129 - PPR

The document is a Work Inspection Request (WIR) for the installation of high-level PPR pipes and fittings for the water supply system at Reem Hills Villas, Abu Dhabi. The inspection is scheduled for May 2, 2025, and highlights issues with the installation of a water supply valve due to improper orientation, which does not comply with project specifications. The request includes a checklist for installation and requires approval from the relevant engineers and consultants.

Uploaded by

m.hammoury
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views6 pages

129 - PPR

The document is a Work Inspection Request (WIR) for the installation of high-level PPR pipes and fittings for the water supply system at Reem Hills Villas, Abu Dhabi. The inspection is scheduled for May 2, 2025, and highlights issues with the installation of a water supply valve due to improper orientation, which does not comply with project specifications. The request includes a checklist for installation and requires approval from the relevant engineers and consultants.

Uploaded by

m.hammoury
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

WORK INSPECTION REQUEST - WIR

Project Name Reem Hills Villas (218), Al Reem Island, Abu Dhabi
WIR Ref.No: P0124-K00183-TGC-RV06-00-6VZM-WI-WS-002620[00]

Contract No
Request Submission
Employer Reem Hills Sole-Proprietorship LLC 01-May-25
(Date & Time)
Inspection 02-May-25
PMC Royal Development Company
(Date & Time ) 11:00AM
Engineer AECOM Middle East LLC Rev No: "00
Main Contractor Trojan General Contracting LLC WIR Submitted By: M/s.TROJAN

MEP Contractor Royal Advance Electro Mechanical Works LLC WIR Submitted To: Consultant-AECOM

Part A: By the Contractor:


B.O.Q Ref: N/A Discipline:
B.O.Q. Description of Works to be inspected and / or tested: General MCC Works
Civil Landscaping
Storm Water Architectural
Description of Works to be inspected and /or tested: Sewer Dredging
Water Highway Bridge Works
Inspection Request for Installation of high level PPR Pipes and Irrigation LRT Bridge Works
fittings with Valves & Accessories for water supply system ( Telephone MSE Wall
Signal Works Provisional Sum
Excluded TMV) in Ground Floor & Ground floor riser, as per
Electrical Other (state)
attached and highlighted drawing
Street Lighting Drainage
Works Location: Villa 127 - 6VZM Landscape Lighting Water supply system

Works Quantity: Gas Network

Drawing attached to show the location(s) Yes No Checklist attached Yes No


Attached Test Certificates Yes No

Shop Drawing Ref: As per Attached Highlighted Drawing. Method Statement Ref: RHP1P1-BW-TGC-ZZ-XX-MS-ME-00003_00

Type of Attachment: Check list ITP Ref:

Eng. Dayal Pushpakumar


(QA/QC Manager )

Date & Signature


Part B: By the Engineer:
Received by Engineer on: Date: Time: Signed by:
Engineer's Comments:

Installation of water supply valve/water hammer arrestor found not acceptable due to following
reason;

Water supply gate valve/water hammer arrestor installed with the stem in a downward
orientation, which is against the project specification reference#220523/9. The specification
allows for horizontal installation as well as manufacturers installation guidelines.

The installed gate valve/water hammer arrestor with the stem pointing downwards shows
improper installation and the risk of debris accumulation within the valve/water hammer arrestor.

Name: Ashique Date & Signature


Discipline Engineer Decision:
A - Approved

B - Approved with comments 02-05-2025


C - Revise & Resubmit

D - Rejected
Sr.Resident Engineer / Resident Engineer :
04 May 2025

Name : Sabri Gars


Date & Signature
Project : Reem Hills Villas (218), Al Reem Island, Abu Dhabi

Employer : Reem Hills Sole Properietorship LLC

Employer Project Manager : Royal Development Company

Consultant : Aecom Middle East – Abu Dhabi

Main Contractor : Trojan General Contracting LLC

MEP Contractor : Royal Advance Electro Mechanical Works LLC

CHECKLIST FOR INSTALLATION OF WATER SUPPLY PIPING SYSTEM (INCLUDING VALVES)

WIRNO.:P0124-K00183-TGC-RV06-00-
Location: Villa 127 - 6VZM Date: 30-04-2025
6VZM-WI-WS-002620[00]
Checked by Checked by

SN Items to be checked Contractor Consultant Remarks

N/A

N/A
Yes

Yes
No

No
HSE Requirements

1 All the HSE requirements are fulfilled.

QA/QC Requirements

1 Check the site is well coordinated

Check PPR Pipes & fitting & conduits,valves are free from Visible
2
damage
Pipe surface is thoroughly cleaned without traces of dust, oil,
3
grease, etc.

4 Check Size and location are as per drawing

5 Condition of the pipe and fittings,valves used are acceptable.

6 Verify the supports are provided ok

Condition of the pipe and fittings & valves after the time duration of
7
inspection are acceptable

8 Check the Joints are done Properly

9 Check the open end of pipes are sealed properly

For Final Approval


MEP Contractor Engineer MEP QA/QC Engineer Consultant Representative
Eng. Muhammad Saad Ur
Name: Eng. Abdelwahid Saeed Name: Name:
Rehman
Signature: Signature: Signature:

Date: 30/04/2025 Date: 30/04/2025 Date:

TGC/QAQC/CHK/MEP/ELECT-01 REV-00 Page 1 of 1