10 1109@TPWRD 2020 3016717
10 1109@TPWRD 2020 3016717
fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 1
Abstract—The aim of this paper is to present a novel phasor However, many cable sections such as cables connecting
measurement unit (PMU) data-based cable temperature moni- off-shore wind park to land substation or cables connecting so-
toring method with an intended application towards facilitating lar and wind parks to the grid transport intermittent renewable
dynamic line rating. First part of the paper presents the method
to estimate and track the temperature of a 3-phase cable segment. power. Many urban load centers have time-dependent peaks.
The benefit of this temperature monitoring method is that no In such cases, if steady-state current rating is applied then due
additional temperature measurement sensors are required to to the thermal inertia of the cable system, the cable may never
be placed along the cable. The method is based on a novel approach its thermal limits. This results in under-utilization of
algorithm which gives accurate resistance estimates for 3-phase the loading capacity of the cables. To utilize the cables more
cable segments even in the presence of random and bias errors
in the grid measurements. The performance of the method is optimally, dynamic loading models are required.
demonstrated by utilizing data from PMUs in a distribution Increasing the loadability of the cables to maximize the
grid. The results from the grid data show that the method is accommodation of the intermittent peaks of power flows would
capable of monitoring the cable temperature up to an accuracy help acquire more clean energy and deliver more power to
of ±5◦ C. The later part of the paper presents a system to utilize load centers using the existing cable infrastructure. Time based
the temperature estimates given by the monitoring method to
predict the dynamic thermal state of the cable for forecasted flexibility in loading limits of power lines, also known as
power-flow scenarios. This is demonstrated by using the available dynamic line rating (DLR) has been a topic of interest in
temperature estimates to initialize and solve the system of the recent past. Authors in [2] presented a case where DLR
equations given by the thermoelectric equivalent (TEE) model applied to a 132 kV overhead line section enabled connection
of the cable. of up to 50% extra wind power. Results from a large number
Index Terms—Cable Temperature Monitoring, Cable TEE of simulations presented in [3] investigating the application of
Model, Dynamic Line Rating, PMU Application. DLR on overhead conductors connecting wind farms showed
DLR to have a significant economic potential.
For underground power cables, two ways to decide the
I. I NTRODUCTION flexible loading limits are the cyclic and the emergency rating
OST-OPTIMIZED generation and distribution of elec- for cables which are presented in the standard IEC 60853:2
C trical energy from eco-friendly sources has become the
objective of modern power network operation. Distribution
[1]. Cyclic rating of the cables can be used when cables are
exposed to a daily cyclic pattern. However, no such pattern
networks are being reinforced with more decentralized and is required to calculate the emergency rating which gives the
renewable power generation sources. Electrical power demand amount of current a cable can carry for a specified time period
of urban areas is also increasing continuously. This increasing before the temperature limit is breached. The emergency
generation and demand of electrical energy puts growing stress rating is calculated by studying the dynamic thermal response
on the network assets including the distribution cables. One of the cable system in presence of a load step. The state
of the constraints for routing the extra power away from the variables of the TEE cable thermal model are the conductor,
source centers or towards the load centers is the capacity or screen, jacket and soil temperature. Initial temperature of these
loadability of the cables. The loadability is dependent on the state variables are necessary to calculate the dynamic thermal
thermal rating of the cables and the ambient conditions. For response and hence the emergency rating.
cables, the insulation especially is very sensitive to the tem- A method to estimate the time-dependent thermal state of
perature higher than the recommended maximum temperature. the power cables utilizing the TEE model was presented in
For example, thermal limit of XLPE cable is 90 ◦ C. [4]. A finite element model (FEM) based method was used to
IEC standard 60287 presents a method to calculate the compute dynamic rating in [5]. However both methods require
steady-state rating of a cable system [1]. Steady-state cable temperature measurements to initialize the TEE model. This
ratings are suitable for cables under high load factor. This requires one or more temperature sensing measurements in-
means that the ratio of daily average of hourly load to the stalled along the cable path. Information about the temperature
daily maximum load is close to unity. The standard uses the could be achieved using the distributed temperature sensing
thermoelectric equivalent (TEE) model for cables which has (DTS) equipment [6]. However, installation of sensors for DTS
lumped thermal resistance and capacitance parameters in a in existing cables requires retrofitting the cable system with
thermal ladder network. fiber-optic cables and could be a major challenge in multiple
ways. This paper presents a solution to this challenge using
the presented temperature estimation method.
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 2
In absence of temperature measuring devices, data from Previous methods also did not provide any confidence interval
phasor measurement units (PMUs) at both ends of a cable (CI) for the calculated resistance and temperature parameters.
could be used to estimate the cable resistance and eventually CIs around the results would make the application more
the cable temperature in real-time. However, for medium and trustworthy when tracking the temperature of a critical cable-
short length cable sections, achieving temperature estimates section in real-time. To overcome these drawbacks, this paper
with the desired accuracy and precision could be challenging. presents a new method which is capable of giving accurate
It is also important to get accurate temperature estimates and reliable temperature estimates for 3-phase cable systems
continuously using the real-time data. In the past, work has in presence of bias and random errors.
been presented to showcase the feasibility of this idea albeit
mostly in a simulation environment and only for high-voltage
long-distance overhead lines. A. Paper Contribution
Authors in [7] proposed a method to estimate parameters
and temperature of overhead line conductors. However the This paper presents a solution to perform thermal assess-
algorithm is presented only for single phase line and no ment of cable sections to implement DLR without using
measurements errors were considered. A review of different specific temperature measurement infrastructure. The focus is
methods to estimate the parameters of a 3-phase overhead line on a relatively new domain of MV-distribution networks where
is presented in [8] and [9]. Single and double measurement the feeder lengths are relatively short.
methods and multiple measurement method using linear and At first, a new method to provide temperature estimates in
non-linear regression were compared. It was shown that the real time is presented. Unlike the other methods, this method
multiple measurement method using linear regression per- uses a 3-phase cable model to give accurate temperature
formed the best for short lines. However, quantitative effect estimates of all the conductors, even in the presence of random
of random errors and systematic bias errors present in the and systematic bias errors. This paper presents the modelling
measurement chain was not studied. The results from a field of a 3-core cable to make the impedance matrix and discusses
experiment using a robust estimator showed that further in- how an error in the model is a contributing factor to the
vestigation of the uncertainty caused by bias errors is required errors in resistance and temperature estimates. To facilitate the
[10]. According to the authors, the uncorrected systematic bias small thermal time-constant of the cables and small duration
present in the measurement chain could cause the algorithm power-flow transients a much shorter and continuously sliding
to give incorrect results. 1 hour data window was used. To complete the temperature
A calibration method to accurately estimate the line param- estimation process, CI around the estimates are computed. The
eters of a 1-phase line segment along with the bias errors was performance of the algorithm is demonstrated using two days
presented in [11]. This method uses simplification based an long field PMU data. This long period is useful in observing
assumptions that the phase errors in the current and voltage any trends in the change of cable temperature along with the
transformers (CTs and VTs) are smaller that 0.530◦ . This trends in the power flow.
however, could be untrue for real cases. An optimization- Subsequently, application of the proposed temperature mon-
based method was presented in [12] which estimated the bias itoring method in thermal assessment of a cable in presence
errors along with other unknown parameters of a 1-phase of load forecasts is presented. A flowchart describing the
line segment which would minimize the difference function whole process of temperature estimation and its utilization for
between the measured and estimated phasors at one end of advance dynamic thermal assessment of cables is presented in
the line. Fig. 1. The capability to track cable conductor temperature in
A review of methods to enable PMU based thermal moni- real-time also becomes an important tool for monitoring and
toring of overhead transmission lines is presented in [13]. Real a safe implementation of a DLR scheme.
PMU data from a 400 kV overhead line was utilized and the
results based on methods presented in [8], [11] and [12] are
compared. It was concluded that only the optimization based B. Paper Structure
method could give reasonably accurate results. However, the
data-window to calculate the parameters was 6 hours long, The remainder of the paper is arranged as follows: Sec-
while the duration of power-flow transients and the thermal tion II discusses the requirements in terms of accuracy of
time constant for the cables could be as low as 30 minutes. the resistance estimates which in turn help to estimate the
Such a long window may give smoother average results but temperature of the cable conductors within a desired range.
might miss the vital transients in the temperature. Section III presents the resistance estimation algorithm in
Both calibration and optimization methods presented in detail. The process of cable modelling to identify significant
[11] and [12] calculate the line parameters and bias error parameters and the process of uncertainty calculation is also
correction coefficients considering a 1-phase line model. The presented. Section IV presents the process of estimation of the
impedance model used did not include any mutual impedance temperature and associated uncertainty. Demonstration of the
parameters which might be present in a 3-phase line segment. method utilizing the field PMU data is presented in Section
Estimating the parameters for a 3-phase system could be more V. The intended application of thermal assessment using TEE
challenging if it includes additional mutual impedance and models of underground cable is discussed in Section VI. The
admittance parameters depending on the nature of the system. conclusions are drawn in Section VII.
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 3
Start
TABLE II
ACCURACY R EQUIREMENTS OF R ESISTANCE E STIMATES .
Real-time
Temperature Uncertainty Resistance Uncertainty
Resistance
Cu Al
Temperature Monitoring
The change in the DC resistance of the copper coil in the
temperature range 10 - 50 ◦ C was used to calculate α using a
New Loading Cable Temperature
Scenario Response linear regression model. The hypothesis for the linear model
was found correct in the measured temperature range and the
value of α with uncertainty up to 3 standard deviations was
found to be 0.003742 ±2.7914 × 10−4 ◦ C−1 . The uncertainty
No Satisfies Thermal
Constraint? calculated for α was used as a contributing factor for uncer-
tainty in the final temperature estimates. The value of α for
Yes aluminum conductor was taken to be 0.00403 ◦ C −1 [1]. Table
II shows the accuracy requirement of resistance estimates
Dispatch corresponding to different range of accuracy of estimation of
the Cu and Al conductor temperature. It serves the purpose
Fig. 1. Flowchart showing the process of utilizing the resistance estimates to
of a reference maximum level of uncertainty budget we have
assess flexible loading limits. for the resistance estimates to achieve a certain desired range
of accuracy in the temperature estimates. It is presented as
maximum allowed uncertainty because there are several other
II. R EQUIRED ACCURACY OF R ESISTANCE E STIMATES sources of uncertainties as well. It is calculated using the
This section discusses about the required accuracy in resis- value of α in (1). So, for monitoring method to determine
tance estimates for the cable temperature estimation method. the temperature of a cable conductor made of aluminum with
The fundamental factor is the desired accuracy range of the an accuracy of ± 5 ◦ C, the errors in resistance estimates must
temperature of the cable being monitored. This temperature be less than 2.01% of the true resistance.
range could then be translated into the accuracy range for
resistance estimates. According to IEC-60287-1-1, the AC III. R ESISTANCE E STIMATION
resistance of a conductor at temperature Ti is given by [14]: This section presents the cable resistance parameter es-
Ri = R0 (1 + α(Ti − T0 ))(1 + ys + yp ) (1) timation which is the core of the temperature estimation
process. The resistance estimation process was divided into
where α is the temperature coefficient (◦ C −1 ) of the resistivity three parts. First a correct model of the cable system was
for a given material, R0 is the DC resistance of the conductor made to identify the other unknown parameters needed to
at temperature T0 , and ys and yp are the skin and proximity be estimated along with the resistance. After estimating the
coefficients. The above constants depend upon the particular parameters, uncertainty of the estimates are evaluated. The
conductor material which is typically copper or aluminum. three parts are presented in the following subsections.
A test in the laboratory was performed to investigate the
effect of heat on the resistance of a copper coil. The DC
A. Cable System Modelling
resistance was measured at temperature ranging 10-50 ◦ C. At
each temperature point, 200 readings were taken. The mean Accurate modelling of the cable system impedance and
and uncertainty up to three standard deviations of the measured admittance matrix is of prime importance as it facilitates the
values are presented in Table I. selection of significant parameters to estimate. Impedance and
admittance models of overhead line and a cable for 3-phase
parameter estimation is shown in [10] and [15] respectively.
TABLE I The cable section in the grid was a 3-core cable whose cores
R ESISTANCE MEASUREMENT AT VARIOUS TEMPERATURES are arranged in a trefoil arrangement. A cross-section with
representational construction details of the cable is presented
Temperature (◦ C) DC Resistance (Ω)
in Fig. 2. As the PMUs are measuring current and voltage at
10.425 ±0.1 2.3561 ±0.0420 the conductors, only core-core sub-matrices of the complete
19.972 ±0.1 2.4458 ±0.0432 cable impedance and admittance model are used to select the
29.753 ±0.1 2.5365 ±0.0417 significant parameters [16].
39.587 ±0.1 2.6288 ±0.0426
Unless a very low current, the percentage current unbalance
49.000 ±0.1 2.7245 ±0.0426
in the grid cable was found out to be between 1-2%. Thus
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 4
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 5
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 6
small errors in the elements of A and hence would have high K5 and K6 . The total standard deviation in the resistance
variance. estimates is given by:
This is an important realization because all the variables q
used to form the LS problem shown in (21) are measurements u(Ri ) = u2rnd + u2b (25)
with some amount of error. Hence for a given power-flow The following section presents the process of calculating
condition, the accuracy of the resistance parameters estimate the temperature estimates and associated uncertainty of the
would depend on the validity of the cable model along with estimates.
the accuracy of the measurement devices.
After estimation of the cable parameters, uncertainty in the IV. T EMPERATURE E STIMATION
estimates was quantified in terms of CI associated with each
parameter. Since cable resistance has a direct relationship with The resistance estimates from the solution given by (22) are
the cable temperature, accuracy of the resistance estimates was used in (1) to achieve the temperature estimates. The uncer-
of prime concern. tainty in the temperature estimates comes from the individual
uncertainty associated with the resistance estimates (Ri ), the
measured DC resistance at 20 ◦ C (R0 ) and the used coefficient
C. Uncertainty in Estimates of resistivity (α). Treating these individual uncertainties as
The deviation in the resistance estimates was calculated independent from each other, the combined uncertainty in the
in two parts. One part of the deviation was due to random temperature estimates is then given by:
errors in PMU estimates and the other part of the deviations XN ∂f 2
2
was caused by the bias errors in the CTs, VTs and the u (Ti ) = u2 (xi ) (26)
i=1 ∂xi
phasor estimates given by the PMUs. The uncertainty due
to random errors in PMU estimates were taken as per the where, u(Ti ) is the standard deviation of each temperature
specification provided by the manufacturer. The random errors estimate Ti , f is the function given in (1) and each u(xi ) is the
were the absolute maximum errors distributed uniformly with standard deviation associated with all the parameters xi . The
zero probability of errors outside the range. The standard skin and proximity effects however, were ignored in this paper
deviation caused by the random errors (urnd ) of the impedance because the values of harmonic currents are limited in the
estimates were derived based on the co-variance of solution analyzed system 50 kV network. The total harmonic distortion
of the LS problem. It can be shown that expected variance in (THD) of the current ranges between 5-10 % with about 95
the impedance estimates is given by: % of the contribution by the lower order fifth harmonic (250
Hz). This makes the impact of the skin effect very limited, if
0
0 not negligible.
u2rnd := V ar[b|A] = (A A)−1 (23)
n−K The following section V demonstrates the results using
PMU data from the mentioned 50 kV ring network in the
where, is the residual vector, n is length of the vector Y and
Netherlands.
K is the number of parameters.
The CT and VT correction coefficients are used by the
V. R ESULTS FROM FIELD DATA
PMUs while estimating the voltage and current phasors.
However, to cater any change in correction coefficients and This paper takes data from a 50 kV ring distribution network
minimize the effect of bias errors in the measurements, promi- in the Netherlands provided via the Dutch National Metrology
nent adjusted coefficients K1 and K4 were added. However, Institute (VSL) [21]. The ring network has five substations and
neglecting the coefficients of K2 , K3 , K5 (assumed 1) and six PMUs. One of the intended research goal for installing
assuming K6 as B2 causes deviation in the cable impedance PMUs in the network was application of PMU data to estimate
parameters from their true values. This deviation is quantified the cable impedance and explore possibilities of implementing
as a bias error (ub ). The deviation in the impedance parameters DLR. Hence the cable between substations Oosterland and
caused by the bias errors in measurements is estimated by Tholen has two PMUs (one at each end). The monitored cable
calculating the combined uncertainty calculation as specified between substations Oosterland and Tholen is 15.313 km long
in the Guide to the Expression of Uncertainty in Measurement and has an AC resistance of 1.98 Ω at 20 ◦ C [22]. The current
(GUM) [20]. In this work the magnitude and phase errors were rating of the cable per phase is 350 A.
assumed to vary normally with a standard deviation of ±10% Voltage and current phasors at both sides of the monitored
from their last calibrated values. The uncertainty (variance u2b ) cable were collected for 40 hours at a rate of 5 phasor estimates
in resistance estimate due to believed bias in the measurements
was quantified by:
TABLE III
2 U NCERTAINTY SPECIFICATIONS OF USED PMU S
XN ∂f
u2b = u2 (xi ) (24)
i=1 ∂xi Entity Uncertainty
where, f is the analytical function to calculate the resistance voltage magnitude ±0.02%
current magnitude ±0.03%
and is given by the real part of (18). Each u(xi ) is the believed
voltage and current phase ±0.01◦
standard deviation in real and imaginary parts of coefficients
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 7
A TEE model of the cable is created as per recommen- Fig. 5. Cable TEE model with lumped resistance and capacitances for long
dations in [1] and [4]. In the TEE model, various layers of duration transient. Cable and soil components are shown in two boxes. The
the cable and its surroundings are represented using lumped soil is divided into three layers for representational purpose.
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 8
thick layers. Thermal resistance of the insulator, jacket and where parallel thermal capacitances are added together such
the surrounding soil is represented by T1 , T3 and Tsi . The that Q1 = Qc + pQi and Q2 = Qj + Qscr + (1 − p)Qi .
modelled cable in Fig. 5 has no armor hence the thermal However, this system of equation implies that the resistance
resistance of armor (T2 ) is ignored. of the cable remains constant. The heat generated by joule
heating is dependent on varying current values but a constant
A. Parameters of the TEE model resistance. This is contradictory to realistic case where the
resistance of the cable also varies according to the temperature
Thermal resistances (Ti ) and capacitances (Qi ) for various of the cable. This relationship between the cable temperature
layers of the cable and its surrounding need to be accurately and resistance is defined by the (1). To rectify this, Wc at time
computed. For known internal and external diameters Di and ti is modified and written as:
De of a layer, its thermal resistance is [1]:
Wc (ti ) = I(ti )2 (R0 (1 + α(θc (ti ) − θc (t0 ))) (32)
ρi Dei
Ti = ln (27)
2π Dii where R0 and θc0 are the cable conductor resistance and
where, ρthi is the thermal resistivity of the material of layer temperature estimated by the temperature monitoring method
i. For each sub-layer of the soil, thermal resistivity Tsi was and used as the initial conditions for (31) at time t0 .
calculated as [4]: The modified system (31) can be written using the state-
space notation:
ρi Dei ln(2) 0
Tsi = ln + (28) x = Ax + Bu (33)
2π Dii N
where, N is the number of soil sub-layers. Thermal capacitance where the state vector x is [θc θscr θj θs1 ... θsN ]T and
of any layer can be calculated as [1]: conductor and ambient temperatures (θc and θa ) are known.
π The driving function (B) for a given time period can be
Qi = (De2i − Di2i )Ci (29) determined using the forecasts of the generation and load units.
4
The thermal response of the cable over the given period of time
where, Ci is the volumetric specific heat of the respective cable can be obtained by solving the system of differential equations.
layer or soil sub-layer. The time domain solution of (33) is the superposition of
A transient is considered long when it lasts longer than natural and forced response of the system and for a given
1
3 ΣT.ΣQ, where ΣT and ΣQ are the internal thermal resis- period (t0 -t1 ) can be given as:
tance and capacitance of the cable. Short duration transients Z t1
for different cable types last anywhere between 10 minutes to Λt −1
x(t) = P e P x(t0 ) + P e B Λt
e−Λt dt (34)
1 hour. This paper focuses on transients lasting longer than 1 t0
hour that is the long transients. For long duration transients,
van Wormer coefficient p to divide the insulation is given by where Λ is the diagonal matrix made of the eigenvalues of
[1]: the matrix A and P is the left eigenvector.
1 1 As discussed, the initial value of the state vector (x(t0 ))
p= − 2 (30)
Deins Deins can be calculated during the steady-state conditions using the
2ln −1 available real-time estimates of the conductor temperature.
Diins Diins
Using the steady-state condition x0 = 0, and substituting the
where, Deins and Diins are the external and internal diameter value of conductor temperature (θc ) and the known ambient
of the insulator. temperature (θa ), (31) can be rewritten as a system of lin-
ear equations of form (21). Initial Values of unknown state
B. Transient Thermal Analysis variables are estimated using the solution given by (22) and
utilized in (34).
The state variables of interest are the temperature of the
The solution of the complete TEE model of a cable and the
conductor, screen, jacket and the multiple soil layers. The rate
surrounding soil was verified by comparing it to the solution
of change of the state variables can be described by the set of
given by a FEM based model created in the commercial
equations:
software Comsol Multipysics 5.4. For demonstration purpose
1 θc − θscr
0 a single-phase 10 kV cable was modelled with four layers. A
θc = Wc + Wd1 −
Q1 T1 copper conductor, an XLPE insulation, a Lead alloy sheath as
0 1 θ c − θscr θs − θj screen and jacket made up of PVC. The cross section area of
θs = Ws + Wd2 + −
Q3 T1 T3 the conductor is 330 mm2 . The properties of other cable layers
θ0 = 1 θscr − θj − θj − θs1
j
and the surroundings are presented in the Table IV and can be
Qs1 T3 Ts1 (31) found in detail in [1]. The cable is buried at a depth of 1 m.
0 1 θ − θ θ − θs2
θ s1 =
j s1
−
s 1
Ambient soil temperature was chosen to be 15 ◦ C. In the TEE
Qs2 Ts1 Ts2
model the soil layer was divided into 100 equal thickness sub-
.
.
. layers. In the Comsol model, the soil is modelled as a rectangle
0 1 θsN −1 − θj θs − θa of width of 20 m and a depth of 20 m. The boundaries of the
θsN = − N
QsN TsN −1 TsN rectangle have fixed ambient temperature.
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 9
1.5
TABLE IV Predicted current
S PECIFICATIONS OF THE C ABLE USED IN THE CABLE MODELLING AND Rated currrent
1
Current (p.u.)
Current (kA)
THERMAL SIMULATION PROCESS . 1
0.5 0.5
Layer Dex (mm) ρth (Km/W) C (MJ/m3 K)
Temperature (°C)
Thermal limit
60
60
capacity planning of cables.
4
Temperature (oC)
2
Difference
50
0
40
-2 ACKNOWLEDGMENT
30 -4
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2020.3016717, IEEE
Transactions on Power Delivery
JOURNAL OF LATEX CLASS FILES, VOL. , NO. , MONTH YEAR 10
R EFERENCES [22] N. Save, “Phasor Measurement Unit (PMU) based power system analysis
of mv distribution grid,” Master’s thesis, Delft University of Technology,
Delft, Netherlands, 2016.
[1] G. J. Anders, Rating of Electric Power Cables in Unfavorable Thermal
[23] J. Zhang, G. Welch, G. Bishop, and Z. Huang, “A two-stage kalman
Environment. Wiley-IEEE Press, 2005.
filter approach for robust and real-time power system state estimation,”
[2] T. Yip, C. An, G. Lloyd, M. Aten, and B. Ferri, “Dynamic line rating
IEEE Transactions on Sustainable Energy, vol. 5, no. 2, pp. 629–636,
protection for wind farm connections,” in 2009 CIGRE/IEEE PES Joint
2014.
Symposium Integration of Wide-Scale Renewable Resources Into the
Power Delivery System, July 2009, pp. 1–5.
[3] C. J. Wallnerstrom, Y. Huang, and L. Soder, “Impact from dynamic line
rating on wind power integration,” IEEE Transactions on Smart Grid,
vol. 6, no. 1, pp. 343–350, Jan 2015.
Ravi Shankar Singh received his B.Tech degree
[4] R. Olsen, G. J. Anders, J. Holboell, and U. S. Gudmundsdttir, “Mod-
in electrical engineering from National Institute of
elling of dynamic transmission cable temperature considering soil-
Technology Rourkela in India in 2009 and M.Sc.
specific heat, thermal resistivity, and precipitation,” IEEE Transactions
in electrical engineering from Aalto University in
on Power Delivery, vol. 28, no. 3, pp. 1909–1917, July 2013.
Finland in 2016. From 2009 to 2012 he worked as
[5] R. Huang, J. A. Pilgrim, P. L. Lewin, and D. Payne, “Dynamic cable an Electrical engineer in Alstom T&D India. From
ratings for smarter grids,” in IEEE PES ISGT Europe 2013, Oct 2013, 2014 to 2016, he was a Research Engineer with
pp. 1–5. the Department of Electrical Power System, KTH,
[6] A. Ukil, H. Braendle, and P. Krippner, “Distributed temperature sensing: Stockholm. From 2016, he is a Ph.D. candidate at
Review of technology and applications,” IEEE Sensors Journal, vol. 12, Eindhoven University of Technology, The Nether-
no. 5, pp. 885–892, May 2012. lands. His research is focused on measurement data-
[7] Yan Du and Y. Liao, “Online estimation of power transmission line based dynamic line rating and grid harmonic modelling applications. His
parameters, temperature and sag,” in 2011 North American Power interests lie in the fields of power systems monitoring, power quality and
Symposium, 2011, pp. 1–6. integration of renewable sources in the grid.
[8] D. Shi, D. J. Tylavsky, K. M. Koellner, N. Logic, and D. E. Wheeler,
“Transmission line parameter identification using PMU measurements,”
European Transactions on Electrical Power, vol. 21, no. 4, pp.
1574–1588, may 2011. [Online]. Available: http://doi.wiley.com/10.
1002/etep.522 Sjef Cobben is a part-time professor in Power
[9] D. Shi, D. J. Tylavsky, and N. Logic, “An adaptive method for detection Quality with the research group Electrical Energy
and correction of errors in PMU measurements,” IEEE Transactions on Systems at the TU/e department of Electrical En-
Smart Grid, vol. 3, no. 4, pp. 1575–1583, 2012. gineering. In 2002, he received his Master’s degree
[10] V. Milojevi, S. alija, G. Rietveld, M. V. Aanski, and D. Colangelo, in Electrical Engineering from Eindhoven University
“Utilization of PMU measurements for three-phase line parameter of Technology (TU/e, The Netherlands) with the
estimation in power systems,” IEEE Transactions on Instrumentation distinction ’cum laude’. From 2003 until 2007, he
and Measurement, vol. 67, no. 10, pp. 2453–2462, Oct 2018. performed part-time PhD research at the same uni-
[11] D. Ritzmann, P. S. Wright, W. Holderbaum, and B. Potter, “A method versity, resulting in his 2007 thesis ’Power Quality,
for accurate transmission line impedance parameter estimation,” IEEE Implications at the Point of Connection’. In 2009,
Transactions on Instrumentation and Measurement, vol. 65, no. 10, pp. he founded the company CO-Education, providing
2204–2213, Oct 2016. knowledge services and education in the field of electrical engineering, in
[12] C. Pisani, A. Vaccaro, and D. Villacci, “Conceptualization and ex- particular regarding power quality, smart grids, and the sustainability of the
perimental deployment of an adaptive synchronized sensing system electricity supply. In 2011, he was appointed part-time professor in Power
for power line thermal monitoring,” IEEE Transactions on Industrial Quality at the TU/e department of Electrical Engineering, research group
Informatics, vol. 12, no. 6, pp. 2158–2165, 2016. Electrical Energy Systems. His areas of expertise are LV- and MV-network
[13] G. Coletta, A. Vaccaro, and D. Villacci, “A review of the enabling safety, power quality, and safety of installations connected to the networks. His
methodologies for pmus-based dynamic thermal rating of power TU/e research theme of Power Quality concerns the quality of voltage, current,
transmission lines,” Electric Power Systems Research, vol. 152, pp. 257 and their mutual interaction. This is of relevance to smart grid technologies,
– 270, 2017. [Online]. Available: http://www.sciencedirect.com/science/ the integration of renewable energy sources, and the compatibility of devices,
article/pii/S0378779617303012 installations and networks.
[14] L. Lindstrom, “Evaluating impact on ampacity according to IEC-60287
regarding thermally unfavourable placement of power cables,” Master’s
thesis, KTH, Stockholm, 2011.
[15] R. S. Singh, H. van den Brom, S. Babaev, S.Cobben, and V. Ćuk,
“Estimation of impedance and susceptance parameters of a 3-phase Vladimir Ćuk received the Dipl.Ing. (M.Sc.) degree
cable system using pmu data,” Energies, vol. 12, no. 23, 2019. [Online]. in electrical engineering from the School of Electri-
Available: https://www.mdpi.com/1996-1073/12/23/4573 cal Engineering, University of Belgrade, Belgrade,
[16] A. A. Hafner, M. V. Ferreira da Luz, and W. P. Carpes Jr., “Impedance Serbia, in 2005, and the Ph.D. degree from the
and admittance calculations of a three-core power cable by the finite Electrical Energy Systems Group, Eindhoven Uni-
element method,” in 2015 IPST -International Conference on Power versity of Technology, Eindhoven, The Netherlands,
Systems Transients, 2015, pp. 1–8. in 2013. From 2006 to 2009, he was with the
Department of Electrical Measurements, Electrical
[17] L. L. Grigsby, Electric Power Generation, Transmission, and Distribu-
Engineering Institute Nikola Tesla, Belgrade. He is
tion. Taylor & Francis Group, 2012.
currently an Assistant Professor with the Eindhoven
[18] H. Saadat, Power System Analysis. McGraw-Hill, 1999.
University of Technology. His research is focused on
[19] A. Rakowska and K. Hajdrowski, “Influence of different test conditions electrical power quality.
on volume resistivity of polymeric insulated cables and polyethylene
samples,” in 2000 Eighth International Conference on Dielectric Mate-
rials, Measurements and Applications (IEE Conf. Publ. No. 473), 2000,
pp. 281–284.
[20] “JCGM 100:2008, Evaluation of measurement data guide to the
expression of uncertainty in measurement.”
[21] G. Rietveld, A. Jongepier, J. van Seters, M. Visser, P. Liu, M. Acanski,
D. Hoogenboom, and H. van den Brom, “Application of pmus for
monitoring a 50 kv distribution grid,” in Proceedings of the 23rd
International Conference on Electricity Distribution (CIRED 2015), June
2015, p. 1046.
0885-8977 (c) 2020 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 08,2020 at 20:29:30 UTC from IEEE Xplore. Restrictions apply.