Part 7b
Reinforcement
in Pad Footing
Prepared by:
Dr. Sylvia Gala anak Mong @ Agam
Taking off list
•   Excavation                                    • Stump
    • Excavate to reduce level             m3        • Concrete in stump                 m3
    • Remove excavated material            m3        • Formwork to side of stump         m2
    • Excavate pit for pad foundation      m3
    • Remove excavated material            m3        • Reinforcement bar in stump        kg
    • Excavate in rock                     m3        • Links in stump                    kg
    • Filling to excavation                m3
    • Excavate trench for ground beam      m3     • Ground Beam
    • Remove excavated material            m3
                                                    • Concrete blinding to ground beam   m3
    • Excavate in rock                     m3
    • Disposal of surface water                     • Concrete in ground beam            m3
            Item                                    • Formwork to sides of ground beam   m/m2
                                                    • Reinforcement bar in ground beam   kg
• Pad Footing                                       • Stirrups in ground beam            kg
   • Concrete blinding to pad foundation   m3
   • Concrete in pad foundation            m3
   • Formwork to sides of foundation       m/m2   • Ground Slab
   • Reinforcement bar in foundation       kg       • Hardcore                           m2/m3
                                                    • DPM                                        m2
                                                    • Concrete bed                       m3
                                                    • BRC                                m2
Drawings
Calculation
Calculation
Calculation
Calculation
Heading:                                          Element:   Slip No.
Reinforcement to pad foundation                   wblff      19
Description:                                                 Qty
16mm Diameter High Yield bar reinforcement in straight and
bend bars in foundation according to BS4466                  Unit
                                                             kg
Heading:                                          Element:   Slip No.
Reinforcement to pad foundation                  wblff       20
Description:                                                 Qty
10mm Diameter Mild steel bar reinforcement in straight and
bend bars in foundation                                      Unit
                                                             kg