Preparatory Study ON Gas-Fired Power Plant Development IN Southern Mozambique
Preparatory Study ON Gas-Fired Power Plant Development IN Southern Mozambique
PREPARATORY STUDY
ON
GAS-FIRED POWER PLANT DEVELOPMENT
IN
SOUTHERN MOZAMBIQUE
FINAL REPORT
MARCH 2013
Table of Contents
Page
i
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
ii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
iii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
v
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
vi
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
List of Tables
Page
vii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Table 3.5-9 Conclusion of Analysis Results under EDM’s Current Network Expansion
Plan System (2016) ············································································ 3-28
Table 3.7-1 Major Combined Cycle Power Generation Plants for Beluluane (GT
One-shaft Configuration) ····································································· 3-30
Table 3.7-2 Major Combined Cycle Power Generation Plants for CTM (GT One-shaft
Configuration) ·················································································· 3-30
Table 3.8-1 Comparison of the Candidate Sites ·························································· 3-31
Table 4.1-1 Applicable major CCGT model ································································ 4-1
Table 4.2-1 Type of CCGT configuration ·································································· 4-2
Table 4.2-2 Comparison of performance of CCGT configuration ······································ 4-4
Table 4.2-3 Construction cost of CCGT····································································· 4-5
Table 4.2-4 Feature of Type of CCGT Configuration····················································· 4-6
Table 4.2-5 Feature of Each Case of CCGT ······························································ 4-12
Table 4.3-1 Features of Condenser Cooling Systems ··················································· 4-13
Table 4.3-2 Comparisons of intake facilities ····························································· 4-17
Table 4.3-3 Feature of condenser cooling system ······················································· 4-19
Table 4.3-4 Overall judgment of steam turbine condenser cooling system ·························· 4-20
Table 5.1-1 Results of standard penetration test ··························································· 5-4
Table 6.1-1 Requirement unit starting hours of each mode ·············································· 6-2
Table 6.1-2 Requirement Plant Start Times for Design ··················································· 6-3
Table 6.1-3 Shaft Vibration Limits··········································································· 6-5
Table 6.2-1 Performance of Applicable GT Model························································ 6-6
Table 6.2-2 Performance of Applicable CCGT Model ··················································· 6-8
Table 6.2-3 New Models for 30 – 40 MW ································································ 6-14
Table 6.2-4 Summary of GT Exhaust Gas Bypass System ············································· 6-17
Table 6.2-5 GT and Steam Turbine Facilities With and Without Buildings ························· 6-18
Table 6.4-1 Design conditions ·············································································· 6-28
Table 6.4-2 Emission Limits of Pollutants ································································ 6-33
Table 6.4-3 Noise Standards ················································································ 6-33
Table 6.4-4 Effluent Standards ············································································· 6-34
Table 6.4-5 HRSG Circulation Comparison ······························································ 6-37
Table 6.4-6 Gas Flow Orientation Comparisons ························································· 6-38
Table 6.4-7 Gas Properties ·················································································· 6-40
Table 6.4-8 List of protected areas and fire fighting and detection systems types ·················· 6-42
Table 6.5-1 Generator specifications ······································································ 6-44
Table 6.5-2 Transformer specifications ··································································· 6-47
Table 6.5-3 Generator protection relays ··································································· 6-51
Table 6.5-4 Generator step-up transformer protection relays ·········································· 6-52
Table 6.5-5 Auxiliary transformer protection relays ···················································· 6-52
Table 6.6-1 Rainfall intensity for various return periods ··············································· 6-63
viii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
x
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Table 11.8-12 Prediction Result of the Maximum Future Concentration at the Ground Level
under the Special Conditions Resulting from Installation of New CCGT (1
Hour Value) ···················································································· 11-65
Table 11.9-1 Mitigation measures during construction phase ·········································· 11-70
Table 11.9-2 Mitigation measures during operation phase ············································· 11-72
Table 11.10-1 Environmental monitoring plan during construction phase ····························· 11-74
Table 11.10-2 Environmental Monitoring during operation phase ······································ 11-75
xi
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
List of Figures
Page
xii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 3.5-9 The Fluctuation Curves of Generator Voltage Angles under EDM’s Current
Network Expansion Plan System (2016) ··················································· 3-27
Figure 3.6-1 Location of Gas Station and Gas Pipeline Route ········································· 3-29
Figure 4.2-1 Type of CCGT configuration ··································································· 4-3
Figure 4.2-2 An example of a 50 MW class CCGT Plant Layout ········································ 4-7
Figure 4.2-3 An example of a CCGT Layout at the Beluluane site······································· 4-8
Figure 4.2-4 Typical CCGT Layout of a heavy duty GT··················································· 4-9
Figure 4.2-5 Typical CCGT Layout of an aero-derivative GT ············································ 4-9
Figure 4.2-6 Plant Layout (Case 1) ·········································································· 4-10
Figure 4.2-7 Plant Layout (Case 2) ·········································································· 4-11
Figure 4.2-8 Plant layout (Case 3) ··········································································· 4-12
Figure 4.3-1 Schematic diagram of cooling system ······················································· 4-15
Figure 4.3-2 Water intake facilities for the old Maputo coal-fired power plant ······················ 4-16
Figure 4.3-3 Intake facilities (conceptual drawing) ······················································· 4-16
Figure 4.3-4 Intake facilities (conceptual drawing) ······················································· 4-17
Figure 4.3-5 Assessment of soundness of existing intake facilities ···································· 4-18
Figure 4.3-6 Schematic Diagram of Cooling System ····················································· 4-19
Figure 4.3-7 Sea area development around project site ·················································· 4-20
Figure 5.1-1 Topographical situation around CTM Maputo ··············································· 5-1
Figure 5.1-2 Geological setting around the Project site ···················································· 5-2
Figure 5.1-3 Location of boreholes ············································································ 5-3
Figure 5.2-1 Cyclone frequency and paths ··································································· 5-5
Figure 5.2-2 Satellite image showing the progression of the first tropical depression that hit
Mozambique in early February ································································ 5-6
Figure 5.2-3 Daily precipitation recorded at Maputo City from February 3 to 7, 2000 ··············· 5-7
Figure 6.1-1 Operation time limitation ········································································ 6-4
Figure6.2-1 Ambient Temperature Performance Characteristics Curve ································· 6-9
Figure 6.2-2 Heat Balance Diagram of 2 x LM6000PD Sprint at the rated site conditions
performance ···················································································· 6-10
Figure 6.2-3 Heat Balance Diagram of 2 x LM6000PD Sprint at the maximum capacity site
conditions ······················································································· 6-11
Figure 6.2-4 Heat Balance Diagram of 2 x H-25 at the rated site conditions performance ········· 6-12
Figure 6.2-5 Heat Balance Diagram of 2 x H-25 at the maximum capacity site conditions ········ 6-13
Figure 6.2-6 GT Package ······················································································ 6-19
Figure 6.3-1 Terminal Point ·················································································· 6-27
Figure 6.4-1 Plant Layout ····················································································· 6-30
Figure 6.4-2 Example of Gas Turbine and HRSG························································· 6-31
Figure 6.4-3 Example of Steam Turbine with Air Cooled Condenser ································· 6-32
Figure 6.4-4 Water Treatment Flow (Water Balance) ···················································· 6-41
Figure 6.5-1 Outline of electrical system ··································································· 6-44
xiii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 8.5 3 Conceptual Figure of Maintenance Management (By Level) ···························· 8-20
Figure 8.5 4 Standard Management Flow Based on PDCA ············································· 8-21
Figure 8.5 5 Heinrichs Principle Disaster Pyramid ······················································· 8-22
Figure 8.5 6 Environmental Management Systems (Plant Level) ······································ 8-34
Figure 8.5 7 Environmental Management System (Public Level) ······································ 8-36
Figure 9.3-1 Price trend of combined cycle power facilities ·············································· 9-7
Figure 9.3-2 Proportion of Equipment FOB Price in EPC Cost··········································· 9-8
Figure 10.4-1 Average Sales Price of Electricity and Willingness to Pay ···························· 10-19
Figure 11.2-1 Average monthly highest and lowest temperatures at Station No. 64
(2009–2011) ···················································································· 11-2
Figure 11.2-2 Average monthly humidity at station No. 64 (2009–2011) ···························· 11-3
Figure 11.2-3 Average monthly solar radiation at Station No. 64 (2009–2011) ···················· 11-3
Figure 11.2-4 Wind rose for Maputo at Station No. 64 (2007–2011) ································· 11-4
Figure 11.2-5 Wind class frequency distribution at Station No. 64 (2007–2011) ·················· 11-4
Figure 11.2-6 Monthly rainfall, Maputo 2007–2011 ····················································· 11-5
Figure 11.2-7 Location of air quality monitoring points ················································ 11-6
Figure 11.2-8 Typical sound levels (dB(A))······························································· 11-8
Figure 11.2-9 Location of noise monitoring points ······················································ 11-9
Figure 11.2-10 Average noise level at MP11 over 9 days period (Nov 23–Dec 01/2012) ········· 11-11
Figure 11.2-11 Location of water quality monitoring points ··········································· 11-15
Figure 11.3-1 Schematic presentation of the EIA process in Mozambique ························· 11-27
Figure 11.3-2 Organization structure of MICOA ························································ 11-33
Figure 11.8-1 Wind rose (Average from 2009 to 2011) ················································ 11-56
Figure 11.8-2 Wind rose (2009–2011) ···································································· 11-57
Figure 11.8-3 Prediction Result of the Maximum Concentration at the Ground Level of
NO2 under the Normal Conditions Resulting from Installation of New CCGT
(1 Hour Value) for Atmospheric Stabilities A and B ··································· 11-60
Figure 11.8-4 Prediction Result of the Maximum Concentration at the Ground Level of
NO2 under the Normal Conditions Resulting from Installation of New CCGT
(1 Hour Value) for Atmospheric Stabilities C and D ··································· 11-61
Figure 11.8-5 Predicted Concentration Distribution Chart of NO2 (Southwest Wind,
Stability A, Wind Speed 1.0 m/s) ·························································· 11-63
Figure 11.8-6 Predicted Concentration Distribution Chart of NO2 (Southwest Wind,
Stability B, Wind Speed 4.0 m/s) ·························································· 11-63
Figure 11.8-7 Predicted Concentration Distribution Chart of NOx (Southwest wind,
Maximum Level at the Stability Level, C-1 Hour Value) ······························ 11-64
Figure 11.8-8 Predicted Concentration Distribution Chart of NOx (Southwest Wind,
Maximum Level at the Stability Level, D-1 Hour Value) ······························ 11-64
xv
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 11.8-9 Prediction Result of the Maximum Future Concentration at the ground level
of NO2 under the Special Conditions Resulting from Installation of New
CCGT (1 Hour Value) ······································································· 11-66
Figure 11.11-1 Participants from the Heads of 10 Houses, Urban Blocks 40 and 40a ············· 11-76
Figure 11.11-2 Participants from the Companies and Institutions adjacent to the Site ············· 11-76
xvi
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Abbreviations
Abbreviation English Original Language
(Portuguese language)
ACC Air Cooled Condenser
ADB Asian Development Bank
AdeM Águas de Moçambique
AFD French Development Agency L'Agence Française de Développement
AGFUND Arab Gulf Programme for Development
ANE National Roads Administration Administração Nacional de Estradas
APFR Automatic power factor regulator
AQR Automatic reactive power regulator
ASME American Society of Mechanical Engineers
ASTM American Society of Testing and Materials
AVR Automatic voltage regulator
BCF Billion cubic feet
BCP Boiler circulating pumps
BDM Break down maintenance
BOP Balance of Plant
BS British Standards
C/P Counterpart
CBM Condition based maintenance
CCR Central Control Room
CCGT Combined Cycle Gas Turbines
CCTV Closed-circuit television
CEMS Continuous Emission Monitoring System
CF Conversion Factor -
CLDC Central load dispatching center
Mozambican Hydrocarbon Company
CMH Companhia Moçambicana de Hidrocarbonetos
(no official English name)
COD Commercial operation date
CPF Central Processing Facility
CPI Investment Promotion Centre Centro de Promocao de Investimentos
CPU Central Processing Unit
CTM Maputo Thermal Power Station Central Térmica de Maputo
DCS Distribution control system
DIN German standards Deutsches Institut fur Normung
DLP Defect Liability Period
Provincial Directorate for Co-ordination of
DPCA Provinciais para Coordenação da Acção Ambiental
Environmental Affairs
DSCR Debt Service Coverage Ratio -
DSR Debt Service Ratio
Mozambican Electricity Company
EDM Electricidade de Moçambique
(no official English name)
EIA Environmental Impact Assessment
EIRR Economic Internal Rate of Return
EIS Environmental Impact Study
EIB European Investment Bank
Empresa Nacional de Hidrocarbonetos de
ENH Mozambican National Hydrocarbon Company Moçambique
EOH Equivalent operation hours
Engineering, Procurement and Construction
EPC
(contract)
Environmental Pre-Feasibility Study and Scope Estudo de Pré-Viabilidade Ambiental e Definição do
EPDA
Definition Âmb
EPRi Electric Power Institute, Inc.
ESIA
Environmental and Social Impact Assessment
EU European Union
FCT Fault clearing time
xvii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Original Language
Abbreviation English
(Portuguese language)
FDI Foreign Direct Investment
FIDIC International Federation of Consulting Engineers Fédération Internationale Des Ingénieurs-Conseils
Fundo de Investimento e Património de
FIPAG Water Supply Investment and Assets Fund
Abastecimento de Água
FIRR Financial Internal Rate of Return
FOB Free on board
FS Feasibility Study
Mozambican National Rural Electrification Fund
FUNAE Fundo de Energia
(no official English name)
GDP Gross Domestic Product
Deutsche Gesellschaft für Internationale
GIZ German Agency for International Cooperation
Zusammenarbeit
GMCB Generator main circuit breakers
GNI Gross National Income
GoM Government of Mozambique
GOV Governor control unit
GPS Global positioning system
GS Gas Station
GSA Gas Sales Agreement
GT Gas Turbine
HCB Cahora Bassa Hydroelectric Hidroeléctrica de Cahora Bassa
HHV Higher Heating Value -
HQ Head office
HRSG Heat Recovery Steam Generator
JIS Japanese Industrial Standard
I&C Instrumentation and control
I/O Input/ output
IDA International Development Association
IDC Interest During Construction
IFC International Financial Corporation
INAHINA National Institute of Hydrography and Navigation Instituto Nacional de Hidrografia e Navegação
INP National Petroleum Institute Institudo Nacional de Petróleos
IPP Independent Power Producer
JICA Japan International Cooperation Agency
JIS Japanese Industrial Standards
L1, L2, L3 Line bus
LAN Local area network
LC Local Currency -
LCD Liquid Crystal Display
LHV Lower Heating Value
LCOE Levelised Cost of Electricity
LTPM Long Term Parts Management
LTSA Long Term Service Agreement
MCC Motor control center
MDF Main distributing frame
ME Ministry of Energy
MGC Matola Gas Company
MGJ Million gigajoules
MICOA Ministry of Coordination of Environmental Affairs Ministério para Coordenação de Acção Ambiental
MMR Ministry of Mineral Resources
MOH
MPDC Maputo Port Development Company
MSL Mean Sea Level
MUSD Millions of US Dollars
MZN Mozambique Metical
N Neutral bus
NEDAP National Energy Development and Access Program
xviii
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Original Language
Abbreviation English
(Portuguese language)
NGV Natural Gas Vehicle
NGO Nongovernmental Organization
NOK Norwegian Krone
Government of Norway Agency for Development
NORAD
Cooperation
NPFA National Protection Fire Association
O&M Operation and Maintenance
OC Oriental Consultants Co., Ltd.
ODA Official Development Assistance
OEL Over excitation limiter
OEM Original equipment manufacturers
OH Overhaul
OJT On the job training
ONAF Oil natural air forced
ONAN Oil natural air natural
PDCA Plan-do-check-act
PDCA Provincial Directorate for Environmental Affairs
PIP Project implementation procedure
PIU Project Implementation Unit
PM Particulate matter
PMU Project Management Unit
POED Project for Entrepreneurial Development
PPA Petroleum Production Agreement
PQ Product quality
PRS Pressure Reduction Station
PS Power station
PSA Production Sharing Agreement
PSS Power system stabilizer
PSS/E Power System Simulator for Engineering
PVB Private branch exchange
Republic of Mozambique Pipeline Investments
ROMPCO
Company Ltd.
RSA Republic of South Africa
SA Surge arrestor
SADC Southern African Development Community
SAPP Southern African Power Pool
SBU Strategic Business Unit
SCADA Supervisory Control and Data Acquisition
SEIA Simplified Environmental ImpactAssessment
SER Simplified Environmental Report
Swedish International Development Cooperation
SIDA
Agency
SOAPP State of the Art Power Plant
SPI Sasol Petroleum International Ltd.
SPT Sasol Petroleum Temane Limitada
ST Steam turbine
Mozambique Regional Transmission Backbone Projecto Regional de Transporte de Energia,
STE
Project Centro-Sul
SUS Steel Use Stainless
TAC Technical Assessment Commission
TBM Time-based maintenance
TCF Trillion cubic feet
TEPSCO Tokyo Electric Power Services Co., Ltd.
TFD Time of Flight Diffraction
TOR Terms of Reference
TQM Total quality management
UAT Unit auxiliary transformer
xix
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Original Language
Abbreviation English
(Portuguese language)
UEL Under excitation limiter
UPS Uninterrupted power supply
USD US dollars
USGS U.S. Geological Survey
UT Ultrasonic Testing
VAC Volts alternating current
VAT Value Added Tax
VCB Vacuum circuit breaker
VDC Volts direct current
VT Voltage transformer
WACC Weighted Average Cost of Capital
WB World Bank
WHO World Health Organisation
WTP Willingness-to-pay
XLPE Cross-linked polyethelene
xx
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Appendices
xxi
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
EXECUTIVE SUMMARY
ES-1
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The Cahora Bassa Hydroelectric Power Plant (“HCB”) with an output of 2,075 MW, the
major power source in Mozambique, is linked to the network for the central and northern
areas. A part of the generated power is transmitted to the central and northern areas by means
of a 220 kV AC transmission line and the power supplied meets the load of these areas.
Power is also sent to a neighboring country, Zimbabwe, by means of a 400 kV AC
transmission line. However, the majority of the power generated by HCB is sent to the
Apollo substation in South Africa by a 535 kV DC transmission line and it is then sent to the
Southern African Power Pool (“SAPP”).
Since the system for the southern area, which covers Maputo, is located over 1,000 km from
HCB, power is imported from SAPP via the networks of South Africa and Swaziland by
means of a 400 kV AC transmission line. As a result, more than 80% of domestic demand is
supplied by re-imported power.
EDM has been conducting an update study to the existing study, “Mozambique Electricity
Master Plan Study”, which was completed in 2004. The update study, “Update of Master
Plan 2010-2027”, is scheduled to be completed by April 2013. Based on the update of the
master plan, it is expected that the power supply plan for supply stable power will get off the
drawing board.
ES-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
of the system, fuel supply constraints, condenser cooling method, and selectivity of CCGT
equipment were objectively and comprehensively compared and studied.
As a result, the CTM site was selected as the project site for a power plant up to 100 MW.
The major determining factor was transmission network capacity constraint.
5. Site Conditions
The meteorological, geological and topographical characteristics regarding the project site are
summarized as follows:
The ground level of the site was raised by 1.5 to 2.0 meters when the former coal-fired
power plant was constructed in the 1950s, and the present ground level is approximately 3.3
m above mean sea level (“M.S.L.”) of Port Maputo.
Since the embankment of the highway (EN2) located to the north acts as a topographic
divide, rain that falls on the north side of the highway generally does not flow in the
direction of the CTM site.
As a result of field investigation by a standard penetration test (“SPT”) conducted at CTM
ES-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
site, it was found that all boreholes feature a minimum of 4 consecutive SPT refusals (> 50
blows per 25 mm penetration), starting at depths ranging between 5 m and 15 m.
Tropical storms hit Mozambique once a year on average and lesser-magnitude tropical
depressions hit the country three to four times per year.
In February 2000, two tropical cyclones landed in Mozambique and devastated the economic
and social infrastructure across the country. The maximum total precipitation of 653 mm was
a record for this month and accounted for approximately 80% of Maputo’s normal annual
precipitation of 800 mm.
On February 6, 2000, the turbine buildings in CTM site suffered from flood damage. This
damage was not caused by inundation from river water or storm surges, but was due to poor
drainage within the CTM.
6. Basic Design
The basic design of the power plant is as follows:
The proposed project at the CTM site has the following features:
(i) Major specifications
- Rated generation capacity: 70 to 110 MW
- Thermal efficiency (LHV): More than 50%
- Capacity factor: More than 80% (for base power supply)
- Fuel: Natural gas from Pande gas field
(ii) Major equipment
Combined Cycle Gas Turbine (“CCGT”) plant
- GT and generator: 2 sets
- ST and generator: 1 set
- Heat recovery steam generator: 2 sets
- Air cooled condenser: 1 set
- Auxiliary facilities such as 11 kV switch gear, step-up transformer, and fuel
gas supply facility, water supply tank, etc.
Civil works such as foundation piling, buildings
Other facilities for water treatment, wastewater treatment, and fire fighting
The control and monitoring system that will realize all-automatic operation of the generator
facility will be configured as a DCS that takes technology and costs into consideration. The
DCS facility will make it possible to control and monitor the whole generator facility,
including control and monitoring of common facilities.
ES-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
9. Project Cost
Project cost is as follows:
Project cost was estimated based on the proposed project implementation schedule, price
trends of combined cycle power facilities, construction prices in Mozambique, required
manpower for consulting services, required activities and materials for operation and
maintenance (“O&M”) and other results of studies related to project cost estimates, and the
results of the project cost estimate is summarized in the following table.
JICA Finance Portion Cost (Million USD)
Power plant construction and associated works (EPC cost) 124,171
LTSA, training and spare parts 18,403
Consulting services 14,344
Contingencies and interest during construction 26,387
Total of JICA Finance Portion 183,305
Non Eligible Portion (site preparation, administration cost and tax) 11,487
Total 194,791
ES-5
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
ES-6
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Although there would be some impacts on air quality, noise & vibration and wastes
arising from construction works, these impacts are minor and temporary, and can be
readily reduced to a permissible level by application of appropriate mitigation measures.
- During operation
Since the power plant shall be designed and built to meet applicable environmental
regulations and standards in Mozambique, there is no significant environmental issues
expected.
Land acquisition and resettlement are not necessary for the Project because the proposed
site is within the vicinity of the existing power plant owned and operated by EDM, and
there are no resettlements involved in the Project because there are no legal and/or illegal
settlers that will be displaced.
ES-7
Chapter 1
Introduction
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Chapter 1 Introduction
1-1
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Mozambiqu
CTM Site
Maputo
Maputo
Matola city
Maputo city
Maputo
1-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
This study shall be organized and implemented based on the study items in Table 1.3-1
consistent with the Japan International Cooperation Agency’s (“JICA’s”) operational guidance.
Stage-1 Basic Survey: Background and consistency with key national plans
4.1.1 Submission and discussion of Inception Report
(1) Analysis of relative documents and planning of surveys
(2) Draft of Inception Report
(3) Discussion of Inception Report with JICA and counterpart (“C/P”)
4.1.2 Review of background and consistency with key national plans
(1) Review of the power development master plan of Mozambique
Review of track records and plans of other international donors for the
(2)
power sector
(3) Review of social and economic status of Maputo and surrounding area
Review of power demand forecasts, operational records and development
(4)
plan of Mozambique’s power system
(5) Confirmation of comprehensive benefits from the Project
Stage-2 Selection of the project site
4.1.3 Selection of the project site
(1) Comparative study
(2) Draft and discussion of Progress Report for decision making
Stage-3 Feasibility study
4.2.1 Survey of relevant information for basic design
(1) Site conditions
(2) Socio-economic conditions
(3) Fuel gas supply plan
(4) Power transmission and power system stability
4.2.2 Planning of project outline
(1) Purpose of the Project
(2) General overview of Combined Cycle Power Plant (“CCPP”)
Terms of Reference (“TOR”) and scope of works for the consulting service
(3)
to the project
4.2.3 Basic design
(1) Plot plan
(2) Type of power plants and unit capacity
(3) Fuel gas supply plan
(4) Condenser cooling system
(5) Civil work
(6) Mechanical work
(7) Electrical work
(8) Common facility
(9) Substation and transmission facility
(10) Other auxiliary equipment
(11) Transportation route for major parts of equipment
4.2.4 Planning of procurement and construction
4.2.5 Project implementation plan
4.2.8 Socio-environmental consideration
(1) Legal regulation of socio-environmental consideration
1-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 1.3-2 shows every component of the Study and the linking structure. The implementation
schedule of the Study is shown in Figure 1.3-2.
1-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
1-5
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Events 1st Survey in Japan 2nd Survey in Japan 3rd Survey in Japan
Stage-1 Basic Survey
Review of the power development master plan Stage-3 Feasibility Study
1st Workshop in 2nd Workshop in
Power demand forecast and supply balance Setting development scale Workshop in
Power system development plan Maputo Power demand forecast Maputo
Transmission loss, generation cost, tariff Attendance Japan(around 1
Gas demand forecast Attendance from
Review of track records and plans of other international donors
Review of social and economic status of Maputo and surrounding area
from C/P Comparative study of plant type, power output, and unit C/P (EDM, week)
Confirmation of comprehensive benefits from the Project (EDM, capacity MOE, etc.), JICA
Visits to CCPP,
Improvement of electrification rate and planned outage rate MOE, etc.), Analysis of transmission capacity mission, and
Power Development Improvement of living standards in Maputo area turbine factory,
JICA JICA Study
Job creation Stage-4 Project Implementation Plan etc.
Planning Study mission, and Financial and economic analysis, and setting up project monitoring Team
JICA Study index Confirmation of
Team Listing of points to consider for ODA projects
feasibility and
Selection of Stage-3 Feasibility Study decision of
the project Site survey project
Stage-1Basic Survey
Review of up-front surveys and data collection site Environmental and social considerations survey implementation
Topographic, geological, and oceanographic surveys plan
Facility design
Design of power block and auxiliary facility
Stage-2 Comparative Study of Candidates Estimation of EPC cost and other costs
Pros and cons analysis by criterion Procurement and transportation
Draft report of basic design and construction plan
Land, transportation access
Socio-environmental consideration
Geography, geology, vegetation, meteorology, natural disasters
Collection and review of data required for assessment of
Condenser cooling system, cooling water, industrial water, fuel
indicated/predicted environmental and social impacts
Power network constraints Assessment of indicated/predicted environmental and social
Socio-environmental considerations impacts
Over dimension cargo Stakeholder meeting and workshops
Technical and Assistance for making compensation plans
Socio-Environmental
Study
Hideyuki OKANO
(Fuel Planning)
Masaho AOKI
(Electric & IC)
Teruhiko TSUMURA
(Chief Economical & Financial Analysis) Exchange
Information,
Discussion Toshiyuki KOBAYASHI
Takahiro MOJI (Cooling system)
(Assistant Economical & Financial
Analysis)
Mitsuru MIYASHITA
Discussion
Info.
Exchange
(Power Civil)
Exchange
Environmental and Social Consideration
Information, Kazutora KONO
1-7
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
When the need arises for smooth operation of the Survey in any part thereof, MOE and/or EDM
are kindly requested to assign counterpart personnel, who will work closely with the members
of the JICA Study Team, on a full time or a part time basis depending on the requirements, to
the greatest extent as is practically possible. The expected roles of the counterpart personnel are,
for instance, as follows:
To make appointments and to set up meetings with authorities, departments and other
organizations and firms the JICA Study Team intends to visit for the purpose of this
Survey.
To attend field surveys and other locations with the JICA Study Team and to provide any
assistance in relation to accommodation, work rooms, adequate transportation, obtaining
permissions if required, etc.
To assist and to advise the JICA Study Team as much as possible on their collection of data
and information.
1-8
Chapter 2
Table 2.1-1 Total Population, Area and Population Density by Province, 2011
Percent
Provinces Population Area km2 Inhab/km2
Struct.
Total 23,049,621 100 799,380 29
Niassa 1,415,157 6 129,056 11
Cabo Delgado 1,764,194 7.6 82,625 21
Nampula 4,529,803 19.2 81,606 56
Zambezia 4,327,163 18.7 105,008 41
Tete 2,137,700 9.2 100,724 21
Manica 1,672,038 7.3 61,661 27
Sofala 1,857,611 8 68,018 27
Inhambane 1,402,245 6.5 68,615 20
Gaza 1,320,970 6.1 75,709 17
Maputo Province 1,444,624 6.3 26,058 55
Maputo City 1,178,116 5.1 300 3,927
2-1
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
weather shocks that reduced the yields, decline trade due to increase in international food and
fuel, among others.
In recent years, the country has undertaken a series of economic reforms. Almost all aspects of
the economy have been liberalized to some extent. Mozambique has considerable mineral
resources although exploitation has been limited by its recently ended civil war. But the large
reserves of natural gas in the Pande and Temane of Inhambane province have exploited, which
is set to become a major source of foreign exchange.
Agriculture is the most important sector and is mostly carried out by peasant farmers who
cultivate 92% of the total cropland. Commercial farming occupies only 250,000 hectares, or 8%
of the total land cultivated. Though the contribution of agriculture to the Gross Domestic
Product (GDP) is between 25% and 30%, an estimated 80% of the country's population gains its
livelihood from this sector emphasizing the importance of agriculture to the nation. Most of the
agricultural activities rely on rain that falls from November to December and are limited to one
season.
Mozambique is one of the largest power producers in the SADC region. Hydropower is
Mozambique’s most important commercial energy resource, with the potential estimated at
about 14,000 MW, of which about 2,300 MW has so far been developed, 2,075 MW at Cahora
Bassa Dam located at the Zambezi River and the remaining is distributed among a number of
sites throughout the country. The capacity at Cahora Bassa is committed to the supply electricity
to Mozambique, Zimbabwe, and Malawi. However, the majority of the power generated by
2-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Cahora Bassa is sent to the Apollo substation in South Africa and is then sent to the Southern
African Power Pool.
Apart from hydro resources, Mozambique has not yet to exploit its oil reserves. Presently,
accumulation of natural gas deposits have been discovered on-shore in the provinces of the
aforesaid Inhambane and Cabo Delgado. According to statistical estimate, the total natural gas
reserves in Mozambique are 4.8 to 8.8 TCF in the Mozambique Basin and 52.5 to 110 TCF in
the Rovuma Basin. The majority of production of gas is now being exported to South Africa
through a pipeline.
Moreover, Mozambique has three relatively large known deposits of coal located in the
Province of Tete. Total coal reserves are estimated at about three billion tonnes. Coal has been
produced since 1940, from Moatize mines, both for in country use and export. Although the
operations had to be suspended due to civil war, it restarted the activities.
(1) Macroeconomic
The Gross Domestic Production (GDP) per capita of the country was estimated at around USD
635 in 2012 and had steadily increased during the period of 2005 to 2012 (refer to Table 2.1-2).
The GDP between 2005 and 2012 had also increased. Fiscal performance remained strong until
2012, with government revenue rising from 20.12% of GDP in 2005 to 28.74% of GDP in 2012.
Government Gross Debt had decreased from 131.87% of GDP in 2000 to 39.98% in 2012.
Receipts of Official Development Assistance (ODA), which has increased year by year,
amounted to USD 2,013 million in 2009 and ODA will be continuously carried out, while the
amount of the Foreign Direct Investment (FDI) recorded at USD 881 million in the same year.
The detailed condition of FDI will be described afterward.
Indicators Unit 2000 2005 2006 2007 2008 2009 2010 2011 2012
National Accounts
GDP at Current Prices Billion US $ 4.138 6.579 7.215 8.121 9.943 9.967 9.481 12.830 14.27 (f)
GDP per Capit at Current Prices US$ 236.46 336.49 361.80 399.26 479.23 471.00 439.25 582.61 (f) 635.44 (f)
Real GDP Growth Rate % 14.7 8.4 8.7 7.3 6.8 6.4 8.1 … …
Government Finance
Government Revenue % GDP 21.93 20.12 22.93 25.2 25.34 27.06 29.68 29.44 (f) 28.74 (f)
Total Expenditure and Net Lending % GDP 23.66 22.90 26.99 28.15 27.81 32.57 33.64 34.38 (f) 35.06 (f)
Overall Deficit (-) / Surplus (+) % GDP -5.3 -3.5 -0.5 -2.4 -2.7 -5.1 -5.4 … …
External Sector
Exports Volume Growth (Goods) % 19.95 16.78 10.45 -3.499 8.713 -1.195 -9.380 4.278 (f) 1.459 (f)
Imports Volume Growth (Goods) % -13.68 -0.0990 5.561 1.495 19.67 13.90 -2.061 22.83 (f) 9.504 (f)
Current Account Balance Billion US $ -0.697 -0.7610 -0.7730 -0.7850 -1.179 -1.220 -1.113 -1.667 (f) -1.818 (f)
Current Account Balance % GDP -16.66 -11.56 -10.72 -9.670 -11.86 -12.24 -11.74 -12.99 (f) -12.74 (f)
Debt and Financial Flows
Government Gross Debt % GDP 131.87 80.96 53.61 41.92 42.14 40.13 39.51 33.20 (f) 39.98 (f)
Net Official Development Assistance Million US $ 906.2 1,297.00 1,605.70 1,778.10 1,996.10 2,013.30 … … …
Net Foreign Direct Investment Million US $ 139.2 107.9 153.7 427.4 591.6 881.2 … … …
(Source: ADB Statistics Department; IMF: World Economic Outlook, October 2010 and International Financial Statistics, April
2011; ADB Statistics Department: Development Data Platform Database, April 2011. United Nations: OECD, Reporting),
Notes… Data Not Available; (f) Forecast
As the GDP by sector is shown in Table 2.1-3, the agriculture, livestock, hunting and forestry
2-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
sector has a 24% share of GDP and is the largest sector in the country, followed by
manufacturing sector, transport, storage and communication sector, trade sector, real estate
activities, rentals and services sector, financial activities sector, water and electricity sector and
education sector, public administration, defense and social security sector and construction
sector and so forth. Those shares have hardly changed for the last ten years. The proportion of
the sector of electricity, gas and water had been almost stable 4.4% to 4.8% during the period of
2001 to 2010 in the above table.
2-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
2005 2006 2007 2008 2009 2005-2009 2005 - 2009 Mozambique Total
No. of Committed No. of Committed No. of Committed No. of Committed No. of Committed No. of Committed No. of Committed
Sector Employ investment Employ investment Employ investment Employ investment Employ investment Employme investment Employm investment
ment (MZN) ment (MZN) ment (MZN) ment (MZN) ment (MZN) nt (MZN) ent (MZN)
Transport &
209 5,852,549 1,388 158,026,142.00 515 57,681,514 356 83,813,954 365 17,794,625 2,833 323,168,785 4,134 439,361,325
communication
Agriculture and
25 10,500,000 147 3,203,875 172 13,703,875 816 53,397,122
fishiries
Agriculture and
3,511 112,771,297 1,232 23,073,927 2,401 57,314,514 1,698 31,147,316 1,100 37,834,066 9,942 262,141,121 49,545 6,303,139,512
fishiries
Construction 50 1,150,000 83 1,983,036 933 7,529,977 298 13,426,833 206 3,975,800 1,570 28,065,646 4,375 149,649,500
Industrial 708 28,592,271 959 21,777,570 5,079 325,242,053 2,065 137,485,597 858 21,291,616 9,669 534,389,108 18,705 892,668,673
Mineral
resources and 154 15,638,650.00 292 23,000,000 446 38,638,650 1,903 6,627,891,567
energy
Services 1,445 43,877,978 1,445 43,877,978 3,545 167,730,328
Tourism &
2228 47,511,506 1,709 368,823,696 605 28,044,286 1,615 68,165,022 73 8,002,172 6,230 520,546,682 17,139 1,310,411,321
hotels
Banking,
insurance, and 84 1,900,000 62 2,933,500 20 1,532,857 29 12,833,333 195 19,199,690 394 39,883,750
leasing
Others 540 14,545,747 6,378 48,766,443 314 51,957,706 562 32,382,301 7,794 147,652,197 8,651 239,389,817
TOTAL 7,484 227,962,021 12,103 648,384,314 9,892 539,802,908 6,623 379,254,357 4,194 135,980,132 40,296 1,931,383,732 109,207 16,223,522,916
No. of Committed No. of Committed No. of Committed No. of Committed No. of Committed No. of Committed
District Employ investment Employ investment Employ investment Employ investment Employ investment Employme investment
ment (MZN) ment (MZN) ment (MZN) ment (MZN) ment (MZN) nt (MZN)
City of Maputo 1,322 46,336,999 9,910 558,554,512 2,438 140,704,758 1,022 129,724,692 14,692 875,320,961
Matola 301 9,978,178 844 29,333,173 3,692 52,720,855 2,470 90,051,628 1,361 64,810,142 8,668 246,893,976
Boane 323 14,894,037 25 5,435,000 718 174,885,695 398 41,167,965 158 4,503,000 1,622 240,885,697
Inhaca 15 320,800 15 320,800
Machava 18 187,217 1,152 14,050,606 1,170 14,237,823
Magude 25 2,857,143 10 160,000 35 3,017,143
Manhiça 10 325,000 514 4,280,000 265 9,001,200 460 2,570,100 1,249 16,176,300
Marracuene 5,000 50,000,000 30 450,000 660 114,714,286 366 4,915,652 214 6,549,119 6,270 176,629,057
Matutuine 335 3,883,447 149 44,609,432 1,738 51,655,714 805 82,301,903 687 41,534,199 3,714 223,984,696
Moamba 150 99,500,000 534 4,297,680 1,141 18,969,300 112 1,462,966 1,937 124,229,946
Namaacha 601 5,544,517 117 520,800 61 1,732,731 50 500,000 829 8,298,048
Xinavane 95 1,389,285 95 1,389,285
TOTAL 7,484 227,962,021 12,103 648,384,314 9,892 539,802,908 6,623 379,254,357 4,194 135,980,132 40,296 1,931,383,732
Total
15,113 482,186,373 19,372 850,209,001 27,469 8,062,268,793 20,495 1,080,254,032 26,758 5,748,620,716 109,207 16,223,538,916.00
Mozambique
Still, Maputo province remains the predominant business and financial center of the country,
and within the province, the bulk of new investments continue to take place in Maputo City,
with Matola District being a distant second (refer to Table 2.1-5). FDI has given rise to
employment promotion, capital such as machinery and infrastructure, creation of added value
products, and economic development.
The country‘s largest industrial park, Beluluane, and the Mozal aluminum smelter are both
2-5
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
located in Maputo, as are other large beer, soft drink, cement, and cereal milling industries (e.g.,
Cimentos de Mozambique, Cervejas de Moçambique, Coca-Cola). There are also a number of
large and promising agribusiness investments such as the Maragara sugar mill and Bananalandia,
which supplies bananas to both the domestic and South Africa markets. The province also
benefits from a number of universities and technical schools. Further, much of the country‘s
tourism growth has taken place in the Maputo area, which includes the Maputo Elephant
Reserve and the Kruger Transfrontier Park, which Mozambique shares with South Africa and
Swaziland.
As for the Mozal aluminum smelter, since 1998, Mozambique has been engaged in an intensive
effort to attract megaprojects in order to establish itself as a favorable environment for FDI. The
US$2.8 billion aluminum smelter projects Mozal I and II, which had been constructed in the
Matola district in the late 1990s and in the early 2000s, are the largest aluminum smelter
projects in this country. Non mega-projects FDI rose in importance during the period of 2006 to
2010 and the inflows have become increasingly diversified, which accounted for close to 44
percent of total FDI inflows.
The smelters produce about 506, 000 tons of aluminum ingots per year. Alumina is sourced in
Australia and aluminum ingots are exported mainly to the EU. The firm is a joint venture of the
Australian-British BHP Billiton mining company (47%), the Japanese Mitsubishi Corporation
(25%), the Industrial Development Corporation of South Africa (24%), and the Government of
Mozambique (4%).
With regards to Beluluane Industrial Park, as noted above, Maputo Province hosts Beluluane
Industrial Park, located in the Matola Industrial Zone. The World Bank‘s Private Sector
Development Project financed establishment of the park in 2007. The park spans 24 hectares
and has attracted 22 businesses employing some 1,000 workers and has generated US$20
million in investment. The park is located across from Mozal.
(4) The Industrial Customers for the Power Demand in Maputo Area
In and around Maputo area there are substantial business enterprises that demand the new power
in order to operate their business. Such enterprises require new electricity of 527MW as a whole
by 2015/16 (Table 2.1-6). There is a growing likely that the economic situation in Maputo area
is and will be quite active due to being the increasing energy demand for the industrial
customers in Maputo.
2-6
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Table 2.1-6 Current and Future Industrial Customers for Power Demand in
Maputo
INITIAL LOAD
No. CUSTOMER NAME LOCATION STATUS
(MW)
1 Incomati Sugar Xinavane/Maputo 15 Operational
2 Maragra Sugar Manhiça/Maputo 10 Operational
3 Steel Tube Factory Beluluane/Maputo 10 Operational
4 Exports to SEC Swaziland 100 Operational
5 Exports to LEC Lesotho 20 Operational
6 CIF MOZ Salamanga 20 Construction
7 Facim-Sogex Multipurpose Maputo 15 Construction
8 Intaka 5000 Houses Maputo 20 Construction
Catembe Bridge + Residential
9 Maputo 30 Construction to start 2013
Expansion Zone
10 GS Cimentos Beluluane/Maputo 20 Committed 2014
11 Cim Magude/Africa Great Wall Magude/Maputo 22 Committed 2014
12 New Sommershield Maputo 15 Committed 2014
13 Matola Mall Matola Maputo 15 Committed 2014
14 ADIL Cimentos Maputo 10 Potential 2014
15 Techobanine Port Salamanga/Maputo 18 Potential 2015-16
16 FerroxChang Belluluane/Maputo 7 Potential 2015-16
17 Cim Moç-Matola/CIMPOR Matola/Maputo 15 Operational/Expansion
18 Matola Coal Terminal – Fase IV Matola/Maputo 10 Expansion
19 Chibuto Heavy Sands Chibuto/Gaza 45 Potential
20 Chibuto Heavy Sands Smelting Chibuto/Gaza 88 Potential
21 Arcellor Mittal Beluluane/Maputo 22 Potential
TOTAL 527
(Source: EDM)
The Cahora Bassa Hydroelectric Power Plant (“HCB”) with an output of 2,075 MW, the major
power source in Mozambique, is linked to the network for the central and northern areas. A part
of the generated power is transmitted to the central and northern areas by means of a 220 kV AC
transmission line and the power supplied meets the load of these areas. Power is also sent to a
neighboring country, Zimbabwe, by means of a 400 kV AC transmission line. However, the
majority of the power generated by HCB is sent to the Apollo substation in South Africa by a
2-7
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
535 kV DC transmission line and is then sent to the Southern African Power Pool (“SAPP”).
Since the system for the southern area, which covers Maputo, the capital of Mozambique, is
located over 1,000 km from HCB, power is imported from SAPP via the networks of South
Africa and Swaziland by means of a 400 kV AC transmission line. As a result, more than 80%
of domestic demand is supplied by re-imported power.
2-8
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
2-9
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Power is currently transmitted from the power pool of South Africa to Mozambique via a 400
kV transmission line stepped down from 400 kV to 275 kV and 132 kV at the Maputo
substation. Power is transmitted to the Mozal aluminum refinery plant, the biggest user of
Mozambique located in the neighborhood of the Maputo substation and accounting for about
70% of the total power demand of the southern system, via three dedicated transmission lines of
132 kV (275 kV designed).
Power to general consumers is further stepped down to 110 kV or 66 kV at the Infulene and
Matola substations. The 110 kV voltage is used only in the northern region of the southern
system, while the 66 kV system plays a role of power transmission in the other regions. The
transmitting capacity of the 66 kV transmission lines is relatively small, standing at 36 MW to
57 MW (with the power factor assumed to be 95%). There are concerns that overloading may
occur in the near feature as demands grow.
Turning attention to the two candidate sites for the southern gas-fired thermal power plant, the
Beluluane site is located close to the existing Beluluane substation which is connected with the
main system through T-shape branching from the 66 kV Matola Gare-Boane line with a
transmission capacity of 36 MW. On the other hand, the CTM site is situated adjacent to the
existing CTM substation and is connected to eight 66 kV lines with a transmission capacity of
36 to 57 MW.
2-10
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Legend Lindela
64
400kV
Chongoene
275kV Lionde
132kV 94 64
94
110kV Corumana Xinavane 94
66kV Xai-Xai
South Africa Macia
Power station
94 94 Riopele
Substation Matola 455 Manhica
Gare 36
36 Laulane
Unit : MW 36
36
36 Infulene 36
South Africa 36
455 36 47 36 72
Maputo Machava SE6 SE8
455 62
1631
SE4
660 36
660 36
47 36
660 36
47
1631 Mozal 36 36 36 47
36 Matola 57 83 SE5
57 SE7
47
47 47
47
Swaziland Beluluane 47
CTM 47
47
Matola P.Mozal
47 47
36 Rio SE2
SE1
Cimentos SE3
Boane 47
Salamanga
(Source: Created with reference to PSSE network analysis data provided by EDM) (Unit: MW)
Table 2.2-2 shows the details of the substation facilities. A 400 kV transformer is employed in
the Maputo substation to transform the receiving voltage from international interconnection
lines into 275 kV or 132 kV for domestic use. There are 275 kV transformers located at the
Infulene and Matola substations that are the supply bases of the southern system, and these
transformers are used for connection with the 110 kV or 66 kV system, aiming at local supply.
In addition, there are transformers with a primary voltage of 110 kV or 66 kV located at
substations for distribution to serve general loads.
2-11
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
2-12
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
2-13
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
power flow of the transmission line branching off at the Infulene-CTM line and leading to the
SE6 substation is 38 MW, which is slightly higher than the transmitting capacity. However,
power flow exceeding the capacity is found only in this transmission line.
Lindela 12
13
Chongoene 11
Lionde 7
7
30 25
5
Corumana Xinavane 46 9
Komatiport Xai-Xai
South Africa +3 11 Macia
3
61 Riopele
Matola 3 Manhica
61 11 8
Gare Laulane
18 43 8
21
161 13
3
Amot Infulene 32
4
South Africa 144 23
24 15
Maputo 336
Machava 26
33 SE6 SE8
4
885 15 16
337 851 SE4
851 38 16
30 24 2
850 8
17
5
302 Mozal 20
191 105 17 22
Matola 6 6 10 SE5
5 SE7
48
Edwaleni Beluluane 41
14 30
3
4
Swaziland 4
CTM
16 33
10 14
2 24
Matola P.Mozal 29
19 29
Rio 10 SE2 23
SE1
Cimentos SE3
Boane 14 8
8 Salamanga
2-14
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The power system of the country is small-scaled and the southern system does not have a main
power supply. For these reasons, the fault current is as small as about 10 kA for each voltage
class, except on the Mozal 132 kV bus. Mozal is located close to the 400 kV Maputo substation
and is connected with three separate transmission lines. For this reason, Mozal is expected to
produce a fault current as large as 19.3 kA when faults occur.
Lindela 0.3
Chongoene 0.5
Lionde 0.7
0.7
Corumana Xinavane 0.9
Komatiport Xai-Xai
South Africa 1.0 0.9 Macia
Riopele
Matola 2.1 Manhica
Gare 1.1
4.1 5.5 Laulane
2.7
12.8, 5.8 8.4
Amot Infulene
South Africa
Maputo Machava 10.0 SE6 SE8
9.8 9.8 6.6
SE4
6.5
18.6 8.7
19.3
Boane 4.2
0.9 Salamanga
2-15
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The Northern regional system is operated by ATNO (Nampula) while the Central regional
system is operated by the two operators of ATCN (Quelimane) and ATCE (Chimoio) whose
supply areas are geographically defined. In the Southern regional system, ATSU (Maputo) is the
only system operator (refer to Figure 2.3-1). In making power demand forecasts, therefore,
power consumption is estimated by each regional system and summed up as the national power
demand for the whole country.
The Backbone Transmission Project is planned to come into operation in the early 2020s,
although starting operation had originally been expected in 2017. Thereby, the desired power
transmission line between the Central and Southern regional systems is no longer expected to
start during this decade to enable central-to-south power transmission by using some large hydro
and/ or coal-fired power sources to be developed in Tete province. The synchronization and
implementation of a variety of billion-dollar projects (like long-distance-and-multi-circuit
transmission projects and large scale hydro/thermal power projects) is quite difficult particularly
from a financial viewpoint, and EDM has expressed its opinion that many projects could be
increasingly delayed. In this context, it is recommended that power development planning in the
Southern regional system be considered independently from other regional systems with the
pursuit of supply/demand balance within the Southern system only.
2-16
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Source: EDM)
Figure 2.3-1 Regional Power Systems in Mozambique
2-17
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Maximum demand occurs every November in the summer. It also tends to peak at around 8 pm.
Mozambique has a similar lighting-demand structure as other developing countries (refer to
Figure 2.3-2).
(Source: EDM Demand Forecast Report, partially modified by the JICA Study Team)
(Source: EDM)
Figure 2.3-2 Load Profile for Maximum Daily Demand (November 16, 2011)
Regional power demand is shown in Table 2.3-2, however the figures of total demand are
different from those in “Saleable Energy” in Table 2.3-1. One possible reason for this difference
is that Table 2.3-1 has counted power consumption by Large Customers whereas Table 2.3-2 has
not. Meanwhile, the Southern region, including the capital city Maputo, consumes approximately
2/3 of the electric energy of the entire country. This means that ensuring a stable supply of power
to the Maputo area is essential for the further development of the country.
2-18
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Taking the Southern region’s power supply/demand balance into account as shown in Figure
2.3-3, power purchases from Cahora Bassa HPP (2,075 MW) have been ramped up since 1988
when EDM started buying electricity from the said HPP. In 2011, EDM bought 1,800 GWh of
electricity energy from Cahora Bassa HPP, accounting for more than 90% of the Southern
region’s power demand.
Under the power purchase agreement between EDM and Cahora Bassa HPP, EDM has the right
to increase the amount of “Additional Power” on a mutual agreement basis while 300 MW of
firm power is securely fixed. Table 2.3-3 shows both the actual data and projection of purchased
power from Cahora Bassa HPP, illustrating that the amount of purchased power has increased
from year to year. Moreover, EDM plans to increase purchased power by 600 MW in 2015 and
subsequently by 700 MW in 2015 or later. However, there appears to be a low likelihood of
buying additional electricity after 2015 because of insufficient surplus hydro energy.
2-19
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
In respect to power demand forecasts for large consumers, each and every potential key project
consuming power at more than 2 MW has been listed and summarized. The key projects are
aluminum smelters, natural gas/ coal/ other natural resource developers, large agro-industries and
relevant infrastructure industries.
The report also refers to three cases of demand forecast such as Base case, High case, and Low
case in consideration of any deviation of power demand for key projects and regional economic
growth.
Figure 2.3-4 shows three regional demand forecasts. The Southern region, including Maputo city,
is one of the fastest growing areas in Mozambique where power demand is expected to increase
by 2.2 times in 5 years and 2.7 times in 10 years. Figure 2.3-5 shows the Southern region’s
demand forecast by each economic development case.
2-20
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
1400
North Demand Forecast (Base Case)
1200
Central
South
1000
Power Demand (MW)
800
600
400
200
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
(Source: Master Plan Update Project, Load Forecast Report, August 7, 2012)
1600
High Demand Forecast (South Region)
1400
Low
1200 Base
Power Demand (MW)
1000
800
600
400
200
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
(Source: Master Plan Update Project, Load Forecast Report, August 7, 2012)
2-21
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
EDM and Norconsult have jointly prepared the “Generation Master Plan for the Mozambican
Power Sector” of which the first draft was issued in July 2009. The Master Plan reflects
large-scale hydropower projects in the Zambezi river system and coal-fired power projects
adjacent to the planned coal mining projects in Tete province, synchronizing the construction of
the DC/AC transmission line projects with a total capacity of 6,000 MW. This is the so-called
Backbone Transmission Project which would substantially have a strong impact on EDM’s
power development plan. With huge financial costs of approximately US$2.8 billion, the
Backbone Project is a massive multi stakeholders’ project. Therefore, EDM is of the opinion that
some relevant institutions have not anticipated the timely implementation of the project. It is, for
example, assumed that the coal-fired power projects in Tete province are vulnerable in their
timely operation as the project owner, Vale, one of the world’s biggest mining companies, may
be significantly affected by the status of their core mining business and may potentially make the
decision to delay the project if global coal markets fall. In this regard, the Backbone Project is
NOT a reliable project for the purpose of stable power supply at this point in time.
Assuming all the power generation projects along with the Backbone Project are successfully put
into operation, the power output from the projects will largely exceed the power demand in
Mozambique. This requires careful preparation and arrangements between EDM and the
owners/operators of the Backbone Project in terms of sale of surplus energy to other countries,
long-term shutdown of aged power plants, and particularly power system operation including
interconnections with neighboring countries. However, such preparation work has not progressed
yet because the projects have low likelihood of implementation so far.
In this regard, EDM is still seeking a practical power development plan 1 with no uncertainty of
the above-mentioned issues. At the working level, Figure 2.3-4 and Figure 2.3-5 are considered
as a likely power development scenario of power supply/demand balance in kW and kWh. In this
plan, part of the generation capacity of Mpanda Nkuwa HPP (1,500 MW) is expected to be put
into operation in 2019 while other large projects are still under consideration on whether or not
to reflect to EDM’s power development plan.
In addition, some medium-scaled hydropower projects across the countries are planned to start
operation during the next few decades. As to thermal power projects, two IPPs such as Benga
1
The CTM is to be commissioned in 2016 under the EDM’s practical power development plan. It is emphasized that
even if EDM is successfully able to start commissioning the CTM project in 2016, the power shortage will not be
solved. This report, however, indicates that the commissioning year of the CTM project will be 2018 based on a
realistic schedule.
2-22
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(coal, 250 MW) and Moatize (coal, 300 MW) are to start operations in 2016 with only 50 MW
respectively. In this power development plan, it is worth mentioning that the assumption was
made that the Backbone Transmission Project was not expected to start operation. It was
assumed that only the interconnected transmission line would be in operation, by which
electricity from Cahora Bassa HPP is transferred to the Southern regional system via the South
African Power Grid. Therefore, electricity generated by the power projects planned in the
Northern/Central areas is to be transferred and then distributed to the Central and Northern
regional systems first through the existing interchange transmission line. Subsequently,
remaining electricity, that may be limited, could be transferred to the Southern regional system
via the South African Power Grid.
2-23
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
1400
Southern Power Shortage (=Requirement for imported power from SAPP)
Southern Interchange Power (incoming: +)
1200
Maximum Demand / Supply Capacity (MW)
800
600
400
200
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
2-24
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
In the low demand case, power supply/demand can be equalized with less imported peak power
compared to the base demand case. However, the chance remains of peak power shortage
potentially after 2019 even if CTM-CCGT starts operation in 2016.
In summary, CTM-CCGT is essential to secure the capacity balance in the Southern regional
system until 2026 at the least. This project can contribute to reduce the likelihood of any power
shortages during peak time/season and the amount of importing costly peak power from the
South African Power Grid.
1200
Southern Power Shortage (=Requirement for imported power from SAPP)
Southern Interchange Power (incoming: +)
1000
Maximum Demand / Supply Capacity (MW)
600
400
200
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
2-25
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 2.3-11 illustrates the energy demand/ supply balance in the Southern region. Even if the
power plants were operating at their full capacity, the Southern regional system would face a
critical power shortage situation in the period until 2018 just before Mpanda Nkuwa HPP starts
operation. After 2019, it is assumed that there is still the potential of a lack of power supply in
the South, provided that the power plants are operated in an ordinary manner with time for
regular maintenance and monitoring the actual conditions of river water flow to the dams. In any
case, the electricity energy generated at CTM-CCGT (assumed at 100 MW) is essential for
securing stable energy supply.
2-26
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
12000
Southern Power Shortage (=Requirement for imported power from SAPP)
Southern Interchange Power (incoming: +)
10000
Southern Supply w/o CTM-CCGT
Southern Supply (CTM-CCGT)
Electricity Energy (GWh)
6000
4000
2000
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
For the case of low demand, Figure 2.3-11 presents the supply/demand balance in kWh in the
Southern regional system. It is clearly shown that over the period of 2010 to 2026 the amount of
power shortage can be decreased. After 2019, it is expected that lower efficient thermal power
projects need to be in standby mode and generate electricity during peak time/season. The
CTM-CCGT project, with its much higher thermal efficiency, would need to continue operation
as a base power supply source even in the case of low demand.
2-27
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
12000
Southern Power Shortage (=Requirement for imported power from SAPP)
Southern Interchange Power (incoming: +)
10000
Southern Supply w/o CTM-CCGT
Southern Supply (CTM-CCGT)
Electricity Energy (GWh)
6000
4000
2000
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
2-28
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Unit: MW) 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Northern Maximum Demand (Base) 87 85 93 138 206 262 311 404 457 480 487 492 500 508 517 527 537
Supply Capacity 0 0 0 0 0 0 0 0 60 180 180 180 180 180 180 180 180
-Alto Malema HPP (60 MW) 60 60 60 60 60 60 60 60 60
-Lurio HPP (120 MW) 120 120 120 120 120 120 120 120
Interchange Power (incoming: +) 87 85 93 138 175 188 296 329 315 300 307 312 320 328 337 347 357
Balance (shortage: -) 0 0 0 0 -31 -74 -15 -75 -82 0 0 0 0 0 0 0 0
Power Shortage 0 0 0 0 31 74 15 75 82 0 0 0 0 0 0 0 0
Central Maximum Demand (Base) 128 154 246 372 462 549 590 557 571 587 604 619 636 651 665 678 694
Supply Capacity 468 568 568 537 637 737 886 886 886 1,336 1,336 1,336 1,336 1,336 1,336 1,336 1,336
-Chicamba HPP (38 MW) 38 38 38 12 12 12 44 44 44 44 44 44 44 44 44 44 44
-Mavuzi HPP (42 MW) 30 30 30 25 25 25 42 42 42 42 42 42 42 42 42 42 42
-Cahora Bassa HPP (2,075 MW) 400 500 500 500 600 700 700 700 700 700 700 700 700 700 700 700 700
-Cahora Bassa North HPP (1,245 MW)
-Mpanda Nkuwa HPP (1,500 MW) 150 150 150 150 150 150 150 150
-Benga Coal TPP (250 MW) 50 50 50 50 50 50 50 50 50 50 50
-Moatize Coal TPP (300 MW) 50 50 50 50 50 50 50 50 50 50 50
-Mavuzi HPP (60 MW)
-Lupanta HPP (600 MW) 200 200 200 200 200 200 200 200
-Boroma HPP (200 MW) 100 100 100 100 100 100 100 100
Interchange Power (incoming: +) -340 -414 -322 -165 -175 -188 -296 -329 -315 -749 -732 -717 -700 -685 -671 -658 -642
Balance 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Southern Maximum Demand (Base) 344 369 407 488 587 687 794 876 932 976 1,009 1,043 1,080 1,118 1,159 1,201 1,245
Supply Capacity 16 16 81 88 421 356 406 456 456 456 456 456 456 456 456 456 456
-Corumana HPP (14 MW) 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
-CTM Existing GTPP (52 MW) 50 50
-Temane GTPP (7-62 MW) 7 12 12 12 62 62 62 62 62 62 62 62 62 62
-Aggreko GTPP (65 MW) 65 65 65
-Ressano Sasol-EDM (140 MW) 140 140 140 140 140 140 140 140 140 140 140 140 140
-Ressano Gigawatt-Mozambique (100 MW) 100 100 100 100 100 100 100 100 100 100 100 100 100
-Kuvaninga GTPP (38 MW) 38 38 38 38 38 38 38 38 38 38 38 38 38
-Massingir HPP (30 MW)
-CTM CCGT (100 MW) 100 100 100 100 100 100 100 100 100 100 100
Interchange Power (incoming: +) 253 329 229 27 0 0 0 0 0 449 425 405 380 357 334 311 285
Power Shortage (= Requirement for
75 24 97 373 166 331 388 420 476 71 128 182 244 305 369 434 504
imported power from SAPP)
Balance 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total (Country) Maximum Demand 559 608 746 998 1,255 1,498 1,695 1,837 1,960 2,043 2,100 2,154 2,216 2,277 2,341 2,406 2,476
Supply Capacity 484 584 649 625 1,058 1,093 1,292 1,342 1,402 1,972 1,972 1,972 1,972 1,972 1,972 1,972 1,972
Power Shortage (= Requirement for
75 24 97 373 166 331 388 420 476 71 128 182 244 305 369 434 504
imported power from SAPP)
Balance 0 0 0 0 -31 -74 -15 -75 -82 0 0 0 0 0 0 0 0
(Source: EDM and some estimations by the JICA Study Team)
2-29
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Unit: GWh) 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Northern Demand (Base) 447 494 531 808 1,066 1,655 1,991 2,661 3,003 3,147 3,186 3,208 3,252 3,297 3,346 3,397 3,450
Supply 0 0 0 0 0 0 0 0 499 1,498 1,498 1,498 1,498 1,498 1,498 1,498 1,498
-Alto Malema HPP (60 MW) 499 499 499 499 499 499 499 499 499
-Lurio HPP (120 MW) 999 999 999 999 999 999 999 999
Interchange Power (incoming: +) 447 494 531 808 1,066 1,655 1,991 2,661 2,504 1,649 1,688 1,710 1,754 1,799 1,848 1,899 1,952
Balance (shortage: -) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Central Demand (Base) 617 678 1,143 1,714 2,229 2,699 2,918 2,614 2,675 2,742 2,818 2,877 2,952 3,020 3,083 3,134 3,204
Supply 3,644 4,485 4,485 4,357 5,145 5,934 6,968 6,968 6,968 10,712 10,712 10,712 10,712 10,712 10,712 10,712 10,712
-Chicamba HPP (38 MW) 156 156 156 49 49 49 181 181 181 181 181 181 181 181 181 181 181
-Mavuzi HPP (42 MW) 124 124 124 103 103 103 173 173 173 173 173 173 173 173 173 173 173
-Cahora Bassa HPP (2,075 MW) 3,364 4,205 4,205 4,205 4,993 5,782 5,782 5,782 5,782 5,782 5,782 5,782 5,782 5,782 5,782 5,782 5,782
-Cahora Bassa North HPP (1,245 MW)
-Mpanda Nkuwa HPP (1,500 MW) 1,248 1,248 1,248 1,248 1,248 1,248 1,248 1,248
-Benga Coal TPP (250 MW) 416 416 416 416 416 416 416 416 416 416 416
-Moatize Coal TPP (300 MW) 416 416 416 416 416 416 416 416 416 416 416
-Mavuzi HPP (60 MW)
-Lupanta HPP (600 MW) 1,664 1,664 1,664 1,664 1,664 1,664 1,664 1,664
-Boroma HPP (200 MW) 832 832 832 832 832 832 832 832
Interchange Power (incoming: +) -3,027 -3,807 -3,342 -2,643 -2,916 -3,235 -4,050 -4,354 -4,293 -7,970 -7,894 -7,835 -7,760 -7,692 -7,629 -7,578 -7,508
Balance 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Southern Demand (Base) 1,897 2,085 2,324 2,784 3,402 4,070 4,855 5,460 5,799 6,055 6,242 6,438 6,646 6,864 7,095 7,337 7,591
Supply 66 66 66 95 2,188 2,805 3,254 3,680 3,680 3,680 3,680 3,680 3,680 3,680 3,680 3,680 3,680
-Corumana HPP (14 MW) 66 66 66 66 66 66 66 66 66 66 66 66 66 66 66 66 66
-CTM Existing GTPP (52 MW) 146 350
-Temane GTPP (7-62 MW) 29 51 76 87 513 513 513 513 513 513 513 513 513 513
-Aggreko GTPP (65 MW)
-Ressano Sasol-EDM (140 MW) 777 1,165 1,165 1,165 1,165 1,165 1,165 1,165 1,165 1,165 1,165 1,165 1,165
-Ressano Gigawatt-Mozambique (100 MW) 832 832 832 832 832 832 832 832 832 832 832 832 832
-Kuvaninga GTPP (38 MW) 316 316 316 316 316 316 316 316 316 316 316 316 316
-Massingir HPP (30 MW)
-CTM TPP (100 MW) 788 788 788 788 788 788 788 788 788 788 788
Interchange Power (incoming: +) 2,580 3,313 2,811 1,835 1,850 1,580 2,059 1,693 1,789 6,321 6,206 6,125 6,006 5,893 5,781 5,679 5,556
Power Shortage (= Requirement for
0 0 0 854 0 0 0 87 330 0 0 0 0 0 0 0 0
imported power from SAPP)
Balance 749 1,294 553 0 636 315 458 0 0 3,946 3,644 3,367 3,040 2,709 2,366 2,022 1,645
Total (Country) Maximum Demand 2,961 3,257 3,998 5,306 6,697 8,424 9,764 10,735 11,477 11,944 12,246 12,523 12,850 13,181 13,524 13,868 14,245
Supply Capacity 3,710 4,551 4,551 4,452 7,333 8,739 10,222 10,648 11,147 15,890 15,890 15,890 15,890 15,890 15,890 15,890 15,890
Power Shortage (= Requirement for
0 0 0 854 0 0 0 87 330 0 0 0 0 0 0 0 0
imported power from SAPP)
Balance 749 1,294 553 0 636 315 458 0 0 3,946 3,644 3,367 3,040 2,709 2,366 2,022 1,645
(Source: EDM and some estimations by the JICA Study Team)
2-30
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The Ministry of Energy (“ME”), which holds jurisdiction over the power sector in Mozambique,
and EDM, which is the publicly-owned electricity company under the jurisdiction of the ME,
with the support from foreign countries, have engaged in human capacity building, the
establishment of policy and regulatory framework of the Mozambican power sector, and the
development and operation of power equipment and facilities. This chapter provides an outline
of power projects implemented (or to be implemented) in cooperation with other donor
agencies.
Table 2.4-1 shows the on-going power projects in Mozambique, classified into three categories:
technical cooperation projects, transmission projects, and rural electrification projects, with total
project costs amounting to USD 669.19 million.
The technical cooperation projects are supported by aid agencies such as the World Bank
(“WB”), International Development Association (“IDA”), L'Agence Française de
Développement (“AFD”), the Government of Norway (through the Agency for Development
Cooperation, “NORAD”) and the Government of Sweden (through the Swedish International
Development Cooperation Agency, “SIDA”). The technical cooperation projects for the power
sector are characterized by the wide range of aid agencies and countries involved.
The Mozambique Electricity Master Plan was prepared with the assistance of NORAD in 2004.
In 2008, however, the need to upgrade the Master Plan was recognized so terms of reference
(“TOR”) for an update of the previous Master Plan were prepared. Currently, the Master Plan is
being updated to be completed by April 2013. Sub-Item 1.1.3: "Update of Master Plan 2010 -
2027" in Table 2.4-1 corresponds to this project.
2-31
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
1. Ongoing projects
1.1 Feasibility Study and Technical Assistance
1 Feasibility Study of Second Line Caia - Nampula 1.80 IDA
2 Integrated Management System (Sigem) 6.74 IDA
3 Update of Master Plan 2010-2027 1.30 AFD
4 Capacity Building 4.00 Swedish
5 Feasibility Study for Electrification of Vilanculos (OHL 110 kV Chibabava - Vilankulos) 0.05 Swedish
Sub Total - Item 1.1 13.84
1.2 Transmission Projects
1 Rehabilitation and Reinforcement of Distribution network. Maputo City (Lot 1) 33.35 Portugal
2 Rehabilitation and Reinforcement of distribution network. Maputo City (Lot 2) 31.90 Portugal
3 Mobil Substation 6.09 Reino Belga
4 66kV Lines in Maputo 6.65 EDM
5 Mixed credit 150.00 Danida
6 Assembly of the Second Transformer in Matambo SS 13.00 World Bank
7 110kV Transmission Line Mavuzi - Chibabava 19.50 EU
8 SVC in Mocuba 10.03 GdM
9 Rehabilitation Chimoio SS and Acquisition of Mobile SS 110/33/22 kV 10 MVA 6.30 Kingdom of Belgium
10 Electricity II (Line DL8) 0.40 EDM
11 Electricity IV (Chibata - Dondo 220kV) 55.00 ADB/OPEC
12 Rural Electrification of North area of Gaza Province (110kV Lionde - Mapai) 54.00 Korean Exim Bamk
13 Transmission line 275 KV Corumana - Lionde 25.30 Danida
Sub Total - Item 1.2 386.22
1.3 Rural Electrification Projects
1 LCREP of Niassa 11.40 IDB
2 EDAP (Expansion MV Network in Maputo, Manica, Tete, Nampula and Cabo Delgado) 147.70 BM/Afund/OFID/AFD/EIB
3 Rural Electrification Sofala, Manica and Tete Provinces (Lot B) 15.80 Suecia/Noroega
4 Rehabilitation of Bilene SS 1.90 EDM
5 Rural Electrification of Inhambane, Zambezia and Nampula Provinces 30.00 EXIM BANK/INDIA
6 Rural Electrification of Niassa, Cabo Delgado and Manica Provinces 25.00 EXIM BANK/INDIA
7 Electricity III 19.33 ADB/OPEC
8 Rural Electrification of Cabo Delgado Phase III - Addendum (Ibo) 13.00 NORWAY
9 Rural Electrification of Pande 3.00 GoM
10 Rural Electrification of Chimbonila 2.00 Norway
Sub Total - Item 1.3 269.13
TOTAL - Item 1 669.19
Table 2.4-2 shows the priority power projects to be implemented in accordance with the power
development plan for which a funding source has not been determined. This table shows only
the projects to be implemented over the period 2010 - 2015. The projects are divided into four
categories: transmission projects, rural electrification projects, distribution and rehabilitation
projects, and generation projects with a total project cost expected to amount to USD 2,906.07
million. Although some transmission projects have already gained financial commitment, most
of the projects still require a large amount of funds for implementation, thus requiring financial
support from developed countries.
The Beluluane Gas-Fired Power Plant Project requested by the Government of Mozambique
through ME and EDM corresponds to Sub-Item 2.10.2: “1. Beluluane 50 MW Gas Fired Power
Plant: 75 MUSD.” In addition, the Project for Rehabilitation of the existing Maputo Thermal
Power Plant corresponds to Sub-Item 2.10.2 “10. Expansion of Gas Turbine HRSG Coupled to
Existing Plant: 70 MUSD.” Both are designated as priority projects to be implemented.
2-32
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Table 2.4-3 shows recently completed power projects, which are separated into two categories:
2-33
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
transmission projects and rural electrification and distribution projects. Total project costs
amount to USD 385.51 million.
Similar to the case for on-going transmission projects and rural electrification projects described
in Subsection 2.10.1, the projects have been implemented with the support from a wide range of
foreign countries and aid agencies.
A simple sum of all project costs listed in Subsections 2.10.1, 2.20.2 and 2.10.3 adds up to USD
3,800 million as shown in Table 2.4-4. The sum of the costs of the on-going projects and the
recently completed projects accounts for only 27.8% of the total project costs. The projects to be
2-34
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
implemented by 2015 (listed in Section 4.2) still require a large amount of investment. For the
recently completed projects, the project costs incurred by ME and EDM account for 10.1% of
the total amount with the rest dependent on foreign aid. As this trend continues, both
government-based support from other countries and private investment are considered essential
for the future of the power sector of Mozambique.
As mentioned in Subsection 2.10.2, the total project costs for priority power projects without
funding amounts to USD 2,745.3 million with the breakdown shown in Table 2.4-5 and
Figure 2.4-1. The cost of transmission projects accounts for the largest share (56.0%), followed
by generation projects (22.3%). However, the sources of funding necessary to implement these
projects have still not been identified.
2-35
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Transmission
611.5, 22% projects
Rural electrification
projects
Distribution & rehab
projects
243.1, 9% Generation projects
1,537.7, 56%
352.9, 13%
WB, in cooperation with IDA, has provided assistance to the Mozambican power sector. The
most recent case is the “Energy Development and Access Project (EDAP APL-2)”, which
primarily aims at improving the access rate to electricity and the quality of power supply in rural
and peri-urban areas. The project extends for five years from 2010 to 2015 and the total project
cost is expected to reach USD 80 million. The project has the following three components:
Reinforcement of the Primary Networks and Grid Extension Component (USD 50.0 million)
Energy Sector Planning, Policy and Institutional Development Component (USD 10.2
million)
WB is also providing support for the “Mozambique Regional Transmission Backbone Project
(CESUL)” in collaboration with NORAD. Figure 2.4-1 shows the locations of the
above-mentioned WB assisted projects as well as other major power projects. The project
information on the above-mentioned “EDAP APL-2” and information on WB’s assistance
program for the Mozambican power sector are detailed in the following document:
Project Appraisal Document on a Proposed Credit in the Amount Of SDR 49.7 Million (US
$80 Million Equivalent) to the Republic of Mozambique for an Energy Development and
Access Project (APL-2) (January 6, 2010)
2-36
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Norway is one of the developed countries that is most actively involved in assistance to the
Mozambican power sector, and it currently provides support to the following six projects:
Institutional Capacity Building in the Ministry of Energy, 2007–2010, Norwegian Krone
(“NOK) 41 million
Technical Assistance to Electricidade de Moçambique, 2008–2010, NOK 13 million
Cabo Delgado Electrification Project, 2006–2013, NOK 342 million
Marrupa-Cuamba-Mecanhelas Electrification Project, 2007–2012, NOK 41 million
Chimbonila Electrification Project, 2011–2012, NOK 11 million
Support to the National Energy Fund (“FUNAE”), 2010–2011, NOK 3 million
As a member of the International Cooperation Partner (“ICP”) countries, Norway has taken a
leading role in dealing with common issues shared by the Southern African Development
Community (“SADC”), which Mozambique is affiliated with. Projects that Norway is currently
involved in are as follows:
Support to the SADC Secretariat on Energy Related Issues
Mozambican Regional Transmission Backbone Project (CESUL)
Electricity Regulators’ Peer Review Network
The Southern African Power Pool – Regional Electricity Market
Germany has often provided both grant and loan assistance to the Mozambican power sector.
Among the most significant projects is the project for construction of a database regarding the
energy sector. This database is intended to capture, store and sort all the literature on the energy
sector published in the past 15 years, and the results are expected to be incorporated into this
survey. The project is being implemented by the German Agency for International Cooperation
(“GIZ”) in collaboration with Universidad Pedagogica (Pedagogica University) and it is
currently underway. It is necessary to maintain contact with GIZ, in order to obtain this database
upon its completion.
2-37
Chapter 3
This chapter describes how the approximate scale of the power plant facility was estimated, how
each candidate site was compared and assessed from technological and economical viewpoints,
and how the best-suited planned construction site was selected. The selected candidate sites
were Beluluane industrial complex, which EDM had been studying, and a site on the CTM
premises from which a coal-fired power plant had been removed. The Ressano Garcia region
near PRS-1 gas decompression station was excluded as a candidate site for this survey because
the construction of a power generation facility using a gas engine had already been planned at
this site.
In addition, the following three points were considered, in respect of the views of EDM, as
prerequisites for the comparison and study:
1. Output of the CCGT power station should be maximized so that the contracted gas volume
of 6 MGJ/ year can be fully used, considering that the gas contract is a take-or-pay
contract.
2. The existing GT power station in CTM will perform base operations from 2013 to 2017
(when the CCGT power station is expected to start operation), using the contracted gas
volume of 6 MGJ/ year.
3. From 2017, the CCGT power station will fully operate and the GT power station of CTM
will operate only in the case of an emergency, e.g., if the CCGT power station stops.
Table 3.1-1 Survey Items for Selection of Sites for a Power Plant
3-1
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
3-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
3.2.1 Setting Conditions for the Layout of the Power Plant for the Candidate Sites
The planned new CCGT is expected to have continuous full load operation as base load
operation, and to supply electric power to meet Mozambique’s tight power demand. Based on
previous experience with CCGTs, it is assumed that the CCGT will operate continuously,
except for outages for periodic inspections (e.g., combustion inspections, hot gas pass
inspections and major inspections) and maintenance, and regular work (washing GT
compressors with water, changing generators’ brushes, etc.). The plant capacity factor is
assumed to be 83%. This CCGT plant efficiency (lower heating value, “LHV”) is estimated to
be 50%.
Power generation capacity is restricted by the volume of natural gas. The volume of gas to be
supplied to the new gas-fired power plant is 6.0 MGJ/ year at both candidate sites. Calculating
from this gas supply volume, the new power plant capacity will be approximately 114 MW.
Available generation capacity = 6.0 x 106 x 109 x (50/100) /(24 x 365 x (83/100) x 3.6 x 109)
EDM had two prospective areas for the planned CCGT. The first area was the Beluluane site,
neighboring the Beluluane transformer station, is 1.5 ha (100 m x 150 m). The second area was
3-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
the CTM site of approximately 3.7 ha consisting of a former coal-fired power plant area and an
area of diesel oil tanks for existing GTs. One typical 110 MW class multi-shaft 2-on-1 CCGT
could be located on the Beluluane site, and two units of CCGT could be located on the CTM
site.
1.5 ha
Available site area 3.7 ha
(100 m 150 m)
Air Cooled
Condencer
Fuel Gas
Compressor Beluluane Substation
100m
100000
Waste Water
Treatment
Plant
Steam Turbine Generator Heat Recovery
Steam Generator
150000
150m
3-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
270m
Air Cooled
Condencer
Fuel Gas
New Gas
Compressor
Station
100000
Demineralize Water Plant,
Demineralized Water Tank &
Raw Water Tank
Water Tie-in
Plant
Steam Turbine Generator Heat Recovery
Steam Generator
point 150000
Electrical room &
Control room
145m
125m
(3) Conclusion
From (1) and (2) above, it is possible to install one block of multi-shaft 110MW class CCGT,
consisting of two 30 MW to 40 MW class GT generators, two HRSGs, one ST generator, and
related equipment, at both the Beluluane and CTM sites..
The necessity for land preparation and the accessibility at CTM Maputo and Beluluane sites are
evaluated in this chapter.
3-5
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 3.3-1 Location of CTM Maputo & Beluluane Sites and Access Route from Port Maputo
(2) Accessibility
(a) Accessibility from Port Maputo
The site is located about 20 km from Port Maputo and is adjacent to the existing Mozal
aluminum refinery. As shown in Figure 3.3-1, major trunk roads (EN1, 2 & 4) can be used for
the transportation of heavy equipment from Port Maputo to the site.
3-6
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
3-7
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(2) Accessibility
(a) Accessibility from Port Maputo
The site is located about 3 km from Port Maputo. As shown in Figure 3.3-1, major trunk roads
(EN1 & 2) can be used for the transportation of heavy equipment from Port Maputo to the site.
3-8
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Table 3.4-1 Topographical, Geological and Meteorological Conditions of the Two Candidate
Sites
Item CTM Site Beluluane Site
Topography and The site is situated on alluvial soil The site is situated on diluvial upland at
geology deposited at the river mouth. Hard clay approximately 30 m above M.S.L. Since the
(N-value >50) is approximately 10 site is located on flat land, large-scale grading
meters below the ground level. work is not required. Although information
Accordingly, it is recommended to about geological conditions of the site is not
adopt the pile foundation for heavy available, it can be inferred that there are no
machinery and structures. significant problems in foundation design. In
fact, an aluminum smelter and cement
factories, which use heavy machinery
supported by strong foundations, are located in
the Beluluane Industrial Park.
Meteorology There is no risk of flood or storm surge There is no risk of flood damage.
damage. However, a proper drainage
system would be newly established
within the CTM in order to avoid water
inundation.
(Source: JICA Study Team)
Three technical constraints, i.e., power flows, fault currents, and stability, must be satisfied for
the stable operation of a power system and the system must be analyzed in order to make this
judgment. Power flow analysis has been conducted to ascertain whether the facilities, such as
the transmission line and transformer, would not be overloaded and whether the proper value of
voltage could be maintained.
The power system facility cannot avoid faults such as short-circuiting. Should a fault occur, the
facility must be isolated from the system by a breaker. Fault current analysis must be carried out
to check if the fault current is lower than the rated breaking current of the breaker and thus the
breaker could break the fault current without any problems.
If a fault has occurred in the system and after the faulty facility has been isolated from the
system, the system must be able to continue the stable operation as prior to the occurrence of the
fault. Stability analysis must be performed to confirm whether any disturbances after the
occurrence of the fault have settled down as time passes and whether the system can return to
stable status.
3-9
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The current published future demand for power is forecast in the CESUL project, however
EDM is currently executing a Master Plan study to be completed at the end of 2012. EDM
provided the JICA Study Team with the network analysis data that it is using to develop the
plan. The JICA Study Team has also conducted network analysis of the power system in EDM’s
current network expansion plan.
Concretely, the following two cases of demand and system configuration, which are
prerequisites for analyzing the power system, are assumed:
Base case: Demand is assumed as the forecast value of the CESUL project, and the existing
system will not be reinforced and will remains as it is in 2011 until the new southern gas-fired
power station is completed
Reference case: Work data of demand and network configuration as of October 2012 from
EDM’s current network expansion plan are used
Values forecast in the CESUL project, which are the newest published data, are used.
Table 3.5-1 shows the expected growth of demand for the Southern system in the case where
demand grows moderately. Since the Southern gas-fired power station is expected to start
operation in 2017, that year is used as the subject of network analysis, and the expected demand
in that year is 653 MW as the average growth rate from 2015 to 2020 is expected to be 7.9%.
(Source: Final Feasibility Study Report Mozambique Regional Transmission Backbone Project)
It is assumed, as described above, that the network configuration of 2011 will be maintained in
2017 when the power plant will begin operation. Figure 3.5-1 shows the network system of
2011 including the Beluluane and CTM substations, which are the related substations for the
3-10
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
candidate sites. Both the sites use the 66 kV system that is supplied from the 275/66 kV Matola
and Infulene substations.
The Beluluane substation is 32 km away from the Matola substation, connected by one circuit of
transmission line with a transmitting capacity of 36 to 47 MW. From the Infulene transformer
station, the Beluluane substation is located 28 km away and is connected by one circuit of
transmission line with a transmitting capacity of 36 MW.
By contrast, the CTM substation is 5 km away from the Matola substation and connected with
three circuits of transmission lines with a transmission capacity of 47 to 57 MW, and 8 km away
from the Infulene substation and connected with three circuits of transmission lines of 36 to 47
MW. It is also connected to two circuits of 66 kV transmission lines that supply load. This
means that the CTM substation is connected with as many as eight circuits of transmission lines
and is closer to the 275 kV substation that is the source of supply. This gives an advantage in
terms of power transmission to the CTM site over the Beluluane site.
Legend Lindela
400kV AC
275kV AC Lionde
132kV AC
110kV AC Corumana
Komatiport Macia Xai-Xai
66kV AC
South Africa
Power station
Matola
Substation Gare Manhica Laulane
Amot Infulene
South Africa
Maputo Machava P.Canico
SE6
SE4
Mozal
Matola SE5
Beluluane SE7
Edwaleni
Swaziland
P.Mozal CTM
Matola SE2
Rio
SE1
Cimentos SE3
Boane
Salamanga
3-11
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Power is transmitted to the existing Beluluane substation from the 66 kV Matola Gare-Boane
line via a T-shape branching line. If a fault occurs anywhere along the total of 26 km
transmission line and the 24 km Matola Gare-Boane line or the 2 km T-shape branching line,
therefore, a blackout occurs. The role of the existing Beluluane substation is to supply power to
medium to small-size factories and it seems that this level of supply reliability is considered
sufficient. If a new power plant is constructed, however, it will be regarded as an important
power source for the Southern system and improving its reliability is of vital importance. It is
therefore assumed that one circuit of branch transmission line of 2 km will be newly installed as
shown in Figure 3.5-2, so that the branch section will consist of two circuits, changing the
branch method to a π-shape branching. By changing the branching method in this way, the
section that will be affected by any fault can be halved and, even if a fault occurs on one of the
transmission lines, power can still be transmitted by the healthy transmission line.
Matola
Gare Matola
Gare
14km
Beluluane
Beluluane
2km
10km
New plant
Boane
Boane
T-Branching π-Branching
(Source: JICA Study Team)
It is necessary to assume output of the power plant in order to analyze the power system. The
Southern gas-fired power plant will be required to generate as much power as possible because
the power plant is expected to serve as the main power supply source from 2015 and onward.
Therefore, the output of the Beluluane and CTM sites is assumed as follows.
Firstly consideration is given to the capacity of the generator that can be installed on the
Beluluane site on the assumption that the branch method will be changed. The transmitting
capacity from Beluluane to Matola Gare and Boane is 36 MW in both directions. Even if it is
3-12
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
assumed that the transmission lines in both directions are healthy and power generated by the
generator flows equally in both directions, the capacity of the generator that can be installed is
the sum of the total transmitting capacity of 72 MW in both directions plus the Beluluane
substation load (i.e., 5 MW according to the records of 2011). The actual power flow in the
transmission lines is unequal because power flow is determined by the load distribution and
power distribution of the total system. In addition, considering that the remaining healthy
transmission lines are used to transmit power in the case of any transmission line faults, it is
assumed that the capacity of the generator that can be installed at the Beluluane site is 50 MW.
On the other hand, the capacity of the generator that can be installed at the CTM site is assumed
to be 100 MW because this site is connected to a total of eight circuits with transmission
capacity of 36 to 57 MW.
(4) Power Flow Analysis Results
Figure 3.5-3 shows the results of the power flow analysis and Table 3.5-2 shows the main
overloaded transmission lines. The pink lines in this figure indicate overloaded transmission
lines. Even though demand has increased to about 1.7 times that of 2011, the system has not
been reinforced and there are as many as 15 overloaded transmission lines in the case of the
Southern gas-fired power plant.
In the case that a 50 MW plant is developed in Beluluane, the overload of the Infulene-Matola
Gare line and Matola-Matola Rio line can be eliminated and the number of overloaded lines can
be decreased to 13. However, the effect is limited only to the Beluluane neighborhood.
In the case that a 100 MW plant is developed at the CTM site, the overload of seven
transmission lines around CTM can be solved and the overloaded lines can be decreased in
number to eight. This is effective for eliminating the overload to some extent but cannot be a
fundamental solution to the problem. Overloading occurs on load supply lines such as the
CTM-SE2 and CTM-SE3 lines and is attributable to increasing demand. Moreover, after
installing 100MW CCGT, overloading caused by generator stoppage due to periodic inspection
or sudden stoppages by faulty occurrence should be considered. These indicate the necessity of
drastic measures for reinforcing the transmission lines.
3-13
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Matola
Infulene
Gare
50 MW power plant at Beluluane 30
12
26
268 43
59
Machava 45
43 SE6
584
25
SE4
64 26
19 71 39 12
Maputo 30
12
Beluluane 172
34
312 30 37
Matola 12 5 18 SE5
7 50 SE7
81
CTM
44 51 4
2.5
27 57
22 24
17 49
Matola 33 49
Rio SE2 39
SE1
SE3
Boane 24
3-14
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Boane 24
(Source: Network analysis results from the JICA Study Team using data provided by EDM)
Table 3.5-3 and Figure 3.5-4 show the results of analyzing fault currents. The maximum fault
current of the 275 kV bus is sufficiently low at 9.4 kA in Maputo if a 100 MW power plant is
installed at the CTM site, indicating that there are no problems such as an excess of the break
current. The maximum fault current of the 66 kV bus is at 17.0 kA in Infulene substation and
lower than 25 kA of the breaking capacity of the breaker if a 100 MW plant is installed at the
CTM site, indicating there are no problems.
A change in the fault current when a power plant is installed is a 2.0 kA increase from 4.3 kA to
6.3 kA at the 66 kV bus in Beluluane in the case of a 50 MW power plant development at
Beluluane, and a 3.4 kA increase from 13.2 kA to 16.6 kA at the 66 kV bus in CTM in the case
of a 100 MW power plant development at CTM. In either of the above cases, there will be no
excess breaking capacity caused by the installation of the power plant.
3-15
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Matola
Power plant not developed Gare
4.6 6.7
3.9
14.6, 6.8
Infulene
275kV AC CTM
132kV AC 5.9 9.6
9.9
110kV AC
Matola P.Mozal
66kV AC Rio 8.9 SE2 9.8
Power station Cimentos SE3
Substation
Boane 4.6
Unit : kA
Boane 5.7
3-16
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
SE3
Boane 4.7
(Source: Network analysis results from the JICA Study Team using data provided by EDM)
Transmission lines are subject to faults from lightning and contact with trees. After the faulted
line is isolated from the system by opening a breaker, the disturbance of the fault must settle
down and the system must be able to return to the original stable condition. For stability
analysis, it was assumed that the fault occurred at the closest to the power plant, where fault
conditions for stability are severe, ignoring control systems such as the automatic voltage
regulator (“AVR”) and governor control unit (“GOV”), in order to assess stability inherent in
the system. In addition, it was assumed that the fault clearing time of the 66 kV transmission
line was 0.1 to 0.15 seconds from the records of EDM shown below.
Table 3.5 4 shows the results of stability analysis and Figure 3.5-5 shows the fluctuation curve
of the generator voltage angle. In the case where a 50 MW power plant is installed at the
Beluluane site, the network will be stable if the fault clearing time is 0.1 second. If the clearing
time is 0.15 seconds and in the case where a fault occurs at the Beluluane end of the
Beluluane-Boane line (Case 2), fluctuation of the generator voltage angle diverges, and the
system cannot be kept stable. This is because the Beluluane-Boane line will be opened after the
fault and thus there is no choice but to transmit power with one circuit of the Beluluane-Matola
Gare line.
Conversely, in the case where a 100 MW power plant is installed at the CTM site, fluctuation
3-17
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
converges in all fault cases even if the fault clearing time is 0.15 seconds. This is because a total
of eight circuits of transmission lines – three circuits to Matola substation, three circuits to
Infulene substation, and two circuits to SE3 substation – are connected to CTM, therefore, even
if one circuit of transmission line is opened due to a fault, connection to the main system is
ensured by the remaining seven circuits. This is substantiated by the fact that the fluctuation
amplitude after the fault is smaller than that at the Beluluane site.
(7) Conclusion
Table 3.5-5 provides the results of the network analysis. Installable generator capacity is limited
to 50 MW at the Beluluane site due to constraints of the transmitting capacity, whereas
approximately 100 MW can be installed at the CTM site. While there are two transmission lines
3-18
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
that are set free from overload by installation of a generator at the Beluluane site, there are
seven circuits if a generator is installed at the CTM site. The fault current after installation of a
generator is sufficiently smaller than the current breaking capacity of the breakers, and there is
no problem in both cases.
In the case of installation of a generator at the Beluluane site and if a fault occurs on the
Beluluane-Boane line and is cleared 0.15 seconds later, the network is deemed unstable. By
contrast, in the case where a generator is installed at the CTM site, the network is stable in all
fault cases. It can be judged from the above that installing a generator at the CTM site is
advantageous over the installation at the Beluluane site.
Moreover, in the case that the CCGT plant is developed at the CTM site, a generator of 110
MW capacity can be developed for the following reasons:
1) increase of generator capacity does not encourage overloading of transmission lines because
overloading is caused in supply lines,
2) fault currents are much lower than permissible value, and
3) no small margin for stability limits seems to exist because the fluctuation curve of the
generator voltage angle converges well.
EDM is currently making a network expansion plan to be completed at the end of 2012, and in
October 2012 the JICA Study Team obtained the network analysis data reflecting the current
network expansion plan, as this data can be used as reference for studying methods to connect
the Southern gas-fired power plant. The JICA Study Team analyzed the network system based
on this data. As the obtained data is still in draft version, it is possible that the final version may
have different content.
The Southern gas-fired power plant is expected to start operation in 2016 or 2017. EDM’s
current network expansion plan predicts that power demand will substantially increase in the
3-19
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
future, to 794 MW in 2016, which is greater than the value of 653 MW for 2017 estimated by
the CESUL project, described in (1) of 3.5.3. Therefore, the system for 2016 was selected as the
subject analysis reflecting EDM’s current network expansion plan.
Figure 3.5-6 shows the 2016 system of EDM’s current network expansion plan. According to
the plan, a 275 kV Matola-CTM line using the transmission route of the existing 66 kV
Matola-CTM line and a 275 kV Infulene-CTM line will be installed. A 275 kV system leading
to the CTM substation will be introduced to the demand center area, and new 275 kV
transmission lines that go around Maputo City from CTM via a new Facim substation and SE5
substation, that will be upgraded from the existing 66 kV to 275 kV, will be introduced.
Moreover, a new 275 kV transmission line that goes from the existing 400/275/132 kV Maputo
substation to the Infulene substation will be installed. As a result, overloading of the 66 kV
transmission lines can be eliminated and reliability of supply to the capital city can be expected
to improve.
Legend
Lindela
400kV AC
275kV AC Chongoene
Magude Lionde
132kV AC
110kV AC
66kV AC Komatiport
South Africa R Garcia Corumana
Power station Xai-Xai
Macia
Xinavane
Substation
Riopele
Matola
Gare Manhica Laulane
Amot
South Africa Infulene
SCMAPARN
Machava SE8
Maputo SE6
SE4
91361
Mozal 91371 SE5
Matola
90961 SE7
SCMAPSEB 90962
Beluluane 90991
90992
SEB400
CTM SE1
Matola P.Mozal
Rio SE2
Cimentos SE3
Edwaleni
Swaziland Boane
Facim
Salamanga
(Source: Diagram drawn by the JICA Study Team based on EDM’s current network expansion plan
provided by EDM)
Table 3.5-6 and Figure 3.5-7 show the results of power flow analysis before and after the start
of operation of the 100 MW plant of CTM under the system of EDM’s current network
expansion plan (2016). Before the 275 kV transmission line is reinforced, fifteen lines are
overloaded. Overloading of the transmission line around CTM will be solved by introducing a
275 kV transmission line to the capital city and the number of overloaded lines will decrease to
three: the Matola-Matola Rio line, Infulene-Matola Gare line and SE5-SE8 line.
3-20
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The main function of all these overloaded transmission lines is to supply power to regional
loads which have become overloaded as regional loads increase. Measures, such as circuit
additions, will have to be taken as these overloaded transmission lines will not receive the
benefits of the introduction of a 275 kV transmission line to the capital city.
If a 100 MW plant is installed at CTM, the CTM-SE2 line will be newly overloaded. This is
because the power flow of this transmission line before installation of the plant is 43 MW
against the transmission capacity of 47 MW, which is a small margin, and because the power
flow increases in the directions of SE2, SE3, and SE7 as a result of the installation of the plant
at CTM.
As a countermeasure against this overloading and exceeding the permissible value of fault
current, which will be described later, the case in which the CTM-SE3, SE2-SE3, SE3-SE7,
SE4-SE6, and Infulene-SE7 lines are always open and each 66 kV network is operated radially
in 275 kV substation units, is considered. This countermeasure solves the overloading of the
CTM-SE2 line.
However, overloading of the Matola-Matola Rio, Infulene-Matola Gare, and SE5-SE8 lines is
not solved. In addition, the Infulene-Laulane line is newly overloaded. The essential cause of
overloading of the 66 kV transmission lines is that the transmission line constructed in the early
years had a capacity as small as 36 MW, which was used without being reinforced.
Fundamental measures such as thickening conductors of the lines and circuit additions will be
needed in the future.
Table 3.5-6 Results of the Power Flow Analysis for EDM’s Current Network
Expansion Plan System (2016)
Power Flow (MW) Red: Overload
Voltage Capacity
Line Before CTM After CTM 100MW
(kV) (MW)
100 MW Closing Lines Opening Lines
Maputo-Matola 275 455 289 250 248
Matola-Infulene 275 455 10 2 6
Matola-CTM 275 >455 161 120 112
Infulene-CTM 275 >455 108 75 62
Infulene-Matola Gare 66 36 55 55 55
Matola-Matola Rio 66 47 58 58 58
CTM-SE2 66 47 43 53 43
CTM-SE3 66 47 27 39 -
Infulene-SE7 66 36 1 0 -
Infulene-SE6 66 36 26 25 26
Infulene-Laulane 66 36 35 35 38
SE5-SE8 66 36 42 43 39
(Source: Analysis results using PSSE network data provided by EDM)
3-21
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
73
1 Infulene
245 R Garcia 3
174 7
72
20 Infulene
After 100 MW development 245 R Garcia 3
153 7
Matola 21
at CTM Gare
36
55
159 35
Laulane
18
53
230
148
10
2 25 18
3
Maputo 0 SE8
Machava 42
0
26
936 75 24
850 250 1
1330 SE6 29
38 43
850 SE4
29
395 91361
Mozal 156
91371 SE5
Matola 127
21
4
14 SE7
90961 CTM 87
Beluluane 58 120 90962
54
90991 39
31 90992 8
56 53 26
20 5
26 100
SE1
4 9
P.Mozal 43 2
37 Matola 50
Rio 26 SE2 68
5 141 49 48
Cimentos SE3
133
Boane 20 21
36
Overloaded line Facim
21 Salamanga
72
20 Infulene
After 100 MW development 245 R Garcia 3
152 7
Matola 21
Gare 55 Laulane
at CTM and line opening 18
36
152 38
53
232
162
10
6 26 15
3
Maputo SE8
Machava 42
26
935 62 24
850 248
1330 SE6 29
38 39
850 SE4
29
395 91361
Mozal 177
91371 SE5
Matola 129
21
22
14 SE7
90961 CTM 87
Beluluane 58 112 90962
5
90991
31 90992 14
5 56 43
20 SE1
26 100
4
P.Mozal 43 6
37 Matola 50
Rio 26 SE2 68
5 169 62 56
Cimentos SE3
154
Boane 20 21
Overloaded line 36
Facim
21 Salamanga
Figure 3.5-7 Results of Power Flow Analysis using EDM’s Current Network
Expansion Plan System (2016)
3-22
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Table 3.5-7 and Figure 3.5-8 show the results of fault current analysis using EDM’s current
network expansion plan system (2016). The fault current of the 66 kV bus will substantially
increase as a result of introducing the 275 kV system to the metropolitan area but its value will
not exceed the permissible value, i.e., 25 kA, although it will come close, before the 100 MW
plant at CTM starts operating. After the plant is up and running, however, the fault current will
increase 3.3 kA at CTM to 26.2 kA, exceeding the permissible value. It will also exceed the
permissible values in Facim, SE5, SE3, and SE7, and the maximum value will be 26.7 kA in
SE3.
The reason for exceeding the maximum value of 25 kA is that the 66 kV substations are closely
interconnected to each 275 kV substation through the 66 kV transmission lines. Before the 275
kV transmission line will be introduced to the metropolitan area, there is no choice but to use all
66 kV transmission lines in parallel because it will be necessary to supply power from Matola
and Infulene substations to the metropolitan area with transmission lines having small
transmitting capacity. After the 275 kV line is introduced to the metropolitan area, however, it
will transmit power to the metropolitan area and the 66 kV transmission line will change its role
to supplying power regionally to the 66 kV substations from 275 kV/66 kV substations of CTM,
Facim, and SE5. Consequently, the reliability of supply is not greatly influenced even if the 66
kV system is divided into plural systems by opening the 66kV transmission lines.
Therefore, the case in which the CTM-SE3, SE2-SE3, SE3-SE7, Infulene-SE7, and SE4-SE6
transmission lines are opened is considered as an example of a countermeasure against
overloading of the CTM-SE2 line. In this case, the maximum value of the fault current
significantly falls to 21.9 kA at the CTM and Infulene substations.
Table 3.5-7 Results of Fault Current Analysis using EDM’s Current Network Expansion
Plan System (2016)
Fault current (kA)
Voltage
Station Before CTM After CTM 100 MW
(kV)
100 MW Closing Lines Opening Lines
Maputo 275 9.7 10.4 10.3
Matola 275 8.9 9.6 9.6
66 20.3 21.2 20.5
Infulene 275 9.2 9.9 9.9
66 23.6 25.0 21.9
CTM 275 8.8 9.5 9.5
66 22.9 26.2 21.9
Facim 275 8.3 8.9 8.8
66 24.1 26.0 17.8
SE5 275 8.3 8.9 8.8
66 23.7 25.1 19.9
SE3 66 24.7 26.7 16.7
3-23
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
R Garcia
10.0
Matola
Before power plant development Gare
7.8
9.2
2.5
Laulane
23.6 14.6
Infulene
deundeveloped
Maputo SE8
Machava 19.9
16.1
10.8 15.3
9.7 SE6 16.3
20.2
21.0 SE4
8.3
91361
Mozal 8.9 91371
23.7 SE5
Matola 20.3
23.9
6.7 90961
CTM SE7
8.8
90962
Beluluane 90991
22.9
90992
8.5 14.3
SE1
P.Mozal 19.1
Matola 23.0
Rio 12.7 SE2 24.7
Cimentos SE3
8.3
Boane 6.5 24.1
Facim
1.0 Salamanga
3-24
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Maputo SE8
Machava 19.5
11.2
11.0 14.8
10.3 SE6 11.2
20.6
21.4 SE4
8.8
91361
Mozal 9.6 91371
19.9 SE5
Matola 20.5
13.2
6.7 90961
CTM SE7
9.5
90962
Beluluane 90991
21.9
90992
8.5 14.5
SE1
P.Mozal 11.8
Matola 16.7
Rio 12.9 SE2 16.7
Cimentos SE3
8.8
Boane 6.5 17.8
Facim
1.0 Salamanga
The stability of the system that opens transmission lines, such as the CTM-SE3 and SE2-SE3
lines, as a countermeasure against the excess of permissible values of the fault current after a
100 MW plant is installed at CTM was analyzed. In regards to the control systems of the
generator, such as AVR and GOV, both the case where the control systems were ignored in
order to identify the stability inherent to the system and the case where they were considered
were analyzed. In addition, both fault clearing times of 0.1 second and 0.15 seconds were
considered.
Table3.5-8 shows the result of stability analysis. Figure 3.5-9 shows the fluctuation curve of the
generator voltage angle.
In the case where the control systems were ignored and the fault clearing time was 0.10 second,
the network was stable in all cases including the case where it was assumed that a fault occurred
on the CTM 275 kV bus or 66 kV bus, the closest end to the generator which is severe in terms
of stability. In the case where the fault clearing time was 0.15 seconds, however, the effect of
introducing the 275 kV transmission line to the metropolitan area could not be seen and the
network was unstable in all cases.
Comparing these results with the case described in (6) of 3.5.3 where the CTM power plant was
connected to the 66 kV system before the introduction of the 275 kV system and the network
was stable with the control systems ignored and fault clearing time being 0.15 seconds, it can be
said that introducing the 275 kV system will not be effective for improving stability. The reason
for this is considered as follows: Before the 275 kV system will be introduced, the CTM plant
3-25
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
will be connected to eight circuits of 66-kV transmission lines. Even if one of the circuits will
be opened as a result of a fault, the generator will be kept connected to the main system by the
other seven circuits. After the 275 kV system will be introduced, however, the case where the
CTM-SE3 line will always be opened to suppress the fault current is assumed. After the
CTM-SE2 line will be opened to remove faulted lines, connection to all the 66 kV transmission
lines will be lost and the generator will be connected to the main system only by a 275/66 kV
transformer with high impedance.
In practice, the fault clearing time of the 275 kV transmission line will be 0.1 second or less,
shorter than that of the 66 kV transmission line, and it is expected that stability will be
maintained even if a fault occurs on the 275 kV transmission line.
In the case where the control systems of the generator are considered, stability will be
maintained in all cases where a fault on all the 275 kV and 66 kV transmission lines is assumed,
even if the fault clearing time is assumed to be 0.15 seconds. In general, a control system will be
installed for all generators, and it is considered that the network will not become unstable.
Table 3.5-8 Results of Stability Analysis under EDM’s Current Network Expansion Plan
System (2016)
Control Fault Clearing
Faulted Line Fault Point Stability Case No.
System Time
0.10 sec Stable 8
275 kV Matola-CTM
0.15 sec Unstable 9
0.10 sec Stable 10
275 kV Infulene-CTM CTM 275kV
0.15 sec Unstable 11
Ignored
0.10 sec Stable 12
275 kV CTM-Facim
0.15 sec Unstable 13
0.10 sec Stable 14
66 kV CTM-SE2 CTM 66kV
0.15 sec Unstable 15
275 kV Matola-CTM 0.15 sec Stable 16
275 kV Infulene-CTM CTM 275kV 0.15 sec Stable 17
Considered
275 kV CTM-Facim 0.15 sec Stable 18
66 kV CTM-SE6 CTM 66kV 0.15 sec Stable 19
(Source: Network analysis results from the JICA Study Team using data provided by EDM)
3-26
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(5) Conclusion
Table 3.5-9 provides the analysis results under EDM’s current network expansion plan system.
The ascertained results by power flow analysis are as follows:
Overloading of many existing 66 kV transmission lines will be solved by introducing 275 kV
transmission lines to the metropolitan area but some overload will remain for some transmission
lines for regional supply to which the effects of introducing the 275 kV lines are not reached.
This is an intrinsic problem that rises as demand grows. To solve this problem, the conductors
of existing transmission lines need to be changed to thick ones or new transmission lines must
be installed.
The ascertained results by fault current analysis are as follows:
As a result of introducing the 275 kV transmission line, the fault currents of the 66 kV bus will
substantially increase, exceeding the maximum permissible value of 25 kA at five stations. As a
countermeasure against this, replacing the existing breaker with a new one having a high rated
3-27
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Fuel gas supply is considered as a part of the natural gas distribution project to Maputo by Empresa
Nacional de Hidrocarbonetos de Mocambique (“ENH”, English name - Mozambican National
Hydrocarbon Company). Therefore, any construction cost for gas feeding to the CCGT Project is
basically out of the scope of the CCGT Project . Since natural gas supply volume is limited to 6
MGJ per year, the power output of the new CCGT is also limited to approximately 100 MW.
3-28
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Gas incoming
Gas Station
The Environmental Impact Assessment (“EIA”) for the gas pipeline construction works from PRS-2
to CTM and Maputo City have already been approved by the government. In the meantime, in the
case of the Beluluane site, it is necessary to newly install a gas pipeline from PRS-2 to the Beluluane
site and a concession agreement with Matola Gas Company, etc., may be required and thus another
EIA for this work may also be required. Therefore, it is anticipated that it would take a longer time
to construct a power plant at the Beluluane site. Getting approval for the EIA and making a
concession agreement would likely cause a delay of construction of the power plant at Beluluane.
According to the sections on “Development area and general layout”, “Fuel gas volume
constraints” and “Transmission constraints,” one block multi-shaft 1-on-1 CCGT, with capacity
3-29
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
of Maximum 50 MW can be installed at the Beluluane site and one block of multi-shaft 2-on-1
110 MW CCGT can be installed at the CTM site. Applicable CCGT models for each site are
shown Tables 3.7-1 and 3.7-2 from the 2012 GTW Handbook. At the CTM site, a GGCT model
can be selected from many manufactures. However, at the Beluluane site, only a few applicable
CCGT models can be selected.
Table 3.7-1 Major Combined Cycle Power Generation Plants for Beluluane (GT
One-shaft Configuration)
Efficiency (%]
Manufacturer Model Output (MW)
(LHV)
GE 106F 118.4 55.0
Siemens SCC800 66.1 53.7
GE 106B 64.8 50.4
IHI (GE licensee) LM6000PD 55.2 53.3
Hitachi 1025(H-25) 43.8 50.1
Rolls-Royce RB211-GT61 42.6 52.8
(Source: JICA Study Team)
Table 3.7-2 Major Combined Cycle Power Generation Plants for CTM
(GT One-shaft Configuration)
The results of the comparison and study of the two power plant construction sites are shown in
3-30
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Table 3.8-1. The CTM site was selected as the project site for a power plant up to 100 MW. The
major determining factor was transmission network capacity constraint. The results of the
comparison and study of the two power plant construction sites are shown below.
CTM Beluluane
3-31
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(3) Other
The location of the CCGT power plant at CTM requires environmental approval from MICOA.
Prior to the approval, an application for determining the category of a social EIA must be filed.
In accordance with the intentions of EDM to promptly advance these administrative procedures,
the basic specifications of the CCGT power plant were assumed as follows and local
applications were moved forward in parallel and simultaneously.
Generated electricity is delivered to mainly Maputo City via the existing CTM 66 kV
substation ajacent to the CTM power station.
The monitoring and control system will be integrated into the exisiting Supervisory Control
and Data Aquisition (“SCADA”) at the Southern region load dispatch center adjacent to the
power station.
The power plant is expected to start construction in 2014 and be put into commercial
operation in 2017 using Japan’s Offical Development Assistance (“ODA”) financial
source.
The power plant is expected to achieve a lower production cost of approximately 0.07 –
0.08 USD/kWh, and its construction cost on EPC contact basis is estimated to be
approximately USD 120 million in consideration of international practices so far.
3-32
Chapter 4
CCGT capacity is restricted by the amount of fuel natural gas that will be supplied. Since the
gas supply amount to the new gas-fired power plant is 6.0 MGJ/year, the power plant capacity is
calculated at approximately 114 MW.
The available generation capacity (MW) = 6.0 x 106 x 109 x (50/100) /(24 x 365 x (83/100) x 3.6
x109)
where the plant thermal efficiency and capacity factor are assumed to be 50% and 83%,
respectively.
Table 4.1-1 shows applicable CCGTs which can support the power generating possible output of
114 MW calculated from the gas supply amount in the CCGT with the multi-shaft 2-on-1 CCGT
in the order from larger output. Each CCGT output and efficiency is from under ISO conditions
(i.e., 15C, humidity 60%, 1013hPa).
4-1
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
For CCGT rated capacity, the CCGT range for selection can be expanded by making a setting
with a margin of 70-110 MW and the promotion of proper and active competition bidding
among EPC contractors.
There are two types of CCGT configurations: one-shaft configurations and multi-shaft
configurations. One-shaft configurations connect the GT, steam turbine, and the power
generator on the common shaft. If the common shaft is not shared by the GT and compressor, a
one-shaft configuration cannot be used.
In Japan, nuclear power plants operate 100% load as the base load of power demand, and
thermal power stations operate for middle and peak loads for changing electric power demand.
For one-shaft configurations it is possible to quickly stop and start high thermal efficiency at
plant partial loads, therefore one-shaft configurations are adopted in great quantities in Japan.
Multi-shaft configurations use different shafts for the GT generator and for the steam turbine
generator. They are used in the world in great quantities.
In addition, multi-shaft configurations include 1-on-1 types having one block of one GT
generator, HRSG, and one steam turbine generator and 2-on-1 type including two GT generators,
two HRSGs, and one steam turbine generator.
4-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Fuel
Gas Stack
Generator
Turbine
Heat Recovery Steam
Compressor Generator
Air Pump
Steam Turbine
Generator Gas Stack
Generator
Turbine
Heat Recovery Steam
Generator
Condenser Air Pump
4-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The following compares the output and efficiency between one block of multi-shaft type 2-on-1
CCGT and two blocks of multi-shaft 1-on-1 type and one-shaft type CCGT.
(2) Operability
CCGT is operated only by automatic control of the fuel flow to the GT and starting, normal
operation, and stopping operation can be automated completely regardless of the shaft
configuration. The difference of shaft configuration does not mean any essential difference of
operability. For one-shaft CCGP, since auxiliary steam is ensured from the auxiliary boiler and
operating unit and both the GT and steam turbine are started or stopped, it can start or stop more
quickly than the multi-shaft type.
For multi-shaft 2-on-1, even if other GTs stop because of maintenance, it can continue to
operate with about 50% of the load in the plant.
In case of the single-shaft configuration, however, the steam for the flow passage cooling and
gland sealing of the steam turbine which must be started up together with the GT is required
from any external source or the operating unit. For this purpose, any auxiliary steam from the
existing boilers or a standalone auxiliary boiler will be needed.
4-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
G:1
HRSG GT ST Generator
Single ST = 0.66 x 0.7 x 2
shaft GT =1.28 x 0.3 x 2
0.5 G:1.5
(Type C) Total = 1.69
0.5 G:1.5
4-5
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
4-6
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The concerned power generation plant will be built in southern Maputo city in Mozambique to
cope with the tight power demand in Mozambique. For this plant, one unit operation is assumed
for the present and continuous operation of the power plant with as high efficiency as possible is
required.
Globally, in the case of plants that require high efficiency operation and high capacity factor,
multi-shaft 2 and more-on-1 CCGTs are installed.
The JICA Study Team recommends multi-shaft 2-on-1 CCGT since it is superior in the total
efficiency of the power plant and it allows partial load operation with high efficiency of about
50% even if a GT stops because of periodic maintenance, etc., and it has maintenance costs. In
addition, after an investigation of the gas supply amount, site area, and applicable CCGT
models to be supported, 70-110 MW of CCGT rated capacity was recommended to EDM in the
first workshop and was approved.
Cooling Tower
Stack
Waste Water
Treatment
Plant
Heat Recovery
Steam Generator
100000
Workshop
GIS &
Transformer
Fuel Gas
Compressor
Electrical room &
Control room
Air Compressor
100000
4-7
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Cooling Tower
Stack
Waste Water
Treatment
Plant Beluluane
Heat Recovery
Steam Generator
Substation
Workshop
GIS &
Transformer
Fuel Gas
Compressor
Electrical room &
Control room
Air Compressor
100000
(i) Former coal-fired power station: Yard of 270 m x 96 m (approx. 2.6 ha)
EDM has the intention of separating the power station from the substation located to the east of
the power station and plans to install a fence at the boundary and a road to access the substation
along the boundary to the north of the power station.
4-8
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
type 2-on-1 CCGT. Typical CCGT layouts using each GT are shown in Figure 4.2-4 and Figure
4.2-5. In either case, two GT Generators, two HRSGs, one steam turbine generator, and utility
equipment such as switching gear, water treatment equipment, and wastewater treatment
equipment fit in an area of 150 m x 100 m.
Emergency
Fuel Gas Diesel GIS &
Station Generator Transformer
Waste Water
Treatment Plant
Generator
Generator
Air Inlet
Room
100000
Steam Turbine Air Compressor
Gas Turbine Gas Turbine
Condenser
Workshop
Stack
Stack
150000
Air Cooled
Condenser
Fuel Gas
Gas Turbine Compressor
Generator
100000
Waste Water
Treatment
Heat Recovery Plant
Steam Turbine Steam Generator
Generator
150000
4-9
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Using the site conditions of CTM Maputo and a typical plant layout for reference, three cases of
plant layouts were studied.
1) Case 1: Installing the main facility in the diesel oil tanks area and the utility facility in the
existing No. 3 gas turbine area
In case 1, the area of the former coal-fired power plant facilities can be used as the site for future
plant extension. In addition, expenses for land clearing and demolition removal can be reduced
because the foundation of the thermal power plant facilities is available at the site of the former
coal-fired power station. The tie-in point of portable water and fuel gas are close by. Sufficient
space is also available for construction and maintenance for the power plant facilities. Moreover,
because the site is far from the northern boundary of the power station where residents live, there
is no need to protect against noise, such as installing soundproof barriers.
EDM intends to modify the control equipment of the existing Nos. 2 and 3 GTs and install a
distributed control system (“DCS”) in the central operation room of the new power plant, so that
the existing GTs can be started from the central operation room in case of an emergency
shutdown, e.g., if the new power plant stops due to trouble. Both the equipment and site can be
operated and managed combining the existing Nos. 2 and 3 GTs and new power plant.
270m
New Gas
Station
Portable
Water Tie-in
point
145m
Air Cooled
Condencer
125m
2) Case 2: All facilities installed at the former coal fired power plant area
Taking into consideration any future construction for power plant extensions, the power plant
will be constructed from the side of the former coal fired power plant turbine building behind
4-10
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
the power station. The longitudinal direction is 96 m, i.e., narrower than 100 m. It will be even
narrower if an access road to the switching yard is built along the northeastern boundary fence.
Consequently, sufficient work area will not be available during power plant construction work
and for maintenance and inspection. In addition, the former coal fired power plant site needs to
be demolished and cleared for construction of the new power plant. The site is closest to the
substation as compared with the other cases and the distance over which cables would be laid
down to the substation is short. As there is a nearby residential area, noise prevention measures
may be necessary. For future extension of the power plant, both the part of the former coal fired
power plant site that will become available after construction and the diesel oil tank area will be
reserved.
270m
150000
Control room
Electrical room &
Steam Generator
Heat Recovery Steam Turbine Generator
Plant
Treatment
Waste Water
New Gas
Station
Raw Water Tank
Demineralized Water Tank &
100000
Portable Compressor
Fuel Gas
Water Tie-in
Gas Turbine Generator
Condencer
Air Cooled
point
145m
125m
3) Case 3: All facilities installed in the current diesel oil tank area
The 110 MW class multi-shaft 2-on-1 CCGT does not fit into the diesel oil tank area. The
equipment that spills over must be installed in the former coal fired power plant area. It is
therefore necessary to demolish the former coal fired power plant area. The area for future
power plant extension will be smaller than case 1 and the land area will be an odd shape.
In case 3, the tie-in points of fuel gas and portable water are close, like in case 1, and the
distance over which pipes must be laid down is short. There is a sufficient work area for
construction work and inspection and maintenance work for the equipment and power plant
extension.
Since the plant is far from the northern boundary of the power station where residents live, there
is no need to have any noise protection such as installing soundproof barriers.
4-11
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
270m 270m
New Gas
Station
100000
Waste Water
Demineralized Water Tank &
Treatment
Demineralize Water Plant,
Plant
Portable
Control room
point
145m
145m
Gas Turbine Generator
Steam Generator
Heat Recovery
150000
Steam Turbine Generator
Condencer
Air Cooled
125m 125m
Case Results
・Area of former coal fired power plant can be used for any power plant extensions
in the future.
Advantages ・Very close to the new gas station and portable water tie-in point.
Case 1 ・No need for any noise protection on the boundary line.
・Sufficient construction and maintenance work area.
Disadvantages ・Existing No. 3 GT area is used.
・Site area can be reserved for future extensions of the power plant.
Advantages
・Close to substation.
Case 2 ・Site for the power plant is slightly narrow.
Disadvantages ・Therefore, sufficient construction and maintenance work area is not available.
・Noise protection is needed on the site boundary line.
・Very close to the new gas station and portable water tie-in point.
Advantages ・No need for any noise protection on the boundary line.
・Sufficient construction and maintenance work area
Case 3
・Area for future power plant extension is narrower than the other two cases.
Disadvantages ・Facility protrudes into the former coal fired power plant area, making layout
inappropriate.
(Source: JICA Study Team)
4-12
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
4.3.1 Outline
There are three types of cooling facilities for the condenser of the steam turbine in this power
generation plant, i.e., once-through cooling system, wet cooling tower system, and air-cooled
condenser system. The merits and demerits of the cooling systems vary depending on the site
peripheral conditions, operation conditions, and economic conditions such as power cost and
fuel cost. This examination of the three types of cooling facilities has been done from the
viewpoint of mechanical and constructional technology, and economic and environmental
influences to select the cooling system suitable for this project.
While the performance of the GT which is the topping cycle in CCGT has no influence on the
type of cooling system, the performance of the steam turbine which is the bottoming cycle has
an influence on it.
Since the cooling medium of water is abundant and the vacuum of the condenser can be lowered,
the output and efficiency of the steam turbine are the highest of the three cooling systems.
However, facility costs, maintenance costs, and management costs are the highest because of the
4-13
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
construction facility for water intake and discharge, equipment to remove debris from the sea,
and the facilities to keep the tube in the condenser clean. In addition, because of hot drainage,
environmental impact studies and permits/ licenses from harbor authorities, etc., are required.
The figure below shows the schematic system diagrams of the three types of cooling facilities.
4-14
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Steam
Turbine
Heat Recovery Steam Steam Heat Recovery Steam Steam Heat Recovery Steam
Generator Turbine Generator 150m 3 /h Turbine Generator
Make-up Water
for Plant Condense Condense Air Cooled
r Make-up Water r Condenser
20m 3 /h
for Plant
Make-up Water
Circulating Pump 7000m 3 /h 20m 3 /h for Plant
15m 3 /h
20m 3 /h
Make-up Water
300m 3 /h
7000m 3 /h
River/Sea
4-15
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Water intake point of former coal fired power Intake/outlet facilities (expanded view)
plant (complete view)
(Source: JICA Study Team)
Figure 4.3-2 Water intake facilities for the old Maputo coal-fired power plant
4-16
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
2) Beluluane site
At the Beluluane site, water of 3,500m3/h will always be necessary for cooling the condenser in
addition to make-up water of 10m3/h for the plan if a once-through cooling system is employed.
However, there is no water source near the site nor is there a place where river water or sea water can
be used. It will therefore be necessary to construct an inlet channel of 7 to 8 km long connecting to the
Matola River. In the case of a wet air cooling system, about 150m3/h of cooling water is necessary and,
like the once-through cooling system, constructing water conveyance facilities will be necessary.
Water other than make-up water for the plant will not be needed if an air-cooling condenser is used.
3) Comparisons
Comparisons of intake facilities in both locations are as shown in the table below.
Table 4.3-2 Comparisons of intake facilities
Cooling Wet Cooling Air-cooled
Site Item Once-through Type
Method Tower Condenser
Make-up water 20m3/h 20m3/h 20m3/h
Cooling water - 300m3/h -
CTM 7,000m3/h
Expendable
Maputo (sea water)
water Water for cooling
Site Need to construct - -
condenser inlet channel of
1.2km
Make-up water 10m3/h 10m3/h 10m3/h
Cooling water 150m3/h
Need to construct
inlet channel
- -
7-8km from
Beluluane Expendable Matola River
Site water
3,500m3/h
(river)
Water for cooling
Need to inlet - -
condenser
channel 7-8km from
Matola River
(Source: JICA Study Team)
pump and pipeline have been removed and only a pipe bridge of steel-reinforced concrete and a pump
house are left. As a result of the site survey, the facilities have been found to have been substantially
degraded and a conclusion has been reached that it would be difficult to reuse the existing
structures.(Figure 4.3-5 shows photographs of the current situation of the intake facilities at the old
coal-fired power plant.
Intake bridge for old Maputo coal-fired power plan Conspicuous exposure of reinforcing bars
(partially damaged)
(Source: JICA Study Team)
Figure 4.3-5 Assessment of soundness of existing intake facilities
4-18
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
410
400
Lifetime cost (Million USD)
390
380
370
360
350 Base
340 Gas Price 2% escalation
Higher EPC cost
330
Once-through Wet cooling Tower Air cooled condenser
(Source: JICA Study Team)
4-20
Chapter 5
Site Conditions
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
5.1.1 Topography
The proposed site is located in the existing Maputo Thermal Power Station (CTM site),
which is approximately 3 km west of the city center of Maputo city and close to the border
of Matola city. A railway linking Port Maputo and Swaziland runs immediately north of the
CTM site and a highway (EN2) is situated to the north of the railway.
The ground level of the site was raised by 1.5 to 2.0 meters when the former coal-fired
power plant was constructed in the 1950s, and the present ground level is approximately 3.3
m above MSL of Port Maputo. Since the embankment of the highway located to the north
acts as a topographic divide, rain that falls on the north side of the highway generally does
not flow in the direction of the CTM site.
As shown in Figure 5.1-1, the area surrounded by the railway embankment once suffered
from inundation caused by heavy rain. Several years ago, drainage channels with sufficient
capacity were provided on both sides of the railway embankment. Since then, no flood
damage has been reported in this area.
Infulene River
Flood-prone Railway
Highway (EN2)
CTM site
5-1
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
5.1.2 Geology
As shown in Figure 5.1-2, the stratigraphic sequence occurring at the site location consists of
Holocene superficial deposits that overlie Pleistocene (Congolote and Machava formation)
and Pliocene (Ponta Vermelha formation) geological units as described in the following
paragraphs.
Holocene deposits make up all of the surface soils of the surveyed area, comprising landfill
materials used to modulate terrain morphology in previous interventions. These materials are
mainly constituted by silty-sandy soils with coal fragments and vegetal residues.
By this description, one assumes that most of it is of alluvium nature, which might also occur
in the depths beneath the landfill deposits. Given these circumstances, it will be extremely
difficult to differentiate one from the other and all should be treated as one unit.
The Pleistocene unit, known as the Congolote formation (Qco), is mainly described as a
coarse to fine-grained sandy soil, poorly consolidated, of white, yellow or orange coloration.
It represents aeolian materials of continental dunes, constituting a sandy stratum that overlies
succeeding geological units.
Underlying the Congolote formation is the Machava formation (Qmc), mainly described as
an interbedded sedimentary deposit of clayey sands with carbonated, salty and ferruginous
formations and with a basal conglomerate.
Although its lateral limits are generally well defined, this geological unit may not be
represented throughout all of the lower Pleistocene, enabling the Congolote formation to
settle directly on the Pliocene unit Ponta Vermelha through a stratigraphic unconformity.
Ponta Vermelha formation (TPv) comprises sand, siltstones and sandstones of reddish to
yellowish coloration, occasionally with a ferruginous hard cover.
5-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Given the presented geological conditions, there are no structural evidences of tectonic
nature on the referred geomorphologic unit as the deposited sediments overlie any bedrock
that may exhibit any type of fragmentation. For this reason, there are no geological structural
constraints at the proposed site.
Field investigation by standard penetration test (SPT) was conducted at CTM site. The
locations of the boreholes (11 nos.) are exhibited in Figure 5.1-3.
5-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The following points highlight the results obtained by the field investigation.
In general, the N-value, which represents soil resistance, increases with depth with
occasional breaks, particularly when intersected with clayey interbeds.
All boreholes feature a minimum of 4 consecutive SPT refusals (> 50 blows per 25 mm
penetration), starting at depths ranging between 5 m and 15 m.
For sandy soils, a layer with an N-value greater than 50 is deemed suitable for foundation
support1. Accordingly, it is concluded that only the geological layer with an N-value of more
than 50 is rated well enough for the foundation of heavy loads, such as major machines and
structures.
1
Specifications for Highway Bridges (2002), Japan Road Association.
5-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
5.2.1 General
For general information about meteorological conditions of the site, see Section 11.2.1 of this
report, “Natural Environment Conditions.”
(Source: Atlas for disaster preparedness and response in the Limpopo Basin)
5-5
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
It is inferred that the southern coast of Mozambique, which includes Maputo city, receives
fewer cyclones than the northern and central coasts do. Furthermore, it has been reported that
tropical cyclones that hit southern Mozambique tend to lose strength, since they dissipate energy
while crossing Madagascar before hitting Mozambique.
(Source: Atlas for disaster preparedness and response in the Limpopo Basin)
Figure 5.2-2 Satellite image showing the progression of the first tropical
depression that hit Mozambique in early February
3
One of these was Cyclone Eline, which traversed almost the entire Indian Ocean and made devastating
strikes on Madagascar and Mozambique.
5-6
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
400.0
350.0
300.0
Precipitation (mm)
250.0
200.0
150.0
100.0
50.0
0.0
3 Feb. 4 Feb. 5 Feb. 6 Feb. 7 Feb. 8 Feb.
(Thu.) (Fri.) (Sat.) (Sun.) (Mon.) (Tue.)
Day
(Source: Atlas for disaster preparedness and response in the Limpopo Basin)
Figure 5.2-3 Daily precipitation recorded at Maputo City from February 3 to 7, 2000
On February 6, the No.1 GT and No.2 GT buildings in CTM site suffered from flood damage.
As explained in Section 6.7.6, it can be concluded that the damage was not caused by
inundation from river water or storm surges, but was due to the poor drainage within the CTM
site.
The tropical storms of early February were followed by Cyclone Eline, which moved into the
central region of Mozambique and caused excessive rainfall in that area. However, the southern
region including Maputo was not severely affected by this cyclone.
5-7
Chapter 6
Basic Design
(A part of this chapter has been removed because of confidential information.)
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(1) The maximum average air temperature in Maputo is expected to be 28.4C over the next five
years with many days of 35C or above. Therefore we will evaluate the effectiveness of the
GT intake cooling system with water spray and plan the installation if it is found to be
effective.
(2) The fuel natural gas will be supplied by ENH.
(3) As to the cooling system of the steam turbine condenser, as a result of the JICA Study
Team’s evaluation of technologies and economics of a once-through cooling system, a wet
cooling tower system, and an air-cooled condenser, it was determined to use the air-cooled
condenser.
6-1
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The start-up time shall be defined as the time required from the push of the start button to the
full load conditions, provided that a condenser vacuum is built and the new plant is ready for
start. The time for air purging of special volume post GT and synchronization shall be excluded
The new plant shall be designed for a continuous load operation with more than 6,132 actual
operating hours per year on the basis of a full load. The necessary hours for starting and shut
down cycle are not included in the above operating hours.Through the service time, the new
plant and associated equipment shall continue to be operated with high efficiency, high
reliability and excellent economy.
Any components of which service lives may be less than the above figures shall be designed for
ease of replacement and maintenance.
1
) Equivalent Service Hours: 24 x 365 x 30 x Plant Load Factor 83%
6-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
For the design requirements as stated above, the following annual start-up times shall be
considered:
The start-up/loading procedures, including draining and venting of the new plant, shall be
selectable and controlled automatically dependent upon such state conditions of the new plant as
very hot, hot, warm, or cold status.
The Central Processing Unit (“CPU”) shall be of duplicate configuration using the standby
redundant system to ensure the reliability of the control system. A Switching operation of
generator circuit breaker shall also be performed from the DCS located in the CCR. A
Switching operation of electrical circuits in 132/230 kV substations shall be performed from the
DCS located in the substation control room.
6-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
3.0
operation time limitation (sec)
0.0
46.5 Network Frequency (Hz) 48.5
6-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The vibration levels of the GT/generator and steam turbine/generator shafts shall not exceed 80
μm throughout the Reliability Test. Should the vibration level of any equipment exceed the
specified value during the Reliability Test of two weeks, then the Test shall be cancelled and a
new two weeks Test shall be repeated after the vibration level problem has been rectified. After
taking-over of the new plant, vibration levels shall not exceed the values during the Defect
Liability Period.
The relative vibration level at the alarm point shall be set at the level not more than 120 μm for
both the GT/generator and the steam turbine/generator. The trip value shall be set at 240 μm, if
it is acceptable depending upon the operating experience of the same types of the GT/generator
and the steam turbine/generator.
6-5
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Model of CCGT Net Plant Output (kW) Net Plant Efficiency (%)
2 x LM6000PD Sprint 120,220 53.0
2 x LM6000PD 110,970 53.6
2025(2 x H-25) 87,800 50.3
2 x RB211-GT61 85,300 52.8
SCC700 2 x 1(2 x SGT-700) 83,630 52.5
Where, the net specific energy (lower heating value) of the natural gas is assumed to be 49,826
6-6
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
kJ/kg (40.2MJ/Nm3 at 15C) calculated from the fuel gas data received by the JICA Survey
Team . The correction of the performance data of the above GTs to the site, inlet and exhaust
conditions was conducted in accordance with various correction factors based on the wide
experience of the JICA Survey Team in dealing with this type of data. The inlet and exhaust
pressure loss changes for combined cycle configuration are also predicted. The site conditions
are designated as tabulated below, as per the site survey results:
The rated site conditions are specified in accordance with ones for the existing GT power plants,
while the maximum capacity site conditions are specified as the monthly averaged minimum
ambient temperature and the relative humidity for the time. The installation capacities of
electrical and auxiliary equipment must be determined to cope with the GT maximum capacity
and the performances of the bottoming system (HRSG and steam turbine) dependent upon it.
The GT maximum capacity is widely changeable depending upon the site ambient conditions
(especially ambient dry bulb temperature). To determine the installation capacities of electrical
and auxiliary equipment, therefore, the site ambient conditions where the GT maximum
capacity is defined must be specified.
According to the records for five years from 2007 to 2011 in Maputo International Airport in
the suburb of the CTM Power Plant, the average lowest air temperatures in the winter months
were +13C to +14C and sometimes +10C to +11C. From the viewpoint of effective use of
the power generation facility, 10C is considered to be the lowest air temperature. Therefore, the
installation capacities of electrical and auxiliary equipment shall be determined to meet the
operating performances of GTs and bottoming system at the ambient dry bulb temperature of
10C. The relative humidity for the ambient temperature is 75%.
To obtain the plant net power output, auxiliary power requirements, including the step-up
transformers under steady state conditions at 100% load of the plant, must be predicted. The
JICA Study Team calculated the plant net power output by using computer plant analysis
software and carrying out calculations for each large-output GT model. The cycle
configurations and parameters of the bottoming system may be variable depending upon
manufacturers of combined cycle power plants. However, the following cycle configurations
and parameters are preliminarily assumed for calculation of CCGT heat balances.
6-7
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
At this point, because the temperatures of the exhaust gas from the GTs differ by the model, the
high-pressure steam temperatures were calculated taking the exhaust gas temperature of each
model into consideration. Leakage of 0.5% of the exhaust gas flow rate from the GTs is
assumed for the calculation of the heat balance of the bottoming system.
6-8
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
From this table of the calculation results, it was calculated that the net power output of the
CCGT models under the rated site conditions is 72.3 to 106.5 MW or 86 MW on average.
Therefore, the net output of these power facilities is 85 MW and, taking into consideration the
appropriate likelihood for the above calculated value, the net power output will be specified on
the purchase specification as 70 MW to 110 MW to encourage many parties to participate in the
bidding.
The net thermal efficiency of the power generation facilities under the rated site conditions was
calculated to be 46.8 to 51.4%. Therefore, the net thermal efficiency of these power facilities is
specified on the purchase specification as 46% or more. The maximum total power output of the
power facilities is calculated to be in the range of 73.8 to 108.8 MW.
Air temperature performance characteristics of the two CCGT models are shown below. From
this chart, it is evident that each CCGT has similar output characteristics.
As representative CCGT models using GTs of aircraft conversion types and those of
heavy-structural industrial types, LM6000PD Sprint and H-25 were chosen to show below the
heat balance diagrams under the rated CCGT site conditions and the maximum capacity CCGT
site conditions.
140
LM6000PD Sprint
LM6000PD
120
H-25
RB211-GT61
100
Net Power Output (MW)
80
60
40
20
0
0 5 10 15 18 20 25 28 30 35 40 45 50
Ambient Temperature (C)
6-9
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
117.3 T
P : kPa 529.1 P
o From Other HRSG
T: C 251.1 T
HP
G : kg/s HP Eva 7194.1 P 4.133 G
H : kJ/kg 270.6 T 2,962.0 H
11.243 G 529.1 P
Demi Water 1,187.0 H 500.0 P 251.1 T
From Other HRSG
Steam B LOW 6471.6 P 250.0 T 4.133 G
Gas (Air) 0.220 G 431.8 T 9.404 G 2962.0 H
11.238 G 6000.0 P 2,962.0 H
3250.0 H 429.0 T
22.475 G
HP SH DeSH
3,251.0 H
2.20 G
6471.6 P
431.8 T
11.238 G FUEL
COMBUSTOR
3,250.0 H
GENETATOR
104.0 P
464.0 T GAS COMP STEAM TURBINE
122.280 G TURBINE
491.9 H
11.9 P 739.6 P
49.2 T 49.2 T
30.740 G 31.470 G
2,311.0 H 206.0 H
AIR
AIR COOLED
101.3 P CONDENSER
28.0 T FROM STEAM
TURBINE
GLANDS
Figure 6.2-2 Heat Balance Diagram of 2 x LM6000PD Sprint at the rated site conditions performance
6-10
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
111.2 T
P : kPa 529.1 P
o From Other HRSG
T: C 251.1 T
HP
G : kg/s HP Eva 7194.1 P 4.700 G
H : kJ/kg 270.6 T 2,962.0 H
11.534 G 529.1 P
Demi Water 1,187.0 H 500.0 P 251.1 T
Steam B LOW From Other HRSG 6471.6 P 250.0 T 4.700 G
Gas (Air) 0.226 G 425.2 T 9.404 G 2,962.0 H
11.308 G 6000.0 P 2,962.0 H
3,233.0 H 422.4 T
22.616 G
HP SH DeSH
3,234.0 H
2.43 G
6471.6 P
425.2 T
11.308 G FUEL
COMBUSTOR
3,233.0 H
GENETATOR
104.0 P
448.0 T GAS COMP STEAM TURBINE
133.913 G TURBINE
469.5 H
4.7 P 739.6 P
31.8 T 31.9 T
32.021 G 32.800 G
2,214.0 H 134.0 H
AIR
AIR COOLED
101.3 P CONDENSER
10.0 T FROM STEAM
TURBINE
GLANDS
Figure 6.2-3 Heat Balance Diagram of 2 x LM6000PD Sprint at the maximum capacity site conditions
6-11
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
106.2 T
P : kPa 529.1 P
o From Other HRSG
T: C 251.1 T
HP
G : kg/s HP Eva 7194.1 P 2.011 G
H : kJ/kg 270.6 T 2,962.0 H
11.461 G 529.1 P
Demi Water 1,187.0 H 500.0 P 251.1 T
From Other HRSG
Steam B LOW 6471.6 P 250.0 T 2.011 G
Gas (Air) 0.225 G 502.8 T 4.022 G 2962.0 H
11.481 G 6000.0 P 2,962.0 H
3424.0 H 500.0 T
22.961 G
HP SH DeSH
3,422.0 H
1.62 G
6471.6 P
502.8 T
11.481 G FUEL
COMBUSTOR
3,424.0 H
GENETATOR
105.3 P
562.0 T GAS COMP STEAM TURBINE
85.169 G TURBINE
605.4 H
13.9 P 739.6 P
52.5 T 52.6 T
26.983 G 27.624 G
2,369.0 H 220.0 H
AIR
AIR COOLED
101.3 P CONDENSER
28.0 T FROM STEAM
TURBINE
GLANDS
Figure 6.2-4 Heat Balance Diagram of 2 x H-25 at the rated site conditions performance
6-12
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
95.9 T
P : kPa 529.1 P
o From Other HRSG
T: C 251.1 T
HP
G : kg/s HP Eva 7194.1 P 2.181 G
H : kJ/kg 270.6 T 2,962.0 H
11.811 G 529.1 P
Demi Water 1,187.0 H 500.0 P 251.1 T
From Other HRSG
Steam B LOW 6471.6 P 250.0 T 2.181 G
Gas (Air) 0.231 G 502.8 T 4.022 G 2962.0 H
11.838 G 6000.0 P 2,962.0 H
3424.0 H 500.0 T
23.675 G
HP SH DeSH
3,422.0 H
1.73 G
6471.6 P
502.8 T
11.838 G FUEL
COMBUSTOR
3,424.0 H
GENETATOR
105.3 P
556.0 T GAS COMP STEAM TURBINE
90.176 G TURBINE
592.4 H
5.6 P 739.6 P
34.8 T 34.9 T
28.038 G 28.703 G
2,268.0 H 146.0 H
AIR
AIR COOLED
101.3 P CONDENSER
10.0 T FROM STEAM
TURBINE
GLANDS
Figure 6.2-5 Heat Balance Diagram of 2 x H-25 at the maximum capacity site conditions
6-13
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-14
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
There are no differences between plants with and without the exhaust gas bypass system as far as
the start-up capability of the plant is concerned.
A bypass stack (3.3 m summit diameter, 28 m height) with a silencer (depending upon
environment protection requirements)
A diverter damper
A guillotine damper (for maintenance of the bottoming system during the simple cycle
operation)
6-15
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
operation of the GT/generator package will start earlier by approximately six months. This
advantage shall be evaluated by the plant purchaser depending upon the extent of the strong
demand for power supply.
(5) Performance
Excess exhaust pressure loss will occur due to the installation of the bypass system between the GT
exhaust and the heat recovery steam generator. Moreover, there will be an amount of exhaust gas
leaked into the atmosphere through the bypass damper, which will result in power loss of the steam
turbine. Consequentially, both the plant power output and efficiency will be lower in comparison
with plants that do not have the bypass system. Depending upon the type, size and system design of
the damper, the steam turbine power output drop is reportedly approximately 0.5 – 1.5% as an
average value over the lifetime of the plant. It means that the plant efficiency drops by 0.17 – 0.5%.
In the case that a silencer is installed in the bypass stack, the steady and proper function over the
plant lifetime of the silencer, which is exposed to high temperatures and high velocity of gas, is a
concern. Additional deliberate and daily maintenance work is required to maintain the exhaust gas
bypass system in good condition so that it can be reliably used whenever it is needed. There are
many CCGTs using exhaust gas bypass facilities worldwide.
6-16
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Low
The constructed damper, which will
Base be exposed to high temperature
2. Operational Reliablity
atmospheres, cannot keep the
originally dimensioned shape over the
lifetime of the plant.
Base
Construction cost not necessary +Approx. USD 2M for facility and
3. Cost Impact construction
Operation & maintenance cost not Operation & maintenance cost
necessary necessary
Base
4. Footprint Necessary for the facility
Unnecessary
5. Phased Construction Impossible Possible
0.17 - 0.5% lower
6. Performance
Base due to increase of exhaust pressure
(Thermal Efficiency)
loss and leakages of GT exhaust gas
Maintenance and operation
7. Other Base
experience necessary.
(1) Necessity
In the case of a multi-shaft CCGT without a standalone auxiliary boiler, the GT can be started up
together with the HRSG separately from the steam turbine/generator. After a certain period of time
the necessary steam for start-up will become available from its own HRSG and then the steam
turbine/generator can be started up under its own steam; however the HRSG will be started up with
a higher oxygen concentration in the HRSG inlet feed water than under normal operating
conditions because of the start up without gland sealing of the steam turbine.
In the case of multi-shaft CCGT with a standalone auxiliary boiler, gland sealing of the steam
turbine can be supplied from external sources before the GT and HRSG are operated. As the
necessary steam for start-up can become available from external sources, the steam
turbine/generator can be started up without any loss of time and the HRSG can be started up within
permissible oxygen concentration in the HRSG inlet feed water by gland sealing of the steam
6-17
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
turbine.
If a standalone auxiliary boiler is applied to this project, then the tender shall recommend the
specifications for a standalone auxiliary boiler.
A review of the GS and steam turbine buildings was conducted, and the characteristics of the GT
and steam turbine facilities with or without buildings are shown in the table below:
Table 6.2-5 GT and Steam Turbine Facilities With and Without Buildings
6-18
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Source: GE brochure)
6-19
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-20
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-21
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The construction scope of the contractor shall include the preparatory construction in the early
phase including the power supply for construction, the construction of temporary facilities for trial
operation and tests that are necessary for the operation of the power generation facility, and the
construction of the permanent facilities.
The work scope of the contractor shall include technical instructions to the sub-contractors and the
equipment suppliers so that the operation of the power generation facility can be commenced in
addition to the training of the operation and maintenance personnel of the newly-installed power
generation facility.
In cooperation with the CTM CCGT operation personnel, the contractor shall start the
newly-installed power generation facility and execute early-phase operation thereof. The contractor
shall instruct the new operation personnel of the CTM CCGT and, in cooperation with the same
personnel, plan smooth technical instructions from construction of the newly-installed power
generation facility to commencement of operation thereof. Note that any additional construction
and work items shall require agreement by contract.
6-22
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-23
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
1) Supervision of construction
2) Management of construction schedule
3) Preparation and control of construction workers and preparation of tools to be used by them
4) Preparation of construction machines
5) Safety and loss control program
6) Quality assurance program
7) Procurement promotion assurance
8) Receiving, handling and storing devices and materials
9) Preparation condition check, tests, start up and trial operation
10) Supplying lubricants necessary for start up, tests and operation in the early phase and chemicals
necessary for water treatment and chemical analyses
6-24
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
11) Supplying lubrication devices and lubricants for flushing and filling in the early phase
12) Performance and reliability tests
13) In-factory and on-site training of operation/maintenance personnel from EDM
14) Support supervision of operation and maintenance for six months after the acceptance test by
three engineers resident on site (i.e., mechanical, electrical and control)
15) Completion of construction and finish of site
16) Construction of a storage warehouse
17) Safety and medical aid during construction
18) Participating in arrangement meetings required by CTM CCGT and other meetings
19) Payment of lodging expenses, wages and traveling expenses with regard to factory tests and
inspections
20) Obtaining local, provincial and national approvals and authorizations necessary for
construction of the newly-installed power generation facility
The period of each design meeting shall be within every four weeks. The meeting shall be
separated into four or more working groups including engineering, mechanical, electrical and
instrumentation/control working groups. The meetings shall be held in those periods that are
effective for promotion of the project in conformity with the contract between EDM and the
contractor.
All the documents and drawings to be discussed at each design meeting shall be submitted to EDM
at least one month prior thereto. The contractor shall participate in the meetings at its own expense.
To obtain the approval of EDM and the consultant, the contractor shall, within one month after
commencement of work, submit a list of participants, a list of discussion items, detailed schedule
documents and a list of drawings, as well as a design meeting schedule with regard to the
requirements from EDM. If it is determined that an interpreter is necessary at the design meetings,
the contractor shall prepare an interpreter at its own expense. To complete the CTM CCGT as
6-25
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
scheduled, EDM will review and supervise the contractor’s designs and construction and, if
necessary, make the contractor execute changes, improvements and amendments. Any changes in
the contract amount for these design changes shall require the mutual consent of EDM and the
contractor.
(1) Supplying drinking water, warm water, natural gas and electric power during construction
(2) Supplying power for start up and auxiliary steam
(3) Preparing an environment assessment
(4) Supporting the obtainment of all approvals and authorizations necessary for the construction
and operation of the newly-installed power generation facility
(5) Offering information on natural gas and electric power loads for trial operation and
assurance and reliability tests
(6) Evaluation of the periodical items of the operation and maintenance data and information
during the two-year guarantee period and operation and maintenance conditions
(7) Preparation of on-site manpower, facilities and tools with regard to inspection to be executed
after the expiration of the guarantee period
(8) Removal of the existing oil tanks and relocation of power cables for existing No.3 Gas Turbine
6-26
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Portable
Wate r Tie- in
point
66 kV Tie -in
point
Contraction
Spare Are a
6-27
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-28
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
construction for the engineering and construction work shall be in conformity with the related standards
and criteria of Mozambique.
6-29
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Ste am Tu rbin e
Ge n e rator
He at Re c ove ry
Ste am Ge n e rator
Air Coole d
Con de n se r
Ele c tric al Room &
Con trol Room
Waste Water
Tre atme n t Work Sh op
De min e ralize Wate r Plan t, Plan t
De min e ralize d Wate r Tan k &
Raw Wate r Tan k
Stac k
Heat Recovery
Steam Gene rator
Gas Turbine
Gen erator
6-32
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
All measurements of noise and testing shall be done in accordance with ANSI B133.8. To comply
with the above stated noise criteria, any modifications necessary, including the installation of
additional and/or improved sound attenuation equipment, shall be implemented.
6-33
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-34
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The continuous monitoring system for the amount of effluents from the wastewater treatment
system and its pH value and turbidity shall be monitored. The monitoring shall be conducted at the
treated water pit of the wastewater treatment system in the Plant.
In order to select a GT that satisfies this requirement from the 2-on-1 CCGTs having an output of
70 to 110 MW as described in the “Gas Turbine World 2012 GTW Handbook (Volume 29),” then
there are five models listed below as candidate GTs for this project:
The GT power output shall be specified on the basis of continuous base load with the load
weighting factor of 1.0 for calculation of the equivalent operating hours (“EOH”), which will be a
scale of the inspection intervals of hot gas path parts.
The GT shall be operated with natural gas specified in Section 6.5.8, “Fuel supply facility.”
The GT shall be of an advanced design to meet the NOx emission requirement of less than 25 ppm
6-35
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(15% O2 basis of dry volume) for dry conditions for operation on specified natural gas under 75 –
100% load.
The GT shall be of proven design with manufacturer’s design practices to basically meet the
requirements of ISO 21789 Gas turbine applications – Safety.
The GT may be equipped with the evaporative type inlet air cooling system to augment the GT
power output. According to climate data recorded for five years from 2007 to 2011 at Maputo
International Airport near CTM site, the temperature difference between average dry and wet bulb
temperatures is estimated at 3.5oC. This means that the GT inlet ambient temperature could be
decreased by at least 2.4oC utilizing the current widely-used evaporative cooling system. As a
result, the net power output may be increased by increasing fuel consumption.
The proposed GT shall be of a similar model to GTs, of which at least one GT has the experience
of successful commercial operation of not less than 6,500 hours of actual operating hours as of the
Bid closing date.
The GT design shall be with a minimum number of bearings, and shall be located on a steel frame
or on adequate steel structures and concrete foundation, sized for the transient maximum
transmittal torque imposed on the shaft in case of any short circuit of the generator or out-of-phase
synchronization, whichever is larger. The power output shall be taken out at the cold end of the
shaft.
The GT shall be directly coupled to the generator without any power transmission gear.
6-36
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
the absence of the critical rotating equipment such as circulation pumps. There is no difference in
cold start up time periods due to the fact that in the transient heat up phase, the bulk of the time is
spent on heating the metal and water of the evaporator module, which is nearly the same whether it
is a natural or a forced circulation HRSG. In summary, both natural and forced circulations HRSGs
are widely used in the industry, while the natural circulation design has an edge over the forced
circulation design as discussed above. Hence the natural circulation types HRSG are proposed for
this project.
A comparison table (Table 6.4-5) for the type of HRSG circulation is provided for reference.
6-37
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(3) Conclusion
In view of the above reasons, HRSG of natural or forced circulation types are both acceptable for
this project. However, the natural circulation type HRSG is preferred.
With regard to flue gas flow direction, horizontal or vertical gas flow types are both acceptable for
this project. The flue gas flow direction will be decided based on the manufacturer’s
recommendation and the layout proposed during the contract stage, etc.
6-38
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The steam turbine shall be of the manufacturer's standard proven design and construction to allow
economical and reliable service with minimum maintenance work. The steam turbine to be
proposed shall be of similar design to the steam turbines of which at least one unit has the
commercial operation hours of not less than 6,500 hours as of the Bid closing time.
The steam turbine and auxiliary systems shall be designed to run continuously under all specified
operating conditions over the specified lifetime of the plant. The steam turbine maximum capability
shall satisfy the conditions of steam pressure, temperature, and flow as developed by the HRSG
when the GT is operated on maximum capability ambient conditions. In case that the HRSG is
supplementary fired, the steam turbine shall be sized to cope with the maximized capability of the
HRSG in consideration of the supplementary firing over the specified ambient conditions.
The steam turbine shall be designed so that the expected life expenditure of the main components
(casing and rotor) shall not exceed 75% of the expected lives of the components at the end of the
specified service hours when it will operate on specified conditions.
The steam turbine shall be provided with the necessary number of bore scope ports for easy
inspection of the operating conditions of the blades and rotor at periodical intervals, if applicable.
6-39
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Properties
Compositions (mol%)
Methane 90.823
Ethane 3.452
Propane 1.732
Normal Butane 0.535
Isobutane 0.449
Normal Pentane 1.212
Isopentane 0.152
Normal hexane 0.172
Normal heptane 0.066
Normal octane 0.0018
Nonane 0.0002
Oxygen 0.027
Nitrogen 2.454
Carbon Dioxide 0.001
Hydrogen Sulfide 0
Total 100.0
Hydrogen Sulfide (g/ m3) 0.000
Specific Energy (kJ/kg)
Gross specific energy 52,735
Net specific energy 47,562
Specific Gravity (kg/m3N) 0.8056
Min. 9°C
Temperature (°C) Max. 43°C
Performance point 28°C
Pressure at Tie-in point (bar) 25
(Source: EDM)
6-40
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Stream No. ① ② ③ ④ ⑤ ⑥ ⑦ ⑧ ⑨ ⑩ ⑪ ⑫ ⑬ ⑭ ⑮ ⑯
Flow (㎥/h) 30 2 10 10 9 9 1 18 13 1 8 5 3 3 5 5
Water Make up
Source
① ②
Control &
Office Building
Pretreatment
System
④ ⑤ ⑥ ⑦
③ Demineralizer Demineralized
HRSG Make up
System Water Storage
Water
Tank Blow down
Raw Water
Storage Tank
⑪
To atmosphere
⑩
⑨ GT Compressor
⑧ Inlet air Cooling
Auxiliary Cooling
Water Chiller
Water System
To atmosphere
6-41
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Hazardous areas will be designated and suitable equipment will be selected for use in these areas.
Different fire fighting systems will be installed depending on the operational characteristics of the
equipment, area and buildings to be protected. The fire fighting capacity of the CTM CCGT must be
able to withstand a of two hour fire according to NFPA 850 with a minimum 300 m3 and pressure of
approximately 10 bar.
The CTM CCGT will have its own fire water fighting system with pump house, and
fire water will be provided from the raw water tanks.
The water demand and required pressure for the worst case scenario will be ensured by the electrically
driven main pump, a second duty diesel engine driven pump shall be on stand-by in the case of main
supply failure. The engine driven pump will be of the same capacity as the electric driven main pump.
Table 6.4-8 List of protected areas and fire fighting and detection systems types
Item Building or Area Fire Fighting System
1 Gas turbine CO2 extinguishing system
2 Steam turbine lube oil package, Spray water dry type
lube oil piping
3 Steam turbine bearings Spray water dry type
4 Steam turbine building indoors Wet stand pipe house system
5 Generator unit, auxiliary and start Spray water dry type
6-42
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
A dedicated two hour fire water supply will be assured to cover the system design flow rate for the
facility in accordance with NFPA. A main firewater pipeline will be provided to serve strategically
placed yard hydrants and supply water to the sprinkler and spray system. The firewater distribution
system will incorporate sectionalizing valves so that a failure in any part of the system can be isolated
while allowing the remainder of the system to function properly. Fuel oil tanks will be furnished with
foam fire fighting systems.
6-43
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-44
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The rated output values of the generators shall correspond to the maximum output values of the GT
and the steam turbine. The above generation capacities show approximate ranges with regard to the
CCGT that is expected to be used. In addition, the rated voltage values are those generally used for
20-40 MW-class generators. Finally, the design voltage of the generator manufacturer will be applied.
The rated power factor shall be a delay of 0.85. The normal operation power factor shall be a range
from a lag of 0.85 to a lead of 0.95.
From the viewpoint of system stability, a larger short-circuit ratio is advantageous. However, the
short-circuit ratios have been reduced due to downsizing of machines and speeding up of the
automatic voltage regulators (“AVRs”). For the Maputo CCGT, the specification shall be for a
minimum value of 0.45. This value is also acceptable from the viewpoint of system stability
calculation. (Recommended value by IEC 60034-3: When rated output does not exceed 80 MVA in
the case of air cooling: 0.45 or higher)
c. Excitation system
Each generator is supplied with the field current by a static thyristor exciting arrangement or a rotary
rectifier exciting arrangement (brushless exciter). The excitation system includes necessary
components such as an excitation transformer, a field circuit breaker, and an initial excitation device.
For the stationary thyristor exciting arrangement, the excitation transformer shall be split from the
generator main circuit and thus supply from any other power source shall not be allowed.
d. AVRs
AVRs shall be of an immediate response excitation type. For the AVR, a dual system of a
microprocessor type shall be used. AVR devices should be installed in air-conditioned rooms. The
AVR functions shall include:
Automatic voltage regulator (90R)
Field voltage regulator (70R)
Over excitation limiter (“OEL”)
Under excitation limiter (“UEL”)
Power system stabilizer (“PSS”)
Automatic reactive power regulator (“AQR”)
Automatic power factor regulator (“APFR”)
Other necessary functions
e. GT start up method
The GT start up method shall use a motor-driven torque converter, a hydraulic pump or a thyristor,
depending on the contractor’s recommendation.
6-45
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-46
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Y-Δ (YNd11). The transformer winding type of GT generator-B/ steam turbine generator shall be a
three winding type, Y-Δ-Δ (YNd11d11). As the transformer cooling method, Oil Natural Air Natural/
Oil Natural Air Forced (“ONAN”/ “ONAF”) shall be used. The neutral point on the high voltage side
shall be direct grounding. The rated capacity on the name plate shall be based on calculation and
discussion.
b. Auxiliary transformer
The unit auxiliary transformer (“UAT”) reduces the GT generator voltage (11 kV) to the auxiliary
power voltage (6.6 kV). The UAT shall be an oil-insulation, outdoor-type, three-phase transformer
with an on-load tap changer, and the cooling method shall be ONAN. The transformer winding type
shall be Δ-Y (Dyn1). The neutral point on the 6.6 kV side shall be resistant grounding (5 ohms). Two
UATs with the same capacity shall be installed. Ordinarily, the two transformers shall both be in
service but they shall have the capacity to cover the entire load even if one of them breaks down.
The JICA Study Team has temporarily assumed the transformer capacity to be 3 MVA but the final
capacity shall be based on the auxiliary power design by the contractor. The plan is based on a 6.6 kV
load, and the gas compressor and GT starting equipment are assumed to have a 6.6 kV load. If a bidder
provides a design that is not a 6.6 kV load, the secondary transformer voltage will be set to 400V. In
this case, a transformer neutral point shall be directly grounding.
Table 6.5-2 Transformer specifications
GT Generator-B/ Auxiliary
GT Generator-A
Item Steam Turbine Transformer
Transformer
Transformer (2 sets)
Primary 66 kV 66 kV 11.0kV
Rated 11 kV 11 kV 6.6kV
Secondary-1
voltage
Secondary-2 --------- 11kV ---------
Rated Primary 411A 717A 158A
current Secondary-1 2467A 2467A 263A
Secondary-2 --------- 1638A ---------
Primary 47MVA 82MVA 3 MVA
Rated
Secondary-1 47MVA 47MVA 3 MVA
capacity
Secondary-2 --------- 35MVA ---------
Winding YNd1 YNd1d1 Dyn11
The above list shows an example of using a GT with an output of 40 MW and an steam turbine with
an output of 30 MW. Note that the maximum output of the GT is based on an atmospheric temperature
of 10C and therefore differs from the actual rating described on the plate of the generator step-up
transformer.
6-47
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-48
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-49
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
b. 400 V switchboard
The 400 V switchboard shall supply power to the middle-capacity electric motors and the motor
control center (“MCC”). The power will be supplied from the 6.6 kV bus via a 6.6/ 0.4 kV
dry-type transformer. The neutral point of the transformer shall be directly grounded. The bus
lines shall be of a 3-phase, 4-wire type. Buses are formed with the line bus (“L1”, “L2”, and
“L3”) and neutral bus (“N”).
In composition without a 6.6 kV medium voltage switch board, the electricity will be supplied
from a 11/0.4kV unit axially transformer. Please refer to “Key Single Line Diagram – 2.”
c. MCC
The MCC shall supply power to the small electric motors and 400 V or 230 V power to the
plant. The bus lines are of a 3-phase, 4-wire type. Buses are formed with the line bus (i.e., L1,
L2, and L3) and neutral bus (N). The 230 V single-phase loads are supplied from power
between the neutral line and phase lines. The switchgear shall be of a drawer type.
6-50
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
diesel generator is the safe shut down of the plant in the case of a blackout. It shall not be used
for black start of the plant.
The generator capacity shall be sufficiently tolerant for the safe shut down of the plant. The
major loads will include the AC bearing oil pumps, AC control oil pumps, gas turbine
ventilation fans, battery chargers, uninterrupted power supply (“UPS”) units, and emergency
AC lighting, etc.
a. Generator protection
Table 6.5-3 Generator protection relays
Name Element
Generator Differential protection 87G
Generator Negative Sequence protection 46G
Generator Loss of Excitation protection 40
Generator Reverse Power protection 32R
Rotor Earth Fault Protection 64R
Out-of-Step Protection 78
Generator Stator Earth Fault protection 59NG
Generator Over Current protection 51G
Generator Stator Overload protection 49G
Generator Backup Impedance protection 21G
6-51
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Name Element
Generator Over Voltage protection 59G
Generator Under and Over Frequency protection 81
Generator Under Voltage protection 27G
Over Excitation protection U/f U/F24G
Protection of other exciters
(Source: JICA Study Team)
6-52
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Also by use of hard wires, the current and voltage signals shall be connected from the CT and
the VT to the generator control panel or the protection relay.
Devices with accuracies of 0.2 or higher shall be used for measuring instrumentation with
regard to the watt-hour meters and the performance tests. Gauges for on-site operation
monitoring shall be of class 1.5 or higher.
The connection location of the step up transformer and the current composition of 66 kV GIS
are shown in Figure 6.5-4.
6-53
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
In addition, the existing CTM CCGTs No. 2 and No. 3 shall be controllable from the
newly-built central control room as well as from the CTM CCGT. The system outline is shown
in Figure 6.5-5 “Outline of Plant Control.”
6-54
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-55
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-56
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The DCS facility will consist of an operator console, a turbine control system, a data logging system, a
sequence control system, a process input/ output (“I/O”) system and related peripheral machinery,
which will be connected via a network.
The standard performance of the instrumentation and transducer are as follows:
On-site monitoring instrumentation: Accuracy class 2.0 or higher
Transducer: Accuracy class 0.25 or higher
Transducer related to performance: Accuracy class 0.2 or higher
The operator console installed in the CCR shall consist of a keyboard, a computer mouse and a dual
display (two liquid crystal displays (“LCDs”)). The GT control system, the steam turbine control
system, and the HRSG and local control system shall be connected to the DCS via redundant
communications links and by use of hard wiring signals. The signals from such systems as the air
compressor control system and the auxiliary steam supply control system shall be sent to the DCS I/O
cabinet either directly or via remote I/O units. The LCD graphics will provide the operators
information on the control and monitoring of instrument and process conditions, records and alarms.
The detection system for protection control of the GT, steam turbine and the HRSG shall be
redundancy/ triple configuration (2 out of 3) to improve the reliability of the generator facility. The
control system shall be designed so that the generator facility can be operated and controlled
automatically and the operators can be informed of the power plant status, start up/shut down status,
troubleshooting status and normal operation status.
The configuration of the control logic and graphic display of the control system shall be designed so
that maintenance staff can carry out on-site corrections and modifications easily and without making
mistakes.
DCS shall have the following functions:
a. Turbine control and monitoring functions
GT control and monitoring and GT protection circuit
6-57
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
These systems will have independent monitoring and control. In the event of any defect in the
equipment, the impact on the power station will be large. For this reason, the calculation system and
power supply system, etc., are multiplexed in order to contribute to the reliable operation of the
system.
c. Maintenance functions
Maintenance tools (an Engineering Work Station) for the maintenance of DCS shall be installed and
these tools shall have the following functions:
Control circuit setting/ changing functions
System diagram displaying/ changing functions
When specified under the treaty of LTSA, remote monitoring from the office of the maker of the gas
turbine equipment will be possible.
6-58
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
b. Walkie-talkie system
A walkie-talkie system of a frequency and output recognized by the Mozambique government shall be
used. Using multiple frequency bands and extension handsets, the master station of the wireless
installation, which will be installed in the CCR, will allow broadcast calls and calls between extension
handsets set to the same band
c. Clock device
Clock equipment with a global positioning system (“GPS”) shall be installed. The DCS and major
control equipment shall be synchronized with the clock equipment. Synchronization with the SCADA
system shall also be taken into consideration.
d. LAN system
A local area network (“LAN”) system will be established plus the internet/intranet system to be used
in the CCR, general offices and conference room, etc.
e. CCTV system
Closed-circuit television (“CCTV”) equipment will be installed for remote monitoring of the device
operation conditions and for yard security monitoring. The equipment shall use color cameras and offer the
following functions: nighttime monitoring, zoom functions, tilt functions, and automatic and manual focus
adjustment functions. The monitoring screens shall be installed in the CCR and security office.
6-59
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Foundation works (including removal of the existing oil tanks and relocating the power cable of the
existing No. 3 Gas Turbine)
Steam turbine building
Control building
Other buildings (i.e., warehouse, workshop, etc.)
Storm drainage system
Road work
6.6.2 Earthquakes
Figure 6.6-1 shows the distribution of earthquake epicenters in the Eastern and Southern African regions
for the period 627–1994 for earthquakes with a magnitude stronger than 4.0. This figure reveals that major
earthquakes have not occurred within a radius of around 200 km and only earthquakes with a mid-class
magnitude (<7.0) have occurred within the radius of 300 km.
Furthermore, Figure 6.6-2 shows the distribution of the expected peak horizontal ground acceleration due
to earthquakes, which have a 10% probability of occurring within the next 50 years in Mozambique. From
this figure, it is obvious that Maputo city is situated in an area with a low risk of earthquakes and a peak
horizontal ground acceleration of less than 0.2 g (200 gal).
6-60
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Maputo
Maputo
(Source: USGS)
Figure 6.6-2 Distribution of the expected peak horizontal ground acceleration (possibility of
10% within 50 years)
6-61
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
G.L≒NM+3.3m (=C.D+5.3m)
1.4m
Maximum tidal level
PMmax=C.D +3.9m
Mean high-water springs
PMav=C.D+3.5m
(Source: Prepared by JICA Study Team based on information obtained from INAHINA)
Figure 6.6-3 Relationship between tidal levels and ground level of the site
The maximum tidal level (PMmax) in the above is defined as “the maximum astronomical tide level that can
be observed in normal weather conditions” and it does not mean the highest recorded tidal level. According
to INAHINA, PMmax is usually observed in April.
Since the ground level is the elevation above MSL, the ground level of CTM has an allowance height of 1.4
meters above the maximum tidal level2. In general, a local decrease in surface air pressure over the ocean
produces an increase in the sea surface of 1 cm per hPa. If a perfect coincidence of PMmax and extreme low
pressure (i.e., brunt of a tropical storm) occurs, the expected rise in the sea surface is approximately 1.0
meters, which is still 0.4 meters lower than the ground level of CTM. Accordingly, it is not likely that CTM
will be affected by storm surges.3 Thus, it is not necessary to raise the ground level of the CTM site against
storm surges.
2
According to INAHINA, for planning and design of the facilities in port of Maputo, the planned ground plane
is set at PMmax+0.5 m.
3
According to INAHINA, the recorded maximum tidal level at Port Maputo is not more than C.D+5.0 m.
6-62
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
I(mm/h) = a x t (min)b
Where,
T: return period
I: rainfall intensity (mm/h)
a, b: constants (see the table below)
t: duration of rainfall (mm)
T (year) 2 5 10 20 25 50
a 534.0468 694.504 797.3841 896.5751 930.8815 1026.694
b -0.5075 -0.59383 -0.5869 -0.58197 -0.58119 -0.57749
(Source: Regulation of public systems for water supply and wastewater drainage (Decree 30/2003, 1. July;
DNA, 2003))
In the above formula, assuming a return period of 50 years and a rainfall duration of 1,440 minutes (i.e., 24
hours), the rainfall intensity is estimated at 13.6 mm for a period of 24 hours, which corresponds to the total
daily rainfall of 326 mm. It was found that this figure coincides with the recorded maximum daily rainfall
observed on February 6, 2000. Accordingly, the return period of 50 years shall be adopted for design of the
storm water drainage system of the Project.
6-63
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Source: EDM)
Figure 6.6-4 A photo showing installation of the existing oil tanks (in 1970s)
6-64
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Item Description
Design process and 1) The sectional design of the foundation is based on the allowable stress
evaluation method.
2) A vibration analysis is conducted to ensure that the natural frequency of
the foundation meets the requirements for vibrating machines (e.g., GTG,
STG, etc.)
Soil conditions Soil constants are estimated by using empirical formulas for cohesive soil
based on N-values obtained from the soil investigation.
Loading conditions The following loads are considered for design of foundations.
1) Machine load
2) Dead load (i.e., weight of concrete with a unit weight of 24 kN/m3)
3) Seismic load
Allowable bearing The allowable bearing capacity of cast-in-place pile is estimated by using the
capacity of pile following empirical formula.
- Long-term allowable bearing capacity: Ra = 1/3・Rp + 1/3・Rf
- Short-tem allowable bearing capacity: Ra = 2/3・Rp + 2/3・Rf
- Ultimate end bearing capacity: Rp = 150・N・Ap
- Ultimate skin friction resistance: Rf = 10/3・Ns・Ls・φ + 1/2 qu・Lc・φ
Where,
Ap: Effective sectional area at the tip of pile (m2)
N: Average N-value at the tip of pile
Ns: Average N-value of sandy soil
Ls: Contact length of pile with sandy soil (m)
Φ: Peripheral length of pile (m)
qu: Unconfined compression strength of cohesive soil (kN/m2), which is
estimated by using the empirical formula, qu=12.5 N (<200 kN/m2)4.
Lc: Contact length of pile with cohesive soil (m)
For design of the vibrating machines (gas turbines and a steam turbine), the cross-sectional area of the
foundation is determined based on the required dead weight of foundation against sympathetic vibration
with equipment, as determined in the vibration analysis. For instance, the thickness of the mat foundation
of a gas turbine is estimated at 2.0 meters, which is much bigger than the required foundation depth based
on the static stress analysis and results in minimum reinforcement.
Figure 6.7-5 shows an outline drawing for the foundation of a gas turbine. The structural calculation sheet
for the gas turbine foundation is contained in the Appendix of this report.
4
Guideline for Structural Design of Foundations, Yokohama City.
6-65
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-66
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Since the No.1 GT and No.2 GT buildings are located in a relatively lower area in CTM where rainwater
tends to gather, storm drains are provided in this area. However, periodical maintenance of storm drains is
seemingly not done and the opening of the storm drain nearest the No.1 GT building was completely
clogged with soil (see the right-hand photo in Figure 6.6-6). Furthermore, the drainage pipe (φ300 mm) is
not exposed at the end point but is apparently buried in the ground. Thus, it is obvious that storm water in
CTM is not properly discharged when heavy rain occurs.
6-67
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 6.6-6 A drainage channel parallel to railway (70 cm wide) and a storm drain in CTM
The floor level of GT buildings is set at almost the same level as the ground level of the surrounding area;
thus, it may contribute to flood damage in GT buildings. In fact, no flood damage occurred in the canteen,
which is situated close to GT
buildings but whose floor level is set at approximately 20 cm higher than the ground level of the
surrounding area.
In conclusion, a new storm water drainage system with sufficient capacity in accordance with the design
rainfall intensity (50-year return period) shall be established in CTM. In planning and design of the storm
water drainage system for CTM, the following basic design policy shall be considered:
The catchment area shall be divided into two by the existing road that runs in the east-west direction.
Open ditches shall be used as practicably as possible in order to facilitate easier maintenance of the
drainage system.
Inverted siphons shall be used to convey storm water across existing cable trenches. The diameter of
the inverted siphon pipes shall be at least 800 mm for easy maintenance.
An oil separator shall be provided at the end point of each drainage system.
6-68
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
6-69
Chapter 7
At present, Mozambique has two gas fields: one in the Rovuma Basin of Cabo Delgado province in
the north and the other in the Mozambique Basin of Inhambane province in the south. Their locations
are illustrated in Figure 7.1-1
In the Mozambique Basin, gas was first found in the Pande area in 1961, then in the Buzi area in 1962,
followed by the Temane area in 1967. After that, natural gas development has been sluggish since the
1970s due to the absence of demand and political instability in Mozambique. In 2003, gas was found
in the Inhassoro area, and natural gas development was promoted by the enactment of the Petroleum
Law (3/81) and establishment of the Mozambican National Hydrocarbon Company (“ENH”) since the
1990s. Since the mid-1990s, Production Sharing Agreements (“PSA”) and Engineering, Procurement
and Construction (contracts) (“EPC”) have been signed with international oil developers (Arco in
1997, BP in 1998, and Sasol, Petronas, Hydro and DNO in 2000 and onward). Thus, natural gas
development has been promoted, including the construction of gas pipelines going to South Africa by
Sasol.
In the Rovuma Basin, tenders for development licensing have been invited since 2005. As a result,
development and licensing agreements were signed with global developers such as Anadarko (U.S.A.),
ENI (Italy), Petronas (Malaysia) and Artumas (Canada). Since then, natural gas development has been
promoted.
In the Pande and Temane areas in the Mozambique Basin, natural gas sources have been developed
and natural gas has been produced under a Petroleum Production Agreement (“PPA”) between Sasol
Petroleum Temane and ENH.
In 2004, the first commercial production was initiated in the Temane area. In 2009, production started
in the Pande area.
(Source: ENH)
The following table lists the development and production areas with developers and producers in the
Rovuma Basin and Mozambique Basin.
According to available data, reserves of natural gas in Mozambique are 4.8 to 8.8 trillion cubic feet
(“TCF”) in the Mozambique Basin and 52.5 to 110 TCF in the Rovuma Basin. There are several
sources of data showing recoverable reserves, which lie in the range of 5.504 to about 10 TCF, 7% of
which have already been found. The area-wise recoverable reserves in the Mozambique Basin are
2.321 to 2.7 TCF in the Pande area, 0.618 to 1.0 TCF in the Temane area and 14 billion cubic feet
(“BCF”) in the Buzi area.
Current production volume in Mozambique is approximately 130 million gigajoules (“MGJ”) per
annum from the Pande and Temane areas of the Mozambique Basin. More than 95% of the gas
produced is sent through the 865 km-long pipeline to South Africa, and is consumed in a Sasol factory.
Approximately 3 MGJ is consumed in Mozambique per year (i.e., approximately 3 MGJ per annum in
the Matola area (by Mozal and others) and 0.3 MGJ each year in the Vilankulo and Inhassoro areas
close to a gas field (80% of which is for EDM power generation).
Figure 7.1-2 shows yearly gas production in Mozambique and Figure 7.1-3 shows investment in the
oil and gas sector.
7-2
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
900
800
700
Milhões dolares
600
500
400
300
200
100
0
2004 2005 2006 2007 2008 2009
Ano
In 2004, a gas pipeline leading from the Pande and Temane gas fields of Mozambique to Secunda of
South Africa (ROMPCO pipeline, where a 50% interest is owned by the Government of Mozambique
(ENH) and the Government of South Africa (iGas), and the remaining 50% interest by Sasol of South
Africa) was constructed and was put into commercial operation (refer to Figure 7.2-1). This pipeline
has a total length of 865 km with a diameter of 660 mm. The current gas feed capacity is
approximately 150 MGJ per annum, which can be increased to 240 MGJ per annum by installation of
additional compressor stations. The production volume in the Pande and Temane gas fields for fiscal
2011 (July 2010 to June 2011) was approximately 130 MGJ per annum. According to the MMR report
of January 2012, the production volume for 2012 is anticipated to reach the level of 149 MGJ per
annum. The pipeline from the Pande and Temane gas fields to Secunda is provided with five takeoff
7-3
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
points (also called tap-off points) in Mozambique; however, only the Ressano Garcia takeoff point of
Maputo province was working as of 2011, and in the current stage, a detailed usage plan of the
Chokwa takeoff point is being developed.
In 2006, construction of a pipeline was completed from the takeoff point of Ressano Garcia close to
the national boundary with South Africa to Matola city. This pipeline is currently in commercial
service. This pipeline is run by the Matola Gas Company (“MGC”), established as a joint venture
between ENH and private capital. The current gas demand in Matola city comes mainly from the
Mozal aluminum smelter plant and Ciementos de Mozambique (cement plant), and amounts to
approximately 3 MGJ per annum. This demand is expected to grow due to a firm increase in the future
demand for switching from petroleum over to gas in the Industrial Park in the suburbs of Maputo city
(Vidreira (glass industry) and CDM (beverage manufacturer)), and due to the gas demand for
household (residential) use and for power generation.
(Source: ENH)
Extension work of the central processing facility (“CPF”) at the Pande and Temane gas fields has
already been completed in 2012 and the gas supply volume of the ROMPCO gas pipeline has also
been increased from 120 MGJ/year to 183 MGJ/year.
The maximum gas supply volume of the ROMPCO gas pipeline is 240 MGJ/year. The pipeline still
has a surplus capacity of 57 MGJ/year since the expansion work was completed. However, further
expansion work is not planned.
Gas Sales Agreement One (“GSA 1”)
1) 120 MGJ per annum (for South Africa)
7-4
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
The gas volume for domestic power generation described in 3) above is broken down into: (1) 6 MGJ
per annum for power generation for EDM and other consumers (residential, commercial, industrial)
and NGV, (2) 11 MGJ per annum for power generation for an IPP at Ressano Garcia (by
Gigawatt-Mozambique), and (3) 10 MGJ per annum for another IPP at Ressano Garcia (by Sasol New
Energy and EDM). At present, there are ongoing negotiations between ENH and EDM on the
agreement for the supply of the above-mentioned 6 MGJ per annum.
Gas is branched off at the Pressure Reducing Station (“PRS 1”) at Ressano Garcia, where the gas
pressure is reduced from 100 to 40 bars, and is fed to the Pressure Reducing Station (“PRS 2”) located
in Matola city, where the pressure is further reduced to 10 bar. After that, gas is supplied to users in
Matola city. Figure 7.2-2 illustrates the existing pipeline route.
(Source: ENH)
The following are the basic specifications of the pipeline from Ressano Garcia to the PRS 2.
1) Pipe diameter: 8" (200 mm)
2) Total length: Approx. 68 km
3) Gas feed capacity: 40,000 m3/h at 25C, 1 atm (currently in operation at 12,000 m3/h)
4) Maximum allowable gas pressure: 70 bar (currently in operation at 40 bar)
At present, 10-bar gas is supplied from the PRS 2 of Matola city to gas users through a 22 km-long
piping network. Most (92%) of the gas supplied is consumed by the Mozal aluminum smelter plant
and Ciementos de Mozambique (cement plant). Figure 7.2-3 illustrates the existing gas pipeline
network in Matola city.
It has been decided that ENH and KOGAS will jointly implement the natural gas pipeline project in
the Matola area. The preparation work for the project has already started (see Figure 7.2-4). Gas
pipeline work will begin from March 2013 and will be completed by January 2014. Since EDM has
confirmed that this project includes pipeline work to CTM site, it is not necessary to include the
pipeline work to the new Maputo power plant in the Japanese ODA project. In this case, gas pressure
in the MGC pipeline upstream will be decreased from 40 to 25 bars to meet the increase in gas
demand by laying new pipeline. Figure 7.2-4 illustrates the new pipeline route (from the branch point
situated 1.8 km upstream of the existing PRS-2 to CTM site) and Figure 7.2-5 illustrates the gas
pipeline route near the CTM site and the location of a new pressure reducing station in CTM site.
7-6
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Source: EDM)
Branch point
CTM
(Source: ENH)
7-7
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Source: ENH)
7.2.4 Gas Supply Volume to the Gas-fired Thermal Power Plant in the Southern Region
Gas for the new gas pipeline mentioned above is planned to supply gas to the power plants owned by
EDM and customers in Maputo city. It is expected that the available gas volume would be 6.0
MGJ/year (2.8MGJ/y for CTM and 3.2MGJ/y for Beluluane) However, it is confirmed that gas of 5.8
MGJ/y will be supplied to EDM in contract agreement. Figure 7.2-7 shows the overall gas flow
schematic in the Southern region. The broken line indicates the pipeline to be installed in the future.
The values enclosed in parentheses indicate the future gas volumes.
7-8
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Pande Inhassoro
2.321 Tcf
ROMPCO
100 bar Temane
865 km/660φ 0.618 Tcf
Capacity
164 MGJ/y ~ Current production
240 MGJ/y 183 MGJ/y 0.25 ~ EDM 80%
0.3 MGJ/y Elgas 16%
Domestic 4%
Funhalouro
① + ② = 6 MGJ/y
Vidreira
CDM
②
Chokue Residential
(Macarretane)
EDM NG Vehicles
①
CTM new gas fired CC
11.2km PRS
250φ
Magude IPP (*1) 25 bar PRS
11 MGJ/y MOZAL
Capacity
Secunda 147 MGJ/y Sasol's petrochemical factories
(South Africa)
7-9
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
Figure 7.2-8 shows the organization structure for gas production and pipeline operations of
Pande-Temane Gas Fields.
ENH
iGas
ROMPCO
Figure 7.2-8 Organization Structure for Gas Production and Pipeline Operations of
Pande-Temane Gas Fields
EDM is now negotiating with Maputo Gas Company (“MGC”) about a gas supply agreement and with
ENH about a gas transportation agreement. It seems that both contracts will be made by March 2013.
Gas price is assumed to be 5.6 USD/MGJ for CTM and 5.2 USD/MGJ for Beluluane. The difference
of gas prices between CTM and Beluluane is the length of the gas pipeline.
7-10
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
(Source: EDM)
7.4 Relationship of Relevant Organization related to Gas Supply and Transport Agreements
Figure 7.4-1 shows the relationship of the relevant organizations related to the gas supply and
transport agreements.
7-11
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
EDM
Operation Agreement
MGC ENH-KOGAS, SA
Project Owner
ENH
EPC (contractor)
Contractor
Kogas Mozambique (SPC)
SPT ROMPCO
E: Engineering P: Procurement C: Construction
Byudsan Daejoo ENT cop Sub-Contractor
Engineering
Gas Supply Agreement Gas Transport Agreement
Note:
ENH-KOGAS, SA (new company 30% ENH + 70% KOGAS from Korea): It will transport 5.8 MGJ/y of gas from Matola to Maputo & Marracuene via CTM and will tap the existing MGC pipeline in Matola
Empresa National de Hidrocarbonetos, EP (ENH) – Public company and arm of the government in the petroleum sector which has the allocation of 6 MGJ/y for EDM Power Generation at CTM and for Maputo and Marracuene
Korea Gas Corporation (“KOGAS”) – One of the world’s largest LNG importers, executing with ENH a new project for the construction of a gas pipeline and operating facility to supply gas to Maputo and Marracuene using the build-operate-transfer (“BOT”)
method
Kogas Mozambique: New Mozambican company and KOGAS have majority equity and acting as an EPC company for the construction of the new ENH-KOGAS, SA pipeline from Matola to Maputo and Marracuene
Matola Gas Company, SA (“MGC”): . Private company, has the pipeline from Ressano Garcia to Matola, and provides around 3 MGJ/y to the industrial area at Beluluane and Matola area and will supply 5.8 MGJ/y to EDM
Sasol Petroleum Temane Limitada (“SPT”): Responsible for production activities from the Pande and Temane field reservoirs
Rompco: Has the pipeline property from Temane to Secunda in South Africa and provides five take-off points in Mozambique and only Ressano Garcia Take-off point working at the moment
(Source:EDM)
7-12
Preparatory Study on Gas-Fired Power Plant Development in Southern Mozambique Final Report
As mentioned in the previous item, the gas pipeline works and pressure reducing stations (“PRSs”) are
the scope of supply of ENH/KOGAS. The tie-in point at PRS in CTM between EDM and
ENH/KOGAS is an outlet valve of PRS in CTM.
Currently, the gas pressure at PRS of CTM is approximately 25 bar. In this case, it is not necessary to
treat gas for GT through PRS because the required gas pressure at the GT nozzle inlet is 40 bar for
LM6000 and 26 bar for H25, respectively. After PRS, a gas compressor should be installed to boost
gas to the required gas pressure. In the meantime, if gas will be tapped before PRS2 and gas with more
than 60 bar gas pressure is obtained, it is not necessary to install a gas compressor after PRS in order
to reduce gas pressure.
7-13