Washington DOT Design Manual
Washington DOT Design Manual
M 22-01.18
December 2019
To get the latest information on individual WSDOT publications, sign up for email updates at:
www.wsdot.wa.gov/publications/manuals
Foreword
The Design Manual is for use by Washington State Department of Transportation personnel,
consultants and contractors engaged in transportation design. It provides policies, procedures,
and methods for developing and documenting the design of improvements to the
transportation network in Washington. It has been developed for state facilities and may not
be appropriate for all county roads or city streets that are not state highways.
The Federal Highway Administration has agreed to approve designs that follow the guidance in
the Design Manual; therefore, following the guidance is mandatory for state highway projects.
When proposed designs meet the requirements contained in the Design Manual, little
additional documentation is required.
The Design Manual supplements the engineering analyses and judgment inherent with
practical design and provides uniform procedures for documenting and implementing design
decisions. The Design Manual emphasizes practical design as a means to produce
environmentally conscious, sustainable, context-based designs that achieve the purpose and
need for the lowest cost. Practical design considers the needs of all users, fostering livable
communities and modally integrated transportation systems used safely by all, including
motorists, freight haulers, transit, pedestrians, and bicyclists.
Updating the Design Manual is an ongoing process and revisions are issued regularly. The
addition of new or modified design criteria to the Design Manual through the revision process
does not imply that existing features are deficient in any way, nor does it suggest or mandate
immediate engineering review or initiation of new projects. Comments, questions, and
improvement ideas are welcomed. Use the comment form on the next page or the contact
information on the Design Policy Internet Page: www.wsdot.wa.gov/design/policy
___________________________________________
PO Box 47329
Olympia, WA 98504-7329
Comment:
Division 4 – Surveying
Chapter 400 Surveying and Mapping
400.01 General
400.02 References
400.03 Procedures
400.04 Datums
400.05 Global Positioning System
400.06 WSDOT Survey Monument Database
400.07 Geographic Information System
400.08 Photogrammetric Surveys
400.09 Documentation
Division 7 – Structures
Chapter 700 Project Development Roles and Responsibilities for Projects
With Structures
700.01 General
700.02 Procedures
Chapter 710 Site Data for Structures
710.01 General
710.02 Required Data for All Structures
710.03 Additional Data for Waterway Crossings (Bridges and
Buried Structures)
710.04 Additional Data for Grade Separations
Division 8 – Hydraulics
Chapter 800 Hydraulic Design
800.01 General
800.02 References
800.03 Hydraulic Considerations
800.04 Safety Considerations
800.05 Design Responsibility
800.06 Documentation
Division 12 – Geometrics
Chapter 1210 Geometric Plan Elements
1210.01 General
1210.02 Horizontal Alignment
1210.03 Distribution Facilities
1210.04 Number of Lanes and Arrangement
1210.05 Pavement Transitions
1210.06 Procedures
1210.07 Documentation
1210.08 References
Chapter 1220 Geometric Profile Elements
1220.01 General
1220.02 Vertical Alignment
1220.03 Coordination of Vertical and Horizontal Alignments
1220.04 Airport Clearance
1220.05 Railroad Crossings
1220.06 Procedures
1220.07 Documentation
1220.08 References
Chapter 1230 Geometric Cross Section Basics
1230.01 General
1230.02 Guidance for Specific Facility Types
1230.03 Common Elements
1230.04 Jurisdiction for Design and Maintenance
1230.05 References
Chapter 1231 Geometric Cross Section – Highways
1231.01 General
1231.02 Design Up
1231.03 Common Elements
1231.04 Vehicle Lanes
1231.05 Modally Integrated Cross Sections
1231.06 Road Diets and Retrofit Options
1231.07 References
Chapter 1232 Geometric Cross Section – Freeways
1232.01 General
1270.09 References
1340.08 Mailboxes
1340.09 Documentation
Chapter 1350 Railroad Grade Crossings
1350.01 General
1350.02 References
1350.03 Plans
1350.04 Traffic Control Systems
1350.05 Nearby Roadway Intersections
1350.06 Pullout Lanes
1350.07 Crossing Surfaces
1350.08 Crossing Closure
1350.09 Traffic Control During Construction and Maintenance
1350.10 Railroad Grade Crossing Petitions and WUTC Orders
1350.11 Grade Crossing Improvement Projects
1350.12 Light Rail
1350.13 Documentation
Chapter 1360 Interchanges
1360.01 General
1360.02 Interchange Design
1360.03 Ramps
1360.04 Interchange Connections
1360.05 Ramp Terminal Intersections at Crossroads
1360.06 Interchanges on Two-Lane Highways
1360.07 Interchange Plans for Approval
1360.08 Documentation
1360.09 References
Chapter 1370 Median Crossovers
1370.01 General
1370.02 Analysis
1370.03 Design
1370.04 Plan Updates and Approvals
1370.05 Documentation
1600.04 Medians
1600.05 Other Roadside Safety Features
1600.06 Documentation
1600.07 References
Chapter 1610 Traffic Barriers
1610.01 Introduction
1610.02 Barrier Impacts
1610.03 General Barrier Design Considerations
1610.04 Beam Guardrail
1610.05 High-Tension Cable Barrier
1610.06 Concrete Barrier
1610.07 Bridge Traffic Barriers
1610.08 Other Barriers
1610.09 References
Chapter 1620 Impact Attenuator Systems
1620.01 General
1620.02 Design Criteria
1620.03 Selection Considerations
1620.04 Transportable Attenuators (Truck-Mounted and Trailer-Mounted)
1620.05 Older Systems
1620.06 Inertial Barrier Systems (Sand Barrels)
Glossary
100.01 Purpose
WSDOT has developed the Design Manual to reflect policy, outline a uniformity of methods and
procedures, and communicate vital information to its employees and others who develop
projects on state highways. When properly used, the manual will facilitate the development of a
highway system consistent with the needs of the multimodal traveling public.
WSDOT designers are required to comply with the Design Manual. The Federal Highway
Administration (FHWA) has agreed to approve designs that follow guidance in the Design
Manual; therefore, adherence to the guidance presented is not optional for state highway
projects.
The information, guidance, and references contained herein are not intended as a substitute
for sound engineering judgment. The Design Manual is not a comprehensive textbook on
highway engineering, nor does it attempt to cover all the possible scenarios Washington’s
highways present. It is recognized that some situations encountered are beyond the scope
of this presentation.
If you have design questions not answered by the Design Manual, contact the Headquarters
(HQ) Design Office.
The online version of the manual enables you to conduct a word search of the entire manual.
Opening an individual chapter is faster, but a word search is limited to that chapter.
The Design Manual is continually revised to reflect changing processes, procedures, regulations,
policies, and organizations. Feedback from users is encouraged to improve the manual for
everyone. Comments may be submitted by any method that is convenient for you. There is
a comment form in the front of the manual, or comments may be made via the contact names
on the Design Policy Internet page (see link above). Note that the Design Policy Internet page
includes a link to an errata page, which provides a list of known technical errors in the manual.
Manual users are encouraged to view this page on a regular basis.
A contents section lists all chapters and the major headings of the sections/pages. The exhibits
section lists all the exhibits in the manual.
Most chapters include a list of references, including laws, administrative codes, manuals, and
other publications, which are the basis for the information in the chapter. The definitions for
terms used in the Design Manual are found in the Glossary.
The Design Manual is designed to allow for flexibility in design for specific and unusual
situations. For unusual circumstances, the manual provides mechanisms for documenting
the reasons for the choices made.
The Design Manual is developed for use on Interstate and state highways and may not
be suitable for projects on county roads or city streets.
For state highway routes, projects are designed using the Design Manual practical design
approach (see Chapter 1100 and Division 11). If WSDOT guidance is not used on a project,
appropriate documentation and approvals are required (see Chapters 300 and 1100).
When WSDOT designs facilities that will be turned over to local jurisdictions, those facilities
are to be designed using appropriate local geometric design criteria.
When local jurisdictions design any element of state highway facilities, the Design Manual must
be used. Local jurisdictions are free to adopt this manual for their local criteria or to develop
their own specialized guidance for facilities not on state highway routes.
Division 1 – General Information: Presents an overview of the Design Manual, its contents and
application, as well as a chapter on Design-Build projects.
• Chapter 100 – Manual Description: Chapter content/resources within the Design
Manual.
• Chapter 110 – Design-Build Projects: How the Design Manual applies to design-build
projects: includes terminology and reference to design-build contract documents.
Division 2 – Hearings, Environmental, and Permits: Provides the designer with information
about the public involvement and hearings process, the environmental documentation process,
and the permit process.
• Chapter 210 – Public Involvement and Hearings: Developing a project-specific public
involvement plan; the ingredients of an effective public involvement plan; and methods
for public involvement.
• Chapter 225 – Environmental Coordination: Provides a summary of the relevant
provisions in the Environmental Manual. Gives designers a brief overview and direction
to environmental resources.
• Chapter 301 – Design and Maintenance Coordination – Best Practices: Means and
methods for coordinating design with maintenance concerns and needs.
• Chapter 305 – Project Management: Brief description and links to WSDOT project
management resources.
• Chapter 310 – Value Engineering: A systematic, multidisciplinary process study early in
the project design stage to provide recommendations to improve scope, functional
design, constructability, environmental impacts, or project cost—required by federal
law for high-cost, complex projects.
• Chapter 320 – Traffic Analysis: Procedural guidance and general requirements for
conducting traffic analyses.
• Chapter 321 – Sustainable Safety Analysis: Informational and procedural guidance for
conducting safety analyses, within the current extent of the applications.
Division 4 – Surveying: Includes criteria for surveying, mapping, and monumentation
requirements.
• Chapter 400 – Surveying and Mapping: The procedures within WSDOT for project
surveying.
• Chapter 410 – Monumentation: The requirements and procedures for Monumentation.
Division 5 – Right of Way and Access Control: Provides guidance on right of way considerations;
access revision report; limited/managed access; and fencing.
• Chapter 510 – Right of Way Considerations: The right of way and easement acquisition
process.
• Chapter 520 – Access Control: WSDOT Access Control program information.
• Chapter 530 – Limited Access Control: Clarification on full, partial, and modified limited
access control.
• Chapter 540 – Managed Access Control: The classes of managed access highways and
the access connection permitting process.
• Chapter 550 – Freeway Access Revision: The process for interchange access revisions on
freeways and the steps for producing an access revision report.
• Chapter 560 – Fencing: The purpose of fencing, types of fencing, and fencing design
criteria.
Division 6 – Soils and Paving: Presents guidance for investigating soils, rock, and surfacing
materials; estimating tables; and guidance and criteria for the use of geosynthetics.
• Chapter 610 – Investigation of Soils, Rock, and Surfacing Materials: The requirements
for qualifying a materials source, geotechnical investigations, and the documentation
to be included in the Project File.
• Chapter 620 – Design of Pavement Structures: Estimating tables for the design of
pavement structures.
• Chapter 630 – Geosynthetics: The types/applications of geosynthetic drainage,
earthwork, erosion control, and soil reinforcement materials.
Division 7 – Structures: Provides guidance for the design of structures for highway projects,
including site data for structures, bridges, retaining walls, and noise walls.
• Chapter 700 – Project Development Roles and Responsibilities for Projects With
Structures: WSDOT’s project development process: roles and responsibilities for
projects with structures during the project development phase of a project.
• Chapter 710 – Site Data for Structures: Information required by the HQ Bridge and
Structures Office to provide structural design services.
• Chapter 720 – Bridges: Basic design considerations for developing preliminary bridge
plans and guidelines on basic bridge geometric features.
• Chapter 730 – Retaining Walls and Steep Reinforced Slopes: Design principles,
requirements, and guidelines for retaining walls and steep reinforced slopes.
• Chapter 740 – Noise Barriers: Factors considered when designing a noise barrier.
Division 8 – Hydraulics: Addresses the issue of hydraulics and serves as a guide to highway
designers to identify and consider hydraulic-related factors that may impact the design.
• Chapter 800 – Hydraulic Design: Hydraulic considerations for highway projects involving
flood plains, stream crossings, channel changes, and groundwater.
Division 10 – Traffic Safety Elements: Introduces the designer to traffic safety elements such as
work zone traffic control, signing, delineation, illumination, traffic control signals, and Intelligent
Transportation Systems (ITS).
• Chapter 1010 – Work Zone Safety and Mobility: Planning, design, and preparation
of highway project plans that address work zone safety and mobility requirements.
• Chapter 1020 – Signing: The use of signing to regulate, warn, and guide motorists.
• Chapter 1030 – Delineation: The use of pavement markings to designate safe traffic
movement.
• Chapter 1040 – Illumination: Illumination design on state highway construction
projects.
• Chapter 1050 – Intelligent Transportation Systems (ITS): Applying computer and
communication technology to optimize the safety and efficiency of the highway system.
Division 11 – Practical Design: Provides practical design guidance for WSDOT projects.
• Chapter 1100 – Practical Design: Includes an overview and description of the WSDOT
Practical Solutions initiative, the practical design process, and the relevant chapter
information necessary to complete each process step.
• Chapter 1270 – Auxiliary Lanes: Auxiliary facilities such as climbing lanes, passing lanes,
slow-vehicle turnouts, shoulder driving for slow vehicles, emergency escape ramps, and
chain-up areas.
Division 14 – HOV and Transit: Provides design guidance on HOV lanes and transit facilities.
• Chapter 1410 – High-Occupancy Vehicle Facilities: Evaluating and designing high-
occupancy vehicle (HOV) facilities.
• Chapter 1420 – HOV Direct Access: Design guidance on left-side direct access to HOV
lanes and transit facilities.
• Chapter 1430 – Transit Facilities: Operational guidance and information for designing
transit facilities such as park & ride lots, transfer/ transit centers, and bus stops and
pullouts.
Division 15 – Pedestrian and Bicycle Facilities: Provides guidance on pedestrian and bicycle
facility design.
• Chapter 1510 – Pedestrian Facilities: Designing facilities that encourage efficient
pedestrian access that meets ADA.
• Chapter 1515 – Shared-Use Paths: Guidance that emphasizes pedestrians are users
of shared-use paths and accessibility requirements apply in their design.
• Chapter 1520 – Roadway Bicycle Facilities: Selecting and designing useful and cost-
effective bicycle facilities.
Division 16 – Roadside Safety Elements: Addresses design considerations for the area outside
the roadway, and includes clear zone, roadside, safety mitigation, traffic barriers, and impact
attenuator systems.
• Chapter 1600 – Roadside Safety: Clear zone and roadside design, mitigation guidance,
and roadside safety features, including Rumble Strips.
• Chapter 1610 – Traffic Barriers: Design of traffic barriers.
• Chapter 1620 – Impact Attenuator Systems: Permanent and work zone impact
attenuator systems.
Division 17 – Roadside Facilities: Provides design guidance for the area outside the roadway,
including rest areas and truck weigh sites.
• Chapter 1710 – Safety Rest Areas and Traveler Services: Typical layouts for safety rest
areas.
• Chapter 1720 – Weigh Sites: Guidance on designing permanent, portable, and shoulder-
sited weigh sites.
110.01 General
This chapter emphasizes that the Design Manual applies to the delivery methods of all
Washington State Department of Transportation (WSDOT) capital projects, including design-
build projects. Certain terms are defined to coincide with WSDOT design-build project delivery;
however, it is beyond the scope of this manual to extensively define design-build projects.
Design-build projects are based on their own contractual documents (such as a Request for
Proposal), which present directive language intended to legally define the project and identify
requirements and controls, roles and responsibilities, and procedures and outcomes.
Design-build is a method of project delivery in which WSDOT executes a single contract with one
entity (the design-builder) for design and construction services to provide a finished product. In
a traditional WSDOT design-bid-build contract, the design process is completed independent of
the construction contract. Under WSDOT policy, the Basis of Design (see Chapters 1100 and 300)
is approved prior to issuing an RFP.
Delivering a project using design-build contracting eliminates very few steps when compared to
the typical WSDOT design-bid-build process. The same project work tasks and products are
normally required whether performed by WSDOT or the design-builder. The timing, order, and
level of task detail performed are what make design-build contracting different than design-bid-
build. The design-build process may shift many tasks and responsibilities from WSDOT to the
design-builder depending on the project’s scope/risk analysis. The shift changes the order and
development detail of the tasks and thus must be reflected in the process through contractual
documents.
design-builder The firm, partnership, joint venture, or organization that contracts with WSDOT
to perform the work.
designer This term applies to WSDOT design personnel. Wherever “designer” appears in
this manual, design-build personnel shall deem it to mean: Engineer of Record, Design Quality
Assurance Manager, design-builder, or any other term used in the design-build contract to
indicate design-build personnel responsible for the design elements of a design-build project,
depending on the context of information being conveyed.
Project Engineer This term applies to WSDOT personnel. Wherever “Project Engineer” appears
in this manual, the design-builder shall deem it to mean “Engineer of Record.”
Request for Proposal (RFP) The document package issued by WSDOT requesting submittal of
proposals for the project and providing information relevant to the preparation and submittal of
proposals, including the instructions to proposers, contract documents, bidding procedures, and
reference documents.
With the exclusion of this chapter, the Design Manual is intentionally written to avoid or
minimize the use of directive words like “shall” and “should” in order to retain this important
flexibility for the larger set of users.
In the case of design-build projects, design flexibility applies to the extent allowed by the
contract. The design-builder shall refer to the project-specific RFP for design guidance. The RFP
will identify design decisions and provide technical specifications relating to the project’s design.
For design-build projects, many design responsibilities shift to the design-builder once the
Notice to Proceed is issued. WSDOT is still responsible for establishing the scope, performance
measurements, and existing conditions of the site as part of preliminary design. Any preliminary
design done by WSDOT would be filed and documented in the Design Documentation Package
(DDP) and/or the Project File (PF), which are provided to the selected design-builder to maintain
throughout the design-build project design phase and then returned to WSDOT for retention.
It is important to note that the design content presented in this manual has valid application
based not on delivery method, but on practical design procedures and specified needs such as
roadway and land use context, traffic volumes, and identified performance needs, as presented
in Chapter 1100 (and other chapters).
It is also important to specify that design documentation is a requirement for WSDOT projects,
regardless of delivery method. WSDOT still holds the valid requirement to have an organized
design documentation file and as-constructed plans for future reference after the project is
built.
Plan accuracy, conformance with established design guidelines, and constructability of the
project rests with the design-builder.
The DDP and the PF include all the elements identified in the project RFP. The RFP specifies
various DDP and PF submittals to WSDOT, identifying how each item will be submitted (report,
plan sheet element, Basis of Design and design parameter element, and so on) and who is
responsible for the development status (such as complete, in progress, or not started) of each
item. The RFP also indicates that some of the DDP and PF items have components that were
started by WSDOT and that the design-builder shall complete or update those item(s). It is the
design-builder’s responsibility to obtain copies of the information from WSDOT for use in
completing the DDP and PF items.
The DDP and the PF require retention of original, signed documents—not copies.
The RFP typically specifies that the design-builder shall provide WSDOT with updates to the DDP
and PF items throughout construction of the project.
For further guidance on design documentation and WSDOT acceptance thereof, see Chapter
300, the project RFP, and the Design Documentation Checklist.
110.04 References
Design-Builder Delivers
WSDOT Begins Project Completed Documentation
Design Documentation
Documentation Package to WSDOT
Handoff to Design-Builder
Package 1
Preliminary Design Submittal
Design Approval Final Design Submittal
Design Submittals are released in packages
Released for Construction Submittal by the Design-Builder to WSDOT
Project Scoping
Package 2
Preliminary Design Submittal
Final Design Submittal
Released for Construction Submittal
Package n
Preliminary Design Submittal
Final Design Submittal
Released for Construction Submittal
Project
Completion
Construction
Notes:
• The Design Documentation Package (DDP) is started by WSDOT during scoping/pre-RFP design. The design-builder completes the DDP as the
project proceeds.
• The design-builder shall refer to the RFP for specific review and approval processes. The RFP will specify procedures for design submittals,
including notifications to WSDOT and the time allowed for reviews.
• WSDOT will review design submittals for conformance with requirements of the contract.
210.01 General
The Washington State Department of Transportation (WSDOT) strives to keep
the public informed about transportation issues, involve the public in transportation
decision making, and make transportation decisions based on the public’s
best interests.
One of the best ways to achieve WSDOT’s goals is to collaborate with the public,
community groups, and various agencies. These participants often have differing,
and sometimes conflicting, perspectives and interests. In addition, many participants
and organizations are not able to spend the time and effort required to fully engage
in transportation decision making. Despite these challenges, active collaboration:
• Gives WSDOT access to important information and new ideas.
• Puts us in a position to help solve problems and resolve conflicts.
• Creates a sense of community.
• Fosters greater acceptance of projects.
• Helps us build and sustain a credible and trusting relationship with the public.
• Ultimately leads to transportation improvements that better meet the public’s
needs and desires.
When collaborating with the public about transportation projects or issues, WSDOT
uses more formal techniques like public hearings, direct mail, and presentations to
city councils and legislators; as well as less formal but equally important techniques,
like telephone and e-mail discussions, meetings with community groups, media
relations, and project Internet pages.
Law requires that many types of capital transportation projects go through a formal
public hearing process; thus, the legal procedures necessary for public hearings is
the primary focus of this chapter. Public involvement plans are briefly discussed, and
referrals to WSDOT’s communications resources are included to further guide their
development and implementation.
210.02 References
(1) Federal/State Laws and Codes
United States Code (USC) Title 23, Highways, Sec. 128, Public hearings
USC Title 23, Highways, Sec. 771.111, Early coordination, public involvement,
and project development
23 Code of Federal Regulations (CFR) 200.7, FHWA Title VI Policy
23 CFR 200.9(b)(4), Develop procedures for the collection of statistical data of
participants and beneficiaries of state highway programs
23 CFR 200.9(b)(12), Develop Title VI information for dissemination to the general
public
23 CFR 450.212, Public involvement
28 CFR Part 35, Nondiscrimination on the basis of disability in state and local
government services
49 CFR Part 27, Nondiscrimination on the basis of disability in programs or activities
receiving federal financial assistance
Americans with Disabilities Act of 1990 (ADA) (28 CFR Part 36, Appendix A)
Civil Rights Restoration Act of 1987
Executive Order 12898, Federal Actions to Address Environmental Justice in
Minority Populations and Low-Income Populations
Executive Order 13166, Improving Access to Services for Persons with Limited
English Proficiency
Revised Code of Washington (RCW) 47.50, Highway Access Management
RCW 47.52, Limited Access Facilities
Section 504 of the Rehabilitation Act of 1973, as amended
Title VI of the Civil Rights Act of 1964
210.03 Definitions
affidavit of publication A notarized written declaration stating that a notice of
hearing (or notice of opportunity for a hearing) was published in the legally
prescribed manner.
affidavit of service by mailing A notarized written declaration stating that the
limited access hearing packet was mailed at least 15 days prior to the hearing and
entered into the record at the hearing.
auxiliary aids and services (1) Qualified interpreters, notetakers, transcription
services, written materials, telephone handset amplifiers, assistive listening devices,
assistive listening systems, telephones compatible with hearing aids, open and
closed captioning, telecommunications devices for deaf persons (TDDs), videotext
displays, or other effective methods for making aurally delivered materials available
to individuals with hearing limitations; (2) Qualified readers, taped texts, audio
recordings, Brailled materials, large print materials, or other effective methods for
making visually delivered materials available to individuals with visual impairments;
(3) Acquisition or modification of equipment or devices; (4) Other similar services
and actions; and (5) Providing and disseminating information, written materials,
and notices in languages other than English, where appropriate.
context sensitive solutions (CSS) A collaborative, interdisciplinary approach that
involves all stakeholders to develop a transportation facility that fits its physical *From “Understanding
Flexibility in
setting and preserves scenic, aesthetic, historic, and environmental resources while Transportation Design –
maintaining safety and mobility. CSS is an approach that considers the total context Washington,” WSDOT,
April 2005
within which a transportation improvement project will exist.* (See 210.02 and
210.04(2) for more information.)
court reporter A person with a license to write and issue official accounts of
judicial or legislative proceedings.
findings and order A document containing the findings and conclusions of a limited
access hearing approved by the Assistant Secretary, Engineering & Regional
Operations (see 210.09(12) and (13)).
hearing An assembly to which the public is invited and at which participation is
encouraged. Types of hearings include:
• administrative appeal hearing A formal process whereby a property owner
may appeal WSDOT’s implementation of access management legislation. The
appeal is heard by an administrative law judge (ALJ), who renders a decision.
(See Chapter 540 for administrative appeal hearing procedures.)
• combined hearing A hearing held when there are public benefits to be gained
by combining environmental, corridor, design, and/or limited access subjects.
• corridor hearing A formal or informal hearing that presents the corridor
alternatives to the public for review and comment before a commitment is
made to any one route or location. This type of hearing is beneficial for existing
corridors with multiple Improvement projects programmed over a long duration.
• design hearing A formal or informal hearing that presents the design
alternatives to the public for review and comment before the selection of a
preferred alternative.
• environmental hearing A formal or informal hearing documenting that social,
economic, and environmental impacts have been considered and that public
opinion has been solicited.
• limited access hearing A formal hearing that gives local public officials,
owners of abutting properties, and other interested persons an opportunity to be
heard about the limitation of access to the highway system.
• formal hearing format A hearing conducted by a moderator using a formal
agenda, overseen by a hearing examiner, and recorded by a court reporter, as
required by law. Limited access hearings require the use of the formal hearing
format (see 210.05(3)).
• informal hearing format A hearing where oral comments are recorded by
a court reporter, as required by law. An informal hearing often uses the “open
house” format (see 210.04(1)(a)). A formal agenda and participation by a hearing
examiner are optional.
hearing agenda An outline of the actual public hearing elements, used with formal
hearings. (See 210.05(9)(a) for contents.)
Hearing Coordinator The HQ Access and Hearings Section Manager,
(360) 705-7266.
hearing examiner An administrative law judge from the Office of Administrative
Hearings, or a WSDOT designee, appointed to moderate a hearing.
hearing script A written document of text to be presented orally by department
representatives at a hearing.
hearing summary Documentation prepared by the region and approved by
Headquarters that summarizes environmental, corridor, and design hearings.
(See 210.05(10) for content requirements.)
hearing transcript A document prepared by the court reporter that transcribes
verbatim all oral statements made during the hearing, including public comments.
This document becomes part of the official hearing record.
NEPA National Environmental Policy Act.
notice of appearance A form provided by WSDOT for anyone wanting
to receive a copy of the findings and order and the adopted limited access plan
(see 210.09(3) and (8)).
notice of hearing (or hearing notice) A published advertisement that a public
hearing will be held.
notice of opportunity for a hearing An advertised offer to hold a public hearing.
order of hearing The official establishment of a hearing date by the Director &
State Design Engineer, Development Division.
prehearing packet A concise, organized collection of all necessary prehearing data,
prepared by the region and approved by the HQ Access and Hearings Section
Manager prior to the hearing (see 210.05(4) and Exhibit 210-3).
project management plan A formal, approved document that defines how the project
is executed, monitored, and controlled. It may be in summary or detailed form and
may be composed of one or more subsidiary management plans and other planning
documents. For further information, see the Project Management Online Guide:
http://www.wsdot.wa.gov/projects/projectmgmt/pmog.htm
public involvement plan A plan to collaboratively involve the public in decision
making, tailored to the specific needs and conditions of a project and the people and
communities it serves. It is often part of a broader communications plan.
relocation assistance program A program that establishes uniform procedures for
relocation assistance that will ensure legal entitlements and provide fair, equitable,
and consistent treatment to persons displaced by WSDOT-administered projects,
as defined in the Right of Way Manual.
résumé An official notification of action taken by WSDOT following adoption
of a findings and order (see 210.09(14)).
SEPA State Environmental Policy Act.
study plan A term associated with environmental procedures, this plan proposes
an outline or “road map” of the environmental process to be followed during the
development of a project that requires complex NEPA documentation. (See 210.06
and the Environmental Manual.)
Individuals from minority and ethnic groups and low-income households, who are
traditionally underserved by transportation, often find participation difficult. While
these groups form a growing portion of the population, particularly in urban areas,
historically they have experienced barriers to participation in the public decision-
making process and are therefore underrepresented. These barriers arise from both
the historical nature of the public involvement process and from cultural, linguistic,
and economic differences. For example, a community made up of largely senior
citizens (with limited mobility/automobile usage) may mean:
• Meetings/open houses are planned in locations easily accessible to them, such
as senior centers and neighborhood community centers.
• Meetings are scheduled in the mornings or midday to accommodate individuals
who prefer not to leave home after dark.
• Meetings are scheduled in the evenings to accommodate persons who work
during the day.
A project’s affected area might consist of a population with limitations in speaking
or understanding English. This may entail:
• Developing/disseminating materials in other languages, as appropriate.
• Having a certified translator on hand at the meetings.
Extra effort may be needed to elicit involvement from people unaccustomed to
participating in the public involvement process. They often have different needs
and perspectives than those who traditionally participate in transportation decision
making, and they may have important, unspoken issues that should be heard. They
not only may have greater difficulty getting to jobs, schools, recreation, and shopping
than the population at large, but also they are often unaware of transportation
proposals that could dramatically change their lives.
NEPA and SEPA environmental policies and procedures are intended to provide
relevant environmental information to public officials, agencies, and citizens, and
allow public input to be considered before decisions are made. There are also various
other laws, regulations, and policies that emphasize public involvement, including
23 CFR, Title VI of the Civil Rights Act, the Americans with Disabilities Act, and
Executive Orders 12898 and 13166.
WSDOT’s collaborative process with the public should be open, honest, strategic,
consistent, inclusive, and continual. Initiating a project in an atmosphere of
collaboration and partnership can go a long way toward providing equal opportunities
for all parties (local, state, tribal, private, nonprofit, or federal) to participate in a
project vision. This collaboration requires an intensive communications effort that
is initiated during project visioning and extends through construction and eventual
operation of the facility.
Department specialists in public communications, environmental procedures,
traffic engineering, real estate services, and limited access control are routinely
involved with public outreach efforts and project hearings. Depending on the scale
and complexity of a project, the region is encouraged to engage the participation
of interdisciplinary experts when developing a public involvement plan and
communicating project details.
The plan will outline ways to identify and involve the communities affected by the
project; provide them with accessible information through reader-friendly documents,
graphics, plans, and summaries; and involve them in decision making.
An effective public involvement plan:
• Is tailored to the project.
• Encourages interactive communication.
• Demonstrates to residents that their input is valued and utilized.
• Includes all affected communities.
• Identifies and resolves issues early in the project development process.
• Ensures public access to relevant and comprehensible information.
• Informs the public of the purpose, need for, and benefits of the proposed action.
• Informs the public about the process that will be used to make decisions.
• Gains public support.
• Provides equal opportunity, regardless of disability, race, national origin, color,
gender, or income.
The region Communications and Environmental offices can provide expertise in
developing a public involvement plan tailored to a specific project. The HQ Access
and Hearings Section specializes in procedures for public hearings. Real Estate
Services personnel can provide expertise regarding acquisition, relocation assistance,
and other related programs. Enlisting the support of these groups is essential to the
success of WSDOT projects.
WSDOT recognizes local, state, federal, and tribal staff and elected officials as active
sponsors of proposed projects. Those officials might help develop and implement the
public involvement plan. Early and continued contact with these resources is key to
the success of a project.
Public hearing formats are either formal or informal. Limited access hearings are
always conducted as formal hearings. An informal process can be used for most other
hearings.
Hearings are often conducted in accordance with NEPA/SEPA procedures for
public involvement during the environmental documentation phase of the project.
The region reviews the requirements for hearings during the early stages of project
development and before completion of the draft environmental documents.
the period between the first advertisement and the approval of the hearing
summary or findings and order. The information may also need to be available
in languages other than English if indicated by demographics. The information
need not be in final form, but it must include every item currently included in the
hearing presentation. The environmental documents must also be available for
public review.
These materials are made available in the general locality of the project. The
region reviews the variables (the locations of the Project Office and project site;
the interested individuals; and the probability of requests for review) and selects
a mutually convenient site for the presentation of the information. In accordance
with RCW 42.56, a record should be kept for future evidence, stating who came
in, when, and what data they reviewed and copied.
(b) Hearing Briefing
On controversial projects, the HQ Hearing Coordinator arranges for a briefing
(held before the hearing) for those interested in the project. Attendants typically
include appropriate Headquarters, region, and FHWA personnel, with special
notice to the Secretary of Transportation. Region personnel present the briefing.
(c) Prehearing Presentation
The region is encouraged to give an informal presentation to the public for
discussion of the project prior to the hearing. A prehearing presentation is
informal, with ample opportunity for exchange of information between WSDOT
and the public. Providing community members with opportunities to talk about
their concerns in advance of the hearing promotes positive public relationships,
and can make the actual hearing proceed more smoothly. Prehearing
presentations can be open house meetings, drop-in centers, workshops, or other
formats identified in the public involvement plan.
The prehearing presentation is usually held about one week before the hearing for
more controversial projects, modified as needed.
Include the date, time, and place in the hearing notice and ensure it is mailed in
time to give adequate notice of the prehearing presentation.
The region also sends the limited access hearing packet to:
• The county and/or city.
• The owners of property listed on the county tax rolls as abutting the section
of highway, road, or street being considered at the hearing as a limited access
facility.
• Local agencies and public officials who have requested a notice of hearing or
who, by the nature of their functions, objectives, or responsibilities, are interested
in or affected by the proposal.
• Every agency, organization, official, or individual on the interest list.
The limited access hearing packet is also sent, when applicable, to:
• State resource, recreation, and planning agencies.
• Tribal governments.
• Appropriate representatives of the Department of the Interior and the Department
of Housing and Urban Development.
• Other federal agencies.
• Public advisory groups.
(14) Résumé
The résumé is an official notification of action taken by WSDOT following adoption
of a findings and order. The HQ Access and Hearings Section provides the résumé to
the region. The region must publish the résumé once each week for two consecutive
weeks, not to begin until at least ten days after the mailing of the findings and order.
210.13 Documentation
For the list of documents required to be preserved in the Design Documentation
Package and the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev/
Types of Hearings[1]
Limited Access
Environmental
Proposed Project Actions or Conditions
Combined
Follow-Up
Corridor
Design
Proposed route on new location X X
Major actions not taken within 3 years after date last hearing was held X[2]
An unusually long time has elapsed since the last hearing or the
X
opportunity for a hearing
Notes:
[1] This table presents a list of project actions that correspond to required public hearings. The list is intended
as a guide and is not all-inclusive. In cases where several types of hearings are anticipated for a project,
a combined hearing may be an effective method. Consult with region and Headquarters environmental
staff, the designated Assistant State Design Engineer, and the HQ Access and Hearings Section to identify
specific hearing requirements and strategies.
[2] Posthearing major actions include: FHWA approvals (for Interstate projects); adoption of hearing summaries
and findings and order; and public notification of action taken, such as publishing a résumé.
Hearing Format
Hearing Type
Formal Informal
Notes:
Check with the HQ Hearing Coordinator to identify specific hearing type and
appropriate hearing format.
* If a combined or follow-up hearing includes a limited access hearing, then
that portion of the hearing must adhere to the formal format.
Vicinity map X
News release X
List of newspapers and other media sources that will cover the news
X
release and hearing notice
Notes:
The prehearing packet is prepared by the region and transmitted to the HQ Access and Hearings Section for
review, concurrence, and processing. This information is assembled in advance of the hearing to facilitate timely
announcements and a smooth-flowing event. The HQ Hearing Coordinator requires the prehearing packet 45 days
(or sooner) in advance of the proposed hearing date.
[1] Limited access hearings are required by law to be formal.
[2] For a limited access hearing, each abutting property owner affected by the project must receive the hearing
notice, along with the notice of appearance form and specific limited access hearing plan(s) showing their
parcel(s). Indicate in the prehearing packet the number of affected property owners to whom the packets will
be mailed.
[3] A hearing agenda and hearing script are required for a limited access hearing. Any formal hearing requires a
fixed agenda and a script. It is recognized that the script may be in draft format at the time of submittal of the
prehearing packet. The HQ Hearing Coordinator can assist in its completion and can provide sample scripts
and agendas.
Limited access hearing findings and order Assistant Secretary, Engineering & Regional Operations
Design hearing summary Director & State Design Engineer, Development Division
225.01 General
The term “environmental documentation” refers to the documents produced for a project to
satisfy the requirements contained in the National Environmental Policy Act (NEPA) and the
State Environmental Policy Act (SEPA). The Environmental Manual and supporting web pages
provide detailed instructions on how to determine what level of documentation is required and
how to prepare the documents. This chapter provides a summary of the relevant provisions in
the Environmental Manual.
The purpose of the environmental document is to provide decision makers, agencies, and the
public with information on a project’s environmental impacts, alternatives to the proposed
action, and mitigation measures to reduce unavoidable impacts. Final environmental documents
identify and evaluate the project to be constructed. Because projects vary in their level of
environmental impacts, the rules on environmental documentation allow for different levels of
documentation. As a project’s impacts increase, so does the level of documentation.
The region Environmental Office and the NEPA/SEPA Compliance Section of the Headquarters
Environmental Services Office routinely provide environmental documentation assistance to
designers and project engineers.
The ERS is part of the Project Summary database. The ERS describes the potential environ-
mental impacts, proposed mitigation, and necessary permits for a project. It establishes the
initial environmental classification and identifies the key environmental elements addressed in
the NEPA/SEPA process. The ERS database includes fully integrated “Help” screens. Contact your
region Environmental Office or Program Management Office to get set up to work in the
database.
The typical process for classifying projects and determining the level of environmental
documentation is as follows:
Once the project has been sufficiently developed to assess any environmental impacts,
the region completes the ERS based on the best information available at the scoping
phase of development.
The region Environmental Manager then concurs with the classification by approving
the ERS, which enables the completed form to be included in the Project Summary
package.
For NEPA, if a project has been determined to be a Categorical Exclusion (CE), the
Environmental Classification Summary/SEPA Checklist (ECS/SEPA Checklist) is
completed. The NEPA environmental review process is considered complete when the
region Environmental Manager approves the ECS package (guidance is provided in the
online Help in the ECS/SEPA Checklist database). If it is determined that a Categorical
Exclusion (CE), an Environmental Assessment (EA), or Environmental Impact Statement
(EIS) is required, the region evaluates the project schedule and arranges for
preparation of the appropriate document.
For SEPA, the signing and submittal of the ECS/SEPA Checklist completes the
environmental classification process. On projects that are categorized as exempt from
SEPA, the environmental process is complete unless the project requires consultation
under the Endangered Species Act. On projects that do not meet the criteria for a SEPA
Categorical Exemption (WACs 197-11-800 and 468-12) and require a SEPA checklist
(WAC 197-11-960) or an EIS, those documents are prepared as necessary prior to
Project Development Approval.
At this early stage, the ERS allows environmental staff to consider potential impacts and
mitigations and required permits. For many projects, the WSDOT Geographic Information
System (GIS) Workbench coupled with a site visit provides sufficient information to fill out the
ERS (see the GIS Workbench online Help).
For most WSDOT projects, the Federal Highway Administration (FHWA) is the lead agency for
NEPA. Other federal lead agencies on WSDOT projects are the U.S. Army Corps of Engineers,
Federal Aviation Administration, Federal Railroad Administration, and Federal Transit
Administration.
The region Environmental Office is responsible for creating and maintaining the commitment file
as a project progresses through its development process. Whenever commitments are made,
they are incorporated into project documents and added to the environmental commitment file
once they are finalized. Commitments are typically included within, but not limited to, the
following documents or approvals and any of their supplements or amendments:
Memoranda, Agreements, Letters, Electronic Communications
No-Effect Letters
Biological Assessments
Biological Opinions
Concurrence Letters
SEPA Checklists
NEPA Categorical Exclusions
NEPA Environmental Assessments
NEPA/SEPA Environmental Impact Statements
Finding of No Significant Impact (FONSI)
Record of Decision (ROD)
Section 106 Concurrence Letter from Tribes and Department of Archaeology & Historic
Preservation
Mitigation Plans
Environmental Permits and Applications, and Associated Drawings and Plans
Additional information (see Procedure 490-a) for establishing a commitment file is available
online at WSDOT’s Tracking Commitments webpage. WSDOT has a Commitment Tracking
System to organize and track commitments from the commitment file. Refer to the
Environmental Manual (Chapter 490) for policies associated with tracking commitments.
The Environmental Review Summary, which is prepared as part of the Project Summary,
identifies some of the most common environmental permits that might be required based on
the information known at that stage. As the project design develops, additional permits and
approvals can be identified. Conducting project site visits for engineering and environmental
features may reduce project delays caused by late discoveries. Coordinate with and
communicate any project changes to region environmental staff.
The permit process begins well in advance of the actual permit application. For some permits,
WSDOT has already negotiated permit conditions through the use of programmatic and general
permits. These permits typically apply to repetitive, relatively simple projects, and the permit
conditions apply regardless of the actual facts of the project type. For complex projects, the
negotiations with permit agencies often begin during the environmental documentation phase
for compliance with the National Environmental Policy Act (NEPA) and the State Environmental
Policy Act (SEPA). The mitigation measures developed for the NEPA/SEPA documents are
captured as permit conditions on the subsequent permits.
Environmental permits require information prepared during the design phase to demonstrate
compliance with environmental rules, regulations, and policies. To avoid delays in project
delivery, it is necessary for the designer to understand and anticipate this exchange of
information. The timing of this exchange often affects design schedules, while the permit
requirements can affect the design itself. In complex cases, the negotiations over permit
conditions can result in iterative designs as issues are raised and resolved.
The Project Engineer is encouraged to meet with and discuss expectations with support groups
so that preliminary field investigations are conducted in compliance with environmental
permits, agreements, laws, or regulations. At a minimum, the support groups should know how
to access the environmental commitments for the project and determine which ones apply to
their work. If a non-compliance event occurs, coordinate with support groups so that they know
to initiate the Environmental Compliance Assurance Procedure (see 225.06(1) for details).
2. The Environmental Manager or designee will help generate or make accessible the
appropriate environmental documentation and permits.
3. Support Group / Field Crew is responsible for permit compliance, including the following:
Confirming they have all the permits, and understanding of the permit conditions prior
to beginning work
Evaluating field operations, including access to specific locations, and developing work
plans so that permit conditions are met (Temporary Erosion and Sediment Control
(TESC), etc.)
Recognizing and identifying non-compliance issues.
Notifying the PE and Environmental Manager when non-compliance issues/events happen.
When non-compliance is suspected or known, it is the Project Engineer’s (PE) responsibility to
initiate the Notification and Resolution Process below. The Regional Environmental Manager will
serve as a resource to the PE and give priority to addressing the non-compliance event. The PE
and Environmental Manager shall work together on an appropriate response to avoid or
minimize environmental damage.
5. The Director of the ESO shall notify the ESO Compliance Solutions Branch Manager.
225.05(1)(b) Documentation
1. The PE and the Environmental Manager shall coordinate and prepare the appropriate
responses to all regulatory agencies with jurisdiction. The responses shall include
documentation about the non-compliance event and how it was recognized and rectified.
2. The Environmental Manager, with assistance from the PE, shall record the details of the
non-compliance event in the WSDOT Commitment Tracking System (per RCW 47.85.040),
including but not limited to:
Project Name and location, plus the name of the PE.
Date of event.
Location(s) on the project where the non-compliance event occurred.
The type of work and the underlying root cause that resulted in the non-compliance
event.
The environmental, permit, agreement, law, or regulation violated.
Description of how the non-compliance event was recognized, rectified, and the
lessons learned.
Which regulatory agencies and staff were notified, including dates of notification and
any tracking numbers provided.
Whether or not regulatory agency staff conducted a site review in response to the
notification.
The ESO shall produce a yearly report of all written notifications or violations to the Washington
State Legislature (per RCW 47.85.040).
225.06 Documentation
Refer to Chapter 300 for design documentation requirements.
225.07 References
23 Code of Federal Regulations (CFR) Part 771, Environmental Impact and Related Procedures
23 CFR Part 774; 49 USC Section 303, Policy on Lands, Parks, Recreation Areas, Wildlife and
Waterfowl Refuges, and Historic Sites
40 CFR Parts 1500-1508, Council for Environmental Quality Regulations for Implementing NEPA
Chapter 43.21C Revised Code of Washington (RCW), State Environmental Policy Act (SEPA)
Chapter 47.85 Revised Code of Washington (RCW), Transportation Project Delivery and Review
300.01 General
This chapter provides the WSDOT design procedures, documentation and approvals necessary
to deliver successful projects on the transportation network in Washington, including projects
involving the Federal Highways Administration.
For local agency and developer projects on state highways, design documentation is also
needed. It is retained by the region office responsible for the project oversight, in accordance
with the WSDOT records retention policy. All participants in the design process are to provide
the appropriate documentation for their decisions. See 300‐04(3) for information about the
approval process and authority. For more information about these types of projects, see the
Local Agency Guidelines and Development Services Manual available at the Publications Services
Index website:
www.wsdot.wa.gov/Publications/Manuals/index.htm
For operational changes identified by the Traffic Office Low Cost Enhancement or Field
Assessment Program that are included in a project, design documentation is also needed. It is
retained by the region office responsible for the project oversight, in accordance with the
WSDOT records retention policy. This documentation will be developed by the region Traffic
Office in accordance with HQ Traffic Office direction and included in the design documentation
for the project.
For emergency projects, also refer to the Emergency Funding Manual. It provides the legal and
procedural guidelines for WSDOT employees to prepare all necessary documentation to respond
to, and recover from, emergencies and disasters that affect the operations of the department.
Preservation projects with an overall project cost of $10 million and over—and all other projects
with an overall project cost of $2 million and over—are required to go through the Project
Delivery Method Selection process. The overall project cost is the total of the Preliminary
Engineering, Right of Way, and Construction Costs.
For all projects, the delivery method is determined using WSDOT Project Delivery Method
Selection Guidance (PDMSG), with the following exceptions:
Projects under $2 million are programmatically exempt from PDMSG, do not require a
Project Delivery Method Selection Checklist, and will be Design Bid Build.
Preservation Paving projects under $10 million are programmatically exempt from PDMSG,
do not require a Project Delivery Method Selection Checklist, and will be Design Bid Build.
Design Build’s most likely application would be for improvement projects in the mobility,
economic initiatives, or environmental subprograms where there are opportunities for
innovation, greater efficiencies, or significant savings in project delivery time.
The delivery method is determined using the WSDOT Project Delivery Method Selection
Guidance Memorandum found here:
www.wsdot.wa.gov/Projects/delivery/designbuild/PDMSG.htm
The region develops and maintains documentation for each project using this chapter and the
Project File / Design Documentation Package checklists (see 300.03(3))
Refer to the Plans Preparation Manual for PS&E documentation. Exhibit 300-4 is an example
checklist of recommended items to be turned over to the construction office at the time of
project transition. An expanded version is available here:
www.wsdot.wa.gov/design/projectdev/
Upon receipt of the ERS approval for projects requiring an EA or EIS under NEPA, the region
proceeds with environmental documentation, including public involvement, appropriate for the
magnitude and type of the project (see Chapter 210 and WSDOT Community Engagement Plan).
300.03(1) Purpose
Design documentation records the evaluations and decisions by the various disciplines that
result in design recommendations. Design assumptions and decisions made prior to and during
the scoping phase are included. Changes that occur throughout project development are
documented. Required justifications and approvals are also included.
The Project File (PF) contains the documentation for planning, scoping, programming, design,
approvals, contract assembly, utility relocation, needed right of way, advertisement, award,
construction, and maintenance review comments for a project. A Project File is completed for all
projects and is retained by the region office responsible for the project. Responsibility for the
project may pass from one office to another during the life of a project, and the Project File
follows the project as it moves from office to office. With the exception of the DDP, the Project
File may be purged when retention of the construction records is no longer necessary.
See the Project File checklist for documents to be preserved in the Project File:
www.wsdot.wa.gov/Design/Support.htm
The Design Documentation Package (DDP) is a part of the Project File and preserves the
decision documents generated during the design process. In each package, a summary (list) of
the documents included is recommended. The DDP documents and explains design decisions,
design criteria, and the design process that was followed. The DDP is retained in a permanent
retrievable file for a period of 75 years, in accordance with WSDOT records retention policy.
The Basis of Design, Design Parameters, Alternatives Comparison Table, and Design Analyses are
tools developed to document WSDOT practical design and decisions. Retain these in the DDP.
Refer to the remainder of this chapter and DDP checklist for documents to be preserved in the
DDP. See Design Documentation Package Checklist here:
www.wsdot.wa.gov/Design/Support.htm
Design Approval is entered into the Design Documentation Package and remains valid for three
years or as approved by the HQ Design Office.
If the project is over this three-year period and has not advanced to Project
Development Approval, evaluate policy changes or revised design criteria that are
adopted by the department during this time to determine whether these changes
would have a significant impact on the scope or schedule of the project.
If it is determined that these changes will not be incorporated into the project,
document this decision with a memo from the region Project Development Engineer
that is included in the DDP.
For an overview of design policy changes, consult the Detailed Chronology of Design
Manual revisions: www.wsdot.wa.gov/design/policy/default.htm
For an overview of design policy changes, consult the Detailed Chronology of Design
Manual revisions: www.wsdot.wa.gov/design/policy/default.htm
For design-build projects, the design-builder shall refer to the project Request for Proposal (RFP)
for specification on final and intermediate deliverables and final records for the project. Project
Development Approval is required prior to project completion.
It is a prudent practice to start the compilation of design documentation early in a project and to
acquire Project Development Approval before the completion of the project. At the start of a
project, it is critical that WSDOT project administration staff recognize the importance of all
required documentation and how it will be used in the design-build project delivery process.
In cases where design decisions are imposed on the local agency or developer by WSDOT or
FHWA, in order to secure their approval, those specific decisions are to be documented by
WSDOT. Note that the requirement to submit a Basis of Design for approval may be waived by
the approving authority designated in Exhibit 300-5, based on the criterion in 1100.10(1)(a).
When a Region is the approval authority for the BOD and is considering an exemption, the
Region approving authority can assume the role of the Assistant State Design Engineer to
determine if an exemption is appropriate. For more information about the Basis of Design, see
Chapters 1100 through 1106.
For all projects, on the National Highway System (NHS), the level of FHWA oversight and
approvals can vary for numerous reasons such as type of project, the agency doing the work,
PoDI/non-PoDI designation, and funding sources. Oversight and funding do not affect the level
of design documentation required for a project.
Documents for projects requiring FHWA review, Design Approval, and Project Development
Approval are submitted through the HQ Design Office.
The Stewardship & Oversight Agreement generally defines Projects of Division Interest as:
Major Projects (A federal aid project with total cost >$500M)
TIGER Discretionary Grant Projects
NHS Projects that may require FHWA Project or Program Approvals
Projects Selected by FHWA based on Risk or Opportunity
The S&O Agreement also states: Regardless of retained project approval actions, any Federal-
aid Highway Project either on or off the NHS that the Division identifies as having an elevated
level of risk can be selected for risk-based stewardship and oversight and would then be
identified as a PoDI.
For each project designated as a PoDI, FHWA and WSDOT prepare a Project-Specific PoDI
Stewardship & Oversight Agreement which identifies project approvals and related
responsibilities specific to the project.
The Exhibit 300-1 approval table refers to New/Reconstruction projects on the Interstate.
New/Reconstruction projects include the following types of work:
Capacity changes: add a through lane, convert a general-purpose (GP) lane to a special-
purpose lane (such as an HOV or HOT lane), or convert a high-occupancy vehicle (HOV)
lane to GP.
Other lane changes: add or eliminate a collector-distributor or auxiliary lane. (A rural
truck climbing lane that, for its entire length, meets the warrants in Chapter 1270 is not
considered new/reconstruction.)
New interchange.
Changes in interchange type such as diamond to directional or adding a ramp.
New or replacement bridge (on or over, main line, or interchange ramp).
New Safety Rest Areas Interstate.
Documents for projects requiring FHWA review, Design Approval, and Project Development
Approval are submitted through the HQ Design Office.
See the Project File and Design Documentation Package checklists described in 300.03(3) for
complete list of documents.
For approval levels see Exhibits 300-1 through 300-3 or a project-specific S&O Agreement for
PoDI projects.
The PD identifies the various disciplines and design elements that are anticipated to be
encountered in project development. It also states the purpose and need for the project, the
program categories, and the recommendations for project phasing. The PD is initiated early in
the scoping phase to provide a basis for full development of the ERS, schedule, estimate, Basis
of Estimate, and Basis of Design (where indicated in scoping instructions). If circumstances
necessitate a change to an approved PD, the project manager and the regional program
manager will document the change according to the CPDM Change Management process. For
more information, see the Program Management Manual, Chapter 9 Managing Change.
The ERS lists the potentially required environmental permits and approvals, environmental
classifications, and environmental considerations. The ERS is prepared during the scoping phase
and is approved by the region. If there is a change in the PD, the information in the ERS must be
reviewed and revised to match the rest of the Project Summary. For actions classified as a CE
under NEPA, the approved ERS becomes the ECS when the project is funded and moves to
design. The region may revise the ECS as appropriate (usually during final design) as the project
advances. The ECS serves as the NEPA environmental documentation for CE projects. The region
Environmental Manager approves the ECS and may send it to FHWA for their approval. The
ERS/ECS database includes fully integrated help screens that provide detailed guidance. Contact
your region Environmental Office for access.
A Design Analysis is required where a dimension chosen for a design element that will be
changed by the project is outside the range of values provided for that element in the Design
Manual. A Design Analysis is also required where the need for one is specifically referenced in
the Design Manual.
A region approved Design Analysis is required if a dimension or design element meets current
AASHTO guidance adopted by the Federal Highway Administration (FHWA), such as A Policy on
Geometric Design of Highways and Streets, but is outside the corresponding Design Manual
criteria. See Exhibit 300-1 for Design Analysis approval authorities.
In the case of a shoulder width reduction at an existing bridge pier or abutment, sign structure
or luminaire base in a run of median barrier, the Design Parameter Sheet may be used instead of
a Design Analysis to document the dimensioning decision for the shoulder at that location.
A template is available to guide the development of the Design Analysis document here:
www.wsdot.wa.gov/design/support.htm.
Email a PDF copy of all Region approved Design Analyses to the ASDE supporting your region.
The design and PS&E process review is performed at least once each year by the HQ Design
Office. The documents used in the review process are the Design Documentation Package
Checklist(s), Basis of Design, Basis of Estimate, the PS&E Review Checklist, and the PS&E Review
Summary. These are generic forms used for all project reviews. Copies of these working
documents are available for reference when assembling project documentation. The HQ Design
Office maintains current copies at: www.wsdot.wa.gov/design/support.htm.
Each project selected for review is examined completely and systematically beginning with the
scoping phase (including planning documents) and continuing through contract plans and, when
available, construction records and change orders. Projects are normally selected after contract
award. For projects having major traffic design elements, the HQ Traffic Operations Office is
involved in the review. The WSDOT process reviews may be held in conjunction with FHWA
process reviews.
The HQ Design Office schedules the process review and coordinates it with the region and
FHWA.
300.08 References
Revised Code of Washington (RCW) 47.28.030, Contracts – State forces – Monetary limits –
Small businesses, minority, and women contractors – Rules
www.wsdot.wa.gov/publications/manuals/index.htm
Advertisement and Award Manual, M 27-02, WSDOT
Cost Estimating Manual for WSDOT Projects, M 3034, WSDOT
Design Manual, M 22-01, WSDOT
Emergency Relief Procedures Manual, M 3014, WSDOT
Environmental Manual, M 31-11, WSDOT
Hydraulics Manual, M 23-03, WSDOT
Highway Runoff Manual, M 31-16, WSDOT
Plans Preparation Manual, M 22-31, WSDOT
Roadside Manual, M 25-30, WSDOT
Roadside Policy Manual, M 3110, WSDOT
Temporary Erosion and Sediment Control Manual, M 3109, WSDOT
Mitigation Strategies for Design Exceptions, FHWA, July 2007. This publication provides detailed
information on design exceptions and mitigating the potential adverse impacts to highway
safety and traffic operations.
Highway Capacity Manual (HCM), latest edition, Transportation Research Board, National
Research Council
Design
Basis of Design Design Analysis Approval and
Project Type (BOD) Approval Project
Approval [1] [2] [11] Development
Approval
Project of Division Interest (PoDI) [10] [10] [10]
Interstate
Notes:
[1] These approval levels also apply to Design Analysis processing for local agency and
developer work on a state highway.
[2] See 300.06(4).
[3] For definition of New/Reconstruction, see 300.05(2).
[4] FHWA will provide Design Approval prior to NEPA Approval, but will not provide Project
Development Approval until NEPA is complete.
http://www.wsdot.wa.gov/publications/fulltext/design/ASDE/2015_Stewardship.pdf
[5] For guidance on the need for Design Analyses related to access management, see Chapters
530 and 540.
[6] Includes raised medians (see Chapter 1600).
[7] Curb ramps are still included (see Chapter 1510).
[8] For Bridge Replacement projects in the Preservation program, follow the approval level
specified for Improvement projects.
[9] Refer to RCW 47.24.020 for more specific information about jurisdiction and
responsibilities that can affect approvals.
[10] Projects of Division Interest (PoDI) must receive FHWA approvals per the PoDI Agreement
regardless of funding source or project type.
[11] A region approved Design Analysis is required if a dimension or design element meets
current AASHTO guidance adopted by the Federal Highway Administration (FHWA), such as
A Policy on Geometric Design of Highways and Streets, but is outside the range of
corresponding Design Manual criteria. Email a PDF copy of all Region approved Design
Analyses to the ASDE supporting your region.
[12] Reduction of through lane or shoulder widths (regardless of project type) requires FHWA
review and approval, except shoulder reductions for existing bridge pier or abutment, sign
structure or luminaire base in a run of median barrier as allowed by 300.06(4).
Table continued on the following page, which also contains the notes.
Approval Authority
Item
Region HQ FHWA
Bridge Design Plans (Bridge Layout) X X
Preliminary Bridge Plans for Unusual/Complex Bridges on the Interstate [7] X
Structures Requiring TS&Ls X
Hydraulic Report X [15] [15]
Preliminary Signalization Plans X [6][18]
Signalization Plans X [20]
Illumination Plans X [20]
Intelligent Transportation System (ITS) Plans X [20]
ITS Systems Engineering Analysis Worksheet (Exhibit 1050-2) X [20]
Rest Area Plans X
Roadside Restoration Plans X [16] X [17]
Planting Plans X [16] X [17]
Grading Plans X
Continuous Illumination – Main Line X [18]
Tunnel Illumination X [18]
High Mast Illumination X [18]
Work Zone Transportation Management Plan/Traffic Control Plan X [20]
Public Art Plan – Interstate (see Chapter 950) X [16] X [17][21] X
Public Art Plan – Non-Interstate (see Chapter 950) X [16] X [17][21]
Crash Analysis Report X [20] X
ADA Maximum Extent Feasible Document (see Chapter 1510) X X
Notes: [10] Approved by HQ Capital Program Development
[1] Federal-aid projects only. and Management (CPDM).
[2] Approved by Assistant Secretary, Engineering & [11] Certified by the responsible professional
Regional Operations. licensee.
[3] Approved by Director & State Design Engineer, [12] Submit to HQ Mats Lab for review and approval.
Development Division. [13] Approved by Regional Administrator or designee.
[4] Approved by Right of Way Plans Manager. [14] Per 23 CFR 635.111.
[5] Refer to Chapter 210 for approval requirements. [15] See the Hydraulics Manual for approvals levels.
[6] Final review & concurrence required at the region [16] Applies to regions with a Landscape Architect.
level prior to submittal to approving authority. [17] Applies to regions without a Landscape Architect.
[7] Final review & concurrence required at HQ prior to [18] Approved by State Traffic Engineer.
submittal to approving authority.
[19] Vacant.
[8] On Interstate projects, the Director & State Design
[20] Region Traffic Engineer or designee.
Engineer, Development Division, (or designee)
submits the approved design hearing summary to [21] The State Bridge and Structures Architect reviews
the FHWA for federal approval. (See Chapter 210.) and approves the public art plan (see Chapter
950 for further details on approvals).
[9] See Exhibit 300-1 for BOD Approvals.
[22] State Traffic Engineer or designee.
Exhibit 300-3 PS&E Process Approvals NHS (including Interstate) and Non-NHS
Notes:
FHWA PS&E Approval has been delegated to WSDOT unless otherwise stated differently in a Project
Specific PoDI S&O Agreement.
[1] This work requires a written agreement.
[2] Region approval subject to $250,000 limitation.
[3] Use of state forces is subject to $60,000 limitation and $100,000 in an emergency situation, as stipulated
in RCWs 47.28.030 and 47.28.035. Region justifies use of state force work and state-furnished materials
and determines if the work is maintenance or not. HQ CPDM reviews to ensure process has been
followed.
[4] Applies only to federal-aid projects; however, document for all projects.
[5] Prior FHWA funding approval required for federal-aid projects.
[6] The HQ Design Office is required to certify that the proprietary product is either: (a) necessary for
synchronization with existing facilities, or (b) a unique product for which there is no equally suitable
alternative.
[7] For any federal aid project FHWA only approves Right of Way Certification 3s (All R/W Not Acquired),
WSDOT approves Right of Way Certification 1s and 2s for all other federal aid projects.
References:
* Plans Preparation Manual
** Advertisement and Award Manual
*** Right of Way Manual
This checklist is recommended for use when coordinating project transition from design to construction.
1. Survey
End areas (cut & fill)
Staking data
Horizontal/Vertical control
Monumentation/Control information
2. Design Backup
Index for all backup material
Backup calculations for quantities
Geotech shrink/swell assumptions
Basis of Design, Design decisions and constraints
Approved Design Analyses
Hydraulics/Drainage information
Clarify work zone traffic control/workforce estimates
Geotechnical information (report)
Package of as-builts used (which were verified) and right of way files
Detailed assumptions for construction CPM schedule (working days)
Graphics and design visualization information (aerials)
Specific work item information for inspectors (details not covered in plans)
Traffic counts
Management of utility relocation
3. Concise Electronic Information With Indices
Detailed survey information (see Survey above)
Archived InRoads data
Only one set of electronic information
“Storybook” on electronic files (what’s what)
CADD files
4. Agreements, Commitments, and Issues
Agreements and commitments by WSDOT
RES commitments
Summary of environmental permit conditions/commitments
Other permit conditions/commitments
Internal contact list
Construction permits
Utility status/contact
Identification of the work elements included in the Turnback Agreement
(recommend highlighted plan sheets)
5. Construction Support
Assign a Design Technical Advisor (Design Lead) for construction support
Design
Design
Basis of Design Approval and
Analysis
Project Type (BOD) Project
Approval
Approval Development
Approval
Interstate
All projects FHWA FHWA FHWA
Highways (NHS) & (Non‐NHS)
Projects on limited access highways HQ Design HQ Design Region
Projects on managed access highways Region HQ Design Region
301.01 Introduction
Maintenance plays an important role in the Washington State Department of Transportation’s
(WSDOT’s) asset management program by meeting the daily requirements of maintaining and
operating over 18,000 lane miles, approximately 2,000 miles of ramps and special-use lanes, and
over 3,700 bridge and culvert structures, as well as hundreds of other special-use sites vital to
the state’s transportation system. Activities in the highway maintenance program protect the
public infrastructure as well as provide services necessary for daily operation of the highway
system. Typical maintenance activities include patching potholes, cleaning ditches, painting
stripes on the roadway, repairing damage to guardrail, and controlling noxious weeds. In
addition to maintaining assets, operational services are also provided. They include plowing
snow, cleaning rest areas, responding to incidents, operating structures like draw bridges, and
operating traffic signals, lighting, and Intelligent Transportation Systems (ITS). This limited list
of maintenance and operational activities highlights the significant undertaking of maintaining
and operating the State Highway System as designed.
Highway maintenance and operations staff are unique stakeholders, because they utilize,
maintain, and operate the facilities’ engineering designs and constructs. Given the nature and
cost of maintenance work, as well as the exposure inherent in maintenance and operational
activities, it is important for designers to consider maintenance and operations staff as major
stakeholders in every project. It is also important for maintenance and operations staff to
understand the purpose of the project and to participate in determining the best method(s) to
keep it functioning as designed while maintaining their responsibilities outside of the specific
project limits.
This chapter provides multiple options to help improve coordination with maintenance and
operations staff during project design. These “best practices” are a culmination of responses
from Design Manual user surveys, interviews with maintenance and operations superintendents,
and various regional practices that have demonstrated potential improvement related to the
coordination of design and maintenance efforts and personnel. Note: The concepts and methods
presented herein do not replace any approved communication or documentation processes that
may be currently required by a WSDOT region during the project development process.
301.02 Communication
Communication is the most fundamental component of coordination. Executing communication
is often oversimplified by the phrase “communicate early and often.” In reality, effective
communication is significantly more complex. For example: Who are you communicating with,
what methods of communication are being used, what is being communicated, how are you
responding to communication, where is the communication taking place, and when does the
communication need to occur to maximize effectiveness?
The following sections highlight areas that may increase the necessary communication between
design and maintenance staff.
This procession of snow plows clearing the roadway demonstrates the urgency of labor and equipment
necessary to maintain operations on the highway during certain seasons
Maintenance staff has identified scoping through the 30% design phase as a critical period for
their input. The scoping phase presents opportunities to identify maintenance concerns and
adequately address them within the project scope and budget. The period between scoping
and 30% design presents opportunities to evaluate and refine options, as well as gain more
understanding of project constraints that may impact a previously identified or requested
maintenance feature. As the constraints and design trade-offs become evident, it is necessary
to review the impacts to maintenance needs and requests that were originally captured in the
project scope and ensure they are not impacted by constraints or the options under evaluation.
Maintenance staff are obligated to respond to immediate incidents and weather conditions.
They are not often able to delay their work functions and activities to make time for a design
project review. It is essential that designers understand this issue and plan for reviews through
scheduling techniques (see 301.03(1)(a)). In general, the best time to involve maintenance staff
is during their slower work seasons.
Maintenance responds to emergencies, which are more likely to occur during certain seasons
• Scoping phase
• Prior to the 30% design milestone (may need multiple meetings to evaluate design
options)
• Each time a previously agreed-to maintenance feature is impacted through design
iterations, as appropriate
• Prior to other major design review milestones
A primary purpose for performing field reviews with maintenance is to assist with visualizing the
project and to understand existing conditions. When performing the field review, it is important
to emphasize the following:
• Reiterate the purpose of the project and subprogram, and discuss maintenance
expectations.
• Determine the deficiency being corrected and the understood contributing factors. It is
important to gain an understanding from maintenance staff on any other contributing
factors or physical conditions that engineers may not be aware of.
• Visualize the project with maintenance:
o What will be new?
o What will be removed?
o What will be replaced, and what is the replacement?
o Where will new features be located?
o How will project changes affect neighbors?
• Determine whether the project can be operated and maintained with existing
equipment.
o It is necessary for design and maintenance staff to fully understand the impacts to
both the maintenance and project budgets to analyze and balance the obligations
for the investments as assets are identified on a project. For example, new lighting
means maintenance will be billed for the utility costs. Generally, this increased
cost has not resulted in increased funding.
- Will proprietary item requests be needed so maintenance can maintain
the project items with the tools and equipment they currently have?
- Will new equipment be needed, and who will fund that equipment
acquisition?
o What is the maintenance frequency for affected assets? Will this change?
o What are the environmental and permit restrictions related to the asset or
feature?
o How might maintenance physically maintain features to understand safety and
access needs for the asset or feature?
• Identify explicit action items for design and maintenance staff to follow up on as design
iterations continue.
• Document the outcomes of the field meeting, and follow up to ensure maintenance
needs are addressed, or provide specific explanations.
While independent reviews of plan sheets are meaningful for engineers, it may be an
inappropriate expectation that maintenance staff will see the same value. The repeated
familiarity of reviewing plan sheets is not necessarily present within the maintenance staff,
and plan review training may or may not be feasible for a given regional maintenance
organization based on staffing, workloads, and skill retention.
In some larger regional maintenance organizations, a liaison position has been designated for
designers to coordinate plan reviews. This approach has seen some success. However, this
liaison cannot possibly be aware of all comments/concerns for every maintenance discipline.
Don’t assume that coordinating plan reviews through the liaison meets the expectation for
maintenance stakeholder input. Always check with the various maintenance disciplines for
their preferred contacts and include those contacts within the PMP.
2. Schedule the appropriate duration and timing within the project schedule to complete the
necessary field reviews with maintenance staff.
• There are multiple scheduling techniques that may assist you, ensuring this will be
well planned based on maintenance staff availability and changing work priorities.
Contingency activities, providing more activities detailing the effort, or expanding
the duration for single activities may all be appropriate. If uncertain how to best
represent the needed time within the schedule, consult the Region Project
Management and Reporting System (PMRS) Coordinator for options.
Whenever possible, design should avoid creating environments that might be desirable to the
homeless, both for their safety and the safety of maintenance staff
Maintenance staff should never be in a position to review project details from a plan sheet
without a meeting/discussion, examples, or other means of communicating what feature or
issues they are reviewing on the plan sheet. This effort will help ensure there are “no surprises”
for maintenance and operations staff when the planned project enters construction.
Additionally, maintenance and operations staff should identify some qualitative risks and
opportunities associated with certain assets. Some opportunities, like the one presented in
Exhibit 301-2, may not be possible depending on material availability or funding restrictions.
It is important for designers to understand that some products may have a short shelf-life.
Procuring new replacement parts in the future may not be possible, which may result in a search
for used parts or the total replacement of the particular asset. These are future risks that need
to be identified so design engineers will understand what options or special provisions may be
required to help address the potential risks. Maintenance staff can help design understand the
history of different assets and
determine options that have been
successful for a given maintenance
location. Design engineers also need
to communicate the requirements
and disadvantages of proprietary
items specifically requested by
maintenance. While it may be the
desired product that maintenance is
familiar with, it may not be the best
product for what is being designed.
After analyzing the life cycle cost to maintain a particular asset, and demonstrating an
understanding of the associated risks, design and maintenance staff can justify the best return
on the construction investment. While the primary intent of this process is to document
justification for an asset decision, it is important that region Maintenance is supplied with
the information as well. Providing this information during the design process can inform
maintenance budgetary scenarios. Allow sufficient time for maintenance to capture budget
impacts and apply for the necessary funding in the bi-annual maintenance budgeting process.
Exhibit 301-2 Design Option Worksheet Showing Example of Life Cycle Cost Assessment
Exhibit 301-2 Design Option Worksheet Showing Example of Life Cycle Cost Assessment (continued)
Exhibit 301-2 Design Option Worksheet Showing Example of Life Cycle Cost Assessment (continued)
Exhibit 301-2 Design Option Worksheet Showing Example of Life Cycle Cost Assessment (continued)
Worksheets for each asset are another means to document the discussion, options considered,
and the decided outcome for a particular asset placed or retained within the project limits (see
example in Exhibit 301-2).
The asset management system reviews are necessary to confirm the assets present on a project,
as well as any identification numbers associated with the assets to track and list those that will
be removed, replaced, or remain. Work with the appropriate maintenance staff and confirm the
assets identified during field reviews with maintenance staff. Post-construction, any new assets
placed will need to be logged into the appropriate asset management system(s) by maintenance
or construction staff, depending on region procedures.
Information about these assets should be compiled into an Owner’s Manual for maintenance
to reference.
• The Owner’s Manual will be provided in hard copy, an editable electronic copy, and
static electronic versions.
• Electronic versions of the Owner’s Manual must be titled in the following format:
[YYYYMMDD]_Owner’s Manual_[route]_[MP Limits]_[Contract Number].
• Hard copies will be bound in a binder and labeled on the cover and binding with the
same information provided in the required PDF title.
The Owner’s Manual versions will be supplied to both maintenance and the construction office,
upon contract advertisement. Note: This may not be necessary if needed content is captured
within the area’s Integrated Vegetation Management (IVM) Plan.
If changes occur during post advertisement for a particular asset or feature listed in the Owner’s
Manual, it is the responsibility of the construction office and maintenance to coordinate an
update of the Owner’s Manual, as appropriate. As the construction phase ends, after punch
list items are resolved, Maintenance staff should undergo a final review to ensure the Owner’s
Manual is complete and accurate.
Some maintenance and operations agreements between state and local agencies exist for
streets that are also state highways, and are important to the success of these projects. These
agreements may need to be created, updated, or replaced due to the nature of the project.
The potential agreements need to identify the maintenance, operational, and jurisdictional
boundaries, roles, and responsibilities of the parties entering into the agreement, including
liability, indemnification, and insurance. The Conformed Agreement (above) lists the likely split
of jurisdictional responsibilities. However, maintenance jurisdiction(s) may want to create an
operational plan or agreement for the infrequent maintenance functions that designs may not
be able to accommodate. It is also possible that one maintenance jurisdiction will be better
equipped to handle certain maintenance elements than another. It will be necessary to
document the split of maintenance responsibilities even if responsibilities remain the same
as those listed within the Conformed Agreement.
Agreements require a level of detail that will not be known early in project development, so
it is important to document trade-offs, benefits, and impacts with the affected maintenance
jurisdictions while early decisions are being made.
Maintenance patching pavement at an intersection requires significant planning, night work, and traffic control
301.04 Documentation
Refer to Chapter 300 for design documentation requirements. Examples of documentation and
checklists can be found at: www.wsdot.wa.gov/design/policy/default.htm
301.05 References
301.05(1) Federal/State Laws, Codes and Agreements
City Streets as Part of State Highways Guidelines Reached by the Washington State Department
of Transportation and the Association of Washington Cities on Interpretation of Selected Topics
of RCW 47.24 and Figures of WAC 468-18-050 for the Construction, Operations and Maintenance
Responsibilities of WSDOT and Cities for such Streets, 4-30-1997, amended 4-2-2013
www.wsdot.wa.gov/localprograms/lag/construction.htm
305.01 Introduction
The Washington State Department of Transportation (WSDOT) utilizes best practices to develop
project management plans to successfully deliver projects on schedule and within budget.
WSDOT’s project management process provides an organized approach to building collaborative
teams. Resources including methods, processes, tools, templates, and examples offer the
opportunity to enhance project management.
This chapter serves as a reference and gives a brief overview of project management resources
and links for your use. This chapter outlines the steps of project management. Project
management includes strategies to manage:
Teams – identify roles and responsibilities; align team project goal
Collaboration – engage internal and external stakeholders and participants
Deliverables – identify what must be produced
Tasks – plan and organize sequence and levels of effort work to provide the
deliverables
Schedules – determine duration and task linkages
Costs – plan and control project budget
Risks – determine project exposure to threats and opportunities
Integration and coordination of processes – eliminate waste
Change – describe decision making, approving and reporting change
Quality – assure, control and verify quality
Communication – based on project needs, project team and external parties.
Effective project management must include a strong commitment to communication about the
project within and external to the design team. Following are descriptions and links to project
management resources.
Executive Orders 1032, 1038, and 1053 ensure a consistent process for practical design, project
management, and risk management statewide.
resources are consistent with a practical design approach and offer structure for organizing
collaborative teams to engage stakeholders and the community.
Exhibit 305-1 shows the project management process used to deliver projects. Each of the five
parts shown is briefly described in the sections that follow.
Monitoring
Initiating Planning Executing and Closing
Controlling
develop project take action - direct and monitor deliverables, prepare organized
organize team for
management plan and manage work and due dates, costs, and cessation activities;
success
work plan communications quality transition work or staff
The Project Management Plan defines the project performance baseline – including
deliverables, schedule and budget plans – and the management methods used to deliver the
project. As we plan the work for our projects we integrate and coordinate processes in a manner
that optimizes resources and reduces waste. For example if your project requires an interchange
justification report (IJR), national environmental policy act (NEPA) documentation, or a value
engineering study (VE) coordinate and align these efforts in a manner that makes use of
common information and subject matter experts and in a way that ensures the need statements
and function work together for the project.
The performance baseline documents the team goals for project performance. Performance
baseline includes:
Scope – the deliverables to be produced by the project team.
Schedule – the logical sequence of work and related milestones.
Budget – the allocation for the project.
Risk – uncertainty that affects project objectives.
The Project Management Plan includes management plans for Risk, Change, Communication,
Quality, Transition and Closure. These plans align the team toward uniform goals. A complete
project management plan considers how the project will start, how it will be executed,
monitored, and controlled, and how the project will close.
Address the closure and transition phase of the project management process during creation of
the project management plan and the work plan.
At the end of the project it is helpful to review lessons learned and to reward and recognize the
team for successes. Capturing lessons learned and recognize people occurs throughout the
project however, the closure phase provides an opportunity to finalize this and bring it to
conclusion.
Project transitions can be aided by using the Deliverable Expectation Matrix which provides a
range of project development deliverables and the general order in which they will occur.
A project is complete after transition and closure is accomplished and the project manager is
released from responsibility for the project.
Document each estimate review in the Project File, and clearly show any changes made to the
estimate as a result of the review.
305.05 References
Executive Order E 1053, Project Risk Management and Risk Based Estimating
www.wsdot.wa.gov/publications/fulltext/cevp/1053policy.pdf
310.01 General
Value engineering (VE) is a systematic review of a project by a multidisciplinary team not directly
involved in the planning and development phases of the project. The VE process includes
consideration of design; construction; maintenance; contractor; state, local, and federal
approval agencies; other stakeholders; and the public.
Properly timing a Value analysis influences its benefits. Value analyses are typically conducted
fairly early in project development to identify ideas to reduce cost and; refine scope. Section
310.02(3) VE Analysis Timing, of this chapter offers additional information about timing.
Project managers are accountable for ensuring their projects meet all applicable value
engineering requirements. In addition, local programs projects are accountable for ensuring
they comply with Local Agency Guidelines requirements. In all cases, when a VE study is
completed, the project manager is accountable for completing, signing, and submitting the VE
Recommendations Approval Form.
1
The terms “value management”, “value engineering”, “value study” and “value analysis” are used
interchangeably.
WSDOT projects for VE studies may be selected from any of the categories identified in the
Highway Construction Program, including Preservation and Improvement projects, depending
on the size and/or complexity of the project. In addition to cost, other issues adding to the
complexity of the project design or construction are considered in the selection process. These
include projects that have critical constraints, difficult technical issues, expensive solutions,
external influences, and complicated functional requirements, regardless of the estimated
project cost.
WSDOT may conduct VE analyses on any projects the project manager determines will benefit
from the exercise. In addition, WSDOT conducts VE analyses for all projects as required by the
criteria set forth in Federal Highway Administration (FHWA) Value Engineering Policy Order.
1. WSDOT policy requires a value engineering analysis for:
Any project with an estimated cost (which includes project development, design,
right of way, and construction costs) of $25 million or more, regardless of funding;
Each bridge project located on or off of the federal-aid system with an estimated
total cost of $20 million or more (WSDOT policy is to conduct a VE analysis
regardless of funding source); and
Any other projects the Secretary or FHWA determines to be appropriate.
2. In addition to the projects described above, WSDOT strongly encourages a VE analysis on
other projects where there is a high potential for cost savings or improved project
performance or quality. Projects involving complex technical issues, challenging project
constraints, unique requirements, and competing community and stakeholder objectives
offer opportunities for improved value by conducting VE analyses.
3. Any use of Federal-Aid Highway Program (FAHP) funding on a Major Project2 requires that a
VE analysis be conducted. In some cases, regardless of the amount of FAHP funding, a
project team may be required to perform more than one VE analysis for a Major Project.
4. After completing the required VE analysis, if the project is subsequently split into smaller
projects in final design or is programmed to be completed by the advertisement of multiple
construction contracts, an additional VE analysis is not required. However, splitting a project
into smaller projects or multiple construction contracts is not an accepted method to avoid
the requirements to conduct a VE analysis.
5. WSDOT may require a VE analysis to be conducted if a region or public authority encounters
instances when the design of a project has been completed but the project does not
immediately proceed to construction.
a. If a project meeting the above criteria encounters a three-year or longer delay prior to
advertisement for construction, and a substantial change to the project’s scope or
2
Based on the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU), signed into law on
August 10, 2005, a Major Project is defined as "a project with a total estimated cost of $500 million or more that is receiving financial
assistance." FHWA also has the discretion to designate a project with a total cost of less than $500 million as a Major Project.
design is identified, WSDOT may require a new VE analysis or an update to the previous
VE analysis; or
b. If a project’s estimated cost was below the criteria identified above but the project
advances to construction advertisement, and a substantial change occurs to the
project’s scope or design, causing an increase in the project cost so that it meets the
criteria identified above and results in a required re-evaluation of the environmental
document, WSDOT requires that a VE analysis be conducted.
6. When the design of a project has been completed but the project does not immediately
proceed to construction, the requirement to conduct a VE analysis is considered to be
satisfied, or not necessary, if:
a. A project met the criteria identified above and had a VE analysis conducted, and the
project advances to advertisement for construction without any substantial changes in
its scope or its design; or
b. A project’s estimated cost initially fell below the criteria identified above, but when
advancing to advertisement for construction, falls above the criteria due to inflation,
standard escalation of costs, or minor modifications to the project’s design or contract.
Other projects that should be considered for value engineering have a total estimated cost
exceeding $5 million and include one or more of the following:
Alternative solutions that vary the scope and cost
New alignment or bypass sections
Capacity improvements that widen the existing highway
Major structures
Interchanges
Extensive or expensive environmental or geotechnical requirements
Materials that are difficult to acquire or that require special efforts
Inferior materials sources
New/Reconstruction projects
Major traffic control requirements or multiple construction stages
Timing is very important to the success of the VE analysis. A VE analysis should be coordinated
with other project development activities. For example, a project requiring an Access Revision
Report (ARR), NEPA and a VE should consider how to best integrate the processes with
development of project need statements.
Benefits can be realized by performing a VE analysis at any time during project development;
however, the WSDOT VE program identifies the following three windows of opportunity for
performing a VE analysis.
1. Scoping Phase
Early in preliminary engineering is a good time for value analysis consideration. This is a time to
consider alternatives or design solutions with a high potential for implementing VE
recommendations. At the conclusion of the VE study, the project scope, preliminary costs, and
major design decisions are informed by the recommendations.
When conducting value engineering during the scoping phase of a project, the VE analysis
focuses on project drivers. This stage often provides an opportunity for community engagement
and building consent with stakeholders.
2. Start of Design
At the start of design, the project scope and preliminary costs have been established and major
design decisions have been made. Some Plans, Specifications, and Estimates (PS&E) activities
may have begun, and coordination with support groups and subject matter experts is underway.
At this stage, the project scope, costs, and schedule define the limits of the VE analysis. There is
opportunity to focus on the technical issues of the design elements.
3. Design Approval
After Design Approval, most of the important project decisions have been made and the
opportunity to affect the design is limited. Provided there is time to incorporate VE
recommendations, the VE analysis may likely focus on constructability, construction sequencing,
staging, traffic control, and significant design issues.
An additional VE analysis may be beneficial late in the development stage when the estimated
cost of the project exceeds the project budget. The value engineering process can be applied to
the project to lower the cost while maintaining the value and quality of the design.
The quality of the VE analysis largely depends on the skills of the VE team leader. This individual
guides the team’s efforts and is responsible for its actions during the analysis. The VE team
leader should be knowledgeable and proficient in transportation design and construction and in
the VE analysis process for transportation projects.
Team leaders from within WSDOT are encouraged, but not required, to be certified by the
Society of American Value Engineers (SAVE) as an Associate Value Specialist, Certified Value
Specialist (CVS) or as a Value Methodology Practitioner (VMP). Team leadership can be supplied
from within the region, from another region, or from Headquarters. A statewide pool of
qualified team leaders is maintained by the State VE Coordinator, who works with the Region VE
Coordinator to select the team leader.
The VE teams are usually composed of six to ten people with diverse expertise relevant to the
project under study. The team members may come from regions; Headquarters; other local,
state, or federal agencies; or the private sector.
Team members are not directly involved in the planning and development phases of the project.
They are selected based on the expertise needed to address major functional areas and critical
high-cost issues of the study. All team members must be committed to the time required for the
study. It is desirable for team members to have attended Value Engineering Module 1 training
before participating in a VE study.
310.03 VE Procedure
The WSDOT VE analysis uses the Seven-Phase Job Plan shown in Exhibit 310-1. A detailed
discussion of how each phase is supposed to be conducted can be found in the document, Value
Methodology Standard and Body of Knowledge, developed by SAVE International, The Value
Society. This document can be downloaded at the SAVE website: www.value-eng.org/
Note: Phases 1–6 are performed during the study; see Value Standard and Body of Knowledge for
procedures during these steps.
*Not all information listed may be available to the team, depending on the project
stage. Work with your Region VE Coordinator or the State VE Coordinator to verify that
all needed information is available.
**If a site visit is not possible, perform a “virtual” tour of the project.
http://www.wsdot.wa.gov/publications/fulltext/CEVP/VE_JobPlan.pdf
Exhibit 310-3 Value Engineering Job Plan
310.06 Documentation
Refer to Chapter 300 for design documentation requirements.
310.07 References
MAP-21 (Moving Ahead for Progress in the 21st Century), Section 1503
320.01 General
This chapter is intended to address policy-related issues associated with WSDOT multimodal
traffic analysis. It is not intended to address the specifics of demand forecasting; mesoscopic,
analytical/deterministic, stochastic microsimulation; or safety performance analyses. For those
items, see the latest versions of the Highway Capacity Manual, Traffic Analysis Procedures
Manual (TAPM), and Highway Safety Manual (HSM).
Traffic analysis is intended to produce information for decision makers; it is not intended as a
stand-alone tool for making decisions. Consideration of empirical data, similar traffic situations,
studies, local knowledge, and seasoned traffic engineering and planning experience can also add
to a pool of traffic information that is provided to decision makers.
Be aware that operational models were not primarily intended for use with planning-level future
year projected volumes, but there is a need to understand the difference between proposed
future scenarios. Therefore, operational models need to use data from forecasting models, but
analysts need to do so with an understanding of the imperfections.
Forecasting demand volumes 20 years into the future can be difficult to do well, so there should
be little expectation that intersection turning movement projection-related traffic analyses by
themselves will be sufficient to produce actionable designs. Consequently, some future year
Measures of Effectiveness (MOEs) such as turn lane queue length should not be considered
accurate, but they may be useful when comparing various scenarios if the reported differences
are substantial.
With the aforementioned limitations, project-specific traffic volumes, forecasts, and system
capacities are used to establish the extent of improvements needed for facilities to operate
acceptably from year of opening or through interim phases and, eventually, through to the
horizon year; for example: Number of general purpose/HOV/HOT lanes
• Length and number of ramp or auxiliary lanes
• Intersection or interchange spacing
• Channelization
• Signal timing
• Right of way needs
• Roundabout design parameters
• Width of sidewalks
• Extent of bike lanes
• Ferry holding lanes
Traffic analysis should examine multimodal access, mobility, and safety objectives; project
benefits and costs; development impacts; and mitigation needs.
Not all projects will require the same level of effort. The specific depth and complexity of
a traffic analysis will depend on a variety of factors, including:
• Project proponents (federal, tribal, state, local, and private sector)
• Legal requirements (laws, regulations, procedures, and contractual obligations)
• Lead agency
• Purpose or scope of the traffic analysis
• Data availability
• Time of day (am/pm peak hour or other)
• Funding
• ROW availability
For projects that fall under FHWA approval, coordinate with the Headquarters (HQ) Traffic
Office for concurrence on traffic analysis details. Other projects can be coordinated through
region Traffic offices. (See Chapter 300 for FHWA oversight and approval policy.)
For Access Revision Reports (AARs), the design year and multimodal travel demand forecasting
methodologies are to be documented by the project stakeholders in the Methods and
Assumptions (M&A) Documents.
Guidance on the horizon year and interim design year(s) for projects is given in Chapter 1103,
Design Controls. When selecting horizon year and interim design year phases, stakeholders need
to consider the regional significance of a proposed project, how it functions within the existing
system, and the expected lifespan. The traffic analysis for developer-related projects will
typically focus on existing conditions and the build-out year of the proposed project. Some
larger developer projects will need to be evaluated in multiple phases, as they have the
potential to significantly impact the transportation system and will thus require a longer-term
focus. Mitigation measures may also be phased with these projects.
Project teams are encouraged to consider the strategic importance, economic potential,
network constraints, and investment scale when determining the analysis methodologies for
project phasing, design year, and forecasts. With acceptance/concurrence by the Traffic Office
of purview,1 the following are possible approaches to be used individually or in concert to
develop future year demand volumes:
• Travel demand models
• Trend line projections
• Cumulative impacts
• Limitations of the surrounding network
The software mentioned above may have version limitations due to WSDOT purchased rights
and contract limitations. For details about these and other traffic analysis software used by
WSDOT, see the Traffic Analysis Procedures Manual or contact the region or HQ Traffic Office.
1
See Chapter 300 and the Federal-Aid Highway Program Stewardship and Oversight Agreement: Generally, region
for non-Highways of Statewide Significance (HSS) or non-National Highway System (NHS), and Headquarters for
HSS and NHS.
conclusions from operational model Measures of Effectiveness (MOEs) that are based on such
forecasts, because specific and accurate turning movement volumes are needed to produce
credible MOEs. Forecast models are most commonly used to produce general volumes that
can help traffic planners evaluate and compare the relative merits of potential solutions
against each other.
This approach needs to demonstrate that the maximum amount of upstream traffic flowing into
a project, as well as all project-area traffic flowing into downstream sections, can be handled
acceptably. This does not require traditional travel demand forecasting, which has a limitation of
about 20 years. Instead, it requires a sensitivity approach where maximum up- and downstream
flows are used to right-size the project area’s proposed improvements. The simplest example is
the SR 520 Floating Bridge: constraints on either end of the bridge limit the usefulness of adding
more lanes on the bridge.
TIAs and ARRs (see Chapter 550) shall clearly describe the methodology and process used to
develop forecasts in support of a proposed project’s analysis. For example, include only those
projects that:
• Are on the six-year Transportation Improvement Plan.
• Are fully funded.
• Have entered the environmental review process.
For some example MOEs, see the FHWA MOE List, which describes measures typically used for
analyzing state and local agency facilities such as freeway segments, signalized intersections,
ramp terminals/junctions, sidewalks, and transit services.
Depending on the facility and when HCM Level of Service MOE is used, WSDOT thresholds are
“C” for rural and “D” for urban non-NHS facilities, unless a WSDOT region specifies otherwise
for specific route segments. (See each WSDOT region for details.) Refer to the WSDOT State
Highway Log for a determination of existing route segment definitions for urban or rural status.
Depending on the project type and purpose, multimodal MOEs may be employed.
If the amount or character of traffic in the study area is significantly different from an earlier
analysis, an update will be required. The definition of significant is 10% (volume, flow rate, travel
time, delay, density, or other key MOEs) where existing operations are currently acceptable. If
they are not currently acceptable, the threshold is reduced to 5%. In cases where greater than
10% change or failed MOEs have been found, consultation and concurrence with WSDOT Traffic
Office of purview is required to avoid a full ARRs or TIA update.
Developer-initiated TIAs are typically valid for 5 or 6 years, as that is the window provided under
the Growth Management Act for concurrency. The Development Services Office should be
consulted regarding the need for updates to TIAs for developer, tribal, and local agency projects.
2
WSDOT sets level of service (LOS) standards for state highways and ferry routes of statewide significance (HSS)
based on RCW 47.06.140(2). Regional transportation planning organizations (RTPOs) and WSDOT jointly develop
and RTPOs establish LOS standards for regionally significant state highways and ferry routes (non-HSS) based on
RCW 47.80.030(1)(c).
Depending on the type of work being analyzed, required TIA scenarios can range from simple
“existing conditions with and without project,” to more complex analyses where TIA scenarios
could include: existing; opening year with and without project; interim years with and without
project; and design year with and without project. If developed with WSDOT, and if following
ARR guidance, pre-ARR work such as Area Study TIAs can be used in future ARRs.
The appropriate and necessary scenarios shall be agreed upon by the TIA study team and
documented in the TIA Methods and Assumptions (M&A) Document.
For interim scenario networks, include only projects or developments within the forecasting
process that have the highest probability within the 10-year horizon. For example, include
projects that are fully funded or have a construction phase in the six-year Transportation
Improvement Plan.
For scenarios with phases beyond 10 years, TIA or ARR teams should discuss and document
the merits of including other potential projects. For example:
• Projects on current long-range regional transportation plans (or the locally-adopted
transportation plan, if the TIA is not on a regionally-significant facility)
• Projects on the HSP or MTP
All other potential influences with lower probability should not be allowed to affect travel or
trip demand forecast results—with one exception: TIAs and ARRs may include multiple scenarios
for the design year. For example, if a major assumption for unfunded additional lanes “feeding
traffic into” or “allowing traffic from” the project is desired for the design year to allow for a
better understanding of expensive infrastructure sizing (such as ultimate bridge widths), ensure
a constrained design year scenario is included so that proper funding-based phasing solutions
are communicated.
Prior to any substantial fieldwork or traffic/facility data collection, consultation between the
lead agency, WSDOT, and those preparing the TIA is encouraged to help reach and document
consensus on study data needs and assumptions. These and other items should be documented
and the M&A signed by all lead staff that conduct work in association with the TIA M&A
document. For further guidance, consult the Traffic Analysis Procedures Manual and
Development Services Manual.
The procedures in the Highway Capacity Manual do not explicitly address operations of
closely spaced signalized intersections, nor does WSDOT currently endorse microsimulation
or roundabout guidance as noted in the HCM/S. Under such conditions, several unique
characteristics must be considered, including spill-back potential from the downstream
intersection to the upstream intersection; effects of downstream queues on upstream
saturation flow rates; and unusual platoon dispersion or compression between intersections.
An example of such closely spaced operations is signalized ramp terminals at urban
interchanges. Queue interactions between closely spaced intersections can seriously
distort the results of analyses that follow the procedures in the HCM.
Other analysis methods may be accepted; however, consultation between the lead agency,
region or HQ Traffic, and those preparing the TIA is encouraged to reach consensus on the
data necessary for the analysis if meso- or microsimulation is employed. When a state highway
has saturated flows, the use of a meso- or microsimulation models can provide additional
understanding. Note, however, that the simulation model must be calibrated and validated
for reliable results and is intended for near-term operational analyses (see the Traffic Analysis
Procedures Manual for guidance on calibration and validation).
Operational MOEs for simulation models based on long-term forecasts should be used primarily
to determine which scenarios are better than others. The models can only do so if the resultant
MOEs demonstrate significant differentiation between scenarios. TIA or ARR teams will
determine what is considered significant and will document those findings in the study. However,
at a minimum, significant must be greater than the expected error band of the models used. For
example, if Vissim is considered to be calibrated to a given MOE within 15% of existing conditions
(a very wide band), the scenarios need to show greater than 15% differentiation between each
other to be significant.
Development work in the state highway right of way requires a WSDOT permit or agreement.
Normally, this work is coordinated by the region Development Services Office.
(c) Introduction
1. TIA M&A (see the Traffic Analysis Procedures Manual for a template or the Development
Services Manual).
2. Existing and projected conditions of the site: posted speed; traffic counts (to include
turning movements); sight distance; channelization; design analyses; pedestrian and
bicycle facilities; design vehicle; and traffic controls, including signal phasing and multi-
signal progression where appropriate (exhibit(s)).
3. DHV and ADT; project trip generation and distribution map, including references and a
detailed description of the process involved in forecasting the projected trips, including
tables.
4. Project-related transportation mode split, with a detailed description of the process
involved in determining transportation mode split.
5. Project-generated trip distribution and assignment with a detailed description of the
process involved in distributing and assigning the generated traffic, including exhibit(s).
6. If intersection control additions are employed and traffic signals are assumed, include
functionality and warrant analyses. With roundabouts or signals, include existing
conditions, cumulative conditions, and full-build of plan conditions with and without
project.
7. Safety performance analysis (see Chapter 321 and the Traffic Analysis Procedures
Manual).
1. Quantified or qualified LOS, QOS, and other appropriate MOEs of impacted facilities
with and without mitigation measures.
2. Predicted safety performance with and without mitigation measures.
3. Mitigation phasing plan with dates of proposed mitigation measures.
4. Defined responsibilities for implementing mitigation measures.
5. Cost estimates for mitigation measures and financing plan.
(f) Appendices
1. Description of traffic data and how data was collected and manipulated.
2. Description of methodologies and assumptions used in analyses.
3. Worksheets used in analyses; for example, signal warrants, LOS, QOS, and traffic
count information.
4. If microsimulation is used, provide a copy of the Confidence and Calibration Report.
320.11 References
320.11(1) Federal/State Laws and Codes
42 United States Code 4321, National Environmental Policy Act (NEPA) of 1969
Revised Code of Washington (RCW) 43.21C, State environmental policy (Chapter 197-11
WAC and Chapter 468-12 WAC)
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as
adopted and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices
for streets and highways” (MUTCD)
Highway Capacity Manual (HCM), latest edition, Transportation Research Board, National
Research Council
Roadside Design Guide and A Policy on Geometric Design of Highways and Streets, latest
editions, American Association of State Highway and Transportation Officials (AASHTO)
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01,
WSDOT
The Secretary’s Executive Order E 1085, Sustainable Highway Safety Program, sets the policy for
the Washington State Department of Transportation (WSDOT) to embark on a targeted and
scientifically-based Engineering approach for identifying and addressing crash risks that is
multimodal and coordinated with the other three “E”s, Education, Enforcement, and Emergency
Services. Sustainable Safety employs a “5th E”, Evaluation, this is the analysis and diagnosis of
crashes and to target their contributing factors in addressing highway safety performance.
Evaluation relies on quantifying safety performance using scientific tools and assessment
techniques to determine appropriate safety countermeasures.
Sustainable Safety is the approach to transportation safety at WSDOT through the use of
“…tools and procedures based on accepted science, data, and proven practice” in accordance
with Secretary’s Executive Order E 1096, Agency Emphasis and Expectations, to target safety
needs, and “deliver the right solutions at the right time and at the right location.”
Practical Solutions is an approach to making project decisions that focus on resolving the project
need for the least cost without adversely impacting safety performance. Sustainable Safety is
the approach for resolving safety performance within WSDOT’s Practical Solutions as directed in
both E 1096 and Secretary’s Executive Order E 1090, Moving Washington Forward: Practical
Solutions.
E 1085 directs engineers to base project-level decisions on safety analysis of specific locations
and corridors and focus on proven lower-cost targeted countermeasures at specific locations
that optimize the return on investment of safety dollars. These lower-cost investments allow for
additional identified locations to be addressed. Sustainable Safety is therefore an essential part
of successful Practical Design implementation. It provides the process and methods to
incorporate safety performance assessment and peer-review into Performance-Based Practical
Design. Sustainable Safety allows the planner, engineer, and decision maker, to identify and
quantify the safety performance of alternatives during project development.
Implementing Sustainable Safety improves WSDOT’s effectiveness in reducing the risk of fatal
and serious injury crashes statewide. It focuses on the contributing factors and types of crashes
through the use of state-of-the-art principles and analytical methods to diagnose, quantify, and
predict safety performance. The Sustainable Highway Safety Policy directs WSDOT to use
effective and efficient resources, like the AASHTO Highway Safety Manual (HSM) to achieve the
goals of the Washington State Strategic Highway Safety Plan: Target Zero. This approach:
1. Optimizes the reduction in fatal and serious injury crash potential on Washington’s
highways.
2. Provides quantifiable assessment of crash potential.
3. Identifies locations that have a higher potential for crash reduction.
4. Provides reliable and accurate assessment of potential crash reduction benefits.
5. Identifies and deploys solutions with optimal benefit/cost within the WSDOT safety priority
programming process or through low cost operational improvements.
6. Reduces waste by focusing on design elements that provide a reduction in crash potential.
7. Addresses locations that will result in a higher crash risk reduction potential for a given
investment level.
8. Provides an accurate assessment of project and program performance.
9. Provides scientific and engineering tools to continually improve and refine safety analyses.
Sustainable Safety is a critical, integral part of Practical Solutions that supports Washington in
reaching its Target Zero goal.
If a CAR was developed using the template for the 2019-21 biennium or newer, the project does
not need a BOD.
321.06 References
Revised Code of Washington (RCW) 47.05.010 – The statement of purpose for priority
programming of transportation projects
Secretary’s Executive Order 1096 – WSDOT 2015-17: Agency Emphasis and Expectations
A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO, 2011
Sustainable Highway Safety Internal Web Page – Contains all of the procedures and tools to
implement highway safety: http://wwwi.wsdot.wa.gov/HighwaySafety/
400.01 General
The Washington State Department of Transportation (WSDOT) is permitted, by an agreement
with the Board of Registration for Professional Engineers and Land Surveyors, to practice land
surveying “under the direct supervision of a licensed professional land surveyor OR a licensed
professional engineer” (see Exhibit 400-1, Interagency Agreement).
400.02 References
400.02(1) Federal/State Laws and Codes
Revised Code of Washington (RCW) 58.09, Surveys – Recording
WAC 332-130, Minimum standards for land boundary surveys and geodetic control surveys and
guidelines for the preparation of land descriptions
Interagency Agreement Between the Washington State Department of Transportation and the
Board of Registration for Professional Engineers and Land Surveyors (1990)
400.03 Procedures
For WSDOT projects, it is recommended that surveying activities include (if appropriate) but not
be limited to the following items.
(a) Record any pertinent surveying information as detailed in the Design Documentation
Checklist: www.wsdot.wa.gov/design/projectdev/
(b) Conduct research to find recorded survey monuments existing within the project area.
(c) Determine and prioritize project survey needs and tasks to be completed. Needs and tasks
may include the following issues:
• Cadastral
• Right of way
• Geodetic
• Photogrammetry
• Other issues as needed
(d) Contact city, county, state, and federal agencies, the Region Survey Office, and the
GeoMetrix Geodetic Survey section for potential impact to existing monuments.
(a) The project manager and project surveyor hold a preliminary survey meeting, regarding:
• Project schedule.
• Anticipated survey requests.
For preliminary survey meeting specifics and roles and responsibilities of the project
manager and project surveyor, see the Highway Surveying Manual.
(b) Perform field reconnaissance, mark existing recorded survey monuments, and determine
the location of possible new survey monuments. Also, mark found unrecorded monuments
for preservation if practical.
(c) Contact the GeoMetrix Geodetic Survey section by email, memo, or other written
notification for assistance in determining the impact to state and federal geodetic
monuments.
(d) Refer to the Highway Surveying Manual to:
• Convert Washington State Plane Coordinates to project datum.
• Document the procedure and combined factor used for converting between
datums.
• Determine survey collection methods.
• Collect primary, secondary, and tertiary survey data.
• Process and import secondary, tertiary, or other survey data into design software
for use by designers.
(e) Apply to the Department of Natural Resources (DNR) for permits for monuments that will
be disturbed or removed (see Chapter 410).
(f) The GeoMetrix Geodetic Survey section will archive new primary survey control data in
the WSDOT Monument Database for future retrieval.
(g) Ensure that all survey monuments within the project right of way are shown on the
contract plans in order to avoid accidental damage.
(h) Develop a Record of Survey (RCW 58.09) or a Monumentation Map as required (see
Chapter 410).
400.04 Datums
A datum is a geometrical quantity (or set of quantities) that serves as a reference, forming the
basis for computation of horizontal and vertical control surveys in which the curvature of the
earth is considered. Adjusted positions of the datum, described in terms of latitude and
longitude, may be transformed into State Plane Coordinates.
All engineering work (mapping, planning, design, right of way, and construction) for WSDOT
projects is based on a common datum.
400.04(1) Horizontal
WAC 332-130-060 states, “The datum for the horizontal control network in Washington shall be
NAD83 (1991) [the North American Datum of 1983] as officially adjusted and published by the
National Geodetic Survey of the United States Department of Commerce and as established in
accordance with Chapter 58.20 RCW. The datum adjustment shall be identified on all documents
prepared; i.e., NAD83 (1991).” (See the Highway Surveying Manual for further information.)
400.04(2) Vertical
The North American Vertical Datum of 1988 (NAVD88) as defined by the National Geodetic
Survey (NGS) is the official civilian datum for surveying and mapping activities in the United
States. WSDOT has adopted this datum. (See the Highway Surveying Manual for further
information.)
GPS technology is changing rapidly. The key point is for the designer and surveyor to select
the best tool (GPS or conventional applications) for doing the survey fieldwork. Often, a
combination of GPS and conventional (Total Station) surveying is appropriate.
To access the WSDOT Survey Monument Database, see the following website:
www.wsdot.wa.gov/monument/
The usefulness of aerial photography is not limited to mapping. Taking the form of
enlargements, mosaics, and digital images, it can be used as a visual communication tool
(displays and exhibits) for planning, design, property acquisition, engineering, construction,
litigation, and public relations.
400.09 Documentation
For documentation related to monuments, see Chapter 410.
Primary and secondary survey control data are archived in the WSDOT Survey Monument
Database and GIS when available.
For the list of documents required to be preserved in the Design Documentation Package
and the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev/
410.01 General
Proper monumentation is important in referencing a highway’s alignment, which is used
to define its right of way. The Washington State Department of Transportation (WSDOT)
can contribute to the body of public records and minimize duplication of survey work by
establishing and recording monuments that are tied to a state plane coordinate system and
to a standard vertical datum. WSDOT is required by law to perpetuate existing recorded
monuments (Chapter 58.09 RCW). The department provides monuments for realignments
and new highway alignments and perpetuates existing monuments impacted by a project.
The Department of Natural Resources (DNR) is designated as the official agency for surveys
and maps. New monuments set to establish property corners, highway alignment, and so on,
shall be recorded on a Record of Survey or Monumentation Map and filed with the DNR Public
Land Survey Office and the appropriate county auditor or county engineer. Records of Survey
and Monumentation Maps are retained at DNR. Geodetic monuments are established and the
Headquarters (HQ) GeoMetrix Office retains their placement records. Geodetic monuments
are recorded on a Report of Survey Mark. These records are made available to the public on
the following website: www.wsdot.wa.gov/monument/
Existing monuments are not to be disturbed without first obtaining the DNR permits required
by state law. DNR allows the temporary covering of a string of monuments under a single permit.
State law requires replacement of land boundary monuments after temporary removal according
to permit procedures. WSDOT control and alignment monuments may not be removed without
replacement unless the location of the original position is perpetuated by reference and the
appropriate document(s) prepared and filed with the county and the HQ Right of Way Plans
Section. Other requirements pertaining to specific monuments are discussed below.
Exhibit 410-1 summarizes the documentation requirements for new and existing monuments.
The region is responsible for identifying and locating existing monuments, obtaining required
permits before any existing monument is disturbed, and conducting the research to locate
existing monuments as required by WAC 332-120-030, as follows:
Any person, corporation, association, department, or subdivision of the state, county
or municipality responsible for an activity that may cause a survey monument to be
removed or destroyed shall be responsible for ensuring that the original survey point
is perpetuated. It shall be the responsibility of the governmental agency or others
performing construction work or other activity (including road or street resurfacing
projects) to adequately search the records and the physical area of the proposed
construction work or other activity for the purpose of locating and referencing
any known or existing survey monuments.
410.02 References
410.02(1) Federal/State Laws and Codes
Chapter 18.43 Revised Code of Washington (RCW), Engineers and land surveyors
Chapter 58.09 RCW, Surveys – Recording
Chapter 58.24 RCW, State agency for surveys and maps – Fees
Chapter 332-120 Washington Administrative Code (WAC), Survey monuments – Removal
or destruction
Chapter 332-130 WAC, Minimum standards for land boundary surveys and geodetic control
surveys and guidelines for the preparation of land descriptions
When any property corner monument is set, the licensed land surveyor shall file a Record
of Survey with the county auditor. A copy of the recorded Record of Survey is sent to the
HQ Right of Way Plans Section and HQ Real Estate Services.
410.08 Documentation
Refer to Chapter 300 for design documentation requirements.
SET NEW
Control Monument
Before: Obtain DNR permit.
After: File a copy of the Monumentation Map with the county engineer.
Send the original to the HQ Right of Way Plans Section.
Alignment Monument
Before: Obtain DNR permit.
After: File a copy of the Monumentation Map with the county engineer.
Send the original to the HQ Right of Way Plans Section.
Section Corner, BLM, or GLO Monument
Before: Obtain DNR permit.
After: File Land Corner Record with the county engineer. Send a copy to the
HQ Right of Way Plans Section.
All Other Monuments
Before: Obtain DNR permit. Contact governmental agency.
After: File a copy of the Monumentation Map with the county engineer.
Send the original to the HQ Right of Way Plans Section.
* Property corner monuments must be filed within 90 days of establishment, re-establishment,
or restoration.
510.01 General
Washington State Department of Transportation (WSDOT) Real Estate Services personnel
participate in the project definition phase of a project to assist in minimizing right of way costs,
defining route locations and acquisition areas, and determining potential problems and possible
solutions.
Due to the variables in land acquisition, the categories of right of way costs considered in the
project definition phase are:
• Purchase costs (acquisition compensation).
• Relocation assistance benefits payments.
• Other Real Estate Services staff expenses (acquisition services, relocation services, and
interim property management services).
Right of way cost estimates are made by Real Estate Services specialists. When the parcels from
which additional right of way will be acquired are known, title reports (including assessors’ land
areas) can be requested.
Real Estate Services personnel also make project field inspections at appropriate times
throughout the development of a project to ensure adequate consideration is given to
significant right of way elements involved (including possible social, economic, and
environmental effects) in accordance with the Right of Way Manual.
Engineering considerations for right of way are contained in many chapters in this manual.
Examples include chapters in the 700 series related to bridges and walls and in Chapter 1230,
Geometric Cross Section. (See Chapter 1102, Context Identification, as a recommended first
read for discussion of right of way.) Preliminary right of way widths are developed and may be
modified based on Real Estate Services’ input, but cannot be moved to coincide with property
boundaries in anticipation of a total take. Jogs in the final widths of the right of way are held to
a minimum. (See Right of Way Manual, Chapter 6, for discussion of remainders.)
All acquisition documents are processed through Headquarters (HQ) Real Estate Services except
temporary permits that are not shown on right of way plans and are not needed for the project
(such as for driveway connections).
On limited access highways, road approaches of any type must be approved by the Director &
State Design Engineer, Development Division, before there is legal basis for negotiation by Real
Estate Services. When approved, approaches will be specifically reserved in the right of way
transaction and will contain the identical limitations set by the Director & State Design Engineer,
Development Division, and as shown on the approved right of way and limited access plan.
On limited access highways, approval by the Director & State Design Engineer, Development
Division, and the addition of a traffic movement note on the right of way and limited access
plan (see the Plans Preparation Manual) are required.
Easements and permits to accommodate WSDOT activities outside the right of way usually fall
into one of the categories defined below.
Easements and permits are processed in accordance with the requirements of the Right of Way
Manual. The region Real Estate Services Office drafts the legal descriptions for all easements
and permits for acquisition of property and property rights. HQ Real Estate Services drafts the
legal description for all easements and permits for disposition of property or property rights.
The region Real Estate Services Office either obtains or assists in obtaining easements and
permits. The region is responsible for compliance with and appropriate retention of the final
documents. Records of permanent property rights acquired are maintained by HQ Real Estate
Services. Easements and permits are to be shown on the contract plans in accordance with the
Plans Preparation Manual.
When WSDOT is paying for the rights or when the encroachment is significant, temporary
easements are shown on the right of way plans, in accordance with the Plans Preparation
Manual. Consult the region Plans and Real Estate Services personnel for exceptions. If the
easement is not mapped, mark and submit plans according to the following information.
(a) The region provides a right of way plan with the required temporary easement(s) delineated
in red to the region Real Estate Services Office. These plan sheets provide:
• Ownership boundaries. Confirmation of ownership and parcel boundaries may be
completed by a search of county records and mapping; a formal title report is
required for temporary easements.
• A parcel number assigned to each ownership.
• Sufficient engineering detail to write legal descriptions.
• A statement of the intended use of each temporary easement area.
(b) In limited access areas, contact the HQ Access and Hearings Office.
When there is a benefit to the property owner (for example, driveway or parking lot approach
improvements) the construction permit is usually obtained without the payment of
compensation (for example, donation or mutual benefits). Consult the region Plans and Real
Estate Services offices for exceptions.
When federal funds are involved, special attention must be given to Federal Highway
Administration (FHWA) requirements. When federal participation in right of way costs is
anticipated, specific authorization must be obtained from the FHWA. The rules and procedures
provided in RCW 8.26, WAC 468-100, and the Right of Way Manual must be followed to ensure
federal and state participation. In many cases, federal funds are contingent upon the department
setting up a relocation advisory procedure for any owner or tenant who is displaced by a project
and desires such assistance. Relocation advisory assistance is a function of HQ Real Estate
Services.
510.05(2) Exceptions
Exceptions can be made to the requirements in Exhibit 510-1 if unusual hardships result for
the individual or the state. The approval of right of way hardship action will be based on the
individual parcel merit and is processed in accordance with hardship acquisition policy (see
the Right of Way Manual).
510.06 Transactions
510.06(1) Private Ownerships
Right of way is ordinarily acquired from private property owners by region-level negotiation
between the owner and the right of way agent.
510.06(2) Utilities
The region determines the ownership of all utilities and makes arrangements for necessary
adjustment, including relocation of portions of the utility, if necessary. Provisions for relocation
or adjustment are included in the Plans, Specifications, and Estimates (PS&E) when:
• The items are normal construction items and the department is obligated for the
moving expense.
• The utility requests that relocation be performed by the department and the
department has approved the request.
Readjustment may require WSDOT to purchase substitute rights of way or easements for
eventual transfer to the utility. Such rights of way or easements must be shown on the right
of way plans with the same engineering detail as highway right of way. On limited access
highways, if an approach is required for maintenance of a utility, the approach will be shown
on the approach schedule. (See the Utilities Accommodation Policy regarding location of and
access to utilities.)
Negotiations with the utilities are often done by HQ Real Estate Services. Because of the
considerable time required to obtain approvals, processing of utility relocation agreements
must begin as soon as possible.
510.06(3) Railways
Right of way is generally not acquired in fee from a railroad company. Instead, the state
acquires a perpetual easement for encroachment or crossing. A construction and maintenance
agreement may also be required. The easement must be shown on the right of way plan and
identified by both highway and railroad stationing.
The HQ Design Office coordinates with the railroad design staff to determine a mutually
agreeable location before the proposed easement is sent to Real Estate Services. The
negotiations with the railroads are generally done by HQ Real Estate Services. Because
of the considerable time required to obtain approvals, processing of railroad agreements
must begin as soon as possible.
The perpetual easement document is executed by the Real Estate Services Director.
510.06(6) Condemnations
Condemnation can result from a disagreement between the department and the owner
regarding a fair settlement or a faulty title. Since several months might elapse between the
filing of a condemnation case and a court decision, the region Real Estate Services Office can be
requested to investigate the possibility of obtaining a negotiated possession and use agreement
as in the case of an emergency project or when a sundry site is required immediately.
510.07 Documentation
Refer to Chapter 300 for design documentation requirements.
510.08 References
510.08(1) Federal/State Laws and Codes
23 Code of Federal Regulations (CFR) Part 710
49 CFR Part 24, Uniform Relocation Assistance and Real Property Acquisition for Federal and
Federally Assisted Programs
Revised Code of Washington (RCW) 8.26, Relocation assistance – Real property acquisition
policy
Washington Administrative Code (WAC) 468-100, Uniform relocation assistance and real
property acquisition
Director & State Design Engineer, Development Program appraisals of total takes.
Division,* approves access report plan for (No acquisition.)
prehearing discussion with county and city officials.
Director & State Design Engineer, Development Program all appraisals and
Division,* approves access hearing plan for use at a acquisitions.
public access hearing. R/W information is complete.
PHASE 2 Note: Do not appraise or purchase
Access The access hearing plan may be used for the partial takes in areas subject to
Hearing Plan preparation of federal-aid program data for controversy. Appraise or purchase
negotiations on federally funded projects and for total takes only if federal design
the preparation of true cost estimates and fund hearing requirements are met.
requests.
Director & State Design Engineer, Development Program all remaining appraisals
Division,* approves final R/W and L/A plans or and all remaining acquisitions.
PHASE 4 approves revisions to established R/W and L/A
Final R/W Note: If appeal period is not
plans.
and L/A Plan complete, delay action in areas
subject to controversy and possible
appeal.
*Or a designee.
520.01 General
The Washington State Department of Transportation (WSDOT) controls access to the state’s
highways (with a few exceptions) in order to preserve the safety and efficiency of these
highways as well as the public investment. All Washington State highways are distinguished as
being either limited access or managed access highways. Control of access is accomplished by
either acquiring rights of access from abutting property owners (limited access control) or by
regulating access connections to the highway (managed access control). Until limited access
rights have been acquired from abutting property owners, the route is a managed access
highway. Managed access permits are issued either by a local authority (city or town) or by
WSDOT.
Numerous studies have shown that controlling and limiting access to highways is a cost-effective
way to help maintain the safety, capacity, and functional integrity of a highway. Adding more
lanes to an existing highway is expensive and frequently not possible. Controlling access to our
state highways by promoting the use of frontage roads or other existing county or city roads,
and advocating the internal shared circulation within adjacent developments, is a proactive
and cost-effective way to accomplish this objective.
WSDOT has been purchasing access rights and implementing limited access control since 1951
(RCW 47.52). While this has been effective, it is an expensive way to control access to the state
highway system. Adequate funding to accomplish the purchasing of access rights has not kept
up with the state’s continual population growth and land use development over the years.
As a result, state lawmakers introduced a bill in the early 1990s recognizing that controlling
access to the state highway system by regulation was a cost-effective means to preserve the
safety and capacity of our state highway system.
In 1991, the Legislature passed and the Governor approved RCW 47.50, titled “Highway access
management.” This new law directed WSDOT to develop new rules to be included in the
Washington Administrative Code for those state highways not already limited access highways.
The result was a new class of access control called managed access.
Chapter 530 describes limited access highways in greater detail. Chapter 540 describes managed
access highways in greater detail.
The following references and definitions apply to Washington’s access control as presented in
Chapters 530 and 540.
520.02 References
520.02(1) Federal/State Laws and Codes
Revised Code of Washington (RCW) 18.43, Engineers and land surveyors
RCW 35.78, Streets – Classification and design standards
RCW 46.61, Rules of the road
RCW 47.17, State highway routes
RCW 47.24, City streets as part of state highways
RCW 47.32, Obstructions on right-of-way
RCW 47.50, Highway access management
RCW 47.52, Limited access facilities
Washington Administrative Code (WAC) 468-51, Highway access management access permits –
Administrative process
WAC 468-52, Highway access management – Access control classification system and standards
WAC 468-54, Limited access hearings
WAC 468-58, Limited access highways
520.03 Definitions
access A means of entering or leaving a public road, street, or highway with respect to
abutting property or another public road, street, or highway.
access control The limiting and regulating of public and private access to Washington State’s
highways, as required by state law.
Access Control Tracking System Limited Access and Managed Access Master Plan A database
list, related to highway route numbers and mileposts, that identifies either the level of limited
access or the class of managed access: www.wsdot.wa.gov/design/accessandhearings
access connection permit A written authorization issued by the permitting authority for a
specifically designed access connection to a managed access highway at a specific location; for
a specific type and intensity of property use; and for a specific volume of traffic for the access
connection based on the final stage of the development of the applicant’s property. The actual
form used for this authorization is determined by the permitting authority.
access design analysis A design analysis (see Chapter 300) that authorizes deferring or staging
acquisition of limited access control, falling short of a 300-foot requirement, or allowing an
existing access point to stay within 130 feet of an intersection on a limited access highway.
Approval by the Director & State Design Engineer, Development Division, is required (see
Chapter 530).
access hearing plan A limited access plan prepared for presentation at an access hearing.
access point Any point that allows private or public entrance to or exit from the traveled way
of a state highway, including “locked gate” access and maintenance access points.
access point spacing On a managed access highway, the distance between two adjacent
access points on one side of the highway, measured along the edge of the traveled way from
one access point to the next (see also corner clearance).
access report plan A limited access plan prepared for presentation to local governmental
officials at preliminary meetings before preparation of the access hearing plan.
access rights Property rights that allow an abutting property owner to enter and leave the
public roadway system.
allowed Authorized.
approach and access connection These terms are listed under the specific access section
to which they apply. The first section below is for limited access highways and uses the term
approach. The second section below is for managed access highways and uses the term access
connection. Approaches and access connections include any ability to leave or enter a highway
right of way other than at an intersection with another road or street.
(a) limited access highways: approach An access point, other than a public road/street, that
allows access to or from a limited access highway on the state highway system. There are
five types of approaches to limited access highways that are allowed:
• Type A An off and on approach in a legal manner, not to exceed 30 feet in width,
for the sole purpose of serving a single-family residence. It may be reserved by the
abutting owner for specified use at a point satisfactory to the state at or between
designated highway stations. This approach type is allowed on partial and modified
control limited access highways.
• Type B An off and on approach in a legal manner, not to exceed 50 feet in width,
for use necessary to the normal operation of a farm, but not for retail marketing. It
may be reserved by the abutting owner for specified use at a point satisfactory to
the state at or between designated highway stations. This approach type is allowed
on partial and modified control limited access highways. This approach type may
be used for wind farms when use of the approach is limited to those vehicles
necessary to construct and maintain the farm for use in harvesting wind energy.
• Type C An off and on approach in a legal manner, for a special purpose and width
to be agreed upon. It may be specified at a point satisfactory to the state at or
between designated highway stations. This approach type is allowed on partial
and modified control limited access highways and on full control limited access
highways where no other reasonable means of access exists, as solely determined
by the department.
• Type D An off and on approach in a legal manner, not to exceed 50 feet in width,
for use necessary to the normal operation of a commercial establishment. It may
be specified at a point satisfactory to the state at or between designated highway
stations. This approach type is allowed only on modified control limited access
highways.
• Type E This type is no longer allowed to be constructed because of the
requirements that there be only one access point per parcel on a limited access
state highway.
• Type F An off and on approach in a legal manner, not to exceed 30 feet in width,
for the sole purpose of serving a wireless communication site. It may be specified
at a point satisfactory to the state at or between designated highway stations. This
approach type is allowed only on partial control limited access highways. (See
WAC 468-58-080(vi) for further restrictions.)
(b) managed access highways: access connection An access point, other than a public road/
street, that permits access to or from a managed access highway on the state highway
system. There are five types of access connection permits:
• conforming access connection A connection to a managed access highway that
meets current WAC and WSDOT location, spacing, and design criteria.
• grandfathered access connection Any connection to the state highway system
that was in existence and in active use on July 1, 1990, and has not had a significant
change in use.
• joint-use access connection A single connection to a managed access highway
that serves two or more properties.
• nonconforming access connection A connection to a managed access highway
that does not meet current WSDOT location, spacing, or design criteria, pending
availability of a future conforming access connection.
• variance access connection A connection to a managed access highway at
a location not normally allowed by current WSDOT criteria.
(c) managed access connection category There are four access connection permit categories
for managed access connections to state highways: Category I, Category II, Category III, and
Category IV (see Chapter 540).
annual daily traffic (ADT) The volume of traffic passing a point or segment of a highway,
in both directions, during a period of time, divided by the number of days in the period, and
factored to represent an estimate of traffic volume for an average day of the year.
average annual daily traffic (AADT) The average volume of traffic passing a point or segment
of a highway, in both directions, during a year.
average weekday vehicle trip ends (AWDVTE) The estimated total of all trips entering plus all
trips leaving the applicant’s site based on the final stage of proposed development.
contiguous parcels Two or more pieces of real property, under the same ownership, with one
or more boundaries that touch and have similarity of use.
easement A documented right, as a right of way, to use the property of another for designated
purposes.
findings and order (F&O) A legal package containing information based on the hearing record
from a limited access hearing (see Chapters 210 and 530).
findings and order (F&O) plan A limited access plan, prepared after a limited access hearing,
which is based on the hearing record.
intersection An at-grade access point connecting a state highway with a road or street duly
established as a public road or public street by the local governmental entity.
limited access Full, partial, or modified access control is planned and established for each
corridor and then acquired as the right to limit access to each individual parcel.
• planned limited access control Limited access control is planned for some time in the
future; however, no access hearing has been held.
• established limited access control An access hearing has been held and the Assistant
Secretary, Environmental and Engineering & Regional Operations Programs Director,
has adopted the findings and order, which establishes the limits and level of control.
• acquired limited access control Access rights have been purchased.
limited access highway All highways listed as “Established L/A” on the Limited Access and
Managed Access Master Plan (see below) and where the rights of direct access to or from
abutting lands have been acquired from the abutting landowners.
• full access control This most restrictive level of limited access provides access, using
interchanges, for selected public roads/streets only, and prohibits highway
intersections at grade.
• partial access control The second most restrictive level of limited access. At grade
intersections with selected public roads are allowed, and there may be some crossings
and some driveway approaches at grade. Direct commercial access is not allowed.
• modified access control The least restrictive level of limited access. Characteristics
are the same as for partial access control except that direct commercial access is
allowed.
Limited Access and Managed Access Master Plan A map of Washington State that shows
established and planned limited access highways:
www.wsdot.wa.gov/design/accessandhearings
managed access highway Any highway not listed as “Established L/A” on the Limited Access
and Managed Access Master Plan and any highway or portion of a highway designated on
the plan as “Established L/A” until such time as the limited access rights are acquired. Under
managed access legislation, the property owner’s access rights are regulated through an
access connection permitting process.
median The portion of a divided highway separating vehicular traffic traveling in opposite
directions.
median opening An opening in a continuous median for the specific purpose of allowing
vehicle movement.
MOU Memorandum of Understanding. There is one MOU (Highways Over National Forest
Lands) between the United States Forest Service (USFS) and WSDOT that requires the USFS to
obtain a road approach permit for new access to a state highway that is crossing Forest Service
land.
permit holder The abutting property owner or other legally authorized person to whom an
access connection permit is issued by the permitting authority.
permitted access connection A connection for which an access connection permit has been
issued by a permitting authority.
permitting authority The agency that has legal authority to issue managed access connection
permits. For access connections in unincorporated areas, the permitting authority is WSDOT;
for access connections within corporate limits, the permitting authority is a city or town.
right of way (R/W) A general term denoting land or interest therein, acquired for or
designated for transportation purposes. More specifically, lands that have been dedicated for
public transportation purposes or land in which WSDOT, a county, or a municipality owns the
fee simple title, has an easement devoted to or required for use as a public road/street and
appurtenant facilities, or has established ownership by prescriptive right.
right of way and limited access plan (R/W and L/A plan) A right of way plan that also shows
limited access control details.
road approach A road or driveway built to provide private access to or from the state highway
system.
shoulder The portion of the highway contiguous with the traveled lanes for the
accommodation of stopped vehicles for emergency use and, where allowed, for bicycles
(see Chapter 530).
state highway system All roads, streets, and highways designated as state routes in
compliance with RCW 47.17.
520.04 Vocabulary
The entries shown in Exhibit 520-1 are examples of suitable wording for the distinctly different
types of access control in Chapters 530 and 540.
These entries demonstrate the difference in terminology between limited access and managed
access in the applicable WACs. For instance, there is nothing about permit, connection, category,
or class in the limited access vocabulary and, likewise, nothing about approach or type in the
managed access vocabulary.
Also note that Chapter 1340 uses road approach, access, and driveway in a generic way,
unrelated to WAC legal terminology, and makes no distinction related to access control.
Access point (freeway ramp or other access break) Access point (public or not)
Approach (street, road, driveway) • Public access point
• Road approach (street, road, driveway) • Access connection (not public)
• Driveway approach (not street or road)
(Level of) limited access (highway) Managed access highway class
• Full/partial/modified control limited • Class (1-5) managed access highway
access highway
Terms Not Used in Chapter 530 Terms Not Used in Chapter 540
category type
connection approach
permit or permitted
530.01 General
Limited access control is established to preserve the safety performance and efficiency of
specific highways for all modes and to preserve the public investment. Limited access control is
achieved by acquiring access rights from abutting property owners and by selectively limiting
approaches to a highway, considering all modes in the control and treatment of access. (For an
overview of access control and the references list and definitions of terminology for this
chapter, see Chapter 520, Access Control.)
Requirements for the establishment of limited access highways are set forth in the Revised Code
of Washington (RCW) 47.52. The type of access control applied to a location is considered a
design control (see Chapter 1103), and is determined during planning, scoping, or the early
stages of design in conformance with this chapter.
Highways controlled by acquiring abutting property owners’ access rights are termed limited
access highways and are further distinguished as having full, partial, or modified control. The
number of access points per mile, the spacing of interchanges or intersections, and the location
of frontage roads or local road/street/trail approaches are determined by the:
Functional classification and importance of the highway
Context-based modal priorities and relevant considerations
Character of the traffic
Current adjacent land use and future planned changes to land use
Environment and aesthetics
Highway design, operation, safety and connectivity for all modes
Economic considerations involved
The Federal Highway Administration (FHWA) has jurisdiction on the Interstate System. The
Washington State Department of Transportation (WSDOT) has full jurisdiction on all other
limited access highways, whether they are inside or outside incorporated city limits.
WSDOT maintains a record of the status of limited access control, by state route number and
milepost, in the Access Control Tracking System Limited Access and Managed Access Master
Plan database (Access Master Plan). See the Access and Hearings website:
http://www.wsdot.wa.gov/Design/accessandhearings/
530.02(1) Evaluation
The benefits of maintaining or acquiring full, partial, or modified control are to be evaluated
during project development if the route is shown in the Access Control Tracking System Limited
Access and Managed Access Master Plan database as either “established” or “planned” for
limited access. It is generally known that full limited access control applies to interstates and
freeways. However, state highways that do not fall under full access control may have more
flexibility in the type of control applied (whether limited or managed control). These highways
can benefit by having access control evaluations conducted early in planning and project
development.
The cost of acquiring limited access is evaluated to determine whether those costs will be
included in the project. The evaluation includes the societal costs of crashes, current and future
land use development, and the improved level of service for motor vehicle traffic of limited
access highways. Use the Basis of Design documentation tool to summarize key results of the
evaluation process, considering connectivity, mobility, safety and accessibility for all modes.
(See chapters in the 1100 series for more information on using the Basis of Design tool.)
530.02(2) Process
All Washington State highways are managed access highways (see Chapter 540), except where
limited access rights have been acquired. The right of way and limited access plans for routes
show the acquired limited access boundaries. This is further represented in the Access Control
Tracking System, a database that identifies the status and type of access control for all state
highways. The database lists the specific types of limited access control (full, partial, or
modified) and identifies whether the control is planned, established, or acquired for a specific
route segment. If limited access has not been acquired, the database reports the type of
managed access classification that currently applies.
regarding hearings, and Chapter 510, Right of Way, for the phases of appraisal and
acquisition.)
a. Phase 1
The region develops a limited access report and a limited access report plan for department
approval and presentation to local officials. The plan notes the level of limited access
proposed to be established.
b. Phase 2
The region develops a limited access hearing plan for Director & State Design Engineer,
Development Division (or designee), approval and for presentation at the hearing.
c. Phase 3
After the hearing, the region develops the findings and order and revises the limited access
hearing plan to become the findings and order plan (see Chapter 210). The findings and
order is processed and sent to the HQ Access and Hearings Section for review and approval.
The Assistant Secretary, Regions and Mega Programs/Chief Engineer, adopts the findings
and order and thus establishes the limits and level of limited access control to be acquired.
d. Phase 4
The findings and order plan is now revised by the HQ Right of Way Plans Section for
approval by the Director & State Design Engineer, Development Division (or designee), as a
Phase 4 final right of way and limited access plan.
3. Real Estate Services acquires limited access rights from individual property owners based on
final design decisions and updates the right of way and limited access plans and the
property deed.
4. These highways or portions thereof are now limited access highways and no longer fall
under the managed access program.
Traffic data, together with counts of existing traffic available from state or local records, is
normally adequate for motor vehicle analysis. Special counts of existing traffic are obtained
only if circumstances indicate that the available data is inadequate or outdated. Data for
pedestrian and bicyclist traffic may rely on demographics, land-use context, and an analysis
of the active transportation network where volume information is not available.
The limited access report plan shows the effects of the proposed highway on the street and
road system, transit service and pedestrian/bicyclist network by delineating the points of
public access. (See the Plans Preparation Manual for a list of the minimum details to be
shown on the plan and for a sample plan.)
7. Notifications and reviews. Upon receipt of the Phase 1 approval (see Exhibit 510-1) from the
Director & State Design Engineer, Development Division, the region publishes the necessary
copies, submits the limited access report to the county or city officials for review and
approval, and meets with all involved local governmental agencies to discuss the report.
Providing a form letter with a signature block for the local agency to use to indicate its
approval of the limited access report can help expedite the review and approval process.
The region reviews any requests for modification and submits recommendations, with copies
of any correspondence or related minutes, to the HQ Access and Hearings Section.
When the plan review is completed by Headquarters, the access hearing plan is placed before
the Director & State Design Engineer, Development Division, for approval of Phase 2 authority
(see Exhibit 510-1).
530.02(5) Documentation
Documentation for the establishment of limited access control is in Chapter 210.
530.03(1) Introduction
Full control limited access highways allow access only through interchanges at selected public
roads/streets, rest areas, viewpoints, or weigh stations, and by prohibiting at-grade crossings
and approaches.
At times, on state highways (except interstate) where full access control has been established,
staged acquisition of limited access may be used, subject to the approval of an access design
analysis, with initial acquisition as partial or modified control and with ultimate acquisition of
full control planned on the highway. When there is no feasible alternative within a reasonable
cost, the decision to defer acquisition of limited access control must be documented and is
subject to the approval of an access design analysis.
530.03(2) Application
Terminate full control limited access sections at apparent logical points of design change. The
following guidelines are to be used for the application of full control on limited access highways.
530.03(2)(a) Interstate
Documentation assessing the evaluation of full control is required for principal arterial highways
requiring four or more through traffic lanes within a 20-year design period unless approved for
partial or modified control on existing highways.
530.03(2)(c) Minor Arterial and Collector
Minor arterial and collector highways will not normally be considered for development to full
control. However, short sections of full control to preserve the operational and safety
performance of all modes may be appropriate in some situations.
530.03(3)(a) Ramps
At-grade intersections and approaches are prohibited within the full length of any interchange
ramp. The ramp is considered to terminate at its intersection with the local road or street.
530.03(3)(b) Frontage Roads
Direct access from the highway to a local service or frontage road is allowed only via the
interchange crossroad (see Exhibits 530-1a, 1b, 1c, and 1f).
530.03(3)(c) Interchange Crossroads
In both urban and rural areas, full control limited access must be established and then acquired
along the crossroad at an interchange for a minimum distance of 300 feet. This distance is
measured from the centerline of the intersection of the crossroad and ramp terminal unless
noted otherwise in the conditions below. Control designs in all crossroad contexts should
address and incorporate connectivity for shared-use paths, trails and sidewalks in and beyond
the control area.
If a frontage road or local road is located at or within 350 feet of a ramp terminal, limited access
will be established and then acquired up to the intersection, then along the crossroad and for an
additional minimum distance of 130 feet in all directions from the centerline of the intersection
of the crossroad and the frontage or local road, or measured from the outside edge of the
outermost circulating roadway for roundabouts (see Exhibits 530-1a, 1b, 1c, and 1f).
For interchanges incorporating partial cloverleaf or buttonhook ramps (see Exhibit 530-1b),
limited access is required for all portions of the crossroad and frontage roads between the ramp
terminals and for a distance of 300 feet beyond the ramp terminals. If an at-grade intersection
for a local road or street is served directly opposite the ramp terminals, limited access will be
extended for a minimum of 300 feet along that leg of the intersection.
When the intersection in question is a roundabout, see Exhibit 530-1c. This shows extension of
full control along the crossroad to be 300 feet, measured from the center of the roundabout for
an intersection with a ramp terminal.
Exhibit 530-1d shows the terminus of transition taper and that full control limited access is
extended a minimum distance of 300 feet beyond the end of the farthest taper.
For a single point urban interchange (SPUI) with a right- or left-turn “ramp branch” separated by
islands, limited access control is established and acquired for a minimum distance of 300 feet
from the intersection of the centerline of the ramp branch with the centerline of the nearest
directional roadway (see Exhibit 530-1e.)
For a diverging diamond interchange, limited access control is established and acquired for a
minimum distance of 300 feet from the end of the splitter island nose (see Exhibit 530-1f).
Not all interchange configurations match with the basic illustrations in this chapter. Consult with
the HQ Access and Hearings Section for confirmation of limited access boundary requirements
for non-traditional interchange configurations.
Provide full control for a minimum of 300 feet from the centerline of the ramp or terminus of a
transition taper (see Exhibits 530-1a through 530-1f). The intent is to ensure approaches are far
enough away from a frontage road intersection to provide efficient intersection operation.
If the economic considerations to implement full control for the entire 300 feet are excessive,
then provide full control for at least the first 130 feet; partial or modified control may be
provided for the remainder, for a total minimum distance of 300 feet of limited access. Full
limited access should be extended as far as possible before any partial or modified access is
implemented. Contact the HQ Access and Hearings Section when considering this option.
An approved access design analysis is required if the limited access control falls short of 300 feet
or for any approach that has been allowed to remain within the first 130 feet.
Connecting utility lines are allowed along the outer right of way line between intermittent
frontage roads. (See the Utilities Accommodation Policy regarding the location of and access to
utilities.)
530.03(4)(b) Bus Stops
Common carrier or school bus stops are not allowed, except at:
Railroad crossings (see Chapter 1350).
Locations provided by the state on the interchanges (such as flyer stops).
In exceptional cases, along the main roadway where pedestrian separation is available.
530.03(4)(c) Mailboxes
Mailboxes are not allowed on full control limited access highways. Mail delivery will be from
frontage roads or other adjacent local roads.
Paths and trails, and access to and from, within a limited access highway are best planned and
designed with the local agency’s participation. Pedestrians and bicyclists are allowed, consistent
with “Rules of the Road” (RCW 46.61), within the limits of full control limited access highways.
Where existing or future planned paths are allowed they must be documented on the right of
way and limited access plan. The plan shows the location of the existing or proposed path and
where the path crosses limited access and provides movement notes (see 530.10(1)). See
Chapter 1515 for shared-use path design guidance.
530.04(1) Introduction
Partial control may be established, when justified, on any highway except interstate. Partial
control provides a considerable level of protection from motor vehicle traffic interference and
protects the highway from future strip-type development while maintaining and improving
appropriate active transportation network connections.
Upon acquisition of partial control limited access rights, the number, type, and use of access
approaches of abutting property are frozen. The abutting property access rights and type of use
are recorded on the property deed. The rights and use may not be altered by the abutting
property owner, the local jurisdiction, or the region. This authority resides with the Director &
State Design Engineer, Development Division (see 530.10).
530.04(2) Application
Partial control will not normally be used in urban areas, urbanizing area, suburban area, rural
town centers or inside corporate limits on existing principal arterial highways where motor
vehicle traffic volumes are less than 700 design hourly volume (DHV).
Partial control is considered when the estimated motor vehicle traffic volumes exceed 3,000
average daily traffic (ADT) within a 20-year design period on principal arterial highways requiring
two through motor vehicle traffic lanes. For multilane principal arterial highways, see
530.03(2)(b).
530.04(2)(b) Minor Arterial
The minimum route length is: urban, 2 miles; rural, 5 miles; and combination urban and rural, 3
miles.
Other rural minor arterial highways with only two motor vehicle lanes may be considered for
partial control if any of the following conditions applies:
The partial control can be acquired at a reasonable cost.
The route connects two highways of a higher functional classification.
The highway traverses publicly owned lands where partial control is desirable.
530.04(2)(c) Collector: New Alignment
Partial control is considered on collector highways in new locations requiring four or more
through motor vehicle traffic lanes in a 20-year design period
Existing collector highways will normally be considered for partial control limited access only
when all of the following conditions apply:
The highway serves an area that is not directly served by a higher functional
classification of highway.
Existing or planned development will result in motor vehicle traffic volumes
significantly higher than what is required for partial control on minor arterials.
Partial control can be established without a major impact on development of abutting
properties within the constraints of established zoning at the time the partial control is
proposed.
Where an interchange occurs on a partial control limited access highway, full control applies at
the interchange and interchange ramps. Refer to 530.03(3) and see Exhibits 530-1a, 1b, 1c, and
1f for required minimum lengths of access control along the crossroad. For these and other
interchange configurations not shown, consult with the HQ Access and Hearings Section for
support developing limits of access control. (See Chapter 1360 for guidance on interchange
spacing.) Where appropriate, address and incorporate connectivity for shared-use paths, trails
and sidewalks in and beyond the control area.
530.04(3)(b) Intersections
If another frontage or local road is located at or within 350 feet of the at-grade intersection,
limited access will be established and then acquired along the crossroad, between the
intersections, and:
For an additional minimum distance of 130 feet in all directions from the centerline of
the intersection of the frontage or local road (see Exhibit 530-2a).
In the case of a roundabout, for an additional minimum distance of 300 feet along the
crossroad, measured from the center of the roundabout (as shown in Exhibit 530-2b).
On multilane highways, measurements will be made from the centerline of the nearest
directional roadway (see Exhibit 530-2a).
An approved access design analysis is required if the limited access control falls short of 300 feet
or for any access that has been allowed to remain within the first 130 feet.
At-grade intersections with public roads are limited to the number allowed for the functional
classification of highway involved, as follows:
530.04(3)(b)(1) Principal Arterial
If the ADT of the crossroad is less than 2,000, 1-mile spacing (minimum), centerline to
centerline. If over 2,000 ADT within 20 years, plan for grade separation.
If the ADT of the crossroad is less than 2,000, ½-mile spacing (minimum), centerline to
centerline. If over 2,000 ADT within 20 years, plan for grade separation.
530.04(3)(b)(3) Collector
Road (or street) plus property approaches, not more than six per side per mile.
With approval from the Director & State Design Engineer, Development Division, shorter
intervals may be used where topography or other conditions (such as parcel sizes in some
cases) restrict the design. Where intersecting roads are spaced farther apart than one per
mile, median crossings may be considered for U-turns, in accordance with Chapter 1310.
Keep U-turns to a minimum, consistent with requirements for operation and maintenance
of the highway.
from the intersection. Ensure a private approach directly opposite a tee intersection cannot
be mistaken for a continuation or part of the public traveled way.
Partial control limited access highways allow at-grade intersections with selected public roads,
trails/shared-use paths, and private approaches using Type A, B, C, and F approaches. (See
Chapter 520 for the definitions of approach types.)
Type D, commercial approaches, are not allowed direct access to partial control limited access
highways. Commercial access is allowed only by way of other public roads.
The type of approach provided for each parcel is based on current and potential land use and on
an evaluation that assesses connectivity for all modes. (See 530.05(4) for a list of evaluation
criteria.)
530.04(4)(b) Design Considerations
The following considerations are used to determine the number and location of access
approaches on partial control limited access highways.
1. Access approaches must be held to a minimum. The number is limited as follows:
Principal arterial: two per side per mile
Minor arterial: four per side per mile
Collector: six per side per mile, including at-grade intersections
2. Approaches in excess of the number listed above may be allowed as staged construction
(until full buildout is complete) if approved by the Director & State Design Engineer,
Development Division.
3. Approaches are not allowed for parcels that have reasonable access to other public roads
unless a parcel has extensive highway frontage.
4. Relocate or close approaches in areas where sight limitations create undue hazards.
5. Allow only one approach for each parcel, except for very large ownerships, or where
terrain features do not allow the property to be served by a single approach. This includes
contiguous parcels under a single ownership.
7. The approved design is to provide for future development of frontage roads that will
eliminate an excessive number of approaches.
Connecting utility lines are allowed along the outer right of way line between intermittent
frontage roads. (See the Utilities Accommodation Policy regarding the location of and access to
utilities.)
Bus stops for both common carriers and school buses are not allowed on either two-lane or
four-lane highways except:
At railroad crossings (see Chapter 1350).
At locations of intersections with necessary pullouts to be constructed by the state.
Where shoulder widening has been provided for mail delivery service.
For a designated school bus loading zone on or adjacent to the traveled lane, that has
been approved by WSDOT.
Buses are not allowed to stop in the traveled lanes blocking at-grade intersections or private
approaches to load or unload passengers.
School bus loading zones on partial control limited access highways must be posted with school
bus loading zone signs, in accordance with the latest edition of the Manual on Uniform Traffic
Control Devices (MUTCD).
530.04(5)(c) Mailboxes
Locate mailboxes on frontage roads or at intersections, with the following exceptions for
properties that are served by Type A or B approaches:
Locate mailboxes on a four-lane highway only on the side of the highway on which the
deeded approach is provided.
Locate mailboxes on a two-lane highway on the side of the highway that is on the right
in the direction of the mail delivery.
Wherever mailboxes are allowed on a partial control limited access highway, provide mailbox
turnouts to allow mail delivery vehicles to stop clear of the through traffic lanes.
(See Chapter 1600 for additional information concerning mailbox locations and turnouts.)
On two-lane highways not less than 100 feet from a school bus loading zone (pullout)
adjacent to the traveled lane, if school district and WSDOT personnel determine that
the bus stopping in the traveled lane is hazardous.
On two-lane highways where the school bus is stopped on the traveled lane to load or
unload passengers and the required sign and signal lights are displayed.
On partial control limited access highways, pedestrian and bicyclist traffic is allowed, consistent
with “Rules of the Road” (RCW 46.61), except where unusual safety conditions support
prohibition. Information pertaining to such prohibitions is available from the WSDOT website:
http://wsdot.wa.gov/bike/closed.htm
Paths and trails, and access to and from, within a partial control limited access highway are best
planned and designed with the local agency’s participation. Where existing and future planned
paths are allowed, they must be documented on the right of way and limited access plan. The
plan shows the location of the existing or proposed path and where the path crosses limited
access, and it provides movement notes (see 530.10(1)), with the intention of maintaining and
improving active transportation connectivity.
530.05(1) Introduction
Modified control is intended to prevent further deterioration in the safety and motor vehicle
operational characteristics of existing highways by limiting the number and location of access
points.
Upon acquisition of modified control limited access, the number, type, and use of access
approaches of abutting property are frozen. The abutting property access rights and type of use
are recorded on the property deed. The rights and use may not be altered by the abutting
property owner, the local jurisdiction, or the region. This authority resides with the Director &
State Design Engineer, Development Division (see 530.10).
530.05(2) Application
In general, modified control is applied where some level of control is desired, but existing and
potential commercial development precludes the implementation of full or partial control.
Modified control may be established and acquired on existing highways other than main line
interstate. Priority is given to highway segments where one or more of the following conditions
applies:
Commercial development potential is high, but most of the adjoining property remains
undeveloped.
There is a reasonable expectation that the adjoining property will be redeveloped to a
more intensive land use, resulting in greater motor vehicle traffic congestion and
increased presence of people walking, bicycling, and/or accessing transit service.
At interchange areas if full or partial access cannot be provided as described in
530.03(3)(d).
Selection of highways on which modified control may be applied is based on an evaluation that
includes the following contextual factors for all modes:
The current form of managed access control
Traffic volumes
Level of service, or other selected mobility performance metric
Selected safety performance
Functional class
Route continuity
Mix of residential, destination and employment densities
Operational considerations related to achieving the selected motor vehicle target
speed
Operational considerations related to transportation efficiency for people utilizing
active transportation
Local land use planning
Current and potential land use
Predicted growth rate
Economic analysis
530.05(2)(c) Exceptions
530.05(3) Intersections
At an intersection on a modified control limited access highway, access control will be
established and acquired along the crossroad for a minimum distance of 130 feet:
Measured from the centerline of a two-lane highway (see Exhibit 530-3b).
Measured from the centerline of the nearest directional roadway of a four-lane
highway (see Exhibit 530-3b).
Measured from the outside edge of the circulating roadway of a roundabout (see
Exhibit 530-3a).
Approaches are allowed within this area only when there is no reasonable alternative. An
approved access design analysis is required for any access that has been allowed to remain
within the first 130 feet. Where appropriate, address and incorporate connectivity for shared-
use paths, trails and sidewalks in and beyond the control area.
Modified control limited access highways allow at-grade intersections with selected public
roads, shared-use paths/trails, and with private approaches using Type A, B, C, and D
approaches. (See Chapter 520 for definitions of the approach types.)
The type of approach provided for each parcel is based on present and potential land use and an
evaluation of the following criteria:
Local comprehensive plans, zoning, and land use ordinances
Property covenants and agreements
City or county ordinances
The highest and best use of the property
The highest and best use of adjoining lands
A change in use by merger of adjoining ownerships
All other factors bearing upon proper land use of the parcel
The following items are used to determine the number and location of approaches:
1. Parcels that have access to another public road or street are not normally allowed direct
access to the highway.
2. Meets sight distance criteria (see Chapter 1340).
3. Hold the number of access approaches to a minimum. Access approaches are limited to one
approach for each parcel of land or where adjoining parcels are under one contiguous
ownership.
4. Encourage joint use of access approaches where similar use of land and topography allows.
5. Additional approaches may be allowed for future development consistent with local zoning.
Once limited access has been acquired, this will require a value determination process (see
530.10).
Connecting utility lines are allowed along the outer right of way line between intermittent
frontage roads. (See the Utilities Accommodation Policy regarding location of and access to
utilities.)
530.05(5)(c) Mailboxes
Where mailboxes are allowed, a mailbox turnout is recommended to allow mail delivery vehicles
to stop clear of the through traffic lanes. (See Chapter 1600 for additional information
concerning mailbox locations and turnouts.)
Pedestrians and bicyclists are allowed, consistent with “Rules of the Road” (RCW 46.61), on
modified control limited access highways except where unusual safety considerations support
prohibition. Information pertaining to such prohibitions is available from the WSDOT website:
http://wsdot.wa.gov/bike/closed.htm
Paths and trails, and access to and from, within a modified control limited access highway are
best planned and designed with the local agency’s participation. Where existing or future
planned paths are allowed, they must be documented in the right of way and limited access
plan. The plan shows the location of the existing or proposed path and where the path crosses
limited access, and it provides movement notes (see 530.10(1)) with the intention of
maintaining and improving active transportation connectivity.
530.06(1) General
Access approaches may be allowed on limited access highways, consistent with the
requirements outlined in 530.03, 530.04, and 530.05.
The widths for the approach types are negotiated, and only the negotiated widths are shown on
the right of way and limited access plan. (See Chapter 520 for definitions of the approach types.)
530.07(1) General
Frontage roads are provided in conjunction with limited access highways to:
Limit access to the main line.
Provide access to abutting land ownerships.
Restore the continuity of the local street or roadway system and active transportation
network.
Refer to Chapter 1210 for frontage road general policy and Chapter 300 for required
documentation.
By agreement under which the state is reimbursed for all costs involved, frontage roads that are
not the responsibility of the state may be built by the state upon the request of a local political
subdivision, a private agency, or an individual.
530.07(3) Cul-de-sacs
For a frontage road or local street bearing substantial traffic that is terminated or closed at one
end, provide a cul-de-sac or other street or roadway consistent with local policy or practice, that
is sufficient to allow vehicles to turn around without encroachment on private property.
Consider and address continued connectivity and provision of alternate routes for pedestrians
and bicyclists.
530.08 Turnbacks
When WSDOT transfers jurisdiction of operating right of way to a city, town, or county, a
turnback agreement is required. (See the Agreements Manual for turnback procedures.)
Locate the turnback limits at points of logical termination. This will allow WSDOT to retain an
adequate amount of right of way for maintenance of the highway and for other operational
functions.
In areas where limited access rights have been acquired from the abutting property owners, the
limited access rights will continue to be required for highway purposes; therefore, the limited
access rights will not be included as part of a turnback agreement.
When a signalized intersection is in the area of a turnback, locate the turnback limit outside the
detector loops if WSDOT is continuing the ownership, operation, and maintenance of the signal
system. For a roundabout, locate the turnback limit at the back of the raised approach splitter
island if WSDOT is continuing the ownership, operation, and maintenance of the roundabout.
530.09(1) General
A limited access highway and a railroad are considered adjacent when they have a common
right of way border with no other property separating them. The allowed approaches apply only
to adjacent railroad property that is directly used for current railroad operation.
530.09(2) Requirements
It is in the public’s interest to provide access to the railroad right of way, from limited access
highways, for maintenance of the railroad and the utilities located on the railroad right of way
where other access is not feasible. This applies to both new highways and to existing highways
where limited access has been acquired.
Direct access is allowed where local roads are infrequent or there are few highway-railroad
crossings from which trail-type access for maintenance purposes is feasible, and where unique
topography or other unusual conditions lead to its use.
To provide direct approaches for access to railroad right of way, all of the following conditions
must be met:
A maximum of one approach is allowed for every 2 miles of highway.
The approach must not adversely affect the design, construction, stability, traffic
safety, or operation of the highway.
Except where the railroad is located in the median area, the approach is to be
accomplished in a legal manner by right turns only, to and from the roadway nearest
the railroad. Median crossing is not allowed.
The approach is secured by a locked gate under arrangements satisfactory to the
department. (See the Definitions section in Chapter 520 for Approach Type C, and
Chapter 550.)
The parking of any vehicles or railroad equipment is prohibited within limited access
highway right of way.
A special emergency maintenance permit must be obtained for periods of intensive
railroad maintenance.
The approach must be closed if the railroad operation ceases.
Approaches are limited to use by the railroad company unless specific provisions for
other use are shown on the right of way and limited access plan and included in the
right of way negotiations.
530.09(3) Restrictions
Direct access to a railroad from the highway is considered unnecessary and is not allowed
where:
530.10(1) General
When non-highway purpose activities are proposed that involve either crossing limited access
boundaries or entering into roadside areas from within limited access facilities, a formal request
shall be approved prior to the activity or use. The request will be either an access break or an
inner corridor access.
An access break is needed when the limited access boundary is to be crossed. This refers to any
point from inside or outside the state limited access right of way limited access hachures that
crosses over, under, or physically through the plane of the limited access.
An inner corridor access is needed when entry into roadside areas inside of the limited access
corridor is to be made from within the limited access boundary. Inner corridor access may be
from a mainline, a ramp, or from a local road or street that is also within limited access.
Evaluate the following factors concerning a potential access break or inner corridor access:
Crash potential for all modes, including how crash types and contributing factors and
how operational considerations related to the access break would change
Level of access control (full, partial, or modified)
Existing and planned land use changes
Functional classification
Land use and zoning
Environment impacts/mitigation
Determination from a Corridor Sketch, Basis of Design and/or CMAR
Regional staff or Program staff work with the requesting party to compile and submit access
break and inner corridor access requests to the HQ Access and Hearings Section. The request
package will contain the completed access request checklist and all supporting documents and
will be submitted electronically using instructions located on the Access and Hearings Section
website: www.wsdot.wa.gov/design/accessandhearings
530.10(1)(a) Approvals
Access breaks (either temporary or permanent) and inner corridor access for all limited access
state highways require approval prior to implementation.
For permanent access breaks or inner corridor access approvals involving existing property
rights, the right of way and limited access plan must be revised and deeds may need to be
rewritten.
On non-interstate limited access routes, WSDOT HQ approves access breaks and inner corridor
access.
On interstate routes, 23 CFR 710.403 requires prior approval from FHWA. Note that any changes
proposed on Interstate limited access facilities must include environmental documentation in
the request, as required by FHWA. Contact the HQ Access and Hearings Section for assistance.
530.10(2)(a) Requirements
Plan revisions that provide for additional access to abutting properties after WSDOT has
purchased the access rights are discouraged. However, these revisions may be considered if the
following can be established:
There are no other reasonable alternatives.
The efficiency and safety of the highway will not be adversely impacted.
The existing situation causes extreme hardship on the owner(s).
The revision is consistent with the limited access highway requirements.
530.10(2)(b) Procedures
The region initiates a preliminary engineering review of the requested modification to or break
in limited access and contacts the HQ Access and Hearings Section to determine whether
conceptual approval can be granted for the request. If conceptual approval can be granted,
then:
The region initiates an engineering review of the requested modification.
The region prepares and submits to the HQ Right of Way Plans Section a preliminary
right of way and limited access plan revision, together with a recommendation for
Headquarters approval. When federal-aid funds are involved in any phase of the
project, the proposed modification will be sent to FHWA for review and approval.
The recommendation will include an item-by-item analysis of the factors listed in
530.10(1) and 530.10(2)(a).
Upon preliminary approval, region Real Estate Services prepares an appraisal for the value of the
access change using a before and after appraisal.
The appraisal follows the requirements set forth in the Right of Way Manual.
The appraisal package is sent to HQ Real Estate Services for review and approval.
If federal-aid funds were involved in purchasing access control, HQ Real Estate Services
will send a copy of the appraisal package to FHWA for review and approval.
530.10(2)(d) Final Processing
Region Real Estate Services informs the requester of the approved appraised value for
the change.
If the requester is still interested, the region prepares a “Surplus Disposal Package” for
HQ Real Estate Services’ review and approval.
At the same time, the preliminary right of way and limited access plan revision
previously transmitted is processed for approval.
After the department collects the payment from the requester, the region issues a
permit for the construction, if required.
If an existing approach is being surrendered, region Real Estate Services obtains a
conveyance from the property owner.
HQ Real Estate Services prepares and processes a deed granting the change to the
access rights.
The region submits an intersection plan for approval (see Chapter 1310) and a right of
way and limited access plan revision request (see the Plans Preparation Manual). This
plan includes the limited access design requirements for all modes along the proposed
public at-grade intersection.
The Director & State Design Engineer, Development Division, approves the intersection
plan.
The Assistant Secretary, Regions and Mega Programs/Chief Engineer (or designee),
approves the access revision.
The region submits the construction agreement to the Director & State Design
Engineer, Development Division (see the Agreements Manual).
The Assistant Secretary, Regions and Mega Programs/Chief Engineer (or designee),
approves the construction agreement.
530.11 Documentation
Refer to Chapters 210, 300, and 550 for design documentation requirements.
Exhibit 530-1d Full Access Control Limits: Ramp Terminal with Transition Taper
Exhibit 530-1e Full Access Control Limits: Single Point Urban Interchange
540.01 General
Access management is the systematic regulation of the location, spacing, design, and operation
of driveway, city street, and county road connections to state highways. This chapter describes
the access management process for granting permission to connect to managed access
highways within cities and unincorporated areas. For an overview of access control, references
to related state laws and codes, and definitions of terminology for this chapter, see Chapter 520,
Access Control.
In Washington State, managed access highways include all state highways that are not limited
access highways. State highways that are planned for or established as limited access, are
treated as managed access highways until the limited access rights are acquired.
The Access Control Tracking System Limited Access and Managed Access Master Plan (Access
Master Plan) identifies not only the limits of limited access control, but also managed access
control segments. The current managed access classification is based on access connection
densities, distance between access connections, spacing of intersections, and context (see
Washington Administrative Code (WAC) 468-52-040). The existing access classification is
periodically updated by Headquarters (HQ) with region input to reflect changes on a corridor
segment. Conditions may have changed since the Access Master Plan was envisioned or the last
managed access classification update. On non-freeways it is important to consider the current
classification and any classifications previously planned, and determine the access design
control most appropriate for the agreed context (see Chapters 1102 and 1103 for context and
design control guidance, respectively). The Access Master Plan database is available at:
www.wsdot.wa.gov/design/accessandhearings
Access to managed access highways is regulated by the governmental entity with jurisdiction
over a highway’s roadsides. Access connection permits are issued on managed access highways.
The Washington State Department of Transportation (WSDOT) has access connection permitting
authority over all state highways outside incorporated towns and cities. Incorporated towns and
cities have access connection permitting authority for city streets that are part of state
highways, as specified in Revised Code of Washington (RCW) 47.24.020. When any project is
developed on a state highway outside an incorporated city or town, state law requires that
existing access connections be evaluated to determine whether they are consistent with all
current department spacing, location, and design standards (see 540.03).
Review all connections and verify whether they are in the Roadway Access Management Permit
System (RAMPS) database. Contact the region Development Services Office or the HQ Access
and Hearings Section for permission to log on to the link through this page:
www.wsdot.wa.gov/design/accessandhearings
Where current department standards cannot be met while providing the same general
functionality, classify the connection as nonconforming and process the appropriate
documentation as discussed below. This documentation is part of the permit process.
The classification system for state managed access highways consists of five classes. The classes
are arranged from the most restrictive, Class 1, to the least restrictive, Class 5. In general, most
state highways outside the incorporated limits of a city or town have been designated as Class 1
or Class 2, with only the most urban and lowest-speed state highways within an incorporated
town or city designated as Class 5. Exhibit 540-1 shows the five classes of highways, with a brief
description of each class. WSDOT keeps a record of the assigned managed access classifications,
by state route and milepost, in the Access Control Tracking System database:
www.wsdot.wa.gov/design/accessandhearings
One of the goals of state law is to restrict or keep access connections to a minimum in order to
help preserve the safety, operation, and functional integrity of the state highway. On Class 1
highways, mobility is the primary function, while on Class 5 highways, access needs have priority
over mobility needs. Class 2 highways also favor mobility, while Class 3 and Class 4 highways
generally achieve a balance between mobility and access.
The most notable distinction between the five highway classes is the minimum spacing
requirements of access connections. Exhibit 540-1 shows the minimum distances between
access points on the same side of the highway. Exhibit 540-2 applies to the minimum clearance
from a public road or street.
In all five highway classes, access connections are to be located and designed to minimize
interference with transit facilities and high-occupancy vehicle (HOV) facilities on state highways
where such facilities exist or are proposed in state, regional, metropolitan, or local
transportation plans. In these cases, if reasonable access is available to the local road/street
system, access is to be provided to the local road/street system rather than directly to the state
highway. Following are the functional characteristics and the legal requirements for each class.
540.03(1) Class 1
540.03(1)(a) Functional Characteristics
Class 1 highways provide for high-speed and/or high-volume traffic movements for interstate,
interregional, and intercity (and some intracity) travel needs. Service to abutting land is
subordinate to providing service to major traffic movements.
1. It is the intent that Class 1 highways be designed to have a posted speed limit of 50 to
65 mph. Intersecting streets, roads, and highways are planned with a minimum spacing
of 1 mile. Spacing of ½ mile may be allowed, but only when no reasonable alternative access
exists.
2. Private access connections to the state highway are not allowed except where the property
has no other reasonable access to the local road/street system. When a private access
connection must be provided, the following conditions apply:
The access connection continues until such time other reasonable access to a
highway with a less restrictive access control class or access to the local road/street
system becomes available and is allowed.
The minimum distance to another (public or private) access point is 1,320 feet
along the same side of the highway. Nonconforming access connection permits
may be issued to provide access connections to parcels whose highway frontage,
topography, or location otherwise precludes issuance of a conforming access
connection permit; however, variance permits are not allowed.
No more than one access connection may be provided to an individual parcel or to
contiguous parcels under the same ownership.
All private access connections are for right turns only on multilane facilities. Where
special conditions apply, justify the exception in a traffic analysis in the access
connection permit application that is signed and sealed by a qualified professional
engineer who is registered in accordance with RCW 18.43.
Additional access connections to the state highway are not allowed for newly
created parcels resulting from property divisions. All access for these parcels must
be provided by an internal road/street network. Access to the state highway will be
at existing permitted locations or revised locations.
540.03(2) Class 2
540.03(2)(a) Functional Characteristics
1. It is the intent that Class 2 highways be designed to have a posted speed limit of 35 to
50 mph in urbanized areas and 45 to 55 mph in rural areas. Intersecting streets, roads,
and highways are planned with a minimum spacing of ½ mile. Intersection spacing of less
than ½-mile may be allowed, but only when no reasonable alternative access exists.
In urban areas and developing areas where higher volumes are present or growth that will
require a change to intersection control is expected in the foreseeable future, it is
imperative that the location of any public access point be planned carefully to ensure
adequate traffic progression. The addition of all new public or private access points that
might require signalization or other form of intersection control will require an engineering
analysis that is signed and sealed by a qualified professional engineer who is registered in
accordance with RCW 18.43.
2. Private access connections to the state highway system are allowed only where the property
has no other reasonable access to the local road/street system or where access to the local
road/street system will cause unacceptable traffic operational conditions or safety concerns
on that system. When a private access connection must be provided, the following
conditions apply:
The access connection continues until such time other reasonable access to a
highway with a less restrictive access control class or acceptable access to the local
road/street system becomes available and is allowed.
The minimum distance to another (public or private) access point is 660 feet on the
same side of the highway. Nonconforming access connection permits may be
issued to provide access to parcels whose highway frontage, topography, or
location precludes issuance of a conforming access connection permit.
Variance permits may be allowed if there are special conditions and the exception
can be justified to the satisfaction of the department by a traffic analysis in the
540.03(3) Class 3
540.03(3)(a) Functional Characteristics
Class 3 highways provide for moderate travel speeds depending on context, and moderate
traffic volumes for medium and short travel distances for intercity, intracity, and
intercommunity travel needs. There is a reasonable balance between access and mobility needs
for highways in this class. This class is to be used primarily where the existing level of
development of the adjoining land is less intensive than maximum buildout and where the
probability of significant land use change and increased traffic demand is high.
1. It is the intent that Class 3 highways be designed to have a posted speed limit of 30 to 40
mph in urbanized areas and 45 to 55 mph in rural areas. In rural areas, intersecting streets,
roads, and highways are planned with a minimum spacing of ½ mile. Intersection spacing of
less than ½-mile may be allowed, but only when no reasonable alternative access exists.
In urban areas and developing areas where higher volumes are present or growth that will
require a change to intersection control is expected in the foreseeable future, it is
imperative that the location of any public access point be planned carefully to ensure
adequate traffic progression. Where feasible, major intersecting roadways that might
ultimately require signalization or other intersection control type are planned with a
minimum of ½-mile spacing. The addition of all new public or private access points that may
require signalization or other intersection control type, will require an engineering analysis
The minimum distance to another (public or private) access point is 330 feet on the
same side of the highway. Nonconforming access connection permits may be
issued to provide access to parcels whose highway frontage, topography, or
location precludes issuance of a conforming access connection permit.
Variance permits may be allowed if there are special conditions and the exception
can be justified to the satisfaction of the department by a traffic analysis in the
access connection permit application that is signed and sealed by a qualified
professional engineer who is registered in accordance with RCW 18.43.
540.03(4) Class 4
540.03(4)(a) Functional Characteristics
Class 4 highways provide for moderate travel speeds and moderate traffic volumes for medium
and short travel distances for intercity, intracity, and intercommunity travel needs. There is a
reasonable balance between direct access and mobility needs for highways in this class. This
class is to be used primarily where the existing level of development of the adjoining land is
more intensive and where the probability of major land use changes is less than on Class 3
highway segments.
1. It is the intent that Class 4 highways be designed to have a posted speed limit of 30 to 35
mph in urbanized areas and 35 to 45 mph in rural areas. In rural areas, intersecting streets,
roads, and highways are planned with a minimum spacing of ½ mile. Intersection spacing of
less than ½ mile may be allowed, but only when no reasonable alternative access exists.
In urban areas and developing areas where higher volumes are present or growth that will
require a change in intersection control is expected in the foreseeable future, it is
imperative that the location of any public access point be planned carefully to ensure
adequate traffic progression. Where feasible, major intersecting roadways that might
ultimately require intersection control changes are planned with a minimum of ½-mile
spacing. The addition of all new public or private access points that may require
signalization, or other intersection control type, will require an engineering analysis that is
signed and sealed by a qualified professional engineer who is registered in accordance with
RCW 18.43.
The minimum distance to another (public or private) access point is 250 feet on the
same side of the highway. Nonconforming access connection permits may be
issued to provide access connections to parcels whose highway frontage,
topography, or location precludes issuance of a conforming access connection
permit.
Variance permits may be allowed if there are special conditions and the exception
can be justified to the satisfaction of the department by a traffic analysis in the
access connection permit application that is signed and sealed by a qualified
professional engineer who is registered in accordance with RCW 18.43.
540.03(5) Class 5
540.03(5)(a) Functional Characteristics
Class 5 highways provide for moderate travel speeds and moderate traffic volumes for primarily
short travel distances for intracity and intracommunity trips and for access to state highways of
a higher class. Access needs generally may be higher than the need for through-traffic mobility
without compromising the public’s health, welfare, or safety. These highways will normally have
nonrestrictive medians.
1. It is the intent that Class 5 highways be designed to have a posted speed limit of 25 to 35
mph. In rural areas, intersecting streets, roads, and highways are planned with a minimum
spacing of ¼ mile. Spacing of less than ¼ mile may be allowed where no reasonable
alternative exists. In urban areas and developing areas where higher volumes are present or
growth that will require changes to intersection control is expected in the foreseeable
future, it is imperative that the location of any public access point be planned carefully to
ensure adequate traffic progression. Where feasible, major intersecting roadways that
might ultimately require changes to intersection control are planned with a minimum of ¼
mile spacing. The addition of all new public or private access points that might require
signalization, or other control type, will require an engineering analysis that is signed and
sealed by a qualified professional engineer who is registered in accordance with RCW 18.43.
the state highway in accordance with the assigned managed access Class 5 and will
not adversely affect the safety or operation of the state highway.
The minimum distance to another (public or private) access point is 125 feet on the
same side of the highway. Nonconforming access connection permits may be
issued to provide access to parcels whose highway frontage, topography, or
location precludes issuance of a conforming access connection permit.
Variance permits may be allowed if there are special conditions and the exception
can be justified to the satisfaction of the department by a traffic analysis in the
access connection permit application that is signed and sealed by a qualified
professional engineer who is registered in accordance with RCW 18.43.
Conforming[1]
Conforming[3]
Access Point
Variance[2]
Spacing**
Class Limitations[4]
Non-
Class 1 • One access only to contiguous
Mobility is the parcels under same ownership
primary function Yes* No No 1,320 ft • Private access connection is not
allowed unless no other reasonable
access exists (must use local road/
street system if possible)
Class 2 • One access connection only to
Mobility is favored contiguous parcels under same
over access ownership unless frontage > 1,320 ft
Yes* Yes* No 660 ft • Private access connection not
allowed unless no other reasonable
access exists; must use local
road/street system if possible
Class 3 • One access connection only
Balance between to contiguous parcels under
mobility and access same ownership
Yes Yes Yes 330 ft
in areas with less • Joint access connection for
than maximum subdivisions preferred; private
buildout connection allowed, with justification
Class 4 One access connection only
Balance between to contiguous parcels under same
mobility and access ownership, except with justification
Yes Yes Yes 250 ft
in areas with less
than maximum
buildout
Class 5 More than one access connection
Access needs may per ownership, with justification
Yes Yes Yes 125 ft
have priority over
mobility
*The access connection continues only until such time other reasonable access to a highway with a less restrictive
class or acceptable access to the local road/street system becomes available and is allowed.
The modified highway classification list shall be submitted to Headquarters for approval by the
Director & State Design Engineer, Development Division, or a designee. WSDOT regions shall
notify the RTPOs, MPOs, and local governmental entities in writing of the final determination of
the reclassification.
Corner clearance spacing must meet or exceed the minimum access point spacing requirements
of the applicable managed access highway class. A single access connection may be placed
closer to the intersection, in compliance with the permit application process specified in WAC
468-51 and in accordance with the following criteria:
The minimum corner clearance criteria in Exhibit 540-2 may be used where access
point spacing cannot be obtained due to property size and where a joint-use access
connection cannot be secured or where it is determined by WSDOT not to be feasible
because of conflicting land use or conflicting traffic volumes or operational
characteristics.
Some local agencies have adopted corner clearance as a design element in their design
standards; these standards are to meet or exceed WSDOT standards. Coordinate with
the local agency regarding corner clearance of an access connection on or near an
intersecting local road or street.
When a joint-use access connection or an alternate road/street system access—
meeting or exceeding the minimum corner clearance requirements—becomes
available, the permit holder must close the permitted access connection unless the
permit holder shows to WSDOT's satisfaction that such closure is not feasible.
Exhibit 540-2 Minimum Corner Clearance: Distance From Access Connection to Public
Road or Street
minimum corner
clearance
State Hwy.
public road/street
access connection
All access connections are determined by WSDOT to be in one of the following categories
(WAC 468-51-040):
540.05(1) Category I
“Category I – minimum connection” provides connection to the state highway system for up to
ten single-family residences, a duplex, or a small multifamily complex of up to ten dwelling units
that use a common access connection. This category also applies to permanent access
connections to agricultural and forestlands, including field entrances; access connections for the
operation, maintenance, and repair of utilities; and access connections serving other low-
volume traffic generators expected to have average weekday vehicle trip ends (AWDVTE) of 100
or less.
540.05(2) Category II
“Category II – minor connection” provides connection to the state highway system for medium-
volume traffic generators expected to have an AWDVTE of 1,500 or less, but not included in
Category I.
540.05(4) Category IV
“Category IV – temporary connection” provides a temporary, time-limited connection to the
state highway system for a specific property for a specific use with a specific traffic volume. Such
uses include, but are not limited to, logging, forestland clearing, temporary agricultural uses,
temporary construction, and temporary emergency access. The department reserves the right
to remove any temporary access connection at its sole discretion and at the expense of the
property owner after the expiration of the permit. Further, a temporary access connection
permit does not bind the department, in any way, to the future issuance of a permanent access
connection permit at the temporary access connection location.
All new access connections to state highways, as well as alterations and improvements to
existing access connections, require an access connection permit. Every owner of property that
abuts a managed access state highway has the right to reasonable access, but not a particular
means of access. This right may be restricted with respect to the highway if reasonable access
can be provided by way of another local road/street.
When a new private road or street is to be constructed, approval by the permitting authority is
required for intersection design, spacing, and construction work on the right of way. However, if
an access connection permit is issued, it will be rendered null and void if and when the road or
street is duly established as a local road or street by the local governmental entity.
It is the responsibility of the applicant or permit holder to obtain all necessary local, state, and
federal approvals and permits (which includes all environmental permits and documentation).
The access connection permit only allows the applicant permission to connect to the state
highway. It is also the responsibility of the applicant to acquire any and all property rights
necessary to provide continuity from the applicant’s property to the state highway.
The alteration or closure of any existing access connection caused by changes to the character,
intensity of development, or use of the property served by the access connection or the
construction of any new access connection must not begin before an approved access
connection permit is obtained.
If a property owner or permit holder with a valid access connection permit wishes to change the
character, use, or intensity of the property or development served by the access connection, the
permitting authority must be contacted to determine whether an upgraded access connection
permit will be required.
The permitting process begins with the application. Upon submittal of the application with all
the attached requirements, it is reviewed and either denied or accepted. If denied, the
department must notify the applicant in writing stating the reasons, and the applicant will have
thirty (30) days to submit a revised application. Once the application is approved and the permit
is issued, the applicant may begin construction.
The Access Manager in each region keeps a record of all access points, including those that are
permitted and those that are grandfathered (see 540.08). A permit for a grandfathered access
point is not required but may be issued for recordkeeping reasons.
In such instances, the permit is to be noted as being a nonconforming access connection permit
and may contain the following specific restrictions and provisions:
Limits on the maximum vehicular use of the access connection.
The future availability of alternate means of reasonable access for which a conforming
access connection permit can be obtained.
The removal of the nonconforming access connection at the time the conforming
access is available.
The properties to be served by the access connection.
Other conditions as necessary to carry out the provisions of RCW 47.50.
In such instances, the permit is to be noted as being a variance access connection permit and
may contain the following specific restrictions and provisions:
Limits on the maximum vehicular use of the access connection
The properties to be served by the access connection
Other conditions as necessary to carry out the provisions of RCW 47.50
This permit will remain valid until modified or revoked by the permitting authority unless an
upgraded permit is required due to changes in property site use (see 540.08(1)).
A variance access connection permit must not be issued for an access connection that does not
conform to minimum corner clearance requirements (see 540.04).
A design analysis request will be required for nonconforming access connections if corner
clearance criteria are not met. The ASDE should be involved early in the process. Such an access
will be outside the corner radius and as close as feasible to the property line farthest away from
the intersection.
An exception to the above may be allowed for a single-family residence, serving a single
residence, not meeting the minimum corner clearance criteria and having no feasible
connection to the local cross street. One single family home generates a very low volume of
traffic and will pose a low conflict potential for traffic on the State Highway System. A single-
family access connection exception is to comply with the following criteria:
In accordance with RCW 35.78.030 and RCW 47.50, incorporated cities and towns have
jurisdiction over access permitting on streets designated as state highways and, therefore, no
design analysis by WSDOT will be required. On WSDOT projects, document decisions made on
these accesses in the DDP.
A significant change is one that will cause a change in the category of the access connection
permit or one that causes an operational, safety, or maintenance problem on the state highway
system based on objective engineering criteria or available collision data. Such data will be
provided to the property owner and/or permit holder and tenant upon written request (WAC
468-51-110).
Any access connections that were in existence and in active use on July 1, 1990, are
grandfathered.
540.08(2)(b)(1) Notification
The department must notify affected property owners, permit holders, business owners,
and emergency services in writing, when appropriate, whenever the department’s work
program requires the modification, relocation, or replacement of its access connections. In
addition to written notification, the department will facilitate, when appropriate, a process
that may include, but is not limited to, public notices, meetings, or hearings, as well as
individual meetings.
When the number, location, or design of existing access connections to the state highway is
being modified by a department construction project, the resulting modified access
connections must provide the same general functionality for the existing property use as
they did before the modification, taking into consideration the existing site design, normal
vehicle types, and traffic circulation requirements. These are evaluated on an individual
basis.
It is important to remember that the intent is not to damage the property owner by
removing nonconforming access connections, but to eliminate access connections that are
both nonconforming and not needed.
The costs of modifying or replacing the access points are borne by the department if the
department construction project caused the replacement or modification. Modification of
the connection may require a change to the existing permit.
An appeal of a decision by the department can be requested only if the administrative fee has
been paid. If the fee has not been paid, the permit application is considered incomplete and an
adjudicative proceeding cannot be requested.
Following is a brief summary of the adjudicative proceeding process. For the purpose of this
summary, the responsibilities of the department are separated into those actions required of
the region and those actions required of Headquarters. The summary is written as if the
appealable condition was a denial of an access connection request.
2. The region processes the application and makes a determination that the access connection
request will be denied.
3. The region sends the applicant a written letter denying the access connection. Included in
this letter is notification that the applicant has thirty (30) days to request an adjudicative
proceeding if the applicant disagrees with the region’s denial decision. The region must
notify affected property owners, permit holders, business owners, tenants, lessees, and
emergency services, as appropriate.
5. The region reviews its initial denial decision and determines whether there is any additional
information presented that justifies reversing the original decision.
6. If the region determines that the original denial decision will stand, the region then forwards
copies of all applicable permit documentation to the HQ Development Services & Access
Manager for review and processing.
7. The HQ Development Services & Access Manager reviews the permit application and sends
the permit documentation and appeal request to the Office of the Attorney General (AG).
8. If the initial findings of the AG agree with the region’s denial decision, the AG’s Office sends
the applicant a written letter, with the AG’s signature, informing the applicant that a hearing
will be scheduled for the applicant to appeal in person the department’s decision to deny
access.
9. The region reserves a location and obtains a court reporter, and Headquarters obtains an
Administrative Law Judge (ALJ) to conduct the proceeding. The AG, by written letter, notifies
the applicant of the time and place for the hearing. The AG’s Office has ninety (90) days
from receipt of the applicant’s appeal to approve or deny the appeal application, schedule a
hearing, or decide not to conduct a hearing. The actual hearing date can be set beyond this
ninety-day (90-day) review period.
10. The AG’s Office leads the department’s presentation and works with the region regarding
who will testify and what displays and other information will be presented to the ALJ. The
HQ Development Services & Access Manager will typically not attend these proceedings.
11. After hearing all the facts, the ALJ issues a decision, usually within a few weeks after the
proceedings. However, the ALJ has ninety (90) days in which to serve a written Initial Order
stating the decision.
12. The ALJ’s decision is final unless the applicant, or the department through the HQ
Development Services & Access Manager, decides to appeal the ALJ’s decision to the
Director & State Design Engineer, Development Division. This second appeal must occur
within twenty (20) days of the ALJ’s written decision.
13. If appealed to the Director & State Design Engineer, Development Division, the Director &
State Design Engineer has ninety (90) days to review the Initial Order and all the facts and
supporting documentation and issue a Final Order. The review by the Director & State
Design Engineer does not require the applicable parties to be present and may involve only
a review of the material submitted at the adjudicative proceeding.
14. The Director & State Design Engineer’s decision is final unless appealed within thirty (30)
days to the Washington State Superior Court.
The above represents a general timeline if all appeals are pursued. Based on the noted
timelines, it can take nearly a year before a Final Order is issued. If appealed to Superior Court,
up to an additional 18 months can be added to the process. In any case, contact the region
Development Services Engineer for further guidance and direction if an appeal might be
forthcoming.
540.11 Documentation
Refer to Chapter 300 for design documentation requirements.
540.12 References
Chapters in the 1100 series for guidance on practical design, context, and design controls
Chapters 1300 and 1310, for intersection design policy and guidance
550.01 Overview
It is in the national and state interest to preserve and enhance the Interstate and non-Interstate
freeway system in Washington providing an appropriate level of service in terms of safety and
mobility performance for the movement of people and goods. Full control of access along the
freeway mainline and ramps, along with control of access on the local roadway network within
the interchange functional area, is critical to providing such service. Therefore, decisions to
approve new or revised interchange access points on Washington’s freeways depend on
consistent application of procedures, analysis, and supporting documentation.
In May 2017, the Federal Highway Administration (FHWA) significantly revised its access policy.
In the memorandum transmitting the new policy to the FHWA Division Administrators, FHWA
states:
“The FHWA has identified several areas where the current Policy may be streamlined to
eliminate duplication with other project reviews. The new Policy will now focus on the
technical feasibility of any proposed change in access in support of FHWA's
determination of safety, operational, and engineering acceptability. Consideration of
the social, economic, and environmental impacts and planning considerations will be
addressed through the National Environmental Policy Act (NEPA) review of the project.
This change will eliminate the potential for duplicative analysis of those issues in the
State DOT's Interstate Access report and the NEPA documentation. The change will
allow State DOTs to submit only a single technical report describing the types and
results of technical analyses conducted to show that the change in access will not have
significant negative impact on the safety and operations of the Interstate System.”
The federal policy change points to a clear link between the NEPA and access revision processes.
The NEPA process will account for the social, economic, and environmental impacts and a
technical report herein called the Access Revision Report (ARR) will account for the safety and
operational impacts.
Interstate freeways: New or revised access to Interstate freeways requires collaboration with
and approval from FHWA. WSDOT and local partners need to include FHWA from the beginning
of the planning process throughout the development of the proposal. WSDOT is the only entity
recognized by FHWA Washington Division that is allowed to submit requests for Interstate
access revisions for review and approval.
For consistency in analysis and reporting, the policy to revise freeway access is the same for
both Interstate and non-Interstate freeways. The only major difference is in the approving
authorities, described above. Exhibit 550-4 helps clarify what is considered an access revision
and presents approval authorities for both Interstate and non-Interstate access revisions.
The contents of this chapter provides the requirements and expectations to fulfill this policy.
Note: For breaks in freeway limited access that do not involve new, revised, or abandoned
traffic interchanges, follow procedures given in Chapter 530 Limited Access Control. Examples
include locked gates, pedestrian structures, and access to fire hydrants within the full control
limited access. Contact the HQ Design Office, Access and Hearings Section for support.
For the process to be successful, there needs to be a clear link to the planning and
environmental processes. The planning linkage should be addressed at the beginning of the
process to make sure the access revision decision aligns with local, regional, and state planning
efforts. This planning linkage is discussed in more detail in Section 550.05(2)(a). The
environmental linkage exists throughout the process as the Federal policy promotes a more
direct link between this access revision process and the environmental process. This chapter
includes callouts to the environmental process at key points to highlight this linkage and to help
align the processes and reduce duplication between the two processes.
The access revision and practical design processes correlate through the use of the Context and
Modal Accommodation Report (CMAR) and the Basis of Design (BOD). The CMAR can help
determine modal priority and accommodation on non-freeway segments, such as the crossroad
proposed for the freeway access connection. The CMAR may be completed during the feasibility
study. The BOD can help document baseline and contextual needs and set the direction for a
future project. Sections 1 through 3 of the BOD (Project Need, Context, and Design Controls)
may be completed at the end of the Non-Access Feasibility Study. Sections 4 and 5 (Alternatives
Analysis and Design Element Selection) of the BOD should be completed in conjunction with the
ARR. The BOD completed with the ARR may be considered the scoping BOD.
Use the Design Support website to download the CMAR, the CMAR learners Guide, the Basis of
Design and Alternatives Comparison Table. http://www.wsdot.wa.gov/Design/Support.htm
550.03(1) Scalability
The access revision process varies greatly due to the complexities of the transportation system
and context environment planned for the horizon year (see Chapter 1103). Not all access
revision cases require a full-scale ARR. Exhibit 550-4 reflects the access revision documentation
levels for select project types. For variation from Exhibit 550-4 or clarification on scalability,
discuss with the Assistant State Design Engineer (ASDE). Document the scalability in the method
and assumptions documents.
The new FHWA policy states clearly that the environmental documentation and access revision
processes be linked and aligned to reduce duplication of effort. Throughout this access revision
analysis process, key points correlate with the environmental process. For best results, make
sure the environmental staff is fully engaged and involved in the process. Region Environmental
staff will help determine the best NEPA / SEPA compliance strategy. The team, including FHWA,
determines the type of environmental document required during
the feasibility phase of access review. Since FHWA approval of
Interstate access revisions entails a federal action, National Best Practice: Engage
Environmental Policy Act (NEPA) requirements apply to Interstate
access reviews. If NEPA does not apply to a freeway access WSDOT Environmental
revision, environmental documentation through the State experts to determine
Environmental Policy Act (SEPA) does apply. In either case, the NEPA / SEPA strategy.
team, comprised of experts and agents from WSDOT and FHWA,
is authorized to determine the type of environmental
documentation required.
If the team determines the project can be documented as a Categorical Exclusion/ Exemption
(CE), involvement from environmental staff at key decision points will help ensure the project is
appropriately scoped and environmental considerations are integrated into the ARR as
appropriate. For a CE, information from the Non-Access Feasibility Study can be useful, but is
typically much more detailed than the information required for the CE checklist.
Due to the scalability of the process, the executive support team can vary with each access
revision case but will typically have a core of the following individuals:
FHWA Safety and Geometric Design Engineer
Region Representatives (Assistant Regional Administer, Traffic Engineer, Local
Programs Engineer, Environmental Manager, and/or Planning Manager)
Assistant State Design Engineer
HQ Traffic
Local agency representatives (city, county, port, transit and/or tribal government)
Due to the scalability of the process, the technical support team can vary with each access
revision case. Work with the executive support team to make sure the right personnel are on
the team. The team members may include representation from the following groups:
Planning organization (Metropolitan Planning Organization (MPO) and/or Regional
Transportation Planning Organization (RTPO))
FHWA (Area Engineer, Environmental Program Manager, and/or ITS Engineer)
WSDOT Region (planning, design, environmental, maintenance, and/or traffic)
WSDOT HQ Multimodal Development & Delivery
Local agency specialist (planning, developer services, public works, and/or engineering)
Project proponents specialists (developer and/or consultant)
Multimodal specialist (transit, bike, and/or pedestrian)
Other identified stakeholders/partners
Executive Team
Agrees There Is a
Identify transportation performance gaps and Gap No
develop draft purpose and need [see 550.05]
Yes
Stop Study
Plannaing and Environmental Linkages (PEL) [see 550.03(2)]
ü Signature Page
ü Establish study purpose
Prepare Feasibility Study ü Establish Team roles and
NEPA/SEPA Process [see 550.03(2); 550.05(1); 550.05(2)(f)
Yes
The above list is not all-encompassing nor is everything in the list covered in every study. The
technical support team refines the above list as necessary and submits the outline of the
feasibility study to the executive support team for concurrence.
The Non-Access Feasibility Study M&A document contains a signature page for concurrence by
the executive support team. A template for the M&A document is here:
http://www.wsdot.wa.gov/design/accessandhearings
The Non-Access Feasibility Study may begin upon concurrence of the M&A document.
Project Background
Vicinity Map
Study Area
Planning Linkage (see Chapter 550.05(2)(a))
Multimodal Needs
Traffic Volumes (see Chapter 550.05(2)(b))
Traffic Operational Analysis (see Chapter 550.05(2)(c))
Safety Performance Analysis (see Chapter 550.05(2)(d))
Reasonable Non-Access Alternatives (see Chapter 550.05(2)(e))
Conclusion (see Chapter 550.05(2)(f))
Purpose and Need for Access Revision
Non-Access Feasibility Study is compiled and reviewed first by the technical support team prior
to being sent to the executive support team for signature. If the process does not go into the
ARR phase, then send a final copy of the Non-Access Feasibility Report to your ASDE for filing. If
the process continues into the ARR phase, then attach the Non-Access Feasibility Report to the
ARR as an appendix.
550.05(2)(a) Planning Linkage
It is essential to create the linkage to the transportation planning processes and outputs by the
WSDOT and other agencies in the non-access feasibility study. Any transportation improvement
considered in the access revision process should align with these planning processes. Describe
how the improvements are consistent with local land use plans, and local, regional, and state
transportation plans including possible future interchanges, bicyclist/pedestrian networks,
transit service, and possible development.
While the need for freeway access is motor vehicle based, it is also
important to address the needs of all modes that will access and use Consistent and
the local networks and freeway crossroad(s). An important aspect of
purposeful
the planning linkage is to address multimodal connectivity on the
crossroad. While interchange crossroads may provide vehicle access planning linkages
to and from the freeway mainline, they also provide critical between agency
multimodal connectivity between land uses on either side of the partners helps the
freeway. Consult comprehensive land use and transportation plans for
process.
multimodal elements. Document multimodal needs, priority, and
accommodation in the Non-Access Feasibility Study.
If another planning process or study appears to meet the requirements of the Non-Access
Feasibility Study, have the technical support team review it and determine if it is applicable. If
the technical team finds the process or study meets the requirements of the feasibility study,
then present it to the executive support team and request an exemption from the feasibility
study process. Clearly document this exemption and receive written approval from the
members of the executive support team.
550.05(2)(b) Traffic Volumes
Traffic volumes for the existing, opening, design, and horizon year are determined and reported
in the feasibility study. It is important to consider pedestrian, bicyclist, and transit volumes
where applicable. The existing year is the year the traffic data is collected. Consult Chapter 1103
for definitions and details of opening, design, and horizon years.
The data for the future years may come from a regional transportation model or linear
projections unique to the study. Exponential growth projections are not recommended.
Regional transportation models may also be used for the opening and design year volumes.
Transportation models are commonly maintained by a Metropolitan Planning Organization.
These models predict traffic volumes by dividing the area into zones, populating these zones
with the appropriate type of land use, and predicting travel demand on the road network based
upon the trip demand and travel time between destinations. The process to develop these
models is extensive; therefore, the models are not continuously updated. Opening/design years
that do not correlate with the years of the regional transportation model may be adjusted by a
linear growth rate to the opening/design year of the traffic study. The technical support team
determines how to best use an available model. Document the model used, how the model was
calibrated and validated.
Traffic models used for the ARR process should incorporate transit, bicyclists, and pedestrians.
If the model does not have the ability to incorporate these other modes, investigate the viability
of modifying link and intra-zone trips with the technical support team to reflect the multimodal
trips. Consider how changing access to these other modes may impact travel demand within
and through the study area.
If linear projections are used, be careful to not base projection on a valley or peak in historic
traffic volumes. Record any assumptions applied to linear projections in the feasibility study.
Conduct the operational analysis over the study area, using the tools and methodology in
accordance with the M&A document. Conduct the operational analysis on the opening and
design year. The technical support team determines if it is necessary to have existing year
analysis or if the no-build at opening year is sufficient. For these years:
Conduct the Existing operational analysis over the study area (if required by the
technical support team)
No change in the existing roadway network.
Use the existing traffic volumes and calibrate to existing conditions to determine
if the analysis reflects existing conditions and the model is validated.
Conduct Base Improvements operational analysis over the study area
The existing roadway network with the addition of local or non-access
transportation projects and services that are funded for construction/delivery or
have a high likelihood of being constructed/delivered, as identified as base
network improvements in the M&A document. Incorporate base network
improvements into the analysis.
The result of this base improvements operational analysis is a list of the locations
where the transportation system has potential performance gaps. Compare this
list of locations to the performance gaps identified in the beginning of the access
revision process. The analysis helps clarify whether or not performance gaps
exist. Identify these gaps in the report. These identified gaps will be where the
technical support team focuses in the operational analysis done for the
reasonable non-access alternatives. This leads to identification of performance
targets by mode.
Conduct the Build operational analysis over the study area
Incorporate the base improvements as the starting point, then evaluate
reasonable non-access alternatives as discussed in 550.05(2)(e)
The build operational analysis assess whether the non-access alternatives
address the identified performance gaps.
550.05(2)(d) Safety Analysis
Conduct a safety analysis per Chapter 321.04 and Section 8.1 of the Safety Analysis Guide. In
this section of the feasibility study, discuss the safety performance of the existing transportation
network. For the non-access Feasibility Study, the safety analysis needs to focus on the non-
access network; safety analysis of the freeway mainline is not required.
550.05(2)(e) Reasonable Non-Access Alternatives
The Non-Access Feasibility Study must look at reasonable alternatives that can address the
performance gaps noted in the operational analysis and/or safety performance analysis. The
determination of reasonable alternatives follows the process as noted in Chapter 400.07(1)4 of
the WSDOT Environmental Manual. Each reasonable alternative must consider the change in
safety performance per the Safety Analysis Guide.
The goal of the alternatives is to identify non-access improvements and performance targets
that address operation gaps and safety performance
characteristics for all modes. Alternatives should first
consider non-access, operational and/or demand Performance target – an
management improvements. Coordinate these outcome or desired state
improvements with local and state planning staff. The intended for a part of the
technical support team initiates alternatives for
consideration and presents them to the executive support system.
team for approval. Include alternatives comprised of See Chapter 1101.
varying types such as intersection solutions, corridor
solutions, land use modifications, transit improvements,
mode shift, travel demand management or other systematic network-based Practical Solutions
approaches. Use the measures of effectiveness discussed in the methods and assumptions
document to compare alternatives.
If the non-access improvements do not completely address the performance gaps, but do show
value, then they should be carried forward into the access revision analysis for further inclusion
in the project.
550.05(2)(f) Non-Access Conclusion
If the non-access improvements can address the performance gaps within the criteria defined in
the M&A, then state such in this section and conclude the access revision process.
If the feasibility study indicates that addressing performance gaps cannot be reasonably
achieved without revising freeway access, then write a purpose and need for access revision in
this section of the feasibility study. This purpose and need statement should be written in close
coordination with the Environmental Office as this is a key linkage point between the
NEPA/SEPA process and the access revision process. The goal of this section is to provide a
purpose and need statement that can be used for the Access Revision Report, a Basis of Design
for an access revision, and the NEPA/SEPA process.
In addition to the purpose and needs statement, summarize the non-access alternatives that are
needed and carried this list forward into the ARR.
Yes
Finding of Engineering
and Operational
Acceptability
granted while NEPA /
NEPA / SEPA SEPA
is being completed. No
complete?
Interstates: FHWA
Non-interstates:
WSDOT
[see 550.06(3)]
NEPA / Yes
SEPA
completed
[550.06(3)]
The following provides details for completing the Access Revision Report.
Consider alternatives in the Non-Access Feasibility Study that are carried forward into the ARR
process and any new alternatives that may be developed for on-system alternatives. Then
narrow the alternatives down to a few reasonable alternatives that will go through the
evaluation process. Determine the reasonable alternatives for the ARR phase near the beginning
of the process. This is necessary because the alternatives will set the course for the operational
and safety analysis and determine exactly what must be analyzed.
The technical team evaluates each reasonable alternative with respect to operations and safety
performance for all modes (see Section 550.06(2)(b) and (c)). Alternatives are refined based
upon the results of the analysis and then presented to the executive support team for
acceptance.
Conduct the alternatives selection and analysis process within the ARR with full consideration of
the environmental process and environmental documentation that will be required. The ARR
must be fully compatible with the corresponding environmental process. Include Region
environmental staff in the alternatives selection process.
In the ARR document, include a description of the reasonable alternatives identified for
consideration. At this point, you should have a few reasonable alternatives that will be carried
forward through the whole ARR process and will have detailed operations and safety analysis
conducted (see Section 550.06(2)(b) and (c)). The results of this analysis will be used to
compare the alternatives and ultimately reach a preferred alternative. To document the
evaluation criteria and the results of the analysis, use the Alternatives Comparison Table (ACT)
or a similar tool.
The ARR must show that the proposed access will connect to a public road network.
Less than “full interchanges” may be considered on a case-by-case basis for applications
requiring special access, such as managed lanes (e.g., transit or high occupancy vehicle and high
occupancy toll lanes) or park and ride lots.
In other cases where all basic movements are not provided by the proposed design, the ARR
typically includes a full interchange option with a comparison of the operational and safety
performance analyses to the partial-interchange option. The ARR should also include the
mitigation proposed to compensate for the missing movements, including wayfinding signage,
impacts on local intersections, mitigation of driver expectation leading to wrong-way
movements on ramps, etc. The ARR should demonstrate that the future provision of a full
interchange is not precluded by the proposal or describe how that future decision will be
accommodated.
The crossroad must address the needs of all modes that are supported by the land use and
demographics of the area. While the needs and priority of multimodal users are identified in the
feasibility study, the ARR helps ensure multimodal needs are incorporated in the design.
FHWA policy requires that AASHTO Interstate standards (A Policy on Design Standards –
Interstate System, AASHTO, latest edition) are used. This Design Manual provides criteria to
meet FHWA and WSDOT policy on geometric standards. To achieve design standards
requirements, apply the criteria in these key Design Manual Chapters:
Chapters 1100 – 1106 for an overview of practical design procedures, development of
need statements, procedures for selecting appropriate multimodal design controls and
design element dimensions. Assume the crossroad design will have implications and
effects on all travel modes legally allowed. Provide obvious traffic control for all modes.
Chapters in the 1200 series provide geometrics including plan and profile elements and
freeway and other roadway type cross section criteria. Chapter 1232 provides
geometric cross section dimensions for Interstate and non-Interstate freeways. Other
chapters in this series provide cross section criteria for roadway types which could
apply to multimodal crossroads and local street or roadway contexts.
Chapters in the 1300 series provide design criteria for Interchange spacing and design,
and procedures for evaluating intersection control types. Chapters 1300 - Intersection
Control Type and 1360 - Interchanges
For special interchanges for HOV or Transit, see chapters in the 1400 series.
Chapters in the 1500 series provide design guidance for pedestrian and bicyclist
facilities.
See other chapters as applicable for various aspects of design and approvals.
The operational analysis for the ARR builds upon the operational analysis from the feasibility
study. If demonstrated in the feasibility study that local solutions will not completely satisfy the
Purpose and Need, the scope of the ARR operational analysis includes reasonable alternatives
that consider revisions in freeway access as well as non-access improvements that are carried
forward from the Non-Access Feasibility Study. This analysis must conclude that the proposed
change in access does not have a significant adverse impact on the safety and operation of the
freeway facility or on the local street network for all modes, based on both current and planned
future traffic projections. The freeway facility includes the main line lanes, collector-distributor
lanes, existing, new, or modified ramps, and ramp intersections with crossroad.
The following are typical requirements for the analysis. The technical support team makes the
ultimate decisions on transportation operational and safety performance analysis requirements.
However, FHWA policy suggests the following expectations.
The analysis includes, particularly in urbanized areas, a minimum of the first adjacent
existing or proposed interchange on either side of the proposed change in access.
The crossroads and the local street network, to a minimum of the first major
intersection on either side of the proposed change in access, should be included in this
analysis to the extent necessary to fully evaluate the safety performance and
operational impacts that the proposed change in access and other transportation
improvements may have on the local street network.
The requested proposed change in access should include a description and assessment
of the impacts and ability of the proposed changes to collect, distribute, and
accommodate traffic on the Interstate facility, ramps, intersection of ramps with
crossroad, and local street network.
The Access Revision Report also includes fulfilling the requirements of the Intersection Control
Evaluation (ICE) to verify the chosen intersection(s) control at the interchange are adequate for
all modes. An ICE will not be required if the ARR documents the criteria required for an ICE. See
Chapter 1300 for ICE instruction.
Conduct a safety performance analysis per Chapter 321 and Section 8.1 of the Safety Analysis
Guide. For the ARR, discuss the safety performance of the reasonable alternatives. Use the
results of the safety performance analysis to compare alternatives.
Include a conceptual plan of the type and location of the signs proposed for the preferred
alternative to support the Access Revision Report. The conceptual plan is typically limited to
guide signage, but regulatory or warning signs may be required if the interchange configuration
is unusual.
Draft ARR review: The draft ARR is first reviewed by the executive and technical support teams.
After their review, the Region submits an electronic copy (in PDF format), including appendices,
to the ASDE along with a cover memo requesting review. The ASDE responds in writing either
with needed revisions or to request the final draft.
Final ARR Submittal: For final submittal, send the final ARR in PDF format to the ASDE. Contact
the ASDE for the necessary number of hard copies. The Region submits a memo to the
appropriate ASDE, requesting final approval of the ARR. After ASDE concurrence, the ASDE
submits Interstate ARRs to FHWA for approval.
FHWA provides final approval of the Interstate ARR when the appropriate final environmental
document is complete: CE, FONSI, or ROD. The intent of the federal policy is to create a clear
link between the ARR and NEPA processes. The ARR may be used as the transportation discipline
report for an EIS/EA or included as an attachment to a CE. Coordinate with the Region
Environmental Staff to integrate the ARR with the environmental documentation.
WSDOT provides final approval of the non-Interstate ARR when the appropriate final
environmental document is complete.
If no work has begun within three years of completion of the environmental documentation, a
re-evaluation of the CE/EA/EIS may be required (see Environmental Manual 400.06(1)). Contact
the Region Environmental Office to determine if the environmental documentation must be re-
evaluated.
550.07 Documentation
This chapter discusses in detail the requirements for the following documents:
Non-Access Feasibility Study Method and Assumptions
Non-Access Feasibility Study
Access Revision Report Method and Assumptions
Access Revision Report
For levels of approval for each of these documents, refer to Exhibit 550-4 and Chapter 300.
The final Access Revision Report is archived by the HQ Access and Hearings Section.
550.08 References
40 CFR Parts 51 and 93 (regarding federal conformity with state and federal air quality
implementation plans)
23 USC Sections 111 (requires the U.S. Secretary of Transportation to approve access revisions
to the Interstate System), 134 (metropolitan transportation planning), and 135 (statewide
transportation planning)
Safety Analysis Guide, WSDOT; See Sustainable Highway Safety Tools here:
http://www.wsdot.wa.gov/Design/Support.htm
WSDOT Planning: find resources including Corridor Sketch Initiative, Corridor Planning Studies,
links to the Highway System Plan, and other supporting information.
http://www.wsdot.wa.gov/planning/default.htm
WSDOT HQ Access and Hearings (including Freeway Access Revisions Resource Document)
www.wsdot.wa.gov/design/accessandhearings
FHWA Traffic Analysis Toolbox (tools used in support of traffic operations analyses)
www.ops.fhwa.dot.gov/trafficanalysistools/index.htm
“MP to MP”
This Access Revision Report has been prepared under my direct supervision, in accordance with Chapter 18.43
RCW and appropriate Washington State Department of Transportation manuals.
By:__________________________________________ P.E.
Date:________________________________________
By:________________________________________ P.E.
Date:______________________________________
By:________________________________________ P.E.
WSDOT Approval –
Assistant State Design Engineer
Date:______________________________________
FHWA Approval –
FHWA Safety and Design Engineer
By:________________________________________
Date:______________________________________
Concurrence –
Region Traffic Engineer
By:________________________________________ P.E.
Date:______________________________________
HQ and
Transit flyer stop on main line No [5] ü [4] Concurrence
FHWA
HQ and
Transit flyer stop on a ramp No [5] ü [4] Concurrence
FHWA
Abandonment of a ramp No [5] ü [4] HQ FHWA Concurrence
Locked gate
Access breaks that do not allow any type of
access to main line or ramps (i.e. access
doors in noise walls, gates to storm water
retention/detention facilities from outside See Chapter 530
limited access, etc.)
Structure over or under with no ramps
(including pedestrian, bike, or trail)
Construction/emergency access break
* NAFS = Non-Access Feasibility Study, ARR = Access Revision Report. For notes, see next page.
Notes:
[2] “Revision” includes changes in interchange configuration even if the number of access points does
not change. Changing from a cloverleaf to a directional interchange is an example of a “revision.”
[3] “Revision” includes changes that might adversely affect the level of service of the through lanes.
Examples include: doubling lanes for an on-ramp with double entry to the freeway; adding a loop
ramp to an existing diamond interchange; and replacing a diamond ramp with a loop ramp.
Revisions to the ramp terminal intersections may not require an ARR unless the traffic analysis
shows an impact to the main line traffic.
[4] The scale and scope of the access revision dictate the level of effort needed. Consult the Assistant
State Design Engineer (ASDE), Region Traffic, and the FHWA Area Engineer, if applicable, for
direction.
[5] Consult the Region Planning Manager for the status of planning at this location.
560.01 General
Fencing is provided primarily to discourage encroachment onto Washington State Department
of Transportation (WSDOT) highway right of way from adjacent property, to delineate the right
of way, and to replace fencing that has been disrupted by construction.
Encroachment onto the right of way is discouraged to limit the presence of people and animals
that might disrupt the efficient flow of traffic on the facility. Although not the primary intent,
fencing does provide some separation between people, animals, traffic flow, and other features.
560.02(1) General
Fencing on a continuous alignment usually has a pleasing appearance and is the most
economical to construct and maintain. The recommended practice is to locate fencing on or,
depending on the terrain, 12 inches inside the right of way line.
Where the anticipated or existing right of way line has abrupt irregularities over short distances,
coordinate with Maintenance and Real Estate Services personnel to dispose of the irregularities
as excess property (where possible) and fence the final property line in a manner acceptable to
Maintenance.
Whenever possible, preserve the natural assets of the surrounding area and minimize the
number of fence types on any particular project.
On new alignment, fencing is not provided between the frontage road and abutting property
unless the abutting property was enclosed prior to highway construction. Such fencing is
normally part of the right of way negotiation.
Unless there is a possibility of access control violation, fencing installation may be deferred until
needed at the following locations:
When in doubt about fencing installation, consult the Headquarters (HQ) Access and Hearings
Manager.
If fencing is essential to the safe operation of the highway, it will be constructed and maintained
by the state. An example is the separation of traveled highway lanes from adjacent facilities with
parking or pedestrian areas (such as rest areas and flyer stops).
Fencing is not normally installed around stormwater detention ponds. Evaluate the need to
provide fencing around stormwater detention facilities when pedestrians or bicyclists are
frequently present. Document your decision in the Design Documentation Package.
Fencing proposed at sites that will be outside WSDOT right of way requires that local ordinances
be followed if they are more stringent than WSDOT’s.
Wetland mitigation sites are not normally fenced. When evaluating fencing for wetland
mitigation sites, balance the need to restrict human access for safety considerations (such as the
presence of children) with the need to provide animal habitat.
Other special sites where fencing may be required are addressed in the following chapters:
Chapter 720, Bridges (refers to protective screening)
Chapter 1510, Pedestrian Design Considerations
The fencing types and designs for special sites are determined by the requirements of each
situation.
The Standard Plans contains details for the approved types of chain link fence. The
recommended uses for each type of fence are as follows:
560.03(1)(a) Type 3
This is a high fence for areas of intensified use, such as industrial areas or school playgrounds.
Use this fence for new installations of high fencing. It may be used within the Design Clear Zone.
560.03(1)(b) Type 4
This is a lower fence for special use, such as between the traveled highway lanes and a rest area
or flyer stop or as a rest area boundary fence if required by the development of the surrounding
area. This fence may be used along a bike path or hiking trail to separate it from an adjacent
roadway.
Justify why corrective action is not taken when existing fencing with a rigid top rail will be left in
place within the limits of a proposed project. For cases where a more rigid fence is needed,
contact the HQ Design Office.
Coated galvanized chain link fence is available in various colors and may be considered in areas
where aesthetic considerations are important. Coated ungalvanized chain link fence is not
recommended.
560.03(2)(a) Type 1
This fence is used in urban and suburban areas where improvements along the right of way are
infrequent and future development is not anticipated. It may also be used adjacent to livestock
grazing areas. The lower portion of this fence is wire mesh and provides a barrier to children and
small animals.
560.03(2)(b) Type 2
This fence is used in farming areas to limit highway crossings by farm vehicles to designated
approaches. These areas include irrigation districts to prevent ditch riders, maintenance
personnel, and farmers from making unauthorized highway crossings, and where new alignment
crosses parcels previously enclosed by barbed wire.
Metal fencing can interfere with airport traffic control radar. When locating fencing in the
vicinity of an airport, contact the Federal Aviation Administration to determine whether metal
fence will create radar interference at the airport. If so, use nonmetallic fencing.
560.04 Gates
Keep the number of fence gates along limited access highways to a minimum. On limited access
highways, all new gates must be approved as described in Chapter 550.
Usually such gates are necessary only to allow highway maintenance personnel and operating
equipment to reach the state right of way without using the highway or freeway main line.
Gates may be needed to provide access to utility supports, manholes, and so on, located within
the right of way.
Use gates of the same type as each fence, and provide locks to deter unauthorized use.
In highly developed and landscaped areas where maintenance equipment is parked outside the
fence, provide the double gate shown in the Standard Plans.
Where continuous fencing is not provided on limited access highways (see Chapter 530),
approaches are normally gated and locked, with a short section of fence on both sides of the
gate.
560.05 Procedure
Fencing is addressed in the access report (see Chapter 530) and the Plans, Specifications, and
Estimates, in accordance with the Plans Preparation Manual.
560.06 Documentation
Refer to Chapter 300 for design documentation requirements.
560.07 References
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
610.01 General
It is the Washington State Department of Transportation’s (WSDOT’s) responsibility to
understand the characteristics of the soil and rock materials that support or are adjacent to
a transportation facility so that, when designed, constructed, and maintained, the facility will
be adequate to safely carry the estimated traffic. It is also the responsibility of WSDOT to
ensure the quality and quantity of all borrow, soils, rock, and surfacing materials used in the
construction of transportation facilities. Specific requirements for geotechnical investigation,
design, construction, and maintenance support are set forth in the WSDOT Geotechnical Design
Manual.
The following information serves as guidance in the above areas. When a project consists of
a surface overlay on an existing highway, the WSDOT Pavement Policy is used.
Before making project budget and schedule commitments to the Legislature, other agencies,
and the public, it is necessary to identify the extent and estimated cost for a project. Contact
the Region Materials Engineer (RME) and the Headquarters (HQ) Geotechnical Office as early
as possible to obtain conceptual-level recommendations regarding how the project soil, rock,
and groundwater conditions may affect the design of the project elements. The project soil, rock,
and groundwater conditions, and the availability, quantity, and quality of borrow and surfacing
materials, can affect the project scope, schedule, and budget.
The RME and the HQ Geotechnical Office will use existing subsurface information and their
Coordinate early
in your project knowledge of the project area to assess the subsurface conditions within the project limits. If there
for geotechnical is little information available or the information is poor, and the subsurface conditions have the
reporting and potential to significantly affect the project budget or schedule, it may be necessary to obtain
design. a limited number of geotechnical borings or test pits during Project Definition to assess soil,
rock, and groundwater conditions within the project limits. Once the Project Definition
has been developed and project funding secured, a more detailed geotechnical investigation
follows during the design and Plans, Specifications, and Estimates (PS&E) phases.
It is essential to involve the RME and the HQ Geotechnical Office in the design as soon as
possible once the need for geotechnical work is identified. (See 610.04(3) for time-estimate
information.) If major changes occur as the project is developed, inform the RME and the HQ
Geotechnical Office as soon as possible so that the geotechnical design can be adapted to the
changes without significant delay to the project.
610.02 References
610.02(1) Design Guidance
Construction Manual, M 41-01, WSDOT
Geotechnical Design Manual, M 46-03, WSDOT
Hydraulics Manual, M 23-03, WSDOT
Plans Preparation Manual, M 22-31, WSDOT
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01,
WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
WSDOT Pavement Policy – See Pavements website:
www.wsdot.wa.gov/business/materialslab/pavements/default.htm
The region Project Office is also responsible for providing survey locations of test holes once
the test holes have been drilled. The survey information includes the station, offset, elevation,
and test hole coordinates. Coordinates are the latitude and longitude or state plane coordinates
(north or south as appropriate), but not project coordinates.
610.04(6) Earthwork
610.04(6)(a) Project Definition
The designer contacts and meets with the RME (and the HQ Geotechnical Office as needed) at
the project site to conduct a field review to help identify the geotechnical issues for the project.
In general, if soil/rock conditions are poor and/or large cuts or fills are anticipated, the RME
requests that the HQ Geotechnical Office participate in the field review and reporting efforts.
The designer provides a description and location of the proposed earthwork to the RME as
follows:
• For widening of existing facilities, the anticipated width, length, and location of the
widening, relative to the current facility, are provided.
• For realignments, the approximate new location proposed for the facility is provided.
• Locations in terms of length can be by milepost or stations.
A brief conceptual-level report that summarizes the results of the investigation is provided
to the designer.
610.04(6)(b) Project Design
Geotechnical data necessary to allow completion of the PS&E-level design is compiled during
the design phase. This includes soil borings, testing, and geotechnical design based on final
geometric data. Detailed design of cut and fill slopes can be done once the roadway geometry
is established and geotechnical data are available. The purpose of this design effort is to
determine the maximum stable cut or fill slope and, for fills, the potential for short- and long-
term settlement. Also, the usability of the cut materials and the type of borrow needed for the
project (if any) are evaluated. Evaluate the use of soil bioengineering as an option for building
steeper slopes or to prevent surface erosion. (See Roadside Manual Chapter 740, Soil
Bioengineering, for more information.)
The designer requests a geotechnical report from the RME. The site data given in 610.04(4),
as applicable, is provided. It is important that the request for the geotechnical report be made
as early as possible in the design phase. Cost and schedule requirements to generate the report
are project-specific and can vary widely. The time required to obtain permits and rights of entry
must be considered when establishing schedule requirements.
The Geotechnical Design Manual, Chapter 24, summarizes the type of information and
recommendations that are typically included in the geotechnical report for earthwork. The
recommendations should include the background regarding analysis approach and any
agreements with the region or other customers regarding the definition of acceptable
level of risk.
The region Project Office uses the report to finalize design decisions for the project. To meet
slope stability requirements, additional right of way might be required or a wall might be needed.
Wall design is covered in Chapter 730. Construction timing might require importing material
rather than using cut materials. The report is used to address this and other constructibility issues.
The report is also used to proceed with completion of the PS&E.
610.04(6)(c) PS&E Development
Adequate geotechnical design information to complete the PS&E is typically received during
the design phase. Additional geotechnical work might be needed when right of way cannot be
acquired, restrictions are included in permits, or other requirements are added that result in
changes to the design.
Special provisions and plan details, if not received as part of the report provided during design,
are developed with the assistance of the RME or the HQ Geotechnical Office. The designer uses
this information, as well as the design phase report, to complete the PS&E documents. Both the
region Materials Laboratory and the HQ Geotechnical Office can review (if requested) the
contract plans before the PS&E review process begins. Otherwise, they will review the
contract plans during the normal PS&E review process.
is typically important to know, it is essential to have adequate time to determine the effect of
seasonal variations on groundwater.
The RME, with support from the HQ Geotechnical Office as needed, provides the following
information in addition to the overall requirements specified in the Geotechnical Design Manual,
when requested and where applicable, as part of the project geotechnical report:
• Soil boring logs.
• Soil pH and resistivity.
• Water table elevation.
• Soil infiltration rates (the highest rate for assessing spill containment/aquifer protection
and the long-term rate for determining pond capacity).
• Bearing capacity and settlement for hydraulic structure foundations.
• Slope stability for ponds.
• Retention berm/dam design.
• Potential for and amount of differential settlement along culverts and pipe arches and the
estimated time required for settlement to occur.
• Soil pressures and properties (primarily for underground detention vaults).
• Erosion potential.
• Geosynthetic design in accordance with Chapter 630.
• Recommendations for mitigation of the effects of soft or unstable soil on the hydraulic
structures.
• Recommendations for construction.
Note that retaining walls that are part of a pond, fish passage, and so on, are designed in
accordance with Chapter 730 and the Geotechnical Design Manual.
The designer uses the geotechnical information to:
• Finalize design decisions.
• Evaluate and mitigate environmental issues.
• Proceed with completion of the PS&E design. This includes determining the most cost-
effective hydraulic structure/pond to meet the desired objectives; locating and sizing ponds
and foundations for hydraulic structures; structural design; mitigating the effects of
settlement; and satisfying local jurisdictional requirements for design.
610.04(7)(c) PS&E Development
During PS&E development, the designer uses the information provided in the geotechnical report
to:
• Select pipe materials in accordance with corrosion, resistivity, and abrasion guidelines in the
Hydraulics Manual.
• Consider and include construction recommendations.
Additional design and specification guidance and support from the RME or the HQ Geotechnical
Office are sought as needed. Both sections provide careful review of the contract plans before the
PS&E review process begins, if requested. Otherwise, they will review the contract plans during
the normal PS&E review process.
610.04(9) Buildings, Park & Ride Lots, Communication Towers, and Rest Areas
In general, the RME functions as the clearinghouse for the geotechnical work to be conducted
in each of the phases, for technical review of the work if it is performed by consultants, or for
getting the work done in-house. For sites and designs that are more geotechnically complex, the
RME contacts the HQ Geotechnical Office for assistance. (See the Geotechnical Design Manual
for geotechnical investigation and design requirements for these types of facilities.)
The level of work in the Project Definition phase for unstable slopes is conceptual in nature, not
a final design. The geotechnical investigation generally consists of a field review, a more detailed
assessment of the unstable slope, review of the conceptual mitigation developed during the
programming phase of the project, and proposed modification (if any) to the original conceptual-
level unstable slope mitigation. The design phase geotechnical services cost and schedule,
including any required permits, are determined at this time. A brief conceptual-level report is
provided to the designer that summarizes the results of the Project Definition investigation.
610.04(11)(b) Project Design
Geotechnical information and field data necessary to complete the unstable slope mitigation
design is compiled during this design phase. This work includes, depending on the nature of the
unstable slope problem, test borings, rock structure mapping, geotechnical field instrumentation,
laboratory testing, and slope stability analysis. The purpose of this design effort is to provide
design-level geotechnical recommendations to stabilize the known unstable slope.
The designer requests a geotechnical report from the HQ Geotechnical Office through the RME.
The site data given in 610.04(4), as applicable, is provided along with the following information:
• A plan sheet showing the station and location of the proposed unstable slope mitigation
project.
• If requested, the Digital Terrain Model (DTM) files necessary to define the on-ground
topography of the project site (the limits of the DTM will have been defined during the
Project Definition phase).
It is important that the request for the geotechnical report be made as early as possible in the
design phase. Cost and schedule requirements to generate the report are project-specific and
can vary widely. Unstable slope design investigations might require geotechnical monitoring
of ground movement and groundwater over an extended period of time to develop the required
field information for the unstable slope mitigation design. The time required to obtain rights of
entry and other permits, as well as the long-term monitoring data, must be considered when
establishing schedule requirements for the geotechnical report.
In addition to the geotechnical report requirements specified in the Geotechnical Design Manual,
the HQ Geotechnical Office provides the following information as part of the project
geotechnical report (as applicable):
• Unstable slope design analysis and mitigation recommendations.
• Constructibility issues associated with the unstable slope mitigation.
• Appropriate special provisions for inclusion in the contact plans.
The region Project Office uses the geotechnical report to finalize the design decisions for the
project and the completion of the PS&E design.
610.04(11)(c) PS&E Development
Adequate geotechnical design information to complete the PS&E is typically obtained during the
project design phase. Additional geotechnical work might be needed when right of way cannot
be acquired, restrictions are included in permits, or other requirements are added that result in
changes to the design.
Special provisions, special project elements, and design details, if not received as part of the
design phase geotechnical report, are developed with the assistance of the RME and the HQ
Geotechnical Office. The designer uses this information in conjunction with the design phase
geotechnical report to complete the PS&E document. The RME and the HQ Geotechnical Office
can review the contract plans before the PS&E review begins, if requested. Otherwise, they will
review the contract plans during the normal PS&E review process.
• Blasting requirements, including limitations on peak ground vibrations and air blast over-
pressure if required.
• Usability of the excavated material, including estimates of shrink and swell.
• Constructibility issues associated with the rock excavation.
The region Project Office uses the geotechnical report to finalize the design decisions for the
project and the completion of the PS&E design for the rockslope elements of the project.
610.04(12)(c) PS&E Development
Adequate geotechnical design information to complete the PS&E is typically obtained during
the design phase. Additional geotechnical work might be needed when right of way cannot
be acquired, restrictions are included in permits, or other requirements are added that result
in change to the design.
Special provisions, special blasting requirements, and plan details, if not received as part of
the design phase geotechnical report, are developed with the assistance of the RME or the HQ
Geotechnical Office. The designer uses this information in conjunction with the design phase
geotechnical report to complete the PS&E documents. The RME and the HQ Geotechnical Office
can review (if requested) the contract plans before the PS&E review begins. Otherwise, they will
review the contract plans during the normal PS&E review process.
610.04(14) Geosynthetics
For design guidance on geosynthetics, refer to Chapter 630.
610.08 Documentation
610.08(1) Design Documentation
Refer to Chapter 300 for design documentation requirements.
Design Project
Identified
Region Determines
Source Required
RME Determines
Materials Source
RME Determines
Source Approved Source Not Approved
Source Status
RME Rejects
Geotechnical Report
Materials Site
RME Prepares
Materials Source Approval by Others
Report
HQ Materials Lab
Reviews Report
Materials Source in
Contract
620.01 General
Detailed criteria and methods that govern pavement design are in the Washington State
Department of Transportation (WSDOT) Pavement Policy, which is available from the Pavements
website: www.wsdot.wa.gov/business/materialslab/pavements/default.htm
The pavement design for all Design-Build project Request For Proposals (RFPs) will be conducted
by the State Materials Lab, Pavement Division.
Notes:
Weights shown are dry weights and corrections are required for water contents.
The tabulated weights for the materials are reasonably close; however, apply corrections in
the following order:
For specific gravity: Wt. = tabular wt. x specific gravity on surface report
2.65
For water content: Wt. = tabular wt. x (1 + free water % in decimals)
Exhibit 620-2 Estimating: Hot Mix Asphalt Pavement and Asphalt Distribution Tables
Fog Seal
Asphalt
Type of Tons/Mile Width (ft)
Application Tons* per
Application Emulsified
gal* per sy sy 10 11 12
Asphalt
Fog Seal CSS-1/CSS-1h 0.07 0.000292 1.7 1.9 2.1
*Quantities shown are retained (residual) asphalt.
Specific Data[1][2]
Hot Mix Asphalt Paving Quantities (tons/mile)*
Width Depth of Pavement (ft)
(ft) 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 0.55 0.60 0.65 0.70 0.75
4 161 241 321 402 482 563 643 723 804 884 964 1045 1125 1206
6 241 362 482 603 723 844 964 1085 1206 1326 1447 1567 1688 1808
8 321 482 643 804 964 1125 1286 1447 1607 1768 1929 2090 2250 2411
10 402 603 804 1005 1206 1407 1607 1808 2009 2210 2411 2612 2813 3014
11 442 663 884 1105 1326 1547 1768 1989 2210 2431 2652 2873 3094 3315
12 482 723 964 1206 1447 1688 1929 2170 2411 2652 2893 3135 3376 3617
22 884 1326 1768 2210 2652 3094 3536 3978 4421 4863 5305 5747 6189 6631
24 964 1447 1929 2411 2893 3376 3858 4340 4822 5305 5787 6269 6751 7234
*Based on 137 lbs/sy (0.0685 tons/sy) of 0.10 ft compacted depth = 2.05 tons/cy
Notes:
[1] The specific gravity of the aggregate will affect the weight of aggregate in the completed mix.
[2] Quantities shown do not provide for widening, waste from stockpile, or thickened edges.
First Application 0.50 2933 11.8 3227 13.0 3520 14.1 CRS-2P
Crushed Screenings 3/4 inch – 1/2 inch 35 0.0146 103 86 113 94 123 103
Second Application 0.48 2787 11.2 3065 12.3 3344 13.4 CRS-2P
Crushed Screenings 1/2 inch – No. 4 32 0.0121 93 71 103 78 113 85
Choke Stone No. 4 – 0 5 0.0017 15 10 16 11 18 12
Totals 72 0.0284 211 167 232 183 254 200 0.98 5720 23.0 6292 25.3 6864 27.5
First Application 0.50 2933 11.8 3227 13.0 3520 14.1 CRS-2P
Crushed Screenings 1/2 inch – No. 4 35 0.0132 102 77 113 85 123 93
Second Application 0.48 2787 11.2 3065 12.3 3344 13.4 CRS-2P
Crushed Screenings 1/2 inch – No. 4 32 0.0121 93 71 103 78 113 85
Choke Stone No. 4 – 0 5 0.0017 15 10 16 11 18 12
Totals 72 0.0270 210 158 232 174 254 190 0.98 5720 23.0 6292 25.3 6864 27.5
Seal Coats 5/8 inch – No. 4
Seal Coat 0.53 3109 12.5 3420 13.7 3731 15.0 CRS-2P
Crushed Screenings 5/8 inch – No. 4 35 0.0130 102 76 113 84 124 92
Notes:
[1] Quantities shown do not provide for widening, waste from stockpile, or thickened edges.
[2] Quantities of asphalt shown are based on 60°F temperature. Recompute to the application temperature for the particular grade.
[3] The column “Basic Asphalt Used” is shown for the purpose of conversion to proper weights for the asphalt being used and does not imply that
the particular grade shown is required for the respective treatment.
[4] For stress-absorbing membrane (rubberized asphalt), increase asphalt by 25%.
Exhibit 620-4 Estimating: Base and Surfacing Typical Section Formulae and Example
WS
S1
d S
S2
Pavement Section Shoulder Section
A
d WS 1 / S S1 2 S WS2 1 / S S
21 SS 2
1
2
1 / S 0.02
21 0.05S
2
2
21 0.02S 2
21 0.05S 2
*Limit: Positive Values of A only when d = WS(0.03)
Shoulder Section
Shldr. Side Quantity in Tons Per Mile*
Width Slope Case Surfacing Depth (ft)
Ws (ft) S:1 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50
1 73 148 226 304 385 468 553 639 728 818
2 171 251 333 417 504 592 682 774 869 965
2
3 N/A N/A 131 205 281 360 440 522 605 691
4 73 149 226 306 387 470 556 643 733 824
1 74 150 230 313 398 486 577 671 768 868
2 178 262 350 442 536 634 734 838 945 1056
3
3 N/A N/A 131 206 285 366 450 537 627 720
4 74 151 231 315 402 492 585 681 780 883
4
1 74 153 235 321 411 505 603 705 810 920
2 185 275 370 469 572 681 793 910 1032 1158
4
3 N/A N/A 131 208 288 373 461 554 650 750
4 75 154 237 326 418 516 617 724 834 950
1 75 157 245 339 439 545 658 776 901 1032
2 204 307 417 535 661 794 936 1085 1242 1406
6
3 N/A N/A 131 210 296 387 485 589 699 815
4 76 160 252 351 459 574 696 827 965 1111
1 109 221 334 449 566 685 806 929 1053 1180
2 325 444 565 688 812 939 1068 1199 1332 1467
2
3 N/A N/A N/A 239 349 461 575 691 809 929
4 110 221 335 450 568 687 809 933 1058 1186
1 110 223 339 457 579 703 830 961 1094 1230
2 338 462 590 722 856 994 1134 1278 1426 1576
3
3 N/A N/A N/A 239 350 464 581 701 824 949
4 110 223 340 460 583 709 838 970 1106 1245
6
1 110 225 343 466 592 722 856 994 1136 1282
2 352 483 619 760 905 1055 1209 1368 1531 1699
4
3 N/A N/A N/A 239 351 467 587 711 839 971
4 111 226 346 470 599 733 871 1013 1160 1311
1 112 229 353 483 620 762 911 1066 1227 1394
2 386 534 690 853 1025 1204 1391 1585 1788 1998
6
3 N/A N/A N/A 239 353 474 600 733 871 1016
4 112 233 360 496 640 791 950 1116 1291 1473
1 146 293 443 594 747 902 1059 1218 1379 1541
2 526 683 843 1004 1167 1333 1500 1670 1841 2015
2
3 N/A N/A N/A N/A 376 522 670 820 972 1125
4 146 293 443 595 749 904 1062 1222 1384 1548
1 146 295 447 602 760 920 1084 1250 1419 1591
2 546 711 879 1050 1224 1402 1583 1766 1954 2144
3
3 N/A N/A N/A N/A 376 523 673 825 981 1139
4 146 296 448 604 763 926 1091 1260 1432 1607
8
1 147 297 452 610 773 939 1109 1284 1462 1644
2 568 741 919 1101 1288 1479 1675 1875 2080 2290
4
3 N/A N/A N/A N/A 376 524 675 831 990 1153
4 147 298 454 615 780 950 1124 1302 1486 1673
1 148 302 462 628 801 979 1164 1355 1552 1755
2 622 816 1017 1226 1443 1668 1900 2140 2388 2643
6
3 N/A N/A N/A N/A 376 525 681 842 1009 1183
4 149 305 469 641 820 1008 1203 1406 1616 1835
*Tabulated quantities are based on compacted weight of 1.85 tons/yd 3
Shoulder Section
Shldr. Side Quantity in Tons Per Mile*
Width Slope Case Surfacing Depth (ft)
Ws (ft) S:1 0.55 0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.95 1.00
1 910 1004 1100 1198 1297 1399 1502 1608 1715 1824
2 1063 1163 1266 1370 1476 1585 1695 1807 1922 2038
2
3 779 868 960 1053 1148 1245 1344 1445 1548 1652
4 918 1013 1110 1210 1311 1415 1520 1628 1738 1849
1 971 1076 1185 1296 1410 1527 1647 1770 1896 2024
2 1169 1286 1406 1529 1655 1785 1918 2053 2193 2335
3
3 816 914 1016 1120 1228 1338 1451 1567 1686 1807
4 989 1098 1210 1326 1444 1566 1691 1820 1951 2086
4
1 1034 1151 1273 1398 1528 1661 1798 1939 2085 2234
2 1289 1424 1564 1708 1857 2010 2168 2330 2497 2668
4
3 855 963 1075 1191 1311 1435 1562 1694 1830 1969
4 1070 1194 1323 1456 1594 1737 1884 2035 2191 2352
1 1169 1312 1462 1617 1779 1947 2121 2301 2488 2680
2 1579 1759 1947 2142 2346 2557 2776 3002 3237 3479
6
3 937 1066 1200 1341 1488 1641 1800 1966 2138 2315
4 1265 1426 1596 1773 1957 2150 2350 2558 2774 2998
1 1308 1438 1570 1704 1840 1978 2117 2259 2402 2548
2 1603 1742 1883 2026 2171 2318 2467 2618 2771 2926
2
3 1050 1174 1299 1426 1555 1686 1819 1954 2090 2229
4 1315 1447 1581 1716 1854 1994 2135 2279 2425 2573
1 1369 1510 1655 1802 1953 2106 2262 2421 2583 2748
2 1729 1886 2046 2209 2376 2545 2718 2894 3073 3255
3
3 1078 1209 1343 1480 1620 1763 1909 2058 2209 2363
4 1387 1532 1681 1832 1987 2145 2306 2471 2638 2809
6
1 1432 1586 1743 1905 2070 2240 2413 2591 2772 2957
2 1871 2048 2229 2415 2606 2801 3000 3204 3412 3625
4
3 1106 1246 1389 1537 1688 1843 2003 2166 2333 2504
4 1467 1628 1793 1963 2137 2315 2499 2686 2878 3075
1 1567 1746 1932 2124 2322 2526 2736 2953 3175 3404
2 2215 2441 2674 2916 3164 3421 3685 3957 4237 4525
6
3 1167 1325 1488 1658 1833 2015 2203 2398 2598 2805
4 1663 1861 2066 2279 2500 2729 2965 3209 3461 3721
1 1706 1872 2040 2211 2383 2557 2732 2910 3090 3271
2 2190 2367 2547 2728 2912 3097 3285 3475 3666 3860
2
3 1281 1438 1597 1758 1921 2086 2253 2422 2592 2765
4 1713 1881 2051 2223 2397 2573 2751 2930 3112 3296
1 1766 1944 2125 2309 2495 2685 2877 3072 3271 3472
2 2338 2534 2734 2937 3144 3353 3566 3782 4001 4223
3
3 1300 1464 1631 1801 1974 2149 2328 2509 2693 2880
4 1785 1966 2151 2339 2530 2724 2921 3122 3326 3533
8
1 1830 2020 2214 2411 2613 2819 3028 3242 3459 3681
2 2504 2722 2945 3172 3404 3641 3882 4128 4378 4632
4
3 1320 1491 1666 1845 2028 2215 2405 2600 2799 3001
4 1865 2062 2263 2469 2679 2894 3114 3337 3566 3799
1 1965 2181 2402 2630 2864 3105 3351 3604 3863 4128
2 2907 3178 3457 3743 4038 4340 4650 4967 5292 5626
6
3 1363 1549 1741 1940 2144 2355 2572 2795 3024 3259
4 2061 2295 2536 2786 3043 3308 3580 3861 4149 4445
*Tabulated quantities are based on compacted weight of 1.85 tons/yd 3
Shoulder Section
Shoulder Section
Shoulder Section
Quantity in Tons Per Mile*
Shldr. Side
Width Slope Case Surfacing Depth (ft)
Ws (ft) S:1
1.05 1.10 1.15 1.20 1.25 1.30 1.35 1.40 1.45 1.50
1 1935 2048 2163 2279 2398 2518 2640 2765 2891 3019
2 2157 2277 2399 2524 2650 2779 2909 3042 3176 3312
2
3 1759 1867 1977 2089 2203 2319 2437 2557 2678 2802
4 1963 2078 2196 2315 2437 2561 2686 2814 2943 3075
1 2156 2290 2428 2568 2711 2857 3006 3157 3312 3470
2 2480 2629 2781 2936 3094 3255 3420 3588 3759 3933
3
3 1932 2059 2190 2323 2459 2598 2740 2885 3033 3183
4 2223 2364 2509 2656 2806 2960 3117 3277 3441 3607
4
1 2387 2543 2704 2869 3038 3210 3387 3567 3752 3940
2 2844 3025 3210 3399 3593 3792 3995 4202 4415 4631
4
3 2113 2260 2412 2567 2726 2890 3057 3228 3403 3582
4 2517 2686 2860 3039 3222 3410 3602 3799 4000 4206
1 2879 3084 3295 3513 3736 3966 4201 4443 4691 4946
2 3729 3986 4252 4525 4806 5094 5391 5695 6007 6327
6
3 2499 2689 2886 3088 3297 3512 3733 3960 4193 4433
4 3229 3468 3715 3969 4232 4502 4779 5065 5358 5659
1 2695 2844 2995 3147 3302 3459 3617 3778 3940 4104
2 3083 3242 3403 3566 3731 3898 4067 4238 4411 4586
2
3 2369 2511 2655 2802 2949 3099 3251 3404 3560 3717
4 2722 2874 3028 3184 3341 3501 3663 3827 3993 4160
1 2916 3086 3260 3436 3615 3798 3983 4170 4361 4555
2 3440 3629 3821 4016 4214 4416 4620 4828 5039 5253
3
3 2521 2681 2844 3010 3179 3351 3525 3703 3883 4067
4 2983 3160 3341 3524 3711 3901 4094 4290 4490 4692
6
1 3146 3339 3536 3737 3942 4151 4364 4580 4801 5026
2 3843 4065 4291 4523 4758 4998 5243 5492 5746 6004
4
3 2679 2858 3041 3228 3418 3613 3812 4014 4221 4431
4 3276 3482 3692 3907 4127 4350 4579 4812 5049 5291
1 3639 3880 4127 4381 4640 4906 5178 5456 5741 6031
2 4820 5123 5434 5753 6079 6413 6755 7105 7462 7827
6
3 3017 3236 3461 3693 3930 4174 4423 4679 4941 5210
4 3989 4264 4547 4837 5136 5442 5756 6078 6407 6745
1 3454 3640 3827 4016 4207 4399 4594 4791 4989 5189
2 4055 4253 4452 4654 4858 5063 5271 5480 5692 5906
2
3 2939 3115 3293 3473 3655 3839 4024 4212 4401 4592
4 3482 3670 3860 4052 4246 4442 4640 4840 5042 5246
1 3675 3882 4092 4304 4520 4738 4959 5183 5410 5640
2 4449 4677 4909 5144 5382 5624 5869 6116 6367 6622
3
3 3070 3263 3459 3658 3859 4064 4271 4481 4695 4911
4 3743 3956 4173 4392 4615 4841 5071 5303 5539 5778
8
1 3906 4135 4368 4606 4847 5092 5341 5593 5850 6111
2 4891 5155 5423 5696 5973 6255 6541 6832 7127 7427
4
3 3208 3418 3632 3851 4073 4299 4529 4763 5001 5243
4 4036 4278 4524 4775 5031 5291 5556 5825 6098 6376
1 4399 4676 4959 5249 5545 5847 6155 6469 6790 7116
2 5966 6315 6671 7035 7407 7787 8174 8569 8972 9383
6
3 3501 3749 4002 4262 4529 4801 5079 5364 5655 5952
4 4748 5060 5379 5706 6040 6383 6733 7091 7456 7830
*Tabulated quantities are based on compacted weight of 1.85 tons/yd3
Shoulder Section
Shldr. Side Quantity in Tons Per Mile*
Width Slope Case Surfacing Depth (ft)
Ws (ft) S:1 1.55 1.60 1.65 1.70 1.75 1.80 1.85 1.90 1.95 2.00
1 3148 3280 3414 3549 3687 3826 3967 4110 4255 4402
2 3451 3591 3734 3878 4025 4173 4324 4477 4631 4788
2
3 2927 3054 3183 3314 3447 3582 3718 3857 3997 4139
4 3209 3344 3482 3622 3763 3907 4053 4201 4350 4502
1 3630 3793 3959 4129 4300 4475 4653 4834 5017 5203
2 4110 4291 4475 4662 4852 5045 5242 5441 5644 5850
3
3 3337 3493 3652 3814 3979 4147 4318 4492 4668 4848
4 3777 3950 4126 4305 4488 4673 4862 5054 5250 5448
4
1 4133 4329 4529 4733 4941 5153 5369 5589 5812 6040
2 4852 5078 5308 5543 5782 6026 6274 6527 6784 7046
4
3 3764 3951 4142 4337 4535 4738 4944 5155 5369 5587
4 4416 4631 4850 5074 5302 5535 5773 6015 6261 6512
1 5206 5473 5745 6024 6310 6601 6898 7202 7512 7828
2 6654 6989 7332 7683 8041 8407 8781 9163 9552 9950
6
3 4678 4930 5188 5452 5722 5999 6282 6570 6865 7166
4 5968 6285 6609 6941 7281 7628 7984 8347 8718 9096
1 4270 4438 4608 4779 4953 5128 5306 5485 5666 5849
2 4763 4942 5123 5306 5491 5678 5868 6059 6252 6447
2
3 3876 4038 4201 4365 4532 4701 4871 5044 5218 5394
4 4330 4502 4676 4852 5030 5210 5391 5575 5761 5949
1 4752 4951 5153 5359 5567 5778 5992 6208 6428 6651
2 5471 5691 5915 6142 6372 6605 6842 7082 7325 7571
3
3 4253 4442 4634 4829 5026 5227 5430 5637 5846 6058
4 4898 5107 5320 5535 5754 5976 6201 6429 6660 6895
6
1 5254 5486 5723 5963 6207 6455 6707 6963 7223 7487
2 6267 6534 6806 7082 7363 7648 7938 8233 8532 8835
4
3 4645 4864 5086 5312 5542 5776 6014 6256 6501 6751
4 5537 5788 6044 6304 6569 6838 7111 7389 7672 7959
1 6328 6630 6939 7254 7576 7903 8237 8577 8923 9275
2 8200 8581 8969 9365 9769 10181 10600 11028 11463 11905
6
3 5484 5765 6051 6344 6643 6949 7260 7578 7901 8231
4 7090 7442 7803 8171 8547 8931 9322 9721 10128 10543
1 5391 5595 5801 6009 6219 6431 6644 6859 7077 7296
2 6121 6339 6559 6780 7004 7230 7457 7687 7919 8153
2
3 4785 4980 5177 5376 5577 5779 5984 6190 6398 6608
4 5452 5660 5870 6082 6296 6512 6730 6950 7172 7396
1 5873 6109 6347 6589 6833 7080 7330 7583 7839 8098
2 6879 7140 7403 7670 7940 8214 8490 8770 9053 9339
3
3 5129 5351 5576 5803 6034 6267 6503 6743 6985 7229
4 6020 6265 6514 6765 7020 7278 7539 7804 8071 8342
8
1 6376 6644 6917 7193 7473 7758 8046 8338 8634 8934
2 7731 8040 8354 8671 8994 9321 9652 9988 10329 10674
4
3 5488 5738 5992 6249 6511 6776 7046 7319 7596 7877
4 6659 6946 7238 7534 7835 8140 8450 8764 9083 9406
1 7449 7788 8133 8485 8842 9206 9575 9951 10333 10722
2 9801 10227 10661 11103 11552 12009 12474 12947 13427 13915
6
3 6255 6565 6880 7202 7530 7864 8204 8550 8903 9262
4 8211 8600 8997 9401 9813 10233 10661 11096 11539 11990
*Tabulated quantities are based on compacted weight of 1.85 tons/yd3
Shoulder Section
Shoulder Section
630.01 General
Geosynthetics include a variety of manufactured products that are used by the
Washington State Department of Transportation (WSDOT) in drainage, earthwork,
erosion control, and soil reinforcement applications.
The following geosynthetic applications are addressed in the Standard Specifications
for Road, Bridge, and Municipal Construction (Standard Specifications):
• Low survivability underground drainage
• Moderate survivability underground drainage
• Separation
• Soil stabilization
• Moderate survivability permanent erosion control
• High survivability permanent erosion control
• Ditch lining
• Temporary silt fence
The Standard Specifications addresses geosynthetic properties as well as installation
requirements and are not site-specific. The geosynthetic properties provided are
based on the range of soil conditions likely to be encountered in Washington for the
applications defined. Other applications, such as prefabricated edge drains, pond
liners, and geotextile retaining walls, are currently handled by special provision.
Design responsibilities are discussed in 630.05 and illustrated in Exhibits 630-4
and 630-5.
This chapter does not address applications where geosynthetics are used to help
establish vegetation through temporary prevention of erosion (vegetation mats).
630.02 References
(1) Design Guidance
Highway Runoff Manual, M 31-15, WSDOT
Hydraulics Manual, M 23-03, WSDOT
Plans Preparation Manual, M 22-31, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard
Specifications), M 41-10, WSDOT
WSDOT Pavement Policy, available at the Pavements website:
www.wsdot.wa.gov/business/materialslab/pavements/default.htm
The application will also affect the geosynthetic installation conditions. These
installation conditions influence the remaining geosynthetic properties needed,
based on the survivability level required.
(f) Geosynthetic Survivability
The ability of the geosynthetic to resist installation conditions without significant
damage, such that the geosynthetic can function as intended. Survivability affects
the strength properties of the geosynthetic required.
Obtain soil samples for geotextile underdrain design every 300 feet along the
roadway alignment, using hand holes, and at major soil type transitions. This may
be spread to every 1000 feet if the soil conditions appear to be uniform. Use existing
soil data where feasible instead of taking new soil samples.
If soil conditions vary widely along the alignment where underground drainage
geotextile is anticipated, different classes of drainage geotextile may be required for
specific sections of a continuous system.
Strength properties for the underground drainage geotextile depend on the
survivability level required to resist installation stresses.
Low survivability designates that the installation stresses placed on the geotextile
will be relatively low, requiring only moderate geotextile strength to resist potentially
damaging installation conditions. Examples of low survivability level underground
drainage applications include:
• Trench drains.
• Drains placed behind walls or other structures to drain the backfill.
• A geotextile filter sheet placed behind a gabion wall to prevent fines from
being washed through the gabion wall face. Trench depths, or the height of the
geotextile filter sheet behind gabion walls, must be less than or equal to 6 feet for
the low survivability level.
In moderate survivability applications, significant installation stresses may occur,
requiring higher geotextile strength. Examples of the moderate survivability
application include:
• Trench drains with a depth of greater than 6 feet.
• A geotextile filter sheet behind a gabion wall with a height greater than 6 feet.
• Any area drain.
An area drain is defined as a geotextile placed over or under a horizontal-to-
moderately sloping (1.5H:1V or flatter slope) layer of drainage aggregate. Examples
of area drains include:
• Drainage layers over cut-and-cover tunnels.
• Rock buttress drainage.
• Permeable base beneath highway pavement (see the WSDOT Pavement Policy
for additional information on permeable bases).
• A parking lot drainage layer.
Note that pipe wrapping (the geotextile is wrapped around the surface of the pipe)
is not included as an underground drainage application.
Locate the geotextile such that it will function as intended. For example, if the
objective is to keep the drainage aggregate surrounding a drain pipe clean, locate
the geotextile so that it completely separates the drainage aggregate from more silty
surrounding soils, which may include native soils as well as relatively silty roadway
base or fill materials.
Consider the flow path of any groundwater or surface water when locating
the geotextile.
The flow path from the geotextile, as part of the groundwater drainage, is typically
directed to a surface water conveyance system. Design of surface water conveyance
is guided by the Hydraulics Manual. The surface water conveyance must be low
enough to prevent backflow and charging of the groundwater drainage—typically,
by matching inverts of groundwater drainage to crowns of surface water conveyance
pipes. A 1-foot allowance is usually applied when connecting to open water
or ditches.
(2) Separation
Geotextile used for separation must prevent penetration of relatively fine grained
subgrade soil into the ballast or other roadway or parking lot surfacing material
to prevent contamination of the surfacing material (the separation function). This
application may also apply to situations other than beneath roadway or parking
lot surfacing where it is not necessary for water to drain through the geotextile
unimpeded (filtration), but where separation of two dissimilar materials is required.
Separation geotextile should only be used in roadway applications where
the subgrade is can be prepared and compacted as required in the Standard
Specifications, but without removal and replacement of the subgrade soil with
granular material. Such removal and replacement defeats the purpose of the
geotextile separator.
Separation geotextile placed beneath roadway surfacing is feasible if the subgrade
resilient modulus is greater than 5,800 psi and if a saturated fine sandy, silty, or
clayey subgrade is not likely to be present. Note that the feasibility of separation
geotextile may be dependent on the time of year and weather conditions expected
when the geotextile is to be installed.
For separation applications, a geotextile is not needed if the subgrade is dense
and granular (silty sands and gravels), but is not saturated fine sands. In general,
a separation geotextile is not needed if the subgrade resilient modulus is greater
than 15,000 psi.
Soil stabilization geotextile is used in roadway applications if the subgrade is too soft
and wet to be prepared and compacted as required in the Standard Specifications. Soil
stabilization geotextile is placed directly on the soft subgrade material, even if some
overexcavation of the subgrade is performed. Backfill to replace the overexcavated
subgrade is not placed below the geotextile soil stabilization layer, as this would
defeat the purpose of the geotextile.
Anticipate the need for soil stabilization geotextile if the subgrade resilient modulus
is less than or equal to 5,800 psi, or if a saturated fine sandy, silty, or clayey subgrade
is likely to be present.
Consider the flow path of any groundwater or surface water when locating the soil
stabilization geotextile and when selecting the geotextile to be used. For saturated
fine sandy or silty subgrades, water must be able to flow from the subgrade
through the geotextile soil stabilization layer during the pumping action caused
by traffic loads.
Even if the subgrade is not anticipated to be saturated based on available data, if the
subgrade is silty or clayey and it is anticipated that the geotextile will be installed
during prolonged wet weather, a soil stabilization geotextile may still be needed.
Soil stabilization geotextile should not be used for roadway fills greater than 5 feet
high or when extremely soft and wet silt, clay, or peat is anticipated at the subgrade
level (for example, the deposits encountered in wetlands). In such cases, the
reinforcement function becomes more dominant, requiring a site-specific design.
If soil conditions vary widely along the alignment where permanent erosion control
geotextile is anticipated, different classes of erosion control geotextile may be
required for specific sections of a continuous system.
Examples of the permanent erosion control application are the placement of
geotextile beneath riprap or gabions along drainage channels, shorelines, and
waterways; around bridge piers; and under slope protection for highway cut or
fill slopes.
If a moderate survivability geotextile is to be used, the geotextile must be protected
by a 12-inch aggregate cushion and be placed on slopes of 2H:1V or flatter to keep
installation stresses to a relatively low level. Large stones can cause significant
damage to a moderate survivability geotextile if the geotextile is not protected in
this manner. If these conditions are not met, then a high survivability erosion control
geotextile must be used.
pipe through the geotextile. (Blinding is the coating of the geotextile surface with soil
particles such that the openings are effectively plugged.) If the geotextile openings
(AOS) are designed to be small enough to capture most of the suspended soil
particles, the geotextile will likely blind, reducing the permeability enough to allow
water to overtop the fence. Therefore, it is best to allow some geotextile openings
that are large enough to allow the silt-sized particles to easily pass through. Even if
some silt particles pass through the fence, the water flow rate below the fence will be
decreased and the volume of silt-laden water passing through the geotextile is likely
to be relatively small and the water is partially filtered.
The geotextile apparent opening size (AOS) and permittivity are typically used
to specify the filtration performance of geotextiles. The geotextile function in silt
fence applications is more complex than this and AOS and permittivity do not relate
directly to how well a silt fence will perform. However, nominal values of AOS and
permittivity can be specified such that the types of geotextile products known to
perform satisfactorily in this application are selected. These values are provided in
the Standard Specifications.
The source of load on the geotextile is from silt buildup at the fence and water
ponding. The amount of strength required to resist this load depends on whether or
not the geotextile is supported with a wire or polymer grid mesh between the fence
posts. Obviously, unsupported geotextile must have greater strength than supported
geotextile. If the strength of the geotextile or its support system is inadequate, the
silt fence could fail. Furthermore, unsupported geotextile must have enough stiffness
that it does not deform excessively and allow silt-laden water to go over the top of
the fence.
(a) Need for Silt Fence
The need for a silt fence can be anticipated where construction activities
disturb and expose soil that could erode. The ground surface is considered
disturbed if vegetative cover is at least partially removed over a significant
area by construction activities. Consider whether or not silt-laden runoff
water from the disturbed area can reach an environmentally sensitive area or a
constructed stormwater system. If the exposed soil is a clean sand or gravel or
if a significant zone of heavy vegetative cover separates the exposed soil from
the environmentally sensitive area, a silt fence may not even be needed. Contact
the Headquarters (HQ) Hydraulics Section for help in determining whether or not
a silt fence is needed in such situations.
(b) Feasibility of Silt Fence
The feasibility of a geotextile silt fence depends on the magnitude of water flow
to the fence, the steepness of the slope behind the fence ,and whether or not flow
is concentrated at the fence. If the silt fence is not feasible, alternative erosion
control methods may be needed (see the Highway Runoff Manual).
Consider all feasible erosion control options in terms of potential effectiveness
and economy before making the final decision to use a silt fence. Select the best
option for the site conditions, including site geometry and contours, soil type, and
rainfall potential. Consider silt fences for temporary erosion control in disturbed
areas in the following circumstances:
• Fully covering disturbed areas temporarily with polyethylene sheeting or
other temporary covering is not feasible or practical.
The sheet flow length represents the area contributing runoff water from
precipitation. The sheet flow length is defined in Exhibit 630-8. The sheet
flow lengths provided in Exhibit 630-2 were determined assuming a bare soil
condition, with the soil classified as a silt. These are worst-case assumptions
because less runoff would be expected for sand or gravel soils or when some
vegetation is present.
The sheet flow length is usually equal to or greater than the disturbed soil slope
length. However, undisturbed sloping ground above the disturbed slope area may
also contribute runoff to the silt fence area. The length of undisturbed sloping
ground above the disturbed slope to be included in the total contributing slope
length depends on the amount and type of vegetation present, the slope steepness,
and the degree of development above the slope.
If unsure whether the proposed silt fence meets the requirements in
Exhibit 630-2, contact the HQ Hydraulics Section for assistance.
Allowable Contributing Area
Average or Ditch Ditch or Swale
per Foot of Ditch or Swale
Swale Grade Storage Length
Storage Width
16% 13 ft 200 ft2
10% 20 ft 250 ft2
5% 40 ft 300 ft2
4% 50 ft 400 ft2
3% 65 ft 500 ft2
2% 100 ft 600 ft2
1% 200 ft 1000 ft2
Where this is impossible, and a silt fence must be used, a special design may
be necessary.
Temporary silt fences are sometimes used to completely encircle underground
drainage inlets or other similar features to prevent silt from entering the drainage
system. This is acceptable, but the silt fence functions primarily as a barrier, and
not as a ponding or filtering mechanism, unless the drainage inlet is in a
depression that is large enough to allow water to pond behind the silt fence.
• If the drainage inlet and silt fence are not in a large enough depression, silt-
laden water will simply be directed around the fence and must be captured
by another fence or sedimentation pond downslope.
• If the depression is deep, locate the silt fence no more than 2 feet below the
top of the depression to prevent overtopping. A site-specific design may be
needed if the silt fence is located deeper than 2 feet within the depression.
It may be necessary to relocate silt fences during the course of a construction
project as cuts and fills are built or as disturbed areas change. An erosion
control/silt fence plan that accounts for the anticipated construction stages
(and eventual removal) should be developed. Do not assume that one silt fence
location can routinely be used for the entire life of the contract. Periodically
check the locations in the field during the construction project, and field-adjust
the silt fence locations as necessary to ensure the silt fences function as intended.
• Soil in the vicinity of the proposed geotextile location that consists of alternate
thin layers of silt or clay with potentially water-bearing sand layers on the order
of 1 to 3 inches thick or less.
• Soil known through past experience to be problematic for geosynthetic drains.
• Drains in native soil behind structures except drains contained within granular
backfill.
• Drains designed to stabilize unstable slopes.
• Drains designed to mitigate frost heave.
In such cases, obtain assistance from the HQ Materials Laboratory, Geotechnical
Services DivisionOffice. To initiate the special design, provide a plan and cross
section showing:
• The geosynthetic structure to be designed.
• The structure’s relative location to other adjacent structures that it could
potentially affect.
• The structure’s intended purpose.
• Any soil data in the vicinity.
Consider a site-specific design for temporary silt fences:
• If silt fence must be used in intermittent streams or where a significant portion
of the silt fence functions as a barrier that directs flow to the lower portions of
the silt fence.
• If the fence must be located on steep slopes.
• In situations not meeting the requirements in Exhibits 630-2 and 630-3.
• If the 2-year, 24-hour design storm for the site is greater than the 3 inches
assumed for the development of Exhibits 630-2 and 630-3.
• Where concentrated flow is anticipated.
• If closer than 7 feet from an environmentally sensitive area.
• If more than 2 feet of storage depth is needed.
For a site-specific temporary silt fence design, obtain assistance from the HQ
Hydraulics Section. To initiate the design, send the following information to
the HQ Hydraulics Section and a copy to the HQ Materials Laboratory,
Geotechnical Services DivisionOffice:
• Plan sheets showing proposed silt fence locations and grading contours.
• Estimate of the area contributing runoff to each silt fence, including percentage
and general type of vegetative cover within the contributing area.
• Any available site soil information.
For all site-specific designs of applications not covered by the Standard
Specifications, complete plans and special provisions are needed. In general, for site-
specific designs of Standard Specifications applications, only a minor modification
of the appropriate geotextile property table will be needed.
The region Project Manager incorporates the plan details and special provisions into
the PS&E.
630.07 Documentation
For the list of documents required to be preserved in the Design Documentation Package and
the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev/ Refer to Chapter 300 for design documentation
requirements.
RPM selects/modifies
RPM = Region Project Manager appropriate details from the
RML = Region Materials Laboratory Standard Plans and
HQGSD = HQ Geotechnical Services Division completes silt fence plans
Surfacing
Gravel Buttress
Base Course
Subgrade < 6 ft
Geotextile
Geotextile
Surfacing
> 6 ft
Wall Backfill
Geotextile > 6 ft
Geotextile
Surfacing
Base Course
Subgrade
Geotextile
Surfacing
New Pavement
Base Course
Subgrade Geotextile
Existing Pavement
Riprap
Aggregate Cushion
Geotextile
Riprap
Geotextile
< 16 ft
Quarry Spalls
1
2 min.
Geotextile
K. Ditch Lining
Fence
Geotextile
Runoff
Geotextile
Fence
Geotextile off
Run
Fence
Wall Top
Surfacing
Base Course
Subgrade
Soil Nail
Sand Backfill
Wall Base
Prefabricated Geotextile
Wrapped Drain Prefabricated Geotextile
Wrapped Drain Strip
Geosynthetic
Geosynthetic
Layers Layers
Fill
Base Course
gth*
lo p e Len
nal S
A dditio
)
(L
h
n gt
Le
o pe e
Sl n of
Sl o p
rti o d
Po isturb
e
Not D
to
u e es
ti
o il D tivi
S Ac
b e d io n
r ct
i stu stru
D n
Co
Lowest Point
at top of
d
Geotextile
Silt Fence
Storage Length
d
Cross Section
of Ditch or Swale
Bottom of Ditch or Swale
Storage Width
Top of Slope
Top of Slope
Bottom of Slope
Silt Fence
Sheet Flow
Top of Slope
2 ft. min
Silt fence plan and profile illustrating how silt fence will capture
runoff water and not allow water to run around ends of fence.
Silt Fence
1
3 min
Gravel
Check Dam 1 ft
Ground Line A
max.
10 ft
Profile
Geotextile
Ground Line
1 ft
700.01 General
This chapter presents the project development process used by the Washington State
Department of Transportation (WSDOT) in the regions and the Headquarters (HQ)
Bridge and Structures Office to determine the roles and responsibilities for projects
with structures during the project development phase of a project. This chapter
complements WSDOT’s Project Management Online Guide:
http://www.wsdot.wa.gov/projects/projectmgmt/pmog.htm
For design procedures, see Division 7 chapters and the Bridge Design Manual.
The primary objective of this process is to provide a consistent means of selecting
a bridge design team to perform the structural design work, whether it is by a
consultant or the HQ Bridge and Structures Office.
If the local agency will be requesting any services from WSDOT, the local agency
will contact WSDOT’s Local Programs Engineer, who will help define the level
of WSDOT’s involvement in design and construction.
700.02 Procedures
The flow diagram (see Exhibit 700-1) begins at the left with the initial approval
and funding of the project and ends at the right with the start of the project
delivery process.
After a project is programmed, WSDOT is tasked with confirming the project scope
and defining the structural team’s level of involvement in design and construction.
If a consultant is not used, the bridge design work will be performed by the HQ
Bridge and Structures Office. If a consultant is used, the region and the HQ Bridge
and Structures Office will determine the level of involvement and responsibility
for the design.
Agreements defining the level of involvement and responsibility will be developed
and executed between the region office responsible for project development and the
HQ Bridge and Structures Office, and the appropriate project delivery process will
be implemented.
More information on this process and the desired outcomes is available on the
HQ Bridge and Structures Office’s home page:
http://www.wsdot.wa.gov/bridge/structures
Considerations:
· On/off state system
· In/out state ROW
· Funding source
No
Potential B&SO level
of involvement:
· Administrator
Confirm Project Delivery · Designer
Process: · Technical review
Obtain structural & other · CN contract (DB, DBB) · Advise
technical assistance & · Phasing · Specific tasks
guidance for project · Schedule · Portions of projects
scoping · Environmental · None
Considerations:
· Total project done by
consultant: Region
administrators, B&SO
technical review and
consultant selection
· Bridge work by
consultant, other work
by region: B&SO
administrators, technical
review and consultant
selections
· Some bridge work by Proceed with Project
consultant Management Online Guide
· Consultant responsibilities
during construction
No
Yes
No
710.01 General
The Washington State Department of Transportation (WSDOT) Headquarters (HQ) Bridge and
Structures Office provides preliminary site data reviews to determine the applicability of, and
requirements surrounding, proprietary structural solutions, or the need for specific structural
design strategies, as well as structural design services to the regions. This chapter describes the
information required by the HQ Bridge and Structures Office to perform these functions.
Submit the structure site data to the HQ Bridge and Structures Office, Project Support unit, by
email. In the email message, provide a general description of the project and provide a bullet
list itemization of the structure site data forms, files, and data attached or linked in the email.
Submit the structure site data as a CAD file with associated supplemental drawings and a report.
(See Exhibit 710-1 for items to include in a structure site data submittal). Direct any questions
relating to the preparation of structure site data to the HQ Bridge and Structures Office, Project
Support unit. The Bridge Design Manual shows examples of required WSDOT forms.
710.02(1) Scour
At any location where a structure can be in contact with water (such as culvert outfall, lake,
river, or floodplain), there is a risk of scour. This risk is to be analyzed as part of the Hydraulic
Report. Contact the HQ Geotechnical Office and the HQ Hydraulics Office to determine whether
a scour analysis is required.
Prepare plan, profile, and section drawings for all structures. Include copies of the CAD site data
and supplemental drawings in the 11 x 17 plan sheet format with the submittal.
Use a complete and separate CAD file for each structure. Create the base map in 2D expanded
level format only at 1:1 scale, with only one model per DGN or DWG file, and all base map levels
in accordance with the Electronic Engineering Data Standards manual. Create a separate base
map in 3D with the alignment and contour lines only—no contour text. Turn on all levels
(existing and proposed) and merge all reference files, leaving the reference file list empty. Put
the new and existing alignments in the same file.
The Bridge Design Manual contains examples of completed bridge preliminary plans. These
plans show examples of the line styles and drawing format for site data in CAD.
Structure site data is used to prepare the layout plan, which is to be used in the contract plans.
Include the following information in the CAD files or in the supplemental drawings.
710.02(2)(a) Plan
Vertical and horizontal datum control (see Chapters 400 and 410).
Contours of the existing ground surface (index and intermediate). Use intervals of 2
feet. Show contours beneath an existing or proposed structure and beneath the water
surface of any waterway. Do not partially delete contour lines that cover index contour
text.
Alignment of the proposed highway and multimodal traffic channelization in the
vicinity.
Location by section, township, and range.
Type, size, and location of all existing or proposed sewers, telephone and power lines,
water lines, gas lines, traffic barriers, culverts, bridges, buildings, and walls.
Location of right of way lines and easement lines.
Distance and direction to nearest state highway intersections along the main alignment
in each direction.
Location of all roads, streets, and detours.
Stage construction plan and alignment.
Type, size, and location of all existing and proposed sign structures, light standards, and
associated conduits and junction boxes. Provide proposed signing and lighting items
when the information becomes available.
Location of existing and proposed drainage.
Horizontal curve data. Provide the Inroads report for each alignment. Include
coordinates for all control points.
710.02(2)(b) Profile
Profile view showing the grade line of the proposed or existing alignment and the
existing ground line along the alignment line.
Vertical curve data. Provide the Inroads report for each alignment along with the CAD
detail.
Superelevation transition diagram for each alignment as applicable.
710.02(2)(c) Section
Channelization roadway sections on the structure and at structure approaches.
Indicate the lane and shoulder widths, cross slopes and side slopes, ditch dimensions,
and traffic barrier requirements.
Stage construction roadway geometrics with the minimum lane and roadway widths
specified.
710.02(3) Report
Submit DOT Form 235-002, Bridge Site Data-General. Supplement the CAD drawings with the
following items:
Vicinity maps
Class of highway
Design speed
Special requirements for replacing or relocating utility facilities
ADT and DHV counts
Truck traffic percentage
Requirements for road or street maintenance during construction
Color photographs of the structure site are desirable. Include detailed photographs of existing
abutments, piers, end slopes, and other pertinent details for widenings, bridge replacements, or
sites with existing structures.
Show a profile of the waterway. The extent will be determined by the HQ Hydraulics
Section.
Show cross sections of the waterway including new streambed design, defining the
bankfull width and the bank shelf widths and slopes. The extent will be determined by
the HQ Hydraulics Section. The requirements for waterway profile and cross sections
may be less stringent if the HQ Hydraulics Section has sufficient documentation (FEMA
reports, for example) to make a determination. Contact the HQ Hydraulics Section to
verify the extent of the information needed. Coordinate any rechannelization of the
waterway with the HQ Hydraulics Section.
Many waterway crossings require a permit from the U.S. Coast Guard (see Bridge
Design Manual Chapter 2.2.4 and the Environmental Manual). Generally, ocean tide-
influenced waterways and waterways used for commercial navigation require a Coast
Guard permit. These structures require the following additional information:
Names and addresses of the landowners adjacent to the bridge site.
Quantity of new embankment material within the floodway. This quantity
denotes, in cubic yards, the material below and the material above normal
high water.
For all waterway crossings, where the structure parallel to the centerline of roadway width is
less than 20 feet, the Region’s designer shall contact the US Coast Guard for determination of
waterway jurisdiction and any associated permit requirements. For all waterway crossings,
where the structure parallel to the centerline of roadway width is 20 feet or greater, the Bridge
and Structures Office US Coast Guard Liaison will contact the US Coast Guard for determination
of waterway jurisdiction and any associated permit requirements.
The Region is responsible for coordination with the HQ Bridge and Structures Office, U.S. Army
Corps of Engineers, and U.S. Coast Guard for waterways that may qualify for an exemption to
navigation permit requirements. The HQ Bridge and Structures Office is responsible for
coordination with the U.S. Coast Guard for waterways that require a navigation permit.
710.04(1)(a) Plan
Alignment of all existing and proposed railroad tracks.
Center-to-center spacing of all tracks.
Angle, station, and coordinates of all intersections between the highway alignment and
each track.
Location of railroad right of way lines.
Horizontal curve data. Include coordinates for all curve control points.
710.04(1)(b) Profile
For proposed railroad tracks: profile, vertical curve, and superelevation data for each
track.
For existing railroad tracks: elevations accurate to 0.1 foot taken at 10-foot intervals
along the top of the highest rail of each track. Provide elevations to 50 feet beyond the
extreme outside limits of the existing or proposed structure. Tabulate elevations in a
format acceptable to the HQ Bridge and Structures Office.
710.04(2)(a) Plan
Alignment of all existing and proposed highways, streets, and roads.
Angle, station, and coordinates of all intersections between all crossing alignments.
Horizontal curve data. Include coordinates for all curve control points.
710.04(2)(b) Profile
For proposed highways: profile, vertical curve, and superelevation data for each.
For existing highways: elevations accurate to 0.1 foot taken at 10-foot intervals along
the centerline or crown line and each edge of shoulder, for each alignment, to define
the existing roadway cross slopes. Provide elevations to 50 feet beyond the extreme
outside limits of the existing or proposed structure. Tabulate elevations in a format
acceptable to the HQ Bridge and Structures Office.
710.04(2)(c) Section
Roadway sections of each undercrossing roadway indicating the lane and shoulder
widths, cross slopes and side slopes, ditch dimensions, and traffic barrier requirements.
Falsework or construction opening requirements. Specify minimum vertical clearances,
lane widths, and lateral clearances.
710.05(1)(b) Profile
Elevations accurate to 0.1 foot taken at 10-foot intervals along the curb line of the side
of the structure being widened. Pair these elevations with corresponding elevations
(same station) taken along the crown line or an offset distance (10-foot minimum from
the curb line). This information will be used to establish the cross slope of the existing
bridge. Tabulate elevations in a format acceptable to the HQ Bridge and Structures
Office.
Take these elevations at the level of the concrete roadway deck. For bridges with concrete
overlay, elevations at the top of the overlay will be sufficient. For bridges with a
nonstructural overlay, such as an asphalt concrete overlay, take elevations at the level of
the concrete roadway deck. For skewed bridges, take elevations along the crown line or at
an offset distance (10-foot minimum from the curb line) on the approach roadway for a
sufficient distance to enable a cross slope to be established for the skewed corners of the
bridge.
710.07 Documentation
Refer to Chapter 300 for design documentation requirements.
710.08 References
Bridge Design Manual, M 23-50, WSDOT
PLAN (in CAD file) FORMS (information noted on the form or attached
Survey Lines and Station Ticks on supplemental sheets or drawings)
Survey Line Bearings Bridge Site Data General
Roadway and Median Widths Pedestrian Barrier/Pedestrian Rail Height
Lane and Shoulder Widths Datum
_____Bicycle and Pedestrian Facility and widths Control Section
Bridge Deck Sidewalk Width Project Number
Profile Grade and Pivot Point Region Name
Roadway Superelevation Rate (if constant) Project Name
Traffic Arrows Bridge Site Data for Stream Crossings
Existing utilities Type, Size, and Location Water Surface Elevations and Flow Data
Contours Bankfull Width
Stream Flow Arrow Bank shelf width
R/W Lines and/or Easement Lines BRIDGE, CROSSROAD, & APPROACH ROADWAY
Exist. Bridge No. (to be removed, widened) CROSS SECTIONS (may be in CAD file or on
Section, Township, Range Separate drawings)
County, City or Town Bridge Roadway Width
North Arrow Lane and Shoulder Widths
SR Number _____Bicycle facility width
Scale _____Pedestrian facility width
TABLES (in tabular format in CAD file) Profile Grade and Pivot Point
Curb Line Elevations at Top of Existing Br. Deck Superelevation Rate
Undercrossing Roadway Existing Elevations Survey Line
Undercrossing Railroad Existing Elevations PB/Pedestrian Rail Dimensions
Curve Data
OTHER SITE DATA (may be in CAD file or on
supplemental sheets or drawings)
Superelevation Diagrams
Profile Grade Vertical Curves
Railroad Agreement Status
Highway Classification
Design Speed
ADT, DHV, and % Trucks
In Roads reports
720.01 General
The National Bridge Inspection Standards (NBIS), published in the Code of Federal Regulations
(23 CFR 650, Subpart C), defines a bridge as:
The term “bridge” as used in this chapter applies to all structures conforming to the above
definition. This includes all buried structures of a span greater than 20 feet measured along the
overcrossing alignment, such as precast reinforced concrete three-sided structures, precast
reinforced concrete box culverts, and precast reinforced concrete split box culverts.
The structural capacity of a bridge is a measure of the structure’s ability to carry vehicle loads.
For new bridges, the bridge designer chooses the design load that determines the structural
capacity. For existing bridges, the structural capacity is calculated to determine the “load rating”
of the bridge. The load rating is used to determine whether or not a bridge is “posted” for legal
weight vehicles or “restricted” for overweight permit vehicles.
All new structures that carry vehicular loads are designed to HL-93 notional live load in
accordance with AASHTO’s LRFD Bridge Design Specifications.
When the structural capacity of a bridge will be affected by the project, the Region requests a
Structural Capacity Report from the Risk Reduction Engineer in the HQ Bridge and Structures
Office. Permanent redistribution of traffic, introduction of median barrier, and widening or deck
rehabilitation are among the triggers for evaluation of a bridge’s structural capacity. The report
will state:
The structural capacity status of the structures within the project limits.
What action, if any, is appropriate.
The Region requests the Bridge and Structures Asset Manager to provide status about whether a
bridge is included in the 6-year or 20-year plans for replacement or rehabilitation under the
P2 program and, if so, in which biennium the P2 project is likely to be funded.
The criteria used by the Bridge and Structures office to evaluate the structural capacity of a
bridge are as follows:
1. On National Highway System (NHS) routes (including Interstate routes):
• The operating load rating is at least 36 tons (which is equal to HS-20).
• The bridge is not permanently posted for legal weight vehicles.
• The bridge is not permanently restricted for vehicles requiring overweight
permits.
2. On non-NHS routes:
• The bridge is not permanently posted for legal weight vehicles.
• The bridge is not permanently restricted for vehicles requiring overweight
permits.
Include the Structural Capacity Report in the Project File (see Chapter 300).
The Design Manual contains multiple chapters that provide geometric cross section criteria and
procedures relevant to determining design element widths. See Chapter 1230 for a guide to
chapters that provide geometric cross section element widths.
While it is preferred not to alter the continuity of a roadway, there may be situations where
providing a structure width more or less than the roadway approaching the structure is
appropriate.
All structures on city or county routes crossing over a state highway must conform to the Local
Agency Guidelines.
For structures involving railroads, contact the HQ Design Office Railroad Liaison.
Horizontal clearance for structures is the distance from the edge of the traveled way to bridge
piers and abutments, traffic barrier ends, or bridge end embankment slopes. Minimum
distances for this clearance vary depending on the type of structure. (See Chapters 1239, 1600,
and 1610 and the Bridge Design Manual for guidance on horizontal clearance.)
For structures involving railroads, contact the HQ Design Office Railroad Liaison.
Designs for bridges on divided multilane highways often include the decision to join parallel
bridges as one or build them as independent structures. There are several factors in this
decision, such as in new corridor construction, phased construction of corridors, and the general
median width of the divided highway. This section covers some common design considerations
related to bridge medians.
Advances in crash barriers and their applications have resulted in an expanded set of choices for
bridge medians on divided highways.
Modern barrier designs and applications have allowed for longer runs of traffic barrier, different
barrier types, and bullnose guardrail designs for shielding the gap between parallel structures.
These tools have reduced collisions with abrupt bridge ends as well as shielded the opening
between bridges.
Some highway corridors are initially planned as multilane divided highways but may be
developed in logical, affordable phases and individual projects. This could result in an initial
phase where a corridor may open as a two-lane rural highway used by both travel directions. A
later phase could convert the facility to a divided highway, bringing with it the need for median
separation. Consider the long-range plans when determining median widths for bridges. The
photos in Exhibit 720-1 show a completed multilane highway where two separate bridges were
ultimately constructed years apart and a new corridor underway where one bridge is now built.
Joining two structures may not be the most cost-effective or sustainable solution for all projects.
Coordinate with the Bridge and Structures Office and the local Maintenance Office when
discussing options and concerns. For bridges on parallel horizontal and vertical alignments,
practical considerations for joining two structures as one include, but are not limited to:
• Phased development where one structure exists and another is planned.
• Old and new structure types and compatibility (with phased corridor construction).
• Median width.
• Median barrier treatment options.
• Environmental contexts and regulations.
• Seismic conditions and load ratings.
• Bridge maintenance and inspection techniques: accessibility options and equipment
for terrain in specific contexts. An open area between structures may be needed for
bridge inspection.
• Skew angles and/or curvature of waterways or roadways beneath the structures.
• Economics.
• Historical/aesthetic value of existing bridges to remain in place.
When there is a median gap between bridges of 6 inches or more, the Region PEO will evaluate
whether or not the median gap needs to be screened. Address the potential for pedestrians on
the bridge and if closing the median gap to less than 6 inches, or installing fencing, netting, or
other elements to enclose the area between the bridges would be beneficial. Document this
evaluation in the Basis of Design and Alternatives Comparison Table.
Vertical clearance is the critical height under a structure that will accommodate vehicular and
rail traffic based on its design characteristics. This height is the least height available from the
lower roadway surface (including usable shoulders) or the plane of the top of the rails to the
bottom of the bridge. Usable shoulders are the design shoulders for the roadway and do not
include paved widened areas that may exist under the structure.
In addition to the following vertical clearance guidance, consider whether the corridor
experiences overheight loads. Consider a vertical clearance such that it will not create a new
“low point” in the corridor.
Construction of new bridges and the reconstruction or widening of existing structures often
requires the erection of falsework across the traveled way of a highway. The erection of this
falsework can reduce the vertical clearance for vehicles to pass under the work area. The
potential for collisions to occur by hitting this lower construction stage falsework is increased.
1. On all routes that require a 16.5-foot vertical clearance, maintain this same clearance
for falsework vertical clearance.
• On structures that currently have less than a 16.5-foot vertical clearance for the
falsework envelope, maintain existing clearance.
• On new structures, maintain the falsework vertical clearance at least to those of
the minimum vertical clearances referenced below.
2. Any variance from the above must be approved by the Regional Administrator or
designee in writing and made a part of the Project File.
720.03(5)(b) Minimum Clearance for New Structures
The minimum vertical clearance for a bridge over a roadway is 16.5 feet.
The minimum vertical clearance for a bridge over a railroad track is 23.5 feet (see Exhibit
720-2). A lesser clearance may be negotiated with the railroad company based on certain
operational characteristics of the rail line; however, any clearance less than 22.5 feet
requires the approval of the Washington State Utilities and Transportation Commission
(WUTC) per WAC 480-60. Vertical clearance is provided for the width of the railroad
clearance envelope. Coordinate railroad clearance issues with the HQ Design Office Railroad
Liaison.
The minimum vertical clearance for a pedestrian bridge over a roadway is 17.5 feet.
Notes:
Use 22.5-foot vertical clearance for existing structures.
Lesser vertical clearance may be negotiated (see 720.03(5)).
Increase horizontal clearance when the track is curved.
Coordinate railroad clearance issues with the HQ Design Office Railroad Liaison.
The criteria used to evaluate the vertical clearance for existing structures depend on the work
being done on or under that structure. When evaluating an existing structure on the Interstate
System, see 720.03(5)(e), Coordination. This guidance applies to bridge clearances over state
highways and under state highways at interchanges. For state highways over local roads and
streets, city or county vertical clearance requirements may be used as minimum design criteria.
(See Exhibit 720-3 for bridge vertical clearances.)
720.03(5)(c)(1) Bridge Over a Roadway
For a project that will widen an existing structure over a highway or where the highway will
be widened under an existing structure, the vertical clearance can be as little as 16.0 feet on
the Interstate System or other freeways or 15.5 feet on nonfreeway routes. An approved
design analysis is required for clearance less than 16.0 feet on Interstate routes or other
freeways and 15.5 feet on nonfreeway routes.
For a planned resurfacing of the highway under an existing bridge, if the clearance will be
less than 16.0 feet on the Interstate System or other freeways and 15.5 feet on nonfreeway
routes, evaluate the following options and include in a design analysis request:
Pavement removal and replacement
Roadway excavation and reconstruction to lower the roadway profile
Providing a new bridge with the required vertical clearance
Reducing roadway paving and surfacing thickness under the bridge to achieve the minimum
vertical clearance can cause accelerated deterioration of the highway and is not
recommended. Elimination of the planned resurfacing in the immediate area of the bridge
might be a short-term solution if recommended by the Region Materials Engineer (RME).
Solutions that include milling the existing surface followed by overlay or inlay must be
approved by the RME to ensure adequate pavement structure is provided.
For other projects that include an existing bridge where no widening is proposed on or
under the bridge, and the project does not affect vertical clearance, the clearance can be as
little as 14.5 feet. For these projects, document the clearance in the Design Documentation
Package. For an existing bridge with less than a 14.5-foot vertical clearance, an approved
design analysis request is required.
For an existing structure over a railroad track (see Exhibit 720-2), the vertical clearance can
be as little as 22.5 feet. A lesser clearance can be used with the agreement of the railroad
company and the approval of the Washington State Utilities and Transportation
Commission. Coordinate railroad clearance issues with the HQ Design Office Railroad
Liaison.
Documentation
Vertical
Project Type Requirement
Clearance [8]
(see notes)
Interstate and Other Freeways [1]
New Bridge > 16.5 ft [2]
> 16 ft [2]
Widening Over or Under Existing Bridge
< 16 ft [4]
> 16 ft [2]
Resurfacing Under Existing Bridge
< 16 ft [4]
> 14.5 ft [3]
Other With No Change to Vertical Clearance
< 14.5 ft [4]
Nonfreeway Routes
New Bridge > 16.5 ft [2]
> 15.5 ft [2]
Widening Over or Under Existing Bridge
< 15.5 ft [4]
> 15.5 ft [2]
Resurfacing Under Existing Bridge
< 15.5 ft [4]
> 14.5 ft [3]
Other With No Change to Vertical Clearance
< 14.5 ft [4]
Bridge Over Railroad Tracks [7]
> 23.5 ft [2]
New Bridge
< 23.5 ft [4][5]
> 22.5 ft [2]
Existing Bridge
< 22.5 ft [4][5]
Pedestrian Bridge Over Roadway
New Bridge > 17.5 ft [2]
Existing Bridge 17.5 ft [6]
Notes:
[1] Applies to all bridge vertical clearances over highways and under highways at interchanges.
[2] No documentation required.
[3] Document to Design Documentation Package.
[4] Approved design analysis required.
[5] Requires written agreement between railroad company and WSDOT and approval via
petition from the WUTC.
[6] Maintain 17.5-ft clearance.
[7] Coordinate railroad clearance with the HQ Design Office Railroad Liaison.
[8] See 720.03(5).
720.03(5)(d) Signing
Low-clearance warning signs are necessary when the vertical clearance of an existing bridge is
less than 15 feet 3 inches. Refer to the Manual on Uniform Traffic Control Devices and the Traffic
Manual for other requirements for low-clearance signing.
720.03(5)(e) Coordination
The Interstate System is used by the Department of Defense (DOD) for the conveyance of
military traffic. The Military Traffic Management Command Transportation Engineering Agency
(MTMCTEA) represents the DOD in public highway matters. The MTMCTEA has an inventory of
vertical clearance deficiencies over the Interstate System in Washington State. Contact the
MTMCTEA, through the Federal Highway Administration (FHWA), if either of the following
changes is proposed to these bridges:
A project would create a new deficiency of less than a 16.0-foot vertical clearance over
an Interstate highway.
The vertical clearance over the Interstate is already deficient (less than 16.0 feet) and a
change (increase or decrease) to vertical clearance is proposed.
Coordination with MTMCTEA is required for these changes on all rural Interstate highways and
for one Interstate route through each urban area.
To determine the amount of settlement and the potential for the soil to flow laterally during the
design level earthquake due to liquefaction, an analysis performed by the HQ Geotechnical
Office is needed for each bridge project site location. The information collected is used by bridge
engineers to determine the bridge’s capability to withstand the movement and loading in a
seismic event and to explore other foundation mitigation options not necessitating total bridge
replacement.
The HQ Bridge and Structures Office, in collaboration with the HQ Geotechnical Office, evaluates
bridge-widening projects involving liquefiable soils and recommends appropriate liquefaction
mitigation.
When pedestrians or bicyclists are anticipated on bridges, provide facilities consistent with
guidance in Chapters 1510, 1515, and 1520.
Evolving programs and technologies such as incident response, personal cell phones, and ITS
cameras have further reduced the probability of motorists becoming pedestrians. Investigate
other methods of treatment such as pedestrian scale signing or other low-cost safety
improvement measures. Document decisions in the Basis of Design.
Bridge approach slabs are reinforced concrete pavement installed across the full width of the
bridge ends. They provide a stable transition from normal roadway cross section to the bridge
ends, and they compensate for differential expansion and contraction of the bridge and the
roadway.
Bridge approach slabs are provided on all new bridges. If an existing bridge is being widened and
it has an approach slab, slabs are required on the widenings. The region, with the concurrence
of the State Geotechnical Engineer and the State Bridge Design Engineer, may decide to omit
bridge approach slabs. Document decisions in the DDP.
Plans for new bridge construction and bridge traffic barrier modifications include provisions for
the connection of bridge traffic barriers to the longitudinal barrier approaching and departing
the bridge. Indicate the preferred longitudinal barrier type and connection during the review of
the bridge preliminary plan.
The design of embankment slopes at bridge ends depends on several factors. The width of the
embankment is determined not only by the width of the roadway, but also by the presence of
traffic barriers, curbs, and sidewalks, all of which create the need for additional widening.
Examples of the additional widening required for these conditions are shown in the Standard
Plans.
The end slope is determined by combining the recommendations of several technical experts
within WSDOT. Exhibit 720-4 illustrates the factors taken into consideration and the experts
involved in the process.
Slope protection provides a protective and aesthetic surface for exposed slopes under bridges.
Slope protection is normally provided under:
Structures over state highways.
Structures within an interchange.
Structures over other public roads unless requested otherwise by the public agency.
Railroad overcrossings if requested by the railroad.
The type of slope protection is selected at the bridge preliminary plan stage. Typical slope
protection types are concrete slope protection, and rubble stone.
The HQ Hydraulics Section determines the slope protection requirements for structures that
cross waterways. The type, limits, and quantity of slope protection are shown on the bridge
preliminary plan.
Legend
A = Superstructure depth: recommended by HQ Bridge and Structures Office
B = Vertical clearance from bottom of superstructure to embankment: recommended by Bridge
Preservation Engineer
C = Distance from end of retaining wall or wing wall to back of pavement seat: recommended by
HQ Bridge and Structures Office
H & V = Embankment slope: recommended by Geotechnical Engineer
The Washington State Patrol (WSP) classifies the throwing of an object from a highway structure
as an assault, not an accident or collision. Therefore, records of these assaults are not contained
in WSDOT’s crash databases. Contact the Region Traffic Engineer, RME’s office and the WSP for
the history of reported incidents.
Screening might reduce the number of incidents, but will not stop a determined individual at
that location, or deter them from moving to other locations in the area. Enforcement provides
the most effective deterrent and is typically the first approach used.
In most cases, the installation of a screen on a new structure can be postponed until there are
indications of need.
Submit all proposals to install screening on structures to the Director & State Design Engineer,
Development Division, for approval. Contact the HQ Bridge and Structures Office for approval to
attach screening to structures and for specific design and mounting details.
Because these impacts are temporary and are limited to the duration of the construction or
maintenance activity, they do not affect or change the actual USCG bridge permit. However,
such temporary adjustments still require coordination with the US Coast Guard early in the
project design schedule.
The primary responsibility for this contact and coordination lies with the Region Design Project
Office. The scope of such coordination varies depending on the extent of the infringement into
the defined horizontal or vertical navigation clearance opening, the extent of the change to the
bridge operation notice or process as defined in current regulation, and the duration of the
construction or maintenance activity.
This coordination activity may require the Design Project Office to conduct a survey of waterway
users or to perform other background information tasks requested by the US Coast Guard.
Projects with more extensive impacts may lie outside the approval authority of the local USCG
Commander and may require review and action by US Coast Guard HQ in Washington, DC. In all
cases, the earlier in the design process that the Region Design Project Office initiates these
coordination efforts, the more likely the USCG can complete their regulatory process without
impacting the project schedule.
720.05 Documentation
Refer to Chapter 300 for design documentation requirements.
720.06 References
*Note: railroads may have stricter clearances than what is required in law and each railroad
should be consulted as early as possible as to allowable clearances.
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-10, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO, current edition
730.01 General
The function of a retaining wall is to form a nearly vertical face through confinement
and/or strengthening of a mass of earth or other bulk material. Likewise, the function
of a reinforced slope is to strengthen the mass of earth or other bulk material
such that a steep (up to 1H:2V) slope can be formed. In both cases, the purpose
of constructing such structures is to make maximum use of limited right of way.
The difference between the two is that a wall uses a structural facing, whereas a steep
reinforced slope does not require a structural facing. Reinforced slopes typically use
a permanent erosion control matting with low vegetation as a slope cover to prevent
erosion. (See the Roadside Manual for more information.)
To lay out and design a retaining wall or reinforced slope, consider the
following items:
• Functional classification
• Highway geometry
• Design Clear Zone requirements (see Chapter 1600)
• Amount of excavation required
• Traffic characteristics
• Constructability
• Impact to adjacent environmentally sensitive areas
• Impact to adjacent structures
• Potential added lanes
• Length and height of wall
• Material to be retained
• Foundation support and potential for differential settlement
• Groundwater
• Earthquake loads
• Right of way costs
• Need for construction easements
• Risk
• Overall cost
• Visual appearance
If the wall or toe of a reinforced slope is to be located adjacent to the right of way
line, consider the space needed in front of the wall/slope to construct it.
Rockeries (rock walls) behave to some extent like gravity walls. However,
the primary function of a rockery is to prevent erosion of an oversteepened
but technically stable slope. Rockeries consist of large, well-fitted rocks stacked
on top of one another to form a wall.
An example of a rockery and reinforced slope is provided in Exhibit 730-10.
730.02 References
(1) Federal/State Laws and Codes
Washington Administrative Code (WAC) 296-155, Safety standards for
construction work
For wall/slope geometry, also consider the foundation embedment and type
anticipated, which requires coordination between the various design groups involved.
Retaining walls are designed to limit the potential for snagging vehicles by removing
protruding objects (such as bridge columns, light fixtures, or sign supports).
Provide a traffic barrier shape at the base of a new retaining wall constructed 12 feet
or less from the edge of the nearest traffic lane. The traffic barrier shape is optional
at the base of the new portion when an existing vertical-faced wall is being extended
(or the existing wall may be retrofitted for continuity). Depending on the application,
precast or cast-in-place Single Slope Concrete Barrier with vertical back or Type 4
Concrete Barrier may be used for both new and existing walls except when the
barrier face can be cast as an integral part of a new wall. Design analyses may be
considered, but they require approval as prescribed in Chapter 300. A design analysis
is not required where sidewalk exists in front of the wall or in other situations where
the wall face is otherwise inaccessible to traffic.
needs to be considered in the design stage and reviewed by the region Materials
Engineer during construction. The drainage features shown in the Standard Plans are
the minimum basic requirements. Underdrains behind the wall/slope need to daylight
at some point in order to adequately perform their drainage function. Provide positive
drainage at periodic intervals to prevent entrapment of water.
Native soil may be used for retaining wall and reinforced slope backfill if it meets the
requirements for the particular wall/slope system. In general, use backfill that is free-
draining and granular in nature. Exceptions to this can be made depending on the site
conditions as determined by the Geotechnical Office of the Headquarters (HQ)
Materials Laboratory.
A typical drainage detail for a gravity wall (in particular, an MSE wall) is shown in
Exhibit 730-11. Include drainage details with a wall unless otherwise recommended
to be deleted by the Region Materials Engineer or HQ Geotechnical Office.
(5) Aesthetics
Retaining walls and slopes can have a pleasing appearance that is compatible with the
surrounding terrain and other structures in the vicinity. To the extent possible within
functional requirements and cost-effectiveness criteria, this aesthetic goal is to be met
for all visible retaining walls and reinforced slopes.
Aesthetic requirements include consideration of the wall face material, top profile,
terminals, and surface finish (texture, color, and pattern). Where appropriate, provide
planting areas and irrigation conduits. These will visually soften walls and blend
them with adjacent areas. Avoid short sections of retaining wall or steep slope
where possible.
In higher walls, variations in slope treatment are recommended for a pleasing
appearance. High continuous walls are generally not desirable from an aesthetic
standpoint, because they can be quite imposing. Consider stepping high or long
retaining walls in areas of high visibility. Plantings may be considered between
wall steps.
Approval by the State Bridge and Structures Architect is required on all retaining
wall aesthetics, including finishes, materials, and configuration (see Chapter 950).
(6) Constructability
Consider the potential effect that site constraints might have on the constructability
of the specific wall/slope. Constraints to be considered include but are not limited
to site geometry, access, time required to construct the wall, environmental issues,
and impact on traffic flow and other construction activities.
These types of walls generally have a narrower base width than MSE structures (on
the order of 50% of the wall height). Both of these factors make these types of walls
feasible in fill situations as well as many cut situations.
Reinforced slopes generally require more room overall to construct than a wall
because of the sloping face, but they typically are a feasible alternative to a
combination wall and fill slope to add a new lane. Reinforced slopes can also
be adapted to the existing ground contours to minimize excavation requirements
where fill is placed on an existing slope. Reinforced slopes might also be a feasible
choice to repair slopes damaged by landslide activity or deep erosion.
Rockeries are best suited to cut situations as they require only a narrow base width,
on the order of 30% of the rockery height. Rockeries can be used in fill situations,
but the fill heights they support need to be kept relatively low. It is difficult to get the
cohesive strength needed in granular fill soils to provide minimal stability of the soil
behind the rockery at the steep slope typically used for rockeries in a cut (such as
1H:6V or 1H:4V).
The key considerations in deciding which walls or slopes are feasible are the amount
of excavation or shoring required and the overall height. The site geometric constraints
are defined to determine these elements. Another consideration is whether or not an
easement will be required. For example, a temporary easement might be required for a
wall in a fill situation to allow the contractor to work in front of the wall. For walls in
cut situations, especially anchored walls and soil nail walls, a permanent easement may
be required for the anchors or nails.
usually increase the cost of any of these facing systems. Special wall terracing
to provide locations for plants will also tend to increase costs. Therefore, weigh the
costs against the value of the desired aesthetics.
Other factors that affect the costs of wall/slope systems include wall/slope size and
length; access at the site and distance to the material supplier location; overall size
of the project; and competition between wall suppliers. In general, costs tend to be
higher for walls or slopes that are high, but short in length, due to lack of room for
equipment to work. Sites that are remote or have difficult local access increase wall/
slope costs. Small wall/slope quantities result in high unit costs. Lack of competition
between materials or wall system suppliers can result in higher costs as well.
Some of the factors that increase costs are required parts of a project and are
therefore unavoidable. Always consider such factors when estimating costs because
a requirement may not affect all wall types in the same way. Current cost information
can be obtained by consulting the Bridge Design Manual or by contacting the HQ
Bridge and Structures Office.
(7) Summary
For wall/slope selection, consider factors such as the intended application; the soil/
rock conditions in terms of settlement, need for deep foundations, constructibility,
and impacts to traffic; and the overall geometry in terms of wall/slope height and
length, location of adjacent structures and utilities, aesthetics, and cost. Exhibits
730-1 through 730-6 provide a summary of many of the various wall/slope options
available, including their advantages, disadvantages, and limitations. Note that
specific wall types in the exhibits may represent multiple wall systems, some or all
of which will be proprietary.
The Standard Plans provides design charts and details for standard reinforced
concrete cantilever walls. The Standard Plans are used to size the walls and
determine the factored bearing pressure to compare with the factored bearing
resistance determined from the geotechnical investigation. The charts provide
maximum soil pressure for the LRFD service, strength, and extreme event limit
states. Factored bearing resistance for the LRFD service, strength, and extreme
event limit states can be obtained from the HQ Geotechnical Office for standard
walls over 10 feet in height and from the region Materials Laboratory for
standard walls less than or equal to 10 feet in height. The Standard Plans can be
used for the wall design if the factored bearing resistance exceeds the maximum
soil pressure shown in the Standard Plans for the respective LRFD limit states.
Contact the HQ Bridge and Structures Office if the factored bearing resistance
provided by the geotechnical investigation does not exceed the maximum soil
pressure shown in the Standard Plans for one or all of the LRFD limit states.
The wall is considered a nonstandard wall design and the Standard Plans
cannot be used.
If the standard wall must support surcharge loads from bridge or building
foundations, other retaining walls, noise walls, or other types of surcharge
loads, a special wall design is required. The wall is considered to be supporting
the surcharge load and is treated as a nonstandard wall if the surcharge load
is located within a 1H:1V slope projected up from the bottom of the back of
the wall. Contact the HQ Bridge and Structures Office for assistance
The Standard Plans provides eight types of reinforced concrete cantilever walls
(which represent eight loading cases). Reinforced concrete retaining walls
Types 5 through 8 are not designed to withstand western Washington earthquake
forces and are not to be used in western Washington (west of the Cascade crest).
Once the geotechnical and architectural assessments have been completed, the
region completes the PS&E for the standard wall option(s) selected, including
a generalized wall profile and plan, a typical cross section as appropriate,
and details for desired wall appurtenances, drainage details, and other details
as needed.
Metal bin walls, Types 1 and 2, have been deleted from the Standard Plans
and are therefore no longer standard walls. Metal bin walls are seldom used
due to cost and undesirable aesthetics. If this type of wall is proposed, contact
the HQ Bridge and Structures Office for plan details and toe bearing pressures.
The applied toe bearing pressure will then have to be evaluated by the HQ
Geotechnical Office to determine whether the site soil conditions are appropriate
for the applied load and anticipated settlement.
(b) Preapproved Proprietary Walls
Final approval of preapproved proprietary wall design, with the exception
of geosynthetic walls, is the responsibility of the HQ Bridge and Structures
Office. Final approval of the design of preapproved proprietary geosynthetic
walls is the responsibility of the HQ Geotechnical Office. It is the region’s
responsibility to coordinate the design effort for all preapproved wall systems.
back of the wall. For MSE walls, the back of the wall is considered to be the
back of the soil reinforcement layers. If this situation occurs, the wall is treated
as a nonpreapproved proprietary wall.
For those alternative wall systems that have the same face embedment criteria,
the wall face quantities depicted in the plans for each alternative are to be
identical. To provide an equal basis for competition, the region determines
wall face quantities based on neat lines.
Once the detailed wall plans and designs are available as shop drawings after
contract award, the HQ Bridge and Structures Office will review and approve
the wall shop drawings and calculations, with the exception of geosynthetic
walls. They are reviewed and approved by the HQ Geotechnical Office.
(c) Nonpreapproved Proprietary Walls
Final approval authority for nonpreapproved proprietary wall design is the same
as for preapproved proprietary walls. The region initiates the design effort for
all nonpreapproved wall systems by submitting wall plan, profile, cross section,
and other information for the proposed wall to the HQ Bridge and Structures
Office, with copies to the HQ Geotechnical Office and the State Bridge and
Structures Architect. The HQ Bridge and Structures Office coordinates the
wall design effort.
Once the geotechnical and architectural assessments have been completed and
the desired wall types selected, the HQ Bridge and Structures Office contacts
suppliers of the selected nonpreapproved wall systems to obtain and review
detailed wall designs and plans to be included in the contract PS&E.
To ensure fair competition between all wall alternatives included in the PS&E,
make the wall face quantities identical for those wall systems subject to the
same face embedment requirements.
The HQ Bridge and Structures Office develops the special provisions and
cost estimates for the nonpreapproved proprietary walls and sends the wall
PS&E to the region for inclusion in the final PS&E in accordance with the
Plans Preparation Manual.
(d) Nonstandard Nonproprietary Walls
With the exception of rockeries over 5 feet high, nonproprietary geosynthetic
walls and reinforced slopes, and soil nail walls, the HQ Bridge and Structures
Office coordinates with the HQ Geotechnical Office and the State Bridge and
Structures Architect to carry out the design of all nonstandard, nonproprietary
walls. The HQ Bridge and Structures Office develops the wall preliminary plan
from site data provided by the region, completes the wall design, and develops
the nonstandard nonproprietary wall PS&E package for inclusion in the contract.
For rockeries over 5 feet high, nonproprietary geosynthetic walls and reinforced
slopes, and soil nail walls, the region develops wall/slope profiles, plans, and
cross sections and submits them to the HQ Geotechnical Office to complete
a detailed wall/slope design.
For geosynthetic walls and slopes and for rockeries, the region provides overall
coordination of the wall/slope design effort, including coordination with the
State Bridge and Structures Architect regarding aesthetics and finishes, and
the region or HQ Landscape Architect if the wall uses vegetation on the face.
The HQ Geotechnical Office has overall approval authority for the wall design.
Once the wall design has been completed, the HQ Geotechnical Office, and in
some cases the HQ Bridge and Structures Office, provides geotechnical and
structural plan details to be included in the region plan sheets and special
provisions for the PS&E. The region then completes the PS&E package.
For soil nail walls, once the HQ Geotechnical Office has performed the
geotechnical design, the HQ Bridge and Structures Office, in cooperation
with the HQ Geotechnical Office, coordinates the design effort and completes
the PS&E package.
730.07 Documentation
Refer to Chapter 300 for design documentation requirements.
Specific
Advantages Disadvantages Limitations
Wall Type
Steel soil Relatively low Can tolerate little settlement; Applicable primarily to fill
reinforcement with cost. generally requires high- situations; maximum feasible
full height precast quality backfill; wide base height is approximately
concrete panels width required (70% of 20 feet.
wall height).
Steel soil Relatively low Generally requires high-quality Applicable primarily to fill
reinforcement with cost; flexible backfill; wide base width situations; maximum height
modular precast enough to handle required (70% of wall height). of 33 feet; heights over
concrete panels significant 33 feet require a special
settlement. design.
Steel soil Can tolerate Relatively high cost; cannot Applicable primarily to fill
reinforcement large short-term tolerate long-term settlement; situations; maximum height
with welded wire settlements. generally requires high- of 33 feet for routine designs;
and cast-in-place quality wall backfill soil; wide heights over 33 feet require
concrete face base width required (70% a special design.
of wall height); typically
requires a settlement delay
during construction.
Steel soil Can tolerate Aesthetics, unless face Applicable primarily to fill
reinforcement large short-term plantings can be established; situations; maximum height
with welded wire settlements; generally requires high- of 33 feet for routine designs;
face only low cost. quality backfill; wide base heights over 33 feet require
width required (70% of a special design.
wall height).
Segmental Low cost; flexible Internal wall deformations Applicable primarily to fill
masonry concrete enough to handle may be greater for steel situations; in general, limited
block-faced walls, significant reinforced systems, but to a wall height of 20 feet
generally with settlement. are acceptable for most or less; greater wall heights
geosynthetic soil applications; generally may be feasible by special
reinforcement requires high-quality backfill; design in areas of low
wide base required (70% of seismic activity and when
wall height). geosynthetic products are
used in which long-term
product durability is well
defined. (See Qualified
Products List.)
Geosynthetic walls Very low cost, Internal wall deformations Applicable primarily to fill
with a shotcrete especially with may be greater than for situations; in general, limited
or cast-in-place shotcrete face; steel reinforced systems, to wall height of 20 feet
concrete face can tolerate but are still acceptable for or less unless using
large short-term most applications; generally geosynthetic products in
settlements. requires high-quality backfill; which long-term product
wide base width required durability is well defined.
(70% of wall height). (See Qualified Products
List.) For qualified products,
heights of 33 feet or more
are possible.
Specific
Advantages Disadvantages Limitations
Wall Type
Geosynthetic walls Very low cost; can Internal wall deformations Applicable primarily to fill
with a welded tolerate large long- may be greater than for situations; in general,
wire face term settlements. steel reinforced systems, limited to wall height
but are still acceptable for of 20 feet or less unless
most applications; generally using geosynthetic products
requires high-quality wall in which long-term product
backfill soil; wide base durability is well defined.
width required (70% of (See Qualified Products
wall height). List.) For qualified products,
heights of 33 feet or more
are possible.
Geosynthetic walls Lowest cost of all Internal wall deformations Applicable primarily to fill
with a geosynthetic wall options; can may be greater than for situations; use only for
face tolerate large long- steel reinforced systems, temporary applications due
term settlements. but are still acceptable for to durability of facing; can
most applications; generally be designed for wall heights
requires high-quality backfill; of 40 feet or more.
wide base width required
(70% of wall height);
durability of wall facing.
Soil nail walls Relatively low cost; Allow adequate standup Applicable to cut situations
can be used in time for soil/rock to stand in only; not recommended
areas with restricted a vertical cut approximately in clean or water-bearing
overhead or lateral 6 feet high for at least sands and gravels,
clearance. 1 to 2 days; not feasible for in bouldery soils that
bouldery soils; may require can interfere with nail
an easement for the nails. installation, or in landslide
deposits, especially where
deep potential failure
surfaces are present;
maximum wall heights
of 35 feet are feasible,
though greater wall heights
are possible in excellent
soil/rock conditions. A
special design is always
required.
Specific
Advantages Disadvantages Limitations
Wall Type
Concrete crib walls Relatively low cost; Aesthetics. Applicable to cut and
quantity of high- fill situations; reinforced
quality backfill concrete typically can be
required relatively designed for heights of up
small; relatively to 33 feet and unreinforced
narrow base concrete up to 16 feet; not
width, on the order used to support bridge
of 50 to 60% of the or building foundations.
wall height; can
tolerate moderate
settlements.
Metal crib walls Quantity of high- Relatively high cost; Applicable to cut and fill
quality backfill aesthetics. situations; can be designed
required relatively routinely for heights
small; relatively up to 35 feet; not used
narrow base to support bridge or building
width, on the order foundations.
of 50 to 60% of the
wall height; can
tolerate moderate
settlements.
Timber crib walls Low cost; minimal Design life relatively short; Applicable to cut and fill
high-quality backfill aesthetics. situations; can be designed
required; relatively for heights up to 16 feet; not
narrow base used to support structure
width, on the order foundations.
of 50 to 60% of the
wall height; can
tolerate moderate
settlements.
Concrete bin walls Relatively low cost; Aesthetics. Applicable to cut and fill
narrow base situations; can be designed
width, on the order routinely for heights
of 50 to 60% of the up to 25 feet; not used
wall height; can to support bridge or building
tolerate moderate foundations.
settlements.
Gabion walls Relatively narrow Relatively high cost, Applicable to cut and fill
base width, depending on proximity situations; can be designed
on the order to source of high-quality routinely for heights up
of 50 to 60% of the angular rock to fill baskets. to 15 feet, and by special
wall height; can design up to 21 feet; not
tolerate moderate used to support structure
settlements. foundations.
Specific
Advantages Disadvantages Limitations
Wall Type
Mortar rubble Quantity of high- High cost; relatively wide Applicable mainly to fill
masonry walls quality backfill base width, on the order situations where foundation
required is relatively of 60 to 70% of the wall conditions consist of very
small. height; cannot tolerate dense soil or rock; due
settlement. to expense, only used in
areas where other mortar
rubble masonry walls are
present and it is desired
to match aesthetics;
typically can be designed for
maximum heights of 25 feet.
Unreinforced Quantity of high- High cost; relatively wide Applicable mainly to fill
concrete gravity quality backfill base width, on the order situations where foundation
walls required is relatively of 60 to 70% of the wall conditions consist of very
small. height; cannot tolerate dense soil or rock; due
settlement. to expense, only used in
areas where other gravity
walls are present and it is
desired to match aesthetics;
typically can be designed for
maximum heights of 25 feet.
Reinforced concrete Relatively narrow High cost; cannot tolerate Applicable to cut and fill
cantilever walls base width on much settlement; relatively situations; can be routinely
the order of 50 to deep embedment might be designed for heights up
60% of the wall required on sloping ground to 35 feet.
height; can be used due to toe in front of face
to support structure wall.
foundations by
special design.
Reinforced concrete Relatively narrow High cost; cannot tolerate Applicable to cut and fill
counterfort walls base width on much settlement; relatively situations; can be routinely
the order of 50 deep embedment might be designed for heights up
to 60% of the wall required on sloping ground to 50 feet; proprietary
height; can be used due to toe in front of wall versions are typically 33 feet
to support structure face. maximum.
foundations by
special design.
Specific
Advantages Disadvantages Limitations
Wall Type
Soldier pile wall Very narrow Relatively high cost. Applicable mainly to cut
base width; deep situations; maximum
embedment to get feasible exposed height
below potential is on the order of 10 feet;
failure surfaces; difficult to install in bouldery
relatively easy soil or soil with water-
to obtain. bearing sands.
Sheet pile wall Low to moderate Difficult to get embedment Applicable mainly to cut
cost; very narrow in dense or bouldery soils; situations in soil; maximum
base width. difficult to protect against feasible exposed height is
corrosion. on the order of 10 feet.
Cylinder pile wall Relatively narrow Very high cost. Applicable mainly to cut
base width; can situations; maximum
produce stable wall feasible exposed height is
even if deep on the order of 20 to 25 feet
potential failure depending on the passive
surfaces present. resistance available; can be
installed in bouldery
conditions, though cost will
increase.
Slurry wall Relatively narrow Very high cost; difficult Applicable mainly to cut
base width; can construction. situations; maximum
produce stable feasible exposed height is
wall even if deep on the order of 20 to 25 feet,
potential failure depending on passive
surfaces present. resistance available.
Specific
Advantages Disadvantages Limitations
Wall Type
All nongravity Relatively narrow Very high cost; difficult Applicable only to cut
cantilever walls with base width; can to install in areas where situations; can be designed
tiebacks produce stable vertical or lateral clearance for heights of 50 feet
wall even if deep is limited; easements may or more depending on the
potential failure be necessary; installation specifics of the structure of
surfaces present. activities may impact the wall.
adjacent traffic.
All nongravity Relatively narrow Moderate to high cost; Applicable to partial cut/
cantilever walls with base width; can access required behind wall fill situations; can be
deadman anchors produce stable wall to dig trench for deadman designed for wall heights
even if deep anchor; may impact traffic of approximately 16 feet.
potential failure during deadman installation;
surfaces present. easements may be
necessary.
Wall/Slope Specific
Advantages Disadvantages Limitations
Classification Wall Type
Rockeries Only variations Low cost; narrow Slope needs Applicable to both cut and
are in rock sizes base width on to be at least fill situations; maximum
used and overall the order of 30% marginally stable feasible height in a cut,
wall dimensions. of the wall height without rockery even for excellent soil
required. present; cannot conditions, is approx.
tolerate much 16 feet and 8 feet in fill
settlement. situations.
Reinforced Only variations Low cost; can Room required Best suited to sloping fill
slopes are in tolerate large between the right situations; maximum height
geosynthetic settlements; of way line and limited to 30 feet unless
products can adapt well the edge of the geosynthetic products are
used and in to sloping ground shoulder to install used in which long-term
erosion-control conditions a 1H:1V slope. product durability is well
techniques used to minimize defined. Certain products
on slope face. excavation can be used in critical
required; high- applications and for greater
quality fill is not slope heights on the order
a requirement. of 60 feet or more, but
consider need, landscaping
maintenance, and the reach
of available maintenance
equipment.
Design Process – Initiated by region, except by HQ Bridge Office for walls included in bridge preliminary plan.
Coordination with State Bridge and Structures Architect, HQ Bridge Office and
HQ Geotech Office to identify wall concepts and constraints (0.5 to 1 month)
See Exhibit
730-13b for
proprietary Region develops and submits wall profile, plan, and cross sections
(site data) with design request to RME
Yes
Standard wall
No (Std. Plan walls, gabions Yes
Proprietary up to 6 ft and rockeries
No up to 5 ft)
> 10 ft
Wall Ht ** 10 ft *
Wall type:
nonstandard
nonproprietary Gabions 6 ft
[2] walls [1] [1] Rockeries 5 ft
HQ Geotech Office
HQ Geotech Office
performs geotech performs geotech Geotech by region
design and design and Materials Lab [3]
recommends wall recommends wall (1.5 to 3 months)
alternatives as alternatives as
appropriate appropriate
(1.5 to 4.5 months)
(1.5 to 4.5 months)
Proprietary
Yes
No Yes
Preapproved
>10 ft < 10 ft *
Wall Ht.**
Submit wall site data
with design request to
HQ Bridge Office, with a Geotech by region Materials
Submit wall site data with
copy to the Geotech Office Lab (1.5 to 3 months)
and the State Bridge and design request to
Structures Architect Geotech Office
Notes:
“HQ Bridge Office” refers to the WSDOT HQ Bridge and Structures Office.
“Geotech Office” refers to the WSDOT HQ Geotechnical Office.
“State Bridge and Structures Architect” refers to the Architecture Section, HQ Bridge and Structures Office.
Regarding time estimates:
Assumes no major changes in the wall scope during design.
Actual times may vary depending on complexity of project.
Contact appropriate design offices for more accurate estimates of time.
Legend:
Region provides courtesy copy of geotechnical report to HQ Geotechnical Office.
*Assumes soft or unstable soil not present and wall does not support other structures.
**The preapproved maximum wall height is generally 33 feet. Some proprietary walls might be less. (Check with the
HQ Bridge and Structures Office.)
***If the final wall selected is a different type than assumed, go back through the design process to ensure that all the
steps have been taken.
740.01 General
The function of a noise barrier is to reduce traffic noise levels in adjoining areas. The noise
abatement decisions are made during the environmental stage of project development, which is
a highly interactive process. Before a noise barrier is designed, the Washington State
Department of Transportation (WSDOT) needs to be confident that there is significant need, a
cost-effective and environmentally acceptable noise barrier, a source of funds, and acceptance
by adjacent property owners, local governmental agencies, and the general public.
Preliminary design information that may be found in the noise report includes:
Sources of noise.
Noise receiver locations.
Predicted level of noise reduction.
Locations of existing and future noise ¬impacts along the project corridor.
Barrier location and height recommendations based on what is feasible and
reasonable.
Design of a noise barrier project is the result of a team effort coordinated by the Project
Engineer.
This chapter addresses the factors that are considered when designing a noise barrier and the
associated procedures and documentation requirements.
740.02 Design
The two basic types of noise barriers are the earth berm and the noise wall. An earth berm can
be constructed to the full height required for noise abatement or to partial height in conjunction
with a noise wall to reach the required height. A noise wall can be made of concrete, masonry,
metal, wood, or other approved innovative products, and can be supported by spread, pile,
shaft, or trench footings.
Consideration of the noise report and the visual characteristics of adjacent land forms,
vegetation, and structural elements (such as buildings, bridges, and retaining walls) will
determine whether a proposed noise barrier might be berm, wall, or both.
An earth berm is the primary alternative if the visual and environmental quality of the corridor
will be preserved or enhanced and materials and right of way widths are available. (See the
Roadside Manual for criteria for determining whether a vegetated earth berm is appropriate.)
The region uses the noise report and other environmental documents (see the Environmental
Manual) to help determine the location, exposure conditions, length, and height of the
proposed noise barrier.
To design and locate a noise barrier of any kind, consider the following:
Desired noise abatement
Future right of way needs
Cost and constructability
Neighborhood character
Visual character and quality of the corridor
Future maintenance of the noise barrier and the whole right of way
Wind
Supporting soil
Earthquakes
Groundwater
Existing drainage systems and water courses
Exposure to vehicular impacts
Potential for vandalism
Existing vegetation and roadside restoration required
Access for maintenance equipment and enforcement, traffic service, and emergency
vehicles
Access to fire hydrants from both sides
Pedestrian and bicycle access
Available and attainable width of right of way for berms
Aesthetic and structural characteristics of available wall designs
Visual compatibility of each wall design with other transportation structures within the
corridor
Construction limits for footings
Locations of existing survey monuments
Access to and maintenance of right of way behind a wall, including drainage structures
Use of right of way and wall by adjacent property owners
Drainage and highway runoff
Drainage from adjacent land
Existing utilities and objects to relocate or remove
Water and electricity needs, sources, and access points
Avoid objects such as bridge columns, light fixtures, or sign supports that protrude and may
present a potential for snagging vehicles.
There are noise wall designs in the Standard Plans. Additional designs are in various stages of
development to become standard plans. The draft-standard design sheets and other
preapproved plans are available from the Headquarters (HQ) Bridge and Structures Office. The
HQ Bridge and Structures Office also works with the regions to facilitate the use of other designs
as bidding options.
When a noise wall has ground elevations that are independent of the roadway elevations, a
survey of ground breaks (or cross sections at 25 foot intervals) along the entire length of the
wall is needed for evaluation of constructability and to assure accurate determination of panel
heights.
Size of openings (whether lapped, door, or gated) depends on the intended users. Agencies such
as the local fire department can provide the necessary requirements. Unless an appropriate
standard plan is available, such openings are designed and detailed for the project.
When a noise wall is inside the Design Clear Zone, design its horizontal and vertical (ground
elevation) alignment as if it were a rigid concrete traffic barrier. (See Chapter 1610 for maximum
flare rates.)
Provide a concrete traffic barrier shape at the base of a new noise wall constructed 12 feet or
less from the edge of the nearest traffic lane. The traffic barrier shape is optional at the base of
the new portion when an existing vertical-faced wall is being extended (or the existing wall may
be retrofitted for continuity). Standard Concrete Barrier Type 4 is recommended for both new
and existing walls except when the barrier face can be cast as an integral part of a new wall.
Design analyses may be considered, but they require approval as prescribed in Chapter 300.
A design analysis is not required where sidewalk exists in front of the wall or in other situations
where the wall face is otherwise inaccessible to traffic. For flare rates and approach slopes for
concrete barriers, see Chapter 1610, Traffic Barriers.
To designate a standard noise wall, select the appropriate general special provisions (GSPs) and
state the standard plan number, type, and foundation type.
Wall type is a function of exposure and wind speed (see Exhibit 740-1).
A geotechnical report identifying the angle of internal friction “f” and the allowable bearing
pressure is needed for selection of a standard foundation. The standard spread footing designs
require an allowable bearing pressure of 1 Tsf. The standard trench and shaft footing designs
require an “f” of at least 32° for D1 and 38° for D2.
A special design of the substructure is required for noise walls on substandard soil, where winds
exceed 90 mph, and for exposures other than B1 and B2 as defined in Exhibit 740-1.
For maintenance of the surface of a tall wall (10 feet or more), consider harness tie offs for the
fall protection required by the Department of Labor and Industries.
Exposure
B1 B2 C
Wind speed is according to Figure 1-2.1.2.A of the (AASHTO) Guide Specifications for Structural
Design of Sound Barriers. Assume the wind to be perpendicular to the wall on both sides and
design for the most exposed side.
Exposure is determined by the nature of the immediately adjacent ground surface and the
extension of a plane at the adjacent ground surface elevation for 1500 feet to either side of the
noise wall:
Exposure B1 = Urban and suburban areas with numerous closely spaced obstructions having
the size of single-family or larger dwellings that prevail in the upwind direction
from the noise barrier for a distance of at least 1,500 feet.
Exposure B2 = Urban and suburban areas with more open terrain not meeting the
requirements of Exposure B1.
Exposure C = Open terrain with scattered obstructions that includes flat, open country,
grasslands, and elevated terrain.
*For a noise wall with Exposure C, on a bridge or overpass or at the top of a slope, consult the
HQ Bridge and Structures Office, as a special design will probably be necessary.
740.03 Procedures
The noise unit notifies the Project Engineer’s Office when a noise barrier is recommended in the
noise report.
The Project Engineer’s Office is responsible for interdisciplinary teams, consultation, and
coordination with the public, noise specialists, maintenance, construction, region Landscape
Architecture Office (or the HQ Roadside and Site Development Section), right of way personnel,
Materials Laboratory, State Bridge and Structures Architect, HQ Bridge and Structures Office,
CAE Support Team, HQ Development Services & Access Manager, consultants, and many others.
If a noise wall is contemplated, the region evaluates the soils (see Chapters 610 and 710) and
obtains a list of acceptable wall design options. The list is obtained by sending information
pertaining to soils and drainage conditions, alignment, and height of the proposed wall to the
State Bridge and Structures Architect.
If a vegetated earth berm is considered, see the Roadside Manual for procedures.
The State Bridge and Structures Architect coordinates with the HQ Bridge and Structures Office,
HQ Hydraulics Section, HQ Geotechnical Office, and the region to provide a list of acceptable
standard, draft-standard, and preapproved proprietary noise wall designs, materials, and
finishes that are compatible with existing visual elements of the corridor. Only wall designs from
this list may be considered as alternatives. Limit design visualizations of the highway side of
proposed walls (available from the CAE Support Team in Olympia) to options from this list. The
visual elements of the private property side of a wall are the responsibility of the region unless
addressed in the environmental documents.
After the noise report is completed, any changes to the ¬dimensions or location of a noise
barrier must be reviewed by the appropriate noise unit to determine the impacts of the changes
on noise abatement.
On limited access highways, coordinate any opening in a wall or fence (for pedestrians or
vehicles) with the HQ Development Services & Access Manager and obtain approval from the
Director & State Design Engineer, Development Division.
On nonlimited access highways, an access connection permit is required for any opening
(approach) in a wall or fence.
The HQ Bridge and Structures Office provides special substructure designs to the regions upon
request; reviews contract design data related to standard, draft-standard, and preapproved
designs; and reviews plans and calculations that have been prepared by others (see Chapter
710).
Approval by the State Bridge and Structures Architect is required for any attachment or
modification to a noise wall and for the design, appearance, and finish of door and gate-type
openings.
Approval by the State Bridge and Structures Architect is also required for the final selection of
noise wall appearance, finish, materials, and configuration.
740.04 Documentation
Refer to Chapter 300 for design documentation requirements.
740.05 References
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
800.01 General
Hydraulic design factors can significantly influence the corridor, horizontal
alignment, grade, location of interchanges, and necessary appurtenances required
to convey water across, along, away from, or to a highway or highway facility.
An effective hydraulic design conveys water in the most economical, efficient,
and practical manner to ensure reasonable public safety without incurring excessive
maintenance costs or appreciably damaging the highway or highway facility, adjacent
property, or the total environment.
This chapter is intended to serve as a guide to highway designers so they can
identify and consider hydraulic-related factors that impact design. Detailed
criteria and methods that govern highway hydraulic design are in the Washington
State Department of Transportation (WSDOT) Hydraulics Manual and
Highway Runoff Manual.
Some drainage, flood, and water quality problems can be easily recognized and
resolved; others might require extensive investigation before a solution is developed.
Specialists experienced in hydrology and hydraulics can contribute substantially
to the planning and project definition phases of a highway project by recognizing
potentially troublesome locations, making investigations, and recommending
practical solutions. Regions may request that the Headquarters (HQ) Hydraulics
Section provide assistance regarding hydraulic problems.
Since hydraulic factors can affect the design of a proposed highway or highway
facility from its inception, consider these factors at the earliest possible time during
the planning phase.
In the project definition phase, begin coordination with all state and local
governments and Indian tribes that issue or approve permits for the project.
800.02 References
(1) Design Guidance
Highway Runoff Manual, M 31-16, WSDOT
Hydraulics Manual, M 23-03, WSDOT
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans),
M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard
Specifications), (Amendments and General Special Provisions), M 41-10, WSDOT
Utilities Manual, M 22-87, WSDOT
(g) The drainage pattern. Do not redirect flow from one drainage basin to another;
follow the historical drainage pattern.
800.06 Documentation
For the list of documents required to be preserved in the Design Documentation
Package and the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev
900.01 General
The Washington State Department of Transportation (WSDOT) recognizes roadsides as an asset.
WSDOT is committed to highway designs that meet the transportation needs in a way that
reduces the potential for fatal and injury crashes, is cost-effective, ecologically appropriate,
context appropriate, and maintainable by managing roadsides that balance the natural and
environmental functions within the right of way.
The roadside integrates natural processes and visual continuity into the built (roadway)
environment, preserving and promoting these natural and environmental functions. Highway
projects achieve this integration through introduction and configuration of specific design
elements such as structures, vegetation, signs, pedestrian and bicycle movement, erosion
control, stormwater treatment facilities, etc.
Develop highway designs in accordance with the criteria provided in the current version of
WSDOT Roadside Policy Manual (RPM). Use guidance provided in the WSDOT Roadside Manual
(RM), where appropriate, when implementing the provisions of the RPM. Provide coordination
and engagement with WSDOT partners when designing roadsides. Also refer to the RM when
addressing design issues such as law and policy, soil bioengineering, contour grading,
vegetation, irrigation, etc. These manuals can be found at:
www.wsdot.wa.gov/design/roadside/.
The Headquarters (HQ) Roadside and Site Development Section will provide roadside and
mitigation design, visual impact assessment, and construction inspection work for the project
offices in regions without a Landscape Architect. Refer to the Project Management Online Guide
for further descriptions of the roles and responsibilities of project teams.
WSDOT Design Manual M 22-01.17 Page 900-1
September 2019
Roadsides Chapter 900
900.02(2)(a) Regulatory
The first type of project is work related to regulatory or permit requirements. Examples are
wetland mitigation work or Hydraulic Permit Approvals (HPAs). This work typically must occur
by the time the impacting project is complete.
900.02(2)(b) Restoration
The second type of project is the restoration of construction impacts to roadside functions to
meet the WSDOT policy requirements outlined in the Roadside Policy Manual.
The goal is to give WSDOT Maintenance a site that is nearly self-sustaining after the plant
establishment period is complete.
900.03 Documentation
Refer to Chapter 300 for design documentation requirements.
900.04 References
Maintenance Manual, M 51-01, WSDOT
Roadside Manual, M 25-30, WSDOT
Roadside Policy Manual, M 3110, WSDOT
Understanding Flexibility in Transportation Design – Washington, WSDOT, 2004
Utilities Accommodation Policy, M 22-86, WSDOT
For utility-related roadside issues, see the Utilities Manual, and for Scenic Classification ratings,
see the Utilities Accommodation Policy
For WSDOT Project Management web resources, start here:
www.wsdot.wa.gov/projects/projectmgmt/
Roadside Design Guide, AASHTO, 2011
Roadside development concepts covered elsewhere in the Design Manual include the following:
Fencing (Chapter 560)
Jurisdiction (Chapters 300, 1100, 1600)
Noise barriers (Chapter 740)
Pedestrian facilities (Chapter 1510)
WSDOT Design Manual M 22-01.17 Page 900-3
September 2019
Roadsides Chapter 900
950.01 General
There has been a growing interest on the part of communities What is public art?
to use art within the transportation facilities of the Washington
State Department of Transportation (WSDOT). It can be used For the purposes of WSDOT
to provide visual interest along roadsides, make unique policy, public art is an
statements about community character, and create a positive enhancement to a functional
public response that will last over time. element, feature, or place
within a transportation
Proponents for public art might be local agencies or engaged corridor to provide visual
citizens’ groups with interest in the outcome of a WSDOT interest. The enhancement
project. The environmental and public involvement processes could be an addition to a
offer opportunities for community partnership on the visual functional element,
and aesthetic qualities of a corridor. integrated into a design,
or for purely aesthetic
The public art policy in this chapter is intended to: provide
purposes.
guidance for managing public art on WSDOT facilities and
within its rights of way; reinforce the existing policy in the An element is considered
Roadside Policy Manual; designate appropriate locations for “public art” if it is beyond
the incorporation of public art features; and provide for the WSDOT standard practice
consistent use of statewide development, review, and approval for architectural treatment.
processes on new and existing features.
The appropriateness of public art is frequently dependent upon its location and composition.
For example, an art piece or feature chosen for the back side of a noise wall, at a safety rest
area, or along a bike path may not be suitable at the end of a freeway ramp or along the main
line of a highway. In addition to appropriate placement, WSDOT must balance the requests for
proposed public art projects with the need to provide corridor continuity, improve the unity of
highway elements, and provide roadsides that do not divert motorists’ attention from driving.
While some local jurisdictions dedicate a percentage of their project budgets for art, WSDOT
has no such dedicated funding. Section 40 of the State Constitution specifies that gas tax money
must be used for a “highway purpose.” Therefore, public art beyond WSDOT standard design
is typically funded by communities or other entities outside of WSDOT.
When city or community entrance markers are proposed, this policy should be used in
conjunction with the guidance contained in Chapter 1600, Roadside Safety, the Traffic Manual,
and the Roadside Policy Manual.
950.02 References
950.02(1) Federal/State Laws and Codes
Chapter 47.42 Revised Code of Washington (RCW), Highway advertising control act –
Scenic vistas act
To discuss the details of proposed public art projects, contact the State Bridge and Structures
Architect, and the region or Headquarters (HQ) Landscape Architect for regions without a
Landscape Architect. They are key members of the Public Art Specialty Services Team (described
in 950.05) and can answer questions and assist in determining an appropriate course of action.
The following criteria are to be addressed and documented in the public art plan:
• The public art proponent, the funding source, and those responsible for the installation
and maintenance of the proposed art.
• Safe maintenance access.
• Maintenance Agreement with local agencies for maintenance where appropriate. If
there is a potential for vandalism, address this issue in the associated maintenance
agreement.
The following are examples of types and locations of acceptable public art features:
• Concrete surface treatments (beyond WSDOT standard)
• Colored paving/colored pavers/scoring patterns (beyond WSDOT standard)
• Specially designed benches, trash cans, planters, or other street furnishings
• Soft lighting and lighting fixtures
• Small-scale sculptures or art pieces (when not viewed from the main line)
• Attachments to decorative railings, light poles, or fences
• Decorative bus shelters
A public art plan is developed to incorporate public art into projects on state highways. Include
the review of the public art plan by the Public Art Specialty Services Team in project reviews.
Without an approved public art plan, a Maintenance Agreement (as appropriate), and funding,
the “art” will not be constructed or installed.
For public art proposed within Interstate Limited Access, the following team members are also
required:
• Assistant State Design Engineer
• Federal Highway Administration (FHWA) Safety/Geometric Engineer or a designee
Consider team membership from the following functional areas when their expertise is
applicable:
• Maintenance
• Planning
• Environmental
• Real Estate Services
950.06 Approvals
950.06(1) Intermediate Approvals
The Public Art Specialty Services Team is responsible for approving the public art; therefore,
be sure to involve them in the development of art during the earliest possible phase of project
development. This will ensure approvals happen smoothly and WSDOT and FHWA are aware
of the public art as soon as possible.
950.07 Documentation
The public art plan, complete with approval signatures, is retained in the Design Documentation
Package (DDP).
1010.01 General
Addressing work zone impacts to all road users is an important component in the design of a
project and needs to be given adequate consideration early in the design process. Most work
zones create some level of traffic impacts and require additional safety features; therefore,
all work areas and operations needed for construction must be identified and addressed
during the project design. Planners, designers, construction engineers, maintenance
personnel, and others all play a role in developing a comprehensive work zone design.
Consider including Rail, Freight, and Ports, Commercial Vehicle Services, and Public
Transportation Divisions for help coordinating with freight and transit industries. See the
WSDOT Project Management website for information on project teams.
This chapter provides the designer with guidance to develop comprehensive work zone
strategies and plans to address a project’s safety and mobility benefits/improvements for all
modes, as well as constructability. A systematic process for addressing work zone impacts is
required by federal regulations and state policy.
1010.02 Definitions
The following terms are defined in the Design Manual Glossary:
Transportation Management Area (TMA)
Transportation Management Plan (TMP)
work zone
work zone impact
work zone traffic control
traveling public
All WSDOT employees are directed to make the safety of workers and the
traveling public our highest priority during roadway design, construction,
maintenance, and related activities.
Designers should be familiar with this document. The policy defines how WSDOT programs
address work zone safety and mobility issues during project planning, design, and
construction.
The TO components are those strategies for improving traffic flow and safety through the
work zone. Some of these strategies may be included in the PS&E, but could also be WSDOT-
managed elements outside the contract. The TO components may include but are not limited
to the following strategies:
• Demand Management Strategies such as Transit service improvements, transit
incentives, and park & ride promotion.
• Corridor/Network Management (traffic operations) Strategies such as Signal
timing/coordination improvements, temporary signals, bus pullouts, reversible
lanes, and truck/heavy-vehicle restrictions.
• Work Zone Safety Management Strategies such as using positive protective devices,
speed limit reductions, automated flagger assistance devices, radar speed display
signs, and smart work zone systems.
• Traffic/Incident Management and Enforcement Strategies such as Work Zone
Intelligent Transportation Systems (ITS), Washington State Patrol, tow service,
WSDOT Incident Response Team vehicle(s), traffic screens, and emergency pullouts
in long work zones with narrowed shoulders.
The TMP Checklist in Exhibit 1010-3 will help identify and organize TMP components. Include
the completed checklist in the Project File. For significant projects, develop this checklist and
the supporting plans, data, impacts assessment, strategies, capacity/delay analysis and
endorsements into a formal TMP document to be included in the Project File. For TMP
examples, see:
http://www.ops.fhwa.dot.gov/wz/resources/final_rule/tmp_examples/sample_tmps.htm
http://www.ops.fhwa.dot.gov/wz/resources/publications/trans_mgmt_plans/trans_mgmt
_plans.pdf
policy and federal regulations, and they are key to the successful development of a project’s
TMP.
• Determine work zone impacts through an impact assessment process.
• Minimize, mitigate, and manage work zone impacts.
• Integrate work zone impacts strategies early, during planning, programming, and
design.
• Develop an accurate scoping estimate based on the work zone strategies.
• Hold a Work Zone Design Strategy Conference early in the design process. (Include
bridge, construction, traffic, maintenance, freight, transit, local agency, and law
enforcement personnel.)
• Utilize the Work Zone TMP Checklist/TMP document (required for significant projects).
• Emphasize flagger safety.
• Assess work zone mobility through a capacity analysis.
• Integrate project constructability, work efficiency and cost containment into the work
zone strategy.
• Attend work zone training.
• Address Washington State traffic and safety regulations as provided for by state law.
• Use the legally adopted Manual on Uniform Traffic Control Devices (MUTCD), with
Washington State modifications as the minimum standard.
• Provide an appropriate level of traffic control plans (TCPs).
• Consider work zone ITS elements.
• Use established design criteria in work zone roadway and roadside design.
• Accommodate pedestrian access (including ADA requirements) and maintenance of
existing transit stops and bicycle traffic.
• Consider maintenance issues and needs through the duration of the project.
• Consider school, hospital, emergency services, and postal delivery, impacts.
• Consider economic impacts (business access) due to traffic delay or restricted access.
• Consider freight mobility; total roadway widths to less than 16 feet should be avoided if
possible. Truck routes can be found here:
http://www.wsdot.wa.gov/Freight/EconCorridors.htm
• Address traffic impacts extending beyond the project limits and impacting other roads.
• Identify seasonal or special event impacts that affect recreation or business due to work
zone impacts.
• Consider risk management and tort liability exposure.
• Approach the work zone design from the road user’s perspective.
• Incorporate worker safety needs (positive protection) in your work zone designs.
• Account for all needed work areas, operations and possible staging areas.
• Address work vehicle ingress and egress to each work area.
• Use of law enforcement
A complete and accurate impacts assessment will allow for the development of an effective
TMP that should only need minor modifications to address construction issues. The Traffic
Manual provides information on how to determine expected work zone congestion along
with mobility management strategies.
5. What type of temporary marking is most appropriate for the installation, work duration,
and the pavement surface? Will the final pavement surface have a “ghost stripe”
potential?
6. Lane shifts onto existing shoulders:
• Is the depth of the existing shoulder adequate to carry the extra traffic and are
there rumble stripe that need to be removed?
• Are there any existing catch basins or junction boxes located in the shoulder that
cannot accept traffic loads over them?
• What is the existing side slope rate? If steeper than 4H:1V, does it need mitigation?
Are there existing roadside objects that, when the roadway is shifted, are now
within the clear zone limits?
• Shifting of more than one lane in a direction is only allowed with temporary
pavement markings. Shifting lanes by using channelizing devices is not allowed due
to the high probability that devices used to separate the traffic will be displaced.
• Signal head alignment: When the lane is shifted approaching the intersection, is the
signal head alignment within appropriate limits?
7. Roundabout construction at an existing intersection requires site-specific staging plans.
Roundabouts create many unique construction challenges and each roundabout has very
site-specific design features.
Do not assume that strategies chosen for past projects will adequately address the impacts
for similar current projects. There may be similarities with the type of work, but each project
is unique and is to be approached in that manner. Always look for other options or
innovative approaches; many projects have unique features that can be turned to an
advantage if carefully considered. Even a basic paving project on a rural two-lane highway
may have opportunities for detours, shifting traffic, or other strategies.
The Traffic Manual contains comprehensive information regarding work zone traffic analysis
to determine expected delay and queuing.
When one or more traffic lanes are closed, a capacity analysis is necessary to determine the
extent of congestion that may result. Night work or peak hour work restrictions may be
required if the analysis shows adverse traffic impacts. On highways with speeds over 40
MPH, traffic safety drums and truck-mounted attenuators should be used in lane closures
and the drums should not encroach on the open lanes. Additional lanes should be closed if
encroachment is necessary. Consider closing additional lanes to increase the lateral buffer
space for worker safety.
A shoulder closure is used for work areas off the traveled way. On high-volume freeways or
expressways, they should not be allowed during peak traffic hours. Channelization devices
should not encroach on the open lanes of roadways with speeds of 45 mph and above.
stop bars is required for signal use. For assistance on using these devices, contact the region
Traffic Office.
Refer to WAC 296-155-305 for flagging requirements.
Staged construction entails combining multiple work areas into a logical order to provide
large protected work areas for long durations, which maximizes work operations and
minimizes daily impacts to traffic. Temporary alignment and channelization plans must
be designed to place traffic in these semi-permanent locations. Minimum geometric
design criteria are to be used when developing these plans. Design strategies such as
overbuilding for future stages or the use of temporary structures are often part of staged
construction on significant impact projects or mega projects. Develop detailed capacity
analysis and traffic modeling for each stage.
Utilizing the existing shoulder may be necessary to accommodate the shifting movement.
First, determine the structural capacity of the shoulder to ensure its ability to carry the
proposed traffic. Remove and inlay existing shoulder rumble strips prior to routing traffic
onto the shoulder.
This strategy separates lanes of traffic traveling in one direction around a work area. On
higher-speed roadways, temporary barriers are provided to prevent errant vehicles from
entering the work area. Some drivers have difficulty understanding "lane split"
configurations, which sometimes results in poor driving decisions such as unnecessary or
late lane changes. Braking and erratic lane changes decrease the traffic capacity through
the work zone, which results in an unstable traffic flow approaching the lane split.
Evaluate other strategies, such as overbuilding, to keep traffic on one side of the work
area to avoid a traffic split if possible.
Limit the duration the traffic split can be in place. Consider incentives and
disincentives to encourage the contractor to be as efficient as possible. A higher
level of traffic impacts may be acceptable if offset with fewer impacted days.
This strategy involves total closure of one or both directions of travel on the roadway.
Traffic is routed to a temporary bypass usually constructed within the highway right of
way. An example of this is the replacement of an existing bridge by building an adjacent
temporary structure and shifting traffic onto the temporary structure. A temporary
channelization plan will show pavement markings, barrier and attenuators, sign and
device placement.
This strategy involves placing all multilane highway traffic on one side of the median.
Lanes are usually reduced in both directions and one direction is routed across the
median. The design for elements of temporary crossovers needs to follow the same
guidance as permanent design for alignment, barriers, delineation, and illumination.
Design crossovers for operating speeds not less than 10 mph below the posted
speed limit unless unusual site conditions require a lower design speed.
Median paving may be required to create crossover locations (consider
drainage for the added pavement).
Straight line crossover tapers work best for highways with narrow paved
medians.
Temporary pavement markings, removal of conflicting existing markings, and
construction signs are also required.
A good array of channelizing devices and properly placed pavement markings is
essential in providing clear, positive guidance to drivers.
Provide a clear roadside recovery area adjacent to the crossover. Consider how
the roadway safety hardware (guardrail, crash cushions, and so on) may be
impacted by the traffic using the crossover if the traffic is going against the
normal traffic flow direction. Avoid or mitigate possible snagging potential.
Avoid placing crossover detours near structures.
Include work zone ITS elements in the project or coordinate with TMC to use existing
equipment.
Provide a dedicated tow service to clear incidents.
In addition to work zone signs, provide driver information using highway advisory radio (HAR)
and changeable message signs (existing or portable). Include a Smart Work Zone System to
provide drivers with real time information on queuing and delays. Involve the region TMC in
the development and implementation of these strategies. Additional information on smart
work zone systems can be found on the Work Zone Safety web page:
www.wsdot.wa.gov/safety/workzones/
The Freight Alert system should be used to communicate information with freight industry
on work zones. Each region has the capability to send alerts with this system.
http://www.wsdot.wa.gov/freight/
Work zone strategy development is a fluid process and may be ongoing as project
information and design features are developed during the design process. There may be
many factors involved with strategy development, and it is necessary to be well organized to
make sure all the relative factors are identified and evaluated.
users. These types of traffic control strategies must include demand management and public
information plans to notify road users and mitigate and manage the impacts as much as
possible.
A work zone capacity analysis helps determine whether a work zone strategy is feasible.
Mitigation measures that provide the right combination of good public information, advance
signing and notification, alternate routes, detours, and work hour restrictions, as well as
innovations such as strategic closures, accelerated construction schedules, or parallel
roadway system capacity improvements, can be very effective in reducing mobility impacts.
Some of the impact issues and mitigating measures commonly addressed by traffic analyses
include:
Work hour time restrictions
Hourly liquidated damage assessment
Use of staged construction
Working day assessment
Public information campaign
User cost assessment
Local roadway impacts
Special event and holiday time restrictions
Closure and detour options
Mitigation cost justification
Level of service
Queue lengths
Delay time
Running speed
Coordination with adjoining projects (internal and local agency)
Many projects will have several potential work zone strategies, while other projects may only
have one obvious work zone strategy. It is possible that a significant mobility impact strategy
may be the only option. TMP strategies still need to be considered. An analysis will help show
the results of these mitigating measures.
There is no absolute answer for how much congestion and delay are acceptable on a project;
it may ultimately become a management decision.
Reductions in traffic capacity are to be mitigated and managed as part of the TMP. The traffic
analysis process helps shape the TMP as the work zone strategies are evaluated and refined
into traffic control plans and specifications. Maintain analysis documents in the Project File.
Office and the HQ Transportation Data & GIS Office can assist with collecting traffic volume
data. Coordination with local agencies may be needed to obtain data on affected local roads.
Refer to the Traffic Manual for additional information and guidance.
*These are average capacity values. The actual values would be dependent on several factors, which
include the existing number of lanes, number of lanes closed, traffic speed, truck percentage,
interchanges/intersections, type of work, type of traffic control, and seasonal factors (among others).
For further information, consult the Highway Capacity Manual.
The following resources are also available to assist with the actual analysis and mitigation
strategy development upon request:
HQ Transportation Data & GIS Office
HQ Traffic Offices
Training is also available to obtain further knowledge and expertise in traffic analysis (see
1010.12).
A lateral buffer provides space between the vehicles and adjacent work space, traffic
control device, or a condition such as an abrupt lane edge or drop-off. As a minimum,
a 2-foot lateral buffer space is used. Positive Protective Devices may be required if
workers are within one lane width of traffic. When temporary barriers are used,
place a temporary edge line 2-foot laterally from the barrier.
When feasible, a longitudinal buffer space is used immediately downstream of a
closed or shifted traffic lane or shoulder. This space provides a recovery area for
errant vehicles as they approach the work space.
Devices used to separate the driver from the work space should not encroach into adjacent
lanes. If encroachment is necessary, it is recommended to close the adjacent lane to
maintain the lateral buffer space.
In order to achieve the minimum lateral buffer, there may be instances where pavement
widening or a revision to a stage may be necessary. In the case of short-term lane closure
operations, the adjacent lane may need to be closed or traffic may need to be temporarily
shifted onto a shoulder to maintain a lateral buffer space. During the design of the traffic
control plan, the lateral buffer needs to be identified on the plan to ensure additional width
is available; use temporary roadway cross sections to show the space in relation to the traffic
and work area.
Steep fill slopes and high traffic volumes. (Although it is not presented as absolute
guidance, the Design Clear Zone exhibit in Chapter 1600 may be used as a tool to
assess increases in WZCZ values.)
When a temporary barrier is used to protect the drop-off, the back side the barrier shall be
placed a minimum of 3-feet from the drop-off and a new edge line is required on the traffic
side of the barrier with a 2-foot lateral buffer space minimum. The space behind the barrier
can be reduced if the barrier is anchored. Barrier end attenuators may be required.
Open trenches within the traveled way or auxiliary lane shall have a steel-plate cover placed
and anchored over them. A wedge of suitable material, if required, shall be placed for a
smooth transition between the pavement and the steel plate. Warning signs shall be used to
alert motorists of the presence of the steel plates.
Abrupt lane edges, and drop-offs and steel plates require additional warning and
considerations for motorcyclists, bicyclists, and pedestrians, including pedestrians with
disabilities. Adequate signing to warn the motorcycle rider, bicyclists and pedestrians,
including pedestrians with disabilities of these conditions is required. (See RCW 47.36.200
and WAC 468-95-305.) See Design Manual Chapter 1510 for work zone pedestrian
accommodation guidance.
See Standard Specifications section 1-07.23(1) for the contract requirements for drop off
protection and address project specific protection if necessary.
over-height vehicle impacts and possible additional signing needs and coordination with
permit offices. Widening of existing structures can prove challenging when the existing
height is at or less than legal height, so extra care is required in the consideration of over-
height vehicles when temporary falsework is necessary. Coordination with the HQ Bridge and
Structures Office is essential to ensure traffic needs have been accommodated. Vertical
clearance requirements associated with local road networks may be different than what is
shown in Chapter 720. Coordinate with the local agency.
Refer to the Traffic Manual for additional information, guidance and approval requirements
for speed limit reductions in work zones. Include approval documents in the Project File.
around a work zone. Bicyclists may be required to dismount and walk their bikes through a
work zone on the route provided for pedestrians.
It may be possible to make other provisions to transport pedestrians and bicyclists through a
work zone or with a walking escort around the active work area. Roadway surfaces are an
important consideration for pedestrian and bicycle use. Unacceptable conditions such as
loose gravel, uneven surfaces, milled pavement, and asphalt tack coats endanger the bicyclist
and restrict access to pedestrians with disabilities.
Information can be gathered on bike issues by contacting local bike clubs. Coordination with
local bike clubs goes a long way to ensuring their members are notified of work zone
impacts, and it helps maintain good public relations. (See Chapter 1520 for more bicycle
design requirements and Chapter 1510 and MUTCD Chapter 6D for pedestrian work zone
design requirements.)
or routes that are already strategic oversized load routes may not be able to rely only on
warning or prohibition signs. Protective features or active early warning devices may be
needed. If the risk is so great that one oversized load could potentially cause significant
damage or injury to workers, failsafe protection measures may be needed to protect
structures and workers. The structure design, staging, and falsework openings may need to
be reconsidered to safely accommodate oversized loads.
Details for their design are in Chapter 1020 and the Standard Plans. Sign messages, color,
configuration, and usage are shown in the MUTCD and the Sign Fabrication Manual. Existing
signs may need to be covered, removed, or modified during construction.
To separate workers from motorized traffic when work zone offers no means of
escape for the worker, such as tunnels, bridges, and retaining walls, or for long-
duration worker exposure within one lane-width of high-volume traffic with speeds
of 45 mph and above.
Contract plans showing temporary impact attenuator placement need to include a list of the
approved attenuators that a contractor may use for that installation. See the Attenuator
Selection Template at:
http://www.wsdot.wa.gov/publications/fulltext/design/ProductFolder/Impact_attenuator_s
election_template.xlsx
1010.10(1) Delineation
Temporary pavement markings will be required when permanent pavement markings are
obliterated due to construction operations or temporary reconfigurations needed for long-
term work zone strategies. Temporary pavement markings can be made using paint,
preformed tape, or raised pavement markers. Complex projects will most likely require both
long- and short-duration temporary markings. All temporary pavement markings must be
retroreflective and match permanent pavement marking colors. All conflicting pavement
markings must be completely removed. Temporary pavement markings are installed in
accordance with the Standard Plans and Standard Specifications.
Short-duration temporary pavement markings are made with materials intended to last only
until permanent markings can be installed on paving and BST projects, or for short durations
between construction stages. Short-duration broken line patterns typically consist of a 4-foot
line with a 36-foot gap for paint and tape markings but may be increased to a 10-foot line
with a 30-foot gap when specified in the Contract. Short-duration broken line patterns
consist of a grouping of three raised pavement markings at 3-foot spacing with a 34-foot gap.
Flexible raised pavement markers are required for bituminous surface treatments but
typically are not allowed on other pavement types. Temporary edge lines are installed only
when specified in the plans. When specified, temporary edge lines are either solid lines or
raised pavement markers at 5-foot spacing.
Pre-formed tapes should be used on the final pavement surface to avoid leaving scars when
removed.
Lateral clearance markers are used at the angle points of barriers where they encroach on or
otherwise restrict the adjacent shoulder. Barrier delineation is necessary where the barrier is
less than 4 feet from the edge of traveled way.
1010.10(2) Screening
Screening devices can be used to reduce motorists’ distraction due to construction activities
adjacent to the traveled way. Consider screening when a highway operates near capacity
during most of the day. Screening should be positioned behind traffic barriers to prevent
impacts by errant vehicles and should be anchored or braced to resist overturning when
buffeted by wind. Commercially available screening or contractor-built screening can be
used, provided the device meets crashworthy criteria if exposed to traffic and is approved by
the Engineer prior to installation.
Glare screening may be required on concrete barriers separating two-way traffic to reduce
headlight glare from oncoming traffic. Woven wire and vertical blade-type screens are
commonly used in this installation. This screening also reduces the potential for motorist
confusion at nighttime by shielding construction equipment and the headlights of other
vehicles on adjacent roadways. Make sure that motorists’ sight distance is not impaired by
these glare screens. Contact the HQ Design Office and refer to AASHTO’s Roadside Design
Guide for additional information on screening.
1010.10(3) Illumination
Illumination might be justified if construction activities take place on the roadway at night for
an extended period of time. Illumination might also be justified for long-term construction
projects at the following locations:
Road closures with detours or diversions.
Median crossovers on freeways.
Complex or temporary alignment or channelization.
Haul road crossings (if operational at night).
Temporary traffic signals.
Temporary ramp connections.
Projects with lane shifts and restricted geometrics.
Projects with existing illumination that needs to be removed as part of the
construction process.
Illumination is required when:
Traffic flow is split around or near an obstruction.
1010.10(4) Signals
A permanent signal system can be modified for a temporary configuration such as temporary
pole locations during intersection construction, span wire systems, and adjustment of signal
heads and alternative detection systems to accommodate a construction stage (see Chapter
1330).
1010.12(2) Resources
The responsibility of the designer to fully address all work zone traffic control impacts is very
important because the level of traffic safety and mobility will be directly affected by the
effectiveness of the transportation management plan (TMP). The following resources are
available to assist the designer with various aspects of the work zone design effort.
1010.13 Documentation
Refer to Chapter 300 for design documentation requirements.
1010.14 References
Use the following checklist to develop a formal TMP document on significant projects.
TMP Component √
1. Introductory Material
Cover page
Licensed Engineer stamp page (if necessary)
Table of contents
List of figures
List of tables
List of abbreviations and symbols
Terminology
2. Executive Summary
3. TMP Roles and Responsibilities
TMP manager
Stakeholders/review committee
Approval contact(s)
TMP implementation task leaders (public information liaison, incident management coordinator)
TMP monitors
Emergency contacts
4. Project Description
Project background
Project type
Project area/corridor
Project goals and constraints
Proposed construction phasing/staging
General schedule and timeline
Adjacent projects
5. Existing and Future Conditions
Data collection and modeling approach
Existing roadway characteristics (history, roadway classification, number of lanes, geometrics,
urban/suburban/rural)
Existing and historical traffic data (volumes, speed, capacity, volume-to-capacity ratio, percent trucks,
queue length, peak traffic hours)
Existing traffic operations (signal timing, traffic controls)
Incident and crash data
Local community and business concerns/issues
Traffic growth rates (for future construction dates)
Traffic predictions during construction (volume, delay, queue)
6. Work Zone Impacts Assessment Report
Qualitative summary of anticipated work zone impacts
Impacts assessment of alternative project design and management strategies (in conjunction with
each other)
Construction approach/phasing/staging strategies
Work zone impacts management strategies
TMP Component √
Traffic analysis results (if applicable)
Traffic analysis strategies
Measures of effectiveness
Analysis tool selection methodology and justification
Analysis results
Traffic (volume, capacity, delay, queue, noise)
Safety
Adequacy of detour routes
Business/community impact
Seasonal impacts
Cost-effectiveness/evaluation of alternatives
Selected alternative
Construction approach/phasing/staging strategy
Work zone impacts management strategies
7. Selected Work Zone Impacts Management Strategies
Temporary Traffic Control (TTC) strategies
Control strategies
Traffic control devices
Corridor Project coordination, contracting, and innovative construction strategies
Public Information (PI)
Public awareness strategies
Motorist information strategies
Transportation Operations (TO)
Demand management strategies
Corridor/network management strategies
Work zone safety management strategies
Traffic/incident management and enforcement strategies
8. TMP Monitoring
Monitoring requirements
Evaluation report of successes and failures of TMP
9. Contingency Plans
Trigger points
Decision tree
Contractor's contingency plan
Standby equipment or personnel
10. TMP Implementation Costs
Itemized costs
Cost responsibilities/sharing opportunities
Funding source(s)
11. Special Considerations (as needed)
12. Attachments (as needed)
1020.01 General
The Washington State Department of Transportation (WSDOT) uses signing as the primary
mechanism for regulating, warning, and guiding traffic. Signing must be in place when any
section of highway is open to the motoring public. Each highway project has unique and specific
signing requirements. For statewide signing uniformity and continuity, it is sometimes necessary
to provide signing beyond the project limits. Design characteristics of the facility determine the
size and legend for a sign. As the design speed increases, larger sign sizes are necessary to
provide adequate message comprehension time. The MUTCD, the Traffic Manual, and the Sign
Fabrication Manual contain standard sign dimensions, specific legends, and reflective sheeting
types for all new signs.
Guide signing provides the motorist with directional information to destinations. This
information is always presented in a consistent manner. In some cases, there are specific laws,
regulations, and policies governing the content of the messages on these signs. All proposed
guide signs for a project require the approval of the region Traffic Engineer. The use of
nonstandard signs is strongly discouraged and their use requires the approval of the State
Traffic Engineer.
Apply the following criteria when determining whether to replace or modify existing signs:
Current sign’s service life is reached
Lack of nighttime retroreflectivity
Substantial damage, vandalism, or deterioration
Replace signs with Type I sheeting
Change in sign use policy
Improper location
Message or destination changes necessary to satisfy commitments to public or local
agencies
Substandard mounting height
Change in jurisdiction (for example, a county road becomes a state route)
1020.02(1) Location
The MUTCD contains the guidelines for positioning signs. Check sign locations to ensure the
motorist’s view of the sign is not obscured by other roadside appurtenances. Also, determine
whether the proposed sign will obstruct the view of other signs or limit the motorist’s sight
distance of the roadway. Reposition existing signs, when necessary, to satisfy these visibility
requirements. Where possible, locate signs behind existing traffic barriers, on grade separation
structures, or where terrain features will minimize their exposure to errant vehicles.
Use breakaway sign support features, when required, for signs located within the Design Clear
Zone and for signs located beyond this zone where there is a possibility they might be struck
by an errant vehicle. Breakaway features are not necessary on signposts located behind traffic
barriers. Install longitudinal barriers to shield signs without breakaway features within the
Design Clear Zone when no other options are available.
Sign bridges and cantilever sign structures have limited span lengths. Locate the vertical
components of these structures as far from the traveled way as possible and, where
appropriate, install traffic barriers (see Chapter 1610).
Do not locate signposts in the bottom of a ditch or where the posts will straddle the ditch. The
preferred location is beyond the ditch or on the ditch backslope (see the Standard Plans). In
high-fill areas where conditions require placement of a sign behind a traffic barrier, consider
adding embankment material to reduce the length of the sign supports.
Do not attach supplemental guide signs to the posts below the hinge mechanism or the saw
cut notch on multiple-post installations. The location of these hinges or saw cuts on the sign
supports are shown in the Standard Plans.
A minimum 7-foot vertical height from the bottom of the sign to the ground directly below the
sign is necessary for the breakaway features of the sign support to function properly when
struck by a vehicle. The minimum mounting height for new signs located behind longitudinal
barriers is 7 feet, measured from the bottom of the sign to the edge of traveled way. A lower
mounting height of 5 feet may be used when replacing a sign panel on an existing sign assembly
located behind the longitudinal barrier. The Standard Plans shows typical sign installations.
12 feet from the edge of traveled way in cut sections, the minimum height clearance between
the sign and the ground for the post farther from the edge of traveled way is as follows:
For slopes 2H:1V and steeper, the minimum height clearance is 2 feet.
For slopes 3H:1V or flatter, the minimum height clearance is 7 feet.
Signs used to reserve parking for people with disabilities are installed at each designated parking
stall and are mounted 7 feet above the surface at the sign location.
1020.02(5) Foundations
Foundation details for timber and steel ground-mounted sign supports are shown in the
Standard Plans, which also contains foundation designs for truss-type sign bridges and
cantilever sign structures. Three designs, Types 1, 2, and 3, are shown for each structure.
If a nonstandard foundation or monotube structure design is planned, forward the report to the
Headquarters (HQ) Bridge and Structures Office for use in developing a suitable foundation
design (see Chapter 610).
1020.02(6) Signposts
Ground-mounted signs are installed on either timber posts, laminated wood box posts, or steel
posts. The size and number of posts required for a sign installation are based on the height and
surface area of the sign, or signs, being supported. Use the information in Exhibits 1020-2, 1020-3,
and 1020-4 and the Standard Plans to determine the posts required for each installation.
Coordinate with the region Maintenance Office concerning signpost installation.
Use steel posts with breakaway supports that are multidirectional if the support is likely to be
hit from more than one direction. For any wide flange multiple-steel post installations located
within the Design Clear Zone, the total weight of all the posts in a 7-foot-wide path is not to
exceed a combined post weight of 34 lbs/foot. Use the Wide Flange Beam Weights table in
Exhibit 1020-3 to determine wide flange steel post weights. If the proposed sign configuration
does not meet the weight criterion, relocate, resize, or provide barrier protection for the
proposed installation.
All signposts are to be designed to 90 mph wind loads. Design features of breakaway supports
are shown in the Standard Plans. Steel signposts commonly used are: Perforated Square Steel
Tube (PSST); Square Steel Tube (SST); Round Pipe (RP); and Wide Flange "H-Beam." Steel posts
with Type TP-A, TP-B, PL, PL-T, PL-U, AS, AP, SB-1, and SB-2 bases have multidirectional
breakaway features.
Details for the construction of truss-type sign bridges and cantilever sign supports are shown
in the Standard Plans.
The HQ Bridge and Structures Office designs structure-mounted sign mountings, monotube sign
bridges, and monotube cantilever sign supports. For overhead sign installation designs, provide
sign dimensions, horizontal location in relation to the roadway, and location of the lighting
fixtures to facilitate design of the mounting components by the HQ Bridge and Structures Office.
1020.03(1) Illumination
The retroreflectivity of currently approved sign sheeting removes the need to provide
illumination for most sign installations.
The sign lights for existing illuminated overhead and ground-mounted signs can only be
de-energized and removed if the retroreflective sheeting is adequate for nighttime legibility,
or replace the existing sign with a new sign (see Exhibit 1020-1 for sheeting requirements).
A nighttime assessment of all nonilluminated overhead signs within the project limits is
required. Replace all signs that have inadequate retroreflectivity (contact the region Traffic
Office). In situations where a nonhighway light source interferes with a sign’s legibility, consider
relocating the sign or providing sign lights.
Flashing beacon signs are used to alert motorists of unusual or unexpected driving conditions
ahead. Sign lights are unnecessary on flashing beacon signs when appropriate sign sheeting,
full circle or tunnel signal head visors, and automatic dimmer devices are used.
All other overhead signs are illuminated only when one of the following conditions is present:
Sign visibility is less than 800 feet due to intervening sight obstructions such as highway
structures or roadside features.
Signs directly adjacent to other overhead signs have sign lights.
Vandalism of signs, particularly in the form of graffiti, can be a major problem in some areas.
Vandals sometimes use the service walkways and vandalize the signs. Maintenance costs for
cleaning or replacing the vandalized signs at these locations can exceed the benefit of providing
the service walkway.
1020.05 Mileposts
Milepost markers are a part of a statewide system for all state highways and are installed in
accordance with Executive Order E 1064, “State Route Mileposts,” and Chapter 2 of the Traffic
Manual.
1020.07 Documentation
Refer to Chapter 300 for design documentation requirements.
1020.08 References
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic
Signals, 4th Edition, Washington DC, AASHTO, 2001
Y/2
Y/2
Y
Y
0.6X
H1
H
H2
V
Z
V
B
A
A
D
B
D
C
Notes: D = Embedment depth
The following designs are not permitted when a sign is to H = Total post height
be located in or outside the Design Clear Zone in an area V = Vertical clearance from edge of traveled way
where it is likely to be struck by an errant vehicle: W = Distance from edge of traveled way to the
1. A sign with any post larger than 6x8 inches. centerline of the post nearest the roadway
2. A 2-post, 3-post, or 4-post sign that uses Design Example – Single Post
6x6-inch or larger posts and has two posts spaced Given:
less than 7 ft apart on center. Sign 3 ft wide, 3.5 ft high; a secondary sign 1.5 ft
wide, 2 ft high, mounted 3 inches (0.25 ft) below;
Table 1 Timber Post Selection
8-ft shoulder with 2% slope; 6H:1V embankment;
(X)(Y)(Z) (ft3)
Post Size D W = 15 ft; V = 5 ft
Number of Posts
(in) (ft) Solution:
1 2 3 4
X = 3 ft
4x4 60 115 175 235 3
Y = 3.5 + 2 + 0.25 = 5.75 ft
4x6 125 335 500 675 4
A = (0.02)(8) = 0.16
6x6 200 415 620 815 4
B = (W-8)/6 = (15-8)/6 = 1.17
6x8 330 695 1150 1515 5
Z = Y/2 + V + A + B
6 x 10 670 1355 2030 2700 6
8 x 10 835 1685 2515 3360 6 = (5.75/2) + 5 + 0.16 + 1.17 = 9.2 ft
6 x 12 985 2005 2965 3945 7 (X)(Y)(Z) = (3)(5.75)(9.2) = 158.7 ft3
Values shown are the maximum permitted. Since 159 ft3< 200 ft3, from Table 1, select 6x6 post
H = 9.2 + (5.75/2) + 4 = 16.1 ft
For timber grade requirements, see the Standard
Design Example – Double Post
Specifications.
Given:
Foundation depths are based on allowable lateral bearing
pressure in excess of 2500 psf. Sign 12 ft wide, 4 ft high; 10-ft shoulder with 2%
slope; 6H:1V embankment; W = 25 ft; V = 7 ft
If the value (X)(Y)(Z) amount exceeds the limit for 6x12
Solution:
post(s), use steel post(s) for sign installation.
X = 12 ft; Y = 4 ft
A = Vertical distance from edge of traveled
A = (0.02)(10) = 0.2
way to edge of shoulder
B = [(W-10) + (0.6X)]/6 = [(25-10) + (0.6)(12)]/6 = 3.7
B = Vertical distance from slope catch point
C = (0.6)(12)/6 = 1.2
to centerline of longest post
Z = Y/2 + V + A + B = 4/2+7 + 0.2 + 3.7 = 12.9 ft
C = Vertical distance between adjacent posts
(X)(Y)(Z) = (12)(4)(12.9) = 619 ft3
X & Y = Single sign or back-to-back signs: Overall
dimensions of the sign Since 619 ft3 < 695 ft3, select two 6x8 posts.
Multiple signs: Dimensions of the area within H2 = Y/2 + Z + D = 4/2 + 12.9 + 5 = 19.9 ft
the perimeter of a rectangle enclosing the H1 = H2-C = 19.9-1.2 = 18.7 ft
extremities of the sign
Note: 6x6 and larger posts require 7-ft spacing. Sign
Z = Height from ground line to midheight of sign
at the centerline of the longest post may be installed within the Design Clear Zone.
Y/2
Given:
Y
Sign 22 ft wide, 12 ft high; 10 ft shoulder with 2% slope;
3H:1V embankment; W = 32 ft; V = 7ft.
0.2X 0.6X
Solution:
H2
H1
Z
X = 22
Y = 12 V
A = (0.02)(10) = 0.2
B = [(W-10) + (0.7)(X/3)] = [(32-10) + (0.7x22)]/3 = 12.5
B
A
C = (0.35)(22)/3 = 2.6
Z = Y/2 + V + A + B-0.21
= 12/2 + 7 + 0.2 + 12.5-0.21 = 25.5 ft
(X)(Y)(Z) = (22)(12)(25.5) = 6729 ft3
Since 6729 ft3 < 9480 ft3, select three W10x26 (ASTM
A36) or W10x22 (ASTM A992) (see the Standard Plans)
Edge of traveled way
Y/2
Table 1 Wide Flange Steel Post Selection
Y
H1
H2
Y/2
Y
0.6X
H1
H2
V
B
A
D
X & Y = Single sign or back-to-back signs: C
Table 1 Laminated Wood Box Post Selection
Overall dimensions of the sign Post Type Size (in) Z (ft) (X)(Y)(Z) ft3
Multiple signs: Dimensions of the area within M 7 7/8 x 7 7/8 15 < Z< 26 1329
the perimeter of a rectangle enclosing the M 7 7/8 x 7 7/8 Z < 15 1661
extremities of the signs L 7 7/8 x 14 7/8 15 < Z < 26 3502
L 7 7/8 x 14 7/8 Z < 15 4378
Z = Height from ground line to the midheight of
the sign at the centerline of the longest post Table 2 Embedment Depth (D)
D = Embedment depth Sign Area ft 2
H = Post length Z (ft) Up to 51 to 101 to 151 to 201 to 251 to
V = Vertical clearance from edge of traveled way 50 100 150 200 250 290
9 to 12 6 6 7 8 9 10
W = Distance from edge of traveled way to the 13 to 15 6 6 7.5 9 10
centerline of the post nearest the roadway 16 to 18 7 7.5 9
(see the Standard Plans) 19 to 22 7 8 10
23 to 26 7.5 8.5
Design Example – M Post Selection
Design Example – L Post Selection
Given:
Two-post assembly sign 16 ft wide, 6 ft high; 10 ft Given:
shoulder with 2% slope; 6H:1V embankment; W = 25 Two-post assembly sign 18 ft wide, 8 ft high;10 ft
ft; V = 7 ft shoulder with 2% slope; 6H:1V embankment W = 25
Solution: ft; V = 7 ft
X = 16 Solution:
Y =6 X = 18
A = (0.02)(10) = 0.2 Y=8
B = [(W-10) + 0.6X]/6 A = (0.02)(10) = 0.2
= [(25-10) + (0.6)(16)]/6 = 4.1 B = [(W-10) + (0.6X)]/6 = [(25-10) + (0.6)(18)]/6 = 4.3
C = (0.6X)/6 = (0.6)(16)/6 = 1.6 C = 0.6X/6 = (0.618)/6 = 1.8
Z = Y/2 + V + A + B = 6/2 + 7 + 0.2+4.1 = 14.3 ft Z = Y/2 + V + A + B = 8/2 + 7 + 0.2 + 4.3 = 15.5 ft
(X)(Y)(Z) = (16)(6)(14.3) = 1373 ft3 (X)(Y)(Z) = (18)(8)(15.5) = 2232 ft3
Since 1373 ft3 < 1661 ft3, select a post type M from Since 2232 ft3 < 3502 ft3, select a post type L from
Table 1. Table 1.
H2 = Y/2 + Z + D = 6/2 + 14.3 + 6 = 23.3 ft H2 = Y/2 + Z + D = 8/2 + 15.5 + 9 = 28.5 ft
H1 = H2-C = 23.3-1.6 = 21.7 ft H1 = H2-C = 28.5 – 1.8 = 26.7 ft
1030.01 General
The primary function of delineation is to provide the visual information needed by a driver to
operate a vehicle in a variety of situations. Delineation includes the marking of highways with
painted or more durable pavement marking lines and symbols, guideposts, and other devices
such as curbs. These devices can use retroreflectance, which is the reflecting of light from a
vehicle’s headlights back to the driver, to enhance an object’s visibility at nighttime.
Delineation is a required design element (see Chapter 1105) on most projects. A decision to
omit delineation is possible if the existing delineation is unaffected by construction and a safety
performance evaluation (see Chapter 321) clearly shows that delineation is not a contributing
factor to crashes. The Washington State Department of Transportation (WSDOT) uses the latest
edition of the Manual on Uniform Traffic Control Devises (MUTCD) as a guide for the design,
location, and application of delineation.
Consult with the region Traffic Office early in the design process to ensure the proposed
delineation is compatible with current WSDOT policy and guidance regarding types of markings
and material selection.
1030.02 Definitions
The following terms are defined in the Design Manual Glossary:
Longitudinal pavement markings define the boundary between opposing traffic flows, and they
identify the edges of traveled way, multiple traffic lanes, turn lanes, and special-use lanes. The
Standard Plans shows the dimensions of longitudinal pavement markings. Longitudinal
pavement markings are as follows:
barrier centerline A very wide—18 inches minimum, usually 20 inches: five 4 inch lines—solid
yellow line or a combination of two single 4-inch solid yellow lines with yellow crosshatching
between the lines, with a total width not less than 18 inches, used to separate opposing traffic
movements where all movements over the line are prohibited. Barrier centerline locations
require the approval of the region Traffic Engineer and Access Engineer.
centerline A broken yellow line used to separate lanes of traffic moving in opposite directions,
where passing in the opposing lane is allowed.
dotted extension line A broken white or yellow line that is an extension of an edge line or
centerline used at exit ramps, intersections on horizontal curves, multiple turn lanes, and other
locations where the direction of travel for through or turning traffic is unclear.
double centerline Two parallel solid yellow lines used to separate lanes of traffic moving in
opposite directions where passing in the opposing lane is prohibited.
double lane line Two solid white lines used to separate lanes of traffic moving in the same
direction where crossing the lane line marking is prohibited.
double wide lane line Two solid wide white lines used to separate a concurrent preferential
lane of traffic where crossing is prohibited.
drop lane line A wide broken white line used in advance of a wide line to delineate a lane that
ends at an off-ramp or intersection.
edge line A solid white or yellow line used to define the outer edges of the traveled way. Edge
lines are not required where curbs or sidewalks are 4 feet or less from the traveled way.
lane line A broken white line used to separate lanes of traffic moving in the same direction.
no-pass line A solid yellow line used in conjunction with a centerline where passing in the
opposing lane is prohibited.
reversible lane line Two broken yellow lines used to delineate a lane where traffic direction is
periodically reversed.
solid lane line A solid white line used to separate lanes of traffic moving in the same direction
where crossing the lane line marking is discouraged.
two-way left-turn centerline Two yellow lines, one solid and one broken, used to delineate
each side of a two-way left-turn lane.
wide broken lane line A wide broken white line used to designate a portion of a high-
occupancy vehicle (HOV) lane located on a divided highway where general-purpose vehicles may
enter to make an exit.
wide dotted lane line A wide broken white line used to designate a portion of a high-
occupancy vehicle (HOV), or business access and transit (BAT) lane located on an arterial
highway where general-purpose vehicles may enter to make a turn at an intersection.
wide lane line A wide solid white line used to separate lanes of traffic moving in the same
direction, at ramp connections, storage lanes at intersections, and high-occupancy vehicle (HOV)
lanes, or at business access and transit (BAT) lanes, bike lanes, and other preferential lanes
where crossing is discouraged.
Transverse pavement markings define pedestrian crossings and vehicle stopping points at
intersections. They are also used to warn motorists of approaching conditions, required
vehicular maneuvers, or lane usage. See the Standard Plans for details of these pavement
markings. Typical transverse pavement markings are as follows:
access parking space symbol A white marking used to designate parking stalls provided for
motorists with disabilities. The marking may have an optional blue background and white
border.
aerial surveillance marker White markings used at one-mile and one-half-mile intervals on
sections of highways where the State Patrol uses airplanes to enforce speed limits.
bicycle lane symbol A white marking consisting of a symbol of a bicyclist and an arrow used in
a marked bike lane. The bicycle lane symbol is to be placed immediately after an intersection
and at other locations as needed (see the MUTCD). Typical spacing is 500 feet, with a maximum
distance of 1,500 feet.
crosswalk line A series of parallel solid white lines used to define a pedestrian crossing.
drainage marking A white line used to denote the location of a catch basin, grate inlet, or
other drainage feature in the shoulder of a roadway.
HOV symbol A white diamond marking used for high-occupancy vehicle lanes. The spacing of
the markings is an engineering judgment based on the conditions of use. Typical spacing is 1000
feet for divided highways and 500 feet for arterial highways.
railroad crossing symbol A white marking used in advance of a railroad crossing where grade
crossing signals or gates are located or where the posted speed of the highway is 40 mph or
higher.
stop line A solid white line used to indicate the stopping point at an intersection or railroad
crossing.
traffic arrow A white marking used in storage lanes and two-way left-turn lanes to denote the
direction of turning movement. Arrows are also used at ramp terminals and intersections on
divided highways to discourage wrong-way movements.
traffic letters White markings forming word messages, such as “ONLY,” used in conjunction
with a traffic arrow at drop-lane situations. Traffic letters are not required for left- and right-
turn storage lanes where the intended use of the lane is obvious.
wide line A wide solid line used for traffic islands, hash marks, chevrons, and other
applications. A wide line used in conjunction with a centerline marking shall be yellow. A wide
line used in conjunction with a lane line or right edge line marking shall be white.
Yield line markings A series of white triangular markings indicating that the lane yields.
Both painted and plastic pavement markings can accomplish the goal of providing a visible
(daytime) and retroreflective (nighttime) pavement marking at the completion of a contract. The
difference between the two marking materials is the projected durability of the markings. Paint
used on sections of highway subjected to high traffic volumes and/or snow-removal operations
might have a durability of only two to three months. Maintenance crews cannot restripe a
highway during winter months; therefore, if a painted marking wears out prematurely, the
highway will not have a stripe until maintenance crews can restripe in April or May. When these
conditions are encountered in a highway project, consider a more durable plastic marking
material and application type that will provide the desired durability for the marking.
Check with your region Traffic Office for any specific pavement marking policy. For the
recommended pavement marking material for different highway types and snow-removal
practices, see Exhibit 1030-1. Consult with the region’s Traffic and Maintenance offices to select
the best material for the project.
1030.03(2)(a) Paint
Paint is the most common pavement marking material. It is relatively easy to apply and dries
quickly (30–90 seconds in warm, dry weather) after application. This allows the application to be
a moving operation, which minimizes traffic control costs and delays to the roadway users. On
construction contracts, paint is applied with two coats: the first coat is 10 mils thick, followed by
a second coat 15 mils thick. The disadvantage of using paint as a pavement marking material is
its limited durability when subjected to traffic abrasion, sanding, or snow-removal activities.
Specify paint only where it will have a durability that will provide a retroreflective stripe until
maintenance crews can repaint the line and extend its usefulness until the next repainting.
Paint is one of two material types dependent upon the solids carrier: solvent or water. The
designer is encouraged to specify waterborne paint. Solvent paint is subject to a monetary
penalty because it contains a high level of volatile organic compounds (VOCs). There is an
Environmental Protection Agency (EPA) Clean Air Act penalty assessed on solvent paint that is
passed on to those who purchase solvent paint in quantity.
Low-temperature waterborne paint is intended to extend the paint season later into the fall,
although it may also be used earlier in the spring. The paint is formulated for application
temperatures of 35° Fahrenheit and rising, though durability can be affected when applied
during conditions where standard waterborne paint could have been used.
1030.03(2)(b) Plastic
Plastic markings have a higher installation cost than paint. They can, however, be a more cost-
effective measure than paint because of their longer service life. Plastic marking materials may
provide a year-round retroreflective pavement marking, while paint may not last until the next
restriping. Plastic marking materials currently listed in the Standard Specifications include the
following:
1. Type A: Liquid Hot Applied Thermoplastic
Thermoplastic material consists of resins and filler materials in solid form at room
temperature. The material is heated to a semiliquid, molten state (400° Fahrenheit) and is
then applied to the roadway by spray or extrusion methods. This material can be used for
both transverse and longitudinal line applications. Special equipment is required for both
the initial application and subsequent maintenance renewal. Sprayed material can be
applied at a thickness of 30 mils and dries in 30 to 60 seconds. The durability of material
applied in this manner is slightly longer than that of paint. Extruded material is applied at a
thickness of 125 mils and has a drying time of 15 minutes. This material can be applied as a
flat line or applied with ridges or profiles (bumps) that enhance wet night visibility. These
profiles produce a rumble effect similar to raised pavement markers when a vehicle crosses
over the marking. (Profiles come in the shape of a raised bar at set intervals and are formed
simultaneously with the extruded baseline.)
This material consists of a mixture of pigment, fillers, resins, and beads that are factory
produced in sheet form, 125 mils thick. The material is applied by heating (drying) the
pavement and top heating the material. The heating process fuses the preformed
thermoplastic material to the pavement surface. These materials, which are used for
transverse markings, are available in white, red, blue, and other colors.
Preformed tape is composed of thermoplastic or other materials that are fabricated under
factory conditions. After curing, the material is cut to size and shipped to the work site in
rolls or in flat pieces. The material is then applied to the roadway with an adhesive on the
underside of the tape. Preformed tape is available in 60, 90, or 125 mils (WSDOT does not
currently specify 125 mil tape.) The most durable application of preformed tape is achieved
when the tape is either inlaid (rolled) into hot asphalt with the top of the tape flush with the
surface of the pavement, or placed in a groove cut into the pavement surface with the top
of the tape slightly below the surface of the pavement.
ASTM has classified preformed tape into two categories: Type 1 and Type 2. Type 1 tape has
a profiled surface and a requirement to have a retroreflectivity of over 500 mcd/m2/lux.
Type 1 tape has proven to be very durable. It is used on high-volume, high-speed highways.
Type 2 tape has a flat surface and a requirement to have a retroreflectivity of over
250 mcd/ m2/lux. Field tests show that Type 2 tape has a shorter durability than Type 1
tape.
1030.03(2)(c) Beads
Glass beads are small glass spheres used in highway markings to provide the necessary
retroreflectivity. The beads are dropped onto the wet marking material immediately after it is
applied (drop-on beads), or premixed into the wet marking material.
Large glass and composite beads are effective when roads are wet. Large glass or composite
beads are not appropriate for standard mil paint as the paint is too thin to properly embed the
large glass or composite beads; therefore, WSDOT specifies small glass or composite beads for
such paint applications. The use of large glass or composite beads is limited to high-build
waterborne paint and other materials with a thickness of at least 22 mils.
Because they are higher than the surrounding pavement surface, pavement markings are
subject to rapid wear caused by traffic and snowplows. As they wear, they lose visibility and
retroreflectivity, particularly in wet weather. Wear on the stripes can be greatly reduced and
their durability considerably increased by placing them in a shallow groove in the surface of the
pavement.
2. Profiled Marking
A profiled pavement marking consists of a baseline thickness and a profiled thickness, which
is a portion of the pavement marking line that is applied at a greater thickness than the
baseline thickness. Profiles are applied using the extruded method in the same application
as the baseline. The profiles may be slightly rounded if the minimum profile thickness is
provided for the entire length of the profile. (See the Standard Plans for the construction
details.)
Embossed plastic lines consist of a flat line with transverse grooves. An embossed plastic
line may also have profiles. (See the Standard Plans for the construction details.)
Inlaid plastic line is constructed by rolling Type C tape into hot mix asphalt (HMA) with the
finish roller. This application is used infrequently by WSDOT and is not in the Standard
Specifications.
Grooved plastic line is constructed by cutting a groove into the pavement surface and
spraying, extruding, or gluing pavement marking material into the groove. The groove depth
is dependent upon the material used, the pavement surface, and the location. The groove is
typically in the range of 20 to 250 mils deep and 4 inches wide. Coordinate with the region
Traffic Office on the use and dimensions of grooved plastic line marking.
Type 2 RPMs are not used as a substitute for right edge lines. They may be used to supplement
the right edge line markings at lane reductions, at sections with reduced lane widths such as
narrow structures, and at the gore of exit ramps. All other applications supplementing right
edge line markings require the approval of the region Traffic Engineer.
Red-backed RPMs are not desired and thus are only used at the discretion of the Region Traffic
Engineer for specific locations. Research regarding their effectiveness for addressing wrong-way
driving has been inconclusive to date.
Type 3 RPMs are used in locations where additional emphasis is desired, including vehicle
separations and islands. Obtain approval by the region Traffic Engineer for all installations of
Type 3 RPMs. Retain approval in the Design Documentation Package.
Reflectorized RPMs are not required for centerline and lane line applications in continuously
illuminated sections of highway. However, if illumination policies (see Chapter 1040) affect a
section of limited access roadway, coordinate with the region Traffic Engineer for RPM
placement details. If reflectorized RPMs are used at an intersection within an illuminated
section, they are also to be used throughout that section.
For raised pavement marker application details, see the Standard Plans.
Designers should be aware that the performance of RRPMs can be compromised, especially on
curves, because the groove can block motorists’ view of the markers. Also, the groove for
RRPMs installed on flat grades can fill with water during rain events and cause the RRPM to be
non-reflective.
RRPMs, when specified, are installed at the locations shown in the Standard Plans for Type 2W
RPMs on multilane one-way roadways and Type 2YY RPMs on two-lane two-way roadways.
For recessed pavement marker application details, see the Standard Plans.
1030.04 Guideposts
1030.04(1) General
Guideposts are retroreflective devices installed at the side of the roadway to indicate alignment.
They are guidance devices rather than warning devices. Guideposts are used as an aid to
nighttime driving primarily on horizontal curves; multilane divided highways; ramps; tangent
sections where they can be justified due to snow, fog, or other reduced-visibility conditions; and
at intersections without illumination.
1030.04(1)(a) Types of Guideposts
The retroreflective device may be mounted on either a white or brown post. The types of
guideposts and their application are as follows:
1. Type W
Type W guideposts have silver-white reflective sheeting, are facing traffic, and are used on
the right side of divided highways, ramps, right-hand acceleration and deceleration lanes,
intersections, and ramp terminals.
2. Type WW
Type WW guideposts have silver-white reflective sheeting on both sides and are used on the
outside of horizontal curves on two-way undivided highways.
3. Type Y
Type Y guideposts have yellow reflective sheeting, are facing traffic, and are used on the left
side of ramps, left-hand acceleration and deceleration lanes, ramp terminals, intersections
on divided highways, median crossovers, and horizontal curves on divided highways.
4. Type YY
Type YY guideposts have yellow reflective sheeting on both sides and are used in the median
on divided highways.
5. Type IC1
Type IC1 guideposts have silver-white reflective sheeting on both sides and an additional
silver-white piece of reflective sheeting below the standard silver-white sheeting on the side
facing traffic. They are used at intersections of undivided highways without illumination.
6. Type IC2
Type IC2 guideposts have silver-white reflective sheeting on both sides and an additional
silver-white piece of reflective sheeting below the standard silver-white reflective sheeting
on the back side. They are used at intersections of undivided highways without illumination.
Beam guardrail can be delineated by either mounting flexible guideposts behind the rail or by
attaching shorter flexible guideposts to the wood guardrail posts.
Concrete barrier can be delineated by placing retroreflective devices on the face of the barrier
about 6 inches down from the top. Consider mounting these devices on the top of the barrier at
locations where mud or snow accumulates against the face of the barrier.
The MUTCD contains criteria for the use of object markers to mark objects in and/or adjacent to
the roadway. Follow these criteria in project design.
The terminal ends of impact attenuators are delineated with modified Type 3 object markers.
These are the impact attenuator markers in the Sign Fabrication Manual. When the impact
attenuator is used in a roadside condition, the marker with diagonal stripes pointing downward
toward the roadway is used. When the attenuator is used in a gore where traffic will pass on
either side, the marker with chevron stripes is used.
End of Roadway markers are similar to Type 1 object markers and are detailed in the MUTCD.
They are used to alert users about the end of the roadway. Follow the MUTCD criteria in project
design.
1030.07 Documentation
Refer to Chapter 300 for design documentation requirements.
1030.08 References
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
Exhibit 1030-1 Pavement Marking Material Guide – Consult Region Striping Policy
Guideposts on
Location Guideposts on Tangents [1][3]
Horizontal curves [1][3]
Divided Highways With Continuous Illumination
Main Line None None
Bridge Approaches None None
Intersections None None
Lane Reductions [4] [4]
Median Crossovers None None
Ramps [4] [4]
Divided Highways Without Continuous Illumination
Main Line with RPMs None [4]
Main Line without RPMs Right Side Only (0.10 mile spacing) [4]
Bridge Approaches [4] [4]
Intersections [4] [4]
Lane Reductions [4] [4]
Median Crossovers [4] [4]
Ramps [4] [4]
Undivided Highways With Continuous Illumination
Main Line None None
Bridge Approaches None None
Intersections None None
Lane Reductions [4] [4]
Undivided Highways Without Continuous Illumination
Main Line [2] Standard Plans, Section M[2]
Bridge Approaches [4] [4]
Intersections with Illumination None None
Intersections without Illumination [4] [4]
Lane Reductions [4] [4]
Notes:
[1] For lateral placement of guideposts, see the Standard Plans, Section M.
[2] Installation of guideposts on tangents and on the inside of horizontal curves is allowed at locations
approved by the region Traffic Engineer.
[3] Barrier delineation is required when the traffic barrier is 4 feet or less from the traveled way. Use
delineator spacing of 40 feet or less.
1040.01 General
Illumination is provided along highways, in parking lots, and at other facilities to enhance the
visual perception of conditions or features that require additional motorist, cyclist, or pedestrian
alertness during the hours of darkness.
For the definitions of limited access control and managed access control, see Chapter 520. For a
listing (by milepost) of the limited access or managed access status of all state highways, refer to
the Access Control Tracking System Limited Access and Managed Access Master Plan, under the
“More Information” heading: www.wsdot.wa.gov/design/accessandhearings. For further
information, refer to the WSDOT/Association of Washington Cities agreement “City Streets as
Part of State Highways”: www.wsdot.wa.gov/localprograms/lag/construction.htm
1040.02 Definitions
The following terms are defined in the Glossary: adaptive lighting system, average light level,
complex ramp alignment and grade, continuous load, footcandle (fc), lamp lumens, light
emitting diode(LED), long tunnel, lumen, luminaire, luminance, luminous flux, maximum
uniformity ratio, maximum veiling luminance ratio, minimum average light level, minimum light
level, mounting height – luminaire, multimodal connection, negative illumination, nighttime,
pedestrian crossing, pole height (H1), positive illumination, roadway luminance, security lighting,
short tunnel, SIgnal Maintenance Management System (SIMMS), slip base, spacing, transit flyer
stop, transit stop, uniformity ratio, and veiling luminance.
An electrical service cabinet containing a photocell and circuit breaker for each
illumination circuit.
Runs of conduit with associated junction boxes leading to each luminaire.
Conductors routed from the service cabinet breaker to each luminaire.
A concrete light standard foundation.
A light standard with a slip base or a fixed base.
A luminaire (light) over or near the roadway edge line.
There are design considerations that need to be addressed when performing even the most
minimal work on an existing illumination system. An existing electrical system is acceptable for
use under the design requirements and National Electric Code (NEC) rules that were in effect at
the time of installation. When modifying an existing electrical service or transformer, the
designer is responsible for bringing the whole system up to current NEC design standards.
Retrofitting an existing fixed base light standard with a slip base feature requires the installation
of quick disconnect fittings and fuses in the circuit, at the luminaire only. The existing conductor
configuration for a fixed base luminaire is not acceptable for use on a breakaway (slip base)
installation. Existing conductors and components that no longer meet current NEC requirements
are to be replaced and the whole circuit is to be designed to current standards. This may mean
replacing the whole circuit back to the nearest overcurrent protection device (circuit breaker).
Address the following when modifying an existing illumination system:
Whether the existing circuit is in compliance with current NEC standards (deficient
electrical component).
Whether existing luminaire system components, such as conductors, conduit, junction
boxes, foundation, and pole comply with current standards.
Whether conductors meet NEC requirements for temperature rating (deficient
electrical component).
Conductor material: aluminum conductors or copper conductors (deficient electrical
component).
Whether the existing bonding and grounding system is adequate: cabinets, poles,
junction boxes, including lids, and other appurtenances are bonded and grounded per
NEC requirements.
The condition and adequacy of the existing conduit running between the luminaire and
the nearest junction box (deficient electrical component).
The condition of the junction box next to the luminaire (deficient electrical
component).
The suitability of the existing foundation to meet current design requirements.
The suitability of the location to meet current design standards for illumination.
The location and bolt pattern of the existing foundation to meet current design
standards.
The design life remaining for the existing light standard (deficient electrical
component).
The condition of the existing light standard (deficient electrical component).
Involve appropriate Headquarters (HQ) and region Traffic Office design personnel early in the
process. Ensure potential system deficiencies are reflected in the estimate of work.
Maintain required illumination during all construction activities, except when shutdown is
permitted to allow for alterations or final removal of the system per the Engineer. Site
preparation, widening, drainage, guardrail installation, or other work can easily impact existing
conduit runs or luminaire locations. Also, changed conditions such as merging, weaving, or
unusual alignment due to traffic control often require additional temporary illumination.
Note: The same lighting requirements apply whether a condition is temporary or permanent.
Illumination is not required for minor operational enhancement projects, unless that is the
specific reasoning for the project.
Exhibits 1040-1a through 1040-21 show examples of illumination for roadway, transit flyer
stops, parking lots, truck weigh stations, tunnels, bridges, work zones, and detour applications.
A minimum of two light standards of standard pole height are required at all design areas, with
the exception of some ramp terminals, entrance/exit points at minor parking lots, and basic
transit stop lighting.
Verify with the HQ Traffic Office that the location is acceptable for a single light standard.
1040.04(8) Roundabouts
Provide the necessary number of light standards to illuminate the design areas of roundabouts
(see Chapter 1320 and Exhibit 1040-9).
Luminaires should only be energized during periods when traction tires are required and
vehicles over 10,000 pounds are required to use chains.
The following conditions have to be met when making the decision to provide additional
illumination:
During the last full five calendar years, the site has experienced nighttime crashes that
are correctable with illumination, AND
The benefit-cost analysis for the proposed illumination exceeds 1, AND
Alternative lower-cost countermeasures have been evaluated and did not address the
particular nighttime crash history.
Nighttime crashes are defined as crashes occurring between half an hour after sunset and half
an hour before sunrise. Correctable nighttime crashes are crashes that (a) meet the nighttime
definition in this chapter, (b) have contributing factors related to a lack of lighting, and (c) where
lighting, if installed, would directly address the contributing factor(s) to the crashes.
Collision reporting forms and the crash data are not adequate means to distinguish between day
and nighttime conditions: the crash location, the reported crash times, and seasonal variations
should be used to determine which crashes qualify as nighttime crashes. Also:
For sites where the number of nighttime crashes equals or exceeds the number of
daytime crashes, the above-mentioned crash and benefit-cost analysis should be
performed.
For sites where these nighttime crashes involve pedestrians, refer to 1040.05(11).
The mitigation of nighttime pedestrian crashes requires different lighting strategies than
vehicular crash locations. Provide light levels to emphasize crosswalks and adjacent sidewalks by
using positive lighting of the pedestrians.
Multilane highways with two-way left-turn lanes, in areas transitioning from rural land use to
urban land use, or areas experiencing commercial growth or commercial redevelopment, are
typically high-speed facilities with numerous road approaches and driveways. These approaches
allow numerous vehicle entry and exit points and provide few crossing opportunities for
pedestrians; consider additional illumination.
1040.05(2) Highways
Proposals to provide full (continuous) illumination require the approval of the Region and State
Traffic Engineers. Regions may choose to develop (regional or corridor-specific) system plans for
providing full (continuous) illumination. The State Traffic Engineer’s approval of a system plan
will eliminate the need for a project-specific approval from the State Traffic Engineer.
Continuous illumination can be provided inside city limits at the city’s request provided the city
takes on the maintenance and operational costs and responsibilities of maintaining and
operating the system.
The decision whether to provide full (continuous) illumination is to be made during the scoping
stage and communicated to the designers as soon as possible.
On the main line of highways without full limited access control, consider full (continuous)
illumination if the segment of highway is in a commercial area and the crash analysis
requirements in 1040.05(1) are met, has raised channelization, has medium or high pedestrian
activity during night time hours, and an engineering study indicates that nighttime driving
conditions will be improved.
1040.05(3) Ramps
Consider additional illumination at ramps where the alignment or grade is complex.
1040.05(4) Crossroads
Consider additional illumination if the crossroad is in a short tunnel, an underpass, or a lid.
1040.05(9) Bridges
Justification for illuminating the roadway/sidewalk portion of bridges is the same as that for
highways on either end of the bridge with or without full limited access control, as applicable.
Justification for illuminating the architectural features of a bridge structure requires the
approval of the State Traffic Engineer. For justification for illuminating pedestrian walkways or
bicycle trails under a bridge, see 1040.05(11).
The access areas used for interior inspection of floating bridges or steel box/concrete box girder
bridges are exempt from lighting level and lighting ratio design requirements.
The types of activity areas (shown below) are related to the number of pedestrian crossings
through the design area. These crossings need not occur within a single crosswalk and can be at
several locations along the roadway in an area with pedestrian generators. Land use and activity
classifications are as follows:
1040.06(1)(a)(1) High Activity
Areas with over 100 pedestrian crossings during nighttime peak hour pedestrian usage.
Examples include downtown retail areas; near outdoor stage theaters, concert halls, stadiums,
and transit terminals; and parking areas adjacent to these facilities.
1040.06(1)(a)(2) Medium Activity
Areas with pedestrian crossings that number between 11 and 100 during nighttime peak hour
pedestrian usage. Examples include downtown office areas; blocks with libraries, movie
theaters, apartments, neighborhood shopping, industrial buildings, and older city areas; and
streets with transit lines.
1040.06(1)(a)(3) Low Activity
Areas with pedestrian crossings that number less than 11 during the nighttime peak hour
pedestrian usage. Examples include suburban single-family areas, low-density residential
developments, and rural or semirural areas.
Design area requirements for various applications are shown in Exhibits 1040-1a through 1040-
21 and are described in the following:
1040.06(2)(a)(1) Single-Lane Off-Ramp
Two main line through lanes and the ramp lane, including gore area, from the gore point
(beginning of wide line) to a point 200 feet (minimum) downstream of the gore point. A 100 foot
longitudinal tolerance either way from the gore point is allowed.
1040.06(2)(a)(2) Two-Lane Off-Ramp
Two main line through lanes and both ramp lanes, including gore area, from a point 200 feet
upstream of the gore point (beginning of wide line) to a point 200 feet downstream of the gore
point. A 100-foot longitudinal tolerance either way from the gore point is allowed.
Two main line through lanes and the ramp lane, from a point where the ramp lane is 10 feet
wide to a point 200 feet downstream. A 100-foot longitudinal tolerance either way is allowed;
this includes auxiliary lane on-connections and lane reductions.
1040.06(2)(a)(4) Two-Lane On-Ramp
Two main line through lanes and the ramp lanes from a point where the ramp width is 22 feet
wide to a point 200 feet upstream and 200 feet downstream. A 100-foot longitudinal tolerance
either way is allowed.
1040.06(2)(a)(5) Intersections Channelized With Pavement Markings
When the leg of an intersection is two lanes wide or less, the design area starts at the stop bar
and encompasses the intersection area. When the leg of an intersection is three or more lanes
wide, the design area starts 25’ before the stop bar and encompasses the intersection area.
1040.06(2)(a)(6) Intersections With Raised Channelization
The design area has two components: the intersection area and the approach areas. When the
leg of an intersection is two lanes wide or less, the intersection design area starts at the stop bar
and encompasses the intersection area. When the leg of an intersection is three or more lanes
wide, the intersection design area starts 25 feet before the stop bar and encompasses the
intersection area on both the main road and the minor road, including marked or unmarked
crosswalks. The approach areas are the areas on the main roadway between the intersection
design area and where the left-turn taper begins.
1040.06(2)(a)(7) Unchannelized Intersection
The area between the stopping points on both the main road and the minor road, including
marked or unmarked crosswalks.
1040.06(2)(a)(8) Railroad Crossing
The roadway width from a point 50 feet on either side of the track (the approach side only for
one-way roadways).
1040.06(2)(a)(9) Transit Loading Area
The entire area designated for parking, including internal access lanes.
1040.06(2)(a)(11) Scale Platform at Weigh Site
The approach width from the beginning of the scale platform to the end of the platform.
1040.06(2)(a)(12) Inspection Area at Weigh Site
The area dedicated to inspection as agreed upon with the Washington State Patrol.
Fixtures are to be ceiling mounted. For steel box girders bridges, the spacing shall not be greater
than the smaller of 4 times the web depth or 25 ft. For concrete box girder bridges, the spacing
shall not be greater than the smaller of 8 times the web depth or 50 ft. Illumination is to consists
of a 100 watt incandescent (or fluorescent equivalent) fixture. The bulb should have a minimum
of 1600 lumens. Each fixture is to be designed with a 20 amp rated ground fault circuit interrupt
(GFCI) receptacle. A light switch is needed at each entrance to any common inspection area. For
inspection areas with two or more entrances, three-way or four-way switches are required.
Light standards are the most common supports used to provide illumination for highway
facilities. The 40-foot light standard with a slip bases and Type 1 mast arm is predominantly
used on state highways. In areas with continuous illumination, 50-foot light standards may be
used. Use Type 1 mast arms on all new systems and when modifying existing systems. Cities and
counties may elect to use different mounting heights to address factors unique to their
environments. On state highways, alternative colored light standards may be considered if
requested by the city or county, provided they agree to pay any additional costs associated with
this change.
The typical location for a light standard is on the right shoulder. When considering designs for
light standards mounted on concrete barrier in the median, consider the total life cycle cost of
the system, including the user costs resulting from lane closures required for relamping and
repair operations, and higher maintenance costs since the work will most likely be done during
night time hours due to decreased traffic volumes. Region Signal Maintenance approval is
required for all median mounted luminaires except chain on/off areas. Light standards located in
the vicinity of overhead power lines require a minimum 10 foot circumferential clearance from
the power line (including the neutral conductor) to any portion of the light standard or
luminaire. Depending on the line voltage, a distance greater than 10 feet may be required (WAC
296-24-960). Consult the HQ Bridge and Structures Office when mounting light standards on
structures such as retaining walls and bridge railings.
It is preferable to locate a light standard as far from the traveled way as possible to reduce the
potential for impacts from errant vehicles. The typical luminaire position is mounted directly
over the edge line plus or minus 4 feet. However, some flexibility is acceptable with the
luminaire position to allow for placement of the light standard provided light levels, uniformity,
and maintenance considerations are addressed, and with the Region Traffic Engineer’s approval.
On Type III signal standards, luminaires may be placed more than 4 feet from the edge line.
Standard mast arm lengths are available in 2-foot increments between 6 and 16 feet. The
preferred design for a single-arm light standard is a 16-foot mast arm installed on a 40-foot
standard. The maximum allowable mast arm length for a single-arm light standard is 16 feet.
The preferred design for a double mast arm light standard has mast arms between 6 feet and 12
feet in length, installed on a 40-foot standard. The maximum allowable mast arm length for a
double luminaire light standard is 12 feet.
Light standards should always use slip bases, unless a fixed base is justified as described in
Chapter 1610.
In curb and sidewalk sections, locate the light standard behind the sidewalk. In
locations where the light standard cannot be placed behind the sidewalk and still have
the luminaire mounted within 4’ of the edge line, the luminaire should be located in
the sidewalk. When installed in the sidewalk, ensure that the minimum sidewalk width
is available to at least one side of the light standard for the pedestrian access route
(see Chapter 1510).
Standard pole heights (20-foot, 30-foot, or 40-foot) are readily available from local distributors
and manufacturers. Light standards can also be supplied with other lengths. However, WSDOT
Maintenance offices cannot stock poles with nonstandard lengths for use as replacements in the
event of a knockdown. Nonstandard lengths in 5-foot increments (25-foot, 35-foot, or 45-foot)
will require a longer delivery time. Other nonstandard lengths (for example, 27-foot, 33-foot, or
37-foot) will not only require a longer delivery time, they will also be more expensive.
In almost all cases, use a standard pole heights of 40 feet for roadway illumination. Structure-
mounted light standards may need to be shorter than the standard 40-foot grade-mounted
pole. It is acceptable to use 20-foot or 30-foot light standards on bridges, retaining walls, or
other structures to compensate for top-of-structure elevation above the roadway surface.
Luminaires with a mounting height over 40 feet should only be used in continuously illuminated
areas that are not in residential areas. Use of these standard pole heights will result in variable
mounting heights for the luminaires. Luminaire mounting height is defined as the actual
distance from the roadway surface directly under the luminaire to the luminaire itself. Use the
actual mounting height at each location when calculating light standard spacing. Luminaires
with a mounting height over 50 feet require lowering devices.
High mast light supports may be considered for complex interchanges where continuous lighting
is justified. High mast lighting may be considered for temporary illumination areas during
construction. Initial construction costs, long-term maintenance, clear zone mitigation, spillover
light onto adjacent properties, and negative visual impacts are important factors when
considering high mast illumination.
Shorter light standards of 30 feet or less may be used for minor parking lots, trails, pedestrian
walkways, and locations with restricted vertical clearance.
1040.06(4)(c) Standard Luminaire
The standard luminaire in use now for roadway lighting is a cobra head style type III LED fixture.
The list of LED fixtures approved for use on WSDOT projects can be found at:
http://www.wsdot.wa.gov/Design/Traffic/ledluminaires.htm
For continuously illuminated area a type V distribution pattern can be used for the interior areas
with type III distribution on the perimeters.
For an example of circuit layout, conductor sizing, conduit sizing, overcurrent protection device
sizing, and other electrical design calculations, see the Power Supply Design material located at:
http://www.wsdot.wa.gov/design/traffic/electrical/training.htm
An example of illumination design grid layouts and calculations is located in the Illumination
Design for Transportation Applications material located in the link above.
The illumination circuitry is to be laid out so that if four or more luminaires are installed, it
should have a minimum of two circuits. The intent is to make sure that if a circuit fails, there will
still be partial lighting from the other circuits.
2. 180 feet when conduit run is along a curve or when the conduit makes a 30 degree or
greater change in direction.
3. 180 feet between NEMA junction boxes in traffic barrier, retaining wall, or structure.
4. A junction box is required within 5 feet minimum (preferred) & 10 feet maximum of the
luminaire base, regardless of the luminaire spacing.
5. 360 feet between NEMA junction boxes when fiber optic cable is run through conduit in
traffic barrier, retaining wall, or structure.
6. Pull Box interconnect to Traffic Signal – spacing is 500 feet maximum. Disclaimer: This would
only apply to a single fiber optic cable.
7. 1,000 feet between cable vaults or pull boxes – main line fiber optic cable.
1040.07 Documentation
Justify and document any additional illumination in the Design Documentation Package (DDP).
The approval from maintenance to install median mounted luminaires can be an email or memo
from the area maintenance superintendent and is kept in the design file.
Any areas in this section that says to “consider” a design element should have the logic of the
consideration and decision documented in the design file for future reference.
1040.08 References
WAC 468-18-040, Design standards for rearranged county roads, frontage roads, access roads,
intersections, ramps and crossings
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
NFPA 502: Standard for Road Tunnels, Bridges, and Other Limited Access Highways, NFPA,
Quincy, MA 2011
Recommended Practice for Tunnel Lighting, IESNA RP-22-05, New York, NY 2011
Roadway Lighting Handbook, Addendum to Chapter Six: Designing the Lighting System Using
Pavement Luminance, Federal Highway Administration, Addendum to Implementation Package
78-15, Washington, DC 1983
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
City Streets as Part of State Highways Guidelines Reached by the Washington State Department
of Transportation and the Association of Washington Cities on Interpretation of Selected Topics
of RCW 47.24 and Figures of WAC 468-18-050 for the Construction, Operations and
Maintenance Responsibilities of WSDOT and Cities for such Streets, 4-30-1997 amended 4-2-
2013
Light Trespass: Research Results and Recommendations, IES TM-11-00, New York, NY 2000
Single-Lane Off-Connection
The design area may be shifted up to 100 ft from the beginning of the wide line; a minimum
of two light standards of standard pole height required for design area.
Single-Lane On-Connection
The design area may be shifted up to 100 ft from the 10-ft-wide ramp point; a minimum of
two light standards of standard pole height required for design area.
Single-Lane On-Ramp
A minimum of two light standards of standard pole height required for each design area.
A minimum of two light standards of standard pole height required for design area;
A minimum of two light standards of standard height is required for the design area.
Legend
Note:
For temporary work zone plan applications, a site-specific traffic control plan is required. Refer to Chapters 1610
and 1620 for traffic barrier and attenuator information, Chapter 1010 for work zone information, and Chapter
1020 for signing information.
Detour Traffic
Note:
For temporary work zone plan applications, a site-specific traffic control plan is required. Refer to Chapters 1610
and 1620 for traffic barrier and attenuator information, Chapter 1010 for work zone information, and Chapter
1020 for signing information. Refer to the MUTCD Typical Application 12 for additional details.
Sidewalks, Walkways & Shared Use Paths 0.8 0.8 0.8 4:1 0.3:1
Weigh Scales 0.8 0.8 0.8 4:1 0.3:1
Transit Stops [4] 2.0 2.0 2.0 NA [7] 0.3:1
Midblock Ped X-ing 2.0 2.0 2.0 4:1 0.3:1
Notes:
[1] The minimum light level is 0.2 footcandle (fc) for any application with a minimum average maintained
horizontal light level of 0.6 fc. The minimum light levels for all other applications are controlled by the
uniformity ratio.
[2] The minimum average maintained light level may be reduced to 0.6 fc and the uniformity ratio may be ignored
when only one light standard is used. Also applies to minor parking lot entrances and exits, and basic transit
stop lighting.
[3] Light levels shown also apply to modified and partial limited access control.
[4] For single light standard installations, provide the light level at the location where the bus stops for riders
(see Exhibit 1040-12).
[5] Minimum Average Maintained Light Level/Minimum Light Level = Maximum Uniformity Ratio.
[6] Maximum Veiling Luminance/Average Luminance = Maximum Veiling Luminance Ratio.
[7] The Maximum Uniformity Ratio is 4:1 when more than one light standard is justified.
[8] Roundabout illumination shall meet intersection lighting requirements for the associated roadway classification.
1050.01 General
Intelligent Transportation Systems (ITS) have the potential to reduce crashes and increase
mobility of transportation facilities. They also enhance productivity through the use of advanced
communications technologies and their integration into vehicles and the transportation
infrastructure. These systems involve a broad range of wireless and wire line communications-
based information, electronics, or information processing technologies. Some of these
technologies include cameras, variable message signs, ramp meters, road weather information
systems, highway advisory radios, traffic management centers, and adaptive signal control
technology (ASCT). ASCT is a traffic signal system that detects traffic conditions and adjusts
signal timing remotely in response. More information on ASCT can be found at:
www.fhwa.dot.gov/everydaycounts/technology/adsc
The purpose and direction of ITS for the Washington State Department of Transportation
(WSDOT) can be found in the Statewide Intelligent Transportation Systems Plan, which is
available upon request from the Headquarters (HQ) Traffic Operations Office. The plan identifies
the current and long-term ITS needs to meet the objectives identified in Moving Washington,
WSDOT’s program to fight traffic congestion.
Due to the dynamic nature of ITS, printed guidance is soon outdated. Detailed design guidance
and current practices are located on the following websites. For additional information and
direction, contact the region Traffic Engineer or the HQ Traffic Operations Office:
www.wsdot.wa.gov/design/traffic/
1050.02 References
23 Code of Federal Regulations (CFR), Part 940, Intelligent Transportation System
Architecture and Standards
http://www.ecfr.gov
USDOT, Model Systems Engineering Documents for Adaptive Signal Control Technology
(ASCT) Systems, FHWA HOP-11-027, August 2012
http://www.ops.fhwa.dot.gov/publications/fhwahop11027/index.htm
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as
adopted and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices
for streets and highways” (MUTCD)
www.wsdot.wa.gov/publications/manuals/mutcd.htm
SAFETEA-LU (Safe Accountable Flexible Efficient Transportation Equity Act: A Legacy for Users)
http://www.fhwa.dot.gov/safetealu/index.htm
Using systems engineering on ITS projects has been shown to increase the likelihood of a
project’s success. A successful project is one that meets the project scope and stakeholder/
project sponsor expectations, is completed on time and within budget, and is efficient and
cost-effective to operate and maintain.
The level of systems engineering used for a project should be on a scale commensurate with
the scope, cost, and risk of the project. Complete the Intelligent Transportation Systems (ITS)
Systems Engineering Analysis Worksheet in Exhibit 1050-2, or a document with the same
information, for all federal-aid projects that include ITS elements. Completing the Worksheet
will meet the minimum requirements in 23 CFR 940.11 for systems engineering, determine the
project’s risk, and determine if a more in-depth systems engineering analysis is required. The
Worksheet and the four systems engineering documents outlined below are to be completed
with coordination between the project engineer and region Traffic Engineer.
As shown in the Worksheet, a more in-depth analysis requires that the following four
documents be completed and used to implement the project. These documents are produced
as the result of the steps in the systems engineering process.
1. Concept of Operations: This document defines the problem, the project’s goals, stakeholder
needs and expectations, constraints, and the way the ITS system is required to operate and
be maintained.
2. System Requirements: This document contains specifications of what the system is required
to do, how well it is required to do it, and under what conditions. These requirements are
based on the goals, stakeholder needs and expectations, constraints, and operation and
maintenance requirements documented in the Concept of Operations.
3. System Verification Plan: This document describes how the agency will verify that the
system being built meets the requirements in the System Requirements document. The
agency will implement the System Verification Plan to ensure all system requirements are
verified before it accepts the system.
4. System Validation Plan: This document describes how the agency will assess the system’s
performance against the goals, stakeholder needs and expectations, constraints, and
operation and maintenance requirements documented in the Concept of Operations. The
goal is for the agency to understand and review the strengths and weaknesses of the system
and identify any new opportunities and needs if appropriate. The agency will implement the
System Validation Plan after it accepts the system. This evaluation sets the stage for the
next time the system/project is changed or expanded.
For specific guidance on developing the four systems engineering plans listed above, see the
plan templates in the USDOT/CalTrans document, Systems Engineering Guidebook for Intelligent
Transportation Systems, Version 3, November 2009. Pertinent page numbers include:
• Concept of Operations Template: Page 254
• System Requirements Template: Page 257
• Verification Documents Plan Template: Page 269
• Validation Documents Plan Template: Page 278
For Adaptive Signal Control Technology Projects (ASCT) using the latest edition of the USDOT
Model Systems Engineering Documents for Adaptive Signal Control Technology (ASCT)
Systems, FHWA-HOP-11-027, August 2012, is required.
As each phase of an ITS project is completed, a report is to be submitted by the Project Engineer
to the region Traffic Engineer describing how the project is meeting the requirements outlined
in the above systems engineering plans. Approvals for ITS projects are dependent upon project
complexity and cost. (See Chapter 300 for ITS project approval requirements.)
Systems engineering costs are to be estimated and incorporated into the construction
engineering (CE) and project engineering (PE) portions of the construction estimate.
The Federal Highway Administration (FHWA) and WSDOT are in agreement that, for project
development and delivery, the most critical portions of the systems engineering process are
the Concept of Operations; System Requirements; System Verification; and System Validation.
As a result, the Intelligent Transportation Systems (ITS) Systems Engineering Analysis Worksheet
in Exhibit 1050-2 is focused on these core areas.
1050.04(2) Scope
This document is intended to be used by the FHWA Washington Division Office, WSDOT, and
local agencies as a guide on the proper types of procurement methods for various types of ITS
projects. This guidance is not all-encompassing, as ITS projects can vary significantly in scope.
However, it should provide adequate information to address a majority of situations. Specific
questions about an individual ITS project should be directed to the Washington Division Office.
Exhibit 1050-3 provides further information about each of these ITS project types.
1050.05 Documentation
Include all ITS systems engineering documentation in the Design Documentation Package (DDP).
All systems engineering documentation requires region Traffic Engineer approval.
Exhibit 1050-2 Intelligent Transportation Systems (ITS) Systems Engineering Analysis Worksheet
This worksheet, or a document with the same information, must be completed for all federal-aid
projects that include Intelligent Transportation Systems (ITS) elements. This worksheet must be
completed prior to submitting a construction authorization request and must be kept in the project
file for the entire document retention period of the project. If Concept of Operations, System
Requirements, Verification Plan, and Validation Plan documents are required for the project, as
determined by this spreadsheet, these documents must be submitted for review prior to submitting
a construction authorization request and must be kept in the project file for the entire document
retention period.
4. Amount of total project cost for ITS elements: Click here to enter text.
5. Will this project implement a new or expand an existing adaptive signal control
technology (ASCT) system?
☐ Yes FHWA and WSDOT consider the project to be high risk. Four additional systems
engineering documents (Concept of Operations, System Requirements,
Verification Plan, and Validation Plan) are required. (See definitions in 1050.03
Systems Engineering.) These documents must be produced using the latest
edition of the USDOT Model Systems Engineering Documents for Adaptive Signal
Control Technology (ASCT) Systems, FHWA-HOP-11-027, August 2012. Please
skip questions 6 and 7.
☐ No
Exhibit 1050-2 Intelligent Transportation Systems (ITS) Systems Engineering Analysis Worksheet (continued)
☐ The project includes new and unproven hardware and/or communications technology
that is considered “cutting edge” or not in common use. This could include custom-
developed or unproven commercial-off-the-shelf (COTS) technology that has not been
used by the agency previously. Please explain why you selected or did not select this
item.
Click here to enter text.
☐ The project will add new software that will be custom developed for this project or will
make major modifications to existing custom-developed software. Please explain why
you selected or did not select this item.
Click here to enter text.
☐ The project will add new interfaces to systems operated or maintained by other
agencies. Please explain why you selected or did not select this item.
Click here to enter text.
☐ The project will develop new system requirements or require revisions to existing
system requirements that are not well understood within the agency and/or well
documented at this time. These system requirements will be included in a request for
proposal, or plans, specifications, and estimate bid document package. Therefore, it will
require significant stakeholder involvement and/or technical expertise to develop these
items during the project delivery process. Please explain why you selected or did not
select this item.
Click here to enter text.
☐ Multiple agencies will be responsible for one or more aspects of the project design,
construction, deployment, and/or the ongoing operations and maintenance of the
system. Please explain why you selected or did not select this item.
Click here to enter text.
Exhibit 1050-2 Intelligent Transportation Systems (ITS) Systems Engineering Analysis Worksheet (continued)
7. If you answered yes to any of the items in question 6, FHWA and WSDOT consider the
project to be high risk. See the following table for additional requirements.
Notes:
[1] A decision not to complete the additional systems engineering documents for high-risk
projects that have less than $1,000,000 of ITS elements requires FHWA concurrence
prior to submitting a construction authorization request.
[2] See definitions in 1050.03, Systems Engineering.
[3] Use the amount from question 4.
8. What is the name of the regional ITS architecture and which portions of the architecture will
be implemented? Is the project consistent with the architecture? Are revisions to the
architecture required? Also, which user services, physical subsystem elements, information
flows, and market/service packages will be completed, and how will these pieces be part of
the architecture?
Click here to enter text.
9. Identify the participating agencies, their roles and responsibilities, and the concept of
operations. For the elements and market/service packages to be implemented, define the
high-level operations of the system. This includes where the system will be used, its
performance parameters, its life cycle, and who will operate and maintain it. Discuss the
established requirements or agreements on information sharing and traffic device control
responsibilities. The regional ITS architecture operational concept is a good starting point for
discussion.
If this is a high-risk project and a more extensive Concept of Operations document is being
prepared for this project (see question 7), this answer can be a simple reference to that
document.
Click here to enter text.
Exhibit 1050-2 Intelligent Transportation Systems (ITS) Systems Engineering Analysis Worksheet (continued)
10. Define the system requirements. Based on the concept of operations, define the “what”
and not the “how” of the system. Define the detailed requirements for eventual detailed
design. The applicable high-level functional requirements from the regional architecture
are a good starting point for discussion. A review of the requirements by the project
stakeholders is recommended.
If this is a high-risk project, and a more extensive System Requirements document is being
prepared for this project (see question 7), this answer can be a simple reference to that
document.
Click here to enter text.
11. Provide an analysis of alternative system configurations and technology options to meet
requirements. This analysis should outline the strengths and weaknesses, technical
feasibility, institutional compatibility, and life cycle costs of each alternative. The project
stakeholders should have had input in choosing the preferred solution.
Click here to enter text.
12. Identify procurement/contracting options. Since there are different procurement methods
for different types of projects, the decision regarding the best procurement option should
consider the level of agency participation, compatibility with existing procurement
methods, the role of the system integrator, and life cycle costs. Some options to consider
include: consultant design/low-bid contractor, systems manager, systems integrator, task
order, and design/build.
If the ITS portions of the project significantly meet the definition of construction, then
construction by low-bid contract would be used. Non-construction ITS portions of the
project, such as services for software development, systems integration, systems
deployment, systems management, or design, will be either engineering or service
contracts. In these cases, a qualifications-based selection (QBS) or best value procurement
may be more appropriate. For guidance on procurement options for ASCT systems, refer to
Pages 15-20 of USDOT’s Model Systems Engineering Documents for Adaptive Signal Control
Technology (ASCT) Systems, FHWA-HOP-11-027, August 2012.
Click here to enter text.
Exhibit 1050-2 Intelligent Transportation Systems (ITS) Systems Engineering Analysis Worksheet (continued)
13. Identify the applicable ITS standards and testing procedures. Include documentation on
which standards will be incorporated into the system design. Also, include justification for
any applicable standards not incorporated. The standards discussion in the regional
architecture is a good starting point for discussion.
Click here to enter text.
14. Outline the procedures and resources necessary for operations and management of the
system. In addition to the concept of operations, document any internal policies or
procedures necessary to recognize and incorporate the new system into the current
operations and decision-making processes. Also, resources necessary to support continued
operations, including staffing and training, must be recognized early and be provided for.
Such resources must also be provided to support necessary maintenance and upkeep to
ensure continued system viability.
Click here to enter text.
ITS
Project Description Examples
Type
Planning/Research
Generally, involves studies that research new concepts • Regional ITS architecture development and
or develop plans or procedures at a broader agency- or maintenance
region-wide level. These are generally not construction • Regional Concept of Operation
and are often done by agency personnel. • Traffic incident management planning
• Standards testing and specification development
• Public outreach and communication
• Scoping/field surveys
Engineering/Project
Generally, involves projects that develop new or • Traffic Management Center (TMC) central
Development/System
upgraded ITS-related software or involve integrating ITS software design, development, installation
Integration
services and equipment. These are typically not • Modifying existing central system software
Software
construction and often fall under a service contract. to communicate with new field equipment
• Incorporation of device control software into
central systems
• Acceptance testing and configuration
management
installation of equipment or work in the field. Design-Bid- • Installation of poles, controller cabinets,
Build (low bid) or Design-Build contracting are foundations, guardrail, gantries
appropriate for this type of work. • Installation of radio towers and civil
infrastructure for wireless systems
• Installation of tolling field equipment (tag
readers, video cameras, etc.)
• Installation of underground infrastructure
(trenching, cable installation, etc.)
Maintenance
Ongoing operations and/or maintenance of ITS services, • Operating costs for traffic monitoring,
Operations/
software, and equipment. Typically is a service contract management, control systems (e.g., rent,
(non-construction). communications, labor, utilities)
• Preventative maintenance
1100.01 General
The Washington State Department of Transportation (WSDOT) is committed to context-
appropriate, multimodal, performance-based designs. WSDOT’s goal is to optimize existing
system capacity and safety through better interconnectivity of all transportation modes.
Community engagement is an essential element.
This chapter provides an overview of the practical design approach that WSDOT uses to make
project decisions. The remaining chapters in Division 11 provide specific design policy details for
each procedural step. WSDOT’s practical design approach is context-appropriate, multi-modal
and performance-based. Practical design utilizes a collaborative approach, design flexibility, and
a high likelihood of variable solutions. As a result, WSDOT’s practical design finds consistency
through the procedural process applied rather than pre-determined outcomes for projects.
Practical Solutions enables more flexible and sustainable transportation investment decisions. It
encourages this by: (1) increasing the focus on addressing identified performance needs
throughout all phases of development, and (2) engaging local partners and stakeholders at the
earliest stages of scope definition to account for their input at the right stage of the
development process. Practical Solutions includes one or a combination of strategies, including,
but not limited to, operational improvements, off-system solutions, transportation demand
management, and incremental strategic capital solutions.
1100.01(1)(a) Practical Solutions Planning
Practical Solutions planning is an approach to making planning decisions that considers a variety
of conceptual strategies to achieve the desired system performance targets for the lowest cost.
Central to practical solutions planning is a process that identifies regional and corridor
performance areas, engages communities to ascertain local contexts and needs, and applies
methods to evaluate and implement short- and long-term solutions.
The outcome of practical solutions planning is a recommended set of multimodal strategies that
are cost-effective and balance the goals and objectives of state and local needs. WSDOT’s
corridor sketch initiative and planning studies inform practical solutions through the following:
Identify performance gaps for a corridor segment, now and in the future.
Identify potential strategies to address the gaps.
Integrate inputs from partners that support corridor segment performance.
Define context and corridor variables.
Identify and rank demand management and operational improvements first, then consider
capital solutions. Note that Executive Order (EO) E 1090 instructs that the solution may or may
not be on a state corridor.
1100.01(1)(b) Practical Design
Practical design focuses on the specific problem or problems identified during the planning and
scoping process. This performance-based approach looks for lower-cost solutions that meet
outcomes that WSDOT, collaborating agencies, communities, and stakeholders have identified.
Practical design is a fundamental component to the Vision, Mission, Values, Goals, and Reforms
identified in Results WSDOT, the department’s Strategic Plan. The primary objectives of the
practical design approach are: (1) focusing on project need(s), and (2) seeking the most
reasonable low-cost solution to meet that need(s).
Practical design allows flexibility and encourages innovation. Practical design considers
incremental solutions to address uncertainties in future scenarios. Practical design can be
applied at all phases of project development; however, it is most effective at the scoping level or
earlier, where key decisions are made as to what design controls and elements are affected by
alternatives and how they can best be configured to meet the project objectives.
With practical design, decision-making focuses on the maximum benefit to the system, rather
than the maximum benefit to the project.
4. Select design controls compatible with the context (see Chapter 1103).
5. Formulate and evaluate potential alternatives that resolve the baseline need for the
selected context and design controls (see Chapter 1104).
6. Select design elements that will be included in the alternatives (see Chapter 1105).
7. Determine design element dimensions consistent with performance needs, context, and
design controls (see Chapter 1106).
The Basis of Design (BOD) documents the outcomes of applying these procedural steps. It also
serves as a management tool throughout the design phase, to keep a project team focused on
the baseline performance need and agreed performance trade-offs in order to prevent scope
creep. During the design phase, a BOD is required on all projects unless design elements are not
changed (see exceptions in 1100.10). During the scoping phase, a BOD is only required as
determined by the Capital Program Development and Management (CPDM) Office. See
1100.10(1) for further information about the BOD.
Use the WSDOT Community Engagement Plan and document the findings of community
engagement efforts (see 1100.10(5)).
The Engineer of Record, or project manager, convenes an advisory team that has the skills,
knowledge, and responsibilities needed for design decision-making; including planning, project
development, environment, active transportation, and context sensitive design. Include WSDOT
members on the advisory team who have positional or delegated authority to make decisions
associated with the areas outlined in this chapter.
The project manager and project team consider recommendations offered by the advisory team.
The project manager decides which recommendations, if any, will be included in the project and
informs the advisory team, providing an opportunity for feedback. Document recommendations
and their treatment to the Basis of Design prior to its approval.
The project manager has discretion in how to work with internal and external stakeholders in
documenting decisions. For more information on organizing, managing, and collaborating with
advisory teams, see the WSDOT Project Management Guide:
www.wsdot.wa.gov/projects/projectmgmt/onlineguide/preconstructioninitiatealign
WSDOT’s practical design approach requires that the need be translated into specific
performance metrics and that targets be selected to be achieved by the design. A contributing
factors analysis (see Chapter 1101) refines focus in order to resolve the specific performance
problems and helps define the potential scope of project alternatives.
Chapter 1101 provides guidance for identifying project performance needs. Understanding
performance and associated performance terms is critical to the application of Chapter 1101.
See the guidance document Performance Based Design before proceeding with application of
Chapter 1101. Direct link to guidance document:
www.wsdot.wa.gov/publications/fulltext/design/ASDE/Practical_Design.pdf
1. Design Year
2. Modal Priority
3. Access Control
4. Design Speed
5. Terrain Classification
Exhibit 1100-1 shows the major activities associated with WSDOT’s practical design approach
and corresponding Design Manual chapters and Basis of Design sections.
When using a BOD, start as early as possible. During planning or scoping, a BOD may be only
partially completed. Information documented on the BOD provides an opportunity for greater
consistency between strategies developed in planning and solutions developed in scoping and
design. Information documented in the BOD comes through use of consent-based
recommendations (see Section 1100.04).
Contact the region Program Management regarding the need to initiate a BOD during the
project-scoping phase. Since the BOD is ultimately a document that supports design decisions,
the approval of a BOD, which ideally takes place at 30% design level or earlier, is a part of, and
included in, the project Design Approval process (see Chapter 300).
See 1100.02 for guidance regarding when a BOD is required for scoping projects. For design-
phase projects, a BOD supports design decisions and is required on all projects where one or
more design elements are changed (see Chapter 1105). Exceptions are listed below.
1100.10(1)(a)(1) All Projects
If the only design elements changed by the project are listed in Exhibit 1105-1, a Basis of Design
(BOD) may not be required. The Assistant State Design Engineer (ASDE) shall concur with the
request to exempt the BOD requirement. Submit a request, by email, for an exemption from the
BOD requirement. The request should explain the unique circumstances that make use of the
BOD unnecessary. Each request is evaluated on a case-by-case basis. If a BOD has been prepared
for the project and no design elements were changed, an ASDE approval of the BOD is not
required.
1100.10(1)(a)(2) Preservation Projects
A Basis of Design form is not required for Preservation projects if the only design elements
changed are listed in Chapter 1120, and the criteria/guidance provided in Chapter 1120 is
followed.
Safety projects (developed under the I-2 funding program) may not require a BOD even though
design elements are changed. The Assistant State Design Engineer (ASDE) shall provide
concurrence to exempt the project from the BOD requirement. Submit exemption requests to
the ASDE by email explaining why an exemption is applicable. The request should explain the
unique circumstances that make use of the BOD unnecessary. Exemption requests are evaluated
on a case-by-case basis.
Circumstances that may contribute to a decision to exempt a safety project from the need to
prepare a BOD include:
A programmatic project endorsed by the WSDOT Highway Safety Panel (e.g.
Intersection Improvement Program ISIP treatments, Rumble Strips, etc.)
A Collision Analysis Report (CAR) was approved by the WSDOT Highway Safety Panel
AND:
The CAR clearly identifies the project need.
The CAR compared and rated alternatives.
Document community engagement for all projects. There is no strict format for this.
1100.11 References
Revised Code of Washington (RCW) 47.05.010 – The statement of purpose for priority
programming of transportation projects
Secretary’s Executive Order 1096 – WSDOT 2015-17: Agency Emphasis and Expectations
1101.01 General
Practical design starts with identification of issues associated with the performance of a
transportation facility. First, one or more project needs associated with these issues are
identified. These project needs represent the gap in performance between the existing and
desired state. Once they are identified, a project need statement is then developed which
expresses only the most fundamental causes of these performance gaps.
Example: A local agency desires to fund a revitalization project for a community bordering a
state highway. The local agency’s baseline need in this case is the local land use’s economic
vitality. If WSDOT also happens to have a prioritized and funded baseline need at the same
location, and the two parties decide to partner in a combined project, that project will have
at least two baseline needs. The two parties will work to develop solutions compatible for
both baseline needs.
To determine, develop, and refine the project’s baseline need(s), examine the conditions
surrounding the original project identification, which was completed in the priority
programming phase.
After developing and refining the baseline need(s), define the baseline performance metrics.
(see 1101.02(1)) and determine the baseline need targets (see 1101.02(2)).
Threshold performance metrics are used in the priority programming process to screen the full
state network under each performance category (for further information on threshold
performance metrics and performance categories, see the guidance document Performance-
Based Decisions: www.wsdot.wa.gov/Design/Support.htm). The baseline performance
metric for preservation category projects is predetermined, and is the same as the threshold
performance metrics determined by Subject Matter Experts (SMEs) and HQ Capital Program
Development and Management (CPDM) Office.
The baseline performance metrics for a mobility or economic vitality category project may be
different from the threshold performance metrics. However, the baseline metric chosen is to be
consistent with the priority programming performance category that identified the location to
be evaluated.
Example: A routinely congested corridor has been screened to identify locations with a
potential mobility performance gap. Screening used a threshold performance metric of
estimated operations at 70% of posted speed during the peak hour. After considering the
context of the location, and the relevance of the threshold performance metric to the site
specific conditions and operations, the advisory team recommends that travel time
reliability is a more appropriate metric for the location.
Safety projects are expected to continue project development as directed by the Multimodal
Safety Executive Committee (MSEC), and described in the Safety Scoping Flowchart and Chapter
321.
Other projects are to coordinate up front with the HQ Safety Technical Group to determine the
scale and scope of crash analyses appropriate for different types and sizes of projects. For
additional information see Chapter 321.
There may be situations where the targets cannot practicably be met by any alternative or
where there are unacceptable performance trade-offs in other performance categories. In these
situations it may be appropriate to accept performance trade-offs, in one of the other
categories during the alternatives evaluation (see Chapter 1104), in order to balance competing
needs and outcomes. In other situations, it may be appropriate to refine the performance target
under consideration.
Develop metrics for contextual needs to compare alternatives. Interpret and translate each
issue into a statement that is measureable, to the extent feasible. Contextual need metrics can
be either quantitative or qualitative.
Practical design relies on CFA to find the root reason(s) a need exists, rather than focusing on a
symptom that may only temporarily or partially resolve the need.
Note: It is recognized that completely solving a problem may not be possible by a single
corrective action due to the number of contributing factors or because of constraints.
Diagnosis of contributing factors yields the best results when data is available for the analysis.
Comprehensive crash data, organized by travel mode, is important when considering safety
performance. In other performance categories, where quantitative data is not available,
qualitative analysis may be used to reveal the underlying contributing factor(s).
Contributing factor analysis is only required for evaluation of baseline performance needs.
However, it may be relevant to perform CFA for contextual performance metrics.
Diagnosing contributing factors using CFA is not necessarily a simple linear process. It’s possible
to find that a contributing factor identified by one discipline is the root cause of another
discipline’s contributing factor. In some cases, mapping the contributing factors in a network or
fishbone diagram can help identify these relationships more clearly (see the guidance document
Contributing Factors Analysis: www.wsdot.wa.gov/Design/Support.htm).
Consider other processes applicable to their projects that may require need statements such as:
value engineering, NEPA/SEPA, and Access Revision Reports. Consider timing of these processes
as well as integration and alignment of the need statements with the processes required for the
project.
For more information and examples of need statements, see the guidance document Writing
Effective Needs Statement: www.wsdot.wa.gov/Design/Support.htm
1101.06 Documentation
Use the Basis of Design, Section 1, to document decision-making and conclusions associated
with project need identification.
1101.07 References
Contributing Factors Analysis, WSDOT Guidance Document:
www.wsdot.wa.gov/Design/Support.htm
For the purposes of transportation planning and design, WSDOT divides context into two
categories: land use and transportation. Each of these contexts is further defined and
categorized in this chapter. Note that context categories, and the information pertinent to
deriving them, may have been documented in a planning study.
The concepts and method described in this chapter are adapted from National Cooperative
Highway Research Program Report 855: “An Expanded Functional Classification System for
Highways and Streets” (see http://www.trb.org/NCHRP/Blurbs/176004.aspx).
On larger projects, more than one land use category may apply within project limits.
Land use context categories are described in detail in 1102.02(1). These categories represent
distinctive land use environments beyond simply “rural” and “urban” to help determine a more
accurate context. These categories influence roadway design, including determining appropriate
operating speeds, mobility and access demands, and modal users. The land use categories are:
Rural
Suburban
Urban
Urban Core
Use the following factors to determine your initial land use context category:
1. Land uses (primarily residential, commercial, industrial, and/or agricultural)
2. Density
3. Setbacks
Quantify these factors through an assessment of the area adjacent to the existing or planned
roadway (see Exhibit 1102-1).
Using the same factors and categories, consult with local agency staff, and review state,
regional, and local planning documents to consider and document potential or anticipated
changes to land use context. Sources of information include the local comprehensive plan,
WSDOT Highway System Plan, WSDOT corridor sketches, and WSDOT planning studies in the
corridor.
Exhibit 1102-1 Factors for Determining Initial Land Use Context
Factor Criteria
Land Use Land uses within ½ mi of roadway
Density Housing units / acre
Density Jobs / acre
Density Intersections per sq. mi.
Density Typical building height
Setback Typical building setback
Setback Parking (on street or off street)
Specific metrics guiding the use of these criteria in determining the initial land use context
category (both current and future) are provided on the WSDOT Design Office website.
Step 3. Select final land use context category (current and future state)
Once an initial land use category is determined, additional (primarily qualitative) considerations
are used to verify that the selected category is appropriate. Because data used in the initial
determination may be incomplete, conflicting, or difficult to interpret, it’s expected that
professional judgment is used to confirm the context result. Even when the overall assessment
is clear, discontinuities or transitions between categories may exist and require further
interpretation.
Confirm or make adjustments to the initial context category based on a qualitative analysis. Use
information gathered from consultations with local agency staff, as well as the project’s
community engagement processes, to validate a final determination about current and future
context. Information about topography, soil type, land value, population density, average
building square footage, visual assessments, aerial photos, zoning, and other local agency land
use data and/or maps may also be used in this step.
Document the process used to make this final context determination. Include the data used,
interdisciplinary input, and issues encountered and resolved in the process. Conclude with a
final land use context determination that confirms, or adjusts, the initial category(s) for the
project, and seek the endorsement of this final determination from the project advisory team
(see Chapter 1100).
1102.02(1)(a) Rural
The rural category ranges from no development (natural environment) to some light
development (structures), with sparse residential and other structures mostly associated with
farms. The land is primarily used for outdoor recreation, agriculture, farms, and/or resource
extraction. Occasionally non-incorporated communities will include a few residential and
commercial structures. Rural characteristics also include:
No or very few pedestrians – except those locations used for outdoor recreation and
modal connections, and where socioeconomic factors suggest that walking is likely to
serve as an essential form of transportation
Bicycle use mostly recreational– except for tourist destinations, modal connection
locations and between communities where bicycle commuters may be expected or
where socioeconomic factors suggest that bicycling is likely to serve as an essential
form of transportation.
Low development density
Isolated residential or commercial activities
Commercial uses include general stores, restaurants, and gas stations, normally at
crossroads
Setbacks for structures are usually large, except in the immediate vicinity of small
settlements
Transit service availability is often absent or highly limited, but varies widely depending
on the jurisdiction. On-demand service is typically found to provide specialized
transportation services
1102.02(1)(b) Suburban
Locations classified as suburban include a diverse range of commercial and residential uses that
have a low or often, medium density. Suburban areas are usually (but not always) connected
and closely integrated with an urban area. The buildings tend to be multi-story with off-street
parking. Sidewalks are usually present and bicycle lanes may exist. These areas include mixed
use town centers, commercial corridors, and residential areas. Big box commercial and light
industrial uses are also common. The range of uses encompasses health services, light industrial
(and sometimes heavy industrial), quick-stop shops, gas stations, restaurants, and schools and
libraries. Suburban characteristics also include:
Heavy reliance on passenger vehicles
Transit may be present
Residential areas may consist of single and/or multi-family structures
Building and structure setbacks from the roadway vary from short to long
May have well planned and arranged multi-uses that encourage walking and biking
Planned multi-use clusters may integrate residential and commercial areas along with
schools and parks
Some highways that fit this category may be designated by WSDOT as “Main Street
Highways” (see Appendix B: Identification of State Highways as Main Streets,
http://www.wsdot.wa.gov/research/reports/fullreports/733.1.pdf.)
1102.02(1)(c) Urban
Urban locations are high density, consisting principally of multi-story and low to medium rise
structures for residential and commercial use. Areas usually exist for light and sometimes heavy
industrial use. Many structures accommodate mixed uses: commercial, residential, and parking.
Urban areas usually include prominent destinations with specialized structures for
entertainment, athletic and social events as well as conference centers and may serve as a Main
Street (see 1102.03(6)). Urban characteristics also include:
Various government and public use structures exist that are accessed regularly
Building setbacks are both short and long
Streets normally have on-street parking
Wide sidewalks and plazas accommodate more intense pedestrian traffic
Bicycle lanes and transit corridors are frequently present
Off-street parking includes multi-level structures that may be integrated with
commercial or residential uses
Some highways that fit this category may be designated by WSDOT as “Main Street
Highways” (see Appendix B: Identification of State Highways as Main Streets
Due to the differences in developmental scale among urban areas as well as growth demand
urban-urban core, context boundaries change over time with the urban core area expanding in
high growth situations and possibly contracting in low or no growth situations.
1102.02(1)(d) Urban Core
Urban core locations include the highest level of density with its mixed residential and
commercial uses accommodated in high-rise structures. There is commonly on-street parking,
although it is usually time restricted. Most parking is in multi-level structures attached or
integrated with other structures. The area is accessible to automobiles, commercial delivery
vehicles, biking, walking, and public transit. Urban Core characteristics also include:
Sidewalks and pedestrian plazas are present
Bicycle facilities and transit corridors are common
Typical land uses are mixed commercial, residential, with some government or similar
institutions present
Commercial uses predominate, including financial and legal
Structures (predominantly high rises) may have multiple uses
With the highest land value of any category, setbacks from the street are small
Some highways that fit this category may be designated by WSDOT as “Main Street
Highways” (see Appendix B: Identification of State Highways as Main Streets
Seek endorsement from the project advisory team (see Chapter 1100) for determinations of
these transportation context types and considerations, including input from local agency (local
jurisdictions and transit agencies) and stakeholders. Document determination of each of these
transportation contexts for both current and future states in Section 2 of the Basis of Design,
and carry these results forward into determination of modal compatibility and modal priority
(Chapter 1103).
Additional information supporting work described in this section is provided on the WSDOT
Design Office website.
Contact Rail, Freight, and Ports Division for help identifying freight classifications, industry needs
and truck operations.
Source: TRPC Report 165: Transit Capacity and Quality of Service Manual.
Local routes serve many stops along a route and emphasize access to transit over
speed.
Limited stop routes (also known as frequent routes, including bus rapid transit)
balance transit access with speed. These routes run frequently and serve higher
volume stops (e.g. major activity centers and transfer points).
Express routes emphasize speed over transit access, and are often used for longer
distance trips.
When evaluating transit needs and the potential for transit to improve highway performance in
the project area, document relevant information or data about current transit capacity and
quality of service (as defined in the Transit Capacity and Quality of Service Manual) and current
and potential future use and travel markets. Include consideration for people walking and biking
to/from transit connections. Contact the Public Transportation Division for help or for more
information about identifying and coordinating with transit agencies and local jurisdictions that
serve the project area ( http://wwwi.wsdot.wa.gov/PubTran/).
The Main Streets designation for highways is a point of reference and consideration when
documenting transportation context, and should be noted on the Basis of Design. Main Street
highways serve the aesthetic, social, economic, and environmental values in a larger community
setting in addition to transportation. They are set up as specific state route and milepost
designations.
See the Complete Streets and Main Street Highways Program document listed in Supporting
Information at the end of this chapter for more information. For the list of designated highways
see State Highways as Main Streets: A Study of Community Design and Visioning, Appendix B:
Identification of State Highways as Main Streets,
http://www.wsdot.wa.gov/research/reports/fullreports/733.1.pdf.
1102.04 Documentation
Document the following in Section 2 of the Basis of Design:
Land use category
Roadway type
Bicycle route type
Pedestrian route type
Freight route classification
Transit use considerations
Main Streets designation
Describe the process that was followed to reach these designations. If the work involved review
and verification of previous work, document that process as well. If characteristics vary within
project limits include the milepost ranges to which each of the designations apply.
The Context and Modal Accommodation Report is a template available for use in this
documentation process (see https://www.wsdot.wa.gov/design/support.htm).
1102.05 References
Revised Code of Washington (RCW) 35.58.2795, Public transportation systems – Six-year transit
plans
RCW 35.77.010(2) and RCW 36.81.121(2), Perpetual advanced six-year plans for coordinated
transportation program expenditures – Nonmotorized transportation – Railroad right-of-way
Secretary’s Executive Order 1096 – WSDOT 2015-17: Agency Emphasis and Expectations
State Highways as Main Streets: A Study of Community Design and Visioning, WSDOT, 2009
Appendix B: Identification of State Highways as Main Streets
http://www.wsdot.wa.gov/research/reports/fullreports/733.1.pdf
Other References
Complete Streets Planning and Design Guidelines, North Carolina Department of Transportation,
July 2012. http://www.pedbikeinfo.org/pdf/PlanDesign_SamplePlans_CS_NCDOT2012.pdf
Evaluating Transportation Land Use Impacts, Victoria Transport Policy Institute, 2015
http://www.vtpi.org/landuse.pdf
The Innovative DOT: A Handbook of Policy and Practice, Smart Growth America, Washington
D.C., 2015
http://www.smartgrowthamerica.org/the-innovative-dot
Land Use and Regional Planning: Achieving Integration Between Transport and Land Use,
European Commission, 2006 http://www.transport-
research.info/Upload/Documents/200608/20060831_102457_87241_Land_use.pdf
NCHRP Report 855 – An Expanded Functional Classification System for Highways and Streets
http://www.trb.org/NCHRP/Blurbs/176004.aspx
Urban Street Design Guide, National Association of City Transportation Officials, New York, NY,
2013 http://nacto.org/
WSDOT policy on design year is intentionally flexible. The design year can be any interim year
selected between the project year of opening year and the horizon year. Many lower-cost
projects result in immediate performance improvements when construction is completed.
Safety projects are an example of this where the basis of design may show design year as the
year of opening.
Some projects may require horizon year analysis of an alternative regardless of the selected
design year. A project may be required to evaluate alternatives based on the horizon year
(20 years from the scheduled beginning of construction) if the project:
Involves a federal nexus (federal funds involved, involves federal lands, or requires
federal approvals or permits)
Is a Project of Divisional Interest (See Chapter 300)
Is a new/reconstruction project as defined in Chapter 300
level for both the current year (prior to opening) and the design year. These are referred to as
existing and future conditions in the guidance that follows. Note that in many cases, the
planning documentation, data, or information in the project vicinity may not be available for the
project’s design year. In those cases, identify the forecast or horizon year used by the local
agency or planning organization in its work and planning products, and document the use of
that year as the future year for purposes of determining the modal accommodation level.
1. An initial modal accommodation determination, for both the current and design years, are
made using Exhibit 1103-2. The initial determination uses the roadway type and land use
contexts that were determined earlier and documented in Section 2 of the Basis of Design
(See Chapter 1102).
2. A final determination for both the current and design years is made using additional
information and evidence to validate or modify the initial determination.
Make the final modal accommodation determination for each mode in consultation with the
project advisory team and/or subject matter expert(s), as they may recommend modifications
to the initial determinations (see 1100.04 for more information about working with the project
advisory team). Exhibit 1103-3 provides examples of land-use and transportation characteristics
that a project advisory team or subject matter expert(s) may consider in adjusting
accommodation up or down for any particular travel mode. These characteristics can represent
either the current suitability of a facility to accommodate a mode, or its future strategic role
with respect to accommodating that mode. Note that the Context and Modal Accommodation
Report provides a template for making and documenting decisions about modal
accommodation.
Additional guidance on the use of the following criteria in determining final modal
accommodation level is provided on the Design Support site:
http://www.wsdot.wa.gov/Design/Support.htm
Consider the vehicle modal accommodation level when making design decisions that address or
affect needs associated with vehicle travel. Start with the initial modal accommodation level for
motor vehicles per Exhibit 1103-2, and adjust it to establish the final level based on documented
project specific conditions related to the quality of travel experience, and identified
performance targets, that can be influenced by the project design, such as vehicle Level of
Service, travel time, access classification, and other factors determined by subject matter
experts or the project advisory team.
1103.03(2)(b) Bicycle modal accommodation level
Consider the bicycle modal accommodation level when making design decisions that address or
affect needs associated with bicycle travel. Start with the initial modal accommodation level for
bicycles per Exhibit 1103-2, and adjust it to establish the final level based on documented
project specific conditions related to the quality of travel experience, and identified
performance targets, that can be influenced by the project design, such as bicycle route type,
efficiency of travel, range, bicyclist safety, route spacing, bicycle volumes, and other factors
determined by subject matter experts or the project advisory team.
Consider the pedestrian modal accommodation level when making design decisions that
address or affect needs associated with pedestrian travel. Start with the initial modal
accommodation level for pedestrians per Exhibit 1103-2, and adjust it to establish the final level
based on documented project specific conditions related to the quality of travel experience, and
identified performance targets, that can be influenced by the project design, such as pedestrian
route type, efficiency of travel, range, pedestrian safety, block length, and other factors
determined by subject matter experts or the project advisory team.
Modal priority addresses all modes expected to use the facility. Determine modal priority using
the accommodation level results, as well as other relevant information about freight, transit,
and any other modes considered and documented in the Context and Modal Accommodation
Report and Basis of Design. Engage the project advisory team as provided in Section 1100.04.
If the modal priority is inconsistent with assumptions made about the project during a planning
or scoping phase, work with program management staff to consider the need for any changes to
project scoping documentation, including scope, schedule, and budget.
Document the modal priority on the Basis of Design for both the current and future conditions.
An intersection design vehicle is a specific selection made at each intersection leg. Select a
design vehicle that allows the largest vehicles commonly encountered to adequately complete a
required turning maneuver. The objective is not necessarily to size the specific intersection curb
radius (unless there is a baseline need associated with the larger vehicles), but rather to account
for a reasonable path to accommodate the large vehicle turning maneuver without conflicts (see
Chapter 1310). Use turn simulation software (such as AutoTURN®) to analyze turning
movements.
Conversely, if the crossroad was identified as being within a Freight Economic Corridor, with
frequent turning movements from larger vehicles, it would be appropriate to size the
intersection to prevent the second lane incursion.
Consider origins and destinations of large vehicles to understand their needs at specific
intersection locations. Also, consider alternatives that may help lower turning speeds and
minimize pedestrian exposure. Work with stakeholders, businesses, and service providers to
understand their needs (like transit, school bus and emergency vehicle movements) and define
the frequency of use at specific intersections. Municipalities may have established truck routes
or restrictions that govern local freight patterns.
During development of the state highway system, access management functioned to preserve
the safety and efficiency of regional highways. However, the level of access management can
also significantly affect accessibility to land uses, modal mobility needs and the economic vitality
of a place.
Unless access control has already been acquired by the purchase of access rights, it is necessary
to select the appropriate type of limited access control or managed access control during
planning and design. Appropriate access control should be considered so as not to hinder
bicycle and pedestrian accessibility, mobility, and safety.
A choice to change the current or planned access control is a major decision and is to be
consistent with the context, desired performance targets, and modal priorities for a location.
Example: The area around a managed access Class 2 route has incurred significant
development, increasing the number of local trips on a segment of the route. Over time,
additional intersections and access connection permits have been granted. In this situation,
it may be appropriate to consider selecting managed access Class 4 or 5 because of the
changes in functions and activities along the segment over time.
Conversely, a route may have a need to improve motor vehicle travel time performance,
and managed access Class 1 may be appropriate.
Exhibit 1103-4 shows possible (planning level) target speeds for the various roadway types and
land use contexts discussed in Chapter 1102. The target speeds shown in the exhibit are
suggestions only, and the target speed for the specific location may vary from those shown in
the exhibit.
Exhibit 1103-4 Target Speed Based on Land Use Context and Roadway Type
Land-Use Context
Rural Suburban Urban Urban Core
Intermediate / Low /
Principal Arterial High Low
High Intermediate
Low/ Low /
Minor Arterial High Low
Intermediate Intermediate
Low/ Low/
Collector Low Low
Intermediate Intermediate
Low/
Local Low Low Low
Intermediate
Engage the public, local agency staff and officials, and transit agencies prior to selecting the
target speed. Once the target speed has been selected, it becomes the design speed for the
project. The goal of the target speed approach is that the speed ultimately posted on the
completed project is the same as the design, and ultimately, the operating speed. In order to
achieve this outcome, consider:
The impact of existing or proposed contextual characteristics
Modal priorities
Access control selection
Performance need(s)
Contributing factors analyses that have been developed for the project
Lowering target speed: When selecting a target speed in excess of the existing posted speed, or
where excessive operating speeds were identified from contributing factors analysis of the
baseline performance need, consider the use of roadway treatments that will help achieve the
selected target speed (see 1103.05(2)) during alternatives formulation.
Speed management treatments are used to achieve lower vehicle speeds. When speed
management treatments are proposed to accomplish a desired target speed operation
concurrence of the Region Traffic Engineer is required. When a design speed is proposed for a
project that is lower than the existing posted speed, the approval of the State Traffic Engineer is
also required. See 1103.05(2) below for more on speed management. Careful consideration of
other modal needs should be evaluated before raising target speeds.
Raising target speed: When selecting a target speed in excess of the existing posted speed,
measures such as greater restriction of access control and segregation of modes may be
necessary to reduce conflicts in activities and modal uses. Wider cross sectional elements like
lanes and shoulders are used with higher speed facilities.
Setting the posted speed: Use caution when basing a target speed on one or more contextual
characteristics that are proposed to take place after project opening, as the goal of ending up
with a posted speed equal to the design speed at opening may be jeopardized.
The Region Traffic Engineer is responsible for setting the posted speed on the highway once the
project is completed. Target speed is only one of the considerations used when establishing
posted speed. Engage and include the Region Traffic Engineer and Traffic Office staff in key
decision-making that will affect the target, design, and operating speed selection. . Incorporate
consideration of traffic calming measures as needed.
Include a speed transition segment where there is a need to obtain a target speed lower than
the existing operating speed. A speed transition segment is not needed where existing operating
speeds are within 5 mph of the target speed for a given location. The transition segment may
not always directly precede the speed zone segment as shown in Exhibit 1103-5.
Example: A residential segment could benefit from introducing a speed transition segment
farther upstream to increase the likelihood that approaching vehicles operate at the desired
speed, for both segments.
The speed transition segment may incorporate a variety of treatments that alert motorists to a
changing roadway environment. These treatments are intended to narrow driver focus and/or
affect driver decision-making on that segment. Consider the transition segment location and
length when providing multiple treatments in a short distance.
Traffic calming treatments can serve a variety of purposes, from deterring higher volumes of
motorized traffic to providing speed management. This section presents traffic calming
treatment options to increase the reliability of reducing vehicular speed. Speed reduction traffic
calming treatments applied independently or in combination may be beneficial depending on
the type and use of the treatments. Many speed management treatments have demonstrated
varied effectiveness for single applications. Multiple treatments in series and parallel that build
upon the context characteristics are more effective. Contact the Headquarters Design and
Traffic offices for any project implementing a speed transition segment, for assistance on
selection and monitoring of treatments.
Speed management techniques vary and have different results depending on the speed and
types of users at a given location. The following subsections present different options for speed-
reducing traffic calming treatments.
1103.05(2)(b)(1) Geometric Treatments
Geometric treatments can include overall changes of the horizontal or vertical geometry to
introduce features that will support maintaining the targeted speed. Exhibit 1103-6 shows
geometric traffic calming treatments and potential considerations when selecting these types of
treatments.
1103.05(2)(b)(2) Roadside and Pavement Treatments
There are a number of treatments that create an environment that influences human factors
and perception. Many successful roadside treatments use landscaping in an attempt to achieve
the desired behavioral effect. It is important to coordinate with project partners to evaluate
landscaping features and provide for traveled way operations and sight lines. The introduction
of roadside features like trees, parking, and/or bicycle lanes to alert travelers to a change in
conditions may be appropriate. Applying features like vegetated medians or trees is appropriate
at some locations and contexts. In landscaping discussions, include Traffic Engineers,
Maintenance, Urban Forestry, Landscape Architects, and Human Factors and Safety Experts. If
the landscaping proposed is in a managed access segment with local jurisdiction responsibility
for the roadside, coordinate to understand the jurisdictions’ capabilities to sustain the
landscaping and that it meets their clear zone goals.
Pavement-related treatments can also produce undesirable impacts on other users. For
pavement-related treatments, include Materials Engineers, Maintenance, Traffic, and ADA
Compliance Experts to review what sustainable and effective treatments can be employed.
Exhibit 1103-7 lists roadside and pavement-related traffic calming treatments and
considerations to evaluate.
Treatment Considerations
Narrowing the lane width can be achieved by restriping lane lines. A decision to
taper in or out may depend on other treatments planned, such as introducing a
Taper for Narrow Lanes median or chicanes. Base taper rates on the target speed entering the context or
speed transition segment, as appropriate. It is recommended that this be the first
treatment employed.
This treatment may be achieved with curbed features, like planter strips or striping
combined with additional fixed delineators. These treatment types are more
appropriate when reducing speeds from an initial intermediate speed or less. When
Chicanes/Lane Shifts
introducing this treatment with initial high speeds, the treatment should utilize
paint striping, in addition to using other treatments preceding the chicane/lane
shift, rather than constructing hardscape features.
Applies on intermediate to low target speed situations unless completed with
striping or other pavement markings. This treatment uses striping, roadside
features, or curb extensions to temporarily narrow the vehicle lane. It is likely more
Pinch Points appropriate for maintaining a desired target speed within a segment than as part of
a speed transition segment. Pinch points are not appropriate for high-speed
segments. Use of pinch-point treatments on intermediate speed segments requires
concurrence from the Region Traffic Engineer.
On state highways, this treatment will likely have limited application, but should
not be excluded from consideration. Impacts to freight, transit, and emergency
Speed
service vehicles need to be evaluated prior to selecting these vertical types of
Cushion/Humps/Tables
treatments. These treatments may only be used when maintaining a 25 mph target
speed within a segment.
Raised intersections, similar to other vertical treatments, will have limited
application on state highways. This treatment typically has higher costs to construct
due to the pavement needs. This treatment may be a good option when a
roundabout cannot be accommodated at a narrow intersection. It can also be
Raised Intersections
considered where there is a need to improve visibility of the intersection and modal
conflicts, especially at problematic stop control intersections planned to remain in
place. This treatment may only be used when maintaining a 25 mph target speed
within a segment.
Roundabouts can be a unique feature, providing reduced fatal and serious injury
crash potential, traffic calming, and gateway functions (See Chapter 1320 and the
Roadside Policy Manual for details on roundabout design). Roundabouts are
effective from a collision reduction and operational perspective, and they provide
Roundabouts reduced driver workload, lower speeds, and limited conflict points. They can assist
with access management or when turning movements are limited or restricted on a
segment. To determine if a roundabout is appropriate at a specific location, follow
the Intersection Control Evaluation process described in Chapter 1300.
Treatment Considerations
Landscaping can be used in conjunction with other treatments to reinforce the
surrounding context and the driver’s perception of the context. It can also provide
Landscaping
width for modal separation. Annual maintenance impacts need to be considered,
weighed, and documented prior to selecting types of vegetation to be included.
Introduce a raised vegetated median following other treatments that prepare the
Raised Vegetated
driver for this feature. Appropriate for low to intermediate target speed locations and
Medians
transition segments.
These in-lane rumble strips are intended to alert drivers to a condition change. They
Transverse Rumble are likely placed in conjunction with and prior to traffic signing revisions or in advance
Strips of other speed-reducing traffic calming treatments. Appropriate for high,
intermediate, or low target speed locations and transition segments.
This treatment is intended to influence a driver’s perception. The treatment consists
of 8-inch transverse paint strips within the vehicular lane extending from lane and
edge markings (or curb). The striping intervals sequentially decrease, providing the
Optical Speed
perception of increasing speed, an indication to drivers to slow their operating speed.
Markings
Optical Speed Markings are ideal for speed transition segments, and are
recommended to be applied in conjunction with lane narrowing for high or
intermediate target speed locations.
This treatment consists of actively alerting motorists about their operating speed.
Dynamic Warning There are many different systems that accomplish this, including portable radar
Systems trailers and post-mounted systems. These can be either permanent or temporary
installations. Appropriate for all speeds.
The intent of a gateway feature is to alert travelers to a context change. A gateway
feature is typically found on the edge of cities or towns, but can be used to highlight
specific segments within cities or towns. The gateway can be anything from a
banner/structure spanning the facility, to artistic work, landscaping, and/or a
roundabout at the first intersection approaching a defined environment context. The
Gateways gateway feature should be developed by the community. It may be of interest to
design a gateway feature fitting the cultural and historic character of the location.
Consideration for potential fixed object collisions is an important aspect of gateway
design. Gateway features that span or are placed within state right of way will need
specific approvals, as identified in Chapter 950. Appropriate for low to intermediate
target speed locations and transition segments.
To provide a general reference between terrain and geometric design, three classifications of
terrain have been established:
1. Level: Level to moderately rolling, this terrain offers few or no obstacles to the construction
of a highway having continuously unrestricted horizontal and vertical alignment.
2. Rolling: Hills and foothills, with slopes that rise and fall gently; however, occasional steep
slopes might offer some restriction to horizontal and vertical alignment.
3. Mountainous: Rugged foothills; high, steep drainage divides; and mountain ranges.
Designate terrain as it pertains to the general character along the alignment of a corridor.
Roadways in valleys or passes in mountainous areas might have the characteristics of roads
traversing level or rolling terrain and are usually classified as level or rolling, rather than
mountainous. See the Highway Log for terrain classification.
1103.07 Documentation
Document selections for design controls in Section 3 of the Basis of Design.
1103.08 References
Secretary’s Executive Order 1096 – WSDOT 2015-17: Agency Emphasis and Expectations
A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO, Washington, D.C.,
Current Edition www.transportation.org/Pages/Default.aspx
Urban Street Design Guide, National Association of City Transportation Officials, New York, NY,
2013 www.nacto.org
NCHRP Report 613 – Guidelines for Selection of Speed Reduction Treatments at High Speed
Intersections, Transportation Research Board, Washington D.C., 2008
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_613.pdf
NCHRP Report 737 – Design Guidance for High-Speed to Low Speed Transition Zones for Rural
Highways, Transportation Research Board, Washington D.C., 2012
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_737.pdf
NCHRP Report 600 – Human Factors Guidelines for Road Systems, 2nd Edition, Transportation
Research Board, Washington D.C., 2012
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_600Second.pdf
NCHRP Report 855 – An Expanded Functional Classification System for Highways and Streets
http://www.trb.org/NCHRP/Blurbs/176004.aspx
NCHRP Synthesis 443 – Practical Highway Design Solutions, Transportation Research Board,
Washington D.C., 2012 http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_syn_443.pdf
1104.01 General
Washington State Department of Transportation practical design policy requires formulating
and evaluating alternatives while considering acceptable performance trade-offs to meet the
need(s) of a project at the lowest level of investment. This chapter discusses how:
Information determined from planning phases and Chapters 1101, 1102, and 1103 is
utilized in alternative solution formation
To evaluate the alternative solutions developed
This chapter presents methods for developing alternatives. For projects requiring an
Environmental Assessment (EA) or an Environmental Impact Statement (EIS), a final proposed
alternative may only be determined through the National Environmental Policy Act (NEPA)
process and/or the State Environmental Policy Act (SEPA) process (see Chapter 400 of the
Environmental Manual for more information). If an EA or EIS has not been initiated under
NEPA/SEPA, follow the procedures in this chapter. To help advance the project, consider and
use appropriate NEPA/SEPA terminology. Perform public and agency outreach and document all
information regarding alternatives development for use later in the NEPA/SEPA process,
according to 23 CFR 168(d). Terminology used in this chapter assumes that NEPA/SEPA have not
been initiated. In the event that the NEPA/SEPA process has been initiated and an EA or EIS will
be required, coordinate with the region Environmental Office staff to make sure that this
alternative formulation and evaluation is performed in accordance with NEPA/SEPA guidance.
Planning phase corridor sketches or studies may identify WSDOT’s strategy for the corridor (see
the guidance document section titled Alternative Strategies and Solutions for more information
regarding different strategies that may be considered). If this has occurred, develop at least one
alternative based on that identified strategy and bring forward into the alternative evaluation
process (see 1104.03).
In some cases, planning studies may have developed specific alternatives. Carry planning phase
alternatives into the alternative evaluation process, unless planning phase alternatives are
obsolete. In some cases, alternatives may present opportunities for phased implementation.
Use the Alternative Comparison Table (ACT) to assist in evaluating alternatives and identified
baseline and contextual performance. The intent of comparing alternatives is to:
Obtain an alternative solution for the least cost while understanding associated
performance trade-offs.
Compare alternatives against their ability to accomplish the baseline need.
Evaluate alternatives against their relative effects on contextual needs.
Provide the opportunity to incorporate mitigation or countermeasures.
Document alternative formulation and evaluation outcomes that are consistent with
the environmental process and expectations.
Note that if there are a large number of contextual needs under consideration, it may be
beneficial to prioritize or use a weighted evaluation of the contextual needs in order to expedite
the alternative evaluation.
As discussed in 1104.02, at least one alternative based on the outcome of Contributing Factors
Analysis should be compared against other alternatives.
The Alternative Comparison Table template and examples can be found at:
www.wsdot.wa.gov/Design/Support.htm
1104.04 Documentation
The Alternative Comparison Table (ACT) is used to assist in evaluating alternatives. Summarize
the alternatives evaluated with the ACT in Section 4 of the Basis of Design (BOD). Alternative
formulation and evaluation will also be documented through the NEPA process. Environmental
staff will help account for consistency with the environmental process, expectations and
requirements throughout any alternative formulation and evaluation that occurs within project
development.
1104.05 References
Chapter 43.21C Revised Code of Washington (RCW), State Environmental Policy Act (SEPA)
Secretary’s Executive Order 1096 – WSDOT 2015-17: Agency Emphasis and Expectations
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
NCHRP Report 642 – Guidelines for Quantifying the Benefits of Context Sensitive Solutions,
Transportation Research Board, Washington D.C., 2014
http://www.trb.org/Publications/Blurbs/162282.aspx
NCHRP Synthesis 443 – Practical Highway Design Solutions, Transportation Research Board,
Washington D.C., 2013
http://www.trb.org/Main/Blurbs/168619.aspx
1105.01 General
Design elements are specific components associated with roadway design, such as lane widths,
shoulder widths, alignments, clear zone, etc. Design controls (see Chapter 1103) are carefully
chosen and used to determine the dimensions of design elements. The relative effect that a
given design element will have on performance will depend on the selected design controls and
context identification. For more information, see: Guidance Documents - Information on
WSDOT's Practical Design Procedures, Research Summary of Different Design Elements on
Performance, which is the last section.
A design element that is not changed is not documented in the Basis of Design.
The next step after selecting design elements is to choose the appropriate dimension for each
element. (See Chapter 1106 for information on selecting design element dimensions.)
Design Elements
Roadside
Program or Signing &
Clear Safety Illumination Signal
Sub-Program ADA Delineation ITS [8]
Zone [1] Hardware [7] Hardware
[4]
[3]
Apply the
I-1 Mobility Apply the Apply the content in
Apply the Apply the Apply the
I-3 Economic content in content in Chapter 1020
content in content in content in
Initiative - Trunk Chapter Chapters for signing [5]
Chapter Chapter Chapter
System 1510 1600, 1610 and Chapter
1600 1040 1050
I-6 Sound Transit (1510.05) and 1620 1030 for
delineation
Apply the
content in Apply the
All Preservation
Chapter [2] content in [2] [6] [2] [2] [5]
(P-1, P-2, P-3)
1120 Chapter 1120
(1120.03(2))
Apply the
I-2 Safety
content in
I-4 Environmental
Chapter [2] [2] [2] [6] [2] [2] [5]
Retrofit
1510
I-3 All Other
(1510.05)
Notes:
[1] See Chapter 1600
[2] Only include when changed as described in 1105.02.
[3] Includes all roadside safety design elements in Chapters 1600, 1610, and 1620.
[4] See Chapter 1020 for signing and Chapter 1030 for delineation
[5] Consult the Assistant State Design Engineer (ASDE), HQ Traffic Office, and Capital Program
Development and Management Office (CPDM) to determine policy requirements.
[6] Consult the ASDE for policy requirements if the roadway channelization is changed.
[7] See Chapter 1040
[8] See Chapter 1050
Example: A project team proposes to provide a left-turn lane along a portion of their project
in order to address a baseline need related to safety for turning traffic, by reducing the
width of each highway shoulder. By reducing the shoulder width, the traveled way will be
closer to the roadside than in the existing condition. The project team determines whether
the project would adversely affect safety performance due to roadside conditions such as
steep slopes or objects in the clear zone along with considering impacts to bike and
pedestrian use.
1105.04 Documentation
Document design elements that are changed in Section 5 of the Basis of Design (BOD) form
unless the exemptions listed in 1100.10(1) apply.
As a design alternative matures over time, it is likely that design elements may be added or
dropped through the iterative process inherent with design. It is important to update the Basis
of Design documentation with these changes at the various documentation and approval
milestones.
1105.05 References
Guidance Documents - Information on WSDOT's Practical Design Procedures
https://www.wsdot.wa.gov/publications/fulltext/design/ASDE/Practical_Design.pdf
When choosing any dimension, read the guidance for the specific facility type (for example,
for ramps see Chapter 1360) and also read the guidance for the specific element (for example
for side slopes see Chapter 1239).
When a range of dimensions is given, consider modal needs, required function, and desired
performance (1106.03) and, where possible, use quantitative tools to help choose a
dimension within the range.
1106.01 General
Practical design resolves the project need with the least investment. Flexibility in the choice of
design element dimensions helps accomplish this.
For guidance related to geometric cross-section elements, first see Chapter 1230. For guidance
related to all other design elements, see the appropriate chapter.
For some roadways, the optimum solution is very dependent on the location (context) of the
roadway. In these cases, you will likely see a range of widths to choose from. For example, the
geometric cross section guidance chapters for highways (Chapter 1231) and freeways (Chapter
1232) show cross-sections that list ranges to choose from for lane and shoulder widths.
Example: Exhibit
1360-14b calls out
one specific
dimension for the
lane width of this
section of a parallel
off connection.
Example: Exhibit
1231-3 calls out a
range of dimensions
for the lane width.
When a single dimension is given: If the decision is to use the dimension shown, no further
evaluation is needed; just document the dimension choice on the Design Parameter Sheets.
If a particular roadway warrants use of a dimension that is different than the value given, the
mode/function/performance approach described in 1106.03 can be used to determine the
appropriate dimension. Results will need to be documented in a Design Analysis.
When a range of widths is given: Understand any width considerations specific to the design
element (for example, lane width considerations are described in Chapter 1231). Use the
mode/function/performance approach described in 1106.03 to choose the appropriate value
within the range. If the dimension chosen is within the range given in the Design Manual,
document the reasoning in the Design Parameter Sheets. If the value chosen is outside of the
given range, document the decision in a Design Analysis.
Some dimension choices can be complex, and involve trade-off evaluations, including
comparisons of alternatives, benefit/cost analysis, etc. In these instances, it may be appropriate
to record the dimension choice on the Design Parameter Sheets and reference any related
documents that support the dimension choice.
Modes, function and performance overlap and are interrelated. These considerations are part of
a tradeoffs discussion. Cost is always a consideration in a tradeoffs discussion. Engineering
judgment and stakeholder involvement will be required.
For example, it is important to understand the vehicle mix that will be using the lanes and to
understand the modes that will be using the shoulder. For lanes, a significant number of trucks
and oversized vehicles may affect the lane width choice, especially if the alignment is not
tangent. Read Chapter 1231 when choosing lane widths.
For shoulders, it is important to understand bicyclist and pedestrian use. The width
requirements that come with accommodating various modes are discussed in Chapter 1239.
For example, the shoulder width requirements that come with providing various functions bring
a wide range of associated widths (see Exhibit 1239-2, Shoulder Function & Modal
Accommodation Width Considerations).
Performance: When choosing a dimension from a range of possible choices, consider safety
performance and mobility performance. Meeting safety or mobility performance targets may
drive the dimension choice.
When evaluating performance, the use of quantitative engineering methods and tools is
encouraged whenever possible. See 1106.05 for more information on quantitative tools and
methodology for evaluating safety and mobility performance.
For some projects, modal accommodation needs may drive lane and shoulder width decisions.
In other cases, the need to provide a specific function may drive width decisions. And, in some
cases, meeting established performance targets may drive width decisions. Regardless of
whether modal accommodation, function, or performance drives the dimension choice, the
effect of the decision on mobility and safety performance has to be considered.
In addition to being the primary method to choose a dimension when a range of dimensions is
given, the mode/function/performance approach can also be used in support of a Design
Analysis.
Design up means considering the smallest dimension first. Increasing dimensions are then
considered until the smallest dimension is identified that accommodates modal needs, provides
the desired functions, and provides appropriate safety and mobility performance. Using the
mode/function/performance approach described in 1106.03 is an important part of design up.
The application of the Highway Safety Manual (HSM) and its companion tools provides an
understanding of how a particular design can perform with respect to safety. This enables
analysis of safety-specific performance metrics that may be more critical to address. The HSM
covers multiple transportation road types and can be a valuable tool to analyze various
geometric alternatives in any program type.
For guidance regarding whether or not to include a baseline safety need see Chapter 1101. For
more information on sustainable highway safety tools and analysis, see Chapter 321.
Important Note: If the dimension for an existing design element does not change, no
documentation is required on the Design Parameter sheets. A Design Parameter Sheet entry left
blank means that the element was not selected to be included in the project. (See Chapter 1105
for design element selection guidance.) A Design Parameter Sheet template can be found here:
http://www.wsdot.wa.gov/Design/Support.htm.
1106.08 References
Highway Capacity Manual (HCM), latest edition, Transportation Research Board, National
Research Council
http://www.targetzero.com/plan.htm
1120.01 General
This chapter provides information specific to preservation project types.
This chapter identifies those elements and features to be evaluated and potentially
addressed during the course of a preservation project. The elements listed here may be in
addition to the project need identified in the Project Summary or Basis of Design (see
1120.03(8)). Preservation projects may also provide opportunities for project partnering and
retrofit options involving additional elements (for example see Section 1231.06).
For more information on these programs see the Planning & Programming – Scoping
website:
http://wwwi.wsdot.wa.gov/Planning/CPDMO/PlanProgScoping.htm
See Chapter 300 for documentation requirements. If the project changes a geometric design
element, replaces an existing bridge or installs a new bridge additional documentation may
be required; contact your ASDE to discuss appropriate documentation.
Evaluate drainage grates and gutter pans, and adjust or replace as needed to address the
potential for bicycle crashes (see Drainage Grates and Manhole Covers in Chapter 1520).
Replace rumble strips if they are removed through project actions, or if their average depth is
less than 3/8”, unless there is a documented justification for their removal (see Chapter
1600).
If the vertical clearance of a structure will be changed by the project, use Sections
720.03(5)(c) and 1020.03(2) for vertical clearance requirements.
Include vertical clearance and any other changed geometrics in the Basis of Design, the
Design Parameters sheets, and the Design Documentation Package.
See DM Section 720.03(5)(c) for details about bridge clearances for existing structures and
Section 1020.03(2) for vertical clearance of overhead sign assemblies.
Contact the Commercial Vehicle Services Office when changes to vertical clearance are
planned.
1120.03(6) Delineation
Install and replace delineation in accordance with Chapter 1030 (this includes pavement
markings, guideposts, and barrier delineation).
Where practicable, install a pavement edge treatment at locations where asphalt concrete
pavement is applied to the outside edge of the existing pavement. Examples where
pavement edge treatment may not be practicable include, locations with roadside barrier
and/or curb. After installing the pavement edge treatment, trim shoulders with material that
is graded back over the edge treatment and flush with the paved roadway surface.
For more information about pavement edge treatment, contact the HQ Design Office, and
visit the FHWA website at:
https://www.fhwa.dot.gov/innovation/everydaycounts/edc-1/safetyedge.cfm
1120.04 Documentation
For Roadway Preservation (P1) projects, use the Basis of Design and Design Parameter Sheets
to document decisions when the project changes design elements that are not listed in
1120.03(1) through 1120.03(8).
1210.01 General
This chapter provides guidance on the design of horizontal alignment, frontage roads, number
of lanes, arrangement of lanes, and pavement transitions. For additional information, see the
following chapters:
Chapter Subject
1230 Lane and shoulder widths
1240 Lane widths on turning roadways for full design level
1250 Superelevation rate and transitions
1260 Sight distance
1310 Guidelines for islands
1360 Ramp lane and shoulder guidelines
a. Determine whether sufficient contextual elements exist within the roadway cross
section to indicate the desired low-speed environment (street trees, lack of building
setbacks, streetside amenities, etc.).
b. Determine whether horizontal geometric traffic calming treatments will be needed to
maintain the selected design speed (see Chapter 1103).
c. Avoid placing pedestrian midblock crossings within horizontal curves.
a. Make the highway alignment as direct as practicable and still blend with the topography
while considering developed and undeveloped properties, community boundaries, and
environmental concerns.
d. Avoid any abrupt change in alignment. Design reverse curves with an intervening tangent
long enough for complete superelevation transition for both curves. (See Chapter 1250 for
more information on superelevation transitions.)
e. Avoid the use of curves in the same direction connected by short tangents (broken back
curves); substitute a single larger curve.
f. Avoid compound curves on open highway alignment if a simple curve can be obtained.
When compound curves are used, make the shorter radius at least two-thirds the longer
radius. Make the total arc length of a compound curve not less than 500 feet.
h. The desirable locations for bridges, interchanges, intersections, and temporary connections
are on tangent sections in clear view of drivers.
i. On two-lane two-way highways, strive for as much passing sight distance as possible (see
Chapter 1260).
Spiral curves, although no longer used on new highway construction or major realignment, still
exist on Washington’s highways. Spirals were used to transition between tangents and circular
curves with the horizontal curvature rate increasing from tangent to the central curve and
decreasing from curve to tangent. Spirals do not pose an operational concern and may remain
in place. (See A Policy on Geometric Design of Highways and Streets for information on spirals.)
To avoid the appearance of a kink in the road, the desirable length of curve for deflection angles
larger than given in Exhibit 1210-1 is at least 500 feet.
Exhibit 1210-1 Maximum Angle Without Curve
A city or county may be asked to accept a proposed distribution facility as a city street or county
road. Plan and design these facilities according to the applicable design values as city streets or
county roads (see Chapter 1230).
Frontage roads are generally not permanent state facilities. They are usually turned back to the
local jurisdiction. Plan and design frontage roads as city streets or county roads (see Chapter
1230). Initiate coordination with the local agency that will be the recipient of the facility early
in the planning process, and continue through design and construction. (See Chapter 530 for
additional guidance on frontage roads and turnbacks.)
Outer separations function as buffers between the through traffic on the highway and the
local traffic on the frontage road. The width is governed by requirements for grading, signing,
barriers, aesthetics, headlight glare, and ramps. Where possible, make the separation wide
enough to allow for development on both sides of the frontage road. Wider separations also
move the intersection with the frontage road and a crossroad farther from the intersection
with the through roadway, and they can reduce the amount of limited access control rights
to be acquired (see Chapter 530).
Where two-way frontage roads are provided, make the outer separation wide enough to
minimize the effects of approaching traffic on the right, particularly the headlight glare. (See
Chapter 1600 for information on headlight glare considerations.) With one-way same-direction
frontage roads, the outer separation need not be as wide as with two-way frontage roads.
Wide separations lend themselves to landscape treatment and can enhance the appearance of
both the highway and the adjoining property.
Where ramp connections are provided between the through roadway and the frontage road,
the minimum outer separation width depends on design of the ramp termini.
Change the basic number of lanes for general changes in traffic volume over a substantial length
of the route. The desirable location for a reduction in the basic number of lanes is on a tangent
section between interchanges or intersections. However, there can be advantages in using
dedicated turn lanes at intersections as a means to reduce the number of lanes.
To accommodate high traffic volumes for short distances, such as between adjacent
interchanges, use auxiliary lanes. When auxiliary lanes are provided on consecutive sections
between interchanges, consider increasing the basic number of lanes through the entire length.
Chapter Subject
1270 Truck climbing and passing lanes
1310 Left- and right-turn lanes and storage for turning
1360 Weaving and auxiliary lanes associated with interchanges
L VT
Where:
L = Length of transition (ft)
V = Design speed (mph)
T = Tangential offset width (ft)
• Use the following formula to determine the minimum length of the lane transition for
speeds less than 45 mph:
L = TV2
60
Where:
L = Length of transition (ft)
V = Design speed (mph)
T = Tangential offset width (ft)
1210.06 Procedures
When the project realigns the roadway, develop horizontal alignment plans for inclusion in the
Plans, Specifications & Estimates. Show the following as needed to maintain clarity and provide
necessary information:
• Horizontal alignment details (tangent bearing, curve radius, and superelevation rate)
• Stationing
• Number of lanes
• Intersections, road approaches, railroad crossings, and interchanges (see Chapters
1310, 1340, 1350, and 1360)
• Existing roadways and features affecting or affected by the project
Justify any realignment of the roadway. Include the reasons for the realignment, profile
considerations, and alternatives considered, and the reasons the selected alignment was
chosen.
When the project changes the number of lanes, include a capacity analysis supporting the
number selected (see Chapter 320) with the justification for the number of lanes.
Include with the justification for a frontage road any traffic analyses performed; the social,
environmental, and economic considerations; the options considered; and the reasons for the
final decision.
1210.07 Documentation
Refer to Chapter 300 for design documentation requirements.
1210.08 References
1210.08(1) Federal/State Laws and Codes
Washington Administrative Code (WAC) 468-18-040, Design standards for rearranged county
roads, frontage roads, access roads, intersections, ramps and crossings
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
1220.01 General
Vertical alignment (roadway profile) consists of a series of gradients connected by vertical
curves. It is mainly controlled by the following:
• Topography
• Class of highway
• Horizontal alignment
• Safety
• Sight distance
• Construction costs
• Drainage
• Adjacent land use
• Vehicular characteristics
• Aesthetics
This chapter provides guidance for the design of vertical alignment. For additional information,
see the following chapters:
Chapter Subject
1103 Design controls, terrain
1210 Horizontal alignment
1260 Sight distance
1310 Grades at intersections
1360 Maximum grade for ramps
• Avoid “roller coaster” or “hidden dip” profiles by use of gradual grades made possible
by heavier cuts and fills or by introducing some horizontal curvature in conjunction
with the vertical curvature.
• Avoid grades that affect truck speeds and, therefore, traffic operations.
• Avoid broken back grade lines with short tangents between two vertical curves.
• Use long vertical curves to flatten grades near the top of long, steep grades.
• Where at-grade intersections occur on roadways with moderate to steep grades, it
is desirable to flatten or reduce the grade through the intersection.
• Establish the subgrade at least 1 foot above the high water table (real or potential),
or as recommended by the Region Materials Engineer. Consider the low side of
superelevated roadways.
• When a vertical curve takes place partly or wholly in a horizontal curve, coordinate the
two as discussed in 1220.03.
Sag vertical curves may have a length less than required for stopping sight distance when all
three of the following are provided:
• An analysis to justify the length reduction.
• Continuous illumination.
• Design for the comfort of the vehicle occupants. For comfort, use:
AV 2
L
46 .5
Where:
L = Curve length (ft)
A = Change in grade (%)
V = Design speed (mph)
The sag vertical curve lengths designed for comfort are about 50% of those for sight distance.
Minimum ditch gradients of 0.3% on paved materials and 0.5% on earth can be obtained
independently of roadway grade. Medians, long sag vertical curves, and relatively flat terrain are
examples of areas where independent ditch design may be justified. A closed drainage system
may be needed as part of an independent ditch design.
When long, steep downgrades are unavoidable, consider an emergency escape ramp, and for
grades longer than indicated, consider an auxiliary climbing lane (see Chapter 1270).
Exhibit 1220-1 Grade Length
9
7
Percent Upgrade
0
0 1,000 2,000 3,000
Desirable Maximum Length of Grade
For grades longer than indicated, consider an auxiliary climbing lane (see Chapter 1270).
Table 3 Maximum Grades for Interstate and Full Limited Access Control Facilities
Guides for the coordination of the vertical and horizontal alignment are as follows:
• Balance curvature and grades. Using steep grades to achieve long tangents and flat
curves or excessive curvature to achieve flat grades are both poor designs.
• Vertical curvature superimposed on horizontal curvature generally results in a more
pleasing facility. Successive changes in profile not in combination with horizontal
curvature may result in a series of dips not visible to the driver.
• Do not begin or end a horizontal curve at or near the top of a crest vertical curve.
A driver may not recognize the beginning or ending of the horizontal curve, especially
at night. An alignment where the horizontal curve leads the vertical curve and is longer
than the vertical curve in both directions is desirable.
• To maintain drainage, design vertical and horizontal curves so that the flat profile of
a vertical curve is not located near the flat cross slope of the superelevation transition.
• Do not introduce a sharp horizontal curve at or near the low point of a pronounced sag
vertical curve. The road ahead is foreshortened and any horizontal curve that is not flat
assumes an undesirably distorted appearance. Further, vehicular speeds, particularly
of trucks, often are high at the bottom of grades and erratic operation may result,
especially at night.
• On two-lane roads, the need for passing sections (at frequent intervals and for an
appreciable percentage of the length of the roadway) often supersedes the general
desirability for the combination of horizontal and vertical alignment. Work toward
long tangent sections to secure sufficient passing sight distance.
• On divided highways, consider variation in the width of medians and the use of
independent alignments to derive the design and operational advantages of one-
way roadways.
• Make the horizontal curvature and profile as flat as practicable at intersections where
sight distance along both roads is important and vehicles may have to slow or stop.
• In residential areas, design the alignment to minimize nuisance factors to the
neighborhood. Generally, a depressed facility makes a highway less visible and less
noisy to adjacent residents. Minor horizontal adjustments can sometimes be made
to increase the buffer zone between the highway and clusters of homes.
• Design the alignment to enhance attractive scenic views of the natural and constructed
environment, such as rivers, rock formations, parks, and outstanding buildings.
When superelevation transitions fall within the limits of a vertical curve, plot profiles of the
edges of pavement and check for smooth transitions.
1220.06 Procedures
When the project modifies the vertical alignment, develop vertical alignment plans for inclusion
in the Plans, Specifications, and Estimates (PS&E) to a scale suitable for showing vertical
alignment for all proposed roadways, including ground line, grades, vertical curves, and
superelevation. (See the Plans Preparation Manual for guidance.)
When justifying any modification to the vertical alignment, include the reasons for the change,
alternatives addressed (if any) and why the selected alternative was chosen. When the profile
is a result of new horizontal alignment, develop vertical and horizontal alignments together, and
include the profile with the horizontal alignment justification.
1220.07 Documentation
Refer to Chapter 300 for design documentation requirements.
1220.08 References
1220.08(1) Federal/State Laws and Codes
Washington Administrative Code (WAC) 468-18-040, Design standards for rearranged county
roads, frontage roads, access roads, intersections, ramps and crossings
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
Horizontal curve
Horizontal curve
Horizontal alignment
Horizontal tangent
Desirable profile
Profile
Horizontal curve
Horizontal alignment
Perspective
Line of sight
Profile
Disjointed Effect
A disjointed effect occurs when the beginning of a horizontal curve is hidden by an intervening crest while the
continuation of the curve is visible in the distance beyond the intervening crest.
30 ft
A A
30 ft
Rails
30 ft
Level 3 in max
3 in max
When choosing any geometric cross section dimension, including lane or shoulder width, read the
guidance that is specific to the facility type. Also, read the general guidance related to common
elements such as lanes, shoulders, side slopes, etc.
1230.01 General
The geometric cross section is composed of multiple lateral design elements such as lanes,
shoulders, medians, bike facilities, and sidewalks. The designer’s task is to select, size, and
document these elements appropriately. There is flexibility in the selection of design element
dimensioning.
All WSDOT routes, regardless of context, are referred to in the Design Manual as “highways.”
Under this definition, freeways are a subset of highways while Interstate freeways are one
specific type of freeway.
Refer to the Design Manual Glossary for many of the terms used in this chapter. See Chapter
300 for design documentation requirements.
Exhibit 1230-1 shows some common facility types along with the corresponding chapter that
geometric cross section guidance can be found in.
Geometric cross section guidance for other special purpose facilities is in various
chapters. Examples include special use lanes, bridges, transit facilities, bus pull
Other
outs, median U-turns and crossovers, enforcement areas, truck weighing facilities,
pedestrian bridges and tunnels, sidewalks & bicycle facilities
Notes:
General guidance for curb design is in Chapter 1239. Guidance for curb is also found for numerous
types of facilities (Chapter 1310 and others.)
[1] Passing and climbing lanes, see Chapter 1270; Auxiliary lanes between interchanges see Chapter
1360.
Exhibit 1230-1 is not a comprehensive list of guidance associated with either a facility or a
design element. It is intended to be a quick reference to the chapter containing the primary
guidance related to the specific element and facility type.
For guidance related to intersections see Chapter 1310. For guidance related to sidewalks see
Chapter 1510. For guidance related to bicycle facilities see Chapter 1520. For guidance related
to bridges see Chapter 720.
1230.05 References
1230.05(1) Design Guidance
Highway Runoff Manual, M 31-16, WSDOT
Standard Plans for Road, Bridge, and Municipal Construction, M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction, M 41-10, WSDOT
Urban Street Design Guide, National Association of City Transportation Officials, New York, NY,
2013
www.nacto.org
A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO, current edition
Available from the WSDOT Library.
1231.01 General
Geometric cross sections for state highways are governed by the need to balance performance
metrics, the context, and selected design controls. The objective is to optimize the use of
available public space while avoiding an unreasonable investment in right of way acquisition.
The term “highways” refers to all WSDOT roadways, including freeways. However, note that
freeways have their own geometric cross section guidance. This chapter is not intended for
freeway design. See Chapter 1232 for freeways.
1231.02 Design Up
Unless otherwise specified, use the “design up” method described in Chapter 1106 to choose a
design element width when a range of widths is given in this chapter.
Through Lanes
Through lanes are the most common lane type. All highways have at least one lane in each
direction to provide unimpeded traffic flow from Point A to Point B.
Turn Lanes
Dedicated turn lanes are separated from the through lanes and provide storage for turning
vehicles waiting for a signal or gap in opposing traffic. There are a number of different types of
turn lanes which are discussed in detail in Chapter 1310. Turn lanes are critical to meet mobility
and accessibility performance for motorized and bicycle modes. Traffic analysis determines the
type, storage length, and number of turn lanes that are needed to achieve the balance of
multimodal performance needs.
Turn lanes present potential conflicts, particularly with bicyclists and pedestrians. See Chapters
1510 and 1520 for additional discussion on ways to mitigate for these conflicts.
Bicycle Lanes
There are several different types of bicycle lanes and many different ways to arrange bike lanes
within the geometric cross section (see Chapter 1520). Shoulders designed to function for bikes
are not considered bike lanes.
Transit-Only Lanes
Transit-only lanes are ideal for improving transit mobility performance and segregating heavily
used or complex intermodal connections. There are many different ways to configure these
within a geometric cross section. Some configurations are limited due to passenger loading
needs for both the transit vehicle type and the stop locations. Develop widths for transit-only
lanes with the partnering transit agency. See Chapter 1430 for additional information on Transit
Facility considerations.
Auxiliary lanes
Auxiliary lanes enhance mobility performance for motor vehicles. See Chapter 1270 for design
guidance and a detailed discussion on the types of auxiliary lanes.
There are many different types of managed and shared lanes. Some examples include:
High occupancy vehicle (HOV) lanes (see Chapter 1410)
High occupancy toll lanes (discuss with Tolling Division and see Chapter 1410)
Hard shoulder running
Peak hour use
Bicycle shared lane (see Chapter 1520)
Business access and transit (BAT) lane (see Chapter 1410, Arterial Street HOV)
* The width shown is exclusive of the gutter if the gutter is a color that contrasts with the
roadway.
Exhibit 1231-2 lists some considerations that may be helpful in choosing the most appropriate
lane width from the range given in Exhibit 1231-1. This is not a comprehensive list. The
considerations listed are meant to help understand the modal needs and function associated
with different lane widths. Work with your Region Traffic Office when choosing lane widths.
traveling in opposing directions. Especially beneficial when high volumes or high truck
percentages expected
On multilane facilities with width constraints, utilizing narrower inside lanes may permit wider
outside lanes for bicycles, freight, and transit
Reduced lane widths allow more lanes to be provided in areas with constraints and allow
shorter pedestrian crossing times because of reduced crossing distances
12 ft lanes provide increased benefit where there are higher truck volumes, especially for
intermediate and high speed facilities
Safety and mobility performance difference between 11 ft and 12 ft lanes can be negligible.
Work with Region Traffic Office to evaluate performance differences for the subject roadway
Lane widths of 10 ft may be appropriate in constrained areas with low truck and bus volume
Once a decision is made regarding which modes to accommodate and which modes will have
priority, a geometric cross section can be developed. The cross sections in this chapter are
organized by modal priority for the following primary modes:
Bicycles
Pedestrians
Transit
The cross-section examples shown in Exhibits 1231-3 through 1231-7 depict various
combinations of elements that may be included in a cross section. The examples are intended to
stimulate designer creativity and awareness of modal accommodations, and are not intended to
be standard cross sections to be reproduced for a given modal priority. It is expected that
innovative project alternatives will result in diverse configurations that best balance baseline
and contextual needs (see Chapter 1101).
Since the cross-sections shown are only examples, and are really combinations of various
elements, it is important to read the guidance associated with the specific elements (see
1231.03) in order to understand the considerations that may affect a choice of width, and to
understand documentation requirements.
The cross section examples provide a range of dimensions for different design elements. See
Chapter 1106 for guidance regarding choosing a width when a range of widths is given.
The objective is to achieve the Pedestrian Circulation Path (PCP) necessary to support mobility,
socioeconomic, and accessibility needs and provide access to intermodal connections. The
configuration and dimension of streetside elements varies significantly depending on the
performance needs being addressed. See Chapter 1510 for additional pedestrian design
requirements and considerations.
Exhibit 1231-6 Example A shows a central configuration for transit service that provides a
separated bus-only lane. Other transit vehicle types may require different widths and may also
require other center cross section configurations for passenger loading. Exhibit 1231-6 Example
B shows a side configuration where transit vehicles occupy the outside lane. This example can
also be configured as business access and transit [BAT] lanes. Note the importance of streetside
elements to assist with intermodal connections. Exhibit 1231-6 Example C is an example of a
type of special use lane for high-speed routes that are routinely congested. In this example, the
shoulder allows the restricted use for buses.
There are different potential configurations for complete streets, such as:
A rural two-lane highway with wide shoulders; the shoulders can be used by motor
vehicles in emergencies and by pedestrians and bicyclists.
An urban highway or street with vehicle lanes, bike lanes, bus lanes, and sidewalks.
Retrofitting a highway or street to clearly mark and sign a shared-use lane.
An urban highway that undergoes a “road diet” (see 1231.06) or installation of
additional pedestrian crossings.
The low speed examples in Exhibit 1231-7 illustrate roadway cross sections that:
Separate access lanes from through traffic lanes using curbed islands.
Reduce conflicts between pedestrian, bike, transit and auto modes by separating them.
Provide transit stops integrated with raised islands.
May result in improved operations for all modes.
Typical Road Diet Basic Design from FHWA Road Diet Informational Guide
The success of road diet implementation varies due to a number of factors such as signal spacing
and timing, access connection density, modal priority, and average daily traffic (ADT). ADT is a
reasonable indicator for implementation. FHWA recommends limiting road diet applications to
roadways of 20,000 ADT or less, although road diets have been successful at locations with
25,000 ADT in various parts of the country (see Chapter 540 for additional restrictions on the
use of TWLTLs). Motor vehicle mobility performance is most likely deemed the primary measure
of success for the road diet configurations with higher ADT values described. However, locations
with a different modal priority and higher ADT may still be candidates for road diets. The Region
Traffic Engineer must approve road diet applications on state highways.
Retrofit options refer to the application of lower-cost treatments that utilize paint and other
delineation devices rather than hardscape features. See Chapter 1238 for more information on
retrofit options such as relocating the curb, parklets and plazas.
1231.07 References
Standard Plans for Road, Bridge, and Municipal Construction, M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction, M 41-10, WSDOT
Urban Bikeway Design Guide, National Association of City Transportation Officials, New York,
NY, 2012 revised 2013
www.nacto.org
Urban Street Design Guide, National Association of City Transportation Officials, New York, NY,
2013
www.nacto.org
Guide for Geometric Design of Transit Facilities on Highways and Streets, AASHTO, Washington,
D.C., 2011
www.transportation.org/Pages/Default.aspx
A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO, current edition
www.transportation.org/Pages/Default.aspx
NCHRP Synthesis 443 – Practical Highway Design Solutions, Transportation Research Board,
Washington D.C., 2013
http://www.trb.org/Main/Blurbs/168619.aspx
NCHRP Report 785 – Performance-Based Analysis of Geometric Design of Highways and Streets,
Transportation Research Board, Washington D.C., 2014
www.trb.org/Main/Blurbs/171431.aspx
NCHRP Report 783 – Evaluation of the 13 Controlling Criteria for Geometric Design,
Transportation Research Board, Washington D.C., 2014
www.trb.org/Main/Blurbs/171358.aspx
If your roadway fits the definition of a freeway, use the guidance in this chapter for geometric cross-
section elements. If your roadway is not a freeway, see Chapter 1230.
1232.01 General
Freeways are defined as divided highways with a minimum of two lanes in each direction for the
exclusive use of vehicular traffic and with full control of access. Interstate is one type of freeway.
Freeways are high-speed facilities that prioritize through travel for vehicles, freight and transit.
Lanes must be wide enough for all vehicles that use them. Shoulders provide very important
functions for freeways.
Freeways can be thought of as a unique context. This is reflected by the fact that design controls
(Chapter 1103) are fairly consistent for all freeways:
Modal priority: motor vehicles
Access control: full control
Design speed: high
Freeways do not present the challenges of accommodating the competing needs of other
modes such as pedestrians. Also, adjacent land use is generally not an issue due to freeways
being limited access facilities. For these reasons, choosing cross-sectional element dimensions
for freeways does not have as many complexities as for some other roadway types.
Note that there are locations where bicyclists are allowed use of the freeway shoulder.
The geometric cross-section for interstate freeways is shown in Exhibit 1232-1. The geometric
cross-section for non-interstate freeways is shown in Exhibit 1232-2.
Refer to the Design Manual Glossary for terms used in this chapter. Refer to Chapter 300 for
design documentation requirements.
Exhibit 1232-1 Geometric Cross Section - Interstate (4 lanes shown, can vary)
Notes:
See Chapter 1410 for HOV lane guidance.
Use of the shoulder on a freeway for transit only use or as an HOV lane requires a Design Analysis.
[1] 4 ft minimum on facilities up to 4 lanes, and 10 ft minimum on 6-lane facilities.
In mountainous terrain, inside shoulder may be reduced to 4 ft on facilities up to 6 lanes.
[2] In mountainous terrain, outside shoulders may be reduced to 8 ft on facilities up to 6 lanes.
[3] Overall median width and design will vary. See Chapter 1239 and 1610.
Exhibit 1232-2 Geometric Cross Section – Non-Interstate (4 lanes shown, can vary)
Notes:
See Chapter 1410 for HOV lane guidance.
Use of the shoulder on a freeway for transit only use or as an HOV lane requires a Design Analysis.
[1] 4 ft minimum on facilities up to 4 lanes, and 8 ft minimum on 6-lane facilities.
In mountainous terrain, inside shoulder may be reduced to 4 ft on facilities up to 6 lanes
[2] Overall median width and design will vary. See Chapter 1239 and 1610.
The high-speed nature of freeways reinforces the importance of providing these functions. For
instance, the high speed differential between a stopped vehicle and adjacent traffic leads to a
greater need to get stopped traffic out of the travelled way. Also, the limited access nature of
freeways generally means that there are fewer access points to provide potential refuge.
When a range is given for shoulder width, use the mode/function/performance approach
described in Chapter 1106 and “design up” to choose a width within the range. See Chapter
1239 for additional considerations for choosing a shoulder width.
If this is the case for your project, and you choose widths different than shown in the Design
Manual, formulate alternative solutions that consider the tradeoffs associated with various lane
and shoulder widths and document the decision in a Design Analysis. Where appropriate,
include documentation of your consultation with the project advisory team (see Chapter 1100)
in the Design Analysis. When compiling the Design Analysis, consider recent design resources
that explore options, performance, functions, and mitigation associated with various lane and
shoulder dimensions. One source is FHWA HOP-16-060 “Use of Narrow Lanes and Narrow
Shoulders on Freeways.” Another source is NCHRP 15-47, “Developing an Improved Highway
Geometric Design Process”.
1232.06 References
Standard Plans for Road, Bridge, and Municipal Construction, M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction, M 41-10, WSDOT
A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO, current edition
www.transportation.org/Pages/Default.aspx
1238.01 General
The geometric cross section of a roadway is composed of different elements. The cross sections
shown in Chapter 1231 include parking and various zones within the streetside (see Exhibit
1238-1). This chapter provides information on parking and streetside elements. The need to
provide a particular element is dependent on the context and modal needs for a given section of
roadway.
1238.02 Parking
On-street parking is typically provided in urban and rural town center areas, but is not
necessarily required. On-street parking can help visually narrow the street in places to assist in
conveying the surrounding context for the segment. Refer to municipal codes regarding parking
requirements, and coordinate with the municipality involved. Also, if on-street parking will be
either delineated or metered, the ADA has requirements on the number and configuration of
parking stalls for people with disabilities. Consult with a regional ADA subject matter expert.
On-street parking can be either parallel or angled. However, angled parking on any state route
requires approval from the State Traffic Engineer.
Submit a request for angled parking approval through the region Traffic Office. Include an
engineering study documenting that the parking will not unduly reduce safety and that the
roadway is of sufficient width that parking will not interfere with the normal movement of
traffic.
Provide for vehicle overhang within the furnishing zone for all angled parking locations. Consider
back-in angled parking if bike lanes are present to improve conflict management through
increased visibility.
When designing parking locations for freight loading areas, it is important to consider both the
delivery vehicle size and how the vehicle loading/unloading is done. Consult with business
owners and freight carriers to locate and configure the freight loading areas.
Width considerations: Cross sections in the Design Manual generally show a range for parallel
parking of 7 to 9 feet. AASHTO defines a passenger car width as 7 feet. Additional width can
allow a buffer for car doors opening, a buffer for bike riders, or a stall that can accommodate
delivery trucks.
Work with stakeholders to determine the appropriate width to provide within the site-specific
constraints.
1238.03 Streetside
The area behind the curb is referred to as the “streetside” and is described in terms of “zones.”
Information about each zone is provided below. Note, local agency partners may have policy
containing additional streetside zones to consider.
WSDOT uses the following terminology to describe the zones found within the streetside:
Frontage Zone
Pedestrian Zone
Furnishing Zone
Exhibit 1238-01 Zones within the Streetside
The streetside is the interface between pedestrians and land use. A robust streetside can serve
as both a pedestrian thoroughfare and a destination, which is desirable in many urban core and
main street contexts to help promote economic vitality. The streetside can also reinforce the
target speed. The pedestrian zone will always be present in streetside design, but other zones
are optional and dependent on the modal and contextual needs and desired balance of
performance needs within the available right of way.
The Americans with Disabilities Act (ADA) requires specific design element dimensions for
streetside elements, depending on the configuration. In general, the pedestrian zone and
frontage zone will always be part of the pedestrian circulation path (PCP). The furnishing zone
may or may not be part of the PCP, depending on how it is designed. See Chapter 1510 for
detailed accessibility criteria and design guidance for pedestrian facilities.
without interfering with the required pedestrian access route (PAR) within the pedestrian zone.
The frontage zone may also provide space for sidewalk cafes, temporary retail product displays,
advertisements, and/or outdoor seating for customers. If there is no retail or residential access
need adjacent to the streetside, a frontage zone may not be necessary.
Width considerations: Cross sections in Design Manual generally show a range for the frontage
zone width of 2 to 12 feet.
Narrow, 2-ft frontage zones provide for a clear area where protruding objects from the building
can be located without compromising the pedestrian access route. Two feet also provides an
offset from the building and minimal space for entering/exiting the building.
Wider frontage zones, such as 12-ft can provide width for a variety of possible elements, such as
sidewalk café dining with tables and chairs along the building. If a frontage zone is to be
provided, work with stakeholders to determine the appropriate width to provide within the site-
specific constraints.
The pedestrian zone is located within the Pedestrian Circulation Path and includes the
Pedestrian Access Route (PAR) needed to meet ADA accessibility criteria (see Chapter 1510). The
pedestrian zone may be considerably wider than the PAR.
A generous pedestrian zone width promotes the mobility and accessibility typically anticipated
within some urban and suburban contexts.
Width considerations: The minimum pedestrian zone width of 5 feet corresponds to WSDOT’s
minimum sidewalk width (see Chapter 1510). Other considerations when choosing a pedestrian
zone width include:
In many downtown environments, the focus is on multimodal transportation and, in
particular, pedestrian accessibility and use. Wider streetside zones promote a greater
sense of safety, and can provide a comfortable and inviting area that can attract
pedestrians.
Work with stakeholders to determine the appropriate width to provide within site-specific
constraints.
Traffic signs and signal cabinets; utility poles; fire hydrants; parking meters; transit boarding,
queuing, and shelters; and bike racks are also generally found within the furnishing zone.
Involve the local agency, regional Landscape Architect, and safety professionals to determine
optimal vegetation types.
Other width accommodations for on-street parking may be needed for vehicle overhang or
entering/exiting movements when parking is present.
Coordinate with region Program Management to understand potential funding limitations for
furnishing zone features described within this section. Partnerships or grants may be necessary
to complete all desired features within the furnishing zone.
Width considerations: A width of 2 feet provides the minimum width to accommodate utilities
and street furniture. Greater widths accommodate a larger variety of possible features within
the furnishing zone. Other considerations when choosing a furnishing zone width include:
Applied retrofit options may require additional maintenance over long-duration applications.
Coordination with maintenance jurisdictions as described in Chapter 301 is critical to evaluating
the potential maintenance outcomes for retrofit options being considered. The retrofit options
discussed within the following subsections are more likely to be applied in urban context
settings. Note that cities over 25,000 population will have the responsibility of maintaining any
retrofit delineation, and it will be critical to ensure they have the resources to maintain striped
retrofit features.
Use retrofit features as a low-cost solution to create wider sidewalk areas, curb extensions,
bicycle parking areas, parklet areas, and/or green street low-impact development solutions.
1238.05 References
Standard Plans for Road, Bridge, and Municipal Construction, M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction, M 41-10, WSDOT
Urban Street Design Guide, National Association of City Transportation Officials, New York, NY,
2013
www.nacto.org
Urban Street Stormwater Guide, National Association of City Transportation Officials, New York,
NY, 2017
www.nacto.org
A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO, current edition
www.transportation.org/Pages/Default.aspx
1239.01 Introduction
This chapter provides information on geometric cross section components that are common to
many facility types. Cross section elements include: shoulders, medians and outer separations,
side slopes, and curbing.
1239.02 Shoulders
Shoulders are typically used on high, or intermediate speed limited and non-limited access
facilities, some rural contexts, as well as intermediate-speed locations that do not have
streetsides (curb-sections) (see Chapter 1238). Intermediate-speed locations in suburban and
urban contexts that utilize streetsides do not need to include a shoulder unless determined to
be necessary by shoulder function, (where intended for bicyclists for example) or safety
performance analysis, hydraulic analysis or engineering judgment.
Shoulders provide space to escape potential collisions or reduce their severity. They also provide
a sense of openness, contributing to driver ease at higher speeds. Shoulders also convey
drainage away from the traveled way as determined by hydraulic analysis.
Notes:
[1] Bus use only shoulder width range is 12-ft to 14-ft.
[2] If curb or barrier present, see Exhibit 1239-9.
[3] Intermediate-speed and low-speed locations in urban and suburban contexts utilizing
streetsides do not need to include a shoulder unless necessary for safety performance,
hydraulic performance or engineering judgment. See Exhibit 1231-5, Exhibit 1231-6 (A & B),
Exhibit 1231-7 (B & C), and Section 1239.02.
1239.02(1)(a) Shoulder Width Considerations
Exhibit 1239-2 lists considerations for choosing an appropriate shoulder width from the range
given. The considerations listed help one to understand the modal needs and function
associated with different shoulder widths.
Contact the Area Maintenance Superintendent to determine the shoulder width appropriate for
maintenance operations. In some cases, a continuous width is not necessary; instead, the focus
is placing the shoulder width near assets with high-frequency maintenance needs. Compare the
added cost of the wider shoulders to the added benefits to maintenance operations as well as
other benefits that may be derived (see Chapter 301).
The usable shoulder is the width necessary to provide the desired function (see Exhibit 1239-2).
Usable shoulder width is less than the constructed shoulder width when vertical features (such
as traffic barrier or walls) are at the edge of the shoulder. This is because drivers tend to shy
away from the vertical feature. For widening for traffic barrier, see Chapter 1610. For
requirements for lateral clearance to barrier or curb, see 1239.06.
Shoulder widths greater than 10 feet may encourage use as a travel lane. Therefore, use
shoulders wider than 10 feet only to meet one of the listed functions (see Exhibit 1239-2).
When walls are placed adjacent to shoulders, see Chapters 730 and 740 for barrier guidance.
See Exhibit
1239-4 for
ditch details
See Exhibit
1239-4 for
ditch details
See Exhibit
1239-4 for
ditch details
Notes:
The top three drawings illustrate angle points in subgrade to drain stormwater away from the
roadbed.
For applicable numbered notes, see next page.
Notes:
[1] Shoulder cross slopes are normally the same as the cross slopes for adjacent lanes. (For examples
and additional information for locations where it may be desirable to have a shoulder cross slope
different than the adjacent lane, see Chapter 1250).
[2] Provide widening and slope rounding outside the usable shoulder when foreslope is steeper than
4H:1V.
[3] For shoulder width guidance, see Exhibit 1239-1.
[4] For additional requirements for sidewalks, see Chapter 1510.
[5] See 1239.05 for curb design guidance.
[6] Provide paved shoulders wherever extruded curb is placed. (See the Standard Plans for additional
details and dimensions.)
[7] Consider using the same application of slope rounding on all ramps and crossroads, as well as the
main roadway. Use end rounding on the crossroad just beyond the ramp terminals and at a similar
location where only a grade separation is involved.
[8] When widening beyond the edge of usable shoulder for curb or barrier, additional widening for
slope rounding may be omitted.
[9] For widening guidelines for guardrail and concrete barrier, see Chapter 1610.
General:
On divided multilane highways, see Exhibits 1239-12a through 1239-12c for additional details for
median shoulders.
Fill sections – Roadway sections where the height of the roadway is higher than the existing
natural ground.
Ditch sections - Roadway sections where the height of the roadway is higher than the existing
natural ground but not as high as the needed roadside ditch so that after the needed ditch is
installed there is a foreslope into the ditch and a back slope out of the ditch up to where it
catches the natural ground.
Cut sections - Roadway sections where the height of the roadway is lower than the existing
ground. This typically produces a foreslope into the ditch and a back slope out of the ditch up to
where it catches the natural ground.
When designing side slopes, attempt to fit the slope selected for any fill section, ditch section, or
cut section into the existing terrain to give a smooth transitional blend from the construction to
the existing landscape when practicable. Flatter slopes are desirable, especially with higher
posted speeds and when the associated cost does not significantly exceed other design options.
Fill side slopes not steeper than 4H:1V, with smooth transitions where the slope changes, will
provide a reasonable opportunity to recover control of an errant vehicle. Fill side slopes
designed to 4H:1V or flatter are preferred. Provide widening and slope rounding outside the
usable shoulder when the foreslope is steeper than 4H:1V (see Exhibit 1239-3). Do not disturb
existing stable cut slopes just to meet the 4H:1V foreslope preference.
Fill-slopes steeper than 4H:1V but flatter than 3H:1V are considered traversable, but not
recoverable. When providing a slope that meets these characteristics, placement of a clear area
extending from the toe of the slope to the outside edge of the design clear zone is needed for an
errant vehicle runout and stop (see Chapter 1600 for design clear zone guidance). Consult with
Region Maintenance to determine if mowing is contemplated. When providing fill-slopes
steeper than 3H:1V, it is a best practice to document the reason for the decision in the design
documentation package. When mowing is contemplated, provide slopes not steeper than
3H:1V.
Where unusual geological features or soil conditions exist, treatment of the slopes depends
upon results of a review of the location by the Region Materials Engineer.
See Section 1600.03(1) for when to use traffic barrier to mitigate a side slope. Unmitigated
critical slopes will require a Design Analysis. The steepest slope allowed is determined by the
Region Materials Engineer based on soil conditions. If more material is needed to build the
roadway, consider obtaining it by flattening cut slopes uniformly on one or both sides of the
highway. Consult the Region Materials Engineer to determine what percentage of the excavated
material will likely be suitable for fill material. Where considering wasting excess material on an
existing fill side slope, consult the Region Materials Engineer to verify that the subgrade will
support the additional material.
Provide for drainage from the roadway surface and drainage in ditches (see Chapter 800). For
drainage ditches, see Section 1239.03(1). At locations where vegetated filter areas or detention
facilities will be established to improve highway runoff water quality, provide appropriate slope,
space, and soil conditions for that purpose. (See the Highway Runoff Manual for design criteria
and additional guidance.)
It is desirable to plant and establish low-growing vegetation on non-paved roadsides. This type
of treatment relies on the placement of a lift of compost or topsoil over base course material in
the roadway cross section. Consult with the area Maintenance Superintendent and the region or
HQ Landscape Architect to determine the appropriate configuration of the roadway cross
section and soil and plant specifications. This kind of treatment would not be done where
barrier is installed along the roadway as the lift of compost or topsoil is not a suitable barrier
foundation.
Flatten freeway section median cross-over foreslopes to 10H:1V (See Section 1370.03). Flatten
crossroad and road approach foreslopes not steeper than 6H:1V on other highways. Grade
crossroad and road approach foreslopes flatter than 6H:1V where feasible. Provide smooth
transitions between the main line foreslopes and the crossroad or road approach foreslopes.
Move the crossroad or road approach drainage as far away from the main line as feasible. This
can locate the pipe outside the Design Clear Zone and reduce the length of pipe.
Provide slope treatment as shown in the Standard Plans (Slope treatment) at the top of roadway
cut slopes except for cuts in solid rock. Unless Class B slope treatment is called for, Class A slope
treatment is used. Call for Class B slope treatment where space is limited, such as where right of
way is restricted.
When topographic restrictions exist, consider an enclosed drainage system with appropriate
inlets and outlets.
Maintenance operations are also facilitated by adequate width between the toe of the slope
and an adjacent drainage ditch. Where this type of facility is anticipated, provide sufficient right
of way for access to the facility and place the drainage ditch as close to the right of way line as
feasible.
Notes:
Freeboard is the vertical distance from the bottom of base course to the 10-year
storm water surface (see the Hydraulics Manual for more information.)
Coordinate ditch depth and bottom of ditch width with region Hydraulics.
Coordinate foreslope and backslope and ditch location with region Materials
Engineer.
See other sections of this chapter for shoulder and side slope details.
Early in the bridge plan development, determine preliminary bridge geometrics, end slope rates,
and toe of slope treatments. Exhibit 1239-5a provides guidelines for use of slope rates and toe
of slope treatments for overcrossings. Exhibit 1239-5b shows toe of slope treatments to be used
on the various toe conditions.
Notes:
[1] See Exhibit 1239-5b.
[2] Slope may be 1¾H:1V in special cases.
[3] In interchange areas, continuity may require variations.
[4] See 1239.03.
1239.04(1) Design A
This design is shown in stage development to aid the designer in selecting an appropriate
section for site conditions in regard to backslope, probable rockfall, hardness of rock, and so on.
The following guidelines apply to the various stages shown in Exhibit 1239-6:
Stage 1 is used where the anticipated quantity of rockfall is small, adequate fallout
width can be provided, and the rock slope is ½H:1V or steeper. Controlled blasting is
recommended in conjunction with Stage 1 construction.
Stage 2 is used when a “rocks in the road” problem exists or is anticipated. Consider
it on flat slopes where rocks are apt to roll rather than fall.
Stage 3 represents the full implementation of all protection and safety measures
applicable to rock control. Use it when extreme rockfall conditions exist.
Show Stage 3 as the ultimate stage for future construction in the Plans, Specifications, and
Estimates (PS&E) if there is any possibility that it will be needed.
The use of Stage 2 or Stage 3 alternatives (concrete barrier) is based on the designer’s analysis
of the particular site. Considerations include maintenance; size and amount of rockfall; probable
velocities; availability of materials; ditch capacity; adjacent traffic volumes; distance from
traveled lane; and impact severity. Incorporate removable sections in the barrier at
approximately 200-foot intervals. Provide appropriate terminal treatment (see Chapter 1610).
Occasionally, the existing ground above the top of the cut is on a slope approximating the design
cut slope. The height (H) is to include the existing slope or that portion that can logically be
considered part of the cut. Select cut slopes for a project that provide stability for the existing
material.
Benches may be used to increase slope stability; however, the use of benches may alter the
design given in Exhibit 1239-6.
The necessity for benches, as well as their width and vertical spacing, is established after an
evaluation of slope stability. Make benches at least 20 feet wide. Provide access for
maintenance equipment to the lowest bench and to the higher benches if feasible. Greater
traffic benefits in the form of added safety, increased horizontal sight distance on curves, and
other desirable attributes may be realized from widening a cut rather than benching.
Notes:
[1] For widening for guardrail and concrete barrier, see Chapter 1610.
General:
Treat cut heights less than 20 feet as a normal roadway unless otherwise determined by the Region
Materials Engineer.
Stage 2 and Stage 3 Alternates may be used when site conditions dictate.
Fence may be used in conjunction with the Stage 3 Alternate. (See Chapter 1600 for clear zone
guidelines.)
1239.04(2) Design B
A talus slope treatment is shown in 1239-7. The rock protection fence is placed at any one of the
three positions shown, but not in more than one position at a particular location. Consult with
the RME for the placement of the rock protection fence in talus slope areas.
Fence position a is used when the cliff generates boulders less than 0.25 yd3 in size
and the length of the slope is greater than 350 feet.
Fence position b is the preferred location for most applications.
Fence position c is used when the cliff generates boulders greater than 0.25 yd3 in
size regardless of the length of the slope. On short slopes, this may require placing
the fence less than 100 feet from the base of the cliff.
Use of gabions may be considered instead of the rock protection shown in fence
position a. Because gabion treatment is considered similar to a wall, provide
appropriate face and end protection (see Chapters 730 and 1610).
Use of the alternate shoulder barrier is based on the designer’s analysis of the particular site.
Considerations similar to those given for Design A alternatives apply.
Evaluate the need for rock protection treatments other than those described above for cut
slopes that have relatively uniform spalling surfaces (consult with the RME).
Notes:
[1] For widening for guardrail and concrete barrier, see Chapter 1610.
General:
Ordinarily, place fence within a zone of 100 feet to 200 feet maximum from base of
cliff, measured along the slope.
Rock protection fence may be used in conjunction with the Shoulder Barrier
Alternate when site conditions dictate.
Notes:
[1] Staked slope line: Maximum slope 1H:1V.
[2] Step rise: Height variable 1 foot to 2 feet.
[3] Step tread: Width = staked slope ratio x step rise.
[4] Step termini: Width ½-step tread width.
[5] Slope rounding.
[6] Overburden area: Variable slope ratio.
1239.05 Curbs
Curbs are designated as either vertical or mountable. Vertical curbs have a face slope 1H:3V or
steeper. Mountable curbs have a sloping face that is more readily traversed.
Curbs can also be classified as mountable. Mountable curbs are sloped curb with a height of 6
inches or less; 4 inches or less is recommended to reduce underside vehicle damage if driven
over. When the face slope is steeper than 1H:1V, the height of a mountable curb is limited to 4
inches or less.
(b) Provide mountable curb where a curb is needed, but accommodation for specific design
user(s) makes mountability necessary.
(c) Use mountable curbs in roundabouts. See Chapter 1320 and Standard Plan F-10.18-01.
Intermediate speed facilities may use vertical curbs; however, consider mountable curbs for
intermediate target speeds. Consider use of 12-inch to 18-inch vertical curb when analysis
demonstrates a need to reduce concerns of lane departure into oncoming lane on intermediate-
speed facilities. All curb types are appropriate for low-speed facilities.
In some areas, curb may be needed to control runoff water until ground cover is attained to
control erosion. Document the plan to remove the curb when the ground cover becomes
adequate. A best practice is to arrange for curb removal with region maintenance staff as part of
the future maintenance plans (see Maintenance Owner’s Manual guidance in Chapter 301).
When curb is used in conjunction with guardrail, see Chapter 1610 for guidance. For existing
curb, particularly on high-speed facilities, evaluate the continued need for the curb. Remove
curbing that is no longer needed.
When an overlay will reduce the height of a curb, evaluate grinding (or replacing the curb) to
maintain curb height if needed for pavement performance design and/or drainage performance.
(See 1250.02(2) for shoulder cross slope considerations.) To maintain or restore curb height,
consider lowering the existing pavement level and improving cross slope by grinding before an
asphalt overlay or as determined by the pavement design. The cross slope of the shoulder may
be steepened to maximize curb height and minimize other related impacts. Note that grinding
can cause issues with meeting ADA criteria at curb ramps for counter slope and crosswalk
running slope. See Chapter 1510 for more information.
Curbs can hamper snow-removal operations. In areas of heavy snowfall, ask the Area
Maintenance Superintendent to review and concur with the use of curbing.
For curbs at traffic islands, see Chapter 1310. For curbs at roundabouts, see Chapter 1320 and
Standard Plan F-10.18-01.
Posted Speed Curb - Median [1] [2] Curb - Right [1] [2] Barrier
Notes:
[1] For HOV lanes on arterials streets, see Section 1410.06(4)(d)
[2] Measured from the edge of traveled way to the face of curb.
[3] On low speed urban roadways (35 mph or less), maintaining shoulder width is desirable;
however, with justification, curb (mountable or vertical) may be placed at the edge of
traveled way.
[4] With justification, mountable curb may be placed at the edge of traveled way for access
management in urban areas. Adding mountable curb reduces lane and/or shoulder width
and may require additional documentation.
[5] Raised median for two-way ramps (see 1360.03(5).)
[6] 2 ft min. for ramp design where speeds are ≤35mph (usually near the ramp terminal
intersection) and 4 ft. min. where design speeds are > 35mph.
The width of a median is measured from edge of traveled way to edge of traveled way and
includes shoulders. Median widths can vary greatly based on the functional use of the median,
the functional use of the shoulders, target speed, and context. Guidance for median and
shoulder widths depending on their function and context is given in:
When the horizontal and vertical alignments of the two roadways of a divided highway are
independent of one another, determine median side slopes in conformance with 1239.03 and
Chapters 1600 and 1610. Independent horizontal and vertical alignment, rather than parallel
alignment, can allow for reduced grading or cut sections.
In areas where land is expensive, make an economic comparison of wide medians to narrow
medians with barrier. Consider right of way, construction, maintenance, and safety
performance. The widths of medians need not be uniform. Make the transition between median
widths as long as practical. (See Chapter 1210 for minimum taper lengths.)
When using concrete barriers in depressed medians or on the insides of curves, provide for
surface drainage on both sides of the barrier. The transverse notches in the base of precast
concrete barrier are not intended to be used as a drainage feature, but rather as pick-up points
when placing the sections.
At locations where the median will be used to allow vehicles to make a U-turn, consider
increasing the width to meet the needs of the selected design vehicles making the U-turn. (For
information on U-turn locations, see Chapter 1310.) Document the selected design vehicle and
provide alternate route information for vehicles not serviced by the U-turn.
Where feasible, widen medians at intersections on rural divided multilane highways. Provide
sufficient width to store vehicles crossing the expressway or entering the expressway with a left
turn.
When the median is to be landscaped, or where fixed objects are to be placed in the median,
see Chapter 1600 for traffic barrier and clear zone guidance. When the median will transition for
use as a left-turn lane, see Chapter 1310 for left-turn lane design considerations.
Exhibit 1239-10 Median Functions and Guidance: High and Intermediate Speeds
Separating opposing traffic Varies[1] and see Chapters 1600 and 1610
Separating alignments Varies See 1239.03 and Chapters 1600 and 1610 [2]
Recovery/Refuge areas for errant vehicles See 1239.03 and Chapter 1600
Median signing and illumination – 6 ft [1] or as recommended for signing and illumination
Undivided highways and ramps design
Storage space for snow Consult Region Maintenance
See Chapters 1370 and 1410, and consult with
Enforcement areas
Washington State Patrol
Vehicle storage space for crossing at See Chapter 1310, and consult with region traffic
intersections engineer
Median U-turn or Median crossover See Chapters 1310 and 1370
Outer separation for frontage or collector- 12 ft min plus shoulders [1] See Exhibit 1360-15a and
distributer roads Chapters 1360, 1600 and 1610
Varies; see Chapter 1420 and discuss with Transit
Transit use
Agency [3]
6 ft minimum, excluding curb width
Pedestrian refuge for crossing locations
(see Chapter 1510)
Notes:
[1] Conduct a safety performance analysis and include potential countermeasures identified to obtain
the desired safety performance. Consult with maintenance; additional width may be appropriate
for unconstrained right of way locations, maintenance functions, or for divided highways on
independent alignments.
[2] An economic comparison of wide medians to narrow medians with barrier is recommended.
[3] For planning and scoping purposes, 32 ft can be the assumed minimum for two-way transit
operations or 22 ft for one-way transit operations.
A common form of restrictive median on urban managed access highways is the raised median.
For more information on traffic volume thresholds for restrictive medians on managed access
highways, see Chapter 540.
Exhibit 1239-11 Median Functions and Guidance: Low and Intermediate Speeds
Notes:
[1] The width of a raised median can be minimized by using a dual-faced cement concrete traffic
curb, a precast traffic curb, or an extruded curb.
[2] Consider width necessary for lateral clearance.
[3] 2 ft minimum if adjacent lane widths are less than 11 ft.
[4] Consult Region Landscape Architect; width will depend on type of plantings. Over-excavation may
be necessary to prepare soil for the selected plantings to ensure mature heights are obtained.
[5] Consult Hydraulic Report for width necessary for drainage or treatment facilities.
[6] Consult with the transit provider. If a transit shelter is planned, a minimum 5 ft clear area
measured from the edge of shelter roofing to face of curb width, is necessary for pedestrians to
move to and around the shelter and for lift extension (see Chapter 1430).
[7] Consider width needed for plantings or street furniture to create the appropriate pedestrian zone
segregation and environment.
[8] See also Chapter 1510
Note:
For applicable notes, see Exhibit 1239-12c.
Note:
For applicable notes, see Exhibit 1239-12c.
[11]
Edge of Edge of
[7] [7] traveled way
traveled way
[12] [12]
Notes:
[1] For guidance on median widths, see Exhibits 1239-10 and -11
[2] Consider vertical clearances, drainage, and aesthetics when locating the pivot point.
[3] Generally, slope pavement away from the median. When barrier is present and the
roadway is in a superelevation, size the shoulder so that standing water is not in the travel
lane. Where appropriate, a crowned roadway section may be used in conjunction with the
depressed median.
[4] Design B may be used uniformly on both tangents and horizontal curves. Use Alternate
Design 1 or Alternate Design 2 when the "rollover" between the shoulder and the inside
lane on the high side of a superelevated curve exceeds 8%. Provide suitable transitions at
each end of the curve for the various conditions encountered in applying the alternate to
the basic median design.
[5] Method of drainage pickup to be determined by the designer.
[6] Median shoulders normally slope in the same direction and rate as the adjacent through
lane. See 1250.02(2) for examples and additional information for locations where it may be
desirable to have a shoulder cross slope different than the adjacent lane.
[7] For guidance on shoulder widths, see 1239.02.
[8] Future lane width of a planned phase.
[9] Widen and round foreslopes steeper than 4H:1V as shown in Exhibit 1239-3. See Chapter
1600 for barrier recommendations.
[10] Designs C, D, and E are rural high-speed median designs. See Exhibit 1239-10 for
recommended median widths.
[11] Raised medians may be paved or landscaped. For clear zone and barrier guidelines when
fixed objects or trees are in the median, see Chapter 1600.
[12] Lane and shoulders normally slope away from raised medians. When they slope toward the
median, provide for drainage.
[13] See 1239.05 and 1239.06 for curb design guidance.
1239.08 Documentation
Refer to Chapter 300 for design documentation requirements and approving authorities.
1240.01 General
The roadway on a curve may need to be widened to make the operating conditions comparable
to those on tangents. There are two main reasons to do this. One is the off-tracking of vehicles
such as trucks and buses. The other is the increased difficulty drivers have in keeping their
vehicles in the center of the lane. Apply turning roadway widths only when there is a need to
optimize the operational or safety performance of a particular segment of roadway with larger
volumes of trucks or when trucks are the identified modal priority. The application of turning
roadway width is not applicable on managed access low-speed roadways or managed access
intermediate-speed highways in suburban or urban contexts.
Minimum traveled way width (W), based on the delta angle of the curve (shown in Exhibit 1240-
1b), may be used. Document the reasons for using the minimum width. Round W to the nearest
foot.
Widths given in Exhibits 1240-1a and 1b are for facilities with 12-foot lanes. When 11-foot lanes
are selected, width (W) may be reduced by 2 feet.
Minimum traveled way width (W), based on the delta angle of the curve (shown in Exhibit 1240-
2b), may be used. Document the reasons for using the minimum width. Round W to the nearest
foot.
Widths given in Exhibits 1240-2a and 2b are for facilities with 12-foot lanes. When 11-foot lanes
are selected, width (W) may be reduced by 2 feet.
To keep widths to a minimum, the traveled way widths for Exhibits 1240-2a and 2b were
calculated using the WB-40 design vehicle. When volumes are high for trucks larger than the
WB-40 and other traffic, consider using the widths from Exhibits 1240-1a and 1b.
Minimum width (W), based on the delta angle of the curve for one-lane roadways, may be used.
Exhibit 1240-3b gives W using the radius to the outer edge of the traveled way. Exhibit 1240-3c
gives W using the radius on the inner edge of the traveled way. Document the reasons for using
the minimum width. Round W to the nearest foot.
Build shoulder pavements at full depth for one-lane roadways. To keep widths to a minimum,
traveled way widths were calculated using the WB-40 design vehicle, which may force larger
vehicles to encroach on the shoulders. This also helps to maintain the integrity of the roadway
structure during partial roadway closures.
Small amounts of widening add to the cost with little added benefit. When the traveled way
width for turning roadways results in widening less than 0.5 foot per lane, or a total widening
of less than 2 feet on existing roadways that are to remain in place, it may be disregarded.
1240.03 Documentation
Refer to Chapter 300 for design documentation requirements.
1240.04 References
1240.04(1) Design Guidance
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
Exhibit 1240-1a Traveled Way Width for Two-Lane Two-Way Turning Roadways
Note:
[1] Width (W) is based on:
WB-67 design vehicle
3-ft clearance per lane (12-ft lanes)
Centerline
Edge of shoulder
W
Edge of
traveled way
R
Exhibit 1240-1b Traveled Way Width for Two-Lane Two-Way Turning Roadways: Based on the Delta Angle
45
ft
ft
00
75
1
R= R=150 ft
R=
40
Traveled Way Width, W (ft)
R=200 ft
35 R=250 ft
R=300 ft
R=350 ft
R=400 ft
30 R=500 ft
R=600 ft
R=800 ft
R=1,000 ft
R=2,000 ft
25
0 30 60 90
Note:
Width (W) is based on:
WB-67 design vehicle
3-ft clearance per lane (12-ft lanes)
Exhibit 1240-2a Traveled Way Width for Two-Lane One-Way Turning Roadway
3,000 to tangent 24
1,000 to 2,999 25
999 26
600 26
500 27
400 27
300 28
250 29
200 29
150 31
100 34
Note:
[1] Width (W) is based on:
WB-40 design vehicle
3-ft clearance per lane (12-ft lanes)
Centerline
Edge of shoulder
W
Edge of
traveled way
R
Exhibit 1240-2b Traveled Way Width for Two-Lane One-Way Turning Roadways: Based on the Delta Angle
35
ft R=100 ft
7 5
R=
Traveled Way Width, W (ft)
R=150 ft
30
R=200 ft
R=250 ft
R=300 ft
R=400 ft
R=600 ft
R=1,000 ft
25
0 30 60 90
Note:
Width (W) is based on:
WB-40 design vehicle
3-ft clearance per lane (12-ft lanes)
Note:
[1] On tangents, the minimum lane width is selected based on Chapters 1230 and 1106.
Width (W) is based on:
WB-40 design vehicle
4-ft clearance
Edge of shoulder
W
Edge of
R on outside
traveled way
R on inside
Exhibit 1240-3b Traveled Way Width for One-Lane Turning Roadways: Based on the Delta Angle, Radius on
Outside Edge of Traveled Way
22
21 ft
5 0 R=75 ft
R=
Traveled Way Width, W (ft)
20
R=100 ft
19
18
R=150 ft
17
R=200 ft
16 R=250 ft
15
14
0 10 20 30 40 50 60 70 80 90 100
Note:
All radii are to the outside edge of traveled way.
Width (W) is based on:
WB-40 design vehicle
4-ft clearance
Exhibit 1240-3c Traveled Way Width for One-Lane Turning Roadways: Based on the Delta Angle, Radius on
Inside Edge of Traveled Way
22
R=50 ft
21
Traveled Way Width, W (ft)
20
R=75 ft
19
R=100 ft
18
R=150 ft
17
R=200 ft
16 R=250 ft
15
14
0 10 20 30 40 50 60 70 80 90 100
Delta Angle of Curve (degrees)
Note:
All radii are to the inside edge of traveled way.
Width (W) is based on:
WB-40 design vehicle
4-ft clearance
1250.01 General
Use this chapter to design roadway cross slopes and superelevation. Cross slopes function to
drain water away from the roadway and 2% is a commonly used slope rate. To maintain the
design speed, highway and ramp curves are usually superelevated to overcome part of the
centrifugal force that acts on a vehicle.
1250.02(1) Lanes
The cross slope on tangents and curves is a main element in roadway design. The cross slope or
crown on tangent sections and large radius curves is complicated by the following two
contradicting controls:
Reasonably steep cross slopes aid in water runoff and minimize ponding as a result of
pavement imperfections and unequal settlement.
Steeper cross slopes are noticeable in steering, increase the tendency for vehicles to
drift to the low side of the roadway, and increase the susceptibility of vehicles to slide
to the side on icy or wet pavements.
A 2% cross slope is normally used for tangents and large-radius curves on high and intermediate
pavement types, although cross slopes may vary from the target 2%.
The algebraic difference in cross slopes is an operational factor that can affect vehicles making a
lane change across a grade-break during a passing maneuver on a two-lane two-way roadway.
Its influence increases when increased traffic volumes decrease the number and size of available
passing opportunities.
On ramps with metering, consider how cross slopes can impact driver comfort within the queue.
Additionally, larger cross slopes may present concerns about maintaining vehicle lateral position
within the queue lane, depending on weather and resulting pavement conditions.
A somewhat steeper cross slope may be needed to facilitate recommended drainage design,
even though this might be less desirable from an operational point of view. In such areas,
consider not exceeding design cross slopes of 2.5% with an algebraic difference of 5%.
For a two-lane two-way roadway, provide an algebraic difference to meet the appropriate
conditions stated above except when drainage design recommends otherwise.
1250.02(2) Shoulders
Shoulder cross slopes are normally the same as the cross slopes for adjacent lanes. With
justification, shoulder slopes may be increased to 6%. On the high side of a roadway with a
plane section, such as a turning roadway in superelevation, the shoulder may slope in the
opposite direction from the adjacent lane. The maximum difference in slopes between the lane
and the shoulder is 8%. Locations where it may be desirable to have a shoulder slope different
than the adjacent lane are:
Where curbing is used.
Where shoulder surface is bituminous, gravel, or crushed rock.
Where overlays are planned and it is desirable to maintain the grade at the edge of the
shoulder.
On divided highways with depressed medians where it is desirable to drain the runoff
into the median.
On the high side of the superelevation on curves where it is desirable to drain
stormwater or meltwater away from the roadway.
At intersections where pedestrian signal accommodations are provided within the
shoulder
Where extruded curb is used, see the Standard Plans for placement (see Chapter 1239 for
information on curbs). Widening is also normally provided where traffic barrier is installed (see
Chapter 1610 and the Standard Plans).
On ramps with metering, where the shoulder is or could be utilized for queuing, consider how
the shoulder cross slope can impact driver comfort within the queue. Additionally, larger
shoulder cross slopes may present concerns of maintaining vehicle lateral position within the
queue lane, depending on weather and resulting pavement conditions.
Depending on design speed, construct large-radius curves with a normal crown section. The
minimum radii for normal crown sections are shown in Exhibit 1250-1. Superelevate curves
with smaller radii as follows:
Exhibit 1250-4a (emax=10%) is desirable for all open highways, ramps, and long-term
detours, especially when associated with a main line detour.
Exhibit 1250-4b (emax =8%) may be used for freeways in urban design areas and areas
where the emax =6% rate is allowed but emax =8% is preferred.
Exhibit 1250-4c (emax =6%) may be used—with justification—for non-freeway
highways in urban design areas, in mountainous areas, and for short-term detours,
which are generally implemented and removed in one construction season.
Exhibit 1250-5 may be used for turning roadways at intersections, urban managed
access highways with a design speed of 40 mph or less, and—with justification—ramps
in urban areas with a design speed of 40 mph or less.
When selecting superelevation for a curve, consider the existing curves on the corridor. To
maintain route continuity and driver expectance on open highways, select the chart (see
Exhibits 1250-4a, 4b, or 4c) that best matches the superelevation on the existing curves.
In locations that experience regular accumulations of snow and ice, limit superelevation from
the selected chart to 6% or less. In these areas, provide justification for superelevation rates
greater than 6%. Vehicles moving at slow speeds or stopped on curves with supers greater than
6% tend to slide inward on the radius (downslope).
6.68V 2
R
e f
Where:
R = The minimum allowable radius of the curve (ft)
V = Design speed (mph)
e = Superelevation rate (%)
f = Side friction factor from Exhibit 1250-3
Address superelevation when the existing radius is less than the minimum radius calculated
using the equation or when the maximum speed determined by a ball banking analysis is less
than the design speed. When modifying the superelevation of an existing curve, provide
superelevation as given in 1250.02.
Pay close attention to the profile of the edge of traveled way created by the superelevation
runoff; do not let it appear distorted. The combination of superelevation transition and grade
may result in a hump and/or dip in the profile of the edge of traveled way. When this happens,
the transition may be lengthened to eliminate the hump and/or dip. If the hump and/or dip
cannot be eliminated this way, pay special attention to drainage in the low areas to prevent
ponding. Locate the pivot point at the centerline of the roadway to help minimize humps and
dips at the edge of the traveled lane and reduce the superelevation runoff length.
When reverse curves are necessary, provide sufficient tangent length for complete
superelevation runoff for both curves—that is, from full superelevation of the first curve, to
level to full superelevation of the second curve. If tangent length is longer than this, but not
sufficient to provide full super transitions—that is, from full superelevation of the first curve, to
normal crown to full superelevation of the second curve—increase the superelevation runoff
lengths until they abut. This provides one continuous transition, without a normal crown
section, similar to Designs C2 and D2 in Exhibits 1250-6c and 6d, except that full super will be
attained rather than the normal pavement slope as shown.
1250.08 Documentation
Refer to Chapter 300 for design documentation requirements.
1250.09 References
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
10
8
Superelevation (%)
6
20 m
30
40
mp
m
ph
ph
h
4
25
15
m 35 45 m
ph mp ph
mp
h
h
2
0 1,000 2,000 3,000 4,000 5,000 6,000
Radius (ft)
10
8
Superelevation (%)
6
55
65
75
mp
m
ph
ph
h
4
50 60 70 80 m
mp mp mp ph
h h h
2
0 2,000 4,000 6,000 8,000 10,000 12,000 14,000
Radius (ft)
8
Superelevation (%)
4
45
1 5 mp
25
35
mp
mp
h
m
ph
30
h
h
40
20
m mp
ph h
mp
h
2
0 1,000 2,000 3,000 4,000 5,000 6,000
Radius (ft)
8
Superelevation (%)
4 60 70 80
50
m m mp
ph ph
mp
h
h
55 65 75
mp mp mp
h h h
2
0 2,000 4,000 6,000 8,000 10,000 12,000 14,000
Radius (ft)
6
Superelevation (%)
40
20
30
m
ph
mp
m
ph
h
25
15 m
m 35 45 m
ph mp ph
h
ph
2
0 1,000 2,000 3,000 4,000 5,000
Radius (ft)
6
Superelevation (%)
65 75
55
m mp
ph
m
h
ph
50 60 70
m mp mp 80 m
ph h h ph
2
0 2,000 4,000 6,000 8,000 10,000 12,000 14,000
Radius (ft)
Exhibit 1250-5 Superelevation Rates for Intersections and Low-Speed Urban Roadways
10
6
Superelevation (%)
2
15 mph
20 mph
2 5 mp h
30 m
35
40
mp
m
ph
ph
h
Flat 0
NC -2
0 100 200 300 400 500 600 700 800
Radius (ft)
NC = Normal crown
*Based on one 12-ft lane between the pivot point and the edge of traveled way. When the distance
exceeds 12 ft, use the following equation to obtain LR:
LR = LB(1+0.04167X)
Where:
X = The distance in excess of 12 ft between the pivot point and the farthest edge of traveled way, in ft.
ce
LR
e
Begin (end)
full super
Begin (end) transition
LR
0.7LR 0.3LR
c c ay
LR LR
v e le d w A
e e tra
e of urve
Ed g s i d e o f c
ou t
or PT
PC
A CL
wen
100
B B
wcn
100
Pivot point
C Ed g
e of
wcn trave
i n si d le d w
C ro w n e of ay
C ro w n
100 curv
e C
A B C Level Crown Crown slo
pe Full
s upe
Pivot point r
ce
Begin (end)
e
full super
LR
0.7LR 0.3LR
PC or PT
wcn
100 Edge of traveled way
B
wcn
100
wen
100
B
c c Ed g
LR LR eo
e e insi f trave
d e o le d C
f cu w a y
rve
C ro w n
C ro w n Level Crown
A B C C ro w n
slope Full
Pivot point s upe
r
Begin (end)
full super
LR
Begin (end) transition
0.7LR 0.3LR
c c C
LR LR ay
2e 2e
v e l ed w
tra e
e of curv
or PT
wen
100
Edg tside of B
PC
C ou CL
B
wcn
100
LR
Begin (end)
full super
0.7LR 0.3LR
or PT
Begin (end)
PC
transition
c
LR
e
d way
f travele
Edge o ide of curve A
outs
A
CL
wen
wcn
100
100
B B
Pivot point
C
Ed g e o
f tr
C ro w n
slope
C ro w n
slope inside oaveled way C
f curve
A B C Full
Pivot point su p
er
ce
LR
e
Begin (end) transition
Begin (end)
LR
full super
0.7LR 0.3LR
or PT
c c
PC
LR LR
d way
e e f travele
Edge o ide of curve C
outs
A
CL
wcn
wen
100
100
B B
Pivot point
C
Ed g e o
f tr
C ro w n
slope n slope
inside oaveled way A
C ro w f curve
A B C er
su p
Pivot point Full
LR
0.7LR 0.3LR
Begin (end)
full super
c
Begin (end)
or PT
transition
LR
PC
e
wen
100
Ed g e o
f tr
C ro w n
slope
C ro w n
slope inside oaveled way B
f curve
A B Full
Pivot point su p
er
ce
LR
e
Begin (end) transition
Begin (end)
LR
full super
0.7LR 0.3LR
or PT
c c
PC
LR LR
d way
e e
d g e o f traveleurve
E of c B
outside
wen
100
Edge of traveled way inside
A A
wcn
100
Begin (end)
Begin (end)
transition
full super
LR
0.7LR 0.3LR
or PT
PC
c y A
LR c d wa
LR
tra ve l e e
3e e e of curv
Ed g i d e of B
s
wen
t
100
ou
C
C
Edge of traveled way inside
wcn
100
B&D D
of curve pivot point
A
C ro w n Level Crown
C ro w n
C Full
C ro w n
A B D slope sup
e r
Pivot point
c c or PT
LR LR
PC
e e
C
Edge of traveled way outside
wcn
100
B&D D
of curve pivot point
A
C
Ed
ge
wen
C ro w n C ro w n
100
o
C B Level Crow
n ins f tra
D A i d e ve l B
of ed w
Pivot point cu
C ro w n
slope rve ay
A
Full
supe
r
LT.
Begin (end)
Begin (end)
PC
or PT
transition
full super
2 2
0.7L T 0.3L T 0.3 LT LT
e2 e 2
CL WL e
0.02 WL
Pivot point 100
Crown
slope
Full
Pivot point s upe
r
Begin (end)
transition
full super
2 2 2
LT 0.7 LT LT 0.3 LT LT
e2 e 2 e 2
or PT
PC
CL WL e
0.02 WL
Pivot point 100
Crown
slope Level
r
s upe
Pivot point Full
LT.
Begin (end)
Begin (end)
2
PC
or PT
2
transition
full super
0.7L T 0.3L T 0.3 LT LT
e2 e 2
CL
0.02 WL Pivot point WL e
Crown 100
slope
LT.
Begin (end)
Begin (end)
transition
full super
2 2 2
LT 0.7 LT LT 0.3 LT LT
e2 e 2 e 2
or PT
PC
WL e
CL 100
0.02 WL Pivot point
Crown r
slope Level s upe
Full
Pivot point
1260.01 General
Sight distance allows the driver to assess developing situations and take actions appropriate
for the conditions. Sight distance relies on drivers being aware of and paying attention to their
surroundings and driving appropriately for conditions presented. For the purposes of design,
sight distance is considered in terms of stopping sight distance, passing sight distance, and
decision sight distance.
For additional information, see the following chapters:
Chapter Subject
1250 Sight distance at railroad crossings
1310 Sight distance at intersections at grade
1320 Sight distance at roundabouts
1340 Sight distance at driveways
1515 Sight distance for shared-use paths
1260.02 References
1260.02(1) Design Guidance
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as
adopted and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices
for streets and highways” (MUTCD)
1260.03 Stopping Sight Distance (Eye height – 3.5 ft, Object height – 2.0 ft)
1260.03(1) Design Criteria
Stopping sight distance is provided when the sight distance available to a driver equals or exceeds
the stopping distance for a passenger car traveling at the design speed.
Stopping distance for design is very conservatively calculated, with lower deceleration and
slower perception reaction time than normally expected from the driver. Provide design stopping
sight distance at all points on all highways and on all intersecting roadways, unless a design
deviation is deemed appropriate.
For stopping sight distances on grades between those listed, interpolate between the values
given or use the equation in Exhibit 1260-3.
V2
S 1.47V (2.5)
G
300.347826
100
Where:
S = Stopping sight distance on grade (ft)
V = Design speed (mph)
G = Grade (%)
When the sight distance is greater than the length of curve and the length of curve is critical,
the S>L equation given in Exhibit 1260-5 shall be used to find the minimum curve length.
When a new crest vertical curve is built or an existing one is rebuilt with grades less than 3%,
provide design stopping sight distance from Exhibit 1260-1. For grades 3% or greater, provide
stopping sight distance from 1260.03(2).
The minimum length can also be determined by multiplying the algebraic difference in grades by the
KC value from Exhibit 1260-1 (L=KC*A). Both the exhibit and the equation give approximately the
same length of curve. Neither use the S>L equation.
16
t.
ft.
t.
t.
50 f
ft.
ft.
0f
5f
5
.
25
49
S=155 ft
=200
36
30
=
S=2
=4
,S
S=
S=
,S
14 t.
ph 0f
ph
ph, S
h,
m
ph,
h,
57
mp
55
m
S=
mp
,
50
35 m
2 5 mp h ,
ph
45
Algebraic Difference in Grade, A (%)
30 m
m
40
12
60
.
5 ft
=6 4
10 h, S
mp
65
.
0 ft
= 73
8 h, S
mp
70
.
20 ft
6 p h, S=8
75 m 10 ft
.
p h , S= 9
80 m
4
0
0 500 1000 1500 2000
When S>L
2158
2158 L
L 2S A
A S
2
When S<L
AS 2 2158L
L S
2158 A
Where:
L = Length of vertical curve (ft)
S = Sight distance (ft)
A = Algebraic difference in grades (%)
1°
2.0'
The minimum length can also be determined by multiplying the algebraic difference in grades by the KS
value from Exhibit 1260-1 (L=KS*A). Both the exhibit and equation give approximately the same length
of curve. Neither use the S>L equation.
16
0 ft
ft ft
5 ft
ft
ft
ft
ft
5 95
42
60
70
= 20
05
=4
50
5
S= =5
=3
S=1
=3
,S ,S
2
14 , h
h, S
,S
S=
ph h
,S
p
m mp
ph
m
ph
55
p h,
60
h,
50 5 ft
mp
m
m
mp
= 64
Algebraic Difference in Grade, A (%)
45
25 m
40
h, S
30
12
35
mp
65
0 ft
, S =73 t
h f
10 mp S=820
70 h ,
mp 10 f
t
75 S=9
p h ,
8
80 m
0
0 200 400 600 800 1000 1200 1400 1600 1800 2000
When S>L
400 3.5S LA 400
L 2S S
A 2 A 3.5
When S<L
L
AS 2 3.5L 3.5L2 1600AL
400 3.5S S
2A
Where:
L = Curve length (ft)
A = Algebraic grade difference (%)
S = Sight distance (ft)
Note:
Values for A less than 1.75 are within the 1-degree diverge
of the headlight beam and therefore do not need to be
evaluated for SSD on sag curves.
60
Lateral Clearance to Obstruction, M (ft)
50
60
65
80
70
75
mp
m
mp
40
m
ph
ph
ph
h, S
,S
h,
,S
,S
=9
S
10
=8
=
=6
=5
73
20
ft
45
70
ft
ft
30
ft
ft
20
10
25 mph, 30 mph, 35 mph, 40 mph, 45 mph, 50 mph, 55 mph,
S=155 ft S=200 ft S=250 ft S=305 ft S=360 ft S=425 ft S=495 ft
0
0 1,000 2,000 3,000 4,000 5,000 6,000
When the road grade is less than 3%, provide design stopping sight distance from Exhibit 1260-1.
When the grade is 3% or greater, provide stopping sight distance from 1260.03(2).
Roadside objects with a height (h0) between 2.0 feet and 2.75 feet might not be a stopping sight
distance sightline obstruction. Objects with an h0 between 2.0 feet and 2.75 feet can be checked
graphically to determine whether they are stopping sight distance sightline obstructions.
Where a sightline obstruction exists and site characteristics preclude design modifications to meet
criteria, consult with the region Traffic Engineer and Assistant State Design Engineer for a
determination of appropriate action.
28.65S R 1 R M
M R 1 cos S cos
R 28.65 R
Where:
M = Horizontal sightline offset measured from the centerline of
the inside lane of the curve to the sightline obstruction (ft)
R = Radius of the curve (ft)
S = Sight distance (ft)
The following equation may be used to determine the sight distance for roadside sightline
obstructions inside the horizontal sightline offset (M) distance (see Exhibit 1260-9) with
a height of 2.0 feet or less above the centerline of the lane on the inside of the curve on
overlapping horizontal and crest vertical curves.
S
100L 2h1 h0 2h2 h0 2
A
Where:
L = Length of vertical curve (ft)
S = Sight distance (ft)
A = Algebraic difference in grades (%)
h1 = Eye height (3.5 ft)
h2 = Object height (2.0 ft)
h0 = Height of roadside sightline obstructions above the
centerline of the inside curve lane (2.0 ft or less)
Note:
The above equation cannot be used for sightline obstruction
height (h0) more than 2.0 ft above the centerline of the lane on
the inside of the curve. The available sight distance must be
checked graphically for these sightline obstructions.
1260.04 Passing Sight Distance (Eye height – 3.5 ft, Object height – 3.5 ft)
1260.04(1) Design Criteria
Minimum passing sight distance Minimum Passing Sight
is the distance (on a two-lane Design Speed (mph)
Distance (ft)
highway) used for a driver
to execute a normal passing 20 400
maneuver based on design 25 450
conditions and design speed. 30 500
The potential for passing maneuver 35 550
conflicts is ultimately determined 40 600
by the judgments of the driver and
the conditions present at the time 45 700
of the maneuver. Exhibit 1260-12 50 800
gives the passing sight distances 55 900
for various design speeds.
60 1000
65 1100
70 1200
75 1300
80 1400
On two-lane two-way highways, provide passing opportunities to meet traffic volume demands.
This can be accomplished with roadway sections that provide passing sight distance or by adding
passing lanes at locations that would provide the greatest benefit to passing (see Chapter 1270).
In the design stage, passing sight distance can be provided by adjusting the alignment either
vertically or horizontally to increase passing opportunities.
These considerations also apply to multilane highways where staged construction includes a
two-lane two-way operation as an initial stage. Whether auxiliary lanes are provided, however,
depends on the time lag proposed between the initial stage and the final stage of construction.
A
Eye height h1=3.5' Object height h2=3.5'
When S>L
2800 L 1400
L 2S S
A 2 A
When S<L
AS 2 2800L
L S
2800 A
Where:
L = Length of vertical curve (ft)
A = Algebraic grade difference (%)
S = Sight distance (ft)
10
t
t
0f
ft
00 f
9 ft
ft
80
9
25
0
1,0
7
,2
S= 9
6
,4
1,
=1
=1
=
S=
,S
,S
8 t
5f
ph ,
ph
Algebraic Difference in Grade, A (%)
h,
h,
ph
3
m 1,8
mp
mp
25 m
m
45 S=
40
35
,
30
7 ph t
50
m 5f
1, 98
=
,S
6
m ph 5 ft
55 2 ,13
S=
ph, 5 ft
5
60
m
= 2 ,28
h, S
mp 80 f
t
65 =2,4
4 , S
ph
70 m
0
0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000
1260.05 Decision Sight Distance (Eye height – 3.5 ft, Object height – 2.0 ft)
Decision sight distance values are greater than stopping sight distance values because they
give the driver an additional margin for error and afford sufficient length to maneuver at the
same or reduced speed rather than to just stop.
Consider decision sight distances (see Exhibit 1260-15) at locations where there is high
likelihood for driver error in information reception, decision making, or control actions.
If site characteristics and budget allow, locate these highway features where decision sight
distance can be provided. If this is not practicable, use suitable traffic control devices and
positive guidance to give advanced warning of the conditions.
1260.06 Documentation
It is recognized that some designs do not allow all criteria and guidelines to be followed as
outlined in this chapter.
Refer to Chapter 300 for design documentation requirements.
1270.01 General
Auxiliary lanes are used to comply with capacity demand; maintain lane balance; accommodate
speed change, weaving, and maneuvering for entering and exiting traffic; and encourage
carpools, vanpools, and the use of transit.
For signing and delineation of auxiliary lanes, see the Standard Plans, the Traffic Manual, and
the MUTCD. Contact the region Traffic Engineer for guidance.
Although slow-vehicle turnouts, shoulder driving for slow vehicles, and chain-up areas are not
auxiliary lanes, they are covered in this chapter because they perform a similar function.
Chapter Subject
1103 Design controls, including speed
1230 Geometric cross section components
1310 Turn lanes
1310 Speed change lanes at intersections
1360 Collector-distributor roads
1360 Weaving lanes
1410 High-occupancy vehicle lanes
1270.02(1) General
Climbing lanes (see Exhibit 1270-1) are normally associated with truck traffic, but they may also
be considered in recreational or other areas that are subject to slow-moving traffic. Climbing
lanes are designed independently for each direction of travel.
Exhibit 1270-2a shows how the percent and length of grade affect vehicle speeds. The data is
based on a typical commercial truck.
The maximum entrance speed, shown in the graphs, is 60 mph. This is the maximum value
regardless of the posted speed of the highway. When the posted speed is above 60 mph, use 60
mph in place of the posted speed. Examine the profile at least ¼ mile preceding the grade to
obtain a reasonable approach speed.
If a vertical curve makes up part of the length of grade, approximate the equivalent uniform
grade length.
Whenever the gradient causes a 10 mph speed reduction below the posted speed limit for a
typical truck for either two-lane or multilane highways, the speed reduction warrant is met (see
Exhibit 1270-2b).
1270.02(2)(b) Warrant No. 2: Level of Service (LOS)
The level of service warrant for two-lane highways is met when the upgrade traffic volume
exceeds 200 vehicles per hour and the upgrade truck volume exceeds 20 vehicles per hour. On
multilane highways, a climbing lane is warranted when a capacity analysis shows the need for
more lanes on an upgrade than on a downgrade carrying the same traffic volume.
Design climbing lane width equal to that of the adjoining through lane and at the same cross
slope as the adjoining lanes. Whenever possible, maintain a shoulder width equal to the
adjacent roadway segments (preserve shoulder width continuity). On two-way two-lane
highways, the shoulder may be reduced to 4 feet. If the shoulder width is reduced to 4 feet
document the reasoning for the decision in the design parameter sheets. If the shoulder width is
reduced to less than 4 feet, a design analysis is required.
1% 2% 3% 4% 5% 7%
15,000
6%
10,000
5,000
-1%
-2%
-3%
-4%
0
60 50 40 30 20 10 0
Speed (mph)
4%
30
5%
6%
20 7%
1,200'
4,000'
10
0
0 5,000 10,000 15,000
Distance on Grade, L (ft)
1% Grade,
1% Grade 0 ft
L=L1= 00
,010,0 ft
2% 2% G
d,e000 ft Gra
Sp e e Sp e e G=ra4
4e%, L d e ra d e
41 mph
d ft
Gr L= 4, 0
35 mph
60 m d a 0
35 mph
41 mph
60 d 0
p h mp h 4%
50 mph
50 mph
2,800 ft 1,000 ft 700 ft
2,800 ft 1,000 ft 700 ft
50 mph
300 ft
50 mph
300 ft
60 mph
2 3 4
60 mph
1,200 ft 4,800 ft
1,200 ft 4,800 ft
Given:
A two-lane highway meeting the level of service warrant, with the above profile, and a 60 mph posted
speed.
Determine:
Is the climbing lane warranted? If so, what is its length?
Solution:
1. Follow the 4% grade deceleration curve from a speed of 60 mph to a speed of 50 mph at 1,200 ft.
The speed reduction warrant is met and a climbing lane is needed.
2. Continue on the 4% grade deceleration curve to 4,000 ft. Note that the speed at the end of the 4%
grade is 35 mph.
3. Follow the 1% grade acceleration curve from a speed of 35 mph for 1,000 ft. Note that the speed at
the end of the 1% grade is 41 mph.
4. Follow the -2% grade acceleration curve from a speed of 41 mph to a speed of 50 mph, ending the
speed reduction warrant. Note that the distance is 700 ft.
5. The total auxiliary lane length is (4,000-1,200)+1,000+700+300=4,800 feet. 300 ft is added to the
speed reduction warrant for a two-lane highway (see 1270.02(3) and Exhibit 1270-3).
200 >0.50-0.75
400 >0.75-1.00
≥700 >1.00-2.00
Source: Transportation Research Board, Highway Capacity Manual, 2000
For assistance in developing a passing lane length, see the following website for an example of a
self-modeling spreadsheet. This spreadsheet develops passing lane lengths based primarily on
vehicle speed differentials and is to be used in conjunction with traffic modeling efforts. Contact
the Headquarters Design Office for assistance
( www.wsdot.wa.gov/design/policy/default.htm).
When passing lanes are provided at an isolated location, their typical objective is to reduce
delays at a specific bottleneck; for example, climbing lanes (see 1270.02). The location of the
passing lane is dictated by the needs of the specific traffic operational problem encountered.
When passing lanes are provided to improve traffic operations over a length of road, there is
flexibility in the choice of passing lane locations to maximize their operational effectiveness and
minimize construction costs.
If delay problems on an upgrade are severe, the upgrade will usually be the preferred location
for a passing lane.
Passing lanes at upgrades begin before speeds are reduced to unacceptable levels and, where
possible, continue over the crest of the grade so that slower vehicles can regain some speed
before merging.
The cost of constructing a passing lane can vary substantially, depending on terrain, highway
structures, shoulders, and adjacent development. Thus, the choice of a suitable location for a
passing lane may be critical to its cost-effectiveness.
Generally, passing lanes in level and rolling terrain can be placed where they are least expensive
to construct, avoiding locations with high cuts and fills and existing structures that would be
expensive to widen.
1270.03(3)(c) Intersection-Related Considerations
Consider a corridor evaluation of potential passing lane locations for each direction, avoiding
placement of passing lanes near intersections. Avoid or minimize turning movements on a road
section where passing is encouraged.
Low-volume intersections and driveways are allowed within passing lanes, but not within the
taper transition areas.
Where the presence of higher-volume intersections and driveways cannot be avoided, consider
including provisions for turning vehicles, such as left-turn lanes.
Provide right- and left-turn lanes in passing lane sections where they would be provided on a
conventional two-lane highway.
Left turns within the first 1,000 feet of a passing lane are undesirable. Strategies to address the
turning movement could include left-turn lanes, right-in/right-out access, beginning the passing
lane after the entrance, and so on.
The recommended minimum transition distance between passing lanes in opposing directions is
500 feet for “tail-to-tail” and 1,500 feet for “head-to-head” (see Exhibit 1270-7).
Some separation between lanes in opposite directions of travel is desirable; however, passing
lanes can operate effectively with no separation. In either situation, address pavement markings
and centerline rumble strips as appropriate.
It is desirable to channelize the beginning of a passing lane to move traffic to the right lane in
order to promote prompt usage of the right lane by platoon leaders and maximize passing lane
efficiency.
Widening symmetrically to maintain the roadway crown at the centerline is preferred, including
in continuous passing lane configurations. However, the roadway crown may be placed in other
locations as deemed appropriate. Considerations for crown locations might include: costs,
constructability, right of way, environmentally sensitive roadsides, or other factors.
Where a passing lane will be provided, evaluate the configurations shown in Exhibit 1270-6. In
the exhibit, general passing lane configurations and their typical applications are described in
the following:
Carefully design transitions between passing lanes in opposing directions. Intersections, bridges,
other structures, two-way left-turn lanes, painted medians, or similar elements can be used to
provide a buffer area between opposing passing lanes. The length of the buffer area between
adjoining passing lanes depends on the configuration (see Exhibit 1270-7).
Exhibit 1270-6 illustrates five passing lane design configurations. Part (c) illustrates a continuous
three-lane section with alternating passing lanes. Consider a four-lane cross section when
volume demand exceeds the capacity of a continuous three-lane roadway.
Exhibit 1270-8 illustrates taper rates, cross slopes, and section lengths for three and four-lane
passing sections. Where practicable provide shoulder width in a passing lane section equal to
the shoulder width on the adjacent segments of a two-lane highway. However, the shoulder
may be reduced to 4 feet. If the shoulder width is reduced to 4 feet, document the reason for
the decision on the design parameter sheets. If the shoulder width is reduced to less than 4 feet,
a design analysis is required. See Chapter 1600 for shoulder rumble strip criteria and
considerations.
Where practicable, design the passing lane width the same as the lane width on the adjacent
segments of the two-lane highway.
Provide a 25:1 or flatter taper rate to increase the width for a passing lane. When all traffic is
directed to the right lane at the beginning of the passing lane, provide a taper rate of the posted
speed:1. Provide a posted speed:1 taper rate for the merging taper at the end of a passing lane.
(Refer to the Lane Transitions section in Chapter 1210 for additional information on taper rates.)
Consider a wide shoulder at the lane drop taper to provide a recovery area for drivers who
encounter a merging conflict.
Provide signing and delineation to identify the presence of an auxiliary passing lane. Refer to the
Standard Plans, the Traffic Manual, and the MUTCD for passing lane signing and marking
guidance.
Tail-to-tail
buffer[1]
Note:
1500 ft min
“Head to head” buffer
Taper peed:1
er
or flatt
S
Posted
500 ft min
“Tail to tail” buffer
25:
1
ape [1]
or flatt r
er
25:1 T
eed:1
eed:1
tter
tter
fla
fla
Posted Sp
Posted Sp
r
r
o
Taper o
Ta p e r
1,500 ft min
1,500 ft min
2 mi max
2 mi max
Through traffic
Through traffic
Through traffic
Through traffic
eed:1
fla tter
Posted Sp
Tape r o r
ape [1]
ape [1]
or flatt r
or flatt r
er
er
25:1 T
25:1 T
Notes:
[1] Provide a posted speed:1 taper when all traffic is directed to the right lane at the beginning of the
passing lane.
[2] Where practicable provide the same lane and shoulder widths in the passing section as on adjacent
segments. See 1270.03(4)(b).
1270.04(1) General
RCW 46.61.427 states:
A slow-moving vehicle turnout is not an auxiliary lane. Its purpose is to provide sufficient room
for a slow-moving vehicle to pull out of through traffic and stop if necessary, allow vehicles to
pass, and then return to the through lane. Generally, a slow-moving vehicle turnout is provided
on existing roadways where passing opportunities are limited, where slow-moving vehicles such
as trucks and recreational vehicles are predominant, and where the cost to provide a full
auxiliary lane would be prohibitive.
1270.04(2) Design
Base the design of a slow-moving vehicle turnout primarily on sound engineering judgment.
Designs may vary from one location to another. Provide a length between 100 and 1,320 feet,
excluding tapers. Select a width adequate for the vehicle type expected to use the turn-out,
between 8 to 12 feet in width. Surface the turnouts with a stable, unyielding material (such as
BST or HMA) with adequate structural strength to support the heavier traffic.
To improve the ability of a vehicle to safely reenter through traffic, locate slow-moving vehicle
turnouts where adequate sight distance is available. The minimum design range for slow-vehicle
turnouts may be where at least design stopping sight distance is available. See Chapter 1260.
Sign slow-moving vehicle turnouts to identify their presence. For guidance, see the Standard
Plans, the Traffic Manual, and the MUTCD.
1270.05(1) General
Use of a shoulder driving section is an alternative means to meet the performance objectives
provided by climbing or passing lanes.
• Character of traffic
• Presence of bicycles
1270.05(2) Design
When designing a shoulder for shoulder driving, locate where full design stopping sight distance
(speed/path/direction decision sight distance is desirable) and a minimum length of 600 feet are
available. Where practicable, avoid sharp horizontal curves. When barriers or other roadside
objects are present, the minimum width is 12 feet. The shoulder width depends on the vehicles
that will be using the shoulder. Where trucks will be the primary vehicle using the shoulder, use
a 12-foot width; when passenger cars are the primary vehicle, a 10-foot width may be used.
Shoulder driving and bicycles are not compatible. When the route has been identified as a local,
state, or regional significant bike route, shoulder driving for slow vehicles is undesirable.
Reconstruct the shoulders to provide adequate structural strength for the anticipated traffic.
Select locations where the side slope meets the criteria of Chapter 1239. When providing a
transition at the end of a shoulder driving section, use a 50:1 taper.
Signing for shoulder driving is required (see the Standard Plans, the Traffic Manual, and the
MUTCD). Install guideposts when shoulder driving is to be permitted at night.
1270.06(1) General
Consider an emergency escape ramp (see Exhibit 1270-9) whenever a long, steep downgrade is
encountered. In this situation, the possibility exists of a truck losing its brakes and going out of
control at a high speed. Consult local maintenance personnel and check crash data to determine
whether or not an escape ramp is justified.
Exhibit 1270-9 Emergency Escape Ramp Example
1270.06(2) Design
1270.06(2)(a) Types
The location of an escape ramp depends on terrain, length of grade, sight distance, and roadway
geometrics. Desirable locations include before a critical curve, near the bottom of a grade, or
before a stop. It is desirable that the ramp leave the roadway on a tangent at least 3 miles from
the beginning of the downgrade.
1270.06(2)(c) Lengths
The length of an escape ramp depends on speed, grade, and type of design used. The minimum
length is 200 feet. Calculate the stopping length using the equation in Exhibit 1270-10.
Exhibit 1270-10 Emergency Escape Ramp Length
V2
L
0.3R G
Where:
L = Stopping distance (ft)
V = Entering speed (mph)
R = Rolling resistance (see Exhibit 1270-11)
G = Grade of the escape ramp (%)
Speeds of out-of-control trucks rarely exceed 90 mph; therefore, the desirable entering speed is
90 mph. Other entry speeds may be used when justification and the method used to determine
the speed are documented.
Material R
Roadway 1
Sand 15
Pea gravel 25
1270.06(2)(d) Widths
The width of each escape ramp depends on the needs of the individual situation. It is desirable
for the ramp to be wide enough to accommodate more than one vehicle. The desirable width of
an escape ramp to accommodate two out-of-control vehicles is 40 feet and the minimum width
is 26 feet.
The following items are additional considerations in the design of emergency escape ramps:
If possible, at or near the summit, provide a pull-off brake check area. Also, include in
this area informative signing about the upcoming escape ramp.
Free-draining, smooth, non-crushed gravel is desirable for an arrester bed. To assist in
smooth deceleration of the vehicle, taper the depth of the bed from 3 inches at the
entry to a full depth of 18 to 30 inches in not less than 100 feet.
Mark and sign in advance of the ramp. Discourage normal traffic from using or parking
in the ramp. Sign escape ramps in accordance with the guidance contained in the
MUTCD for runaway truck ramps.
Provide drainage adequate to prevent the bed from freezing or compacting.
Consider including an impact attenuator at the end of the ramp if space is limited.
A surfaced service road adjacent to the arrester bed is needed for wreckers and
maintenance vehicles to remove vehicles and make repairs to the arrester bed.
Anchors are desirable at 300-foot intervals to secure the wrecker when removing
vehicles from the bed.
Typical examples of arrester beds are shown in Exhibits 1270-9 and 1270-12.
Include justification, all calculations, and any other design considerations in the emergency
escape ramp documentation.
Wrecker anchors
Service road
Arrester bed
Length
G2
G1
Chain-up or chain-off areas are widened shoulders, designed as shown in Exhibit 1270-13.
Locate chain-up and chain-off areas where the grade is 6% or less and desirably on a tangent
section.
Consider illumination for chain-up and chain-off areas on multilane highways. When deciding
whether or not to install illumination, consider traffic volumes during the hours of darkness and
the availability of power.
The wide shoulders at chain-up and chain-off areas may encourage parking. When parking is
undesirable, consider parking restrictions.
CL
Edge of shoulder
Through traffic
5 0: 1
20 ft min[1]
165 ft min
Constant
cross slope[2]
1
2 5:
Notes:
[1] Where traffic volumes are low and trucks are not a concern, the width may be reduced to 10 ft min,
with 15 ft desirable.
[2] 2% desirable. (See Chapter 1250 for traveled way cross slope.)
1270.08 Documentation
Refer to Chapter 300 for design documentation requirements.
1270.09 References
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Emergency Escape Ramps for Runaway Heavy Vehicles, FHWA-T5-79-201, March 1978
Highway Capacity Manual, latest edition, Transportation Research Board, National Research
Council
1300.01 General
It is WSDOT practice to analyze potential intersection solutions at all intersection improvement
locations in accordance with E 1082 – Business Practices for Moving Washington and E 1090 –
Moving Washington Forward: Practical Solutions. The objective is to provide the optimum
solution within available resources, with an emphasis on low-cost investments. The analysis can
be done for individual intersections, or on a corridor or network basis. This chapter provides
guidance on preliminary intersection analysis and selection of control type. Intersection design
is completed using Chapter 1310 for the geometrics of intersections, Chapter 1320 for
roundabouts, and Chapter 1330 for traffic signals. Use the aforementioned chapters in
conjunction with chapters 1106, 1230 series, 1430, 1510, and 1520 to assist with dimensioning
design elements.
Consider design users and the balance between modes, safety and mobility performance
considerations, context-sensitive/sustainable design, and economics when selecting and
evaluating alternatives to meet the needs of the project.
Identification of intersection projects can come from a variety of programs and sources,
including those funded by local agencies and developers. The intent of this chapter is that the
procedures apply to all types of intersection modifications on the state highway system.
Potential safety project locations are identified through the safety priority programming
process. Other programs may identify intersection needs through the priority programming
process, but the influence of the type of intersection control with respect to specific
performance category needs may not be fully understood until contributing factors analysis is
completed (see Chapter 1101).
It is WSDOT policy to focus on lower cost solutions with the intent to optimize return on
investment. Only when all at-grade intersection alternatives are ruled out, including turn
restrictions and complete intersection removal, should other more-costly measures be
considered, such as grade-separation. Ramp terminal intersections are subject to the analysis
requirements of this chapter. See chapters 1360 and 550 for additional information.
Chapter Subject
320 Traffic analysis
321 Sustainable Safety Analysis
530 Limited access control
540 Managed access control
550 Access Revision Report
1100 Practical Design
1101 Need Identification
1103 Design Controls
1106 Design Element Dimensioning
1230 Geometric Cross Section Basics; and other 1230 series chapters
1310 Intersections
1320 Roundabouts
1330 Traffic signals
1340 Driveways
1360 Interchanges
1510 Pedestrian facilities
1515 Shared-use paths
1520 Bicycle facilities
Design users have varying skills and abilities. Younger and older drivers in particular are subject
to a variety of behavioral or human factors that can influence elements of their driving ability.
See NCHRP Report 600 – Human Factors Guidelines for Road Systems: Second Edition for
additional information (http://www.trb.org/Main/Blurbs/167909.aspx). Bicyclists, from
recreational to commuters, also have a variety of skill sets that can influence the effectiveness
of bike facilities and intersection operational design (see Chapter 1520 for additional
information). Meeting the needs of one user group can directly influence the service that other
groups experience. The selection process evaluates these competing needs and results in an
optimal balance of tradeoffs for all design users, recognizing the context and priorities of the
location.
The intent of an ICE is not to design an intersection, but to evaluate the compatibility of
different intersection control types with respect to context, modal priority, intersection design
vehicle, and the identified balance of performance needs. Four basic intersection design
consideration categories are shown in Exhibit 1300-1 and can affect the intersection control
types depending on the situation.
Human Factors
Conformance to natural paths of
Driving habits
movement
Driver workload
Pedestrian use and habits
Driver expectancy
Bicycle traffic use and habits
Driver error
Visual recognition of roadway cues
Driver distractions
Compatibility with context characteristics
Perception-reaction time
Demand for alternative mode choices
Traffic Considerations
Design users, modal priority, and Vehicle size and operating characteristics
intersection design vehicle Vehicle speeds
Design and actual capacities Transit involvement
Design-hour turning movements Crash Experience
Variety of movements Bicycle movements
(diverging/merging/weaving/crossing) Pedestrian movements
Physical Elements
Traffic control devices
Character and use of abutting property
Illumination
Vertical alignments at the intersection
Roadside design features
Sight distance
Environmental factors
Angle of the intersection
Crosswalks
Conflict areas
Transit facilities
Speed-change lanes
Driveways
Managed lanes (HOV, HOT, shoulder)
Streetside design features
Accessible facilities
Adjacent at-grade rail crossing
Parking zones
Access management treatments including
Geometric design features
turn restrictions
Economic Factors
Cost of improvements, annual maintenance, operations and life cycle costs, and salvage value
Effects of controlling access and right of way on abutting properties where channelization
restricts or prohibits vehicular movements
Energy consumption and emissions
1300.03(5) Roundabouts
Roundabouts are often circular (or near-circular) at-grade intersections, where traffic on the
approaches yield to traffic within the circulating roadway. Roundabouts are an effective
intersection type that may offer the following:
Reduced fatal and injury crashes compared
with other at-grade intersection types.
Fewer conflict points.
Lower potential for wrong-way driving.
Reduced traffic delays.
Traffic-calming and lower speeds.
More capacity than a two-way or multi-
way stop.
Quickly serves pedestrians needing to
cross the intersection and shortens
crossing distance for pedestrians by allowing for crossing in stages using splitter islands
as pedestrian refuges.
Reduced vehicular approach speeds that result in reduced crash and severity potential
to pedestrians.
Ability to serve high turning volumes with minimal number of approach lanes.
Improved operations where space for queuing is limited.
Improved capacity at ramp terminals intersections with high left-turn volumes without
affecting the structure.
Facilitation of u-turn movements and can be appropriate when combined with access
management along a corridor.
Aesthetic treatments and gateways to communities.
Flexibility to fit funding and a variety of site constraints. Roundabouts are scalable and
site-specific solutions. See Chapter 1320 for more information on roundabout types
and design.
Indiscriminate use of traffic signals can adversely affect the safety performance and operational
efficiency of vehicle, bicycle, and pedestrian traffic. Therefore, and as required by the MUTCD, a
traffic signal should be considered for installation only after if it is determined to meet specific
“warrants” and an engineering study shows that the installation would improve safety and/or
operations. Satisfying a signal warrant does not mandate the installation of a traffic signal nor by
itself meet the requirements of 1300.05; but failing to satisfy at least one warrant shall remove
the signal from consideration.
Not all crashes are correctable with the installation of a traffic signal. Traffic signals may
decrease the potential for crashes of one type and increase the potential for another type. For
instance, at-angle crashes are less frequent with signals because the traffic movements are
controlled, but rear-end crashes are more frequent with signals because of stopping and starting
of vehicles. At-angle crashes are usually more severe than rear-end crashes; however, the
severity of these rear-end crashes tend to be higher at operating speeds above 40 mph. This
requires careful consideration of the location characteristics, traffic flow, and crash history.
State statutes (RCW 46.61.085) require WSDOT approval for the design and location of all
conventional traffic signals and for some types of beacons located on city streets forming parts
of state highways. The Traffic Signal Permit (DOT Form 242-014 EF) is the formal record of the
department’s approval of the installation and type of signal. For traffic signal permit guidance,
see Chapter 1330.
As alternative intersections may be relatively new to Washington State and its users, more
education and community engagement will be necessary to help ensure project success.
However, extensive experience shows that many of these intersection types can provide better
operational and safety performance, often at much less cost than traditional strategies.
Three types of alternative intersections are highlighted in the subsections below: median u-turn,
restricted crossing u-turn, and displaced left-turn intersections. For more information about
these and other intersection design solutions, see the Federal Highway Administration (FHWA)
Alternative Intersection Design web page:
http://safety.fhwa.dot.gov/intersection/alter_design/
The MUT intersection treatment relocates left turn movements downstream from the
intersection resulting in lower delays, higher throughput, and reduction in the number and
severity of crashes. Left-turning drivers proceed straight through the at-grade intersection, and
then execute a u-turn at some distance downstream at a new or existing median opening. The
main intersection is typically signalized and can be highly efficient needing only two signal
phases. By removing the left turns at the main intersection, the MUT design results in a
significant reduction in rear-end, angle, and sideswipe crashes; while reducing the number of
conflict points from 32 to 16 when compared to a conventional signalized intersection. The MUT
can also have advantages for pedestrians with fewer conflict points and a lower delay. However,
the intersection design may reduce bicyclist mobility as they are expected to use the pedestrian
crossings in order to perform left turns at the intersection. The MUT intersection design is more
likely to be suitable for consideration in situations where:
The intersection is over capacity.
There are heavy through volumes and low to moderate left turn volumes.
The intersection is within a higher-speed, multilane, median-divided corridor.
There are safety concerns at an existing signalized intersection or corridor.
Refer to FHWA’s Median U-Turn Intersection Informational Guide for geometric design
considerations and recommendations. (See Chapter 1310 for geometrics when designing the
u-turn movement for the MUT intersection.)
RCUT intersections, also known as superstreets or J-turns, have similarities with the MUT in that
the minor road left-turning movements are redirected (see Exhibit 1300-2). RCUTs, however,
also redirect minor road through movements as shown in Exhibit 1300-3. This intersection type
results in lower delays, improved progression, and a potential reduction in the total number of
crashes and fatal and injury crashes.
Drivers on the minor road approaches must turn right onto the major road and then perform a
u-turn maneuver at a median opening downstream. However, the major road left turn
movements may still be allowed at the main intersection. RCUT intersections may or may not
warrant signalization due to traffic volumes, and those with signalization require fewer signal
phases and shorter cycle lengths than a traditional signalized intersection. The RCUT
intersection is more likely suitable for consideration in situations where:
The intersection is over capacity.
There is a need to improve travel time and progression for the major road.
There are crashes at the intersection related to turning movements that can be
reduced by a RCUT.
The intersection is within a higher-speed, multilane corridor.
There are low through and left turn volumes on the minor road.
Pedestrian volumes are low.
The major roadway contains sufficient median width, or total right of way width, to
support the u-turn movements.
Exhibit 1300-3 Restricted Crossing U-Turn Intersection Example with Stop-control
Example of RCUT Intersection with stop-control from FHWA’s Restricted Crossing U-Turn Intersection Informational Guide
The DLT intersection, also known as a continuous flow intersection, works mainly by relocating
one or more left turn movements to the other side of the opposing traffic via an interconnected
signalized crossover. This essentially causes the traffic signal system to be more efficient by
eliminating the left turn phase at the main intersection allowing for more green time to be
allocated to other movements. The DLT can reduce delays by up to 40%, but often can be
delivered for just slightly more cost than a typical signalized intersection. Compared with a
conventional intersection, the DLT can be more challenging for pedestrians due to longer
crossing distances and counter-intuitive left turn vehicular movements. However, the DLT
typically has shorter cycle lengths and potentially shorter delays. The DLT intersection design is
best applied in situations where:
There are high left-turn and through volumes.
Intersection is over capacity.
There are excessive delays and queuing, especially when left turn queues extend past
the available storage bays.
Pedestrian volumes are low.
Sufficient right-of-way exists on the leg(s) that need to be widened to accommodate
the new lanes.
Context is urban/suburban.
Exhibit 1300-4 Displaced Left Turn Intersection Example
Example of DLT Intersection from FHWA’s Displaced Left Turn Intersection Informational Guide
It is not appropriate to design for specific modal treatments on the outset of evaluating
intersection control types. However, modally oriented intersection treatments may be
necessary to enhance specific modal baseline or contextual performance needs (see Chapter
1101), and may influence the control type selection. Include a discussion of the potential
modally oriented treatments relevant to the control types being analyzed and modal
performance needs. Evaluate the potential effect of modal specific treatments on all design
users relevant for the control types evaluated in the ICE.
For example, a signalized intersection with a long cycle length, high vehicle speeds, or frequent
permitted turning movements is generally not appropriate for areas with moderate to high
pedestrian demand. However, a roundabout or responsive signal in an urban downtown core
with low speeds is typically well respected with high compliance and short delays.
For signalized intersections, sidewalk and ramp designs have additional requirements to
accommodate the pedestrian features of the traffic signal system (see Chapter 1330).
depending on the proximity of stop locations with respect to the intersection location and origin
of the transit movement (see Chapter 1430 for bus stop placement guidelines), and the type of
transit vehicle (such as a fixed guideway vehicle). Discuss treatment options and any operating
restrictions the transit provider may have regarding different intersection control types.
Intersection control can have an influence on road user behavior and modal operations, not just
at the intersection itself, but also along the corridor or surrounding network, even when the
intersection has an acceptable LOS. Delay affects route and mode choice and sometimes
whether a user will decide to complete the trip. A user’s willingness to accept delay depends on
many factors including the user’s knowledge of the transportation network, anticipated traffic
conditions, and alternative options. The increasing presence of in-vehicle guidance systems and
real-time traffic apps further aids the user in selecting the route with shortest travel times. Also,
some alternatives that may improve mobility for one mode, such as the addition of turn lanes,
may result in a performance degradation or even discourage trips for pedestrians or other
modes. Thus, it is important to consider the effects of intersection control on the surrounding
network and for all potential users. The following are some factors when selecting and
evaluating alternatives:
Access management strategies can be effective in promoting efficient travel patterns
and rerouting traffic to other existing intersections. Check with the WSDOT region
Planning Office for future land use plans or comprehensive plans to provide for future
growth accommodation.
Consider the volume to capacity (V/C) ratio, the delay, and the queue length of each
approach. Some scenarios may require additional sensitivity analysis to determine the
impacts of small changes in volumes.
Examine the effects of existing conditions. Consider progression through nearby
intersections (corridor and network analysis) and known risky or illegal driving
maneuvers.
Consider the possibility that traffic from other intersections with lower LOS will divert
to the new/revised intersection.
1300.05 Procedures
For new intersections: determine and document intersection control according to the
applicable procedures in this chapter.
For existing intersections: An Intersection Control Evaluation (ICE) is required for intersection
improvement projects involving pavement construction and/or reconstruction, or preservation
projects such as signal replacement/rehabilitation. Evaluate intersection control in accordance
with this chapter unless there is documentation that this analysis has already been completed
and is referenced in the Project Summary.
An ICE is not required, but should be considered, for existing intersections that are unaffected
by the project (per the contributing factors analysis) or are receiving minor revisions such as
signal timing changes or rechannelization of existing pavement. Intersection rechannelization
within existing pavement can result in operational and safety performance changes that should
be evaluated within the existing project framework. Consideration should be given to mainline
traffic volume, entering volume, and availability of mainline gaps for additions of left- or right-
turn storage within existing intersection width.
For each alternative, provide a brief description of the assumed layout. Include the number of
lanes on major and minor approaches and any measures necessary to accommodate multi-
modal users. For a roundabout, document the assumed inscribed circle diameter. For a signal,
document the assumed cycle length and phasing strategy used for the analysis.
Step 1: Background and Project Needs – Describe the existing conditions. Include physical
characteristics of the site, posted speed, AADT, turning movement volumes, channelization and
control features, multimodal facilities, context, and modal priority.
Document the project’s baseline and contextual needs and performance metrics and targets
that will be affected by the intersection. These needs, metrics, and targets will be used for
alternative comparison in Step 3. Identify all project alternatives under consideration. For each
alternative, determine if it is expected to meet the basic needs of the project. Remove
alternatives that do not pass the initial screening, and document their removal. All remaining
alternatives are to proceed to Step 2.
Step 2: Feasibility – Develop the alternatives at a sketch level to determine the footprint
required to achieve performance measures. Consider right-of-way, environmental, cost,
context-sensitive/sustainable design, and geometrics/physical constraints for each remaining
alternative. If an alternative is not practicable from any of these perspectives, remove it from
consideration. For documentation purposes, state why alternatives were removed from further
consideration. All remaining alternatives are to proceed to Step 3.
Determine the right of way requirements and feasibility. Discuss the right of way
requirements and the feasibility of acquiring that right of way in the analysis. Include
sketches or plan sheets with sufficient detail to identify topography, existing utilities,
environmental constraints, drainage, buildings, and other fixed objects. An economic
evaluation will be useful if additional right of way is needed. Include the right of way
costs in the alternatives evaluation (Step 4).
Identify known environmental concerns that could influence control type selection. At
this stage, are there any red flags or obvious concerns between potential control
types? Are there any known environmental risks that may substantially increase the
cost of the project or available information that could help in alternatives comparison?
Consult with region Environmental staff for support.
Step 3: Operational and Safety Performance Analysis – Perform and report the results of
applicable analyses for all remaining alternatives and the no-build condition for performance
metrics and targets identified in Step 1. The analysis is scalable, but typically should include the
metrics below. The level of effort should be based on project complexity, cost of proposed
alternatives, context, and impact to the network and other modes. Contact the region Traffic
Office early in the process to determine the network area of influence and scope of analysis.
Include the following:
Traffic Analysis – Use the opening year and selected design year for analysis (see
Chapter 1103). In some cases, it may also be appropriate to analyze the horizon year as
well. Identify and justify any growth rates used and provide turning movements for all
scenarios. There are several deterministic and microsimulation tools for analyzing delay
and intersection performance. Traffic volumes and the proximity to other access points
will dictate the modeling effort required. Contact the region Traffic Office to determine
the appropriate approved tool(s). For more information and guidance on traffic
analysis, refer to Chapter 320 and the Traffic Analysis webpage
(http://www.wsdot.wa.gov/Design/Traffic/Analysis/).
Peak hour(s) – Report the delay for each alternative.
Off-Peak – Report the delay for an additional time period representative of
off-peak travel. Depending on location, up to 80% of total delay can occur in
off-peak hours.
If a traffic signal is under consideration, perform and report the findings of the
signal warrant analysis.
Safety Performance Analysis – See the Safety Analysis Guide for ICE safety analysis
procedures.
Multimodal safety and operations – Briefly discuss how the design for each alternative
is expected to affect applicable multimodal users. Potential items to consider include
pedestrian delay, number of lanes to cross, protected vs permitted turning
movements, motorist approach speed, speed differential of users, etc. When
applicable, evaluate multimodal treatments that may be necessary for each alternative
to meet the performance needs of each user type.
Step 4: Alternatives Evaluation – Compare the alternatives based on their ability to address the
baseline and contextual needs using the established performance metrics and targets. When
applicable, report the Benefit/Cost (B/C) for mobility (due to change in travel time or delay)
and/or the B/C for safety (due to change in crash frequency/severity). The B/C analysis may
include the following:
Estimated project costs. May use project costs from similar locations of the alternative
as cost justification.
A qualitative discussion of life cycle cost using the following considerations:
Annual maintenance and operations cost. For signals, this should include the
cost of signal engineers and technicians to review and implement signal
timings and respond to malfunctions and emerging issues. This value can be
obtained from the region Traffic Office.
Travel time savings in all hours of the day.
Societal cost savings (considered as the Benefit in the analysis) of reduced crash
frequency and/or severity using a predictive method as described in Chapter 321 and
the Safety Analysis Guide. See the Safety Analysis Guide for WSDOT Societal Costs for
crash severities.
Salvage value of right of way, grading and drainage, and structures.
Step 5: Selection – Based on performance tradeoffs and documented project needs, select the
recommended alternative.
Discuss the following in the ICE as needed to further support the selection (is it an item that will
have a significant effect on the decision?):
Review the corridor sketch plans and database with the regional planning office.
Information from a corridor or planning study.
Current and future land use and whether or not the intersection control will reasonably
accommodate future land use traffic changes.
Community engagement and local agency coordination and comments.
Effect on future local agency projects.
Other elements considered in the selection of the intersection control.
There is often concern from communities regarding control types that may be under
consideration, especially the types of intersections that may seem unfamiliar or that break from
the traditional approach. Education and outreach efforts, if necessary, are collaborative and are
most useful during the analysis and early scoping stages.
1300.05(3) Approval
The ICE shall be prepared by or under the direct supervision of a licensed Professional Engineer.
Approval of the ICE (see Chapter 300 for more information) requires the following:
Region Traffic Engineer Approval
HQ Traffic Approval
1300.06 Documentation
Refer to Chapter 300 for additional design documentation requirements.
1300.07 References
Washington Administrative Code (WAC) 468-52, Highway access management – access control
classification system and standards
Secretary’s Executive Order: E 1082, Business Practices for Moving Washington, August 2012,
WSDOT
Highway Capacity Manual (HCM), latest edition, Transportation Research Board, National
Research Council
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
A Comparison of a Roundabout to Two-way Stop Controlled Intersections with Low and High
Traffic Volumes, Luttrell, Greg, Eugene R. Russell, and Margaret Rys, Kansas State University
Guidance for Implementation of the AASHTO Strategic Highway Safety Plan, Volume 5: A Guide
for Addressing Unsignalized Intersection Collisions, NCHRP Report 500, Transportation Research
Board, 2003
Guidance for Implementation of the AASHTO Strategic Highway Safety Plan Volume 12: A Guide
for Reducing Collisions at Signalized Intersections, NCHRP Report 500, Transportation Research
Board, 2004
Synthesis of the Median U-Turn Intersection Treatment, Safety, and Operational Benefits,
FHWA-HRT-07-033, USDOT, FHWA
Roundabouts and Sustainable Design, Ariniello et al., Green Streets and Highways – ASCE, 2011
1310.01 General
Intersections are a critical part of Washington State Department of Transportation (WSDOT)
highway design because of increased conflict potential. Traffic and driver characteristics, bicycle
and pedestrian needs, physical features, and economics are considered during the scoping and
design stages to develop channelization and traffic control to provide multimodal traffic flow
through intersections.
See chapters in the 1100 series for instruction on multimodal practical design, including
identifying project needs, context, design controls, modal performance, alternatives analysis,
and design element dimensioning.
This chapter provides guidance for designing intersections, including ramp terminals. Refer to
the following chapters for additional information:
Chapter Subject
1103 Design controls
1320 Roundabouts
1340 Driveways
1360 Interchanges
For assistance with intersection design, contact the Headquarters (HQ) Design Office.
In addition to reducing the number of conflicts, minimize the conflict area as much as possible
while still providing for the design vehicle (see Chapter 1103). This is done to control the speed
of turning vehicles and reduce the area of exposure for vehicles, bicycles, and pedestrians. For
additional information on pedestrian needs, see Chapter 1510. For intersections with shared-
use paths, see Chapter 1515. For bicycle considerations at intersections, see Chapter 1520.
When feasible, locate intersections such that curves do not begin or end within the intersection
area. It is desirable to locate the PC and PT 250 feet or more from the intersection so that a
driver can settle into the curve before the gap in the striping for the intersection area. Do not
locate short curves where both the PC and PT are within the intersection area.
6 ft max
offset Posted Speed Taper Rate
allowed
55 mph 55:1
See table for lane
alignment taper rate. 50 mph 50:1
45 mph 45:1
40 mph 27:1
35 mph 21:1
30 mph 15:1
25 mph 11:1
As a minimum, provide enough space between intersections for left-turn lanes and storage
length. Space signalized intersections and intersections expected to be signalized to maintain
efficient signal operation. Space intersections so that queues will not block an adjacent
intersection.
Evaluate existing intersections that are spaced less than shown in Chapters 530 and 540. Also,
evaluate closing or restricting movements at intersections with operational issues. Document
the spacing of existing intersections that will remain in place and the effects of the spacing on
operation, capacity, and circulation.
There are competing design objectives when considering the crossing needs of pedestrians and
the turning needs of larger vehicles. To design for large design vehicles, larger turn radii are
used. This results in increased pavement areas, longer pedestrian crossing distances, and longer
traffic signal arms. (See Chapter 1103 for design vehicle selection criteria.)
When appropriate, to reduce the intersection area, consider accommodating for large vehicles
instead of designing for them. This reduces the potential for vehicle/pedestrian conflicts,
decreases pedestrian crossing distance, and controls the speeds of turning vehicles. Use turn
simulation software (such as AutoTURN®) to verify the design.
1310.02(7) Crossroads
When the crossroad is a city street or county road, design the crossroad beyond the intersection
area in cooperation with the local agency.
When the crossroad is a state facility, design the crossroad according to the Design Manual.
Continue the cross slope of the through roadway shoulder as the grade for the crossroad. Use a
vertical curve that is at least 60 feet long to connect to the grade of the crossroad.
Evaluate the profile of the crossroad in the intersection area. The crown slope of the main line
might need to be adjusted in the intersection area to improve the profile for the cross traffic.
Design the grade at the crosswalk to meet the requirements for accessibility. (See Chapter 1510
for additional crosswalk information.)
In areas that experience accumulations of snow and ice for all legs that require traffic to stop,
design a maximum grade of ±4% for a length equal to the anticipated queue length for stopped
vehicles.
Where stop control or signal control is implemented, the intersection configuration criteria for
ramp terminals are normally the same as for other intersections. One exception is that an angle
point is allowed between an off-ramp and an on-ramp. This is because the through movement
of traffic getting off the freeway, going through the intersection, and getting back on the
freeway is minor.
Another exception is at ramp terminals where the through movement is eliminated (for
example, at a single-point interchange). For ramp terminals that have two wye connections, one
for right turns and the other for left turns, and no through movement, the intersection angle has
little meaning and does not need to be considered.
Due to the probable development of large traffic generators adjacent to an interchange, width
for a median on the local road is desirable whenever such development is expected. This allows
for future left-turn channelization. Use median channelization when justified by capacity
determination and analysis or by the need to provide a smooth traffic flow.
Adjust the alignment of the intersection legs to fit the traffic movements and to discourage
wrong-way movements. Use the allowed intersecting angles of 60° to 120° in designing the best
alignment for efficiency and intersection operations.
[1]
60º-120º
Angular corners to
discourage wrong- CL ramp Taper Rates [3]
way right turns.
Notes:
[1] For right-turn corner design, see Exhibit 1310-6.
[2] Use turn simulation software to verify that the design vehicle can make the turn.
[3] For taper rates, see Exhibit 1310-10a, Table 1.
Signing can be a more effective countermeasure when the signs are lowered. At night,
lowered signs are better illuminated by low-beam headlights. Other improvements may
include a second set of signs, supplemental sign placards, oversized signs, flashing beacons,
internal illumination, overhead-mounted signs, red reflective tape on the back of signs,
extra overhead lighting, and red-backed guideposts on each side of the ramp up to the
WRONG WAY sign.
1310.02(10)(a)(2) Intelligent Transportation Systems (ITS)
Wrong-way ITS countermeasures are wrong-way detection and warning systems. Contact
the region Traffic Office for assistance when considering an ITS wrong-way warning system.
1310.02(10)(a)(3) Geometric Design
Consider the separation of on- and off-ramp terminals, particularly at interchanges where
the ramp terminals are closely spaced (for example, partial cloverleaf ramps combined with
other ramps). Wider medians between off- and on-ramp terminals provide room for signing
and allow the median end to be shaped to help direct vehicles onto the correct roadway.
The minimum width of the raised median is 7 feet, face of curb to face of curb, to
accommodate a 36 inch sign.
Extend the raised median on a two-way ramp from the ramp terminal intersection to the
split of the on- and off-ramps. The median outside of the intersection area may be reduced
to the width of a dual-faced mountable curb. (See Exhibit 1310-3 for an example of the
minimum median at the terminal of a two-way ramp.)
Raised median
Minimum raised
median width is
sign width plus 4 ft
Pavement marking
extensions
(see the MUTCD)
Reducing the width of the off-ramp throat has been a successful method of discouraging
wrong-way movements. A smaller opening makes the wrong-way entry less inviting,
particularly for closely spaced ramps. When off-ramp terminals have right-turn lanes, a
raised island will reduce the potential for a wrong-way movement.
Increasing the width of the on-ramp throat can encourage right-way movements. A larger
opening for the on-ramp makes it easier to turn into. To increase the throat width of on-
ramps, use flat radii for left- and right-turning traffic and remove islands.
d. Intersection Balance
When drivers make a left turn, they are required to leave the intersection in the extreme
left-hand lane lawfully available. As a result, left-turning drivers tend to head for a point
between 50% and 60% of the way through the intersection.
At a two-way ramp terminal, the desirable throat width for the on-ramp roadway is not less
than the off-ramp roadway width to accommodate this behavior (see Exhibit 1310-4). Much
of this can be achieved by adjusting the stop bar position on the interchange cross street.
60% L max
e. Visibility
When drivers can see and recognize the roadway they want to turn onto, they are less likely
to make a mistake and turn onto the wrong roadway. For two-way ramps and divided
multilane roadways with barrier in the median, end the barrier far enough from the
intersection that a left-turning driver can see and recognize the roadway going the correct
direction. Drivers need to see the delineation pavement markings, curbs, or other elements
to locate the correct roadway.
Angular corners on the left side of off-ramp terminals will discourage wrong-way right turns.
Provide a corner design as angular as feasible that will provide for the left turn from the off-
ramp. Circular curves can look inviting for a wrong-way right turn onto the off-ramp (see
Exhibit 1310-2).
1310.02(10)(b) Countermeasure Applications
Following are applications of wrong-way countermeasures for some common locations. For
assistance with signing and delineation, contact the region Traffic Office.
1310.02(10)(b)(1) All Ramps
Countermeasures that can be used on almost any ramp or intersection with potential
wrong-way concerns include:
• Enlarged warning signs.
• Directional pavement arrows at ramp terminals.
• Redundant signing and pavement arrows.
• Roundabout ramp terminal intersections, where room is available.
• Red-backed RPMs.
1310.02(10)(b)(2) One-Way Diamond Off-Ramp
Diamond interchanges are common, and although drivers are familiar with them, they can
still get confused and go the wrong way. In addition to signing and pavement markings for
these interchanges, provide:
• Angular corners to discourage wrong-way right turns.
1310.02(10)(b)(3) Diamond Interchange With Advance Storage
Diamond interchanges with advance storage have left-turn storage lanes that extend from
the on-ramp past the off-ramp (see Exhibit 1310-5). This allows for a potential early left turn
onto the off-ramp. Following are additional countermeasures for interchanges with
advanced left-turn storage:
• Provide a raised median to discourage the wrong-way left turn.
• Provide signing and directional arrows to direct traffic to the correct left-turn
point.
Provide raised
median island.
Two-way ramps have the on- and off-ramp adjacent to each other. They are used at partial
cloverleaf, trumpet, and button hook interchanges. Because the on and off roadways are
close to each other, they are more vulnerable to wrong-way driving. Also, when the
separation between on and off traffic is striping only, the ramps are susceptible to drivers
entering the correct roadway and inadvertently crossing to the wrong ramp. In addition to
signing and delineation, the following are countermeasures for two-way ramps:
• Separate the on- and off-ramp terminals.
• Reduce off-ramp terminal throat width.
• Increase on-ramp terminal throat width.
• Maintain intersection balance.
• Improve on-ramp visibility.
• Provide a raised median or dual-faced curb from the ramp terminal
intersection to the gore nose.
1310.02(10)(b)(5) HOV Direct Access Ramps
HOV direct access ramps are two-way ramps in the median; therefore, the ability to provide
separation between the on and off traffic is limited by the width of the median. An
additional concern is that HOV direct access ramps are left-side ramps. Drivers normally
enter the freeway using a right-side ramp and they may mistakenly travel the wrong way on
a left-side ramp. Review existing and proposed signing for inadvertent misdirection. (See
Chapter 1420 for HOV direct access and countermeasures for wrong-way driving at HOV
direct access ramps.)
Wrong-way driving can also occur on multilane divided nonfreeway facilities. Wrong-way
drivers may enter multilane divided facilities at driveways and at-grade intersections.
Countermeasures for wrong-way driving on nonfreeway multilane divided highways include:
• Wrong-way signing and delineation at the intersections.
• Right-in/right-out road approaches.
If pedestrian facilities are present, the design objective becomes one of reducing the potential
for vehicle/pedestrian conflicts. This is done by minimizing pedestrian crossing distances and
controlling the speeds of turning vehicles. Pedestrian refuge islands can be beneficial. They
minimize the pedestrian crossing distance, reduce the conflict area, and minimize the impacts
on vehicular traffic. When designing islands, speeds can be reduced by designing the turning
roadway with a taper or large radius curve at the beginning of the turn and a small radius curve
at the end. This allows larger islands while forcing the turning traffic to slow down. Use turn
simulation software (such as AutoTURN®) to verify the design.
Depending on the context of the roadway and right-turn corner (and whether the right-turn
corner will be designed for or will accommodate a design vehicle), there may be several design
considerations. Consider vehicle-pedestrian conflicts; vehicle encroachment on the shoulder or
adjacent same-direction lane at the exit leg; capacity restrictions for right-turning vehicles or
other degradation of intersection operations; and the effects on other traffic movements.
Other design considerations may include a combination of simple or compound curves, tapers at
the beginning or end of the turn, and so on. Verify the design vehicle can make the turn using
turn simulation software (such as AutoTURN®).
through traffic lanes. Provide a minimum storage length of 100 feet for one-way left-turn lanes.
When evaluating left-turn lanes, include impacts to all intersection movements and users.
At signalized intersections, use a traffic signal analysis to determine whether a left-turn lane is
needed and the storage length. If the length determined is less than the 100-foot minimum,
make it 100 feet (see Chapter 1330).
A traffic analysis based on the Highway Capacity Manual (HCM) may also be used to determine
whether left-turn lanes are needed to maintain the desired level of service.
900
800
Total DHV*
700
2
1
600
2
1
40 m
500 ph*
*
2
1 50 m
ph**
400
60 mp
h* *
300
0 5 10 15 20 25
1,600
1,400
Opposing Through Volume (DDHV)
1,200
1,000
800
600
S=
Storage not needed
30
0f
400 t
S=
S=
S=
S=
20
25
10
15
0
0
0f
ft
ft
ft
t
200
0
0 50 100 150 200 250 300 350 400 450 500
Left-Turning Volume (DHV)
Determine the storage length on two-lane highways by using Exhibits 1310-8a through 8c. On
four-lane highways, use Exhibit 1310-7b. These lengths do not consider trucks. Use Exhibit
1310-9 for storage length when trucks are present.
Use turn simulation software (such as AutoTURN®) to verify that left-turn movements for the
design vehicle(s) do not have conflicts. Design opposing left-turn design vehicle paths with a
minimum 4-foot (12-foot desirable) clearance between opposing turning paths.
Where one-way left-turn channelization with curbing is to be provided, evaluate surface water
runoff and design additional drainage facilities if needed to control the runoff.
Provide illumination at left-turn lanes in accordance with the guidelines in Chapter 1040.
1300 250 ft
1200
200 ft
DHV (Total, Both Directions)
1100
1000
900
150 ft
800
700 100 ft
600
0 100 200 300
1300
250 ft
1200
DHV (Total, Both Directions)
1100
200 ft
1000
900
800
150 ft
700
100 ft
600
500
0 100 200 300
1300
250 ft
1200
DHV (Total, Both Directions)
1100
200 ft
1000
900
800
150 ft
700
100 ft
600
500
0 100 200 300
At signalized intersections with high left-turn volumes, double (or triple) left-turn lanes may be
needed to maintain the desired level of service. For a double left-turn, a throat width of 30 to 36
feet is desirable on the exit leg of the turn to offset vehicle offtracking and the difficulty of two
vehicles turning abreast. Use turn simulation software (such as AutoTURN®) to verify that the
design vehicle can complete the turn. Where the design vehicle is a WB 40 or larger, it is
desirable to provide for the design vehicle in the outside lane and an SU-30 vehicle turning
abreast rather than two design vehicles turning abreast.
Exhibits 1310-10a through 10f show left-turn lane geometrics, which are described as follows:
1310.03(2)(a)(1) Widening
It is desirable that offsets and pavement widening (see Exhibit 1310-10a) be symmetrical
about the centerline or baseline. Where right of way or topographic restrictions, crossroad
alignments, or other circumstances preclude symmetrical widening, pavement widening
may be on one side only.
1310.03(2)(a)(2) Divided Highways
Widening is not needed for left-turn lane channelization where medians are 11 feet wide or
wider (see Exhibits 1310-10b through 10d). For medians between 13 feet and 23 feet or
where the acceleration lane is not provided, it is desirable to design the left-turn lane
adjacent to the opposing lane (see Exhibit 1310-10b) to improve sight distance and increase
opposing left-turn clearances.
A median acceleration lane (see Exhibits 1310-10c and 10d) may be provided where the
median is 23 feet or wider. The median acceleration lane might not be needed at a
signalized intersection. When a median acceleration lane is to be used, design it in
accordance with 1310.03(4), Speed Change Lanes. Where medians have sufficient width,
provide a 2-foot shoulder adjacent to a left-turn lane.
1310.03(2)(a)(3) Minimum Protected Left Turn With a Median
At intersections on divided highways where channelized left-turn lanes are not provided,
provide the minimum protected storage area (see Exhibit 1310-10e).
The left-turn lane designs discussed above and given in Exhibits 1310-10a through 10e may
be modified when determined by design element dimensioning (see Chapter 1106.)
Document the benefits and impacts of the modified design, including changes to vehicle-
pedestrian conflicts; vehicle encroachment; deceleration length; capacity restrictions for
turning vehicles or other degradation of intersection operations; and the effects on other
traffic movements. Provide a modified design that is able to accommodate the design
vehicle, and provide for the striping (see the Standard Plans and the MUTCD). Verify the
design vehicle can make the turn using turn simulation software (such as AutoTURN®);
include a plot of the design and verification.
Left-turn storage
100 ft min [2] 50 ft
Taper length = T1 X taper rate [5]
T1[1][7]
T2 [1][7]
Deceleration
100 ft min 50 ft taper [6]
Left-turn storage [2]
15
1
[1] 13 ft [7]
[5]
[3]
[4]
Notes:
[1] Where curb is provided, add the width of the curb and the shoulders. For shoulder widths
at curbs, see 1310.03(6) and Chapter 1230.
[2] For left-turn storage length, see Exhibits 1310-7b for 4-lane roadways or 1310-8a through 8c for
2-lane roadways.
[3] Verify the design vehicle can make the turn using turn simulation software (such as AutoTURN®).
[4] For right-turn corner design, see Exhibit 1310-6.
[5] For median widths greater than 13 ft, it is desirable to locate the left-turn lane adjacent to the
opposing through lane with excess median width between the same-direction through lane and the
turn lane.
[6] For increased storage capacity, the left-turn deceleration taper alternate design may be used.
[7] Reduce to lane width for medians less than 13 ft wide.
General:
For pavement marking details, see the Standard Plans and the MUTCD.
15
1
11 ft min [1]
12 ft min
Notes:
[1] For left-turn storage length, see Exhibits 1310-7b for 4-lane roadways or 1310-8a through 8c for 2
lane roadways.
[2] Verify the design vehicle can make the turn using turn simulation software (such as AutoTURN®).
[3] For right-turn corner design, see Exhibit 1310-6.
[4] The minimum length of the median acceleration lane is shown in Exhibit 1310-14.
[5] For acceleration taper rate, see the Table on Exhibit 1310-10c.
[6] The desirable length of the left-turn deceleration lane including taper is shown in Exhibit 1310-13.
General:
For pavement marking details, see the Standard Plans and the MUTCD.
15 ft min
15
1
[3]
2 ft min
[2]
[1]
Notes:
[1] Verify the design vehicle can make the turn using turn simulation software (such as AutoTURN®).
[2] For right-turn corner design, see Exhibit 1310-6.
[3] For median width 17 ft or more. For median width less than 17 ft, widen to 17 ft. or use Exhibit 1310-
10b.
General:
For pavement marking details, see the Standard Plans and the MUTCD.
Use TWLTLs only on managed access highways where there are no more than two through lanes
in each direction. Evaluate installation of TWLTLs where:
• A crash study indicates reduced crashes with a TWLTL.
• There are existing closely spaced access points or minor street intersections.
• There are unacceptable through traffic delays or capacity reductions because of left-
turning vehicles.
TWLTLs can reduce delays to through traffic, reduce rear-end crashes, and provide separation
between opposing lanes of traffic. However, they do not provide refuge for pedestrians and can
encourage strip development with additional closely spaced access points. Evaluate other
alternatives (such as prohibiting midblock left turns and providing for U-turns) before using a
TWLTL. (See Chapter 540 for additional restrictions on the use of TWLTLs, and Chapter 1230 for
discussion of road diets, which commonly employ a center turn lane.)
The basic design for a TWLTL is illustrated in Exhibit 1310-10f. Additional criteria are as follows:
• The desirable length of a TWLTL is not less than 250 feet.
• Provide illumination in accordance with the guidelines in Chapter 1040.
• Pavement markings, signs, and other traffic control devices must be in accordance
with the MUTCD and the Standard Plans.
• Provide clear channelization when changing from TWLTLs to one-way left-turn lanes
at an intersection.
Major
cross street
100 ft min
Left-turn storage
Match line
[1] 13 ft desirable
11 ft min
[2]
Posted speed < 50 mph = 390 ft min
Posted speed ≥ 50 mph = 420 ft min
Match line
Minor
cross street
Notes:
[1] Verify the design vehicle can make the turn using turn simulation software (such as AutoTURN®).
[2] For right-turn corner design, see Exhibit 1310-6.
General:
For pavement marking details and signing criteria, see the Standard Plans and the MUTCD.
100
Consider right-turn
pocket or taper [4]
60
40
20
0
0 100 200 300 400 500 600 700
Peak Hour Approach Volume (DDHV) [1]
Notes:
[1] For two-lane highways, use the peak hour DDHV (through + right-turn).
For multilane, high-speed highways (posted speed 45 mph or above), use the right-lane peak
hour approach volume (through + right-turn).
[2] When all three of the following conditions are met, reduce the right-turn DDHV by 20:
• The posted speed is 45 mph or below
• The right-turn volume is greater than 40 VPH
• The peak hour approach volume (DDHV) is less than 300 VPH
[3] For right-turn corner design, see Exhibit 1310-6.
[4] For right-turn pocket or taper design, see Exhibit 1310-12.
[5] For right-turn lane design, see Exhibit 1310-13.
11 ft min
Right-Turn Pocket
See Exhibit
1310-6 for right-
turn corner
design
100 ft
13 ft
Right-Turn Taper
Below 40 mph 40 ft
When either deceleration or acceleration lanes are to be used, design them in accordance with
Exhibits 1310-13 and 1310-14. When the design speed of the turning traffic is greater than
20 mph, design the speed change lane as a ramp in accordance with Chapter 1360. When a
deceleration lane is used with a left-turn lane, add the deceleration length to the storage length.
A dedicated deceleration lane (see Exhibit 1310-13) is advantageous because it removes slowing
vehicles from the through lane.
An acceleration lane (see Exhibit 1310-14) is not as advantageous because entering drivers can
wait for an opportunity to merge without disrupting through traffic. However, acceleration lanes
for left-turning vehicles provide a benefit by allowing the turn to be made in two movements.
55 515 3% to less
0.9 1.2
than 5%
60 605
5% or more 0.8 1.35
65 715
70 820 Adjustment Multiplier for Grades
3% or Greater
Minimum Deceleration Lane Length (ft)
Notes:
[1] When adjusting for grade, do not reduce the deceleration lane to less than 150 ft.
[2] For right-turn corner design, see Exhibit 1310-6.
[3] See 1310.03(6) and Chapter 1230.
General:
For pavement marking details, see the Standard Plans and the MUTCD.
[4]
Notes:
[1] At free right turns (no stop required) and all left turns, the minimum acceleration lane length is
not less than 300 ft.
General:
For pavement-marking details, see the Standard Plans and the MUTCD.
When a lane is dropped beyond signalized intersections, provide a lane of sufficient length to
allow smooth merging. For facilities with a posted speed of 45 mph or higher, use a minimum
length of 1,500 feet. For facilities with a posted speed lower than 45 mph, provide a lane of
sufficient length that the advanced lane reduction warning sign can be placed not less than 100
feet beyond the intersection area.
When a lane is dropped beyond unsignalized intersections, provide a lane beyond the
intersection not less than the acceleration lane length from Exhibit 1310-14.
1310.03(6) Shoulders
Shoulder width is controlled by its intended functional use and its contribution to achieving the
desired safety performance when balanced with other design elements. See Exhibit 1239-2 for
functional uses and recommended shoulder widths.
Reducing the shoulder width at intersections facilitates the installation of turn lanes without
unduly affecting the overall width of the roadway. A narrower roadway also reduces pedestrian
exposure in crosswalks and discourages motorists from using the shoulder to bypass other
turning traffic.
1310.03(7) Islands
An island is a defined area within an intersection between traffic lanes for the separation of
vehicle movements or for pedestrian refuge. Within an intersection, a median is considered an
island. Design islands to clearly delineate the traffic channels to drivers and pedestrians.
Channelization islands are normally triangular. In rural areas, 75 ft2 is the minimum island area
and 100 ft2 is desirable. In urban areas where posted speeds are 25 mph or below, smaller
islands are acceptable. Use islands with at least 200 ft2 if pedestrians will be crossing or traffic
control devices or luminaires will be installed.
Design triangular-shaped islands as shown in Exhibits 1310-15a through 15c. The shoulder and
offset widths illustrated are for islands with vertical curbs 6 inches or higher. Where painted
islands are used, such as in rural areas, these widths are desirable but may be omitted. (See
Chapter 1240 for desirable turning roadway widths.)
Provide barrier-free access at crosswalk locations where raised islands are used. For pedestrian
refuge islands and barrier-free access requirements, see Chapter 1510.
1310.03(7)(b) Location
Design the approach ends of islands so they are visible to motorists. Position the island so that a
smooth transition in vehicle speed and direction is attained. Begin transverse lane shifts far
enough in advance of the intersection to allow gradual transitions. Avoid introducing islands on
a horizontal or vertical curve. If the use of an island on a curve cannot be avoided, provide sight
distance, illumination, or extension of the island.
[3]
[4]
[1] Widen shoulders when right-turn radii or roadway width cannot be provided for large trucks. Design
widened shoulder pavement the same depth as the right-turn lane.
[2] Use turn simulation software (such as AutoTURN®) for the intersection design vehicle
[3] For turning roadway widths, see Chapter 1240.
[4] For additional details on island placement, see Exhibit 1310-15c.
[5] Small traffic islands have an area of 100 ft2 or less; large traffic islands have an area greater than 100
ft2.
General:
• Provide an accessible route for pedestrians (see Chapter 1510).
• 60° to 90° angle at stop or yield control.
• For right-turn corner design, see Exhibit 1310-6.
[4]
[2][3]
Notes:
[1] Widen shoulders when right-turn radii and roadway width
280 ft radius min cannot be provided for large trucks. Design widened shoulder
pavement the same depth as the right-turn lane.
[2] Use the truck turn simulation software (such as AutoTURN®)
for the intersection design vehicle.
[3] For turning roadway widths, see Chapter 1240.
[4] For right-turn corner design, see Exhibit 1310-6.
General:
Provide an accessible route for pedestrians (see Chapter 1510).
For additional details on island placement, see Exhibit 1310-15c.
1310.03(7)(d) Curbing
Provide vertical curb 6 inches or higher for:
• Islands with luminaires, signals, or other traffic control devices.
• Pedestrian refuge islands.
Also consider curbing for:
• Divisional and channelizing islands.
• Landscaped islands.
• Stormwater conveyance.
In general, except to meet one of the uses listed above, it is desirable not to use curbs on
facilities with a posted speed of 45 mph or above.
Avoid using curbs if the same objective can be attained with pavement markings.
Refer to Chapter 1230 for additional information and design criteria on the use of curbs.
R =1.5 ft
e
lan
1 ft min
rn
t-tu
gh
Ri
R=2.5 ft
R=1.5 ft
1 ft min
lane
1 ft offset min
n
t-tur
Shoulder
Righ
width [1]
R=2.5 ft
R=2.5 ft
2 ft offset min
1310.03(8) U-Turns
For divided multilane highways without full access control that have access points where the
median prevents left turns, evaluate the demand for locations that allow U turns. Normally, U
turn opportunities are provided at intersections. However, where intersections are spaced far
apart, U-turn median openings may be provided between intersections to accommodate U-
turns. Use the desirable U-turn spacing (see Exhibit 1310-16) as a guide to determine when to
provide U-turn median openings between intersections. Where the U-turning volumes are low,
longer spacing may be used.
Locate U-turn median openings where intersection sight distance can be provided.
When designing U-turn median openings, use Exhibit 1310-18 as a guide. Where the median is
less than 40 feet wide, with a large design vehicle, provide a U-turn roadway (see Exhibit 1310-
17). Design A, with the U-turn roadway after the left-turn, is desirable. Use Design A when the
median can accommodate a left-turn lane. Use Design B only where left-turn channelization
cannot be built in the median.
On-connection*
Design A
Off-connection*
Design B
Document the need for U-turn locations, the spacing used, and the selected design vehicle. If
the design vehicle is smaller than the largest vehicle using the facility, provide an alternate
route.
U-turns at signal-controlled intersections do not need the acceleration lanes shown in Exhibit
1310-18. For new U-turn locations at signal-controlled intersections, evaluate conflicts between
right-turning vehicles from side streets and U-turning vehicles. Warning signs on the cross street
might be appropriate.
[2]
W
300 ft Acceleration length [1]
F2
[3] T
R
W
[3] T
F1 L
Vehicle W R L F1 F2 T
P 52 14 14 12 12 —
SU-30 87 30 20 13 15 10:1
CITY-BUS 87 28 23 14 18 10:1
WB-40 84 25 27 15 20 6:1
WB-67 94 22 49 15 35 6:1
U-Turn Design Dimensions
Notes:
[1] The minimum length of the acceleration lane is shown in Exhibit 1310-14. Acceleration lane may be
eliminated at signal-controlled intersections.
[2] When U-turn uses the shoulder, provide shoulder width sufficient for the intersection design vehicle
to make the turn and shoulder pavement designed to the same depth as the through lanes for the
acceleration length and taper.
[3] Lane width as determined by Chapters 1106 and 1230.
General: All dimensions are in feet.
The driver of a vehicle that is stopped and waiting to cross or enter a through roadway needs
obstruction-free sight triangles in order to see enough of the through roadway to complete all
legal maneuvers before an approaching vehicle on the through roadway can reach the
intersection. Use Exhibit 1310-19a to determine minimum intersection sight distance along the
through roadway.
The sight triangle is determined as shown in Exhibit 1310-19b. Within the sight triangle, lay back
the cut slopes and remove, lower, or move hedges, trees, signs, utility poles, signal poles, and
anything else large enough to be a sight obstruction. Eliminate parking to remove obstructions
to sight distance. In order to maintain the sight distance, the sight triangle must be within the
right of way or a state maintenance easement (see Chapter 510).
The setback distance for the sight triangle is 18 feet from the edge of traveled way. This is for a
vehicle stopped 10 feet from the edge of traveled way. The driver is almost always 8 feet or less
from the front of the vehicle; therefore, 8 feet are added to the setback. When the stop bar is
placed more than 10 feet from the edge of traveled way, providing the sight triangle to a point 8
feet back of the stop bar is desirable.
Provide a clear sight triangle for a P vehicle at all intersections. In addition, provide a clear sight
triangle for the SU-30 vehicle for rural highway conditions. If there is significant combination
truck traffic, use the WB-67 rather than the SU-30. In areas where SU-30 or WB vehicles are
minimal and right of way restrictions limit sight triangle clearing, only the P vehicle sight
distance needs to be provided.
At existing intersections, when sight obstructions within the sight triangle cannot be removed
due to limited right of way, the intersection sight distance may be modified. Drivers who do not
have the desired sight distance creep out until the sight distance is available; therefore, the
setback may be reduced to 10 feet. Document the right of way width and provide a brief
analysis of the intersection sight distance clarifying the reasons for reduction. Verify and
document that there is no identified crash trend at the intersection. Document the intersection
location and the available sight distance as a Design Analysis.
If the intersection sight distance cannot be provided using the reductions in the preceding
paragraph, where stopping sight distance is provided for the major roadway, the intersection
sight distance, at the 10-foot setback point, may be reduced to the stopping sight distance for
the major roadway, with a Design Analysis and HQ Design Office review and concurrence. (See
Chapter 1260 for required stopping sight distance.) Document the right of way width and
provide a brief analysis of the intersection sight distance clarifying the reasons for reduction.
Verify and document that there is no identified crash trend at the intersection. Document the
intersection location and the available sight distance as a Design Analysis.
In some instances, intersection sight distance is provided at the time of construction, but
subsequent vegetative growth has degraded the sight distance available. The growth may be
seasonal or occur over time. In these instances, intersection sight distance can be restored
through the periodically scheduled maintenance of vegetation in the sight triangle within the
WSDOT right of way or state maintenance easement.
At intersections controlled by traffic signals, provide sight distance for right-turning vehicles. For
intersections controlled by the geometry of roundabouts, see Chapter 1320.
Designs for movements that cross divided highways are influenced by median widths. If the
median is wide enough to store the design vehicle, with a 3-foot clearance at both ends of the
vehicle, sight distances are determined in two steps. The first step is for crossing from a stopped
position to the median storage. The second step is for the movement, either across or left into
the through roadway.
Design sight distance for ramp terminals as at-grade intersections with only left- and right-
turning movements. An added element at ramp terminals is the grade separation structure.
Exhibit 1310-19b gives the sight distance guidance in the vicinity of a structure. In addition,
when the crossroad is an undercrossing, check the sight distance under the structure graphically
using a truck eye height of 6 feet and an object height of 1.5 feet.
Document a brief description of the intersection area, sight distance restrictions, and traffic
characteristics to support the design vehicle and sight distances chosen.
Sight Line
V
V
(A) Si
X
n
X
8 ft See Detail A 18 ft
Sight obstruction
Detail A
Line of sight
(B)
8 ft
See Detail B
n b
X
b
Line of sight
18 ft Sight obstruction
X Detail B
Si
(C)
L Line of sight
Si
A
Curb, sidewalk, or
See Detail C other low sight HC
H1 obstruction Detail C
H2 Line of sight
For sight obstruction driver cannot see over: For crest vertical curve over a low sight
Si
26 b X obstruction when S<L:
18 b n
Si
100 L 2H 1 HC 2H 2 HC 2
A
Where:
Si = Available intersection sight distance (ft)
n = Offset from sight obstruction to edge of AS i2
L
lane (ft)
b = Distance from near edge of traveled way
100 2H 1 HC 2H 2 HC 2
Painted or plastic pavement markings are normally used to delineate travel paths. For pavement
marking details, see the MUTCD, Chapter 1030, and the Standard Plans.
Contact the region or HQ Traffic Office for additional information when designing signing and
pavement markings.
1310.06 Procedures
Document design decisions and conclusions in accordance with Chapter 300. For highways with
limited access control, see Chapter 530.
1310.06(1) Approval
An intersection is approved in accordance with Chapter 300. Complete the following items, as
needed, before intersection approval:
• Intersection Control Type Approval (see Chapter 1300)
• Design Analyses approved in accordance with Chapter 300
• Approved Traffic Signal Permit (DOT Form 242-014 EF) (see Chapter 1330)
For information to be included on the intersection plan for approval, see the Intersection/
Channelization Plan for Approval Checklist on the following website:
www.wsdot.wa.gov/design/projectdev/
The project initiator submits an intersection plan and the documentation of design decisions
that led to the plan to the region for approval. For those plans requiring a Design Analysis, the
Design Analysis must be approved in accordance with Chapter 300 prior to approval of the plan.
After the plan approval, the region prepares a construction agreement with the project initiator
(see the Utilities Manual).
1310.07 Documentation
Refer to Chapter 300 for design documentation requirements.
1310.08 References
1310.08(1) Federal/State Laws and Codes
Americans with Disabilities Act of 1990 (ADA) (28 CFR Part 36, Appendix A)
Revised Code of Washington (RCW) 35.68.075, Curb ramps for persons with disabilities –
Required – Standards and requirements
Washington Administrative Code (WAC) 468-18-040, Design standards for rearranged county
roads, frontage roads, access roads, intersections, ramps and crossings
WAC 468-52, Highway access management – Access control classification system and standards
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Aspects of Traffic Control Devices, Highway Research Record No. 211, pp 1 18, “Volume
Warrants for Left-Turn Storage Lanes at Unsignalized Grade Intersections,” Harmelink, M.D.
Highway Capacity Manual (HCM), Special Report 209, Transportation Research Board, National
Research Council
1320.01 General
Modern roundabouts are near-circular intersections at grade. They are an effective intersection
type with fewer conflict points and lower speeds, and they provide for easier decision making
than other intersection types. They also require less maintenance than traffic signals. Well-
designed roundabouts have been found to reduce crashes (especially fatal and severe injury
collisions), traffic delays, fuel consumption, and air pollution. They also have a traffic-calming
effect by reducing vehicle speeds using geometric design rather than relying solely on traffic
control devices.
Roundabout design is an
iterative process.
A well-designed
roundabout achieves a
balance of safety and
efficiency.
The decision to install a roundabout is the result of an Intersection Control Evaluation (ICE) (see
Chapter 1300) approved by the region Traffic Engineer or other designated authority.
1320.02(1) Mini-Roundabouts
Compact roundabouts are a hybrid of attributes found in mini- and single-lane roundabouts.
Similar to a mini-roundabout, a compact roundabout may require minimal additional pavement,
has a completely mountable center island, and in many cases existing curb or sidewalk can be
left in place. As a result, compact roundabouts rarely require the purchase of right of way.
Compact roundabouts are similar to single-lane roundabouts regarding design vehicle
assumptions, ability to process traffic volumes, and signing.
Compact roundabouts
Single-lane roundabouts have single-lane entries at all legs and one circulating lane. They
typically have mountable raised splitter islands, a mountable truck apron, and a landscaped
central island.
Single-lane roundabout
Multilane roundabouts have at least one entry or exit with two or more lanes and more than
one circulating lane. The operational practice for trucks negotiating roundabouts is to straddle
adjacent lanes.
Multilane roundabout
Teardrops are usually associated with ramp terminals at interchanges: typically, at diamond
interchanges. Teardrop roundabouts allow the “wide node, narrow link” concept. Unlike circular
roundabouts, teardrops do not allow for continuous 360° travel resulting in less vehicle conflicts
as traffic traveling on the crossroad (link) between ramp terminal intersections (nodes) does not
encounter a yield as it enters the teardrop intersections. At higher ADT locations this lack of
conflicting vehicles can result in a higher throughput, but can also result in limited gaps for the
off ramp approach. Consult HQ or region Traffic Office for guidance.
Teardrop roundabouts
1320.04(1)(b) Non-Circular
A non-circular roundabout is a good choice when constraints such as right of way, existing
roadway alignments, buildings, and/or environmentally sensitive areas influence the shape.
Experiment with different roundabout sizes and radii, and use design vehicle turning software
(such as AutoTURN®) to refine the shape to find the best operation while retaining desired
speeds.
Non-circular roundabout
with example dimensions
1320.04(2)(a) Curbing
All curbing within a roundabout should be rolled. The type of rolled curbing appropriate for a
roundabout is shown in the Standard Plan Roundabout Cement Concrete Curbs: F-10.18.
Exception: existing curb untouched as part of a mini or compact roundabout installation may
remain.
A truck apron is the mountable portion of the central island used to accommodate the turning
path of a design vehicle larger than a passenger vehicle or BUS, and helps to minimize the
overall footprint of the roundabout. Generally, the truck tractor can traverse the roundabout in
the circulating lane while the trailer is allowed to off track onto the apron. The apron is raised
above the circulating path to provide guidance for drivers in the circulating lane.
A truck apron’s width is based on the needs of the design vehicle. If buses are a consistent
vehicle using the intersection try to minimize apron use for all movements, however this is not a
requirement. Use turn simulation software (such as AutoTURN®) to fine tune the width of apron
needed, so as not to design an apron that won’t be used.
The apron color should be easily distinguishable in contrast with the adjacent circulating
roadway and pedestrian facilities. Work with the region Landscape Architect (HQ Roadside and
Site Development Section for regions without a Landscape Architect) for concrete color and
texture.
The central island is the portion of the roundabout that is inside of the circulating roadway and
typically includes an inside truck apron and a landscaped area (except for mini-roundabouts and
compact roundabouts, which have no landscaped area and are entirely mountable).
should support the design principles of deflection and low speeds, and the accommodation of
the design vehicle.
Roundabouts present opportunities to create community focal points, landscaping, and other
gateway features within an intersection. The central island may include enhancements (such as
landscaping, sculptures, or fountains), which serve both an aesthetic purpose and provide visual
indication of the intersection for approaching motorists (this is particularly important for high
speed approaches). Ideal central island treatments fit the context and result in minimal
consequence to any vehicle that may encroach on the non-mountable portion of the central
island. These treatments should not attract pedestrians to the central island, as pedestrians
should never cross the circulating roadway. Work with the region Landscape Architect (HQ
Roadside and Site Development Section for regions without a Landscape Architect) for central
island features. See Chapter 950 Public Art for policy and guidance.
A splitter island is the raised island at each two-way leg between entering and exiting vehicles,
designed primarily to control the entry and exit speeds by providing deflection. They also
discourage wrong-way movements, and provide pedestrian refuge. Splitter islands can have
different shapes based on entry angle requirements and exit design speeds.
Raised channelization, or the appearance of raised curbing, is important, as research shows that
drivers will slow down when they perceive that the driving width is narrowing.
The length of the splitter island will vary (typical lengths: 30 ft. to 350 ft.) based on the terrain,
access considerations, site-specific
mainline and crossroad operational
speeds and the stepdown speeds to
the final desired entry speed, which
is usually 15–25 mph. (See
1320.04(3)(a) for using chicanes on
higher-speed roadways.)
The Inscribed Circle Diameter (ICD), that is, the overall outside diameter of a roundabout, is
determined by the variables design vehicle, design speed, and the number of circulatory lanes.
The ranges of ICD in Exhibit 1320-1 are only suggestions to start a roundabout design. The ICD
for noncircular shapes should be defined with dimensions along the X and Y axis.
Number of Lanes 1 1+ 1 2+
Inscribed Circle Diameter [2] 45’ – 80’ 65’ – 120’ 80’ – 150’ 120’ – 165’
Notes:
The “+” symbol used here means that a portion of the circulating roadway may have more
than one lane.
[1] Reserved for urban/suburban intersections with a 25 mph or less posted speed.
[2] The given diameters assume a circular roundabout; adjust accordingly for other shapes.
Some conditions may require ICDs outside ranges shown here.
1320.04(2)(f) Entry
1. Deflection
Ideal alignment offers an entry design that provides deflection, speed control, and reasonable
view angles to drivers while balancing property impacts and costs. While most intersections are
at 90º angles and most through movements are straight, deflection contributes to the safety
performance of a roundabout. Deflection is primarily achieved with the central island and
supporting it with splitter islands on all entries to the roundabout.
2. Alignment Offset
There are three alignment choices for attaching entry legs to the circulatory roadway:
The offset left alignment is preferred. It constrains the entry, slowing a vehicle’s
approach speed, and opens up the exit for efficient egress.
The symmetrical alignment (if needed) is acceptable for lower speed contexts such as
30 mph.
The offset right alignment tends to allow faster entry speeds and constrains the exit; it
is undesirable.
To achieve the proper amount of deflection for each approach to a roundabout, there is a range
of angle values that are desirable. This range is usually between 20 and 40 degrees. The purpose
of entry angle is so vehicles don’t hit broadside.
4. Entry Width
Entry width is determined by the turning template of the design vehicle turning through the
entry curve at the desired entry speed. The ranges of entry widths in Exhibit 1320-1 are only
suggestions to start a roundabout design.
5. Path Overlap
In a multilane roundabout, if the vehicles in the entry are aligned toward the central island or
the truck apron, the vehicle on the right is pointed toward the inside lane and tends to go in that
direction, while the vehicle on the left tends to be squeezed to the right toward the vehicle on
the right. Avoid path overlap. Avoid a design that aligns an entering vehicle at the incorrect lane
in the circulatory roadway. As a vehicle enters the circulating roadway it should be headed
directly toward its respective lane within the circulating roadway. For multilane roundabouts, if
inside lane is pointing at truck apron this is also considered to be path overlap. If right entry lane
is pointing to left circulatory lane, then there is path overlap.
Right-turn slip lanes are a proven way to increase the “life” of an intersection by removing traffic
that would otherwise enter the roundabout and reduce the available capacity to other
movements. If a right-turn movement has 250 vehicles/hour or more, or if over 40% of the total
approach volume is taking right turns, a slip lane should be considered.
The conflicting volume of vehicles on the merge will influence the length of merge lane prior to
termination. Speeds can be very low and vehicles can take turns at these low speeds.
Multimodal considerations will influence the length based on crosswalk location and bicycle use.
Roundabout operation performance is dependent on low, consistent vehicle speeds. Low and
consistent operating speeds facilitate appropriate gap acceptance by an entering driver. Design
for travel path operating speeds between 15 mph and 25 mph (see 1320.04(3)(b)). Design to
have low-speed differentials (12 mph or under) between entering and circulating traffic.
Multilane roundabouts might have higher speeds along their respective travel paths, but
generally 30 mph or less.
The ideal design speed mechanism has the entry and circulating speeds being similar. This varies
due to size, shape and context of the roundabout.
The vehicle then moves into and through the circulation lane, being controlled all along by the
design speed of the circulating lane. The circulating design speed controls the exit speed;
therefore, the exit design speed, as calculated in the Travel Path section below, is not as critical.
Designing geometric entry speed control encourages lower speeds and lower speed differentials
at conflict points, which reduces the potential for collisions.
1320.04(3)(a) Chicanes
Chicanes are a type of horizontal deflection used in traffic calming to reduce the speed of
vehicles. Research has shown that chicanes have value in slowing down higher approach speeds.
Chicane
Consider chicanes where posted speeds near the roundabout are 45 mph or higher. Design
chicane curves with successively smaller radii in order to successively reduce vehicle speeds
approaching the roundabout entry. Use Exhibit 1320-2 to determine the radii-speed relationship
(the radii are measured using the offsets recommended in the Travel Paths section). The normal
cross slope (superelevation in 1320-2) is 2% however, site conditions may require more based
on how you tilt the plane of the roundabout for site specific conditions. A minus (-) 2% drains
toward the central island.
Also, consider the grade of the roadways that enter the roundabout, because a vehicle can more
easily slow down on an upgrade than on a downgrade. Adjust the length of the deceleration
based on the “Adjustment Factors for Grades Greater Than 3%” in Design Manual Exhibit 1360-
10.
Travel path calculations can be used on all roundabout designs to get an understanding of
speeds for different paths throughout the roundabout. A travel path is the shortest path
through the roundabout, no closer than 5 feet from any curb face or lane line as shown. Use
Exhibit 1320-2 and R1 through R5 to determine Travel Path speeds.
Travel paths
Source: NCHRP
1320.04(4) Grades
Do not use grades as a constraint during scoping to rule out a roundabout. Be aware of how the
profiles mesh with sight distances and ADA pedestrian requirements.
1320.04(4)(a) Circulatory Roadway
The circulatory roadway grade value should not exceed 4%. Terrain may require benching the
roundabout to fit conditions.
1320.04(4)(b) Grade Transitions for Roadway Entry and Exit to the Circulatory
Roadway
Consider the grade transitions and make them as long as feasible. When designing for
pedestrians see Chapter 1510 and work with region ADA subject matter expert to ensure that
grades for ADA compliance at all pedestrian crossing are met.
The preferred profile grades of the circulatory roadway of a roundabout are ±4% or flatter
radially around the circulatory lane(s). Profile grades steeper than ±4% require justification. It is
preferred to bench the roundabout if practicable to reduce profile grade.
Preferred grades
and cross slopes
cross slope
The preferred circulatory roadway cross slope may range from 1.5% to 4.0% (2.0% preferred),
away from the central island to promote lower circulating speeds, improve central island
visibility, minimize breaks in cross slope of entry and exit lanes, and facilitate drainage of water
to the outside of the roundabout.
Drawing shows preferred cross slopes. Site conditions and drainage may require slopes outside these
ranges.
During the scoping or preliminary geometric design process, do not to use truck turning paths
alone as a constraint to eliminate a roundabout at an intersection. There are several design
tools available to aid in the design of a roundabout. It is important to understand how the
software works, its default settings, and its application to the design process.
While all highway-to-highway movements require accommodating a WB-67, there are certain
assumptions that must be made with software programs that replicate truck swept paths.
Determine which truck percentage defaults are to be used (recognizing that truck percentages
can range from 2% to 20%) so that different segments can be modeled accurately. Recognize
that within a set percentage, WB-67s may only represent a small sample of the entire truck
volume on any given day. Therefore, consider whether a WB-67 should be designed for, or
accommodated (also see Chapter 1103).
1. Designing for a WB 67
A roundabout that is being designed for a WB-67 may result in wider lane widths and a larger
Inscribed Circle Diameter. For this situation, rolled curb design is critical to the truck’s traversing
the roundabout (see Standard Plan F-10.18 for curb details). Outside aprons may not be needed
in many situations based on AutoTurn® modeling and knowledge of driver turning behavior
when encountering geometric features.
2. Accommodating a WB 67
A roundabout that is designed to accommodate a WB-67 assumes that a WB-67 could utilize
truck aprons to maneuver through the roundabout, if necessary, which should reduce the
overall footprint of the roundabout. For this situation, rolled curb is critical to the truck’s
traversing the roundabout confidently. Although outside truck aprons are needed infrequently,
there may be situations where the design may need to incorporate them. Contact HQ Traffic for
guidance.
In some cases, roundabouts of the perfect circular variety with symmetrical roadway
attachments require less specific knowledge of truck-turning software and its applications.
However, when looking at a non-circular shaped roundabout where the combination of the
truck’s speed, its turning angle settings, its rear axle locations, and its alignment are the critical
design elements to address, a mastery of the software is required. Designers that are unfamiliar
with how to apply the software inputs accurately to model a truck’s swept path need to contact
HQ Traffic Office for guidance. Poor alignment of a truck swept path can result in unnecessarily
large roundabout footprints, higher than desired Travel Path speeds, or uncomfortable driving
maneuvers by the freight community.
Assume that a truck will travel much slower through a roundabout than the Travel Path speed
calculated for passenger vehicles (see 1320.04(3)(b)). Adjust the software input to allow a
slower truck speed in order to make a good engineering judgment about how fast a truck may
use a roundabout (for example, for AutoTURN® use 5 mph). Design tool default settings don’t
necessarily allow the maximization of the tool and can prohibit the designer from getting a
good, balanced design between passenger car speeds and truck accommodation.
When using a truck-turning software tool like AutoTURN® on multilane roundabouts, assume a
truck’s travel path will occupy (straddle) parts of two adjacent lanes.
1320.04(7)(a) Stopping
Use the design stopping sight distance in Chapter 1260. Anticipated speeds throughout the
roundabout can be calculated using Exhibit 1320-2, based on the Travel Path radius and
direction of the particular curve. The design stopping sight distance is measured along the
vehicle’s path as it follows the curvature of the roadway; it is not measured as a straight line.
1320.04(7)(b) Intersection
Provide minimum intersection sight distance. Longer sight distances can lead to higher vehicle
speeds that reduce gap opportunities for entering vehicles. For intersection sight distance at
roundabouts, provide entering vehicles a clear view of traffic on the circulating roadway and on
the immediate upstream approach in order to aid in judging an acceptable gap.
The intersection sight distance at roundabouts is given in Exhibit 1320-3. The S1 intersection
sight distance is based on the average of the entering and circulating speeds, and the S2
intersection sight distance is based on the left-turning speed. The sight distance may also be
calculated using the intersection sight distance equation given in Chapter 1310 using a time gap
(tg) of 4.5 seconds.
200
Intersection Sight Distance, S (ft)
180
160
140
120
100
80
60
10 15 20 25 30
Although it is undesirable to locate any intersection near an at-grade railroad crossing, this
situation exists at many locations on the highway system. Experience shows that a roundabout
placed near a crossing has some operational advantages. If there is a railroad crossing near the
roundabout contact HQ Traffic Office for further guidance.
1320.05 Pedestrians
As part of the approved ICE it has already been determined whether pedestrians will use the
roundabout and, if so, which legs (see Chapter 1300).
With the knowledge of where pedestrian facilities are needed, design the roundabout while
keeping in mind the ADA requirements for crosswalks, sidewalks, paths, and other pedestrian
facilities.
The crossing located in the exit side of the roundabout leg can be closer to the roundabout,
because as the vehicles leave the roundabout, they accelerate and make it harder to find a
break in traffic. As speed increases, drivers are less likely and less able to stop. Verify that no
significant, large sight obstructions are located within the sight lines.
1320.05(3) Buffers
Roundabouts with buffers typically have combination-type curb ramps; otherwise, parallel curb
ramps are normally used. (See Chapter 1510 and the Standard Plans for curb ramp information.)
A vehicle sight triangle specific to pedestrians (see 1320.04(7)) must include the whole curb
ramp, including the landing, where pedestrians are likely to wait to cross.
It is also important that pedestrians are also able to see approaching vehicles.
Pedestrian beacons
1320.06 Bicycles
Provide bicyclists with similar options to negotiate roundabouts as they have at other
intersections. Consider how they navigate either as motor vehicles or pedestrians depending on
the size of the intersection, traffic volumes, their experience level, and other factors.
At larger or busier roundabouts, cyclists may be more comfortable using ramps connecting to a
sidewalk around the perimeter of the roundabout as a pedestrian. Where bicycle lanes or
shoulders are used on approach roadways, they should end before the geometry changes the
approach to the roundabout.
1320.07 Signing
The graphic shown is an example of
potential signing for a single-lane
roundabout. For additional information,
refer to the MUTCD, Plan Sheet Library,
and the Standard Plans for details on
signing.
1320.09 Illumination
Provide illumination for each of the conflict points between circulating and entering traffic in the
roundabout and at the beginning of the raised splitter islands. Illuminate raised channelization
or curbing. Position the luminaires on the upstream side of each crosswalk to improve the
visibility of pedestrians. Light the roundabout from the outside in toward the center. This
improves the visibility of the central island and circulating vehicles to motorists approaching the
roundabout. Ground-level lighting within the central island that shines upward toward objects in
the central island can also improve their visibility. Consult with the region Traffic office for
illumination design. (See Chapter 1040 for additional information on illumination.) On higher-
speed approaches, consider internally illuminated bollards (IIB) in lieu of other illumination.
minimum corner clearance cannot be met, document the decision in accordance with Chapters
530 and 540.
Roadways between roundabouts may have restrictive medians with left-turn access provided
with U-turns at the roundabouts.
Parking is not allowed in the circulating roadway or on the entry or exit roadway within the
length of the splitter island.
Transit stops are not allowed in the circulating roadway, in the approach lanes, or in the exit
lanes prior to the crosswalk. Locate transit stops on the roadway before or after the
roundabout, in a pullout, or where the pavement is wide enough that a stopped bus does not
block the through movement of traffic or impede sight distance.
The intent of this peer review is to review, discuss, evaluate, and provide feedback on the 2-D
roundabout layout design in order to finalize the channelization plan.
1320.13 References
See Chapter 1510 for Americans with Disabilities Act Policy and references
Washington Administrative Code (WAC) 468-58-080, Guides for control of access on crossroads
and interchange ramps
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA, as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21 01, WSDOT
Standard Specifications for Road, Bridge, and Municipal Construction (Standard Specifications),
M 41-10, WSDOT
Roundabouts: An Informational Guide (Second Edition 2010), NCHRP Report 672, Transportation
Research Board, 2010 http://nacto.org/docs/usdg/nchrprpt672.pdf
Highway Capacity Manual 2010 (HCM 2010), Transportation Research Board, National Research
Council, Washington D.C., 2000
1330.01 General
Traffic control signals are automated traffic control devices that warn or direct motorists to take
a specific action. Traffic control signals are used to control the assignment of right of way at
locations where conflicts with motorists, bicyclists, and pedestrians exist or where passive
devices such as signs and markings do not provide the necessary flexibility of control to move
motorists, bicyclists, and pedestrians in an efficient manner.
The decision to install a traffic signal is the result of an Intersection Control Evaluation (ICE) (see
Chapter 1300) that is approved by the region Traffic Engineer or other designated authority.
1330.02 Procedures
The Traffic Signal Permit (DOT Form 242-014 EF) is the formal record of the signal warrant
analysis required by the MUTCD and the department’s approval of the installation and type of
signal. Permits are required for the following types of signal installations:
Conventional traffic signals
Emergency vehicle signals
Intersection control beacons
Lane control signals
Movable bridge signals
Ramp meter signals
Pedestrian signals
Pedestrian Hybrid Beacon signals (“HAWK” signals)
Temporary traffic signals (only when not being used in place of a permanent, permitted
signal)
Queue-cutter traffic signals
The Permit and its supporting data must be included in the Design Documentation Package
(DDP.) The permit is completed by the requesting agency and submitted, complete with
supporting data, through the region Traffic Office to the approving authority for approval. See
1330.02(1)(a) for Signal Warrant information required as part of the supporting documentation.
The approving authority is the Regional Administrator or authorized delegate. The approving
authority approves or denies the application and sends it back to the region Traffic Office. The
region Traffic Office retains a record of the approved permit and supporting data and forwards a
copy of the Permit and the supporting data to the State Traffic Engineer at WSDOT
Headquarters (HQ). Preserve the approved permit as required by 1330.07 Documentation.
Emergency vehicle signals require annual permit renewal. The region Traffic Office reviews the
installation for compliance with requirements. If satisfactory, the permit is renewed by the
Regional Administrator with a letter to the operating agency. A copy of this letter is also sent to
the State Traffic Engineer.
Permits are not required for portable traffic signals, speed limit sign beacons, stop sign beacons,
or lane assignment signals at toll facilities.
A new permit application is required when the level of control is increased, such as changing
from an intersection control beacon to a conventional traffic signal or adding an approach to an
existing signal system.
For a reduction in the level of control, such as converting a conventional signal to a flashing
intersection beacon or removal of the signal, submit the “Report of Change” portion of the
traffic signal permit, complete with supporting data, to the approving authority, with a copy to
the region Traffic Office and State Traffic Engineer.
If experimental systems are proposed, region Traffic Engineer review and approval is required.
The region Traffic Office will send the approved proposal to the State Traffic Engineer for review
and approval. The State Traffic Engineer will forward the approved proposal to FHWA for their
approval. A copy of the approval from FHWA will be returned and must be preserved as
required by 1330.07 Documentation.
Any signal system requiring a permit, with the exception of Ramp Meter signals, also requires
Preliminary Signal Plan approval from the WSDOT HQ Traffic Office (see 1330.05).
A signal warrant is a minimum condition that is to be met before a signal may be considered for
installation. Satisfying a warrant does not mandate the installation of a traffic signal. The
warranting condition(s) supports the inclusion of a traffic signal for consideration as part of the
ICE performed during the scoping of the project (see Chapter 1300). For a list of the traffic signal
warrants and information on how to use them, see the Manual on Uniform Traffic Control
Devices (MUTCD). Contact the region Traffic Engineer for region specific practices.
Address all warrants listed in the currently adopted MUTCD as part of the Signal Warrant
Analysis. Mark warrants which do not apply as “Not Applicable” and include a basic supporting
statement or similar justification. Include the Signal Warrant Analysis in the Signal Permit
supporting data. For Warrant 7, the three year period must be used for all traffic signals
installed on state highways as described in FHWA Interim Approval IA-19
(https://mutcd.fhwa.dot.gov/resources/interim_approval/ia19/index.htm).
(a) Inside the corporate limits of cities with a population of 27,500 or greater where there is
no established limited access control: The city is responsible for the funding, construction,
maintenance, and operation of traffic signals. Population figures can be found at:
www.ofm.wa.gov/pop/
(b) Inside the corporate limits of cities with a population of less than 27,500: WSDOT is
responsible for funding, construction, maintenance, and operation of traffic signals.
Population figures can be found at: www.ofm.wa.gov/pop/
(c) Inside the corporate limits of cities with a population of 27,500 or greater where there is
established limited access control: WSDOT is responsible for funding, construction,
maintenance, and operation of traffic signals. Population figures can be found at:
www.ofm.wa.gov/pop/
(d) Outside the corporate limits of cities and outside established limited access control areas:
WSDOT is responsible for funding, construction, maintenance, and operation of a traffic
signal when a new state highway crosses an existing county road. When a new county road
intersects an existing state highway, WSDOT is responsible for only the maintenance and
operation of a traffic signal. The county is responsible for the construction costs of the
traffic signal and associated illumination. When it is necessary to construct a traffic signal at
an existing county road and state highway intersection, the construction cost distribution is
based on the volume of traffic entering the intersection from each jurisdiction’s roadway.
The county’s share of the cost, however, is limited to a maximum of 50%. The state is
responsible for maintenance and operation (WAC 468-18-040).
(e) Outside the corporate limits of cities and inside established limited access control areas:
WSDOT is responsible for funding, construction, maintenance, and operation of traffic
signals.
(f) Emergency vehicle signals: The emergency service agency is responsible for all costs
associated with emergency vehicle signals.
(g) Third party agreement signals: At those locations where WSDOT is responsible for traffic
signals and third party activity justifies the installation of a traffic signal, as determined by
an ICE, the following rules apply:
The third party is responsible for funding the design and construction of the traffic
signal system, unless another arrangement is agreed upon with WSDOT.
The third party obtains a traffic signal permit.
The third party agrees to design and construct the traffic signal in conformance
with WSDOT’s guidelines and requirements.
The third party agrees to submit the design and construction documents to
WSDOT for review and approval by the region Traffic Engineer.
Preserve all third party provided documents and any third party agreement(s) as
required by 1330.07 Documentation.
Left-turning traffic can operate more efficiently when the opposing left-turn lanes are directly
opposite each other. When a left-turn lane is offset into the path of an opposing through lane,
the left-turning driver may assume the opposing vehicles are also in a left-turn lane and fail to
yield. To prevent this occurrence, less efficient split phasing may be necessary. (See Chapter
1310 for guidance on lane offsets and opposing left-turn clearance.) Where there are opposing
through lanes but no opposing left turn lane, install a striped or raised median area opposite the
left turn lane if possible.
Place stop lines so that they are out of the path of conflicting left turns. Check the geometric
layout by using turning templates or a computerized vehicle turning path program (such as
AutoTURN®) to determine whether the proposed layout and phasing can accommodate the
design vehicles. Also, check the turning paths of opposing left-turn movements. In many cases,
the phase analysis might recommend allowing opposing left turns to run concurrently, but the
intersection geometrics are such that this operation cannot occur. The intersection should be
large enough to accommodate opposing left turning vehicle paths with a 4-foot minimum (12-
foot desirable) separation between them. Where this separation cannot be achieved, less
efficient signal phasing may be required to accommodate opposing left turns.
Some intersections may have multi-lane left turns. At locations with closely spaced
intersections, a multi-lane left-turn storage area might be the only solution to reduce the
potential for the left-turn volume to back up into an adjacent intersection. As with single left
turn lanes, the intersection should be large enough to accommodate opposing left turning
vehicle paths with a 4-foot minimum (12-foot desirable) separation between them. Where this
separation cannot be achieved, less efficient signal phasing may be required to accommodate
opposing left turns.
At smaller intersections, the opposing single-lane left-turn movement might not be able to turn
during the two-lane left-turn phase and it might be necessary to reposition this lane. If the
opposing left turns cannot time together, the reduction in delay from the two-lane left-turn
phase is likely to be nullified by the requirement for a separate opposing left-turn phase. Exhibit
1330-3 shows two examples of two-lane left turns with opposing single-left arrangements.
Two receiving lanes are required for two-lane left-turn movements. In addition, these receiving
lanes are to extend well beyond the intersection before reducing to one lane. A lane reduction
immediately beyond the intersection can cause delays and backups into the intersection
because the left-turning vehicles usually move in dense platoons, which may make merging and
lane changes difficult. (See Chapter 1310 for guidance on lane reductions on intersection exits.)
Conflict point
Turning path for
opposing single
left turn
At intersections with large right-turn radii, consider installing raised traffic islands. These islands
are primarily designed as pedestrian refuge areas. (See Chapter 1510 for pedestrian refuge
islands and traffic island designs.) Traffic islands may decrease the required pedestrian clearance
intervals; however, large radii and raised traffic islands may make it difficult for pedestrians to
navigate the intersection. Where pedestrians are expected to cross a right turn lane to a traffic
island, it is recommended to use a compound right turn-lane design as shown in Chapter 1310.
Management of driveways and road approaches should be determined early (preferably no later
than scoping) so that they can be considered and addressed in the design. (See Chapters 530
and 540 for further guidance.) Consider shifting the location of advance detection upstream to
clear an access point so that vehicles entering from the access point will not affect detection and
operation of the signal.
This greatly improves the efficiency of the signal during railroad preemption when turns are
restricted. Also consider providing a left-turn lane for the minor leg opposing the railroad
crossing. This will allow for more effective signal operations during long periods of railroad
preemption.
Where there is less than 40 feet between the nearest rail and the normal location of the stop
line, do not install a stop line between the tracks and the intersection. Use the same stop line
for the traffic signal and the rail crossing instead. Exhibit 1330-4 shows recommended
intersection features for intersections near rail crossings.
Contact the WSDOT HQ Traffic Office for assistance with standalone queue-cutter signals.
1330.04(1) General
The goal of any traffic signal design is to assign right of way in the most efficient manner
possible and still be consistent with traffic volumes, intersection geometrics, and safety.
An advanced signalized intersection warning sign and beacon assembly to warn motorists of a
signalized intersection should be installed when either of the two following conditions exists:
(b) The posted speed is 55 mph or higher and the next nearest signalized intersection is more
than 2 miles away; this does not apply to freeway off-ramps.
This warning sign and beacon assembly consists of a W3-3 sign with Type IV reflective sheeting
and one or two continuously flashing beacons. Where two beacons are used, the beacons
should flash alternately instead of simultaneously. Locate the sign in advance of the intersection
in accordance with Table 2C-4 (Condition A) of the MUTCD. The warning sign and beacon
assembly may be omitted with approval from the region Traffic Engineer.
Exhibit 1330-5 Standard Intersection Movements, Head Numbers, and Phase Operation
For WSDOT operated signals, the region Signal Operations Engineer will develop the signal
phasing plan or review proposed phasing for systems designed by others. For signals operated
by other jurisdictions, the operating jurisdiction should be involved in signal phasing
development. Phasing development is addressed in 1330.06 Operational Considerations for
Design. Phasing development should begin as soon as the decision is made to install a traffic
signal and may begin as early as the intersection control evaluation. Provide the proposed
channelization plans and traffic count data to the region Signal Operations Engineer or phasing
designer as early as possible, as phasing information is required to complete the signal system
design.
For WSDOT owned and operated signals, vehicle and pedestrian movement phase numbering is
standardized to provide uniformity in signal phase numbering, signal display numbering,
preemption channel identification, detection numbering, and circuit identification. For signals
owned and operated by other jurisdictions, refer to that jurisdiction’s guidelines for phase and
equipment numbering. The following are general guidelines for the WSDOT numbering system:
1. Phases 2 and 6 are normally assigned to the major street through movements, with phase 2
assigned to the northbound or eastbound direction of the major street. This results in phase
2 being aligned with the direction of increasing mileposts.
2. Phases 1 and 5 are normally assigned to the major street protected left-turn movements.
3. Phases 4 and 8 are normally assigned to the minor street through movements, with phase 4
normally assigned to the approach to the left of the phase 2 approach (as viewed from the
phase 2 stop line).
4. Phases 3 and 7 are normally assigned to the minor street protected left-turn movements.
5. Phasing on new signals installed within an already signalized corridor should be assigned to
match the existing corridor phasing – even if it doesn’t follow the standard phasing
conventions listed above.
6. At T intersections, the movement on the stem of the T is normally assigned to either phase 4
or phase 8. Which phase is used will normally depend on the major street phase
assignments.
7. At intersections where split phasing is used (opposing directions time separately) assign
phases normally but show the split phase phasing diagram, unless otherwise directed by
maintenance and operations staff.
8. Signal displays are numbered as follows:
a. The first number indicates the signal phase and the second number is the number of
the signal head, counting from centerline (or left edge line) to the right edge line of
the approach. For example, signal displays for phase 2 are numbered, as viewed from
left to right, 21, 22, 23, and so on. If the display is an overlap, the designation is the
letter assigned to that overlap. For example, signal displays for overlap A are number
A1, A2, A3, and so on.
b. If the display is protected/permissive, the display is numbered with the phase number
of the through display followed by the phase number of the left-turn phase. For
example, a protected/permissive signal display for phase 1 (the left-turn movement)
and phase 6 (the compatible through movement) is numbered 61/11. For overlap
right turns, the protected portion may either be an overlap phase, or it may be the
same phase as the complementing left turn phase.
When a flashing yellow arrow display is used, coordinate with the Signal Operations
Engineer and signal maintenance group to determine appropriate wiring. For new
cabinets, always specify an auxiliary output rack when protected/permissive phasing
will be used.
9. Pedestrian displays and detectors are numbered with the first number indicating the signal
phase and the second number as either an 8 or 9. For example, pedestrian displays and
detectors 28 and 29 are assigned to phase 2. If there are more than two displays or
detectors for a single pedestrian phase, use letter suffixes for additional displays and
detectors (28A / 29A, 28B / 29B, etc.).
10. Vehicle detector numbering depends on the type of detection:
a. Induction loop detectors use three digit numbers for designation. The first number
represents the phase. The second number represents the lane number, starting from
the left lane and moving towards the right edge line. The third number represents the
loop number counting from the stop line back. For example, detection loops for phase
2 detectors are numbered 211, 212, 213 for lane 1; 221, 222, 223 for lane 2; and so
on. For loops tied together in series for a single detection channel, such as a three
loop series stop line detector, the individual loops in the series use a letter suffix. For a
stop line detector in lane 1 for phase 2, using three loops in series, the loops would be
designated 211A, 211B, and 211C.
b. Video detectors are designated V#, where “#” is the through phase number for that
approach, even if it will cover additional phases (such as left turn or overlap) for that
approach. If the video detector is for advance detection, the suffix “A” is added. For
example, the advance video detector for phase 6 would be V6A.
Video detection zones may be drawn on the contract plans if desired, but these will
normally be field established and adjusted and may not end up as shown in the plans.
If used, video detection zones are labeled the same as loop detectors, but with a “V”
suffix. For example, the stop line video detection zone for phase 5 would be 511V.
c. Radar detectors are designated similar to video detectors, but use an “R” prefix in
place of the “V”. For example, the advance radar detector for phase 4 would be R4A.
d. Wireless in pavement sensors use the same numbering scheme as induction loops,
but add a “W” suffix. For example, the phase 7 stop line sensor would be 711W.
The use of ball, steady arrow, or flashing yellow arrow displays is dependent upon the signal
phasing. Use the approved signal phasing diagram to determine which display types can be used
for which movements. Typical vehicle signal displays are shown in Exhibits 1330-7a through 7h.
In addition to the display requirements contained in the MUTCD, the following also apply:
1. A minimum of two indications for the through movement, if one exists at an intersection,
must be provided - even if it is not the primary (predominant) movement. Provide a
minimum of two indications for the major signalized turn movement of an intersection if no
through movement exists, such as on the stem of a T intersection. These signal faces are to
be spaced a minimum of 8 feet apart. At a T intersection, select the higher-volume
movement as the primary movement and provide displays accordingly.
A green left-turn arrow on a primary display and a green ball on the other primary display
do not comply with this rule. At an intersection where left turns are prohibited, the leftmost
through display may use a green up arrow in place of the green ball display. At an
intersection where right turns are prohibited, the rightmost through display may use a
green up arrow in place of the green ball display.
2. All displays for an approach, regardless of phase served, are to be a minimum of 8 feet
apart.
3. Locate displays directly overhead and centered over the associated lane of the applicable
vehicular traffic as it moves through the intersection. (See Exhibits 1330-7a through 7h for
signal head locations.) For intersections with a skew for through traffic, locate signal displays
for through traffic in one of the following ways:
b. Over a line drawn between the center of the approaching lane and the center of the
associated outbound lane, ending at the stop lines
Left turn displays may either be located relative to the through displays or in line with
approaching traffic, dependent on ability to mount the display(s). (See Exhibit 1330-8 for
skew placement examples.)
4. Locate displays a minimum of 50 feet and a maximum of 180 feet from the stop line. The
preferred location of the signal heads is between 60 and 120 feet from the stop line. When
the nearest signal face is located between 150 and 180 feet beyond the stop line,
engineering judgment of conditions, including worst-case visibility conditions, is to be used
to determine whether the provision of a supplemental or nearside signal face would be
beneficial. When it is not physically possible to locate displays at least 50 feet from the stop
line, the distance to the displays may be reduced as follows:
a. 3-section vertical and 5-section cluster (doghouse) displays may be located between
40 and 50 feet from the stop line.
b. 4-section vertical displays may be located between 41 and 50 feet from the stop line.
c. 5-section vertical displays may be located between 45 and 50 feet from the stop line.
The distances listed above are the minimums required to maintain 16.5 feet of clearance
over the roadway with a backplate installed.
Overhead displays should always be located on the far side of the crossing roadway for the
best visibility. Locating overhead displays on the near side of the roadway results in issues
with visibility and driver compliance with stop lines. When an overhead display is located on
the near side of the crossing roadway, the stop line typically has to be pushed back so that
the minimum visibility distance is met. However, this also pushes the stop line back too far
for drivers to see cross traffic, resulting in drivers creeping past the stop line towards the
intersection – especially for turning traffic. This results in both the driver being stopped past
the stop line and being unable to see the signal displays.
For ramp meter signals, place Type RM signal standards and displays at the stop line.
5. Use vertical vehicle-signal display configurations. Horizontal displays are not allowed unless
clearance requirements cannot be achieved with vertical displays or unless they are being
installed at an intersection to match other displays in the intersection. Approval by the State
Traffic Engineer is required for the installation of horizontal displays.
6. Use 12-inch signal sections for all vehicle displays except the lower display for a post
mounted ramp meter signal.
7. Provide displays for turning movements with dedicated lanes as follows:
b. For protected / permissive movements, use four section arrow displays. Alternatively,
a shared five section cluster (doghouse) display may be used for both the turn lane
and the adjacent through lane. Note: A three section arrow display, with bi-modal
flashing yellow arrow / steady green arrow may be used in cases where windload or
vertical roadway clearance will not allow for the use of a four-section display. If
vertical clearance can be accommodated through adjustments to the signal display
mount, such as mounting the Type M mount between different display sections, a
four section arrow display should be used.
c. For permissive right turns, a three-section arrow display with flashing yellow arrow
(Exhibit 1330-7g) is optional. This display is highly recommended where there are
concerns regarding permissive right turns and the conflicting pedestrian crossing
movement, such as known incidents or high volumes of both pedestrian crossings and
right turn movements.
8. Use steady green arrow indications only when the associated movement is completely
protected from conflict with other vehicular and pedestrian movements. This includes
conflict with a permissive left-turn movement. At T intersections, steady green arrow
displays may not be used for a movement that has a conflicting pedestrian movement.
9. Use either Type M or Type N mountings for vehicle display mountings on mast arms, as
directed by the region maintenance staff or owning agency. Provide only one type of
mounting for each signal system. Mixing mounting types at an intersection is not acceptable
except for supplemental displays mounted on the signal standard shaft.
10. Use backplates for all overhead-mounted displays for new, updated, or rebuilt signal faces.
Add backplates to all existing signal displays that do not already have them.
11. Use Type E mountings for pedestrian displays mounted on signal standard shafts unless
otherwise approved by region maintenance staff or the owning agency.
12. Include supplemental signal displays when the approach is in a horizontal or vertical curve
and the intersection visibility requirements of this section and the MUTCD cannot be met,
unless approved otherwise by the region Traffic Engineer.
Supplemental far side displays are recommended at intersections with higher truck volumes,
as the trucks will frequently block visibility of overhead displays for following drivers.
Supplemental far side protected left turn displays are recommended for long left turns.
Exhibit 1330-7e Signal Displays for Shared Through-Left Lanes – Multiple Through Lanes
The minimum mounting height for overhead signal displays is 16.5 feet from the roadway
surface to the bottom of the signal housing, including the backplate. There is also a maximum
height for signal displays allowed by the MUTCD, since the roof of a vehicle can obstruct a
motorist’s view of a signal display. The maximum heights from the roadway surface to the
bottom of the signal display housing with 12-inch displays are shown in Exhibit 1330-9.
At signalized intersections with railroad preemption, install blankout signs for turning
movements that do not have a dedicated signal display (3-section arrow display). Blankout signs
are 36” x 36” and will display either a No Right Turn symbol (R3-1) or No Left Turn symbol (R3-2)
when activated, as appropriate. Blankout signs should be placed the same as equivalent static
signs.
Pedestrian displays are required to be installed with the bottom of the display housing no less
than 7 feet or more than 10 feet above the sidewalk surface. Pedestrian displays are required to
be installed to provide maximum visibility at the beginning of the controlled crosswalks. To
accomplish this, pedestrian displays should be located no more than 5 feet from the outside
edge of the crosswalk, as measured on a line perpendicular to the crosswalk centerline (See
Exhibit 1330-10). The offset distance may be offset up to a maximum of 10 feet from the outside
edge of the crosswalk if physical constraints prevent the display from being placed no more than
5 feet from the outside edge of the crosswalk.
Pedestrian pushbuttons (PPBs) are required to be located within a certain distance of the
crosswalk being served and oriented such that the sign on the pushbutton is parallel to the
crosswalk served. Pedestrian pushbutton location requirements are as follows:
The PPB should be between 4 and 6 feet from the face of curb, where sidewalk is
present, or the edge line of the roadway where there is no sidewalk. The PPB may be
between 1.5 and 4 feet from the curb face or edge line, but this is not recommended
due to proximity to the roadway. The PPB may not be closer than 1.5 feet from the
curb face or edge line. If geometric constraints make it impractical to place the PPB
within the 4-6 foot range, the PPB should not be further than 10 feet from the edge of
curb, shoulder, or pavement. Contact the HQ Traffic Office if the PPB cannot be placed
within 10 feet of the curb face or edge line.
The PPB should be located as close to the outside edge of the crosswalk line as
possible, so that for APS PPBs, the button and sign face towards the core of the
intersection, rather than back down the adjacent approaching roadway. The PPB may
be located no more than 5 feet outside either edge of the crosswalk line.
If possible, PPBs should be located on separate poles and be separated by a minimum
of 10 feet.
See Exhibit 1330-11 for recommended and allowed PPB placement locations.
PPBs are required to be located so that the actual button, not just the assembly, is within 9
inches horizontally of a level all-weather surface (generally sidewalk or paved road shoulder) as
described in Chapter 1510. To accomplish this, certain criteria must be met depending on the
type of pole upon which the pushbutton is installed:
a. For vertical shaft poles (Type PPB, PS, I, FB, or RM), the center of the pole shall be no more
than 9 inches from the edge of the level clear space. The pushbutton shall not be oriented
more than 90 degrees from facing the level clear space. (See Exhibit 1330-12a.)
b. For larger signal standards (Type II, III, IV, IV, or SD), the button must face the level clear
space, with the edge of the pole baseplate no more than 6 inches from the edge of the
level clear space. It is recommended that the pole either be in the sidewalk, or the edge
of the pole base plate be installed as close to the back of sidewalk as possible. (See Exhibit
1330-12b.) Some minor rotation of the button on the pole is possible, but even smaller
angles may quickly exceed the allowed reach limit – particularly on larger poles.
In all cases, it is recommended that the pole be installed in the sidewalk for maximum
accessibility. However, the pole and the pushbutton itself are obstructions and must not
encroach upon the required minimum pedestrian access route widths (see Chapter 1510).
PPBs are required to be installed at 42 inches above the level clear space, as measured to the
center of the actual button. Existing pushbuttons do not require a height adjustment if the
center of the actual button is within a range of 36 to 48 inches above the level clear space.
Where there is a median or center island with a pedestrian refuge, consult with signal
operations to determine if a pushbutton should be installed in the pedestrian refuge area. This
may be justified for locations with particularly long crossings or slower moving pedestrians.
For WSDOT owned systems, pedestrian signal equipment may not be installed on light
standards. Do not install pedestrian signal equipment on light standards for systems owned by
other jurisdictions unless directed to do so by that jurisdiction.
1330.04(4)(a) Accessible Pedestrian Signals and Countdown Pedestrian Displays
Countdown pedestrian displays are displays which use a combination of an overlapping person
(walk) and hand (don’t walk) indication and an adjacent two digit countdown timer display. The
timer counts down the seconds remaining in the pedestrian clearance phase (flashing don’t
walk). For WSDOT owned traffic signals, all new construction traffic signals are required to
include countdown pedestrian displays. For new construction traffic signals owned by other
jurisdictions, countdown pedestrian displays are required unless directed otherwise by the
owning jurisdiction.
For existing signalized intersections where pedestrian equipment was not previously installed,
the installation of APS and countdown pedestrian displays is required for the entire intersection.
This may require new or relocated poles, as well as additional ramp and sidewalk work beyond
that necessary for basic sidewalk and ramp ADA compliance.
At signalized intersections with existing pedestrian equipment, the following criteria determine
when APS pushbuttons and countdown pedestrian displays shall be installed:
1. The following are considered minor signal upgrades, and do not require the installation of
APS pushbuttons or countdown pedestrian displays at that intersection:
a. Where pushbuttons are only being adjusted in height or orientation.
b. Where pushbuttons are being relocated on a single corner, including to a new pole,
and no other work (including sidewalk or ramp work) is taking place at any other
corner, pushbuttons may be relocated or replaced with the same type of
pushbutton as currently exists at that intersection. Countdown pedestrian displays
are not required to be installed at that intersection. New pole location(s) must meet
accessibility requirements for pedestrian pushbuttons (see Chapter 1510.12).
Accessibility for any affected poles must be evaluated for both existing pushbuttons
and future APS pushbuttons.
2. The following types of work shall include the installation of APS pushbuttons and
countdown pedestrian displays as described below:
a. At any signalized intersection included in a project that is designated as an
alteration project, as defined in Chapter 1510.05(2):
i. For WSDOT owned traffic signal systems, install APS pushbuttons and
countdown displays. For any project which has completed its scoping phase
before August 1, 2018, consult with your ASDE to determine if APS
pushbuttons and countdown pedestrian displays can be added to the
project – documentation is not required if the project cannot support the
expanded scope of work.
ii. For traffic signal systems owned by other agencies, install APS pushbuttons
and countdown displays if funded by the owning agency.
b. At any signalized intersection where APS pushbuttons are being installed in
response to a public request, replace all pushbuttons and pedestrian displays with
APS pushbuttons and countdown pedestrian displays at that intersection. Additional
poles may be required and ramp and sidewalk work may be necessary to support
access to new APS locations / orientations.
c. For any other project, not previously described, which requires traffic signal system
work affecting pedestrian pushbuttons, replace all pushbuttons and pedestrian
displays with APS pushbuttons and countdown pedestrian displays. This may require
additional ramp and sidewalk work to provide required accessibility to and for APS
locations / orientations beyond that already required for other ADA compliance
efforts.
Signal displays may also be mounted to bridges where clearance will not allow an alternate
signal standard type. Installation on bridges requires approval of both the region Traffic
Engineer and the HQ Bridge and Structures Office.
When placing signal standards, the primary consideration is the visibility of signal faces. Place
the signal supports as far as feasible from the edge of the traveled way without adversely
affecting signal visibility. (The MUTCD provides additional guidance on locating signal supports.)
Initially, lay out the location for supports for vehicle display systems, pedestrian detection
systems, and pedestrian display systems independently to determine the optimal location for
each type of support. Consider the need for future right-turn lanes or intersection widening
when choosing the final location of the signal standards. Poles should also be located outside of
sight triangles for turning traffic.
If conditions allow and optimal locations are not compromised, pedestrian displays and
pedestrian detectors can be installed on the vehicular display supports. However, pole
placement cannot encroach on pedestrian access route or maneuvering space requirements.
Pole mounted appurtenances, such as pushbuttons, terminal cabinets, and displays, need to be
taken into consideration regarding their encroachment into accessible spaces.
Another important consideration that can influence the position of signal standards is the
presence of overhead and underground utilities. Verify the location of these lines during the
preliminary design stage to avoid costly changes during construction:
b. Overhead Utilities: Signal standards may be located within close proximity to overhead
communications lines (phone, cable, fiber-optic), but the lines should not touch the any
part of the signal system and should not pass in front of any displays. Overhead power
lines require a minimum 10-foot circumferential clearance for lines rated at 50kV (50,000
V) or below, including the neutral. For lines rated over 50kV, the minimum clearance is 10
feet plus 0.4 inches for each kV over 50kV. Overhead utilities may have to be relocated if a
suitable location for signal equipment cannot be found.
Once pole locations have been selected, a soils investigation is required to determine the lateral
bearing pressure, the friction angle of the soil, and whether groundwater may be encountered.
Standard foundations may be used if the soil lateral bearing pressure is at least 1,000 psf, the
friction angle is at least 17°, and the ground slope is 2H : 1V or flatter. Standard foundation
information is found in the Standard Plans, and depends on the type of support system being
used.
Special foundation designs are required if the soil lateral bearing pressure is less than 1,000 psf,
the friction angle is less than 17°, or the ground slope is steeper than 2H : 1V. The region
materials group works with the HQ Materials Laboratory to determine the bearing pressure and
friction angle of the soil at the proposed foundation locations. If soils do not meet these
minimum values for lateral bearing pressure and friction angle, the signal standard charts and
soil conditions report (summary of geotechnical conditions for foundations) must be forwarded
to the HQ Bridge and Structures Office with a request for special foundation design. The HQ
Bridge and Structures Office designs foundations for the regions and reviews designs submitted
by others.
Where poles are installed on structures, the anchorage must be designed by the Bridge
designer. Coordinate with the Bridge designer for placement and design of pole anchorages on
structures.
Do not place any signal standard in a median area. The sole exception is a Type PS or Type PPB
signal standard as required for median refuge areas for pedestrians.
Coordinate with all stakeholders (Maintenance, Signal Operations, Civil Design Engineer,
Drainage Engineer, and so on) in the placement of signal equipment to avoid any possible
conflicts. Arrange field reviews with the appropriate stakeholders as necessary.
1330.04(5)(a) Mast Arm Signal Standards and Foundation Design
Mast arm signal standards are normally located on the far right corner of the intersection from
approaching traffic. A typical mast arm signal standard only has one mast arm, however two
may be used. If the angle between the two arms is not exactly 90 degrees, the design must be
sent to the bridge and structures office. In most cases, two arms at 90 degrees can support the
necessary display positioning. Additionally, signal standards on mast arms may be rotated up to
30 degrees from center. Do not allow a mast arm for one direction to cross in front of the mast
arm for a different direction if possible, as it results in a visual obstruction of the signal displays.
Where two double arm signal standards are installed on opposite corners, the preferred
location for the two poles are the far right corners of the mainline roadway. This way, the mast
arms for the mainline traffic will not cross in front of each other.
Mast arm signal standards have a typical arm attachment point of 18 to 20 feet in height. This
height range needs to be taken into consideration when placing signal displays in order to
ensure that the display height requirements shown in 1330.04(3) are met. The attachment point
height may be adjusted throughout this range as necessary, but increments of 0.5 feet are
recommended for ease of fabrication. Connection points outside of this range are a special
design, and require design support from the Bridge and Structures Office.
Mast arm signal standards are designed based on the total wind load moment on the mast arm.
The moment is a function of the surface area of each appurtenance (signal display or sign), X * Y,
and the distance between the vertical centerline of each appurtenance and the vertical
centerline of the signal pole Z. This determines the total wind load moment, referred to as an
XYZ value and measured in cubic feet, which is used to select the appropriate mast arm
fabrication plan and foundation design. Preapproved mast arm fabrication plans are available at
http://www.wsdot.wa.gov/Bridge/Structures/LSS.htm, and will be listed in the Contract
Provisions. To determine the XYZ value for a signal standard, the XYZ value of each
appurtenance must be calculated. These values are then totaled to determine the overall XYZ
value for the signal standard. For signal standards with two mast arms at 90 degrees apart, the
larger of the two XYZ values calculated for each mast arm is used for the overall pole XYZ value.
When determining the XYZ values, use the worst-case scenarios for signal display and sign
placements. All signal displays and mast arm-mounted signs, including street name signs, must
be included in this calculation. Emergency preemption detectors, preemption indicator lights,
cameras, and radar detectors are negligible and are not included in determining the XYZ values.
For mast arm-mounted signs, use the actual sign area (in square feet) to determine the XYZ
value. For poles with luminaire supports, the luminaire and arm is also included in the total XYZ
calculation. Surface areas for vehicle displays are shown in Exhibit 1330-13. Signs are limited in
size as follows:
Street name signs may be a maximum of 36 inches in height and 36 square feet in total
area. Design the mast arm to support the widest sign that will fit within these limits (up
to 144 inches wide), regardless of the actual sign size needed. This allows for future
changes to the street name sign. Street name signs are mounted such that the edge of
the pole is no less than 1 foot but no more than 2.5 feet from the vertical pole
centerline, as shown in the Standard Plans. Use the offset necessary for the largest
possible sign in the signal standard chart for the XYZ value, but refer to the Standard
Plans for actual sign installation requirements using construction notes in the Contract
Plans.
Other mast arm mounted signs may not exceed 36 inches in height and 7.5 square feet
in area.
Signs mounted on the vertical pole may not exceed 36 inches in width and 15 square
feet in area. These signs are not included in the XYZ calculation.
After calculating the total XYZ value, adjust the total XYZ value as follows:
If the total XYZ value is less than or equal to 2850 ft3, round the XYZ value up to the next
standard foundation XYZ value or 2850 ft3, whichever is lower, to determine the design XYZ
value. The design XYZ builds in some flexibility for future modifications.
If the total XYZ value exceeds 2850 ft3, use the calculated XYZ value. There is limited
opportunity for future increased wind load when the XYZ value exceeds 2850 ft3.
After the total XYZ value is determined, if a standard foundation may be used, select the correct
foundation depths for the XYZ values from the table in the Standard Plans, using the next higher
total XYZ value. For WSDOT systems, only the 700, 1350, 1900, 2600, and 3000 columns may be
used. All five foundation options should be provided unless there is a known constraint
preventing the use of one of the options, such as insufficient space for 4 ft diameter foundation
or expected loose soil requiring the use of the Alternate 2 foundation construction.
Span Wire Systems use poles and aerial wires to support signal displays, signs, and emergency
preemption equipment. Cameras, radar detectors, and street name signs are installed on the
vertical strain poles. When laying out span wires, the preferred layout is similar to mast arm
supports. Displays for an approach should be installed on a span on the far side of the
intersection, with poles on the two far corners. Do not use diagonal spans unless absolutely
necessary, as they are extremely difficult to maintain and if the wire is broken, the entire signal
system is lost and blocks the entire intersection, rather than the equipment for only one
approach.
Span wire signal standards include both steel and timber strain poles. Steel and timber strain
poles are designated by pole class, which is based on the horizontal tension load the pole will
support. The loads and resultant forces imposed on strain poles are calculated and a pole class
greater than that load is specified. Steel Pole Classes and their allowed tension loads are listed in
the Standard Plans. Exhibit 1330-14 lists the pole classes and tension loading available for
timber strain poles.
Headquarters Traffic and Headquarters Bridge and Structures office support is required for
determining span tension load and pole classes. Provide the pole and span layout, the locations
and sizes of all signal displays and span wire mounted signs, and the soils report. Span wire
mounted signs are limited to a maximum of 36 inches in height and 7.5 square feet in area.
Emergency preemption equipment locations do not need to be submitted, as they are not
included in load calculations. Spans should not exceed 150 feet, if possible, in order to reduce
the complexity of the design.
After the pole classes are provided by the Headquarters Bridge and Structures office, select the
appropriate foundation information from the Standard Plans using the pole classes and soil
conditions. If a standard foundation cannot be used, a foundation design will be provided along
with the pole class information.
2 3700
1 4500
H1 5400
H2 6400
H3 7500
Special case signal supports include signal bridges and structure (typically bridge) mounts. These
should only be selected if absolutely necessary, as they are difficult to design, construct, and
maintain, and they frequently result in signal display locations that are difficult for drivers to
see. Use of these types of supports requires approval from the Headquarters Traffic Office.
Signal bridges function the same as a diagonal span wire system, with the two supports on
opposite corners of the intersection. Signal bridges require windload calculations similar to mast
arm signal standards, so display and sign locations and offsets must be provided. Signal bridge
foundations must be designed by the Headquarters Bridge and Structures office.
Signal displays and other equipment may be installed on structures when there is insufficient
clearance below the structure to allow for a different type of signal support. Coordinate with the
Bridge designer to place mounts and determine routing paths for conduit and wiring out of the
structure. Structure mounts are not desirable, as they typically cannot be modified without
reconstruction of the structure itself, and any equipment embedded in the structure is
inaccessible after the structure is complete.
Signal displays may not be installed on sign structures such as cantilever sign structures or sign
bridges. Signal displays also may not be installed on railroad cantilever structures unless the
signal system and the railroad are owned by the same jurisdiction and maintained by the same
staff.
Vertical steel shaft supports include the following types of signal standards:
(a) Type PPB: Sometimes referred to as a “stub pole”, this pole is typically 5 feet tall and 3
inches in diameter. It is used strictly to support pedestrian pushbuttons. Due to the
frequency of damage, regardless of location, it is recommended that breakaway bases
always be used.
(b) Type PS, I, RM, and FB: These poles are effectively identical, with the difference being
the total height to the slipfitter top.
Type PS are 8 ft tall and may only have pedestrian displays mounted on the
top.
Type I are 10 ft tall and may have vehicle displays mounted on the top and
pedestrian displays mounted on the side. Type RM are identical to Type I but
are used for ramp meter systems only.
Type FB are 14 feet tall, and may be used like Type I when additional height is
needed for the vehicle display(s).
Placement of vertical steel shaft supports will depend on visibility requirements for displays and
accessibility requirements of pedestrian features. Generally, these supports should be located at
back of sidewalk, as they are farther from traffic and more likely to be out of both the
pedestrian access route and the path of any users. Fixed bases should be used when located at
the back of sidewalk, but slip bases may be used if circumstances recommend it. Supports
located within sidewalk (includes planter strips) or in locations with only paved shoulders should
always use slip bases.
The detection system at a traffic-actuated signal installation provides the control unit with
information regarding the presence or movement of vehicles, bicycles, and pedestrians. Vehicle
detection systems perform two basic functions: queue clearance and the termination of phases.
Depending on the specific intersection characteristics, either of these functions can take
priority. The merits of each function are considered and a compromise might be necessary.
There are two basic types of detection zones: stop bar and advance. Stop bar detection is a zone
that extends from the stop line to a point 30 to 40 feet in advance of that location. Advance
detection is a discrete zone (or zones) placed in advance of the stop line at a distance dependent
on vehicle speed.
Basic vehicle detection requirements depend upon the speeds of the approaching vehicles:
(a) When the posted speed is below 35 mph, provide stop bar detection or one advance
detection zone. See Exhibit 1330-15 for advance detection zone distances.
(b) When the posted speed is at or above 35 MPH, provide stop bar detection and at least
two advance detection zones. Multiple advance detection zones are normally required to
accommodate decision zone detection.
(c) Side street advance detection is not required for WSDOT owned signal systems, but may
be provided through means that do not require equipment to be installed off of WSDOT
right of way. For signals owned by other jurisdictions, the use of side street advance
detection is at the discretion of the owning jurisdiction.
A decision zone is a location along the intersection approach where a motorist is forced to make
a decision between two alternatives. As applied to vehicle detection design, this situation can
occur when two vehicles are approaching a traffic signal and the signal indication turns yellow.
The motorist in each vehicle must decide whether to continue through the intersection or stop
prior to the intersection. If the lead vehicle decides to brake and the following vehicle does not,
there may be a rear-end crash.
For posted speeds of 35 MPH or higher, there are two options for placing advance detectors to
address the decision zone:
1. Fixed locations based on posted speed, which is generally the 85th percentile speed. Place
loops according to the table in Exhibit 1330-15.
2. Calculated locations based on calculated decision zone detection design. This design
increases the opportunity for a range of vehicles from the 90th percentile speed vehicle to
the 10th percentile speed vehicle to either clear the intersection or decelerate to a
complete stop before reaching the intersection. The method of calculating the decision zone
and the required detection loops is shown in Exhibit 1330-16.
Although the exhibits reference loops, advance detectors may be of any approved type.
For new intersection construction where there is no existing traffic, the fixed locations based on
posted (target design) speed are to be used. Fixed locations based on posted speed use the
same methods as the calculated decision zone detection design, but set V90 at 5 MPH above
posted speed and V10 at 5 MPH below posted speed. Engineering judgment based on similar
intersections (such as geometrics and traffic volumes) may justify modifying the V90 and V10
speeds used in the calculation, with concurrence from the region Signal Operations Engineer.
Both methods require a study of the approach speeds at the intersection. For intersection
approaches, conduct the speed study as follows:
Collect data at the approximate location or just upstream of the decision zone;
Collect data during off-peak hours in free-flow and favorable weather conditions;
Collect data during regular commuting hours in a high volume signalized corridor
during favorable weather conditions
Only document the speed of the lead vehicle in each platoon.
It is important that the person conducting the speed study remain inconspicuous so they do not
influence drivers to slow down. Normal driving patterns are needed for proper speed studies.
Prior speed-study information obtained at this location may be used if it is less than 18 months
old and driving conditions have not changed significantly in the area.
Preserve detection zone placements and any supporting calculations as required by 1330.07
Documentation.
For posted speeds below 35 MPH, only the PMID detection location is used.
(V90 )2
UDZ90 = +V90
16
(V10 )2
DDZ10 = +V10
Single Advanced Loop Design UDZ90 -DDZ10 40
LC1 =
Use when LC1 ≤ 3 seconds V10
Where grades are +/- 4% or steeper:
(V90 )2
UDZ90 = +V
2(8+32.2G) 90
(V10 )2
DDZ10 = +V
2(20+32.2G) 10
Where:
V90 = 90th percentile speed, in feet per second G = Grade of roadway, in decimal form,
V10 = 10th percentile speed, in feet per second including + or – (Example: -4% = -0.04)
UDZ90 = Upstream end of decision zone, LC1 = V10 travel time to DDZ10
for 90th percentile speed LC2 = V10 travel time from UDZ90 to PMID
DDZ10 = Downstream end of decision zone, LC3 = V10 travel time from PMID2 to DDZ10
for 10th percentile speed
Non-Invasive: These are detectors installed outside of the roadway, typically overhead in a
strategic location. These include camera (optical and infra-red) and radar systems.
In-Pavement: These are detectors which are installed in the road itself. These include
induction loops and wireless in-pavement sensors.
Stop line detection should use non-invasive systems for detection. Although induction loop
detectors are typically the most reliable for detecting cars and trucks, they do not consistently
detect bicycles and motorcycles. RCW 47.36.025 specifically requires that vehicle-activated
traffic control signals be capable of detecting motorcycles and bicycles.
Selection of detector types will depend on a variety of environmental factors and locations
available for placement.
1. Radar Detectors
Radar detectors are located on either the signal mast arms or the signal vertical strain poles,
depending on lane configuration, detector type, and location availability. Radar detectors
are not affected by weather, and are typically minimally affected by mast arm motion in
high wind. Consult the detector manufacturer’s installation guidance for placement details.
One detector can normally cover all lanes of an approach for that type of detection (stop
line or advance).
2. Video Detectors
Placement of video detectors depends on the function of the detector. Exhibit 1330-17
provides placement examples.
Stop line detectors should be installed on the same mast arm as the vehicle displays for that
approach. The detector should be placed on an extension of the wide line between the left
turn and through lanes, if present; if there is no wide line, the detector should be centered
on the through lanes. One detector can cover all lanes of an approach for that type of
detection (stop line or advance).
Advance detectors should be installed on a luminaire arm, preferably on the adjacent corner
to the approaching lanes, as the effectiveness of the advance detection depends on height.
Consider requiring a luminaire arm even if no luminaire is needed, in order to provide an
optimal installation site for the detector. Advance detectors may be installed on a mast arm,
but will typically have less effective range.
Both infra-red and optical cameras are available, but optical cameras are not recommended
due to the adverse effects of rain, snow, fog, sun glare, and sharp shadows on their
effectiveness. However, infra-red cameras may still be affected by heavy fog or other major
thermal events. All video detection may be affected by mast arm motion due to high winds.
Exhibit 1330-17 Video Detector Placement
3. Induction Loops
Induction Loops are coils of wire in the roadway that use the magnetic properties of vehicles
to detect them. Induction loops can last a very long time when undisturbed. However,
induction loops require bicycles to be in a very specific location in order to be detected, and
may not detect carbon fiber bicycles. Induction loops must be installed with one per lane
per detection zone – stop line loops may be larger or series loops. Where induction loops
are used, loops need to be numbered in order to keep track of the wiring and lanes they are
detecting. See 1330.04(2) for detector numbering requirements.
4. Wireless In-Pavement Sensors
Wireless in-pavement sensors are compact detectors installed in pavement, and use either
radar or magnetics to detect vehicles. They use a wireless connection to the signal cabinet.
The sensors rely on a battery for operation, and require replacement of the entire unit when
they fail. Sensor placement is similar to induction loops – one per lane per detection zone.
The magnetic versions are subject to the same difficulties with bicycles as loop detectors. All
wireless sensors are also subject to various factors that affect wireless signals such as range,
signal obstructions, and possible signal interference from other radios depending on the
frequency used.
Non-invasive detectors are preferred with concrete (Portland cement concrete pavement)
roadway surfaces. In-pavement detectors installed in concrete panels typically cannot be revised
or replaced until all affected concrete panels are replaced. In-pavement detectors installed in
bridge decks must be installed when the bridge deck is constructed, and cannot be replaced
unless the bridge deck is replaced. Non-invasive detection is also useful for approaches where
advance detection is desired, but the approach is outside the jurisdiction of the agency that
owns the signal, or for non-standard approaches such as driveways.
Temporary detection should be installed for all stop lines where existing detection will be
disabled or ineffective (such as lane shifts) during construction. Temporary advance detection is
recommended for high speed (45 MPH or higher) approaches where the decision zone detection
will be disconnected for an extended period of time. Consult with the Signal Operations
Engineer to determine if temporary advance detection should be used. Temporary advance
detection zone placement should take into account any temporary speed limit revisions.
Emergency vehicle preemption (EVP) is required for all traffic signals unless approved otherwise
by the region Traffic Engineer. WSDOT is responsible for installing EVP detection equipment at
new and rebuilt signalized intersections on state highways. At existing signalized intersections
that do not have EVP detection equipment, or where an emergency service agency requests
additional equipment beyond the basic required equipment, the emergency service agency is
responsible for all material and installation costs. The emergency service agency is responsible
for preemption emitters in all cases.
Optically activated EVP systems are used to ensure compatibility with all area emergency service
agency emitters. Approval by the State Traffic Engineer is required for the installation of any
other type of emergency vehicle preemption system.
Locate optical detectors facing each approach to the intersection – only one detector per
approach – with a clear view of the approaching roadway. Detectors have a cone of vision of
approximately 8 degrees, and an effective range of 200 to 2500 feet. Detectors should have an
unobstructed view of the approach for a minimum of 1800 feet. Primary detectors are normally
installed on the same support as the vehicle displays for that approach. Place the detector
between the left turn lane and through lane displays on approaches with left turn lanes, or
centered on the approaching lanes where left turn lanes are absent.
When the approach is in a horizontal or vertical curve, or there are other sight obstructions,
non-standard placement of the primary detector or additional supplemental detectors may be
necessary. Primary detectors may be located on other signal display supports (arms or spans) or
vertical strain poles, depending on visibility requirements. Supplemental detectors may also be
located on separate Type I or Type FB poles in advance of the intersection. On higher speed
roadways, supplemental detectors can provide extended detection range – one mile in advance
of the intersection is usually sufficient.
Preserve any documentation associated with the EVP system, including system type selected
and any associated agreements or approvals, as required by 1330.07 Documentation.
The Railroad Crossing Evaluation Team will determine what design considerations are needed at
all signalized intersections near railroad crossings. For locations where the railroad tracks are
located greater than 500 feet from the signalized intersection, and it can be demonstrated that
the 95% maximum queue length(s) will not extend to within 200 feet of the tracks, railroad
preemption may be omitted with the approval of the Railroad Crossing Evaluation Team. Include
the demonstration and approval in the documentation required by 1330.07 Documentation.
Railroad preemption and interconnection are recommended when any of the following
conditions occurs:
The distance from the stop bar to the nearest rail is less than or equal to 200 feet.
There is no dedicated left turn lane and the distance from the stop bar to the nearest
rail is less than or equal to 500 feet.
The 95% maximum queue lengths from the intersection stop bar are projected to cross
the tracks. (Use a queue arrival/departure study or a traffic analysis “micro-simulation
model” to determine 95% maximum queue lengths.)
The 95% maximum queue lengths from the railroad are projected to affect an
upstream traffic signal. (Use a queue arrival/departure study or a traffic analysis
“micro-simulation model” to determine 95% maximum queue lengths.)
If it is determined that advanced preemption is needed, the HQ and region Signal Operations
Engineers will calculate the amount of railroad preemption time required using the Guide for
Determining Time Requirements for Traffic Signal Preemption at Highway-Rail Grade Crossings
(TxDOT Form 2304).
The addition of a pre-signal is recommended when any of the following conditions occurs:
The distance from the stop bar to the nearest rail is less than 88 feet but is at least 40
feet. (For reference, the 88 feet is derived from: the longest design vehicle permitted
by statute (75 feet) + front overhang (3 feet) + rear overhang (4 feet) + downstream
clear storage (6 feet)).
The distance from the stop bar to the nearest rail is > 88 feet and < 120 feet and there
are no gates for the railroad crossing.
The sight distance triangle in Chapter 1350, Exhibit 1350-1 (Sight Distance at Railroad
Crossing), cannot be met, and the railroad crossing does not have active control (lights
or gates).
When pre-signals are used, two stop lines are used: one for the rail crossing, and one for the
intersection. The pre-signal displays stop traffic at the rail crossing stop line, and the second set
of signal displays stop traffic at the intersection. Use louvers on the intersection displays so that
they are not visible from the stop line for the rail crossing. Optically programmed displays may
be used in place of louvers, but are not recommended due to the limited benefits, complexity of
installation and maintenance, and high cost.
Where the distance between the normal location for the stop bar and the approach is less than
40 feet, the same stop bar should be used for both the traffic signal and the rail crossing. Install
vehicle displays on the near side of the intersection, but on the far side of the tracks from the
stop line, to improve visibility and discourage drivers from stopping between the tracks and the
intersection. Do not install vehicle displays on the far side of the intersection.
Exhibit 1330-18 shows examples of the distances and typical system layouts referenced above.
The Railroad Crossing Evaluation Team has final review and approval authority for all PS&E
documents for signal design and operation at all signalized intersections near railroad crossings.
All documentation associated with railroad preemption and a memo with each team member’s
concurrence with the PS&E documents must be preserved as required by 1330.07
Documentation.
Display Placement
Less than 40 feet between tracks (dynamic envelope marking) and intersection
Display Placement
40 to 88 feet between tracks and intersection
Transit Priority Preemption allows for transit operations to influence signal timing, similar to
emergency vehicle preemption. This can be included in mobility projects, but the transit agency
assumes all costs for providing, installing, and maintaining this preemption equipment. WSDOT’s
role is limited to approving preemption operational strategies (phasing, timing, software, and so
on) and verifying the compatibility of the transit agency’s equipment with the traffic signal
control equipment. Preserve all transit priority preemption decisions and agreements as
required by 1330.07 Documentation.
Type 2070 controllers and newer NEMA controllers are functionally equivalent for basic signal
operations. However, Type 2070 controllers and NEMA controllers use different operating
software and communications protocols, and therefore cannot be interconnected together. The
type of controller should be specified as follows:
1. For WSDOT traffic signals, specify Type 2070 controllers, unless:
a. The signal is interconnected with other signals. If the other controllers in the
interconnected system are not being replaced, specify a controller (2070, NEMA, or
other) that matches the rest of the interconnected system.
b. The signal is operated by another agency. In this case, work with WSDOT and the other
agency’s maintenance staff to determine the appropriate controller type.
2. For traffic signals owned by other agencies, specify the controller type used by that agency.
The region or operating agency will determine the controller brand and operating software,
which are included in the cabinet specifications. Each region or operating agency will provide
specifications for their cabinets and the equipment contained therein. For 2070 controllers,
double-width cabinets (two racks) should be specified if physically possible to allow for future
communications and ITS equipment.
It is often beneficial for one of the agencies to assume responsibility for the operation of the
traffic signals. This is accomplished by negotiating an agreement with the other agency. The
designer needs to check region policy and make sure someone initiates the process for setting
up an operational agreement with the other agency or modifying an existing agreement when
applicable. (See the Agreements Manual for more information on signal systems and
maintenance agreements.) At a new intersection, where the state owns the signal, but WSDOT
has agreed to let another agency operate the signal, the controller should be compatible with
that agency’s system. When installing a new controller in an existing interconnected corridor,
the controller should be capable of operating with the existing controllers in the corridor. In
situations where it is necessary to coordinate the traffic movements with another agency, it is
important that the agencies work together.
Intersections within ½ mile of each other on state highways should be interconnected. Perform
an operational analysis to determine need for interconnection where intersections are within 1
mile of each other on state highways with a posted speed of 45 MPH or higher. The preferred
method for interconnection is fiber optic cable, but other methods such as IP over copper or
wireless interconnect may be considered after discussion with maintenance staff and approval
by the region Traffic Engineer. Where fiber optic cable is used, it must be routed through pull
boxes and cable vaults – bending fiber optic cable through standard junction boxes typically
results in the cable being broken. Consider using a separate pull box or vault for coiling the fiber
optic interconnect cable to allow for the large-bend radii. Add a construction note in the plans
stating to coil additional cable in the adjacent pull box or vault, not the controller cabinet. This
will save on space in the controller cabinet and provides additional cable in case an errant
vehicle hits the cabinet.
Coordinate with the operations and maintenance staff to determine the optimum controller
cabinet location and the cabinet door orientation. The controller cabinet is positioned to
provide the best maintenance access and clearest view of the intersection possible. Preferred
visibility allows for as many signal displays and roadway approaches visible as possible from a
single location. Cabinets should not be placed where they might block the view of turning traffic
(intersection sight triangle). If possible, position the controller where it will not be affected by
future highway construction.
Cabinets require a minimum of 36 inches of level space in front of each door, including the
concrete pad. Do not place cabinets where flooding might occur or where the cabinet might be
hit by errant vehicles. If there is a steep down slope or drop off near the cabinet, personnel fall
protection (such as fencing) is required in accordance with standards established by the
Department of Labor and Industries. Fall protection may not encroach on the required clear
space for the cabinet. The location must also have adequate room for a maintenance vehicle to
park near the cabinet. Sufficient space for a bucket truck to park is preferable.
If a telephone line (voice or DSL), fiber optic, wireless, or other connection is desired for remote
access to the equipment in the cabinet, provide the appropriate equipment in the controller
cabinet and/or nearby junction box or cable vault with separate conduits and junction boxes for
the remote communications equipment. Communications connections to outside utilities
require their own separate conduit and box/vault system.
Consult with maintenance and operations staff to determine if a backup power source, such as
an Uninterruptible Power Supply (UPS) or backup generator, is needed for the signal cabinet.
Install the backup power supply on the same concrete pad as the signal cabinet. Service and
other cabinets may also be installed on the same concrete pad as the signal cabinet (see the
Standard Plans for concrete cabinet pad layouts). Refer to Chapter 1040 for electrical service
types, overcurrent protection, and descriptions and requirements for other components.
Traffic signal systems use multi-conductor cables to connect most of the equipment. Single
conductor cable is limited to cabinet power and street lighting circuits.
To simplify potential repairs for smaller signal standards (Type FB and smaller), consider routing
signal display and detection conductors through terminal cabinets on larger signal standards
(Type II and larger) before connecting to smaller signal standards. This reduces the amount of
wire which may need to be replaced if a smaller signal standard is knocked down and the wiring
damaged.
1330.04(9)(b) Conduit
1. Conduits entering Type PPB signal standards shall be 1 inch. This may be increased to 1 1/4
inch when two APS PPBs are installed on the same pole.
2. Lighting conduits entering pole foundations (signal or light standards) shall be a minimum of
1 inch. See Chapter 1040 for additional requirements for light standards with slip bases.
3. Conduits entering Type PS, I, RM, and FB poles may be a minimum of 1-inch and a maximum
of 2-inch.
4. The conduit for the service grounding electrode conductor may be a minimum of ½-inch.
Install spare conduits at all road crossings. Spare conduits at road crossings should be a
minimum of one 3-inch conduit or two 2-inch conduits. Install a minimum 2-inch (preferably 3-
inch) spare conduit into the controller cabinet.
It is recommended to use full inch conduit sizes to simplify construction and reduce the different
types of conduits required for the system. This helps to provide future capacity and reduce costs
through bulk material purchasing. Size all conduits to provide 26% maximum conductor fill for
new signal installations. A 40% fill area can be used when installing conductors in existing
conduits. (See Exhibit 1330-19 for conduit and signal conductor sizes.)
Minimize roadway crossings whenever possible. Usually only three crossings are needed (one
main line) for a four-leg intersection, and only two roadway crossings are needed for a T
intersection. In most cases, the conduit should cross both the main line and side street from the
corner where the controller is located.
Directional boring should normally be used when crossing the state route (main line). Open cut
trenching may only be used to install conduits under the following circumstances:
1. Existing roadways where the roadway is being resurfaced.
2. Existing roadways where substantial obstacles under the roadway will be encountered.
3. Where there is insufficient room for jacking or boring pits at the edges of the roadway.
Open cut trenching is not permitted across limited access roadways unless the entire pavement
surface is being replaced. Sign or signal bridges may not be used for roadway crossings.
Where possible, locate junction boxes out of paved areas and adjacent to (but not in) sidewalks.
New junction boxes may not to be placed in the pedestrian curb ramp or ramp landing of a
sidewalk. If a new junction box must be placed within sidewalk, locate it at the edge of the
sidewalk and designate it to be slip-resistant. Existing junction boxes located within new or
existing sidewalk, including ramps or landings, must be revised as follows:
Existing junction boxes containing power conductors for the traffic signal (not including
street lighting), or wiring for the signal displays, may remain in place, even if they will
be within a sidewalk ramp or ramp landing.
Existing junction boxes containing detector wiring may remain in sidewalks, but must
be relocated outside of sidewalk ramps and ramp landings. Designate that the
relocation work, including conduit adjustments and rewiring, be completed within a
single shift or provide temporary detection using another conduit path.
All junction boxes which will be within sidewalk, sidewalk ramps, or ramp landings,
must be slip-resistant junction boxes. This includes replacing existing junction boxes
with slip-resistant junction boxes.
Under no circumstances may a junction box be located in a grade break for a sidewalk
ramp. Either the ramp must be redesigned or additional accommodations made in
construction to allow for the box to be relocated.
The fundamental principle is that if relocating a junction box requires shutting down a traffic
signal system, the junction box may remain in its existing location but must be replaced with a
slip-resistant junction box. See Chapter 1510 for additional ADA requirements.
Do not place junction boxes within the traveled way unless absolutely necessary. Make every
effort to locate new junction boxes and to relocate existing junction boxes outside the travel
lane or paved shoulder. If there is no way to avoid locating the junction box in the traveled way
or paved shoulder, heavy-duty junction boxes must be used. Avoid placing junction boxes in
areas of poor drainage. Do not place junction boxes within 2 feet of ditch bottoms or drainage
areas, or within vegetative filter strips or similar water treatment features which may be
present. The maximum conduit capacities for various types of junction boxes are shown in the
Standard Plans.
Submit a copy of the preliminary signal plan to the State Traffic Engineer for review and
comment. A preliminary signal plan must be submitted to the State Traffic Engineer regardless
of the originator of the design. Allow two to three weeks for review of the preliminary signal
plan. After addressing all review comments, finalize the plan and preserve as required by
1330.07 Documentation. Prepare the contract plans in accordance with the Plans Preparation
Manual.
If HQ Traffic is preparing the contract Plans, Specifications, and Estimate (PS&E) package for the
signal system portion of the project, submit the following items with the preliminary signal plan:
1. Contact person.
2. Charge numbers.
3. Critical project schedule dates.
4. Existing and proposed utilities, both underground and overhead.
5. Existing intersection layout, if different from the proposed intersection.
6. (Turning movement traffic counts (peak hour for isolated intersections) and a.m., midday,
and p.m. peak-hour counts if there is another intersection within 500 feet.
7. Electrical service location, source of power, and utility company connection requirements.
After the PS&E package for the signal system portion of the project is prepared, the entire
package is transmitted to the region for incorporation into its contract documents.
c. Drainage items.
g. Illumination treatment, including a calculation summary showing the average light level,
average/minimum uniformity ratio, and maximum veiling luminance ratio. (See Chapter
1040 for more information on illumination design requirements.)
i. Speed study information indicating 90th, 85th, and 10th percentile speeds for all
approaches. For any new approach, or any approach where the existing speed will
change, the design posted speed may be provided instead.
All traffic signals should be periodically re-evaluated, to determine if timing or phasing changes
would result in more efficient operation of the traffic signal, or in the case of interconnected
systems, the corridor or network. Changes in traffic volumes, posted speeds, or other factors
may influence turning movement phasing operations (protected, protected/permissive, or
permissive), green times, yellow change intervals, and other operational parameters.
For permissive left turns, the permissive left turn phase shall not terminate separately from
the conflicting phase(s) (typically, the opposing through phase). This is to prevent placing
left turning traffic in a yellow trap.
1. Permissive Left-Turn Phasing
Permissive left-turn phasing requires the left-turning vehicle to yield to opposing through
traffic and pedestrians. Permissive left-turn phasing is used when the following are true:
This phasing is more effective on minor streets where providing separate protected turn
phasing might cause significant delays to the higher traffic volume on the main street. On
single-lane approaches with a posted speed of 45 mph or above, or where sight distance
approaching the intersection is limited, channelization should include a separate left-turn
storage lane for the permissive movement to reduce the potential for rear-end-type
collisions and delay to through movements.
Unless there is a dedicated left-turn lane, do not provide a separate display for permissive
left turns. When there is a dedicated left-turn lane, a three-section flashing yellow arrow
display (with steady red arrow, steady yellow arrow, and flashing yellow arrow displays)
should be used for the left-turn lane, as this provides a more positive indication of the
permissive turning movement.
2. Protected/Permissive Left-Turn Phasing
a. For new signals, on an approach where Warrant 7 is met and there are five or more left-
turning collisions on that approach included in the warranting collisions. This condition
requires protected left turn phasing.
b. For existing signals, when documentation shows that existing protected left-turn phasing
was installed due to left-turn collisions.
c. When sight distance for left-turning vehicles, as outlined in AASHTO’s A Policy on the
Geometric Design of Highways and City Streets, cannot be met.
d. On intersection approaches where the opposing approach has three or more lanes
(including right-turn lanes) and either the posted speed limit or 85th percentile speeds
for the opposing approach are at or above 45 mph.
e. On intersection approaches that have dual left-turn lanes, including approaches with left
only and through-left lanes.
Where there is a separate left-turn lane, protective/permissive displays may use either of
the following display arrangements:
A dedicated four-section arrow display, with steady red arrow, steady yellow arrow,
flashing yellow arrow, and steady green arrow displays (four-section FYA). A three-
section display with a bi-modal flashing yellow arrow / steady green arrow may only
be used if the signal support cannot accommodate a four-section signal display.
A shared five-section cluster (doghouse) display, placed over the wide line between
the left turn lane and the adjacent through lane.
Protected/permissive displays may run as lead or lag. The display cycle will depend on the
display type and whether the protected left leads or lags:
Leading 4-section FYA: steady green arrow, steady yellow arrow, steady red arrow,
flashing yellow arrow, steady yellow arrow, steady red arrow.
Leading 5-section: green arrow, yellow arrow, red ball, green ball, yellow ball, red
ball. Option: green ball may come up with green arrow, but the arrow and ball
displays should cycle to yellow and red together (similar to lagging 5-section)
Lagging 4-section FYA: flashing yellow arrow, steady green arrow, steady yellow
arrow, steady red arrow
Lagging 5-section: green ball, green ball with green arrow, yellow ball with yellow
arrow, red.
Protected left-turn phasing provides the left-turning vehicle a separate phase, and
conflicting movements are required to stop.
a. Multi-lane left turn movements, including left and through-left from the same approach.
c. Where Warrant 7 is met and there are five or more left-turning collisions on that
approach included in the warranting collisions. Protected left-turn phasing is
recommended even when there are as few as three left-turning collisions on that
approach. This includes left-turning collisions involving pedestrians.
d. Where the peak-hour turning volume exceeds the storage capacity of the left-turn lane
and one or more of the following conditions is present:
i. The posted speed or the 85th percentile speed of the opposing traffic is 45 mph or
higher.
ii. The sight distance to oncoming traffic is less than 250 feet when the posted or 85th
percentile speed is 35 mph or below, or less than 400 feet when the posted or 85th
percentile speed is above 35 mph.
iii. The left-turn movement crosses three or more lanes (including right-turn lanes) of
opposing traffic.
There are three typical operational arrangements for protected left turns:
Leading Lefts: The left turns are served before the associated through movements.
This is the most common operational arrangement. Example: Phases 1 and 5 (major
street lefts) are served first, then phases 2 and 6 (major street throughs) are served.
Lagging Lefts: The left turns are served after the associated through movements.
Example: Phases 4 and 8 (minor street throughs) are served first, then phases 3 and
7 (minor street lefts) are served.
Offset (or Lead/Lag) Lefts: One left turn is served before the associated through
movements, and the opposing left turn is served after the associated through
movements. Example: Phase 1 (one major left turn) is served first (phase 6 may be
served at the same time), then phases 2 and 6 (major throughs) are served, and
then phase 5 (opposing major left turn) is served (phase 2 may still be served with
phase 5).
Check that all turning movements provide turning clearance for opposing turn phases. If the
opposing left-turning vehicle paths do not have 4-foot minimum—12-foot desirable—separation
between them, split or offset (lead/lag) phasing will have to be used.
Dedicated right turn lanes may be operated the same as left turn lanes: permissive,
protected/permissive, or protected. However, right turn phase operation needs to take into
account any pedestrian crossing on the receiving side of the right turn. If there is a conflicting
pedestrian phase – typically a pedestrian phase running concurrent with the through phase from
which the right turn is being made – the right turn phase may only be operated as permissive.
Dedicated right turn lanes operated as permissive and protected/permissive are recommended
to have their own displays, but may use a shared display with the adjacent through lane.
Dedicated right turn lanes operated as protected must use their own display. Right turn displays
are arranged and operated the same as those listed for left turns in 1330.06(1). As with left
turns, a permissive right turn phase shall not terminate separately from the conflicting phase(s)
(typically, the opposing through phase).
Separate right turn phasing also needs to consider some additional operational modes and
issues:
A right turn overlap is when a protected right turn is allowed at the same time as a
complementary protected left turn, and is recommended when the lane and phase
configuration will support this operation. When this operation is used, the left turn must be
signed that U-turns are prohibited.
When right turn overlaps are used, the wiring of the right turn displays will depend on the
operating mode of each display section:
Permissive: Connect permissive display sections to the same terminals as the
associated through phase.
Protected: Protected display sections may either be:
(a) Connected to the complementary left turn phase. Use this arrangement when the
protected right turn will only be run concurrent with the complementary left turn
phase.
(b) Connected to an overlap phase. Use this arrangement when the protected right turn
will be run with both the complementary left turn phase and with the through phase
associated with the right turn.
Multiple-lane right turns may be run independent or overlapped as described above. Multiple-
lane right turns can cause operational challenges when “right turn on red” is permitted at the
intersection. Verify that there is adequate sight distance and adequate receiving lanes are
available to minimize the possibility of collisions. In most cases, a single unrestricted “right-turn-
only” lane approach with a separate receiving lane (auxiliary lane) will have a similar capacity as
the two lane right-turn phasing.
Just prior to LSO, when railroad preemption is used, the traffic signal will shift to a “Track
Clearance Green” (TCG) phase. TCG shifts non-conflicting phases to green to allow vehicles to
clear the railroad tracks. Examples of a TCG phase and LSO are shown in Exhibit 1330-22.
Standalone queue cutter signals do not have a TCG phase – contact the HQ Traffic Office for
operational guidance on standalone queue cutter signals.
1330.07 Documentation
The following original signal design documents shall be included in a Signal System file and
provided to the region Traffic Office or owning agency:
1. Signal Permit, including Signal Warrant Analysis and supporting documentation.
2. FHWA Approval for Experimentation.
3. Signal Standard Design Chart, including signal support engineering calculations.
4. Signal Detection Zone Placement. Include calculations if used.
5. Signal Wiring Diagram and Conduit Fill calculations.
6. Railroad preemption calculation and interconnect setup.
7. Any third party documentation provided.
8. Approved Preliminary Signal Plan.
9. Emergency Preemption Equipment selected.
10. Transit Priority Preemption and associated agreements.
Copies of items 1 and 2 are also required to be included in the DDP. Copies of items 3 through
10 are also required to be included in the Project File (PF).
1330.08 References
The following references are used in the planning, design, construction, and operation of traffic
control signals installed on state highways. The RCWs noted are specific state laws concerning
traffic control signals, and conformance to these statutes is required.
Revised Code of Washington (RCW) 35.77, Streets – Planning, establishment, construction, and
maintenance
RCW 46.61.080, Interference with official traffic-control devices or railroad signs or signals
RCW 46.61.085, Traffic control signals or devices upon city streets forming part of state
highways – Approval by department of transportation
RCW 47.36.025, Vehicle-activated traffic control signals – Detection of motorcycles and bicycles
Washington Administrative Code (WAC) 468 18-040, Design standards for rearranged county
roads, frontage roads, access roads, intersections, ramps and crossings
“City Streets as Part of State Highways: Guidelines Reached by the Washington State
Department of Transportation and the Association of Washington Cities on the Interpretation of
Selected Topics of RCW 47.24 and Figures of WAC 468-18-050 for the Construction, Operations
and Maintenance Responsibilities of WSDOT and Cities for Such Streets,” April 30, 1997.
WAC 468-95, Manual on Uniform Traffic Control Devices for Streets and Highways (Washington
State Supplement)
1340.01 General
For the purpose of this chapter, and to remain consistent with WSDOT’s Standard Plans and
AASHTO terminology, the terms “access” and “approach” will be referred to as “driveway.” An
access on a managed access highway is defined as an “access connection,” while an access on a
limited access highway is defined as an “approach.”
Driveways are as much about access as they are about driveway design. This chapter describes
the pertinent access criteria along with the design guidelines, including two design templates
based on design vehicle, sidewalks, and sight distance criteria, for driveway connections on the
state highway system. WSDOT controls driveways on all limited access state highways, and
regulates driveways on all managed access state highways outside the incorporated limits of a
city or town. RCW 47.50.030 states that cities and towns, regardless of population size, are the
permitting authority for managed access state highways within their respective incorporated
city and town limits. The RCW also requires those cities and towns to adopt standards for access
permitting on managed access state highways that meet or exceed WSDOT standards, provided
those adopted standards are consistent with WSDOT standards.
in the deed and right-of-way limited access plan. Chapter 530 describes the three levels of
limited access highways: full, partial, and modified. Any change to the number, type, and use of
a limited access driveway must be approved by Headquarters through the process outlined in
Chapter 530 and Chapter 550. A general permit is required to allow any new construction or
repairs for a deeded road approach on a limited access highway. Access connection permits are
not issued on limited access highways.
Any state highway that is not a limited access highway is a managed access highway. Chapter
540 describes the five classes of managed access highways: Class 1 (most restrictive) to Class 5
(least restrictive). In addition to the five access control classes, there are also corner clearance
criteria that must be used for access connections near intersections (see Section 540.04 and
Exhibit 540-2). An access connection permit is required to allow the use, operation, and
maintenance of a driveway connection on a managed access highway, outside incorporated
cities, where WSDOT is the access permitting authority. Check with Development Services
to ascertain where WSDOT has permitting authority (such as tribal lands or National Parks).
When evaluating access connections or approaches on a project, review existing driveways for
possible alterations, relocations, consolidations, or closures. The first step in that process is to
determine the legality of each driveway. The region Development Services Office can provide a
list of the permitted driveway connections on a managed access highway, noting that, per RCW
47.50.080, Permit removal, “Unpermitted connections to the state highway system in existence
on July 1, 1990, shall not require the issuance of a permit and may continue to provide access to
the state highway system, unless the permitting authority determines that such a connection
does not meet minimum acceptable standards of highway safety.” As a result, driveway
connections on a managed access state highway can be considered to be permitted,
grandfathered, or unpermitted as described below:
• Permitted driveways hold a valid permit and shall remain valid until modified or revoked.
• Grandfathered driveways that were in existence and in active use consistent with the type
of connection on July 1, 1990, may continue to provide connection to the state highway
system. The term “Grandfathered” driveway, or connection, is not a term defined in statute
or rule. It is a commonly used term to define legal connections to managed access state
highways, in place prior to July 1, 1990. They do not require the issuance of a new permit
and may continue to provide access to the state highway system, unless the permitting
authority determines that such a connection does not meet minimum acceptable standards
of highway safety.
• Unpermitted driveways are not allowed. The permitting authority may initiate action to
close the unpermitted driveway in compliance with the applicable chapters of 47.50 RCW
and 468-51 and 468-52 WAC. These are driveways that do not have a permit and were
constructed after July 1, 1990.
Additional information regarding this process can be obtained by contacting your region’s
Development Services Office.
On limited access highways, both the region Development Services and Real Estate Services
offices may provide assistance to determine the legality of an existing driveway. Federal
Highway Administration approval is required for driveway modifications on Interstate facilities.
However, if the property owner regularly has larger-wheelbase vehicles using the driveway, such
as a home-based work vehicle, recreational vehicle, or truck and boat trailer combination, then
a larger driveway may be appropriate.
Conversely, some driveways, such as a rural locked and gated utility, farm, or logging access that
larger vehicles sometimes use, may be better served with a smaller and narrower access. This is
based on infrequent use and to prevent unauthorized use or dumping of debris on or near the
driveway. Other design considerations are:
• Prevent stormwater from flowing onto the roadway from the driveway.
• Properly size culverts under the driveway to adequately accommodate the conveyance of
stormwater in the roadway ditches and swales.
• Provide driveway sight distance.
• Accommodate for mailbox placement.
• Ensure surfacing materials and depths are appropriate.
• Generally, extend paving to the right of way line depending on the location/purpose of the
driveway. The desirable intersection angle of the driveway is 90°, with 60° to 120° allowed.
• Where driveways intersect sidewalks, bike lanes, shared-use paths, or trails especially near
schools, consider narrowing the driveway and/or reducing the radii to the minimum
required to accommodate the design vehicle. Narrower driveway width and/or smaller
driveway radii can reduce exposure and speed differentials between vehicles entering /
exiting the driveway and pedestrians or bicycles.
requirements for access approaches to limited access facilities. Design driveways with as small a
foot print as possible while accommodating the design vehicle specific to that driveway. Use
turn simulation software (such as AutoTURN®) to verify the driveway design will accommodate
the largest vehicle that will regularly use the driveway. Considering the context of use, Exhibit
1340-1 is generally used for private, special use, and low volume commercial driveways with
design vehicles of SU-30, BUS, and smaller. Exhibit 1340-2 is generally used for low volume
commercial and special use driveways with design vehicles of SU-30, BUS, and larger.
Driveways to developments with greater than 1,500 (estimated) average daily trips both
entering and exiting the development (shopping malls, housing developments, commercial
complexes, etc.) should be designed as an intersection leg (see Chapter 1310).
Notes:
[1] Culvert pipe with beveled end treatment (see Chapter 1600). See Hydraulics Manual, Road
Approach and Driveway Culverts for details.
[2] When the travel lanes are bituminous, a similar surface may be used on the approaches.
[3] For mailbox location and type, see Section 1340.07 and Chapter 1600.
[4] Not to exceed ±8% maximum algebraic difference from shoulder slope.
[5] Vertical alignment not to exceed a 3¼-inch hump or a 2-inch depression in a 10-foot chord
Notes:
[1] Culvert pipe with beveled end treatment (see Chapter 1600). See Hydraulics Manual,
“Private Road Approach and Driveway Culverts” for details.
[2] When the travel lanes are bituminous, a similar surface may be used on the approaches.
[3] For mailbox location and type, see Section 1340.07, Chapter 1600.
[4] Not to exceed ±8% maximum algebraic difference from shoulder slope.
[5] Vertical alignment not to exceed a 3¼-inch hump or a 2-inch depression in a 10-foot chord.
[6] Check turning template of driveway design vehicle
1340.03(2) Sidewalks
Driveways adjacent to sidewalks shall be designed and constructed in accordance with this
chapter and Standard Plan F-80.10. Driveway width will be as stated on the access permit. The
sidewalk shall be designed and constructed in accordance with Chapter 1510 and Section F of
the Standard Plans.
Design and locate driveways such that the sight distances, based on an eye height of 3.5 feet
and an object height of 3.5 feet, meet or exceed the distances shown in Exhibit 1340-3; these
distances may require an approaching vehicle to reduce speed or stop to prevent a collision. In
addition, provide decision sight distance for through traffic at all utility and special-use
driveways on facilities with limited access control (see Chapter 1260). The sight triangle areas
created by the sight lines should be clear of sight obstructions that might block or affect a
driver’s view of potentially conflicting vehicles. See Exhibit 1340-3.
Use intersection sight distance (see Section 1310.05) for road approaches with greater than
1,500 (estimated) average daily trips both entering and exiting the development at full build out.
Notes:
[1] Measured from the edge of traveled way to the drive’s eye. If the desirable 18-foot setback cannot
be achieved, obtain as much as practicable, down to a 10-foot minimum.
[2] Not required for driveways that are restricted by raised channelization to be right in and right out
only.
Install beveled end culverts sized in accordance with the Hydraulics Manual if the driveway
traverses an existing ditch or swale in the state highway right of way. Contact either the Region
Hydraulic Engineer or the applicable Region Maintenance Office for assistance. Consider placing
quarry spalls at each end of the open culvert to prevent erosion.
Profile the road approach as shown in Exhibits 1340-1 or 1340-2 while ensuring that roadway
runoff is not a problem. Locate culverts as far from the traveled way as possible. In Exhibits
1340-1 and 1340-2, roadway runoff can be a concern if the grade from the edge of shoulder to
the right of way line and the slope parallel to the mainline is a flat or minus grade. If needed, a
curb may be placed and if needed, a catch basin can also be placed as shown in Exhibit 1340-2.
When considering a curb, see Chapter 1239 as allowable curb locations, heights, and offset
distances can vary based on mainline speed. Construct road approaches and related areas such
that they do not impair drainage within the right of way or alter the stability of the roadway
subgrade.
1340.03(5) Mailboxes
Refer to Chapter 1600, Roadside Safety, Mailboxes, for guidance regarding the placement of
mailboxes.
1340.04 Documentation
Refer to Chapter 300 for design documentation requirements.
1340.05 References
RCW 47.32.170, Approach roads, other appurtenances – Removal of installations from right-of-
way for default
Chapter 468-52 WAC, Highway access management – Access control classification system
and standards
1350.01 General
1350.02 References
1350.03 Plans
1350.04 Traffic Control Systems
1350.05 Nearby Roadway Intersections
1350.06 Pullout Lanes
1350.07 Crossing Surfaces
1350.08 Crossing Closure
1350.09 Traffic Control During Construction and Maintenance
1350.10 Railroad Grade Crossing Petitions and WUTC Orders
1350.11 Grade Crossing Improvement Projects
1350.12 Light Rail
1350.13 Documentation
1350.01 General
Highway-rail grade crossings (“grade crossings”) are the intersection of two modes of
transportation with very different physical and operational characteristics. Because of the
inherent limitations associated with train operations, RCW 46.61.350 gives train traffic
the right of way at grade crossings, thereby assigning motorists the primary responsibility
to avoid collisions.
There are many variables that influence a motorist’s ability to react appropriately at
grade crossings, including what information is available to them as they approach the
crossing and human factors such as competing decisions, distractions, and impaired
driving. Primary factors to consider in the design of grade crossings are roadway and
railway geometry; available sight distance; highway and railway speeds; competing
decisions or visual distractions; and the types of warning devices at the grade crossing.
Another aspect of grade crossing design is coordination of highway traffic signal
operations with grade crossing active warning devices (“railroad preemption”) when
signalized intersections are located near grade crossings. In such instances, railroad
preemption is designed to clear the tracks of any vehicles that may be stopped as a
result of the highway traffic signal when a train is approaching the grade crossing.
Further guidance on railroad preemption requirements is provided in Chapter 1330.
Grade crossings are also unique due to their multijurisdictional nature. Highway
authorities and railroad companies are each legally responsible for different elements
at grade crossings. Additionally, the Washington Utilities and Transportation
Commission (WUTC) is the state regulatory agency with oversight of public grade
crossings in Washington, except within the limits of first class cities in accordance
with RCW 81.53.240. Establishing new crossings, altering existing crossings, or
closing crossings all require WUTC approval. Therefore, highway projects that
include a grade crossing will generally require close coordination with both the
railroad company and the WUTC.
Projects that include grade crossings will generally require execution of construction and
maintenance agreements between the Washington State Department of Transportation
(WSDOT) and the railroad company. These agreements specify the design elements of
the crossing, work that the railroad will perform on behalf of the project, payment terms,
and legal provisions. It may also be necessary for WSDOT to obtain easements from the
railroad company for new grade crossings on railroad property. The Headquarters (HQ)
Railroad Liaison is responsible for facilitating highway project coordination with railroad
companies, including developing agreements and obtaining WUTC approvals. Obtaining
necessary approvals from the railroad company may take several months. Contact the HQ
Railroad Liaison early in the design phase so that all necessary design and agreement
coordination can be completed according to project schedules.
1350.02 References
(1) Federal/State Laws and Codes
Revised Code of Washington (RCW) 81.53, Railroad crossings
http://apps.leg.wa.gov/rcw/default.aspx?cite=81.53
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA;
as adopted and modified by Chapter 468-95 WAC “Manual on uniform traffic control
devices for streets and highways” (MUTCD)
www.wsdot.wa.gov/publications/manuals/mutcd.htm
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans),
M 21-01, WSDOT
www.wsdot.wa.gov/publications/manuals/m21-01.htm
Manual on Uniform Traffic Control Devices Part 8. Traffic Control for Railroad
and Light Rail Transit Grade Crossings
http://mutcd.fhwa.dot.gov/htm/2009/part8/part8_toc.htm
1350.03 Plans
(1) Proposed Improvements
Include plans for proposed improvements to existing crossings and any new crossings
in the Plans, Specifications, and Estimates (PS&E) package. In addition to basic roadway
dimensions, signs, and markings, indicate the angle of crossing; number of tracks;
location of signals and other railway facilities (such as electrical/communications lines
and control boxes); and the limits of property ownership by the railroad company at the
crossing location.
For any project proposing to alter the horizontal or vertical alignment at a grade crossing,
including grade separations, show the alignment and profile for both the railroad and the
roadway for a minimum of 500 feet on all legs of the crossing. Show all other important
features that might affect the safety, operation, and design of the crossing, such as nearby
crossroads, driveways/entrances, buildings, and highway structures on the plans.
Notes:
Adjust for skewed crossings.
Assume flat highway grades adjacent to and at crossings.
1. The following signing elements are shown in the MUTCD, Part 8, Traffic
Control for Highway-Rail Grade Crossings:
• Highway-Rail Grade Crossing (Crossbuck) sign: Crossbuck signs
identify the location of the grade crossing and convey the same meaning as
a yield sign. The railroad is responsible for installation and maintenance of
Crossbuck signs.
Note: Railroads are required to upgrade standard Crossbuck signs at passive
grade crossings to “Crossbuck Assemblies” by December 31, 2019.
Crossbuck Assemblies are Crossbuck signs mounted in conjunction with
STOP or YIELD signs. Any projects that establish new passive crossings
or result in reconstruction of passive crossings should include design of
Crossbuck Assemblies. (See Chapter 8 of the MUTCD for additional
guidance.)
• Supplemental Number of Tracks (inverted “T”) sign: This sign is
mounted below the Crossbuck sign to indicate the number of tracks when
two or more tracks are involved. The railroad is responsible for installation
and maintenance of these signs.
• Grade Crossing Advance Warning sign (W10 sign series): The road
authority is responsible for installation and maintenance of these signs.
• Exempt sign: This is a supplemental sign that, when authorized by the
WUTC, may be mounted below the Crossbuck sign. When this sign is
approved, certain classes of vehicles, otherwise required to stop before
crossing the tracks, may proceed without stopping, provided no train is
approaching. The road authority is responsible for installation and
maintenance of these signs.
• Do Not Stop on Tracks sign: This sign is used where it is determined that
additional emphasis is needed to remind motorists of this legal requirement,
such as where nearby roadway intersections result in queuing back across the
tracks. The road authority is responsible for installation and maintenance of
these signs.
2. Pavement markings on all paved approaches are the responsibility of the road
authority and consist of RR Crossing markings in accordance with the Standard
Plans, No Passing markings, and Pullout Lanes, as appropriate.
1. Railroad Flashing Light Signals and Gates: These are active devices intended
to warn motorists of approaching trains and impose a stopping requirement. The
railroad is responsible for installation and maintenance of these devices.
At a minimum:
• All public grade crossings are required to be equipped with Crossbuck signs,
a supplemental plaque indicating the presence of multiple tracks (if applicable),
and advance warning signs.
• Railroad pavement markings are required at all crossings where active warning
devices are present or the posted legal speed limit is 40 mph or higher.
Passive warning devices notify drivers that they are approaching a grade crossing
and to be on the lookout for trains. In general, consider stand-alone passive warning
devices at grade crossings with low volumes and speeds on both the highway and
railway, and where adequate sight distances exist. Active warning devices are to be
considered at all other crossings. No national or state warrants have been developed
for installation of traffic control devices at grade crossings. Furthermore, due to the
large number of significant variables that need to be considered, there is no single
system of active traffic control devices universally applicable for grade crossings.
Warning systems at grade crossings should be based on an engineering and traffic
investigation, including input from the railroad and the WUTC. Primary factors to
consider in selecting warning devices are train and highway volumes and speeds;
highway and railway geometry; pedestrian volume; accident history; and available
sight distance.
Evaluate railroad signal supports and gate mechanisms as roadside features to be
considered for mitigation. Use traffic barrier or impact attenuators as appropriate
(see Division 16).
Where the distance between the grade crossing and the roadway intersection is not
sufficient to store a design vehicle, a pre-signal may be considered to prevent subsequent
vehicles from entering the grade crossing limits during the track clearance phases of the
downstream highway signal. Additionally, whenever a signalized roadway intersection
is located 500 feet from a grade crossing, a Railroad Crossing Evaluation Team, which
includes representatives from both WSDOT and the railroad company, will jointly
determine the need for and design of railroad preemption systems. (See Chapter 1330
for further guidance on railroad preemption requirements.)
Vehicle queues over the tracks can also result from operations at nonsignalized roadway
intersections; for example, where there is a short distance between the grade crossing and
a roadway intersection controlled by a STOP or YIELD sign. A “Do Not Stop on Tracks”
sign should be installed at locations where the distance between the grade crossing and
the roadway intersection is not sufficient to store a design vehicle or it is otherwise
determined that vehicle queues originating from the roadway intersection routinely
extend back to the grade crossing. To determine whether or not to consider a highway
traffic signal in such instances, refer to MUTCD Traffic Signal Warrant 9.
Contact H&LP or the HQ Railroad Liaison in the Utilities, Railroads, and Agreements
Section for more information.
1350.13 Documentation
For the list of documents required to be preserved in the Design Documentation Package
and the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev/
1360.01 General
The primary purpose of an interchange is to reduce conflicts caused by vehicle crossings and
minimize conflicting left-turn movements. Provide interchanges on all Interstate highways and
freeways, and at other locations where traffic cannot be controlled efficiently by intersections at
grade.
Chapter Subject
520 Access control
530 Limited access
550 Access Revision Report
1103 Design controls
1106 Design element dimensions
1240 Turning widths
1250 Cross Slope and Superelevation
1310 Intersections
1410 HOV lanes
1420 HOV direct access connections
1360.02(1) General
All freeway exits and entrances, except HOV direct access connections, are to connect on the
right of through traffic. Variations from this will be considered only for special conditions.
HOV direct access connections may be constructed on the left of through traffic when they are
designed in accordance with Chapter 1420.
Provide complete ramp facilities for all directions of travel wherever possible. However, give
primary consideration to the basic traffic movement function that the interchange is to fulfill.
Complications are rarely encountered in the design and location of rural interchanges that
simply provide a means of exchanging traffic between a limited access freeway and a local
crossroad. Carefully consider the economic and operational effects of locating traffic
interchanges along a freeway through a community, particularly with respect to local access, to
provide convenient local service without reducing the capacity of the major route(s).
Where freeway-to-freeway interchanges are involved, do not provide ramps for local access
unless they can be added conveniently and without detriment to efficient traffic flow or
reduction of capacity, either ramp or freeway main line. When exchange of traffic between
freeways is the basic function, and local access is prohibited by access control restrictions or
traffic volume, separate interchanges for local service may be needed.
Selection of the final design is based on a study of projected traffic volumes, site conditions,
geometric controls, criteria for intersecting legs and turning roadways, driver expectancy,
consistent ramp patterns, continuity, and cost.
The patterns most frequently used for interchange design are those commonly described as
directional, semi directional, cloverleaf, partial cloverleaf, diamond, and single point (urban)
interchange (see Exhibit 1360-1).
1360.02(2)(a) Directional
A directional interchange is the most effective design for connection of intersecting freeways.
The directional pattern has the advantage of reduced travel distance, increased speed of
operation, and higher capacity. These designs eliminate weaving and have a further advantage
over cloverleaf designs in avoiding the loss of sense of direction drivers experience in traveling a
loop. This type of interchange is costly to construct, commonly using a four-level structure.
A semi directional interchange has ramps that loop around the intersection of the highways.
This results in multiple single-level structures and more area than the directional interchange.
1360.02(2)(c) Cloverleaf
The full cloverleaf interchange has four loop ramps for the left-turning traffic. Outer ramps
provide for the right turns. A full cloverleaf is the minimum type interchange for a freeway-to-
freeway interchange. Cloverleaf designs often incorporate a C-D road to minimize signing
difficulties and remove weaving conflicts from the main roadway.
The principal advantage of this design is the elimination of all left-turn conflicts with one single-
level structure. Because all movements are merging movements, it is adaptable to any grade
line arrangement.
The cloverleaf has some major disadvantages. The left-turn movement has a circuitous route on
the loop ramp, the speeds are low on the loop ramp, and there are weaving conflicts between
the loop ramps. The cloverleaf also needs a large area. The weaving and the radius of the loop
ramps are a capacity constraint on the left-turn movements.
A partial cloverleaf has loop ramps in one, two, or three quadrants that are used to eliminate
the major left-turn conflicts. These loops may also serve right turns for interchanges where
ramp cannot be built in one or two quadrants. Outer ramps are provided for the remaining
turns. Design the grades to provide sight distance between vehicles approaching these ramps.
1360.02(2)(e) Diamond
A diamond interchange has four ramps that are essentially parallel to the major arterial. Each
ramp provides for one right-turn and one left-turn movement. Because left turns are made at
grade across conflicting traffic on the crossroad, intersection sight distance is a primary
consideration.
The diamond design is the most generally applicable and serviceable interchange configuration
and usually has a smaller footprint than any other type. Consider this design first unless another
design is clearly dictated by traffic, topography, or special conditions.
1360.02(2)(f) Single Point Urban (SPUI)
A single point urban interchange is a modified diamond with all of its ramp terminals on the
crossroad combined into one signalized at-grade intersection. This single intersection
accommodates all interchange and through movements.
A single point urban interchange can improve the traffic operation on the crossroad with less
right of way than a typical diamond interchange, but a larger structure.
Directional Semidirectional
1360.02(3) Spacing
To avoid excessive interruption of main line traffic, consider each proposed facility in
conjunction with adjacent interchanges, intersections, and other points of access along the
route as a whole.
The minimum spacing between adjacent interchanges is 1 mile in urban areas, 3 miles on the
Interstate in rural areas, and 2 miles on non-Interstate in rural areas (see Exhibit 1360-2). In
urban areas, spacing less than 1 mile may be used with C-D roads or grade-separated (braided)
ramps. Interchange spacing is measured along the freeway centerline between the centerlines
of the crossroads.
The spacing between interchanges may also be dependent on the spacing between ramp
connections. The minimum spacing between the gore noses of adjacent ramps is given in
Exhibit 1360-3.
Consider either frontage roads or C-D roads to facilitate the operation of near-capacity volumes
between closely spaced interchanges or ramp terminals. C-D roads may be needed where
cloverleaf loop ramps are involved or where a series of interchange ramps have overlapping
speed change lanes. Base the distance between successive ramp terminals on capacity. Check
the intervening sections by weaving analyses to determine whether capacity, sight distance, and
effective signing can be provided without the use of auxiliary lanes or C-D roads.
In maintaining route continuity, interchange configuration may not favor the heavy traffic
movement, but rather the through route. In this case, design the heavy traffic movements with
multilane ramps, flat curves, and reasonably direct alignment.
1360.02(5) Drainage
Avoid interchanges located in proximity to natural drainage courses. These locations often result
in complex and unnecessarily costly hydraulic structures. The open areas within an interchange
can be used for stormwater detention facilities.
L L[1]
L L
System[2] Service[3]
Freeway C-D Road Freeway C-D Road A B C D
Interchange Interchange
1,000 800 500 400 800 600 2000 1600 1600 1000
Gore nose
L = Minimum distance in feet from gore nose to gore nose.
A = Between two interchanges connected to a freeway: a system interchange[2] and a service
interchange.[3]
B = Between two interchanges connected to a C-D road: a system interchange[2] and a service
interchange.[3]
C = Between two interchanges connected to a freeway: both service interchanges.[3]
D = Between two interchanges connected to a C-D road: both service interchanges.[3]
Notes:
These values are based on operational experience, need for flexibility, and signing. Check them in
accordance with Exhibit 1360-12 and the procedures outlined in the Highway Capacity Manual, and
use the larger value.
[1] With justification, these values may be reduced for cloverleaf ramps.
[2] A system interchange is a freeway-to-freeway interchange.
[3] A service interchange is a freeway-to-local road interchange.
1360.03 Ramps
It is desirable that the ramp design speed at the connection to the freeway be equal to the free-
flow speed of the freeway. Meet or exceed the upper range values from Exhibit 1360-4 for the
design speed at the ramp connection to the freeway. Transition the ramp design speed to
provide a smooth acceleration or deceleration between the speeds at the ends of the ramp.
However, do not reduce the ramp design speed below the lower-range speed of 25 mph. For
loop ramps, use a design speed as high as feasible, but not lower than 25 mph.
These design speed guidelines do not apply to the ramp in the area of the ramp terminal at-
grade intersection. In the area of the intersection, use a design speed of 15 mph for turning
traffic or 0 mph for a stop condition. Use the allowed skew at the ramp terminal at-grade
intersection to minimize ramp curvature.
For freeway-to-freeway ramps and C-D roads, the design speed at the connections to both
freeways is the upper range values from Exhibit 1360-4; however, with justification, the
midrange values from Exhibit 1360-4 may be used for the remainder of the ramp. When the
design speed for the two freeways is different, use the higher design speed.
Existing ramps meet design speed criteria if acceleration or deceleration criteria are met (see
Exhibit 1360-9 or 1360-10) and superelevation meets the criteria in Chapter 1250.
Exhibit 1360-4 Ramp Design Speed
1360.03(3) Grade
The maximum grade for ramps for various design speeds is given in Exhibit 1360-5.
Exhibit 1360-5 Maximum Ramp Grade
Ramp Desirable 5 4 3
Grade (%) Maximum * 7 6 5
* On one-way ramps, downgrades may be 2% greater
Number of Lanes 1 2
Traveled Way [1] 11-13 [5] 23-25 [3] [5]
Right 4-8 [2] [5] 4-8 [2] [5]
Ramp Width (ft) Shoulders
Left 2 2-4
Medians [4] 6 6-8
Notes:
[1] Evaluate shoulder use to accommodate offtracking, if determined inadequate for
operational performance needs, apply turning roadway widths in Chapter 1240.
[2] Provide width necessary to accommodate offtracking by large vehicles.
[3] Add 12 ft for each additional lane.
[4] The minimum two-way ramp median width (including shoulders) is given. Wider
medians may be required for signs or other traffic control devices and their respective
clearances. When either the on- or off-ramp is single-lane, use the one-lane column. If
both directions are two lanes, use the two-lane column.
[5] Use the mode/function/performance approach described in Chapter 1106 to choose
between the range of widths given.
Ramp shoulders may be used by large trucks for offtracking and by smaller vehicles cutting to
the inside of curves. Evaluate the need to pave shoulders full depth for larger vehicle offtracking
using turn simulation software on one-way ramps to accommodate this type of use. If
operational performance needs demonstrate that accommodation of offtracking on shoulders is
inadequate apply turning roadway widths in Chapter 1240.
mountable or extruded curb. Traffic barrier or a depressed median may be provided in place of
the raised median.
The location of the ramp meter is a balance between the storage and acceleration criteria.
Locate the ramp meter to maximize the available storage and so that the acceleration lane
length, from a stop to the freeway main line design speed, is available from the stop bar to the
merging point. With justification, the average main line running speed during the hours of meter
operation may be used for the highway design speed to determine the minimum acceleration
lane length from the ramp meter. (See 1360.04(4) for information on the design of on-
connection acceleration lanes and Chapter 1050 for additional information on the design of
ramp meters.)
Driver compliance with the signal is required for the ramp meter to have the desired results.
Consider enforcement areas with metered ramps.
Consider HOV bypass lanes with ramp meters. (See Chapter 1410 for design data for ramp meter
bypass lanes.)
Avoid on-connections on the inside of a main line curve, particularly when the ramp approach
angle is accentuated by the main line curve, the ramp approach results in a reverse curve to
connect to the main line, or the elevation difference will cause the cross slope to be steep at the
nose.
Provide justification when curb is used adjacent to traffic with a design speed of 40 mph or
higher.
A C
Merge
B C³A+B-1
F D
Diverge
F = D + E - 1* E
*Note: Number of lanes (F) may increase by one lane, when the lane is an auxiliary lane between closely spaced
entrance and exit ramps.
1360.04(1)(a) Entrances
At entrances, make the number of lanes beyond the merging of two traffic streams not less than
the sum of all the lanes on the merging roadways less one (see Exhibit 1360-7a).
1360.04(1)(b) Exits
At exits, make the number of approach lanes equal the number of highway lanes beyond the
exit plus the number of exit lanes less one (see Exhibit 1360-7a). Exceptions to this are:
At a cloverleaf.
At closely spaced interchanges with a continuous auxiliary lane between the entrance
and exit.
In these cases, the auxiliary lane may be dropped at a single-lane, one-lane reduction off-
connection (Exhibit 1360-14c), with the number of approach lanes being equal to the sum of the
highway lanes beyond the exit and the number of exit lanes. Closely spaced interchanges have a
distance of less than 2,100 feet between the end of the acceleration lane and the beginning of
the deceleration lane.
Maintain the basic number of lanes, as described in Chapter 1210, through interchanges. When
a two-lane exit or entrance is used, maintain lane balance with an auxiliary lane (see Exhibit
1360-7b). The exception to this is when the basic number of lanes is changed at an interchange.
3 2 3
2
Undesirable: Lane balance, but no compliance with basic number of lanes.
3 3 3
2
Undesirable: Compliance with basic number of lanes, but no lane balance.
3 4 3 4 3
2
Desirable: Compliance with both lane balance and basic number of lanes.
Reduce the traveled way width of the freeway by only one lane at a time.
500 to 1,000 ft
500 to 1,000 ft
1,500 to 3,000 ft
1360.04(4) On-Connections
On-connections are the paved areas at the end of on-ramps that connect them to the main lane
of a freeway. They have two parts: an acceleration lane and a taper. The acceleration lane
allows entering traffic to accelerate to the freeway speed and evaluate gaps in the freeway
traffic. The taper is for the entering vehicle to maneuver into the through lane.
On-connections are either tapered or parallel. The tapered on-connection provides direct entry
at a flat angle, reducing the steering control needed. The parallel on-connection adds a lane
adjacent to the through lane for acceleration with a taper at the end. Vehicles merge with the
through traffic with a reverse curve maneuver similar to a lane change. While less steering
control is needed for the taper, the parallel is narrower at the end of the ramp and has a shorter
taper at the end of the acceleration lane.
Provide the minimum acceleration lane length, given in Exhibit 1360-9, for each ramp design
speed on all on-ramps. When the average grade of the acceleration lane is 3% or greater,
multiply the distance from the Minimum Acceleration Lane Length table by the factor from the
Adjustment Factor for Grades table.
For existing ramps that do not have significant crashes in the area of the connection with the
freeway, the freeway posted speed may be used to calculate the acceleration lane length for
Preservation projects. If corrective action is indicated, use the freeway design speed to
determine the length of the acceleration lane.
The acceleration lane is measured from the last point designed at each ramp design speed
(usually the PT of the last curve for each design speed) to the last point of the ramp width.
Curves designed at higher design speeds may be included as part of the acceleration lane length.
1360.04(4)(b) Gap Acceptance
For parallel on-connections, provide the minimum gap acceptance length (Lg) to allow entering
motorists to evaluate gaps in the freeway traffic and position their vehicles to use the gap. The
length is measured beginning at the point that the left edge of traveled way for the ramp
intersects the right edge of traveled way of the main line to the ending of the acceleration lane
(see Exhibits 1360-13b and 13c). The gap acceptance length and the acceleration length overlap,
with the ending point controlled by the longer of the two.
Upgrade Downgrade
Highway Design
Grade Ramp Design Speed All Ramp Design
Speed (mph)
20 30 40 50 Speeds
40 1.3 1.3 0.70
45 1.3 1.35 0.675
50 3% to less 1.3 1.4 1.4 0.65
55 than 5% 1.35 1.45 1.45 0.625
60 1.4 1.5 1.5 1.6 0.60
70 1.5 1.6 1.7 1.8 0.60
40 1.5 1.5 0.60
45 1.5 1.6 0.575
50 1.5 1.7 1.9 0.55
5% or more
55 1.6 1.8 2.05 0.525
60 1.7 1.9 2.2 2.5 0.50
70 2.0 2.2 2.6 3.0 0.50
Note: Lane widths are shown for illustrative purposes. Determine lane widths based on Exhibit 1360-6.
Single-lane on-connections may be either tapered or parallel. The tapered is desirable; however,
the parallel may be used with justification. Design single-lane tapered on-connections as shown
in Exhibit 1360-13a and single-lane parallel on-connections as shown in Exhibit 1360-13b.
1360.04(4)(d) Two-Lane On-Connections
For two-lane on-connections, the parallel is desirable. Design two-lane parallel on-connections
as shown in Exhibit 1360-13c. A capacity analysis will normally be the basis for determining
whether a freeway lane or an auxiliary lane is to be provided.
Justify the use of a two-lane tapered on-connection. Design two-lane tapered on connections in
accordance with Exhibit 1360-13d.
1360.04(5) Off-Connections
Off-connections are the paved areas at the beginning of an off-ramp, connecting it to a main
lane of a freeway. They have two parts: a taper for maneuvering out of the through traffic and a
deceleration lane to slow to the speed of the first curve on the ramp. Deceleration is not
assumed to take place in the taper.
Off-connections are either tapered or parallel. The tapered is desirable because it fits the
normal path for most drivers. When a parallel connection is used, drivers tend to drive directly
for the ramp and not use the parallel lane. However, when a ramp is on the outside of a curve,
the parallel off-connection is desirable. An advantage of the parallel connection is that it is
narrower at the beginning of the ramp.
Provide the minimum deceleration lane length given in Exhibit 1360-10 for each design speed
for all off-ramps. Also, provide deceleration lane length to the end of the anticipated queue at
the ramp terminal. When the average grade of the deceleration lane is 3% or greater, multiply
the distance from the Minimum Deceleration Lane Length table by the factor from the
Adjustment Factor for Grades table.
For existing ramps that do not have significant crashes in the area of the connection with the
freeway, the freeway posted speed may be used to calculate the deceleration lane length for
Preservation projects. If corrective action is indicated, use the freeway design speed to
determine the length of the deceleration lane.
The deceleration lane is measured from the point where the taper reaches the selected ramp
lane width to the first point designed at each ramp design speed (usually the PC of the first
curve for each design speed). Curves designed at higher design speeds may be included as part
of the deceleration lane length.
D e ce D e ce Off-
leratio Off- leratio ram
n la n e ram n lane p
p
A A
First point at each First point at each
ramp design speed ramp design speed
Note: Lane widths are shown for illustrative purposes. Determine lane widths based on Exhibit 1360-6.
1360.04(5)(b) Gores
Gores (see Exhibits 1360-11a and 11b) are decision points. Design them to be clearly seen and
understood by approaching drivers. In a series of interchanges along a freeway, it is desirable
that the gores be uniform in size, shape, and appearance.
The paved area between the physical nose and the gore nose is the reserve area. It is reserved
for the installation of an impact attenuator. The minimum length of the reserve area is
controlled by the design speed of the main line (see Exhibits 1360-11a and 11b).
In addition to striping, raised pavement marker rumble strips may be placed for additional
warning and delineation at gores. (See the Standard Plans for striping and rumble strip details.)
Keep the unpaved area beyond the gore nose as free of obstructions as possible to provide a
clear recovery area. Grade this unpaved area as nearly level with the roadways as possible.
Avoid placing obstructions such as heavy sign supports, luminaire poles, and structure supports
in the gore area.
When an obstruction is placed in a gore area, provide an impact attenuator (see Chapter 1620)
and barrier (see Chapter 1610). Place the beginning of the attenuator as far back in the reserve
area as possible, desirably after the gore nose.
For single-lane off-connections, the tapered is desirable. Use the design shown in
Exhibit 1360-14a for tapered single-lane off-connections. Justify the use of a parallel single-lane
off-connection, as shown in Exhibit 1360-14b.
1360.04(5)(d) Single-Lane Off-Connection With One Lane Reduction
The single-lane off-connection with one lane reduction, shown in Exhibit 1360-14c, is used when
the conditions from lane balance for a single-lane exit, one-lane reduction, are met.
1360.04(5)(e) Tapered Two-Lane Off-Connection
The tapered two-lane off-connection design, shown in Exhibit 1360-14d, is desirable where the
number of freeway lanes is reduced or where high-volume traffic operations will be improved by
the provision of a parallel auxiliary lane and the number of freeway lanes is unchanged.
The parallel two-lane off-connection, shown in Exhibit 1360-14e, allows less operational
flexibility than the taper, requiring more lane changes. Justify the use of a parallel two-lane off-
connection.
R a mp
Gore nose
Ed g e
o f sh o
ulder
4 ft min
12 ft [1]
L
1
[2]
Z [2] Z
1 R = 4 ft min[3]
Shoulder plus 2 ft
Shoulder width
Notes:
[1] The reserve area length (L) is not less than:
Design Speed
[2] Z , design speed is for the main line.
2
R a mp
Gore nose
Ed g e
o f sh o
ulder
Edge of through-lane
Shoulder width
Notes:
[1] The reserve area length (L) is not less than:
a. Exhibit 1360-15a shows the designs for collector-distributor outer separations. Use Design
A, with concrete barrier, when adjacent traffic in either roadway is expected to exceed 40
mph. Design B, with mountable curb, may be used when adjacent posted speed does not
exceed 40 mph.
b. The details shown in Exhibit 1360-15b apply to single-lane C-D road off-connections. Design
a two-lane C-D road off-connection, with the reduction of a freeway lane or an auxiliary
lane, as a normal two-lane off-connection in accordance with 1360.04(5).
Because weaving sections cause considerable turbulence, interchange designs that eliminate
weaving or remove it from the main roadway are desirable. Use C-D roads for weaving between
closely spaced ramps when adjacent to high-speed highways. C-D roads are not needed for
weaving on low-speed roads.
PT PC
3000
D
B
LOS
S
LO
LO
Total Weaving Volume, DHV
2000
av in g
f we
mo
eal
t of r
Ou
1000
Note:
To determine whether or not lane balance for weaving exists, see Exhibit 1360-8.
The design of interchanges on two-lane two-way highways may vary considerably from
traditional concepts due to the following conditions:
The potential for cross-centerline crashes due to merge conflicts or motorist confusion.
The potential for wrong-way or U-turn movements.
Future construction considerations.
Traffic type and volume.
The proximity to multilane highway sections that might influence a driver’s impression
that these roads are also multilane.
Provide the deceleration taper for all interchange exit ramps on two-lane highways. Design the
entering connection with either the normal acceleration taper or a “button hook” configuration
with a stop condition before entering the main line. Consider the following items:
Design the stop condition connection in accordance with a tee (T) intersection as
shown in Chapter 1310. Use this type of connection when an acceleration lane is not
possible. Provide decision sight distance as described in Chapter 1260.
Since designs may vary from project to project, analyze each project for the most
efficient signing placement, such as one-way, two-way, no passing, do not enter,
directional arrows, guideposts, and traffic buttons.
Prohibit passing through the interchange area on two-lane highways by means of
signing, pavement marking, or a combination of both. The desirable treatment is a 4
foot median island, highlighted with raised pavement markers and diagonal stripes.
When using a 4-foot median system, extend the island 500 feet beyond any merging
ramp traffic acceleration taper. The width for the median can be provided by reducing
each shoulder 2 feet through the interchange (see Exhibit 1360-17).
Include signing and pavement markings to inform both the entering and through
motorists of the two-lane two-way characteristic of the main line.
Use as much of the ultimate roadway as possible. Where this is not possible, leave the
area for future lanes and roadway ungraded.
Design and construct temporary ramps as if they were permanent unless second-stage
construction is planned to rapidly follow the first stage. Design the connection to meet
the needs of the traffic.
Compass directions (W-S Ramp) or crossroad names (E-C Street) may be used for ramp
designations.
Prepare a preliminary contour grading plan for each completed interchange. Show the desired
contours of the completed interchange, including details of basic land formation, slopes, graded
areas, or other special features. Coordinate the contour grading with the drainage design and
the roadside development plan.
1360.08 Documentation
Refer to Chapter 300 for design documentation requirements.
1360.09 References
Procedure for Analysis and Design of Weaving Sections: A User’s Guide, Jack E. Leisch, October
1985
Notes:
A [2]
Acceleration lane LA[1] 300 ft min
R=4 ft[4]
] 90.0° See paving
[5 Edge of
detail
Lg=300 ft min shoulder
[3].
PT of ramp curve[6]
PCC of End of ramp stationing
Ramp curve
Edge of
through lane
10 ft
8 ft 2 ft
Edge of shoulder
Paving detail
Notes:
General:
For striping, see the Standard Plans.
A [2]
Acceleration lane LA[1] 300 ft min [7].
R=4 ft[4]
]. 90.0° Edge of
[5 10 ft
shoulder
[3]. Lg=300 ft min
PT of ramp curve[6]
PCC of End of ramp stationing
Ramp curve
Notes:
General:
Notes:
General:
Notes:
General:
Notes:
Notes:
[4] Lane and shoulder widths are shown for illustrative purposes. For ramp lane and shoulder widths,
see Exhibit 1360-6.
General:
Notes:
General:
For striping, see the Standard Plans.
Notes:
General:
For striping, see the Standard Plans.
Notes:
[1] With justification, the concrete barrier may be placed with 2 ft between the edge of either shoulder
and the face of barrier. This reduces the width between the edge of through-lane shoulder and the
edge of C-D road shoulder to 6 ft and the radius at the nose to 3 ft.
[2] For collector-distributor road lane and shoulder widths, see ramp lane and shoulder widths,
Exhibit 1360-6.
Notes:
[2] Point A is the point controlling the C-D road or ramp design speed.
[3] For gore details, see Exhibit 1360-11a.
[4] For C-D road and ramp lane and shoulder widths, see Exhibit 1360-6.
[5] Approximate angle to establish alignment.
[6] May be reduced with justification (see Exhibit 1360-15a).
General:
For striping, see the Standard Plans.
Lane and shoulder widths are shown for illustrative purposes. Determine lane and shoulder widths
based on Exhibit 1360-6.
Notes:
Notes:
[1] For minimum weaving length, see Exhibit 1360-12.
[2] Lane and shoulder widths are shown for illustrative purposes. For minimum ramp lane and shoulder
widths, see Exhibit 1360-6.
[3] For gore details, see Exhibit 1360-11b.
General:
For gore details, see Exhibit 1360-11b.
1370.01 General
1370.02 Analysis
1370.03 Design
1370.04 Plan Updates and Approvals
1370.05 Documentation
1370.01 General
This chapter provides guidance for locating and designing median crossovers.
Median crossovers are provided at locations on divided highways for crossing by
maintenance, traffic service, emergency, and law enforcement vehicles. The use
of all median crossovers is restricted to these users.
Crossovers may be provided:
• Where main line safety will not be compromised by providing a crossover.
• Where access through interchanges or intersections is not practical.
• As part of region maintenance operations.
• As necessary for law enforcement and emergency services functions.
For information about median openings to provide turning movements for public
access to both sides of the roadway, see Chapter 1310, Intersections at Grade.
1370.02 Analysis
A list of existing median crossovers is available from the Headquarters (HQ) Access
and Hearings Section. The Statewide Master Plan for Median Crossovers website is:
www.wsdot.wa.gov/design/accessandhearings/tracking.htm
• New crossovers should not be located closer than 1,500 feet to the end of a ramp
taper or to any structure. This distance may be decreased to improve winter
maintenance efficiency based on an operational analysis. Include an operational
analysis in the Design Documentation Package (DDP).
• Crossovers should be located only where stopping sight distance is provided and
preferably should not be located on superelevated curves.
1370.03 Design
Use the following design criteria for all median crossovers, taking into consideration
the intended vehicle usage. Some of these criteria may not apply to crossovers intended
primarily for law enforcement.
• Adequate median width at the crossover location is required to allow the design
vehicle to complete a U-turn maneuver without backing. Use of the shoulder area
is allowed for the execution of the U-turn maneuver. Typical design vehicles for
this determination are a passenger car and a single-unit truck.
• When median barrier is placed in the vicinity of a median crossover, position the
barrier to minimize the potential for errant vehicles to cross through the median.
(See the Standard Plans for typical barrier layout.)
• Consider the types of vehicles using the median crossover.
• The minimum recommended throat width is 30 feet.
• Use grades and radii that are suitable for all authorized user vehicles (see
Chapter 1340).
• In most cases, 10-foot inside paved shoulders are adequate for deceleration and
acceleration lanes. Consider full 10-foot shoulders for a distance of 450 feet upstream
of the crossover area to accommodate deceleration, and extend downstream of the
crossover area for a distance of 600 feet to allow acceleration prior to entering the
travel lane. In cases where the median width is narrower than the design vehicle
turning path, widening shoulders may not provide a benefit. Document decisions
to provide inside shoulders of less than 10 feet.
• Provide adequate stopping sight distance for vehicles approaching the crossover area.
This is due to the unexpected maneuvers associated with these inside access points
and the higher operating speeds commonly experienced in the inside travel lanes
(see Chapter 1260).
• Provide adequate intersection sight distance at crossover locations where authorized
user vehicles must encroach on the travel lanes (see Chapter 1310).
• For the crossing, use sideslopes no steeper than 10H:1V. Grade for a relatively
flat and gently contoured appearance that is inconspicuous to the public.
• Consider impacts to existing drainage.
• Do not use curbs or pavement markings.
• Flexible guideposts may be provided for night reference, as shown in the
Standard Plans.
• Consider the terrain and locate the crossover to minimize visibility to the public.
• Use vegetation to minimize the visibility of the crossover. Low vegetation
with a 3-foot year-round maximum height is recommended for this purpose
(see Chapter 900).
• In locations where vegetation cannot be used to minimize visibility by the traveling
public, and there is a high incidence of unauthorized use, use appropriate signing
such as “No U-Turns” to discourage unauthorized use.
• A stabilized all-weather surface is required. Paving of crossings is determined on
a case-by-case basis.
1370.05 Documentation
For the list of documents required to be preserved in the Design Documentation Package
and the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev/
1410.01 General
High-occupancy vehicle (HOV) facilities include separate HOV roadways, HOV lanes, transit
lanes, HOV direct access ramps, and flyer stops. The objectives for the HOV facilities are:
Improve the capability of corridors to move more people by increasing the number of
people per vehicle.
Provide travel time savings and a more reliable trip time to HOV lane users.
Provide travel options for HOVs without adversely affecting the general-purpose lanes.
Plan, design, and construct HOV facilities that provide intermodal linkages. Give consideration to
future highway system capacity needs. Whenever possible, design HOV lanes so that the level of
service for the general-purpose lanes is not degraded.
In urban corridors that do not currently have planned or existing HOV lanes, complete an
analysis of the need for HOV lanes before proceeding with any projects for additional general-
purpose lanes. In corridors where both HOV and general-purpose facilities are planned,
construct the HOV lane before or simultaneously with the construction of new general-purpose
lanes.
Chapter Subject
1230 Geometric cross section
1240 General-purpose turning roadway widths
1420 HOV direct access
A queue or bottleneck bypass can be effective without satisfying all of the above. An isolated
bypass can be viable when there is localized, recurring traffic congestion, and such treatment
can provide a travel time saving to a sufficient number of HOV users.
The efficiency of the HOV facility can be affected by the access provisions. Direct access
between park & ride/transit facilities and an HOV lane is the most desirable, but it is also an
expensive alternative. Direct access options are discussed in Chapter 1420.
Document the need for the HOV lane and how the proposed lane will meet those needs.
The separated roadway can be either a one-way reversible or a two-way operation. The
directional split in the peak periods, available space, and operating logistics are factors to be
considered. A separated HOV roadway may be located in the median of the freeway, next to the
freeway, or on an independent alignment. Separated HOV facilities are more effective for:
Large HOV volumes.
Large merging and weaving volumes.
Long-distance HOV travel.
Reversible separated roadways operate effectively where there are major directional splits
during peak periods. Consider potential changes in this traffic pattern and design the facility to
accommodate possible conversion to a two-way operation. The separated roadway is normally
more efficient, provides for the higher level of safety, and is more easily enforced. However, it is
generally the most expensive type of HOV facility.
A buffer-separated HOV lane is similar to a freeway nonseparated HOV lane on the left, but with
a buffer between the HOV lane and the general-purpose lanes. The addition of a buffer provides
better delineation between the lanes and controls access between the HOV lane and general-
purpose lanes to improve operations.
Nonseparated HOV lanes operate in the same direction and immediately adjacent to the
general-purpose lanes. They are located either to the left (desirable) or to the right of the
general-purpose lanes. Nonseparated HOV lanes are normally less expensive and easier to
implement, and they provide more opportunity for frequent access. However, the ease of access
can create more problems for enforcement and a greater potential for conflicts.
System continuity and consistency of HOV lane placement along a corridor are important, and
they influence facility development decisions. Other issues include land use, trip patterns,
transit vehicle service, HOV volume, ramp volume, congestion levels, enforcement, and direct
access to facilities.
The inside (left) HOV lane is most appropriate for a corridor with long-distance trip patterns,
such as a freeway providing mobility to and from a large activity center. These trips are
characterized by long-distance commuters and express transit service. Maximum capacity for an
effective inside HOV lane is approximately 1,500 vehicles per hour. When HOVs weaving across
the general-purpose lanes cause severe congestion, consider providing HOV direct access
ramps, separated HOV roadways, or a higher-occupancy designation. Inside lanes are preferred
for HOV lanes on freeways.
The outside (right) HOV lane is most appropriate for a corridor with shorter, more widely
dispersed trip patterns. These trip patterns are characterized by transit vehicle routes that exit
and enter at nearly every interchange. The maximum capacity for an effective outside HOV lane
is reduced and potential conflicts are increased by heavy main line congestion and large
entering and exiting general-purpose volumes.
1410.02(3)(b) Conversion of a General-Purpose Lane
The use of an existing general-purpose lane for an HOV lane is an undesirable option; however,
conversion of a lane to an HOV lane might be justified when the conversion provides greater
people-moving capability on the roadway. Use of an existing freeway lane as an HOV lane will be
considered only with a Design Analysis.
Given sufficient existing capacity, converting a general-purpose lane to an HOV lane can provide
for greater people moving capability in the future without significantly affecting the existing
roadway operations. The fastest and least expensive method for providing an HOV lane is
through conversion of a general-purpose lane. Restriping and signing are sometimes all that is
needed. Converting a general-purpose lane to HOV use will likely have environmental benefits.
This method, however, is controversial from a public acceptance standpoint. Public support
might be gained through an effective public involvement program (see Chapter 210).
Do not convert a general-purpose lane to an HOV lane unless it enhances the corridor’s people-
moving capacity. Conduct an analysis that includes:
Public acceptance of the lane conversion.
Current and long-term traffic impacts on the adjacent general-purpose lanes and the
HOV lane.
Impacts to the neighboring streets and arterials.
Legal, environmental, and safety impacts.
When considering the alternatives in order to provide additional width for an HOV lane, the use
of the existing shoulder is an undesirable option. Use of the shoulder on a freeway or freeway
ramp as an HOV lane will be considered only with a Design Analysis.
Consider shoulder conversion to an HOV lane when traffic volumes are heavy and the
conversion is a temporary measure. Another alternative is to use the shoulder as a permanent
measure to serve as a transit-only or queue bypass lane during peak hours and then revert to a
shoulder in off-peak hours.
The use of the shoulder creates special signing, operational, and enforcement issues. An
agreement is required with the transit agency to limit transit vehicle use of the shoulder to peak
hours. Provide signing that clearly defines the use of the shoulder. Institute special operations to
clear the shoulder for the designated hours.
The existing shoulder pavement is often not designed to carry heavy volumes of vehicles,
especially transit vehicles. As a result, repaving and reconstruction of the shoulder might be
required.
1410.02(3)(d) HOV Direct Access Ramps
To improve the efficiency of an HOV system, exclusive HOV access connections for an inside
HOV lane may be considered. (See Chapter 1420 for information on HOV direct access
connections.) Direct access reduces the need for HOVs to cross the general-purpose lanes from
right-side ramps. Transit vehicles will be able to use the HOV lane and provide service to park &
ride lots, flyer stops, or other transit stops by the HOV direct access ramps.
1410.02(3)(e) Queue Bypass Lanes
A queue bypass lane allows HOVs to save time by avoiding congestion at an isolated bottleneck.
Consider a queue bypass if the time savings for bypassing HOVs is one minute or more. Typical
locations for queue bypasses are at ramp meters, signalized intersections, toll plazas or ferry
approaches, and locations with isolated main line congestion. Queue bypass lanes can be built
along with a corridor HOV facility or independently. In most cases, they are relatively low cost
and easily implemented.
Where an HOV bypass is being considered at a ramp metering site, consult the Region Traffic
Engineer prior to implementation. When an HOV bypass is constructed at a ramp metering site,
the ramp meter system should be designed to allow for metering the HOV bypass lane as well.
At a minimum, an overhead signal support (Type II) with a tenon position for a signal display for
Flyer stops reduce the time required for express transit vehicles to serve intermediate
destinations. However, passengers must travel greater distances to reach the loading platform.
(See Chapter 1420 for information on flyer stops.)
1410.02(3)(g) Hours of Operation
An HOV designation on freeway HOV lanes 24 hours a day provides benefits to users during off-
peak periods, minimizes potential confusion, makes enforcement easier, and simplifies signing
and striping. However, 24-hour operation also might result in a lane not used during off-peak
periods, negative public opinion, and the need for full-time enforcement.
Lanes can be transit-only or include all HOVs. Transit-only lanes are desirable where bus
volumes are high with a high level of congestion. They increase the speed of transit vehicles
through congested areas and improve the reliability of the transit service. Lanes that allow use
by all HOVs are appropriate on corridors with high volumes of carpools and vanpools. They can
collect carpools and vanpools in business and industrial areas and connect them to the freeway
system.
1410.02(4)(b) Left-Side or Right-Side HOV Lane
Continuity of HOV lane location along a corridor is an important consideration when making the
decision whether to locate an arterial street HOV lane on the left or right side of the street.
Other issues include land use, trip patterns, transit vehicle service, safety, enforcement, and
presence of parking.
The right side is desirable for arterial street HOV lanes on transit routes with frequent stops. It is
the most convenient for passenger boarding at transit stops. It is also the most common
location for HOV lanes on arterial streets. General-purpose traffic must cross the HOV lane to
make a right turn at intersections and to access driveways. These turns across the HOV lane can
create conflicts. Minimizing access points that create these conflict locations is recommended.
Other issues to consider are on-street parking, stopping areas for delivery vehicles, and
enforcement areas.
Left-side arterial street HOV lanes are less common than right-side lanes. HOV lanes on the left
eliminate the potential conflicts with driveway access, on-street parking, and stopping areas for
delivery vehicles. The result is fewer delays and higher speeds, making left-side arterial street
HOV lanes appropriate for longer-distance trips. The disadvantages include the difficulty
providing transit stops and the need to provide for left-turning general-purpose traffic.
An arterial street HOV lane can either operate as an HOV lane 24 hours a day or during peak
hours only. Factors to consider in determining which to use include type of HOV lane, level of
congestion, continuity, and enforcement.
HOV lanes operating 24 hours a day are desirable when congestion and HOV demand exists for
extended periods throughout the day. The 24-hour operation provides benefits to users during
off-peak periods, minimizes potential confusion, makes enforcement easier, and simplifies
signing and striping. The disadvantages include negative public opinion if the lane is not used
during off-peak periods, the need for full-time enforcement, and the loss of on-street parking.
Peak period HOV lanes are appropriate for arterial streets with HOV demand or congestion
existing mainly during the peak period. Peak period HOV lanes provide HOV priority at the
critical times of the day, lessen negative public perception of the HOV lane, and allow on-street
parking or other shoulder uses at other times. The disadvantages include possible confusion to
drivers, more difficult enforcement, increased signing, and the need to institute special
operations to clear the shoulder or lane for the designated period.
1410.02(4)(d) Spot Treatments
An HOV spot treatment is used to give HOVs priority around a bottleneck. It can provide time
savings, travel time reliability, and improved access to other facilities. Examples include a short
HOV lane to provide access to a freeway on-ramp, one lane of a dual turn lane, a priority lane at
ferry terminals, and priority at traffic signals.
Signal priority treatments that alter the sequence or duration of a traffic signal are techniques
for providing preferential treatment for transit vehicles. The priority treatments can range from
timing and phasing adjustments to signal preemption. Consider the overall impact on traffic.
Preemption would normally not be an appropriate treatment where traffic signal timing and
coordination are being utilized or where there are high traffic volumes on the cross streets.
1410.02(4)(e) Bus Stops
Normally, with arterial HOV lanes, there is not a shoulder suitable for a bus to use while stopped
to load and unload passengers without blocking the lane. Therefore, bus stops are either in-lane
or in a pullout. In-lane bus stops are the simplest type of bus stop. However, stopped buses will
block the HOV lane; therefore, in-lane bus stops are only allowed in transit lanes. Bus pullouts
1410.03 Operations
Establish an initial occupancy designation. It is WSDOT policy to use the 2+ designation as the
initial occupancy designation. Consider a 3+ occupancy designation if it is anticipated during
initial operation that the volumes will be 1,500 vehicles per hour for a left-side HOV lane, or
1,200 vehicles per hour for a right-side HOV lane, or that a 45 mph operating speed cannot be
maintained for more than 90% of the peak hour.
1410.03(2) Enforcement
Enforcement is necessary for the success of an HOV facility. Coordination with the Washington
State Patrol (WSP) is critical when the operational characteristics and design alternatives are
being established. This involvement ensures the project is enforceable and will receive their
support.
Provide both enforcement areas and observation points for high-speed HOV lanes and ramp
facilities.
Barrier-separated facilities, because of the limited access, are the easiest facilities to enforce.
Shoulders provided to accommodate breakdowns may also be used for enforcement. Reversible
facilities have ramps for the reverse direction that may be used for enforcement. Gaps in the
barrier may be needed so emergency vehicles can access barrier-separated HOV lanes.
Buffer-separated and nonseparated HOV lanes allow violators to easily enter and exit the HOV
lane. Provide strategically located enforcement areas and observation points.
Consider the impact on safety and visibility for the overall facility during the planning and design
of enforcement areas and observation points. Where HOV facilities do not have enforcement
areas, or where officers perceive that the enforcement areas are inadequate, enforcement on
the facility will be difficult and less effective.
It is important that an ITS system be incorporated into the HOV project and that the HOV facility
fully utilize the ITS features available. This includes providing a strategy of incident management
since vehicle breakdowns and crashes have a significant impact on the efficient operation of the
HOV facilities. (For more information on ITS, see Chapter 1050.)
Reconstruction involves creating roadway width. Additional right of way may be required.
1410.04(3)(b) Restriping
Restriping involves reallocating the existing paved roadway to create enough space to provide
an additional HOV lane.
Reconstruction and restriping can be combined to maximize use of the available right of way.
For example, a new lane can be created through a combination of median reconstruction,
shoulder reconstruction, and lane restriping. Handle each project on a case-by-case basis.
Generally, consider the following reductions in order of preference:
Reduction of the inside shoulder width, provided the enforcement and safety
mitigation issues are addressed. (Give consideration to not precluding future HOV
direct access ramps by over-reduction of the available median width.)
Reduction of the interior general-purpose lane width to 11 feet.
Reduction of the outside general-purpose lane width to 11 feet.
Reduction of the HOV lane to 11 feet.
Reduction of the outside shoulder width to 8 feet.
If lane width adjustments are made, thoroughly eradicate the old lane markings. It is desirable
that longitudinal joints (new or existing) not conflict with tire track lines. If they do, consider
overlaying the roadway before restriping.
R (ft)[1] WR (ft)
1-Lane 2-Lane
[2]
3,001 to Tangent 13 24
3,000 14 24
2,000 14 25
1,000 15 26
500 15 27
300 15 28
200 16 29
150 17 31
100 18 34
75 19 37
50 22 45
Notes:
[1] Radius (R) is on the outside edge of traveled
way on 1-lane and centerline on 2-lane roadways.
[2] May be reduced to 12 ft on tangent.
For both inside and outside HOV lanes, the minimum lane width is 12 feet and the minimum
shoulder width is 10 feet (see Exhibit 1410-2).
When a left shoulder less than 10 feet wide is proposed for distances exceeding 1.5 miles,
provide enforcement and observation areas at 1- to 2 mile intervals (see 1410.04(7)).
Where left shoulders less than 8 feet wide are proposed for lengths of roadway exceeding 0.5
mile, provide safety refuge areas at 0.5- to 1-mile intervals. These can be in addition to or in
conjunction with the enforcement areas.
Design buffer-separated HOV lanes the same as for inside nonseparated HOV lanes, except for a
buffer 2 to 4 feet in width or 10 feet or greater in width with pavement marking, with
supplemental signing, to restrict crossing. For buffer-separated HOV lanes with a buffer at least
4 feet wide, the left shoulder may be reduced to 8 feet. Buffer widths between 4 and 10 feet are
undesirable because they may appear to be wide enough for a refuge area, but they are too
narrow. Provide gaps in the buffer to allow access to the HOV lane.
The minimum width for an arterial street HOV lane is 12 feet. Allow general-purpose traffic to
cross the HOV lanes to turn at intersections and to access driveways (see Exhibit 1410-2).
For right-side HOV lanes adjacent to curbs, provide a 4-foot shoulder between the HOV lane and
the face of curb. The shoulder may be reduced to 2 feet with justification.
For HOV lanes on the left, a 1-foot left shoulder between the HOV lane and the face of curb is
required. When concrete barrier is adjacent to the HOV lane, the minimum shoulder is 2 feet.
1410.04(4)(e) HOV Ramp Meter Bypass
An HOV bypass may be created by widening an existing ramp, constructing a new ramp where
right of way is available, or reallocating the existing pavement width (provided the shoulders are
full depth). For ramps with a single general purpose lane and an HOV bypass, consider installing
an overhead signal support to allow for the installation of an overhead sign (7.5 square feet
maximum) and a ramp meter display for the HOV bypass. For ramps with two general-purpose
lanes and an HOV bypass, provide an overhead signal support capable of supporting the
installation of a sign (7.5 square feet maximum) and a ramp meter display for the HOV bypass.
Ramp meter bypass lanes may be located on the left or right of metered lanes. Typically, bypass
lanes are located on the left side of the ramp. Consult with local transit agencies and the region
Traffic Office for guidance on which side to place the HOV bypass.
Consider the existing conditions at each location when designing a ramp meter bypass. Design a
single-lane ramp with a single metered lane and an HOV bypass as shown in Exhibit 1410-4a.
Make the total width of the metered and bypass lanes equal to a 2-lane ramp (see Chapters
1240 and 1360). Design a ramp with two metered lanes and an HOV bypass as shown in Exhibit
1410-4b. Make the width of the two metered lanes equal to a 2-lane ramp (see Chapters 1240
and 1360) and the width of the bypass lane as shown in Exhibit 1410-3. The design shown in
HOV direct access ramps provide access between an HOV lane and another freeway, a local
arterial street, a flyer stop, or a park & ride facility. Design HOV direct access ramps in
accordance with Chapter 1420.
Locate the beginning and end of an HOV lane at logical points. Provide decision sight distance,
signing, and pavement markings at the termination points.
The desirable method of terminating an inside HOV lane is to provide a straight through move
for the HOV traffic, ending the HOV restriction and dropping a general-purpose lane on the
right. However, analyze volumes for both the HOV lanes and general-purpose lanes, as well as
the geometric conditions, to optimize the overall operational performance of the facility.
Enforcement of the inside HOV lane can be done with a minimum 10-foot inside shoulder. For
continuous lengths of barrier exceeding 2 miles, a 12-foot shoulder is recommended for the
whole length of the barrier.
For inside shoulders less than 10 feet, locate enforcement and observation areas at 1 to 2-mile
intervals or based on the recommendations of the WSP. These areas can also serve as refuge
areas for disabled vehicles (see Exhibits 1410-5a and 5b).
Provide observation points approximately 1,300 feet before enforcement areas. They can be
designed to serve both patrol cars and motorcycles or motorcycles only. Coordinate with the
WSP during the design stage to provide effective placement and utilization of the observation
points. Median openings give motorcycle officers the added advantage of being able to quickly
respond to emergencies in the opposing lanes (see Exhibit 1410-5b). The ideal observation point
places the motorcycle officer 3 feet above the HOV lane and outside the shoulder so the officer
can look down into a vehicle.
Locate the enforcement area on the right side for queue bypasses and downstream from the
stop bar so the officer can be an effective deterrent (see Exhibits 1410-4a and 4b).
An optional signal status indicator for enforcement may be placed at HOV lane installations that
are metered. The indicator faces the enforcement area so that a WSP officer can determine
whether vehicles are violating the ramp meter. The indicator allows the WSP officer to
simultaneously enforce two areas: the ramp meter and the HOV lane. Consult with the WSP
regarding use at all locations.
For additional information on enforcement signal heads, see the Traffic Manual regarding HOV
metered bypasses.
1410.04(8)(a) Signs
Provide post-mounted HOV preferential lane signs next to the HOV lane or overhead-mounted
signs over the HOV lane. Make the sign wording clear and precise, stating which lane is
restricted, the type of HOVs allowed, and the HOV vehicle occupancy designation for that
section of road. The sign size, location, and spacing are dependent upon the conditions under
which the sign is used. Roadside signs can also be used to convey other HOV information such as
the HERO program, carpool information, telephone numbers, and violation fines. Some
situations may call for the use of variable message signs.
Place overhead signs directly over the HOV lane to provide maximum visibility. Use a sequence
of overhead signs at the beginning and end of freeway HOV facilities. Overhead signs can also be
used in conjunction with roadside signs along the roadway.
1410.04(8)(b) Pavement Markings
Provide pavement markings that conform to the Traffic Manual and the Standard Plans.
1410.04(8)(c) Interchanges
In the vicinity of interchange on- and off-connections where merging or exiting traffic crosses an
HOV lane, make provisions for general-purpose traffic using the HOV lane. These provisions
include signing and striping that clearly show the changes in HOV versus general traffic
restrictions. (See the Standard Plans for pavement markings and signing.)
1410.05 Documentation
Refer to Chapter 300 for design documentation requirements.
1410.06 References
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21 01, WSDOT
Guide for the Design of High-Occupancy Vehicle Facilities, American Association of State
Highway and Transportation Officials (AASHTO)
[3]
Separated Roadway
Nonseparated
Buffer-Separated
Arterial HOV
Notes:
[1] The sum of the two shoulders is 12 ft for one-lane and 14 ft for two-lane facilities. Provide
one shoulder with a width of at least 10 ft for disabled vehicles. The wider shoulder may be
on the left or the right. Maintain the wide shoulder on the same side throughout the facility
(see 1410.04(4)(a)2).
[2] 12-ft minimum for single lane, 24-ft minimum for two lanes. Wider width is required on
curves (see 1410.04(4)(a)1 and Exhibit 1410-1).
[3] For total width requirements, see 1410.04(4)(a)3.
[4] Width as required, and the number of lanes.
[5] Buffer 2 to 4 ft or 10 ft or more.
[6] When buffer width is 4 ft or more, may be reduced to 8 ft.
[7] 2 ft when adjacent to concrete barrier.
[8] Arterial HOV lanes on the left operate in the same direction as the adjacent general-purpose
lane.
[9] May be reduced to 2 ft with justification.
1,000 to Tangent 12
999 to 500 13
499 to 250 14
249 to 200 15
199 to 150 16
149 to 100 17
Notes:
[1] Apply additional width to two-lane ramp widths.
[2] For turning roadway widths, see traveled way width for two-lane one-way turning roadways
in Chapter 1240.
Notes:
[1] For on-connection details and for acceleration lane length, see Chapter 1360.
[2] For ramp lane and shoulder widths for a 2-lane ramp, see Chapters 1240 and 1360.
[3] A transition curve with a minimum radius of 3,000 ft is desirable. The minimum length is 300
ft. When the main line is on a curve to the left, the transition may vary from a 3,000 ft radius
to tangent to the main line.
General:
For striping details, see the Standard Plans.
Notes:
[1] For acceleration lane length, see Chapter 1360.
[2] For 2-lane ramp lane and shoulder widths, see Chapters 1240 and 1360. For 3rd lane width, see
Exhibit 1410-3.
[3] A transition curve with a minimum radius of 3000 ft is desirable. The minimum length is 300 ft. When
the main line is on a curve to the left, the transition may vary from a 3000 ft radius to tangent to the
main line.
General:
For striping details, see the Standard Plans.
Note:
[1] For median width transition, see Chapter 1210.
1420.01 General
This chapter provides WSDOT design guidance for left-side direct access facilities for high-
occupancy vehicles (HOVs) between freeway HOV lanes and flyer stops within the freeway right
of way or facilities outside of the right of way. Design right-side HOV-only access facilities in
accordance with Chapter 1360.
Direct access eliminates the need for left-side HOV lane users to cross the general-purpose lanes
to right-side general-purpose ramps. Also, transit vehicles can use the HOV lane and provide
service to the HOV direct access facility.
Providing the HOV user access to the inside HOV lane without mixing with the general-purpose
traffic saves the user additional travel time and aids in safety, enforcement, incident handling,
and overall operation of the HOV facility.
Locations for direct access ramps include HOV facilities on intersecting routes, park & ride lots,
flyer stops, and locations with a demonstrated demand. Coordinate with the local transit
agencies to identify these key locations. Give priority to locations that serve the greatest
number of transit vehicles and other HOVs.
Provide an Access Revision Report (ARR) (see Chapter 550) when there is a proposal to add,
delete, or change an access point. Provide the operational analysis from the report for all flyer
stops. For left-side connections, include the commitment that the connection will be used solely
by HOVs or will be closed.
Constructability of HOV direct access facilities is an important consideration during the design
phase. These facilities will typically be constructed on existing highways with traffic maintained
on-site. Key goals are to:
Provide a project that can be built.
Plan a construction strategy.
Provide a safe work zone.
Minimize construction delays.
Consider access to these facilities by maintenance crews. Avoid items that require a significant
maintenance effort and might result in lane closure for routine maintenance or repair.
To select an option, first establish the need, choose possible locations, evaluate site features
(such as terrain, existing structures, median widths), and evaluate existing HOV information
(such as lanes, park & ride facilities, transit routes and schedules, and origin and destination
studies). Choose a location that meets access point spacing requirements and will not degrade
traffic operations on the main line.
For minimum ramp connection spacing, see Chapter 1360. When evaluating the spacing of left-
side direct access ramps, include only left-side connections.
Traffic operations can be degraded by the weaving caused by a left-side on-connection followed
closely by a right-side off-connection (or a right-side on-connection followed by a left-side off-
connection). As a general rule, if the spacing between the HOV direct access ramp and the
general-purpose ramp is less than one gap acceptance length (see 1420.03(6)(c)) per lane, make
the HOV lane buffer-separated (see Chapter 1410).
Conduct an analysis to make certain that the new ramp will not degrade traffic operations. (See
Chapter 550 for the studies and report required for a new access point.)
When an off-connection follows an on-connection, provide full speed-change lane lengths and
tapers or at least sufficient distance for full speed-change lanes that connect at full width with
no tapers (see 1420.03(6) and (7)). An auxiliary lane can be used to connect full-width speed-
change lanes if there is not sufficient distance for both tapers.
1420.02(1)(b) Sight Distance
Locate both on- and off-connections to the main line where decision sight distance exists on the
main line (see Chapter 1260).
Access to the HOV lane can be provided by a ramp that terminates at a local street or road. The
local street or road may incorporate HOV lanes, but they are not required. (See 1420.05 for
signing and pavement markings.)
Consider traffic operations on the local road. Locate the terminal where:
It has the least impact on the local road.
Intersection spacing criteria are satisfied.
Queues from adjacent intersections do not block the ramp.
Queues at the ramp do not block adjacent intersections.
Wrong-way movements are discouraged.
When off-ramps and on-ramps are opposite each other on the local road, consider incorporating
a transit stop with the intersection.
1420.02(2)(b) Park & Ride Lots
HOV direct access ramps that connect the HOV lane with a park & ride lot provide easy access
for express transit vehicles between the HOV lane and a local service transit stop at the park &
ride facility. Other HOV traffic using the access ramp enters through the park & ride lot, which
can create operational conflicts.
Median flyer stops do not provide general access to the HOV lane. Access is from the HOV lane
to the transit stop and back to the HOV lane. No other vehicle access is provided. Ramps to and
from the flyer stops are restricted to transit vehicles only.
Drop ramps are generally straight, stay in the median, and connect the HOV lane with a local
road or flyer stop. Following is a photo and an example of a drop ramp.
Local street
HOV lane
Freeway
Ramp on bridge
or between walls On-connection
in a cut section
Consider this example for gore area characteristics for drop lanes:
R a mp
Painted nose
1420.02(3)(b) T Ramps
Freeway
HOV lane
HOV lane
Freeway
Flyer stops are transit stops inside the limited access boundaries for use by express transit
vehicles using the freeway. They may be located in the median at the same grade as the main
roadway or on a structure, on a ramp, or on the right side of the main line.
The advantage of a median flyer stop is that it reduces the time for express transit vehicles to
serve intermediate destinations. A disadvantage is that passengers travel greater distances to
reach the loading platform.
With left-side HOV lanes, flyer stops located on the right side increase the delay to the express
transit vehicles by requiring them to cross the general-purpose lanes. However, these stops
improve passenger access from that side of the freeway.
Consider an at-grade passenger crossing flyer stop only when passenger volumes are expected
to be low. Design at-grade passenger crossing flyer stops as the first stage of the stop, with the
ultimate design being side-platform flyer stops with grade-separated access to both platforms.
When ramp flyer stops are located on an HOV direct access drop ramp, the delay for the express
transit vehicle will not be much more than for a median stop, and passenger access and
connectivity to local service transit routes, on the local street or road, are improved. A flyer stop
on a right-side ramp works well with right-side HOV lanes and diamond interchanges in which
express transit vehicles can use the off-ramp to connect with a bus route on the local road and
the on-ramp to return to the HOV lane. However, a stop on a general-purpose right-side ramp
with a left-side HOV lane will increase the delay by requiring the express transit vehicle to use
the general-purpose lanes and possibly degrade main line traffic operations by increasing
weaving movements.
Transit stops located at park & ride lots provide transfer points between the express transit
system and the local transit system, and there is convenient passenger access to the park & ride
lot. When a direct access ramp is provided, express transit delays from the HOV lane to the stop
are reduced. These delays can be reduced more by providing a median flyer stop with passenger
access facilities connecting the park & ride lot to the flyer stop; however, this might be more
inconvenient for the passengers.
To minimize the passenger travel distance between express and local service transit stops,
locate local system transit stops near passenger access facilities for the flyer stops.
Consider locating observation and pull-out areas near any point where violators can enter or
exit an HOV direct access facility. Examples of potential locations are:
Freeway on- and off-connections for HOV direct access ramps.
HOV direct access ramp terminals at parking lots.
For freeway HOV lanes, locate enforcement areas on the adjacent shoulders so officers and
violators are not required to cross several lanes of traffic.
Because left-side ramps are rare and therefore less expected, signing is an important issue. (For
signing guidance, see 1420.05(2).)
Refer to Chapters 1300 and 1430, and the AASHTO Green Book for vehicle descriptions and
dimensions. Use turn simulation software (such as AutoTURN®) to verify turning movements.
1420.03(4) Grades
Grades for ramps are covered in Chapter 1360. Design Analyses will be considered for:
Downgrade on-ramps with grades increased by an additional 1%.
Upgrade off-ramps with grades increased by an additional 2%.
These increased grades help when geometrics are restricted, and they assist transit vehicles
with the acceleration when entering and the deceleration when exiting the freeway.
The vehicle width and the lateral clearance are about the width of an A-BUS from edge of mirror
to edge of mirror.
The table above gives the minimum ramp width (WR), including shoulders, at various radii (R) for
an articulated bus. For ramp locations on a tangent section or on a curve with a radius greater
than 150 feet, consider the WR width when requesting a reduced lane or shoulder width. For
ramp curves with a radius less than 150 feet, check the total ramp width and, if necessary,
widen the shoulders to provide the WR width.
1420.03(6) On-Connections
1420.03(6)(a) Parallel On-Connections
For left-side on-connections, use the parallel on-connection.
A parallel on-connection adds a parallel lane that is long enough for the merging vehicle to
accelerate in the lane and then merge with the through traffic. This merge is similar to a lane
change and the driver can use side and rear view mirrors to advantage.
See Paving
See note [4] PT of ramp curve
Se e n o Detail
te [5] End of ramp stationing
Edge of
[6] shoulder
90°
Notes:
[1] For acceleration lane length L A, see 1420.03(6)(b). Check LA for
10 ft [8]
each ramp design speed.
[2] Lg is the gap acceptance length. Begin Lg at the beginning of the
parallel lane, as shown, but not before the end of the
acceleration lane LA. (See 1420.03(6)(c) for the length Lg.) 2 ft
[3] Point A is the point controlling the ramp design speed or the
end of the transit stop zone or other stopping point.
[4] For ramp lane and shoulder widths, see 1420.03(5). Paving Detail
[5] A transition curve with a minimum radius of 3,000 ft is desirable.
The desirable length is 300 ft. When the main line is on a curve to the right, the transition may vary
from a 3,000 ft radius to tangent to the main line. The transition curve may be replaced by a 50:1
taper with a minimum length of 300 ft.
[6] Angle point for width transitions, when required. (See Chapter 1210 for pavement transitions.)
[7] For ramp shoulder width, see 1420.03(5)(b).
[8] The 10 ft left shoulder is the minimum width; 14 ft is desirable. Maintain this shoulder width for at
least 500 ft; 1,000 ft is desirable.
[9] Radius may be reduced when concrete barrier is placed between the ramp and main line.
General:
For striping, see the Standard Plans.
Ramp lane width shown for illustrative purposes. Determine lane width according to 1420.03(5).
Verify ramp width selection with transit providers that may utilize these connections.
The table below gives the minimum acceleration lane length (LA) for left-side HOV direct access
on-connections.
The buses using HOV direct access ramps merge with high-speed traffic. Acceleration lanes that
are longer than normally used are needed.
For left-side on-connections, consider at least the normal 10-foot-wide (14-foot desirable) left
shoulder for the main line for a minimum length of 500 feet (1,000 feet desirable) beyond the
end of the on-connection taper. This gives additional room for enforcement, merging, and
erratic maneuvers.
On-ra
m p
12 ft
Edge of through HOV lane
Gap acceptance length is a minimum distance traveled while a merging driver finds a gap in the
through traffic and begins the merge. For left-side parallel on-connections, the gap acceptance
length is added to the acceleration length. The Lg values are given in the table below. These
values are larger than for right-side on-connections to account for drivers’ visibility constraints.
Design left-side HOV direct access on-connections in rural areas using mainline design speed.
1420.03(7) Off-Connections
1420.03(7)(a) Parallel Off-Connection
The parallel off-connection is desirable for left-side direct access off-connections. For freeway-to
freeway off-connections, provide a parallel lane with a length sufficient for signing and
deceleration. The desirable minimum length is not less than the gap acceptance length (see
1420.03(6)(c)).
See Paving
PC of ramp curve
Detail
Begin of ramp stationing See note [3]
Edge of
shoulder [5] 90°
Edge of through HOV lane See note [4] See note [6]
12 ft
Notes:
[7]
[1] For deceleration lane length LD, see 1420.03(7)(c).
Check LD for each ramp design speed.
2 ft
[2] Point A is the point controlling the ramp design
speed or the end of the transit stop zone or other
stopping point.
[3] Ramp lane width shown for illustrative purposes. Determine lane and shoulder widths
according to 1420.03(5). Verify ramp width selection with transit providers that may utilize
these connections.
[5] Angle point for width transitions, when required. (See Chapter 1210 for pavement
transitions.)
[6] Gore area characteristics at drop ramp connections are shown on 1420.02(3)(a).
(See Chapter 1360 for gore details at other connection types.)
General:
For striping, see the Standard Plans.
The tapered off-connection may be used, with justification. (See Chapter 1360 for the design of
tapered off-connections.)
Bus passenger comfort requires longer deceleration lanes. Use the deceleration lane lengths
from the table below for HOV direct access facilities.
tion lane
Decelera mp
Off-ra
12 ft
Edge of through HOV lane
1. Either the parallel (desirable) or the taper (with justification) design may be used.
2. Use the longer deceleration length of: the Deceleration Length for Buses (see 1420.03(7)(c))
from a 60 mph freeway speed to the ramp design speed (see 1420.03(2)) or the Minimum
Deceleration Length given in Chapter 1360 from the freeway design speed to the ramp
design speed.
Design left-side HOV direct access off-connections in rural areas using mainline design speed.
The minimum vertical clearance for a pedestrian grade separation over any road is 17.5 feet.
Design the ramp to the flyer stop in accordance with 1420.03(3), 1420.03(4), and 1420.03(5).
When a flyer stop is in the median, provide enough median width for the flyer stop roadway,
passenger facilities, and barrier separation without reducing the width of the through lanes or
shoulders (see 1420.04).
The approval of a flyer stop requires the operational analysis portion of the Access Revision
Report (see Chapter 550).
Provide pavement
marking extensions
Extend right barrier
using wide lines.
and install barrier
terminal with reflective
Locate left barrier end so that sheeting or yellow
left-turning drivers can see and paint for visibility.
recognize both the freeway entrance
and the barrier end. Install barrier Use redundant directional arrows.
terminal with reflective sheeting or
yellow paint for visibility. Provide a staggered traffic arrow.
ONE WAY
ONE WAY
DO NOT
NORTH ENTER
INTERSTATE
ONE WAY
ONE WAY
ONE WAY
FREEWAY WRONG
ENTRANCE WAY
FREEWAY
ENTRANCE
DO NOT
WRONG
WAY
ENTER
ONE WAY
1420.04(1) Passengers
To encourage use of the passenger access facility for an express transit stop, provide a route
that is the shortest distance to travel from the park & ride lot or local transit stop. Failure to do
so might generate the use of undesirable shortcuts. To encourage local use of the passenger
access facilities, provide direct access from surrounding neighborhoods.
Provide grade separations for pedestrian access to transit stops in the median. Consider
stairways, ramps, elevators, and escalators, but provide at least one access for the individuals
with disabilities at every loading platform, as required by the American with Disabilities Act of
1990. (See Chapter 1510 for guidance when designing pedestrian grade separations.)
The ADA Accessibility Guidelines for Buildings and Facilities states, “Platform edges bordering a
drop-off and not protected by platform screens or guard rails shall have a detectable warning …
24 inches wide running the full length of the platform drop-off.” (See the Standard Plans for the
detectable warning pattern.)
At transit stops, at-grade crosswalks are only permitted in the at-grade crossing flyer stop layout
described in 1420.02(4)(a)2. Use traffic calming techniques, such as horizontal alignment,
textured pavement and crosswalk markings, barrier openings, and other treatments, to
channelize pedestrian movements and slow the transit vehicle’s movements. Illuminate transit
stop crosswalks (see Chapter 1040).
Where at-grade crosswalks are not permitted, take steps to minimize unauthorized at-grade
crossings. Fencing, taller concrete traffic barrier, enclosed walkways, and ramps are examples of
steps that may be taken.
1420.04(2) Bicycles
Bike lanes on nearby streets and separate trails encourage people to bicycle from surrounding
neighborhoods. Provide these bicyclists direct access to passenger access facilities.
Design bicycle access facilities in conjunction with the access for individuals with disabilities (see
Chapters 1510, 1515, and 1520).
Locate bicycle parking outside of the passenger walkways (see Chapter 1430).
Locations near colleges and universities and locations with good bicycle access, especially near
trails, will attract bicyclists. Contact the region Bicycle Coordinator for information on the
predicted number of bicycle parking spaces needed and the types of bicycle racks available.
Provide crashworthy end treatments to the approach ends of traffic barriers (see Chapter 1620).
When the operating speed is 25 mph or lower, and where an at-grade pedestrian crossing
transit stop has an opening in a concrete barrier, a sloped-down end as shown in the Standard
Plans is acceptable.
When providing a break in the barrier for turning maneuvers, consider sight distance (see
Chapter 1260) when determining the location for stopping the barrier.
In areas where headlight glare is a concern, consider glare screens such as taller concrete
barrier. Other glare screen options that mount on the top of a barrier tend to be high-
maintenance items and are discouraged.
Taller barrier might also be desirable in areas where pedestrian access is discouraged, such as
between opposing flyer stops or between a flyer stop and the main line.
1420.05(2) Signing
Design and place HOV signing to clearly indicate whether the signs are intended for motorists in
the HOV lane or the general-purpose lanes. The purposes of the signs are to:
Enhance safety.
Convey the message that HOV lanes are restricted to HOVs.
Provide clear directions for entrances and exits.
Define vehicle occupancy requirements or other restrictions.
Because HOV facilities are not found in many regions, the signing not only considers the
commuter but also the occasional user of the facility who might be unfamiliar with the HOV
facility and its operation.
1420.05(2)(a) Safety
Much of HOV signing relates to enhancing safety for motorists. Not only are geometrics often
minimized due to the lack of right of way, but there are unusual operational characteristics such
as the differential speed between the HOV vehicle and the adjacent general-purpose traffic. To
allow for the lack of passing opportunities in the HOV lane and the necessity for frequent
merging and weaving actions, use messages that are clear and concise, and use symbols
wherever possible.
Because left-side off-connections are unusual, advance warning signing alerting motorists that
an exit is on the left becomes more important.
For T ramps, provide traffic control at the T to assign priority to one of the turn movements and
to avert wrong-way movements.
The diamond symbol is used to designate HOV facilities where carpools are allowed. For all
signs, whether regulatory, guide, or warning, the symbol is white on a black background to
convey the restrictive nature of the HOV lane and to make the signs more uniformly
recognizable. The use of the symbol with all HOV signs also informs drivers that the message is
intended for HOVs. The diamond symbol is only for HOV lanes where carpools are allowed; it is
not used for bus, taxi, or bicycle preferential lanes.
The signing details given throughout this section provide for the HOV geometric configurations
used within the right of way. Signing for other types of HOV facilities (such as those used for
reversible-flow and for HOV direct access between freeways and temporary HOV lanes used
during construction) is designed on a case-by-case basis and requires consultation with the
appropriate Headquarters and region traffic personnel. In addition to the normal regulatory
signs, include HOV guide signs, both advance and action, in the design of signing for HOV direct
access between freeways.
Notes:
Place signs in accordance with the MUTCD.
For non-HOV sign details, see the Sign Fabrication Manual.
Regulatory signs for HOV facilities follow the normal regulatory signing principles: black legend
with a white reflective background on a rectangular panel. Keep in mind that messages
conveyed by the HOV signs (such as signs concerning violations and those indicating the
beginning of an HOV lane downstream) are not necessarily intended only for the HOV vehicle.
Therefore, it might be prudent to place additional signs on the right side of the freeway when
doing so conforms to sound engineering practice.
Guide striping provided for left-hand turns. Do Not Enter sign located on the left side at the
top of each off-ramp.
Keep Right sign located at the top of the median HOV Entrance sign located on the right side at
barrier separating on- and off-ramps. the beginning of each on-ramp.
Wrong Way signs (30° rotation at potential wrong- Diamonds and Turn Only pavement markings on
way entrance point). off-ramps.
Guide signs for HOV facilities are generally used at intermediate on and off locations to inform
HOV motorists of upcoming freeway exits and the appropriate location to exit the HOV lane. For
HOV direct access to and from arterials, guide signs are used in a fashion similar to normal
arterial interchange signing practice. The guide signs for HOV facilities have a black nonreflective
legend on a white reflective background. The exception is the diamond, where the white
reflective symbol is on a black nonreflective background. For all HOV-related guide signs, the
diamond is placed in the upper left-hand corner of the sign.
Notes:
Sign placement shall be in accordance with the MUTCD.
For non-HOV sign details, see the Sign Fabrication Manual.
1420.05(3) Lighting
Provide illumination of HOV direct access ramps, loading platforms at transit stops, major
parking lots, and walkways as defined in Chapter 1040.
Fully utilize available ITS elements in the design of HOV direct access facilities. Need for ITS
elements varies depending on project features, such as facility design and operation, and
whether the site has existing ITS components.
ITS elements that might be applicable to HOV direct access facilities include: closed circuit
television surveillance; ramp metering; data collection; exit queue detection and override;
dynamic signing; transit signal priority; and automatic vehicle identification and location.
Guidance on the development of ITS elements is found in Chapter 1050. Include the region
Traffic Office, transit operator, and affected local agency in the coordination for the design and
implementation of ITS.
1420.06 Documentation
Refer to Chapter 300 for design documentation requirements.
1420.07 References
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
Revised Draft Guidelines for Accessible Public Rights-of-Way (PROWAG), November 23, 2005,
U.S. Access Board. The current best practices for evaluation and design of pedestrian facilities
in the public right of way per the following FHWA memoranda:
www.fhwa.dot.gov/environment/bikeped/prwaa.htm
www.fhwa.dot.gov/civilrights/memos/ada_memo_clarificationa.htm
http://www.access-board.gov/guidelines-and-standards
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
FHWA/PB, HOV Interactive 1.0 High Occupancy Vehicle Data Base from the U.S., Canada and
Europe (CD ROM), USDOT, FHWA and Parsons Brinkerhoff
“Transit Implications of HOV Facility Design,” WA-RD 396.1, September 1996, WSDOT and
USDOT, Federal Transit Administration
1430.01 General
This chapter provides general siting and design information for transit facilities. It is intended for
Washington State Department of Transportation (WSDOT) engineering and planning staff, local
transit providers, developers, and local agencies engaged in the collaborative development of
transit facilities on or adjacent to state highways.
The design and planning information that follows supports the development of public transit
infrastructure and services on state highways.
Design Manual topics and chapters commonly used in conjunction with this chapter include:
• Right of way and access control: Chapters 510 through 560.
• Intersections and road approaches: Chapters 1300 through 1370.
• Americans with Disabilities Act (ADA) and sidewalk design: Chapter 1510.
• High-occupancy vehicle (HOV) facilities: Chapters 1410 and 1420.
On limited access facilities, bus stops are only allowed at designated locations, such as flyer
stops. (See Chapters 520, 530, and 540 for access control policy and guidance.)
Bus stops may be approved on non-limited access facilities at the transit agency’s request and
upon formal review by WSDOT for sight distance and universal access requirements at the
proposed location. At a transit agency’s option, a bus stop on these highways may be located
either within the travel lane, or outside the travel lane in a pullout. Contact the State Traffic
Engineer for information on how to process a transit agency proposal for either an in-lane or
pullout bus stop and for more information about the approval process.
Refer to WAC 468-46, Transit Vehicle Stop Zones, for additional details.
The bus stop is the point of contact between the passenger and the transit services. The
simplest bus stop is a location by the side of the road. The highest quality bus stop is an area
that provides passenger amenities and protection from the weather. Bus stops are typically
maintained by the transit agency. The bus boarding and alighting pad, the path to the shelter,
and the area within the shelter must meet the requirements for universal access. Coordinate
with the local transit agency regarding the location and what type of bus stop to use.
Placement of bus stops addresses the needs and convenience of transit providers, riders, and
highway or street operations. Basic considerations include:
• The need for safe, secure, and convenient service for patrons
• Access for people with disabilities
• Convenient passenger transfers to other intersecting bus routes or transfer points
• Connection to nearby pedestrian circulation systems
• Presence and width of sidewalks, crosswalks, and curb ramps
• Pedestrian activity through intersections
• Ability of the stop to accommodate transit dwell time and the loading/unloading of
wheel chairs and bicycles
• Adequate curb space for the number of buses expected at the stop at one time
• Ease of reentering traffic stream (if a pullout)
• Design characteristics and operational considerations of the highway or street
• Presence of on-street automobile parking and truck delivery zones
• Traffic control devices near the bus stop, such as signals or stop signs
• Volumes and turning movements of other traffic, including bicycles
Where blocks are exceptionally long or where bus patrons are concentrated well away from
intersections, midblock bus stops and midblock crosswalks may be beneficial. Contact the
Region Traffic Engineer when a midblock bus stop is being considered on a multilane roadway to
determine crossing design details and treatments that may be required. (See Chapter 1510 and
the Traffic Manual for more information on midblock crossings.)
It is common to clearly mark the bus stop as a NO PARKING zone or as a BUS ONLY zone with
signs and/or curb painting.
Exhibit 1430-1 illustrates these three types of stops and provides some general dimensions.
Consult the AASHTO Guide for Geometric Design of Transit Facilities on Highways and Streets for
additional guidelines on bus stop spacing, including information on these types of stops.
Examine each case separately and determine the most suitable location, giving consideration to
service and safety of patrons, efficiency of transit operations, and traffic operation in general.
Advantages:
• Right turns can be accommodated with less conflict.
• Minimum interference is caused at locations where traffic is heavier on the approach
side of the intersection.
• Stopped buses do not obstruct sight distance for vehicles entering or crossing from
a side street.
• At a signalized intersection, buses can often find a gap to enter the traffic stream,
except where there are heavy turning movements onto the street with the bus route.
• Waiting passengers assemble at less-crowded sections of the sidewalk away from the
intersection corners.
• Buses in the bus stop do not obscure traffic control devices or pedestrian movements
at the intersection.
Disadvantages:
• Intersections may be blocked if other vehicles park illegally in the bus stop or if more
buses than the stop can accommodate arrive at the same time.
• If signal priority is not used, the bus stops at the red light and again at the far-side stop,
interfering with traffic and efficient bus operations.
Disadvantages:
• Can cause conflicts with right-turning traffic.
• Buses often obscure sight distance to stop signs, traffic signals, or other control
devices, as well as to pedestrians crossing in front of the bus.
• Where the bus stop is too short to accommodate buses arriving at the same time, the
overflow may obstruct the traffic lane.
• If a queue bypass or bus lane is not used at a signalized intersection, then vehicles
waiting at a red signal may block buses from accessing the bus stop, which will require
the bus to wait through multiple signal cycles to enter and then depart the bus stop.
Advantages:
• Buses cause a minimum of interference with the sight distance of both vehicles and
pedestrians.
• Stops can be located adjacent to major bus passenger generators and attractors.
• Allows riders to board buses closest to the crosswalk.
Disadvantages:
• Increases walking distance for passengers crossing at intersections.
• Buses may or may not have difficulty reentering the flow of traffic.
• Driveway access may or may not be negatively impacted.
Bus
Midblock Bus Stop Parked car
Notes:
[1] Based on bus 1 ft from curb on 40 ft wide streets. When bus is 0.5 ft from curb, add 20 ft near-side, 15 ft far-
side, and 20 ft midblock. Add 15 ft when street is 35 ft wide, and 30 ft when street is 32 ft wide.
[2] Measured from extension of building line or established stop line. Add 15 ft where buses make a right turn.
[3] Add 30 ft where right-turn volume is high for other vehicles.
[4] Measured from head of bus zone as determined by the transit agency (may depend on ADA considerations).
Add 15 ft where buses make a right turn.
Exhibit 1430-2 illustrates general dimensions and design features of a bus pullout located along
a road. It could also apply to a pullout integrated at the edge of a park and ride lot or transit
center.
Exhibit 1430-3 illustrates the dimensions and design features of bus pullouts associated with
near-side, far-side, and midblock bus pullouts.
Exhibit 1430-4 illustrates the dimension and design of far-side bus zones and pullouts where
buses stop after making a right turn. Adherence to these designs allows buses to stop with
minimal interference to legally parked vehicles.
120' (2 buses)
Passenger waiting area
Notes:
This exhibit provides some general values; coordinate with transit provider for actual dimensions.
[1] For right-turn lane design, see Chapter 1310.
[2] Based on a 40 ft bus. Add 20 ft for articulated bus. Add 45 ft (65 ft articulated) for each additional bus.
30'
Far-Side Bus Stop
130' *
50' - 100' R
25' - 50' R * Based on 40' bus. Add 20' for articulated bus.
Providing protection from passing traffic involves locating stops where there is enough space, so
passengers can wait away from the edge of the traveled roadway. The buffering distance from
the roadway increases with traffic speed and traffic volume. Where vehicle speeds are 30 mph
or below, 5 feet is a satisfactory distance. In a heavy-volume arterial with speeds up to 45 mph,
a distance of 10 feet provides passenger comfort.
Passengers arriving at bus stops, especially infrequent riders, want information and reassurance.
Provide information that includes the numbers or names of routes serving the stop. Other
important information may include a system route map, the hours and days of service,
schedules, and a phone number for information. Information technology systems are evolving
and some transit agencies now provide information about wait time until the next bus and
kiosks to purchase the fare before boarding.
Where shelters are not provided, a bus stop sign and passenger bench are desirable, depending
on weather conditions. The sign indicates to passengers where to wait and can provide some
basic route information. The information provided and format used is typically the responsibility
of the local transit agency.
Providing shelters (and footing for shelters) is normally the responsibility of the local transit
agency; it provides for shelter design and footing needs. State motor vehicle funds cannot be
used for design or construction of shelters, except for the concrete pad.
Lighting can enhance passenger safety and security. Lighting makes the shelter visible to passing
traffic and allows waiting passengers to read the information provided. General street lighting is
usually sufficient. Where streetlights are not in place, consider streetlights or transit shelter
lights. For information on illumination, see Chapter 1040.
A properly drained paved surface is needed so passengers do not traverse puddles and mud in
wet weather. Protection from the environment is typically provided by a shelter, which offers
shade from the sun, protection from rain and snow, and a wind break.
Shelters can range from simple to elaborate. The latter type may serve as an entrance landmark
for a residential development or business complex and be designed to carry through the
architectural theme of the complex. If a non-public transportation entity shelter is provided, its
design and siting must be approved by the local transit agency. The reasons for this approval
include safety, barrier-free design, intermodal connections, and long-term maintenance
concerns.
Consider shelters at bus stops in new commercial and office developments and in places where
large numbers of elderly and disabled persons wait, such as at hospitals and senior centers. In
residential areas, shelters are placed at the highest-volume stops.
In order to use buses that are accessible, bus stops must also be accessible. The nature and
condition of streets, sidewalks, passenger loading pads, curb ramps, and other bus stop facilities
can constitute major obstacles to mobility and accessibility. State, local, public, and private
agencies need to work closely with public transportation officials to provide universal access.
Involve the local transit agency in the bus stop pad design and location so that lifts can actually
be deployed at the site.
In order to access a bus stop, it is important that the path to the stop also be accessible. This can
be accomplished by the use of sidewalks with curb ramps. For sidewalk design and curb ramp
information, see Chapter 1510 and the Standard Plans. Exhibit 1430-5 depicts ADA standards for
bus stop locations.
Design bus shelter clear space to meet the requirements found in ADA Standards for
Transportation Facilities.
Chapter 3, ADA Standards for Transportation Facilities, United States Access Board
www.access-board.gov/guidelines-and-standards/transportation/facilities/ada-standards-for-
transportation-facilities/chapter-3-building-blocks
Chapter 8, ADA Standards for Transportation Facilities, United States Access Board
www.access-board.gov/guidelines-and-standards/transportation/facilities/ada-standards-for-
transportation-facilities/chapter-8-special-rooms,-spaces,-and-elements
HOV facilities are often considered and included in larger park and ride lots, to improve access
for transit and carpools (see Chapter 1410).
A Cooperative Agreement is written by Headquarters (HQ) Real Estate Services for the purpose
of assigning maintenance and/or operational responsibilities for a WSDOT park and ride lot to a
transit agency or local governmental agency. (See the Agreements Manual and the HQ Real
Estate Services Cooperative Agreement form.)
When a memorandum of understanding (MOU) or other formal agreement exists that outlines
the design, funding, maintenance, and operation of park and ride lots, it must be reviewed for
requirements pertaining to new lots. If the requirements in the MOU or other formal agreement
cannot be met, the MOU must be renegotiated.
Consider sizing the facility to allow for a conservative first-stage construction with expansion
possibilities. As a rule of thumb, 1 acre can accommodate approximately 90 vehicles in a park
and ride lot. This allows approximately 40% of the area for borders, landscaping, passenger
amenities, bus facilities for larger lots, and future expansion. (See the AASHTO Guide for
Geometric Design of Transit Facilities on Highways and Streets, Appendix E, for complementary
information.)
The local transit authority can give critical input on the need for and design of the park and ride
lot. The comprehensive transit plan may already specify a location, and coordination with the
transit agency will ensure the site works well for transit vehicle access. Good coordination with
the transit agencies through the entire design process is necessary to ensure a well-planned
facility that meets the needs of all modal users.
Develop a list of potential sites to identify properties that can be most readily developed for
parking and that have suitable access. Sources for selecting sites can include State Route
Corridor Sketches and useful tools such as GIS or existing aerial photos, detailed land use maps,
or property maps.
Factors influencing site selection and design of a park and ride facility include:
• Local transit authority master plan
• Regional transportation plan
• Local agency codes
• Ability to use existing underutilized paved parking areas within proximity of the
desired location
• Local public input
• Proximity to demand
• Local traffic operations, characteristics, parking availability, and roadway geometry
• Local government zoning
Purchasing or leasing property increases costs. Therefore, the first choice is state- or transit-
owned right of way, assuming the other selection criteria are favorable. Also, give prime
consideration to the use of city- or county-owned right of way. Select a site that complements
the current and future land use and highway needs.
Investigate each potential site in the field. The field survey serves to confirm or revise
impressions gained from the office review. When conducting the investigation, consider the
following:
• Physical characteristics of the site
• Current use and zoning of the area
• Land use surrounding the property (such as residential or commercial use)
• Street network and condition of the roadways
• Visibility from adjacent streets to enhance security
• Potential for additional expansion
• Ability to meet ADA requirements and accessibility for motorists and other modes of
travel, including transit
• Proximity of any existing parking facilities (such as church or shopping center parking
lots) that are underutilized during the day
• Potential for joint use of facilities with businesses (such as day care centers or dry
cleaners) or land uses compatible with park and ride patrons
• Congestion and other design considerations
• Avoiding locations that encourage noncommuter use (such as proximity to a high school)
The desirable location for park and ride lot along one-way couplets is between the two one-way
streets, with access from both streets. When this is not achievable, provide additional signing to
guide users to and from the facility.
Establish potential sites, with transit agency input, and complete public meetings and
environmental procedures prior to finalizing the design. Follow the procedures outlined
in Chapter 210.
The degree to which the desirable attributes of any component are sacrificed to obtain the
benefits of another component can only be determined on a site-specific basis. However, these
guidelines present the optimum design elements of each factor.
Large park and ride lots are intended to be transfer points from private automobiles and other
modes to transit buses. The same basic principles are used in designing all park and ride lots.
Park and Ride lots that serve a large number of buses and/or routes may also serve as
Transfer/Transit Centers; in these cases section 1430.05 would also apply.
1430.04(2)(a) Access
Provide for all modes of transport used to arrive at and depart from transit facilities. The six
basic modes are pedestrian, bicycle, motorcycle, automobile, vanpool, and bus.
Coordinate with the local jurisdiction and transit authorities to develop the park and ride lot’s
ingress and egress locations for transit and for other vehicles. Design the access route, circulation
patterns, and return routes to minimize travel time. Exclusive direct connections for buses,
vanpools, and carpools may reduce transit costs and save time for riders.
Design transit facility access points on intersecting collector or local streets where possible.
Locate the access to avoid the queues from nearby intersections. Provide vehicle storage lanes
for entering and exiting vehicles to ensure ease of access and encourage use of the facility. To
avoid increasing congestion on the highway or the community that the facility serves, locate
entrances and exits where a traffic signal, or other intersection control type (see Chapter 1300),
can be reasonably installed at a later time, if needed.
Entrances and exits to park and rides range in scale from full public intersections to driveways,
depending on contextual factors such as traffic volumes and remoteness. Design access points
using criteria in the 1300 chapter series (Division 13) or other published design guidelines used by
the local agency.
When locating access points on a state highway, see chapters in the 500 series (Division 5) for
information about access control types (managed or limited access) and standard access spacing
and other requirements.
When designing the entrance/exit locations used by buses, start the design using a 15-foot lane
width, and then adjust as needed using the bus design vehicle and turn simulation software
(such as AutoTURN®) to verify the design.
Make the pedestrian circulation path from any parking stall to the loading zone as direct as
possible. Where pedestrian movement originates from an outlying part of a large parking lot,
consider a walkway that extends toward the loading zone in a straight line.
Close coordination with the local transit authority is critical in the design of internal circulation
for buses and vanpools. Design bus circulation routes to provide for easy movement, with
efficient terminal operations and convenient passenger transfers. Design bus routes within the
internal layout, including entrance and exit driveways, to the turning radius of the design bus
vehicle.
Normally, internal circulation is two way with 90° parking. However, one-way aisles with angled
parking may be advantageous in a smaller lot due to the limited available space or to promote a
specific circulation pattern.
Provide parking for bicycles, motorcycles, and private automobiles, as well as carpools,
vanpools, and buses. Locate accessible parking stalls close to the transit loading and unloading
area. Two accessible parking stalls may share a common access aisle. For information on the
number and design of accessible stalls, see the Roadside Manual and the parking space layouts
in the Standard Plans. Sign accessible parking stalls in accordance with the requirements of RCW
46.61.581. Parking stalls and access aisle surfaces shall be even and smooth, with surface slopes
not exceeding 2%.
Locate the bicycle-parking area relatively close to the transit passenger loading area, separated
from motor vehicles by curbing or other physical barriers, without landscaping that hides the
bike area from view, and with a direct route from the street.
• Design the bike-parking area to discourage pedestrians from inadvertently walking into
the area and tripping. Provide lots that are served by public transit, with lockers or with
a rack that will support the bicycle frame and allow at least one wheel to be locked.
• Consider providing shelters for bicycle racks. For bicycles, the layout normally consists
of stalls 2.5 feet x 6 feet, at 90° to aisles, with a minimum aisle width of 4 feet.
Coordinate decisions to provide bicycle lockers, racks, and shelters with the local
transit authority and the region subject matter experts.
1430.04(2)(d) Drainage
Provide sufficient slope for surface drainage, as ponding of water in a lot is undesirable for both
vehicles and pedestrians. This is particularly true in cold climates where freezing may create icy
spots. The maximum grade is 2%. Install curb, gutter, and surface drains and grates where
needed. Coordinate designs for drainage and pedestrian access routes to avoid conflicts.
Coordinate drainage design with the local agency to make sure appropriate codes are followed.
For additional drainage information, see Design Manual Chapter 800 and the Roadside Manual.
Design pavement to conform to design specifications for each of the different uses and loadings
that a particular portion of a lot or roadway is expected to handle. Bus lanes are typically
Portland cement concrete pavement. Within the parking area, HMA-type pavements are
typically used. Coordinate the pavement designs with the local transit agency and local
jurisdiction. Consult with the Region Materials Engineer on pavement section requirements.
There may be benefits to permeable pavement if space for stormwater facilities is limited.
1430.04(2)(g) Shelters
Coordinate with the transit agency on the need, location, design, and installation of pedestrian
shelters. To satisfy local needs, shelters may be individually designed, provided by the transit
agency, or selected from a variety of commercially available designs. These designs must meet
ADA accessibility requirements. Consider the following features in shelter design:
• Select open locations with good visibility for user safety.
• Situate enclosed shelters away from edges of driveways and roadways to keep
users dry.
• Select materials and locations where the bus driver can see waiting passengers.
• Avoid using doors, for ease of maintenance and to limit vandalism opportunities.
• Allow for a small air space along the bottom of the enclosure panels, to permit air
circulation and reduce debris collection.
• Optional features you may provide are: lighting; heat; telephone; static or electronic
travel information (schedules); electronic fare collection equipment; commercial
advertisements for revenue generation; and trash receptacles.
The Guide for Geometric Design of Transit Facilities on Highways and Streets, AASHTO, 2014,
states: “Security at stations and major stops—both manned and unmanned—should be
achieved by closed circuit television monitoring, provision of call boxes, good visibility and
lighting, police surveillance, and effective designs. Both the actual security and the passengers’
perceptions of security are important for a viable service or operation.” (See the Guide for more
information.)
Selectively preserve existing vegetation and provide new plantings to afford a balanced
environment for the park and ride lot user. For guidance and policy, see the Roadside Manual
and the Roadside Policy Manual, respectively.
1430.04(2)(j) Fencing
For fencing guidelines, see Chapter 560 and discuss with the partnering transit agency.
1430.04(2)(k) Maintenance
Maintenance of park and ride lots outside state right of way is the responsibility of the local
transit authority. Negotiate maintenance agreements with local transit authorities or other
appropriate parties during the design phase, to identify the requirements and responsibilities
for the maintenance. A Cooperative Agreement is written by HQ Real Estate Services for the
purpose of assigning maintenance and/or operational responsibilities for a WSDOT park and ride
lot to a transit agency or local governmental agency. (See the Agreements Manual and the HQ
Real Estate Services Cooperative Agreement form.)
Transit centers are frequently major activity centers and serve as destination points.
Many factors dictate the particular needs of each transit center. Design of a transit center
considers such features as passenger volume; number of buses on the site at one time; local
auto and pedestrian traffic levels; and universal access.
Transit agencies generally lead in the development of transfer/transit centers, and their
standards apply. Consult the AASHTO Guide for Geometric Design of Transit Facilities on
Highways and Streets for more comprehensive overviews and design guidelines for these
facilities.
An important aspect in multiple bus berthing is proper signing and marking for the bus bays for
both operators and passengers. Clearly delineate the route served by each bay. Consider
pavement marking to indicate stopping positions. Separate layover bays may be needed for
terminating bus routes, or the layover function can be provided at the passenger platform if the
platform only serves a single route. Consider future service plans and maximize flexibility in the
design of transit center bays and circulation.
Portland cement concrete pavement is desirable for pedestrian walkways on the platform, for
ease of cleaning.
Where buses are equipped with a bicycle rack, provide for the loading and unloading of bicycles.
Exhibit 1430-6 shows typical parallel and sawtooth designs for parking 40-foot buses for
passengers boarding and alighting at a platform. The sawtooth design does not require buses to
arrive or depart in any order.
Exhibit 1430-7 is an example of a platform design that has a combination of parallel and
sawtooth bus berths at a platform. The sawtooth design provides more space-efficient berthing,
as the parallel design shown may require that buses arrive and/or depart in order. Coordinate
the bus berth style and platform design with the local transit authority throughout the design
process, and obtain its concurrence for the final design.
In the design of parallel bus berths, additional roadway width is needed for swing-out
maneuvers if shorter bus loading platforms are utilized. The roadway width and the amount
of lineal space required at the bus platform are directly related where designs allow departing
buses to pull out from the platform around a standing bus. The shorter the berth length
allowed, the wider the roadway. Use turn simulation software (such as AutoTURN®) to verify
the design.
Considerable length is needed in a parallel design to permit a bus to pass and pull into a
platform in front of a parked bus. Design the bus aisle so that a bus can by-pass another bus
stopped at the platform. The decision to provide a parallel design to accommodate a by-pass
maneuver may depend on how many routes service the location, and the frequency of service.
Consult the AASHTO Guide for Geometric Design of Transit Facilities on Highways and Streets for
more comprehensive overviews and design guidelines.
10' min.
12' des.
[1] [1]
80' 80'
Parallel Design
16'
8'
[1]
40' 15' 10'
[2]
Sawtooth Design
Notes:
[1] Dimensions shown are for a 40-ft bus; adjust the length when designing for a longer bus.
[2] Design shown is an example; contact the local transit agency for additional information.
1430.06(1) Pavement
Coordinate the pavement design (type and thickness) of a transit project, whether initiated by
a public transportation agency or a private entity, with WSDOT or the local agency public works
department, depending on highway, street, or road jurisdiction. These agencies play a major
role in determining the paving section for the particular project.
1430.06(2) Grades
Roadway grades refer to the maximum desirable slope or grade, or the maximum slope based
on the minimum design speed that a 40-foot bus can negotiate efficiently. For roadway grade
guidance, see Chapter 1220 or the Local Agency Guidelines.
Bus speed on grades is directly related to the weight/horsepower ratio. Select grades that
permit uniform operation at an affordable cost. In cases where the roadway is steep, a climbing
lane for buses and trucks may be needed. For climbing lane guidance, see Chapter 1270. Avoid
abrupt changes in grade due to bus overhangs and ground clearance.
Refer to Chapters 1300 and 1310 for intersection design guidance, and take the following factors
into consideration in designing intersection radii:
• Right of way availability
• Angle of intersection
• Width and number of lanes on the intersecting streets
• Feasibility of channelization adjustments such as set-back stop bar or adjusted center
line
• Design vehicle turning radius
• On-street parking and/or curb extensions (see Chapter 1510)
• Allowable bus encroachment
• Operating speed and speed reductions
• Adequate intersection sight distance
• Needs of pedestrians, bicyclists, and other design users (see chapters in the 1100 series
(Division 11) for contextual discussions and Chapter 1230 for roadway types.)
Because of space limitations and generally lower operating speeds in urban areas, curve radii for
turning movements are typically smaller than those used in rural areas.
1430.07 Documentation
Refer to Chapter 300 for design documentation requirements.
1430.08 References
1430.08(1) Federal/State Laws and Codes
Americans with Disabilities Act of 1990 (ADA) (28 Code of Federal Regulations [CFR] Part 36,
Appendix A, as revised July 1, 1994)
Revised Code of Washington (RCW) 46.61.581, Parking spaces for persons with disabilities –
Indication, access – Failure, penalty
RCW 70.92.120, Handicap symbol – Display – Signs showing location of entrance for
handicapped
Washington Administrative Code (WAC) Chapter 468-46, Transit vehicle stop zones
ADA Standards for Accessible Design, U.S. Department of Justice (USDOJ), 2010; consists of 28
CFR parts 35 & 36 and the ADA and Architectural Barriers Act (ABA) Accessibility Guidelines for
Buildings and Facilities (ADA-ABAAG; also referred to as the 2004 ADAAG), July 23, 2004, U.S.
Access Board. (For buildings and on-site facilities; applies to new construction or alterations as
of March 15, 2012.)
www.access-board.gov/guidelines-and-standards
ADA Standards for Transportation Facilities, USDOT, 2006; consists of 49 CFR Parts 37 & 38 and
the ADA and ABA Accessibility Guidelines for Buildings and Facilities (ADA-ABAAG; also referred
to as the 2004 ADAAG), July 23, 2004, U.S. Access Board as modified by USDOT. (For transit, light
rail, and similar public transportation facilities.)
www.access-board.gov/guidelines-and-standards
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Revised Draft Guidelines for Accessible Public Rights-of-Way (PROWAG), November 23, 2005,
U.S. Access Board. The current best practices for evaluation and design of pedestrian facilities
in the public right of way per the following FHWA memoranda:
http://www.fhwa.dot.gov/environment/bikeped/prwaa.htm
http://www.fhwa.dot.gov/civilrights/memos/ada_memo_clarificationa.htm
www.access-board.gov/guidelines-and-standards
Transit Capacity and Quality of Service Manual, Third Edition (TCRP Report 165), Transportation
Research Board.
http://www.trb.org/Main/Blurbs/169437.aspx
Bus Use of Highways: Planning and Design Guidelines, National Cooperative Highway Research
Program Report 155, Transportation Research Board, 1975
Guide for Geometric Design of Transit Facilities on Highways and Streets, AASHTO, 2014
The AASHTO Guide provides a comprehensive reference of current practice in the geometric
design of transit facilities on streets and highways.
Guidelines for the Location and Design of Bus Stops, Transit Cooperative Research Program
(TCRP) Report 19, Transportation Research Board, 1996
1510.01 General
Pedestrian travel is a vital transportation mode. It is used at some point by nearly everyone and
is a critical link to everyday life for many. Designers must be aware of the various physical needs
and abilities of pedestrians in order to ensure facilities provide universal access.
Section 504 of the Rehabilitation Act and the Americans with Disabilities Act of 1990 (ADA)
require pedestrian facilities to be designed and constructed so they are readily accessible to and
usable by persons with disabilities. This chapter provides accessibility criteria for the design of
pedestrian facilities that meet applicable state and federal standards.
The pedestrian facilities included in a project are determined during the planning phase based on:
access control of the highway; local transportation plans; comprehensive plans and other plans
(such as Walk Route Plans developed by schools and school districts); the roadside environment;
pedestrian volumes; user age group(s); and the continuity of local walkways along or across the
roadway.
When developing pedestrian facilities within a limited amount of right of way, designers can
be faced with multiple challenges. It is important that designers become familiar with the ADA
accessibility criteria in order to appropriately balance intersection design with the often
competing needs of pedestrians and other roadway users.
Similar to the roadway infrastructure, pedestrian facilities (and elements) require periodic
maintenance in order to prolong the life of the facility and provide continued usability. Title II
of the ADA requires that all necessary features be accessible and maintained in operable working
condition for use by individuals with disabilities.
1510.02 References
1510.02(1) Federal/State Laws and Codes
ADA – 28 Code of Federal Regulations (CFR) Part 35, as revised September 15, 2010
23 CFR Part 652, Pedestrians and Bicycle Accommodations and Projects
49 CFR Part 27, Nondiscrimination on the Basis of Disability in Programs or Activities
Receiving Federal Financial Assistance (Section 504 of the Rehabilitation Act of 1973
implementing regulations)
Revised Code of Washington (RCW) 35.68, Sidewalks, gutters, curbs and driveways –
All cities and towns
RCW 35.68.075, Curb ramps for persons with disabilities – Required – Standards and
Requirements
RCW 46.04.160, Crosswalk (definition)
RCW 46.61, Rules of the Road
RCW 47.24.020, City streets as part of state highways – Jurisdiction, control
1510.03 Definitions
Refer to the Design Manual Glossary for definitions of many of the terms used in this chapter.
1510.04 Policy
1510.04(1) General
It is WSDOT policy to provide appropriate pedestrian facilities along and across sections of state
routes as an integral part of the transportation system. Federal Highway Administration (FHWA)
and WSDOT policy is that bicycle and pedestrian facilities be given full consideration in the
planning and design of new construction and reconstruction highway projects, except where
bicycle and pedestrian use is prohibited.
1510.04(2) Jurisdiction
Proposed projects in public rights of way must address ADA compliance as described in this
chapter. (See 1510.05 for ADA requirements by project type.) Regardless of which public
agency has jurisdiction within the right of way, the public agency that is sponsoring the
project is responsible for ensuring ADA compliance is addressed on its project.
On all state routes outside of incorporated cities and on those with limited access (full, partial,
and modified) within incorporated cities, jurisdiction remains with the state unless modified
by a maintenance agreement. In turnback areas where the turnback agreement has not been
completed, the state maintains full jurisdiction (see Chapters 510, 520, and 530).
When project work occurs on a managed access state route inside an incorporated city that has
jurisdiction beyond the curbs (RCW 47.24.020), design pedestrian facilities using the city design
standards adopted in accordance with RCW 35.78.030 and the most current ADA requirements.
Document the coordination with the city in the Design Documentation Package (DDP). Refer
to Chapter 300 for information about the DDP.
1510.04(4) Maintenance
As noted in 1510.01, Title II of the ADA requires that a public entity maintain in operable
working condition those features of facilities and equipment that are required to be readily
accessible to and usable by persons with disabilities.
• A crosswalk served by a curb ramp must also have an existing curb ramp in place
on the receiving end unless there is no curb or sidewalk on that end of the crosswalk
(RCW 35.68.075). If there is no existing curb ramp in place on the receiving end, an
accessible curb ramp must be provided. This requirement must be met regardless of
whether the receiving end of the crosswalk is located within the project’s limits.
• Within the construction impact zone of an alteration project, evaluate all existing curb
ramps to determine whether curb ramp design elements meet the accessibility criteria. (See
1510.09(2) for curb ramp accessibility criteria.) Modify existing curb ramps that do not meet
the accessibility criteria to meet applicable accessibility requirements to the maximum
extent feasible. This may also trigger modification of other adjacent pedestrian facilities
to incorporate transitional segments in order to ensure specific elements of a curb ramp
will meet the accessibility criteria.
• Within the construction impact zone of an alteration project that includes hot mix asphalt
overlay (or inlay) of an existing roadway and does not include reconstruction, realignment,
or widening of the roadway, evaluate all existing marked and unmarked crosswalks. (See
1510.10(2) for crosswalk accessibility criteria.) If it is not possible to meet the applicable
accessibility requirements for crosswalks, document this in the DDP.
• Within the construction impact zone of an alteration project that includes reconstruction,
realignment, or widening of the roadway, evaluate all existing crosswalks (marked or
unmarked) to determine whether crosswalk design elements meet the accessibility criteria.
(See 1510.10(2) for crosswalk accessibility criteria.) Modify crosswalk slopes to meet the
applicable accessibility requirements to the maximum extent feasible.
It may not always be possible to fully meet the applicable accessibility requirements during
alterations of existing facilities. If such a situation is encountered, consult with the Regional
ADA Liaison to develop a workable solution to meet the accessibility requirements to the
maximum extent feasible. Cost is not to be used as a justification for not meeting the accessibility
criteria. Physical terrain or site conditions that would require structural impacts, environmental
impacts, or unacceptable impacts to the community in order to achieve full compliance with the
accessibility criteria are some of the factors that can be used to determine that the maximum
extent feasible is achieved. If it is determined to be virtually impossible to meet the accessibility
criteria for an element, document the decision in one of the following ways, as applicable:
• Within the construction impact zone of an alteration project that does not include
reconstruction, realignment, or widening of the roadway, document the following deficient
elements in the DDP:
o Perpendicular curb ramp or parallel curb ramp landing cross slope that is constrained
by the existing roadway gutter profile and exceeds 2%, but is less than or equal to 5%,
that cannot be constructed to fully meet applicable accessibility requirements.
o Flared side of a perpendicular curb ramp that is constrained by the existing roadway
gutter profile and has a slope that exceeds 10%, but is less than or equal to 16.7%,
that cannot be constructed to fully meet applicable accessibility requirements.
o For any deficient element that does not match the preceding description, document the
decision via a stamped and signed Maximum Extent Feasible (MEF) document. The MEF
document will be reviewed by the appropriate Assistant State Design Engineer (ASDE)
and the Headquarters (HQ) ADA Compliance Manager. If acceptable, the MEF document
will be approved and included in the DDP.
Highway shoulders are an extension of the roadway and are not typically considered pedestrian
facilities. Pedestrians are allowed to use many state highways. Although pedestrians are allowed
to travel along the shoulder in these cases, its main purpose is to provide an area for disabled
vehicles, a recovery area for errant vehicles, and positive drainage away from the roadway.
Shoulders may serve as a pedestrian facility when sidewalks are not provided. If pedestrian
generators, such as bus stops, are present and pedestrian usage is evident, a 4-foot-wide
paved shoulder is adequate. Note that detectable warning surfaces should not be installed
where a sidewalk ends and pedestrians are routed onto a shoulder since the shoulder is not
a vehicular traveled way.
Where pedestrian traffic is evident, consider a separate PCP during the planning and
programming of the project. Consult with the State Bicycle and Pedestrian Coordinator.
Continuous Buffer
(Planting Strip)
Note: Provide wheel stops or a wider sidewalk to remedy the encroachment into the PAR.
1510.07(1)(c) Surface
• The surface of the PAR shall be firm, stable, and slip resistant. Use hard surfaces like cement
or asphalt concrete; crushed gravel is not considered to be a stable, firm surface.
• Vertical alignment shall be planar within curb ramps, landings, and gutter areas within the
PAR and within clear spaces for accessible pedestrian signals, street furniture, and operable
parts.
• Grade breaks shall be flush.
• Surface discontinuities (see Exhibits 1510-4 and 1510-5) on existing surfaces in the
pedestrian access route (such as at the joints of settled or upheaved sidewalk panels) may
not exceed ½ inch maximum. Vertical discontinuities between ¼ inch and ½ inch maximum
shall be beveled at 2H:1V or flatter. Apply the bevel across the entire level change.
Exception: No surface discontinuity is allowed at the connection between an existing curb
ramp or landing and the gutter. This grade break must be flush.
2
1/2 inch max. 1
1/4 inch max.
2
1
1/2 inch
max.
1/4 inch max.
Beveling Options
Exhibit 1510-4
• Gratings, access covers, utility objects, and other appurtenances shall not be located on curb
ramps, landings, or gutters within the PAR.
• Locate gratings, access covers, utility objects, and other appurtenances outside the PAR on
walkways and sidewalks. Where this is not possible, ensure covers, grates, and lids are
designed to be slip resistant and are installed flush with the surrounding surface (see the
Standard Plans).
1510.07(1)(d) Horizontal Openings
• Any sidewalk joints or gratings that are in the PAR shall not permit passage of a sphere more
than ½ inch in diameter.
• Elongated openings shall be placed so that the long dimension is perpendicular to the
dominant direction of travel.
• Openings for wheel flanges at pedestrian crossings of nonfreight rail track shall be 2½ inches
maximum (3 inches maximum for freight rail track).
• For additional requirements when a PAR crosses a railroad, see 1510.13.
1510.08 Sidewalks
Sidewalks are one type of PCP. (See 1510.06 for PCP accessibility criteria.) Plan the design of
sidewalks carefully to include a PAR that provides universal access. (See 1510.07 for PAR
accessibility criteria.) Sidewalk design elements are found in Exhibit 1510-7 and details for raised
sidewalks are shown in the Standard Plans. Wherever appropriate, make sidewalks continuous
and provide access to side streets. The most pleasing and comfortable installation for the
pedestrian is a sidewalk separated from the traveled way by a planted buffer. This provides a
greater separation between vehicles and pedestrians than curb alone.
2% max.
2% max.
1' - 0"
Biofiltration area 5' - 0" min
2% max.
Notes:
If vertical drop is within the Design Clear Zone and the posted speed is > 35 mph, then barrier may be needed
(see Chapter 1600).
If vertical drop is > 2 feet 6 inches and barrier is not needed, then railing is indicated.
If vertical drop is < 2 feet 6 inches and barrier is not needed, then a 4-inch curb at back of sidewalk is adequate.
General:
See the Standard Plans for details on slopes at back of sidewalk.
See Chapter 1230 for slope selection criteria.
Sidewalks may be sloped away from the roadway for stormwater treatment (see the Highway Runoff Manual).
Typical Driveways
Exhibit 1510-8
• Having the path of travel aligned to cross the gutter grade break at a right angle facilitates
usage by individuals with mobility devices.
• The height of the ramp run relative to the gutter elevation may facilitate drainage.
• The height of the ramp run relative to the gutter elevation discourages vehicular traffic
from cutting across the corner.
• On small-radius corners, the ramp alignment may be more closely aligned with the
alignment of the crosswalk markings, which facilitates direction finding for the
visually impaired.
2. Disadvantages
• The ramp run and landing might not fit within available right of way.
• On small-radius corners, the flares may not fit between closely spaced perpendicular
curb ramps.
• On larger-radius corners, there will be less facilitation of direction finding for the
visually impaired due to the requirement that the path of travel cross the gutter
grade break at a right angle.
Level landing
Wi
dth
Fl
a n gth
re Le
mp
Ra
Detectable
warning surface Flar
e
Counter slope
Gutter
Curb
• Depending on the style of parallel curb ramp, pedestrian through traffic on the sidewalk
may need to negotiate two ramp grades instead of one, possibly making it more difficult
to traverse for some.
• The installation of additional drainage features in the upstream gutter line may be
necessary to prevent the accumulation of water or debris in the landing at the bottom
of the ramp.
Level landing
p
am
Counter slope
Detectable
Curb warning
surface
Note: The pedestrian curb shown on the back of the curb ramp is intended to retain material in a cut
section and is not required if there is no material to retain due to the nature of the roadside topography.
• Has a higher construction cost than other curb ramp types due to extensive use
of curbing and a larger footprint.
• Due to generally flatter ramp grades and multi-tiered ramp elements, inadequate
drainage and accumulation of debris can occur.
1510.09(2)(d) Landing
A level landing is required either at the top of a perpendicular ramp or the bottom of a parallel
curb ramp, as noted in 1510.09(1)(a) and (b) for the type of curb ramp used.
• Provide a landing that is at least 4 feet minimum length by 4 feet minimum width.
• The running and cross slopes of a curb ramp landing shall be 2% maximum.
Note: It is recommended that cross slopes be designed to be less than the allowed maximum
to allow for some tolerance in construction. For example, design for a maximum 1.5% cross
slope (rather than 2% maximum).
Exception: The running and cross slopes of landings for curb ramps at midblock crossings
are permitted to match the street or highway grade.
1510.09(2)(e) Flares
• Flared sides are to be used only where a PCP crosses the curb ramp from the side.
• Flared sides are to have a slope of 10% maximum, measured parallel to the back of curb.
1510.09(2)(f) Counter Slope
• The counter slope of the gutter or street at the foot of a curb ramp or landing shall be 5%
maximum.
1510.09(2)(g) Detectable Warning Surfaces
• Detectable warning surfaces are required where curb ramps or landings connect to
a roadway. (See the Standard Plans for placement details and other applications.)
• Detectable warning surfaces shall contrast visually (either light-on-dark or dark-on-light)
with the adjacent walkway surface, gutter, street, or highway.
Note: Federal yellow is the color used to achieve visual contrast on WSDOT projects.
Within cities, other contrasting colors may be used if requested by the city.
1510.09(2)(h) Surfaces
• Surfaces of curb ramps shall be firm, stable, and slip resistant.
• Gratings, access covers, utility objects, and other appurtenances shall not be located
on curb ramps, landings, or gutters within the pedestrian access route.
Flow direction of
surface runoff
Drainage feature
Flow direction of
(catch basin or inlet)
surface runoff
Curb ramps
1510.10 Crosswalks
1510.10(1) Designing Crossing Facilities
Evaluate the following for crossing facilities to address the needs of all user modes:
• Minimize turning radii to keep speeds low. (See Chapter 1300 for design vehicle guidance.)
• Place crosswalks so they are visible and connect to the adjacent pedestrian facilities.
• Provide sight distance (driver to pedestrian; pedestrian to driver).
• Use a separate left-turn phase along with a “WALK/DON’T WALK” signal.
• Restrict or prohibit turns.
• Shorten crossing distance.
• Use a raised median/cut-through island for a pedestrian refuge.
• Use accessible pedestrian signals (APS).
• Use signing and delineation as determined by the region Traffic Engineer.
• Place crosswalks as close as practicable to the intersection traveled way.
• Provide pedestrian-level lighting.
• Consider the crosswalk location in relation to transit stops.
• Provide a PAR that meets the accessibility criteria at all pedestrian crossings.
The Traffic Manual provides recommendations for determining pedestrian markings based on lane
configuration, vehicular traffic volume, and speed. However, coordinate with the region Traffic
Engineer early on with any existing or proposed crosswalks. The Traffic Engineer makes the final
determination on appropriate signing and delineation.
Unmarked
crosswalk
areas 10 FEET
SHOULDER
SHOULDER
VARIES VARIES
(To back of curb ramp (To back of curb ramp
connection to street) connection to street)
SIDEWALK SIDEWALK
VARIES
(To back of curb ramp
connection to street)
Unmarked Crosswalks
Exhibit 1510-15
Marked crosswalks
Refuge Island
Curb ramp
Marked crosswalks
Vacant
Exhibit 1510-17
Crosswalk
Conventional right-turn
curb radius
Right-turning
vehicle
Driver's line of
sight
Pedestrian waiting to
cross street
Crosswalk
vehicles to provide visibility of pedestrians. At intersections with traffic signals, the curb
extensions can be used to reduce pedestrian signal timing. Examples of sidewalk curb extensions
are shown in Exhibits 1510-20 and 1510-21.
Approaching
vehicle
Driver's line
of sight
Crosswalk
The right-turn path of the design vehicle is a critical element in determining the size and shape
of the curb extension. Sidewalk curb extensions tend to restrict the width of the roadway and
can make right turns difficult for large trucks. Ensure the geometry of the curb extension is
compatible with the turn path for the design vehicle selected.
Avoid interrupting bicycle traffic with curb extensions.
Do not use curb extensions on state highways when:
• The design vehicle (see Chapter 1300) encroaches on curbs or opposing lanes, and other
solutions will not improve the circumstances.
• On-street parking is not provided/allowed.
• The posted speed is above 35 mph.
Site features such as landscaping, cabinets, poles, benches, planters, bollards, newspaper
stands, and sandwich boards should be selected and placed so they do not obstruct the vision
of pedestrians or drivers within curb extension areas, as shown in Exhibit 1510-21. Take into
account motorist and pedestrian visibility and Design Clear Zone guidelines (see Chapter 1600).
• A passing space shall be provided that is at least 5 feet wide for a distance of at least
5 feet for each PAR in a raised median or on a traffic island (see
Exhibit 1510-22).
Note: It is recommended that cut-throughs be designed to have a minimum width of
5 feet to ensure a passing space is provided.
• Medians and pedestrian refuge islands shall be 6 feet minimum in length in the direction
of pedestrian travel.
• Detectable warning surfaces are to be separated by 2 feet minimum length in the direction
of pedestrian travel.
• Detectable warning surfaces are located at each curb ramp or roadway entrance of a PAR
through a raised median or traffic island. The detectable warning surface shall be located
at the back of the curb (see Exhibit 1510-22).
• PARs of shared-use paths that go through raised medians or traffic islands shall be the same
width as the shared-use path (see Chapter 1515).
Detectable warning
surface (Typ.)
2' - 0"
Min.
5' - 0"
Min.
Island Cut-Through
Island Cut-Through
Detectable warning
surface (Typ.)
5' - 0"
Min.
Curb ramp
(Typ.)
NOTE: See Exhibits 1330-14a and 1330-14b for pole setback limits
Undesirable Recommended
Pedestrian Railroad Crossings
Exhibit 1510-26
There are a number of railroad crossing warning devices (see Exhibit 1510-27) intended
specifically for pedestrian facilities (see the MUTCD). When selecting warning devices, factors
such as train and pedestrian volumes, train speeds, available sight distance, number of tracks, and
other site-specific characteristics should be taken into account. Coordinate with the HQ Design
Office Railroad Liaison early in the design process so that all relevant factors are considered and
an agreement may be reached regarding the design of warning devices and crossing surfaces.
Except for crossings located within the limits of first-class cities,* the Washington Utilities and
Transportation Commission (WUTC) approves proposals for any new railroad at-grade crossings
or changes to warning devices or geometry at existing crossings. Additionally, any project that
requires the railroad to perform work such as installation of warning devices or crossing surfaces
must obtain a railroad construction and maintenance agreement. Contact the HQ Design Office
Railroad Liaison to coordinate with both the WUTC and the railroad company.
*RCW 35.22.010: A first class city is a city with a population of ten thousand or more at the time
of its organization or reorganization that has a charter adopted under Article XI, section 10, of the
state Constitution.
Note: There are very few first-class cities in the state of Washington. Verify with the HQ Design
Office Railroad Liaison.
It is sometimes necessary to install fencing or other physical barriers to channel the pedestrians
to the structure and reduce the possibility of undesired at-grade crossings. Note: The HQ Bridge
and Structures Office is responsible for the design of pedestrian structures.
Consider a grade-separated crossing where:
• There is moderate to high pedestrian demand to cross a freeway or expressway.
• There are large numbers of young children, particularly on school routes, who regularly cross
high-speed or high-volume roadways.
• The traffic conflicts that would be encountered by pedestrians are considered unacceptable
(such as on wide streets with high pedestrian volumes combined with high-speed traffic).
• There are documented crashes or close calls involving pedestrians and vehicles
• One or more of the conditions stated above exists in conjunction with a well-defined
pedestrian origin and destination (such as a residential neighborhood across a busy street
from a school).
Pedestrian Bridges
Exhibit 1510-28
Pedestrian Tunnel
Exhibit 1510-29
Pedestrian tunnels need adequate right of way to accommodate accessible approaches leading
to the tunnel structure. The tunnel structure must comply with ADA requirements and meet the
accessibility criteria for either a pedestrian circulation path (if the grade is less than or equal to
5%) or an access ramp (if the grade is greater than 5% and less than or equal to 8.3%), and must
include a pedestrian access route. (See 1510.06 and 1510.07 for PCP and PAR accessibility
criteria; see 1510.15(2) for access ramp accessibility criteria.)
Page 1510-42 WSDOT Design Manual M 22-01.15
July 2018
Chapter 1510 Pedestrian Facilities
1510.15(2) Access Ramps Serving Transit Stops, Park & Ride Lots, Rest Areas,
Buildings, and Other Facilities
An access ramp (see Exhibit 1510-30) provides an accessible pedestrian route from a pedestrian
circulation path to a facility such as a transit stop, park & ride lot, rest area, pedestrian
overcrossing/undercrossing structure, or building. When the running slope is 5% or less, it can be
designed as a pedestrian circulation path that includes a pedestrian access route. When
the running slope is greater than 5% to a maximum of 8.3%, it must be designed as an access
ramp. (See 1510.06 and 1510.07 for PCP and PAR accessibility criteria; see 1510.15(2)(a) for
access ramp accessibility criteria.)
• Handrail gripping surfaces with a circular cross section shall have an outside diameter
between 1¼ inches minimum and 2 inches maximum.
• Handrail gripping surfaces with a noncircular cross section shall have a perimeter
dimension between 4 inches minimum and 6¼ inches maximum, and a cross section
dimension of 2¼ inches maximum.
• Handrail gripping surfaces and the surfaces adjacent to them shall be free of sharp
or abrasive elements and shall have rounded edges.
• Handrails shall not rotate in their fittings.
3. Placement and Continuity
• Access ramp handrails shall extend horizontally above the landing for 12 inches
minimum beyond the top and bottom of ramp runs.
• At the top of a stair flight, handrails shall extend horizontally above the landing for
12 inches minimum beginning directly above the first riser nosing.
• At the bottom of a stair flight, handrails shall extend at the slope of the stair flight for
a horizontal distance at least equal to one tread depth beyond the last riser nosing.
• Handrail extensions shall return to a wall, guard, or the landing surface, or shall
be continuous to the handrail of an adjacent access ramp run or stair flight.
Exception: Handrail extensions shall not be required for continuous handrails
at the inside turn of switchback or dogleg access ramps or stairs.
1510.18 Documentation
Refer to Chapter 300 for design documentation requirements.
1515.01 General
Shared-use paths are designed for both transportation and recreation purposes and are used by
pedestrians, bicyclists, skaters, equestrians, and other users. Some common locations for
shared-use paths are along rivers, streams, ocean beachfronts, canals, utility rights of way, and
abandoned railroad rights of way; within college campuses; and within and between parks as
well as within existing roadway corridors. A common application is to use shared-use paths to
close gaps in bicycle networks. There might also be situations where such facilities can be
provided as part of planned developments. Where a shared-use path is designed to parallel a
roadway, provide a separation between the path and the vehicular traveled way in accordance
with this chapter.
As with any roadway project, shared-use path projects need to fit into the context of
a multimodal community. Exhibits are provided throughout this chapter to illustrate possible
design solutions, which should be treated with appropriate flexibility as long as doing so
complies with corresponding laws, regulations, standards, and guidance. Engage various
discipline experts, including landscape architects, soil and pavement engineers, maintenance
staff, traffic control experts, ADA and bicycle coordinators, and others. Additionally, when
designing such facilities, consider way-finding.
This chapter includes technical provisions for making shared-use paths accessible to persons
with disabilities. Design shared-use paths and roadway crossings in consultation with your
region’s ADA Coordinator, Bicycle Coordinator, and State Bicycle and Pedestrian Coordinator.
For additional information on pedestrian and bicycle facilities, see Chapters 1510 and 1520,
respectively.
Approaching intersections 12 27
When minimum radius curves cannot be obtained because of right of way, topographical, or
other constraints, consider installing the following mitigation measures for traffic calming to
slow bicyclists when approaching curves:
Intermittent curves to slow or maintain desired speeds.
Standard curve warning signs and supplemental pavement markings in accordance
with the MUTCD.
The negative effects of tight radius curves can also be partially offset by widening the pavement
through the curves. Steeper vertical grades affect the running speed of bicycles. A shared-use
path should be designed not to exceed 5%. Refer to 1515.04(3) for further guidance.
The appropriate paved width for a shared-use path depends on the context, volume, and mix of
users. The desirable paved width of a shared-use path, excluding the shoulders on either side, is
12 feet. The minimum paved width, excluding the shoulders on either side, is 10 feet.
A paved width of more than 12 feet, excluding the shoulders on either side, may be appropriate
when substantial use by both pedestrians and bicyclists is expected or maintenance vehicles are
anticipated.
Shared-use path shoulders are typically unpaved and 2 feet wide on either side. Exhibits 1515-3
through 1515-5 provide additional information and cross-sectional elements.
On bridges or tunnels, it is common to pave the entire shared-use path, including shoulders. This
usable width can be advantageous for emergency, patrol, and maintenance vehicles and allows
for maneuvering around pedestrians and bicyclists who may have stopped. It also keeps the
structure uncluttered of any loose gravel shoulder material.
1515.02(2)(b) Exceptions to Minimum Path Widths
A reduced path width of 8 feet may be designed at locations that present a physical constraint
such as an environmental feature or other obstacle. Refer to the MUTCD for signing and
pavement markings for such conditions.
In very rare circumstances, a reduced width of 8 feet may be used where the following
conditions prevail:
Bicycle traffic is expected to be low, even on peak days or during peak hours.
Pedestrian use of the facility is not expected to be more than occasional.
Horizontal and vertical alignments provide frequent, well-designed passing and
resting opportunities.
The shared-use path will not be regularly subjected to maintenance vehicle loading
conditions that would cause pavement edge damage.
The share-use path is a short distance such as a spur connection to a neighborhood.
Some existing shared-use paths were constructed with narrower dimensions, generally
providing 8 feet of pavement. Evaluate existing older paths for current needs. Consider widening
an existing shared-use path to meet current geometric standards.
The maximum cross slope on a paved shared-use path is to be 2%. The cross slope of the
shoulders can be no steeper than 6H:1V. To accommodate drainage, the entire section,
including shoulders, should transition through curves. It is desirable to design the pivot point on
the outside edge of one side of the shoulder or the other to avoid a pavement crown (see
Exhibits 1515-3 through 1515-5).
It is best practice to design the cross slope to be less steep than the allowed maximum to
account for some tolerance in construction. For example, design for a 1.5% cross slope (rather
than the 2% maximum).
Sloping the pavement surface to one side is desirable and usually simplifies drainage design and
surface construction. Generally, surface drainage from the path is dissipated as it flows down
the side slope.
Side slopes along shared-use paths are an important design feature. Embankment side slopes of
6H:1V or flatter provide a gently sloping path border.
For shared-use paths with side slopes steeper than 3H:1V, or where obstacles or waterways may
exist, evaluate the potential risk and provide mitigation such as:
A minimum 5-foot separation from the edge of the pavement to the embankment
edge. This can be accomplished by providing a 5-foot shoulder as shown in Exhibit
1515-5, Example 2.
A natural barrier such as dense shrubbery on the side slopes.
A physical barrier, such as a pedestrian rail.
Where a shared-use path is adjacent to a vertical drop of 2 feet 6 inches or more, a
pedestrian rail is needed (see Exhibit 1515-5, Example 4).
If the vertical drop is less than 2 feet 6 inches, a pedestrian rail, chain link fence, or
4-inch curb at the edge of the shared-use path may be installed to delineate the
edge.
Where a shared-use path is constructed on the side of a hill, drainage facilities may
need to be considered.
1515.02(2)(f) Clearances
The minimum horizontal clearance from the edge of pavement to an obstruction (such as bridge
piers or guardrail) is 2 feet. For vertical clearances see 1515.04 Grade Separation Structures.
Note:
[1] 3 ft minimum. Provide as much separation from the roadway as practicable.
Notes:
A separation greater than 5 feet is required for path user comfort. If separation greater than 5 feet cannot be
obtained, provide barrier separation in accordance with Exhibit 1515-4c.
See Chapter 1600 for roadway clear zone design guidance for fixed objects.
Notes:
It is desirable for the cross slope to slope toward grass areas for drainage.
See Chapter 1610 for barrier design. Pedestrian rail height minimum is 42 inches.
2 ft
min Pedestrian Railing
Not
stee
p
3H: er than 42 in min
1V 2 ft
WALL
≥ 2.5 ft = 30 in
n r
2 ft e gio ee
R gin
min s u l t En
n ls
2:1 Co eria
at
M
0.5 ft min
Design running slopes (grades) on shared-use paths less than or equal to 5% to accommodate all
user types, including pedestrians with disabilities.
When the path is within the highway right of way, its running slope can match the general grade
established for the adjacent roadway.
1515.02(3)(b) Landings
Shared-use path landings provide users a level place to rest on extended grades. Exhibits 1515-6
and 1515-7 show these features.
Landing
Landing
2.0% max.
5' min
2.0% max.
Notes:
Landings are desirable on extended grades.
Design vertical curves to transition from the grade to the landing.
Exhibit 1515-7 illustrates a landing and a rest area.
Although not required, rest areas may be provided adjacent to the shared-use path outside of
the path travelled way as shown in Exhibit 1515-7.
Notes:
Design inline landings at least 5 feet long and as wide as the shared-use path.
Design inline landings with a maximum cross slope and running slope of 2%.
Design the pavement structural section as recommended by the Region Materials Engineer.
Use crushed rock or other suitable material for shoulder graded areas as recommended by the
Region Materials Engineer. On bridges or tunnels, it is common to pave the entire shared-use
path, including shoulders across the structure.
Exhibit 1515-15 provides a chart or equations to obtain the minimum lengths of crest vertical
curves for varying stopping sight distances and algebraic differences in grade. The values are
based on a 4.5-foot eye height for the bicyclist and a 0-foot height for the object (path surface).
1515.02(5)(b) Stopping Sight Distance on Horizontal Curves
Exhibit 1515-16 gives the minimum clearances to line-of-sight obstructions for sight distance on
horizontal curves. Provide lateral clearance based on the sum of stopping sight distances from
Exhibits 1515-14a and 14b for bicyclists traveling in both directions and the proposed horizontal
curve radius. Where this minimum clearance cannot be obtained, provide curve warning signs
and use centerline pavement markings in accordance with the MUTCD.
Exhibits 1515-14a, 14b, 15, and 16 are presented at the end of the chapter.
The common types of shared-use path/roadway at-grade intersection crossings are midblock
and adjacent.
Midblock crossings are located between roadway intersections. When possible, locate the path
crossings far enough away from intersections to minimize conflicts between the path users and
motor vehicle traffic. It is preferable for midblock path crossings to intersect the roadway at an
angle as close to perpendicular as practicable. A minimum 60-degree crossing angle is
acceptable to minimize right of way needs. A diagonal midblock crossing can be altered as
shown in Exhibit 1515-8.
There are other considerations when designing midblock crossings. They include traffic right of
way assignments; traffic control devices; sight distances for both bicyclists and motor vehicle
operators; refuge island use; access control; and pavement markings.
Intersecting roadway
or railroad
Path
Notes:
For path and highway signing and markings, see the MUTCD and the Standard Plans.
http://www.wsdot.wa.gov/publications/fulltext/Standards/english/PDF/m09.60-00_e.pdf
For radii approaching roadway intersections, see Exhibit 1515-2.
Adjacent path crossings are located at or near public intersection crosswalks and are normally
placed with them. These crossings are usually placed with pedestrian crossings, where motorists
can be expected to stop. If alternate intersection locations for a shared-use path are available,
select the one with the greatest sight distance.
Adjacent path crossings occur where a path crosses an existing intersection of two roadways, a T
intersection (including driveways), or a four-way intersection, as shown in Exhibit 1515-9. It is
desirable to integrate this type of crossing close to an intersection so that motorists and path
users recognize one another as intersecting traffic. The path user faces potential conflicts with
motor vehicles turning left (A) and right (B) from the parallel roadway and on the crossed
roadway (C, D, and E).
Important elements that greatly affect the design of these crossings are traffic right of way
assignments, traffic control devices, and the separation distance between path and roadway.
Intersecting Roadway
Parallel Roadway E
Path
See Chapter
1510 and the
Standard Plans.
C D
Note:
For signing and pavement markings, see the MUTCD and the Standard Plans.
Signing
Provide sign type, size, and location in accordance with the MUTCD. Place path STOP signs as
close to the intended stopping point as feasible. Do not place the shared-use path signs where
they may confuse motorists or place roadway signs where they may confuse shared-use path
users. For additional information on signing, see the MUTCD and Chapter 1020.
Approach Treatments
Design shared-use path and roadway intersections with level grades, and provide sight
distances. Provide advance warning signs and pavement markings that alert and direct path
users that there is a crossing (see the MUTCD). Do not use speed bumps or other similar surface
obstructions intended to cause bicyclists to slow down. Consider some slowing features such as
horizontal curves (see Exhibits 1515-2 and 1515-8). Avoid locating a crossing where there is a
steep downgrade where bike speeds could be high.
Sight Distance
Sight distance is a principal element of roadway and path intersection design. At a minimum,
provide stopping sight distance for both the roadway and the path at the crossing. Decision sight
distance is desirable for the roadway traffic. Refer to Chapter 1260 for stopping sight distance
for the roadway and 1515.04(5) for shared-use path stopping sight distance.
Refuge Islands
Consider refuge islands where a shared-use path crosses a roadway when one or more of the
following applies:
High motor vehicle traffic volumes and speeds
Wide roadways
Use by the elderly, children, the disabled, or other slow-moving users
The refuge area may either be designed with the storage aligned perpendicularly across the
island or be aligned diagonal (as shown in Exhibit 1515-10). The diagonal storage area has the
added benefit of directing attention toward oncoming traffic since it is angled toward the
direction from which traffic is approaching.
Roadway
Shoulder
L
Sidewalk
Raised Island
X
Ramp Landing Ramp
Shared-Use Path
Y
Shared-Use Path
L = Length of taper
Sidewalk
X = Length of island
each side of path
Shoulder
not less than L
Roadway
Y = Width of refuge
6 ft = minimum
10 ft = maximum
For striping details, see the
Standard Plans and the MUTCD.
Note:
This exhibit shows a case where a path intersects a roadway framed with both a sidewalk and a paved shoulder,
for the purpose of showing detectible warning surface placements.
For undercrossings and tunnels, it is the Designer’s responsibility to determine the correct
minimum vertical clearance (shared use path pavement surface to overhead obstruction) of
each undercrossing or tunnel based on coordination with maintenance and emergency services.
The minimum vertical clearance for bicyclists and equestrians is 10 feet.
Consult the region Maintenance Office and the HQ Bridge Preservation Office to verify that the
planned path width and vertical clearance meets their needs. If not, widen and/or increase
vertical clearance to their specifications.
Use expansion joints that accommodate shared-use path users. Expansion joints should be
perpendicular to the path and have a maximum gap of ½ inch or be covered with a slip-resistant
plate.
The installation of protective screening is analyzed on a case-by-case basis. Refer to Chapter 720
for guidance.
Note:
On structures, the bridge railing type and height are part of the structure design. Contact the HQ Bridge and
Structures Office for additional information.
Notes:
The photo above shows a bridge with a shared-use path separating the users from the roadway. Pedestrian rail is
used on the outside edge.
On structures, the bridge railing type and height are part of the structure design. Contact the HQ Bridge and
Structures Office for additional information.
Refer to the MUTCD for guidance and directions regarding signing (regulatory, warning, and way
finding) and pavement markings.
The Standard Plans shows shared-use path pavement markings at obstructions in accordance
with the MUTCD and also shows placement of detectible warning surfaces.
For pavement marking around bollards and other obstructions, see Standard Plan M-9.60:
http://www.wsdot.wa.gov/publications/fulltext/standards/english/pdf/m09.60-00_e.pdf
The level of illumination on a shared-use path is dependent on the amount of nighttime use
expected and the nature of the area surrounding the facility. If illumination is used, provide
illumination in accordance with Chapter 1040.
1515.06(1) Fencing
Limited access highways often require fencing or other forms of controlling access. Shared-use
paths constructed within these corridors, such as shown in Exhibit 1515-13, likely require
fencing. For guidance on fencing, limited access controls, and right of way, refer to Division 5 of
the Design Manual. Evaluate the impacts of fencing on sight distances.
Bollards have been used by many path owners to prevent unauthorized vehicle access.
However, bollards should not be applied indiscriminately, and there are other considerations to
bollard installation.
A preferred method of restricting entry of motor vehicles is to split the entry way into two
sections separated by low landscaping, thereby splitting a path into two channels at roadway
intersections. This method essentially creates an island in the middle of the path rather than
installing a bollard. Such an island could be planted with low-growing, hardy vegetation capable
of withstanding the occasional authorized vehicle traveling over it. When splitting a path,
employ MUTCD pavement markings and signing, such as is used for bollards and obstructions.
Typically, one bollard located in the center of the path is sufficient to control motor vehicle
access to the path. If more than one bollard is needed, the additional bollards should be placed
at the edge of the shared-use path.
Install bollards at entrances to shared-use paths to discourage motor vehicles from entering. Do
not use bollards to divert or slow path traffic. When locating such installations, stripe an
envelope around the bollards and paint and reflectorize them to be visible to path users both
day and night. Bollards located on or adjacent to shared-use paths represent an object that
needs to be avoided by bicyclists and pedestrians. To increase the potential for appropriate
maneuvering to occur, provide designs where the post is clearly visible and recognizable.
Refer to the Standard Plans for bollard designs and the Standard Plans and MUTCD for pavement
markings at bollards.
When bollards need to be placed near the roadway, see Chapter 1600 for clear zone
requirements.
1515.07 Documentation
For the list of documents required to be preserved in the Design Documentation Package and
the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev/
Exhibit 1515 - 14a Stopping Sight Distance for Downgrades
Grade, G (%)
2
V
S 3.67V
0.30 f G
Where:
S = Stopping sight distance (ft)
V = Speed (mph)
f = Coefficient of friction (use 16)
G = Grade (%)
Note:
Shaded area represents grades greater than 5%.
2
V
S 3.67V
0.30 f G
Where:
S = Stopping sight distance (ft)
V = Speed (mph)
f = Coefficient of friction (use 16)
G = Grade (%)
AS 2 Where:
L when S < L S = Stopping sight distance (ft)
900
A = Algebraic difference in grade (%)
L = Minimum vertical curve length (ft)
900
L 2S when S > L Based on an eye height of 4.5 ft and an
A object height of 0 ft.
Note:
Below represents S ≤ L.
Shaded area represents A>10%.
R 1 R M
S COS Where:
28.65 R S = Sight distance (ft)
S ≤ Length of curve R = Centerline radius of inside lane (ft)
Angle is expressed in degrees. M = Distance from inside lane centerline (ft)
1520.01 General
The Washington State Department of Transportation (WSDOT) encourages and relies on bicycle
use on and interconnecting with its facilities. Bicycle facilities or improvements for bicycle
transportation are included in WSDOT’s project development and highway programming
processes.
This chapter is a guide for designing bicycle facilities within state highway right of way or
between the curb lines on city streets designated as state highways. When designing facilities
outside of state highway right of way or beyond the curb on city streets designated as state
highways, use the local agency’s design guidance. If the bicycle facility will have shared use with
pedestrians incorporate ADA requirements in Chapter 1515.
Guidance in this chapter applies to typical situations encountered on state highways, and
includes options for intersection and interchange design. Unique design challenges are resolved
using expertise and guidance from the regional Bicycle Coordinator or if none exists, the WSDOT
headquarters Bicycle Coordinator. Additional concepts to resolve unique bicycle facility design
situations can be found in guides referenced (1520.07), but may require additional approvals for
signing, pavement markings or bike facility types not presented within this chapter.
The region Traffic Engineer is responsible for determining which sections are inappropriate for
bicycle traffic on state highways. The State Traffic Engineer, after consultation with the Bicycle
Advisory Committee, prohibits bicycling on sections of state highways through the traffic
regulation process. Contact the region Traffic Office for further information.
Shared-use paths (see Chapter 1515) are the most protected type of bike facility because the
path is physically separated from motor vehicle traffic most commonly by a wide vegetated
outer separation or other physical barrier. Roadway bicycle facilities can range from separated
from motor vehicle traffic to physically sharing a lane with motor vehicle traffic. The following
subsections discuss five types of roadway bicycle facilities adopted for use on state highways.
All roadway bicycle facility types will be designated by striping, signage, and pavement markings
to indicate the preferential or exclusive use for bicycle users. See 1520.05(1) for more
information.
There are advantages in utilizing streetside zones in conjunction with a raised and curb-
separated bike facility. A furnishing zone can be used to help segregate pedestrian and bicycle
users or for additional separation between the bike facility and motor vehicle traffic. If a
furnishing zone is not used to separate the raised bike facility from the pedestrian zone,
consider different pavement types, signs, pavement borders, or striping within the streetside
zone to effectively separate pedestrian and bicycle users.
When the raised and curb-separated bike facility is placed adjacent to motor vehicle traffic,
consider using a sloped and mountable curb (see Chapter 1230) to enable passing maneuvers
between cyclists.
Within incorporated limits, raised and curb-separated bike facilities are located behind the curb
and therefore fall under a local agency’s jurisdiction. (See Chapters 1230, and 1600 for
additional information on jurisdictional boundaries). In these situations, follow the local
agency’s design guidance for this type of bike facility.
If parked vehicles within the parking zone are used as the vertical separator, the parking zone
cannot encroach onto the buffer area. When a separated buffered bike lane is positioned
between motor vehicle lanes and a parking zone, consider including an additional buffer area
between the parking zone and bike lane. Use of the buffer area described in these two
configurations facilitates loading and unloading of the parked vehicles, and reduces the risk of a
cyclist being struck when a parked vehicle door opens (aka “dooring”). See NACTO’s Urban
Bikeway Design Guide and Urban Street Design Guide for examples.
Exhibit 1520-2 shows an example of separated buffered bike lane using a flexible tubular marker
as the vertical separator. A painted buffer strip with flexible tubular marker helps accentuate
the bicycle facility from the motor vehicle lane, when curbing or a raised median (also
considered vertical separation) is not used for the buffer strip. Consider a 3-foot-wide buffer
strip whenever possible. When utilizing a buffer, the bike lane itself may be 3 feet in width.
However, 5 feet is recommended exclusively to the bike lane to enable passing maneuvers
between cyclists, and account for the effective width needs of bicyclists when drainage features
are present in the bike lane. In space constrained areas where inexperienced bicyclists, such as
children, are expected or where there is a steep uphill grade use a 4 foot minimum for the
bicycle lane. High bicyclist volume locations should consider more width to facilitate mobility
performance for this mode. In constrained spaces where lower volumes of cyclists are
anticipated and inexperienced bicyclists are not expected, the minimum total width of both the
bike lane and buffer combined is 5 feet.
Exhibit 1520-2 Separated Buffered Bike Lane
Shared lane markings (aka “sharrows”) are pavement markings specifically used to indicate a
shared lane or intersection space. The position of the marking can encourage a desired lateral
position within the lane for cyclists, as well as alerting motor vehicle users. Consider the shared
lane marking placement with respect to on-street parking and the potential for dooring that will
lower safety performance for the cyclist. Shared lane markings must be placed at least 4 feet
from the face of curb, or in the center of the shared lane (or at least 11 feet from face of curb)
when an adjacent parallel parking zone is present.
Conventionally, wide lanes have been encouraged for shared-lane applications, to allow for
motor vehicles to pass cyclists, or for cyclists to pass motor vehicles in a queue. However, wider
lanes may also encourage motor vehicle drivers to travel at higher speeds and a detriment for a
shared lane application. Permitting in-lane passing between motor vehicles and bicyclists can
lower safety performance for cyclists.
The speed of cyclists can vary significantly between users, and depends on the experience,
fitness level of the user, bike technology, and roadway grade. If a shared lane is proposed on an
hill, consider a conventional bike lane in the upgrade direction of travel.
1520.02(5)(a) Accommodating Bikes on Shoulders
Many rural highways are used by bicyclists for commuting between cities or for recreation.
Providing and maintaining paved shoulders can significantly improve convenience and safety for
both bicyclists and motorists along such routes.
Accommodating bicycle use on shoulders is appropriate at many locations. Note, however, that
bike on shoulder accommodations are not dedicated bicycle facilities, and bicycle users do not
have the same operating privileges as with designated roadway bike facilities. In rural to
suburban/urban transition areas consider converting the shoulder to a protected buffered bike
lane, both to encourage speed management of motor vehicle users through the transition and
to establish a dedicated special-use lane for cyclists to tie into the local network.
Understand how the state highway interfaces with routes identified as local, state, or regional
bike routes. If the state highway is the bike route, intersects with an existing route, or if bicycle
users are an identified modal priority (See Chapter 1103), account for the bike facility needs
within the design. Other projects need to consider a design that does not preclude the future
vision for a planned bike route, depending on the context identification selection (See Chapter
1102) and design year selection (See Chapter 1103).
The only instance during planning or design when performance effects on existing or planned
bike facilities may not be considered is in locations being designed for the existing context, and
the location is prohibits bicycle use. State highways that prohibit bike use can be found here:
http://www.wsdot.wa.gov/bike/closed.htm
The Interested, but Concerned cyclist constitutes the largest segment of cyclist types within
suburban, urban and small town populations. Bike facility selection on state routes is based on
designing for the “Interested, but Concerned” user type as a starting point. Exhibit 1520-6a
shows ranges of applications for the different types of bicycle facilities related to generally
accepted safety and mobility performance for this design user.
Other performance needs may increase or decrease the viability of certain types of bike
facilities, such as shared-use paths through aesthetic areas or those planned for a mixture of
commute and recreational purposes. Further considerations for cyclist perception of comfort
are another factor that can affect use of the facility. Designing for a higher level of separation
may be more important at locations that serve community activity centers, schools or popular
destinations (such as a retail oriented segment of a route) where additional accommodations
are appropriate for either the functional uses or less skilled cyclists (including children). In these
situations, separated facilities or wider dimensions may provide the level of comfort needed to
satisfy user needs and context considerations. Additionally, some suburban, urban, and small
town contexts will have more specific bicycle performance needs that will help identify either
spot improvements or alteration of the type of existing facility to enhance a specific
performance area. Bike facility selection in 1520.03(1)(b) are provided for these reasons.
In some contexts, it is appropriate to design for the Strong and Fearless, and Enthused and
Confident user types. In cases, where right of way is very constrained or where bicycles are
not considered the modal priority (see Chapter 1103), it is appropriate to use Exhibit 1520-
6b for determining facility selection after input from community engagement efforts.
However, understand that the application of Exhibit 1520-6b may result in less mode shift or
use of the capacity provided.
Exhibit 1520-6a Bicycle Facility Selection Chart – Interested, but Concerned Cyclists
Note: Adapted from Montgomery County Bicycle Planning Guidance, Montgomery County Department of Transportation, 2014.
Intersection design to meet the bicycle safety and mobility performance of the cyclist is unique
to each location. The primary emphasis is to create a visible, distinct, predictable and clear path
for the cyclist to reduce conflicts between cyclists and other design users. This is most
commonly achieved through clear delineation of the bike facility leading up to and through the
intersection, along with segregating or prioritizing movements between design users. Several
proven state-of-the-practice intersection treatments are presented within this section.
However, pavement marking or aspects about the configuration may not currently be supported
by the Manual on Uniform Traffic Control Devices.
At the time of publication, bike boxes (1520.04(2)) and two-stage left turn lanes (1520.04(3)) are
subject to an experimentation request to FHWA. Obtain Headquarters (HQ) Traffic Office
approval and assistance with submitting a request for experimentation. Consult, as appropriate,
the Federal Highway Administration’s (FHWA) MUTCD website for bicycle facilities for a listing of
the current status of bicycle-related pavement markings and treatments:
http://www.fhwa.dot.gov/environment/bicycle_pedestrian/guidance/mutcd/index.cfm.
See 1520.05(1) for additional information on bicycle pavement markings under MUTCD
evaluation.
Note: Exhibits 1520-7 through 1520-9 all show colored pavement markings to increase the
safety performance of intersection designs. However, colored pavement markings are not
required, and may be added at a later stage if the desired safety performance is not met.
There are several different ways to delineate bike lanes through the intersection. Dotted lines
are the most common, but can be combined with sharrows or green pavement markings (see
1520.05(1)) to further enhance the bike facility’s presence and position within an intersection.
This treatment can increase safety performance by reducing conflicts between cyclists and other
users, segregating motor vehicle and bicycle users, and separating turning cyclists from through
cyclists.
The position of the queue box is a critical aspect of this intersection design. Depending on the
size and configuration of the intersection, it may present a modal performance trade-off
between bicycle mobility and safety versus motor vehicle mobility performance. Use turn
simulation software to verify the queue box is outside the crossroad left-turn path, or restrict
left turns at the crossroad to accommodate the queue box. Similarly, right turns may need to be
restricted for motor-vehicles approaching the queue box if motor vehicle right-turn lanes or
right-turn pockets are not present.
Notes:
Not to scale and not all dimensions shown.
See 1520.05(1)(a) for criteria when considering the use of green colored pavement markings.
Consider both the speed of motorized vehicles and bicyclists when determining the length of weave and degree of taper for the bike lane.
Notes:
• This exhibit is intended to illustrate options for bike facilities through interchange areas, and not intended to represent recommended practice for any
other features including ADA criteria (See Chapter 1510 for ADA and pedestrian design).
• See 1520.05(1)(a) for criteria when considering the use of green colored pavement markings.
Notes:
• This exhibit is intended to illustrate options for bike facilities through interchange areas, and not intended to represent recommended practice for any
other features including ADA criteria (See Chapter 1510 for ADA and pedestrian design).
• Consider both the speed of motorized vehicles and bicyclists when determining the length of weave and degree of taper for the bike lane.
• See 1520.05(1)(a) for criteria when considering the use of green colored pavement markings.
Push button actuators may also be used to facilitate movement of bicyclists through a signalized
intersection. However, requiring bicyclists to go out of their way to use push button actuators
may create motor vehicle driver confusion of the bicyclists intended path through the
intersection, as well as inconveniencing the bicyclist. If pushbutton actuators are used, consider
their position relative to the bike facility. Pushbutton actuators are more effective when the
bike facility is adjacent to the curb (curb extensions at intersections can create this
environment). Consider an additional push button actuator for the exclusive use of cyclists when
positioning of the actuator is in conflict with ADA design requirements (see Chapter 1510). For
additional guidance on signal design, see Chapter 1330.
1520.04(4)(a) Bike Signals
Intersections with separated bike lanes, other complex multimodal intersection treatments or
those with a specific baseline need to increase bicycle user safety performance may incorporate
a dedicated bike signal head with detection or actuation systems. Bike signal heads further
separate modal user movements at intersections, while also allowing for priority to cyclists at
intersections. Contact the region Traffic Engineer for approval for application of this treatment.
At the time of this publication, bike signal faces are subject to requirements of FHWA Interim
Approval for this treatment. For current status of the treatment and conditions of the Interim
Approval, if still applicable, see
http://www.fhwa.dot.gov/environment/bicycle_pedestrian/guidance/mutcd/index.cfm
Median refuge islands provide a refuge for bicyclists to cross one direction of traffic at a time
while restricting motor-vehicle through movements on crossroads designated as primary bicycle
corridors or bike boulevards. The treatment minimizes impacts for bicyclists on the crossroad
while prohibiting motor vehicle left turn movements from the cross street to eliminate conflicts.
Consider median refuge islands when one or more of the following occurs:
Bike facilities cross a roadway with median restricted left turns.
Bike facilities cross a moderate to high (motor vehicle) volume roadway, with
intermediate motor-vehicle speeds
Bike facilities cross a 4 lane divided highway.
Separated or buffered bike facilities used on the cross street.
There is a performance need to restrict motor vehicle through traffic on a bike route.
Safety or mobility performance need of mainline cyclists exist for left turning
movements onto a bike route or shared use pathway
Exhibit 1520-10 shows an example of a median refuge designed for cyclists. Design refuge areas
between 4 and 5 feet wide (longitudinally with respect to the median), additional width may be
needed if high volumes of cyclists exist or are anticipated at the crossing. Consider the types of
cyclists and destinations when determining the median refuge length (lateral dimension with
respect to the median) to adequately store the bicycle. Consider what locations may need to
accommodate the length of a bicycle and trailer. The refuge area is to be in alignment with the
approach and receiving lanes of the crossroad. In other situations the median refuge island may
be designed for both pedestrians and bicycle users. When this is the case, design the median
refuge predominately for the pedestrian as with midblock crossings (See Chapter 1510), note
that additional lateral and longitudinal dimensions will be necessary.
HQ Traffic Office approval is necessary for traffic control devices not currently approved for use
through the MUTCD.
Green -colored pavement markings are a traffic control device whose need must be
demonstrated before use and documented with a design decision. The highest benefit of
applying green colored pavement markings occurs where the potential conflicts exist between
cyclists and other design users, or when other design users should yield to cyclists. Green
colored pavement markings are only intended as a supplemental treatment for standard striping
configurations for bicycle facilities.
The below criteria are provided when evaluating the need to apply green colored pavement
markings.
1. Existing Bike Facilities – retrofitting an existing facility with green pavement may be
considered when two or more of the following apply:
a. It is the engineering judgment of the Region Traffic Engineer
b. There is an existing traffic conflict area, such as bike lane crossing a motor vehicle
turn lane, and there are one or more observed motor vehicle and bicyclist crashes in
the last 5 years.
c. The bike mode is a modal priority (see Chapter 1103), and there is a baseline or
contextual need identified associated with increasing safety performance of the
mode.
d. When a bike route intersects a multilane highway, and the crossing is neither
signalized nor a roundabout.
2. Changing of Bike Facility Type –consider green pavement markings when one or more of the
following apply:
a. It is the engineering judgment of the Region Traffic Engineer.
b. A transition from a separated facility through a functional intersection or
interchange area necessitates additional delineation to create a clear, visible,
predictable and distinct travel path for bike users, and a bike signal or actuation
device is not used.
c. The facility type change does not substantively alter the configuration of an existing
conflict area, and there are one or more observed motor vehicle and bicyclist
crashes in the last 5 years at that conflict area.
3. New Bike Facility – Generally, the immediate application of green colored pavement on a
new bike facility is discouraged until the need for increased safety performance is
demonstrated. This said, consider green colored pavement when two or more of the
following conditions exist:
a. It is the engineering judgment of the Region Traffic Engineer
b. The bike mode is a modal priority (see Chapter 1103), and there is a baseline or
contextual need in which the application of green colored pavement markings is
needed to meet the stated modal safety performance target (see Chapter 1101).
c. The bike facility nodes and/or crossings are within 1 mile of activity centers, such as
schools, libraries, colleges, etc.
d. The bike facility crosses a motor vehicle free right turn to or from an interchange
ramp.
e. The bike facility is a bike route or bike boulevard (for definition, see NACTO’s Urban
Bikeway Design Guide).
f. The state route is also a city street, and the city policy or municipal code requires
green colored pavement markings as their standard.
g. The bike facility is raised and curb separated, and the city engineer requests green
colored pavement markings at either crossings or conflict areas.
Use green pavement markings to supplement the conventional white bike lane striping as
required by the MUTCD. Apply green colored pavement markings in conflict areas, consistent
with what is shown in Exhibits 1520-7 through 1520-9. Preceding the conflict area, apply solid
green 25-50 feet in length (see Exhibit 1520-11), use green ladder striping between the required
white dotted striping through the extent of the conflict area, and apply solid green after the
ladder striping for at least 25 ft but no more than 50 ft. If closely spaced conflict areas exist, it
may be appropriate to carry solid green into the next conflict area as determined by the Region
Traffic Engineer.
1520-11 Length of Solid Green Pavement Marking Preceding Conflict Area
30 mph 30 ft
Additional configurations or styles exist for the application of green colored pavement and can
be used with the approval of HQ Traffic Office. Consider specifically when bike route continuity
with a local agency’s bike facilities is a concern.
Provide drainage inlet grates on bicycle facilities that have openings narrow enough and short
enough that bicycle tires will not drop into the grates. Replace existing grates that are not
designed for bicycles: a WSDOT vanned grate, herringbone grate, or other grate with an opening
4 inches or less center to center and perpendicular to the direction of travel.
Direction of
bicycle travel
c ks
Bikeway Tra
RR
Large radii desirable
Striped
Widen to permit right
angle crossing
Bikeway
R a il
ro a d
Shoulder
14 ft
R/W
45°
Additional R/W
required
Bikeway
Curve
widening
Curve
widening
Additional R/W
required
R a ilr
Highway R/W
R a ilr
oad
oad
R/W
R/W
Bikeway
Bikeway
Shoulder
Shoulder
Notes:
Provide additional width at railroad crossings to allow bicyclists to choose their own crossing routes.
When pedestrians are provided for, design as a shared-use path (see Chapters 1510 and 1515).
On structures, the bridge railing type and height are part of the structure design. Contact the HQ
Bridge and Structures Office for additional information. (See Chapter 720 for further
considerations.)
Exhibit 1520-13 Barrier Adjacent to Bicycle Facilities
Bike lane
42" [1][2]
Edge of
traveled way
Bike Lane
Edge of
traveled way
Notes:
[1] Height does not apply to bridge railing. On structures, the bridge railing type and height are part of
the structure design. (Contact the HQ Bridge and Structures Office for additional information.)
[2] Applies to bike lanes. Additional height is not needed for shared-use roadways.
Consider providing bicycle parking facilities near public transportation stops to improve
accessibility performance needs.
In some cases, it is possible to align the bike facility to cross an off ramp with a more direct path
for the bike crossing (see Exhibit 1520-14d). Breaking up the work load for the motor vehicle
driver is one advantage of this configuration, similar to pedestrian treatments common in
roundabout design. Shortening the crossing distance required for the bicyclist is another
advantage with this configuration. Consider the inclusion of Rectangular Rapid Flashing Beacons
(RRFB) or a refuge island when there are multiple travel lanes. This configuration may also
require additional speed management (see Chapter 1103), signing or striping treatments on the
ramp.
Other situations may dictate additional delineation parallel to and matching the length of the
auxiliary lane provided at the ramp terminal as shown in Exhibit 1520-14b. This configuration
can be coupled with additional signing preceding the motor vehicle merge, and additional
separation or a buffer between the ramp’s auxiliary lane and the through bike lane. The length
of the motorized auxiliary lane will vary depending on speed and volume, so the length of green
markings shown in Exhibit 1520-11 may not adequately satisfy the delineation desired at these
locations. Consult with the Region Traffic Engineer for determining the length of green
pavement markings at interchange locations, when they are provided according to
1520.05(1)(a).
Exhibit 1520-14c provides a design option in which the bike lane merges with the sidewalk, and
requires bicyclists to cross an interchange ramp at the pedestrian crossing. This configuration is
ideal when bicycle mode is not identified as a modal priority, there is high motor vehicle ADT,
there is a large intersection design vehicle, there is intermediate to high motor vehicle speeds,
or when there are identification design users (see Chapter 1103) that suggests low experienced
bicyclists will be present. Consider inclusion of an RRFB or a median refuge island when there
are multiple lanes. Exhibits 1520-14b and 1520-14d also show the option of providing a bike
ramp to the sidewalk. Providing options for cyclists at interchanges is encouraged, since the
range of comfort among users is known to be diverse. Consult with the local agency regarding
any prohibitions against bicyclists using the sidewalk that may negate the ability to implement
this configuration.
Notes:
• Adapted from the Draft Recommended Design Guidelines to Accommodate Pedestrians and Bicycles at Interchanges, ITE, unpublished.
• This exhibit is intended to illustrate options for bike facilities through interchange areas, and not intended to represent recommended practice for any other features including ADA criteria (See Chapter 1510 for ADA and pedestrian
design).
Notes:
• Adapted from the Draft Recommended Design Guidelines to Accommodate Pedestrians and Bicycles at Interchanges, ITE, unpublished.
• This exhibit is intended to illustrate options for bike facilities through interchange areas, and not intended to represent recommended practice for any other features including ADA criteria (See Chapter 1510 for ADA and pedestrian
design).
• Consider both the speed of motorized vehicles and bicyclists when determining the length of weave and degree of taper for the bike lane.
Exhibit 1520-14c – Bicycle Facility Crossing Option for Dual Lane On-Ramp Configuration
Notes:
• Adapted from the Draft Recommended Design Guidelines to Accommodate Pedestrians and Bicycles at Interchanges, ITE, unpublished.
• This exhibit is intended to illustrate options for bike facilities through interchange areas, and not intended to represent recommended practice for any other features including ADA criteria (See Chapter 1510 for ADA and pedestrian
design).
Notes:
• Adapted from the Draft Recommended Design Guidelines to Accommodate Pedestrians and Bicycles at Interchanges, ITE, unpublished
• This exhibit is intended to illustrate options for bike facilities through interchange areas, and not intended to represent recommended practice for any other features including ADA criteria (See Chapter 1510 for ADA and pedestrian
design).
It is important to obtain information from maintenance regarding the facility type and
dimensioning, and discuss methods for maintaining the facility. The Maintenance Owner’s
Manual (See Chapter 301) is suggested to contain frequency, equipment needs and material
types necessary for the continual maintenance of facility features, including but not limited to:
Sweeping
Snow removal
Striping and pavement markings
Signing
1520.06 Documentation
Document the type of bike facility employed or changed in section 5 of the Basis of Design.
Dimensions chosen for the facility are documented on design parameter sheets.
1520.07 References
23 Code of Federal Regulations (CFR) Part 652, Pedestrian and Bicycle Accommodations and
Projects
Separated Bike Lane Planning and Design Guide, FHWA, current edition
http://www.fhwa.dot.gov/environment/bicycle_pedestrian/publications/separated_bikelane
_pdg/page00.cfm
Bicycle Parking Guidelines, Association of Pedestrian and Bicycle Professionals, current edition
http://www.apbp.org/?page=Publications
Manual on Uniform Traffic Control Devices for Streets and Highways, USDOT, FHWA; as adopted
and modified by Chapter 468-95 WAC “Manual on uniform traffic control devices for streets and
highways” (MUTCD)
www.wsdot.wa.gov/publications/manuals/mutcd.htm
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
www.wsdot.wa.gov/publications/manuals/m21-01.htm
NCHRP Report 766: Recommended Bicycle Lane Widths for Various Roadway Characteristics,
Transportation Research Board of the National Academies, 2014
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_766.pdf
NCHRP Report 500 Volume 18: A Guide for Reducing Collisions Involving Bicycles, Transportation
Research Board of the National Academies, 2006
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_500v18.pdf
Four Types of Cyclists?, Dill, Jennifer, and Nathan McNeil, Transportation Research Record:
Journal of the Transportation Research Board 2387.1 (2013): 129-138.
Separated Bike Lane Planning and Design Guide, Massachusetts Department of Transportation
(MassDOT), 2015
http://www.massdot.state.ma.us/highway/DoingBusinessWithUs/ManualsPublicationsForms
/SeparatedBikeLanePlanningDesignGuide.aspx
1600.01 General
Roadside safety addresses the area outside the roadway and is an important component of total
highway design. There are numerous reasons why a vehicle leaves the roadway, including driver
error and behaviors. Regardless of the reason, a roadside design can reduce the severity and
subsequent consequences of a roadside encroachment. From a crash reduction and severity
perspective, the ideal highway has roadsides and median areas that are relatively flat and
unobstructed by objects. It is also recognized that different facilities have different needs and
considerations, and these issues are considered in any final design.
It is not possible to provide a clear zone free of objects at all locations and under all
circumstances. The engineer faces many tradeoffs in design decision-making, balancing needs of
the environment, right of way, and various modes of transportation. The fact that
recommended design values related to the installation of barrier and other mitigation
countermeasures are presented in this chapter, does not mean that WSDOT is required to
modify or upgrade existing locations to meet current criteria.
Roadside safety may be addressed by projects identified through priority programming, during
certain preservation project activities (See Chapter 1120), or may be considered by projects as
part of a safety analysis (See Chapter 321). Elements such as sideslopes, fixed objects, and water
are all features that a vehicle might encounter when it leaves the roadway and become part of
such an analysis.
On projects where the need to mitigate objects is determined based on location related to
Design Clear Zone, consider the following mitigation measures in this order: (See 1600.02 Clear
Zone)
1. Remove
2. Relocate
3. Redesign a fixed object by using breakaway features or making the fixed object traversable
(See Section 1600.03)
4. Shield with a traffic barrier
5. Delineate (To only delineate requires a Design Analysis. If this seems to be your only option,
consult your Region traffic barrier expert or your Region’s ASDE.)
Factors for selecting a mitigation measure include, but may not be limited to:
Crash severity potential
Maintenance needs
Cost (initial and life cycle costs)
Rumble strips can be employed to reduce the potential for lane departure or roadside
encroachment in certain contexts (see Section 1600.05(1)). Use traffic barriers when other
measures cannot reasonably be accomplished and conditions are appropriate based on an
engineering analysis (See Chapter 1610).
In situations where the Design Clear Zone is beyond WSDOT right of way, evaluate options on a
case-by-case basis. Consider the nature of the objects within the Design Clear Zone, the roadway
geometry, traffic volume, and crash history. Coordinate with adjacent property owners when
proposed options include any work beyond WSDOT right of way. At a minimum, provide clear
zone to the limits of the WSDOT right of way.
Clear zone is measured from the edge of the through traveled way. All projects that alter the
relationship between the through lane and the roadside by widening or realignment have
altered the existing clear zone, and require an evaluation of objects in the clear zone. Auxiliary
lanes longer than 400 feet generally operate the same as a through lane and should be
considered through lanes for the purpose of determining Design Clear Zone.
1600.02(1) Design Clear Zone along Limited Access State Highways and
Other State Highways Outside Incorporated Cities and Towns
Use the Design Clear Zone Inventory form (Exhibit 1600-3) to identify features to be mitigated
and propose actions taken to address those features.
Guidance for establishing the Design Clear Zone for highways outside incorporated cities is
provided in Exhibit 1600-2. This guidance also applies to limited access facilities within the city
limits. Providing a clear recovery area that is consistent with this guidance does not require any
additional documentation. However, there might be situations where it is not practicable to
provide these recommended distances. In these situations, document the decision as a Design
Analysis as discussed in Chapter 300.
There is flexibility in establishing the Design Clear Zone in urbanized or urbanizing areas where
operating speeds are 35 mph or less. To achieve this flexibility, use a Design Analysis to establish
the Design Clear Zone that presents the tradeoffs associated with the decision. Provide
information on the benefits and effects of the Design Clear Zone selected in the Design Analysis,
including safety, aesthetics, the environment, economics, modal needs, and access control.
Although not a WSDOT policy document on clear zone, Chapter 10 of the AASHTO Roadside
Design Guide provides information to consider when performing a Design Analysis in urbanized
areas.
In curbed sections, and where applicable (e.g. parking), provide an 18-inch operational offset
beyond the face of curb for lateral clearance to accommodate opening car doors or large side
mirrors.
For projects on city streets as state highways that include work in those areas that are the city’s
responsibility and jurisdiction (see Exhibit 1600-1), design the project using the city’s develop-
ment/design standards. The standards adopted by the city must meet the requirements set by
the City Design Standards Committee for all arterial projects, bike projects, and federal-aid
projects. See the Local Agency Guidelines, Chapter 42, for more information on this Committee.
CL Auxiliary Lane
R/W R/W
or Bus Pullout
For managed access state highways inside incorporated cities, it is the city’s responsibility to
establish an appropriate Design Clear Zone in accordance with guidance contained in the City
and County Design Standards (Local Agency Guidelines, Chapter 42.) Exhibit 1600-1 shows an
example of state and city responsibilities and jurisdictions. Document the Design Clear Zone
established by the city in the Design Documentation Package. Have the responsible
transportation official from the city (e.g., City Engineer) document the Design Clear Zone, and
their acknowledgement and acceptance of the design and maintenance responsibilities for
project roadsides and medians, in a letter addressed to WSDOT, and file this letter as part of the
local agency coordination in the Design Documentation Package. Respond to the sender
acknowledging receipt.
free of fixed objects, these slopes are defined as nonrecoverable slopes. A vehicle might be able
to begin recovery on the shoulder, but likely will not be able to further this recovery until
reaching a flatter area (4H:1V or flatter) at the toe of the slope. Under these conditions, the
Design Clear Zone distance is called a recovery area. The method used to calculate the recovery
area and an example are shown in Exhibit 1600-4.
For ditch sections, the following criteria determine the Design Clear Zone:
(a) For ditch sections with foreslopes 4H:1V or flatter (see Exhibit 1600-5, Case 1, for an
example), the Design Clear Zone distance is the greater of the following:
The Design Clear Zone distance for a 10H:1V cut section based on speed and the
average daily traffic (ADT); or
A horizontal distance of 5 feet beyond the beginning of the backslope.
When a backslope steeper than 3H:1V continues for a horizontal distance of 5 feet beyond
the beginning of the backslope, it is not necessary to use the 10H:1V cut slope criteria.
(b) For ditch sections with foreslopes steeper than 4H:1V and backslopes steeper than 3H:1V,
the Design Clear Zone distance is 10 feet horizontal beyond the beginning of the backslope
(see Exhibit 1600-5, Case 2, for an example).
(c) For ditch sections with foreslopes steeper than 4H:1V and backslopes 3H:1V or flatter, the
Design Clear Zone distance is the distance established using the recovery area formula (see
Exhibit 1600-4; also see Exhibit 1600-5, Case 3, for an example).
The use of a traffic barrier for features other than those described below requires justification.
Fill slopes can increase the crash potential for an errant vehicle with the degree of severity
dependent upon the slope and height of the fill. Providing fill slopes that are 4H:1V or flatter can
mitigate this condition. If flattening the slope is not feasible or cost-effective, the installation of
a barrier might be appropriate. Exhibit 1600-6 represents a selection procedure used to
determine whether a fill sideslope constitutes a condition for which a barrier is a cost-effective
mitigation. The curves shown on Exhibit 1600-6 are based on the severity indexes and represent
the points where total costs associated with a traffic barrier are equal to the predicted cost of
crashes over the service life for selected slope heights without traffic barrier. If the ADT and
height of fill intersect on the “Barrier Recommended” side of the embankment slope curve, then
provide a barrier if flattening the slope is not feasible or cost-effective.
Do not use Exhibit 1600-6 for slope design. Design slopes consistent with guidance in Chapter
1239, evaluating designs with clear, traversable slopes before pursuing a barrier option. Also, if
Exhibit 1600-6 indicates that barrier is not recommended at a slope, that result is not
justification for a Design Analysis. For example, if the ADT is 4,000 and the embankment height
is 10 feet, barrier might be cost-effective for a 2H:1V slope, but not for a 2.5H:1V slope. This
process only addresses the crash potential on the slope. Objects on the slope can compound the
condition. Where barrier is not cost-effective, use the recovery area formula to evaluate fixed
objects on critical fill slopes less than 10 feet high.
A traversable cut slope reduces crash potential. The exception is a rock cut with a rough face
that might cause vehicle snagging rather than providing relatively smooth redirection.
Analyze the location and evaluate the roadside characteristics, crash potential, and other
benefits of treatment of rough rock cuts located within the Design Clear Zone. Conduct an
individual investigation for each rock cut or group of rock cuts. A cost-effectiveness analysis that
considers the consequences of doing nothing, removal, smoothing of the cut slope, grading at
the base of the rock cut to provide a smooth surface, and other viable options to reduce the
severity of the condition can be used to determine the appropriate treatment. Some potential
mitigative options are roadside barrier and rumble strips.
1600.03(2)(a) Trees
When evaluating new plantings or existing trees in the Design Clear Zone, consider the
maximum allowable diameter of 4 inches, measured at 6 inches above the ground when the
tree has matured. When removing trees within the Design Clear Zone, complete removal of
stumps is preferred. However, to avoid significant disturbance of the roadside vegetation, larger
stumps may be mitigated by grinding or cutting them flush to the ground and grading around
them.
Removal of trees may reduce the severity of impacts of roadway departure. It is recognized that
different facilities have different needs and considerations, and these issues are considered in
any design. For instance, removal of trees within the Design Clear Zone may not be desirable in
suburban, urban, or urban core areas, or in other land use contexts that provide for non-
motorized uses, such as a forest, park, or within a scenic and recreational highway. In these
situations, analyze crash reports’ contributing factors to determine whether roadside vegetation
is contributing to the severity of crashes. If large vegetation is removed, consult guidance
contained in established vegetation management plans, corridor plans, or the WSDOT Roadside
Manual. Additional guidance for maintenance of roadside vegetation can be found for some
routes in the Memorandum of Understanding between the US Forest Service and WSDOT,
Highways Over National Forest Lands, dated July 2002. In incorporated cities, refer to guidance
in 1600.02(2).
1600.03(2)(b) Mailboxes
For mailboxes located within the Design Clear Zone, provide supports and connections as shown
in the Standard Plans. The height from the ground to the bottom of the mailbox is 3 feet 3
inches. This height may vary from 3 feet 3 inches to 4 feet if requested by the mail carrier. If the
desired height is to be different from 3 feet 3 inches, provide the specified height in the contract
plans. (See Exhibit 1600-7 for installation guidelines.) Coordinate with homeowners when
upgrading mailboxes.
Where sidewalks are present, contact the postal service to determine the most appropriate
mailbox location. Locate mailboxes on limited access highways in accordance with Chapter 530,
Limited Access. A turnout, as shown in Exhibit 1600-7, is not needed on limited access highways
with shoulders of 6 feet or more where only one mailbox is to be installed. On managed access
highways, mailboxes are to be on the right-hand side of the road in the postal carrier’s direction
of travel. Avoid placing mailboxes along high-speed, high-volume highways. Locate
Neighborhood Delivery and Collection Box Units outside the Design Clear Zone.
1600.03(2)(c) Culvert Ends
Provide a traversable end treatment when the culvert end section or opening is within the
Design Clear Zone. No part of the culvert or end treatment should protrude more than 4"
above the ground line. Traversable end treatments include:
Culverts perpendicular to direction of travel:
o Culverts 36” and smaller as measured parallel to the direction of travel (Consider
treating these culvert ends even outside Design Clear Zone)
For roadway side slopes 4:1 or steeper, see Standard Plan B-70.20
For slopes flatter than 4:1 (see Standard Plan B-70.20 and note “treatment for
slopes flatter than 4:1”)
o Culverts larger than 36 inches, as measured parallel to the direction of travel,
require Type 1 safety bars. (See Standard Plan B-75.50)
Bars are permitted where they will not significantly affect the stream hydraulics and where
debris drift is minor. Consult the Region Maintenance Office and Region Hydraulics to verify
these conditions. If debris drift is a concern, consult Region Hydraulics for options to reduce the
amount of debris that can enter the pipe.
1600.03(2)(d) Signposts
Whenever possible, locate signs behind the standard run, but not the end terminals, of existing
or planned traffic barrier installations to eliminate the need for breakaway posts, and place
them such that the sign face is behind the barrier. (See Chapter 1020 for additional information
regarding the placement of signs.) Use the MUTCD to guide placement of the warning sign.
Signposts with cross-sectional areas greater than 16 square inches that are within the Design
Clear Zone and not located behind a barrier are to have breakaway features as shown in the
Standard Plans.
Sign bridges and cantilever sign supports are designed for placement outside the Design Clear
Zone or must be shielded by barrier.
1600.03(2)(e) Traffic Signal Standards/Posts/Supports
Breakaway signal posts generally are not feasible or desirable, and barrier is not generally an
option due to constraints typically found at intersection locations. To reduce potential for
drivers making contact with posts, and to avoid impeding the movement of pedestrian or
bicyclist traffic in the vicinity, locate posts in accordance with Chapter 1330.
For ramp meter systems, single lane ramp meters use breakaway Type RM signal standards.
Multilane ramp meters normally use Type II signal standards, which must either be located
outside of clear zone for all adjacent roadways or be protected by some type of barrier.
Fire hydrants are typically allowed on WSDOT right of way by franchise or permit. Fire hydrants
that are made of cast iron can be expected to fracture on impact and can therefore be
considered a breakaway device. Any portion of the hydrant that will not be breakaway must not
extend more than 4 inches above the ground. In addition, the hydrant must have a stem that
will shut off water flow in the event of an impact. Provide mitigation to address potential vehicle
impact with hydrant types not expected to fracture on impact.
Since utilities often share the right of way, utility objects such as poles are often located along
the roadside. It is normally undesirable or infeasible to install barrier for all of these objects, so
mitigation is usually in the form of relocation (underground or to the edge of the right of way) or
delineation. In some instances where there is a history of impacts with poles and relocation is
not possible, a breakaway design might be appropriate.
Evaluate roadway geometry and crash history as an aid in determining locations that exhibit the
greatest need. Contact the Headquarters (HQ) Design Office for information on breakaway
features. Coordinate with the HQ Utilities Unit when appropriate.
For policy and guidance on locating utility poles along state highways, also see Chapter 9 of the
Utilities Manual. Document the determination of appropriate mitigative measures and
coordination with the region Utilities Office.
Provide breakaway light standards unless fixed light standards can be justified, even if outside of
the Design Clear Zone. Fixed light standards may be justified if one of the following criteria are
met:
Posted speed is below 35 MPH (See 1600.02(1) for Design Clear Zone in urbanized and
urbanizing areas, and 1600.02(2) in cities).
Mounted on barrier (top or elbow mount).
Behind traffic barrier, beyond the barrier’s deflection design value (see Chapter 1610).
Within a parking lot.
Along isolated walkways and shared-use paths that are outside of Design Clear Zone.
1600.03(3) Water
Water with a depth of 2 feet or more and located with a likelihood of encroachment by an
errant vehicle is to be evaluated for mitigation.
Perform a benefit-cost analysis that considers the consequences of doing nothing versus
installing a longitudinal barrier to determine the appropriate treatment (see Chapter 321 for
more information). For fencing considerations along water features see Chapter 560.
1600.04 Medians
Median barriers are normally used on limited access, multilane, high-speed, high-volume
highways. These highways generally have posted speeds of 45 mph or higher. Median barrier is
normally placed on limited access state highways. Where median barrier is used on managed
access highways where bicyclists, pedestrians, and transit users are present, consider providing
accessible barrier openings at crossing locations. Providing access through median barrier
results in openings, therefore, end treatments are needed.
Provide median barrier on full access control multilane highways with median widths of 50 feet
or less and posted speeds of 45 mph or higher. Consider median barrier on highways with wider
medians or lower posted speeds when there is a history of cross-median crashes. Contact the
HQ Design Office for more information.
Provide a left-side shoulder when installing median barrier using width criteria given in Chapter
1230. Consider a wider shoulder area where the barrier might cast a shadow on the roadway
and hinder the melting of ice. (See Chapter 1239 for additional criteria for placement of median
barrier, Chapter 1610 for information on the types of barriers that can be used, and Chapter
1260 for lateral clearance on the inside of a curve to provide the needed stopping sight
distance.) Consider the need to accommodate drainage as a result of the addition of median
barrier treatments.
When median barrier is being placed in an existing median, identify the existing crossovers and
enforcement observation points. Provide the needed median crossovers in accordance with
Chapter 1370, considering enforcement needs. Chapter 1410 provides guidance on HOV
enforcement.
The pavement receiving rumble strips needs to be in good condition and thick enough to
support the rumble strips. Certain pavement types, such as open graded pavements, are not
suitable for rumble strip installation. Grinding rumble strips into inadequate pavement will lead
to premature deterioration of the surrounding pavement. Areas where the pavement is
inadequate for rumble strip installation require removal and replacement of the existing
pavement at and adjacent to the location of the rumble strip. Consult with the Region Materials
Engineer to determine whether the existing pavement is adequate for rumble strip installation.
The Region Materials Engineer will provide a pavement design for removing and replacing the
existing pavement near the rumble strip if needed. When installing both rumble strips and
recessed lane markers, follow the Standard Plan to avoid overlapping the grindings.
Installing rumble strips in bituminous surface treatment (or BST) or other thin surface
treatments can expose pavement structure and lead to delamination. In new rumble strip
locations where BST will be applied on an Hot Mix Asphalt (HMA) pavement, install the rumble
strips in the HMA pavement before placing the BST. In existing rumble strip locations, note that
a single application of BST on top of an existing rumble strip installation typically results in
satisfactory rumble strip depth. Where rumble strips currently exist and an additional BST
application is contemplated, evaluate whether the depth of the grooves following paving will
provide their continuing function to alert drivers. If not, or in the case of an HMA overlay, it may
be necessary to remove existing rumble strips and install new ones.
Provide an offset to the longitudinal paving joint so that rumble strips are not ground into the
joint where practicable. For additional guidance on surface preparation and pavement stability,
refer to the WSDOT Pavement Policy.
The noise created when vehicle tires contact a rumble strip may adversely impact nearby
residences and other land uses. Left-turning or passing vehicles, frequent passing maneuvers on
two lane highways, and off-tracking of vehicles or trailers in tight radius curves, are examples of
situations where incidental contact can happen. Noise impacts may be anticipated, and a low
noise rumble strip design may be warranted, when installing rumble strips in urban growth
areas, and/or within 600 feet of a residence, school, church, or campground. In situations where
a low noise rumble strip is desired but is not feasible, measures can still be taken to reduce
incidental contact, including discontinuing the rumble strip through frequently used road
approaches, through passing zones, and in tight radius curves. Contact HQ Design for more
information about low noise rumble strip designs, noise mitigation strategies, and the criteria
for employing them.
There are three types of rumble strip functions: roadway, shoulder, and centerline, and each are
described in the following sections.
Roadway rumble strips are placed transversely in the traveled way to alert drivers who are
approaching a change of roadway condition or object that requires substantial speed reduction
or other maneuvering. Some locations where advance roadway rumble strips may be placed
include:
Stop-controlled intersections
Port of entry/customs stations
Lane reductions where crash history shows a pattern of driver inattention, and
Horizontal alignment changes where crash history shows a pattern of driver
inattention.
They may also be placed at locations where the character of the roadway changes, such as at
the end of a freeway.
Contact the HQ Design Office for additional guidance on the design and placement of roadway
rumble strips.
Document decisions to use roadway rumble strips in the Design Documentation Package.
Shoulder rumble strips (SRS) are placed parallel to the traveled way just beyond the edge line to
warn drivers they are entering a part of the roadway not intended for routine traffic use.
Shoulder rumble stripes are rumble strips placed immediately under the shoulder delineation
paint, with any excess width milled or placed outward towards the shoulder. Shoulder rumble
stripes are only installed where there is insufficient space to install shoulder rumble strips per
one of the standard configurations (see Section 1600.05(1)(b)(2)).
When shoulder rumble strips and shoulder rumble stripes are used, discontinue them where no
edge stripe is present, such as at intersections and where curb and gutter are present.
Discontinue shoulder rumble strips and rumble stripes where shoulder driving is allowed.
Shoulder rumble strip and rumble stripe patterns vary depending on whether bicyclists are
expected to use the highway shoulder, and whether they are placed on divided or undivided
highways. Rumble strip patterns for undivided highways are shallower and may be narrower
than patterns used on divided highways. Rumble strips and rumble stripes installed on
undivided highways also provide gaps in the pattern, providing opportunities for bicycles to
move across the pattern without having to ride across the grooves. There are four shoulder
rumble strip and four shoulder rumble stripe patterns. Consult the Standard Plans (rumble
strips) or Plan Sheet Library (rumble stripes) for patterns and construction details.
1. Divided Highways
Install shoulder rumble strips on both the right and left shoulders of rural Interstate highways.
Consider them on both shoulders of rural divided highways. Use the Shoulder Rumble Strip or
rumble stripe Type 1 pattern on divided highways.
Shoulder rumble strips and rumble stripes may be omitted under any of the following
conditions:
When another project scheduled within two years of the proposed project will overlay
or reconstruct the shoulders or will use the shoulders for detours.
When overall shoulder width is less than 4 feet wide on the left and 6 feet wide on the
right. The minimum right shoulder width is reduced to 5 feet where rumble stripes are
used.
2. Undivided Highways
Shoulder rumble strips or rumble stripes are considered on undivided highways during
centerline rumble strip installation or pavement rehabilitation. A list of prospective locations are
provided to regions by HQ Design as a starting point in their development of a final list. The final
list is compiled based on a detailed review of the prospective locations using the following
criteria. Document decisions to omit prospective locations in the final list.
Shoulder rumble strips or stripes may be omitted from a highway segment under any of the
following conditions:
Where at least 4 feet of usable shoulder between the rumble strip and the outside
edge of shoulder cannot be provided. In cases where guardrail or barrier is present,
increase this dimension to a minimum of 5 feet of usable shoulder. Field-verify these
dimensions.
Where downhill grades exceed 4% for more than 500 feet in length along routes where
bicyclists are frequently present.
Where sections of rumble strips are omitted as a measure to reduce noise (see Section
1600.05(1)).
When selecting a rumble strip or rumble stripe design, consult the Standard Plans and Plan
Sheet Library for the patterns and construction details, and apply the following criteria:
Consider using a low noise pattern, or employ measures to reduce incidental contact,
in areas where noise impacts are anticipated (apply criteria in Section 1600.05(1)).
Consider using a rumble stripe pattern where usable shoulder width is less than 4 feet
(5 feet where barrier is present).
The Shoulder Rumble Strip Type 2 or Type 3 pattern is used on highways with minimal
bicycle traffic. Use the Shoulder Rumble Strip Type 4 pattern where the bicycle traffic
level on the shoulder is determined to be high. Consult the region and Headquarters
Bicycle and Pedestrian Coordinators to determine the bicycle traffic level, and engage
them in decision-making processes related to the use of rumble strips or rumble
stripes on bike touring routes, and/or on other routes where bicycle events are
regularly held.
Document the decision to omit shoulder rumble strips or rumble stripes in a Design Analysis,
when that decision is outside of the policy provided in this section (see Chapter 300.)
Centerline rumble strips are installed on the centerline of undivided highways to alert drivers
that they are entering the opposing lane. They are installed with no differentiation between
passing permitted and no passing areas. Refresh pavement markings when removed by
centerline rumble strips.
Centerline rumble strips are typically installed on rural highways where the posted speed is 45
mph or higher. They may also be installed on urban routes with posted speeds as low as 35
mph. A list of prospective centerline rumble strip installation locations are provided to regions
by HQ Design as a starting point in their development of a final list. The final list is compiled
based on a detailed review of the prospective locations using the following criteria.
Field verify lane and shoulder widths. See Chapter 1230 for guidance on lane and
shoulder widths. Centerline rumble strips are only installed where the combined lane
and shoulder width in either direction is greater than 12 feet.
In locations where the combined lane and shoulder width in either direction is 14 feet
or less, consider the level of bicyclist and pedestrian use along the route before
installing centerline rumble strips. When drivers shift their lane position away from
centerline to avoid the rumble strips, they are moving closer to pedestrians and
bicyclists on the shoulder.
Consider using a low noise rumble strip design in locations where noise is an issue, or
employ measures for reducing incidental contact where a low noise design is not
feasible (apply criteria in Section 1600.05(1)).
In urban areas, do not consider installing rumble strips where the need to interrupt the
rumble strip pattern to accommodate left-turning vehicles is very frequent, or where
the posted speed is 35 mph and below.
Do not use centerline rumble strips where two way left-turn lanes exist.
Document the decision to omit centerline rumble strips in a Design Analysis, when that
decision is outside of the policy provided in this section (see Chapter 300.)
Between a highway and an adjacent frontage road, multi-use path, or parallel highway,
especially where opposing headlights might seem to be on the wrong side of the driver.
At an interchange where an on-ramp merges with a collector-distributor and the ramp
traffic might be unable to distinguish between collector and main line traffic.
Where headlight glare is a distraction to adjacent property owners. Playgrounds, ball
fields, and parks with frequent nighttime activities might benefit from screening if
headlight glare interferes with these activities.
Glare screening is normally not justifiable where the median width exceeds 20 feet, and the ADT
is less than 20,000 vehicles per day. Document the decision to use glare screening using the
following criteria:
Higher frequency of night crashes compared to similar locations or based on statewide
experience.
Higher than normal ratio of night-to-day crashes.
Unusual distribution or concentration of nighttime crashes.
Over-representation of older drivers in night crashes.
Combination of horizontal and vertical alignment, particularly where the roadway on
the inside of a curve is higher than the roadway on the outside of the curve.
Direct observation of glare.
Public complaints concerning glare.
There are currently three basic types of glare screening available: chain link (see the Standard
Plans), vertical blades, and concrete barrier (see Exhibit 1600-8).
When the glare is temporary (due to construction activity), consider traffic volumes, alignment,
duration, presence of illumination, and type of construction activity. Glare screening may be
used to reduce rubbernecking associated with construction activity, but less expensive methods,
such as plywood that seals off the view of the construction area, might be more appropriate.
1600.06 Documentation
Refer to Chapter 300 for design documentation requirements.
1600.07 References
Local Agency Guidelines (City and County Design Standards), M 36-63, WSDOT
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01, WSDOT
Understanding Design Clear Zone – This e-learning course for WSDOT employees covers how to
determine the appropriate Design Clear Zone for recoverable and nonrecoverable slopes as well
as ditches. Request this training via the web-based Learning Management System.
Highways Over National Forest Lands, MOU, 2013, US Forest Service and WSDOT,
www.wsdot.wa.gov/publications/manuals/m22-50.htm
Utilities Manual, M 22-87, WSDOT. Chapter 9 provides Control Zone guidance for utilities in the
WSDOT right of way.
Notes:
This exhibit applies to:
All state highways outside incorporated cities.
Limited access state highways within cities.
For Roadside and Median areas on managed access state highways within incorporated cities, see 1600.02 for
guidance. Curb is not considered adequate to redirect an errant vehicle.
Design Clear Zone distances are given in feet, measured from the edge of traveled way.
*When the fill section slope is steeper than 4H:1V, but not steeper than 3H:1V, the Design Clear Zone distance is
modified by the recovery area formula (see Exhibit 1600-4) and is referred to as the recovery area. The basic
philosophy behind the recovery area formula is that the vehicle can traverse these slopes but cannot recover
(control steering); therefore, the horizontal distance of these slopes is added to the Design Clear Zone distance to
form the recovery area. Provide a minimum of 10 feet at the toe of all traversable, non‐recoverable fill slopes.
See: www.wsdot.wa.gov/design/support.htm for this form template in PDF, Word, or Excel spreadsheet.
(PDF Shown Below) Remember, this form has 2 sides when copying.
Front sheet
Back sheet
* When the fill section slope is steeper than 4H:1V, but not steeper than 3H:1V, the Design Clear Zone
distance is modified by the recovery area formula (see Exhibit 1600-4) and is referred to as the recovery
area. The basic philosophy behind the recovery area formula is that the vehicle can traverse these slopes
but cannot recover and return to the roadway (control steering); therefore, the horizontal distance of
these slopes is added to the Design Clear Zone distance to form the recovery area.
Formula:
Conditions:
Speed = 45 mph
Traffic = 3,000 ADT
Fore Slope = 3H:1V (Nonrecoverable)
Fill Slope = 6H:1V = 17 ft from Exhibit 1600‐2
Criteria:
Fore Slope 3H:1V Use recovery area formula
Recovery area = (shoulder width (8 ft)) + (nonrecoverable slope distance (12 ft)) + Greater of (1) or (2):
(1) 10 ft
(2) Design Clear Zone distance for 6H:1V (17 ft) – shoulder width (8 ft)) = 9 ft
Case 2: Cut section with ditch (foreslope steeper than 4H:1V and backslope steeper than 3H:1V)
Conditions: NA
Design Clear Zone = 19 ft
Criteria: 10 feet horizontal beyond
beginning of backslope 3 ft 6 ft 10 ft
Shld
Design Clear Zone = 19 feet
1V
2H :
3H:1
Edge of V
traveled way
Case 3: Cut section with ditch (foreslope 3H:1V or steeper and backslope not steeper than 3H:1V)
Conditions:
Design Clear Zone = 21 ft
Speed = 45 mph
Traffic = 3,000 ADT 6 ft 6 ft
Shoulder
Foreslope = 2H:1V
Backslope = 4H:1V 2H
:1V
Edge of 4H:1V
Criteria: Use recovery area formula traveled way
Recovery area = (shoulder width) + (horizontal distance) + (Design Clear Zone distance – shoulder width)
= 6 + 6 + (15 – 6 ) = 21
Note:
Chapter Organization: The first sections (Introduction and Barrier Impacts) present information to
consider when deciding whether to install a barrier. The next section (General Barrier Design
Considerations) contains guidance common to ALL barrier types, such as deflection distance, length
of need and sight distance. The remaining sections present design information organized by
specific barrier type (beam guardrail, cable barrier, etc.).
Refer to the Design Manual Glossary for many of the terms used in this chapter.
1610.01 Introduction
WSDOT uses traffic barriers to reduce the overall severity of crashes. Consideration is given
as to whether a barrier is preferable to the recovery area it may replace. In some cases,
installation of a traffic barrier may result in more crashes as it presents an object that can be
struck. Barriers are designed so that such encounters might be less severe and not lead to
secondary or tertiary crashes. However, traffic barriers are not guaranteed to redirect an
impacting vehicle without resulting injury to its occupants or triggering additional crashes.
Barrier performance is affected by the characteristics of the vehicles that collide with them.
Different vehicles will react differently given the characteristics and dynamics of the crash.
Therefore, vehicles will be decelerated and redirected differently given the size, weight and
direction of force imparted from the vehicle to the barrier.
Barriers are not placed with the assumption that the system will restrain or redirect all
vehicles in all conditions. It is recognized that the designer cannot design a system that will
address every potential crash situation. Instead, barriers are placed with the assumption
that, under typical crash conditions, they might decrease the potential for excessive vehicular
deceleration or excessive vehicle redirection when compared to the location without the
barrier.
Traffic barriers do not prevent crashes or injuries from occurring. They often lower the
potential severity for crash outcomes. Consequently, barriers should not be used unless a
reduced crash severity potential is likely. No matter how well a barrier system is designed,
optimal performance is dependent on drivers’ proper maintenance and operation of their
vehicles and the proper use of passenger restraint systems. The ultimate choice of barrier
type and placement should be made by gaining an understanding of site and traffic
conditions, having a thorough understanding of and applying the criteria presented in
Chapters 1600 and 1610, and using engineering judgment.
Barrier systems and vehicle fleets continue to evolve. The choice of a barrier is based on the
characteristics of today’s vehicle fleet and testing criteria, not on speculative assumptions of
future vehicle designs. This continuum of change does not allow engineers to predict the
future with any degree of certainty. Consequently, engineering decisions need to be made
based on the most reliable and current information.
Engineers are constantly striving to develop more effective design features to improve
highway safety. However, economics, asset management and maintenance needs, and
feasibility do not permit the deployment of new designs as soon as they become available on
the market or are invented by a manufacturer. Further, most new designs only make
marginal changes to systems and do not imply that old designs are unsafe or need
modification.
Solutions may consider crash frequency and severity. As discussed previously, performance
of the system relies on the interaction of the vehicle, driver, and system design at any given
location. Additionally, the ability to safely access, maintain and operate over time is
incorporated into the final barrier decision.
As roadside safety hardware changes occur on the highway system they will use MASH crash
testing criteria instead of NCHRP Report 350. To learn more about WSDOT’s plan for
implementing MASH-compliant hardware see the following website:
http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm
Traffic-related wildlife mortality may play a role in the decline of some species listed under
the Endangered Species Act. To address wildlife concerns, see Exhibit 1610-1 to assess
whether barrier placement needs to have an evaluation by the HQ Environmental Services
Office to determine its effect on wildlife. Conduct this evaluation early in the project
development process to allow adequate time for discussion of options.
Chapter 1120 identifies those elements and features to be evaluated and potentially
addressed during the course of a Preservation project.
Follow the guidance in this chapter for any project that introduces new barrier onto the
roadside (including median section) and follow the guidance in Chapter 1600 for removal of
barrier that is not needed. Slope flattening is recommended when the crash reduction
benefit justifies the additional cost to eliminate the need for barrier.
When selecting a barrier, consider the barrier system’s deflection characteristics, cost,
maintainability and impacts to traffic flow during repair. Barriers are categorized as flexible,
semi-rigid, or rigid depending on their deflection characteristics (see Exhibit 1610-3). Barrier
types include:
Beam Guardrail
Cable Barrier
Concrete Barrier
Bridge Traffic Barrier
Other Barriers
Since non-rigid systems typically sustain more damage during an impact, consider the
amount of traffic exposure maintenance crews might incur with the more frequent need for
repairs.
The costs for procuring and maintaining the barrier system are important factors when
considering what system to install. Considerations may include:
Consultation with the Area Maintenance Superintendent to identify needs or
recommendations.
Drainage, alignment, and drifting snow or sand are considerations that can
influence the selection of barrier type. Beam guardrail and concrete barrier can
contribute to snow drifts. Consider long-term maintenance costs associated with
snow removal at locations prone to snow drifting. Cable barrier is not an
obstruction to drifting snow.
Analysis of potential reduction of sight distance due to barrier selection and
placement.
Additional widening and earthwork requirements. With some systems, such as
concrete barrier and beam guardrail, the need for additional shoulder widening or
slope flattening is common. Selection of these types of barriers may require
substantial environmental permitting or roadway reconstruction. Permits issued
under the SEPA and NEPA processes may lead to the use of a barrier design, such as
cable barrier, which has fewer potential environmental impacts and costs.
For concrete barrier systems:
o Lower maintenance costs than for other barrier types.
o Deterioration due to weather and vehicle impacts is less than most other
barrier systems.
o Unanchored precast concrete barrier can usually be realigned or
repaired after a vehicle impact. However, heavy equipment may be
necessary to reposition or replace barrier segments. Therefore, in
medians, consider the shoulder width and the traffic volume when
determining the acceptability of unanchored precast concrete barrier
versus rigid concrete barrier. See Exhibit 1610-3 for deflection area
requirements.
For roadside or wide median installations of flexible and semi-rigid roadside barriers (high
tension cable barrier and beam guardrail), the deflection distance is designed to prevent the
impacting vehicle from striking the object being shielded. For unrestrained rigid systems
(unanchored precast concrete barrier), the deflection distance is designed to help prevent
the barrier from being knocked over the side of a drop-off or steep fill slope (2H:1V or
steeper).
For narrower median installations, design systems so that the anticipated deflection will not
enter the lane of opposing traffic. When evaluating new barrier installations, consider
whether impacts would require significant traffic closures to accomplish maintenance. Rigid
embedded barrier systems are used when no barrier deflection is necessary or desired (areas
such as narrow medians, at the edge of bridge decks, or other vertical drop-off areas). Runs
of rigid embedded concrete barrier can be precast, cast in place, or extruded with
appropriate footings.
In locations where deflection distance is limited, precast concrete barrier can be anchored.
Some movement can be expected for rigid anchored barrier systems and repairs may be
more expensive (anchoring pins may damage the asphalt or concrete surface that the barrier
is placed upon during a vehicle collision).
Use of an anchored precast concrete barrier and other deflecting barrier systems placed on
top of a retaining wall at less than the deflection distances provided in Exhibit 1610-3
requires approval from the HQ Design Office. See 1610.06 for more information on concrete
barrier.
Exhibit 1610-3 provides barrier deflection design values when selecting standard runs of
longitudinal barrier. This exhibit does not provide deflection values for specialty barrier
systems or installations (for example long span guardrail systems, box culvert guardrail
systems, Type 31 barrier installed on a flare, etc.). Contact HQ Design for specialty barrier
systems or installations deflections. The deflection values for cable and beam guardrail are
minimum distances measured between the face of the barrier to the fixed feature. The
deflection values for concrete barrier are minimum distances measured from the back edge
of the barrier to the fixed feature, drop-off, or slope break.
Notes:
This exhibit provides deflection values for standard runs of barrier. It does not provide
deflection values for specialty systems or installations (e.g. long span guardrail systems, box
culvert guardrail systems, Type 31 barrier installed on a flare, etc.).
[1] See 1610.05(2)
[2] When placed in front of a 2H:1V or flatter fill slope and not shielding fixed
objects, the barrier deflection distance can be reduced to 2 feet.
[3] When used as temporary bridge rail, anchor all barrier when the back of barrier
is located within 3 feet of a drop-off.
[4] Place any new objects a minimum of 5 feet from the face of existing beam
guardrail type 1.
[5] Steel barrier is also available for temporary applications. See Ch. 1010 for more
information.
[6] When anchoring temporary precast concrete barrier on bridges or other drop-
offs, see applicable Standard Plans for anchorage details, lateral offsets, and
deflection distances.
[7] When placed in front of a fill slope or on top of an MSE wall, provide a minimum
distance of 2-feet of widening with a 10:1 or flatter slope from the back of barrier to
the slope break point.
Flare the ends of longitudinal barriers where site constraints allow (see 1610.01(1)). The four
functions of a flare are to:
Maximize the distance between the barrier (and its terminal) and the travelled way.
Reduce the length of need.
Redirect an errant vehicle.
Minimize a driver’s reaction to the introduction of an object near the traveled way.
Keeping flare rates as flat as site constraints allow preserves the barrier’s redirectional
performance and minimizes the angle of impact. It has also been shown that an object (or
barrier) close to the traveled way might cause a driver to shift laterally, slow down, or both.
The flare reduces this reaction by gradually introducing the barrier so the driver does not
perceive the barrier as an object to be avoided. The flare rates in Exhibit 1610-4 are intended
to satisfy the four functions listed above. Flares that are more gradual may be used. Flare
rates are offset parallel to the edge of the traveled way. Transition sections are not flared.
Situations exist where hardware installations may have barrier flare rates different than
shown in Exhibit 1610-4. If a Standard Plan for a barrier installation shows a different flare
rate than is shown in Exhibit 1610-4, the flare rate shown on the Standard Plan can be used.
In many cases, there may be a portion of the traffic barrier installation that is not redirective
in capability. For instance, if a run of concrete barrier is terminated with an impact
attenuator, there will likely be a section of the impact attenuator that is not redirective (see
Chapter 1620 for more information). Therefore, in most cases, the Length of Need does not
equal (i.e., it is shorter than) the actual physical length of the traffic barrier installation
required to achieve that length of need.
Length of need is dependent on the location and geometrics of the object, direction(s) of
traffic, posted speed, motor vehicle traffic volume, and type and location of traffic barrier.
When designing a barrier for a fill slope (see Chapter 1600), the length of need begins at the
point where the need for barrier is recommended. For fixed objects and water, Exhibit 1610-
5 shows design parameters for determining the needed length of a barrier for both adjacent
and opposing traffic on relatively straight sections of highway.
When barrier is to be installed on the outside of a horizontal curve, the length of need can be
determined graphically as shown in Exhibit 1610-7. For installations on the inside of a curve,
determine the length of need as though it were straight. Also, consider the flare rate, barrier
deflection, and barrier end treatment to be used.
When beam guardrail is placed in a median, consider the potential for impact from opposing
traffic when conducting a length of need analysis. When guardrail is placed on either side of
objects in the median, consider whether the trailing end of each run of guardrail will shield
the leading end of the opposing guardrail. Shield the leading end when it is within the Design
Clear Zone of opposing traffic (see Exhibit 1610-8). This is also a consideration when objects
are placed in the outer separations between the main line and collector-distributors.
Before the actual length of need is determined, establish the lateral distance between the
proposed barrier installation and the object shielded. Provide a distance that is greater than
or equal to the anticipated deflection of the longitudinal barrier. (See Exhibit 1610-3 for
barrier deflections.) Place the barrier as far from the edge of the traveled way as possible
while maintaining the deflection distance.
If the end of the length of need is near an adequate cut slope, extend the barrier and embed
it in the slope (see 1610.04(5)). Avoid gaps of 300 feet or less. Short gaps are acceptable
when the barrier is terminated in a cut slope. If the end of the length of need is near the end
of an existing barrier, it is recommended that the barriers be connected to form a continuous
barrier. Consider maintenance access issues when determining whether or not to connect
barriers.
Note:
For supporting length of need equation factors, see Exhibit 1610-6
Design Parameters
ADT Barrier Type
Posted
Rigid &
Speed Rigid
Over 5,000 to 1,000 to Under Rigid Semi-rigid
(mph) Unrestrained
10,000 10,00 4,999 1,000 Anchored Barrier
Barrier
Barrier
LR (ft) LR (ft) LR (ft) LR (ft) F F F
70 360 330 290 250 20 18 15
65 330 290 250 225 20 18 15
60 300 250 210 200 18 16 14
55 265 220 185 175 16 14 12
50 230 190 160 150 14 12 11
45 195 160 135 125 12 11 10
40 160 130 110 100 11 10 9
35 135 110 95 85 11 10 9
30 110 90 80 70 11 10 9
25 110 90 80 70 11 10 9
L1 = Length of barrier parallel to roadway from adjacent-side fixed feature to beginning of barrier flare. This is
used if a portion of the barrier cannot be flared (such as a bridge rail and the transition).
L2 = Distance from adjacent edge of traveled way to portion of barrier parallel to roadway.
L4 = Length of barrier parallel to roadway from opposite-side fixed feature to beginning of barrier flare.
L5 = Distance from centerline of roadway to portion of barrier parallel to roadway. Note: If the fixed feature is
outside the Design Clear Zone when measured from the centerline, it may only be necessary to provide a
crash-tested end treatment for the barrier.
LH1 = Distance from outside edge of traveled way to back side of adjacent-side fixed feature.
Note: If a fixed feature extends past the Design Clear Zone, the Design Clear Zone can be used as LH1.
LH2 = Distance from centerline of roadway to back side of opposite-side fixed feature. Note: If a fixed feature
extends past the Design Clear Zone, the Design Clear Zone can be used as LH2.
LR = Runout length, measured parallel to roadway.
X1 = Length of need for barrier to shield an adjacent-side fixed feature.
X2 = Length of need for barrier to shield an opposite-side fixed feature.
F = Flare rate value.
Y = Offset distance needed at the beginning of the length of need.
Different end treatments need different offsets:
For the SRT 350 and FLEAT 350, use Y = 1.8 feet.
For evaluating existing BCTs, use Y = 1.8 feet.
For the FLEAT TL-2, use Y = 0.8 feet.
No offset is needed for the non-flared terminals or impact attenuator systems. Use Y = 0.
Notes:
This is a graphical method for determining the length of need for barrier on the
outside of a curve.
On a scale drawing, draw a tangent from the curve to the back of the fixed feature.
Compare T to LR from Exhibit 1610-6 and use the shorter value.
If using LR, follow Exhibits 1610-5 and 6.
If using T, draw the intersecting barrier run to scale and measure the length of
need.
Exhibit 1610-8 W-Beam Guardrail Trailing End Placement for Divided Highways
Installed incorrectly, strong post W-beam guardrail can cause vehicle snagging or spearing.
This can be avoided by lapping the rail splices in the direction of traffic (as shown in the
Standard Plans), by using crash-tested end treatments, and by blocking the rail away from
the posts.
Type 31 guardrail offers tolerance for future HMA overlays. The system allows a 3-inch
tolerance from 31 inches to 28 inches without adjustment of the rail element.
Existing runs of Type 1 guardrail are acceptable to leave in place. If an existing run of Type 1
guardrail requires extending, use the Beam Guardrail Type 31 to Beam Guardrail Type 1
Adaptor shown in the Standard Plans, and complete the guardrail extension using Type 31
guardrail.
Type 4 guardrail is a double-sided version of the Type 1 guardrail system. For new
installation, use the Type 31 double-sided w-beam guardrail instead of Type 4 guardrail.
Existing runs of Type 4 guardrail are acceptable to leave in place. If the existing run of Type 4
requires extending contact WSDOT Design Office to identify appropriate extension methods
to transition to the Type 31 double-sided system.
Type 10 and Type 11 are thrie-beam guardrail systems. Existing runs of Type 10 or 11
guardrail are acceptable to leave in place. If an existing run of Type 10 or Type 11 guardrail
requires extending, contact the WSDOT Design Office to discuss options.
Weak post W-beam guardrail (Type 20) and thrie beam guardrail (Type 21) are flexible
barrier systems primarily used in conjunction with a Service Level 1 bridge rail system for
bridges with timber decks. These systems use weak steel posts. For information on Type 20
and Type 21 guardrail see: http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm
of a fill slope (see Exhibit 1610-9, Case 2). If the slope is 2H:1V or flatter, this
distance can be 2.5 feet measured from the face of the guardrail rather than the
back of the post (see Exhibit 1610-9, Case 1).
On projects where no roadway widening is proposed and site constraints prevent
providing the 2-foot shoulder widening behind the barrier, long post installations
are available as shown in Exhibit 1610-9, Cases 3, 4, 5, and 6. When installing
guardrail where the roadway is to be widened or along new alignments, the use of
Cases 5 and 6 requires a Design Analysis.
Notes:
Use Cases 1 and 3 when there is a 2.5-foot or greater shoulder widening from face
of guardrail to the slope breakpoint.
Use Case 2 when there is a 4.0-foot or greater shoulder widening from the face of
the guardrail to the slope breakpoint.
Use Cases 4, 5, and 6 when there is less than a 2.5-foot shoulder widening from face
of guardrail to the slope breakpoint.
Cases shown do not apply to terminals, transition sections or anchors. Install
terminals, transition sections and anchors per the Standard Plans.
For other projects requiring evaluation of guardrail (see Section 1105.02(1)), evaluate the
guardrail system height as follows:
For existing Type 1 guardrail with heights falling outside the range from 26.5 inches
to 31 inches, adjust or replace the rail to a minimum height of 28 inches up to a
maximum height of 30 inches, or replace the run with 31-inch-high Type 31 beam
guardrail.
For existing Type 31 guardrail runs with heights falling outside the range of 28 to 32
inches, adjust or replace the rail to a height of 31 inches, or replace the run with a
new run of 31-inch-high Type 31 beam guardrail.
For Type 1 and Type 31 standard run W-beam guardrail, the blockout and rail element may
be raised up to 4 inches by field drilling a new hole in the guardrail post. Verify that the
condition of the posts and blockouts are suitable for raising in this manner. If not, the post or
block will need to be replaced. See the Standard Plans.
If Type 1 Alternative W-beam guardrail is present, the blockout and rail element may be
raised after each overlay by using the pre-drilled holes in the guardrail posts.
See Section 1610.04(5) for information on adjusting the height of guardrail terminals.
See Chapter 1120 for guidance regarding the evaluation of terminals on Preservation
projects (P1, P2, and P3).
For other projects requiring evaluation of terminals (see Section 1105.02(1)), evaluate the
terminals as follows:
Replace guardrail terminals that do not have a crash-tested design with MASH compliant
crash-tested guardrail terminals. Common features of systems that do not meet current
crash-tested designs include:
No cable anchor.
A cable anchored into concrete in front of the first post.
Second post not breakaway (CRT).
Design A end section.
Design C end sections may be left in place if the terminal is otherwise a crash-tested
design —see the Standard Plans for end section details.
Terminals with beam guardrail on both sides of the posts (two-sided).
Buried guardrail terminals that slope down such that the guardrail height is reduced
to less than 28 inches (measured in relation to a 10H:1V line extended from the
breakpoint at edge of shoulder).
When the height of a terminal or anchor, as measured from the ground to the top of the rail
element, will be affected by the project, adjust the terminal or anchor based upon the
following criteria:
If the height of the terminal or anchor adjoining Types 1, 2, 3, or 4 guardrail will be
reduced by the project to be less than 26.5 inches or increased to greater than 30
inches, adjust the height of the terminal to a minimum of 28 inches and a maximum
of 30 inches. A terminal height of 30 inches is desirable to accommodate future
overlays.
If the height of the terminal or anchor adjoining Type 31 guardrail will be reduced
by the project to be less than 28 inches or increased to greater than 32 inches,
adjust the height to 31 inches.
When adjusting terminals that are equipped with CRT posts, the top-drilled holes in
the posts need to remain at the surface of the ground.
When adjusting the height of a terminal or anchor, adjust it by raising the posts of
the terminal or anchor and tamping the ground around the posts to prevent
settlement of the raised posts. Note: do not raise the blockouts or rail of the
terminal or anchor by drilling new holes in the terminal posts.
One terminal that was used extensively on Washington’s highways was the Breakaway Cable
Terminal (BCT). This system used a parabolic flare similar to the Slotted Rail Terminal (SRT)
and a Type 1 anchor (Type 1 anchor posts are wood set in a steel tube or a concrete
foundation). For guidance regarding BCT’s and other terminals on Preservation projects see
Chapter 1120. For non-Preservation projects, replace BCTs with a currently approved
terminal using the following guidance:
Replace adjacent transition sections that are not compliant with 1610.04(6).
Transition from Type 1 to Type 31 using the adaptor (Standard Plan C‐25.80) where
required.
Raise or replace the entire run if engineering judgement indicates that it is prudent
for that situation.
Use the grading criteria shown on the terminal standard plans (C‐22.40 or C‐22.45).
When using existing grading, check to see that it complies with the grading criteria
shown on the current terminal standard plans.
Information regarding (Old) Type 1 beam guardrail terminals can be found at:
http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm
For new BT installations, use the Buried Terminal Type 2. Previously, another BT option (the
Buried Terminal Type 1) was an available choice. For existing installations, it is acceptable to
leave this option in service as long as height requirements and other design criteria is met.
See the plan sheet at: www.wsdot.wa.gov/design/standards/plansheet.
The BT uses a Type 2 anchor to develop the tensile strength in the guardrail. The backslope
needed to install a BT is to be 3H:1V or steeper and at least 4 feet in height above the
roadway. The entire BT can be used within the length of need for backslopes of 1H:1V or
steeper if the barrier remains at full height in relation to the roadway shoulder to the point
where the barrier enters the backslope.
For backslopes between 1H:1V and 3H:1V, design the length of need beginning at the point
where the W-beam remains at full height in relation to the roadway shoulder—usually
beginning at the point where the barrier crosses the ditch line. If the backslope is flatter than
1H:1V, provide a minimum 20-foot-wide by 75-foot-long clear area that is free of fixed
features behind the barrier and between the beginning length of need point at the terminal
end to the mitigated object to be protected.
Flare the guardrail to the foreslope/backslope intersection using a flare rate that meets the
criteria in 1610.03(4). Provide a 4H:1V or flatter foreslope into the face of the guardrail and
maintain the full guardrail height to the foreslope/backslope intersection in relation to a
10H:1V line extending from edge of shoulder breakpoint. (See the Standard Plans for details.)
or above, use only a TL-3 (Test Level 3) product. For highways with a posted speed of 45 mph
or below, either a TL-2 or a TL-3 product is acceptable. See the Standard Plans.
The availability and acceptance of these systems is expected to change rapidly over time.
Refer to the Type 31 Beam Guardrail Terminals website for the latest information on
availability or acceptance of different systems (see
http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm).
Although non-flared terminals do not need to have an offset at the end, a flare is
recommended so that the end piece does not protrude into the shoulder. See the Standard
Plans.
Four feet of additional widening behind the terminal is needed at the end posts to properly
anchor the systems (See the Standard Plans). When widening includes an embankment,
properly placed and compacted fill material will be necessary for optimum terminal
performance (see the Standard Specifications for embankment widening for guardrail).
No snowload rail washers are allowed within the limits of these terminals.
WSDOT does not currently use a flared terminal system for the Type 31 guardrail system.
Note: Approved shop drawings for terminals can be found by accessing the following
website: http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm
Note: If questions arise concerning the current approval status of a device, contact the HQ
Design Office for clarification when replacement is being considered.
1610.04(5)(d) Anchors
A guardrail anchor is needed at the end of a run of guardrail to develop tensile strength
throughout its length.
Use the Type 10 anchor to develop the tensile strength of the guardrail on the end
of Type 31 guardrail runs where a crash-tested terminal is not needed.
A Type 2 anchor is used with the buried terminal.
For information on anchor types used in runs of (Old) Beam Guardrail Type 1, see:
http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm.
into the more rigid barrier. This is commonly referred to as “pocketing.” A transition stiffens
the more flexible barrier by decreasing the post spacing, increasing the post size, and using
stiffer beam elements to reduce the possibility of pocketing.
When connecting beam guardrail to a more rigid barrier or a structure use the transitions
and connections that are shown in Exhibits 1610-10 and 1610-11 and detailed in the
Standard Plans. Verify the length of need (see 1610.03(5)) when designing transitions,
particularly transitions between beam guardrail or end terminals to bridge structures.
Type 21 transitions can be used on highways with all posted speeds to connect w-beam
guardrail to single slope, safety shape or vertical concrete barriers.
Type 22 and Type 23 transitions are used to connect w-beam guardrail to thrie beam on
bridges.
Type 24 transitions can be used on highways with a posted speed of 45 mph or less to
connect w-beam guardrail to single slope, safety shape or vertical concrete barriers.
When connecting a Type 21 or Type 24 Transition to an existing vertical faced bridge rail with
a low parapet, a special connection plate may be required. Coordinate with the WSDOT
Bridge and Structures Office (BSO). The transition pay item includes the connection.
Install transitions on 10:1 or flatter slopes with the 10:1 or flatter slope extending a minimum
of 2 feet behind the guardrail transition post similar to what is shown in DM Exhibit 1610-9
Placement Case 2.
For information regarding transitions used with (Old) Type 1 guardrail see:
http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm.
Condition Connection
Unrestrained precast concrete barrier A
Rigid, rigid anchored, untapered safety shape bridge rails or barriers [1] B
Bridge rails with curbs 9 inches or less in width B
Bridge rails with curbs between 9 and 18 inches wide C
Vertical walls, single slope bridge rail or concrete barrier, or tapered safety
D
shape barrier [1]
All bridge rail and concrete barrier types located on trailing ends of one-way
F
roadways
Note:
[1] New single slope and safety shape bridge rails are designed with the toe of the barrier
tapered so that it does not project past the face of the approach guardrail.
Transition
Connecting Type 31 W-Beam Guardrail to: Connection
Type*
New Installation 21, 24 [3] D
Concrete Parapet > (Greater Than) 20 in. 21, 24 [3] Exh. 1610-10 [2]
Existing Concrete
Concrete Parapet < (Less Than) 20 in. 21, 24 [3] Exh. 1610-10 [2]
Bridge Rail [1] Thrie Beam at Face Approach End 23 n/a
of Curb Trailing End (two-way traffic only) 23 n/a
Transition
Connecting Thrie Beam Guardrail to: Connection
Type*
Bridge Rail or
Concrete See the thrie beam transition in the Plan Sheet Library Exhibit 1610-10
Barrier
Information regarding placement cases for (Old) Type 1 beam guardrail can be found at
http://www.wsdot.wa.gov/Design/Policy/RoadsideSafety.htm.
which does not meet the minimum deflection distance of the Type 31 guardrail
system. Contact HQ Design to discuss barrier placement options when this occurs.
There are a number of manufacturers of high-tension cable barrier systems. These systems
have been designed using either three or four-cables fixed to metal posts placed at a fixed
spacing. Each cable system has specially designed anchors placed at both ends of the barrier
run to provide the proper tensioning in the cables. Currently, both three and four-cable high-
tension cable barrier systems are installed along WSDOT state routes. See additional
information about these approved cable barrier systems here:
http://www.wsdot.wa.gov/publications/fulltext/design/Policy/CableBarriers.pdf.
Use four-cable high-tension cable barrier systems for all new installations.
Note: Additional placement cases are shown in the WSDOT Standard Plans. For non-typical
installations, such as double runs of cable barrier or median ditch cross sections that differ
significantly from those shown, contact the HQ Design Office for guidance.
Notes:
2 Avoid installing cable barrier in the area between 1-foot to 8-foot offset from the
ditch centerline (left or right).
Provide an obstruction free zone within the cable barrier’s lateral deflection
3
distance, and provide sufficient lateral barrier deflection distance to prevent a
vehicle’s encroachment into the opposite lane of travel. See 1610.05(2) for more
information.
Notes:
1 Provide an obstruction free zone within the cable barrier’s lateral deflection
distance, see Section 1610.05(2)
In the direction of travel (located in the median or along roadside), locate the cable barrier
system so that there are no fixed objects within the limits of the cable barrier lateral
deflection distance.
For opposing traffic (where present), locate the cable barrier to provide lateral deflection
distance to prevent a vehicle’s encroachment into the opposite lane of travel.
Low–tension cable barrier systems require 12 feet of lateral deflection. Use high-tension
cable barrier systems in new cable barrier installations. High-tension barrier systems have
lateral deflection distances between 6 to 10 feet. Specify the maximum allowable lateral
deflection distance in the contract documents in order for the contractor to select a cable
barrier manufacturer that meets the lateral deflection requirements.
Note: There are new high-tension cable barrier systems under development that may change
selection and placement criteria. For example, newer systems may allow placement on
steeper slopes or have reduced deflection distances. Contact the HQ Design Office for
guidance.
Often, high-tension cable barrier systems will overlap/interface with a stiffer barrier system
(typically beam guardrail but can be concrete barrier). When terminating a cable barrier run
to begin a beam guardrail run, there are essentially four choices for the overlap/interface of
the two barrier systems (contact HQ Design when terminating a cable barrier run to begin a
concrete barrier run). The four choices are:
Connect Cable Barrier to Beam Guardrail: This placement connects the cable barrier directly
onto the beam guardrail runs (such as cable barrier connected to beam guardrail transitions
coming off bridge rails) or to a different cable barrier anchorage system.
When connecting cable barrier onto beam guardrail, the guardrail must continue at least 75
feet downstream from the point where the cable barrier attaches to the beam guardrail, or
the beam guardrail needs to be connected to a stiffer system (i.e. bridge rail, concrete
barrier) to reduce the chance of beam guardrail posts pulling out of the ground from the
tension in the cable barrier system. When terminating cable barrier in this manner; review
field conditions, check local maintenance personnel needs, and specify the required
connection option in the contract documents.
When cable barrier is connected directly to a more rigid barrier, a transition section is
typically needed. Contact the HQ Design Office for further details.
Install Cable Barrier Behind Beam Guardrail: This placement terminates the cable barrier
behind the beam guardrail system. Ensure the lateral distance between the two barrier
systems exceeds the deflection distance of the beam guardrail system placed in front of the
cable barrier system. This will reduce the chances of having the two barrier systems
interfering with each other during a vehicle impact, or having an errant vehicle rebound off
the cable barrier into the back of the beam guardrail during a vehicle impact. Exhibit 1610-
13b shows an example of terminating cable barrier behind a beam guardrail system.
Install Cable Barrier in Front of Beam Guardrail: This placement terminates the cable barrier
in front of the beam guardrail system. Ensure that the standard run of cable barrier extends
to, or past, the Length of Need post of the beam guardrail terminal, and provide a minimum
lateral distance of 4-feet between the two barrier systems. This will reduce the chances of
having the two barrier systems interfere with each other during a vehicle impact. Exhibit
1610-13b shows an example of terminating cable barrier in front of a beam guardrail system.
Terminate Cable Barrier in Advance of Beam Guardrail: This placement terminates the cable
barrier in advance of the beam guardrail system. This placement leaves a gap in guardrail
coverage and can be a maintenance concern if both terminals are hit by an errant vehicle.
However, this placement can be used when side slope grades become an issue (i.e. slope is
too steep to place cable barrier or beam guardrail, slope widening requires large amounts of
fill to accommodate barrier systems). Exhibit 1610-13b shows an example of terminating
cable barrier in advance of a beam guardrail system.
𝐿𝐻1−𝐿2
𝐵𝑂 = 𝐿𝐻1 (Direction A shown)
𝐿𝑅
Notes:
[1] Calculate barrier overlap (BO) from both directions of travel. Use the greatest value
of BO obtained.
[2] For supporting length of need equation factors, see Exhibit 1610-6.
Exhibit 1610-13b Cable Barrier Placement: Cable Barrier Termination/Overlap with Beam
Guardrail
LH1 − L2
BO =
LH1/LR
Exhibit 1610-13b Cable Barrier Placement: Cable Barrier Termination/Overlap with Beam
Guardrail (cont)
[1] The beam guardrail may need to be extended and flared in advance of a cable barrier
terminal to maintain adequate barrier overlap, lateral offset distance between
barrier systems, and shoulder width.
[2] Typical applications may be at either bridge transitions or where high-tension cable
and beam guardrail systems end or begin.
[3] For supporting length of need equation factors, see Exhibit 1610-6.
The single-slope barrier face is the recommended option for embedded rigid concrete barrier
applications.
Bridge Transitions: When the single-slope or F-Shape face is used on structures and precast
barrier is selected for use on the approaches; a transition section is needed to provide
gradual stiffening from the less rigid precast barrier system to the more rigid bridge rail
system and to ensure that no vertical edges of the barrier are exposed to oncoming traffic
due to the difference in shapes and height of the barriers. Note: Precast concrete barrier
transitions to bridges are currently under development. Contact HQ Design for more
information. For details on bridge rail designs, see the Bridge Design Manual.
Stiffness Transitions: A transition section is also needed when changing the stiffness of the
barrier system within a single run but not the barrier shape (i.e. Type F anchored to Type F
unanchored). This type of transition requires a change in anchoring pin configuration when
moving from an unanchored barrier system to an anchored barrier system. There is no other
change to the barrier other than the anchoring pin configuration. Note: Precast concrete
barrier transition plans for barrier system stiffness changes are currently under development.
Contact HQ Design for more information.
For aesthetic reasons, avoid changes in the shape of the barrier face within a project or
corridor.
The New Jersey shape and F-shape barriers are commonly referred to as “safety shapes.” The
New Jersey shape and F-shape have an initial overall height of 32 inches. This height includes
provision for up to a 3-inch future pavement overlay that can reduce the barrier height to 29
inches minimum.
Concrete Barrier Type F (see the Standard Plans) is a freestanding precast barrier that has the
F-shape on both sides. The F-Shape barrier can be used in permanent or temporary
installations. It can be used for both median and shoulder installations. Unanchored units are
connected with steel pins through metal loops. For permanent installations, this barrier is
placed on a paved surface and a paved surface is provided beyond the barrier for deflection.
For temporary installations, this barrier can be placed on a paved or a compacted unpaved
surface with the respective surface provided beyond the barrier for deflection. Do not anchor
Type F barrier on a compacted unpaved surface. See Exhibit 1610-3 for deflection
requirements.
Concrete Barrier Type 2 (see the Standard Plans) is a freestanding precast barrier that has
the New Jersey shape on two sides. The Type 2 barrier is only used in temporary installations.
It can be used for both median and shoulder installations. Unanchored units are connected
with steel pins through wire rope loops. For temporary installations, this barrier can be
placed on a paved surface or a compacted unpaved surface with the respective surface
provided beyond the barrier for deflection. Do not anchor Type 2 barrier on a compacted
unpaved surface. See Exhibit 1610-3 for deflection requirements.
The cost of precast safety shape barrier is significantly less than the cost of the cast-in-place
barriers. Therefore, consider the length of the barrier run and the deflection needs to
determine whether transitioning to precast barrier is desirable. If precast safety shape
barrier is used for the majority of a project, use the single slope barrier for small sections that
need cast-in-place barrier (such as for a light standard section). Precast concrete barrier
transitions are currently under development. Contact HQ Design for more information.
Type F narrow base is a precast, single-faced F-Shape barrier. These units are not
freestanding and are to be placed against a rigid structure (or anchored to the pavement in
temporary installations). If Type F narrow base barriers are used back to back, fill any gap
between them to prevent tipping.
Type F barrier can be anchored where a more rigid barrier is needed. The barrier can be
anchored in permanent or temporary installations on asphalt pavement, concrete pavement,
or bridge decks (Anchoring methods are shown in the Standard Plans). Consult with the
WSDOT BSO for details when anchoring permanent precast concrete barrier to a rigid
(Portland cement concrete) pavement or bridge deck.
Precast Type 2 barrier can be anchored where a more rigid barrier is needed. The barrier can
be anchored in temporary installations using Type 1 and Type 2 anchors for rigid concrete
pavement, and Type 3 anchors for asphalt pavement (Anchoring methods are shown in the
Standard Plans). Consult with the WSDOT BSO for details when anchoring precast concrete
barrier to a bridge deck.
Precast barrier used on the approach to bridge rail is to be connected to the bridge rail by
installing loops or a loop bar embedded into the bridge rail with epoxy resin and as detailed
in the Standard Plans.
Single-slope barrier is available in various heights as shown in the Standard Plans. Single-
slope concrete barrier can be cast-in-place or precast. Single-slope barrier is considered a
rigid system regardless of the construction method used provided that precast barrier is
embedded a minimum of 3-inches in the roadway wearing surface (asphalt or concrete) on
both sides, precast barrier is embedded a minimum of 10-inches in compacted soil (i.e. CSBC,
select borrow, gravel borrow, native soil) on both sides, and cast-in-place barrier is
embedded a minimum of 3-inches in the roadway wearing surface (asphalt or concrete) or
compacted soil on both sides.
For new installations in asphalt, concrete, or compacted soil; the minimum height of the
single-slope barrier above the roadway is 2 feet 10 inches which allows a 2-inch tolerance for
future overlays. The minimum total height of the barrier section is 3-feet-6 inches (including
embedment). The single-slope barrier can be installed with grade separation between
roadways as follows:
For cast-in-place barrier with a minimum 3-inch embedment, or pre-cast barrier
installed in asphalt or concrete with a minimum 3-inch embedment; a grade
separation of up to 4-inches is allowed when using a 3-foot-6-inch tall barrier
section, a grade separation of up to 7-inches is allowed when using a 4-foot tall
barrier section, and a grade separation of up to 10-inches is allowed when using a 4-
foot-6-inch tall barrier section as shown in the Standard Plans.
For pre-cast barrier installed in compacted soil with a minimum 10-inch
embedment; a grade separation of up to 4-inches is allowed when using a 4-foot tall
barrier section, and a grade separation of up to 10-inches is allowed when using a 4-
foot-6 inch tall barrier section.
The barrier is to have a depth of embedment equal to or greater than the grade
separation. Contact the WSDOT BSO for grade separations greater than 10-inches.
Cast-in-place and pre-cast High Performance single-slope barrier can be installed
with a grade separation between the roadways as well, see the Standard Plans.
Use HP Barrier in freeway medians of 22 feet or less. Also, use HP Barrier on Interstate or
freeway routes where crash history suggests a need or where roadway geometrics increase
the possibility of larger trucks hitting the barrier at a high angle (for example, on-ramps for
freeway-to-freeway connections with sharp curvature in the alignment).
Consider the use of HP Barrier at other locations such as highways with narrow medians,
near highly sensitive environmental areas, near densely populated areas, over or near mass
transit facilities, or on vertically divided highways.
To bury the blunt end of the barrier into a backslope, the following conditions must be met:
The backslope is 3H:1V or steeper
The backslope extends minimum of 4 feet in height above the edge of shoulder
Flare the concrete barrier into the backslope using a flare rate that meets the
criteria in Section 1610.03(4)
Provide a 10H:1V or flatter foreslope into the face of the barrier and maintain the
full barrier height until the barrier intersects with the backslope. This might create
the need to fill ditches and install culverts in front of the barrier face.
The 10- to 12-foot single-slope barrier terminal (precast or cast-in-place) may be used in the
following conditions:
Outside the Design Clear Zone.
On the trailing end of the barrier when it is outside the Design Clear Zone for
opposing traffic.
On the trailing end of one-way traffic.
Where the posted speed is 25 mph or below.
See the Standard Plans for barrier terminal details. Note: The Type F concrete barrier
terminal standard plans are currently under development. Contact HQ Design for
information.
When considering work on a bridge traffic barrier consult the WSDOT Bridge and Structures
Office (BSO).
The standard bridge traffic barrier is a 3 foot 6 inch single slope or F Shape traffic barrier.
For corridor continuity, a 2 foot 10 inch single slope or 2 foot 8 inch F Shape traffic barrier
may be used with a pedestrian railing attached to the top for a total height of 3 foot 6 inch
height inches. This also meets requirements for worker fall protection.
Approach barriers, transitions, and connections are usually needed on all four corners of
bridges carrying two-way traffic and on both corners of the approach end for one-way traffic.
(See 1610.04(6) for guidance on beam guardrail transitions). A concrete barrier transition is
being made available to connect the Type F concrete barrier (F-shape) and the bridge barrier
(F-Shape or Single Slope) (Note: Transitions are currently under development. Contact HQ
Design for further details).
Bridge railing attaches to the top of the bridge barrier. When bridge barrier is included in a
project, the bridge rails, including crossroad bridge rail, are to be addressed. Consult the
WSDOT BSO regarding bridge rail selection and for design of the connection to an existing
bridge. Consider the following:
Use an approved, NCHRP 350 or MASH crash-tested bridge traffic barrier on new
bridges or bridges to be widened. The Bridge Design Manual provides examples of
typical bridge rails. The BSO’s minimum crash test level for all state and interstate
bridges is a TL-4.
An existing bridge rail on a roadway with a posted speed of 30 mph or below may
remain in place if it is not located on a bridge over a National Highway System (NHS)
highway. When Type 7 bridge rail is present on a bridge over an NHS highway with a
posted speed of 30 mph or below, it may remain in place regardless of the type of
metal rail installed. Other bridge rails are to be evaluated for strength and
geometrics. (See 1610.07(1) for guidance on retrofit techniques.)
The Type 7 bridge rail is common. Type 7 bridge rails have a curb, a vertical-face
parapet, and an aluminum top rail. The curb width and the type of aluminum top
rail are factors in determining the adequacy of the Type 7 bridge rail, as shown in
Exhibit 1610-15. Consult the WSDOT BSO for assistance in evaluating other bridge
rails.
When considering an overlay on a bridge, consult the WSDOT BSO to verify the
overlay depth can be placed on the bridge deck based on the type of traffic barrier.
There may be instances where the height of the bridge barrier will not allow for the
planned overlay depth without removal of existing pavement.
Curb Width
Aluminum Rail
Type
9 Inches or Less Greater Than 9 Inches*
system and provide design details for the retrofit. Retrofitting with a new concrete bridge
barrier is costly and requires authorization from Program Management when no widening is
proposed.
1610.07(1)(b) Thrie Beam Retrofit
Retrofitting the bridge barrier with thrie beam is an economical way to improve the strength
and redirectional performance of a bridge barrier. The thrie beam can be mounted to steel
posts or the existing bridge barrier, depending on the structural adequacy of the bridge deck,
the existing bridge barrier type, the width of curb (if any), and the curb-to-curb roadway
width carried across the structure. Exhibit 1610-16 shows typical retrofit criteria.
Note that Bridges designated as historical landmarks may not be candidates for thrie beam
retrofitting. Contact the Environmental Services Office regarding bridge historical landmark
status.
Consider the Service Level 1 (SL-1) system on bridges with wooden decks and for bridges with
concrete decks that do not have the needed strength to accommodate the thrie beam
system. Contact the WSDOT BSO for information needed for the design of the SL-1 system.
If a thrie beam retrofit results in reduction in sidewalk width ensure ADA compliance is
addressed, see Chapter 1510.
Notes:
[1] To maximize available curb/sidewalk width for pedestrian use, thrie beam may
be mounted to the bridge rail at a height of 35 inches.
[2] Contact the WSDOT BSO for design details on bridge rail retrofit projects.
One alternative to the use of aesthetic treatments are barriers designed to be aesthetic, such
as steel-backed timber guardrail and stone guard walls. These alternative barriers will likely
necessitate a partnering effort because of their higher costs, although grants may be
available for this purpose if the need is identified early in the project definition phase.
A proprietary (patented) system, called the Ironwood Guardrail, is also available. This system
uses a beam with a round cross section and is supported by steel posts with a wood covering
to give the appearance of an all-wood system from the roadway. The incorporation of the
Ironwood Guardrail will need to be documented. Consult with the Assistant State Design
Engineer to determine what justification (proprietary or a public interest finding) will be
required.
The most desirable method of terminating the steel-backed timber guardrail is to bury the
end in a backslope, as described in 1610.04(5). When this type of terminal is not possible, use
of the barrier is limited to highways with a posted speed of 45 mph or below. On these
lower-speed highways, the barriers can be flared away from the traveled way as described in
1610.03(4) and terminated in a berm outside the Design Clear Zone.
1610.08(5) Dragnet
The Dragnet Vehicle Arresting Barrier consists of chain link or fiber net that is attached to
energy absorbing units. When a vehicle hits the system, the Dragnet brings the vehicle to a
controlled stop with limited damage. Possible uses for this device include the following:
Reversible lane entrances and exits
Railroad crossings
Truck escape ramps (instead of arrester beds—see Chapter 1270)
T-intersections
Work zones
Swing span bridges
1610.09 References
Standard Plans for Road, Bridge, and Municipal Construction (Standard Plans), M 21-01,
WSDOT
Determining Length of Need. This e-learning course for WSDOT employees covers the
“Length of Need,” which is a calculation of how much longitudinal barrier is necessary to
shield objects on the roadside. Request this training via the web-based Learning
Management System.
1620.01 General
Impact attenuator systems are protective systems that help aid an errant vehicle from impacting
an object by either gradually decelerating the vehicle to a stop when hit head-on or by
redirecting it away from the feature when struck on the side. These systems are used for rigid
objects or other features that cannot be removed, relocated, or made breakaway.
Approved systems shall meet standardized testing defined in the American Association of State
Highway and Transportation Officials (AASHTO) Manual for Assessing Safety Hardware (MASH)
as updated in 2016. In addition, these devices shall have an acceptance letter from FHWA that
certifies that the device meets the appropriate crash test criteria and is eligible for federal-aid
reimbursement.
Impact attenuators are placed so that they do not present a feature that requires mitigating in
relation to opposing traffic. For median and reversible lane locations, the backup structure or
attenuator-to-object connection is designed to help in aiding opposing traffic from being
snagged.
Avoid placement of curbs between attenuators and traffic. Refer to the specific attenuator
manufacturer’s instructions if considering placement of curbing between an attenuator and the
travelled way. It is desirable that existing curbing be removed and the surface smoothed with
asphalt or cement concrete pavement before an impact attenuator is installed. However,
mountable curbs 4 inches or less in height may be retained depending on the feasibility of
removal and as long as the manufacturer’s installation requirements are met.
Consult with the Area Maintenance Superintendent who will be maintaining the system prior to
selecting the attenuator systems to include in a construction contract.
For approved systems to choose from, see the WSDOT Impact Attenuator Design page at
http://www.wsdot.wa.gov/publications/fulltext/design/ProductFolder/PENDING_Impact_Att
enuator_Design.docx.
Consider that each application is unique when selecting impact attenuators for use in particular
applications. This applies to both permanent and temporary installations.
To select an appropriate impact attenuator system, the following factors must be assessed:
• Posted speed
• Operating speed
• Average daily traffic (ADT)
• Repair crew exposure
• Proximity to the roadway
• Anticipated number of yearly impacts
• Available space (length and width)
• Lifecycle Maintenance costs
• Initial cost
• Duration (permanent or temporary use)
• Portion of the impact attenuator that is redirective/gating (see Exhibit 1620-1)
• Width of object to be shielded
Entries on the WSDOT Impact Attenuator Design page indicate whether the system is National
Cooperative Highway Research Program (NCHRP) Report 350 or MASH-compliant. If it’s
determined that a MASH-compliant system is not available for the specific configuration
required, document the selection of an NCHRP 350 system in the DDP.
When selecting the appropriate impact attenuator system, consider the portion that is designed
to redirect vehicles during a side impact of the unit, such that fixed objects, either permanent or
temporary (such as construction equipment), are not located behind the gating portion of these
devices (see Exhibit 1620-1).
Notes:
[1] Impact attenuator type and manufacturer varies with application. See the Attenuator Selection
Template at:
http://www.wsdot.wa.gov/publications/fulltext/design/ProductFolder/Impact_attenuator_selectio
n_template.xlsx)
[2] Distance beyond the length of need. This portion is gating.
[3] This portion is redirective (nongating) and can be included as part of the barrier needed to satisfy
length of need.
[4] Concrete barrier shown for illustration purposes only. Type of fixed object varies.
Select the system and configuration appropriate for the posted speed. In the interest of a cost-
effective design, selecting a system applicable for the posted speed is recommended (although
using a system tested for a higher speed is acceptable). Note that attenuators used on highways
with posted speeds of 70 mph have additional considerations discussed below. Where there is
evidence that the average operating speed of the facility is higher than the posted speed,
consider selecting an attenuator system rated at the facility’s operating speed.
Manufacturer’s product information may indicate that a different system is required for speeds
of 70 mph or greater. These models are generally referred to as “high speed” or “70 mph”
systems. Use of these systems on facilities with 70 mph posted speeds is not required, and
selection of a system rated for at least 60 mph will typically be appropriate for most sites on
these facilities. For permanent installations where unusual conditions warrant consideration of a
high-speed device, these systems are available and may be used with justification. Contact the
HQ Design Office for guidance when considering one of these systems.
For information regarding spatial requirements and initial cost information related to impact
attenuator systems, see the Attenuator Selection Template at:
http://www.wsdot.wa.gov/publications/fulltext/design/ProductFolder/Impact_attenuator_sel
ection_template.xlsx.
When considering maintenance costs, anticipate the average annual impact rate. If few impacts
are anticipated, lower-cost devices might meet the need. (See Chapter 301 for examples of how
to determine lifecycle costs for proposed hardware). Attenuators with the lowest initial cost and
initial site preparation will have high maintenance costs after each impact. Labor and equipment
are needed to clean up the debris and install a new attenuator, as the lowest cost attenuators
are typically destroyed after a single impact. Attenuators with higher initial installation cost
typically have lower maintenance costs.
In selecting a system, one consideration is the anticipated exposure to traffic that the workers
making the repairs may encounter. In areas with high traffic exposure, a low-maintenance
system that can be repaired quickly is most desirable. Some systems need nearly total
replacement or replacement of critical components (such as cartridges or braking mechanisms)
after a head-on impact, while others simply need to be reset.
When a transition to connect with a concrete barrier, fixed object, or beam guardrail is needed,
the transition type and connection may need to be specified (see the impact attenuator
descriptions accessible through the Attenuator Selection Template at:
http://www.wsdot.wa.gov/publications/fulltext/design/ProductFolder/Impact_attenuator_sel
ection_template.xlsx).
In most cases, the transition type and connection required will be a custom design per the
manufacturer (these transitions are included in the cost of the impact attenuator). In a few
cases, the transition type and connection to use will be as described in Chapter 1610 and the
Standard Plans (these transition sections are not included in the cost of the impact attenuator
and must be included as a separate bid item in the construction contract).
Consult with the Area Maintenance Superintendent who will be maintaining the systems before
finalizing the list of attenuators to be included in the contract.
Installation of a low-maintenance device is desirable at locations that meet at least one of the
following criteria:
• Sites with an ADT of 25,000 or greater
• Sites with a history/anticipation of more than one impact per year
• Sites with unusually challenging conditions, such as limitations on repair time, a
likelihood of frequent night repairs, or narrow gore locations
Document the decision in the DDP to use any device other than a low-maintenance device at
locations meeting at least one of the criteria above.
The HQ Design Office conducts a periodic review of maintenance records to consider which
devices should be included in the Low-Maintenance category. For a description of requirements
that need to be met in order to be included in the Low-Maintenance category, see:
www.wsdot.wa.gov/publications/fulltext/design/roadsidesafety/low_maint.pdf
1710.01 General
The Washington State Department of Transportation (WSDOT) has developed a
statewide system of traveler stopping opportunities along Interstate highways and
state routes. This system includes safety rest areas (see Exhibit 1710-1), roadside
parks, and viewpoints. These services provide universal access for rest, traveler
information, and restroom facilities. Benefits include improved safety by reducing
driver fatigue and the number of vehicles parked on the shoulders of state routes,
refuge from adverse driving conditions, and increased tourism promotion.
Safety rest areas (SRAs) are spaced approximately every 60 miles on the National
Highway System and on Scenic and Recreational Highways. Use the Safety Rest Area
Program Strategic Plan as a guide when selecting a site location. The link to the SRA
Strategic Plan can be found in the SRA Section of the Capital Facilities Office internal
web page at: http://wwwi.wsdot.wa.gov/operations/facilities/
Safety rest areas are planned and designed by a multidisciplinary team lead through
the Facilities Administrator in the Capital Facilities Office, a branch of Maintenance
Operations. (See 1710.04 for an expanded discussion on team roles and membership.)
1710.02 References
(1) Federal/State Laws and Codes
23 Code of Federal Regulations (CFR) 1.23, Rights-of-way
23 CFR 635, Construction and Maintenance
23 CFR 752, Landscape and roadside development
23 CFR 771, Environmental impact and related procedures
42 United States Code (USC) Chapter 126, Section 12101 et seq., Americans with
Disabilities Act of 1990
20 USC Chapter 6A, Section 107, The Randolph-Sheppard Act
Revised Code of Washington (RCW) 46.17.375, Recreational vehicle sanitary disposal fee
RCW 46.68.170, RV account – Use for sanitary disposal systems
RCW 47.01.460, Adjustments to recreational vehicle fees
RCW 47.06.040, Statewide multimodal transportation plan
RCW 47.28.030, Contracts – State forces
RCW 47.38, Roadside areas – Safety rest areas
RCW 47.39, Scenic and Recreational Highway Act of 1967
RCW 47.42, Scenic Vistas Act
Washington Administrative Code (WAC) 246-290, Group A public water supplies
WAC 468-66, Highway Advertising Control Act
(4) Agreements
Interpretive Signs and Markers Agreement – Washington State Parks Commission
(GM 869) 1989 Highways and Local Programs Division
Traveler and Commercial Information Services – Private Vendor (StoreyCo, Inc.)
(AA-1-12097) 2007 Capital Facilities Office
Vending Machines – Department of Services for the Blind (DSB)
(GCA 10377) Capital Facilities Office
1710.03 Definitions
ancillary services Those secondary services, also considered amenities, provided
at safety rest areas that include, but are not limited to, vending machines, picnic areas,
interpretive signing, telephones, recreational vehicle (RV) sanitary disposal facilities,
trails, scenic viewpoints, commercial and public information displays, and visitor
information centers.
Recreational Vehicle Account In 1980 the RV account was established for use by
the department of transportation for the construction, maintenance, and operation of
recreational vehicle sanitary disposal systems at safety rest areas (RCW 46.68.170).
A recreational vehicle sanitary disposal fee is required for registration of a recreational
vehicle (RCW 46.17.375). Adjustments to the recreational vehicle fee by the department
of transportation may be implemented after consultation with the citizens’ representatives
of the recreational vehicle user community (RCW 47.01.460).
roadside park A roadside user facility for safe vehicular parking off the traveled way
and separated from the highway by some form of buffer. These sites might be equipped
with features or elements such as points of interest, picnic tables, and/or vault toilet
buildings. Unlike a safety rest area, a roadside park does not always provide a permanent
restroom building.
safety rest area (SRA) A roadside facility equipped with permanent restroom
building(s), a parking area, picnic tables, refuse receptacles, illumination, and other
ancillary services. SRAs typically include potable water and might include traveler
information and telephones.
Exhibits 1710-2 and 1710-3 outline the many disciplines involved with SRA planning,
design, construction, and maintenance. The exhibits outline roles during the different
phases of SRA management. Services are provided by internal WSDOT staff, other
government agencies, and private consultants.
Note:
[1] The SRA section in the WSDOT Maintenance Manual provides additional information pertaining to daily
operations at the rest areas. Operations policy is outlined for all the ancillary services provided at each
rest area site, such as the free coffee program, vending machines, literature distribution and posting,
site security, seasonal or temporary closures, and other site activities.
Note:
[1] Recreational Vehicle Citizens Advisory Committee: The department utilizes a volunteer citizen-based
group of recreational vehicle users to help define the RV needs at SRAs. This group provides guidance
on the expenditure of funds from the RV account and fee adjustments. The fee adjustments must be
preceded by an evaluation per RCW 47.01.460.
(14) Walkways
Design walkways for direct pedestrian movement to all facilities and comply with
ADAAG requirements. Provide sidewalk width a minimum of 48 inches, which
exceeds ADAAG requirements.
(15) Vegetation
Vegetation enhances the physical environment by providing shade, shelter from wind,
visual screening, wildlife habitat, and other benefits. Landscape Architects engaged in
the project employ designs that emphasize low-maintenance practices and obstacle-free
lawns, and minimize water usage for irrigation and impacts to existing native vegetation
where practicable.
Variables (ft)
Ø A B C D E
Restroom 30˚ 85 30 50 30 100
35˚ 90 35 55 35 105
(typical location)
40˚ 95 35 60 35 110
Pavement marking 45˚ 100 45 65 45 115
100'
for parking stalls
A
20' min*
20' min
'
15
'
15
20' min
C E
A
Ø
'
20
D
A
* If exit ramp is tangent or has curve radii greater than 1,000', this width may be reduced to 14'.
0.02'/ft 0.02'/ft
Section A-A
0.02'/ft
Section A-A
Alternate
1710.06 Buildings
(1) Codes
Comply with current versions of the International Building Code, International Plumbing
Code, National Electric Code, Americans with Disabilities Act Accessibility Guidelines,
and all applicable state and local code requirements.
(9) Kiosks
Install travel information kiosks at all Interstate rest areas and at non-Interstate rest areas
as needed. A kiosk is usually equipped with backlit information displays.
1710.07 Utilities
Contact the region Utilities Office for acquisition of Utility Service Agreements for
any utility needs. Coordinate with the Capital Facilities Office for long-term planning
considerations. Telephones are provided at most SRAs and must meet ADAAG
requirements. Because of the availability of cellular phones, and due to vandalism
and other reasons, public telephone service may be cancelled after coordination
between the Capital Facilities Office and region Maintenance.
1710.08 Documentation
(1) Design Documentation Checklist
For the list of documents required to be preserved in the Design Documentation Package
and the Project File, see the Design Documentation Checklist:
www.wsdot.wa.gov/design/projectdev/
Also, coordinate design documentation with the Capital Facilities Office for any SRA
design projects.
1720.01 General
Truck weighing facilities are needed to protect state highways from overweight vehicles, to
provide for vehicle safety inspection, and to provide a source of data for planning and research.
The development, construction, and maintenance of these facilities is a cooperative effort
between the WSDOT and the Washington State Patrol (WSP).
1720.02 Definitions
Note: For definitions of roadway, traveled way, lane, median, outer separation, shoulder,
decision sight distance, sight distance, and stopping sight distance, see the Glossary.
Commercial Vehicle Information Systems and Networks (CVISN) A network that links
intelligent transportation systems (ITS) to share information on commercial vehicles. When in
operation at a weigh site, it can enable commercial vehicles to clear the facility without
stopping.
Frontage road: An auxiliary road that is a local road or street located beside a highway for
service to abutting property and adjacent areas and for control of access.
Usable shoulder: The width of the shoulder that can be used by a vehicle for stopping.
Weigh in motion (WIM): A scale facility capable of weighing a vehicle without the vehicle
stopping.
The WSP provides the Program Management Office of Strategic Planning and Programming a
Project Definition, which includes:
A statement of need, the purpose of the project, and the type of work.
The general location of the project.
Program Management sends this information to the region for preparation of a Project
Summary. The region works with the WSP to identify the specific location of the facility. The
region then prepares a design decision estimate and submits it to Program Management.
The region negotiates and the Regional Administrator executes any formal agreements with the
WSP required for the design, construction, or maintenance of vehicle weighing and inspection
facilities.
The exact location of a truck weighing facility is generally controlled by topography, highway
alignment, and geometrics. It is also desirable to select a site where adequate right of way is
already available. Select the most economical site to minimize site preparation, expense, and
impact on the environment. Water, electricity availability, and sewage treatment and disposal
are other considerations for site selection. Additionally, use the following criteria:
Locate the facility such that its operation will not hinder the operation of the
highway or other related features such as intersections and interchanges.
To the extent feasible, eliminate options for truck traffic to bypass the weigh site.
Base the site selection on the type and volume of trucks using the route.
An Access Revision Report (ARR) is required for weigh sites on multilane divided highways with
access control (see Chapter 550).
On multilane highways, provide off- and on-connections as shown in Chapter 1360. Exhibit
1720-1 is the minimal design of a weigh site on multilane highways.
Design weigh facilities on two-lane highways to best fit the existing conditions, with particular
consideration given to the matter of access to and from the site. Off- and on-connections, as
shown in Chapter 1360, are preferred. However, with justification, on-connections may be
designed as intersections (see Chapter 1310). Exhibit 1720-2 is a guide for the design of weigh
sites on two-lane highways.
To optimize scale efficiency, make the storage area flat; however, to facilitate
drainage, the slope may be up to 2%.
Provide illumination when requested by the WSP. Illumination is required if the
facility is to be operated during the hours of darkness and may be desirable at other
locations to deter unauthorized use of the facility. (See Chapter 1040 for additional
information on illumination.)
Design portable truck weighing facilities located on two-lane and multilane roadways to best fit
the existing conditions. Minor portable scale sites, as shown in Exhibit 1720-4, are used with
two-way traffic and on multilane highways with low traffic volumes. Major portable scale sites
(see Exhibit 1720-5) are for use on expressways, freeways, and where traffic volumes are high.
Locate the weighing facility such that its operation will not hinder the operation of the highway
or other related features such as intersections.
An ARR is required for weigh sites on multilane divided highways with access control (see
Chapter 550).
locations to deter unauthorized use of the facility. (See Chapter 1040 for additional
information on illumination.)
Design shoulder sites to best fit the existing conditions. Small shoulder sites (see Exhibit 1720-6)
are for use on lower-volume roadways (ADT 5000 or less) with two-way traffic. Large shoulder
sites (see Exhibit 1720-7) are to be used with higher-volume two-way roadways and multilane
highways. Locate the weighing facility so that its operation will not hinder the operation of the
highway or other related features such as intersections.
Shoulder sites are designed in coordination with the WSP. Input from the local WSP Commercial
Vehicle Enforcement personnel will ensure the proposed site will meet their needs without
over-building the facility. Obtain written concurrence from the WSP for the length, width, and
taper rates before the design is finalized.
When the ADT is 1,500 or less, and with the written approval of the WSP, the tapers at small
shoulder sites may be eliminated. The shoulders on either side of the site may be used as
acceleration and deceleration lanes, whether or not they were designed for this use. Therefore,
provide adequate strength to support truck traffic.
Hot mix asphalt is acceptable for use on all shoulder sites. Design the depth in accordance with
the surfacing report. Design the shoulder pavement at this depth for a length not less than the
deceleration lane length before, and the acceleration lane length after, the site (see Chapter
1360).
When the shoulders are designed to be used for deceleration and acceleration lanes, the
minimum width is 12 feet with full pavement depth for the deceleration/ acceleration lane
lengths (see Chapter 1360).
Use a maximum 2% slope in order to optimize portable scale efficiency and facilitate drainage.
1720.08 Procedures
Prepare site plans for all truck weighing facilities that include:
Class of highway and design speed for main line (see Chapter 1103).
Get WSP approval of the site plans before the final plan approval.
1720.09 Documentation
Refer to Chapter 300 for design documentation requirements.
September 2019
WSDOT Design Manual M 22-01.17
Edge of pavement
E
D
20 ft 15 ft
ft
Exhibit 1720-3 Vehicle Inspection Installation
50
ft
5 0 in C B A
A Truck storage and parking m 50
ft 100 ft typ
B Outside truck inspection and parking
70
C Truck inspection building ft 20 ft 50 ft min (typ)
D Scalehouse
E Scale
Edge of pavement
Weigh Sites
Page 1720-9
Weigh Sites Chapter 1720
Match
1
10 min
4 ft
line
15 ft
10 ft 15 ft
300 ft min
(Not to Scale)
1
Match
25 min
15 ft 8 ft
R = 6 ft
Edge of through lane 34 ft
2 ft 4 ft
Match
1
15 min
4 ft
line
15 ft
10 ft 15 ft
300 ft min
(Not to Scale)
R = 4 ft
10 ft Edge of through lane 2 ft
line
1
Match
50
15 ft 8 ft
20 ft
1 1
15 15
200 ft min
Length to be established by
agreement with the WSP, but not
less than 200 feet
Travel lane
20 ft
1 1
15 25
300 ft min
Exhibit 1720-8 MOU Related to Vehicle Weighing and Equipment: Inspection Facilities on State
Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Exhibit 1720-8 (continued) MOU Related to Vehicle Weighing and Equipment: Inspection Facilities
on State Highways
Acronyms
Glossary of Terms
Glossary of Terms
A B C D E F G H I J K L M N O P Q R S T U V W Y Z
access A means of entering or leaving a public road, street, or highway with respect to abutting
property or another public road, street, or highway.
access break Any point from inside or outside the state limited access right of way limited access
hachures that crosses over, under, or physically through the plane of the limited access, is an access
break or “break in access,” including, but not limited to, locked gates and temporary construction access
breaks.
access connection An access point, other than a public road/street, that permits access to or from a
managed access highway on the state highway system.
access connection permit A written authorization issued by the permitting authority for a specifically
designed access connection to a managed access highway at a specific location; for a specific type and
intensity of property use; and for a specific volume of traffic for the access connection based on the final
stage of the development of the applicant’s property. The actual form used for this authorization is
determined by the permitting authority.
access control The limiting and regulating of public and private access to Washington State’s highways,
as required by state law. A design control (see Chapter 1103) – there are two categories of controlling
access to state highways limited access and managed access.
Access Control Tracking System Limited Access and Managed Access Master Plan A database list,
related to highway route numbers and mileposts, that identifies either the level of limited access or the
class of managed access: www.wsdot.wa.gov/design/accessandhearings
access design analysis A design analysis (see Chapter 300) that authorizes deferring or staging
acquisition of limited access control, falling short of a 300-foot requirement, or allowing an existing
access point to stay within 130 feet of an intersection on a limited access highway. Approval by the
Director & State Design Engineer, Development Division, or designee, is required (see Chapter 530).
access hearing plan A limited access plan prepared for presentation at an access hearing.
access management The programmatic control of the location, spacing, design, and operation of
driveways, median openings, interchanges, and street connections to a roadway.
access point Any point that allows private or public entrance to or exit from the traveled way of a state
highway, including “locked gate” access and maintenance access points.
access point revision A new access point or a revision of an existing interchange/ intersection
configuration. Locked gates and temporary construction breaks are also access point revisions.
access point spacing On a managed access highway, the distance between two adjacent access points
on one side of the highway, measured along the edge of the traveled way from one access point to the
next (see also corner clearance).
access revision report (ARR) A technical report which documents specific analyses in order to approve
or reject a proposed revision to freeway access. See Chapter 550.
access report plan A limited access plan prepared for presentation to local governmental officials at
preliminary meetings before preparation of the access hearing plan.
access rights Property rights that allow an abutting property owner to enter and leave the public
roadway system.
accessible pedestrian signal (APS) A device that communicates information about the “WALK”
phase in audible and vibrotactile (vibrating surface that communicates information through touch,
located on the accessible pedestrian signal button) formats. (ADA term)
ADA An abbreviation for the Americans with Disabilities Act of 1990. The ADA is a civil rights
law that identifies and prohibits discrimination based on disability. Title II of the ADA requires public
entities to design new pedestrian facilities or alter existing pedestrian facilities to be accessible to and
usable by people with disabilities. (ADA term)
adaptive lighting system A lighting system with a control system connected, allowing for dimming,
on/off operation by time of night, and independent scheduling of individual lights for select hours of
operation during nighttime hours.
affidavit of publication A notarized written declaration stating that a notice of hearing (or notice of
opportunity for a hearing) was published in the legally prescribed manner.
affidavit of service by mailing A notarized written declaration stating that the limited access hearing
packet was mailed at least 15 days prior to the hearing and entered into the record at the hearing.
alteration A change to a facility in the public right of way that affects or could affect access,
circulation, or use. Alterations include, but are not limited to: renovation; rehabilitation; reconstruction;
historic restoration; resurfacing of circulation paths or vehicular ways; or changes or rearrangement of
structural parts or elements of a facility. Alterations do not include: Spot pavement repair; liquid-asphalt
sealing, chip seal (bituminous surface treatment), or crack sealing; or lane restriping that does not alter
the usability of the shoulder. (ADA term)
alternative(s) Possible solutions to accomplish a defined purpose and need. These include local and
state transportation system mode and design options, locations, and travel demand management and
transportation system management-type improvements such as ramp metering, mass transit, and high-
occupancy vehicle (HOV) facilities.
Alternatives Comparison Table (ACT) A table that documents and presents the tradeoffs among those
performance metrics identified for each alternative under consideration on a project. The ACT is used to
assist in analyzing the baseline and contextual performance tradeoffs and ultimately to select an
alternative. It is a supplemental document to the “Alternatives Analysis” section of the Basis of Design.
ancillary services Those secondary services, also considered amenities, provided at safety rest areas
that include, but are not limited to, vending machines, picnic areas, interpretive signing, telephones,
recreational vehicle (RV) sanitary disposal facilities, trails, scenic viewpoints, commercial and public
information displays, and visitor information centers.
annual average daily traffic (AADT) The total volume of traffic passing a point or segment of a
highway facility in both directions for one year divided by the number of days in the year. Normally,
periodic daily traffic volumes are adjusted for hours of the day counted, days of the week, and seasons
of the year to arrive at average annual daily traffic.
annual daily traffic (ADT) The average 24 hour volume, being the total volume during a stated period
divided by the number of days in that period. Normally, this would be periodic daily traffic volumes over
several days, not adjusted for days of the week or seasons of the year.
approach An access point, other than a public road/street, that allows access to or from a limited
access highway on the state highway system.
approach and access connection These terms are listed under the specific access section to which they
apply. The first section below is for limited access highways and uses the term approach. The second
section below is for managed access highways and uses the term access connection. Approaches and
access connections include any ability to leave or enter a highway right of way other than at an
intersection with another road or street.
(a) limited access highways: approach An access point, other than a public road/street, that allows
access to or from a limited access highway on the state highway system. There are five types of
approaches to limited access highways that are allowed:
Type A An off and on approach in a legal manner, not to exceed 30 feet in width, for the
sole purpose of serving a single-family residence. It may be reserved by the abutting owner
for specified use at a point satisfactory to the state at or between designated highway
stations. This approach type is allowed on partial and modified control limited access
highways.
Type B An off and on approach in a legal manner, not to exceed 50 feet in width, for use
necessary to the normal operation of a farm, but not for retail marketing. It may be reserved
by the abutting owner for specified use at a point satisfactory to the state at or between
designated highway stations. This approach type is allowed on partial and modified control
limited access highways. This approach type may be used for wind farms when use of the
approach is limited to those vehicles necessary to construct and maintain the farm for use in
harvesting wind energy.
Type C An off and on approach in a legal manner, for a special purpose and width to be
agreed upon. It may be specified at a point satisfactory to the state at or between
designated highway stations. This approach type is allowed on partial and modified control
limited access highways and on full control limited access highways where no other
reasonable means of access exists, as solely determined by the department.
Type D An off and on approach in a legal manner, not to exceed 50 feet in width, for use
necessary to the normal operation of a commercial establishment. It may be specified at a
point satisfactory to the state at or between designated highway stations. This approach
type is allowed only on modified control limited access highways.
Type E This type is no longer allowed to be constructed because of the requirements that
there be only one access point per parcel on a limited access state highway.
Type F An off and on approach in a legal manner, not to exceed 30 feet in width, for the
sole purpose of serving a wireless communication site. It may be specified at a point
satisfactory to the state at or between designated highway stations. This approach type is
allowed only on partial control limited access highways. (See WAC 468 58 080(vi) for further
restrictions.)
(b) managed access highways: access connection An access point, other than a public road/street,
that permits access to or from a managed access highway on the state highway system. There are
five types of access connection permits:
conforming access connection A connection to a managed access highway that meets
current WAC and WSDOT location, spacing, and design criteria.
grandfathered access connection Any connection to the state highway system that was in
existence and in active use on July 1, 1990, and has not had a significant change in use.
joint-use access connection A single connection to a managed access highway that serves
two or more properties.
nonconforming access connection A connection to a managed access highway that does
not meet current WSDOT location, spacing, or design criteria, pending availability of a future
conforming access connection.
variance access connection A connection to a managed access highway at a location not
normally allowed by current WSDOT criteria.
(c) managed access connection category There are four access connection permit categories for
managed access connections to state highways: Category I, Category II, Category III, and Category IV
(see Chapter 540).
area of influence The area that will be directly impacted by the proposed action: freeway main line,
ramps, crossroads, immediate off-system intersections, and state and local roadway systems.
auxiliary aids and services (1) Qualified interpreters, notetakers, transcription services, written
materials, telephone handset amplifiers, assistive listening devices, assistive listening systems,
telephones compatible with hearing aids, open and closed captioning, telecommunications devices for
persons with hearing or speech difficulties (TDDs), videotext displays, or other effective methods for
making aurally delivered materials available to individuals with hearing limitations; (2) Qualified readers,
taped texts, audio recordings, Brailled materials, large print materials, or other effective methods for
making visually delivered materials available to individuals with visual impairments; (3) Acquisition or
modification of equipment or devices; (4) Other similar services and actions; and (5) Providing and
disseminating information, written materials, and notices in languages other than English, where
appropriate.
auxiliary lane The portion of the roadway adjoining the through lanes for parking, speed change,
turning, storage for turning, weaving, truck climbing, and other purposes supplementary to through-
traffic movement.
average light level The average of all light intensities within the design area.
average weekday vehicle trip ends (AWDVTE) The estimated total of all trips entering plus all trips
leaving a road approach on a weekday for the final stage of development of the property served by the
road approach.
backslope A sideslope that goes up as the distance increases from the roadway (cut slopes).
barrier terminal A crash-tested end treatment for longitudinal barriers that is designed to reduce the
potential for spearing, vaulting, rolling, or excessive deceleration of impacting vehicles from either
direction of travel. Barrier terminals include applicable anchorage.
baseline The approved time phased plan (for a project, a work breakdown structure component, a
work package, or a schedule activity), plus or minus approved project scope, cost, schedule, and
technical changes. Generally refers to the current baseline, but may refer to the original or some other
baseline. Usually used with a modifier (e.g., cost baseline, schedule baseline, performance measurement
baseline, technical baseline).
baseline performance metric A description of need in terms that can be measured or assessed in both
the existing and proposed (future) state.
baseline performance need The primary reason a project has been proposed. It refers to the threshold
determination at the project location resulting from a statewide biennial prioritization and funding
process. It may also be the specific issue to be addressed by the project described by a partnering
agency that is providing the funding.
basic number of lanes The minimum number of general purpose lanes designated and maintained
over a significant length of highway.
Basis of Design (BOD) A document and template used to record information, decisions, and analysis
needed in the development of a project design, including all factors leading to the development and
selection of a project alternative, and the selection of design elements associated with that alternative.
benefit/cost analysis A method of valuing a proposition by first monetizing all current expenditures to
execute―cost―as well as the expected yields into the future―benefit, then dividing the total benefit by
the total cost, thus providing a ratio. Alternatives may be rendered and compared in this fashion where,
typically, a higher ratio is preferable, indicating a better return on investment.
bicycle Any device propelled solely by human power upon which a person or persons may ride, having
two tandem wheels, either of which is 16 inches or more in diameter, or three wheels, any one of which
is more than 20 inches in diameter.
bicycle route A system of facilities that is used or has a high potential for use by bicyclists or that is
designated as such by the jurisdiction having the authority. A series of bicycle facilities may be combined
to establish a continuous route and may consist of any or all types of bicycle facilities.
bike lane A portion of a highway or street identified by signs and pavement markings as reserved for
bicycle use.
buffer A space measured from the back of the curb to the edge of the sidewalk that could be treated
with plantings or alternate pavement, or be used for needs such as drainage treatment or utility
placement. (ADA term)
buffer-separated HOV lane An HOV lane that is separated from the adjacent same direction general-
purpose freeway lanes by a designated buffer.
bus A rubber-tired motor vehicle used for transportation, designed to carry more than ten passengers.
business access transit (BAT) lanes A transit lane that allows use by other vehicles to access abutting
businesses.
bus pullout A bus stop with parking area designed to allow transit vehicles to stop wholly off the
roadway.
bus rapid transit (BRT) An express rubber tired transit system operating predominantly in roadway
managed lanes. It is generally characterized by separate roadway or buffer-separated HOV lanes, HOV
direct access ramps, and a high-occupancy designation (3+ or higher).
bus shelter A facility that provides seating and protection from the weather for passengers waiting for
a bus.
bus stop A place designated for transit vehicles to stop and load or unload passengers.
capacity The maximum sustainable flow rate at which vehicles or persons can reasonably be expected
to traverse a point or uniform segment of a lane or roadway during a specified time period under given
roadway, geometric, traffic, environmental, and control conditions. Capacity is usually expressed as
vehicles per hour (vph), passenger cars per hour (pcph), or persons per hour (pph).
Capital Improvement and Preservation Program (CIPP) WSDOT’s program of projects developed each
biennium that delivers capital investments in highway, marine, and rail facilities that have been funded
in part or in whole by the state Legislature. The CIPP is submitted to the Governor and, ultimately, by
the Governor to the Legislature.
Categorical Exclusion (CE) (NEPA) or Categorical Exemption (CE) (SEPA) Actions that do not
individually or cumulatively have a significant effect on the environment.
central island The area of the roundabout, including the truck apron, surrounded by the circulating
roadway.
central island diameter The diameter of the central island, including the truck apron (see Chapter
1320).
circulating roadway The traveled lane(s) adjacent to the central island and outside the truck apron,
including the entire 360° circumference of the circle.
circulating roadway width The total width of the circulating lane(s) measured from inscribed circle to
the central island (see Chapter 1320).
clear run-out area The area beyond the toe of a nonrecoverable slope available for use by an errant
vehicle.
clear width The unobstructed width within a pedestrian circulation path. The clear width within a
pedestrian circulation path must meet the accessibility criteria for a pedestrian access route. (ADA term)
clear zone The total roadside border area, available for use by errant vehicles, starting at the edge of
the traveled way and oriented from the outside or inside shoulder (in median applications) as
applicable. This area may consist of a shoulder, a recoverable slope, a nonrecoverable slope, and/or a
clear run-out area. The clear zone cannot contain a critical fill slope, fixed objects, or water deeper than
2 feet.
climate change vulnerability The risk a transportation facility will be impacted by the effects of climate
change.
climbing lane An auxiliary lane used for the diversion of slow traffic from the through lane.
collector A context description of a roadway intended to provide a mix of access and mobility
performance. Typically low speed, collecting traffic from local roads and connecting them with
destination points or arterials. This term is used in multiple classification systems, but is most commonly
associated with the Functional Classification System.
collector-distributor road (C-D road) A parallel roadway designed to remove weaving from the main
line and reduce the number of main line entrances and exits.
collector system Routes that primarily serve the more important intercounty, intracounty, and
intraurban travel corridors; collect traffic from the system of local access roads and convey it to the
arterial system; and on which, regardless of traffic volume, the predominant travel distances are shorter
than on arterial routes (RCW 47.05.021).
Commercial Vehicle Information Systems and Networks (CVISN) A network that links intelligent
transportation systems (ITS) to share information on commercial vehicles. When in operation at a weigh
site, it can enable commercial vehicles to clear the facility without stopping.
complex ramp alignment and grade As related to Chapter 1040 Illumination. The exit advisory speed
is 35 mph or lower than the posted main line speed, or there is a 6% or greater change in grade from
existing main line grade to the ramp grade.
conflict point A point where road user paths cross, merge, or diverge.
consider To think carefully about, especially in order to make a decision. The decision to document a
consideration is left to the discretion of the engineer.
construction impact zone The area in which an alteration to an existing facility takes place (also known
as the project footprint). If a crosswalk (marked or unmarked) will be reconstructed, paved
(overlay or inlay), or otherwise altered as part of a project, then the curb ramps that serve that
crosswalk are within the construction impact zone. (ADA term)
context Refers to the environmental, economic, and social features that influence livability and travel
characteristics. Context characteristics provide insight into the activities, functions, and performance
that can be influenced by the roadway design. Context also informs roadway design, including the
selection of design controls, such as target speed and modal priority, and other design decisions.
See Chapter 1102.
context categories The naming convention used to describe either a land use or transportation
context (see Chapter 1102).
context characteristic A distinguishing trait within a context, either land use or transportation. Chapter
1102 lists several common characteristics that help distinguish between one type of context versus
another. There may be additional traits not covered in the chapter.
contextual performance metric A restatement of a contextual performance need in terms that can be
measured or assessed in both the existing and proposed (future) state.
contextual performance need A statement of need that applies to a project location which has not
been identified as a baseline need.
contiguous parcels Two or more pieces of real property, under the same ownership, with one or more
boundaries that touch and have similarity of use.
continuous load The electrical load on a circuit that lasts for a duration of three or more hours on any
day.
contributing factors Those operational conditions, human factors, context conditions, design
elements, design controls, or actions identified by data, engineering judgment, or the community that
contribute to a performance need under evaluation.
controlled releasing terminal (CRT) post A standard-length guardrail post that has two holes drilled
through it so it might break away when struck.
conventional traffic signal A permanent or temporary installation providing alternating right of way
assignments for conflicting traffic movements. At least two identical displays are required for the
predominant movement on each approach.
corner clearance On a managed access highway, the distance from an intersection of a public road or
street to the nearest access connection along the same side of the highway. The minimum corner
clearance distance (see Chapter 540) is measured from the closest edge of the intersecting road or
street to the closest edge of the traveled way of the access connection, measured along one side of the
traveled way (through lanes) (see also access point spacing).
corridor sketch An information source that describes the attributes of a state highway corridor, its
current and future function, as well as its performance expectations. It will ultimately identify cost-
effective strategies for future consideration. A completed corridor sketch may have information that is
valuable at the project level in determining contextual performance needs, and project alternatives. A
corridor sketch is not a substitute for detailed planning and analysis, nor is it a list of investments or
projects.
corridor vision The future transportation context from a regional perspective. Practical Design
considers and accounts for the contextual needs of the longer section of highway in the development
and evaluation of alternatives to ensure a favorable outcome for the greater system.
counter slope The slope of the gutter or roadway at the foot of a curb ramp or landing where it
connects to the roadway, measured along the axis of the running slope extended. (ADA term)
court reporter A person with a license to write and issue official accounts of judicial or legislative
proceedings.
Crash Analysis Report (CAR) A template that is used for documenting required analysis for I-2
CAL/CAC/IAL projects, as described in Chapter 321.
critical fill slope A slope on which a vehicle is likely to overturn. Slopes steeper than 3H:1V are
considered critical fill slopes.
cross slope The slope measured perpendicular to the direction of travel. (ADA term)
crossroad The minor roadway at an intersection. At a stop-controlled intersection, the crossroad has
the stop.
crosswalk A marked or unmarked pedestrian crossing, typically at an intersection, that connects the
pedestrian access routes on opposite sides of a roadway. A crosswalk must meet accessibility criteria.
A crosswalk is also defined as:
“…the portion of the roadway between the intersection area and a prolongation or
connection of the farthest sidewalk line or in the event there are no sidewalks then
between the intersection area and a line ten feet therefrom, except as modified by a
marked crosswalk” (RCW 46.04.160).
“(a) That part of a roadway at an intersection included within the connections of the
lateral lines of the sidewalks on opposite sides of the highway measured from the curbs
or in the absence of curbs, from the edges of the traversable roadway, and in the
absence of a sidewalk on one side of the roadway, the part of the roadway included
within the extension of the lateral lines of the sidewalk at right angles to the center
line; (b) any portion of a roadway at an intersection or elsewhere distinctly indicated as
a pedestrian crossing by lines on the surface, which might be supplemented by
contrasting pavement texture, style, or color” (MUTCD, 2003; Guide for the Planning,
Design, and Operation of Pedestrian Facilities, AASHTO, 2004). (ADA term)
curb extension A curb and sidewalk bulge or extension out into the parking lane used to decrease the
length of a pedestrian crossing and increase visibility for the pedestrian and driver. (ADA term)
curb ramp A combined ramp and landing to accomplish a change in level at a curb. This element provides
street and sidewalk access to pedestrians with mobility impairments. (ADA term)
parallel curb ramp A curb ramp design where the sidewalk slopes down to a landing at
road level with the running slope of the ramp in line with the direction of sidewalk
travel
perpendicular curb ramp A curb ramp design where the ramp path is perpendicular to
the curb and meets the gutter grade break at a right angle.
decision sight distance The distance needed for a driver to detect an unexpected or difficult-to-
perceive condition, recognize the condition, select an appropriate maneuver, and complete the
maneuver based on design conditions and design speed.
deflection (in respect to roundabouts) The change in the path of a vehicle imposed by the geometric
features of a roundabout resulting in a slowing of vehicles.
delineation Any method of defining the roadway operating area for the driver.
deliverable Any unique and verifiable product, result or capability to perform a service that must be
produced to complete a process, phase, or project.
Design Analysis A process and tool to record design element changes where the dimensions chosen do
not meet the value, or lie within the range of values, provided for that element in the Design Manual.
(see Chapters 300 and 1106).
Design Approval Documented approval of the design at this early milestone locks in design policy for
three years. Design approval becomes part of the Design Documentation Package (see Chapter 300.)
design-bid-build The project delivery method where design and construction are sequential steps in
the project development process (23 CFR 636.103).
design-build contract An agreement that provides for design and construction of improvements by a
consultant/contractor team. The term encompasses design-build-maintain, design-build-operate,
design-build-finance, and other contracts that include services in addition to design and construction.
Franchise and concession agreements are included in the term if they provide for the franchisee or
concessionaire to develop the project that is the subject of the agreement (23 CFR 636.103).
design-builder The firm, partnership, joint venture, or organization that contracts with WSDOT to
perform the work.
design controls Key parameters that critically shape design decisions and effect calculated dimensions
for some design elements. Design controls are conscientiously selected and work together with the
context characteristics to achieve a particular outcome (see Chapter 1103)
Design Clear Zone The minimum clear zone target value used in highway design.
design element Any component or feature associated with roadway design that becomes part of the
final product. Examples include lane width, shoulder width, alignment, and clear zone (see Chapter
1105.)
designer This term applies to WSDOT design personnel. Wherever “designer” appears in this manual,
design-build personnel shall deem it to mean: Engineer of Record, Design Quality Assurance Manager,
design-builder, or any other term used in the design-build contract to indicate design-build personnel
responsible for the design elements of a design-build project, depending on the context of information
being conveyed.
design hourly volume (DHV) Computed by taking the annual average daily traffic times the K-factor. It
can only be accurately determined in locations where there is a permanent traffic recording device
active 365 days of the year. It correlates to the peak hour (see peak hour), but it is not equivalent. In
some circumstances, it is necessary to use the peak hour data instead of DHV because peak hour can be
collected using portable traffic recorders.
design speed A design control; the speed used to determine the various geometric design features of
the roadway.
design up An approach to developing project alternatives utilizing the smallest dimensions that meet
the need by providing the desired performance.
design users A broad term intended to capture all modal users that currently utilize or are legally
permitted on a roadway segment or node.
design year The forecast year used for design as described in Chapter 1103. See also horizon year.
desirable Design criteria that are recommended for inclusion in the design.
detectable warning surface A tactile surface feature of truncated dome material built into or applied to
the walking surface to alert persons with visual impairments of vehicular ways. Federal yellow is the
color used on WSDOT projects to achieve visual contrast. Colors other than federal yellow that meet the
light-on-dark/dark-on-light requirement may be used on projects where cities have jurisdiction.
(Detectable warning surfaces are detailed in the Standard Plans.) (ADA term)
Determination of Nonsignificance (DNS) (SEPA) The written decision by the Regional Administrator
that a proposal will not have a significant impact and no EIS is required.
Determination of Significance (DS) (SEPA) A written decision by the Regional Administrator that a
proposal could have a significant adverse impact and an EIS is required.
directional design hour volume (DDHV) The traffic volume for the design hour in the peak direction of
flow, in vehicles per hour. For example, if during the design hour, 60% of the vehicles traveled
eastbound and 40% traveled westbound, then the DDHV for the eastbound direction would be the
DHV x 0.60.
divided multilane A roadway with two or more through lanes in each direction and a median that
physically or legally prohibits left turns, except at designated locations.
document (verb) The act of including a short note to the Design Documentation Package that explains
a design decision.
dooring Describes a conflict with a parked vehicle door opening into a roadway bike facility.
driveway A vehicular access point that provides access to or from a public roadway.
easement A documented right, as a right of way, to use the property of another for designated
purposes.
element An architectural or mechanical component or design feature of a space, site, or public right of
way.
emergency escape ramp A roadway leaving the main roadway designed for the purpose of slowing
and stopping out-of-control vehicles away from the main traffic stream.
emergency vehicle signal A special adaptation of a conventional traffic signal installed to allow for the
safe movement of authorized emergency vehicles. Usually, this type of signal is installed on the highway
at the entrance into a fire station or other emergency facility. The signal ensures protected entrance
onto the highway for the emergency vehicle. When not providing for this movement, the signal either
operates continuously (consistent with the requirements for a conventional traffic signal) or displays
continuous green, which is allowed at non-intersection locations only. At least two identical displays are
required per approach.
enforcement observation point A place where a law enforcement officer may park and observe traffic.
entry angle The angle between the entry roadway and the circulating roadway measured at the yield
point (see Chapter 1320).
entry curve The curve of the left edge of the roadway that leads into the circulating roadway (see
Chapter 1320).
entry width The width of an entrance leg at the inscribed circle measured perpendicular to travel (see
Chapter 1320).
Environmental Assessment (EA) (NEPA) A document prepared for federally funded, permitted, or
licensed projects that are not categorical exclusions (CE), but do not appear to be of sufficient
magnitude to require an EIS. The EA provides enough analysis to determine whether an EIS or a FONSI
should be prepared.
Environmental Impact Statement (EIS) A detailed written statement of a proposed course of action,
project alternatives, and possible impacts of the proposal.
Environmental Review Summary (ERS) (see Project Summary) Part of the Project Summary document,
the ERS identifies environmental permits and approvals. It is prepared in the region and is required for
Design Approval.
expressway A divided highway that has a minimum of two lanes in each direction for the exclusive use
of traffic and that may or may not have grade separations at intersections. A transportation context
characteristic that is designated for a divided highway with limited access that provides regional
mobility.
extrude A procedure for applying marking material to a surface by forcing the material through a die
to give it a certain shape.
facility All or any portion of buildings, structures, improvements, elements, and pedestrian or
vehicular routes located in a public right of way.
feature A component of a pedestrian access route, such as a curb ramp, driveway, crosswalk, or
sidewalk.
Federal Highway Administration (FHWA) The division of the U.S. Department of Transportation with
jurisdiction over the use of federal transportation funds for state highway and local road and street
improvements.
Federal Transit Administration (FTA) The division of the U.S. Department of Transportation with
jurisdiction over the use of federal funds for financial assistance to develop new transit systems and
improve, maintain, and operate existing systems.
final design Any design activities following preliminary design; expressly includes the preparation of
final construction plans and detailed specifications for the performance of construction work
(23 CFR 636.103). Final design is also defined by the fact that it occurs after NEPA/SEPA approval has
been obtained.
Finding of No Significant Impact (FONSI) (NEPA) A federal document indicating that a proposal will not
significantly affect the environment and an EIS is not required.
findings and order A document containing the findings and conclusions of a limited access hearing
approved by the Assistant Secretary, Engineering & Regional Operations (see Chapter 210).
findings and order plan A limited access plan, prepared after a limited access hearing, which is based
on the hearing record.
fixed feature (object to be mitigated) A fixed object, a side slope, or water that, when struck, can
result in impact forces on a vehicle’s occupants that may result in injury or place the occupants in a
situation that has a high likelihood of injury. A fixed feature can be either constructed or natural.
flangeway gap The gap for the train wheel at a railroad crossing. The space between the inner edge of
a rail and the pedestrian crossing surface. (ADA term)
flare The widening of the approach to the roundabout to increase capacity and facilitate natural
vehicle paths.
footcandle (fc) The illumination of a surface one square foot in area on which a flux of one lumen is
uniformly distributed. One footcandle equals one lumen per square foot.
foreslope A sideslope that goes down as the distance increases from the roadway (fill slopes and ditch
inslopes).
freeway A divided highway that has a minimum of two lanes in each direction for the exclusive use of
traffic and with full control of access.
frontage road An auxiliary road that is a local road or street located beside a highway for service to
abutting property and adjacent areas and for control of access.
functional classification The grouping of streets and highways according to the character of the
service they are intended to provide.
geocomposites Prefabricated edge drains, wall drains, and sheet drains that typically consist of a
cuspated or dimpled polyethylene drainage core wrapped in a geotextile. The geotextile wrap keeps the
core clean so that water can freely flow through the drainage core, which acts as a conduit.
Prefabricated edge drains are used in place of shallow geotextile-wrapped trench drains at the edges of
the roadway to provide subgrade and base drainage. Wall drains and sheet drains are typically placed
between the back of the wall and the soil to drain the soil retained by the wall.
Geographic Information System (GIS) A computerized geographic information system used to store,
analyze, and map data. Data may be used with GIS if the data includes the Accumulated Route Mile
(ARM) or State Route Milepost (SRMP) programs. Global Positioning System (GPS) technology provides a
means of collecting data and is an alternative to ARM and SRMP. WSDOT’s primary desktop tool to view
and analyze GIS data is ArcGIS software. GIS is used to gather and analyze data to support the purpose
and need as described in the Project Summary
( http://wwwi.wsdot.wa.gov/gis/supportteam/default.asp).
geogrids A polymer grid mat constructed either of coated yarns or a punched and stretched polymer
sheet. Geogrids usually have high strength and stiffness and are used primarily for soil reinforcement.
geomembranes Impervious polymer sheets that are typically used to line ponds or landfills. In some
cases, geomembranes are placed over moisture-sensitive swelling clays to control moisture.
geonets Similar to geogrids, but typically lighter weight and weaker, with smaller mesh openings.
Geonets are used in light reinforcement applications or are combined with drainage geotextiles to form
a drainage structure.
geosynthetic erosion control The minimizing of surficial soil particle movement due to the flow of
water over the surface of bare soil or due to the disturbance of soil caused by construction activities
under or near bodies of water. This is the primary function of geotextiles used as silt fences or placed
beneath riprap or other stones on soil slopes. Silt fences keep eroded soil particles on the construction
site, whereas geotextiles placed beneath riprap or other stones on soil slopes prevent erosion from
taking place at all. In general, the permanent erosion control methods described in Chapter 630 are only
used where more natural means (like the use of biodegradable vegetation mats to establish vegetation
to prevent erosion) are not feasible. These functions control some of the geosynthetic properties, such
as apparent opening size (AOS) and permittivity, and in some cases load-strain characteristics. The
application will also affect the geosynthetic installation conditions. These installation conditions
influence the remaining geosynthetic properties needed, based on the survivability level required.
geosynthetic filtration The passage of water through the geosynthetic relatively unimpeded
(permeability or permittivity) without allowing passage of soil through the geosynthetic (retention). This
is the primary function of geotextiles in underground drainage applications.
geosynthetic survivability The ability of the geosynthetic to resist installation conditions without
significant damage, such that the geosynthetic can function as intended. Survivability affects the
strength properties of the geosynthetic required.
geotextiles (nonwoven) A sheet of continuous or staple fibers entangled randomly into a felt for
needle-punched nonwovens and pressed and melted together at the fiber contact points for heat-
bonded nonwovens. Nonwoven geotextiles tend to have low-to-medium strength and stiffness with high
elongation at failure and relatively good drainage characteristics. The high elongation characteristic
gives them superior ability to deform around stones and sticks.
geotextiles (woven) Slit polymer tapes, monofilament fibers, fibrillated yarns, or multifilament yarns
simply woven into a mat. Woven geotextiles generally have relatively high strength and stiffness and,
except for the monofilament wovens, relatively poor drainage characteristics.
gore The area downstream from the intersection of the shoulders of the main line and exit ramp.
Although generally referring to the area between a main line and an exit ramp, the term may also be
used to refer to the area between a main line and an entrance ramp.
gore nose At an exit ramp, the point at the end of the gore area where the paved shoulders of the
main line and the ramp separate (see Chapter 1360) or the beginning of traffic barrier, not including any
impact attenuator. Also, the similar point at an entrance ramp.
grade break The intersection of two adjacent surface planes of different grade. (ADA term)
hearing An assembly to which the public is invited and at which participation is encouraged. Types of
hearings include:
administrative appeal hearing A formal process whereby a property owner may appeal
WSDOT’s implementation of access management legislation. The appeal is heard by an
administrative law judge (ALJ), who renders a decision. (See Chapter 540 for administrative
appeal hearing procedures.)
combined hearing A hearing held when there are public benefits to be gained by combining
environmental, corridor, design, and/or limited access subjects.
corridor hearing A formal or informal hearing that presents the corridor alternatives to the
public for review and comment before a commitment is made to any one route or location.
This type of hearing is beneficial for existing corridors with multiple Improvement projects
programmed over a long duration.
design hearing A formal or informal hearing that presents the design alternatives to the
public for review and comment before the selection of a preferred alternative.
environmental hearing A formal or informal hearing documenting that social, economic, and
environmental impacts have been considered and that public opinion has been solicited.
formal hearing format A hearing conducted by a moderator using a formal agenda, overseen
by a hearing examiner, and recorded by a court reporter, as required by law. Limited access
hearings require the use of the formal hearing format (see Chapter 210).
informal hearing format A hearing where oral comments are recorded by a court reporter, as
required by law. An informal hearing often uses the “open house” format (see Chapter 210). A
formal agenda and participation by a hearing examiner are optional.
limited access hearing A formal hearing that gives local public officials, owners of abutting
properties, and other interested persons an opportunity to be heard about the limitation of
access to the highway system.
hearing agenda An outline of the actual public hearing elements, used with formal hearings. (See
Chapter 210 for contents.)
Hearing Coordinator The HQ Access and Hearings Section Manager: (360) 705-7266.
hearing examiner An administrative law judge from the Office of Administrative Hearings, or a WSDOT
designee, appointed to moderate a hearing.
hearing summary Documentation prepared by the region and approved by Headquarters that
summarizes environmental, corridor, and design hearings. (See Chapter 210 for content requirements.)
hearing transcript A document prepared by the court reporter that transcribes verbatim all oral
statements made during the hearing, including public comments. This document becomes part of the
official hearing record.
high-occupancy toll (HOT) lane A managed lane that combines a high-occupancy vehicle lane and a
toll lane.
high-occupancy vehicle (HOV) A vehicle that meets the occupancy requirements of the facility as
authorized by WAC 468-510-010.
high pavement type Portland cement concrete pavement or hot mix asphalt (HMA) pavement on a
treated base.
highway A general term denoting a street, road, or public way for the purpose of vehicular travel,
including the entire area within the right of way.
Highway System Plan (HSP) A WSDOT planning document that addresses the state highway system
element of the Washington Transportation Plan (WTP). The HSP defines the service objectives, action
strategies, and costs to maintain, operate, preserve, and improve the state highway system for 20 years.
The HSP is the starting point for the state highway element of the CIPP and the state Highway
Construction Program. It is periodically updated to reflect completed work and changing transportation
needs, policies, and revenues. It compares highway needs to revenues, describes the “constrained”
costs of the highway programs, and provides details of conceptual solutions and performance in the
improvement program.
Highways of Statewide Significance (HSS) Include interstate highways and other principal arterials
that are needed to connect major communities in the state. The designation helps assist with the
allocation and direction of funding. (http://www.wsdot.wa.gov/planning/HSS)
Horizon year Typically considered to be 20 years from the year construction is scheduled to begin, as
described in Chapter 1103. See also design year.
HOV direct access ramp An on- or off-ramp exclusively for the use of HOVs that provides access
between a freeway HOV lane and a street, transit support facility, or another freeway HOV lane without
weaving across general-purpose lanes.
impact attenuator system A device that acts primarily to bring an errant vehicle to a stop at a
deceleration rate tolerable to the vehicle’s occupants or to redirect the vehicle away from a fixed
feature.
inscribed circle diameter (ICD) The diameter of the inscribed circle (see Chapter 1320).
inner corridor access a means of entering or leaving a roadside area inside of the state limited access
right of way without crossing over, under, or physically through the plane of limited access.
intersection An at-grade access point connecting a state highway with a road or street duly established
as a public road or public street by the local governmental entity.
intersection angle The angle between any two intersecting legs at the point the centerlines intersect.
intersection area The area of the intersecting roadways bounded by the edge of traveled ways and the
area of the adjacent roadways to the farthest point: (a) the end of the corner radii, (b) through any
marked crosswalks adjacent to the intersection, (c) to the stop bar, or (d) 10 feet from the edge of
shoulder of the intersecting roadway (see Chapter 1310).
Intersection, at grade The general area where a roadway or ramp terminal is met or crossed at a
common grade or elevation by another roadway.
intersection control beacon (also flashing beacon) A secondary control device, generally suspended
over the center of an intersection, that supplements intersection warning signs and stop signs. One
display per approach may be used; however, two displays per approach are desirable. Intersection
control beacons are installed only at intersections that control two or more directions of travel.
intersection leg Any one of the roadways radiating from and forming part of an intersection.
entrance leg The lanes of an intersection leg for traffic entering the intersection.
exit leg The lanes of an intersection leg for traffic leaving the intersection.
Note: Whether an intersection leg is an entrance leg or an exit leg depends on which movement is
being analyzed. For two-way roadways, each leg is an entrance leg for some movements and an exit
leg for other movements.
intersection design vehicle A specific selection of the vehicle to be used to dimension intersection
design elements at an individual intersection.
intersection sight distance The length of roadway visible to the driver of a vehicle entering an
intersection.
Interstate System A network of routes designated by the state and the Federal Highway
Administration (FHWA) under terms of the federal-aid acts as being the most important to the
development of a national system. The Interstate System is part of the principal arterial system.
island A defined area within an intersection, between traffic lanes, for the separation of vehicle
movements or for pedestrian refuge.
justify Preparing a memo to the DDP identifying the reasons for the decision: a comparison of
advantages and disadvantages of all options considered. A more rigorous effort than document.
K-factor The proportion of AADT occurring in the analysis hour is referred to as the K-factor, expressed
as a decimal fraction (commonly called “K,” “K30,” or “K100”). The K30 is the thirtieth (K100 is the one-
hundredth) highest peak hour divided by the annual average daily traffic. Normally, the K30 or K100 will
be in the range of 0.09 to 0.10 for urban and rural areas. Average design hour factors are available on
the web in the Transportation Data, GIS & Modeling Office’s Annual Peak Hour Report.
lamp lumens The total light output from a lamp, measured in lumens.
lane control signal (reversible lanes) A special overhead signal that permits, prohibits, or warns of
impending prohibition of lane use.
lane width The lateral design width for a single lane, striped as shown in the Standard Plans and the
Standard Specifications. The width of an existing lane is measured from the edge of traveled way to the
center of the lane line or between the centers of adjacent lane lines.
landing A level paved area, within or at the top and bottom of a stair or ramp, designed to provide
turning and maneuvering space for wheelchair users and as a resting place for pedestrians. (ADA term)
lateral clearance The distance from the edge of traveled way to a roadside object.
layered networks Roadway network arrangement where the objective is to separate modes onto
different facilities with planned interconnection locations.
lead agency The public agency that has the principal responsibility for carrying out or approving a
project.
left-cross Describes the intersection conflict between a motor vehicle left-turn and bicycle through
movement in the opposing direction.
legal road approach A road approach that complies with the requirements of Chapter 530 for limited
access facilities and Chapter 540 for managed access facilities.
length of need The length of a traffic barrier used to shield a fixed feature.
level of service (LOS) LOS is based on peak hour, except where noted. LOS assigns a rank (A – F) to
facility sections based on traffic flow concepts like density, delay, and/or corresponding safety
performance conditions. (See the Highway Capacity Manual and AASHTO’s Geometric Design of
Highways and Streets ["Green Book"] for further details.)
life cycle cost The total cost of a project or item over its useful life. This includes all of the relevant
costs that occur throughout the life of a project or item, including initial acquisition costs (such as right
of way, planning, design, and construction), operation, maintenance, modification, replacement,
demolition, financing, taxes, disposal, and salvage value as applicable.
limited access (L/A) Full, partial, or modified access control is planned and established for each
corridor and then acquired as the right to limit access to each individual parcel (see Chapter 520).
Limited Access and Managed Access Master Plan A map of Washington State that shows established
and planned limited access highways: www.wsdot.wa.gov/design/accessandhearings
limited access highway All highways listed as “Established L/A” on the Limited Access and Managed
Access Master Plan and where the rights of direct access to or from abutting lands have been acquired
from the abutting landowners.
full access control This most restrictive level of limited access provides access, using
interchanges, for selected public roads/streets only, and prohibits highway intersections at
grade.
partial access control The second most restrictive level of limited access. At grade
intersections with selected public roads are allowed, and there may be some crossings and
some driveway approaches at grade. Direct commercial access is not allowed.
modified access control The least restrictive level of limited access. Characteristics are the
same as for partial access control except that direct commercial access is allowed.
long tunnel A tunnel, lid, or underpass that is greater than 80’ in length and has a length to vertical
clearance ratio greater than 10:1.
luminaire A complete lighting unit comprised of a light bulb or light emitting Diode (LED) module,
wiring, and a housing unit.
luminance The quotient of the luminous flux at an element of the surface surrounding the point and
propagated in directions defined by an elementary cone containing the given direction, by the product
of the solid angle of the cone and area of the orthogonal projection of the element of the surface on a
plane perpendicular to the given direction. The luminous flux may be leaving, passing through, and/or
arriving at the surface.
managed access highway Highways where the rights of direct access to or from abutting lands have
not been acquired from the abutting landowners.
managed lane A lane that increases efficiency by packaging various operational and design actions.
Lane management operations may be adjusted at any time to better match regional goals.
managing project delivery A WSDOT management process for project delivery from team initiation
through project closing.
maximum extent feasible (MEF) From the U.S. Department of Justice, 28 CFR Part 36.402, Alterations.
The phrase “to the maximum extent feasible” applies to “the occasional case where the nature of an
existing facility makes it virtually impossible to comply fully with applicable accessibility standards
through a planned alteration.” This phrase also refers to a stand-alone piece of design documentation
that WSDOT uses to record its reasons for not being able to achieve full ADA compliance in alteration
projects (called a Maximum Extent Feasible document). (ADA term)
maximum uniformity ratio The average light level within the design area divided by the minimum light
level within the design area (see Chapter 1040).
maximum veiling luminance ratio The maximum veiling luminance divided by the average luminance
over a given design area for an observer traveling parallel to the roadway centerline (see Chapter 1040).
Measures of Effectiveness (MOEs) In the context of Chapter 320, examples are: speed, delay, density,
LOS, QOS, person or vehicle throughput, cost vs. benefit, and queue. (See FHWA’s MOE List.)
median The portion of a divided highway separating vehicular traffic traveling in opposite directions.
median functions one or more reason(s) for a median as described in Chapter 1239.
median opening An opening in a continuous median for the specific purpose of allowing vehicle
movement.
Memorandum of Understanding (MOU) for a road approach permit There is a MOU (Highways Over
National Forest Lands) between the United States Forest Service (USFS) and WSDOT that requires the
USFS to obtain a road approach permit for new access to a state highway that is crossing Forest Service
land.
metering signal A signal used to control the predominant flow rate of traffic at an at-grade facility.
Methods and Assumptions Document A mandatory document developed at the beginning of the ARR
phase to record ARR assumptions, methodologies, criteria, and decisions (see Chapter 550).
Metropolitan Planning Organization (MPO) A lead agency designated by the Governor to administer
the federally required transportation planning process in a metropolitan area with a population over
50,000. The MPO is responsible for the 20 year long-range plan and Transportation Improvement
Program (TIP).
midblock pedestrian crossing A marked pedestrian crossing located between intersections. (ADA term)
minimum average light level The average of all light intensities within the design area, measured just
prior to relamping the system (see Chapter 1040).
minimum light level The minimum light intensity of illumination at any single point within the design
area measured just prior to relamping the system (see Chapter 1040).
minor arterial system A rural network of arterial routes linking cities and other activity centers that
generate long distance travel and, with appropriate extensions into and through urban areas, form an
integrated network providing interstate and interregional service (RCW 47.05.021).
minor operational enhancement projects These projects usually originate from the Q2 component of
the Q Program and are quick responses to implement low-cost improvements. They are typically narrow
in scope and focus on improvements to traffic operations and modifications to traffic control devices.
Guidance on the type of work included in the Q subprograms is in the Chart of Accounts.
modal compatibility An assessment to determine which mode(s) need to be considered strictly based
on the context characteristics present or planned. The assessment is independent of whether any
particular mode is present on the segment, and intended to guide strategic investment opportunities on
a segment.
modal priority Mode(s) that will be prioritized when making design decisions for the project, guided by
the outcome of the modal compatibility assessment.
mode A specific type or form of transportation. Typically for roadway design the modes are:
automobiles, transit, truck freight, pedestrians, skateboards, and bicycles.
monument As defined in Chapter 410, a monument is any physical object or structure that marks or
references a survey point. This includes, but is not limited to, a point of curvature (P.C.), a point of
tangency (P.T.), a property corner, a section corner, a General Land Office (GLO) survey point, a Bureau
of Land Management (BLM) survey point, and any other permanent reference set by a governmental
agency or private surveyor.
monument removal or destruction The physical disturbance or covering of a monument such that the
survey point is no longer visible or readily accessible.
mounting height – luminaire The vertical distance between the surface of the design area and the
center of the light source of the luminaire. Note: This is not to be confused with pole height (H1), but is
the actual distance that the luminaire is located above the roadway edge line.
movable bridge signal (also drawbridge signal) A signal installed to notify traffic to stop when the
bridge is opened for waterborne traffic. Movable bridge signals display continuous green when the
roadway is open to vehicular traffic.
multimodal connection The point where multiple types of transportation activities occur; for example,
where transit buses and van pools drop off or pick up passengers (including passengers with bicycles).
National Highway System (NHS) The NHS was developed by the U.S. Department of Transportation
(DOT) in cooperation with the states, local officials, and metropolitan planning organizations (MPOs).
The NHS includes the following subsystems of roadways (note that a specific highway route may be on
more than one subsystem):
Interstate The Eisenhower Interstate System of highways retains its separate identity within
the NHS.
Other Principal Arterials These are highways in rural and urban areas that provide access
between an arterial and a major port, airport, public transportation facility, or other intermodal
transportation facility.
Strategic Highway Network (STRAHNET) This is a network of highways that are important to
the United States' strategic defense policy and that provide defense access, continuity, and
emergency capabilities for defense purposes.
Major Strategic Highway Network Connectors These are highways that provide access
between major military installations and highways that are part of the Strategic Highway
Network.
Intermodal Connectors These highways provide access between major intermodal facilities
and the other four subsystems making up the National Highway System.
natural vehicle path The natural path that a driver navigates a vehicle given the layout of the
intersection and the ultimate destination.
need A statement that identifies the transportation problem(s) or other performance gap
negative illumination Lighting the background and leaving the object dark to contrast with the light
behind it as the driver views it.
network connectivity How the various roadways and other transportation facilities within a network
interconnect in a defined geographic area.
nighttime The period of time from one-half hour after sunset to one-half hour before sunrise and any
other time when persons or objects may not be clearly discernible at a distance of 500 feet (RCW
46.04.200).
no-build condition The baseline, plus state transportation plan and comprehensive plan
improvements, expected to exist, as applied to the year of opening or the design year.
nonconforming road approach A road approach that does not meet current requirements for location,
quantity, spacing, sight distance, or geometric elements.
nonrecoverable slope A slope on which an errant vehicle might continue until it reaches the bottom,
without having the ability to recover control. Fill slopes steeper than 4H:1V, but not steeper than 3H:1V,
are considered nonrecoverable.
nonseparated HOV lane An HOV lane that is adjacent to and operates in the same direction as the
general-purpose lanes with unrestricted access between the HOV lane and the general-purpose lanes.
notice of appearance A form provided by WSDOT for anyone wanting to receive a copy of the findings
and order and the adopted limited access plan (see Chapter 210).
notice of hearing (or hearing notice) A published advertisement that a public hearing will be held.
occupancy designation The minimum number of occupants required for a vehicle to use the HOV
facility.
operating speed The speed at which drivers are observed operating their vehicles during free flow
conditions.
order of hearing The official establishment of a hearing date by the Director & State Design Engineer,
Development Division.
outer separation The area between the outside edge of traveled way for through traffic and the
nearest edge of traveled way of a frontage road or collector-distributor (C-D) road.
overlapped displays Overlapped displays allow a traffic movement to operate with one or more
nonconflicting phases. Most commonly, a minor street’s exclusive right-turn phase is overlapped with
the nonconflicting major street’s left-turn phase. An overlapped display can be terminated after the
parent phase (the main phase the overlap is associated with) terminates. An overlapped display
programmed for two or more parent phases continues to display until all of the parent phases have
terminated. An overlap is made up of two or more phases—not one phase controlling two movements.
painted nose The point where the main line and ramp lanes separate.
passenger loading zone An area provided for pedestrians to board/disembark a vehicle. (ADA term)
passing lane An auxiliary lane on a two-lane highway used to provide the desired frequency of passing
zones.
passing sight distance The distance (on a two-lane highway) needed for a vehicle driver to execute a
normal passing maneuver based on design conditions and design speed.
pavement marking A colored marking applied to the pavement by spray, extrusion, adhesives, or glue
to provide drivers with guidance and other information.
pavement marking beads Glass: Small glass spheres used in highway pavement markings to provide
retroreflectivity. Composite: any non-glass bead intended to provide wet weather retroreflectivity.
peak hour The 60-minute interval that contains the largest volume of traffic during a given time
period. If a traffic count covers consecutive days, the peak hour can be an average of the highest hour
across all of the days. An a.m. peak is simply the highest hour from the a.m., and the p.m. peak is the
highest from the p.m. The peak hour correlates to the DHV, but is not the same. However, it is close
enough on items such as intersection plans for approval to be considered equivalent.
pedestrian Any person afoot or using a wheelchair (manual or motorized) or means of conveyance
(other than a bicycle) propelled by human power, such as skates or a skateboard. (ADA term)
pedestrian access route (PAR) (synonymous with accessible route) A continuous, unobstructed
walkway within a pedestrian circulation path that provides accessibility. Pedestrian access routes consist
of one or more of the following pedestrian facilities: walkways/sidewalks, curb ramps (excluding flares),
landings, crosswalks, pedestrian overpasses/underpasses, access ramps, elevators, and platform lifts.
Note: Not all transportation facilities need to accommodate pedestrians. However, those that do
accommodate pedestrians need to have an accessible route. (ADA term)
pedestrian circulation path A prepared exterior or interior way of passage provided for pedestrian
travel. Includes independent walkways, shared-use paths, sidewalks, and other types of pedestrian
facilities. All pedestrian circulation paths are required to contain a continuous pedestrian access route
that connects to all adjacent pedestrian facilities, elements, and spaces that are required to be
accessible. (ADA term)
pedestrian facilities Walkways such as sidewalks, walking and hiking trails, shared-use paths,
pedestrian grade separations, crosswalks, and other improvements provided for the benefit of
pedestrian travel. Pedestrian facilities are intended to be accessible routes. (ADA term)
pedestrian refuge island An island in the roadway that physically separates the directional flow of
traffic, provides pedestrians with a place of refuge, and reduces the crossing distance. Note: Islands with
cut-through paths are more accessible to persons with disabilities than are raised islands with curb
ramps. (ADA term)
performance-based decisions Decisions that are made based on performance, performance metrics,
performance targets, and performance gaps. Also, decisions made using performance evaluation tools,
such as the Highway Safety Manual predictive methods for evaluating safety performance.
performance category Any broad area of performance important to an organization, project, or place.
WSDOT’s six performance categories: Economic Vitality, Preservation, Safety, Mobility, Environment,
and Stewardship are the result of legislative policy per RCW 47.04.280.
performance evaluation tools Quantitative tools used to measure performance. Examples of these
tools currently being used by WSDOT are Highway Safety Manual methodology (for safety performance)
and Highway Capacity Manual (for mobility performance).
performance gap The difference between the measured and targeted performance unit for a
performance metric. This gap is another way of describing the performance need(s) at a location.
performance metric Any measurable indicator used to assess the achievement of outcomes.
performance need See baseline performance need and contextual performance need
performance target(s) An outcome or desired state intended for a project. Performance targets are
identified as either baseline or contextual (see Chapter 1101).
permit holder The abutting property owner or other legally authorized person to whom an access
connection permit is issued by the permitting authority.
permitted access connection A connection for which an access connection permit has been issued by a
permitting authority.
permitting authority The agency that has legal authority to issue managed access connection permits.
For access connections in unincorporated areas, the permitting authority is WSDOT; for access
connections within corporate limits, the permitting authority is a city or town.
person with a disability Per the U.S. Department of Justice: An individual with a disability is defined by
the ADA as a person who has a physical or mental impairment that substantially limits one or more
major life activities, a person who has a history or record of such an impairment, or a person who is
perceived by others as having such an impairment. It is defined by law through the American with
Disabilities Act. (ADA term)
physical nose The point, upstream of the gore, with a separation between the roadways of 16 to 22
feet (see Chapter 1360).
planning Transportation planning is a decision-making process required by federal and state law used
to solve complex, interrelated transportation and land use problems.
Planning and Environmental Linkage (PEL) A collaborative and integrated approach to transportation
decision-making that (1) considers environmental, community, and economic goals early in the planning
process, and (2) uses the information, analysis, and products developed during planning to inform the
environmental review process.
Plans, Specifications, and Estimates (PS&E) The project development activity that follows Project
Definition and culminates in the completion of contract-ready documents and the engineer’s cost
estimate.
pole height (H1) The vertical distance from the light source to the pole base. This distance is specified
in contracts and used by the pole manufacturers to fabricate the light standard.
portable traffic signal A type of conventional traffic signal used in work zones to control traffic. This
signal is most commonly used on two-way two-lane highways where one lane has been closed for
roadwork. This signal is most commonly operated in pairs, with one signal at each end of the work zone.
This eliminates the need for 24-hour flagger control. The traffic signal provides alternating right of way
assignments for conflicting traffic movements. The signal has an adjustable vertical support with two
three-section signal displays and is mounted on a mobile trailer with its own power source.
positive illumination Lighting the surface of the object as the driver views it.
posted speed The maximum legal speed as posted on a section of highway using regulatory signs.
Practical Design/Practical Solutions An approach to making project decisions that focuses on the
specific problem the project is intended to address. This performance-based approach looks for lower
cost solutions that meet outcomes that WSDOT, partnering agencies, communities and stakeholders
have identified. Practical design is a fundamental component to the vision, mission, values, goals, and
reforms identified in Results WSDOT- WSDOT’s Strategic Plan. With practical solutions, decision-making
focuses on maximum benefit to the system, rather than maximum benefit to the project. Focusing on
the specific project need minimizes the scope of work for each project so that system-wide needs can be
optimized.
prehearing packet A concise, organized collection of all necessary prehearing data, prepared by the
region and approved by the HQ Access and Hearings Section Manager prior to the hearing (see Chapter
210).
preliminary engineering (PE) A term used to describe the Project Delivery process from project
scoping through PS&E review.
principal arterial system A connected network of rural arterial routes with appropriate extensions into
and through urban areas, including routes designated as part of the Interstate System, that serves
corridor movements with travel characteristics indicative of substantial statewide and interstate travel
(RCW 47.05.021).
Priority Programming Process The rational selection of projects and services according to factual need
and an evaluation of life cycle costs and benefits.
project The Project Management Institute defines a project to be "a temporary endeavor undertaken
to create a unique product or service."
Project Development Approval Final approval of all project development documents by the
designated representative of the approving organization prior to the advertisement of a capital
transportation project (see Chapter 300).
Project Engineer This term applies to WSDOT personnel. Wherever “Project Engineer” appears in this
manual, the design-builder shall deem it to mean “Engineer of Record.”
Project File (PF) A file containing all documentation and data for all activities related to a project (see
Chapter 300).
Design Documentation Package (DDP) The portion of the Project File, including Design
Approval and Project Development Approval that will be retained long term in accordance with
WSDOT document retention policies. Depending on the scope of the project, it contains the
Project Summary and some or all of the other documents discussed in Chapter 300. Technical
reports and calculations are part of the Project File, but they are not designated as components
of the DDP. Include estimates and justifications for decisions made in the DDP (see Chapter
300). The DDP explains how and why the design was chosen and documents approvals.
project management plan A formal, approved document that defines how the project is executed,
monitored, and controlled. It may be in summary or detailed form and may be composed of one or
more subsidiary management plans and other work planning documents. For further information, see
the Project Management Guide:
http://www.wsdot.wa.gov/Projects/ProjectMgmt/OnlineGuide/ProjectManagementOnlineGuide.htm
project need statement A statement identifying the baseline performance need for the project. For
each identified project need, there may be one or more performance metrics, targets, and gaps.
Project Summary A set of documents consisting of the, Environmental Review Summary (ERS), and
Project Definition (PD). The Project Summary is part of the design documentation required to obtain
Design Approval and is ultimately part of the design documentation required for Project Development
Approval (see Chapter 300).
Projects of Division Interest (PoDIs) A primary set of projects for which FHWA determines the need to
exercise oversight and approval authority, as described in Chapter 300.
proposal The combination of projects/actions selected through the study process to meet a specific
transportation system need.
public art An enhancement to a functional element, feature, or place within a transportation facility to
provide visual interest. The enhancement could be an addition to a functional element, integrated into a
design, or for purely aesthetic purposes. An element is considered “public art” if it is beyond WSDOT
standard practice for architectural treatment.
public involvement plan A plan to collaboratively involve the public in decision making, tailored to the
specific needs and conditions of a project and the people and communities it serves. It is often part of a
broader communications plan.
public transportation Passenger transportation services available to the public, including buses,
ferries, rideshare, and rail transit.
purpose General project goals such as improve safety, enhance mobility, or enhance economic
development.
Quality of Service (QOS) Defined by the Highway Capacity Manual or by agreement. Intended to
describe how well a facility or service operates or functions from the perspective of the user.
quantitative tools Analytical tools used to measure performance. Examples of tools currently being
used by WSDOT are:
Highway Safety Manual predictive methods (for safety performance)
AASHTOWare SafetyAnalyst
ISATe (spreadsheet tool for implementing the HSM predictive methods for
freeways and interchanges)
IHSDM (FHWA software tool for implementing the HSM predictive methods)
HSM Enhanced Spread Sheets (spreadsheet tools for implementing the HSM
predictive methods for rural two lane two way roadways, rural multilane roads,
and urban and suburban arterials)
See also http://wwwi.wsdot.wa.gov/highwaysafety
Highway Capacity Manual (for mobility performance)
queue cutter traffic signal A traffic signal used at highway-rail grade crossings where the queue from a
downstream traffic signal is expected to extend within the Minimum Track Clearance Distance. It is used
to keep vehicles from an adjacent signalized intersection from queuing on the railroad tracks.
raised median A raised island in the center of a road used to restrict vehicle left turns and side street
access. Note: Islands with cut-through paths are more accessible to persons with disabilities than are
raised islands with curb ramps. (ADA term)
ramp A walking surface with a running slope steeper than 20H:1V (5%). (ADA term)
ramp (in relation to a Roadway) A short roadway connecting a main lane of a highway with another
facility, such as a road, parking lot, or transit stop, for vehicular use.
ramp connection The pavement at the end of a ramp, connecting to a main lane of a roadway.
ramp meter A traffic signal at a freeway entrance ramp that allows a measured or regulated amount of
traffic to enter the freeway.
Record of Decision (ROD) Under the National Environmental Policy Act, the Record of Decision
accompanies the Final Environmental Impact Statement; explains the reasons for the project decision;
discusses alternatives and values considered in selection of the preferred alternative; and summarizes
mitigation measures and commitments that will be incorporated in the project.
recoverable slope A slope on which the driver of an errant vehicle can regain control of the vehicle.
Slopes of 4H:1V or flatter are considered recoverable.
recovery area The minimum target value used in highway design when a fill slope between 4H:1V and
3H:1V starts within the Design Clear Zone.
Recreational Vehicle Account In 1980 the RV account was established for use by the department of
transportation for the construction, maintenance, and operation of recreational vehicle sanitary disposal
systems at safety rest areas (RCW 46.68.170). A recreational vehicle sanitary disposal fee is required for
registration of a recreational vehicle (RCW 46.17.375). Adjustments to the recreational vehicle fee by
the department of transportation may be implemented after consultation with the citizens’
representatives of the recreational vehicle user community (RCW 47.01.460).
relocation assistance program A program that establishes uniform procedures for relocation
assistance that will ensure legal entitlements and provide fair, equitable, and consistent treatment to
persons displaced by WSDOT-administered projects, as defined in the Right of Way Manual.
Request for Proposal (RFP) The document package issued by WSDOT requesting submittal of
proposals for the project and providing information relevant to the preparation and submittal of
proposals, including the instructions to proposers, contract documents, bidding procedures, and
reference documents.
résumé An official notification of action taken by WSDOT following adoption of a findings and order
(see Chapter 210).
retroreflection The phenomenon of light rays striking a surface and being returned directly back to the
source of light.
right-hook Potential intersection conflicts between motor vehicles making a right turn and the bicycle
through movement.
right of way (R/W) A general term denoting land or interest therein, acquired for or designated for
transportation purposes. More specifically, lands that have been dedicated for public transportation
purposes or land in which WSDOT, a county, or a municipality owns the fee simple title, has an
easement devoted to or required for use as a public road/street and appurtenant facilities, or has
established ownership by prescriptive right.
right of way and limited access plan (R/W and L/A plan) A right of way plan that also shows limited
access control details.
road approach An access point, other than a public road/street, that allows access to or from a limited
access highway on the state highway system.
roadside park A roadside user facility for safe vehicular parking off the traveled way and separated
from the highway by some form of buffer. These sites might be equipped with features or elements such
as points of interest, picnic tables, and/or vault toilet buildings. Unlike a safety rest area, a roadside park
does not always provide a permanent restroom building.
roadway luminance The light projected from a luminaire that travels toward a given area, represented
by a point on the pavement surface, and then back toward the observer, opposite to the direction of
travel. The units of roadway luminance are footcandles.
roundabout A circular intersection at grade with yield control of all entering traffic, channelized
approaches with raised splitter islands, counter-clockwise circulation, and appropriate geometric
curvature to force travel speeds on the circulating roadway generally to less than 25 mph.
rumble strips Rumble strips are grooves or rows of raised pavement markers placed perpendicular to
the direction of travel, or ground in a continuous longitudinal sinusoidal pattern. They are used to alert
inattentive drivers.
running slope A slope measured in the direction of travel, normally expressed as a percent. (ADA term)
Safety Analyst A program developed to implement the Highway Safety Manual methodology
safety rest area (SRA) A roadside facility equipped with permanent restroom building(s), a parking
area, picnic tables, refuse receptacles, illumination, and other ancillary services. SRAs typically include
potable water and might include traveler information and telephones.
Safety Rest Area Strategic Plan Developed in 2008 under a stakeholder-coordinated effort of
executive and advisory team members, this plan provides guidance for current and future management
of the SRA program.
sawtooth berth A series of bays that are offset from one another by connecting curb lines, constructed
at an angle from the bus bays. This configuration minimizes the amount of space needed for vehicle pull
in and pull out.
scoping phase An initial phase of project development for a specific project. The scoping phase
precedes the design and/or preliminary engineering phase and is intended to support priority
programing and budget building scenarios. The Project Summary is the documentation developed during
this phase.
security lighting A minimal amount of lighting used to illuminate areas for public safety or theft
reduction. Security lighting for walkways is the lighting of areas where shadows and horizontal and
vertical geometry obstruct a pedestrian’s view.
separated HOV facility An HOV roadway that is physically separated from adjacent general-purpose
lanes by a barrier or median, or is on a separate right of way.
shared-use landing A level (0 to 2% grade cross slope and running slope) paved area within the
shared-use path, designed to provide turning and maneuvering space for wheelchair users and as a
resting place for pedestrians.
shared-use path A facility physically separated from motorized vehicular traffic within the highway
right of way or on an exclusive right of way with minimal crossflow by motor vehicles. Shared-use paths
are primarily used by bicyclists and pedestrians, including joggers, skaters, and pedestrians with
disabilities, including those who use nonmotorized or motorized wheeled mobility devices. With
appropriate design considerations, equestrians may also be accommodated by a shared-use path
facility.
short tunnel A tunnel, lid, or underpass that is shorter than 80’ in length and has a length to vertical
clearance ratio of 10:1 or less.
shoulder The portion of the roadway contiguous with the traveled way, primarily for accommodation
of stopped vehicles, emergency use, lateral support of the traveled way, and where allowed, use by
pedestrians and bicycles.
shoulder width The lateral dimension of the shoulder, measured from the edge of traveled way to the
edge of roadway or the face of curb.
sidewalk A walkway along a highway, road, or street intended for use by pedestrians. (ADA term)
SIgnal Maintenance Management System (SIMMS) A database used for traffic signals, illumination,
and Intelligent Transportation Systems (ITS). SIMMS is used to establish an inventory base, enter work
reports, print timesheets, and store maintenance records for electrical/electronic systems within
WSDOT right of way.
single-lane roundabout A roundabout having single-lane entries at all legs and one circulating lane.
single-occupant vehicle (SOV) Any motor vehicle other than a motorcycle carrying one occupant.
site Parcel(s) of land bounded by a property line or a designated portion of a public right of way. (ADA
term)
slip base A mechanical base designed to allow the light standard to break away from the fixed
foundation when hit by a vehicle traveling at the design speed and traveling at a departure angle less
than or equal to the design departure angle.
slip lane A lane that separates heavy right-turn movements from the roundabout circulating traffic
(see Chapter 1320).
slip ramp A connection between legs of an intersection that allows right-turning vehicles to bypass the
intersection or a connection between an expressway and a parallel frontage road. These are often
separated by an island.
slow-moving vehicle turnout A shoulder area widened to provide room for a slow-moving vehicle to
pull out of the through traffic, allow vehicles to pass, and then return to the through lane.
speed The operations or target or posted speed of a roadway. There are three classifications of speed
established:
Low speed is considered 35 mph and below.
Intermediate speed is considered 40-45 mph.
High speed is considered 50 mph and above.
speed limit sign beacon A beacon installed with a fixed or variable speed limit sign. The preferred
display is two flashing yellow indications.
speed transition segment An engineered segment of road intended to lower the operating speed
between contexts with different target speeds.
splitter island The raised island at each two-way leg between entering and exiting vehicles, designed
primarily to control the entry and exit speeds by providing deflection. They also discourage wrong-way
movements, and provide pedestrian refuge.
state highway system All roads, streets, and highways designated as state routes in compliance with
RCW 47.17.
stopping sight distance The distance needed for a driver to stop a vehicle traveling at design speed
based on design conditions.
stop sign beacon A beacon installed above a stop sign. The display is a flashing red indication.
street furniture Sidewalk equipment or furnishings, including garbage cans, benches, parking meters,
and telephone booths. (ADA term)
streetside The portion of the public right of way dedicated to the pedestrian thoroughfare and
supporting the accessibility, activities and functions of the local land use. The streetside is comprised of
a frontage zone, pedestrian zone and furnishing zone (see Chapter 1238). Note some local agencies may
divide the streetside zone.
study area The transportation system area to study in the study process and for an ARR. The study
area is a minimum of one interchange upstream and downstream from the proposal. The study area
shall also include the intersecting roadway in the area to the extent necessary to ensure its ability to
collect and distribute traffic to and from the interchange. The study area should be expanded as
necessary to capture operational impacts of adjacent interchanges in the vicinity that are, or will be,
bottlenecks or chokepoints that influence the operations of the study interchange.
study plan A term associated with environmental procedures, this plan proposes an outline or “road
map” of the environmental process to be followed during the development of a project that requires
complex NEPA documentation (see Chapter 210 and the Environmental Manual).
subject matter expert A person who is an authority in a particular area or topic, and understands the
data and the limitations on the use and application of the data.
superelevation The rotation of the roadway cross section in such a manner as to overcome part of the
centrifugal force that acts on a vehicle traversing a curve.
superelevation runoff The length of highway needed to accomplish the change in cross slope from a
section with adverse crown removed (level) to a fully superelevated section, or vice versa.
superelevation transition length The length of highway needed to change the cross slope from normal
crown or normal pavement slope to full superelevation.
support team An integral part of the ARR process consisting of an assemblage of people from the
regions, FHWA (for Interstates), WSDOT HQ Access and Hearings, and other representatives organized
to develop and analyze alternatives to meet the need of a proposal, including approval authorities.
Surface Transportation Program (STP) A federal program established by Congress in 1991 that
provides a source of federal funding for highway and bridge projects.
tangent runout The length of highway needed to change the cross slope from normal crown to a
section with adverse crown removed (level).
target speed A proactive approach to establishing a speed consistent with the context characteristics.
Target speed is the design operating speed, which aligns design, posted and operating speed as the
same value.
temporary traffic signal A conventional traffic signal used during construction to control traffic at an
intersection while a permanent signal system is being constructed. A temporary traffic signal is typically
an inexpensive span-wire installation using timber strain poles.
tradeoffs analysis An analysis method for balancing factors, performance or outcomes, which are not
attainable at the same time.
traffic barrier A longitudinal barrier, including bridge rail or an impact attenuator, used to redirect
vehicles from fixed features located within an established Design Clear Zone, help mitigate median
crossovers, reduce the potential for errant vehicles to travel over the side of a bridge structure, or
(occasionally) protect workers, pedestrians, or bicyclists from vehicular traffic.
traffic barrier/longitudinal barrier A device oriented parallel or nearly parallel to the roadway whose
primary function is to contain or safely redirect errant vehicles away from fixed features or to
(occasionally) protect workers, pedestrians, or bicyclists from vehicular traffic. Beam guardrail, cable
barrier, bridge rail, concrete barrier, and impact attenuators are barriers, and they are categorized as
rigid, rigid anchored, unrestrained rigid, semirigid, and flexible. They can be installed as roadside or
median barriers.
traffic calming Design techniques that have been shown to reduce traffic speeds and unsafe
maneuvers. These techniques can be stand-alone or used in combination, and they include lane
narrowing, curb extensions, surface variations, and visual clues in the vertical plane. (ADA term)
traffic calming treatments Treatments along the roadway that can be used to reduce speeds through
a section of roadway (see Chapter 1103).
Traffic Impact Analysis (TIA) (sometimes called Traffic Impact Study (TIS)) If a traffic analysis is not an
ARR it is a TIA. TIAs are used for environmental reviews and developer projects (see Chapter 320).
transit A general term applied to passenger rail and bus service used by the public.
transit facility A capital facility that improves the efficiency of public transportation or encourages the
use of public transportation.
transit flyer stop A multimodal connection located within the boundaries of a limited access facility.
transition A section of barrier used to produce the gradual stiffening of a flexible or semirigid barrier
as it connects to a more rigid barrier or fixed object.
transitional segments Segments of a pedestrian circulation path that blend between existing
undisturbed pedestrian facilities and newly altered pedestrian facilities. Use of transitional segments
may permit the work of the alteration to more nearly meet the new construction standards. At a later
time, when other segments of the pedestrian circulation path are altered, the noncomplying transitional
segments can be removed and replaced with pedestrian facilities that meet the accessibility criteria.
(ADA term)
transit stop A facility for loading and unloading passengers that is set aside for the use of transit
vehicles only.
transit vehicle A bus or other motor vehicle that provides public transportation (usually operated by a
public agency).
Transportation Management Area (TMA) Urbanized areas with populations of 200,000 or greater are
federally designated as Transportation Management Areas.
transportation management plan (TMP) A set of traffic control plans, transportation operations plans,
and public information strategies for managing the work zone impacts of a project. A TMP is required for
all projects to address work zone safety and mobility impacts.
travel demand The demand travelers will make on the system based on the number and types of trips
they will take and the mode and routes they will use. Local travel demand represents short trips that
should be made on the local transportation system, such as intracity roads and streets. Regional travel
demand represents long trips that are made on the regional transportation system, such as Interstate,
regional, and/or intercity/interregional roads, streets, or highways.
traveled way The portion of the roadway intended for the movement of vehicles, exclusive of
shoulders and lanes for parking, turning, and storage for turning.
traveled way zone The portion of the roadway intended for the movement of people and goods,
exclusive of shoulders, roadsides, on-street parking, medians and streetside zones.
traveler information Commercial and noncommercial information that informs and orients the
traveling public. This includes access information for food, gas, lodging, local attractions, regional tourist
attractions, roadway conditions, and construction schedules.
traveling public Motorists, motorcyclists, bicyclists, pedestrians, and pedestrians with disabilities.
trips Short trips are normally local. Long trips are normally interstate, regional, or interregional.
truck apron The optional mountable portion of the central island of a roundabout between the raised
nontraversable area of the central island and the circulating roadway (see Chapter 1320).
turning radius The radius that the front wheel of the intersection design vehicle on the outside of the
curve travels while making a turn (see Chapter 1320).
turning roadway A curve on an open highway, a ramp, or the connecting portion of the roadway
between two intersecting legs of an intersection.
two-way left-turn lane (TWLTL) A lane, located between opposing lanes of traffic, to be used by
vehicles making left turns from either direction, from or onto the roadway.
undivided multilane A roadway with two or more through lanes in each direction on which left turns
are not controlled.
uniformity ratio The ratio of the minimum average light level on the design area to the minimum light
level of the same area (see Chapter 1040).
universal access Access for all persons regardless of ability or stature. (ADA term)
urban area An area designated by the Washington State Department of Transportation (WSDOT) in
cooperation with the Transportation Improvement Board (TIB) and Regional Transportation Planning
Organizations (RTPO), subject to the approval of the Federal Highway Administration (FHWA).
usable shoulder The width of the shoulder that can be used by a vehicle for stopping.
validation A process to confirm the reasonableness, accuracy and completeness of estimated costs
and quantities.
Value Engineering (VE) Analysis A systematic approach to identifying and removing unnecessary costs
which do not contribute to a desired result by analyzing cost versus function.
Value Engineering Change Proposal (VECP) A construction contract change proposal submitted by the
construction contractor based on a VECP provision in the contract. The intent of these types of
proposals is to (1) improve the project's performance, value, and/or quality, (2) lower construction
costs, or (3) shorten the delivery time, while considering their impacts on the project's overall life-cycle
cost and other applicable factors.
Value Engineering (VE) Job Plan A systematic and structured action plan (see Chapter 310) for
conducting and documenting the results of the VE analysis. While each VE analysis shall address each
phase in the VE Job Plan, the level of analysis conducted and effort expended for each phase should be
scaled to meet the needs of each individual project. The WSDOT VE analysis uses the Seven-Phase Job
Plan shown in Exhibit 310-1.
veiling luminance The stray light produced within the eye by light sources produces a veiling
luminance that is superimposed on the retinal image of the objects being observed. This stray light
alters the apparent brightness of an object within the visual field and the background against which it is
viewed, thereby impairing the ability of the driver to perform visual tasks. Conceptually, veiling
luminance is the light that travels directly from the luminaire to the observer’s eye.
viewpoint A roadside stopping opportunity with a view of some point of interest or area scenery. This
area is not typically separated from the traveled way by some form of highway buffer.
violation rate The total number of violators divided by the total number of vehicles on an HOV facility.
Visitor Information Center (VIC) A staffed or nonstaffed booth or separate building that displays and
dispenses free tourist travel maps and brochures. These are typically located at border-entry SRAs to
provide travel information to highway users as they enter the state.
walk interval That phase of a traffic signal cycle during which the pedestrian is to begin crossing,
typically indicated by a WALK message or the walking person symbol and its audible equivalent. (ADA
term)
walkway The continuous portion of the pedestrian access route that is connected to street crossings
by curb ramps. (ADA term)
warning beacon A beacon that supplements a warning or regulatory sign or marking. The display is a
flashing yellow indication. These beacons are not used with STOP, YIELD, or DO NOT ENTER signs or at
intersections that control two or more lanes of travel. A warning identification beacon is energized only
during those times when the warning or regulation is in effect.
warrant A minimum condition for which an action is authorized. Meeting a warrant does not attest to
the existence of a condition that needs attention. Further justification is required.
Washington Transportation Plan (WTP) A WSDOT planning document developed in coordination with
local governments, regional agencies, and private transportation providers. The WTP addresses the
future of transportation facilities owned and operated by the state as well as those the state does not
own but in which it has an interest. It identifies needed transportation investments, which are defined
by service objectives and specific desired outcomes for each transportation mode.
weaving section A length of highway over which one-way traffic streams cross by merging and
diverging maneuvers.
weigh in motion (WIM) A scale facility capable of weighing a vehicle without the vehicle stopping.
wet film thickness Thickness of a pavement marking at the time of application without beads.
work zone An area of a highway with construction, maintenance, or utility work activities. A work zone
is identified by the placement of temporary traffic control devices that may include signs, channelizing
devices, barriers, pavement markings, and/or work vehicles with warning lights. It extends from the first
warning sign or high-intensity rotating, flashing, oscillating, or strobe lights on a vehicle to the END
ROAD WORK sign or the last temporary traffic control device (MUTCD).
work zone impact Highway construction, maintenance, or utility work operations in the traveled way,
adjacent to the traveled way, or within the highway’s right of way that creates safety and mobility
concerns for workers or the traveling public.
work zone traffic control The planning, design, and preparation of contract documents for the
modification of traffic patterns due to work zone impacts.
wye (Y) connection An intersecting one-way roadway, intersecting at an angle less than 60°, in the
general form of a “Y.”
yield-at-entry The requirement that vehicles on all entry lanes yield to vehicles within the circulating
roadway.
yield point The point at which entering traffic must yield to circulating traffic before entering the
circulating roadway (see Chapter 1320).