0% found this document useful (0 votes)
191 views5 pages

110kV Substation Erection SOP

This Standard Operating Procedure (SOP) outlines the installation processes for equipment at a 110kV substation, detailing responsibilities, pre-erection activities, the erection process, and post-erection activities. It emphasizes safety protocols, quality control, and documentation to ensure compliance and effective installation. The SOP covers various equipment including transformers, circuit breakers, and control panels, providing a comprehensive guide for personnel involved in the erection process.

Uploaded by

ajishkanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
191 views5 pages

110kV Substation Erection SOP

This Standard Operating Procedure (SOP) outlines the installation processes for equipment at a 110kV substation, detailing responsibilities, pre-erection activities, the erection process, and post-erection activities. It emphasizes safety protocols, quality control, and documentation to ensure compliance and effective installation. The SOP covers various equipment including transformers, circuit breakers, and control panels, providing a comprehensive guide for personnel involved in the erection process.

Uploaded by

ajishkanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Standard Operating Procedure (SOP)

Erection of Equipment at 110kV


Substation
1. Objective
This SOP defines the detailed procedures for the installation of equipment in a 110kV
substation, ensuring safe, effective, and compliant erection processes from start to finish.

2. Scope
This SOP covers all activities involved in the erection of the following equipment at a 110kV
substation:
- Transformers (Power and Distribution)
- Circuit Breakers
- Switchgear
- Busbars
- Control and Protection Panels
- Earthing Systems
- Auxiliary Systems (Cooling, HVAC, etc.)

3. Responsibility Matrix
| **Role** | **Responsibility** |
|-------------------------|-----------------------------------------------------------------------------------|
| **Site Supervisor** | Overall supervision of the installation process, ensuring adherence
to standards. |
| **Safety Officer** | Monitor safety compliance and risk mitigation practices.
|
| **Electrical Engineer** | Provide technical guidance and supervision. |
| **Erection Crew** | Conduct physical erection of equipment as per design
specifications. |
| **Quality Control Officer** | Ensure that all installations meet quality and safety standards.
|
4. Pre-Erection Activities

4.1 Site Preparation


• Site Inspection:
- Ensure that the foundations are prepared as per design, leveled, and clear of debris.
Confirm foundation strength to accommodate the equipment’s weight.
• Power and Grounding Verification:
- Ensure electrical supply and grounding systems are complete and tested for reliability.
• Layout Verification:
- Confirm that the equipment layout aligns with the design schematic.

4.2 Material Inspection


• Equipment Delivery Check:
- Inspect all incoming equipment for any visible damages and ensure compliance with
specifications. Verify the availability of manufacturer certificates and manuals.
• Tool and Equipment Availability:
- Confirm that necessary tools, lifting equipment (cranes, forklifts), and PPE are available,
tested, and in good working condition.

4.3 Safety Preparation


• Risk Assessment:
- Conduct a site-specific risk assessment to identify potential hazards. Implement
necessary control measures.
• Safety Briefing:
- Conduct a safety briefing for all personnel, highlighting site-specific hazards and
emergency procedures.
• Lockout-Tagout (LOTO) Implementation:
- De-energize all equipment and ensure all electrical circuits are locked out before work
begins.

5. Erection Process

5.1 Lifting and Transporting Equipment


• Lifting Methodology:
- Use cranes to transport heavy equipment, ensuring that the rigging is performed
according to manufacturer specifications to avoid damage during the process.
• Positioning Equipment:
- Position the equipment accurately as per layout drawings. Verify that each unit has the
required clearance and alignment for safe operation and future maintenance.

5.2 Installation of Transformers


• Positioning and Mounting:
- Position the transformer on the foundation base, ensuring the anchor bolts are correctly
positioned. Align the equipment based on the specified design.
• Electrical Connections:
- Connect the high-voltage bushings and low-voltage bushings as per the circuit diagram,
ensuring secure and tight connections.
• Coolant Systems:
- Install the cooling system and verify that all associated pipes and valves are secure and
leak-free.

5.3 Switchgear and Circuit Breaker Installation


• Mounting and Alignment:
- Mount switchgear and circuit breakers, ensuring correct alignment with the support
structure and adequate space for ventilation.
• Connection to Busbars and Transformers:
- Connect each unit to the busbars and transformers per the schematic layout. Ensure tight
and secure connections to prevent overheating.

5.4 Busbar Installation


• Fabrication and Positioning:
- Fabricate and install busbars according to design specifications. Ensure the supports are
installed correctly to prevent movement or vibration.
• Connection Checks:
- Confirm that all busbar connections are properly aligned and securely fastened.

5.5 Control Panels Installation


• Panel Placement and Mounting:
- Install control panels in their designated locations, ensuring they are securely fastened
and accessible.
• Wiring and Testing:
- Connect control and protection wiring as per the wiring diagram. Verify that connections
are clean, properly insulated, and securely tightened.

5.6 Earthing System Installation


• Grid Layout and Assembly:
- Install the earthing system according to the design. Ensure that all earthing conductors
are correctly positioned and securely connected.
• Testing:
- Conduct earth resistance testing to ensure that all earthing systems comply with local
safety standards.
6. Post-Erection Activities

6.1 Inspection and Testing


• Mechanical Inspection:
- Conduct a thorough visual inspection to verify that all components are installed according
to specifications and that no visible damage exists.
• Electrical Tests:
- Perform insulation resistance tests on all equipment.
- Conduct continuity checks on grounding systems.
- Perform high-voltage dielectric tests where applicable.

6.2 Commissioning
• Pre-Commissioning Check:
- Verify that all mechanical and electrical systems are correctly installed. Check oil levels,
pressure, and temperature settings for transformers.
• Energization:
- Energize the equipment step-by-step, monitoring system performance, including
voltages, currents, and temperatures. Check protection relays and control circuits for
proper operation.
• System Integration:
- Test the synchronization and communication between all components (e.g., breakers,
transformers, control panels) and verify interlocking systems.
• Final Commissioning Report:
- Document all test results, highlighting any issues and the corrective actions taken.
Provide the necessary documentation for client or regulatory approval.

7. Safety Protocols
• Personal Protective Equipment (PPE):
- All personnel must wear the following PPE:
- Hard hats
- Safety gloves
- Insulated boots
- Face shields (when working with live equipment)
- High-visibility vests
• Emergency Procedures:
- All workers must be trained in emergency evacuation and first aid procedures,
particularly for electrical incidents. Ensure fire extinguishers and first aid kits are readily
available.
• Worksite Safety Barriers:
- Install barriers to restrict unauthorized access to high-voltage areas and prevent
accidents.
8. Quality Control and Documentation
• Quality Assurance Checks:
- Conduct in-progress checks for alignment, tightness of connections, cleanliness, and
general workmanship. All deviations from the standard should be documented and
corrected.
• Final Inspection:
- Perform a final inspection to ensure that all equipment is correctly installed, aligned, and
operational. Cross-check with design drawings and manufacturers’ guidelines.
• Documentation:
- Maintain a complete record of the installation process, including inspection reports, test
results, and commissioning data.

9. References
• IEC 61850 – Communication Networks and Systems for Power Utility Automation
• ANSI C37 – American National Standards for Switchgear
• IEEE Std 80 – Guide for Safety in AC Substation Grounding
• Local Electrical Safety Codes and Standards

You might also like