Dar - Toilet 1

The progress report details daily activities from January 4 to January 31, 2025, for the Market 1 Toilet Area project, including tasks such as installation of footing rebars, concrete pouring, and alignment of columns. Each report includes manpower details, equipment used, and photo documentation. The activities show a consistent progression in construction tasks with varying manpower and equipment over the reporting period.

Uploaded by

Aquin Mark Nada
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views25 pages

Dar - Toilet 1

The progress report details daily activities from January 4 to January 31, 2025, for the Market 1 Toilet Area project, including tasks such as installation of footing rebars, concrete pouring, and alignment of columns. Each report includes manpower details, equipment used, and photo documentation. The activities show a consistent progression in construction tasks with varying manpower and equipment over the reporting period.

Uploaded by

Aquin Mark Nada
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 25

Project I.D.

Number:
PROGRESS REPORT
January 4, 2025

ACTIVITIES:
Market 1 - Toilet Area

Daily Activity Report: Jan. 4, 2025

Activity:
* Installation of Footing rebars
* alignment of 4 column rebars
Manpower:
Engineer. - 1
Skilled -5
Laborer. - 1
Others
Equipment

Pictures: pls see below

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 1
Project I.D. Number:
PROGRESS REPORT
January 5, 2025

ACTIVITIES:

Market 1 - Toilet Area


Daily Activity Report: Jan. 5, 2025

Activity:
* Installation of Footing forms
* Excavation of wall footing
Manpower:
Engineer. - 1
Skilled -1
Laborer. - 1
Others
Equipment

Pictures: pls see below

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 4
Project I.D. Number:
PROGRESS REPORT
January 6, 2025

ACTIVITIES:
Market 1 - Toilet Area
Daily Activity Report: Jan. 6, 2025

Activity:
* Installation of Footing forms
* Excavation of wall footing
* Ready for inspection for concrete
pouring.
* Concrete pouring
Manpower:
Engineer. - 1
Skilled -7
Laborer. - 2
Others
Equipment

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 7
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 7, 2025

ACTIVITIES:
Market 1 - Toilet Area

Daily Activity Report: Jan. 7, 2025

Activity:
* Excavation of Footing near septic tank
* Excavation of wall footing
* Ready for inspection for concrete pouring.
* Concrete pouring
Manpower:
Engineer. - 1
Skilled - 4 Market 1
Skilled - 2 Office extension
Laborer. - 2 compound CHB
Others
Equipment
PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 10
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 11, 2025

ACTIVITIES:

Toilet-1
Activity:
*Installation of scaffoldings
*Installation of forms (col. 2units)
*Excavation of wall footing
*Installation & fabrication column rebars
Manpower
Foreman:1
Skilled :7
Laborer. :2
Driver. :

Equipment
Bagger mixer :0
Conc.vibrator. :0
PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 13
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 13, 2025

ACTIVITIES:
Toilet-1

Activity:
*Installation & alignment of scaffoldings
*Installation of forms (col. 4units)
*Installation of column rebars
Manpower
Foreman:1
Skilled :7
Laborer. :3
Driver. :
Equipment
Bagger mixer :0
Conc.vibrator. :0

Concerned: Septic tank location


PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 16
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 16, 2025

ACTIVITIES:
Toilet-1

Activity:
*Installation & alignment of scaffoldings
*Installation of scaffolding for runner of beam.
Manpower
Foreman:1
Skilled :3
Laborer. :1
Driver. :

Equipment
Bagger mixer :0
Conc.vibrator. :0

Concerned: Septic tank location


PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 19
Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 20
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 17, 2025

ACTIVITIES:
Toilet-1
Activity:

*Alignment of column for preparation of concrete pouring of footing


*Concrete pouring of footing 4 unit

Manpower
Foreman:1
Skilled :6
Laborer. :3
Driver. :

Equipment
Bagger mixer :1
Conc.vibrator. :1

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 22
Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 23
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 20, 2025

ACTIVITIES:
Toilet-1

Activity:
*Alignment of column
*Installation of column forms 6 units ready for closure for tomorrow concrete pouring

Manpower
Foreman:1
Skilled :4
Laborer. :3
Driver. :

Equipment
Bagger mixer :0
Conc.vibrator. :0

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 25
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 21, 2025

ACTIVITIES:
Toilet-1
Activity:

*Alignment of 4 column
*Ready for Concrete pouring (waiting only for PFDA & VTLC ME for witbess)
*Concrete pouring 4 columns
Manpower
Foreman:1
Skilled :4
Laborer. :5
Driver. :

Equipment
Bagger mixer :1
Conc.vibrator. :1

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 28
Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 29
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 22, 2025

ACTIVITIES:
Toilet-1
Activity:
*Alignment of 4 columns for concrete pouring preparation.
*Concrete pouring @ 1 pm.
Manpower
Foreman:1
Skilled :4
Laborer. :5

Rescue Labor from MRF: 3


Rescue Fabricatiob team: 3
Equipment
Bagger mixer :1
Conc.vibrator. :1

Site Concerned:
PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 31
Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 32
Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 33
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 23, 2025

ACTIVITIES:
Toilet-1
Activity:
*Stripping of column forms
*Retouch honeycomb concrete

Manpower

Skilled :4
Laborer. :3

Absent 1 Labor

Equipment
Bagger mixer :0
Conc.vibrator. :0

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 34
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 24, 2025

ACTIVITIES:
Toilet-1
Activity:
*Align front wall footing for preparation of concrete pouring
*Concrete pouring of 1 column & wall footing front.
Manpower

Skilled :2
Laborer. :3
Mixer operator :1

Rescue 1 skilled to trim trees


Absent 1 Labor & 1 Skilled

Equipment
Bagger mixer :1
Conc.vibrator. :1
PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 37
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 25, 2025

ACTIVITIES:
Toilet-1
Activity:
*Align front wall footing for preparation of concrete pouring
*Concrete pouring wall footing side & back
Manpower
Skilled :2
Laborer. :4
Mixer operator :0

Rescue 1 skilled to trim trees


Rescue 1 skilled to MRF
Absent 1 Labor (mixer operator)

Equipment
Bagger mixer :0
Conc.vibrator. :0
PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 40
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 27, 2025

ACTIVITIES:
Toilet-1
Activity:
*Alignment of bottom beam runner
*Cont. Wall footing
Manpower

Skilled :3
Laborer. :1

Rescue 1 skilled to trim trees


Rescue 1 skilled from Fabrication team
Rescue 2 laborer to MRF
Absent 1 Labor

Tools
Chipping hammer gun : 1
PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 43
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 28, 2025

ACTIVITIES:

Toilet-1
Activity:

*Cont. Instllation of column rebar splicing & ties


*Cont. Installation of bottom forms beam (runner)

Manpower

Skilled :5
Foreman :1

Site Concerned:

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 46
Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 47
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 29, 2025

ACTIVITIES:

Toilet-1
Activity:

*Cont. Instllation of column rebar splicing & ties


*Cont. Installation of bottom forms beam (runner)
*Fabricate siding beam forms

Manpower

Skilled : 6

Site Concerned:

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 49
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 30, 2025

ACTIVITIES:

Toilet-1

Activity:

*Cont. Instllation of installation of beam rebars


*Installation of siding beam forms
*Fabricate siding beam forms

Manpower

Skilled : 5
Laborer : 2

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 52
Project I.D. Number: 23MO - 0256
PROGRESS REPORT
January 31, 2025

ACTIVITIES:

Toilet-1

Activity:

*Cont. Installation of beam rebars


*Installation of siding beam forms

Manpower

Skilled : 2
Laborer : 4

PHOTO DOCUMENTATION:

Prepared by:

Engr. AQUIN MARK NADA


QCQA / CE Page 55