Monthly Tyre Mounted Mobile Crane Inspection Checklist
Change the document title using the properties option on the Jacobs RibbonProject NameClient Name
Name of Site : Contractor Name :
Crane Make / Model : Model No :
Capacity Main hoist: Auxilliaryty Hoist :
Inspected By : Date :
(Check Mark) Indicates good condition “R” Indicates Repair Required “NA” Indicates not applicable
No Item Inspected Condition No Item Inspected Condition
Carrier: Tire/Track Condition &
1. General: Operators Manual in Cab 27.
Slack
2. Load Charts and Fire Ext. in Cab 28. Tire Pressure/Drive Chain, etc.
3. Signal Chart and Power Line Signs 29. Brakes
Controls Clearly Marked/Function
4. 30. Steering Controls/Linkage
Correctly
5. Windows clear and free of cracks, etc. 31. Axle Lockouts for on Rubber Lifts
Outriggers-Beam, Pad/Pad
6. Windshield wipers 32.
Swivel
Cab/Platforms/Ladders Safe and Upper Works: Counter Weight
7. 33.
Clean Secure
8. All Guards in Place 34. Load Hoist(s)/Boom Hoist Drums
9. Bolts and Rivets Per Spec. and Tight 35. Main/Aux. Hoist Brakes/Pawls
Boom Angle Indicator Functioning
10. 36. Boom Hoist Brakes/Pawls
Correctly
Elect: Lights-Front, rear, brake, turn Swing Gear Assembly and
11. 37.
signals Brakes
12. Horn and Back Up Alarm 38. Pins/Gears/Shafts/Clutches
13. Control Panel Gauges and Hour Meter 39. Locking Devices
Anti-Two Block(s) Functioning Boom Assembly: Boom
14. 40.
Correctly Stops/Pins
LMI Functioning Within Calibration Structure-Tubing, Chords and
15. 41.
Limits Lacing
Power Plant: Water and Oil Levels Telescope Sections
16. 42.
(No Leaks) Droop/Alignment
Telescope Wear
17. Filters clean and in place 43.
Pads/Lubrication
18. Hoses, Belts, and Wiring 44. Jib or Boom Extension
Engine Performance With and W/O Blocks: B. Point Sheave(s)
19. 45.
Load Condition/Lube
Transmission Performance and Oil Load Block/Sheave(s)
20. 46.
Level Condition/Lube
Document number : L&T/HEIC/MRU/S040833/Tyre Mounted Crane/001 1
Monthly Tyre Mounted Mobile Crane Inspection Checklist
No Item Inspected Condition No Item Inspected Condition
Boom Fall Sheave(s)
21. Air System 47.
Condition/Lube
Headache Ball, Hook, Latch,
22. Hydraulic System: Lines/Hoses 48.
Swivel
23. Motors, Pumps, and Cooler 49. Sheave Guards
Wire Rope: Load/ Aux./Whip
Cylinders no Drift/Seal Leaks/Scoring 50.
24. Line
(Boom-crowd and lift, outriggers, etc.)
51. All Lines Reeved Correctly
25. Filters/Strainers/Fluid Level 52. Boom Lines
26. Counter Balance/Load Hold Valves 53. Pendant Lines
Note Hydraulic Pressure Relief Valves should be checked for calibration every six months. Don’t make any
changes with the parts of the crane which are available/provided by manufacturer or don’t do any makeshift
arrangement with any part of the crane or else crane shall be rejected by WORLEY.
Inspector Name: Signature:
Distribution: 1 copy to site equipment coordinator & 1 copy to be kept in crane. Retain indefinitely.
Document number : L&T/HEIC/MRU/S040833/Tyre Mounted Crane/001 2