Concrete Casting Report PIC Manager
- Date : 3 May 2021
- Structure : Top Slab/Wa
- Description : Sta.4+700 to 4+73 - Concrete Type : Class A
- Concrete Volume according to GFC Drawing 96m3
Time Duration Quantity
No. Truck No. Remark
Arrival(A) Start(B) Finish(C) B-A C-B (m3)
1 MT 488 11:25 11:30 11:34 0:05 0:04 6 pump used: PC-067
2 MT 479 11:31 11:35 11:41 0:04 0:06 6
3 MT 498 11:36 11:42 11:49 0:06 0:07 6
4 MT 486 11:40 11:50 12:01 0:10 0:11 6
5 MT 480 11:44 12:02 12:29 0:18 0:27 6
6 MT 488 12:16 12:30 12:42 0:14 0:12 6
7 MT 496 12:27 12:43 12:52 0:16 0:09 6
8 MT 479 12:40 12:53 13:02 0:13 0:09 6
9 MT 498 12:49 13:03 13:14 0:14 0:11 6
10 MT 486 12:58 13:15 13:25 0:17 0:10 6
11 MT 480 1:11 1:26 1:38 0:15 0:12 6
12 MT 488 1:28 1:37 1:46 0:09 0:09 6
13 MT 496 1:37 1:47 1:55 0:10 0:08 6
14 MT 479 1:49 1:58 2:07 0:09 0:09 6
15 MT 498 2:00 2:08 2:22 0:08 0:14 6
16 MT 480 2:47 2:48 3:25 0:01 0:37 5
Total 2:49 3:15 95.00
※ Difference Quantity :
※ Difference Reason
Concrete Casting Report PIC Manager
- Date : 10 May 2021
- Structure : Bottom Slab
- Description : Sta. 4+760 to 4+7 - Concrete Type : Class A
- Concrete Volume according to GFC Drawing 66m3
Time Duration Quantity
No. Truck No. Remark
Arrival(A) Start(B) Finish(C) B-A C-B (m3)
1 MT 478 14:35 14:41 14:49 0:06 0:08 6 pump used: PC-083
2 MT 480 14:47 14:51 14:57 0:04 0:06 6
3 MT 487 14:48 15:00 15:07 0:12 0:07 6
4 MT 498 14:55 15:08 15:15 0:13 0:07 6
5 MT 488 15:01 15:17 15:24 0:16 0:07 6
6 MT 489 15:30 15:32 15:40 0:02 0:08 6
7 MT 478 15:40 15:43 15:51 0:03 0:08 6
8 MT 480 15:51 15:53 16:02 0:02 0:09 6
9 MT 487 16:02 16:04 16:10 0:02 0:06 6
10 MT 498 16:07 16:12 16:20 0:05 0:08 6
11 MT 488 16:16 16:22 16:27 0:06 0:05 6
12 MT 489 16:50 16:52 16:55 0:02 0:03 1.5
Total 1:13 1:22 67.5
※ Difference Quantity : - 1.5m3
※ Difference Reason was due to actual thickness and uneven lean concrete surface
Concrete Casting Report PIC Manager
- Date : 12 May 2021
- Structure : Lean Concrete
- Description : Sta. 4+640 to 4+6 - Concrete Type : Type C
- Concrete Volume according to GFC Drawing 19m3
Time Duration Quantity
No. Truck No. Remark
Arrival(A) Start(B) Finish(C) B-A C-B (m3)
1 MT 478 3:00 3:04 3:11 0:04 0:07 6 pump used: PC-083
2 MT 480 3:01 3:14 3:19 0:13 0:05 6
3 MT 487 3:04 3:22 3:31 0:18 0:09 6
4 MT 498 3:45 3:47 3:54 0:02 0:07 6
5 MT 488 4:14 4:15 4:57 0:01 0:42 2
Total 0:38 1:10 26.00
※ Difference Quantity :