Estimate Manpower / Manpower
Estimate Manpower /
Manpower
Productivity Rates
Productivity Rates
Specify number of resource needed to
execute specific amount of work
- Total facade panels 3000 panel
- Total panels can be installed by tower
crane per Day 30
Quantity
Duration=
Planning Basic Course by Planningengineer.net No. of Crews X Crew Rate