Productivity Rate

The document outlines productivity rates for various construction activities categorized into general requirements, site work, concrete work, masonry work, structural steel work, and plastering work. Each category includes specific tasks, the required manpower, equipment/tools, units of measurement, and the productivity rate per unit. This information is essential for planning and estimating labor and resource allocation in construction projects.

Uploaded by

abo omer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
351 views7 pages

Productivity Rate

The document outlines productivity rates for various construction activities categorized into general requirements, site work, concrete work, masonry work, structural steel work, and plastering work. Each category includes specific tasks, the required manpower, equipment/tools, units of measurement, and the productivity rate per unit. This information is essential for planning and estimating labor and resource allocation in construction projects.

Uploaded by

abo omer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Productivity Rates

item Equipment &


Category Sub-Category Particulars Manpower Unit Productivity Rate Per Unit
no Tools
1. GENERAL REQUIREMENT
FACILITIES

a. Site Cleaning 1H Dozer m²/day 4,200.00


b. Fencing 1C + 2H + 1P m²/day 50.00
SITE

c. Fixing of light weight Scaffolding 1C + 1H m²/day 70.00


d. Demolition and Breaking Down Work 2H Compressor m²/day 1.00
e. Demolition of demolished material/debris. 2H Shovel + D. Truck m³/day 1.00

2. SITE WORK
Excavation
a. Soft Soil (Hand Tools) 1H Hand Tool m³/day 3.00
b. Hard Soil (Hand Tools_) 1H Hand Tool m³/day 1.00
EARTHWORKS

c. Soft Soil 1H Shovel m³/hr 40.00


d. Hard Soil 1H Shovel m³/hr 25.00
e. Soft Soil 1H J.C.B m³/hr 15.00
f. Hard Soil 1H J.C.B m³/hr 8.00
Backfilling
a. Filling in foundation 1H Shovel m³/hr 30.00
b. Level and compaction 1H Roller Compactor m²lday 100.00
c. Spreading 200mm layer (Subkha, Road Base) 1H Shovel m³/hr 100.00
d. Compaction 200mm layer, (Subkha, Road Base) 1H Roller Compactor m²lday 200.00
Interlocking Paving
a. Compaction / Leveling 2H Roller Compactor m²/day 200.00
b. Spreading Sand and Brushing 2H m²/day 200.00
SURFACING
PAVING &

c. Laying Tiles 1M + 2H m²/day 45.00


d. Filling, compaction 1H Plate Compactor m²/day 100.00
Precast Kerb Stone
a. Excavation & Blinding for Curbstone 1H R.M/day 10.00
b. Laying Kerbs 1M + 2H R.M/day 35.00
c. Karb stone omn curved lines 1M + 1H R.M/day 15.00
d. Hunching 1M + 1H R.M/Hr. 20.00

Done By:

GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 1
Productivity Rates

item Equipment &


Category Sub-Category Particulars Manpower Unit Productivity Rate Per Unit
no Tools
3. CONCRETE WORK
Shuttering (with support)
a. Shuttering of Blinding 1C + 1H m²/day 35.00
b. Shuttering of Footing ( Plywood) 1C + 1H m²/day 15.00
c. Shuttering of Footing ( Plates) 1C + 1H m²/day 20.00
d. Shuttering of Stub Column 1C + 1H m²/day 5.00
CONCRETE FORMWORK

e. Shuttering of Strap/ Tie Beam (Plywood) 1C + 1H m²/day 12.00


f. Shuttering of Strap/ Tie Beam (Plates) 1C + 1H m²/day 17.00
g. Shuttering of Wall 1C + 1H m²/day 12.00
h. Shuttering of Column 200mm x 200mm 1C + 1H m²/day 8.00
I. Shuttering of Column 200mm x 400mm 1C + 1H m²/day 8.00
j. Shuttering of Beam with support 1C + 1H m²/day 10.00
k. Shuttering of Roof Slab 1C + 2H m²/day 10.00
l. Shuttering of Lintel 1C + 1H m²/day 6.00
m. Shuttering of Coping Beam (200mm x 200mm ) 1C + 1H m²/day 6.00
n. Shuttering of Parapet 1C + 1H m²/day 12.00
o. Shuttering of Arch. Lintel 1C + 1H m²/day 6.00
p. Expansion Joints / Ground Slab 1C + 1H L.M./day 60.00
q. Shuttering of Beam & Column for 8m to 12m high 1C + 1H m²/day 8.00
r. Shuttering of Staircase 1C + 1H m²/day 12.00
s. De-Shuttering Works 20% of Shuttering Works m²/day

Done By:

GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 2
Productivity Rates

item Equipment &


Category Sub-Category Particulars Manpower Unit Productivity Rate Per Unit
no Tools
Reinforcement ( Lightening for Cut & Bend Steel)
a. Reinforcement of Footng 1 SF + 1 H kg/day 250.00
b. Reinforcement of Stub Column 1 SF + 1 H kg/day 175.00
c. Reinforcement of Strap Beam 1 SF + 1 H kg/day 200.00
RSB Reinforcement

d. Reinforcement of Tie Beam 1 SF + 1 H kg/day 300.00


e. Reinforcement of Wall 1 SF + 1 H kg/day 350.00
f. Reinforcement of Column 1 SF + 1 H kg/day 200.00
g. Reinforcement of Beam 1 SF + 1 H kg/day 200.00
h. Reinforcement of Solid Slab 1 SF + 1 H kg/day 250.00
I. Reinforcement of Lintel 1 SF + 1 H kg/day 150.00
j. Reinforcement of Coping Beam (200mm x 200mm ) 1 SF + 1 H kg/day 200.00
k. Reinforcement of Parapet 1 SF + 1 H kg/day 250.00
l. Reinforcement of Arch. Lintel 1 SF + 1 H kg/day 125.00
m. Reinforcement of Staircase 1 SF + 1 H kg/day 175.00
Mesh Reinforcement
a. Mesh Reinforcement 1 SF + 2 H m²/day 300.00
Casting Concrete ( Ready Mix)
a. Casting of Blinding 50mm 1M+2H m²/day 30.00
b. Casting of Blinding 100mm 1M+2H m²/day 40.00
c. Casting of Blinding 50mm, 100mm 2M+4H pump m²/day 250.00
d. Casting of Footing 2M+4H m³/day 40.00
e. Casting of Footing (Pump) 3M+8H pump m³/day 100.00
CONCRETE CASTING

f. Casting of Strap / Tie Beam 1M+6H m³/day 20.00


g. Casting of Tie Beam (Pump) 2M+6H pump m³/day 40.00
h. Casting of Ground Floor Slab 100mm 3M+5H m³/day 30.00
I. Casting of Ground Floor Slab 150mm 3M+5H m³/day 45.00
j. Casting of Ground Floor Slab 200mm 3M+5H m³/day 50.00
k. Casting of Wall 1M+1C+3H pump m³/day 40.00
l. Casting of Column 1M+4H m³/day 3.00
m. Casting of Beam of Slab 1M+4H m³/day 12.00
n. Casting of Roof Slab 2M+2C+5H pump m³/day 50.00
o. Casting of Lintel 1M+2H Nos./day 3.00
p. Casting of Coping Beam 200x200mm (up to 2.5m) 1C+5H RM/day 150.00
q. Casting of Coping Beam 200x200mm (above to 2.5m) 1C+5H RM/day 60.00
r. Casting of Parapet 1M+1C+4H pump m³/day 10.00
s. Casting of Architectural Lintel 1M+3H m³/day 5.00
t. Casting of Neck Column 1M+3H m³/day 4.00
u. Casting of Staircase 1C+1H m³/day 12.00

Done By:

GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 3
Productivity Rates

item Equipment &


Category Sub-Category Particulars Manpower Unit Productivity Rate Per Unit
no Tools
4. MASONRY WORK
Solid Block
a. 200mm Solid Block up to 2.5m Heigth 1M+2H nos/day 110.00
Hollow Block
a. 100mm Hollow Block up to 2.5m Height 1M+1H nos/day 120.00
MASONRY

b. 100mm Hollow Block up to 2.5m to 6m Height 1M+2H nos/day 100.00


c. 150mm Hollow Block up to 2.5m Height 1M+1H nos/day 100.00
d. 200mm Hollow Block up to 2.5m Height 1M+1H nos/day 120.00
e. 200mm Hollow Block up to 2.5m to 6m Height 1M+2H nos/day 100.00
f. 200mm Block Work above 6m Height 1M+2H nos/day 80.00
g. 200mm Block Work including pointing 1M+1H nos/day 85.00
Claustra Block
a. Claustra Block 200x200 1M+1H m²/day 10.00
b. Claustra Block 150x150 1M+1H m²/day 8.00

5. STRUCTURAL STEEL WORK


a. Painting for steel structure columns 1 Pa + 1 H m²/day/coat 50.00
b. Painting for steel structure rafters 1 Pa + 1 H m²/day/coat 40.00
Erection of steel structure main frame ( Eave Height up
c. 3E+3H m²/day 225
to 6m span up to 25m )
STRUCTURAL STEEL

Erection of steel structure main frame ( Eave Height up


d. 3E+3H m²/day 175
to 6m span up to 36m )
e. Fixing of Single Skin Sheet ( Roof ) 3E+3H m²/day 350.00
f. Fixing of Single Skin Sheet ( Walls ) 3E+3H m²/day 150.00
g. Single skin with fiber glass Insulation ( Roof ) 3E+3H m²/day 250.00
h. Single skin with fiber glass Insulation ( Wall ) 3E+3H m²/day 100.00
I. Sandwitch Panels ( Roof ) 3E+3H m²/day 250.00
j. Sandwitch Panels ( Wall ) 3E+3H m²/day 150.00
k. Corner Flushing & Trims, etc. 1E+3H Rm/day 80.00
l. 4m x 4m Double Siding Door 1E+3H No. 1.00
m. Wall or Roof opening + Frames (1.0mx1.0m) 1E+3H No. 8.00
n. Ridge Ventilator 1E+3H No./day 6.00
o. Gutter / Downspout 1E+3H Rm/day 70.00

Done By:

GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 4
Productivity Rates

item Equipment &


Category Sub-Category Particulars Manpower Unit Productivity Rate Per Unit
no Tools
6. PLASTERING WORK
Internal Plaster
a. Ceiling Plaster 1M+1H m²/day 10.00
b. Wall Plaster up to 3m Height 1M+1H m²/day 20.00
PLASTERING

c. Wall Plaster 3m to 6m Height 1M+2H m²/day 17.00


d. Wall Plaster above 6m Height 1M+2H m²/day 15.00
e. Fixing of Plaster Mesh 1C+1H Rm/day 50.00
f. Fixing Corner Beed 1M+1H Rm 25.00
External Plaster
a. Wall Plaster up to 3m Height 1M+1H m²/day 20.00
b. Wall Plaster 3m to 6m Height 1M+2H m²/day 18.00
c. Wall Plaster above 6m Height 1M+2H m²/day 15.00

7. TILING WORK
Mosaic
a. Floor Mosaic Tiles 1M+1H m²/day 15.00
b. Mosaic Skirting 1M+1H Rm/day 40.00
c. Mosaic Steps (Riser & Tread) 1M+1H Rm/day 14.00
d. Mosaic Polishing 1 Po + 1 H m²/day 100.00
Ceramic
a. Fixing of Ceramic Wall Tiles ( Glue Type) 1M+1H m²/day 12.00
b. Grouting of Ceramic Wall Tiles 1M+1H m²/day 30.00
TILING WORK

c. Fixing of Ceramic Wall Tiles (Cement Mortar Type) 1M+1H m²/day 10.00
d. Fixing of Ceramic Floor Tiles ( 200mmx200mm) 1M+1H m²/day 15.00
e. Fixing of Ceramic Floor Tiles ( 300mmx300mm) 1M+1H m²/day 18.00
f. Fixing of Ceramic Floor Tiles ( 500mmx500mm) 1M+1H m²/day 22.00
g. Grouting of Ceramic Floor Tiles 1M+1H m²/day 40.00
h. Ceramic Skirting 1M+1H Rm/day 30.00
PVC Tiles
a. PVC Tiles 1M+1H m²/day 35.00
b. PVC Skirting 1M+1H Lm/day 40.00
Marble
a. Marble Wall 1M+1H m²/day 8.00
b. Marble Floor 1M+1H m²/day 15.00
c. Marble Skirting 1M+1H Rm/day 30.00
d. Marble Steps (Riser & Treads) 1M+1H Rm/day 15.00

Done By:

GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 5
Productivity Rates

item Equipment &


Category Sub-Category Particulars Manpower Unit Productivity Rate Per Unit
no Tools
8. SCREED
Floor Screed (50mm)
a. Floor Screed (50mm) 1M+1H m²/day 30.00
b. Cement Skirting 1M+1H Rm/day 25.00
Wooden Skirting
SCREED

a. Timber 1C+1H Rm/day 100.00


Threshold
a. Threshold 1M Rm/day 10.00
False Ceiling
a. False Ceiling - Suspended Type 1C+1H m²/day 25.00
Dry Wall Partition
a. Dry Wall Partition 1C+1H m²/day 20.00

9. Irrigation
MainLine Excavation
a. Mainline Excavation 1H Trencher m/day 400.00
b. Mainline Excavation 1H JCB m/day 120.00
UPVC MainLine Installation
Mainline Installation 90mm-315mm 2P+2H m/day 102.00
MainLine Installation ( HDPE Pipes)
a. HDPE Pipe 250mm-450mm 1W+2H Welding/day 7.00
b. HDPE Pipe 160mm-200mm 1W+2H Welding/day 10.00
c. HDPE Pipe 90mm-110mm 1W+2H Welding/day 13.00
Irrigation Cables 2P+2H m/day 80.00
UPVC Laterals Excavation
IRRIGATION

a. Laterals Excavation 1H Trencher m/day 400.00


b. Laterals Excavation 1H JCB m/day 120.00
c. Laterals Installation 1P+1H m/day 125.00
d. Risers Installation 1P+1H No./day 48.00
e. Flushing for Mainline & Laterals 2P+1H one Day All Pipes
Valves Installation
a. Isolation Valve Installation 1P+1H No./day 2.00
b. Solenoid Valve Installation 1P+1H No./day 3.00
c. Valve/Pull Box 1P+1H No./day 4.00
d. Controler Installation 1P+1H No./day 3.00
Driplines & Sprinklers Installation
a. Dripline Installation 1P+1H m/day 500.00
b. Sprinkler Installation 1P+1H No./day 48.00
Pump Set & Filters Installation
a. Pump Set & Filters Installation 2E+2H day/No. 20.00

Done By:

GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 6
Productivity Rates

item Equipment &


Category Sub-Category Particulars Manpower Unit Productivity Rate Per Unit
no Tools
10.Soft Landscaping
Excavation Work
a. For Palm Trees 1H JCB Pit/day 50.00
b. For Trees 1H JCB Pit/day 70.00
Disposal Of Surplus Soil
a. Disposal Of Surplus Soil 1H Loader + 32 m3 Truck m3/day 32.00
Soil Preparation
SOFT LANDSCAPIG

a. Soil Preparation 1H Loader m2/day 1,000.00


b. Soil Preparation 1H JCB m2/day 550.00
c. Soil Preparation 1H Bobcat m2/day 230.00
Plantation
a. Palm Trees Plantation 1G+2H JCB No./day 20.00
b. Trees Plantation 1 G +1 H No./day 25.00
c. Shrubs Plantation 1G No./day 80.00
d. Ground Cover Plantation 1G No./day 200.00
e. Succulents Plantation 1G No./day 80.00
f. Carpet Plantation 1 G +1H m2/day 50.00
g. Stolons Plantation 1 G +1 H m2/day 500.00
h. Boulders Placing 2H JCB No./day 8.00
i. Gravel Placing 5H m2/day 60.00

Done By:

GET -Planning Dep C=Carp., M=Mason, Pa=Painter,SF=Steel Fixer, E=Erector, H=Helper,Po=Polisher, Elec=Ele, P=Plumber, G= Gardener 7