Casas Con Vistas Final

The document outlines the bill of materials and cost estimates for the construction of a comfort room in Brgy. Pangubatan, Kaputian District, IGACOS. It details various construction works including excavation, reinforced concrete, masonry, roofing, tinsmithry, formworks, painting, septic vault, and plumbing, along with associated material and labor costs. The total costs for each section are provided, contributing to the overall project budget.

Uploaded by

Hansel Bumagat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views3 pages

Casas Con Vistas Final

The document outlines the bill of materials and cost estimates for the construction of a comfort room in Brgy. Pangubatan, Kaputian District, IGACOS. It details various construction works including excavation, reinforced concrete, masonry, roofing, tinsmithry, formworks, painting, septic vault, and plumbing, along with associated material and labor costs. The total costs for each section are provided, contributing to the overall project budget.

Uploaded by

Hansel Bumagat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Project Title: CONSTRUCTION OF COMFORT ROOM

Location: Brgy. Pangubatan, Kaputian District, IGACOS


Owner:

BILL OF MATERIALS AND COST ESTIMATES

I. Hardearth Excavation Q= 16.08 cu.m.


Labor:
1 Construction Foreman for 10 days @ 650.00 /day P 6,500.00
6 helpers / laborers for 10 days @ 450.00 /day P 27,000.00
Labor Cost P 33,500.00

ITEM COST P 33,500.00


II. Reinforced Concrete Works Q= 9.82 cu.m
Materials:
89 bags Portland Cement @ 286.00 /bag P 25,454.00
15 cu.m Washed Gravel @ 1,500.00 /cu.m P 22,500.00
7 cu.m Washed Coarsed Sand @ 1,500.00 /cu.m P 10,500.00
26 length 10mm Dia. X 6m Deformed Bar @ 210.00 /length P 5,460.00
34 length 16mm Dia. X 6m Deformed Bar @ 560.00 /length P 19,040.00
1 roll #16 G.I Tie Wire @ 1,500.00 /roll P 1,500.00
Material Cost P 84,454.00
Labor:
1 Construction Foreman for 16 days @ 650.00 /day P 10,400.00
1 Mason for 16 days @ 550.00 /day P 8,800.00
1 Steelman for 16 days @ 550.00 /day P 8,800.00
3 helpers / laborers for 16 days @ 450.00 /day P 21,600.00
Labor Cost P 49,600.00

ITEM COST P 134,054.00

III. Masonry Works Q= 105.6 sq.m


Materials:
1670.00 pcs CHB - 4" @ 21.00 /pc P 35,070.00
146.00 bags Portland Cement @ 286.00 /bag P 41,756.00
14.00 cu.m Washed Coarsed Sand @ 1,500.00 /cu.m P 21,000.00
93 length 10mm Dia. X 6m Deformed Bar @ 210.00 /length P 19,530.00
2 meters sand screen @ 165.00 /meter P 330.00
7 cu.m 100cm-120cm diameter Limestone @ 1,500.00 /cu.m P 10,500.00
Material Cost P 128,186.00
Labor:
1 Construction Foreman for 14 days @ 650.00 /day P 9,100.00
2 Mason for 14 days @ 550.00 /day P 15,400.00
5 helpers / laborers for 14 days @ 450.00 /day P 31,500.00
Labor Cost P 56,000.00

ITEM COST P 184,186.00

IV. Roof Framing Works Q= 1 lot


Materials:
120 bdft 2"x6"x10' Good Lumber @ 60.00 /bdft P 7,200.00
300 bdft 2"x3"x10' Good Lumber @ 60.00 /bdft P 18,000.00
34 bdft 4"x10"x10' Good Lumber @ 60.00 /bdft P 2,040.00
10 kgs 4" CW Nails @ 95.00 /kg P 950.00
Material Cost P 28,190.00
Labor:
1 Construction Foreman for 7 days @ 650.00 /day P 4,550.00
1 fin carpenter for 7 days @ 550.00 /day P 3,850.00
2 helpers / laborers for 7 days @ 450.00 /day P 6,300.00
Labor Cost P 14,700.00

ITEM COST P 42,890.00


V. Tinsmithry Works Q= 30 ln.m.
Materials:
30 ln.m. 0.40 mm thk. Rip Type Roof @ 450.00 /ln.m. P 13,500.00
500 Bundle Thatched roof @ 18.00 /bundle P 9,000.00
1050 pcs 2" Tekscrew @ 3.00 /pc P 3,150.00
Material Cost P 25,650.00

Page 1
Labor:
1 Construction Foreman for 7 days @ 650.00 /day P 4,550.00
1 fin carpenter for 7 days @ 550.00 /day P 3,850.00
2 helpers / laborers for 7 days @ 450.00 /day P 6,300.00
Labor Cost P 14,700.00

ITEM COST P 40,350.00

VI. Formworks and Scaffoldings Q= 1 lot


Materials:
10 sheets 1/2" Ordinary Plywood @ 700.00 /sheet P 7,000.00
336 bd.ft assorted cocolumber @ 32.00 /bd.ft P 10,752.00
1 roll Nylon Rope @ 120.00 /roll P 120.00
10 kgs 4" CW Nails @ 67.85 /kg P 678.50
7 kgs 3" CW Nails @ 65.00 /kg P 455.00
7 kgs 2 1/2" CW Nails @ 73.00 /kg P 511.00
7 kgs 1 1/2" CW Nails @ 83.65 /kg P 585.55
Material Cost P 20,102.05
Labor:
1 Construction Foreman for 6 days @ 650.00 /day P 3,900.00
2 Carpenter for 6 days @ 550.00 /day P 6,600.00
1 helpers / laborers for 6 days @ 450.00 /day P 2,700.00
Labor Cost P 13,200.00

ITEM COST P 33,302.05

VII. Painting Q= 105.6 sq.m


Materials:
6 gals Acrytex Primer (Boysen) @ 1,551.35 /gals P 9,308.10
2 gals Acrytex Reducer @ 751.20 /gals P 1,502.40
2 gals Acrytex Cast (Boysen) @ 668.10 /gals P 1,336.20
6 gals Latex Semi - Gloss , (Boysen) Verify Color @ 712.00 /gals P 4,272.00
6 gals Matte Shield - Boysen @ 1,056.25 /gals P 6,337.50
2 gals QDE Boysen - Verify Color @ 1,062.50 /gals P 2,125.00
1 gals Epoxy Marine , non-sag A B @ 2,011.05 /gals P 2,011.05
4 gal Wood Primer @ 1,088.75 /gals P 4,355.00
10 pcs Sand Paper, 120 @ 27.06 /pc P 270.60
2 pcs Paint Brush 3" @ 88.56 /pc P 177.12
2 pcs Paint Brush 2" @ 64.88 /pc P 129.76
4 pcs Paint Brush 4" @ 191.57 /pc P 766.28
6 pairs Spatula (Paleta) @ 91.02 /pair P 546.12
Material Cost P 33,137.13
Labor:
1 Construction Foreman for 8 days @ 529.00 /day P 4,232.00
2 Skilled Painter for 8 days @ 479.00 /day P 7,664.00
2 helpers / laborers for 8 days @ 396.00 /day P 6,336.00
Labor Cost P 18,232.00

ITEM COST P 51,369.13

VIII. Septic Vault Q= 4.025 cu.m


Materials:
38 bags Portland Cement @ 286.00 /bag P 10,868.00
3 cu.m Washed Coarsed Sand @ 1,500.00 /cu.m P 4,500.00
5 cu.m Washed Gravel @ 1,500.00 /cu.m P 7,500.00
47 lengths 10mm Dia. X 6m Deformed Bar @ 210.00 /length P 9,870.00
20 bags water proofing compound, sahara @ 75.00 /bag P 1,500.00
1 length 4"Ø x 3m PVC Pipe S-1000 @ 900.00 /length P 900.00
1 length 6"Ø x 3m PVC Pipe S-1000 @ 1,936.02 /length P 1,936.02
3 pcs 4"Ø PVC Clean Out @ 73.00 /pc P 219.00
1 pc 6"Ø PVC Clean Out @ 184.50 /pc P 184.50
3 pcs 4"Ø PVC Tee @ 206.64 /pc P 619.92
1 pc 6"Ø PVC Tee @ 307.50 /pc P 307.50
1 can 400cc PVC Solvent Cement @ 320.00 /can P 320.00
Material Cost P 38,724.94
Labor:
1 Construction Foreman for 7 days @ 650.00 /day P 4,550.00
1 Skilled mason for 7 days @ 650.00 /day P 4,550.00
2 helpers / laborers for 7 days @ 450.00 /day P 6,300.00
Labor Cost P 15,400.00

ITEM COST P 54,124.94

Page 2
IX. Plumbing and Fixture Q= 1 lot
Materials:
2 units Water Closet ( American Std.) @ 15,597.70 /unit P 31,195.40
2 units Lavatory ( Wall Mounted Type) w/ comp. accessories @ 3,051.65 /unit P 6,103.30
2 pcs 4" Floor Drain @ 110.70 /pc P 221.40
2 pcs Stainless Steel Faucet (for wall mounted) @ 1,046.73 /pc P 2,093.46
1 unit Urinal . @ 9,373.85 /unit P 9,373.85
12 lengths 4"Ø x 3m (s-1000) PVC Pipe @ 900.00 /length P 10,800.00
3 lengths 2"Ø x 3m (s-1000) PVC Pipe @ 265.00 /length P 795.00
8 pcs 4"Ø PVC Sanitary Wye @ 143.00 /pc P 1,144.00
3 pcs 4"Ø x 2"Ø PVC Reducing Wye @ 154.00 /pc P 462.00
3 pcs 4"Ø PVC Elbow (45°) @ 55.00 /pc P 165.00
3 pcs 4"Ø PVC Clean Out @ 73.00 /pc P 219.00
3 cans 400cc PVC Solvent Cement @ 320.00 /can P 960.00
15 lengths 25mmØ x 4m PPR Pipe PN 20 @ 693.75 /length P 10,406.25
8 pcs 25mmØ PPR Tee @ 50.00 /pc P 400.00
8 pcs 25mmØ PPR Elbow 90° @ 45.00 /pc P 360.00
15 pcs 25mmØ PPR coupling @ 28.29 /pc P 424.35
2 pcs 25mmØ Gate Valve @ 639.60 /pc P 1,279.20
10 pcs Teflon Tape, 1" @ 60.00 /pc P 600.00
Material Cost P 77,002.21
Labor:
1 Construction Foreman for 10 days @ 650.00 /day P 6,500.00
2 Plumber for 10 days @ 650.00 /day P 13,000.00
2 helpers / laborers for 10 days @ 450.00 /day P 9,000.00
Labor Cost P 28,500.00

ITEM COST P 105,502.21

X. Temfacil for Kitchen Q= 1 LOT ITEM COST P 50,000.00

XI. Temfacil for worker & Construction materials Q= 1 LOT ITEM COST P 35,000.00

XII. Doors Q= 4 LOT ITEM COST P 40,000.00

XIII. Contengencies ITEM COST P 120,641.75

XIV. Construction Profit ITEM COST P 80,427.83

GRANDTOTAL P 1,005,347.91