INTERVIEW QUESTIONS
1. Purpose of batteries and auxiliary txf in a s/s.
                 Batteries are used as emergency back-up supply when the s/s loses ac
                 Batteries are used for supplying the protection relays, communication
                    panels, tap changer panel
                 Charging coils after operation
                 Supplying power for alarms and annunciations
                 Auxiliary txf is used for s/s lighting, ac supply for general s/s works i.e.
                    welding, filter plant
                 Battery charging
                 Txf controls i.e. fan and motor operation, tap changing
  2. Maintenance you carry on batteries.
                 First aerate i.e. open all windows and doors and do not use a naked flame
                 Always wear correct protective clothing i.e. acid proof work suit
                 Test terminal voltage with charger on and record
                 Remove/ isolate battery bank, wait for 5 minutes and test terminal voltage
                    and record
                 Test individual cells and record
                 Inspect individual cells for damage and remove sulphation formed on
                    battery terminals, clean the terminals and apply Vaseline on the terminals
                 Check electrolyte level and first check using a hygrometer for the
                    determination of whether level of acidity is low or high, if low add acid
                    and if high add distilled water
                 General battery room housekeeping
                 Measure the terminal voltage from battery charger
                 Measure the now voltage of the battery bank and individual cells after
                    maintenance before connecting to the charger and record
                 Switch on the charger.
  3. Line protection of a 33kv line.
                 SEF (Sensitive Earth fault) or known as common bar protection which
                    protects line when a high resistance fault occurs i.e. live conductor falls on
                    rocky area and the breaker fails to trip or does not sense this as a fault
                    condition.
                 EF (Earth Faults) when a live conductor comes into contact with earth
                    wire or falls to ground or when a tree falls on the line
                 O/C (Overcurrent) when a phase to phase fault occurs and an overcurrent
                    condition arises and hence large fault currents flows back to the source
                 ASC (Arc Suppression Coil) back up protection which is protection when
                    a fdr CB fails to trip and hence an inductance is introduced in form of a
                                               1
                 coil which then counters the capacitive fault current and thereby trips the
                 whole s/s.
4. What do you do on commissioning a 10MVA txf?
              Commissioning is all the checks and tests carried out on plant and
                 equipment before being put to service for the first time.
              Checks
                 (a) Equipment spec and data ratings, operating voltages and frequency,
                     mode of operation must conform to requirements and suit the intended
                     function
                 (b) Electrical connection integrity
                 (c) Good workmanship i.e. work must be neat
                 (d) Wiring checks must be carried out to prevent maloperation of
                     equipment
              CT tests; current ratio, IR, magnetization curve and polarity tests done
              VT tests; IR, voltage ratio and polarity
              Power txf tests; TTR, IR, winding resistance, diverter continuity, ancillary
                 instruments (oil and winding, main tank, buccholz gas and surge, main
                 tank overpressure), manual and automatic cooler control, neutral earth
                 resistance
              Txf oil tests; dielectric, crackle and acidity
              Tests on cb and isolator; ducter tests, IR, timing tests and interlocking
              Dc supplies; on battery charger, test the charging modes output and
                 alarms. On battery bank cells test voltage, specific gravity, acidity, and
                 external resistance
              Relay tests; protection relays and voltage regulating relay tests
              Stability tests; on unit protection schemes like differential and REF
              Measurands; txf tap position indication, local, remote and supervisory,
                 alarms and indications, controls of CB’s and isolators local and remote
                 and supervisory must also be tested and confirmed
              Test LV and HV CB intertrip tests.
              On load tests are carried out after energization and loading of the txf
              Commissioning follow up must be done if applicable
              Commissioning schematics must be submitted to the drawing office for
                 production of the built schematic
5. How can an artisan be a cost to an organization?
              Incompetence, recklessness, abuse of company property which then
                 dilutes company profits
              Arriving at fault sites late prolonging off time
              Accepting bribes on disconnections
             
6. When an individual is involved in an accident, how does it cost the company?
                                           2
          The revenue lost in down time, investigating and then restoring i.e. buying new
           plant and machinery to replace the burnt one
        Revenue lost in compensation, court hearings and fines
7. How does late fault attendance cost the company?
                Loss of revenue when customers are off for a long time
                Loss of customers who opt to use other alternatives for power
                Loss of customer confidence hence loss of future revenue
8. How do you deal with hostile workers?
                Stern reprimand
                If fails workers’ committee for amicable solution
                Approach Foreperson
                Report to manager and call for a hearing
9. Txf protection on a 200KVA txf
                Arcing horn gap protection
                Surge arrestors
                Lv mcb
                Fuse links
10. Procedure when you are changing an oil cb and putting on as sf6.
               
11. Why choose an sf6 cb over an oil?
                SF6 gas is colorless, odorless, non-toxic and does not pollute the
                   environment.
                SF6 does not support combustion as compared to oil which after a number
                   of operation it loses its insulating properties
                Oil cb’s are being phased out as they are bulky and dirty to maintain
12. Procedure when working on high voltage equipment.
                Rule 14 of the safety rules book that no work is done on high voltage plant
                   and equipment unless the equipment has been made
                Dead – steps taken to de-energize the plant and equipment to be worked
                   on i.e. open of cb’s
                Isolated – opening of isolators, hot line taps, links, and locked off from all
                   points of supply which can make equipment live i.e. from all auxiliary
                   supplies
                Earthed – application of approved earth sets to safely discharge at all
                   times
                Screened- use of barricades and screens to minimize accidents
                Released – released for work with the appropriate safety documents
13. History of yourself concerning the job.
                So far underwent apprenticeship training for 4 years and was working
                   under the tutelage of experienced artisans, technicians and foreperson and
                   has gained substantial knowledge in the field raring to apply myself on the
                   job
                                             3
14. Why do you think you are the best candidate?
                 Because I am the best, I have never played second fiddle in what I do
                    professionally with my colleagues and they know it too, however what
                    makes me the ideal candidate besides my superior knowledge is that I can
                    recognize contributions from those around further improving me as a team
                    player as well as my output.
15. Txf protection.
16. How do you treat contractors?
                 Contractors contracted to do works on ZESA plant and equipment are
                    governed by the Safety Rules book (grey) of 1998, to which I will first
                    explain the procedures for work i.e. the relevant qualifications have been
                    met and the age of the working party as well as check if they have proper
                    T&E
                 Explanation of what is required of the contractor in line with the works
                    whether he/she knows the nature of work
17. Grievance handling procedure.
18. How do you treat materials booked from stores that were not used or no longer needed?
19. Depot of your choice.
20. Can overtime be minimized.
21. How do you reduce outages to customers?
22. Code of conduct, some values of the company, mission statement, grievance handling
    procedure.
            (a) Mission statement--- to bring convenience to our valued customers through
                the provision of adequate safe, reliable electricity and related services at
                competitive prices
            (b) Core values---Teamwork, Safety, Efficiency, Commitment, Corporate
                governance, Entrepreneurship
23. Safety documents used in ZESA, accident reporting procedure.
24. What is meant by floating neutral
25. What do you understand by cost cutting?
26. Difference between overcurrent and overload
27. Purpose of health and safety meetings
28. Types of maintenance; statutory, routine, fault, planned and preventative maintenance
29. Zimasset
30. Procedure of a new connection
31. What is switching
32. Prepayment meter fault finding
33. IRBM – Integrated Results Based Management systems
34. Fire-drill
35. Significance of autorecloser in our system
36. Identify yourself- qualifications etc.
37. Duties and responsibilities of an artisan
                 Carry out fault meter change and meter change program
                                            4
                   Pulling up to 2 spans of LV and HV lines
                   Doing cable jointing on HV and LV reticulation
                   Carry out maintenance on authority’s system in accordance with laid down
                    procedure
                Replacing faulty ACB, MCB and load limiters
                Receiving faults from controllers, updating them on the nature of faults
                    and job completion times
                Issuing working documents for personnel working on the authority’s
                    equipment for voltages up to and including 33kv in accordance with safety
                    regulations
                Carry out switching up to 33kv
                Carry out s/s and equipment inspections
                Knowledge of operational procedures and safety regulations
38. Cost cutting -----i) overtime (planning and maintenance)
                      ii) telephone charges (use of emails)
                       iii) fuel (use shorter routes)
                       iv) safe keeping of T&E
39. Demand side management – how do you save power for customers and ZESA
40. S/S construction 1MVA – main and b/up protection…NEF, WR, OT, BEF,
    Differential protection
41. How do you motivate workers – delegate duties to artisan assistants, carrying job
    appraisals, teamwork promotes unity thereby motivating one another
42. Ways of revenue protection.
43. As an electrician at ZESA how can you make sure the public is protected from the
    dangers of electricity
44. Procedure when changing a pg clamp on a 33kv line
45. What kind of protection do you expect to find on a 5MVA txf?
         NEF
         LV BEF
         WT, OTT
         OLT
         Buchholz
46. Procedure for NPS
         Customer applies using an E22 form
         Site visit by cso
         Customer fills a notification of commencement of wiring form E62 this form
           includes the particulars of installation i.e. new installation, supply required,
           number of circuits
         Customer fills a notice to authority upon completion of wiring form E38 this form
           requires the details of the contractor who wired the installation and the number of
           circuits
                                            5
           Inspection is done by the authority and an E1 is filled
           A customer profile is then created using 3e and a quotation is then prepared and a
            pjob number is generated which Is the reference number for the customer profile
            used throughout, for a standard customer gets an email or has one printed after 14
            days but if non-standard it has to go for costing and an ACE is done using NDM
         Customer pays the quotation fee or rather the connection fee
         CSMS (Customer Supplied Meter Scheme) the customer uses pjob number to
            purchase meter and comes with the receipt
         Meter goes to stores
         SCSO assigns job to an electrician and he uses a WEO (Work Execution Order)
            with details of job, and materials to be ordered at stores
         Connection is done and a WOMI, Meter card, LOA, pre-task risk assessment
            form, alongside the WEO is handed back to foreperson
         Foreperson in tandem with commercial officer commissions the job in the system
            for customer to register and start purchasing power
47. Tell us about ICS, DCS and NDM
48. Inspections done on an NPS
         Earthing i.e. all extraneous conductive parts, door, sinks, tapes
         Correct size of wiring cables used
         Correct size of circuit breakers
         Proper conduit bends, saddling, circuit tags, according to set standards
         Connection integrity
         Proper earth termination i.e. spikes
49. Inspections done on a prepaid meter
         Cover intact
         Condition of connections whether bypassed or not, or tightness
         Condition of ciu, inclusive of lcd, buttons etc.
         Terminal seal still intact
50. Advantages of prepaid over conventional
         Enhanced revenue collection
         Meter is user friendly
         Gives power to customers to control their consumption
         Technological advancement from conventional
         Intelligent i.e. able to detect and protect customers from very high and very low
            voltages, loose connections i.e. floating neutrals
         Able to detect temper
         Light
         Easy to diagnose a fault
         Effective cost cutting tool i.e. reduce running cost of meter reading and billing
         Ease of doing business as no need to bill customers
         Control power consumption of customers through the use of tariffs
                                            6
        Save customers from unexpected high bill and
51. Why should ZESA have metering
        Billing
        Come up with maintenance programs for plant and equipment
        Capture what we generate and distribute
        Help us note losses
        Determine upgrades and downgrades of plant and equipment
52. Acts of misconduct
53. Pmt construction and maintenance
54. Line construction and maintenance
55. Cable sizes
       
56. Importance of NEC (National Employment Council)
57. Purpose of a breather on a txf
        Release gasses e.g. Sulphur, hydrogen produced in the txf to the atmosphere
        Allow fresh moisture free air to circulate within the txf
58. Importance of OSHE committee
       
59. Types of tests done on txf oil
        Acidity
        Crackle
        Dielectric test
        Dissolved gas
60. Types of faults
        Transient- fault clears on its own i.e. switching surges, tree branch falling on line
           and clearing
        Permanent – fault fails to clear on its own
        Symmetrical- fault occurs on all phases or is similar on all 3 phases e.g. 3 phase
           o/c and e/f
        Asymmetrical- fault occurs on 2 or one phase but not all 3
61. Pmt inspection
        Check oil leaks
        Condition of mcb
        Meter condition, condition of lt mains
        General s/s condition, including paintwork, undergrowth,
        Lightning arrestor condition
62. Uses of txf oil
        Insulating medium
        Coolant
        Breather
        Checking condition of txf winding
                                             7
          Temperature control in conjunction with CT, mercury switches and alcohol filled
           capillaries
63. Cable fault location
        T&E required acoustic reflectometer, thumper (surge generator), ac generator,
           extension cable, cable pre-locator, HT leads….
        Procedure
           Nb know the rating of the equipment before testing i.e. the voltage, current, age,
           length before injecting any current or pushing a voltage for the purpose of
           testing and make sure earths are removed and everyone is clear from any plant
           or equipment live or being tested…
        Step 1
           Assess test equipment and test apparatus i.e. checking the condition and
           connection integrity
        Step 2
           Do an IR (insulation Resistance), this is done to check the faulted phase(s).
          Step 3
           Use a fault pre-locator to check nature of fault whether it is an open or a short
           circuit, the graph on the monitor will spike upwards for a short circuit and dip for
           an open circuit, this also gives us a rough estimate of the position of the fault
          Step 4
           Using a hi-pot thumper or a surge generator inject a surge impulse usually an
           0.5seconds on the cable to the voltage level required or is applicable to the rating
           and age of cable to avoid damaging it
          Step 5
           With the surge generator still injecting a pulsating dc voltage, armed with an
           acoustic cable reflectometer (listening set), using the monitor to follow the cable
           which shows a pulsating magnetic field as this field is due to the field created by
           the surge generator pulse and a corresponding arrow pointing in the direction of
           the fault, then trace the cable up to a point where there is a thumping or knocking
           sound as well as the arrow changes direction instantly and put a marker on that
           point that is when the fault is located.
64. Procedure when working on an hv cable
        After isolation and earthing and fault has been located
        Issue LOA for exposing cable i.e. digging cable bay
        Cancel LOA and test for dead i.e. spike the cable if they are many at the point of
          fault, or use a frequency generator set to detect the cable with a preset frequency
          higher than the system 50Hz
                                             8
          Issue PTW for cut and open the cable for pressure test
          Cancel PTW and issue an SFT for pressure testing both ends as well as dead
           phasing in
        Cancel SFT and issue PTW for joining the cable
        Cancel PTW and issue an SFT for pressure testing after joining
        Cancel SFT
        Get instructions to energize the cable
        Get instructions to do live phasing in
65. Operation of an AR in conjunction with a sectionaliser
        AR is an intelligent breaker able to sense and operate i.e. whenever a fault occurs
           on the line, it can be a transient (tree falls on line and clears), overcurrent,
           earthfault and SEF. A sectionaliser however is a switch which cannot operate on
           its own and can only operate in the dead time of the AR. So an AR is put on the
           line and in front of it a sectionaliser and for proper coordination of operation the
           sectionaliser must be set at (n-1) counts of the AR, so if a fault occurs on the line
           the sectionaliser senses but does not operate, the AR upstream senses the fault and
           operates i.e. opens the contacts it is at this point that the sectionaliser opens its
           contacts. When the AR recloses it energises the line the line voltage closes the
           coil which closes and makes the contacts, if fault is still there it will repeat the
           process until the sectionaliser has reached maximum set counts and locks out
66. Types of tariffs
        Domestic
        Commercial
        Street lighting
        Mining
        Agriculture
        Clinic and hospital
67. Types of leaves
        Occasional leave- 12 days per year, 3 max per month
        Vacational leave – 30 days per year
        Study leave – 12 days
        Special leave – 12 days
        Maternity leave – 90 days before and after giving birth
        Compassionate leave – 12 days
68. Acts of parliament which govern works conducted by ZESA
                    1. Electricity Act-----Relations between interconnected system, reporting
                       of accidents, controller in charge of loading, wayleave clearance,
                       safety clearances over road and rail.
                    2. Zimbabwe Labor Relations Act---Protection of employee rights to fair
                       labor standards, general offences and penalties
                    3. Factories and works act---machinery, and accidents. Inspection of
                       machinery, accident register and notification of accidents
                                             9
4. NSSA--- worker’s compensation act, worker’s health and safety act
5. SI 177 of 2018
                       10