CM CHK
CM CHK
TABLE OF CONTENTS
Topic                                                                    Page
Purpose and Introduction                                                     1
Methods                                                                      2
Site Visit Agenda                                                            4
Project Information Data Sheet                                               5
Project Assessment Worksheet                                                 6
Environmental, Safety, & Health Assessment                                   8
Prime Contracts Administration Assessment                                   10
Construction Quality Assessment                                             11
Client Satisfaction Assessment                                              12
Constructability Assessment                                                 13
Construction Automation Tool Assessment                                     14
Construction Tool and Equipment Assessment                                  16
Materials Management Assessment                                             18
Cost Control - Planning Phase Assessment                                    19
Cost Control - Execution Phase Assessment                                   20
Construction Organization Assessment                                        21
Craft Worker Management - Planning Phase Assessment                         22
Craft Worker Management - Execution Phase Assessment                        23
Non-Manual Personnel Management Assessment                                  24
Schedule Control - Planning Phase Assessment                                26
Schedule Control - Execution Phase Assessment                               27
Security Management Assessment                                              28
Subcontracts Management Assessment                                          29
Emergency Planning                                                          31
System Completion and Turnover                                              32
                                                                            TOC
Construction Manager
Project Assessment Guidelines
Purpose
This handbook provides the Construction Manager assistance in managing the construction phase
of a project and establishes a convenient method of assessing job performance using metrics
applicable to project goals and objectives. The Construction Manager can then use this data to:
•   Identify and document areas that require special attention and/or resolution.
•   Provide a basis of communicating job status, areas of concern, and corrective actions to others.
Introduction
It is vital to the successful completion of the construction effort that all participants and activities
included in the Construction Execution Plan are monitored and evaluated on a continuing basis
throughout the entire construction phase.
                                                                                                           1
Construction Manager Project Assessment Guidelines
Methods
The elements of a Construction Execution Plan which contribute to project success generally
include:
•   Environmental, Safety, & Health
•   Prime Contract Administration
•   Construction Quality
•   Client Satisfaction
•   Constructability
•   Construction Automation Tools
•   Construction Tools and Equipment
•   Cost Control - Planning Phase
    Cost Control - Execution Phase
•   Construction Organization
•   Craft Worker Management - Planning Phase
    Craft Worker Management - Execution Phase
•   Non-Manual Personnel Management
•   Schedule Control - Planning Phase
    Schedule Control - Execution Phase
•   Security Management
•   Subcontracts Management
•   Emergency Planning
•   System Completion and Turnover
Project work process procedures and reporting methods should be designed to provide the project
team with end product information and data to aid in the project decision making process. Collecting
useful data, correctly interpreting the data, and making timely decisions are essential to successfully
completing the project.
To assist the Construction Manager in developing an effective Construction Execution Plan, this
handbook provides a series of performance guidelines addressing key areas of project planning and
execution. Since no set of guidelines or checklists can be all inclusive, the Construction Manager is
expected to exercise judgment in the use of this or any other set of standard guidelines.
Prior to visiting a construction site, the Construction Manager should develop a list of items to review
based on:
•   Prime Contract
•   Project Management Reports
•   Safety Performance Reports
•   Jobsite Progress Reports
•   Construction Execution Plan review
•   Jobsite Communications
2
                                                    Construction Manager Project Assessment Guidelines
• Client Communications
The Performance Guidelines included in this handbook provide one method of developing a list of
items to review. The following factors should be considered during the project evaluation process:
                                                                                                     3
Construction Manager Project Assessment Guidelines
4
                                                             Construction Manager Project Assessment Guidelines
CONSTRUCTION MANAGER:
SITE MANAGER:
FIELD SUPERINTENDENT:
CLIENT CONTACT(S):
CONSTRUCTION SCHEDULE:
START:                                                    COMPLETE:
PEAK WORKFORCE:
MANUAL:                                                   NON-MANUAL:
                                                                                                             5
Construction Manager Project Assessment Guidelines
                                                                     RATING SCALE
                                            Poor                                                        Excellent
Environmental, Safety, & Health              1       2    3      4        5      6        7      8     9        10
Prime Contract Administration                1       2    3      4        5      6        7      8     9        10
Construction Quality                         1       2    3      4        5      6        7      8     9        10
Client Satisfaction                          1       2    3      4        5      6        7      8     9        10
Constructability                             1       2    3      4        5      6        7      8     9        10
Construction Automation Tools                1       2    3      4        5      6        7      8     9        10
Construction Tools and Equipment             1       2    3      4        5      6        7      8     9        10
Materials Management                         1       2    3      4        5      6        7      8     9        10
Cost Control - Planning Phase                1       2    3      4        5      6        7      8     9        10
Cost Control - Execution Phase               1       2    3      4        5      6        7      8     9        10
Construction Organization                    1       2    3      4        5      6        7      8     9        10
Craft Worker Management - Planning Phase     1       2    3      4        5      6        7      8     9        10
Craft Worker Management - Execution Phase    1       2    3      4        5      6        7      8     9        10
Non-Manual Personnel Management              1       2    3      4        5      6        7      8     9        10
Schedule Control - Planning Phase            1       2    3      4        5      6        7      8     9        10
Schedule Control - Execution Phase           1       2    3      4        5      6        7      8     9        10
Security Management                          1       2    3      4        5      6        7      8     9        10
Subcontracts Management                      1       2    3      4        5      6        7      8     9        10
Emergency Planning                           1       2    3      4        5      6        7      8     9        10
System Completion and Turnover               1       2    3      4        5      6        7      8     9        10
Comments:
6
                 Construction Manager Project Assessment Guidelines
                                                                 7
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                 STANDARDS
ENVIRONMENTAL, SAFETY, & HEALTH ASSESSMENT
                                                                                                                 EXCEEDS
                                                                                                     MEETS
                                                                                       NEEDS
1.   Orientation:
     • An environmental, safety, and health orientation program has been
         implemented on the project
     • The orientation covers new employees, supervisors, and site visitors
     • The orientation covers all applicable project and corporate safety, health,
         and environmental issues
2.   ES&H Programs and Processes:
     • The self-assessment program is in place
     • A worker incentive program is in place
     • The project team has access to the most recent revision of the
        Environmental, Safety, & Health Core Processes Manual
     • The project is committed to the zero accidents philosophy
     • The Safe Worker Observation (SWOP) Program is properly implemented
     • The Back Injury Prevention Program is in place and properly implemented
     • Employee disciplinary actions are initiated for safety violations
     • A construction environmental control plan is in place and is being
        implemented
     • A safety task/job hazard analysis program is in place and being implemented
        on the project
3.   Meetings:
     • Weekly safety tool box meetings are conducted on the project
     • A project safety committee is in place and is being effectively used
     • A weekly project safety tour is jointly conducted by the responsible
        superintendent and ES&H representative
     • Safety is discussed at weekly work planning meetings
     •   Site Manager fully participates in the implementation of the ES&H program
4.   Administration:
     • Project records are maintained documenting receipt of safety information
        and attendance at safety meetings and safety training
     • Minutes are taken at all safety meetings documenting assigned action items
     • All supervisors are aware of the way in which safety statistics are collected
        and assessed and on the high cost of project accidents
     • A medical management/workers’ compensation program is in place
     • All supervisory personnel understand the regulatory information required to
        be completed in the case of accidents and their possible personal legal
        involvement.
     • Subcontractor ES&H programs are in place
8
                                                           Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                      STANDARDS
ENVIRONMENTAL, SAFETY, & HEALTH ASSESSMENT
                                                                                                                      EXCEEDS
                                                                                                          MEETS
                                                                                            NEEDS
(continued)
5.   Site Conditions:
     • Housekeeping adequate
     • Scrap collection and clean-up schedules implemented
     • Ladders, scaffolds, suspended personnel work platforms, etc. properly used
     • Personnel protective equipment in use at the site
6.   Does the site specific Environmental, Safety, & Health action plan include up to
     date information on actions to take in case of emergencies?
     • Are all superintendents who may be on site during off hours aware of
         required actions in the event of both emergency and non-emergency
         situations?
     • Are preferred hospitals, clinics, and doctors been identified?
     •   Are emergency notification lists posted?
     •   Do the emergency notification lists identify the site personnel to notify in the
         event of a serious accident, work stoppage, environmental event or natural
         event such as a tornado, hurricane, or earthquake?
     •   Do emergency notification lists include both work and home phone numbers?
7.   Documentation:
     • Employee files complete including records of orientation training, safety
        seminars, special training, disciplinary action or warnings, workers’
        compensation claims, first aid, and medical treatments
     • Accident reports are complete including type of accident, date, time,
        location, weather, trades involved, name of who was injured, property
        damage, accident details, etc.
     • Project accident documentation used to look for accident trends
     • All safety records and reports comply with corporate core processes manual
     • Records maintained of all government agency visits to the site
     • Records maintained or all directly or indirectly related project incidents (e.g.
        fires, storms, floods, power outages, etc.)
8.   Display:
     • Safety warning posters properly displayed
     • Employee feedback, recognition, and safety slogans prominently on display
9.   Training:
     • Environmental, safety, and health training programs in place
     • Supervisory personnel have completed the safety leadership training and
         environmental compliance workshop
10. Client:
    • Client participates in the project safety program
    • Client’s safety program integrated into the project safety execution plan
    • Client personnel attend project safety meetings
    • The client is represented on the project safety committee
                                                                                                                                  9
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                  STANDARDS
PRIME CONTRACT ADMINISTRATION ASSESSMENT
                                                                                                                  EXCEEDS
                                                                                                      MEETS
                                                                                        NEEDS
1.   A copy of the conformed prime contract is available at the site.
2.   A prime contract division of responsibility (DOR) matrix has been prepared in
     accordance with the Bechtel Prime Contracts Administration Manual, a.k.a. the
     “Red Book”
      • A copy of the DOR is available at the site
      • The construction team is aware of its prime contract administration
          responsibilities
3.   A kick-off meeting has been held with project team members to develop
     consensus on project team member responsibilities
     • The Site Manager participated in the kick-off meeting and is knowledgeable
          of construction responsibilities
4.   The Site Manager is familiar with the duties and responsibilities of the project
     Prime Contract Administrator (if one has been assigned on the project)
5.   The Site Manager is aware of the results of the detailed contract compliance
     matrix review performed by the Prime Contract Administrator (if one has been
     performed on the project)
10
                                                          Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                  STANDARDS
CONSTRUCTION QUALITY ASSESSMENT
                                                                                                                  EXCEEDS
                                                                                                      MEETS
                                                                                        NEEDS
1.   Corporate construction manual information available at the site:
     • Site Managers Manual
     • Field Engineering Manual
     • Construction Quality Manual
     • Bechtel Quality Control Manual (BQCM)
2.   Applicable code information available at the site
3.   Construction procedures prepared and implemented
     • Procedure development and approval
     • Duties and responsibilities
     • Construction training
     • Document control
     • Survey control plan
     • Heavy lift rigging
     • Control of Materials and Test Equipment (M&TE)
     • Construction quality inspections and documentation
     • Control of deficient items
     • Construction completion and turnover
     • Document retention and turnover
4.   Latest Issued for Construction (IFC) drawings available and used by construction
     work force
5.   Material receipt inspection procedure implemented
6.   Material warehousing and storage controls implemented
7.   Project procedures implemented to control the installation of specific
     commodities
     • Excavation and backfill
     • Concrete placement
     • Underground piping
     • Above ground piping
     • Hydrostatic testing
     • Mechanical equipment
     • Electrical equipment
     • Electrical cables and terminations
     • Electrical raceway
     • Instrumentation
8.   Construction manual and non-manual personnel skills evaluated and appropriate
     skills training implemented to ensure quality
                                                                                                                        11
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                             STANDARDS
CLIENT SATISFACTION ASSESSMENT
                                                                                                             EXCEEDS
                                                                                                 MEETS
                                                                                   NEEDS
1. Site manager/client rapport
12
                                                           Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                   STANDARDS
CONSTRUCTABILITY ASSESSMENT
                                                                                                                   EXCEEDS
                                                                                                       MEETS
                                                                                         NEEDS
1. A formalized project constructability plan in place
2. Constructability during the planning stage
   • A constructability coordinator has been assigned
   • Constructability is part of the Project Execution Plan in engineering,
      procurement, and construction
   • Each project account been addressed to ensure that the best construction
      work method is used
   • Outside sources been used to assist in the constructability process in specialty
      areas (e.g. modularization)
   • All project team members have been solicited to contribute constructability
      ideas and each idea has been evaluated or used
   • Formal construction plans been prepared for each major segment of the work
      and cost evaluation methods are used to consider project alternates
3. Constructability during the execution stage
   • A constructabilty coordinator has been identified
   • Constructability methods and options discussed at planning meetings
   • The construction execution team is continually challenged looking for better
      work methods
   • Help solicited from both non-manual and manual project team members
      looking to improved constructability methods
   • Repetitive work processes are reviewed for optimization
   • Productivity engineering methods used to evaluate construction processes
4. Each project account been addressed
5. Constructability is an integral part of the construction planning process
6. New methods are cost justified
7. Formal project lessons learned are prepared and submitted to central construction
8. The full project team is engaged in the implementation of the constructability plan
                                                                                                                         13
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                      STANDARDS
CONSTRUCTION AUTOMATION TOOL ASSESSMENT
                                                                                                                      EXCEEDS
                                                                                                          MEETS
                                                                                            NEEDS
1.   Project Automation Plan
     • The project has prepared a detailed construction project site automation plan
         that is integrated into the overall project automation plan.
     • The plan includes a description of the hardware, software, and
         communication systems that will be used on the project.
2.   Project Automation Budget
     • The construction project has prepared a detailed construction automation
         budget based on the project site automation plan which forecasts the costs of
         implementing the construction automation plan.
     • This budget has been approved by the Site Manager, Construction Manager,
         and Project Manager.
3.   The project has established a project site Local Area Network (LAN) that
     interconnects on-site computers to facilitate communications and sharing of
     information by the project team.
4.   The project has established a project link from the construction site to the Bechtel
     Wide Area Network (WAN)
5.   The project is using an Electronic Mail (E-Mail) service to the site.
6.   The project is using a Windows 3.1 or later operating system at the site.
7.   The project team is using the Microsoft Office suite of applications including:
     Word 6.0 for word processing, Excel 5.0 for spreadsheets, Access 2.0 for
     databases, and PowerPoint 4.0 for presentations.
8.   The project has used Primavera to develop a fully integrated EPC critical path
     project schedule.
     •   The schedule is integrated with the model via 4DPlanner
9.   The project uses PCWorks for earned value reporting and project progress
     evaluation.
10. The project team is using SETROUTE to control the design, procurement, and
    installation of electrical and instrument cables, terminations, and devices.
     • The use of SETROUTE is prescribed in the engineering automation plan in
         addition to the construction automation plan.
11. The project team is using the Pipeline (or TEAMWorks) application to track and
    manage tagged components throughout the EPC process.
    • Engineering provides fully populated Pipeline databases listing all tag
        numbered components that must be installed.
    • Component databases are maintained by engineering for: Pipe Spools, Pipe
        Hangers, Valves, Mechanical Equipment (Pumps, Tanks, etc.), and
        Instruments
    • When piping is modeled in a 3D application, field welds must be shown in
        the 3D model to facilitate the extraction of a pipe spool and field weld
        Pipeline database directly from the 3D CAD model.
14
                                                         Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                   STANDARDS
CONSTRUCTION AUTOMATION TOOL ASSESSMENT
                                                                                                                   EXCEEDS
                                                                                                       MEETS
                                                                                         NEEDS
(continued)
12. The project uses the Procurement Tracking System (PTS) at the construction site
    to manage materials at the site.
     • All site Field Material Requisitions must be prepared, approved, and routed
        to Procurement electronically via PTS
     • Material Receiving Reports must be prepared in PTS
     • Bulk field material inventories must be maintained in PTS
     • Bechtel standard stock codes are used for bulk and consumable materials
     • Material Withdrawal Requests (MWR) must be prepared using PTS
     • Additionally, engineering must provide sufficient design information such as
        detailed material takeoffs by design drawing to enable the full use of the PTS
        application.
13. The project has implemented the use of an accepted field accounting application
    at the site to track payable and labor costs (Timberline for work in the United
    States and Oracle Financials for work outside the United States).
14. The project site uses 2D CAD to view design documents, extract coordinate data
    from design documents, and prepare field sketches and as-builts.
15. The project uses 3D CAD for basic project design and the construction team uses
    3D CAD at the construction site to view design documents and extract coordinate
    data from design documents.
    • The model is broken down by building volumes consistent with the facility
        area/building numbering system.
    • Field welds for piping systems are shown in the model to facilitate
        constructability input and to extract isometric drawings.
    • Field welds are located to reduce construction costs.
    • Each component, including spools, pipe hangers, instruments, and valves,
        must be provided with a unique identification number (CIN) that can be used
        for materials management tracking.
    • Interference checks are routinely run by engineering during the development
        of the 3D model to identify and correct interference problems.
    • All underground commodities are modeled to avoid interferences.
16. The project site uses 3D visualization via WALKTHRU or similar application.
17. The project has access to the OLRL and/or BecWeb at the site through direct
    dial-in access or through the Construction Information Source CD.
18. The project uses Bechtel standard survey technologies and work practices:
    • The project uses the Bechtel Remote As-Built System where appropriate to
        collect as-built coordinate data on projects that involve modifications to
        existing facilities.
    • Engineering models all designs to scale to allow survey coordinate data
        extraction.
19. ALPS is used during the project planning phase to evaluate plot plan layouts and
    to evaluate rigging methods.
                                                                                                                         15
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                 STANDARDS
CONSTRUCTION TOOL AND EQUIPMENT ASSESSMENT
                                                                                                                 EXCEEDS
                                                                                                     MEETS
                                                                                       NEEDS
1. Equipment selection
   •   Bechtel Equipment Operations has participated in heavy lift rigging studies
       and equipment planning
   •   Formal project equipment list and schedule prepared and approved by the
       Project Manager
   •   Climatic and other geographic conditions considered in project equipment
       selection
   •   Jobsite operating environment considered in equipment selection
   •   Spare parts availability considered in equipment selection using information
       obtained from Bechtel Equipment Operations
   •   Bechtel Equipment Operations assisted in the decision to rent, lease, or
       purchase project equipment made
   •   Equipment selection considered maintenance requirements using data
       supplied by Bechtel Equipment
   •   Equipment standardization considered in selection process to minimize
       maintenance and spare parts inventories
   •   Sophistication of selected equipment appropriate for the skills of the local
       operators and mechanics
   •   Equipment selection maximize the use of the Bechtel fleet
   •   Equipment schedule matches manpower staffing and equipment forecasts
       (e.g. welders to welding machines)
2. Equipment allocation
   •   Allocation of equipment to individual superintendents or tasks conform to the
       preplanned equipment schedules
   •   Equipment maintenance schedules show scheduled routine, periodic, and
       preventative maintenance and inspections
   •   Periodic equipment meetings held with the responsible discipline and
       equipment superintendents to plan usage and resolve conflicts
   •   Periodic reports made to Site Manager to report equipment operating and
       down time
3. Equipment planning meetings held
4. Equipment schedules maintained
5. Equipment utilization
   •   Procedure developed and implemented to monitor equipment utilization to
       determine when under-utilized equipment should be surplused
   •   Daily meetings are held to review equipment usage, allocation, selection, and
       surplus actions
   •   Independent observations of mobile equipment being used to determine
       utilization
6. Personal field observations - equipment utilization, condition, etc.
16
                                                         Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                 STANDARDS
CONSTRUCTION TOOL AND EQUIPMENT ASSESSMENT
                                                                                                                 EXCEEDS
                                                                                                     MEETS
                                                                                       NEEDS
(continued)
7. Operator skills are adequate
   •   Equipment operators certified and/or qualified to operate project equipment
8. Operator training is adequate
9. Equipment maintenance
   •   A formal equipment maintenance program implemented for equipment
       maintenance
   •   A maintenance file has been established for each piece of equipment
   •   Formal daily maintenance checks performed for each piece of equipment
   •   Lube and oil change requirements established for each piece of equipment
       and are being followed
   •   Required preventative maintenance is being implemented
   •   An equipment repair process has been developed and implemented
   •   A fuel and lubricant inventory control process been developed and
       implemented
   •   A spare parts inventory control process been developed and implemented
   •   Each equipment file contains applicable operating manuals, manufacturer
       parts lists and repair manuals, capacities, rental rates (if applicable),
       historical records, maintenance costs (labor, parts, and supplies), available
       equipment, and equipment utilization
   •   An equipment maintenance training program been established (if required)
   •   Equipment repair records have been maintained
10. Spare parts inventory maintained
11. Maintenance checklists used
12. Equipment files maintained
13. Required equipment reports issued
14. Surplus equipment released in a timely manner
15. Control of off-site usage of company vehicles
                                                                                                                       17
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                  STANDARDS
MATERIALS MANAGEMENT ASSESSMENT
                                                                                                                  EXCEEDS
                                                                                                      MEETS
                                                                                        NEEDS
1. Is their a written Division of Responsibility between Design and Field Engineering
   for material responsibilities?
     • Responsibility for Take-Off of Bulk Materials
     • Fabricator technical coordination
     • Review and approval of fabrication drawings
     • Scheduling material deliveries
18
                                                         Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                STANDARDS
COST CONTROL - PLANNING PHASE ASSESSMENT
                                                                                                                EXCEEDS
                                                                                                    MEETS
                                                                                      NEEDS
1. Construction input to project estimates
     • Productivity analysis - confirm appropriate standards used
     • Height and congestion
     • Construction Tools and Equipment
     • Non-manual staffing
     • Temporary facilities
     • Subblock definition
     • Tools and consumables
     • Craft wage rates
     • Escalation
     • Contingency
2. Trend program used to evaluate and track constructability program cost savings
                                                                                                                      19
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                   STANDARDS
                                                                                                                   EXCEEDS
                                                                                                       MEETS
                                                                                       NEEDS
1.   Implement, participate, and contribute to all project cost management efforts.
2.    Construction cost control program
     • Distributable cost control
     • Quantity installation curves
     • Project staffing curves
     • Weekly cost review
     • Identifying cost trends
3.   Site process in place for installed quantity reporting
4.   Use of all cost control work processes as outlined in the Principles of
     Construction Controls
5.   Effectiveness in motivating project team in complying with the cost control
     program
6.   Effectiveness in identifying and mitigating construction cost risk areas
7.    Management of cost changes including:
     • Proper consideration of change impact in change order pricing
     • Changes approved prior to starting work
8.   Understanding the final contract and commercial terms, protecting profitability
9.   Effective implementation of a project cost savings program
20
                                                             Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                     STANDARDS
CONSTRUCTION ORGANIZATION ASSESSMENT
                                                                                                                     EXCEEDS
                                                                                                         MEETS
                                                                                           NEEDS
1.   Effectiveness of construction field organization considering the size, complexity,
     and type of project (direct hire, construction management, etc.)
     • Supervisor percentage
     • Field Engineering percentage
     • Technical Services percentage
     • Field Procurement percentage
     • Field Accounting percentage
2.   Effectiveness in using central construction organization
     • Construction Manager
     • Field Contracts Manager
     • Construction Specialists (rigging, survey technologies, etc.)
     • Environmental, Safety, & Health Manager
3.   Effective use of the project organizational matrix
     • Project Manager
     • Engineering Manager
     • Procurement Manager
     • Business Manager
4.   Effective use of new hires and college graduates in the field organization
5.   Field organization chart or staffing plan reflects the following for each position:
     • Position number
     • Position title
     • Name of person
     • Date required
     • Planned release date
     • Single or family status (where applicable)
6.   Field organization chart to reflect:
     • Job number
     • Project title
     • Project location
     • Drawing number
     • Revision number and date
     • Reporting relationships for each functional area
7.   Is project organizational data kept current and distributed to both functional and
     project organization team members (e.g. Project Manager, Construction
     Manager, etc.)
8.   Site Manager conducts regular project team meetings
9.   Effectiveness of non-manual career development and training
                                                                                                                           21
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                 STANDARDS
CRAFT WORKER MANAGEMENT - PLANNING PHASE
                                                                                                                 EXCEEDS
                                                                                                     MEETS
                                                                                       NEEDS
ASSESSMENT
22
                                                             Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                    STANDARDS
CRAFT WORKER MANAGEMENT - EXECUTION PHASE
                                                                                                                    EXCEEDS
                                                                                                        MEETS
                                                                                          NEEDS
ASSESSMENT
                                                                                                                          23
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                   STANDARDS
NON-MANUAL PERSONNEL MANAGEMENT
                                                                                                                   EXCEEDS
                                                                                                       MEETS
                                                                                         NEEDS
ASSESSMENT
1.   Site Manager has access to latest revision of Personnel Policies Manual and
     ensures policies are fairly applied at the site
2.   Site Manager fairly applies project specific employee conditions
3.   Site Manager implements required policy approvals for employee travel
4.   Field organization chart updated monthly and transmitted to Construction
     Manager
5.   Non-manual staffing chart updated monthly and transmitted to Construction
     Manager
6.   Non-manual personnel requisitions
     • Issued for all construction non-manual personnel
     • Requisitions initiated in advance of required need date (at least 60 days prior
        to need)
7.   Recruitment
     • Site Manager has current and accurate status on all open requisitions
     • Requisitions for critical open positions are given special attention
     • Local recruitment is implemented per corporate policy
8.   Job descriptions including work standards are in place for each non-manual
     position
9.   Current Individual Performance Management (IPM) forms are in place for each
     non-manual employee
     • Prepare a new IPM for each employee at the start of the project assignment
     • Review IPM with each employee at least once a year and/or at the conclusion
       of the assignment
     • IPM’s address individual employee development plans
     • Obtain copies of previous assignment IPM’s for information
10. Career discussions are provided for non-manual employees upon request
11. Project employee development plan in place and being implemented:
     • Employees have access to and use the Construction Employee Development
       Handbook
     • Site Manager obtains completed training records from HRIS for each
       employee
     • Construction Employee Development Handbook used to prepare employee
       development plans
     • Project takes advantage of construction training workshop opportunities to
       enhance employee development
12. Replacement planning information for key project assignments maintained by the
    Site Manager and provided to the Construction Manager upon request
24
                                                         Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                STANDARDS
NON-MANUAL PERSONNEL MANAGEMENT
                                                                                                                EXCEEDS
                                                                                                    MEETS
                                                                                      NEEDS
ASSESSMENT (continued)
                                                                                                                      25
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                    STANDARDS
SCHEDULE CONTROL - PLANNING PHASE
                                                                                                                    EXCEEDS
                                                                                                        MEETS
                                                                                          NEEDS
ASSESSMENT
26
                                                          Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                    STANDARDS
SCHEDULE CONTROL - EXECUTION PHASE
                                                                                                                    EXCEEDS
                                                                                                        MEETS
                                                                                          NEEDS
ASSESSMENT
                                                                                                                          27
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                  STANDARDS
SECURITY MANAGEMENT ASSESSMENT
                                                                                                                  EXCEEDS
                                                                                                      MEETS
                                                                                        NEEDS
1.   Security procedures appropriate for the site have been prepared and
     implemented
2.   Security personnel review new hire orientation and are familiar with site
     procedures
3.   Security personnel enforce security rules effectively
4.   Security rules are posted at the site
5.   Security personnel have received fire prevention and fire fighting training
6.   Time clocks are used by security personnel after normal working hours
     • Security clocks are routinely monitored to ensure security checks are made
7.   Security occurrence reports are concise and timely
     • Occurrence report follow-up actions are adequate
8.   Lost/stolen tool report file is reviewed/analyzed on a regular basis
     • The project tracks the dollar value of tools and equipment attributed to theft
         or unexplained loss
9.   The site procedure for the control of vehicle site entry/exit is adequate
10. A log of jobsite equipment exit/re-entry is maintained including equipment
    identification number, operator name, date and time of exit, date and time of
    re-entry, purpose of off-site travel, and authorization signature
11. The site procedure for the control of site visitors is effective and adequate
12. Procedure for control of material entering/exiting the site is adequate and
    effective
    • Material documents contain required authorization signatures
    • Material documentation is checked against load contents
13. Tool issue and control procedure is effective and adequate
    • Company owned tools are properly marked or identified
14. A listing of employee and subcontractor owned tools is maintained
    • Employee and subcontractor tool boxes are checked against tool lists when
         employees and subcontractors exit the site
15. Effective gate control procedure implemented for the entry and exit of
    subcontractor personnel
    • Control of subcontractor materials, equipment, tools, and supplies entering
        and exiting the site is effective and adequate
28
                                                          Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                     STANDARDS
SUBCONTRACTS MANAGEMENT ASSESSMENT
                                                                                                                     EXCEEDS
                                                                                                         MEETS
                                                                                           NEEDS
1.   All subcontract administration procedures in compliance with the Bechtel
     Contract/Subcontract Management Manual or “Brown Book”
     • Deviations (e.g., client preferences) approved by Manager of Contracts
2.   Subcontract formation procedures in compliance with Bechtel Contract/
     Subcontract Formation Manual or “Blue Book”
     • Deviations (e.g., client preferences) approved by Manager of Contracts
3.   Current version of PROFISY used for Bechtel subcontract terms and conditions,
     “Bechtel Proforma”
      • Deviations approved by the Regional Manager of Procurement
4.   Subcontracts administrative controls effective and adequate
     • Administration procedures in place
     • Division of responsibility (DOR) prepared and approved
     • Request for Information (RFI) and Pending Issues (PI) procedure in place
5.   Signature Authorizations for subcontract changes delegated by BCOI - Manager
     of Contracts per Corporate Policy 230
6.   Standard subcontract administration forms used.
7.   Subcontracts Operations Reviews performed at 20% and 70% construction
     complete milestones
8.   Subcontractors not allowed site access until insurance certificates have been
     reviewed and approved by the Subcontract Administrator and Risk Management
     (if required)
9.   Pre-Construction Meeting (PCM) held and formal kick-off letter issued prior to the
     start of any Jobsite work (refer to Exhibit 3.3.2-B of the Brown Book)
     • Authorized Representative (AR) named for each subcontractor
     • AR is present/represented at all times when its forces are at the site
     • Bechtel and/or Bechtel client representatives introduced at PCM and
          documented in the kick-off letter, along with any limitations on the authority
          of the Bechtel Representatives
10. Latest approved subcontractor schedule reconciled against the integrated project
    EPC schedule
    • Schedule discrepancies have been explained and documented
    • Subcontractor schedule is in proper format (i.e. CPM, barchart, resource
        loaded, etc.) and has been formally dispositioned and returned to the
        subcontractor
11. Incoming and outgoing correspondence and appropriate actions are tracked
12. Subcontractor progress routinely reviewed against approved schedule
    • Corrective actions taken to correct subcontractor schedule slippages
    • Corrective actions taken to correct project schedule slippages which could
       impact subcontractor work activities
                                                                                                                           29
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                  STANDARDS
SUBCONTRACTS MANAGEMENT ASSESSMENT
                                                                                                                  EXCEEDS
                                                                                                      MEETS
                                                                                        NEEDS
(continued)
13. Extra work orders and change notices properly reviewed and approved per Policy
    230 requirements prior to starting work
14. Daily reports are promptly prepared and are adequate in detail
    • Follow-up action items noted
    • Follow-up actions tracked until complete and resolution noted in daily report
    • A daily report prepared for each project work day
15. Weekly or bi-weekly subcontract progress review meetings are conducted
    • Action items identified at meetings are documented and tracked until
       resolved
    • Copies of meeting notes are prepared and distributed to the subcontractor,
       Site Manager, Project Manager, and client (if required)
16. Subcontractor invoices paid in a timely fashion
    • Release certification (lien releases) processes
    • Evidence of material supplier invoice payments available
17. Backcharge procedure in place and implemented
    • Backcharges properly documented and tracked through to collection
18. Prior to formal subcontract close-out, electronic copies of subcontract scope and
    reimbursement terms sent to the Manager of Contracts
19. Project files contain essential documents:
    • Conformed subcontract
    • Valid insurance certificates
    • Performance and payment bonds (if required)
    • Correspondence logs
    • Baseline approved subcontract schedule
    • Daily reports
    • Subcontractor force reports
    • Meeting notes including pre-construction and progress review meeting notes
    • Reports of work interruptions
    • Formation group files
    • Subcontractor Requests for Information (RFI)
    • Extra Work Orders, Change Orders, and Change Notices
    • Invoice reviews
    • 3 or 4 week work plan schedules
    • Subcontract amendments
    • Policy 230 authorizations
    • Material assignment schedule
    • Approved subcontractor submittals
    • Notice of authorized representatives
    • Subcontractor safety and accident reports
30
                                Construction Manager Project Assessment Guidelines
                                                                               31
Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                   STANDARDS
EMERGENCY PLANNING ASSESSMENT
                                                                                                                   EXCEEDS
                                                                                                       MEETS
                                                                                         NEEDS
1.   A project Emergency Contingency Plan has been prepared
     • A copy of the plan is available at the site
     • Construction team members are knowledgeable about the details of the plan
2.   Employee and dependent information is complete and current
3.   The Emergency Contingency Plan is reviewed annually to ensure it is current
4.   The list of personnel to be contacted in the event of an emergency is current and
     available to all construction team members
     • Project Manager
     • Construction Manager
     • Manager of Construction
     • Senior Regional Manager
     • Manager of Region/Corporate Security
5.   The project emergency plan lists specific actions to take in the event of:
     • Earthquake
     • Hurricane
     • Tornado
     • Flash flood
     • Fire
     • Severe cold temperatures
     •   Heavy snow/blizzard conditions
     •   A major accident
     •   Local unrest
6.   The project has an adequate supply of emergency equipment and supplies for
     use during potential emergencies
7.   A current list of emergency services is maintained and is available for all
     construction team members:
     •   Ambulance service
     •   Fire department
     •   Police
     •   Rescue squad
     •   Hospital/doctor
     •   Corporate Security hotline
8.   Country evacuation procedures developed and approved by corporate security if
     required
      • Current list of employee and dependent names, home addresses, and home
         telephone numbers maintained and is readily available
32
                                                         Construction Manager Project Assessment Guidelines
IMPROVEMENT
STANDARDS
                                                                                                                  STANDARDS
SYSTEM COMPLETION AND TURNOVER ASSESSMENT
                                                                                                                  EXCEEDS
                                                                                                      MEETS
                                                                                        NEEDS
1.   System scoping boundaries have been assigned to all project systems,
     equipment, and facilities
     • System scoping has been reviewed and accepted by construction, startup,
         and/or the client as appropriate
2.   Specific startup system assignment can be readily determined for each project
     component
3.   An integrated construction/startup project completion schedule has been
     developed for each project system
     • System turnover milestone dates have been established for each system
4.   A formal project completion and turnover procedure has been developed and is
     being implemented on the project
5.   Walkdowns are performed on each system to verify the status of the construction
     work
     • A formal work completion punchlist is maintained for each system
     • Completed punchlist items are verified to be complete and signed off on the
         system punchlist
6.   Project documentation (including inspection records, test records, and open
     nonconformances) is reviewed and verified to be complete prior to system
     turnover
      • Incomplete documentation is listed on the system punchlist and tracked until
         complete
7.   A joint construction/startup/client walkdown is performed when all work is
     complete and the system is presented for final acceptance
     • Responsible construction/startup/client personnel mutually agree on work
          items that are not required to be completed prior to final turnover
8.   A formal turnover package is prepared for each system turnover which includes
     releasing and acceptance signatures
9.   Following turnover, required system jurisdictional boundary tagging is performed
     as required by project procedures
33