BILL OF QUANTITIES
PROJECT: Residential Building
LOCATION: Thiruvananthapuram
COMPANY: Anuraag Engineers Pvt. Ltd.
DATE: 12/02/2025
Item Description of items No. L B H Quantity Unit Rate Amount
No.
1 Earthwork in excavation 1 19.38 0.9 1 17.442 cum 1000 17442
for foundation
2 Lime concrete in 1 19.38 0.9 0.3 5.23 cum 1500 7848.9
foundation
3 I class brickwork in
foundation & plinth in
lime mortar
I Footing 1 19.38 0.7 0.2 2.732 cum 1200 3255.84
II Footing 1 19.38 0.6 0.2 2.325 cum 1200 2790.72
Plinth wall 1 19.38 0.5 0.9 8.721 cum 1200 10465.2
Total 16511.8
4 2cm Damp Proof Course 1 19.38 0.5 9.69 sq. m 900 8721
Deduct door sill 1 1.2 0.5 0.6 sq. m 900 540
Total 9.09 sq. 8181
m
5 I class brickwork in 1 19.38 0.4 3.5 27.132 cum 1200 32558.4
superstructure in lime
mortar
Deduct
Door openings 1 1.2 0.4 2.1 1.008 cum 1200 1209.6
Window openings 5 1.1 0.4 1.5 3.3 cum 1200 3960
Lintels over door 1 1.4 0.4 0.1 0.056 cum 1200 67.2
Lintels over window 5 1.3 0.4 0.1 0.26 cum 1200 312
Total deductions 4.624 cum 5548.8
Net Total 22.508 cum 27009.6
6 R.C.C. work completed
with steel reinforcement
Roof slab 6x1/2x3.46/2x1.732x0.13 4.043 cum 1600 6469.26
Chujja 6x(3.46+3.98)/2x4.5x0.06 0.602 cum 1600 964.224
Lintels same as above item 5 0.32 cum 1600 512
Total 4.965 cum 7945.49
7 8cm Lime concrete in 6x1/2x3.46x3.46/2x1.732 31.1 sq. m 1000 31102.2
roof terracing
8 2.4cm concrete cover 6x1/2x3.46x3.46/2x1.732 23.382 sq. m 900 21043.8
including 7.5cm L.C.
floor
9 12mm cement plastering
1:6 in walls
Inside 6 3 3.5 63 sq. m 800 50400
Outside above plinth 6 3.46 3.5 72.66 sq. m 800 58128
Outside plinth wall 6 3.52 0.7 14.784 sq. m 800 11827.2
Total 150.44 sq. 120355
m
Deduct
Door openings 1 1.2 2.1 2.52 sq. m 800 2016
Windows 5 1.1 1.5 8.25 sq. m 800 6600
Total 10.77 sq. m 8616
Net Total 139.674 sq. 111739
m