D&C B113
D&C B113
POST-TENSIONING OF CONCRETE
Copyright – Transport for NSW
IC-DC-B113
CONTENTS
CLAUSE PAGE
FOREWORD .........................................................................................................................................II
TfNSW Copyright and Use of this Document ............................................................................ii
Base Specification.....................................................................................................................ii
1 GENERAL .................................................................................................................................. 1
1.1 Scope ......................................................................................................................... 1
1.2 Structure of the Specification...................................................................................... 1
1.3 Definitions ................................................................................................................. 2
6 INSTALLATION OF TENDONS.................................................................................................... 12
6.1 Pulling of Tendons and Pushing of Strands ............................................................... 12
6.2 Special Provision for High Tensile Bars ................................................................... 12
10 GROUTING .............................................................................................................................. 18
FOREWORD
This document should be read with all the documents forming the Project Deed.
This copy is not a controlled document. Observe the Notice that appears on the first page of the copy
controlled by TfNSW. A full copy of the latest version of the document is available on the TfNSW
Internet website: http://www.rms.nsw.gov.au/business-industry/partners-
suppliers/specifications/index.html
BASE SPECIFICATION
This document is based on Specification TfNSW B113 Edition 3 Revision 6.
POST-TENSIONING OF CONCRETE
1 GENERAL
1.1 SCOPE
This Specification sets out the requirements for the supply, installation, stressing, grouting and
corrosion protection of post-tensioned internal and external prestressing tendons and their anchorages
and other components for post-tensioned concrete bridge elements.
This Specification does not fully specify post-tensioning systems comprising ungrouted internal
tendons or stay cables.
The schedules in Annexure B113/C list the HOLD POINTS that must be observed. Refer to
Specification TfNSW D&C Q6 for the definition of HOLD POINTS.
The records listed in Annexure B113/C are Identified Records for the purposes of TfNSW D&C Q6.
The PROJECT QUALITY PLAN must include each of the documents and requirements listed in
Annexure B113/D and must be implemented.
The Inspection and Test Plan must nominate the proposed testing frequency to verify conformity of
the item and it must not be less than that specified in Annexure B113/E. Where a minimum frequency
is not specified, nominate an appropriate frequency.
The approved post-tensioning systems and grouting systems are listed in TfNSW Internet website
(refer Clauses 2.1 and 10.2).
Codes, standards, specifications and test methods are referred to in abbreviated form (eg AS 1234).
For convenience, the full titles are given in Annexure B113/M. Whenever a part of a standard is
referenced, the common title of the standard is mentioned in Annexure B113/M as a separate entry
with that part of the standard referred to only by its particular title.
1.3 DEFINITIONS
The terms “you” and “your” mean “the Contractor” and “the Contractor’s” respectively.
(b) Design Elongation: Tendon elongation at the jack stated in the Design Documentation.
(c) Design Jacking Force: Tendon force at the jack stated in the Design Documentation, based on
the design parameters stated thereon
(d) Measured Elongation: Tendon elongation at the jack measured at the nominated jacking force.
(e) Nominated Draw-In: Inward movement of the tendon due to anchorage slip and draw-in when
the post-tensioning force is transferred from the jack, assessed by lift off testing during approval
of the post-tensioning system.
(f) Nominated Elongation: Tendon elongation at the jack nominated by the Contractor
corresponding to the nominated jacking force.
(g) Nominated Gauge Pressure: Gauge pressure at the jack nominated by the Contractor
corresponding to the nominated jacking force.
(h) Nominated Jacking Force: Tendon force at the jack nominated by the Contractor, based on
the design jacking force adjusted for actual tendon and post-tensioning system properties and
parameters, including allowances for losses in addition to and where different to those stated in
the Design Documentation.
(i) Post-Tensioning Supervisor: Employee of, and nominated by, the Post-Tensioning System
Supplier and approved by TfNSW.
(j) Post-Tensioning System Supplier: The owner, or the agent of the owner, that is responsible
for the supply and installation in the Project Works of an approved post-tensioning system, in
accordance with the conditions of approval.
2 POST-TENSIONING SYSTEMS
2.1 GENERAL
The post-tensioning system must be one of the approved Proprietary Post-Tensioning Systems listed in
the TfNSW Internet website:
http://www.rms.nsw.gov.au/business-industry/partners-suppliers/documents/tenders-
contracts/listofapprovedbridgecomponentssystems.pdf.
Where any modifications are necessary to the reinforcement and/or concrete dimensions to suit an
approved post-tensioning system for the type, size and arrangement of tendons shown in the Design
Documentation drawings, submit to the Project Verifier working drawings to the same scale as the
Design Documentation drawings of all necessary modifications together with supporting design
calculations carried out and certified by a Chartered Professional Engineer with Membership of
Engineers Australia practising in the field of Structural Engineering and experienced in this work.
2.2.1 General
Encapsulate external tendons in smooth polyethylene plastic ducts with minimum wall thickness 1/17
of the outside diameter.
The duct design must account for creep rupture effects from the sustained circumferential stresses
induced by pressure grouting, if applicable.
Where duct couplers are used, provide drip rings on the high side above the coupler to prevent water
running along the duct into the coupled joint.
Fit external tendons with suitable connections at fixing points to allow easy replacement. Install with
sufficient access and clearances to allow replacement and stressing.
Adopt one of the following forms of construction where external tendons pass through deviators,
anchorage diaphragms and/or blisters:
(i) Diabolo
Pass the plastic duct through a formed double conical hole (diabolo) in the deviator.
Form diabolos so that the plastic duct is not damaged by localised bearing stresses.
Pass the tendon through a rigid steel pipe located in the deviator to which the plastic duct
is coupled on both sides. Curve the steel pipe to a constant radius between tangent points
located approximately 75 mm inside the concrete faces. Extend the steel pipe at least 150
mm but not more than 300 mm beyond the concrete faces, following the tangential
direction of the tendon. Where the steel pipe exits from the concrete, set a rubber O-ring
50 mm wide and 10 mm thick into the concrete to prevent spalling of the concrete cover
if the steel pipe is misaligned.
Insert and seal the plastic duct into a straight rigid plastic or steel pipe extending from the
cast-in anchorage to approximately 200 mm inside the exit face of the diaphragm or
blister. Provide a conical concrete bell mouth at the exit face of the diaphragm or blister,
ensuring that the distance from the face of the concrete to where the plastic duct contacts
the concrete of the bell mouth is at least 20 mm.
(ii) Tube
Pass the tendon through a rigid steel or smooth plastic tube located in the anchorage
diaphragm or blister to which the plastic duct is coupled on the exit side. Extend the tube
at least 150 mm but not more than 300 mm beyond the concrete faces, following the
tangential direction of the tendon. Where the tube exits from the concrete, set a rubber O-
ring 50 mm wide and 10 mm thick into the concrete to prevent spalling of the concrete
cover if the tube is misaligned. The smooth plastic tube must have a minimum wall
thickness 1/17 of the outside diameter.
Positively connect ducts to the steel or plastic sleeves at the diaphragms and deviators using
connections strong enough to withstand site construction loads and conditions without damage.
Positively seal all connections between steel pipes and plastic ducts, between length of plastic ducts,
and between steel pipes and anchorages/couplers with an air and water tight coupling system capable
of sustaining testing and grouting pressures, to ensure continuity of the ducts for corrosion protection.
The protection against deterioration of the post-tensioning system components must remain effective
for the design life of the structure.
Where ducts are ungrouted, the tendons must be galvanized or epoxy coated, or encapsulated in
individual grease or wax filled polyethylene plastic sheathing. For galvanized or epoxy coated
tendons comprising wire stands, the individual wires must have the same type of protective treatment.
Tendon protection systems must be detailed in the Design Documentation.
The grease or wax used for protection of tendons and/or anchorages must comply with the
performance requirements of Table B113.1.
Spaces filled with grease or wax must be sealed using suitable O-ring seals.
Handle the tendons so that the protective coating or the grease or wax filled sheathing remains intact
and effective after installation into the structure. Undertake special precautions and testing to ensure
the effective gripping and protection of the unprotected length of strands at the anchorages.
Table B113.1 - Performance Criteria for Grease and Wax for Post-Tensioning
Cap all anchorages with permanent heavy-duty plastic caps filled with grease or wax. Coat the cap
and the adjacent faces of anchorage diaphragms with a waterproof membrane and provide suitable drip
catches to prevent deck runoff infiltrating the post-tensioning anchorage and the cap.
The Post-Tensioning Supervisor must certify that the following work conforms to the requirements of
this Specification:
(i) information listed to be supplied (refer to Clause 4);
(ii) placing and fixing ducts and anchorages (refer to Clause 5);
(iii) installation of tendons (refer to Clause 6);
(iv) precautions during and after concreting (refer to clause 7);
(v) clearing of ducts and cleaning of tendons and anchorages (refer to Clauses 7.3 and 8.2);
(vi) preparing for stressing (refer to Clause 8);
(vii) conformity of concrete to strength (refer to Clause 8.3);
(viii) stressing (refer to Clause 9);
(ix) air testing and grouting (refer to Clause 10); and
(x) protection of anchorages (refer to Clause 11).
The list of nominated Post-Tensioning Supervisors acceptable to the TfNSW is held by the Bridge
Engineer (Policy & Specifications), TfNSW Bridge and Structural Engineering (telephone 02 8837
0875 facsimile 02 8837 0025).
3 SUPPLY OF DUCTS
Sheaths and removable formers used to form ducts must maintain their original cross section and
profile during construction. The friction coefficient between the duct and the tendon must not be
higher than 0.20 unless shown otherwise on the Design Documentation drawings.
Where plastic ducts are specified on the Design Documentation drawings, they must comply with the
following:
(a) External ducts must be smooth walled and conform to either:
(i) ASTM D1248 for HDPE with designation IIIC5-P34; or
(ii) Classification PE 80 B to AS 4131.
(b) Internal plastic ducts must have a corrugated profile, an allowance in the wall thickness to
account for abrasion during stressing of the tendon, and conform to either:
(i) ASTM D3350 for HDPE with cell classification 335533C; or
(ii) ASTM D1784 for rigid PVC with classification 13464B.
Provide evidence demonstrating that each supplier has the specified quality management systems in
place, and that supplied materials will comply with this Specification.
Obtain prestressing materials only from suppliers that have implemented quality management systems
to AS/NZS ISO 9001, with third-party certification accredited or accepted by JAS-ANZ. Australian
Certification Authority for Reinforcing Steels Ltd's (ACRS) certification of product compliance to
AS/NZS 4672 will be accepted as conformity to this requirement.
Provide evidence demonstrating that each supplier of prestressing materials has the specified quality
management systems in place, and provide proof of conformity of the supplied materials with the
requirements of this Specification.
Tendons must conform to AS/NZS 4672.1 and TfNSW’s approved post tensioning system. If tendons
conform with other standards, provide to the Project Verifier evidence that the tendons are of
equivalent quality.
4.2.2 Anchorages
Size and shape anchorages or bearing plates to transfer anchor loads to the concrete without overstress,
irrespective of whether the load is applied by the anchorage or the stressing jack.
Provide a centring device or spigot for the anchor head so that the tendon force is applied uniformly on
the anchor head and the bearing plate contact surface.
The combined anchorage must be capable of being loaded in stages so that accurate elongation
measurements can be taken without indeterminate losses between stages.
The loss of prestress during stressing must be uniform and correspond to a pre-established plot of
inward tendon movement versus load.
Unless accepted otherwise, the steel for anchorage bearing plates must be Grade 250 to AS 3678. The
bearing stress at the contact surface between the anchor head and the bearing plate must not exceed
400 MPa.
Anchorage castings or bearing plates manufactured from higher strength materials than Grade 250
steel may be used where higher stresses occur provided supporting calculations and experimental
evidence are supplied demonstrating that an adequate factor of safety exists.
4.2.3 Couplers
Tendons may be joined only by approved couplers designed to develop 100% of the specified
minimum breaking load of the tendon. Carry out efficiency testing to AS 1314 to prove that the
couplers develop greater than 95% of the specified minimum breaking load of the tendon for strand
tendons, and greater than 100% for bar tendons.
Swages and button-heads must develop not less than 95% of the specified minimum breaking load of
the strand or wire.
4.3 TESTING
4.3.1 Tendons
Provide, with each delivery, documentation listing the Lot numbers from which each coil or bar is
taken and NATA endorsed test certificates in accordance with TfNSW D&C Q6 as evidence of
conformity with AS/NZS 4672.
Test at least one sample from each coil of wire and strand.
Submit certificates of compliance to the post-tensioning system approval for all anchorage
components delivered.
Gripping efficiency of the combined anchorage must be maintained by achieving the required
manufacturing tolerances for each component.
Make and test at least one swaged sample during the swaging of each tendon. Cut off non-conforming
swages and install a new die prior to continuing swaging.
Test three sample button headed ends at the commencement of the fabrication of the tendons.
Test further samples throughout the job in accordance with the Inspection and Test Plan.
4.4 INSPECTION
All tendons and anchorage components, including bearing plates and cast-in anchorages, must at all
times be identifiable and traceable to the relevant Lots and test reports, which must be available on
site. Include tendon and component identification and traceability in the Inspection and Test Plan.
Where tendons are from more than one coil, maintain the identification process until stressing is
completed.
Tendons must not be damaged, kinked or bent and must be free of rust, oil, grease, tar, paint, mud or
any other deleterious substance.
Individually inspect high tensile steel bars for superficial tears, nicks, roller marks or any other form of
surface imperfection. A bar with surface imperfections that range up to 0.40 mm deep may be
accepted provided that imperfections ranging from 0.15 mm to 0.40 mm in depth are filed smooth with
a fine cut half round file. A bar with surface imperfections that exceed 0.40 mm in depth must be
treated as nonconforming.
HOLD POINT
Process Held: Assembly of tendons.
Release of Hold Point: The Nominated Authority will consider the submitted documents, before
authorising the release of the Hold Point.
Pull strand out from the coil in such a way that any twisting force which the strand might acquire
during the uncoiling will not loosen the lay of the strand.
Cut strand only with high speed carborundum disc cutters or hydraulic guillotines. Do not use flame
cutting under any circumstances.
Use appropriate methods and equipment to assemble tendons so that individual wires or strands are
not kinked, and maintain approximately the same relative position to the other wires and strands in the
tendon. Bind the wires and strands of the assembled tendon at regular intervals, so that twisting of the
tendon is minimised and no damage will be done to the tendon when it is installed.
Do not use tendons that are damaged, kinked, bent or have been subjected to fire.
5.1 PLACING
Place ducts within a tolerance of ± 6 mm in any direction of the position shown on the Design
Documentation drawings. Position anchorages within tolerances of ± 6 mm across and vertically and
± 15 mm along the tendon. The face of the anchorage must be square to within 0.5o to the line of the
tendon.
Where unavoidable conflict occurs between post-tensioning ducts and bar reinforcement, displace the
reinforcement slightly.
Before placement of the ducts inspect the profile of the duct supports for conformity.
Tie and support ducts so that they do not move during concreting. The ducts must be fixed to the
reinforcement at intervals sufficient to prevent the duct floating and causing reverse curvatures and
increases to the wobble friction factor. Space duct supports at no more than 600 mm in flanges and
1200 mm in webs.
At high points in the tendon profile, space duct supports sufficiently close to prevent crushing of the
ducts and penetration of the duct supports into the duct due to the weight of the tendon. A duct saddle
may be required at such locations.
Set all cast-in anchorages square to the line of action of the tendon with the grout inlet on the bottom
and the outlet on the top. Attach the anchorage securely to the formwork, which must be adequately
designed and constructed to prevent movement of the anchorage during concreting. Remove any
mortar or slurry adhering to bearing or wedging surfaces.
Provide slurry-tight joints at holes or gaps between the ducts and cast-in anchorages or precast end
blocks. Seal cast-in anchorages and ends of ducts at all times to prevent entry of debris, water,
concrete, mortar, slurry or foreign matter.
Prevent ingress of water into ducts, particularly those with tendons installed, before stressing by
covering exposed strands and blocking anchorages with plastic or similar.
Allow in the Inspection and Test Plan for staging of inspections of any ducts, anchorages, and/or
supporting reinforcement that may be inaccessible after the reinforcement placement has reached a
certain stage, particularly where void formers are incorporated into the reinforcement cage.
The Project Verifier must approve the proposed welding procedures before welding operations
commence. The Project Verifier may disallow the proposals if they do not eliminate the risk of
welding leads being earthed to tendons during welding operations.
Where welding is approved adjacent to a tendon, erect a shield to protect the tendon from damage.
Ensure that no damage is caused to tendons either directly by heat or weld spatter, or indirectly by
stray electric currents.
Grout vents must be at least 0.5 m higher than the grout inlet, to ensure effective head of grout.
Fit all grout inlets with a pressure gauge for measuring pressures independent of pressures observed at
the grout pump or air compressor. Unless specified otherwise, measure at the grout inlet all pressures
specified for testing and grouting of ducts.
Fit anchorages with grout caps and seal for grouting and venting operations.
Equip all grout inlets, outlets and vents with a metal valve which can be closed and opened several
times, or another approved method provided for maintaining pressure during air testing, and for
controlling the grout flow during grouting. Exposed grout vents must be in the shut position.
The pressure rating for inlets, outlets and vents must not be less than 1.0 MPa. All tubing must be of
plastic or other non-metallic materials with 20 mm minimum inside diameter, with sufficient strength
to withstand the applied pressures without distortion or damage. Tubing must be protected from
accidental damage during construction operations. Securely fasten the tubing to the duct and make all
joints airtight.
6 INSTALLATION OF TENDONS
Strands or wires may be pushed individually through the ducts provided that before and throughout the
pushing process each strand is fitted with a temporary head sized and shaped e.g. bullet, to prevent
damage to the ducts and to prevent interlocking or crossover of strands, and to prevent damage to the
tendon from the pushing rollers.
Carry out a trial assembly of each set of bars, nuts and couplers before installation.
Mark the bars and/or provide a system of reference marks in the adjacent concrete to confirm by visual
inspection that each end of each bar is fully engaged in its corresponding nut or coupler.
Submit details of the proposed procedures for ensuring that all bars will be fully engaged during
installation, including the method of visual inspection to confirm this before stressing.
7 CONCRETE WORK
7.1 GENERAL
Concrete, reinforcement and embedments must comply with TfNSW D&C B80.
Vibration of concrete around all anchorage zones and grout vents is a Critical Post-Tensioning
Activity that must be carried out under the supervision of a Post-Tensioning Supervisor.
Where required by the design, or where it is essential for construction reasons, that the tendon be
installed in the duct before concreting, provide procedures for preventing the duct being damaged
either by the installation of the tendon or by subsequent concreting operations.
Where a tendon has a dead-end anchorage or is coupled to a previously stressed anchorage, provide a
procedure for preventing ingress of concrete or cement slurry into the duct.
Tubular inserts need not be provided where it has been demonstrated by testing of a concreted
prototype that the duct will not be damaged by:
(a) opening of seams;
(b) separation of joints;
(c) becoming excessively oval;
(d) leakage of mortar or grout.
Any tendon installed in the ducts before stressing for more than:
(a) two weeks under severe corrosivity level;
(b) four weeks under moderate corrosivity level;
(c) eight weeks under low corrosivity level;
as defined in AS/NZS 2312 must be withdrawn and examined, except that where a set of similar
tendons have been in place for a similar period, one representative tendon only need be withdrawn for
examination.
The maximum jacking force must correspond to a gauge pressure between 50 % and 90 % of the
gauge capacity.
Where the bearing plate has been previously cast in concrete, compensate for any misalignment before
stressing.
Take an additional pair of test cylinders from each batch or load of concrete placed around or close to
anchorages.
Take an additional pair of test cylinders from every 30 cubic metres or part thereof of the remaining
concrete in the element.
Do not stress the tendons until testing of cylinders representing all the concrete in the element
confirms the specified transfer strength has been achieved and, unless shown otherwise on the Design
Documentation drawings, the concrete has reached the age of seven (7) days, if moist cured, or two (2)
days if steam cured, and the concrete has cooled to ambient temperature.
If the specified transfer strength is not achieved, the tendons must not be stressed until the concrete
represented by the cylinder is estimated to have attained 105% of the transfer strength.
The calibration test report for the jack and gauge combination must be accurate, not more than 6
months old, and be used to calculate nominated jacking force so that the design jacking force in the
Design Documentation is achieved. The Post-Tensioning System Supplier must nominate the
anchorage friction allowance and other jacking losses to be used when calculating the nominated
jacking force.
Calculations of elongation must account for, amongst other factors, the actual length of the stressed
tendon and the composite Youngs modulus for the tendon derived using the measured Youngs
modulus of all Lots within the tendons of the duct.
HOLD POINT
Process Held: Commencement of stressing operations.
Submission Details: Calculations and Engineer's certification as detailed in Clause 8.4 at least
five (5) working days before the commencement of stressing.
Release of Hold Point: The Nominated Authority will consider the submitted documents prior to
authorising the release of the Hold Point.
Prepare and make available before commencement of stressing forms to record at least the following
information for each tendon:
(a) Identification Number(s) of coil(s);
9 STRESSING OPERATIONS
9.1 GENERAL
9.1.1 Control of Stressing Operations
Stressing is a Critical Post-Tensioning Activity that must be carried out under the supervision of a
Post-Tensioning Supervisor.
HOLD POINT
Process Held: Each phase of stressing operations.
Submission Details: Full conformity records for the relevant tendons, stressing equipment and the
concrete to be stressed at least two (2) working days before the
commencement of each phase of stressing operations.
Release of Hold Point: The Nominated Authority will consider the submitted documents, before
authorising the release of the Hold Point.
Stress the tendons according to the stages and in the order indicated on the Design Documentation
drawings.
Set the jack accurately to the line of action of the post-tensioning tendon at each anchorage.
Stress all strands in each multistrand tendon simultaneously. Strands for flat (slab) ducts with 5 or less
strands may be stressed individually.
The initial force applied to the tendon to take up the slack must seat the jack firmly but must not
exceed 5% of the minimum breaking load of the tendon.
Where tendons consist of a number of individual strands, mark each strand after taking up the slack by
spray painting the strand, at the back of the anchor block, so that any anchorage slip may be observed
and measured accurately.
Measure with an accurate steel ruler the elongation from these markings.
Take readings of force and elongation at stages during the stressing and plot them on the previously
prepared anticipated elongation versus load plots and compare them.
Take sufficient readings before resetting the jack, to accurately determine the zero error for the
stressing graph plots.
Take sufficient readings between one reset and the next, including ones just before and just after, to
detect and compensate for any discontinuity due to the resetting operation.
Once a regular pattern has been established during stressing of the first tendons of each type, the
number of readings may be reduced, provided sufficient readings are taken to detect any significant
irregularities during the stressing of any remaining tendons.
In the case of the slippage of one or more strands, or of tendons of a group tensioned together, a
compensating increase in the elongation of the remaining strands may be permitted provided the
measured jacking force does not exceed 85% of the minimum breaking load of the remaining strands.
Alternatively, use a mono jack to stress the slipped strand until the paint marks line up. If the slipped
strand slips again, replace the wedges and re-stress it to line up the paint marks.
Failures of individual wires in strands may be accepted provided that not more than one wire per
strand is broken and the total area of the broken wires does not exceed 2.0% of the tendon area.
9.1.5 Tolerances
For an individual tendon, a ±5% tolerance applies to the nominated jacking force as measured by the
nominated gauge pressure.
For the element, a ±2% tolerance applies to the total nominated jacking force, except to overcome
friction losses as provided below.
Check the actual jacking force by measuring the tendon elongation and correlate it with the nominated
elongation. The measured elongation in each tendon must be within 5% of the nominated elongation.
Where the measured elongation at the nominated jacking force, is not within 5% of the nominated
elongation the reason for the non-correlation must be established before any further stressing.
HOLD POINT (Where there is non-correlation between jacking force and elongation)
Submission Details: Reasons for the non correlation, revised stressing method and/or revised
stressing calculations in accordance with Clause 8.4.
Release of Hold Point: The Nominated Authority will consider the submitted documents prior to
authorising the release of the Hold Point.
Where the reason for the non-correlation is due to excessive friction, Clause 9.1.7 must apply,
otherwise Clause 9.1.8 must apply.
If the nominated jacking force is attained before the measured elongation reaches 95% of the
nominated elongation, then continue stressing to reach the nominated elongation provided the
measured jacking force does not exceed 105% of the nominated jacking force.
Where the nominated elongation is still not reached, then adopt one or more of the following methods
to obtain the calculated value:
(a) Tendons may be detensioned and re-stressed (secant modulus applicable to second stressing
must be used);
(b) Water-soluble oil may be used as a tendon lubricant and washed out before grouting;
(c) Where only one jack was used, stress tendons from both ends (i.e. use two jacks), applying a
greater force first at one end, then the other, to break up minor duct blockages.
The maximum measured jacking force must not under any circumstances exceed 85% of the minimum
breaking load of the tendon, or the rated capacity of the jacking equipment used, whichever is the
lesser.
If the nominated elongation is obtained at a measured jacking force less than 95% of the nominated
jacking force then continue stressing to the nominated jacking force provided the measured elongation
does not exceed 105% of the nominated elongation. Ascertain the reasons for the excessive elongation
and take appropriate measures before re-commencing stressing.
HOLD POINT
Process Held: Cutting off and grouting of tendons.
Release of Hold Point: The Nominated Authority will consider the submitted documents prior to
authorising the release of the Hold Point.
Do not cut off tendons until all tendons in the element are stressed.
Cut off the ends of tendons with a high speed abrasive disc or wheel.
Cut tendons to maintain a minimum 20 mm length of unstressed tendon protruding from the outermost
part of the anchorage. Provide when the recesses are concreted a minimum cover of concrete over the
tendon stubs of 25 mm.
10 GROUTING
Before air testing, determine the volume of air in the duct taking into account the internal dimensions
of the duct and the space taken up by the tendon.
Before the testing, blow out any water in the duct with compressed oil-free air.
(i) With all valves closed, at the grout inlet pressurise the duct with oil-free air to 250 kPa to
confirm that the installed system has sufficient integrity for grouting;
(ii) Hold the pressure at 250 kPa for 30 seconds. A sudden drop in pressure of more than 100 kPa,
or a need to continuously inject compressed air to maintain pressure indicates that the system is
not sufficiently sealed for grouting. Locate and repair any leaks and repeat the test;
(v) Record the air pressure loss over time; a pressure loss greater than 40% must not occur within a
duration of:
D = (1.1V + 5)/60
Where: D = duration in minutes;
V = the volume of the duct minus the strand volume in litres.
If the pressure loss over time is greater than 40%, make a thorough inspection for any evidence of
leakage from, or between, ducts. Rectify leakages and retest the duct before grouting.
The Post-Tensioning Supervisor must make an assessment of the entire tendon to determine whether
grouting can proceed if the air loss criterion cannot be achieved after rectifying detected leakages.
Where air testing detects leakage between two adjacent ducts that cannot be practically rectified, air
test both as a single system and then grout the two ducts simultaneously with two lines controlled by
individual lock off valves.
10.2 OPERATIONS
Grouting is a Critical Post-Tensioning Activity that must be carried out under the supervision of a
Post-Tensioning Supervisor.
All personnel involved in grouting must be appropriately trained and experienced, and must be
acceptable to the Post-Tensioning Supervisor.
A standby grout pump must be available for use on the Site at all times.
The grouting system comprising procedure, equipment, material and personnel must be one of the
approved Proprietary Grouting Systems listed in the TfNSW Internet website:
http://www.rms.nsw.gov.au/business-industry/partners-suppliers/documents/tenders-
contracts/listofapprovedbridgecomponentssystems.pdf.
Non-approved grouting systems may still be used subject to compliance with the requirements of this
Specification. Refer to Clause 10.5.
Grout tendons as soon as practicable after stressing and in any case no later than:
(a) one week under severe corrosivity level;
(b) two weeks under moderate corrosivity level;
(c) three weeks under low corrosivity level,
Take safety precautions to prevent injury to operators and other workmen in the vicinity during
grouting operations.
Carry out grouting so that the ducts are completely filled with a dense and uniform grout.
Grout mixes may be pre-packaged when only water and admixtures are added to the dry grout mix on
site, or may be designed to meet specific project requirements where different grout mix ingredients
are batched on site.
Use the same make and type of mixing equipment used for approval of the grouting system for grout
production.
Where a grout mix is commercially confidential, forward a full submission of such mixes to the
Bridge Engineer (Policy & Specifications), TfNSW Bridge and Structural Engineering (telephone 02
8837 0875 facsimile 02 8837 0054), in confidence.
Use only fresh cement or fresh packaged grout mixes less than 1 month old.
Hold adequate stocks of cement or pre-packaged grout mixes at the grout mixer to ensure no
interruptions to the continuity of grouting operations.
Use only clean water free from oil, acid, alkali, organic or vegetable matter and from any ingredients
harmful to steel or the grout in the mix. The water must not contain more than 500 mg/l of chloride
ions.
10.5 TESTS
10.5.1 Non-approved Grouting Systems
The verification test is designed to demonstrate and verify the effectiveness of the grouting system.
The verification test comprises making up a fully assembled mock-up tendon comprising one peak and
two valleys with two end anchorages located 12 m apart fitted with grout inlets and outlets. Secure the
tendon to a supporting frame capable of taking the stressing force required to take up the slack. Grout
the mock-up tendon and protect from shock and vibration for 48 hours. Strip the tendon and slice it at
specified locations and determine the extent of air/bleed voids in the duct and the integrity of the
grout.
Prepare additional test specimens for all the performance tests of Table B113.2 during the grouting of
the mock-up tendon.
Full details of the procedures for verification testing and/or grouting system approval are available on
request from the Bridge Engineer (Policy & Specifications), TfNSW Bridge and Structural
Engineering (telephone 02 8837 0875, facsimile 02 8837 0054).
Carry out tests in accordance with Table B113.2 for bleeding, fluidity and compressive strength at the
frequency specified in Table B113.3.
Verify compliance with the approved grout of each batch delivered to the Site by submitting a
certificate of uniformity testing for the supplied grout, supported by evidence of the grout
manufacturer’s quality management system accreditation.
Sample
Test
Non approved grout Approved grout
Bleeding Test One test @ 4 hours, or one test One test per day
per batch, whichever is greater
Fluidity One test @ 4 hours, or one test One test per day
per batch, whichever is greater
Compressive Strength Test* Three cubes per anchorage Three cubes per day or Lot,
whichever larger
* Additional cubes may be taken if testing of strength is required at other than seven days.
Conformity of the batch is achieved when the acceptance tests of the grout comply with the performance
requirements specified in Table B113.2.
Grouting supply lines must connect the pumps directly to the grout inlets. All pumps, lines, tubes,
connections, and valves must be pressure rated to at least 1.0 MPa.
Pumps must be fitted with seals to prevent oil and air contamination of the grout or the loss of its
ingredients during the grouting operation.
Pumps must be capable of operating continuously with little pressure variation, and must have a
system for recirculating the grout while actual grouting is not in progress.
Pumps and grout inlets must be fitted with pressure gauges capable of reading grout pressures up to
1.0 MPa. Pressure gauges must have a full scale reading less than 1.5 MPa and must be maintained in
calibration.
Flowmeters and pressure gauges used during air testing or grouting must have NATA accredited
calibration certificates issued within the last 100 operations for which the device was used or within
the last six months, whichever is less.
Replace immediately with another gauge any gauge that has sustained hydraulic or other shock.
10.7 MIXING
Carry out batching of grout into mixers by mass for all mix constituents except liquids which may be
measured by volume.
Provide accurate control of the water/cement ratio and additives for each batch of grout. Supply
admixtures for the grout mix in single dose containers made up to suit each grout batch size.
Place the water with premixed additive in the agitator tank first, and then disperse the cement
uniformly within it. Heat or cool the mixing water if necessary to keep the grout temperature between
5 °C and 30 °C during mixing and grouting.
Mix the grout at a minimum 1000 rpm in a high-speed mixer capable of imparting a high shear to the
grout components so that a colloidal grout of uniform consistency is produced in a mixing time of less
than five minutes.
Before grouting, determine the volume of grout required for each duct and use it as a basis for control
of volumes and rates of grout injection.
Before commencing grouting, carry out sampling for acceptance (production) testing in accordance
with Clause 10.5 and Table B113.3. Where fluidity testing is required determine the efflux time
before proceeding with grouting. This time must not vary from the target efflux time by more than ± 2
seconds.
Feed the mixed grout to the pump by gravity from a hopper attached to and directly over the pump.
Keep the hopper at least partially full of grout during grouting operations.
Pass the mixed grout through a screen with 2.36 mm nominal apertures between the hopper and the
pump before injecting it into the grout inlet. Use the grout as soon as possible after mixing and in any
case within 45 minutes of adding cement to mixing water.
Inject the grout from a low point or the low end of a tendon. Maintain an even, slow, continuous flow
of grout until the duct is completely filled with pure grout and all entrapped water and air has been
expelled.
Grout to fill the duct at a rate of between 10 m and 15 m of duct per minute. Filling rates for vertical
ducts must not be more than 5 m/minute.
Close off vents and drains progressively once pure grout issues from them except for vents located
downstream (< 1.0 m) of a high point. The downstream vent must be closed off before the high point
vent.
In an unexpected event requiring the use of a high point grout vent as an inlet, implement procedures
to vent the grout from that vent to ensure that no air is entrapped in the duct.
Do not exceed a maximum grouting pressure of 400 kPa. Where the maximum grouting pressure is
not sufficient to grout the duct, then move the grout injection point to the next downstream vent which
is closed off or ready to be closed off, to reduce injection pressures whilst maintaining one way flow.
Use either single metal valves or a single use plastic valve before a reusable metal valve on all grout
lines, inlets, outlets, vents and drains. If only single metal valves are used, leave these in place
undisturbed until removed the following day:
(a) With all vents and valves open, start injecting the grout at a rate of 10-15 m/min through the
inlet in the anchorage casting or at the tendon low point using a suitable grouting pressure
dependent on grout properties and tendon geometry. This pressure is termed the operational
grouting pressure (OGP).
(b) Progressively close off vents using the metal control valves when consistent grout flows from
each vent. The quality of the grout may be checked visually. Carry out a fluidity test if there is
any doubt as to the quality of the grout issuing from the vent. The fluidity must not be less than
3 seconds than that measured during the acceptance testing.
(c) After initial grouting is completed and all the vents have been closed off under OGP:
(i) Check for any grout leaks while maintaining the minimum OGP for 1 minute;
(ii) Reduce the pressure to 100 kPa, and maintain this pressure for 5 minutes. This may
require opening of a high point vent metal control valve to reduce the pressure, closing
that vent’s metal control valve, then reinjecting a very small quantity of grout at 100 kPa;
(iii) Using the minimum possible OGP pressure, maintain grout injection whilst slowly
discharging any water, air and any diluted grout from each vent by opening and
subsequently closing the vent’s metal control valve, successively working in the direction
of grout injection starting with the inlet vent in the grout cap or the closest vent to the
grout injection point;
(iv) Reduce the OGP pressure and close off the grout inlet at 100 kPa pressure if necessary
utilising the pressure reducing procedure set out in (ii) above.
(d) Close off any plastic valves and remove their associated metal valves for cleaning and re-use to
complete the grouting.
Unless accepted otherwise, do not subject grouted ducts to shock, vibration, construction traffic or
similar loads, until 24 hours after completion of grouting.
Remove grout inlets, outlets and vents the following day and inspect the completed grouting.
Fill any voids within anchorages with epoxy. Fill any voids within the ducts at anchorages using
vacuum injected grouting or refer the matter to the Designer if the void is large. Determine the
reasons for the formation of any voids and take steps to stop it being repeated in other tendons.
If, due to blockages, equipment breakdowns, or for other reasons a duct is not filled with grout, locate
all voids, and inform the Project Verifier, together with a disposition for filling the voids.
Do not lift precast elements within three days of grouting, or transport them within seven days of
grouting.
11 PROTECTION OF ANCHORAGES
Where the ends of the tendons are not covered with concrete, apply a protective coating of epoxy in an
approved manner to the exposed parts of the anchorage and then conceal the anchorage within
positively sealed caps.
Use concrete of the same mix as for the element for concreting the anchorage recess where shown on
the Design Documentation drawings.
Clause Description
4.5 Conformity records for tendon materials
8.4 Stressing calculations
9.1.1 Conformity records for tendons, stressing equipment and concrete
9.1.6 Further stressing (where there is a non-correlation between jacking force and
elongation)
9.2 Stressing conformity records and complete grouting procedures
The following documents are a summary of documents that must be included in the PROJECT
QUALITY PLAN. Review the requirements of this Specification and others included in the deed to
determine additional documentation requirements.
The information to be submitted as part of the PROJECT QUALITY PLAN must include the
following:-
(a) Inspection of components (refer to Clause 4.4).
(b) Placement of internal ducts and anchorages (refer to Clause 5.1).
(c) Precautions during welding (refer to Clause 5.2).
(d) Installation of tendons (refer to Clause 6).
(e) Procedure for securing full engagement of high tensile bars (refer to Clause 6.2)
(f) Provision of internal support for ducts during concreting (refer to Clause 7.1).
(g) Inspection and clearing of ducts after concreting and before stressing (refer to Clauses 7.3 and
8.2).
(h) Technical Procedures in accordance with TfNSW D&C Q6 for the stressing operations in
Clause 9. Details of the personnel required to carry out the operations together with proof of
any relevant training and experience must be included.
(i) Technical Procedures in accordance with TfNSW D&C Q6 for the grouting operations in
Clause 10. Details of the personnel required to carry out the operations together with proof of
any relevant training and experience must be included.
For each of the above construction operations or activities, sample record sheets which show full
conformity of the structure after final stressing and grouting must be provided.
M1 REFERENCED DOCUMENTS
TfNSW Specifications
Australian Standards
ASTM Standards
ASTM B117 Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM C939 Standard Test Method for Flow of Grout for Preplaced-Aggregate Concrete
(Flow Cone Method)
ASTM C940 Standard Test Method for Expansion and Bleeding of Freshly Mixed Grouts for
Preplaced-Aggregate Concrete in the Laboratory
ASTM D92 Standard Test Method for Flash and Fire Points by Cleveland Open Cup Tester
ASTM D127-05 Standard Test Method for Drop Meting Point of petroleum Wax, including
Petrolatum)
ASTM D217 Standard Test Methods for Cone Penetration of Lubricating Grease
ASTM D445-06 Standard Test Method for Kinematic Viscosity of Transparent and Opaque
Liquids (and Calculation of Dynamic viscosity)
ASTM D566 Standard Test Method for Dropping Point of Lubricating Grease
ASTM D972 Standard Test Method for Evaporation Loss of Lubricating Greases and Oils
ASTM D937-07 Standard Test Method for Cone Penetration of Petrolatum
ASTM D1092 Standard Test Method for Measuring Apparent Viscosity of Lubricating
Greases
ASTM D1248 Standard Specification for Polyethylene Plastics Extrusion Materials For Wire
and Cable
ASTM D1742 Standard Test Method for Oil Separation from Lubricating Grease During
Storage
ASTM D1743 Standard Test Method for Determining Corrosion Preventive Properties of
Lubricating Greases
ASTM D1784 Standard Specification for Rigid Poly(Vinyl Chloride) (PVC) Compounds and
Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds
ASTM D3350 Standard Specification for Polyethylene Plastics Pipe and Fittings Materials
ASTM D4048 Standard Test Method for Detection of Copper Corrosion from Lubricating
Grease
M2 ABBREVIATIONS
ASTM American Society for Testing and Materials
TfNSW Transport for NSW