140 Ton Crane
140 Ton Crane
CONTENTS
 6. DASH BOARD GAUGE & INDICATOR ELECT. CIRCUITS OF 140 T (OLD DESIGN GOTTWALD
    CRANE) ........................................................................................................................... 174
 7. ELECTRICAL CIRCUIT OF 140T GOTTWALD (OLD DESIGN CRANE) ................................. 175
 8. STARTING CIRCUIT OF 140T GOTTWALD CRANE (NEW DESIGN) FOR CUMMINS ENGINE
    NTA 855 P 335 & NTA 855 LBC ...................................................................................... 176
 9. DUTIES OF THE 140 TE. CRANE OPERATOR: .................................................................. 176
 10. LOAD CHART FOR GOTTWALD 140 T. BREAK DOWN CRANE [NEW] ............................. 178
 11. LOAD CHART FOR GOTTWALD 140 T. BREAK DOWN CRANE [OLD] .............................. 185
 12. SAFETY DEVICES AND SAFETY FITTINGS ON GOTTWALD 140T CRANES ........................ 187
 CHAPTER-4 ....................................................................................................................................... 190
 DOs and DONTs for.......................................................................................................................... 190
 Operation and Maintenance of 140T Gottwald Crane (New design).............................................. 190
 CHECK SHEET FOR INSPECTION OF 140T BREAKDOWN CRANES .................................................... 204
 APPENDIX-A ..................................................................................................................................... 210
 MAINTENANCE SCHEDULES OF 140T CRANE .................................................................................. 210
CHAPTER-1
 1. INTRODUCTION
 1.1 Application of Rules
    These rules apply to the operation and maintenance of all Break Down cranes
    belonging to the Mechanical Department. These rules also apply to the
    operation of cranes belonging to the Engineering or Mechanical Department
    when loaned to the Transportation Department, or when these cranes are
    worked on the open line or in sidings where their working is governed by the
    General and Subsidiary Rules.
    The General Rule governing the attachment of traveling cranes to trains and the
    Subsidiary Rules applying to the working of cranes is G.R.4.27. These rules are
    reproduced in Appendix A.
 1.2 Classification of Cranes
 (A) Cranes belonging to the Railway are divided into three classes:-
 a) Main Line Traveling Cranes
    These types of cranes are fitted with match trucks, suitable wheels, axles, axles-
    boxes and springs, buffers and other gear to enable them to run on the open
    line. These are part of the rolling stock of the Railway and are numbered
    accordingly, being marked with the name of the Department and the station to
    which they are allotted.
 b) Yard Traveling Cranes
    These types of cranes are not fitted with the necessary gear for running on the
    open line but are capable of being traversed from place to place in yards and
    sidings, laid with standard 5’-6" gauge track.
 c) Fixed and Special Cranes
    These types of cranes, which move on special runways or gantries, or are fixed
    in one place and cannot be traversed.
    Yard Traveling Cranes and Fixed and Special Cranes are considered as part of
    the dead stock of the station to which they are posted and are marked with the
    name of the Department and station to which they belong.
 (B) Main Line Traveling Cranes are further sub divided in to:-
 a) Break-Down Cranes
    Break-Down Cranes are attached to Break-down trains specifically for use in
    break-down operations. These cranes must not be utilized for any other purpose
    unless prior permission has been received/obtained from the CMPE(D&R)/Dy
    CME(P&F) HQ.
    A permanent sanction for the utilization of Break-down Cranes for the following
    purposes has been given, and it is not necessary to obtain sanction when:-
 a. Break-down cranes are used to hoist locomotives in order to facilitate repairs at
    the Sheds where these Cranes are posted.
 b. Break-down Cranes are used to load Narrow-Gauge locomotives/ NG coaches
    on to the trucks for dispatch to Workshops, or to off-load these
    locomotives/coaches from trucks on receipt from Shops after POH repairs.
 b) Traffic Cranes
    Traffic Cranes are hand and Diesel cranes allotted to Stations and Yards for the
    handling/Transshipment of heavy consignments.
 1.3 Traveling Cranes. Hire and Haulage Charges: -
    Statement showing the use of the traveling cranes, Stations at which traveling
    cranes are stabled should be furnished to the traffic accounts office. A monthly
    statement in Form Com/C-42 Rev. showing movements of the cranes during the
    month, to enable the traffic accounts office to check accuracy of charges
    collected and accounted for by stations. If there are no movement during a
    month a Nil statement should invariably be submitted.
           [ Authority: Para-1532 of Indian Railway Commercial Manual Vol-II]
 1.4 Expenditure in connection with cranes, belonging to the
    Transportation Department: -
    Though Traffic Cranes are utilized for joint work of Commercial and
    Transportation Department, the following items of expenditure will be borne
    entirely by the Transportation Department for cranes posted at all depots unless
    so specified:-
 (i) Cost of Diesel/Lube oil etc.
 (ii) Cost of repairs executed etc.
 (iii) Wages of staff employed on cranes.
 (iv) Cost of clothing for staff employed on cranes.
 1.5 Responsibility for Maintenance of Cranes: -
    Divisional Railway Managers (Operation/Mech.) are responsible for the running
    repairs, maintenance and periodical examinations of cranes belonging to the
    Transportation/Traffic & Mech. Departments.
    SSE(Diesel)/SSE(C&W) of depots where Break down or other cranes are
    posted are responsible for seeing that the cranes are maintained in good
    condition. Diesel Traffic Cranes will be maintained by SSE(Diesel)/SSE(C&W)
    nominated by the Divisional Railway Manager (Mechanical) of Division
    concerned and the Diesel Break Down Cranes will be maintained by SSE/
    (Diesel Sheds).
    SSE(C&W) will be responsible for the maintenance of hand cranes. Sr
    DME/DME will nominate the hand cranes to be maintained by each SSE(C&W).
    Carriage Inspectors (CWI) will be responsible for the periodical examination of
    hand cranes at depots where no SSE(C&W) is posted.
    Periodical overhauls and heavy repairs to cranes will be carried out in the
    Workshops, including Diesel Hydraulic 140 Te. Cranes.
 2. OPERATION:
 2.1 Qualifications and Examination of Crane men: -
    A crane may only be worked/Handled by a properly Trained/certified crane man.
    The using Department is responsible that this condition is observed.
        The crane must not be used to lift more than the maximum safe working load
        authorized at the radius at which the jib is set. The lifting capacity of the crane
        under different conditions and at various radius is marked/displayed on the
        crane, and these maximum loads must not be exceeded for any particular
        condition of working.
        Precautions should be taken to avoid loads catching on obstructions as this may
        seriously overload the crane and tackle. Sudden shocks and jerks also tend to
        overload the crane and tackle, and these should be avoided.
        Shocks and jerks usually result from: -
 i.     Mistakes in signaling to the crane driver.
 ii.    Want of observation by the crane driver.
 iii.   Sudden application of the Crane break.
 iv.    Kinks in the chain.
 v.     Slipping of the chain due to incorrect slinging or sling hooks not properly secured.
        In case of 140T Diesel Hydraulic Crane of ART, following precautions
        should be taken.
 i.     Before undertaking any lifting operation, the operator must be sure that the duty
        selector or SLI is correctly set according to the configuration of the Crane (i.e.,
        FOR) or blocked counter weight on super structure or carriage, heavy ballast
        weight fitted etc.
 ii. This crane is unstable in super elevated track in free –on- rail condition with
     counter weight or heavy ballast weight fitted to superstructure.
 iii. Swinging load is dangerous and is to be avoided.
 iv. Before raising the jib from the match truck (assuming the crane is in running
     condition) all blocking screws must be screwed down until locked on the top of
     the spring.
 v. Both relieving bogies must be unloaded, prior to raising the jib from match truck.
 vi. Before any movement of the crane by its own power, operator must be sure
     about engagement of travel gear clutch and proper braking of travel brake.
 2.6 Lifting tackle to be of suitable capacity: -
        Lifting tackle, that is hoisting chains, lifting chains, sling chains and wire ropes
        used for lifting hoisting or slinging should be of suitable capacity. Safe working
        loads for different sizes of chains and wire ropes are given in Appendix D.
        The following definitions apply to Chains and Wire Ropes: -
 a) Hoisting Chains - are main chains of cranes, used for hoisting the load.
 b) Hoisting Wire Ropes - are Main wire ropes of cranes used for hoisting the load.
 c) Lifting Chains - are chains fitted to the jib sheaves of jib cranes for lifting
    purposes.
 d) Lifting Wire Ropes - are Wire Ropes fitted to the jib sheaves of jib cranes for
    lifting purposes.
 e) Sling Chains - Chains with a ring at one end and a hook at the other, either with
    a single, double or multiple legs. Sometimes Sling Chains are made as endless
    chains.
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                   Page 12 of 210
Maintenance & Operation Manual                                  Part I- 140 T BD Cranes
 f) Wire Rope Slings - Slings with wire ropes used instead of chains.
2.7 Lifting Tackle to be tested:
    Lifting tackle, that is hoisting chains, lifting chains sling chains and wire ropes
    used for lifting, hoisting or slinging shall be periodically tested and examined.
    The instructions in regard to the testing and examination of chains and wire
    ropes are given in the work shop orders of Zonal Railways. Appendix E.
Ordering of 140T Cranes and Preparation of Disaster Management Plan. [ HLC
Recommendation No.- 15(b)-page No. 9]
The disaster management plan must inter alia include “who is responsible for what
activities in detail”.
 1. Preparation and implementation of Disaster Management plan is the
    responsibility of concerned GM/DRM.
 2. Authority to order ART/ARMV/140TBreak Down Crane, CME/CMPE(D)/Sr
    DME/DME, etc.
 3. Senior most Railway officer at the site of the Accident shall be designated site
    manager.
 4. Management of Rescue operations - Primarily Mechanical and Medical
    Departments. Assistance to be provided by all Railway Men (Irrespective of their
    department) as needed.
 5. Relief operations including care for the dead – Commercial, Medical and RPF
    department.
 6. Communication network- Telecom department.
 7. Crowd control and law and order at site - RPF.
 8. State police clearance for restoration - RPF
 9. Restoration operations -
 a) Rolling Stock – Mechanical Department
 b) Fixed Infrastructure like Track, OHE, Signalling System etc.- Concerned
    Departments.
 10. Maintenance of SPART/ART and ARMV Rolling stock/140TBreak Down Cranes
     including Rail-Cum-Road and Road Mobile Emergency vehicle etc. –
     Mechanical Department.
 11. Maintenance of equipment kept in SPART/ART/ARMV for Rescue and
     Restoration operations – concerned departments.
 12. Media Management at site –
 a) Site manager shall be the Chief spokesman at site and can be assisted by the
    concerned branch officers, if needed.
 b) PR/Commercial departments, to look after the media needs at site.
 13. Check list for the officers and supervisors must be issued in the form of pocket
     booklet indicating do’s and don’ts for the benefit of:
 a) First official reaching the site of accident
 b) Senior most officer at the site
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                               Page 13 of 210
Maintenance & Operation Manual                               Part I- 140 T BD Cranes
       *    Daily                                  Form A
       *    Monthly                                Form B
       *    Three Monthly                          Form C
       *    Six Monthly                            Form D
       *    Yearly                                 Form E
       *    Two Yearly                             Form F
       *    Four Yearly                            Form G
       *    POH                                    Form H
    Officers of the Power/Diesel Shed and Carriage & Wagon Department will
    periodically check that the registers showing particulars of examinations of
    cranes are correctly maintained; those examinations are being made on due
    dates and that the cranes are being kept in good condition.
                                                                          APPENDIX A.
(A)      General and Subsidiary Rules Regarding Working of Cranes
G.R.4.27.
(a) Traveling cranes –
(i) No traveling crane shall be attached to a train until it has been certified by a duly
    authorized person (Crane operator) that it is in proper running order, and with a
    dummy/Match truck for the jib, if necessary.
(ii) When a crane is to work on any line provided with electric traction or any line
     adjacent to it, the procedure and precaution as laid down under special
     instructions shall also be followed.
(b) Working and care of cranes -
1. Crane men - All Crane men must be in possession of a competency certificate
issued by the Divisional Railway Manager (Mech.) under who he is working. The
Crane man is responsible for the efficiency of the crew working under him, who must
be trained men.
(c) in addition to the above, the sketches indicating the principal parts of 140T. diesel
hydraulic breakdown cranes with their load charts for the safe operation at site are
enclosed in annexure- A, B, C, D & E.
1. Lifting capacity - The lifting capacity of all cranes under different conditions and at
various radii to be painted on either side of the carriage or super structure of the
crane as well as the size of the chains and wire rope of each crane must be painted
in white letters on the jib.
2. Weight of balance weight box - The weight of the balance weight box of hand
traveling cranes must not be interfered with in any way. when the crane is in use, the
balance box must be at the extreme end of its tail. The weight contained in the
balance box should be painted conspicuously on both sides.
3. Repairs, Examination and Periodical Overhaul –
(a) The Divisional Railway Manager is responsible for their maintenance.
(b) All cranes with their gears and under gearing must be carefully inspected by the
    SSE (loco)/SSE(C&W) or by the nominated supervisor at intervals of not more
    than three months.
(c) The 140 T Diesel Hydraulic Cranes of ART/BDT are normally due for periodical
    overhaul every 08 years. These cranes however be examined by division at
    various intervals/Schedules as prescribed by RDSO incorporating with the
    schedules as prescribed by Parel workshop for Cowans Sheldon crane &
    Jamalpur workshop for Gottwald design cranes.
      The examination of wire ropes and wire rope slings of 140 T Diesel hydraulic
      crane will be done by the staff specially trained at divisional level as per the
      procedure laid down in Workshop Orders. The Chains will however be sent to
      Mechanical work shop Parel/Jamalpur for periodical inspection and testing.
4. Attachment of Cranes -
(a) No traveling Diesel cranes are to be worked or run-out on the Main line, except
    under the supervision of a certified Crane man.
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                Page 17 of 210
Maintenance & Operation Manual                                   Part I- 140 T BD Cranes
(b) Before a traveling crane is allowed to run outside station limits, the jib must be
lowered on to its dummy/match truck, with the jib resting freely on the bolster. The
cams beneath the balance weight box or such contravene with which the crane is
fitted must brought in to use. on diesel cranes the outrigger girders/beams must be
pushed in and secured properly. on hand cranes the balance weight box must be
fixed close to the crane pillar. The grippers and all other fittings must be securely
stowed away and fastened to prevent their moving. The weight of the crane must be
taken on the springs. The crane man shall ensure this.
In case of 140T. diesel hydraulic cranes for “in-train” in-running/traveling condition,
ensure the following guidelines.
(i)     load the relieving bogies (by operating hand pump) until the centre casting
        locking pins slides into position and then release the loading jack completely.
(ii)    Ensure that the heavy lift ballast weight is removed and placed on its proper
        place on ballast truck provided with crane.
(iii)   The detachable counter weight is also placed on its place provided on
        carriage below the crane jib end side.
(iv)    Load the crane springs by taking the weight of the crane ensuring that the
        blocking screws are screwed up and ensure the gap between top of the
        spring and screw is sufficient for free movement of springs while crane is in
        running condition.
(v)     The traveling gear box must be disengaged when traveling “in-train”.
(vi)    All the six (6)/four (4) outriggers hydraulically operated telescopic draw
        beams incorporating with hydraulic operated jacks which are inbuilt into
        carriage, should be secured in their proper position and locked properly in
        running condition.
(vii)   Ensure that the coupling hoses between the carriage and relieving bogies
        (both end) are connected properly. Also ensure the same between match
        wagon and ballast truck of the crane.
IMPORTANT: After coupling the relieving bogies and before traveling recharge the
spring feed lubricants on the both relieving bogies and the carriage and castings with
recommended lubricants.
(c) The crane man is responsible for seeing that the aforesaid precautions have been
taken and the Guard will verify that the jib has been correctly lowered on the
dummy/match truck and the crane turning table has been locked by means of the
provision available on the crane.
(d) Where possible all cranes should travel with the jib to the rear (i.e., in trailing
direction) but where this is found impracticable, care must be taken to see that the
instructions regarding the securing of the jib have been fully observed.
(e) The JE/SSE (C&W) nominated for train Examination will certify in the Guard's
Memo Book if the crane is fit to run. Before certifying that the crane is fit to run, he
must ascertain from the Crane man that the above rules have been complied with.
5. 140 Ton Diesel Hydraulic Cranes:
140Ton diesel hydraulic cranes may run over any BG section of the Railway.
i       The load shall be brought to the shortest possible radius. The jib should
        normally be brought parallel to the truck.
ii      Based on the type and conditions of the Formation, the Crane Driver/Supervisor
        should take adequate precautions to ensure that there is no settlement of
        formation under the working crane.
iii     During Crane working, a special watch Shall be kept on the condition on fish
        plates. Any damaged fish plates should be replaced before allowing the traffic
        on the restored track.
II      For track of lower standard than that mentioned above the Chief Engineer
        concerned shall decide the lower maximum permissible speed. In this
        connection, Railway Board’s letter No. 65/WDO/SR/26 dt. 19/20.10.1966 may
        be seen. When the Chief Engineer considers that the road bed is not compacted
        or there is improper drainage, he may suitably restrict the maximum permissible
        speed depending on the local conditions.
IV     The Bridges shall be MGB 87, RBG or BGML standard drawings.                  The
       movement of the crane on these bridges shall be restricted as follows:
GENERAL:
1      All permanent and Temporary speed restrictions in force and those imposed
       from time to time due to track, bridges, curves, signaling and interlocking etc.
       shall be observed.
2      A copy of the speed certificate must be available with crane whenever it has to
       work on the Railway lines.
3      The use of crane which is likely to foul the overhead equipment on an electrified
       section are subject to the conditions laid in SRs of zonal railways.
2. OPERATION:
a)     Cranes are not to be operated between sunset and sunrise except in case of
       emergency.
c)     The bearing spring must be relieved of the weight of the crane by the means
       provided, the outrigger girders must be fully extended to project equally on both
     sides of the crane and securely packed up and the claws or grippers must clip
     the rails firmly. On hand cranes the cams beneath the balance weight box must
     be traversed outwards to its full extend and clamped. The rising pulley block on
     the chain just always be used when lifting loads above half lifting capacity of
     hand cranes.
d)   Two cranes of unequal lifting capacity must not be operated together to lift any
     one heavy article, unless the lifting capacity of the smaller crane is at least equal
     to half the weight to be lifted.
e)   When crane is liable to foul another line during working, it must be in charge of a
     responsible subordinate official such as an Inspector. The Station
     Superintendent/ Manager at the either end of the section must be advised to
     issue caution orders to the drivers of trains proceeding into the section. The
     inspector in charge of the crane must when the crane is likely to foul another
     line, protect that line with Banner flags and Hand signals in accordance with
     SRs. Such banner Flags and Hand signals may only be removed on his
     authority when the crane has stopped working and the jib has been placed
     parallel to the track, clear of the adjacent road.
g)   The 140-ton Diesel Hydraulic crane shall only be driven on the bridges as per
     the speed certificate circulated by RDSO vide their letter No.
     SL/CR/SPD/140T/Jessop dated 01/25.02.1991, 29.06/01.07.92 and 03.05.1994
     or latest instructions.
a)   All movement of the crane Jib shall be exercised with great care so as not to
     foul overhead lines where possible the direct blast from crane chimney to
     overhead lines or insulators should be avoided.
b)   The 140 T diesel hydraulic crane provided with ‘A’ frame for derricking the Jib
     when erected, the height is about 9 meters from the rail level when fully raised
     and will in any case foul the overhead lines also foul/infringe with OHE portals.
     In such cases, the overhead lines of the same track on which the 140 T crane is
     working have to be slewed and if necessary to be grounded. The overhead
     lines of the adjacent line are also required to be made dead. Slewing of OHE
     wires will only be done in case when it is essential or obstructing crane working.
                                                                       APPENDIX – B
The code of signals for controlling the movements of the cranes is as under:
2)   Lifting:              Face the jib with the right arm held parallel to the
                           ground extended to the side of a body with the palm
                           upwards and move arm in an upward direction from
                           the shoulder several times.
3)   Lowering:             Face the jib with the right arm held parallel to the
                           ground extended to the side of a body with the palm
                           downwards and move arm in downward direction
                           from the shoulder several times.
4)   Direction of travel: Face direction in which, it is required to travel at the
                          same time giving signal by swinging right arm from
                          rear to front.
No. 2 Lifting
Right hand parallel and extended from the shoulder with palm upwards moved in an
upward direction from the shoulder until the lift is completed.
                            No.3 -Lowering
Right hand held parallel and extended from the shoulder with the palm downwards
moved in downward direction from the shoulder until the lowering is completed.
                            No.4 Direction of Crane travel
Face direction of travel required at the same time giving signal by swinging the arm
nearest the crane driver from rear front in the direction of required travel.
                     No.5 – Travel of Cranes (OH cranes)
Face the job being lifted and give the direction of travel by extending right or left hand
parallel with the shoulder in the direction required.
                     No. 6 Slewing of Cranes (same as above)
Right hand held parallel and extended from the shoulder in front of the body with
palm upwards moved in an upward direction from the shoulder several times.
                          No.8 Lower jib of the Cranes.
Same as No.7 except palm downwards moved in a downward direction from the
shoulder several times.
                                   No. 9 Stop.
Right hand held above the head fully extended and open
                                  No.10 Slowly
Left hand held above the head fully extended and closed.
Note: This signal to precede any of the above in case of slow and slight movements.
5)    Travel or Crab or Face the job being lifted and indicate the direction of
      slowing           movement by extending the right or left arm parallel with
                        the shoulder in the direction required.
6)    Raising Jib         Hold right arm parallel to the ground and extend from
                          the shoulder in front of the body with the palm upwards
                          and move in an upward direction from the shoulder
                          several times.
7)    Lowering jib        As No. 6 except that palm must be downwards and the
                          arm move in a downward direction from the shoulder
                          several times.
8)    Slowly              Hold left hand above the head fully extended and
                          closed. This signal is to precede any of the above in
                          case of slow movements being required.
9.    Stop                Right hand held above the head fully extended and
                          open.
                                                                          APPENDIX – C
1. The safe working loads for different sizes of chains are given in the following table.
      Short link and pitched or          Stud link chains       Short link and pitched
         calibrated * chains              formula 9-d 2           or calibrated chains
            formula 6-d 2                                             formula 6-d 2
   Nominal diameter        Safe        Nominal        Safe      Nominal         Safe
        of chain          working    diameter of     working    diameter      working
                           load         chain         load       of chain       load
     Inch        mm      Ton Cwt    Inch    mm     Ton Cwt        SWG        Ton Cwt
  7/32*        5.6      …     5     1      25.4    9    0           …         …      …
  1/4*         6.4      …     7     1.1/4 31.8     14   1       6 (0.192)     …      4
  9/32*        7.1      …     9     1.1/2 38.1     20   5       5 (0.212)     …      5
  5/16*        7.9      …     11    1.3/4 44.4     27   11      4 (0:232)     …      6
  11/32*       8.7      …     14    2      50.8    36   0       3 (0.252)     …    7.1/2
  3/8*         9.5      …     16                                2 (0.278)     …      9
  13/32*       10.3     …     19                                1 (0.300)     …      10
  7/16*        11.1     1     2
  15/32*       11.9     1     6
  ½*           12.7     1     10
  9/16*        14.3     2     0
  5/8*         15.9     2     6
  ¾            19.0     3     7
  7/8          22.2     4     11
  1            25.4     6     0
  1.1/16       27.0     6     15
  1.1/8        28.6     7     12
  1.1/4        31.8     9     7
  1.3/8        34.9     11    6
  1.1/2        38.1     13    10
  1.5/8        41.3     15    15
  1.3/4        44.4     18    5
  1.7/8        47.6     21    0
  2            50.8     24    0
  2.1/4        57.2     30    7
  2.1/2        63.5     37    10
Notes:
1.      The safe working in the above table and those stamped on tackle and entered
        in the certificates are for vertical pull on a single length of chains under
        conditions of steady loading and with the load absolutely free to move.
2.      The safe working loads given in the above table for pitched or calibrated load
        chains for hand operated pulley blocks apply only to sizes up to and including
        5/8” diameter.
3.      To obtain the safe working loads in tons for any intermediate size, use the
        formula at the head of the respective column d 2, is the square at the nominal
        diameter or the iron or steel in inches. The formula does not apply to pitched
        or calibrated chains above 5/0” diameter.
II.     The working load on the endless sling chains should not exceed the safe
        working load on the single chain.
 III.   The safe working load on double sling chains is generally less than twice the
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                Page 27 of 210
Maintenance & Operation Manual                                  Part I- 140 T BD Cranes
safe working load on a single chain and is given in the following table for different
sizes of chain with the two parts of the sling inclined at various angles.
  Diameter of iron chain             Safe working load for complete sling
                                      o
                                  30                600                 900
     Inch          mm         Ton     Cwt      Ton       Cwt      Ton          Cwt
      1/4          6.4         0       14       0         12       0            10
     5/16          7.9         1       2        0         19       0            16
      3/8          9.5         1       11       1         8        1             3
      1/2          12.7        2       17       2         12       2             2
      5/8          15.9        4       10       4         0        3             6
      3/4          19.0        6       10       5         17       4            15
      7/8          22.2        8       17       7         18       6             9
       1           25.4        11      12       10        7        8             9
    1.1/16         27.0        13      2        11        14       9            11
    1.1/8          28.6        14      12       13        2        10           14
    1.1/4          31.8        18      2        16        5        13            5
    1.3/8          34.9        21      17       19        2        16            0
    1.1/2          38.1        26      1        23        8        19            1
    1.5/8          41.3        30      12       27        8        22            8
    1.3/4          44.4        35      9        31        16       25           19
    1.7/8          47.6        40      14       36        10       29           16
       2           50.8        46      8        41        11       33           18
    2.1/4          57.2        58      8        52        7        42           15
    2.1/2          63.5        72      9        64        19       53            0
                                                                                     o
1.For normal lifting the angle between the parts of the sling should not exceed 90
2.In exceptional cases an angle between the two parts of the sling of not exceeding
1200 may be permitted, but in such cases the capacity of the complete sling is
reduced     to    that  of   a    single   chain    of    the    same      diameter.
The safe working loads for wire ropes of 100-110 tons sq. inch tensile strength of wire
and 6x19.6x24 and 6x37 combinations are given below:
Circumferen                 6X19                        6X24                      6X37
ce of rope            Safe working load           Safe working load         Safe working load
                           Non                           Non                       Non
                                      Pass.                      Pass                      Pass
                Cranes     pass.               Cranes pass.              Cranes pass.
                                      Hoists                    Hoists                    Hoists
                          Hoists                        Hoists                   Hoists
Inch    MM      T   C    T     C     T     C   T C T C T C               T C T C T            C
3/4     19.0    0    6   0    3½     0   2½     0   5   0   3 0 2        … … … … … …
1       25.4    0   11 0      6½     0   4½     0 10 0      6 0 4         0 11 0      7 0     4
1.1/4   31.8    0   17 0      10     0     7    0 16 0 10 0 6             0 16 0      9 0     6
1.1/2   30.1    1    4 0     14 ½ 0      9½     1   3   0 14 0 9          1  3    0 14 0      9
1.3/4   44.4    1   13 1       0     0    13    1 11 0 18 0 12            1 13 0 19 0 13
2       50.8    2    5   1     7     0    18    2   2   1   5 0 17        2  4    1   6 0 17
2.1/4   57.02   2   17 1      14     1     3    2 12 1 11 1 1             2 16 1 14 1         2
2.1/2           3   10 2       2     1     8    3   7   2   0 1 6         3  7    2   0 1     6
2.3/4   69.8    4    4   2    10     1    13    3 19 2      7 1 11        4  2    2   9 1 13
3       76.2    5    6   3     3     2     2    4 13 2 16 1 17            4 19 2 19 1 19
3.1/4   02.6    6    3   3    14     2     9    5 12 3      7 2 5         5 12 3      7 2     5
3.1/2   00.9    7    6   4     7     2    18    6   9   3 17 2 11         6 12 3 19 2 13
3.3/4   95.2    8    6   4    19     3     6    7   6   4   7 2 18        7 13 4 12 3         1
4       101.6   9    7   5    12     3    15    8   9   5   1 3 7         8 16 5      5 3 10
4.1/4   108.0   10 10 6        6     4     4    9   9   5 13 3 15        10 0     6   0 4     0
4.1/2   114.3   11 19 7        3     4    15   10 10 6      6 4 4        10 19 6 11 4         7
4.3/4   120.6   13 5     7    19     5     6   11 18 7      3 4 15       12 7     7   8 4 18
5       127.0   14 12 8       15     5    16   13 2     7 17 5 5         13 15 8      5 5 10
5.1/4   133.4   16 5     9    15     6    10   14 6     8 12 5 14        15 5     9   3 6     2
5.1/2   139.7   17 15 10      13     7     2   15 12 9      7 6 5        16 9     9 17 6 11
5.3/4   146.0   19 6 11       12     7    14   17 6 10 7 6 18            18 2 10 17 7         4
6       152.4   21 5 12       15     8    10   18 14 11 4 7 9            19 16 11 18 7 18
When used for hoists the safe working load of wire ropes is reduced according to
whether the hoist is used as a passenger or non passenger hoist. The reduced safe
working loads are given on the certificate.
                                                                        APPENDIX ‘D’
I.    Testing of chains
                [ Based on workshop orders of Zonal Railways.]
a)    Testing of chains- The mechanical Department will carry out the testing of
      hoisting, lifting and sling chains, Chain pulley blocks, belonging to all
      departments of zonal Railway/ Divisions at nominated Workshop.
b)    All crane Hoisting, lifting and sling chains in the possession of all departments
      must be tested once in a year at nominated workshop.
      Chains from Transportation Department Cranes will be sent for testing in sets
      consisting of one double and one single, lifting and sling chains respectively.
      Cranes should only be out of action when the main hoisting chain (where only
      one is provided) is under test.
c)    Chains and slings used by workshops/sheds and those of cranes in daily use
      must be tested every six months under normal conditions and those
      subjected to severe working conditions; are inspected more often say once in
      three months.
d)    Every chain must bear a number and the workshop Test Mark, to show that its
      use for the above purposes has been authorized.
e)    Every new chain and chain slings so procured shall then be sent to nominated
      Workshop along with procurement documents, heat treatment and test
      examination certificates issued by the manufacturer for testing, numbering and
      entry in the special register maintained for this purpose, before they are put
      into service. details such as maker’s name, safe working load, diameter of link
      and length of chain, date put in service and date on which subsequently tested
      must all be recorded.
f)    Under no circumstances must a chain be cut down, lengthened, or have its
      number altered except at nominated workshop.
g)    When forwarding chains for testing to nominated CWM, it is important that the
      chain number, overall length and diameter of link is entered on the advice note
      under which the chain is dispatched, to facilitate identification with the entries
      in the register.
h)    The above instructions also apply to all cranes fitted with wire ropes in lieu of
      chains.
i)    Chains due for testing must be sent in by those in whose charge they are, to
      concerned CWM l and these officers will deal with any enquiries or
      communications which may be necessary.
V.      Safe working loads of Manila ropes of quality complying with Indian Stores
        Department Specification G/Tax/11-7A are given below:
Circumference     Total No. of                 Safe working load for new ropes
      in           yarn per      Special quality marked with a Special quality marked with
                     rope          black yarn in each of the      a black yarn in one of the
                                    strands of the cordage          strands of the cordage
 Inch     MM                         Ton             Cwt             Ton            Cwt
1        25.4               9          -             1¼                -              1
1¼       31.8              12          -               2               -             1½
1½       38.1              18          -               3               -             2¼
1¾       44.4              24          -               4               -              3
2        50.8              33          -             5¼                -              4
2¼       57.2              39          -             6¼                -              5
2½       63.5              51          -             7¾                -              6
2¾       69.8              60          -             9½                -             7¼
3        76.2              72          -              11               -             8¾
3¼       82.6              84          -              13               -             10
3½       88.9              99          -              15               -            11 ½
3¾       95.2             111          -              17               -            13 ¼
4        101.6            129          -              19               -             15
4¼       108.0            144          1               1               -            16 ½
4½       114.3            162          1               4               -            18 ½
4¾       120.6            180          1               6               1              0
5        127.0            201          1               9               1              4
5½       139.7            243          1              15               1              7
6        152.4            288          2               1               1             12
6½       165.1            339          2               8               1             17
7        177.8            393          2              15               2              3
8        203.2            513          3              11               2             15
9        228.6            648          4               8               3              9
10       254.0            801          5               8               4              4
11       279.4            969          6              11               5              0
12       304.8           1152          7              15               6              0
13       330.2           1356          9               0               7              0
14       355.6           1572         10               8               8              2
15       381.0           1800         12               0               8              2
16       406.4           2049         13              11              10             11
17       431.8           2316         15               5              11             17
18       457.2           2592         17               1              13              0
Note:
1. The above safe working loads are based on a factor of safety of eight on the
   specified minimum breaking strength.
2. Manila rope is adversely affected by climatic conditions. The above safe loads
   refer to rope recently tested in accordance with the rules.
II. Periodical Examination and Maintenance of Wire Ropes and Wire Rope
    Slings:
Unlike chains and chain slings are not subjected to load test during service. They are
to be periodically examined visually.
Wire ropes in use on workshop/Shed/Other Depot cranes and other cranes in daily or
very frequent use must be removed at site every three months. Wire ropes used on
hand and steam cranes not in daily or frequent use may be removed for examination
at site every six months. In case of Breakdown cranes, however, the wire ropes
must be removed after they have been used on heavy breakdown operations for
examination.
In regard to para (i) wire ropes should not be sent to nominated workshop for
periodical test or examination, but should be examined as specified above and a
report may be submitted in Triplicate on the form (G.43.F or prescribed by railway) to
the CWM concerned. The requisitions for the forms referred to, should be submitted
to the controller of stores for the number required.
Method of periodical examination of wire ropes and wire rope slings:
a)    Wire ropes and slings to be detached from cranes and thoroughly cleaned and
      their length, circumference and diameter measured and recorded. The
      circumference/ dia of wire rope should be measured at minimum three places
      beginning with the eye end in shorter length rope and more in longer ropes, at
      least 150 cm apart, with a suitable measuring device such as rope caliper. The
      average or these readings will be the circumference/ diameter of the rope.
b)    The wire ropes and slings are then to be carefully examined for strain and
      distortion. Strain will be indicated by a reduction in the original circumference
      of the rope or diameter which can generally be measured at the eye end.
c)    Each strand should be examined for flat or fractured wires, and projecting
      ends, if any should be broken off. If fractured wires are found in two or more
      places it should be ascertained if they are on the same of separate strands.
      The same also applies to flattened or strained wires. The position of strains or
      fractures should be measured from the centre of the Hook.
d)    No wire rope should be passed if in any length of 8 dias, the total No. of visible
      broken wires exceeds 15% of the total No. of wires, or the ropes shows signs
      of excessive wear, corrosion or other defects, which in the opinion of the
      inspecting authority renders it unfit for service.
e)    On completion of inspection and before it is fixed in position, the rope should
      be well greased with Graphite water proof grease or by Holicoat which should
      be well worked into the interstices of the strands.
                                                                                                                 Prescribed form
                                                  III.                   Particulars of Examination of Wire Ropes
Strands broken
other core
                                                                                                                                                                                                                                                             structure
                                                  Original
                                                                                                                                                                                                                              position
                             Single
                                                                                 strain
                             Block
                                                                                                          No.of
                                                                                   to
1 2 3 4 5 6 7 8 9 10 11 12
* A rope with 6 strands and 37 wires in each strand would be thus 6 X 37.
Note: For instructions regarding examination of wire ropes see clauses (a) to (b) of
      sub-para 2 of para 24.
Memo No……………………………………………………………………………...
Forwarded in triplicate to the CWM /Dy.CME for information and return with his remarks.
Station:                               …….
Date                                   ………
Memo                                   …………………………………………………………………………………
Returned to the DRM (Optg)./DRM (mech)……………………………………….
                                                                                                                                  Signature/Works Manager……………
                                                                           APPENDIX ‘D-1’
The standard “lifting tackles” for 140 T diesel hydraulic crane of accident relief train is
given below, together with a table showing how the lifting tackles can be sent for test
in two periods and have the crane still kept at work.
Lifting tackles
2     1.Two leg wire rope sling     1.Two leg wire rope sling to   1.Two leg wire rope
      to BS-1290 SWL 70 T, with     BS-1290 SWL 70 T, with         sling to BS-1290 SWL
      hook and ring, length = 6 M   hook and ring, length = 6 M    70 T, with hook and
                                                                   ring, length = 6 M
c)    Wire rope: single part        Wire rope: single part         Wire rope: single part
      spliced endless sling  64.   spliced endless sling  64.    spliced endless sling 
      Rope 6/49 construction        Rope 6/49 construction steel   64. Rope 6/49
      steel core with ordinary      core with ordinary Thimbles.   construction steel core
      Thimbles.                                                    with ordinary Thimbles.
d)    Proof load: 81T per leg       Proof load: 81T per leg        Proof load: 81T per
                                                                   leg
4)    Two leg wire Rope sling to    Two leg wire Rope sling to     Two leg wire Rope
                                                                   sling to
      BS-1290. S.W.L 25 Ton         BS-1290. S.W.L 25 Ton with
      with Hook & Ring .Length 2    Hook & Ring .Length 2 Nos =    BS-1290. S.W.L 25
      Nos = 5 M & 2 Nos =7 M        5 M & 2 Nos =7 M               Ton with Hook & Ring
                                                                   .Length 2 Nos = 5 M &
                                                                   2 Nos =7 M
b)    Ring- MAT EN.14A.             Ring- MAT EN.14A. Ablong       Ring- MAT EN.14A.
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                  Page 34 of 210
Maintenance & Operation Manual                                     Part I- 140 T BD Cranes
     Ablong Link of inside Dia      Link of inside Dia 890x540     Ablong Link of inside
     890x540 Matl  100.            Matl  100.                    Dia 890x540 Matl 
                                                                   100.
d)   Proof Load-42.4 Ton per        Proof Load-42.4 Ton per        Proof Load-42.4 T per
     leg.                           leg.                           leg.
4.   Single Leg Wire Rope           Single Leg Wire Rope Sling     Single Leg Wire Rope
     Sling to BS-1290. SWL 70       to BS-1290. SWL 70 Ton         Sling to BS-1290. SWL
     Ton with Hook & Ring.          with Hook & Ring. Length = 6   70 T with Hook & Ring.
     Length = 6 M                   M                              Length = 6 M
d)   Proof Load -To 105.4           Proof Load -To 105.4 Tonne     Proof Load -To 105.4T
     Tonne
4.   Single Leg Wire Rope           Single Leg Wire Rope sling     Single Leg Wire Rope
     sling to BS-1290. SWL.50       to BS-1290. SWL.50 Ton         sling to BS-1290.
     Ton Max with Hook & Ring.      Max with Hook & Ring.          SWL.50 Ton Max with
     Length = 5 M                   Length = 5 M                   Hook & Ring. Length =
                                                                   5M
a) Hook- 50 Ton S.W.L. Hook Hook- 50 Ton S.W.L. Hook Hook- 50 Ton S.W.L.
c)    Wire Rope- Single Part         Wire Rope- Single Part         Wire Rope- Single Part
      Spliced endless sling  64.    Spliced endless sling  64.    Spliced endless sling 
      Rope 6/49 construction         Rope 6/49 construction steel   64. Rope 6/49
      steel core with ordinary       core with ordinary Thimbles    construction steel core
      Thimbles                                                      with ordinary Thimbles
b)    Proof Load-To 140 Ton          Proof Load-To 140 Ton          Proof Load-To 140
                                                                    Ton
                                                                     APPENDIX – E
1.0 140 Ton DSL HYD Crane of BDT
[ Cowans Boyd/NEI. UK]
Sketch shows the principal parts of 140 Te. Dsl Hyd. Crane of BDT
Note: Load Chart indicating safe working load operation (SWL) is enclosed.
      10          4.05     140    25     86       25      63         25          47       25
      11          5.05     130    25     74       25      58         25          43       25
      13          7.05     105    25     58       25      49         25          36       25
      15          9.05      85    25     47       25      42         25          30       25
      16         10.05      70    25     42       25      39         25          27       25
      17         11.05       -    25      -       25       -         25           -       23
      18         12.05       -    25      -       25       -         25           -      21.5
      19         13.05       -    25      -       25       -         25           -       20
 3.0 WARNINGS TO WIRE ROPE USERS (SK-1837)
 1.        Never over load a rope or rope sling
 2.        Never use a rope in which components are not in correct position & alignment
           or without free articulation
 3.        Never place a hook or shackle round the rope to provide bight.
 4.        Never use an excessively corroded or worn rope or rope with flattened or
           fractured/broken wires.
 5.        Never use a sling found frayed, elongated & distorted.
 6.        Never forget that the safe working load of a multiple leg sling decreases as the
           angle between the legs increases also that with a 3 or 4 leg sling, two of the
           legs may be taking the greater part, or even the whole of the load.
 7.        Special precautions must be taken and a larger size rope or sling should be
           used -
           a.     When the exact load is in Doubt
           b.     When there is liability to Shock.
           c.     When the conditions are Abnormal or Severe.
           d.     When there is exceptional Hazard to life and Limb.
 8.        The following Precautions must always be strictly observed -
           a.     Do not cross, twist, kink or knot any rope or sling.
           b.     Do not drag a rope or sling from under a load.
           c.     Do not drop a rope or sling from a height
           d.     Do not roll loads over with a rope or sling
 E.        Do not use a Rope or Sling over Sharp Corners without Protective padding.
 Remember that -
 9.        Wire Rope Slings and components must be periodically examined.
 10. Special care should be taken to avoid snatch or sudden loads
 11. Competent periodic inspection reduces hazard and increases safety.
 4.0 WARNINGS TO CHAIN USERS (SK-1838)
 1.        Never over Load a chain or chain Sling
 2.        Never use a chain in which the links are locked or stretched or are without free
           movement.
 3.        Never hammer a Chain to straighten a link or to force a link in to position.
APPENDIX – F
ORDINARY THIMBLE
                                                             DRAFT
                                                                                        ø 64 ROPE-6/49 CONSTRTUCTION STEEL CORE
                                                                     ORDINARY THIMBLE
                     PROOF LOAD 81 TONNES PER LEG
ITEM -A TWO LEG WIRE ROPE SLING TO BS. 1290 – ( 2 Nos. REQD)
                                                                                       LINK
  A METAL LIABLE TO BE ATTACHED
  STATING BY STAMPING S.W.L. 30 T MAX.
  0-900
                                                                                       ORDINARY THIMBLE
ORDINARY THIMBLE
                                                                                    2 NOS. L = 5M
ITEM -B TWO LEG WIRE ROPE SLING TO BS: 1290 – ( 2 Nos. REQD.)                       2 NOS. L = 7M
DRAFT
                                 ORDINARY THIMBLE
                                 70 TON S.W.L. HOOK
                                 HIGHER TENSILE STEEL
                                 TO BS: 2903-SEE ITEM 'K'
ITEM -C SINGLE LEG WIRE ROPE SLING TO BS: 1290 – (4 Nos. REQD.)
DRAFT
          5M
                                          DOUBLE PART SPLICED ENDLESS SLING ø 64
                                          ROPE
                                          6/49 CONSTRUCTION STEEL CORE
ORDINARY THIMBLE
ITEM -D SINGLE LEG WIRE ROPE SLING TO BS: 1290 – (4 Nos. REQD.)
SOFT EYE
DRAFT
SOFT EYE
ITEM -E SINGLE LEG WIRE ROPE SLING TO BS: 1290 – (2 Nos. REQD.)
 7.Technical Specification for Wire Rope Slings for 140T Diesel Hydraulic
     Crane of Gottwald Make
 A.70-ton Double Leg Wire Rope Sling (DRG No.: SK NO. JMP-CR-160/2003)
     Double leg wire –rope sling complete with hook at one end oblong link at the
     other end 6 m long each certified for 70 t safe working load at an included
     angle of 90° suitable for use with Ramshorn hook 3WDH 140 CR-
     5.2.7701.0087-2.
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
WIRE ROPE USED IN 140T GOTTWALD CRANE (OLD & NEW DESIGN)
4.Recovery Winch Wire Rope (Old Design)- Wire rope of JMP/CR- 187/
  construction 35x7 (IWRC of special design avoiding cross over 03 Alt-8
  between the strands of the core & reducing the danger of internal
                                            DRAFT
5a. Gantry Wire Rope (Old Design) - Wire rope of construction JMP/CR- 188
 8x26 (IWRC) plastic impregnated, compact strands, self- A/ 03 Alt-4
 lubricated, langs/ordinary, RGG, Galvanised, 1960N/mm2, Min.
 breaking load 3080KN, 60x13000 mm fitted with socket at both
 end G10+G10-90º with accessories
5b. Gantry Wire Rope (Old Design) - Wire rope of construction JMP/CR-188 B/
 8x26 (IWRC) plastic impregnated, compact strands, self- 03 Alt-5
 lubricated, langs/ordinary, RGG, Galvanised, 1960 N/mm2,Minm
 breaking load 3080KN. 60x12100 mm fitted with socket at both
 end G10+G10-90º with accessories.
1. Main Hoist Wire Rope (New Design)- Wire rope of construction         JMP/CR-
  35x7 (IWRC of special design avoiding cross over between the          189/03 Alt-6
  strands of the core & reducing the danger of internal rope
  destruction), compact strands, self-lubricated, rotation resistant,
  D26X470M,RGG,Langslay,un-galvanized, 1960 N/mm2,
  minimum breaking load 519.5 KN with accessories.
                                                                      JMP/CR- 190/
2.Aux. Hoist Wire Rope (New Design)- Wire rope of construction 03 Alt-7
  35x7 (IWRC of special design avoiding cross over between the
  strands of the core & reducing the danger of internal rope
  destruction), compact strands, self-lubricated, rotation resistant,
  D22x130M,RGG,          Langslay,       un-galvanized         ,1960
  N/mm2,minimum breaking load 373 KN with accessories.
3.Derrick Wire Rope (New Design)- Wire rope (Left/Right) of JMP/CR- 191/
  construction 8x26 (IWRC) plastic impregnated, compact strands, 03 Alt-6
  self-lubricated, A26x390M, RGG/LGG, ordinary lay, un-
  galvanized, 1770 N/mm2, minimum breaking load 504.7 KN with
  accessories.
(*Part-I to III)
3.     Requirements:
The description, capacity, length and quantity required for different types of wire
ropes slings are indicated in annexure. All these slings shall be suitable for use on
140 Ton Ramshorn hook.
The slings shall be capable of withstanding to the tough break down operations and
shall be made as light as possible, by using alloy steel for links and hooks, so that
they can be separated to a distance of 10 to 12 meters when pulled by two or three
persons (about 100 Kg force) per leg.
4. Components:
4.1 Sigle part spliced/Endless grommet type sling legs/special draw bar sling:
4.1.1 Wire rope
a) The wire rope used in the manufacture of single part spliced sling legs shall
   consists of 6 round strands over a steel core, right hand ordinary lay, galvanized
   and shall conform to IS:2266-1977 with wire of tensile designation 1770.
b) Suitable construction of wire rope shall be selected to provide increased flexibility.
c) The safe working load shall not one-sixth of the minimum strength of wire rope
d) The wire rope shall be tested to a proof load as indicated in column 9 of annexure
4.1.2 Thimbles:
Each end of each part spliced/endless grommet type sling leg shall be fitted with a
galvanized thimble of the ordinary type conforming to IS:2315-1978, appropriate for
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                 Page 59 of 210
Maintenance & Operation Manual                                   Part I- 140 T BD Cranes
the size of the rope, and securely spliced thereto.
4.1.3 Hooks:
a) Suitable point hook of high tensile steel grade 80 ton with trapezoidal cross
   section shall be provided. The manufacturer shall submit a sketch showing all the
   dimensions of hook along with necessary strength calculations. The hook shall be
   fitted with a safety device to prevent displacement of the load.
b) The tolerances of drop-forged hooks shall be as given in IS: 3469-1974.
c) All hooks shall before proof testing, be normalized by heating to a temperature
   within 50 degree above the upper critical point of the steel used, followed by
   cooling in still air.
d) Proof testing of hook shall conform to clause 9 of IS:2759-1969.
e) Depending on the size of the lot, if considered necessary, one sample hook shall
   be selected and tested destruction by the application of test load as per procedure
   laid down in IS: 2759-1969.
f) The inspection, certificate of test and examination shall be as per clause 11 of
   IS:2759-1969.
g) The identification mark on hook shall be as indicated in IS: 2759-1969.
4.1.4 Splicing:
The splicing shall be done by mechanical means.
4.1.5 Serving:
That portion of the splice which contains the wire ends shall be neately and
                                            DRAFT
effectively served with spun yarn or sezing strand to give protection to the user in
handling.
4.2 Oblong Link:
a) A suitable suspension link of high tensile steel grade 80 (T) shall be designed to
   suite Ramshorn hook of 140 ton capacity. The manufacturer shall submit a sketch
   showing all the dimensions of oblong link along with necessary strength
   calculations.
b) The oblong link shall be normalized.
c) the tolerances on dimensions shall be as specified in IS: 2760-1980.
d) The link shall be tested to a proof load as indicated in column (8) of annexure
   before assembly. The permanent set of the link shall not exceed 1% of its mean
   breadth.
e) The procedure of testing of oblong link shall be as indicated in clause 11 of
   IS:2760-1980.
f) The identification marks on oblong link shall be as indicated in IS:2760-1980.
Note: For special draw bar slings, clauses 4.1.2, 4.1.3 and 4.2 are not applicable.
5.0 Technical Data:
The tenderer while submitting proposal shall furnish complete technical data such as
size, dimensions, rate and material of oblong link and hook separately along with
construction, size and weight of wire rope, identifying details of deviations if any.
6.0 Inspection:
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                              Page 60 of 210
Maintenance & Operation Manual                                    Part I- 140 T BD Cranes
The wire rope slings will be inspected by the authorised Railway representative
nominated by the purchasing authority at the works of the manufacturer. The
necessary facilities shall be generated by the manufacturer or carrying out inspection
and various testing of wire rope slings.
7.0 Test Certificate:
With each consignment of slings, the manufacturer shall furnish a test certificate in
the form shown in the appendix B of IS: 2762-1982.
8.0 Maintenance:
The tenderer shall furnish the maintenance manual indicating the method of
maintenance of wire rope slings, periodicity of attentions, if any, procedure of testing,
etc.
9.0 Warranty:
The suppliers will withstand warranty for a period of atleast two years from the date of
commissioning for its satisfactory performance against any design/manufacturing
defect.
10.0 Packing:
The wire rope slings shall be suitably packed to avoid damage during transit.
DRAFT
                                                                                   ANNEXURE-I
                         Ref.                                       Qty/ Proof/
S.N    Description                Type        Capacity    Length                    Load/Leg
                         Fig.                                      Crane Link
 1           2            3          4           5          6        7     8            9
                                Single part
1.0   Double leg Sling    A                    70 ton      6M       02    140 t       81.0 t
                                  spliced
                                Single part
2.0   Double leg Sling    A                    50 ton      7M       02    100 t      71.7.0 t
                                  spliced
                                Single part
3.0   Double leg Sling    A                    30 ton      7M       02    60 t        42.4 t
                                  spliced
                                Single part
4.0   Double leg Sling    A                    30 ton      5M       02    60 t        42.4 t
                                  spliced
                                 Endless
5.0   Single leg Sling    B                    70 ton      6M       04    140 t      105.4 t
                                Grommet
                                 Endless
6.0   Single leg Sling    B                    50 ton      5M       04    100 t       81.0 t
                                Grommet
      Special draw bar
7.0                       C         --         70 ton      6M       02     --         70.0 t
           sling
DRAFT
CHAPTER-2
Auxiliary Hoist
01.   Type                             : Two stage planetary hoist with spring
                                       loaded multi disc brake
02.    Rope diameter                   : 22 mm
03.    Rope speed                      : Max. 60 m/min.
04.    Hoist speed                     : Max. 15 m/min.
05.    Hook block                      : 04 strand, 25 t
06.    Hoist range                     : above track: 18.0 m
                                         Below track: 03.0 m
Slewing Gear
01.   Type: Three stage planetary hoist with spring loaded multi disc      brake,
      Roller slew ring with external teething
02.   Super structure speed            : 0-1.0 rpm
Derricking Gear
01.Type                                          : Three stage planetary hoist with
                                                 spring loaded multi disc brake
02.Rope Diameter                                 : 26 mm
03.Rope speed                                    : Max. 28 m/min.
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                               Page 69 of 210
Maintenance & Operation Manual                                        Part I- 140 T BD Cranes
04.Derricking time                                  : Approx. 165 sec.
05.Rope Tension                                     : 2 X 14 strand, 2200 KN
Counter Weight
01.03 sections
02.Slab-1(transported on the match truck)           : 24 T
03.Slab-2 (Transported on the match truck)          : 15 T
04.Slab-3 (Transported on the under carriage) : 08 T
Boom
01.Length to the main hook                          : 18.75 mts.
02.Length to the Auxiliary hook                     : 19.5 mts.
03.Main hook working range                          : 5.5 m-17.0 m
04.Auxiliary hook working range                     : 6.5 m- 18.0 m
Match Truck
01.Length beyond buffer                             : 16.0 m
02.Distance between wheel sets                      : 2.0 m
03.Track Gauge                                      : 1676 mm
04.Distance between bogie pivots                    : 11.30 m
05.Draw and Buffing Gear                            : side buffers & screw
                                                     Couplings
                                            DRAFT
       hoist
                                 Minimum - 6.5 m             Minimum - 6.5 m
  28   Range of Lift Main        Above rail level - 16.5 m   Above rail level - 17 m
       hoist
                                 Below rail level - 4 m      Below rail level - 4 m
  29   Range of Lift aux hoist   Above rail level - 17.8 m   Above rail level - 18 m
                                 Below rail level - 3 m      Below rail level - 3 m
  30   Max capacity when       130T at 6m radius (360        140T at 6m radius (360
       fully propped with heay degree) 130T at 9m radius     degree) 140T at 9.5m
       duty cwt.               (30 degree leftward &         radius (30 degree
                               rightward)                    leftward & rightward)
  31   Crane Motion and
       Speeds:
       Derricking                1 min from max to min       165 sec from max to min
                                 radius                      radius
       Slewing                   1 RPM                       1 RPM
       Main hoist lifting        2.5 m/min                   4 m/min
       Main hoist rapid          5 m/min                     8 m/min
       lowering
       Auxiliary hoist lifting   15 m/min                    15 m/min
       Auxiliary hoist rapid     30 m/min                    30 m/min
       lowering
37 Gallows
  39    Hydraulic oil tank            one single tank fitted in   one single tank fitted in
                                      the front portion of the    the rear portion of the
                                      superstructure              superstructure
  40    Fuel tank                     box shaped tank in the      box shaped tank in the
                                      centre portion of the       rear portion of the
                                      superstructure              superstructure
DRAFT
                                                      1. Match truck
2        Cowans Sheldon New              02 Nos
                                                      2. 140 T crane.
         design
         (4 propping base)
                                                      3. Match truck
3        Gottwald Old design             02 Nos
                                                      4. 140 T crane.
         (4 propping base)
                                                      5. Match truck
4        Gottwald New design             02 Nos
                                                      6. 140 T crane.
         (4 propping base)
To understand the crane and operate the crane efficiently and safely, the operating
personnel should follow the operating and maintenance manuals supplied along with
the cranes. Some salient features (included also in the manuals) which if followed will
ensure safety during operation are highlighted below:
a) Before raising the jib from match wagon, all blocking screws must be screwed
   down until locked on the top of the spring.
b) Both the relieving bogies must be unloaded prior to raising the jib from match
   wagon.
c) Before any movement of crane on its own power, operator must ensure proper
   engagement of travel clutch and braking of travel brake.
d) In the operating area, the operator should assess the cant with the jib in line with
   the track. If cant exceeds 13 mm, the crane should be leveled by using props
   before load lifting because this crane in free on rail condition is suitable only with
   counter weight on carriage. In this condition, there will be clearance in the side
   bearers.
e) The operator must be thoroughly acquainted with the load charts provided in the
   crane to assess the duty selection.
f) Special care is to be taken during propping of jacks. Packing below footsteps
   should be sound and placed, alternately, perpendicular and parallel to the track,
   to give maximum load distribution. After applying jacks, packing should be
   checked. The load should be lifted slowly just above the ground and held there.
   Packing should be checked again to see if there is any sinking.
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                               Page 81 of 210
Maintenance & Operation Manual                                     Part I- 140 T BD Cranes
g) If the crane is to be moved to another position, then the draw beam jacks should
   be raised, the footsteps removed, the draw beam retracted and locked in position
   before any movement.
h) Before any slew motion, slew lock pin must be removed.
i) Before undertaking any lifting operation, the operator must be sure that the duty
   selector of SLI is correctly set according to the configuration of the crane (i.e., free
   on rail, or blocked, counter weight on super structure or carriage, heavy ballast
   fitted etc.)
j) Extreme caution should be taken while working in super elevated track in free on
   rail condition with counter weight or heavy ballast fitted to superstructure.
k) During fitting of heavy-duty ballast to the superstructure, heavy ballast must be
   raised fully, superstructure must be brought in line with the track before
   introducing ballast arm in to the heavy ballast, and locating pins must be engaged
   in the support beam.
l) Swinging load is dangerous and should be avoided.
m) Emergency lower button should be operated only in case of emergency and the
   operation should not be part of the normal working cycle.
n) During coupling of the relieving bogies with the crane, the operator should move
   the crane close to the beam and the height and position of the beam should be
   adjusted in such a way so that the base of the beam is in line with the carriage
   end castings. This will prevent damage of the castings.
o) It is always better to lift the load from match truck end, if the derailment on the
   same track. Because in this case the operator has to lift the match truck and
                                             DRAFT
   relieving bogie clear of the track. On the ballast wagon side, the operator has to
   remove the heavy ballast first, then the ballast wagon and one relieving bogie.
a. For removing either ballast wagon or match truck, lifting beam need not to be
   used. The 30 T Double legged sling of 7 M long can be used with main hook for
   this operation.
p) To reduce timing, operating personal should practice the operation in idle time.
   Some operations may be combined to reduce timing i.e., while carrying out
   blocking out operations of screws, ‘A’ frame should be raised thus saving the time.
   Lifting of relieving bogies/ match truck / ballast wagon should be as minimum as
   possible above the rail level, before slewing.
q) Since the maximum instantaneous load on an individual prop that may arise with
   the crane being loaded to its capacity is around 150 T, it is essential to prepare
   the packing on the ground, using sleeper over wide area in order to prevent sink
   age of props. In order to reduce time taken in restoration, it is advisable to take
   the help of permanent way staff in leveling the ground and in building up of the
   base for props.
r) Please remember that when you travel on own power with load on hook the axle
   load on track is much higher than normal. Depute a person to check track for
   sinkage and gauge during travel. Insist on PWI to give good attention to track
   where necessary.
s) Before traveling the crane on own power, check the brake power. Apply brakes,
   engage travel clutch and push the travel joystick for a short time to “Full” position.
   If brakes are able to hold the crane, then the brake power is okay.
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                 Page 82 of 210
Maintenance & Operation Manual                                   Part I- 140 T BD Cranes
10.     IMPORTANT INSTRUCTIONS FOR BREAK DOWN STAFF
Following instructions must be followed by break down Incharges, Supervisors and
staff while working at accident sites: -
a. After reaching at accident site, observation of site and damaged wagons/coaches
   to be carried out to ensure safe and efficient restoration.
b. Crane driver as well as staff should be advised regarding lifting load and
   operational activities, explaining situation of spot.
c. Necessary equipments, tools, wooden packings etc. should be unloaded from
   ART without wasting time and be sent the same to the accident spot.
d. Before energizing 140T Crane on electrified section for operations, ensure that
   OHE has been made dead /slewed and secured and power block has been taken
   providing written memo.
e. Suitable and sufficient space to be created for propping and choose the wooden
   packings of required sizes, so that strong and sound propping can be ensured.
f. Lifting load must be assessed properly and crane configuration and radius to be
   determined accordingly.
g. Always take care of cant/super elevation while lifting the load.
h. Ensure that SLI is in working order.
i.   Ensure availability and understanding of load charts.
j.   Rail clamp must be used as and when required.
k. Always utilize suitable capacity chain sling and wire rope slings and insert hooks
                                            DRAFT
 e) E. Movement of ARTs to the accident spots should be given top priority and
    should not be stopped enroute. It is the responsibility of the Controlling DRM and
    his Officers that no slackness is allowed in this regard.
 f) F. ARTs should be moved to the base Depot as soon as the restoration work is
    over.
 g) G. For a minor derailment involving a few wagons, as far as possible MFDs
    should only be deployed leaving the crane at the base station in readiness to
    attend major accidents.
 h) H. Wherever road approach is available, attempt should be made to take the
    MFD equipment by road through lorry and for this purpose, departmental lorry
    should be earmarked. Wherever department lorries are not available to move
    the MFD/HRE, private lorries may be invariably hired.
 i) Wherever MFD/HRE is required to serve both BG and MG territory, arrangement
    for moving MFD/HRE by lorry is a must.
 j) Mock trials of ART should be done earnestly as prescribed to test the efficacy
    and correct any deficiency in the system.
 k) Whenever assistance of additional BD crane/MFD is required from neighboring
    division or adjacent Railways. CMPE or any other HOD of the Mechanical
    Department will do the necessary liaison.
                                     Proof Load       -       81 T
5.    Single Leg Wire Rope Sling (BS-1290)
                                     Capacity         -       70 T
                                     Requirement      -       2 Nos
                                     Length           -       4 Mtrs.
                                     Proof Load       -       140 T
6.    Four Leg Wire Rope Sling (BS-1290)
                                     Capacity         -       25 T
                                     Requirement      -       1 No.
                                     Length           -       4 Mtrs.
                                     Proof Load       -       50 T
7.    Two Leg chain Sling (BS-1290) Capacity          -       25 T
                                     Requirement      -       4 Nos.
8.    Chain Sling (Without hook)-BS-1290) Capacity    -       10 T
                                          Requirement         4 Nos.
5. Emergency Lower
5. Fire Extinguishers
3. Flushing Valves HE 4
a) HE 2A Main Pump
b) HE 2B Main Pump
c) HE 3 Main Pump
a) Main Hoist
b) Auxiliary Hoist
c) Derrick
6. Non-Return Valves
7. Lock Valves
8. Travel Differential
 4. Hauling operation should not be undertaken for more than 5.0 T. loads, because
    hauling load is not shown by SLI.
 5. Traveling operation should only be under taken when the jib is in “inline”. Limits
    of load lifting, given in the load chart, must be strictly followed.
 6. If travel clutch does not engage, then: –
 (a) Release the crane brakes and observe clutch engagement.
 (b) Operate the joystick gradually.
 7. During crane traveling, apply crane brakes for stopping the crane. Do not
    operate joystick reverse to stop the crane, because it will damage the system.
 8. Always keep sharp observation over the crane wheels during restoration.
    Information regarding lifting of any wheels to be immediately communicated to
    the crane driver. Under such conditions, lifted load must be lowered and kept
    on ground level and propping to be examined thoroughly.
 9. Speed selection should be changed only when crane is stopped completely.
 10. Do not operate full joystick until travel clutch is inserted properly.
 11. Before traveling, it must be ensured that, rail clamps have been removed, props
     removed and draw beam retracted and jib turned to “inline”
 12. Before traveling, horn must be sounded to alert the staff.
 13. Travel differential switch should be used only in slow speed operation when
     crane is unable to travel.
     get discharged.
 27. Before under taking slewing movement, observe the train movement on the
     adjacent electrically charged line. Follow the G&SR rules strictly.
      1. Check the battery ammeter. needle 1. After shutting down the main engine,
         should be in + zone                   all circuit breakers and battery isolator
                                               should be put “off”
      2.     Travel    clutch   should   be 2. Ignition key should be removed.
      disengaged.
      3. All the draw beams should be in 3. SA1 valve, brake foot pedal should be
         retracted and locked position.        locked by inserting pin.
      4. Relieving bogie-coupling pin 4. Material to be kept systematically on
         should be in inserted position.       the crane.
      5. Tie cylinders should be lowered 5. All the transition couplings of the
         completely.                           crane unit must be tightened.
      6. Derrick wire rope should not be in 6. All the FP pipes and vacuum hose
         loose position.                       pipes should be coupled. FP cocks
                                               should be opened and outer most FP
                                               cock of last vehicle should be closed.
  c) Remove the tumbler pin retaining the crane casting lever-locking pin on the
     relieving bogies.
  d) Exert a small amount of pull on the centre casting lever locking pin - at the
     same time slowly pump up (close the valve V2 and change the lever position
     P2 as shown in fig. 3) the relieving bogie jack until the locking pin slides out of
     centre casting lever.
  e) With the locking pin withdrawn, lower off the main jack slowly (change the
     lever position to P(N) and open the valve V2 as shown in fig. 3 until the
     relieving bogie frame stops raising. The above operations have to be made for
     both the bogies.
  f) Remove the slew-locking pin.
  g) Erect the 'A' frame erection switch to the raise position at the same time
     particular care should be taken to ensure the derrick rope is kept in a
     reasonably tight condition.
      NOTE: But should not cause jib bridle assembly to lift from the jib structure
      until the 'A' frame is fully erected.
  h) Derrick the jib off the match wagon trestle until the main and aux. hoist blocks
     are clear off the match wagon.
      NOTE: Both the relieving bogies must be unloaded prior to raising the jib from
      the match wagon trestle.
  i) Check the gaps (Which should be about 2 to 3 mm approx.) between both top
     and bottom locating pads RB25 and RB26 (half-moon as shown in fig.1). If
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                               Page 93 of 210
Maintenance & Operation Manual                                  Part I- 140 T BD Cranes
      required load/unload the relieving bogie a bit to achieve these gaps.
      WARNING: Do not operate the wishbone jack at all for this purpose.
  j) After gaps are found to be same take out the coupling pins. If required
     load/unload the relieving bogie a little bit during this operation also.
      Uncouple both the relieving bogies in the same way.
  k) Move the crane slowly away from either relieving bogie.
  l) The relieving bogies can now be moved to any desired position either by
     towing away in which case the hand-brakes will need to be released, or by the
     crane lifting it clear of the work area.
     brake.
  e) Using wishbone jacks of the relieving bogie jack the coupling beam (i.e., by
     hand pump with lever position (I) and valve VI open as shown in fig. 3) to align
     the same with the pockets in carriage end castings. Use turn buckle whenever
     required to align the wishbone to the carriage end casting.
  f) Release the carriage brake and move the crane very slowly to the relieving
     bogie.
      As soon as the coupling beam takes the lead of the pocket of end casting (as
      shown in fig.2) release the wishbone jack completely (i.e., by changing the
      lever position to position (2) as shown in fig. 3).
  g) Travel the crane further so that the gaps between half-moon (RB25 & RB26)
     are minimum. If necessary, load the relieving bogie a little bit as to achieve a
     gap of 2 to 3 mm approx. in both top and bottom half-moons (as shown in fig.).
      WARNING: In no case should there be any sort of loading on wishbone jack
      after coupling beam has taken the lead of end casting pocket. This might
      damage the wishbone cylinder.
  h) Engage the hydraulic coupling pins to lock the relieving bogie to the carriage.
     If required relieving bogies may have to load/unload during this operation.
  i) Slew the superstructure in line to engage the slew lock pin.
  j) Derrick the jib down onto the match wagon trestle by pressing the override
     switch. Slacken the derrick rope and lower 'A' frame until 'A' frame collapsed.
    and fuel supply goes to the main engine. Solenoid IS-1 gets electrical supply
    through 2DI (Low water timer relay) close interlock 8-9, 2D2 (Engine low lube oil
    pressure timer relay) NCI (9-10) and 2D3 (Engine over speed relay) NCI (10-
    11).
    Further when ES-1 switch is kept on position No 2 (Start), solenoid coil gets
    battery positive supply through wire No 7 and solenoid gets energized. On
    energizing solenoid, self-starter bandex couples with the gear of main engine
    and supply of battery goes to the self-starter through solenoid contactor, which
    in turn rotates the self-starter for starting the main engine.
    After starting the main engines, ES-1 (Engine starting switch) is released and it
    automatically gets run position. As soon as ES-1 comes to "Run" position, self-
    starter stops rotation.
      One 2K-1 contactor is provided in starting circuit of main engine. Normally close
      inter lock (5-36) of this contactor controls closing and opening of these high-
      power circuits i.e., Ventilator motor, floodlights and hydraulic circuits.
 a)   Cab Ventilation Fan (M3): The cab ventilation fan is provided in the driver’s
      cabin to exhaust the air from cabin to atmosphere. It is operated by E-8, 5
      Amps Circuit breaker through Wire No.37.
 b)   Jib Floodlight (H-11): Jib floodlight is provided in the mid portion of the jib of
      140 T Crane for providing required illumination level during load lifting at
      accident site. Floodlight is a 150 W, 24 V halogen lamp which is controlled by
      E-9 circuit breaker of 10 Amps rating through Wire No.38.
 c)   Front floodlight (H-12): These lamps are provided on the front side of crane
      super structure at right and left side and works as headlights on the crane.
      These are the halogen lamps of 150 W, 24 V rating which can be operated by
      circuit breaker E-10 of 15 Amps rating through Wire No.39.
 d)   Rear floodlight(13): This headlight is provided in the A- Frame Section of the
      Crane (tail of the super structure) to provide illumination in the Rear side. This is
      also halogen lamp of 70 W, 24 V rating which is operated by E-11 circuit breaker
      of 5 Amps rating through Wire No.40.
 e)   Hydraulic Control Circuit Breaker (E-12): This is main circuit breaker of 15
      Amps rating which provides electrical supply to all electro hydraulic circuit
      breakers of crane through Wire No.41.
 a)     The crane must not be used to lift more than the maximum safe working load
        authorized at the radius.
 b)     Precautions should be taken to avoid load catching on obstructions as this
        may seriously overload the crane.
 c)     Sudden shocks and jerks also tend to overload the cranes and tackles.
 d)     Shocks and jerks usually result from:
 i.     Mistake in signaling to the crane driver.
 ii.    Want of observation by the crane driver.
 iii.   Sudden application of brakes on crane.
 iv.    Kinks in the chains.
 v.     Slipping of chain due to incorrect slinging or sling hooks not
 vi.    properly secured
 e)     05.Lifting tackles i.e., hoisting chains, lifting chains, sling chains and wire
        ropes should be of suitable capacity.
d) On 140 T Crane, make the locations and lubricants with grade wise to be used for
   lubrication have been suggested by the manufacturer. The manufacturers
   recommendations for lubrication should be strictly followed
2.30
LIST OF THE IMPORTANT MATERIAL FOR CRANE SPL.
On ordering of Crane Special, following material should be kept in Staff Van before
departure from Crane siding/Shed.
                                        Description      of     the NOS.
                                        material
                                          Walkie Talkie Sets             04 Nos.
                                          Mega Phone                     02 Nos.
                                          Walkie Talkie Charger          01 No.
                                 2+2      Gas Patromax                   02+02 Nos.
                                          Torch Three Cell               04 Nos.
                                          Signal Torch                   01 No.
                                          Measuring Tap                  01 No.
                                          Helmate (Hard hate)            04 Nos.
                                          Helmate Staff                  20 Nos.
                                          Bed Sheets                     08 Nos.
                                          Pillows                        05 Nos.
                                          Blankets (Supervisor)          08 Nos.
                                          Blankets (Staff)               20 Nos.
                                          Red and Green Flags            02 Nos.
                                          Water Buckets                  01 Nos.
                                          First Aid Box                  01 Nos.
                                 1+1+1    Memo Book and Pad, Stamp       1+1+1 No.
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                             Page 101 of 210
Maintenance & Operation Manual                                           Part I- 140 T BD Cranes
                                                Detention form                      04 Nos.
                                                Umbrellas                           04 Nos.
                                                Pain Relief Spray                   02 Nos.
                                                Spray Pump for cleaning of eye      01 No.
                                                Hyd. Hand Pump Unit                 01 No.
                                                30/60 Te. Jacks                     02 Nos.
                                                120/60 Te. Jack                     01 No.
                                                Displacing Jack                     01 No.
                                                Roller Carriage                     01 No.
                                                Re-railing Bridge                   01 No.
                                                Counter Support                     01 No.
                                                High Pressure Hoses                 03 Nos.
                                                3/2.5Kva Cap. Generator             01 No.
                                                Halogen Lamp                        02 Nos.
                                                Elect. Switch Board                 01 No.
                                                Elect. Extension Board              01 No.
                                                Wrench Bar                          02 Nos.
                                                Punje                               02 Nos.
                                                Video Camera                        01 No.
                                                Kitchen Material                    01 Set
PROPPING ARRANGEMENT
DRAFT
  8   However, in case only one trolley has derailed, the locomotive can
      be re-railed with the help of one crane from derailed trolley side. or
      otherwise also if the loco is not capsized, keeping the one end of it
      on the ground other end can be re-railed or tackled cautiously with
      the help of one crane provided it is free from any entanglement.
DRAFT
 11   WDG-4 locomotives can be tackled with draw bar wire ropes as the
      buffer plate holes are not provided in this loco.
DRAFT
 14   Any accident stock lying very far from the reach of the crane, can
      be brought closer in the reach with the help of HRE.
 15   In case bogie has cracked or damaged to an extent that lowering
      on that may not be safe, spare dummy bogie should be arranged
      from the nearest loco shed.       DRAFT
 16   Uncoupling of Bogies
      In situations where it is needed to uncouple the bogies and run out
      as in above case , air brake pipe connections, TM cable
      connection, Centre Pivot cotter and other connections between
      bogie and chasis needs to be disconnected.Other such coonectios
      are listed as below-
           Axle Generator cable
           Speedometer cable
           Bolster Pin etc
C- Procedure in Practice:
DRAFT
      1. JCB/Poclain machines can also be deployed in case of earth work required for
         filling the deep area as well as for making good the embankment side slopes
         for laying the restored track.
         After assessment of the accident site, if the coaches found tilted infringing
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                Page 112 of 210
Maintenance & Operation Manual                                 Part I- 140 T BD Cranes
  track, the coaches may be Pushed/pulled out by JCB/Poclain Machine maintaining
  safe distance between JCB & damaged coach. For faster clearance of the track, 3-
  4 JCB/Poclain Machines or more may also be deployed for pushing/pulling for
  shifting    it  out   of   the    track.
DRAFT
DRAFT
DRAFT
DRAFT
                             Coach is
                             positioned to
                             leave space
                             for crane
                             movement.                    Crane is
                                                          moved to
                                  1            2          tackle farther
       In single line section the trolley of the coach in end.
                                                           farther side of the
       crane may be re-railed, keeping the coach body still diagonal to the
       crane jib.
                                       This end will be re-railed first.
DRAFT
                     3
       Now the trolley near to the crane will be tackled and re-railed in such
       a manner that coach will move far from the crane rolling on the first
       re-railed trolley to avoid hitting with crane.
       4
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                  Page 117 of 210
Maintenance & Operation Manual                                    Part I- 140 T BD Cranes
 21    Re     railing    of    coaches            in   Single   Line   Section
         (Capsized/Damaged Coaches)
         In case the capsized or damaged coach is lying on the track, it
         should be placed perpendicular or diagonal to the jib and then
         thrown off the track.
  22     Re railing Salvageable LHB coaches on same track
         It is advisable to use two cranes in case an LHB coach is to be re-
         railed on the same track.
  23     Use of Rail skates
         Rail skates can be used in case of axle box bearing damage or for
         any other reason due to which the wheel cannot travel.
DRAFT
(C)     EMU/MEMU/DEMU
        Restoration of derailed EMU/MEMU/DEMU.
      A- Preparation Chart :
 S.N.  Item/Status                               Action
  01 OHE                              To be slewed towards coach movement
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                               Page 118 of 210
Maintenance & Operation Manual                                 Part I- 140 T BD Cranes
                                        and ensure that OHE of adjacent line has
                                        been made dead.
 02     Condition of props and Full propping to be done and 04 staff on
        availability of staff           each prop should be deputed.
 03     Suitable packing and its Wooden packing of size 4’x2’x14” and
        size                            6’x1’x12”
 04     Position of SLI duty selector To be kept on No. 1
 05     Wire rope Sling and SWL         30 Te. 5 Mtrs sling and 70 Te. SWL as per
                                        requirement.
 06     Chain       sling     as   per 25 Te. Capacity chain sling
        requirement
 07     Position of Cant of the track Should not be more than 140 mm
 08     Position of SLI                 SLI should be kept in working.
 09     Maximum working radius          13 meters by main hook.
 10     Place where sling to be (under frame) Solbar
        inserted
 11     Gas cutting equipment           DA and Oxygen gas with equipment
 12     Availability      of    wooden 04 wooden wedges
        wedges
 13     Position of coach trolley       Lashing chain to be used for securing with
                                        structure.
 14     Lighting arrangement            To be arranged during dark/night.
 15     Observation for suitable Analyze suitable place for 360º slewing and
        place                           placing the coach/damaged trolley.
 16     Arrangement of rope for 02 Nos. in sufficient length at both the ends
        coach adjustment                of coach.
                                          DRAFT
DRAFT
       Apart from above these stocks are similar to Coaches. Hence for the
  9    methods of handling these stocks in double/single line sections in different
       conditions see the chapter ‘COACHES’.
 10    For    uncoupling    of    shaku
       coupler, help of locomotive for
       pulling of rake may be taken. In
       case of non-availability of loco,
       the uncoupling may be done by
       providing hydraulic jack under
       the shaku coupler & taking
       precautions mentioned in earlier
       para.
(D)       WAGONS
a)        Restoration of Loaded BCN/BOX-N by 140 T. Crane
A-Preparation Chart :
DRAFT
Center sill
DRAFT
  14    BOX N HL
        For stainless steel wagons like BOX N HL, for body
        cutting, plasma cutting machine or abrasive cutter should
        be used.
  15    BOBYN & BOBRN wagons
        In case CBC has got damaged, hooks can be fixed to the
        draft gear housing.
7. Now, turned wagon can be kept anywhere at 360° within 18 meters radius.
8. Remember that trolleys should not be kept in the coupled position during toppling
   operation. Both trolleys should be removed in the beginning.
Basic Assessment in Handling the Wagons:
The critical factor in handling loaded wagons is not the length but its tonnage.
a) Loaded wagons should be unloaded first before throwing off track as it may not
   be safe to lift loaded wagons or due to beyond reach of the crane.
b) During lifting of any wagon stock fitted with CASNUB bogie, it should be ensured
   that centre pivot U-shackle lock is intact and side frame key of all wheels are intact
   otherwise bogie and wheels must be secured with chains to avoid detaching of the
   bogie from wagon during lifting.
DRAFT
BOX N HL Wagon
i) For stainless steel wagons like BOXN HL, for body cutting, plasma cutting
   machine or abrasive cutter should be used.
DRAFT
DRAFT
 07.     Position of Cant on the track Should not be more than 140 mm
 08.     Position of SLI               SLI should be kept in working.
 09.     Maximum working radius        In empty, 16 meters by main hook and 19
                                       mtrs. By Aux. hook.
 10.     Place, where sling to be Under frame barrel bracket
         inserted
 11.     Position of wagon trolley     Lashing chains to be used for securing with
                                       structure.
 12.     Lighting arrangement          To be arranged during night/dark.
 13.     Observation for suitable Analyze suitable place for 360º slewing and
         place                         placing of wagons.
 14.     Arrangement of rope for 02 Nos. in sufficient length at both the ends
         tank wagon adjustment         of tank.
 15.     Availability of Megaphone/    One person should be deputed with
         Communication                 equipments
 16.     Photography/Vide0ography Videography of all critical operations and
                                       clues collections.
 17.     Average per oil tank timing Average – 55 minutes
         for restoration
      B- Procedure in Practice :
Generally, it is observed that after derailment of oil tank wagons, they catch fire,
which in turn results internal explosions. In this situation, it is not possible to rerail the
BTPN by MFD/LUKAS equipment because machine and breakdown staff may
sustain injuries due to explosions.
DRAFT
A-Preparation Chart:
 S.N.    Item/Status                                  Action
  01 OHE                                Working line OHE to be slewed. OHE of
                                        adjacent line to be made dead.
  02      Condition of props and All props to be prepared and 04 staff on
          availability of staff         each prop should be deputed.
  03      Suitable packing and its size Wooden packing of size 4’x2’x14”/
                                        6’x1’x12”
  04      Position of SLI duty selector To be kept on No. 1
  05      Wire rope sling and SWL       Only 30 T 5 Mtrs wire rope sling
  06      Chain sling                   25 T Capacity chain sling
  07      Position of Cant of the track Should not be more than 140 mm
  08      Position of SLI               SLI should be kept in working.
  09      Maximum working radius        11 meters by main hook and 19 mtrs. By
                                        Aux. hook.
  10      Place, where sling to be Barrel bracket/ Body bracket
          inserted
  11      Gas cutting equipment         DA and Oxygen gas with equipment
  12      Availability of wooden wedges 04 wooden wedges
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                            Page 131 of 210
Maintenance & Operation Manual                                     Part I- 140 T BD Cranes
  13        Position of wagon trolley      Lashing chain to be used for securing
                                           with structure.
  14        Lighting arrangement           To be arranged during night/dark.
  15        Observation for suitable place Analyze suitable place for 360º slewing
                                           and placing of wagons.
  16        Arrangement of rope for 02 Nos. in sufficient length at both the
            brake van adjustment           ends of BVZI.
  17        Availability of Megaphone/ One person should be deputed with
            Communication                  equipment
  18        Photography/Videography        Videography of all critical operations and
                                           clues collections.
  19        Average timing for per wagon Average – 35 minutes
            restoration
B- Procedure in Practice:
01.     Energize the crane, attach counter weight, move towards derailed
        vehicle, establish the crane and ensure full propping.
02.     For BVZI guard brake van: use 30 T 5 mtrs wire rope sling and insert
        hook in the barrel bracket/body bracket.
03.     Initiate lifting operation and place wagon anywhere at 360º within 11
        meters radius.
04.     For light weight brake van, use Aux. Hook with 25 T. Chain sling, lift the job
        and place within the range of 18 meters radius.
(G)     Restoration of Hot Axle/Cold Axle broken Wagons
                                              DRAFT
Preparation Chart:
      S.N.           Item/Status                            Action
       01       MFD/LUKAS power pack Two jacks of 120/60 T Cap. and
                and 120/60 T Cap. Jacks displacing jacks.
                with control table and hoses
       02       Suitable packing and its size Wooden packing of size 3’x1’x6”/
                                               3’x2’x6” and 04 iron plates.
       03       Availability of Lashing chains 03 Lashing chains to be used for
                and bolts                      securing with structure.
       04       Availability     of    wooden 04 wooden wedges
                wedges
       05       Rail skates trolley            02 trolleys with 36/40 mm spanner
    7      The slings should be kept tight while erection of FOBs i.e., the
           load should not be released before final assembly because it is
           required to be maneuvered for assembly. Also, once the hook
           has dis-engaged it is difficult to engage it again at height.
C- Procedure in Practice:
1. The slings should be kept tight while erection of FOBs i.e., the load should not be
   released before final assembly because it is required to be manoeuvred for
   assembly. Instead of wire rope, Chain sling is generally used.
2. Also, once the hook is disengaged it is difficult to engage it again at height.
3. When working in a situation where there is platform on the one side of the crane
   the accessibility of the propping lever of that side should be ensured.
4. Role of Manila Rope is very important in this type of activity.
  A-Preparation Chart:
 S.N.    Item/Status                                  Action
  01 OHE                              Working line OHE to be slewed. OHE of
                                      adjacent line to be made dead.
  02   Condition of props and All props to be prepared and 04 staff on
       availability of staff          each prop should be deputed.
  03   Suitable packing and its size  Wooden packing of size 4’x2’x14”/ 6’x1’x12”
  04   Position of SLI duty selector  To be kept on No. 1
                                        DRAFT
  05   Wire rope sling and SWL        30 T 5 Mtrs or 50 T wire rope sling be used
  06   Chain sling                    25 T Capacity chain sling be used
  07   Position of Cant of the track  Should not be more than 140 mm
  08   Position of SLI                SLI should be kept in working.
  09   Maximum working radius         11 meters by main hook and 19 mtrs. By
                                      Aux. hook as per load chart.
  10   Place, where sling to be As per Engineering dept.
       inserted
  11   Gas cutting equipment          DA and Oxygen gas with equipment
  12   Availability of wooden wedges 04 wooden wedges for crane
  13   Position of Girders            Lashing chain to be used for securing with
                                      structure, Use Manila rope diagonally to
                                      arrest hanging load.
  14   Lighting arrangement           To be arranged during night/dark.
  15   Observation for suitable place Analyze suitable place for 360º slewing and
                                      placing of Girders.
  16   Arrangement of rope for 02 Nos. in sufficient length at both the ends
       Girder adjustment              of Girder.
  17   Availability of Megaphone/ One person should be deputed with
       Communication                  equipment
  18   Photography/Videography        Videography of all critical operations and
                                      clues collections.
  19   Average timing for per Girder Average – minutes
       launching
B- Restoration Plan:
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                         Page 135 of 210
Maintenance & Operation Manual                                Part I- 140 T BD Cranes
  1    Observation of site and load conditions
       Before starting the rigging of the crane check
        Tonnage and dimension of the load to be lifted
        Required radius
        Hook height, slewing range, space for travelling with load if needed etc.
       Then tackle in conformity with the load chart and propping condition.
  2    Axle blocking – Carry out Axle Blocking (for the method of Axle Blocking
       see P-91)
  3    Boom erection – for things to ensure before boom erection see P- 92-94
  4    Do the propping of the crane – detailed instructions given at P- 95-97
  5    Select the counterweight as per load chart - detailed instructions given
       at P-98-100
  6    Operation can now be started following Operating Precautions given at P-
       101-104 and General Precautions for handling of loads given at P-105.
  7    Joint inspection between the involved departments viz.
       Mechanical, Engineering, S&T and TRD should be done as
       per Railway Board’s instruction for site verification /
       obstruction if any / location of propping base for crane /
       assessment of time etc. Prior permission from HQ to be
       obtained by presenting copy of DCN notice along with joint
       note.
  8    Propping base should be prepared before ordering of crane,
       also strength of propping base should be adjudged properly
       before starting the work. It may be required to make
       temporary propping base with engineering cribs etc.
  9
                                         DRAFT
 12    Single Crane
       If one crane is working, the launching / replacing of Girders
       should be started from the farthest end from the crane in case
       multiple spans are to be tackled.
                                                      Temporary
                                                      staging for prop
                                                      base
C- Procedure in Practice:
  1. Joint inspection between the involved departments viz. Mechanical,
     Engineering, S&T and TRD should be done as per Railway Board’s
     instruction for site verification / obstruction if any / location of propping base
     for crane / assessment of time etc.
  2. Propping base should be prepared before ordering of crane, also strength of
     propping base should be adjudged properly before starting the work. It may
     be required to make temporary propping base with engineering cribs etc.
  3. Props by temporary staging should be visible during crane operation
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                Page 137 of 210
Maintenance & Operation Manual                                    Part I- 140 T BD Cranes
   4. Before commencement of the work, a certificate should be obtained from
      Engineer In-charge or SSE/P-Way/Works that the Girder is safe for
      movement of the crane and temporary propping base is safe for propping.
   5. The Steel Girder should be tackled with the help of suitable wire rope slings
      by wrapping around the main boom of the Girder
 2.37 TRACK WITH SUPER ELEVATION
  1     Extreme caution should be taken while working in super elevated
        track.
  2     After propping the crane leveling of the crane should be doubly
        ensured.
  3     The crane should slew with load towards cant rail side i.e. higher
        ground level side preferably as a measure of safety to the crane.
  4     While de-rigging the crane, If supe
        r elevation is more and axles are floating too much above the
        track, while lowering the props derailment of crane trolley may
        occur. Hence it is better to break the axle blocking in such cases.
NOTE: When the crane works free-on-wheels in elevated curves of 40 mm or higher,
the attached loads must be secured against pendulous swinging by means of the
recovery winch or an auxiliary rope designed for the loading - as otherwise the
standing stability of the crane is endangered - Danger of accidents !
DRAFT
 NOTE: When it is required to be work on Free on Rail, It is only permitted when the
3rd counter weight (8t) is lying on the under carriage (frame mechanism is folded in!)
in opposite direction to working position – otherwise the crane stability will be reduced
– Danger of accidents!
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                              Page 138 of 210
Maintenance & Operation Manual                                   Part I- 140 T BD Cranes
(J) TUNNELS
DRAFT
      Restoration Plan :
      1    Match truck should be reversed before reaching the site, as it
           cannot be reversed in Cutting sections before the tunnels.
          see P- 91)
  3       Boom erection – for things to ensure before boom erection see P- 92-94
  4       Do the propping of the crane – detailed instructions given at P-95-97 On
          bridges temporary staging would be necessary for propping.
  5       Select the counter weight as per load chart - detailed instructions given
          at P-98-100
  6       Operation can now be started following Operating Precautions given at P-
          101-104 and General Precautions for handling of loads given at P-105.
  7       Since lifting capacity of the crane on free on
          wheel is very limited accident involved stock
          should be tackled by 140T crane in prop
          condition for that temporary staging for propping
          should be made.
  8       While working on Bridges in high current, safety
          precaution like life jacket etc. must be taken by
          staff working at vulnerable locations.
          RESCUE PLATFORM
 1        Collapsible type rescue platform can be used for rescue of entrapped
          passenger. 25 T chain sling should be used for lifting of Rescue platform
          by 140T crane.
    6    Check for Hyd. Oil, Fuel Oil, Engine Lube oil, Radiator
         water level, and grease in grease cups of both Relieving
         Bogies and Oil level in all the gearboxes.
    7    Do not run engine in low oil level.
AXLE BLOCKING
(Gottwald Crane)
   1    Ensure all
        Blocking Screws
        are locked onto
        the springs.
   2    Unload both
        Relieving
        Bogies.
   2     Engage
         blocking pads
         before raising
         the Jib                 Lower Axle Blocking
                                 jacks to lock top of the   Engage Blocking Pads
                                 spring.
   3     Ensure engagement of the travelling gear if required.
BOOM ERECTION
(Gottwald New & Old Crane)
    1    Before energizing 140T Crane on
         electrified section for operations,
         ensure that OHE has been made
         dead/slewed and secured and
         power block has been taken under
         written memo.                              DRAFT
BOOM ERECTION
(Cowans Sheldon Old Crane)
   1    Before      energizing
        140T      Crane     on
        electrified section for
        operations, ensure
        that OHE has been
        made dead/slewed
        and secured and
        power block has                    DRAFT
DRAFT
BOOM ERECTION
(Cowan Sheldon New Crane)
    1    Before     energizing     140T
         Crane on electrified section
         for operations, ensure that
         OHE     has     been     made
         dead/slewed and secured and
         power block has been taken
         under written memo.
    2    Check for “A” frame fully lifted.
                         Rail clip MG
                         BD Crane
                         Rail clip BG BD
                         Crane
      indication of
      sinking.
  2   When working
      in propped
      condition-
      Relieve
      Laminated
      Springs of
      weight of the
      crane.
                                      Rail clip MG BD
                                      Crane
                                          Rail clip BG BD
                                          Crane
3 Ensure DRAFT
         counterweight
         (CWT) is
         correctly locked.
OPERATING PRECAUTIONS
(Gottwald Crane)
    1    Do proper selection of lifting tackles (Chain & Wire
         rope sling).
    2 Neither lift Match Truck nor slew in Free on Rail
         condition.
    3    Avoid jerk during operation. Pendulum motion of
         load is dangerous.
    4    Don’t pull the load diagonally.
OPERATING PRECAUTIONS
(Cowans Sheldon New Crane)
    1    Ensure Safe Load Indicator
         (SLI) is in working condition.
         Set Safe Load Indicator (SLI)
         to Main
         Hoist (M.H.) or Auxiliary Hoist
         (A.H.) position as per
         requirement.
DRAFT
         disengage      from
         load easily if fixed
         directly with the
         sole bar.
    2    The toppling should be avoided where there is a
         deep ditch or trench adjacent to the track as there
         will be tendency to topple suddenly that may cause
         jerking in the crane or even toppling.
    3    While a load is
         being lifted it
         should        be
         guided        by
         attaching ropes
         on     diagonally
         opposite sides
         held by staff      Rope attached
         cautiously,   to   for guiding the
         avoid pendulum     load
         like motion.
    4    The load should be lifted slowly just above the
         ground level and held for some time to avoid
         swinging.
DRAFT
     5    Remove 32 T CW and
          place at nominated
          location on Ballast Wagon.
     8    Disengage traveling
          Clutches.
DRAFT
DRAFT
           stock.
     8     Ropes should be used for guiding the lifted loads.
DRAFT
14 24 24 20 9 23400
Crane Fully Propped 12.34 x 5.00 Mtrs FREE ON RAIL (FOR) 0- 140 mm SE MATCH TRUCK
Standard duty CWT Heavy duty CWT Heavy Duty CWT With No CWT 10 Degree
                                                                                                                FORWARD
                                 5
  15      9       23    24.5     58   25   26.5   25    67    25              31    25                                                             2     15        28000
                               51.
  16     10       21     22           25   24     25    60    25              28    25                                                             1.5   16        25000
                                 5
  17     11              20           25          25*         25                    25                                                             1
                 Crane Fully Propped 12.76 x 3.40 Mtrs                              Special DUTY CRANE- FREE ON RAIL (FOR)
           Outrea      Standard duty CWT               Heavy duty CWT              0 to 50 mm SE                         0 to 140 mm SE
 Radius
            ch in
 in Mtrs            360 degrees   30 degrees    360 degrees     30 degrees              360 degrees                       360 degrees
            Mtrs
                     MH     AH    MH    AH      MH       AH    MH            AH   MH            AH                MH                     AH
   5.5               73           140            83            140                21                              17.5
   12        6       21.5   23    52       25    25       25    61   DRAFT
                                                                             25   4.3*          5.3               3.4*                   4.4
CHAPTER-3
 TECHNICAL DESCRIPTION OF
   GOTTWALD 140 T BREAK
       DOWN CRANE
                                   DRAFT
                                                   500 mm
 18      Free-on-wheels base                       7.5 m x 1.7 m
 19      Maximum wheel force                       350 kN
 Travel Gear
 20      Driven Wheel Sets on each                 1
         bogie
 21      Speed                                     20 kmph
 Diesel Engine
 22      Type                                      6-Cylinders in Series, water cooled
 23      Model                                     Make-Cummins
                                                   (i) NTA 855 P335
                                                   (ii) NTA 855 LBC
                                                   (iii) QSL-9
                                                   Make- MTU
                                                   (iv) OM 926 LA
 24     Out put                                    205 kW at 1800 rpm
 25     Torque                                     1158 Nm at 1400 rpm
 26     Fuel tank capacity                         900 lts.
 27     Generator                                  28 Volt, 55 Amps
 Emergency Diesel Engine
 28     Type                                       2-Cylinders in series, air cooled
 29     Model                                      Kirloskar HA-294
 30     Out put                                    16.9 kW at 1800 rpm
 Main Hoist
 31     Rope Diameter                              26 mm
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                                     Page 168 of 210
Maintenance & Operation Manual                                       Part I- 140 T BD Cranes
                                                              B.-(iv) OM 926 LA
      Mounting                   Horizontal                   Vertical
      Horse power                (i) 320HP                         (i)270HP,
                                 (ii) 326HP                        (ii) 290HP,
                                                                  (iii) 305HP,
                                                                  (iv) 311HP
      No of cylinder             6                            6
      Bore & stroke (mm)         140 X 152                    140 X 152
      Compression ratio          14.1:1                       14.1:1
      Lube oil sump              28.2 liters                  43 liters
      capacity
      RPM                        2100                         1800
      Fuel tank capacity         1000 liters                  900 liters
 33   Aux. Diesel Engine:
      Make                       Kirlosker                    Kirlosker
      Type/Model                 HA 294                       HA 294
      Horse power                23HP (16.9 KW)               23HP (16.9 KW)
      RPM                        1800                         1800
 34   Brakes crane               Air brake, & Parking         Air brake & Parking brake
                                 brake (disc type)
                                               DRAFT
                                                              (disc type)
 35   Brakes match truck         Air brake, Mechanical        Air brake Mechanical hand
                                 hand brake                   brake
      Other details:
 36   'A' frame                  available                    Rear Section
       Hoists                     separate lever for main   single joystick for main and
                                  and auxiliary hoists      auxiliary hoists
       Rapid motion switch        foot operated             switch on the top of joystick
                                                            for hoist operation
       Max. Travelling speed      100 kmph                  100 kmph
       in "In Train" formation
supply from dash board and negative supply from crane body. The self-start motor
pinion gets energized by power supply of magnetic switch and starts running by
meshing to main engine flywheel gear. On running of main engine, charging
indication is found by fluctuation of indicator in the Ammeter fitted with dash board in
front of operator. When alternator power supply is ok then crane must not be shut
down by put off main engine isolating switch.
5.     BATTERY OPERATED ELECTRICAL CIRCUITES.
1. Socket: 4 Lamp sockets of 24 Volt DC supply have been provided with the 140 T
crane. One socket above the battery stand, second at the rear section, third in the
driver cabin and fourth near to machinery room light is provided. These are denoted
by 7x30,7x31,7x32 and 7x33.
2. Cab Light: It is a CFL, 11-watt 24 volt mounted on the roof of driver cabin. It is
provided for illumination in the driver cabin. Its circuits are controlled by MCB, 7F02.5,
16 AMP. It has been denoted by (14E220).
3. Front wiper motor (M2) - Front wiper motor is a two-pole permanent magnet DC
motor. one small gearbox is mounted on the shaft of this motor. It operates the
windscreen wiper, which cleans look out glass of the crane during rainy season. Its
circuit is controlled by MCB, 7F02.4, 16 AMP. It has been denoted by (14E41). The
roof wiper motor is fitted with roof glass. It has been denoted by (14E42).
4. Slew Circuit: Slew solenoid valve (in two nos.) has denoted by (15Y112 &
15Y122). Slew left Ckt is controlled by Relay 19 K21 having circuit group (15x21.7).
Slew Right Ckt. is controlled by Relay 19 K11 having circuit group (15x21.8). It is also
controlled by MCB, 7F02.6, 16Amp. When slewing is not functioning then it can be
 IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                               Page 173 of 210
Maintenance & Operation Manual                                   Part I- 140 T BD Cranes
fed power supply by circuit group (15x21.1). Because on running position of crane,
power supply is always available at connector point 1 of group (15x21). It is only for
emergency work with the crane on temporary basis.
5. Toggle Switch: It is fitted with Aux. Engine Panel. It is for interlocking system. It
means one engine will be in operation in one time.
a)    Engine Machinery House light: For better illumination in the engine house,
two lamps of 40 watts and 24-volt rating are provided inside the engine machinery
house. One of them is provided at near the auxiliary engine and another on other
side of machinery house. the pump compartment. These lamps are controlled by
MCB, 7F02.5, 16 Amp. It has denoted by (14E221 & 14E222) having Ckt. group
(14x21.10).
Note: Above circuits come in function only when battery isolator is put "ON" while
engine is in shut down condition
6.    DASH BOARD GAUGE & INDICATOR ELECT. CIRCUITS OF
      140 T (OLD DESIGN GOTTWALD CRANE)
Main engine running position
Different types of gauges are provided on 140 T Crane to check the system pressure of
fuel system, water-cooling system, engine lube oil system and hydraulic system. Apart
from this, jib light and front & rear crane head light circuit is also explained in this
chapter.
a)    Battery Ammeter: Ammeter is provided on the dash board in driver cabin and it
      gets supply from battery for charging indication purpose. Under shut down
      position of main engine, when any circuit breaker is kept on, this ammeter
                                           DRAFT
      temperature of engine lube oil product and sends indication to the gauge
      according to rise in temperature through Wire No.11. It has range between 82
      deg. to 107 deg.C.
 f)   Hydraulic Oil Temperature Gauge : This gauge is also provided in the driver’s
      cabin, which shows temperature of hydraulic oil. It gets electrical supply from
      Wire No.8. One sensor similar to thermo coupler is provided in the hydraulic
      tank, which absorbs rise and decrease of temperature and sends the same to
      the gauge.
 h)   Engine Hour Meter Gauge : This gauge is provided to show the running of
      engine in hours as well as recording of the same. It is an electrically operated
      gauge, which gets electrical supply from group (7x21.4). During running
      condition of main engine, it starts showing that how many hours engine has
      worked with cumulative recording in hours.
 7.   ELECTRICAL CIRCUIT OF 140T GOTTWALD (OLD DESIGN
      CRANE)
 These circuits work only in main engine running condition and electrical supply is fed
 to the circuit by the alternator.
 One ignition switch is provided in starting circuit of main engine. Normally one push
 button start switch for starting and one push button stop switch is provided for engine
 starting and stopping.
 a)   Cab Ventilation Fan: The cab ventilation fan is provided in the driver cabin to
      exhaust the air from cabin to atmosphere. It is operated by MCB F02.4, 16
      Amps. It is denoted by 14E-91 and 14E-92. One is left side and another on right
                                            DRAFT
 Note: Engine RPM should not be less than 1500, when floodlight and head light are
     being used.
 8.   STARTING CIRCUIT OF 140T GOTTWALD CRANE (NEW
      DESIGN) FOR CUMMINS ENGINE NTA 855 P 335 & NTA 855
      LBC
 One No. of battery box is provided in between Driver Cabin & Superstructure in
 which two batteries of 12 Volt, 150/180 Amps rating have been provided. These
 batteries feed 24 Volt DC supply to the starting the main engine. One 24 Volt, 60
 Amp Alternator is provided to charge these batteries as well as power supply to
 electrical accessories having electrical items of Crane itself, SLI system & CCTV
 Webcam system.
 Alternator is given drive through V-belt over coupling of main engine. The alternator
 generating voltage is 24 V on idle position & 28 V on full speed of the main engine.
 When battery isolation switch in put on at battery stand, the power supply of battery
 goes to magnetic switch. Further, this magnetic switch supplies electrical power to
 self-starting motor. As the negative terminal of the battery is connected to the crane
 body, negative charge is always available in the crane body. Positive power supply
 comes from batteries via dashboard Ammeter circuit. Again, when main engine
 ignition switch is pressed from ‘’OFF” to ‘’ON’’, the engine fuel solenoid gets
 positive power supply from dashboard & negative supply from crane body. A fluid
 level switch is provided with engine Radiator for engine safety. As soon as engine
 ignition switch is pressed from ‘’ON’’ to ‘’Start’’ , the self-start motor pinion gets
 energized by power supply of magnetic switch & self pinion shifts & starts running
 by meshing to main engine flywheel gear. On running of main engine charging
                                          DRAFT
      prior to commencing work. He must watch the condition of the crane for any
      visible defects.
 b)   He must see to it and ensure that the power to the overhead lines is switched
      off prior to commencing work on the crane.
 c)   When he notices any defects which could be dangerous for operating safety,
      he must stop crane operation.
 d)   He must report any defects on the crane to the supervisor responsible and to
      his replacement on shift change.
 e)   He must ensure that all the controls are brought in to neutral or idling position
      prior to supplying power to the drive assemblies.
 f)   He must ensure that all the controls are brought in to neutral or idling position
      and that the power is shut off prior to exiting the control stand.
 g)   He must ensure that the crane is parked safely according to regulations when
      crane operating and crane travel operation have been completed.
 h)   He must check whether the safety equipment such as the hoist height and
      swing-out section limits must be activated prior to commencing crane
      operation.
 i)   If the crane operator cannot observe the load during all crane motions or the
      lifting gear when there is no load is on the hooks, he may only operate the
      crane based on the instructions of a banks man.
 j)   The Crane operator must provide warning signals when required.
 k)   Loads or lifting gears must not be moved above persons during any crane
                                          DRAFT
      motions
 l)   The crane operator may only move loads attached manually when he has
      received a signal from the person attaching the load, or the hand signaller or
      the person nominated by the crane operating company. If signals must be
      used to communicate with the crane operator, these signals must be agree
      upon between the crane operator and the person responsible for the signals
      before the signals are applied.
 m)   As long as load is suspended on the hook, the crane operator must keep his
      hands near the controls.
 n)   The emergency limit switches must not be activated intentionally during
      operation.
 o)   The crane operator must ensure that all the doors are closed and locked
      during travel.
 p)   Cranes may not be subjected to stress beyond the respective highest
      permissible loading.
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
DRAFT
Location: Fitted with concerning gear box drum and driven by gear box through
reduction (an outer part of limit switch). The limit switches are pre-set.
Setting of main Hoist Limit Switch
i.    At two feet distance between Main Snatch block Pulley and boom had main
      pulley
ii.   At two mtrs distance between snatch block pulleys and boom head.
Setting of Aux. Hoist Limit Switch
i)    At 2 feet distance between Auxiliary snatch block pulleys and Auxiliary head
      pulley.
ii)   At 2 mtrs distance between main snatch block pulley and boom head:
iii)  Setting of DERRICK limit switch – 04 Settings -
a)    At 5 mtrs (steepest boom up).
b)    At 5.5 meters.
c)    At 17 mtrs (steepest boom down)
d)    Approach of the boom for deposition inside trassel box. working range of boom
      radius: 5.5 mtrs to 17 mtrs.
6.    Hydraulic Solenoid Valve
(16 Nos) energized/activated by electrical plug.
Location:
i)    09 Nos at one place inside m/c room.
ii)   03 Nos at one place inside m/c room.     DRAFT
10.    Start Relay: (150 A, 24 VDC) fitted with main engine relay Panel box for crane
       operation, its function is must.
11.    Water Level Switch: Fitted with radiator of main engine. It supplies negative
       power to fuel solenoid valve.
12.    Over speed Switch: Fitted near main engine harness box. When engine rpm
       exceeds the maximum limit, it trips out. Reset it, now main engine starts easily.
13.    Fuel Solenoid Valve Location: Fitted with main engine at mid portion of
       engine. It has two points a) Positive point circuit b) Negative point circuit.
       Positive point circuit gets power supply from Ammeter and negative point
       circuit controlled by water level sensor.
14.    Trouble-shooting
       When main engine not starting, check power supply at following point -
a)     When weak cranking, check -
i)     Battery power: Full charged battery easily starts engine: Specific Gravity must
       be more than 1200 of distilled water of Batteries.
b)     When strong cranking, but not starting, check power supply at -
i)     Water level inside main engine radiator.
ii)    Battery main switch.
iii)   Ignition key switch.
iv)    Magnetic switch.
v)     Over speed switch.
vi)    Self-starting motor.                DRAFT
CHAPTER-4
      Crane Brake should be Do not pull the crane Wheel will get skid due
      released with indication when     indication is to brake binding.
      as “GREEN”               “RED”, in any case.
b)
      Boom should be locked Do not leave the boom Auxiliary boom head &
      in trestle.           unlock in trestle.
                                        DRAFT
                                                  pulley will get damage.
c)
f)
g)
      All stop valves for Hyd. Do not leave any of the The pumps may get
      Lines should be opened stop valves closed.       damaged or the Hyd.
      before    starting   the                         System will seize.
      engine.
 b)
 c)   Before    starting   the Do not allow the Hyd. Hyd.   Pump    may    be
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                     Page 192 of 210
Maintenance & Operation Manual                        Part I- 140 T BD Cranes
e)
      Check for AIR pressure, Do not leave any air Air braking      will   be
      it should like between leakage in the system. difficult.
      6.5 –7.5 bars(kg/cm2).
f)
 3    AXLE BLOCKING
      Ensure engagement of
      the travelling gear.
a)
      Ensure application of
      service brake confirmed
      by the “RED” indication.
b)
 4    BOOM ERECTION:
      Secure rear section lock
      while rear section is fully
      lifted.
a)
      Depute 2 staff to go up
      and watch the reveing
      and unreeling of the wire
 b)   rope.
DRAFT
e)
      Set the propping pads Do not prop the crane The prop may sink
      properly on ground by on loose ground in any causing major accident
      strengthening       the case                 e.g. Toppling of crane.
      ground. Depute one staff
      on each prop to watch
      its movement.
 a)
 6    COUNTERWEIGHT
      Select      the       total                   During rigging of crane
      counterweight         with     DRAFT
                                                    with full counterweight,
      proper assessment of                          Full stroke of Differential
      load, in consultation with                    cylinder,            DEM
      the load chart.                               160/90X270        (Vertical
                                                    cylinder)    should     be
                                                    taken     in   downward
                                                    condition.
 a)
b)
d)
e)
DRAFT
m)
 7    OPERATION
 a)   Ensure proper selection
      of lifting tackle (Chain &
      Wire rope sling).
 b)   Avoid        jerk    during   Don’t pull      the   load
      operation.        Pendulum    diagonally.
      motion of load not
      permitted.            Avoid
      diagonal pull of the load.
 c)   Pull the load which are       Don’t pull loads which
      stacked in the ground         are stuck in the ground
      cautiously. It is ensured     without            close
      that it will not offer        supervision.
      resistance beyond the
      capability of the Crane.
 d)   Take care of High wind
      forces on the boom as it
      is dangerous.
                                            DRAFT
DRAFT
      hoses.
 c)
diameter.
DRAFT
APPENDIX-A
           MAINTENANCE
         SCHEDULES OF 140T
              CRANE
     (As per RDSO Maintenance Schedule no. MP.MI-37 (Rev.-00)
                           June'2018)
DRAFT
DME lP-ll, Railway Board, Rail Bhawan, New Delhi              -   110   001. (Fax no.: 011-2g38   9696)
Scanned by CamScanner
                                                             R.D.S.O
                                                 (For official use only)
                              ,
                    GOVERNMENT OF INDIA
                    MINISTRY OF RAILWAYS
                    Maintenance Schedule of
       140t Diesel Hydraulic Gottwald & Cowans Sheldon
                      Breakdown Cranes
CONTENTS
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 1 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
                   SCHEDULE OF STANDARD EXAMINATION OF
     140t DIESEL HYDRAULIC BREAKDOWN (Gottwald / Cowans Sheldon) CRANE
GENERAL DESCRIPTION:
1. INTRODUCTION:
        Initially, 24 nos. imported 140t diesel hydraulic breakdown cranes of Gottwald design (12
        nos.) & Cowans Sheldon design i.e. Jessop/NEI make (12 nos.) were introduced over IR
        in 1986 & 1987 respectively. Accordingly, RDSO issued maintenance schedule for
        Gottwald & Cowans Sheldon design cranes vide Report nos. MP-727/90 January’1990
        and MP-731/91 March’1991 respectively.
        Later, upgraded versions of both makes were also imported & introduced in year 1998 &
        2000 respectively. Again, RDSO issued maintenance schedule for 8 nos. Gottwald
        (upgraded) i.e. new design cranes vide Report no. MP.MI-19 (Rev.-00)
        September’2001. However, no maintenance schedule for 4 nos. Cowans Sheldon new
        design cranes was issued by RDSO.
        Jamalpur workshop, E. Rly is responsible for maintaining & overhauling the Gottwald
        design cranes beside manufacturing in-house whereas Parel workshop, C.Rly. is
        responsible for maintaining & overhauling the Cowans Sheldon design cranes. Both
        workshops have been maintaining the same as per schedules issued earlier. However,
        over last 30 years there have been several changes in equipments/minor design
        modifications etc. due to obsolescence of equipments as well as up-gradation of
        equipments. As such, existing schedules for 140t diesel hydraulic breakdown cranes of
        Gottwald design & Cowans Sheldon design needed revision.
        Meanwhile, Railway Board advised RDSO to make a common maintenance schedule for
        all variants of cranes like other rolling stocks duly incorporating all changes undertaken
        by concerned workshops over last 30 years. Moreover, ‘SAG Committee on
        maintenance of 140t cranes vide para 5.1 of their report’ recommended to introduce
        a new “Weekly Schedule” in between daily & monthly schedules. SAG Committee also
        recommended to include items like Wheel profile checking, UST of wheel axle etc. in the
        schedule to be elaborated by JAG Committee. ‘JAG Committee vide para no. 2.3.2 of
        their report’ on maintenance of 140t cranes dated 10.04.2017 recommended to include
        wheel related maintenance activities in the “Yearly Schedule” beside other
        recommendations.
        Accordingly, a draft schedule for examination and maintenance of the various parts of
        140t diesel hydraulic cranes viz. Gottwald & Cowans Sheldon cranes was evolved taking
        into account the recommendations of Original Equipment Manufacturers, Eastern
        Railway Loco Workshop, Jamalpur (responsible for indigenously manufacturing &
        maintaining Gottwald design cranes), Central Railway Loco Workshop, Parel
        (responsible for maintaining Cowans Sheldon design cranes) and suitably modified
        keeping in view the experience of the user Railways in the field of crane operation as
        well as maintenance and workshops involved in manufacturing & POH .
        Also, RDSO introduced Weekly Schedule for the first time & incorporated other
        recommendations of SAG & JAG Committees & circulated the same to all user Railways.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 2 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
        Later, a meeting was held with consignees at STC, Secunderabad to obtain their
        feedback based on maintenance experience. Thereafter, draft maintenance schedule
        has been modified after incorporating inputs/suggestions/remarks of user Railways &
        Workshops and a revised common maintenance schedule no. MP.MI-37 (Rev.-00)
        June’2018 has been finalized and supersedes all previous schedules issued by RDSO.
        The service periods of 140t cranes specified in this schedule for maintenance attention
        are the maximum allowable periods between successive examinations. Variation in
        operating conditions in different regions may make it necessary to carry out examination
        more frequently, or introduce examinations not scheduled herein. In such cases, the
        matter should be brought to the notice of the appropriate Sr. DME / Dy. CME (Crane)
        /DME, who alone is authorized to introduce any change in the standard examination
        detailed herein. Sr.DME/DME/AME in all such cases, will bring to the notice of the Motive
        Power Directorate of RDSO, for any modification to the schedules, giving full details.
        The proposed common maintenance schedule has been prepared by incorporating
        suitably the inputs / comments / suggestion received from user Railways & POH shops
        based on their maintenance experiences. Although, every care has been taken to make
        this document free from errors, but if any discrepancy / shortcoming / irrelevant
        information is observed, the user Railways are requested to inform RDSO at the
        following email IDs:
              i. Joint Director/Director /MP/RDSO mp.directorem@gmail.com
             ii. Dy. Director/MP/RDSO                mp.ddelectmachines@gmail.com
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 3 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
2.    REFERENCES:
      The following documents are also required to be referred for further information:
      i)     Cranes:
             a) Operation, Maintenance & Service Manuals issued by M/s Gottwald.
             b) Operation, Maintenance & Service Manuals issued by M/s Cowans Sheldon.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 4 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
      vii) 2- Yearly Schedule or after 2000 Hours*
      viii) 4-Yearly Schedule or after 4000 Hours*
      ix) 8-Yearly Schedule (POH) or after 8000 Hours*
      Note: * indicates ‘whichever is earlier’
3.1   The following proposed periodicity of overhauling of 140t cranes are to be carried
      out by concerned Workshop:-
4.1   Periodicity of maintenance for Main Engine of M/s CIL (NTA 855-R4 & NTA 743 P):
      i)    Daily Schedule
      ii) Weekly Schedule or after 25 Hours*
      iii) Monthly Schedule or after 100 Hours*
      iv) Quarterly Schedule or after 250 Hours*
      v) Half Yearly Schedule or after 500 Hours* - (Only lube oil change)
      vi) Yearly Schedule or after 1000 Hours*
      vii) 2-Yearly Schedule or after 2000 Hours*- (Air Cleaner/Filter & Belts of fuel pump,
            water pump, compressor, cooling fan & charging alternator change)
      viii) 4-Yearly Schedule or after 4000 Hours*- (Calibrate injectors, PT pump & adjust
            Valves)
      ix) Major Overhaul after 8 Years at the time of POH or after 8000 Hours*
4.2 Periodicity of maintenance for Main Engine of M/s MTU (OM 904-926 LA):
      i)         Daily Schedule
      ii)        Half Yearly Schedule or after 500 Hours* - (Only lube oil change)
      iii)       Yearly Schedule (V2) for adjusting valve clearance every 1 st, 3rd, 5th & 7th Year
      iv)        Additional work (M or Z2) every 2nd, 4th, 6th, 8th Yearly schedule
      v)         Additional work (J3 or Z3) every 3rd, 6th, 9th Yearly schedule
4.3   Periodicity of maintenance of Auxiliary Engine of M/s KOEL (TA2 & HA-294) & M/s
      Lister-Peter (LPA-3):
      i)         Daily Schedule
      ii)        Weekly Schedule or after 25 Hours*
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 5 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
      iii)        Monthly Schedule or after 100 Hours*
      iv)         Quarterly Schedule or after 250 Hours*
      v)          Half Yearly Schedule or after 500 Hours*
      vi)         Yearly Schedule or after 1000 Hours*
      vii)        2- Yearly Schedule or after 2000 Hours*
      viii)       4- Yearly Schedule or after 4000 Hours*
      ix)         Major Overhaul after 8 Years at the time of POH or after 8000 Hours*
4.5   The filters, lubricants, oil change etc. provided in the various systems of engine are
      required to be changed as per the instructions of OEM. These are summarized below for
      information.
                               Description                                Periodicity
                                                 Lube Oil System
          1          Full flow lube oil filter                     500 hrs / Half yearly*
          2          By-pass filter                                          do
                                                 Fuel Oil System
          1          Fuel filter                                   500 hrs / Half yearly*
4.7   Lube Oil change periodicity of Main Engine, Auxiliary Engine & all Moving
      Equipments:
                        Description                                Periodicity
              1       Lube Oil                                 500 Hrs / Half yearly *
              2       Gear Box Oil                               1000Hrs / Yearly*
      Note: In case gear box unit is supplied by L&T, gear box oil shall not be changed during
            schedule maintenance because it is filled with long life lubricant oil (optimal long
            time PD 00 or IOC equivalent).
4.8   Recommended Lubricants for Main Engine models of M/s CIL make (NTA 855 &
      743P) & M/s MTU make (OM 904-926 LA) & Auxiliary Engine models of M/s KOEL
      make (TA2 & HA-294) & M/s Lister-Peter make (LPA3):
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 6 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
5.    Hydraulic Oil for Pumps & Motors:
5.1   Recommended brands of anti wear Hydraulic Oil HLP-68 to IS: 11656-1992 / 10522
      are as under:
5.3   Generally, both the oil types, ATF Suffix A & HLP 68 can be used. However, the oils
      should not be mixed. When converting to another oil type, the entire system must be
      drained and flushed, otherwise, it will not operate smoothly. The above recommended
      hydraulic oils shall be changed after one year / 1000hrs schedule.
      However, the above recommended hydraulic oils shall be sent to laboratory for testing at
      the completion of every 6 (six) months or 500 hrs, whichever is earlier to check the
      following test parameters as per limits mentioned below:
a)    During oil change and also during top-up, oil is recommended to be added through two
      stage filtration cart as per following specification:
      Note: Details of the hydraulic oil filtration trolley is provided separately in RDSO
            Instruction Bulletin No. MP.IB. HYD.02.18.01 (Rev.- 0.00)
b)    In the absence of filtration trolley, oil must be added through at least an external oil filter
      with minimum retaining rate of 10µm so that cleanliness of oil is maintained.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 7 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
6.      Oils & Lubricants for other Crane Equipments:
6.1     For Gottwald Cranes (Old & New):-
S.No            Fluid            Cap.                Recommended Oil & Grease
                               Approx MOBIL         SHELL    IOC        BPC           HPC
                               (in Ltrs)
 1.     Lube Oil for Pump         5.5    NA           NA     Servomesh Amocam        HP 90
        Distribution Gearbox                                   SP 90     90
 2.     Lubrication Oil for      0.2   NA             NA       Servo    MAK          Hylube
        Chassis Air                                           Premium   CF4 -         Milcy
        (Air Oiler only for                                  CF4-15W40 15W40         Power
        Old design)
 3.     Lube Oil for Gear units:
 i)     Slewing gear unit       15.5
 ii)    Main hoist gear unit     6.5
 iii)   Aux. hoist gear unit     6.5
                                       NA             NA     Servomesh   Amocam      HP 90
 iv)    Derricking gear unit     9.5
 v)     Recovery winch           3.4                           SP90        90
        gear unit
 vi)    Travel gear unit        12.0
 4.     Lube Grease for Bearings of Gear units:
 i)     Main Hoist gear unit           NA             NA     Servogem      MP        Lithon
 ii)    Aux. Hoist gear unit                                   EP2       Grease 3    EP - 2
 iii)   Derricking gear unit
 5.     Lube Grease for       As per   NA             NA     Servogem       NA       Lithon
        gear wheel / pinion   require                          EP1                   EP - 1
 6.     Lube Grease for       ment.                          Servogem      Bharat
        slew ring                      NA             NA       EP2        Comex      Lithon
 7.     Lube Grease for                                                  compound    EP - 2
        axle gear unit                                                      DEP
6.2     For Cowans Sheldon Cranes (New)
S.No            Fluid            Cap.               Recommended Oil and Grease
                               Approx.     MOBIL    SHELL    IOC        BPC           HPC
                               (in Ltrs)
 1.     Lube Oil for Pump         5         NA        NA       Servo      Bharat    HP Gear
        Distribution Gearbox                                   Super      Spirol     Oil XP-
                                                              85W140     85W140      80W90
 2.     Lubrication Oil for    As per       NA       Hydro-    Servo      MAK -     Turbinol-
        Chassis Air            requir-             vanne 2000 Ultra-40    T- 40        77
        Compressor             ement                 Rimula
 3.     Lube Oil for Gear units:
 i)     Slewing gear unit        29
 ii)    Main Hoist gear unit     14
 iii)   Aux. Hoist gear unit      4
 iv)    Derricking gear unit     30         NA       Omala     SP 220     Bharat  ENKLO -
 v)     Recovery winch gear       4                  220 /               Amocam -   220
        unit                                         Omala                 220
 vi)    Travel gear unit         35                   EP2
 4.     Lube Grease for Bearings of:
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 8 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
 i)     Main Hoist gear unit
 ii)    Aux. Hoist gear unit
 iii)   Derricking gear unit              NA      Alvania      Servo      Bharat      Lithon
 5.     Lube grease for gear    As per            EPLF2        Gem       Lanthex       EP2
        wheel / pinion         require-                        EP-2      LFEP2
 6.     Lube grease for slew     ment
        ring
 7.     Lube grease for axle
        gear unit
6.3     For Cowans Sheldon Cranes (Old)
S.No           Fluid             Cap.        Recommended Oil and Grease
                               Approx MOBIL SHELL     IOC         BPC                  HPC
                               (in Ltrs)
 1      Lube Oil for Pump         7.0              OIL, Servo  BHARAT,
        Distribution Gearbox                      System -100 Hydrol - 100
 2      Lubrication Oil for       7.0    NA  NA    OIL, Servo   BHARAT                  NA
        Chassis of Air                            System - 68 Hydrol - 68
        Compressor
 3      Lube Oil for Gear units:
 i)     Slewing gear unit
 ii)    Main Hoist gear unit
 iii)   Aux. Hoist gear unit                              OIL, Servo    BHARAT,         NA
 iv)    Derricking gear unit     90.0     NA      NA     Transmission Transmission
 v)     Recovery winch gear                              C-3, SAE-30      Fluid
        unit                                                          C-3,SAE-30
 vi)    Travel gear unit
 4.     Lube Grease for Bearings:
 i)     Main Hoist gear unit  As per
 ii)    Aux. Hoist gear unit  require     NA      NA     Servogem-3 BHARAT – MP         NA
 iii)   Derricking gear unit  ment:                                   Grease 3
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 9 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
7.    Hydraulic Oil Pressure:
7.1   Maximum Working Pressure for High Pressure Hydraulic Hoses:
      S. No.         Description of Hoses            Maximum Working Pressure (bar)
                                                  Gottwald cranes Cowans Sheldon cranes
       1.      Main hoist (for Hoisting)               280                330
       2.      Main hoist (for Lowering)               280                108
       3.      Aux. hoist (for Hoisting)               280                290
       4.      Aux. hoist (for Lowering)               280                108
       5.      Derrick - in                            280                330
       6.      Derrick - out                           280                108
       7.      Slewing                                 250                220
       8.      Travelling                              280                340
       9.      Hauling                                 280                200
       10.     Cooling (Radiator) Fan                  280                100
       11.     Draw Beams (Cowans Old only)             NA                170
       12.     Derrick-Tie Cylinder                     NA                 25
7.2 Operating Pressure for Hydraulic Circuits of Gottwald & Cowans Sheldon cranes:
      i) Wire (Round): A single circular rope of continuous length of metal drawn cold drawn
           from a rod.
      ii) Strand: An element of rope consisting of an assembly of appropriate shape and
           dimensions helically wound wires in one or more layer.
      iii) Core: The centre of a strand or the centre of a wire rope (which may be of Steel or
           Fibre).
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 10 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
8.4   Wire Rope Diameter Details:
       S.No. Crane type                        Wire Rope Diameter (in mm) for
                                    Main Hoist       Derrick    Aux. Hoist             Winch
       a.      Gottwald Old            26              26            22                 16
       b.      Gottwald New            26              26            22                 18
       c.      Cowans Old              36              32            26                 22
       d.      Cowans New              32              32            22                 20
            If the rope shows more than 5 wire breakages on a length of 6 x rope diameter
            (e.g. 6 x 26 mm = 156 mm) OR 10 wire breakages on a length of 30 x rope
            diameter (e.g. 30x26 mm = 780 mm).
            If the rope shows more than 5 wire breakages on length of 6 x rope diameter (e.g.
            6 x 22 mm = 132 mm) OR 13 wire breakages on a length of 30 x rope diameter
            (e.g. 30x22mm = 660 mm).
      Reduction in rope diameter by 15% or more from the actual rope diameter in new
      condition over a length of 10 x rope diameter (e.g. 260mm for main hoist & derrick
      and 220 mm for auxiliary hoist rope). The part of rope passing over sheaves and drum is
      more vulnerable & shall be checked for diameter.
Reduction in rope diameter by 10% or more due to wear or friction with any member.
      If deformations like waviness, loop formations, loose wires, nodes, rope thinning,
      misplaced outer wires, kinks and flat areas, are noticed on the rope.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 11 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
8.9    Special observation on wire rope:
       The wire breakages generally occur after a certain number of operating hours and then
       the number increases more quickly. It is recommended to keep watch on the condition of
       wire after any of wire breakage has started. Action for the discarding should to be taken
       as indicated above.
       After every rope change, functional test without load must be carried out. During the test,
       it should be ensured that rope runs smoothly.
       Periodically cleaning & greasing of ropes, if recommended by OEM shall be done for
       proper and smooth running of ropes on drums & sheaves. Refer OEM’s manual.
       If rope change is necessary, then it must be ensured that a wire rope of the same type
       and breaking strength as follow the Steel Wire Rope to IS: 2266/2002 construction IWRC
       standard of the original wire rope in new condition is fitted. When a new wire rope is
       being mounted, ensure that it is not twisted. Prior to operating with a newly fitted rope, it
       must be ensured that the rope is properly placed and guided in the grooves of the rope
       drum, rope pulleys and the compensation rollers. It is always advisable to change both
       main hoist & derricking wire ropes together to ensure the same quality and to maintain
       the same inspection & maintenance intervals.
       Generally, gears with considerable back-lash will continue to function reasonably well but
       with excessive noise. Abnormal back-lash on gears affects the life of other components
       in gear box due to vibration. Care should be taken while checking the back-lash on
       primary side gears because of cyclic variation of torque and speed of diesel engine. If
       premature gear wear or damage is noticed, it may be generally due to bearing trouble,
       mis-alignment, presence of foreign matter or insufficient lubrication. The first indication of
       defective gear(s) would be an increase in the noise level, which indicates rough
       operation. The following indications of undue wear and tear may be looked into, if gear
       damage is suspected:
       i) Fractures
          a) Tooth face fracture generally occurs due to shock loads or foreign matter such as
             broken pieces of metal forced through gear teeth in mesh.
          b) Fatigue fracture generally occurs from the root of the tooth.
          c) Tooth corner fracture or tooth splinter occurs, generally due to misalignment of
             gear. Mis-alignment of gears also results in a great load on tooth corners.
10.1   The following indicative list of tools, machines and accessories are applicable
       only for Gottwald design cranes:
       S. No. Tools
         1.     Hammer - 800 g
         2.     Flat chisel
         3.     Oil spray can
         4.     Hand lever operated grease gun
         5.     17 Double ended open jawed spanners, 8x10-55x60
         6.     6 Single ended open-jawed spanners, 8/41/65/70/75/80 mm
         7.     8 Hexagonal socket head wrench, SE 6/8/12/14/22/27/32
         8.     4 Tubular hexagonal box spanners, 13x7/19x22/24x30/30x36
         9.     4 Tommy bars for spanners, A 10/12/16/18
        10.     Standard Ratchet, ½”
        11.     Extension Piece 10”
        12.     Articulated square-drive socket adapter, 70 mm
        13.     Socket for wrenches, SW 17/19
        14.     Min. 3 Screw drivers
        15.     Light tester
        16.     Hose, DN 6/222bX5000
        17.     Pressure gauge, 0-400 bar with connection fitting
        18.     Union nuts
        19.     Cutting ring
        20.     Seeger Circlip ring pliers, A3/A4
        21.     Flat-nosed and cutting nippers
        22.     Pipe wrench
        23.     Sickle spanner
        24.     Hose, NW18X3 5000
10.2 The following indicative list of tools, machines and accessories are applicable
     only for Cowans Sheldon cranes:
       S. No.   Tools
         1.     A full set of A/F open ended spanner
         2.     A full set of A/F ring spanner
         3.     75 mm capacity adjustable wrench
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 13 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
          4.   Spring Link Bolt spanner
          5.   Blocking Screw spanner
          6.   Set of Allen keys 1.5mm A/F to 17 mm A/F
          7.   1.75 Lb Hand hammer
          8.   10" Insulated Screw Driver (Std. Tip)
          9.   6" Insulated Screw Driver (Std. Tip)
         10.   4" Insulated Screw Driver (Std. Tip)
         11.   Set of Tommy Bars 16" Dia.
         12.   Adjustable Spanners
         13.   Pipe wrench
         14.   Feeler Gauge
         15.   A set of Extension piece of 150, 225, 300 & 375 mm drive extension
         16.   A set of Impact Socket C/W Ring & Pin 24, 30,36,45,& 65 mm A/F
         17.   Peg spanner for dismantling Jacks & Cylinder, manufactured Items.
         18.   Junior Hand Compressor (Grease gun) with connector
         19.   1/2 & 2 Litre oil feeder
         20.   0-70 & 0-400 Bar Pressure Gauges with Hose
         21.   35 mm O/D x 8500 mm Long Hydraulic oil filling hose
         22.   Aluminium extension ladder 3.5 m closed
         23.   Charging unit for accumulator with pressure gauge & hose
         24.   Flushing unit of 15 HP capable of developing at least 1950 psi at 43 LPM
         25.   Hose crimping m/c having cap. to handle1.25" ID hoses including multi-spiral
         26.   Hose skiving tools
         27.   Hose cutting machine
         28.   Pipe bending c/w 6 sets of formers
.4    All measuring devices such as torque wrenches, electric meters, lubricant dispensers
      etc. which require calibration should be checked quarterly or sooner, if required, for
      accuracy.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 14 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
.5    Periodic maintenance of the crane should be done after it is placed on level track and
      parking brakes of crane and match truck applied.
.6 In case any structural part is damaged and is to be rectified, ensure the following:
      a) Direct flame should not damage cables, hoses & pipes. Must take all fire prevention
         measures for hoses, cables etc. from direct heat by shielding the flame.
      b) For any structural repair, ensure proper preheating. Use only recommended
         electrodes and argon shield welding.
      c) If welding is carried out on the crane, it is a wise precaution to disconnect SLI from
         both sides of the crane. Disconnect main battery while welding. Earth the respective
         structure directly.
.7    While carrying out the work of the schedule, all missing nuts, bolts, set-screws, cotters,
      split pins etc. must be REPLACED as and when found defective. Split pins and cotters
      once removed must not be used again, but new ones must be fitted. All loose nuts,
      setscrews etc. must be tightened. Wherever cotters or split pins are fitted, they must be
      of the correct size and so fitted that they bear against the nut or washer properly.
      Examine and ensure that all locking devices, wherever provided, are properly secured.
      Replace all gaskets, seals, rubber items, washers etc. during schedules.
.9    The fire extinguishers should be re-filled and maintained as per the schedule. Under no
      circumstances, should crane be allowed to leave the shed without its required number of
      fire extinguishers in working order. The staff while working under the crane or while
      standing over footboards / superstructure must not smoke or strike up fire nearby.
.10   All tools and parts should be accounted for and removed from the crane after schedule
      maintenance work has been performed. Check and ensure that no tools or replaced
      parts lie over the crane.
.11   Use of waste cotton on crane is PROHIBITED. Use lintless rags or wiping towels. The
      underframe and top surface of fuel tanks should be cleaned to remove dirt and oil.
      Spraying of water directly on electrical equipment should be avoided.
.12   Irrespective of the above, the concerned Workshops are requested to kindly repair the
      inside of Undercarriage of Match Truck & Ballast Wagon. If found damaged/corroded
      etc., the same shall be fully repaired during POH.
      Crane shall be handed over to consignee after carrying out full load testing of crane and
      issuing satisfactory performance certificate of crane as “OK”.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 15 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
 Daily Schedule for Maintenance of 140t Gottwald / Cowans Sheldon Crane
1.    MAIN ENGINE (Applicable only for M/s CIL NTA 855 & 743P):
1.1   Check engine oil level and top up, if necessary. ‘H’ mark must be maintained.
1.2   Check belt tension and condition of belts for cuts, fretting, cracking etc.
1.3   Check for loose foundation bolts. Tighten them, if required.
1.4   Fill/top-up radiator with distilled water / coolant additive which should be free from any
      suspended impurities such as clay, sand etc. Radiator cap should be fitted back after
      necessary fill up since this will cause aeration and overheating of the water coolant.
1.5   Fuel tank to be filled-up with clean diesel oil to ‘Fuel’ capacity.
1.6   Clean the engine.
Note: M/s MTU has not recommended any Daily Schedule. Refer MTU’s manual.
2.    AUXILIARY ENGINE of M/s KOEL (TA2 & HA-294) & M/s Lister-Peter (LPA-3):
2.1   Check for engine sump oil. Top up, if necessary.
2.2   Fuel tank to be filled with clean diesel oil to “Full” capacity, if required.
2.3   Clean the engine.
3.    SUPER STRUCTURE:
3.1   Check for the oil level in pump distribution box (P.T.O. unit) / splitter gear box. Top up, if
      necessary.
3.2   Check hydraulic oil level. Top up, if necessary. For this check, raising of gallows may be
      necessary.
3.3   Check for any leakage or damages of hoses and pipes. Rectify, if necessary.
3.4   Check the cablings connecting various parts of the electrical systems for physical
      damages.
3.5   Check Fire-extinguishers and First-Aid-Box in position and keep them in working order.
3.6   Top up air oiler supply, if necessary.
3.7   Drain condensate from both air reservoirs.
4.    UNDER CARRIAGE:
4.1   Check spring suspension for any breakage or deficiency.
4.2   Check for damage and deficiency in the brake system including pipes and hoses.
4.3   Check travel clutch indicator cable and lubricate, if required.
4.4   Floor plate to be cleaned. Ensure it is free from oil and greasy substances.
4.5   Drain out condensate from all the air reservoirs.
Note: Even minor leakage of oil / air must be noted and eliminated.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 16 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
5.    MATCH TRUCK:
6.    MAIN ENGINE (Applicable only for M/s CIL NTA 855 & 743P):
6.1   Check leakages of fuel, oil, water and exhaust air supply and rectify, wherever required.
6.2   Check for any loose nut, bolt or fastener. Tighten them, if required.
6.3   Check gauge and indicators for engine speed, ammeter, lube oil temperature, lube oil
      pressure, water temperature indicator and fuel indicator in driver’s cab. (For details refer
      Engine Maintenance Manual.)
6.4   Check lube oil pressure (operating pressure 3.5kg/cm2 at idle & 5kg/cm2 at rated speed
      respectively).
6.5   The main engine of crane shall be run at rated rpm for 30 minutes*.
6.6   Clean the engine after shut down.
      Note: M/s MTU has not recommended any Daily Schedule. Refer MTU’s manual.
7. AUXILIARY ENGINE of M/s KOEL (TA2 & HA-294) & M/s Lister- Peter (LPA-3):
8.    SUPER STRUCTURE:
8.1   Check air pressure (Operating pressure to be 6.0 bar to 6.8 bar & 3.8 bar for brake
      cylinder); Rectify faults, if any.
8.2   Check pollution indicator of hydraulic oil filter. Replace the filter, if the indicator is at red
      mark or above 3 bar. (Check filter choke indication available in cab for Cowans
      Sheldon new crane).
8.3   Check hydraulic oil pressure of various circuits indicated above at Para 7.2 of General
      Description.
8.4   Check functioning of fans, lights, screen wipers and horns in cab.
8.5   Check leakage of oil, water and air. Rectify, wherever required.
8.6   Check that all limit switches are in working order.
8.7   Check that solenoid valves are not bridged (manually)
9. UNDER CARRIAGE:
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 17 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
A.      IMPORTANT REPAIRS (Observed by SSE/ JE /Driver):-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 18 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
Weekly Schedule for Maintenance of 140t Gottwald / Cowans Sheldon Crane
                          (At the completion of 25 working hours)
1.    MAIN ENGINE (Applicable only for M/s CIL NTA 855 & 743P) and AUXILIARY
      ENGINES (M/s KOEL TA2 & HA-294 and M/s Lister- Peter LPA-3):
1.1   Check electrolyte level, specific gravity & voltage of batteries. A lead acid battery is fully
      charged with a specific gravity of 1.265 at 27°C and voltage should be 110V. To be
      topped up, if necessary with distilled water. The terminal should be adequately coated
      with petroleum jelly.
1.2   Check battery voltage. Repair, if required.
1.3   Check foundation tightness of auxiliary rotating machines.
1.4   Check coolant level in engine radiator. Use distilled water.
1.5   Clean dust pan and pre-cleaner on dry type air cleaners.
1.6   Clean crankcase breather.
1.7   Drain out water & sediments from water separator.
Note: M/s MTU has not recommended any Weekly Schedule. Refer MTU’s manual.
2. SUPER STRUCTURE:
3.1   Check free running for any damage in pulley, wire rope, bearing & pin for Main hoist and
      Auxiliary hoist pulley. Lubricate, if required.
3.2   Check all sheaves and bottom block bearings & lubricate.
3.3   Lubricate jib head rest pin, if required.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 19 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
3.4   Lubricate jib stop pivot pins & head rest pin.
3.5   Lubricate auxiliary hoist block hook swivel & cross head.
3.6   Lubricate main hoist block hook swivel & cross head.
3.7   Carry out load testing by lifting counterweights & perform crane operations.
4. UNDERCARRIAGE:
4.1   Lubricate relieving bogie coupling pins (only for Cowans old crane).
4.2   Lubricate centre & end draw beam rollers (only for Cowans old crane).
4.3   Lubricate blocking screws.
4.4   Lubricate travel clutch shafting.
4.5   Lubricate bogie pivot oil boxes.
4.6   Lubricate bogie rubbing pads.
4.7   Lubricate brake linkage pivot pins.
4.8   Check spring suspension for any breakage or deficiency.
4.9   Check travel indicator cable and lubricate.
5. MATCH TRUCK:
5.1   Check spring suspension for any breakage or deficiency. Rectify, if required.
5.2   Lubricate bogie side bearer oil boxes.
5.3   Lubricate bolster swing link pins.
5.4   Lubricate brake work and brake rigging.
5.5   Lubricate axle box guides and dash pots.
5.6   Lubricate trestle pad and trestle pivot with grease.
5.7   Lubricate hand brake threads.
6.    RELIEVING BOGIES (Only for Cowans Sheldon Old Crane):
6.1   Check for breakage or deficiency in spring suspension system. Rectify, if required.
6.2   Check for damage and deficiency in the brake system including pipes and hoses.
6.3   Clean floor plate. Ensure it is free from oil and greasy substance.
6.4   Check leakage and functioning of parking brake.
6.5   Lubricate spring hanger pins.
6.6   Lubricate break linkage pivot pins.
6.7   Lubricate locking pins.
6.8   Lubricate adjusting screw.
6.9   Lubricate centre castings.
7.1   Check for breakage or deficiency in spring suspension system. Rectify, if required.
7.2   Check for damage and deficiency in the brake system including pipes and hoses.
7.3   Check leakage and functioning of parking brake.
7.4   Lubricate bogie side bearer oil boxes.
7.5   Lubricate bolster swing link pins.
7.6   Lubricate brake work and brake rigging.
7.7   Lubricate axle box side bearer oil boxes.
7.8   Lubricate hand brake threads.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 20 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
A.      IMPORTANT REPAIRS (Observed by SSE/JE /Driver):-
Certified that examination and repairs have been completed, if not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 21 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
Monthly Schedule for Maintenance of 140t Gottwald/Cowans Sheldon Crane
                            (At the completion of 100 working hours)
2.      AUXILIARY ENGINES of M/s KOEL (TA2 & HA-294) & M/s Lister-Peter (LPA-3):
2.1     Clean dust pan and pre-cleaner on dry type air cleaners.
2.2     Clean crank case breather.
3.      SUPER STRUCTURE:
3.1     Check SLI, all electrical connections and functioning of all sensors.
3.2     Check that display of radius on the SLI console of the crane agrees with actual radius.
3.3     Check that all working parameters of load charts are in relation to SLI cut-off.
3.4     Check wire rope. Clean & lubricate as per Para 8 of General Description. If not
        complying with conditions indicated in Para 8, wire rope must be discarded.
3.5     Lubricate heavy lift ballast extension bearing surface, equalising beam, relieving bogie
        coupling pin, hand brake acme threads and check their working condition (applicable
        only for Cowans Sheldon old design crane).
3.6     Lubricate counter weight bolt pivot & threads, if applicable.
3.7     Lubricate telescopic tie rod bearings, sheave bearings and front strut bottom bearings
        (applicable only for Cowans Sheldon old design crane).
3.8     Lubricate slew lock-pin, bearing of cylinder for retractable arm.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 22 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
4.      JIB:
4.1     Lubricate main and auxiliary snatch block swivel and sheave bearings.
4.2     Lubricate derrick pulley blocks & sheaves bearings only for Cowans Sheldon old crane.
4.3     Lubricate ropes with grease as per Para 8.
4.4     Clean & lubricate jib foot sliding surface (fork & pin) & rollers for Cowans Sheldon crane.
5.      UNDER CARRIAGE:
5.1     Check travel brake equipment, linkage, linings, etc. and pneumatic systems.
5.2     Check functioning of outriggers and hydraulic cylinders.
5.3     Lubricate travel gears with grease and clutches shifts with grease.
5.4     Lubricate brake linkage, outriggers pins with oil & side bearer, hand brake threads and
        rail clip screws with grease for Cowans Sheldon crane).
5.5     Lubricate blocking screws & hanger bracket pins for Cowans Sheldon crane.
5.6     Lubricate bogie pivot oil boxes for Cowans Sheldon crane.
6.      MATCH TRUCK AND BALLAST WAGON (Only for Cowans Sheldon Old crane):
6.1     Check for travel brake equipment, hoses, linkage, shoes etc.
6.2     Lubricate brake linkage pins with oil and side bearer with grease.
6.3     Lubricate hand brake threads & brake linkage pins with oil.
6.4     Lubricate trestle pad and trestle pivot with grease.
Certified that examination and repairs have been completed, if not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 23 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
      Quarterly Schedule for Maintenance of 140t Gottwald/Cowans Sheldon Crane
                              (At the completion of 250 working hours)
1. SUPER STRUCTURE:
2. JIB:
3. UNDERCARRIAGE:
4. MATCH TRUCK & BALLAST WAGON (Only for Cowans Sheldon Old design crane):
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 24 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
B.       SCHEDULE REPAIRS:
Certified that examination and repairs have been completed, if not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 25 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
 Half-yearly Schedule for Maintenance of 140t Gottwald / Cowans Sheldon Crane
                           (At the completion of 500 working hours)
1.    MAIN ENGINES of M/s CIL NTA 855 & 743P (to be done with the help of OEM):
1.1   Check all air cleaner connections for cracks, chafing etc. Tighten all air in-take
      connections.
1.2   Remove, clean and inspect dry type air cleaner for hole and tears. Check gaskets / ‘O’
      rings for damage. Paper type elements should be cleaned by compressed air, in the
      direction flow opposite to the flow of air. Discard element even, if a pin-hole exists.
1.3   Change air cleaner element.
1.4   Change lubricating oil by-pass filter element and gasket.
1.5   Change fuel filter element and gasket.
2.    AUXILIARY ENGINES of M/s KOEL TA2 & HA-294 & M/s Lister-Peter LPA-3 (to be
      done with the help of OEM):
2.1   Check valve tapped clearance (applicable only for Cowans Sheldon crane)
2.2   Service air filter, if required.
2.3   Renew lubricating oil filter element, if required.
      Note: Above job is to be done with help of authorized dealer of Main & Aux. Engine.
2.4   Drain sump. Flush out approved brand of flushing oil and re-fill with new oil.
2.5   Change/replace engine oil, if required.
      Note: Oil change periodicity may be extended, if oil condition is found satisfactory during
             lube oil analysis in a laboratory.
2.6   Clean the oil tank, fuel filter bowl and ceramic filter thoroughly / Re-new fuel filter
      element, as applicable.
2.7   Knock out soot from the exhaust silencer.
2.8   Clean the cooling air duct and space between cooling fins on cylinders.
3.    SUPERSTRUCTURE:
3.1   Check all drive assemblies.
3.2   Check oil level and send it to M&C lab for spectrographic analysis & extend the life, if
      found OK as per OEM manual. Else top up, as necessary for following items of
      respective cranes (Refer Para 6 of General Description):
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 26 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
3.3      Collect sample of hydraulic oil. Get it tested and replace, if clogging gauge pressure is
         more than 3 kg/cm2. Change return line filter element / filter of hydraulic tank (It shall be
         carried out with respective OEM).
3.4      Change fuel tank‘s filter element / filter.
3.5      Check fuel oil hoses for any damage and replace, if required.
3.6      Check the accumulator and recharge it.
3.7      Check ropes for damages / breakages.
3.8      Lubricate:
         a) Counterweight gallows with grease only for Gottwald make crane.
         b) Rope drum bearings with grease.
         c) Foot pedal in cab with oil.
3.9      Clean & re-grease jib foot sliding surface (fork & pin)
4.       UNDERCARRIAGE:
4.1      Clean and lubricate with grease:
         a) Slewing gear teeth.
         b) Travelling gear reduction unit.
         c) Splined shaft
         d) Screw coupling and buffers.
4.2      Lubricate slewing ring bearing with grease through grease nipples. Refer Para 6 of
         General Description.
4.3      Lubricate bogie pivot with grease.
4.4      Lubricate bogie bolster pins with grease.
5.       MATCH TRUCK & BALLAST WAGON (Only for Cowans Sheldon old design crane):
5.1      Clean and lubricate screw coupling and buffers with grease.
5.2      Lubricate bogie pivot with grease.
5.3      Lubricate bogie bolster pins with grease.
6.       RELIEVING BOGIES (Only for Cowans Sheldon Old design crane):
6.1      Clean and lubricate screw coupling and buffers with grease:
6.2      Clean lubricate with grease wishbone beam bushes.
6.3      Collect sample of hydraulic oil from oil tank and relieving bogies, get it tested and
         replace, if required.
A.       IMPORTANT REPAIRS (Observed by SSE/JE /Driver):-
S. No.       NATURE OF DEFECT             ACTION TAKEN         ANY PART RENEWAL SIGNATURE
 1.
 2.
B.       SCHEDULE REPAIRS:
S. No.      ITEM      OBSERVATION        ACTION TAKEN        ANY PART RENEWAL          SIGNATURE
 1.
 2.
Certified that examination and repairs have been completed. If not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 27 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
      Yearly Schedule for Maintenance of 140t Gottwald / Cowans Sheldon Crane
                           (At the completion of 1000 working hours)
Yearly Schedule to be carried out with the help of concerned W/shop & respective OEM.
3. SUPER STRUCTURE:
3.1     Check oil water & air hoses. Change them, if necessary.
3.2     Check for corrosion. Repair, if required and paint.
3.3     Check setting of limit switches for proper cut-off with the help of OEM & Workshop.
3.4     Calibrate SLI system, jib inclinometer, load cell & slew encoder.
3.5     Check windows and doors for corrosion, proper fitting and locks.
3.6     Inspect drive assembly.
3.7     Change gear box oil.
3.8     Clean water and air cooler fans with water jet.
3.9     Clean radiator externally.
3.10    Clean fuel oil tank and flush.
3.11    Drain sediment from hydraulic oil tank.
4. UNDER CARRIAGE:
6.    MATCH TRUCK, BALLAST WAGON & RELIEVING BOGIES (ONLY FOR COWANS
      SHELDON OLD CRANE):
6.1   Check wheel diameter of Match Truck, Ballast Wagon & Reliving Bogie wheels. It shall
      be as under:
       S.No. Crane type            Wheel Diameter (New / Condemning limits in mm) for:
                                  MATCH TRUCK BALLAST WAGON RELIEVING BOGIES
       a.      Cowans Old           915 / 825         915 / 825           915 / 840
6.2   WHEEL PROFILE CHECKING: IRS Thick profile to RDSO Drg. no. CSL-3040 has been
      provided on the new Match Truck wheels. Check for wheel wear i.e. root wear & tread
      wear as per RDSO Drg. no. CSL-2127/M. If wear is found beyond limit, the crane shall be
      sent for wheel turning.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 29 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
6.3      UST OF WHEELS & AXLES:       Check for defects of crane wheels & axles, if any as
         per norms. Rectify the same. Carry out Ultrasonic Testing on wheels & axles as
         recommended by SAG committee in para 5.1 of their report.
B. SCHEDULE REPAIRS:
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 30 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
     2-Yearly Schedule for Maintenance of 140t Gottwald / Cowans Sheldon Crane
                         (At the completion of 2000 working hours)
2-Yearly Schedule to be carried out with the help of concerned W/shop & respective OEM
1. MAIN ENGINE:
1.1.1 Check for turbocharger oil leakage. Tighten turbocharger mounting nuts.
1.1.2 Check engine blow-by, clean radiator, adjust injectors and valves.
1.1.3 Check wobble and eccentricity / alignment marks on rubber type damper. Discard
      damper, if misalignment is more than 1/16”.
1.1.4 Check belt tension and adjust as required.
1.1.5 Remove and clean air compressor breather element.
1.1.6 Clean the oil tank, fuel filter bowl and ceramic filter thoroughly.
1.2.1 Check the poly V-belt for wear and damage & replace, if required.
1.2.2 Change engine lube oil & filter (Ad Blue). Next change in 4 th, 6th & 8th year respectively.
1.2.3 Renew coolant: When renewing the coolant, ensure that it contains 50% corrosion
      inhibitor / antifreeze by volume. This corresponds to antifreeze protection down to -37ºC.
      If there is loss of coolant, don’t top up by using only water, but also add an approved
      corrosion inhibitor / anti-freeze agent. Next change in 4 th, 6th & 8th year respectively.
1.2.4 Clean the fuel filter element.
1.2.5 Replace fuel pre-filter with water separator (fixed to the chassis).
2. AUXILIARY ENGINES (M/s KOEL TA2 & HA-294 & M/s Lister-Peter LPA-3):
3. SUPERSTRUCTURE:
3.1    Check visually for tightness of slewing ring arrangement. Stud, nuts and loose bolts to be
       tightened, if required.
3.2    Check rota white cap on bolts / studs for spinning (only for Cowans Sheldon old crane).
4. UNDER CARRIAGE:
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 31 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
5.       MATCH TRUCK:
6. RELIEVING BOGIES & BALLAST WAGON (only for Cowans Sheldon old crane):
Certified that examination and repairs have been completed. If not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 32 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
     4-Yearly Schedule for Maintenance of 140t Gottwald / Cowans Sheldon Crane
                          (At the completion of 4000 working hours)
4-Yearly Schedule to be carried out with the help of concerned W/shop & respective OEM
1. MAIN ENGINE:
       Note: Arrange for authorised dealer for engine manufacturer’s mechanic to check your
             engine completely- Refer Engine maintenance manual for details.
2.      AUXILIARY ENGINE (M/s KOEL TA2 & HA-294 & M/s Lister-Peter LPA-3):
       Arrange for authorized dealer for engine manufacturer’s mechanic to check your engine
       completely- Refer Engine maintenance manual for details.
3.     SUPER STRUCTURE:
       Overhaul all direction control valves, ‘O Ring’ & seals and replace, if required.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 33 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
A.       IMPORTANT REPAIRS (Observed by SSE/JE /Driver):-
B. SCHEDULE REPAIRS:
Certified that examination and repairs have been completed, if not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 34 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
  8-Yearly Schedule (POH) for Maintenance of 140t Gottwald & Cowans Sheldon Crane
                      (At the completion of 8000 working hours)
                           To be carried out by concerned Workshop
Concerned POH Workshop shall jointly examine the crane to be overhauled with it’s In-charge
for all damages / deficiencies / working problems / abnormalities and should verify with
Consignee reports on crane failures at the time of receipt of crane for POH.
Then workshop shall carry out dimensional check on crane structural components such as
undercarriage, superstructure, jib & match truck etc. for diagonal accuracy, tolerances,
skewness, surface alignment, distortion, straightness of structures etc. with the help of relevant
measuring instruments. Workshop should conduct weldment check using suitable techniques
such as DPT, Radiography / X-ray, Ultrasonic testing or Magnetic Flaw Detection.
Thereafter, workshop should make a pre-shopping report comprising of all structural repairs,
powerpack, hydraulic & pneumatic equipments, other assemblies/sub-assemblies, safety
system including devices, electrical & controls and SLI system.
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 36 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
B.      SCHEDULE REPAIRS:
Certified that examination and repairs have been completed. If not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 37 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
  8-Yearly Schedule (POH) for Maintenance of 140t Gottwald & Cowans Sheldon Crane
                      (At the completion of 8000 working hours)
Crane No __________________Shed________________________Rly__________________
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 39 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
A.      IMPORTANT REPAIRS (Observed by SSE/JE /Driver):-
B. SCHEDULE REPAIRS:
Certified that examination and repairs have been completed. If not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 40 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
   8-Yearly Schedule (POH) for Maintenance of 140t Gottwald & Cowans Sheldon Crane
                       (At the completion of 8000 working hours)
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 41 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
A.      IMPORTANT REPAIRS (Observed by SSE/JE /Driver):-
B. SCHEDULE REPAIRS:
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 42 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
  8-Yearly Schedule (POH) for Maintenance of 140t Gottwald & Cowans Sheldon Crane
                      (At the completion of 8000 working hours)
Crane No __________________Shed________________________Rly__________________
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 43 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
A.      IMPORTANT REPAIRS (Observed by SSE/JE /Driver):-
B. SCHEDULE REPAIRS:
Certified that examination and repairs have been completed. If not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 44 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
  8-Yearly Schedule (POH) for Maintenance of 140t Gottwald & Cowans Sheldon Crane
                      (At the completion of 8000 working hours)
Crane No __________________Shed________________________Rly__________________
 3.    CHECK VALVES:
 a)    Strainer Check Valve & Choke Unit
 b)    Double Check Valve
 c)    Tubular Check Valve
 d)    Soft Seated Check Valve
 e)    Duplex Check Valve
4. BRAKE CYLINDERS
 5.    RESERVOIRS:
 a)    Auxiliary Reservoirs for Crane, M/T & B/W.
 b)    Main Reservoir for Crane
 c)    Brake Supply Reservoir for Crane
 d)    Vac. Chamber for VAP valve for Crane, M/T & B/W.
 6.    DRAIN COCKS:
 a)    Drain Cocks for Crane Aux. & Brake supply
       reservoirs, M/T & B/W reservoirs
 b)    Drain Cock for Auto Drain Valve
 7.    CUT- OUT COCKS:
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 45 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
 a)     Isolating cocks for Crane Distributor V/v, M/T & B/W.
 b)     Self-locking Angle Cocks for Crane, M/T & B/W.
 c)     MR Isolating Cock
 d)     BSP Isolating Cock with vent
 e)     Isolating Cock with sealing for VAP valve.
 8.     GAUGES:
 a).    Duplex Pressure Gauge MR-BC
 b).    Vacuum Gauge VC
 13.    Springs:
 a)     Return Spring
 b)     Release Spring for M/T & B/W.
 B.     HAND BRAKE UNITS: Remove, overhaul, test and
        refit in the following assemblies:
 1.     Superstructure:
 2.     Undercarriage:
 3.     Relieving Bogies:
 4.     Match Truck
 5.     Ballast wagon (only for Cowans old)
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 46 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
B.      SCHEDULE REPAIRS:
Certified that examination and repairs have been completed. If not, reasons as below:-
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 47 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
  8-Yearly Schedule (POH) for Maintenance of 140t Gottwald & Cowans Sheldon Crane
                      (At the completion of 8000 working hours)
Crane No __________________Shed________________________Rly__________________
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 49 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
 b)    Check structural damage of jib
 c)    Check Radius Indicator provided on jib
 d)    Check Jib keep Lock Plate
 e)    Check Jib Bottom Rubbing Plate
 f)    Check Jib Foot Pin & Rollers
 g)    Check Jib Support Roller & Pins
 h)    Check & inspect Jib stopper for alignment with jib
 i)    Front Strut Bearings and Cap
 j)    Snatch Blocks: Overhaul
       � Main Hoist Snatch Block- Pulleys, Bearings,
           Crosshead & Swivel.
       � Auxiliary Hoist Snatch Block- Pulleys, Bearings,
           Crosshead & Swivel.
  k)   Telescopic Tie Rod:
       � Pulley Bearings
       � Grease Seal
 5.    UNDER CARRIAGE:
 a)    Run out bogies.
 b)    Carry out dimensional check for diagonal accuracy.
 c)    Check tolerances, skewness, surface alignment,
       distortion, straightness of structures etc.
 d)    Check structural damages of undercarriage & repair,
       as required.
 e)    Check Carriage End Castings.
 f)    Check cant indicator / sprit level indicator
 g)    Check counterweight lock plates.
 h)    Check access ladders.
 i)    Check Rail Clips.
       Only for Cowans old design:
  j)   Extend draw beams
  k)   Check movement draw beam rollers
  l)   Check draw beam lock pins.
 m)    Check draw beams, it’s jacks & Extension Cylinder.
 n)    Check footsteps of draw beams
 5.1   CARRIAGE BOGIES:
 a)    Open Carriage Bogie Pivot Pin Nuts, Remove
       Carriage from superstructure and keep on Trestle.
 b)    Check bogie frames for alignment
 c)    Check/Replace Blocking Screws (Relieving Screws)
 d)    Check bogie rubbing pads
 e)    Check centre pivots
 f)    Check, clean & refill bogie pivot oil boxes.
 g)    Remove Laminated Springs
 h)    Check / Replace Spring Link Bolts, Pins, Rocker
 i)    Washers & brackets.
 j)    Check / Replace spring slide washers
 k)    Check & reclaim Equaliser Beams & Bar Brackets
 l)    Check Axle Box Guides for wear
 m)    Check Axle Box Liners.
 n)    Check Axle Box Greasing.
 o)    Check Travel Clutch Indicators
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 50 of 52
     Maintenance Schedule of 140t Diesel Hydraulic Gottwald & Cowans Sheldon Breakdown Cranes
___________________________________________________________________________________________
 p)    Check Travel Clutch Cod Piece
 q)    Check & Lube Travel Clutch Shaft
 r)    Check Travel Gears & Lubricate
 s)    Assemble bogies
 t)    Renew Brake Blocks
 6.    ASSEMBLY & TESTING:
____________________________________________________________________________________________
Motive Power Directorate (HYD), RDSO, Lucknow No. MP. MI-37 (Rev. 00) June’2018   Page 52 of 52
           Maintenance & Operation Manual                                 Part II- ART & ARME
                                                                         केवल कार्ाालर्ीन उपर्ोग हे तु
                                                                               (For Official Use Only)
CH/GWL/MECH/2022-23/ART/Manual/1.1                                                                       Pag
Maintenance & Operation Manual                                                                      Part II- ART & ARME
                                                  Table of Content
1     INTRODUCTION ...................................................................................................6
    1.1.      ART Classification and types ......................................................................6
    1.2.      ARME Classification & types .......................................................................6
2. OPERATIONS.......................................................................................................6
    2.1.      Organizational issues, such as yardsticks and selection criteria to provide
              suitable personnel. ......................................................................................6
    2.2.      Staffing Yard Stick of ART & ARME (Including standby gang as RG/LR)
              Staff required for A&B class ART for restoration by HRE ............................7
    2.3.      Staff required for ARME at the accident site. ..............................................8
    2.4.      Staff required for CRACK TEAM .................................................................9
    2.5.      Deployment and work distribution of break down staff at accident site for
              HRE .............................................................................................................9
    2.6.      Composition of ART & ARME ...................................................................10
    2.7.      Staff deployment for Operation and Maintenance – ART ..........................12
    2.8.      Kitchen Management: ...............................................................................15
    2.9.      RELIEF AND RESCUE CRACK TEAMS: .................................................16
    2.10.     Turning out of ARTs/ARMVs: ....................................................................16
    2.11.     Relief and Rescue Operation by ARME staff: ...........................................17
    2.12.     Layout Drawings of ART coaches. ............................................................18
    2.13.     Details of Layout drawings for ART/ARME ...............................................19
    2.14.     Staff Management & Suggested ART/ARME Gangs: ...............................24
    2.15.     Disaster and Train Accident ......................................................................39
    2.16.     Characteristic of railway accident ..............................................................40
    2.17.     Consequence of disaster on a victim caused due to train accident ...........42
    2.18.     Rescue ......................................................................................................42
    2.19.     Rescue Organizing ....................................................................................45
    2.20.     RESCUE PLAN .........................................................................................46
    2.21.     SAFETY IN RESCUE OPERATIONS .......................................................47
    2.22.     SEARCH & EXTRICATION METHODOLOGIES ......................................48
    2.23.     ROPES CHAINS AND SLINGS ................................................................49
    2.24.     VARIOUS EQUIPMENTS USED IN RESCUE OPERATIONS ..................50
    2.25.     OPERATING INSTRUCTIONS FOR ELECTRICAL HAND.......................52
    2.26.     OPERATING INSTRUCTION FOR HYDRAULIC RESCUEDEVICE (HRD) .
              ..................................................................................................................60
Accidents and Disasters are unpredicted and unavoidable. Indian Railway has its
own mechanism to deal with rescue and restoration work during accidents and
disaster is ART & ARME.
Accidents: Any unusual event which affects the safety and transportation of Railway
in the form of damaging rolling stock, permanent structure and serious injuries /
causalities to the Railway passengers / Railway staff is known as Rail accidents. Any
accidents involving more than 100 injuries should be termed as disasters.
Disasters are caused by human mistakes and equipment failures. i.e. Collisions,
Derailments, Fire, Natural Calamities, Sabotages.
1.1.    ART Classification and types
    •   Class A
    •   Class B
    •   Class C
1.2.    ARME Classification & types
    •   Scale – I
    •   Scale - II
2. OPERATIONS
2.1.    Organizational issues, such as yardsticks and selection criteria to
        provide suitable personnel.
    1. The staff for deployment in Accident Relief Trains should be carefully chosen.
       They should be physically fit, must have stamina to do strenuous work for long
       extended hours.
    2. Average age of unskilled persons working in ART/ARME/140 T Crane should
       not be more than 50 years. The upper age limit for artisans should be 52 and
       of supervisors, it should be not more than 52 years. Older persons, who can’t
       perform strenuous duties, should gradually be withdrawn from ART/ARME's.
    3. ART staff inducted for Breakdown duties must be qualified. They must
       possess a certificate in any course from ITI.
    4. Staff deployment for Accident Relief Train should be as under:
       • All nominated staff attached to break down should be deployed at accident
           site.
       • Only core staff will be permanently deployed for the maintenance of break
           down crane and ART equipment.
       • But the staff other than maintenance gangs when not required for break
           down duties shall carry on their normal work at ROH, IOH, and Diesel Trip
           Shed etc.
    5. In “A” class ART total 44+14=58 staff nominated should be deployed at
       accident site to facilitate simultaneous operation of crane and HRE. Total staff
       in “A” class ART for crane operation should be 35 and staff in "A" class ART
       for LUKAS/MFD operation should be 23.
    6. Only core staff required for maintenance of break down crane and ART
       equipment would remain with ART permanently attached to carry out:
2.6.1     In “A” class ART Total number of coaches will be 5+3 wagons with one
          140 T Crane.
 1st    vehicle will 140 T capacity diesel/steam break down crane with Match
 be                   Truck
 2nd    vehicle will RT/BCN HS (Crane packing Van and heavy tools, wire ropes &
 be                   OHE material
 3rd    vehicle will Crane Staff and Kitchen Van.
 be
 4th vehicle will BRN HS (containing Rails and Crossings).
 be
 5th vehicle will BCN HS (complete Engineering Material and OHE items)
 be
 6th vehicle will Tool and Equipment Van (All critical mechanical tools, office,
 be               and Fire fighting section. Provision of guard seat with guard van
                  valve)
 7th vehicle will C&W, Elect. and Telecom.Van (Material of Telecom, Elect. &
 be               C&W)
 8th vehicle will Re-railing Equipment Van (MFD/LUKAS equipment and its
 be               material)
 9th vehicle will Staff and Kitchen Van (MFD/LUKAS staff and Kitchen).
 be
2.6.2     In “B” class ART total number of vehicles would be 6 since ART would
          be without Break down crane and Match Truck. The composition would
          be same as above.
2.6.3  More often than not only LUKAS/MFD is ordered without Break down
       crane, Break down crane too ordered without Lucas/MFD. If only
       LUKAS/MFD is ordered then the Break down formation would be as
       under:
 1st vehicle will BRN HS (containing Rails and Crossings).
 be
 2nd vehicle will BCN HS (complete Engineering Material and OHE items)
 be
 3rd vehicle will Tool and Equipment Van (All critical mechanical tools, office,
 be               and Fire fighting section. Provision of guard seat with guard van
                  valve)
 4th vehicle will C&W, Elect. and Telecom. Van (Material of Telecom, Elect. &
 be               C&W)
 5th vehicle will Re-railing Equipment Van (MFD/LUKAS equipment and its
 be               material)
 6th vehicle will Staff and Kitchen Van (MFD/LUKAS staff and Kitchen).
 be
2.6.4   If only Break down Crane is ordered then the formation of Break down
        train would be as under:
 1st vehicle will be         140 Te. Capacity diesel/steam break down crane
                             with Match Truck.
 2nd vehicle will be         RT/BCN HS (Crane packing Van and heavy tools,
                             wire ropes.
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                           Page 11 of 100
Maintenance & Operation Manual                                         Part II- ART & ARME
 3rd vehicle will be                Crane Staff and Kitchen Van.
Note: Seating arrangement for staff will be available in both formations according to
the staff requirement.
      Only 13 staff for the purpose of maintenance of break down crane and ART
      equipment in “A” class ART would be deployed. When not required for break
      down duties then other 31 staff out of total 44 would carry on their normal
      work at ROH, IOH, Diesel trip shed and Diesel Shed etc. (See item No.2 & 4)
      Only 9 staff for the purpose of maintenance of ART equipment in "B" class
      ART would be deployed. When not required for break down duties then other
      14 staff out of total 23 would carry on their normal work at ROH, IOH, Diesel
      trip shed and Diesel Shed etc. (See item No.6)
2.8.1. Deployment of Staff in the Kitchen for “A” & “B” class ART and
       SPART:
 Dept               Designation             No.        Duties at accident site
                                             of
                                            staff
 Mech.              Artisan/Khalasi             3      Over all supervision and management
                                                       of Kitchen, cooking of meals.
 Elect.             Electrician/Khalasi         1      Assistance in cooking and serving of
                                                       meals
 Engg/S&T           Khalasi/Gangman             1      Assistance in cooking and serving of
                                                       meals
 TOTAL                                          5
2.8.2. Scale of Rations for ART:
(Ref: Appendix IV of committee’s report of 1985)
Scale of ration proposed for 40 breakdown staff attached to the ART, to be
purchased from local market and replaced after every trip.
1.    Puri 80 Kg.
                            a. Potatoes              19.5 Kg
                            b. Beson (flour)         7.0 Kg
                            c. Onions                1.0 Kg
                            d. Ground nut oil        1.8 Kg.
Note: Potatoes’ and Onions may be replaced every two weeks if not used. Scale
      fixed jointly by maintenance loco Inspector/In-charge of Break Down & the
      commercial inspector of BSL Div.(Appendix-IV)
        On reaching at accident site, the crack team shall perform following activities: -
     a. Extrication/removal of injured passengers from the coach.
     b. First Aid to the injured.
     c. Provide succour and help to the passengers at site.
     d. Relieve panic and create re-assurance among passengers.
A-Team:
1. The team will apply Hydraulic rescue device and Power cold cutter on
damaged/capsized coaches.
Team will develop suitable space on the coaches for entry of B-team for removing
injured/dead passengers.
B-Team:
1. On reaching ARME at accident site, the team shall ensure unloading of Power
cutter, Ladders, jacks and chain saw, Gas cutting equipment, etc.
2. The team will enter in to the damaged/capsized coaches and remove Injured/dead
with the help of stretchers.
C-Team:
1. On reaching ARME at accident site, the team shall ensure unloading of medical
items as per instructions of Doctor like Stretchers, Body bags & first aid boxes etc.
2. The team will remove dead bodies for keeping in body bags and shift injured as
well as dead in the tent at specified places.
D-Team:
1. The team will be responsible for unloading of Tents, Chairs, Tables, Umbrellas,
Garden umbrellas and install them at specified spots.
2. The team will provide other required items also to the A & B teams, as and when
IRCAMTECH/GWL/MECH/2022-23/ART/Manual/1.1                             Page 17 of 100
Maintenance & Operation Manual                                       Part II- ART & ARME
required.
E-Team:
1. During night, the team will unload, lighting equipment like, inflatable lighting tower,
Halogen lamps, DG sets, Hand lamps & distribution boards etc. and responsible for
providing lighting arrangement during relief and rescue.
2. During day time, the team will assist to B&C-Teams in first aid activities. The
Barrier tap will also be provided for covering of site of accident.
F-Team:
1. The team will arrange tea, coffee and drinking water to the injured and suffered
passengers at accident site.
2. Team will perform other duties also as per instructions of ARME Incharge.
2.12. The following Layout Drawings of ART coaches have been prepared
       after consulting Supervisors and Officers of CRWS, Bhopal and with
       inputs from various ART incharges.
 Sr.No.     Description of Rolling stock                Proposed Drawing No.
 1          Tool and Equipment van                      TAEV-003 RT
 2          C&W, Electrical and Telecom van             CETV-004 RT
 3          Re-railing Equipment van                    RREV-005 RT
 4          Staff and Kitchen van                       SKV-006 RT
 5          Crane Staff and Kitchen van                 CSKV-003 RT
 6          Engineering and OHE Material van            EOM-002 BCNHS
 7          Crane Packing and OHE Material van          CPOM-002 BCNHS or RT
 1st vehicle           140 T capacity Diesel Hydraulic break down crane with
                       Match Truck
 2nd vehicle           BCN HS (Crane packing Van and heavy tools, wire ropes &
                       OHE material)
 3rd vehicle           Crane Staff and Kitchen Van.
 4th vehicle           BRN HS (containing Rails and Crossings).
 5th vehicle           BCN HS (complete Engineering Material and OHE items)
 6th vehicle           Tool and Equipment Van (All critical mechanical tools,
                       office, and Firefighting section. Provision of guard seat with
                       guard van valve)
 7th vehicle           C&W, Elect. and Telecom Van (Material of Telecom, Elect. &
                       C&W)
 8th vehicle           Re-railing Equipment Van (MFD/LUCAS equipment and its
                       material)
 9th vehicle           Staff and Kitchen Van (MFD/LUCAS staff and Kitchen)
2.12.3 Benefits:
Crack     --             --                 Mechanical-4   --           --           --
Team                                        Medical-2
                                            TOTAL-6