Project Name: WEST BRIDGE Project Address: West bridge 31 building 3rd floor, eco world Bellandur , Bengaluru
Address: HBR layout Nagavara, Bangalore. Project Manager Name: Mr. Suraj
Equipment, Tools & tackles Spec: hammer, grinding M/C, drilling M/C, screwing M/C,
Activities: Duct jointing, threaded rod fixing, duct errection, insulation, material shifting work,
copper pipe brazing work, welding, commissioning, housekeeping
E - Extreme Risk: The hazard has the potential to kill or permanently disableaperson H - High Risk: The hazard has the potential to cause a LTI ≥ 7days
M - Medium Risk: The hazard has the potential to cause a LTI <7days L - Low Risk: The hazard has the potential to cause a minor injury that will not disable a person (ie: NilLTI)
Activity Procedure (in steps) Possible Hazards Risk Rating (See Control Measures Controlled Person who will
(Break the job down into (Identify the hazards below) (Describe what action or procedure will be taken to Risk Score ensure this
steps. Each step should associated with each eliminate or minimize the risk of injury or damage. Use the happens
accomplish some major step. Examine each to Hierarchy of Controls below as a guide
tasks and be in logical find possibilities that 1. Eliminate the Hazard
sequence.) could lead to an accident 2. Substitute the material or equipment
or potential harm arising.) 3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6.PPE
1.Material 1. materials 1. Slips and trips M 1. Obtain necessary PTW from the before start 8 Supervisor/Safety
movement from shifting by 2. Inadequate the work. Officer/project
storage yard to manually illumination 2. Clear all obstructions from the passage ways. manager
working area by 2. above 25 kg 3. Fall of material 3. Adequate illumination shall be provided at
using Trolley
Manually. 4. Hit to Other material movement area.
for shifting
person 4. Sufficient Manpower to be deployed for
work
5. Sharp edges. movement of material.
6. Muscle strain 5. Manual handling training to be conducted
before commencement of job.
6. Material stacking to be away from passage
ways, Fire Exit etc.,
7. Wear all job specific PPEs (Hard hat, Reflective
jacket, Cut resistant hand gloves,
Google’s, Shoulder strap etc) as per IS code.
8. Ensure proper supervision at work area.
9. Manual handling above 20 kg is not allowed.
10.Ensure barricade material storage area.
2.Use of aluminum 1. Mobile scaffold 1. Fall of a person from H 1. Trained, experienced workforce to be deployed. 10 Supervisor/Safety
mobile scaffold erection by height 2. Trained, experienced & authorized operator to be Officer/project
installation of duct authority 2. Fall of a material deployed for the equipment. manager
at 2.5 meter of member. from height 3. Training on the hazards and control measures
2. GRF fitting as
height. 3. Topple of scaffold related to equipment's & related works to be
per work height
Duct fabrication, 1. using GI sheets 1. Use of damaged H 1. Trained, experienced workforce to be deployed. 10 Supervisor/Safety
assembling and for duct scaffolds 2. Trained, experienced & authorized operator to be Officer/project
erection (GI, Pre- fabrication 2. Fall of men and deployed for the equipment. manager
insulated ducts) 2. duct jointing materials 3. Training on the hazards and control measures
duct by duct
3. Ergonomics related to equipment's & related works to be
3. screwing to join
4. Deployment of conducted by the vendor (weekly, fortnightly,
the ducts
untrained persons monthly)
5. Sharp edges, tools 4. Toolbox talks to be given by the vendor to the work
6. Excessive Noise force daily for the precautions to be taken in the
7. Over stacking of activity.
Materials 5. All hand tools, power tools to be inspected and
8. Use of Defective and damaged / defective tools to be rectified / removed.
damaged power tools, 6. Safety helmet, safety shoes / gumboots, hand
duct lifter gloves, reflective jacket, goggles, nose mask to be
9. Electrocution used.
10. Obstruction with 7. Stagnated water to be removed.
Overhead services 8. Materials to be segregated, stacked in order as per
11. Lifting of excessive the shape and size of the materials / objects.
weight 9. Storage area to be identified, barricaded and
12. Obstructions in signage's to be provided.
access 10. Floor cleaning to be done using floor manual
sweeper machines.
11. Sprinkling of water before sweeping the floors to
Duct insulation 1. using K flex 1. Vapors Inhalation H 1. Trained, experienced workforce to be deployed. 10 Supervisor/Safety
(adhesives) adhesive for 2. absorption 3. Training on the hazards and control measures Officer/project
insulation work 3. Spillage of Adhesive related to equipment's & related works to be manager
2. adhesive materials conducted by the vendor (weekly, fortnightly,
applying to
4. Deployment of monthly)
ducts
untrained person 4. Toolbox talks to be given by the vendor to the work
5. Fire force daily for the precautions to be taken in the
6. Unauthorized entry activity.
7. Use of damaged 5. All hand tools, power tools to be inspected and
scaffold damaged / defective tools to be rectified / removed.
8. Fall of men and 6. Safety helmet, safety shoes / gumboots, hand
materials gloves, reflective jacket, goggles, nose mask to be
9. Contact of adhesive used.
with sparks due to hot 7. Material to be stack below 2 m
work 8. Materials to be segregated, stacked in order as per
10. Poor ventilation the shape and size of the materials / objects.
9. Storage area to be identified, barricaded and
signage's to be provided.
10. Floor cleaning to be done using floor manual
sweeper machines.
11. Sprinkling of water before sweeping the floors to
be done.
Copper pipe fixing 1.Copper pipe fixing to 1. Use of damaged H 1. Trained, experienced & medically fit workforce to 10 Supervisor/Safety
laying and jointing out door units and split scaffolds be deployed. Officer/project
work (Brazing work) units 2 Fall of men and 2. Trained, experienced & authorized operator to be manager
2. Copper pipe joining by materials deployed for the equipment.
brazing work
3. Deployment of 3. Training on the hazards and control measures
untrained persons related to equipment's & related works to be
4.Slips and trips conducted by the vendor (weekly, fortnightly,
5. Ergonomics monthly)
6. Fire & Explosion 4. Toolbox talks to be given by the vendor to the work
7. Use of damaged force daily for the precautions to be taken in the
Commissioning & 1. Using nitrogen 1. Sudden release of M 1. Trained, experienced & medically fit workforce to 8 Supervisor/Safety
energizing of new & R410 gas for energy leading to be deployed. Officer/project
In addition to the above, the supervisor is to provide training in the use of this WMS, issue PPE and provide training in the same,
supervise the work, ensure conformity with this WMS, amend the WMS when additional hazards are found (and if applicable, ensure
all workers receive a tool-box talk to discuss the control measures for the additional hazards).
DESCRIPTION OF TRAINING THAT HAS BEEN GIVEN TO PEOPLE INVOLVED WITH THE WORK WORK ACTIVITY
TRAINING: Height work &LOTO
TICKETS, PERMITS or LICENCES REQUIRED undertaking this work (i.e. Certificates of Competency, Confined Spaces etc):
N.B. - Copies of the above must be shown to the Principal Contractor during site induction.
LEGISLATION, CODES OF PRACTICE and GUIDELINES applicable to this work All work to