The document outlines the inspection checklist for in-process and final inspection of internal coating application on field girth welds for Saudi Aramco projects. It details acceptance criteria, inspection procedures, and requirements for coating materials and application methods, emphasizing the use of approved products and adherence to specified standards. Additionally, it includes guidelines for inspections, repairs, and testing to ensure compliance with quality and safety standards.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views8 pages

Saic H 2060

The document outlines the inspection checklist for in-process and final inspection of internal coating application on field girth welds for Saudi Aramco projects. It details acceptance criteria, inspection procedures, and requirements for coating materials and application methods, emphasizing the use of approved products and adherence to specified standards. Additionally, it includes guidelines for inspections, repairs, and testing to ensure compliance with quality and safety standards.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

#

SAUDI ARAMCO ID/PIEU-31-Jul-2022 - REV.2022.07.00 (Standards Cutoff - July 31,2022) Rev 81 31-Jul-22
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process & Final Inspection of Internal coating
SAIC-H-2060 31-Jul-22 COAT-
Application on Field Girth Welds
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Requirements

The Vendor shall use only Saudi Aramco approved products. Approved
SAES-H-201,
Product is a coating material that has been approved by the RUS as
A1 Section 6.9
meeting the requirements of the applicable APCS or SAMSS. Only
& Section 4
approved products are allowed for use in Saudi Aramco jobs.

Internal FBE powder shall meet the requirements of 09-SAMSS-091 SAES-H-201,


A2
and SAES-H-002, APCS-102A/B/C. Para. 7.2

Robotic system shall be used for the inspection, surface preparation SAES-H-201,
A3
and coating application of internal FBE girth weld. Para. 7.4

Application of FBE coating shall be strictly in accordance with the


approved Vendor’s application procedure. FBE materials and method of SAES-H-201,
A3
application and equipment to be used shall be specified in this Para. 8.1.1
procedure

IInternal coatings used in potable water service must meet Food and
SAES-H-002,
Drugs Administration (FDA), National Sanitation Foundation (NSF) or
A4 Para. 5.2.2
equivalent requirements for suitability for use in contact with drinking
water. The certificate shall be renewed every 5 years

The coating system has been selected for specific service from the
SAES-H-002,
A5 various SAP Material Numbers specified in APCS-117 and approved by
Para. 5.3
CSD/Coatings Team . (Refer to Attachment #1)

Robotic crawler (consisting of blasting and coating equipment, dry film


thickness gauge and holiday detector) are used for onshore application
SAES-H-002,
for internal field girth welds of pipe strings with diameters ranging from 8
A6 Para. 5.2.4
to 36". Real time inspection
with a video camera must be conducted to ensure that blast cleaning
and coating application are done properly

For pipe diameters larger than 36", the coating application is done SAES-H-002,
A7 manually by qualified contractors with the approval of CSD/Coatings Para. 5.2.4
Team.

A semi-robotic system is used for offshore applications of specialty


SAES-H-002,
A8 liquid coating on internal girth welds with diameters ranging from 8" and
Para. 5.2.6
above qualified and experienced contractors shall be utilized.

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

A Pre-Production Trial (PPT) must be conducted at the start of each


shift to verify the correct functioning of the used equipment. The PPT SAES-H-201,
A9 should be conducted on a spool similar to the pipes to be coated. Tests Para. 8.1.6
in SAES-H-201, tables 2 and 3 shall be conducted by the Vendor and
the result shall be shared with Saudi Aramco inspector.

Personnel involved in protective coating activities has been qualified SAEP-316,


A10
and certified to perfom their task. Para. 5.1

B In-Process Inspection of Internal FBE Coating

During periods of bad weather (rain, high winds, etc.) cleaning and
SAES-H-201,
B1 coating operations will only proceed if protective canopies are used to
Para. 8.3.7
the satisfaction of the Saudi Aramco Inspector.

As soon as surface preparation is completed, the area to be coated


shall be cleaned of any deleterious matter by blowing with clean, dry,
oil-free compressed air. SAES-H-201,
B2
The area to be coated shall then be immediately heated to a Para. 8.3.2
temperature in accordance with the Powder Manufacturer's
recommendation using induction heating coil.

Application of phenolic primer prior to the application of FBE is carried


out using a machine to ensure that the travel of application is constant
SAES-H-002,
B3 and that the DFT will not exceed 25 microns (One mil) in all areas.
Para. 5.2.3
Note : One mil thickness is exceeded if the “peaks” of steel substrate
are no longer visible.

SAES-H-201,
Preheating shall be accomplished by induction heating coils.
Para. 8.3.3
B4 Preheating temperatures shall be measured with contact pyrometers.
&
Temperature crayons shall not be used.
Para. 8.3.5

As soon as the correct metal temperature has been reached, the


induction coil shall be removed from the welded joint area and the
SAES-H-201,
powder application equipment placed in position. Powder application
B5
shall start immediately. Coating shall be applied before the surface
Para. 8.3.6
temperature drops below the specified application temperature in the
manufacturer datasheet.

The machine shall apply powder to a uniform rate, to a correct width


centered on the girth weld, to the coating thickness specified Table-5, in
the least number of passes possible as per Table 5 . SAES-H-201,
B6
For APCS-102A, the DFT Range (μm) is 375-625 Para. 8.3.6.1
For APCS-102B, the DFT Range (μm) is 500-750
For APCS-102C, the DFT Range (μm) is 500-750

Dirt or other deleterious foreign material shall not contaminate the SAES-H-201,
B7
powder coated area during application and curing stages. Para. 8.3.6.2

C Final Inspection Visual Check or Video Camera:

Cameras fitted on the crawling machine shall be used during the


SAES-H-201,
C1 inspection of internally coated pipeline with diameters from 8" and
Para 9.2.5
above.

The finished coating shall have a uniform, glossy appearance and be SAES-H-201,
C2 free of defects such as holidays, fish eyes, lumps, dry spray, sags, and Para 9.2.4
runs.

Coating overlap shall be within the thickness specified in 09-SAMSS- SAES-H-201,


C3
091 for internal FBE Coating. Para 9.2.4

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

For accessible internal girth weld coating, the quality of cure shall be
checked on the first 5 joints of the job and every 20 joints thereafter, by
maintaining a MEK soaked pad in contact with the coating surface for SAES-H-201,
C4
one minute and then rubbing vigorously for 15 seconds. Para. 9.2.3
There shall be no softening of the coating or substantial color removal
from the coating.

SAES-H-201,
For un-accessible internal girth weld coating, conduct the cure test as Para. 9.2.3
C5
specified in SAES-H-201, paragraph 8.1.6 (This SAIC, item A9) &
Para. 8.1.6

Coating adhesion test is conducted as follows:


A) Using a sharp knife with a narrow width blade, make two,
approximately 13-mm long incisions through to the metal substrate to
form an X in accordance with ASTM D6677.
SAES-H-201,
B) Starting at the intersection of the X, attempt to force the coating from
Para. 9.4.1
C6 the steel substrate with the knife point
&
C) Refusal of the coating to peel constitutes a PASS.
Para. 9.4.2
D) Partial or complete adhesion failure between the
coating and the metal substrate constitutes a failure. Cohesive failure
caused by voids in the coating leaving a honeycomb structure on the
specimen surface also constitutes failure.

If the coating fails adhesion test adjacent field girth weld areas shall
also be tested until acceptable coatings are found on both sides of the
defective coating.
SAES-H-201,
C6 The defective coatings shall all be completely removed and the areas
Para. 9.4.4
recoated. At least one of the repaired areas shall be re-inspected, and
the subsequent inspection frequency shall be as given in SAES-H-201,
Para 9.4.3 (as stated in this SAIC, item# C7 below)

The Adhesion test is performed once every hour. When three


SAES-H-201,
C7 consecutive tests are successful, the frequency shall be reduced to
Para. 9.4.3
once every two hours.

D Dry Film Thickness (DFT) measurement & Holiday Testing

Thickness checks shall be made on each coated weld joint using an


approved, correctly calibrated dry film thickness gauge (e.g., Microtest, SAES-H-201,
D1
Elcometer or equivalent). The instrument shall be calibrated in Para. 9.2.2
accordance with SSPC-PA2.

A minimum number of 8 DFT readings shall be taken on each field joint


coating, 4 readings in each side, to verify compliance with the thickness
requirement in Table-5. SAES-H-201,
D2
For APCS-102A, the DFT Range (μm) is 375-625 Para. 9.2.2
For APCS-102B, the DFT Range (μm) is 500-750
For APCS-102C, the DFT Range (μm) is 500-750

Holiday test applied on 100% of the joints coated, at test voltage of 125 SAES-H-201,
volts DC per 25 microns of maximum coating thickness. Para. 8.3
D3
(Surface temp of pipe shall not exceed 80°C). 09-SAMSS-091
Test results are recorded on SATR-H-2008 Para 10.6.3

All holidays, imperfections, and damaged areas are carefully


identified with a waterproof marker. All markings shall be sufficiently
distant from the area to be repaired to allow surface preparation and SAES-H-201,
D4
coating application without being a detriment to the adhesion of the Para 8.3.2
repair coating. This procedure is applicable for accessible internal
coating.

E Repairs

All holidays, imperfections, and damaged areas are carefully identified SAES-H-201,
E1
and marked with a waterproof marker. para. 9.3.2

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

Girth welds showing more than 3 holidays shall be completely blasted SAES-H-201,
E2
off and the area recoated. Para. 9.5.1

The Pipe surface to be recoated shall be cleaned to remove all dirt and
damaged or disbonded coating using abrasive blasting or other
approved and suitable means. SAES-H-201,
E3
The edges of the original coatings shall be "feathered out" Para. 9.5.2
approximately 50 mm around the specific area to be
coated, and all dust wiped off before applying the patch coating.

To repair holidays in an accessible internal girth weld coating, two part


SAES-H-201,
E4 epoxy should be used in accordance with the coating manufacturer’s
Para. 9.5.4
requirement.

Patch-up coating is applied using materials & methods specified in the Approved Coating
E5
approved Repair Procedure. Procedure

Patch Repair areas are 100% holiday tested applying procedures used
SAES-H-201,
E6 for original coating (Refer to D3 above) and found acceptable, results
Para 9.5.5
recorded on SATR-H-008

To repair holidays in un-accessible internal girth weld FBE coatings,


use the cleaning machine to lightly abrade the existing girth weld
coating for band width of 200 mm (8 inches) to create enough
roughness, about 1.0 mil, for the adhesion of FBE powder coating. The SAES-H-201,
E7
coating shall be inspected for holidays and thickness. If a holiday is Para 9.5.3
detected, the field joint should be cut out to determine the cause. Cold
cutting method shall be used to prevent damaging the internal pipe
coating. Flame cutting is not allowed.

Remarks:
ATTACHMENTS # 1
REFERENCE DOCUMENTS:
1. SAES-H-201: General Specifications for External and Internal FBE Coatings of Pipeline Field Girth Welds (31 May 2018)
2. SAES-H-001, Coating Selection and Application Requirements for Industrial Plants and Equipment (23 May 2019)
3. SAES-H-002 Internal and External Coatings for Steel Pipelines and Piping, 22 February 2018
4. 09-SAMSS-091, Shop-Applied Internal FBE Coatings (17 Jan 2018)
5. SAEP-316 Performance Qualification of Coating Personnel (31 July 2016)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Comp of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

SAUDI ARAMCO ID/PIEU-31-July-2019 - REV.2019.07.00 (Standards Cutoff - July 31,2019) Rev.2019.07.00 31-Jul-19
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process & Final Inspection of Internal coating
SAIC-H-2060 15-Dec-19 COAT-
Application on Field Girth Welds
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Attachment- 1
REQUIREMENTS- SAUDI ARAMCO APPROVED PROTECTIVE COATING SYSTEMS for INTERNAL COATINGS

S.R. No APCS
Coating Specific Requirements for Coating Application
Type/Service Total DFT #1 #2
Specialty Liquid Coating Systems 1- Ceramic/Alloy Filled Epoxy 2- Glass Flakes
for Pumps, Valves, Piping, Fitting Coatings Filled Coatings
and Exchanger Boxes. Filler Coatings: Filler Coatings:
Service Temp: Up to 105C. Belzonas 1311/1111 Corroglass 100, 200,
Purchase Specifications: 09- Barrier Coatings: 600, Polyglass VEF
SAMSS-067 Belzonas 1341/1321/ Barrier Coatings &
1 APCS-28 750 – 1500 microns
SAMS Stock Numbers: N/A 1391S/1391T /5891 Top Coat:
Fluiglide and/or Veil
cote

Shop-Applied Fusion Bonded Epoxy APCS-102A shall not be used on the SAP M/N: (Refer to
for Internal Coating of Treated girth welds of any pipe and fittings SAES-H-002V)
Seawater and Potable Water coated with either APCS-28, APCS- Purchase Spec: 09-
Pipelines (Service Temp: Min. 0°C 375-625 117 or APCS-118. SAMSS-091.
2 APCS-102A
Max. 90°C ) microns

Shop-Applied Fusion Bonded Epoxy APCS-102B shall not be used on the SAP M/N: (Refer to
for Internal Coating of Formation girth welds of any pipe and fittings SAES-H-002V)
Water and Wet Crude Pipelines coated with either APCS-28, APCS- Purchase Spec: 09-
(Service Temp: Min. 0°C 500-750 117 or APCS-118. SAMSS-091.
3 APCS-102B Max. 95°C ) microns

Shop-Applied Fusion Bonded Epoxy Field Girth Weld Area: Crawler- Purchase Spec:
for Internal Coating of Sour/Sweet applied FBE or liquid coating APCS- (Refer to CSD. The
Gas Pipelines. 120 for internal girth welds of pipe coating shall be
(Primarily used for sour and sweet Pipe 625 – 750 microns strings. tested against the
4 APCS-102C gas pipelines excluding girth welds. Girth Welds: As per Coating operating
Temp: Min. 0°C Data sheets conditions.)
Max. 95°C)

Internal coating for water, oil or gas The coating system for specific
service. For spools, valves, service shall be selected from the
elbows, tees, wyes, nozzles, flanges various SAP Material Numbers
and other associated pieces of specified in APCS-117. SAP M/N:
piping systems. When the coating is In this regard, CSD/Coatings Team 1000180021,
glass fiber/flake reinforced, a final shall be contacted 1000180023,
coat of flow coating should be used 1000180276,
5 APCS-117 500 to 1500 microns
to ensure a good flow property. 1000180279,
(Service Temp: depends on coating 1000180328 and
product) 100018033
Purchase Spec: N/A

Saudi Aramco: Company General UseSaudi Aramco: Company General Use


#
#

Internal coating for oil, water and SAP M/N: N/A


gas service. Applied on internal Purchase
of spools, elbows, tees, wyes, Specification: N/A
APCS-118 nozzles, flanges and other
(This Coating System associated pieces of piping 1,500 to 3,000 microns The coating system for specific
6 is removed from SAES- systems. This coating type creates (depending on product service shall be recommended by
H-002 Revised on 8- a “pipe within a pipe” specification) CSD/Coatings Team.
May-2011) concept. (Service Temp: Min. -20°C
Max. 105°C or depends on coating
product)

Internal coating to prevent black Field and/or Shop Girth Weld Areas: SAP M/N: N/A
APCS-119 (This powder and/or enhance flow of Coating is not required Purchase
Coating System is sales gas in pipelines and piping Specification: API
7 removed from SAES- systems. (Service Temp: Min. 0°C 75 to 125 microns 5L2 or ISO 15741
H-002 Revised on 8- Max. 90°C)
May-2011)

Internal coating for water, oil or gas SAP M/N: N/A


service in the girth weld area Purchase Spec: N/A
applied by special semi-robotic 500 to 1,000 microns
8 APCS-120 machines.(Service Temp: depends (depending on product
on coating product) specification)

Saudi Aramco: Company General UseSaudi Aramco: Company General Use


#
#

R NUMBER

OAT-
RACTOR

ATINGS

or Coating Application
#2
2- Glass Flakes
Filled Coatings
Filler Coatings:
Corroglass 100, 200,
600, Polyglass VEF
Barrier Coatings &
Top Coat:
Fluiglide and/or Veil
cote

SAP M/N: (Refer to


SAES-H-002V)
Purchase Spec: 09-
SAMSS-091.

SAP M/N: (Refer to


SAES-H-002V)
Purchase Spec: 09-
SAMSS-091.

Purchase Spec:
(Refer to CSD. The
coating shall be
tested against the
operating
conditions.)

SAP M/N:
1000180021,
1000180023,
1000180276,
1000180279,
1000180328 and
100018033
Purchase Spec: N/A

Saudi Aramco: Company General UseSaudi Aramco: Company General Use


#
#

SAP M/N: N/A


Purchase
Specification: N/A

SAP M/N: N/A


Purchase
Specification: API
5L2 or ISO 15741

Saudi Aramco: Company General UseSaudi Aramco: Company General Use


#