The document outlines a Cost Management Plan for a Delivery Management System project over 6 months for a mid-sized logistics company, detailing required resources, cost estimation, and cost control strategies. The total estimated cost is 710,000 PKR, covering personnel, tools, software, and hardware. It also includes a cost control system with monitoring tools, earned value management, and a contingency reserve for unexpected changes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views3 pages

Solution CS615

The document outlines a Cost Management Plan for a Delivery Management System project over 6 months for a mid-sized logistics company, detailing required resources, cost estimation, and cost control strategies. The total estimated cost is 710,000 PKR, covering personnel, tools, software, and hardware. It also includes a cost control system with monitoring tools, earned value management, and a contingency reserve for unexpected changes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Assignment: Cost Management Plan for Delivery Management System

Project Duration: 6 months


Company Type: Mid-sized Logistics Company
Team Composition: Developers, Testers, UI/UX Designer, Project Manager,
Cost Manager
Role: Cost Manager

1. Resources Required for the Project


Resou
rce Details
Type
Perso 2 Developers, 1 Tester, 1 UI/UX Designer, 1 Project Manager, 1
nnel Cost Manager
Project management software (e.g., Jira), Design tool (Figma),
Tools
Version control (GitHub), Testing tool (Selenium)
Hardw Laptops/Desktops, Network Infrastructure, Test Devices
are (Mobile/Tablets)
Softw Operating Systems, IDEs (VS Code), Database (MySQL), Server
are (AWS), Frontend (React), Backend (Node.js)

2. Cost Estimation of Each Activity


Durati Estimated Cost
Activity Personnel Involved
on (PKR)
Requirement 2 Project Manager, Cost
80000 PKR
Gathering weeks Manager
3
UI/UX Design UI/UX Designer 120,000 PKR
weeks
3.5
Development month Developers (2) 200,000 PKR
s
1.5
Testing month Tester 60,000 PKR
s
2 Developers, Project
Deployment 100,000 PKR
weeks Manager
Tools & Software - All 50,000 PKR
Hardware &
- All 100,000 PKR
Devices
Total
Estimated - - 7,10,000 PKR
Cost

3. Cost Baseline for Each Activity (in PKR)

Baseline Cost
Activity Justification
(PKR)
Requirement
80,000 PKR Meetings, documentation, consultations.
Gathering
UI/UX Design 120,000 PKR Research, wireframes, prototyping.
Backend & frontend development by
Development 2,00,000 PKR
two developers.
Testing 60,000 PKR Manual and automated testing.
Deployment 100,000 PKR Final setup, server, security measures.
Tools & Software 50,000 PKR Jira, GitHub, Figma, testing tools.
Hardware &
100,000 PKR New laptops, devices for testing.
Devices
Total Baseline 7,10,000 PKR Controlled within project limits.

4. Cost Estimation Table Summary (PKR)

Component Cost (PKR)


Personnel 560,000 PKR
Tools &
50,000 PKR
Software
Hardware 100,000 PKR
Total 710,000 PKR
Simple Pie Chart (Data for Chart)
Percenta
Component
ge
Personnel 89%
Tools &
5%
Software
Hardware 6%

4. Cost Control System

To manage and control project costs effectively:

 Cost Monitoring Tools: Use tools like Jira, Trello, or MS Project to track
time and resource usage.
 Earned Value Management (EVM): Track Cost Performance Index (CPI)
and Schedule Performance Index (SPI).
 Weekly Reporting: Review actual vs planned expenses with stakeholders.
 Change Control Board (CCB): Any cost-related change must be approved
by the board.
 Buffer: A 10% contingency reserve (70,000) will be kept aside for
unexpected changes.
 Alerts & Thresholds: Set alerts for exceeding 80% of the budgeted cost for
any activity.

Note: These costs are estimated according to the development standards in


Pakistan.