F5 Becker Mock 1 Answer PDF
F5 Becker Mock 1 Answer PDF
Performance
ol
Management
ho
F5PM-MK1-Z16-A
Sc
Answers & Marking Scheme
y
ud
St
er
ck
Be
Section A Section B
1 D 16 A
2 C 17 A
3 C 18 A
4 A 19 C
5 D 20 C
ol
6 D 21 D
7 C 22 B
ho
8 D 23 D
9 B 24 B
10 B 25 A
Sc
11 A 26 A
12 A 27 C
13 A 28 A
14 B 29 D
y
15 C 30 B
ud
TOTAL
×2=
%
St
er
ck
Be
1 D
Selling price $23·50 Estimated costs:
Less 20% margin $4·70 Materials $10·45
–––––––
Target cost $18·80 Labour ($64 ÷ 20) $3·20
Variable overheads
($82 ÷ 20) $4·10
ol
Fixed costs
($680,000 ÷ 200,000) $3·40
––––––
ho
Reduction required $2·35 Total cost $21·15
––––––
2 C (3) and (4) are the categories where the metal is wasted irrecoverably. The
Sc
company would be happy to increase (2) by recycling more of the waste metal.
4 A The opportunity cost is the benefit foregone by choosing a particular option, instead
of the next best option. (B = differential cost; C = committed cost; D = notional
cost.)
y
ud
5 D Margin of safety = Budgeted sales – breakeven sales
6 D Placing a ruler on the dotted line and moving it parallel to the right shows that the
er
last point in the feasible region is where the line for constraint (1) meets the x-axis.
7 C The maximin decision rule seeks to maximise the minimum payoff from the
possible outcomes. In this case the minimum outcome for each project arises if
ck
market demand is weak. The highest outcome in the event of weak demand is the
$47,000 result from project C.
WORKING
ol
11 A Head office costs are not deducted because they do not relate directly to the
division.
ho
12 A ROI – the manager would accept the project if ROI is greater than the target of
18%. The ROI of the project is 19% (153,900 ÷ 810,000) so would be accepted.
Sc
Profit of the project 153,900
Imputed interest (810,000 × 16%) 129,600
–––––––
Residual income 24,300
–––––––
y
13 A
ud
14 B A throughput accounting approach assumes that materials are the only variable
costs. Consequently the contribution is different to that calculated using the
traditional method.
St
W X Y
Contribution per unit $ 139 130 120
Bottleneck minutes 7 10 7
Contribution per minute 19·9 13 17·1
Rank
er
15 C Fixed cost per unit ($33) × volume (50,000) = Total fixed costs ($1·65m)
Contribution per unit = $80
ck
$
Variable cost per unit 30,000
Absorbed fixed costs:
(200 hours 37.17) 7,434
––––––
ol
Total absorption cost 37,434
––––––
ho
WORKING
Hours $
Budgeted fixed production overhead 26,020,000
Sc
Budgeted machine hours:
Car X: 220,000
Car Y: 480,000
––––––– 700,000
––––––––––
Fixed overhead per machine hour
y 37.17
––––––––––
ud
17 A Car X Car Y
Production (units) 1,100 1,600
Number of cars per production run 10 40
––––– –––––
St
7,020,000
⇒ Cost per inspection = = $1,300
2,200 3,200
ck
WORKING
Car X Car Y
Be
12,000,000
⇒ Setup costs per production run = = 80,000
110 40
When using absorption costing, all overhead costs were apportioned between the
two products based on machine hours. The portion of overheads apportioned to Car
Y was 480,000 ÷ 700,000 = 68.6%. Although absorption costing does not split the
overhead costs into the three activities, in effect, 68.6% of the costs of all activities
are apportioned to Car Y.
(1) Machine costs are apportioned using machine hours; therefore the same portion
ol
of machine costs are apportioned to Car Y using activity based costing. Statement
(1) is NOT true.
ho
(2) Car Y uses 40 setups from a total of 150. This represents 26.7% of total setup
costs, so is lower than the costs apportioned under absorption costing. Statement
(2) is true.
Sc
(3) Car Y uses 3,200 inspections from a total of 5,400, being 59.2%. This is lower
than the 68.6% apportioned under absorption costing.
(4) Statement (4) is correct. Generally activity based costing better reflects the costs
of the activities used to make a product than absorption costing.
y
20 C Actions (2), (4) and (5) would reduce the cost per unit.
ud
(1) reducing the number of cars per production run would increase the number of
setups, thus increasing the setup costs. (3) would increase the cost per unit.
21 D
Actual sales at actual price 385,000
St
360,000
Standard price based on budget is = $30 per unit
12,000
ck
360,000
Budgeted selling price = $30 per unit.
12,000
Be
(2) is incorrect. The standard material cost per unit is $5, so the standard cost of
actual production is 67,500. Actual material costs were $69,000, so some of the
difference between budget and actual is due to either price or usage (or both).
24 B Incremental budgeting means starting with previous years budgets and adjusting
them with incremental items such as inflation.
ol
25 A (3) If there is not a high level of trust, bottom up budgeting would be less
appropriate as managers might attempt to make budgets easier to achieve (e.g. by
ho
adding budgetary slack).
(5) If there is a high degree of dependency, the departments’ budgets will need to be
coordinated with each other. This is more easily achieved with top down budgeting.
Sc
26 A Tutorial note: The approach to maximising profit, in the situation of limited factors
is to maximise contribution per unit of limited factor. In this case, the limited factor
is labour hours, so the approach is to maximise contribution per hour of labour:
PN BE
y
$ per batch $ per batch
Selling price 450 270
ud
Materials 190 177
Labour 90 30
Variable overheads 30 10
––––– –––––
Contribution per batch 140 53
St
Tutorial note: The optimal production plan with 1,000 labour hours is to produce
ck
400 batches of BE in 400 hours and 200 batches of PN (i.e. 600 ÷ 3) in the
remaining 600 hours.
Tutorial note: The shadow price of a scarce resource is the amount by which
contribution would increase if one additional unit of scarce resource becomes
available. Thus it is the maximum amount above the normal price that a business
would be prepared to pay for additional units of the resource.
WORKINGS
ol
Throughput contribution per batch 140
Labour hours per batch 3
––––
ho
Return per factory hour 46.7
––––
(2) Cost per factory hour
$
Total labour cost (1,000 × 30) 30,000
Sc
Variable overheads (1,000 × 10) 10,000
Fixed costs (Based on budgeted quantities)
(40 × 250) + (30 × 340) 20,200
––––––
Total fixed costs per week 60,200
––––––
y
⇒ Fixed cost per factory hour (60,200 ÷ 1,000) 60.20
ud
29 D (3), (4) and (5) could improve TPAR.
(1) Would most likely lead to higher cost of materials, so would reduce the
throughput return per hour and therefore TPAR.
St
(2) Would reduce the throughput return per unit. The number of units sold
could not be increased because output is constrained by the bottleneck – in
this case labour hours.
er
(3) Would increase throughput as labour is the bottleneck, so this would lead
to better use of the bottleneck.
ck
(4) Reducing fixed costs would reduce the factory costs per hour, thus
increasing TPAR.
(5) Automating some tasks would increase output of labour thereby reducing
Be
the labour time per unit. Since labour is the bottleneck, this would
increase throughput return per unit (by reducing labour time per unit).
31 BORO Marks
Tutorial note: The maximum transfer price that Boro would be prepared to accept for 2 kg of
special ingredient Z is the “net revenue” from sales of the Madison (i.e. revenues less costs
before deducting the transfer price). This is calculated as follows:
ol
Selling price per unit (per Q) 115
Less:
Raw material costs (2 × 8.5) (17) ½
ho
Other variable costs (60% × 115) (69) ½
––––
Net revenue 29 1
––––
Sc
This net revenue applies to 2 kg of special ingredient Z. So the maximum price that Boro 1
would be prepared to pay for 1 kg of special ingredient Z would be $14.50 (i.e. ½ × $29). ————
3
(b) Minimum transfer price acceptable to Magpie ————
In this situation Magpie has no alternative opportunity for 4,000 kg of its production of 1
special ingredient Z, so there is no opportunity cost. It should, therefore, offer to transfer this
St
Based on the information given in the question about the external price charged by Magpie
for ingredient X, we can work backwards to find the marginal cost as follows:
er
$
External market price 15
Total cost (15 × 100/125) 12 ½
Variable portion (75% × 12) 9 1
ck
The minimum transfer price applicable in this case would be the marginal cost of $7.5 per 1
kg of material Z. ————
5
————
Where Magpie has an external market, the opportunity cost equals the lost contribution from
selling externally. This is as follows:
$
Selling price 15
Less variable costs 9
––––
Contribution per unit 6 1
––––
ol
The minimum transfer price = marginal cost plus opportunity cost. Marginal cost is $7.5 1
per kilo (see part (i))
= $7.5 + 6 = $13.5. ————
2
ho
Tutorial comment: This can be looked at in a different way: Since Magpie has an external ————
market which is the opportunity foregone, the relevant transfer price would be the external
selling price of $15 per kg. This will be adjusted to allow for the $1.50 per kg avoided on
internal transfers due to packing costs not required:
Sc
The minimum transfer price would be $15 – $ 1.50 = $13.50 per kg.
Magpie has an alternative use for the first 2,000 kg of special ingredient Z production 1
capacity which will yield a contribution of $6,000.
y
ud
The balance of its spare capacity (2,000 kg) has no opportunity cost and should still be 1
offered at marginal cost.
If Magpie were to charge more than $14.5 per kg, Boro would make a loss on producing ½
the Madison therefore Boro will not accept a price greater than $14.5 per kilo. If Magpie ½
insists of a price of $15 therefore, Boro will not buy the ingredient and will not be able to ½+1
make the new product. ————
Be
max 2
————
In this case the managers are acting in a manner which is not beneficial to the organisation as
a whole. There will be a cost to the business of this decision as follows:
$
Lost revenue from sales of new product (2,000 units × $115) (230,000) 1
Saved costs:
Boro – variable costs (2000 × $86) 172,000 1
Magpie – marginal cost of 4,000 kg of Z (4,000 × 7.5) 30,000 1
__________
ol
Lost contribution to the group (28,000) 1
__________
————
4
————
ho
Tutorial note: Boro’s management decided not to make the new product as the transfer
price proposed by Magpie was too high. The impact on group profits is calculated by
determining the relevant cash flows of that decision. These are:
Sc
1. The revenue that Boro would have made from selling the product – this is lost.
2. The variable costs that will be saved by Boro since it will not make the product.
3. The marginal costs that will be saved by Magpie not producing the 4,000 kg of Z
which would have been needed for the new product.
y
4. The opportunity cost that will be saved by Magpie since it will be able to use all its
capacity to meet external demand for its products. However, in this case there
ud
would have been no opportunity cost since Magpie has spare capacity so could
have supplied Boro in full without losing any external sales.
32 GTK CO
St
(a) Calculation of selling price variance and sales volume variance Marks
$
Budgeted contribution (30,000 8.28) 248,400 1
ol
–––––––
Operational price variance
$
ho
Actual quantity actual price (32,000 × 12.36) 395,520
Actual quantity (revised) standard price
(32,000 12.18) 389,760
–––––––
Sc
Operational price variance (favourable) 5,760 2
––––––– ————
4
Tutorial note: The sum of the operational and planning price variances is $3,840 adverse. ————
This is the same as the price variance calculated in part (a).
y
(c) Performance of the sales department
ud
The sales volume variance is favourable. This is because the sales department sold more
headphones than budgeted, which results in higher contribution.
The price variance was adverse which implies that the higher volume was achieved by ½
selling at a lower price than standard. However, the effect on contribution of the two
St
The planning sales price variance simply shows the impact on budgeted profit of revising ½
the standard selling price. In this case the selling price was revised downwards, which would
result in a lower contribution.
er
The operating price variance compares the actual price achieved with the revised standard 1
price. Since the standard price was revised, it should provide a more relevant target than the
original standard. The operating price variance is therefore a better measure of performance
ck
of the sales team than the price variance based on the original standard. The operating price
variance is favourable, showing that the price achieved was higher than expected.
Overall, the sales department appears to have performed well. It has achieved a higher 1
Be
sales volume than expected, as reflected in the sales volume variance, and has also managed
to obtain higher prices than expected.
Before reaching any conclusions, it would be useful to know the basis used to plan the 1
budgeted output. The scenario indicates that the market for headphones is growing rapidly.
Given this fact, it would be useful to know if the actual market for headphones grew by
more than expected. If this is the case, it may not be entirely fair to congratulate the sales
————
team on doing a good job if the market was better than expected. Budgeted market share
max 4
and actual market share achieved would provide better information to assess this. ————
Tutorial note: Other relevant comments would also gain credit.
The purpose of having a standard cost is so that actual performance can be compared 1
against an appropriate target and any deviations from the target can be investigated by means
of variances to identify where performance has not been as expected.
Variances should reflect only factors within the control of the person whose performance is 1
being judged. If factors occurred outside of the control of these persons that meant the
standard could not be achieved, then the standard should be revised to take account of these.
Examples include changes in market price of inputs and changes in operating environment
that are outside the scope of the manager.
ol
Standards may also be revised when it turns out that the original standard was unrealistic. 1
For example, when a standard is set for a new process and the assumptions on which the
ho
standard was based turn out to be incorrect.
Standards should not be revised to change the reported variances, for example to hide 1
inefficiencies. There is a danger that when standards are revised “because the original
Sc
standard was unrealistic” that in reality the standard was fine; the actual performance was
poor and the manager is trying to pass this off as a planning issue. In practice, judgement will
often be required to decide whether or not a proposed revision of a standard should be
allowed.
The production manager has requested that the standard be revised to take into account a pay
rise given to the workers above the expected pay rise when the standard was set.
It could be argued that the standard provided a guide to the production manager about the 2
acceptable level of pay rises. The higher than expected pay rise was a decision of the
er
production manager. Since this was within his control (he chose to ignore the standard, rather
than being forced to do so), the standard should not be revised. The higher pay rise was an
operational decision and should be reflected in the operational variance.
ck
On the other hand, the production manager argued that the staff were demotivated. 1
Perhaps the original pay rise was unrealistic. As such, there is an argument that the standard
should be revised to a more realistic level.
Be
In my opinion, the standard should not be revised. The pay rise was an operational 1
decision. If staff really have been motivated by the pay rise, this may be reflected in the ————
labour efficiency variance, which would be favourable. 4
————
Marks Marks
31 BORO
ol
Calculation of volume variance 1
Reconciliation of actual tobudgeted contribution 1
Actual contribution 1
ho
––– 4
Sc
(c) Comments on performance
1 mark per valid comment max 4
20
–––
er
ck
Be
ol
Text ref coverage
31 (a) Transfer 17 Q81 This question required the calculation of the maximum price that would be acceptable to a buying
ho
pricing Business division. Few candidates were aware that the maximum price should be the lower of the external
Solutions market price (none in this question) and the net revenue of the buying division.
(b) This required the calculation of the minimum transfer price from the perspective of the supplying
Sc
division under three situations. This required candidates to apply the rule that the minimum price is the
marginal cost of production plus the opportunity cost. Candidates performed well in the first two
situations, where the opportunity cost related to sales of the same product externally, but found the
third situation more challenging, where opportunity cost related to sales of a different product.
Students need to just apply the same principle, which is to calculate the opportunity cost.
y
(c) This required candidates to explain the decisions that would be made by the buying division manager
and the effect on group profits if the selling division insisted on a selling price higher than the net
ud
revenue of the selling division. Most candidates could identify that the buying division would not
trade, but few candidates could calculate the impact this would have on profits. A good piece of advice
is to remember that this is really a relevant costing question, where candidates are required to compare
the relevant costs and benefits of not trading with those of trading.
St
er
ck
Be
ol
Text ref coverage
32 (a) & (b) Planning 13 61 Spike The first two parts required calculation of basic sales variances and then analysing the sales price
ho
variances Co variance into planning and operational. The majority of students were able to calculate these
relating to variances correctly. While the preferred approach is to value the price variances using actual sales,
sales price credit would be given for candidates who used budgeted sales.
(c) Planning
Sc
This required and explanation of the variances. This part was done poorly by many candidates, who
variances simply described the calculation of the variances. A good answer should look at the factors behind
the numbers, such as the volume variance reflecting higher demand than expected, probably due to
the actual sales price being lower than budget.
(d) & (e) Revision of This required a discussion of the principles that should be applied when deciding whether to revise a
y
budgets and standard (part (d)) and then a discussion of whether a particular standard should be revised. Answers
standards to these two parts were very thin, reflecting students’ dislike of discussion questions. This was a
ud
shame because part (d) provided four easy marks for simply reciting theory. A good answer to part
(e) would have mentioned both arguments in favour of, and arguments against a revision before
reaching a final conclusion. Many candidates preferred to merely write a conclusion with no
justification.
St
er
ck
Be