Cost Estimate

The document outlines a cost estimate for the XXX Project, detailing expenses across various categories including project management, hardware, software, testing, training, and reserves. The total project cost estimate is $1,521,240, with software costs constituting the largest portion at 40%. Each category is broken down into specific items with associated costs and percentages of the total budget.

Uploaded by

Rajesh Saini
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views3 pages

Cost Estimate

The document outlines a cost estimate for the XXX Project, detailing expenses across various categories including project management, hardware, software, testing, training, and reserves. The total project cost estimate is $1,521,240, with software costs constituting the largest portion at 40%. Each category is broken down into specific items with associated costs and percentages of the total budget.

Uploaded by

Rajesh Saini
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

XXX Project Cost Estimate

Prepared by: Date:


Note: Change the WBS items and other entries to meet your project needs. This data is from Figure 7-1 of Schwalbe's text
Information Technology Project Management, Fourth Edition. Also make sure the formulas work properly based on the data you enter.
# Units/Hrs. Cost/Unit/Hr. Subtotals WBS Level 1 Totals % of Total
WBS Items
1. Project Management $306,300 20%
1.1 Project manager 960 $100 $96,000
1.2 Project team members 1920 $75 $144,000
Contractors (10% of software development and testing) $66,300
2. Hardware $76,000 5%
2.1 Handheld devices 100 $600 $60,000
2.2 Servers 4 $4,000 $16,000
3. Software $614,000 40%
3.1 Licensed software 100 $200 $20,000
3.2 Software development* $594,000
4. Testing (10% of total hardware and software costs) $69,000 $69,000 5%
5. Training and Support $202,400 13%
5.1 Trainee cost 100 $500 $50,000
5.2 Travel cost 12 $700 $8,400
5.3 Project team members 1920 $75 $144,000
6. Reserves (20% of total estimate) $253,540 $253,540 17%
Total project cost estimate $1,521,240
* See software development estimate
a you enter.
* Software development
Contra 3000 $150 $450,000
Projec 1920 $75 $144,000
Total labor estimate $594,000
Funct Quantity ConversioFunction Points
Extern 10 4 40
Extern 3 7 21
Extern 3 5 15
Extern 3 4 12
Logica 6 10 60
Total function points 148
Java 2 languange equival 46
Source lines of code (S 6,808
30.27
T 4,842.55
C $120
T 581,106