later, in 1806, the first gas mains ever laid in a public
street were manufactured from sheet lead and installed in London, England. The first city
in the U.S. to install gas pipelines was Baltimore, Maryland in 1817 [4]. Significant
technological advancements have taken place since this time, improving materials, design
and construction methods, data management, and measurement techniques. World War
II brought advances in metallurgy, welding techniques and pipe rolling [3]. Around the
same time, in 1945, Polyvinylchloride (PVC) plastic pipe was developed. After World
Most customers receive natural gas from a local distribution company (LDC), a
utility that can either be owned by investors or local governments. LDCs typically
transport natural gas to households and businesses through thousands of miles of small-
diameter distribution pipelines. The point where the natural gas is transferred from a
transmission pipeline to the LDC is often termed the city gate. The natural gas is
typically depressurized, scrubbed, filtered, and odorized near the city gate. The odorant,
typically mercaptan, aides in the detection of natural gas, an otherwise odorless and
colorless gas. The natural gas is periodically compressed to ensure pipeline flow.
Supervisory control and data acquisition (SCADA) systems are sometimes used to
provide a comprehensive measurement and control system for the LDC [6].
                                              2
          Current methods used to model the risk of gas pipelines varies from company to
company and sector of the industry. Methods include the use of quantitative risk analysis
(QRA), accident consequence analysis (ACA), and qualitative risk assessment methods
using indices [7], [8], [9], [10], [11]. In some cases, techniques parallel those used in
process safety management [12]. Some studies use nationwide PHMSA data to underpin
the analysis [13]. These existing methods typically incorporate a combination of subject
matter expert opinion and statistical analysis assumptions that are not thoroughly
justified. The results do not support comparison with nationwide risk acceptance criteria
or specific risk insights needed protect against catastrophic events. This study lays out a
framework that would support comparison with nationwide risk acceptance criteria and
allow for additional risk insights to be gleaned upon further development as described
herein.
The safety of natural gas distribution systems has improved in the last 200 years.
Accidents that have occurred as the industry matured have shaped both company and
government policies. One of the most catastrophic accidents occurred when the London
Junior-Senior High School in New London, Texas, exploded on March 19, 1937. The
school board in the affluent town of New London had voted to have a plumber illegally
tap into a residue gas line of a local oil company to save money. The gas line connection
leaked, filling the school’s basement with natural gas which eventually ignited, taking
The responsibility for gas pipeline safety was assigned to the DOT by statute in
1968 [15]. Under the current structure, PHMSA, a DOT agency, is responsible for
                                               3
ensuring adequate protection against risks to life and property posed by pipeline
transportation of natural gas [16], [17]. The regulations governing natural gas distribution
systems are codified in Title 49 of the Code of Federal Regulations (CFR) Parts 190, 191,
192, 196, and 199. Through a partnership with PHMSA, some states assume regulatory
Although pipeline safety has significantly improved over the years, catastrophic
accidents continue to occur. In the nine years that this analysis period includes, there
were three significant gas distribution accidents that resulted in five or more fatalities
                                              4
Chapter 2: PRA Methodology
The safety risks presented by gas distribution systems have been a topic of
national interest for many decades, in part due to catastrophic accidents that have
occurred in our country’s history. The accidents that have occurred in the recent past can
be used to help understand current safety risks. Risk can be defined as a measure of the
probability and severity of adverse events. Risk assessments often consist of answering
In this study, risks associated with the nation’s current gas distribution system
discussed. The risk identification phase will include system characterization and threat
identification. The risk assessment phase will include estimating the likelihood and
consequences of those threats that could lead to hazard exposure, quantifying the
                                             5
                              Figure 1. Methodology Flowchart
The natural gas distribution infrastructure in the U.S., which primarily transports
natural gas, has evolved. Technological advancements have led to improvements in all
aspects of these systems (e.g., materials, design, construction and maintenance practices,
in Figure 2 [22]. The low-pressure distribution system (shown on the top) has various
regulator stations that reduce the pressure of gas coming from the city gate. Downstream
of the regulator stations, natural gas is provided to many customers at very low pressures.
                                             6
If any regulator station fails to perform its function, all areas downstream of the regulator
pressure near each structure and has a diverse safety device, an excess flow valve, to
event that both the excess flow valve and regulator associated with a residence fail, the
single customer would potentially suffer consequences. There is also a possibility that
multiple excess flow valves or multiple regulators could fail by a common cause (e.g.,
In this assessment, gas distribution risks will be estimated across the nation as a
whole. Detailed design information is not available for all of the nation’s gas distribution
systems that contribute to the overall risk. However, there is information that is available
on a nationwide basis from PHMSA’s annual reporting forms, which will be summarized
[2]. PHMSA annual report data were summarized based on mileage, decade installed, the
material of construction, and repairs completed in a given year using a script that was
this study [23]. This data, which was reported in terms of miles of main and number of
service lines, was combined after first converting the number of service lines to miles of
service lines based on the average service length indicated on each report. 2 To establish
     2
       Main refers to a distribution line that serves as a common source of supply for more than one service
line. Service line refers to a distribution line that transports gas from the main to customers as specified in
49 CFR § 192.3.
                                                      7
consistent data within the reporting period, pipelines that were reported to be fabricated
                                             8
Section 2.2: Threat Identification
question in the risk triplet: What can go wrong, or what can go wrong that could lead to
hazard exposure? When the specific pipeline system information is known, the system
can be evaluated to determine those threats that could result in hazard exposure. For
example, the natural gas distribution systems shown in Figure 2 could be evaluated by
considering the failure of any of the various subcomponents (e.g., failure of the pipe, a
regulator station, or an excess flow valve). This can be done by evaluating the associated
piping and instrumentation diagrams and identifying threats to the overall system
distribution system shown in Figure 2 (top) in the open position, would be identified as a
safety threat to all downstream residences. If the regulator stations failed in the closed
position, there could also be a safety risk associated with natural gas curtailment if the
Since specific pipeline system information is not available for this nationwide
assessment, system reliability will be modeled based on failure cause. This is useful
because pipeline safety programs are often established to address particular failure
causes. For example, One-call programs (e.g., 8-1-1) target excavation accident
from the particular failure mechanism(s) they can detect (e.g., cracks, corrosion, dents).
Causes and failure modes of the gas distribution pipeline need to be assessed to define
                                              9
Section 2.3: Likelihood Determination
The likelihood that each of the identified threats will lead to hazard exposure will
PHMSA reportable event should be considered to have led to hazard exposure. System
function as expected for a predetermined amount of time when exposed to actual use, or
system, including the cumulative distribution, probability density, reliability, and hazard
functions.
The cumulative distribution function (cdf) describes the probability that the
component or system will fail before specified time, t. The probability density function
(pdf) describes the relative likelihood that the component or system will fail at a time, t,
and is defined as the derivative of the cdf. The reliability function describes the
The hazard function describes the propensity to fail in the next small interval,
given survival up to that point. Mathematically, the hazard function is represented by:
                                                 1 𝐹𝐹(𝑡𝑡+𝜏𝜏)−𝐹𝐹(𝑡𝑡)       𝑓𝑓(𝑡𝑡)
                                ℎ(𝑡𝑡) = 𝑙𝑙𝑙𝑙𝑙𝑙                        =                 (Eq. 1)
                                         𝜏𝜏→0 𝜏𝜏         𝑅𝑅(𝑡𝑡)           𝑅𝑅(𝑡𝑡)
The hazard function is important because it shows changes in the probability of failure
over the lifetime of a component. For large samples, a nonparametric estimate of the
                                                       𝑁𝑁 (𝑡𝑡 )
                                          𝑅𝑅� (𝑡𝑡𝑖𝑖 ) = 𝑠𝑠 𝑖𝑖                           (Eq. 2)
                                                            𝑁𝑁
                                                    10
where 𝑁𝑁𝑠𝑠 (𝑡𝑡𝑖𝑖 ) is the number of surviving components at a time, 𝑡𝑡𝑖𝑖 , and 𝑁𝑁 is the total
                                                              𝑁𝑁𝑓𝑓 (𝑡𝑡𝑖𝑖 )
                                                  𝑓𝑓̂(𝑡𝑡𝑖𝑖 ) = 𝑁𝑁𝑁𝑁𝑁𝑁                              (Eq. 3)
where 𝑁𝑁𝑓𝑓 (𝑡𝑡𝑖𝑖 ) is the number of failures observed in the interval (𝑡𝑡𝑖𝑖 , 𝑡𝑡𝑖𝑖 + 𝛥𝛥𝛥𝛥). From
Equations 2 and 3, the hazard rate (or failure rate) can be estimated:
                                                              𝑁𝑁𝑓𝑓 (𝑡𝑡𝑖𝑖 )
                                                 ℎ�(𝑡𝑡𝑖𝑖 ) = 𝑁𝑁 (𝑡𝑡  )𝛥𝛥𝛥𝛥
                                                                                                   (Eq. 4)
                                                                 𝑠𝑠   𝑖𝑖
                 𝑁𝑁𝑓𝑓 (𝑡𝑡𝑖𝑖 )
In Equation 4,   𝑁𝑁𝑠𝑠 (𝑡𝑡𝑖𝑖 )
                                estimates the probability that a component will fail in the given
interval, provided it survives up to time, ti. Dividing by 𝛥𝛥𝛥𝛥 estimates the failure rate
This concept allows for the development of life tables, which are used to describe
human mortality and life expectancy. In this application, there are two types of life
tables. The first type of life table is the cohort life table, which is developed by following
a particular birth cohort throughout their life. This life table takes many years to develop
and the development is sometimes not possible due to unavailable or incomplete data.
The second type of life table is the period life table, which represents a hypothetical
cohort that is alive during a specific period. For example, the period life table that was
developed for the year 2015 “assumes a hypothetic cohort that is subject throughout its
lifetime to the age-specific death rates prevailing for the actual population in 2015” [25].
When the human mortality hazard rate is plotted, it illustrates how the hazard rate
changes with age for the hypothetical cohort, decreasing very early in life, remaining
relatively constant, and increasing later in life during the “degradation” period (Figure 3).
                                                           11
       A similar “hypothetical cohort” approach will be used to evaluate the hazard rate
of gas distribution systems. In this study, hazard rate curves (reported in the number of
failures per mile per year) will be developed for each threat based on an analysis of
available historical data. If this analysis demonstrates that the hazard rate is constant, the
exponential distribution will be used to estimate the likelihood that the threat will
challenge the system and lead to a reportable event. If the hazard rate is not constant for
a particular threat, methods for addressing higher hazards at the beginning or end of life
will be discussed.
                                              12
Section 2.4: Consequence Analysis
Natural gas can form an explosive mixture when combined with air in
concentrations between 5% (the lower explosive limit, or LEL) and 15% (the upper
explosive limit, or UEL) natural gas in the air. In a typical gas distribution system
accident sequence, there is the potential for very serious consequences, including
fatalities, injuries, and extensive property damage. It is also possible that the
consequences are relatively minor (e.g., venting gas to the atmosphere, cost of lost
product and repairs). It is often convenient to model consequence scenarios using event
tree models. In the simplified, notional event tree shown in Figure 4, the initiating event
occurs, there are a series of pivotal events (also called top events) that determine the
associated consequences. In the notional event tree shown, the pivotal events include:
is completed prior to the gas presenting a hazard to any person whose safety
• Protection and Response: Success of this top event occurs when gas vents to
            will depend on the specific scenario (potential for gas to reach an ignition
                                            13
            source, ability to detect, diagnose, safely extinguish all ignition sources, and
isolate the gas leak promptly). If a leak persists, natural gas vapors may
consequences.
used. Consequences will be assessed based on the statistical value of the accident, which
is an estimate of the amount the public would have been willing to pay to prevent the
fatalities and injuries that occurred as a result of the accident, plus the actual cost
incurred. To support this portion of the analysis, a concept broadly used in regulatory
cost-benefit analyses – the value of a statistical life (VSL) – will be used. “The Value of
a Statistical Life (VSL) is defined as the additional cost that individuals would be willing
to bear for improvements in safety (that is, reductions in risks) that, in the aggregate,
reduce the expected number of fatalities by one. What is involved is not the valuation of
life, but the valuation of reductions in risks” [26]. The VSL has been estimated based on
existing guidance to adjust for inflation and real incomes since the guidance was
                                             14
developed. Using this procedure, the VSL was updated from $9.6 million in 2016 and
rounded to $10 million in 2019. For this analysis, since injury severity information is
generally not available, it is assumed that all reported injuries had a severity of the
The statistical value is intended to estimate the total amount that the public would
have been “willing to pay” for safety enhancements that would have prevented a given
accident. The statistical value of each accident will be calculated based on the sum of:
• additional costs that individuals would have been willing to bear for improvements in
• actual costs related to property damage, repairs, emergency response, clean-up, and
lost product
Note that the statistical value does not include costs associated with lost productivity or
Risk estimation is used to interpret the various contributors to risk. Because all
Equation 5.
                                               15
The risk will be estimated for each threat.
Risk assessments, like all engineering analyses, involve assumptions that are
made to support the analyses. There are three types of epistemic uncertainty that
typically propagated through the probabilistic model. Model uncertainty occurs when
there are multiple modeling approaches and no consensus model exists. Model
the decision, and quantitatively or qualitatively justifying them [27], [28]. The
completeness, parameter, and model uncertainty that may be important to decisions that
involve a risk assessment of gas distribution pipeline systems will be tabulated and
discussed.
uncertainty evaluation. Importance analysis will be performed to assess the relative risk
contribution of each threat. This is useful to understand which safety improvement areas
                                              16
Section 2.8: Risk Acceptance
Federal guidelines will be reviewed to determine the level of risk that is tolerable
as it relates to gas distribution systems. Risk acceptance thresholds are used in several
industries. One example is the commercial nuclear industry. The Nuclear Regulatory
Commission (NRC) has two safety goals, one that relates to the risk of prompt fatality to
an individual and one that relates to the societal risk of cancer fatalities [29]. The safety
acceptability.
The estimated risk will be compared to the acceptance threshold. If the current
risks are not within the acceptable range, approaches to reduce these risks will be
                                              17
Chapter 3: Results
This case study focuses on adapting PRA methods to the U.S. gas distribution
system to help understand and manage risks. There are some challenges with this
application that do not exist in other industries where PRA is more widely used. When
contrasted with the nuclear and space industries, natural gas distribution systems:
• traverse broad, often populated areas that are not under the direct control of the
operator,
older systems,
• have not been studied as extensively with the intent of establishing the bases for
Despite these challenges, the structure that PRAs offer to support risk
management are valuable and can be applied to other technologies, including gas
distribution systems, to further advance safety performance. The results presented below
show how this structure can be applied, given the currently available information.
The current U.S. gas distribution system primarily transports natural gas. Natural
gas distribution systems include a network of piping that supply gas to various
consumers. According to data provided by PHMSA, there are over two million miles of
main and service lines which distribute gas to customers across the country.
                                            18
The gas distribution infrastructure includes pipelines of various ages. Distribution
pipelines that have known ages were installed between the start of the twentieth century
and today, but the age of some gas distribution pipelines is unknown (Figure 5).
There are several materials that have been used to construct these pipelines, with
the majority being from polyethylene (PE) or coated, cathodically protected (CP) steel.
Most newly constructed gas distribution pipelines are fabricated from PE (Table 2).
The diameter of pipelines used in gas distribution systems varies. The majority
Gas distribution operators track and report leaks that are repaired in a given year
by leak cause (Table 3). The repairs are considered to be associated with a “hazardous”
leak if the operator determines that the leak requires an immediate response. Most
damage.
                                            19
Figure 5. U.S. Gas Distribution Systems – Miles of Main and Service Lines by Decade
Installed [2]
Table 2. U.S. Gas Distribution Systems – Miles of Main and Service Lines by Material
[2]
                                                           2010      2018
                                    Polyethylene (PE)    1,201,543 1,424,057
          Steel, Cathodically Protected (CP), Coated       668,072   636,457
                            Steel, Unprotected, Bare        78,826    50,307
                         Steel, Unprotected, Coated         37,387    36,549
                                                Other       23,431    23,493
                                  Cast/Wrought Iron         34,807    22,952
                                       Steel, CP, Bare      21,058    15,936
                             Polyvinyl Chloride (PVC)       14,949    11,672
                                               Copper       13,835     9,390
                                         Other Plastic       3,258     4,312
              Acrylonitrile-Butadiene-Styrene (ABS)          3,595     2,957
                                          Ductile Iron         796       516
                                                TOTAL 2,101,556 2,238,597
                                           20
   Figure 6. U.S. Gas Distribution Systems – Main and Service Lines by Diameter [2]
                                             Repairs of             Repairs of
                                     Total
  2018                                       Hazardous Repairs/Mile Hazardous
                                     Repairs
                                             Leaks                  Leaks/Mile
                   Excavation         81,464     38,240   3.64E-02    1.71E-02
          Equipment Failure          183,916     12,856   8.22E-02    5.74E-03
                    Corrosion        108,439     74,925   4.84E-02    3.35E-02
  Pipe, Weld, or Joint Failure        56,477     11,366   2.52E-02    5.08E-03
                 Other Cause          37,692     17,437   1.68E-02    7.79E-03
               Natural Force          29,509     42,866   1.32E-02    1.91E-02
         Other Outside Force          16,274      6,950   7.27E-03    3.10E-03
         Incorrect Operation          19,641     15,124   8.77E-03    6.76E-03
Both the American Society of Mechanical Engineers (ASME) and PHMSA have
defined gas pipeline threat categories. ASME B31.8S, Managing System Integrity of Gas
Pipelines: ASME Code for Pressure Piping, B31 Supplement to ASME B31.8, identifies
nine threat categories which are based on an analysis performed by the Pipeline Research
                                            21
Committee International (PRCI). The nine threat categories are further divided into those
and external corrosion and stress corrosion cracking) cause degradation over time and are
addressed by using one of the integrity assessment methods (e.g., in-line inspection,
related, equipment) are addressed through specific, often one-time evaluations (e.g.,
operational procedure, weather-related and outside force) are typically not addressed by
PHMSA’s reporting form has seven major causes (excluding “other incident cause”) that
generally align with the ASME B31.8S threat groups and categories (Table 4).
For the purposes of this evaluation, the major causes defined in the PHMSA
incident reporting form (i.e., Corrosion; Natural Force Damage; Excavation Damage;
Other Outside Force Damage; Pipe, Weld, or Joint Failure; Equipment Failure; Incorrect
Operation; and Other Incident Cause) will be treated as the gas distribution system
                                            22
Table 4. Comparison of Gas Pipeline Threat Categories Used by ASME B31.8S and
PHMSA [30], [31]
Historical data were assessed to determine the hazard rate for accidents that
occurred between 2010-18 [1]. For decades that ended prior to 2010, the hazard rate was
estimated based on the decade that the pipeline was installed (Table 5). For pipelines that
were installed in the most recent decade (2010-19), a complete dataset did not exist for
each reporting year of interest. In 2010, all pipelines that were installed in the current
decade (2010-19) were 0-1 year old; in 2011, they were 0-2 years old. Therefore, the
data for pipelines that were installed in the current decade were analyzed yearly based on
the age of the pipe (Table 6). A script to apply this methodology to PHMSA data was
                                              23
developed in R [5]. The overall resulting hazard curve is shown in Figure 7. The
contribution from each cause is shown in Figure 8 and Figure 9. Note that some data was
grouped in Figure 7 through Figure 9 and the data points do not directly correspond to
those in Table 6.
The higher hazard rate early in life was attributed to the following causes:
excavation, other outside force, equipment, and incorrect operations. Three of these
remaining cause was designated “stable” in ASME B31.8S. The higher hazard at the
the new pipeline for excavation, equipment, and incorrect operation failures. For failures
environmental conditions (e.g., water jet or electrical arcing from nearby utilities)
explained the higher hazard early in life. Initiatives to flatten the hazard curve early in
life may focus on enhancing existing processes to perform new construction safely,
expanding public outreach related to new construction projects, and developing more
The increasing hazard rate later in life was attributed to corrosion and natural
force failures. Higher hazard rates towards the end of life are typically attributed to
degradation, which explains the response for corrosion failures. For natural force
damage, the hazard rate may increase later in life due to less mature requirements that
were in place at the time the system was installed (before 1950), or degradation that may
Initiatives to flatten the hazard curve later in life may focus on enhancing integrity
                                             24
assessments for pipelines that are more than 50 years old, implementing more aggressive
replacement schedules for pipelines with known integrity challenges, and closely
shape of the hazard curve. This approach may lower and flatten the hazard curve at the
beginning and end of life, making it indistinguishable from the useful life portion of the
curve. For the remainder of this evaluation, it is assumed that reliability improvements
will be pursued to improve and flatten the hazard curve. Therefore, the average hazard
rates will be used. The average hazard rate is higher than it would be after improvements
to flatten the hazard curves have been implemented but is appropriate for use at this
point, since the improvements have not yet been made. Systems that exhibit a constant
assessment, an exponential distribution can be used to describe the likelihood for the ages
that exhibit a constant hazard rate. Fitting the data to a parametric curve in this way
would allow for existing off the shelf software to be used to perform a probabilistic
analysis. One program that is suitable for this purpose is the Systems Analysis Programs
The average hazard rates by PHMSA major causes and subcauses are shown in
Table 7. The average hazard rates show that most failures which lead to a PHMSA
reportable accident are attributed to excavation damage or other outside forces. When
are dominant.
                                             25
Table 5. Estimated U.S. Gas Distribution Hazard Rate by Decade Installed [2]
Table 6. U.S. Gas Distribution Hazard Rate by Age (Pipelines Installed 2010-2018) [2]
                                           26
Figure 7. U.S. Gas Distribution Hazard Rate by Age
                                         27
Figure 8. U.S. Gas Distribution Hazard Rates by Age for PHMSA Causes Identified by ASME B31.8S as Time-Dependent, Stable, or
Unknown
Figure 9. U.S. Gas Distribution Hazard Rates by Age for PHMSA Causes Identified by ASME B31.8S as Time-Dependent, Stable, or
Unknown
 Table 7. Average U.S. Gas Distribution Hazard Rate by PHMSA Major Causes and
                                    Subcauses
                                                       λ                                                         λ
Cause/Subcause                                   (#fail/mi/yr)   Cause/Subcause                            (#fail/mi/yr)
Excavation                                           8.74E-06    Other Incident Cause                          2.63E-06
   Insufficient Excavation Practices                 4.17E-06       Miscellaneous                              1.39E-06
   Insufficient One-Call Notification Practice       1.99E-06       Unknown                                    1.24E-06
   Insufficient Locating Practices                   1.54E-06    Pipe, Weld, or Joint Failure                  2.43E-06
   Other                                             5.96E-07       Construction Defect                        1.09E-06
   Previous Damage                                   3.47E-07       Material Defect                            8.44E-07
   Abandoned Facility                                4.96E-08       Other/Unknown                              1.99E-07
   Data Not Collected                                4.96E-08       Design Defect                              1.49E-07
Other Outside Force                                  7.35E-06       Previous Damage                            1.49E-07
   Motorized Vehicle/Equipment                       4.12E-06    Natural Force Damage                          2.08E-06
   Other                                             2.08E-06       Lightning                                  4.47E-07
   Electrical Arcing                                 6.95E-07       Temperature                                4.47E-07
   Intentional Damage                                2.48E-07       Other                                      4.47E-07
   Previous Damage                                   1.49E-07       Earth Movement                             3.97E-07
   Adrift Maritime Equipment                         4.96E-08       Heavy Rains/Floods                         3.47E-07
Incorrect Operation                                  2.73E-06    Equipment Failure                             1.14E-06
   Other                                             1.74E-06       Control/Relief Equipment Malfunction       4.96E-07
   Damage by Operator or Operator's Contractor       4.47E-07       Non-Threaded Connection Failure            2.48E-07
   Valve Left or Placed in Wrong Position            1.99E-07       Valve                                      1.99E-07
   Equipment Not Installed Properly                  1.99E-07       Other                                      1.49E-07
   Pipeline or Equipment Over-Pressurized            9.93E-08       Threaded Connection Failure                4.96E-08
   Wrong Equipment Specified or Installed            4.96E-08    Corrosion                                     7.45E-07
                                                                    External Corrosion                         6.45E-07
                                                                    Internal Corrosion                         9.93E-08
presented in Section 3.3 and the actual observed consequences (number of fatalities,
number of injuries, cost, and statistical value) per accident summarized by accident
cause (Table 8). However, these average values suggest differences in consequences
that are misleading because they do not account for the effect of the small number of
catastrophic accidents.
For example, the statistical value of each significant reported gas distribution
                                                       30
significant reported accident. As discussed above, this value represents the amount
that the public would have been willing to pay to prevent the occurrence and the
actual costs the operator incurred due to property damage, repairs, emergency
response, clean-up, and lost product. This mean value is driven by a relatively low
by the specific circumstances surrounding the event, and the response to the event
itself. Many reportable events do not have the potential to result in catastrophic
consequences and may not even require an evacuation. The data needed to determine
which accidents would have required an evacuation is not available for each
accidents included in this study were considered to be serious accidents, because they
resulted in at least one injury or fatality. In other words, 40% of the reportable
accidents did not successfully remove people from the hazards presented by natural
gas distribution operations (Figure 10). It can be difficult to evacuate people prior to
accident, there is typically an excavation crew and ignition source near the location
that the pipe was breached. However, the consequence data does not show a
significant difference in statistical value between any of the threats. Figure 11 shows
a modified box plot that is used to highlight outliers. This whiskers on this boxplot
were constructed by multiplying the interquartile range by 1.5, adding the result to the
third quartile, and subtracting it from the first quartile. The whiskers were extended
                                           31
to include the maximum and minimum data points within this range. All data points
outside of this range were indicated by circular markers. The modified box plot is
distribution system consequences is the class location. A gas pipeline’s class location
broadly indicates the level of potential consequences for a pipeline release based upon
population density along the pipeline. According to 49 CFR 192.5(a), class locations
are specified by using a “sliding mile” that extends 220 yards on both sides of the
centerline of a pipeline. The number of buildings within this sliding mile at any point
during the mile’s movement determines the class location for the entire mile of
pipeline contained within the sliding mile. Class 1 locations have 10 or fewer
buildings intended for human occupancy. Class 2 locations contain more than 10 but
fewer than 46 buildings intended for human occupancy. Class 3 locations contain 46
5 days a week for 10 weeks in any 12-month period. Class 4 locations have a
prevalence of buildings of at least four stories in height. Class locations are used to
differentiate some regulatory requirements so that they are commensurate with the
potential consequences. The current data shows that the statistical values of accidents
are similar for each class location, but the more catastrophic accidents may be more
consequences of a gas distribution accident. However, the available data does not
                                           32
indicate that these benefits are being realized (Figure 12). This information was also
shutoff valves, remote-controlled isolation valves, training, and public awareness may
help to mitigate consequences, but specific data on these factors as they relate to the
                                           33
    Table 8. Risk Matrices by Accident Cause for Four Consequence Measurements
  (Number of Fatalities, Number of Injuries, Cost (Excluding VSL), and Statistical
                                      Value
Possible            Excavation
>5E-6/mi/yr         Other Outside Force
Very Unlikely
< 1E-6/mi/yr        Corrosion
Possible                                           Excavation
>5E-6/mi/yr                                        Other Outside Force
                                                                                  Incorrect Operation
Unlikely                                                                          Natural Force Damage
1E-6 - 5E-6/mi/yr   Equipment Failure              Pipe, Weld, or Joint Failure   Other Incident Cause
Very Unlikely
< 1E-6/mi/yr                                       Corrosion
Possible
>5E-6/mi/yr         Other Outside Force            Excavation
Very Unlikely
< 1E-6/mi/yr        Corrosion
Possible                                           Excavation
>5E-6/mi/yr                                        Other Outside Force
Very Unlikely
< 1E-6/mi/yr        Corrosion
                                                    34
Figure 10. Serious and Significant U.S. Gas Distribution Accidents (2010-18)
Figure 11. Statistical Value of Significant Accidents by PHMSA Major Cause (2010-
18)
                                        35
Figure 12. Statistical Value of Significant Accidents by Class Location and SCADA
(2010-18)
The gas distribution system risk was estimated based on the results of the
estimate was used to estimate the statistical value. A point estimate is an appropriate
after the consequence analysis development has been completed. The mean statistical
value that could be gained if all risks associated with gas distribution systems being
                                           36
Table 9. Statistical Value of Significant Accidents
                                                            37
Section 3.6: Uncertainty Evaluation
A listing of the assumptions associated with this evaluation and justification for
            Assumption                                    Justification
 Gas distribution infrastructure was        Appropriate for a nationwide analysis.
generalized on a per mile basis (e.g.,    System-specific analyses are recommended
changes in design, configuration, and     to support proposed actions resulting from
    location are not considered)                    this high-level analysis.
 Simplified consequence modeling              Data insufficient to support refined
                                                     consequence modeling
                                                (Recommended Future Work)
          Mean VSL used                    VSL values were based on DOT guidance
                                         which recommended sensitivity study based
                                             on minimum and maximum values. A
                                          sensitivity study is included in Section 3.7.
    Integration of all scenarios to       Each cause is treated as mutually exclusive
          estimate total risk            in this dataset, although contributing causes
                                          are known to exist and may be significant.
                                                (Recommended Future Work)
Quality of data reported to PHMSA is     Data quality limitations are discussed herein
  sufficient to support this analysis           (Recommended Future Work)
Point estimates were used to quantify     Point estimates are an approximation based
 risk; parameter uncertainty was not     on the maturity of the model at this point. A
            accounted for.                 probabilistic model should be developed
                                         after data quality and consequence modeling
                                                       has been improved.
                                                (Recommended Future Work)
                                          38
Data Quality Limitations: Many PHMSA reportable gas distribution accidents are
11 shows a comparison between the cause information reported to PHMSA and the
NTSB determined probable cause for gas distribution accidents investigated by the
NTSB since 2010. Note that the cause information reported to PHMSA is not
consistent with the NTSB determined probable cause for the majority of these
accidents (5/7) which are highlighted in the table. A similar, more comprehensive
comparison could be completed with investigation results from the various State
regulators and/or operators to ensure that the most accurate information is available to
support analysis and consequential safety decisions. In some cases, the operator may
not agree with the probable cause determined by the NTSB, PHMSA, or state
independent assessment of the facts, with input from the operators; they result in the
combine this information with the current operator reported PHMSA data could help
to make the most useful data available for future analysis. This future analysis could
                                          39
    Table 11. Comparison of Cause Information Reported to PHMSA by the
Pipeline Operator and the Probable Cause Determined by the NTSB (Accidents with
Inconsistent Causes are Highlighted)
evaluate the various estimates of VSL was identified. In order to assess the
sensitivity of this analysis to the range of potential acceptable VSLs, the analysis was
repeated using minimum and maximum values. The minimum VSL was estimated to
be $6 million and the maximum VSL was estimated to be $14 million. The results
                                               40
indicated that the annual statistical value has ranged from $305 million to $376
In this initial study, data (particularly consequence data) was not available to
measures were not calculated. However, the estimated risk information can be used
improvements. For example, over 30% of the gas distribution system risk is
attributed to excavation accidents. Of these, almost 50% of the risk from excavation
contribution of each subcause can be calculated (Table 13). This shows that
contributors.
                                                     Statistical Value
                                                           ($/yr)
           Cause                                   min               max
           Excavation                            $95,624,071      $129,435,253
           Other Outside Force                   $80,411,151       $94,627,216
           Incorrect Operation                   $29,882,522       $35,165,519
           Other Incident Cause                  $28,795,885       $33,886,773
           Pipe, Weld, or Joint Failure          $26,622,611       $31,329,281
           Natural Force Damage                  $22,819,381       $26,853,669
           Equipment Failure                     $12,496,327       $14,705,581
           Corrosion                              $8,149,779        $9,590,596
           TOTAL                                $304,801,726      $375,593,889
                                           41
           Table 13. Relative Importance of Subcauses Contributing at Least 1%
The gas distribution industry does not have a specific safety metric that they
are required to meet. However, the current Administrator of PHMSA has advocated
for a goal of zero reportable pipeline accidents [11]. A significant change in our
improvement.
PHMSA’s goal is consistent with an NTSB study, which noted that traditional
cost-benefit criteria are not necessarily applicable to pipeline accidents because those
that are near pipelines when accidents occur are often not the same as those that
                                                42
benefit from them. The NTSB notes that “those who are bearing the risk deserve to
The U.S. gas distribution industry has undergone many safety improvements
over the last two centuries. Despite many successes and improvements, the industry
has not yet achieved an acceptable level of risk. Low frequency, high consequence
events continue to occur, significantly increasing the overall risk across the industry.
events. This concept originated as a military strategy where layered lines of defense
would be used instead of a single strong line of defense. The use of diverse and
redundant components can reduce risk by preventing system failure or mitigating its
The defense-in-depth concept has been employed in nuclear safety since about
1957 [33]. In the nuclear safety arena, one acceptable method of supporting risk-
depth,” a similar framework has been employed in the gas distribution pipeline
industry, also shown in Table 14. However, many of the efforts that have been
                                           43
implemented in gas distribution systems to date have focused on preventing
Additional efforts to strengthen the second and third layers of defense could
yield significant safety benefits. For example, the NTSB’s investigation of a gas
indicated that the NTSB had previously investigated seven accidents that involved
natural gas under high pressure entering low-pressure natural gas lines. A search of
in the cause described in the narrative section of these reports and the cause reported
in the cause field are highlighted in Table 15 (see Data Quality Limitations discussion
in Section 3.6).
In order to mitigate these types of accidents before they occur, the information
relying on sparse and disparate data. In the nuclear industry, industry stakeholders
formed the Institute of Nuclear Power Operations (INPO) after the Three Mile Island
                                            44
        Defense-in-depth concepts can be implemented through many different
strengthening the second layer of defense can help decrease accident consequences.
potential for high consequences (e.g., cast iron pipe replacements, installation
distribution systems)
Table 14. Comparison of Layers of Defense Between Commercial Nuclear Safety and
Gas Distribution Pipeline Safety
                                           45
Table 15. PHMSA Data Indicating Over-Pressurization of a Low-Pressure
Distribution System (Excluding NTSB Investigations)
                                            46
Chapter 4: Recommendations for Future Work
In the U.S. gas distribution industry, many safety improvements have been
implemented since gas distribution first began. Some of these improvements have
been codified and consistently required through regulation and others were
industry strives to reduce safety risks further, a set of risk acceptance criteria or safety
goals should be developed, similar to the risk acceptance criteria used by the nuclear
- After the data quality and consequence modeling improvements have been
update analysis to identify and address any new model and completeness
                                            47
Additionally, this model should be frequently updated since it relies on historical
records to predict the future. Regularly reviewing the model with the goal of
continuous improvement could provide a way to accurately estimate risk given the
quality.
predictive approach [36]. Prognostics and health management may also be explored
for this application that may enhance distribution system safety. There are examples
where predictive approaches have improved safety and reliability, while also saving
money [37].
                                          48
Chapter 5: Conclusion
information, and operator reported accident data to evaluate gas distribution system
risks. Three phases – risk identification, risk assessment, and risk management –
were completed and could be iterated in the future as knowledge is gained and system
estimating the likelihood and consequences of those threats that could lead to hazard
exposure, quantifying the associated risk, evaluating uncertainties, and analyzing the
management phase included evaluating risk acceptance thresholds and the need for
risk reduction.
There are more than two million miles of main and service lines that distribute
information, each cause was identified as a threat to the system. Historical data were
assessed to determine the hazard rate for accidents that occurred between 2010-18.
The overall hazard curve exhibited a higher hazard rate towards the beginning and
end of life. The higher hazard rate early in life was attributed to the following failure
causes: excavation, other outside force, equipment, and incorrect operations. These
requirements that were in place before 1950 may have also contributed to this
response for older pipelines. Initiatives to improve safety performance early in life
expanding public outreach related to new construction projects, and developing more
robust processes to define and design for actual in-service conditions. Initiatives to
assessments for pipeline that are more than 50 years old, implementing more
aggressive replacement schedules for pipelines with known integrity challenges, and
The statistical value was estimated based on the amount the public would have been
willing to pay to prevent the fatalities and injuries that occurred as a result of the
accident plus the actual cost incurred. The mean consequence of $5,754,368 per
significant reported accident was driven by a relatively low number of accidents with
catastrophic consequences.
The overall risk was estimated based on a point estimate of likelihood and
analyses. The mean statistical value that could be gained if all risks associated with
gas distribution systems were eliminated was estimated to be $358 million per year.
                                            50
       The uncertainty evaluation identified several sources of model, completeness,
and parameter uncertainty which were either justified or recommended for future
analysis. Data quality was found to be a significant limitation of this work. For
example, the cause information reported to PHMSA and the probable cause
determined by the NTSB was inconsistent in the majority of cases (5/7). Similarly,
cause information summarized from the narrative provided by the operator and that
reported as the official cause in the same PHMSA form was inconsistent in five of
the use of the estimated VSL. The results indicated elimination of all risks to public
health and safety from the U.S. gas distribution system could provide an estimated
Commonly used importance measures were not calculated because this was
not a full probabilistic risk assessment. However, the estimated risk information was
While the industry does not have a specific safety metric, the current gas
distribution system risks were found to exceed acceptable levels. The current
the overall risk across the industry. One way to protect against such events would be
                                          51
to employ a defense-in-depth philosophy by focusing on preventing serious accidents
known to have the potential for high consequences and installing automatic shutoff
happen.
data quality, develop consequence modeling, and consider contributing causes. Once
software [32].
                                          52
Bibliography
[1] M. J. Valencia, "Toll from natural gas disaster in Merrimack Valley passes $1
     billion," 20 February 2019. [Online]. Available:
     https://www.bostonglobe.com/metro/2019/02/20/merrimack-valley-disasters-
     toll-passes-billion/kZWuK2lPsZGh6i2uLigJrN/story.html.
[2] DOT PHMSA, "Source Data," March 2020. [Online]. Available:
     https://www.phmsa.dot.gov/data-and-statistics/pipeline/source-data.
[3] M. Hosmanek, Pipe Line Construction, Austin: University of Texas at Austin,
     1984.
[4] W. Kilbourn, Pipeline, Toronto: Clarke, Irwin & Company, 1970.
[5] M. Mohitpour, T. Van Hardeveld, W. Peterson and J. Szabo, Pipeline Operation
     & Maintenance: A Practical Approach, New York: ASME, 2010.
[6] NaturalGas.org, "Natural Gas Distribution," March 2020. [Online]. Available:
     http://naturalgas.org/naturalgas/distribution/.
[7] L. Lu, W. Liang, L. Zhang, H. Zhang, Z. Lu and J. Shan, "A Comprehensive
     Risk Evaluation Method for Natural Gas Pipelines Combining a Risk Matrix
     with a Bow-Tie Model," Journal of Natural Gas Science and Engineering,
     2015.
[8] Z. Han and W. Weng, "Comparison Study on Qualitative and Quantitative Risk
     Assessment Methods for Urban Natural Gas Pipeline Network," Journal of
     Hazardous Materials, 2011.
[9] Y.-D. Jo and B. J. Ahn, "A Method of Quantitative Risk Assessment for
     Transmission Pipeline Carrying Natural Gas," Journal of Hazardous Materials.
[10] M. Li, Z. Honglong, X. Xue, L. Xue, M. Ai and W. Ma, "Reliability Evaluation
     and Management of PetroChina's Large-Scale System of Natural Gas Pipeline
     Networks," Journal of Natural Gas Geoscience, 2019.
[11] Z. Han and W. Weng, "An Integrated Quantitative Risk Analysis Method for
     Natural Gas Pipeline Network," Journal of Loss Prevention in the Process
     Industries, 2010.
[12] G. DeWolf, "Process Safety Management in the Pipeline Industry: Parallels and
     Differences Between the Pipeline Integrity Management (IMP) Rule of the
     Office of Pipeline Safety and the PSM/RMP Approach for Process Facilities,"
     Journal of Hazardous Materials, 2003.
[13] C. Lam and W. Zhou, "Statistical Analyses of Incidents on Onshore Gas
     Transmission Pipelines Based on PHMSA Database," International Journal of
     Pressure Vessels and Piping, 2016.
[14] D. M. Davies, "Texas Matters: 80 Years Aftern the New London School
     Explosion," March 2017. [Online]. Available: https://www.tpr.org/post/texas-
     matters-80-years-after-new-london-school-explosion. [Accessed March 2020].
                                       53
[15] Natural Gas Pipeline Safety Act of 1968, Pub. L. No. 90-481, 82 Stat. 720,
     1968.
[16] Norman Y. Mineta Research and Special Programs Improvement Act, Pub. L.
     No. 108-426, 118 Stat. 2423, 2004.
[17] 49 U.S.C. §§ 60102, 2018.
[18] "PUC Approves Settlement with UGI in 2011 Allentown Explosion, Increases
     Civil Penalty to $500,000," 24 January 2013. [Online]. Available:
     http://www.puc.pa.gov/about_puc/press_releases.aspx?ShowPR=3105.
     [Accessed March 2020].
[19] NTSB, "Natural Gas-Fueled Building Explosion and Resulting Fire, New York
     City, New York, March 12, 2014," NTSB, Washington, DC, 2015.
[20] NTSB, "Building Explosion and Fire, Silver Spring, Maryland, August 10,
     2016," NTSB, Washington, DC, 2019.
[21] S. Kaplan and B. J. Garrick, "On the Quantitative Definition of Risk," Risk
     Analysis, 1981.
[22] NTSB, "Overpressurization of Natural Gas Distribution System, Explosions,
     and Fires in Merrimack Valley, Massachusetts, September 13, 2018," NTSB,
     Washington, DC, 2019.
[23] R Core Team, R: A language and environment for statistical computing,
     Vienna, Austria: R Foundation for Statistical Computing, 2017.
[24] M. Modarres, M. Kaminskiy and V. Krivtsov, Reliability Engineering and Risk
     Analysis: A Practical Guide, Boca Raton: Taylor & Francis Group, 2010.
[25] E. Arias, "United States Life Tables, 2015," in National Vital Statistics Reports,
     Vol. 67, No. 7, U.S. Department of Health and Human Services, 2018.
[26] M. J. Moran and C. Monje, Guidance on Treatment of the Economic Value of a
     Statistical Life (VSL) in U.S. Department of Transportation Analyses -- 2016
     Adjustment, Washington, DC: DOT, 2016.
[27] A. Mosleh et al., in Proceedings of Workshop on Model Uncertainty, Its
     Characterization and Quantification: Annapolis, Maryland, USA, October 20-
     22, 1993, College Park, 1995.
[28] NRC, Guidance on the Treatment of Uncertainties Associated with PRAs in
     Risk-Informed Decisionmaking, Final Report (NUREG-1855, Rev. 1),
     Washington, DC: NRC, 2017.
[29] NRC, Safety Goals for the Operations of Nuclear Power Plants; Policy
     Statement; Republication, 51 Fed. Reg. 30028, 1986.
[30] ASME, Managing System Integrity of Gas Pipelines: ASME Code for Pressure
     Piping, B31 Supplement to ASME B31.8, New York: ASME, 2010.
[31] PHMSA, "Instructions (rev 10-2014) for Form PHMSA F 7100.1 (rev 10-
     2014)," PHMSA, Washington, DC, 2014.
[32] INL, "Systems Analysis Programs for Hands-on Integrated Reliability
     Evaluations (SAPHIRE)," March 2020. [Online]. Available:
     https://saphire.inl.gov/.
                                          54
[33] NRC, "Historical Review and Observations of Defense-in-Depth (NUREG/KM-
     0009)," NRC, Washington, DC, 2016.
[34] NRC, "An Approach for Using Probabilistic Risk Assessment in Risk-Informed
     Decisions on Plant-Specific Changes to the Licensing Basis (RG 1.174)," NRC,
     Washington, DC, 2018.
[35] ANSI/API, Pipeline Safety Management Systems: ANSI/API Recommended
     Practice 1173, Washington, DC: API, 2015.
[36] C. Jackson and A. Mosleh, "Oil and Gas Pipeline Third Party Damage (TPD) -
     A New Way to Model External Hazard Failure," in Probabilistic Safety
     Assessment and Management PSAM 14, Los Angeles, 2018.
[37] NextEra Energy, "Changing the Current: Algorithms are Saving FPL Millions
     of Dollars," November 2013. [Online]. Available:
     http://www.nexteraenergy.com/pdf/algorithms.pdf. [Accessed April 2020].
55