15 Rural Development 15
15 Rural Development 15
RURAL DEVELOPMENT
15 (2010-2011)
FIFTEENTH REPORT
lR;eso t;rs
STANDING COMMITTEE ON
RURAL DEVELOPMENT
(2010-2011)
lR;eso t;rs
INTRODUCTION........................................................................................... (v)
CHAPTER I Report............................................................................... 1
ANNEXURES
APPENDICES
MEMBERS
Lok Sabha
(iii)
Rajya Sabha
SECRETARIAT
1. Shri Brahm Dutt — Joint Secretary
2. Shri Shiv Singh — Director
3. Shri A.K. Shah — Additional Director
4. Shri Sumesh Kumar — Executive Officer
(iv)
INTRODUCTION
3. The replies of the Government were examined and the Draft Report
was considered and adopted by the Committee at their sitting held on
7 February, 2011.
(v)
CHAPTER I
REPORT
A. Unspent Balance
2
6. The Ministry in their Action Taken Reply have stated as under:—
2010-11 2091.67 * NA
“As may be seen in the table above, the utilization reported is to the
extent of 98.02% of the funds sanctioned during 2007-08 and 92.02%
in respect of funds sanctioned during 2008-09. In respect of grants
sanctioned during 2009-10, the UCs are due by 31.03.2011 as provided
under the GFR. However, States are at liberty to submit UCs even
before that date. Accordingly, MoPR has so far received UCs worth
Rs. 2035.97 crore which works out to 57.6% of the funds sanctioned
during 2009-10.
It is true that the Ministry of Finance (MoF) had reduced the allocation
for BRGF under 2009-10 owing to slow pace of expenditure during the
first half of the financial year. In fact, MoF had indicated its inclination
to cut the allocation by as much as Rs. 2000 crore owing to slow pace
of expenditure. However, after the Ministry informed the MoF about
the reasons for the slow pace of the expenditure in the initial months,
which was mainly due to the General Elections to the Lok Sabha that
were held in May, 2009, and also showed the improved pace of releases
from October, 2009 onwards, the Ministry of Finance reduced the cut
3
by Rs.1000 crore. Finally, the allocation for the Ministry as a whole
was reduced by Rs.1000 crore, which was reflected entirely in the
BRGF.
However, the releases to States under BRGF are incumbent upon receipt
of annual plans, utilization certificates, audit reports and progress
reports. Some States delay in submission of one or more of these
documents, which leads to delay in release of their entitlements by the
Ministry. As stated above, owing to the sustained efforts of the Ministry,
the pace of sanctions has improved during 2010-11. However, the
Ministry is still finding it difficult to procure the relevant documents
from five States, namely, Assam, J&K, Meghalaya, Tamil Nadu and
Uttarakhand. In respect of Assam, J&K, Meghalaya and Tamil Nadu,
the documents mentioned before have not been received in full whereas
in respect of Uttarakhand the DPCs have not been constituted. The
Ministry has constantly been reminding these States for taking the
suitable action to facilitate release of funds. In respect of other States,
the situation is well under control. Owing to the sustained efforts of
the Ministry, during 2010-11 sanctions under BRGF as on 31.08.2010
have been of the order of Rs. 2091.67 crore, which is about 41.42%
of the annual allocation under BRGF and is in line with the fund flow
expected under the CMS.”
4
B. Role of Gram Sabha and holding their meetings four times in a year
“The States and UTs were sensitized vide Circulars dated 2.10.2009
about the importance of activating Gram Sabhas, Mahila Sabhas,
Ward Sabhas etc. It was also indicated that the good practices that
provide for people’s assemblies below the Gram Sabha such as
Ward Sabhas, Mahila Sabhas and Bal Sabhas should be promoted
and the Ward Sabhas etc. need to meet before the Gram Sabha
meetings. In this context “Monitoring Format for Gram Sabhas”
was also circulated to the States/UTs in which General Information
5
about the Village Panchayat and also the details about functioning,
meetings etc., of Gram Sabha could be incorporated. To ascertain
the position about the activities undertaken by the States/UTs in this
behalf, all States/UTs have been requested to intimate the position
and also indicate the reasons for not holding the meetings of the
Mahila Sabhas before the meeting of the Gram Sabhas in the
concerned cases.”
6
Ministry of Panchayati Raj is still maintaining the information in
this regard which was last collected during 2007-08. While
expressing their dissatisfaction over the way in which the Ministry
of Panchayati Raj is maintaining the information on number of
District Panchayats, Intermediate Panchayats, Village Panchayats
and number of villages in the country, the Committee, strongly
recommend that the Ministry should always maintain the updated
information in this regard with them.”
12. The Ministry in their Action Taken reply have stated as under:—
7
for online uploading of the latest information on this online
directory.”
8
therefore, recommend that the Ministry should obtain the latest
information regarding number of Panchayat Ghars in all States and
Union territories and inform them accordingly. The Ministry may
also in consultation with other Ministries draw up a Plan under
which Panchayat Ghars for all the Panchayats can be constructed
by pooling resources of different Centrally Sponsored and Central
Sector Schemes together in a time bound manner. In view of the
proposed 50 per cent reservation to women in Panchayati Raj
Institutions at three levels and the fact that such reservation for
women has already been made in States like Bihar, Chhattisgarh,
Himachal Pradesh, Kerala, Madhya Pradesh, Rajasthan and
Uttarakhand, it should also be ensured that the Panchayat Ghars
have the provision for office space and basic amenities like toilets
etc.”
15. The Ministry in their Action Taken reply have stated as under:—
16. The Committee have been informed by the Ministry that they
had issued a Circular encouraging the State Governments to avail funds
available under BRGF and RGSY schemes to construct Panchayat
buildings on priority basis. The Committee strongly feel that merely
issuing Circular would not serve the purpose. The Committee fail to
understand as to how the progress would be monitored by the Ministry
in the absence of latest information regarding number of Panchayat
9
Ghars in all States and Union Territories. Needless to say that capacity
building of Panchayati Raj Institutions cannot be made in the absence
of Panchayat Ghars. They, therefore, reiterate that the construction of
Panchayat Ghars be given top priority and compilation of latest
information regarding number of Panchayat Ghars be done at the
earliest.
18. The Ministry in their Action Taken reply have stated as under:—
“The States and UTs were sensitized vide circulars dated 2.10.2009
about the importance of activating Gram Sabhas, Mahila Sabhas,
Ward Sabhas etc. It was also indicated that the good practices that
provide for people’s assemblies below the Gram Sabha such as
Ward Sabhas, Mahila Sabhas and Bal Sabhas should be promoted
and the Ward Sabhas etc. need to meet before the Gram Sabha
meetings. In this context “Monitoring Format for Gram Sabhas”
was also circulated to the States/UTs in which General Information
10
about the Village Panchayat and also the details about functioning,
meetings etc. of Gram Sabha could be incorporated. To ascertain
the position about the activities undertaken by the States/UTs in this
behalf, all States/UTs have been requested to intimate the position
and also indicate the reasons for not holding the meetings of the
Mahila Sabhas before the meeting of the Gram Sabhas in the
concerned cases.”
21. The Ministry in their Action Taken reply have stated as under:—
11
on release and utilisation of Grant, Ministry of Finance has already
released the first instalment of Basic Grant for PRIs amounting to
Rs. 2821.72 crore. In addition, an amount of Rs. 79.90 crore has
also been released under ‘Special Area Basic Grant’ for the
Schedule V & VI areas and areas where Part IX and IXA do not
apply. Share of Basic Grant has not been released to Jharkhand
and J&K due to non-existence of elected Panchayats in these
States.”
12
24. The Ministry in their Action Taken reply have stated as under:—
13
has submitted its First report in early July 2010. Recommendations
of the Committee and response of MoPR is at Annex-9.
This Committee met in July 2010 to discuss the draft TOR for the
study. The institutions/ agencies to conduct the evaluation are being
identified to conduct study.
Evaluation of RGSY:
14
capacity of Panchayati Raj Institutions (PRIs). In many Panchayats,
the members have begun to understand the complexities of their
responsibilities thereby regular training will assist them in fulfilling
the aspirations of their constituencies. According to the findings of
report the impact of training was multi-dimensional viz.; solving
local problems through participatory decision making, responsive
handling of public grievance, equipping participants with
operational skills required for day-to-day performance of
functions devolved to Panchayats, understating the planning and
implementation aspects of rural development programmes more
clearly. The training programmes have made a significant impact
in terms of awareness and sensitization over the Elected Women
Representatives. The agency recommended/ suggested that Scheme
should not merely be confined to training programmes, but should
also include the components like improving infrastructure at
Panchayat level, IT interventions, monitoring and evaluation of
programme. The training strategy should be a composite mix of
various interventions like interactive satellite training, face to face
training, networking, community mobilisation, Panchayati Raj TV
Channel. The first and initial training should be provided to the
newly elected representatives within 2-3 months of their election.
Subsequently, every year there should be a follow up on training
of PRIs. Duration of training for 1-2 days is not sufficient
for effective implementation of programme. Hence, the
report recommended 3-4 days of training programme. It also
recommended that the content of training and processes of training
programme should be relevant to the ground reality.
M/s CTREE had submitted State-wise reports. They have also given
some common suggestions for improving the training programme.
Some of these suggestions are:
15
• Separate and easy to understand training modules be designed
for illiterate elected representatives, as the expected benefits
were not seen reflected among them.
16
RGSY Scheme in the first year of 11th Five Year Plan. The duration
of training programme has been kept for a period of 03 days of
elected representatives of PRIs and 05 days for Central and State
level functionaries. In order to augment the training infrastructure,
this Ministry has provided financial assistance to States for
establishment of distance learning facility via satellite. Further, the
financial assistance was provided to establish training institutes and
resource centres in respect of the Hilly States and States of North
East Region. The provision of reimbursing the travel expense on
actual Rail/Bus fare was made for the elected representatives only
in the guidelines of RGSY Scheme.
17
while appreciating recent efforts of the Ministry for concurrent
evaluation of the BRGF and RGSY Schemes would also like the Ministry
to initiate similar evaluation of other schemes such as PMEYSA, RBH
etc. They also like to be apprised of the findings of the evaluation study
of BRGF and RGSY Schemes.
H. Performance of BRGF
27. The Ministry in their Action Taken reply have stated as under:—
18
of the Planning Commission. However, in April 2010 the Planning
Commission had informed that though there was no budget
allocation for the scheme in 2010-11, yet the scheme would be
better handled by the MoPR. Accordingly the MoPR has submitted
an EFC Memorandum to the Ministry of Finance on 12.08.2010
on the Scheme for Support to Planning Process at National, State,
District and Sub-District Levels. The Ministry has examined the
proposal to transfer a part of the Capacity Building grants to the
ZPs for using it as per their perceived requirements and found it
difficult do so for the following reasons:
19
levels as proposed by Planning Commission. The Ministry have further
stated about opposition of States (except for Andhra Pradesh) on the
proposal for transfer of Capacity Building funds to the District
by-passing the State Government and nature of BRGF as additional
Central assistance to the State plans. The Committee would like to
mention that they have never recommended transfer of funds to the
Districts by-passing the States. What the Committee had desired was
to define the precise role of District Planning Committees and High
Powered Committees. The Committee would also like to be apprised of
salient features of proposal of the Ministry on the Scheme for support
to the planning process at National, State, District and Sub-District
levels.
20
CHAPTER II
21
Recommendation (Serial No. 2, Para No. 3.9)
The Committee are disturbed to note that huge unspent balances of
Rs. 5062.77 crore as on 28.02.2010 were left with the implementing agencies
in six different schemes being implemented by the Ministry. The unspent
balance for six other schemes is not available with the Ministry which shows
lack of sufficient monitoring of the releases made by them. Not only the total
unspent balance in six different schemes equals the budgetary allocation of
the Ministry in 2010-11 BE. They feel, instead of ensuring that the amount
is spent for the purpose it has been sanctioned in the budget, the Government
is mindlessly releasing the funds for the implementing agencies at the fag
end of the year and have become a mute spectator for the huge unspent
balances. The Committee strongly feel that there is need for planned outflow
of funds throughout the year with proper monitoring of expenditure. They
apprehend that such a practice might have been the reason for the revised
estimate 2009-10 of the Ministry being reduced by Rs. 1000 crore. The
Committee while expressing serious concern over the trend of huge unspent
balance would like to strongly recommend that the Government should
analyse the position State and Union territory-wise and take suitable
corrective measures accordingly so that funds flow to the States in time. The
Committee should also be kept apprised of the follow-up action taken in this
regard.
Reply of the Government
Sanctions and utilization reported (as on 31.08.2010), are given in the
table below:
Amount in Rs. Crore
2010-11 2091.67 * NA
22
As may be seen in the table above, the utilization reported is to the
extent of 98.02% of the funds sanctioned during 2007-08 and 92.02% in
respect of funds sanctioned during 2008-09. In respect of grants sanctioned
during 2009-10, the UCs are due by 31.03.2011 as provided under the GFR.
However, States are at liberty to submit UCs even before that date.
Accordingly, MoPR has so far received UCs worth Rs. 2035.97 crore which
works out to 57.6% of the funds sanctioned during 2009-10.
It is true that the Ministry of Finance (MoF) had reduced the allocation
for BRGF under 2009-10 owing to slow pace of expenditure during the first
half of the financial year. In fact, MoF had indicated its inclination to cut
the allocation by as much as Rs. 2000 crore owing to slow pace of
expenditure. However, after the Ministry informed the MoF about the reasons
for the slow pace of the expenditure in the initial months, which was mainly
due to the General Elections to the Lok Sabha that were held in May 2009,
and also showed the improved pace of releases from October 2009 onwards,
the Ministry of Finance reduced the cut by Rs. 1000 crore. Finally, the
allocation for the Ministry as a whole was reduced by Rs. 1000 crore, which
was reflected entirely in the BRGF.
However, the releases to States under BRGF are incumbent upon receipt
of annual plans, utilization certificates, audit reports and progress reports.
Some States delay in submission of one or more of these documents, which
leads to delay in release of their entitlements by the Ministry. As stated above,
owing to the sustained efforts of the Ministry, the pace of sanctions has
improved during 2010-11. However, the Ministry is still finding it difficult
to procure the relevant documents from five States, namely, Assam, J&K,
Meghalaya, Tamil Nadu and Uttarakhand. In respect of Assam, J&K,
Meghalaya and Tamil Nadu, the documents mentioned before have not been
received in full whereas in respect of Uttarakhand the DPCs have not been
23
constituted. The Ministry has constantly been reminding these States for
taking the suitable action to facilitate release of funds. In respect of other
States, the situation is well under control. Owing to the sustained efforts of
the Ministry, during 2010-11 sanctions under BRGF as on 31.08.2010 have
been of the order of Rs. 2091.67 crore, which is about 41.42% of the annual
allocation under BRGF and is in line with the fund flow expected under the
CMS.
The Committee are not at all happy with the financial practices of the
Ministry since its inception in May, 2004. They find that between 2004-05
and 2008-09, Rs. 3715.81 crore was surrendered as compared to the budget
estimates. Not only that, total funds amounting to Rs. 97.35 crore have also
been re-appropriated between 2006-07 and 2009-10, which is not a standard
financial practice. Another disturbing feature is that the Ministry has never
achieved the monthly expenditure plan since 2007-08, the information about
which has been made available to the Committee. The monitoring mechanism
of the Ministry is also found to be not having adequate information with
regard to proper monitoring of funds released to the various State
Governments, Union territory administrations and the Panchayats at different
levels. The Committee, therefore, recommend suitable corrective measures
may be initiated in each of the aforesaid matters and they be apprised
accordingly.
24
the Planning Commission in August-September, 2006 and the
Prime Minister launched the Programme at Barpeta (Assam) in
February, 2007. Consequently there was less expenditure and substantial
reduction at RE stage. In 2007-08 and 2008-09, some States did not have
District Planning Committees (DPCs) for consolidation of local plans into
District Plans, which is a necessary condition for release of Development
Grants under BRGF.
(i) States have been advised to submit their Action Plans latest during
the first quarter of 2010-11;
(ii) States have been advised to enter the Progress Reports online on
Plan Plus;
(iii) State Level Workshops have been convened to discuss the progress
of previous years and Annual Plans of the current year;
These efforts have improved the pace of funds release during 2010-11.
As on 12-08-2010 the Ministry has sanctioned Rs. 1641.74 crore.
25
a formality to re-appropriate the funds from non-functional heads to the
function heads. The detail is as under:—
26
Recommendation (Serial No. 4, Para No. 3.17)
The Constitution (73rd Amendment) Act, 1992 came into effect from
1992 and the Ministry of Panchayati Raj was made a separate Ministry in
2004. The Committee feel that in order to give fillip to the upliftment of
Panchayati Raj Institutions in the country, the allocation for the Ministry of
Panchayati Raj which is a little above Rs. 5000 crore during 2010-11 BE is
too little. Notwithstanding the poor performance and monitoring of
implementation of the schemes by the Ministry of Panchayati Raj, the
Committee feel that attention to the desired extent has not been paid by the
Planning Commission for upliftment of Panchayats at all the three levels as
reflected in the meager allocation to the said Ministry year after year. In order
to implement the historic legislation of the Constitution (73rd Amendment)
Act, 1992 in it’s letter and spirit, they recommend strongly that this concern
of the Committee be taken up at the highest level so as to have the allocation
of the Ministry in the coming years substantially increased.
27
measures in this regard. They, therefore, recommend that the defaulter States
may be impressed upon to adhere to the provisions of Part IX of the
Constitution without any further delay. Action taken in this regard may be
intimated to the Committee.
J&K Government have its own Panchayat Raj Act, but due to
unavoidable circumstances election could not be held in the State.
28
Panchayats as envisaged in Article 243G of the Constitution read with its
Eleventh Schedule. Detailed guidelines were issued vide letter No. N-11019/
681/08-Pol. dated 19.1.2009 (Copy enclosed at Annex-1) to the Central
Ministries and the States/UTs to amend their scheme guidelines. For
devolution of 3Fs through activity mapping also, guidelines were issued vide
letter No.-N-11011/59/2006-Pol.-I(Pt.) dated 1.12.2009 (copy enclosed at
Annex-2). Guidelines on [Panchayat Finances, and Manpower for Panchayati
Raj Institution were also issued to States/UTs vide letter No.M-11011/16/
2009-P&C(AR) dated 9.4.2009 and No.M-11011/162/2008-P&C(AR) dated
23.10.2009] (copies enclosed at Annex-3 & 4).
The report on Devolution Index (DI) for the year 2009-10 was
received from IIPA. Incentive funds were released to the following qualified
States:—
29
from the reply of the Ministry that the major violations in these States relate
to the aspects of minor forest produce, village market and money lending.
They regret to point out that even after knowing this state of affairs, the
Ministry is yet to initiate any concrete measures. The Committee, therefore,
recommend that the defaulter States may be impressed upon to implement
the provisions of the PESA, 1996 without further loss of time and the
Committee be apprised accordingly.
3. A meeting was held on 5th July, 2010 with PESA States and
Central Ministries concerned to further impress the need for
implementation of PESA and speed up its implementation.
30
Functions, Functionaries and Finances (3Fs) is one of the main backbone of
the grassroots planning process which is also in conformity with the
provisions of article 243ZD of Part-IXA of the Constitution. They find
that the Ministry of Panchayati Raj has so far not been able to impress
upon the States and Union territories to constitute and functionalize
District Planning Committees (DPCs) in all districts of the country. They,
therefore, urge the Ministry to vigorously persuade all the States and Union
territories to immediately constitute and functionalize the DPCs without any
further delay. For this purpose, the Ministry may consider linking the
formation of DPCs with the release of funds of different schemes, so that
the States and Union territories may be impressed upon to constitute these
Committees.
At Present, funds under the scheme of BRGF are not provided to the
States where DPCs have not been constituted.
The Committee note with concern that out of 180 Centrally Sponsored
Schemes and over 800 Central Sector Schemes being implemented by
various Ministries/Departments of the Government of India, the activity
mapping showing the centrality of Panchayats has been made in the
guidelines relating to only 28 schemes as on date. Interestingly, the
Committee have found that even though the Ministry of Panchayati Raj is
implementing 9 different Centrally Sponsored/Central Sector Schemes, the
centrality of Panchayats has not been made available for the schemes being
implemented by the Ministry themselves. Further, since only in respect of
31
28 schemes the centrality of Panchayats has been mentioned by 8 different
Ministries/Departments of the Government of India, it is evident that a
gigantic task still lies before all the Ministries if they aim to provide such
facilities in each of the Centrally Sponsored/Central Sector schemes. They,
therefore, urge the Ministry of Panchayati Raj to initiate measures at the
highest level in consultation with the Planning Commission/Ministry of
Finance and Cabinet Secretariat, so that the centrality of the Panchayats can
be established in all the Centrally Sponsored and Central Sector Schemes
within a stipulated time period. They also recommend that to begin with the
Ministry of Panchayati Raj should first of all clearly demarcate the role of
each tier of Panchayats in all the schemes being administered by them within
a month.
The directions given by the Committee have been noted for compliance.
In fact, MoPR has already requested Cabinet Secretariat to revive the Review
Committee, which may have dialogue with the Ministries/Departments
administering CSSs/ACAs. The Committee will be apprised of further action
taken in this regard.
32
Reply of the Government
It is stated that the consultations had been held with the concerned
representatives of States/UTs about the various aspects of the implementation
of Panchayat Mahila Evam Yuva Shakti Abhiyan (PMEYSA) inter-alia the
bottlenecks that impede the smooth implementation of this programme in
achieving the desired results. Various measures are under consideration
including the review of the issues relating to the women empowerment and
for giving a fillip to the capacity building and training of elected women
representatives.
33
Recommendation (Serial No. 16, Paragraph No. 4.78)
34
existence. They feel continuance of implementation of schemes from one plan
to the other without finding out its real impact and benefits through the system
of independent and impartial concurrent evaluation is not a sign of good
governance. They, therefore, recommend that the Ministry should ensure that
each of the schemes being implemented by it is evaluated concurrently during
the Eleventh Five Year Plan itself.
Thereafter, the Ministry had approached the World Bank for under-
taking an independent review cum evaluation of the BRGF. Accordingly a
World Bank Mission was sent to eight key States in July 2009 for evaluating
the implementation of the programme in two districts of each of these States.
The Mission has submitted their report in March 2010. The Ministry has taken
several actions with respect to the recommendations of the Mission and also
forwarded the Report to the States for taking necessary action.
35
(e) Need for modification in the objective and design of BRGF
including the Block as Unit for BRGF funding.
This Committee met in July 2010 to discuss the draft TOR for the study.
The institutions/agencies to conduct the evaluation are being identified to
conduct study.
Evaluation of RGSY:
36
interventions on a sustainable basis are essential to comprehensively build
the capacity of Panchayati Raj Institutions (PRIs). In many Panchayats, the
members have begun to understand the complexities of their responsibilities
thereby regular training will assist them in fulfilling the aspirations of their
constituencies. According to the findings of report the impact of training was
multi-dimensional viz; solving local problems through participatory decision
making, responsive handling of public grievance, equipping participants with
operational skills required for day-to-day performance of functions devolved
to Panchayats, understating the planning and implementation aspects of rural
development programmes more clearly. The training programmes have made
a significant impact in terms of awareness and sensitization over the Elected
Women Representatives. The agency recommended/suggested that Scheme
should not merely be confined to training programmes, but should also
include the components like improving infrastructure at Panchayat level, IT
interventions, monitoring and evaluation of programme. The training strategy
should be a composite mix of various interventions like interactive satellite
training, face to face training, networking, community mobilisation, Panchayati
Raj TV Channel. The first and initial training should be provided to the newly
elected representatives within 2-3 months of their election. Subsequently,
every year there should be a follow up on training of PRIs. Duration of
training for 1-2 days is not sufficient for effective implementation of
programme. Hence, the report recommended 3-4 days of training programme.
It also recommended that the content of training and processes of training
programme should be relevant to the ground reality.
M/s CTREE had submitted State-wise reports. They have also given
some common suggestions for improving the training programme. Some of
these suggestions are:—
37
• Experienced and former Panchayati Raj Representatives should be
involved as trainers in a greater way besides the conventional
trainers.
38
of reimbursing the travel expense on actual Rail/Bus fare was made for the
elected representatives only in the guidelines of RGSY Scheme.
The Committee also find that the Ministry has not been able to adhere
to the monthly expenditure plan under BRGF since inception of the scheme
in 2005-06. They apprehend that this might have been one of the reasons for
the reduction in the revised estimates for the BRGF over that of the budget
estimates during the preceding years. They, therefore, recommend that
suitable corrective measures in the implementation of BRGF may be initiated
this year and the Committee may be apprised accordingly.
This point is amply covered in the response to Paras 3.9 and 3.16.
39
of DPCs may be strengthened. The Ministry may consider empowering the
States to allow PRIs to choose the service that is most useful for them under
the capacity building component.
The Ministry has already advised the State Governments on the role the
DPCs and HPCs should perform (a copy of the circular dated 07.10.2009
in this regard is placed at Annex-12).
40
Comments of the Committee
The Committee note with concern that only Rs. 85 lakh has been
released by the Ministry during 2009-10 so far out of the budget estimates
of Rs. 3.60 crore for the Panchayat Mahila Evam Yuva Shakti Abhiyan
(PMEYSA) which reflects poor financial achievement of the scheme by the
Ministry in different States and Union territories. They also find that non-
availability of proper training institutes in various parts of the country may
be a hindrance for implementing this scheme. They also note that the Ministry
is not utilizing the services of reputed NGOs and the training institutes of
Government of India. While recommending for retrospection by the Ministry
for better implementation of this scheme, the Committee recommend that the
Ministry may consider involving reputed training institutes of Government
of India like the National Institute of Public Cooperation and Child
Development (NIPCCD) and reputed NGOs in different States for training
the functionaries and office bearers of different Panchayati Raj Institutions.
The actual expenditure under the scheme of PMEYSA during the year
2009-10 is Rs. 2.40 crore. The performance of the scheme was reviewed
by the Secretary, Panchayati Raj in a meeting held on 10.3.2010 with the
representatives of State Governments, Conveners PMEYSA and Nodal
Agencies and communications have been issued to them for taking suitable
action on various aspects of PMEYSA including the Capacity Building and
training of Elected Women Representatives (EWRs).
The Committee note with concern that during 2009-10 the utilisation
of funds meant for the training and capacity building component of the
41
Rashtriya Gram Swaraj Yojana (RGSY) has not been satisfactory as they were
informed that only 69 per cent of the funds have been released under the
Yojana so far and only 1.37 lakh elected representatives and functionaries
of Panchayati Raj Institutions (PRIs) have been trained by States and NGOs
upto 31 December, 2009 i.e. 14.29 per cent of the physical targets for
providing training to Elected Representatives and officials has been achieved
till December, 2009. The Committee feel that even though there is a larger
need for training and capacity building the Ministry has not been able to
successfully release the funds to the implementing agencies at the first
instance, resulting in poor financial achievement. The Committee, therefore,
recommend that suitable corrective measures for better performance of the
scheme may be initiated and the Committee be apprised accordingly.
The figures for numbers of ERs of PRIs trained are provided by the
Implementing Agencies generally with a time lag since training programmes
are conducted in most of the States in decentralized manner at various levels.
The Ministry has sought to correct this practice by introducing a system of
online reporting of progress wherein the data regarding Physical/Financial
progress of the scheme would be uploaded by the Implementing Agencies
themselves which would be available to the Ministry for monitoring as well
as to general public for viewing. The system has been started but would take
some time for stabilizing.
Efforts are also being made to make the system of release of funds
to the Implementing Agencies more effective. During 2010-11, as on
18-08-2010, Rs. 27.05 crore, i.e. 54.11% of the allocation has been released,
out of which Rs. 18.30 crore is under Training Component and Rs. 8.75 crore
is under Infrastructure Development Component.
42
as per the report received in respect of 28 States and 2 UTs. During current
year, 42253 Elected Representatives have been trained upto July, 2010 as
reported by 12 States. Information is being collected from all the States.
The Committee note the reply of the Ministry that only seven States
have been covered under RGSY and no gender specific data is being
maintained for this scheme. The Committee recommend that gender specific
information of beneficiaries in each of the States and Union territories along
with the information on beneficiaries of the weaker sections may be given
in the next Outcome Budget of the Ministry.
43
compile gender specific information of beneficiaries as also information on
beneficiaries of weaker sections. As on 12.08.2010, it has been reported by
9 States that 10794 numbers of Women ERs and 17195 ERs from weaker
sections (SC/ST/OBC) have been covered in the training programmes.
44
that before a decision is taken on the said three themes, the Ministry should
wait and request the concerned organization to submit the report in order to
avoid the duplication of work. In addition to these 19 themes, 4 more studies
were sanctioned based on the needs of the concerned divisions of this
Ministry.
45
CHAPTER III
46
Recommendation (Serial No. 20, Paragraph No. 5.16)
47
Under the capacity building component of BRGF, the Ministry releases
funds to the States who in turn transfer the same to the nodal agencies
(usually, the SIRDs) for implementation of training programmes and
provision of training infrastructure. The Ministry had earlier set the target
of covering all the elected representatives of PRIs for at least one training
course during their five year tenure. For 2010-11 MoPR has advised the
States to provide at least one training of 3 days duration to each elected
representatives of the PRIs. The Ministry in this regard has also advised the
States for availing/pooling resources available under various schemes such
as the Capacity Building Component of BRGF, Rashtriya Gram Swaraj
Yojana (RGSY), MGNREGS, etc.
The Committee also observe that one of the reasons for slower
implementation of the programme as admitted by the Ministry is delayed
transfer of funds from the State Governments to the implementing entities,
e.g. Panchayats. They also note that the Ministry has invoked provision of
charging penal interest from the State Governments for cases of delayed
transfer of Grants from States to the Panchayats. The Committee find that
the Ministry of Panchayati Raj has not fixed responsibility themselves for
delay in releasing of grants.
The Committee also note that at present the Ministry displays district-
wise entitlement under BRGF in advance whereas the State Governments
have been given the task to inform the Panchayati Raj Institutions about their
48
entitlement during the financial year. They also note that as per the guidelines
of the scheme the State Government should indicate the normative formula
for the allocation of BRGF funds to each PRIs. The Committee find that this
is not being done in most of the cases rendering the system to be ineffective
from the point of view of the Panchayats. They are of the opinion that Ministry
of Panchayati Raj can obtain the normative formula from the respective State
Governments and place the allocation of each Panchayat on their website at
the beginning of the financial year. Action taken in this regard may please
be intimated to the Committee at the earliest.
49
CHAPTER IV
The Committee note that the Capacity Building and Training of Elected
Representatives is one of the important aspects of the Panchayati Raj system
in the country. They are surprised to find that the Ministry of Panchayati Raj
do not have information even about the number of Panchayat Ghar buildings
in the States of Arunachal Pradesh, Jammu & Kashmir, Meghalaya, Mizoram,
Nagaland, Uttarakhand and in all Union territories of the country except Delhi
and Chandigarh as on date. The Committee also cannot understand how in
the absence of such basic information as also information regarding
availability of electricity in the Panchayat Ghar/Office/Bhawans, the Ministry
ambitiously plans for computer connectivity to Panchayats. The Committee,
therefore, recommend that the Ministry should obtain the latest information
regarding number of Panchayat Ghars in all States and Union territories and
inform them accordingly. The Ministry may also in consultation with other
Ministries draw up a Plan under which Panchayat Ghars for all the Panchayats
can be constructed by pooling resources of different Centrally Sponsored and
Central Sector Schemes together in a time bound manner. In view of the
proposed 50 per cent reservation to women in Panchayati Raj Institutions at
three levels and the fact that such reservation for women has already been
made in States like Bihar, Chhattisgarh, Himachal Pradesh, Kerala, Madhya
Pradesh, Rajasthan and Uttarakhand, it should also be ensured that the
Panchayat Ghars have the provision for office space and basic amenities like
toilets etc.
50
available sources including MGNREGS, BRGF and RGSY. A circular dated
21st January, 2010 has been issued in this regard (copy at Annexure-6).
MoRD has also included construction of Panchayat Ghars as eligible item
of work under the MGNREGS.
51
CHAPTER V
The Committee note with concern that the Ministry of Panchayati Raj
does not have requisite information regarding holding of four Gram Sabha
meetings in a year or holding of Mahila Sabha and Ward Sabha meetings in
the different States and Union Territories across the country. Maharashtra is
the only State which has reported organizing Mahila Sabha meetings before
Gram Sabha meeting. Information in this respect is yet to be collected from
other States/Union Territories. The Committee feel that by merely circulating
a circular on 2.10.2009 regarding holding of the regular Gram Sabha
meetings and declaring 2009-10 as the ‘Year of Gram Sabha’ does not
complete the enormous task entrusted to the Ministry of Panchayati Raj.
The Committee, therefore, urge the Ministry to find out the details of
holding of Gram Sabha, Mahila Sabha and Ward Sabha meetings in all
States and Union Territories without any further delay. They also desire the
Ministry to circulate a model format regarding conduct of Gram Sabha
meetings to each Gram Panchayat in the country and inform the Committee
accordingly.
The States and UTs were sensitized vide circulars dated 2.10.2009 about
the importance of activating Gram Sabhas, Mahila Sabhas, Ward Sabhas etc.
It was also indicated that the good practices that provide for people’s
assemblies below the Gram Sabha such as Ward Sabhas, Mahila Sabhas and
Bal Sabhas should be promoted and the Ward Sabhas etc. need to meet before
the Gram Sabha meetings. In this context “Monitoring Format for Gram
Sabhas” was also circulated to the States/UTs in which General Information
about the Village Panchayat and also the details about functioning, meetings
etc., of Gram Sabha could be incorporated. To ascertain the position about
52
the activities undertaken by the States/UTs in this behalf, all States/UTs have
been requested to intimate the position and also indicate the reasons for not
holding the meetings of the Mahila Sabhas before the meeting of the Gram
Sabhas in the concerned cases.
In this regard, requisite information has been received only from 18 out
of 25 States and 5 out of 6 UTs so far. Details from the remaining 7 States
(Assam, Gujarat, Jammu & Kashmir, Orissa, Rajasthan, Tamil Nadu and Goa)
and 1 UT (Dadra & Nagar Haveli) are yet to be received.
53
The Ministry of Panchayati Raj has developed an online facility viz.
National Panchayat Directory, which is part of National Panchayat Portal,
where States can feed and update the information (such as name, parent local
body, constituent villages etc.) relating to Panchayats at different tiers. With
a view to ensure availability of updated information, an advisory has also been
issued to States/UTs for online uploading of the latest information on this
online directory.
The Committee observe that the Ministry of Panchayati Raj do not have
information on constitution and functioning of Ward Sabhas and Mahila
Sabhas in different Panchayats. They also note that except in Jharkhand,
Pudducherry and Tripura, Standing Committees of Gram Panchayats are
reportedly constituted. The Committee find that only in Maharashtra,
Mahila Sabhas precede the Gram Sabha meetings. Therefore, the reason for
not holding the Mahila Sabha meeting before the Gram Sabha may be
obtained from the States other than Maharashtra and all Union Territories
expeditiously and the Committee be informed accordingly. The Committee
would like the Ministry to collect the detailed information immediately as
is the case in each State and Union Territory and inform them accordingly.
The States and UTs were sensitized vide circulars dated 2.10.2009 about
the importance of activating Gram Sabhas, Mahila Sabhas, Ward Sabhas etc.
It was also indicated that the good practices that provide for people’s
assemblies below the Gram Sabha such as Ward Sabhas, Mahila Sabhas and
Bal Sabhas should be promoted and the Ward Sabhas etc., need to meet before
the Gram Sabha meetings. In this context “Monitoring Format for Gram
Sabhas” was also circulated to the States/UTs in which General Information
about the Village Panchayat and also the details about functioning, meetings
etc., of Gram Sabha could be incorporated. To ascertain the position about
the activities undertaken by the States/UTs in this behalf all States/UTs have
been requested to intimate the position and also indicate the reasons for not
54
holding the meetings of the Mahila Sabhas before the meeting of the Gram
Sabhas in the concerned cases.
55
Reply of the Government
56
ANNEXURE I
No. N-11019/681/08-Pol.I
Government of India
Ministry of Panchayati Raj
Krishi Bhavan,
New Delhi-110001.
Dated: 19th January, 2009
To: Secretaries,
All Ministries/Departments of Government of India.
Sir,
57
guideline is a potential vehicle to carry the message of strengthening
Panchayats as envisaged by the Constitution and the impact of such signals
cannot be underestimated.
58
essential services that are critical to inclusive growth’ (para 1.147). It details
several steps such as activity mapping, creation of Panchayat sector windows
in the State & Central budgets, and IT enabling of Panchayats as key steps
in this direction.
59
structures, does impact outcomes positively by making interventions more
appropriate, location-responsive and user-friendly. The scheme guidelines,
therefore, need to be modified to (a) provide centrality to PRIs (which would
also enhance the coverage & outreach), and (b) specify roles & functions of
different levels of Government, including the three tiers of the PRIs, through
detailed Activity Mapping.
(a) Annual action plan of the scheme to flow out from the participatory
& holistic decentralised Plan of the concerned tier.
60
(d) Specific mode and time line by which funds are transferred, the
entities that handle funds and the system of utilisation report.
Seamless and time bound flow of funds to the expenditure levels
or just-in-time delivery of funds would both require IT for
electronic tagging and tracking of funds.
(g) How data on the planning and implementation of the scheme will
be placed in the public domain through suo moto disclosures, its
process and periodicity.
11. Often, Parallel Bodies (PBs) are created for supposedly speedy
implementation and greater accountability. However, there is little evidence
to show that such PBs have avoided the evils including that of partisan
politics, sharing of spoils, corruption and elite capture. ‘Missions’, in
particular often bypassing mainstream programmes, create disconnect,
duality, and alienation between the existing and the new structures and
functions. In addition, there are issues of continuity beyond the life of CSSs/
ACASs, subsequent operation & maintenance and continued accountability.
PBs usurp the legitimate space of PRIs and demoralize the PRIs by virtue
of their superior resource endowments, though such resources are available
only during the lifetime of schemes. Arguments such as protection of funds
from diversion have now weakened since advances in core banking systems,
61
treasury computerization and connectivity can enable instantaneous, seamless
and just-in-time transfer of funds directly to the implementing PRI.
Expenditures by PRIs can also be monitored on a real time basis thus doing
away with the need for intermediate parallel bodies to manually transfer funds
and collect, pool and analyse data on expenditures. Ministries should,
therefore, rapidly phase out such PBs from their schemes. If necessary, the
technical & professional component of these PBs could be retained as Cells
or Units within the PRIs, for carrying out their technical & professional
functions.
Yours faithfully,
Sd/-
(A.N.P. Sinha)
Copy to :
62
Appendix I of Annex-1
1
[ELEVENTH SCHEDULE
(Article 243G)
15. Fisheries.
20. Libraries.
63
21. Cultural activities.
23. Health and sanitation, including hospitals, primary health centres and
dispensaries.
64
Annexure II of Annex-1
No.503/9/2/2007-CA-IV
CABINET SECRETARIAT
RASHTRAPATI BHAVAN
Copy to:—
Sd/-
(C.S. Kedar)
Joint Secretary to the Govt. of India
Tel: 23011964
65
Annexure IIA of Annex-1
MOST IMMEDIATE
CABINET SECRETARY
NEW DELHI
November 8, 2004
B.K.CHATURVEDI
Dear Secretary,
Prime Minister has directed that all Ministries which are operating
Centrally Sponsored Programmes be requested to review their respective
schemes in the light of Article 243(G) read with Eleventh Schedule with a
view to incorporating in the schemes, the import of constitutional provisions
in letter and spirit. Ministry of Panchayati Raj may also be consulted in
undertaking the exercise. This revised exercise may be completed in the next
two months. Ministries/Departments are requested to strictly adhere to the
time limit in carrying out the review.
With regards,
Yours sincerely,
Sd/-
(B.K.Chaturvedi)
Secretary,
Department of
66
Annexure III of Annex-1
Broad Specific Activity Central State DPCs Panchayati Raj Institutions ULBs GS/GP SHG ,
function Govt. Govt. District Inter- Village Stg./ CBO,
mediate Comm. etc.
1 2 3 4 5 6 7 8 9 10 11
A. Functions
• Consolidation of plans
67
68
1 2 3 4 5 6 7 8 9 10 11
• Construction
• User Charges
• Identification of beneficiaries
• Procurement/Distribution of
assets
• Social audit
• Independent Evaluation
• IEC
B. Functionaries
• Disciplinary control
• Attendance monitoring
• Performance evaluation
C. Funds
• Authorization to release
• Reporting of expenditure
• Expenditure review
• Maintenance of accounts
• Quick audit
Abbr.: DPC-District Planning Committee, ULB-Urban Local Body, GS-Gram Sabha, Stg. Comm.-Standing Committee, SHG-Self Help Group,
CBO-Community Based Organisation.
69
ANNEXURE II
Sir,
70
(f) Disadvantages of creating parallel bodies to the exclusion/dilution
of the role of the PRIs and its Committees.
In fact, these apply to the State Govt. schemes and functions too.
3. While across the key sectors, the State Panchayat laws mandate a
role for the Panchayats, in most cases the law is ambiguous enough to allow
for both decentralized and centralized modes of programme/service delivery
to co-exist. The de-facto situation does not match the de-jure situation. In
some cases, where the States have clearly devolved such responsibilities to
the Panchayats, these are either (a) still largely being provided in a top-down
manner through the State civil service machinery or (b) the ability of
Panchayats to deliver these is limited because of the deficient financial and
administrative powers and therefore services continue to fail the citizen.
71
5. Further, the 2nd ARC in its Sixth Report relating to the Local
Governance, has recommended that there should be a clear cut delineation
of functions for each level of the local governance. This is not a one time
exercise and has to be done continuously while working out locally relevant
socio-economic programmes, restructuring organizations and framing subject
matter laws (Para 3.3.17.a).
6. It may be noted that the Activity Mapping does not imply that the
subjects are devolved wholesale. The Subjects or Sectors need to be
unbundled and assigned to the different levels of Government on the basis
of clear principles of public finance and public accountability, and above all,
the governance principles of Subsidiarity, Democratic Decentralization and
Citizen-Centricity. The result of good Activity Mapping would be to clearly
identify where competence, authority and accountability lie. Good Activity
Mapping would permit higher levels of Government to concentrate more
on policy making, legislation, system building, addressing issues of
equity and regional imbalances and effectively discharging oversight
responsibilities.
(a) The key activities in the delivery of drinking water may include
the development of water supply systems, their O&M, and
monitoring of their implementation. The essential sub-activities
may include formulation of specific water supply schemes,
technical appraisal and approval of the scheme, awarding
contract, monitoring and supervision of the progress including
quality control.
72
(b) The Basic education could be unbundled into activities such as
identifying and recruiting persons with appropriate teaching
skills, monitoring teacher attendance, procuring & maintaining an
inventory of educational materials & equipments, setting up
school buildings with adequate drinking water & sanitation
facilities, repairing & maintaining existing schools and ensuring
an even spread of teachers, wherever necessary.
73
relatable to the individual Heads of Account in the State Budget. Moreover,
since long established codes prescribing technical standards and approval
processes (such as the PWD code), circulars, OMs, transfer orders etc., would
have tendency towards continued implementation of the devolved functions
through the Line Departments, the Departments would need to issue
consolidated revised guidelines for the schemes to be implemented through
the Panchayats. The role and action to be taken by the institutions, officials
and non-officials at different levels should be clearly mentioned in these
guidelines. Moreover, the devolution should not be limited to the planning
and promotional responsibilities but also the implementation. Parallel Bodies
should not be created to implement the subjects devolved to the Panchayats
and the existing ones should either be phased out or made technical units
of the Panchayats for the reasons stated in para 11 of the letter dt. 19.01.2009.
74
Role of the Gram Sabha and Committees
13. Realizing the importance of a vibrant Gram Sabha, the first Round
Table of State Panchayati Raj Ministers at Kolkata on 24-25th July, 2004
(Annex.-V), inter-alia, recommended that the Gram Sabhas may be
empowered through entitlement to all the information required for making
the elected Panchayats answerable, approve plans and programmes (including
budgets) prepared by the Gram Panchayats, authorize issuance of Utilization
Certificates and identification of beneficiaries. Gram Sabhas should in fact
be given power and functions in accordance with Art. 243A of the Constitution
to enable them to make the elected Panchayats answerable to the people.
14. Further, the activity matrix annexed with our letter dated 19.1.2009,
while indicating the broad functions along with specific activities under each
function, also gives scope for assignment of activities to the District Planning
Committees, Urban Local Bodies, Gram Sabhas, Standing Committees of the
Gram Panchayat, etc. besides the 3 tiers of PRIs. This format may be used
suitably so as to have a co-relation with the State level Activity Mapping.
Expectation
Yours faithfully,
Sd/-
(A.N.P. Sinha)
75
Annexure II of Annex-2
76
Devolution of Functions through Legislations and Activity Mapping
(Based on the information furnished by the State Governments and records of the Ministry)
T r a n s fe r o f m a tte r s lis te d in th e E le v e n th S u b je c ts C o v e r e d u n d e r A c tiv ity
S ta te S c h e d u le to th e P a n c h a y a ts th ro u g h M a p p in g / S ta te G o v e rn m e n t C o m m e n ts
L e g is la tio n O r d e rs
Z ila M andal G ra m O n th e S ta te P a n c h a ya ti R a j A c t: T h e A P P a n c h a y a ti R a j A c t h a s e s ta b lish e d th e
ZP MP GP
P a rish a d P a ris h ad P a n c h a ya t P a n c h a ya t s ys te m a s a h ie r a rc h y , w ith th e Z P a t th e to p . T h e r e fo re , a lth o u g h o n ly
1 23 21 o n e c le a r o rig in a l p o w e r re la tin g to a m a tte r lis te d in th e E le v e n th S c h ed u le h a s
1. A n d h ra
b e e n g iv e n to th e Z P (to e s ta b lish , m a in ta in o r e x p a n d se c o n d a r y, v o c a tio n a l a n d
P r ad e s h T h e S ta te a c t a ls o c o n ta in s gen eral
in d u s tria l sc h o o ls ), it h a s a ls o b e e n g iv e n a p p ro v a l, c o o rd in a tio n , p la n n in g a n d
p r o v is io n s th a t e n a b le s it to e n tr u s t 12 10 12 s u p e r v is io n p o w e r s o v e r M a n d a ls a n d p o w e rs to a d v is e th e G o v e r n m e n t.
th ro u g h r u le s , p o w e r s a n d f u n c tio n s
C o m m e n ts o n A c tiv ity M a p p in g : G o v e rn m e n t is su e d 9 O rd e r s b etw e e n J a n u a r y-
r e la tin g to a ll m a tte rs in th e E le v e n th
M a rc h , 2 0 0 8 , d e v o lv in g a c tiv itie s to th e th re e le v e ls o f P an c h a ya ts a s in d ic a te d .
S c h e d u le
Z ila A n c h a lik G ra m T h e S ta te u n d e rto o k a re v ise d a c tiv ity m a p p in g e x e r c is e a n d p u b lish e d it v id e its
ZP AP GP
P a rish a d P a n c h a ya t P a n ch a ya t N o tific a tio n b e a rin g n u m b e r P D A 3 3 6 /2 0 0 1 /P t- II I/3 2 d a te d 2 5 t h J u n e 2 0 0 7 . A s p e r
2. A ssam th is n o tific a tio n , 2 1 fu n c tio n s liste d in th e 1 1 th S c h e d u le h a v e b e e n d e v o lv e d to th e
25 27 28 21 21 21 3 tie r P R Is . I t h a s a ls o m a d e p ro v is io n in th e S ta te B u d g e t to p ro v id e su b sta n tial
fu n d s to P R Is th ro u g h a n e w b u d g e t lin e .
T h e A r u n a c h a l P ra d e s h P a n c h a y a ti R a j A c t, 1 9 9 7 d e v o lv e s a ll th e 2 9 su b je c ts ,
Z ila A nchal G ra m lis te d in th e E le v e n th S ch e d u le , to a tle a st o n e o f th e tie rs o f P a n c h a y a ts in th e
P a rish a d S a m iti P a n ch a ya t S ta te .
3. A r u n a c h a l 29
P r ad e s h 25 28 28 T h e e x e c u tiv e o rd e r fo r d e v o lu tio n o f 2 9 s u b je c ts o f A c tiv ity M a p p in g w a s is su e d
o n 2 1 st O c to b e r , 2 0 0 8 fo r d e v o lu tio n o f 2 9 su b je c ts c o v e rin g 2 0 d ep a rtm e n ts .
T h e r e is o v e rla p o f so m e o f th e fu n c tio n s d e v o lv e d to d iffe re n t tie rs o f P an c h a y a ts .
A s p e r th e B ih a r P a n c h a y a ti R a j A c t, 2 0 0 6 , a ll th e fu n c tio n s o f th e E le v e n th
Z ila P a n c h a ya t G ra m Z ila P a n ch a y a t G ram S c h e d u le h a v e b e e n d e v o lv e d to eith e r o f th e tie rs o f P an c h a y a ts .
P a rish a d S a m iti P a n ch a ya t P a rish a d S a m iti P a n ch a ya t T h e S ta te G o v e rn m e n t h a d is su e d e x e c u tiv e o r d e rs in re s p e c t o f 2 8 m a tte r s a n d
4. B ih a r o n ly th e s u b je c t “ T e c h n ic a l tra in in g a n d v o c a tio n a l e d u c a tio n h a s b e e n e x c lu d e d ” .
25 26 25 23 24 27 T h e S ta te p ro p o s e to r e v is it th e a c tiv ity m a p p in g a im e d a t g re a te r d e v o lu tio n o f
fu n c tio n s, fu n c tio n a r ie s a n d fu n d s to th e P a n c h a ya t.
T h e A c tiv ity M a p p in g h a s b e e n p r e p a r e d fo r 2 7 s u b je c ts e x c lu d in g d rin k in g w a te r
5. C h h a ttis g a r h 27 s u p p ly a n d fo r e sts . T h e e x e c u tiv e o r d e rs w ith re s p e c t to o p e r a tio n a liz in g A c tiv ity
29
M a p p in g a r e y e t to b e is s u ed in C h h a ttisg a rh .
O u t o f 2 9 s u b je c ts to b e d e v o lv e d to P a n c h a ya ts , 6 s u b je c ts h a v e b e e n tr a n s fe r re d
Z ila V illa g e th r o u g h le g is la tio n a n d 1 8 su b je c ts h a v e b e e n c o v e re d u n d e r A c tiv ity M a p p in g .
6. Goa P a n ch a y a t P a n ch a ya t 18 1 8 m a tte rs a r e d e v o lv e d to th e G r a m P a n c h a y a ts w h ile 7 m a tte r s a re d e v o lv e d to
th e Z ila P an c h a y a ts . T h e re is a n o v e r la p in a ss ig n m e n t o f r e sp o n s ib ility b e tw e e n
7 18 th e tw o tie rs .
Zila Panchayat Gram On the State Panchayati Raj Act: In respect of ZPs and PSs, the Act gives specific powers to
ZP PS GP
9. Himachal Parishad Samiti Panchayat the General body and its Standing Committees. Both have been reckoned in the overall
Pradesh devolution to the body.
On Activity M apping: A general notification on devolution of functions issued for
17 16 11 22 23 24 15 departments in July, 1996. However, only 8 departments have issued orders in 2001-02.
Zila Janpad Gram On the State Panchayati Raj Act: The M P Act, apart from devolving powers and
13. Madhya responsibilities to the three Panchayat levels, has also devolved 18 matters to Gram Sabhas.
Parishad Panchayat Panchayat
. Pradesh 25
On Activity M apping: Executive orders have been issued for 25 matters. The State is
7 17 8 revisiting Activity Mapping.
Devolution in M aharashtra is derived from The Bombay Village Panchayats Act, 1958 and
The M aharashtra Zila Parishads and Panchayat Samitis Act, 1961. Except the subject
28 28 Non-Conventional Energy Sources, all other subjects of XIth Schedule are broadly covered in
14. M aharashtra these legislations.
It was reported that activities devolved to Panchayats are listed in the legislations itself.
77
78
15.
16.
17.
18.
19.
20.
21.
Zila Panchayat Gram The UP Panchayati Raj Act 1947 and The UP Kshetra Panchayats and Zila Panchayats
22.
Panchayat Samiti Panchayat Act, 1961 provide for devolution of functions.
Uttar
16
Pradesh
Functions relating to 12 departments have been transferred to Panchayats. Activity
Mapping is still under the consideration of the Government.
29 29 29
The UP Panchayati Raj Act 1947 and The UP Kshetra Panchayats and Zila Panchayats
Act, 1961 providing for devolution of functions are applicable in the State as the State
Zila Panchayat Gram legislation on Panchayati Raj is under preparation.
23. Uttara- Panchayat Samiti Panchayat
14
khand The Activity Mapping of 11 departments related to 14 subjects was released in
August 2005. However, the Government has not issued the necessary notifications to
operationalize the Activity Mapping. Cabinet Sub-Committee has been constituted to
consider the Activity Mapping and the outcome is awaited.
29 29 29
Panchayat Gram The State Government has devolved all 29 functions included in the 11th Schedule to
Zila Parishad
24. West Samiti Panchayat the 3 tier PRIs. Activity Mapping has been completed for 28 subjects accepting
18 technical and vocational education. As per orders dated 7.11.05, 25.7.06 and 29.10.07,
Bengal
18 29 28 9 departments have so far issued necessary matching orders. 3 departments have
opened separate Panchayat Window for transferring funds to the PRIs.
79
Annexure IIA of Annex-2
1 2 3
80
1 2 3
81
1 2 3
82
1 2 3
83
Annexure IIB of Annex-2
1 2
84
1 2
85
1 2
86
1 2
87
1 2
88
1 2
89
1 2
90
1 2
91
1 2
92
1 2
93
Annexure III of Annex-2
1 2 3 4 5
3. Public Health (i) Primary Health (i) Block level District Hospitals
Centre / Rural Primary Health
Dispensary Centres
(ii) Maternity and (ii) Community
Child Welfare Health Centre
Centre (iii) Taluk Hospital /
(iii) Sub Centre Govt. Hospital
94
1 2 3 4 5
95
Annexure IV of Annex-2
1 2 3 4 5
2. Animal Officers and staff of Officers and staff of (i) District Animal
Husbandry Veterinary Sub Cen- Veterinary Poly Husbandry
tre, Veterinary Dis- Clinic, Mobile farm officer and
pensary / Hospital and unit, Mobile veteri- auxiliary posts
ICDP sub centres nary dispensary (ii) Officers and
staff of ICDP
area office,
Mobile Veteri-
nary Dispensary,
Mobile farm
unit, clinical
laboratories not
attached to Dis-
trict Veterinary
centres
96
1 2 3 4 5
3. Dairy One Dairy Extension Block Level Dairy (i) Deputy Director
Development Officer and auxiliary Extension Officer and and auxiliary
Department posts (this unit should auxiliary posts posts
be created in one of
the Gram Panchayats
in the Block and
should cover all the
Gram Panchayats in
the block)
7. Social Welfare Officers and staff of Officers and staff of District Social
Day care centres Child Development Welfare Officer,
and Anganwadis Project Office, Old District Programme
(ICDS Supervisor, Age Homes Care Officer and auxiliary
Anganwadis worker / Homes and similar posts
helper etc.) other institutions
97
1 2 3 4 5
11. Health Services Medical Officers and Medical Officers and (i) District Medical
(Allopathy) other staff of PHCs / staff of Block Level Officer and
Govt. Dispensary and PHC/ CHC / Taluk auxiliary posts
sub-centres Hospital / Govt. Hos- (ii) Medical
pital Officers, Supt.
and all other
staff of District
Hospitals
12. Health Services Medical Officer and Medical Officers and (i) District Medical
(Homoeo) staff of Government auxiliary posts of Officer and
Homoeo dispensaries Taluk Hospital auxiliary posts
and hospitals of the (ii) Medical
respective places Officers, Supt.
and all other
staff of District
Hospitals
13. Health Services Medical Officer and Medical Officers and (i) District Medical
(ISM) staff of Ayurveda dis- auxiliary posts of Officer and
pensary and hospitals Taluk Hospital auxiliary posts
of the respective (ii) Medical
places Officers, Supt.
and all other
staff of District
Hospitals
98
1 2 3 4 5
18 Public Health Medical Officer and Medical Officer and District Medical
staff of Primary staff of Block level Officer and staff
Health Centre/ Primary Health of District Hospitals
Rural Dispensary, Centres, Community
Maternity and Child Health Centres and
Welfare Centre and Taluk Hospital / Govt.
Sub-Centre Hospital
99
Annexure-V of Annex-2
(I) The Constitution (Article 243G) provides for “devolution”, that is,
the empowerment of Panchayati Raj Institutions (PRIs) to function
as institutions of self-government for the twin purposes of
(i) making plans for economic development and social justice for
their respective areas, and (ii) implementing programmes of
economic development and social justice in their respective areas,
for subjects devolved to the PRIs, including those listed in the
Eleventh Schedule, and subject to such conditions as the State
may, by law, specify. Therefore, the key objective is to ensure
that Panchayati Raj Institutions function as institutions of self-
government rather than as mere implementing agencies for other
authorities in respect of such functions as may be devolved on
them;
(IV) In determining the tier of the Panchayati Raj System to which any
given activity is to be attributed, the principle of subsidiarity must,
to the extent possible, be followed. The principle of subsidiarity
100
states that any activity which can be undertaken at a lower level
must be undertaken at that level in preference to being undertaken
at any higher level;
101
(III) With a view to building a cadre of officials and technocrats
specialized in the devolved functions of the PRIs, State
Governments/UT Administrations may consider instituting a
Panchayati Raj Administrative and Technical Service, with the State
Government discontinuing further recruitment of staff to State
services for such devolved functions;
(II) To this end, the devolution of finances to the three tiers of the
Panchayati Raj System should be patterned on activity mapping
for the devolution of functions and functionaries, thus securing
effective devolution of powers to the PRIs through the linking of
the devolution of finances to the devolution of functions and
functionaries;
102
(III) On the basis of the principles adumbrated above, the State
Governments might attempt to prepare a road map, to be made
effective as soon as possible, and, in any case, by the end of the
next fiscal year 2005-06, which might include the following
components:—
(a) Planning;
(b) Budgeting;
103
Gram Sabhas
(III) Based on the two principles stated above, State Governments may
review the extant legislation to determine the legislative and other
steps which remain to be taken to ensure that the “powers” and
“functions” mentioned in Article 243A of the Constitution are
adequately incorporated in the State legislation. In particular, the
following points may be examined:—
(i) The need for constituting Sabhas below the Gram level (such
as Gram Sansad, Upa-Gram Sabha or Ward Sabha, by
whatever name called) with the aim of ensuring that the adult
population in each ward is given the opportunity of conveying
to the Gram Sabha their views on issues coming up for
consideration as also holding the elected Ward representative
responsible to the adult population in each Ward;
(iv) Provision for Mahila Sabha meetings, comprising all the adult
women of a Ward/Gram Panchayat area, to deliberate upon,
and decide the modalities of, expressing their views in the
Gram/Ward Sabhas;
104
good governance, as well as to make the elected
Panchayat truely answerable to the Gram/Ward Sabha;
105
ANNEXURE III
Sir,
106
Fiscal Decentralization
107
5. Article 243-I of the Constitution mandates setting up of
State Finance Commission (SFC) with the objective of reviewing the
financial position of the Panchayats and making recommendations as to
the principles which should govern:
108
imaginative and assertive in tapping their revenue resources. The
State Governments should focus on prescribing band of rates for such taxes
and levies, mentoring, strengthening and incentivising Panchayats.
Market Borrowing
109
Transfer of Funds
14. The need for having a simple and robust accounting and
reporting system for the PRIs is evident. We are working along with the
Comptroller and Auditor General of India, on such a system, having
appropriate MIS/DSS window, covering both the agency and core functions
of PRIs. Suitable advisory on Account and Audit (formal and social) is
being issued separately. The proposed e-PRI Project of this Ministry, which
would also house PRIA Soft (PRI Accounting System Software), should
facilitate the process.
110
Staffing and Capacity Building
17. The above efforts may not bear outcomes if not supplemented
by providing the PRls with adequate manpower, mentoring and guidance.
The States should, therefore, strengthen the administrative and enforcement
capacity of Panchayats through proper staffing including outsourcing,
frequent training programmes comprising well-structured modules
(possibly with the help of ICAI), simple guidelines etc. Sufficient funds
are available for 250 BRGF districts under BRGF and for non-BRGF
districts under RGSY.
Action Plan
18. Last, but not the least, the most important question is how and
where to start. I would suggest the following:
• Assist the SFC to lead policy work for (a) exploring appropriate
tax and non-tax revenue assignments, (b) ways and means of
administering and enforcing them including manpower and
training and (c) achieving a greater linkage between revenue
collection and spending decisions at the local level.
111
• Re-examine the current rates of taxation and consider an upward
revision, remove maximum limits fixed on tax as also the
conditionalities that hamper or restrict taxation powers of
Panchayats. Do not abolish taxes in Panchayat domain
(e.g. some States have abolished house tax).
Role of MoPR
19. The Ministry of Panchayati Raj would, on its part, assist the
States in designing local solutions, designing training programmes,
developing software solutions for tax management and networking with
champions. It would also undertake analysis of the State trends to identify
initiatives and drives, conduct periodical experience sharing workshop,
support policy studies on local taxation particularly on ascertaining taxation
capacity and designing incentive packages.
Yours sincerely,
Sd/-
(A.N.P. Sinha)
112
ANNEXURE IV
No. M-11011/162/2008-P&C(AR)
Government of India
Ministry of Panchayati Raj
Sir,
113
Kolkata on 24th-25th July, 2004 where the following resolutions were
adopted:—
114
(ii) In all States, a detailed review of the staffing pattern and
systems, with a zero-based approach to PRI staffing may be
undertaken over the next one year in order to implement the
policy of PRI ownership of staff. The Zila Parishads, particularly,
should be associated with this exercise.
6. Logically, for the subjects listed in the 11th Schedule and others
that have been devolved, the Panchayats should have the power to (i) recruit
personnel, (ii) regulate their service conditions, and (iii) exercise control
over them, subject to such laws and standards as may be laid. However,
due to several factors such as (i) service conditions of the existing
employees, (ii) lack of enabling administrative and legislative environment
for transferring the State Govt. employees to the Panchayat Cadre,
(iii) resistance from the existing employees etc., there would be problems
in implementing this arrangement. Therefore, the following transitional and
permanent arrangements with a definite time line are suggested.
115
(iv) The District Panchayat Cadre (DP Cadre) could comprise of
officials that have jurisdiction over areas larger than a GP.
Employees of the DP cadre would supervise the work of the
functionaries at the GP level. Examples of this would be:
Extension Officers, junior engineers etc. Some employees listed
above for the GP cadre could also fall in this cadre. The DP
cadre could be constituted by a judicious mix of direct
recruitments and promotion from the GP Cadre. Only those
found to be meeting expected standards measured in quantifiable
terms should be considered for promotion. Perhaps entering the
DP cadre from GP cadre could get more than one promotion
within the DP Cadre, before he/she can move to the next level.
(v) State Cadre: Ideally, even Class I and II officers should belong
to DP Cadre. However, during the transition period, this cadre
could be a State Cadre and people from this cadre should be
posted on deputation to the District/Intermediate Panchayats.
116
increasing responsibilities and complexity of the task in the GP,
it would be desirable to create a post of Panchayat Development
Officer with a degree in Business Administration Rural
Management or a similar degree;
(ii) Scheme Specific Staff: for example, NREGA provides (a) for
GP—Gram Rozgar Sewak; (b) for Block Panchayats—one
Programme Officer, a pool of few Technical Assistants to service
GPs; Computer Assistants and Accountant; and (c) for District
Panchayats Works Manager with Technical assistant, IT Manager
with Computer Assistant, Accounts Manager with Accounts
Assistant, Coordinator for social audit and grievance redressal.
117
the broad principles enunciated above, a road map for gradual transition
to the desired State could be worked out. The Recruitment Rules for these
cadres would require amendments so as to be able to reach the final
destination without resulting disadvantage to the existing personnel. This
Ministry would support States, engage reputed consultancy organizations
and commission studies with, inter-alia, following ToRs:
(v) Give Job description for each post and develop skill
development matrices for training of persons to discharge their
duties efficiently.
Yours sincerely
(A.N.P. Sinha)
118
Annexure–I of Annex. 4
• Freeing PRI office bearers and members from the web of restrictive
administrative instructions.
119
Annexure–II of Annex. 4
120
Annexure-II (part) of Annex.-4
1. Section Officer
2. Superintendent
3. Extension Officer (Statistics)
4. Steno-typist (LG)
5. Steno-typist (HG)
6. Stenographer
7. Senior Assistant
8. Junior Assistant (Acctts.)
9. Driver
10. Asstt. Acctts. Officer
11. Deputy Acctt.
12. Senior Asstt. (Acctts.)
13. Junior Asstt. (Acctts.)
14. Extension Officer (Panchayats)
15. Village Development Officer
16. Gram Sevak
17. Medical Officer
18. Medical Officer (Class III)
19. Pharmacist
20. Lab Technician
21. Leprosy Technician
22. Extension Officer (Health)
23. Health Asstt. (Male)
24. Health Worker (Male)
25. Health Worker (Female)
26. Health Asstt. (Female)
27. Health Supervisor
28. Projectionist
29. Photographer
121
30. Agriculture Officer
31. Extension Officer (Agri.)
32. Junior Engineer (Civil)
33. Asstt. to Jr. Engineer
34. Chief Draftsman
35. Draftsman
36. Junior Draftsman
37. Tracer
38. Mistry (Grade-I)
39. Mistry (Grade-ll)
40. Senior Mechanic
41. Junior Mechanic
42. Electrician
43. Fitter
44. Asstt. Livestock Development Officer
45. Livestock Supervisor
46. Extension Officer (Education) — Grade II
47. Extension Officer (Education) — Grade III
48. Asstt. Teacher (Secondary) — Upper grade
49. Asstt. Teacher (Secondary) — Lower Grade
50. Junior College Teacher
51. Kendra Pramukh (Education)
52. Primary School Teacher
53. Head Master
54. Deputy Head Master
55. Lab Asstt.
56. Asstt. Child Development Officer
57. Supervisor (Child Development)
Class IV
58. Peon
59. Dresser
122
ANNEXURE V
DETAILS OF DISTRICT PANCHAYATS
SI. Name of the No. of Rural Districts No. of Rural No. of Rural District Reasons for not having
No. State/UTs Districts having not having District District Panchayat
District Panchayat Panchayat in terms given by State
in terms of Part IX of Part IX of the Governments
of the Constitution Constitution
as on as on as on as on as on as on
1.4.2009 1.4.2010 1.4.2009 1.4.2010 1.4.2009 1.4.2010
1 2 3 4 5 6 7 8 9
2. Arunachal Pradesh 16 16 16 16 0 0 NA
3. Bihar 38 38 38 38 0 0
4. Chhattisgarh 18 18 16 18 02 Nil Dantewada and Jagdalpur
have been reorganized and
divided into four new
districts, i.e. respectively
Bijapur and Narayanpur
in mid session of the
Panchayat.
123
1 2 3 4 5 6 7 8 9
124
5. Haryana 21 21 19 19 02 02 In district Mewat and
Palwal i.e. two District
Panchayats i.e. Zilla
Parishads have been
established in the month
of Jan. 2010 and the
elections of all these
21 Zilla Parishads are
scheduled in April/May,
2010.
6. Himachal Pradesh 12 12 12 12 0 0 NA
7. Jharkhand 24 24 24 24 - - Election to Panchayats
have not been held so far.
8. Karnataka 29 30 29 30 - - All the Districts are having
District Panchayats.
9. Kerala 14 14 14 14 - - In Kerala State, there
is no classification/
categorization of districts
as rural or urban.
Therefore the question of
rural districts which do
not have District
Panchayats, does not arise.
There are Panchayats (as
laid down in Article 243B
of Part IX of the
Constitution of India) in
all 14 revenue districts.
1 2 3 4 5 6 7 8 9
13. Punjab 20 20 20 20 NA NA -
14. Sikkim 4 4 4 4 Nil Nil NA
15. Tripura 4 4 4 4 4 4 The Part IX of the
(partly) (partly) (partly) (partly) Constitution is not
accessible in the
6th Scheduled Area.
125
1 2 3 4 5 6 7 8 9
126
16. Uttar Pradesh 71 71 71 71 0 0 NA
17. Uttarakhand 13 13 13 13 0 0 Not applicable
18. West Bengal 18 18 18 18 Nil Nil Does not arise.
UTs
1. Andaman & Nicobar 3 3 2 2 1 1 Nicobar District being a
tribal area, has been
notified as reserved areas
under the A & N Islands
PAT Regulation, 1965.
Hence the Andaman &
Nicobar Islands Panchayat
Regulation is not extended
to Nicobar District.
Panchayat Regulation
applies to Non-tribal areas
to this District.
2. Chandigarh UT 1 1 1 1 - - -
3. Daman and Diu 2 2 1 1 1 1 The District Panchayat,
Daman and Diu with
headquarters at Moti
Daman came into
existence from
25.09.1995.
1 2 3 4 5 6 7 8 9
4. Lakshadweep 1 1 1 1 NA NA NA
5. Puducherry 2 2 0 0 2 2 Necessary exemption has
been obtained from the
Government of India to
dispense with the
constitution of District
Panchayat in this Union
Territory — vide
notification bearing
No. S.O. 312(E) dated
13.4.1994 issued by the
Ministry of Home Affairs.
The Puducherry Village
and Commune Panchayats
Act, 1973 envisages only
two tier Panchayats at the
village level and commune
Panchayats (Intermediate
Panchayats) at Commune
level.
*Four districts of Tripura are partly covered under Part IX and partly covered under Scheduled Area.
127
ANNEXURE VI
No. N-11019/59/2006-Pol.I
Government of India
Ministry of Panchayati Raj
Sir,
128
instruments in making NREGS a much better success. It is generally seen that
States having vibrant and optimally sized GPs with requisite capability have
implemented NREGS better. There is self-evident symbiosis between NREGS and
the GPs. It would, therefore, be necessary that GPs offices also have NREGA
offices, to be called Bharat Nirman Rajiv Gandhi Sewa Kendra (BNRGSK).
(i) For the BRGF districts — the material component may be met from
BRGF and the labour component from NREGA. In case, the material
resources support from BRGF is inadequate, the same can be incurred
under NREGS provided the material component does not exceed 40%
at the district level;
(ii) For the non-BRGF district— NREGS would be the main source. The
material component can also be supplemented through other schemes
including RGSY of MoPR.
(i) Building designs have been made through the School of Planning and
Architecture. Evidentally, the Cost norms would be as per the State
129
Schedule of Rates and there would be local design variations
depending on the geo-climatic conditions and the availability of
construction material & skills;
10. Your suggestions in the matter would help us refine the above
guidelines, if need be.
Yours faithfully,
Sd/-
(A.N.P. Sinha)
130
Annexure-I of Annexure-6
2. Register those who are willing to work under NREGA and issue a job card
to them.
3. Receive applications for work and issue a dated receipt to the applicant.
4. Allocate work opportunities among the applicants and ask them to report
for work.
5. Display a list of persons who are being provided with work on its notice
board.
7. Make all relevant documents available to the Gram Sabha for the purpose
of social audits.
8. Keep a copy of the muster rolls available for public scrutiny at the Panchayat
office.
131
ANNEXURE VII
No. H-11016/2/2010-RBH
Government of India
Ministry of Panchayati Raj
To
132
holding of the meetings of Gram Sabha, Mahila Sabha and Ward
Sabha in the current year being observed as the Gram Sabha Year may
be sent to this Ministry urgently.
In case the meetings of the Mahila Sabhas have not been held before
the Gram Sabha the reasons for the same may be intimated to this
Ministry so that the Committee is informed accordingly.
(ii) Para 4.62: In view of the observations made by the Committee it will
be appreciated that it would not be proper if the male Pradhans/
Pramukhs of the Gram Panchayat do not perform their duties and
demonstrate any weakness with regard to performance of their duties
by allowing their relatives who are or other persons to function as
proxy for them. It is, therefore, necessary that appropriate action is
taken against such weak male Pradhans/Pramukhs of the Gram
Panchayat. In addition to this the action may be taken by Secretary
of the Panchayat who are or the concern Government officer in whose
presence the meetings of Gram Panchayats are held and the male
relatives who are or other persons connected with the weak Pradhans/
Pramukhs of the Gram Panchayat are allowed to perform the duties
of elected Pradhans/Pramukhs. It is requested that suitable instructions
may be issued to the concerned authorities at all level of PRIs in the
State and action taken may be reported to this Ministry for further
necessary action.
(iii) Para 4.63: In view of the observations made by the Committee it is
requested that the considered comments of the State Government may
be sent to this Ministry about the performance of the scheme of
Panchayat Mahila Evam Yuva Shakti Abhiyan (PMEYSA) in the
State. The achievements made under the scheme and the bottlenecks
felt in the implementation of the scheme impeding the total success
of the scheme may be intimated to this Ministry so that this Ministry
may consider the matter further.
3. It is requested that the action with regard to the above mentioned paras
may be taken on top priority basis and the position about action taken alongwith
copies of the relevant communications may be sent to this Ministry within a month
so that the Parliamentary Standing Committee is provided with the Action Taken
Report (ATR) accordingly.
Yours faithfully,
133
ANNEXURE VIII
No. N-11019/538/2007-Pol-I(Vol-II)
Government of India
Ministry of Panchayati Raj
OFFICE ORDER
(b) strengthen, to this end the Panchayati Raj and Municipality level
governance through appropriate capacity building, to facilitate
participatory planning, decision making, implementation and
monitoring, to reflect felt local needs;
134
5. Director, XLRI, Jamshedpur — Member
(a) Assess the extent to which objectives of BRGF have been fulfilled;
(e) Need for modification in the objective and design of BRGF including
the Block as Unit for BRGF funding; and
4. The Committee will submit its first report within 3 months and
thereafter quarterly.
Sd/-
(Susan D. George)
Director
Tel. No. 24122938
Distribution:
135
2. Shri B.N. Yugandhar, Member, Planning Commission, New Delhi.
3. Principal Secretary to the Prime Minister of India, South Block, New Delhi.
11. Shri Rajesh Tandon, President, PRIA (Society for Participatory Research
in Asia) 42, Tughlakabad Institutional Area, New Delhi-110 062.
Copy to:
136
ANNEXURE IX
Recommendations of NARC and Response of MoPR
1 2 3
2.2 Every District should come out with the district MoPR has set up an
profile of backwardness to be upgraded once in inter-Ministerial Group
every three years. on the issue of indicators
and geographical unit
for measurement of
backwardness.
137
1 2 3
2.5 Since the purpose of the BRGF is to fill the gaps The Scheme gives
in developmental infrastructure, it is necessary discretion to the States
to identify the level of development of different for identifying the norms
Blocks and give priority to the bottom one-third for distribution of the
of the Blocks for investment under the Grant, district entitlements
to fill all the existing gaps within a given time- among the various local
period. Similarly, identification of backward bodies.
Gram Panchayats can also be undertaken This suggestion would be
wherever feasible as already done in West included in the BRGF
Bengal and Maharashtra. Guidelines.
138
1 2 3
2.9 The process of release needs to be simplified. MoPR has made several
The Districts will plan and indicate a sector and changes in the procedure
scheme-wise requirement of funds, before the for expeditious release of
beginning of the financial year. This will funds. States have been
become the basis for the release of funds. urged repeatedly to
submit this District Plans
timely.
2.10 There should be some incentive for expenditure The EFC Note on
incurred within or before time. Likewise there restructuring of BRGF
ought to be a disincentive for late, tardy or poor has sought for re-
utilization of funds. The disincentive could allocation of Develop-
come in a number of ways such as losing a part ment Grant during the
of the funds; requiring the State to do an year, based on the
additional exercise before further release etc. performance. As for the
However, it may be mentioned that the quality quality of expenditure,
of the expenditure and the outcome of the this is to be ensured by
investment will need to be carefully assessed the State Governments
before arriving at the incentive or disincentive. through (a) Quality
Monitoring Systems and
(b) Social Audit through
Gram Sabhas.
2.11 There is need for close convergence between In fact BRGF intends to
BRGF and other Livelihood Programmes of the promote cross-sectoral,
Government. Sectoral Planning for livelihoods decentralised plans,
should be under one umbrella planning process. including livelihood.
There should be one Integrated Livelihood Plan
for the whole District.
3.1 Considering the strengths and weaknesses MoPR has not found any
of the existing NCBF and the features of significant problem with
the NCDF proposed by Sub-Committee on the NCBF, nor has
Capacity Building and Convergence, a National any State or the World
Capabilities Development Framework may be Bank evaluation stated
prepared, jointly, by MoPR and MoRD. MoPR so. MoPR has been
139
1 2 3
and MoRD may adopt a common strategy for interacting with MoRD,
capabilities development including pooling up MoUD and DoPT
funds and release of these funds. (Training Division) on
various aspects of
training and capacity
building such as training
needs analysis, pooling
of training materials and
training infrastructure etc.
A Standing Committee
including MoRD, MoPR
etc. has also been set up
for the purpose.
3.5 Since the requirements for BRGF Districts The proposals mooted by
themselves may be large, MoPR and MoRD MoPR for launching the
140
1 2 3
3.8 With the vast funds available for rural It would be better to
development, MoRD may take steps to further rename NIRD as NIP
strengthen and transform NIRD, strengthen & RD, with concomitant
SIRDs using innovative methods where changes in its
necessary; and establish an ETC in each district composition and
(initially ensuring they are starting in BRGF mandate.
districts). It is suggested that NIRD may
prepare a proposal for development of the
Centre for Panchayati Raj in NIRD as Centre
of Excellence for capabilities development of
PRI functionaries and strengthening of these
institutions. The proposal may envisage the
role to be played by NIRD with the help of all
the 28 SIRDs and 89 Extension Training
Centres in the country as also other district level
and sub-district level institutions.
141
1 2 3
142
1 2 3
4.2 The guidelines issued by the Planning Commis- We agree. This recom-
sion for the preparation of District Planning mendation is being taken
should be reiterated. MoPR may urge the up with the Planning
Planning Commission that it should insist that Commission.
the draft state plan proposals every year for the
annual plan discussions should be accompanied
by the required material on District Plans and
that there should be a separate working group
for this until the process gets stabilised.
4.3 The guidelines for implementation of CSSs and We agree. MoPR has
planning to be prepared for these schemes at urged upon the Planning
present are narrowly confined to the departmen- Commission to enforce
tal purposes. The MoPR and Planning Commis- the guidelines relating to
sion should take the initiative to ensure that integrated decentralised
these guidelines are in conformity with the planning. Now MoPR has
requirements and the purpose of the District decided to undertake
Level Plans. It should be ensured that the preparation of perspective
scheme-based guidelines and plans are, as a plans for 250 BRGF
first step, integrated with the sectoral sub-plans districts through Technical
and thereafter fully coalesced with the District Support Institutions,
Plan. keeping in view the
experience of a similar
exercise done at the
launch of the BRGF
Programme in 2006-07.
143
1 2 3
4.5 MoPR may also urge the State Governments to We agree. While some
provide an untied portion of the State plan so States have been provid-
that DPCs will have some flexibility in working ing untied grants to the
out schemes and projects of local relevance. Panchayats, none provide
such grants to the DPCs.
The suggestion would get
its intent served only
when States undertake
preparation of integrated
district and sub-district
plans in true spirit, for
which MoPR has been
seeking pivotal action /
lead from the Planning
Commission.
4.7 The complex exercise of preparing district plan We agree. MoPR has
in the context of multiple interventions can be been highlighting upon
facilitated to a great extent by the use of ICT the States, MoRD and the
144
1 2 3
5.2 Having done this, the Planning Commission We agree. It would make
may be urged to constitute a committee or team huge difference in plan-
to scrutinise all CSSs guidelines for schemes ning, implementation and
implemented at local level. Objective should be outcomes of the CSSs/
to bring about as much commonality as possible ACAs.
regarding State level nodal agencies, planning
process, approval, Centre-State contribution
ratio, subsidies, role of Local Government,
audit mechanism including social audit etc. The
overarching objective should be that the guide-
lines are in consonance with the principles of
subsidiarity and decentralised planning. In this,
the local Committees to be constituted under
various CSSs guidelines should be integrated
with standing/functional Committees at different
levels of the Local Government. There should
be the Committees of the Local Government.
145
1 2 3
5.6 The process of convergence will be made easier We agree. MoPR vide its
if electronic transfer of funds is done in the case letter No. N11019/125/
of all CSSs and State Government schemes and 2009-Pol.1 dt. 23.02.2010
programmes. The electronic transfer of funds has proposed a simple
from ministry to State Government and from the but robust scheme to the
State Government to district, sub-districts and Union Ministries and
Panchayats would enable simultaneously States for electronic
monitoring and scrutiny. transfer and tracking of
funds and Financial
Management System.
Planning Commission/
M/o Finance may advise
all Ministries/States for
its adoption.
5.7 MoPR may encourage States—starting with We agree and would work
BRGF districts — to promote the need and alongwith MoRD to
importance of convergence through appropriate implement this.
campaigns, adoption of locally relevant
communication techniques like folk plays,
dances in order to ensure community
involvement. Such involvement enables the
community to view development as a
comprehensive exercise and not as a mere
collection of schemes. It will also encourage
ownership of development, which will, in turn,
make them more committed to maintenance.
146
ANNEXURE X
F.No. PEO/16(98)/2010/TC
Planning Commission
Programme Evaluation Organisation
147
8. Dr. R.C. Dey, Director (PEO-TC), Member
Planning Commission
The Committee may co-opt any additional Member(s) as and when required.
Sd/-
(Nandita Mishra)
Director (PEO)
Telefax: 23096745
To,
Copy:
148
ANNEXURE X1
Criteria for Inter se Distribution of BRGF Fund across States
Sl. State Rural:Urban Inter se Urban Inter se Rural Inter se Three tiers Across Blocks Across GPs
No. (GP:IP:ZP)
1 2 3 4 5 6 7 8
1. Andhra Pradesh Population Population Population and SC/ST 50:30:20 Population and SC/ST Population and SC/ST
Population Population Population
2. Arunachal Pradesh One crore to Urban to NA(info. not available) Equally 50:30:20 Equal (Rs.26.15 lakh Equal (Rs.4.12 lakh
Urban areas. Basis not each) each)
clear.
Population x per capita
3. Assam Population Population x per capita Population x per capita 50:30:20 Population allocation
allocation allocation
5. Chhattisgarh Population As per work list As per work list As per work list As per work list As per work list
approved by DPC approved by DPC approved by DPC approved by DPC approved by DPC
6. Haryana 80:20 as per TFC As per work list As per work list 75:10:15 As per work list As per work list
recommendations approved by DPC approved by DPC approved by DPC approved by DPC.
Normative formula
abandoned due to small
amount reaching GPs.
7. Himachal Pradesh As per work list As per work list As per work list 50:30:20 As per work list As per work list
approved by DPC approved by DPC approved by DPC approved by DPC approved by DPC
149
1 2 3 4 5 6 7 8
150
8. Gujarat Population As per work list As per work list Each tier gets As per work list As per work list
approved by the approved by the minimum 20% of approved by the approved by the
DPC DPC allocation. Other DPC DPC
criterion is population
10. Jharkhand As per work list As per work list As per work list As per work list As per work list As per work list
approved by DPC approved by the DPC approved by the DPC approved by the DPC approved by the DPC approved by the DPC
11. Karnataka 80:20 As per work list As per work list As per work list As per work list As per work list
approved by the DPC approved by the DPC approved by the DPC approved by the DPC approved by the DPC.
Emphasis on SC/ST
colonies
12. Kerala Non SC/ST Population Weighted index (see Weighted index (see 50:40:10 Weighted index (see Weighted index (see
annex-1) annex-1) annex-1) annex-1)
13. Madhya Pradesh As per work list As per work list As per work list 65:22:1 As per work list As per work list
approved by the DPC approved by the DPC approved by the DPC approved by the DPC approved by the DPC
15. Manipur No urban component Population Population Not Applicable Population Population and 25%
except Chandel which retained at the District
has one small level for backward GPs
municipality. Fund
allocated as per
population.
1 2 3 4 5 6 7 8
16. Meghalaya As per work list As per work list As per work list As per work list As per work list As per work list
approved by the DPC approved by the DPC approved by the DPC approved by the DPC approved by the DPC approved by the DPC
19. Orissa 60:40 as per revised 15% SC/ST As per work list 50:30:20 As per work list As per work list
guidelines population, 85% GEN approved by the DPC approved by the DPC approved by the DPC
20. Punjab 80:20 on the basis of Further distribution as Further distribution as Further distribution as Further distribution as Further distribution as
population per list of projects per list of projects per list of projects per list of projects per list of projects
approved by the DPC approved by the DPC approved by the DPC approved by the DPC approved by the DPC
21. Rajasthan Population Population 50% population, 50% None None 50% population, 50%
BPL population BPL population
22. Sikkim 20% tribal fund. Rest As per approved work Each District (North, Not applicable As per work list As per work list
is divided in the ratio list South, East, West) gets
of 80:20 between 1/4th of total allocation
urban and rural
23. Tamil Nadu Population Population 20% District 20:30:50 Population Population
\ Panchayat, out of
remaining 80%, 10 lakh
\ to each Panchayat
Union, and 50% on the
basis of SC/ST
population
151
152
1 2 3 4 5 6 7 8
25. Uttar Pradesh As per work list As per work list As per work list 70:10:20 As per work list As per work list
approved by the approved by the approved by the DPC approved by the DPC approved by the DPC
DPC DPC
26. Uttarakhand NA NA NA NA NA NA
27. West Bengal Population Population As per weighted index 60:20:20 50% Population and Marginal non-workers
on the basis of 2nd 50% on weighted and female literacy.
SFC recommendations index - Annexure-2
(see annexure-2)
ANNEXURE XII
Dr. Sudhir Krishna, Ministry of Panchayati Raj
Additional Secretary, Government of India
Tel.No.011-24122936 6th Floor, Samrat Hotel, Kautilya Marg
lR;eso t;rs
Fax No. 011-24122943 Chanakya Puri, New Delhi-110 021
Email<skrishna@nic.in>
D.O. Lr. No.N-11019/298/2009/BRGF 7th October, 2009
Sub: Annual Plans for 2010-11 for BRGF.
Dear
The BRGF is now in the 4th year of implementation. Experience has shown
that most States submit the Action Plans for the Development Grant and Capacity
Building Grant only during the later half of the financial year. This leads to
inadequate expenditure and poor programme performance. Now the Ministry has
decided to treat the BRGF Grants as lapsable, which makes it imperative to
prepare and approve the Annual Plans well before commencement of the financial
year, so that the first instalment for 2010-11 could be released in the first week
of April 2010.
Accordingly, I request you to prepare the Action Plans for 2010-11 for the
Development Grant and me Capacity Building Grant under BRGF in a manner
that the Plans duly approved by DPC and HPC are received in the Ministry by
31st January, 2010. The Annual Plans should be to the extent of 150% of the
Annual Entitlements and should include works of the Action Plans of 2008-09/
2009-10 that are likely to remain incomplete by 31.3.2010. A note on the role
of DPC/HPC is enclosed as Annexure.
Kindly prepare a calendar for (a) the Gram/Ward Sabha meetings;
(b) approvals of the PRIs and ULBs; (c) consolidation by DPC; and (d) approval
by HPC in a manner that would make it possible for the approved Plans to reach
the MoPR latest by 31st January, 2010. The calendar so worked out by you may
kindly be sent to me by fax/e-mail by 21st, October 2009.
With regards,
Yours sincerely,
Encl: As above.
Sd/-
(Sudhir Krishna)
Shri M.V.P.C.Sastry,
Principal Secretary,
Panchayati Raj & Rural Development Department,
Government of Andhra Pradesh,
A.P.Secretariat,
Hyderabad-500 022
153
Annexure of Annexure-12
As regards the Capacity Building component, tile HPC has the full power
to approve the Perspective/Annual Plans and also to revise the same at a later
date, for adequate reasons.
*****
154
ANNEXURE XIII
RASHTRIYA GRAM SWARAJ YOJANA
GRANTS RELEASED DURING 2009-10
(TRAINING & CAPACITY BUILDING COMPONENT)
155
APPENDIX I
The Committee sat from 1500 hrs. to 1730 hrs. in Committee Room
No. ‘B’, Ground Floor, Parliament House Annexe, New Delhi.
PRESENT
MEMBERS
Lok Sabha
2. Dr. Pulin Bihari Baske
3. Shri Kunvarjibhai Mohanbhai Bavaliya
4. Shri Sanjay Dhotre
5. Shri H.D. Kumaraswamy
6. Shri Govind Chandra Naskar
7. Shri Rakesh Pandey
8. Shri P.L. Punia
9. Shri A. Venkatarami Reddy
10. Shri Navjot Singh Sidhu
11. Shri Jagdanand Singh
12. Shri Makansingh Solanki
13. Shri Kodikkunnil Suresh
Rajya Sabha
14. Shri Ganga Charan
15. Sardar Sukhdev Singh Dhindsa
16. Dr. Ram Prakash
17. Shrimati Maya Singh
18. Shri Mohan Singh
19. Dr. (Smt.) Kapila Vatsyayan
156
SECRETARIAT
***Relevant portions of the Minutes not related to the subject have been kept separately.
157
APPENDIX II
The Committee sat from 1500 hrs. to 1730 hrs. in Committee Room
No. ‘C’, Ground Floor, Parliament House Annexe, New Delhi.
PRESENT
MEMBERS
Lok Sabha
Rajya Sabha
158
SECRETARIAT
***Relevant portions of the Minutes not related to the subject have been kept separately.
159
APPENDIX III
160
“All Parliamentary Publications including DRSC Reports are
available on sale at the Sales Counter, Reception, Parliament House
(Tel. Nos. 23034726, 23034495, 23034496), Agents appointed
by Lok Sabha Secretariat and Publications Division, Ministry
of Information and Broadcasting, CGO Complex, Lodhi Road,
New Delhi (Tel. Nos. 24367260, 24365610) and their outlets. The said
information is available on website ‘www.parliamentofindia.nic.in’.