Productivity Rate
Productivity Rate
2. SITE WORK
Excavation
a. Soft Soil (Hand Tools) 1H Hand Tool m³/day 3.00
b. Hard Soil (Hand Tools_) 1H Hand Tool m³/day 1.00
EARTHWORKS
Done By:
GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 1
Productivity Rates
Done By:
GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 2
Productivity Rates
Done By:
GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 3
Productivity Rates
Done By:
GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 4
Productivity Rates
7. TILING WORK
Mosaic
a. Floor Mosaic Tiles 1M+1H m²/day 15.00
b. Mosaic Skirting 1M+1H Rm/day 40.00
c. Mosaic Steps (Riser & Tread) 1M+1H Rm/day 14.00
d. Mosaic Polishing 1 Po + 1 H m²/day 100.00
Ceramic
a. Fixing of Ceramic Wall Tiles ( Glue Type) 1M+1H m²/day 12.00
b. Grouting of Ceramic Wall Tiles 1M+1H m²/day 30.00
TILING WORK
c. Fixing of Ceramic Wall Tiles (Cement Mortar Type) 1M+1H m²/day 10.00
d. Fixing of Ceramic Floor Tiles ( 200mmx200mm) 1M+1H m²/day 15.00
e. Fixing of Ceramic Floor Tiles ( 300mmx300mm) 1M+1H m²/day 18.00
f. Fixing of Ceramic Floor Tiles ( 500mmx500mm) 1M+1H m²/day 22.00
g. Grouting of Ceramic Floor Tiles 1M+1H m²/day 40.00
h. Ceramic Skirting 1M+1H Rm/day 30.00
PVC Tiles
a. PVC Tiles 1M+1H m²/day 35.00
b. PVC Skirting 1M+1H Lm/day 40.00
Marble
a. Marble Wall 1M+1H m²/day 8.00
b. Marble Floor 1M+1H m²/day 15.00
c. Marble Skirting 1M+1H Rm/day 30.00
d. Marble Steps (Riser & Treads) 1M+1H Rm/day 15.00
Done By:
GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 5
Productivity Rates
9. Irrigation
MainLine Excavation
a. Mainline Excavation 1H Trencher m/day 400.00
b. Mainline Excavation 1H JCB m/day 120.00
UPVC MainLine Installation
Mainline Installation 90mm-315mm 2P+2H m/day 102.00
MainLine Installation ( HDPE Pipes)
a. HDPE Pipe 250mm-450mm 1W+2H Welding/day 7.00
b. HDPE Pipe 160mm-200mm 1W+2H Welding/day 10.00
c. HDPE Pipe 90mm-110mm 1W+2H Welding/day 13.00
Irrigation Cables 2P+2H m/day 80.00
UPVC Laterals Excavation
IRRIGATION
Done By:
GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 6
Productivity Rates
Done By:
GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 7