SQL 3
SQL 3
10 0.014556
46 0.066958
20 0.029112
26 0.037846
14 0.020378
20 0.029112
32 0.046579
27 0.039301
14 0.020378
20 0.029112
32 0.046579
35 0.050946
23 0.033479
29 0.042213
54 0.078603
14 0.020378
14 0.020378
17 0.024745
28 0.040757
30 0.043668
33 0.048035
24 0.034934
29 0.042213
31 0.045124
27 0.039301
10 0.014556
12 0.017467
12 0.017467
16 0.02329
11 0.016012
710 1.033479
tion: 452 Days
rt: 05/07/2025
ish: 12/23/2026
st: ₱ 100,000,000.00
QUIRED :
DESCRIPTION NO.
Project Engineer 1
Site Engineer 1
Foreman 2
Skilled 25
Labor 20
20
26
14
20
32
27
14
20
32
35
23
29
54
14
14
17
28
30
33
24
29
31
27
10
12
12
16
11
ITEM NO. DESCRIPTION % OF UNIT
TOTA
L
101 Pre-Construction 0.000 L.
201 Foundation 0.000 cu.
RC WORKS (Ground Floor)
301 Slab on Ground 0.000 cu.
302 Columns (Ground Floor) 0.000 cu.
303 Stairs (Ground Floor) 0.000 cu.
304 CHB Layering (Ground Floor) 0.000 sq.
RC WORKS (Second Floor)
401 Beam & Slab (Second Floor) 0.000 cu.
402 Columns (Second Floor) 0.000 cu.
403 Stairs (Second Floor) 0.000 cu.
404 CHB Layering (Second Floor) 0.000 sq.
RC WORKS (Third Floor)
501 Beam & Slab (Third Floor) 0.000 cu.
502 Columns (Third Floor) 0.000 cu.
503 CHB Layering (Third Floor) 0.000 sq.
504 Roof Beam 0.000 cu.
Sub-total for B P
C. Tot P
al
(A
D. Output/day +
Name and Specifications Quantity Unit Unit Cost
E. Materials
L50x50x5 angle bar 185 pcs ₱1,014.00
Gusset Plates & Fasteners 19 sets ₱150.00
Welding rods 15 kgs. ₱200.00
C-purlains 10 pcs. ₱1,200.00
Sub-total for E
F. Direct Cost (C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s 2016
H. Contractor's Profit 8% per D.O 197 s
2016 (CP)
I. Value Added Tax 5% per D.O 197 s
2016 (VAT)
J. Total Unit Cost
Amount
52800
118800
69300
240,900.00
Amount
4,800.00
0.00
4,800.00
245,700.00
Amount
₱187,590.00
₱2,850.00
₱3,000.00
₱12,000.00
205440.00
451,140.00
45114
36,091.20
22,557.00
554902.20
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME CBC DORMITORY
Sub-total for A
Name and Capacity No. of No. of Days Daily Ra
Equip.
BEquipment, (2014 ACEL Rates)
Sub-total for B
C. Total (A+B)
480.00
D. Output/day
Name and Specifications Quantity Unit Unit Co
E. Materials
Main Busbar 1 set ₱17,4
Panel Busburs 3 sets ₱10,5
Neutral & Ground Busbars 6 sets ₱7,0
Phase Busbars 9 sets ₱7,0
PANEL BOARD 3 sets ₱1,2
MAIN SAFETY BREAKER(100 AMP) 3 sets ₱1,5
CIRCUIT BREAKER (30 AMP) 18 sets ₱38
CIRCUIT BREAKER (20 AMP) 9 sets ₱35
CIRCUIT BREAKER (15 AMP) 15 sets ₱30
2.0 MM SQ. THWN COPPER WIRE 11 rolls ₱2,2
5.5 MM SQ. THWN COPPER WIRE 6 rolls ₱2,7
3.0 MM SQ. THWN COPPER WIRE 11 rolls ₱2,3
PVC CONDUIT (15 MM) 1700 m ₱50
PVC CONDUIT (30 MM) 600 m ₱80
JUNCTION BOX W/ SCREW 70 sets ₱25
UTILITY BOX 80 sets ₱25
ELECTRICAL TAPE 90 pcs ₱30
KILOWATT HOUR METER 1 pcs ₱1,2
Sub-total for E
F. Direct Cost (C+E)
G. Overhead, Contingencies and Miscellaneous
10%per D.O 197 s
201
H. Contractor's Profit (CP) 8% per D.O 197 s 2016
I. Value Added Tax (VAT) 5% per D.O 197 s 2016
J. Total Unit Cost
te Amount
0 22400
0 50400
0 29400
102,200.00
P Amount
te
0.00
P 0.00
P 102,200.00
st Amount
00.00 ₱17,400.00
00.00 ₱31,500.00
00.00 ₱42,000.00
00.00 ₱63,000.00
50.00 ₱3,750.00
70.00 ₱4,710.00
5.00 ₱6,930.00
0.00 ₱3,150.00
0.00 ₱4,500.00
60.00 ₱24,860.00
00.00 ₱16,200.00
19.00 ₱25,509.00
.00 ₱85,000.00
.00 ₱48,000.00
.00 ₱1,750.00
.00 ₱2,000.00
.00 ₱2,700.00
50.00 ₱1,250.00 384209.00
486,409.00
48640.9
6
38,912.72
24,320.45
598283.07
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME CBC DORMITORY
Sub-total for A
Name and Capacity No. of No. of Days Daily Ra
Equip.
BEquipment, (2014 ACEL Rates)
Sub-total for B
C. Total (A+B)
480.00
D. Output/day
Name and Specifications Quantity Unit Unit Co
E. Materials
1-1/2" gate valve 9 pcs ₱25
150 ф PVC riser pipe 4 pcs ₱30
3" riser pipe 4 pcs ₱40
1-1/2 " CWL pipe 65 rolls ₱30
1-1/2 " tee threaded 11 pcs ₱81
1-1/2 " 90D elbow threaded 20 pcs ₱61
150 ф PVC pipe 63 pcs ₱30
100 ф PVC pipe 53 pcs ₱10
100 ф PVC tee threaded 29 pcs ₱81
100 ф sanitary tee threaded 38 pcs ₱82
100 ф 45D elbow threaded 22 pcs ₱50
100 ф 90D elbow threaded 35 pcs ₱50
100 ф PVC couplings threaded 25 pcs ₱50
150 ф PVC 90D elbow threaded 32 pcs ₱50
Sub-total for E
F. Direct Cost (C+E)
G. Overhead, Contingencies and Miscellaneous Contractor's Profit (CP)
Value Added Tax (VAT) Total Unit Cost 10% per D.O 197 s 201
H. 8% per D.O 197 s 2016
I. 5% per D.O 197 s 2016
J.
te Amount
0 22400
0 33600
0 24500
P 80,500.00
te Amount
0.00
P 0.00
P 80,500.00
st Amount
1.00 ₱2,259.00
0.00 ₱1,200.00
0.00 ₱1,600.00
0.00 ₱19,500.00
.00 ₱891.00
.00 ₱1,220.00
0.00 ₱18,900.00
7.00 ₱5,671.00
.00 ₱2,349.00
.00 ₱3,116.00
.00 ₱1,100.00
.00 ₱1,750.00
.00 ₱1,250.00
.00 ₱1,600.00
62406.00
142,906.00
6 14290.6
11,432.48
7,145.30
175774.38
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME CBC DORMITORY
Sub-total P
for B
C. P
D. Output/da
480.00
y
Sub-total
for E
F. Direct
Cost
(C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s
2016
H. Contractor 8% per D.O 197 s 2016
's Profit
(CP)
I. Value 5% per D.O 197 s 2016
Added
Tax (VAT)
J. Total
Unit
Cost
Amount
52800
79200
0
132,000.00
Amount
54,064.00
0.00
54,064.00
186,064.00
Amount
₱8,640.00
₱1,190.00
₱1,178.32
₱234.84
₱10,500.00
₱6,540.00
₱8,750.00
₱8,640.00
₱9,300.00
₱12,600.00
₱15,400.00
82973.16
269,037.16
26903.716
21,522.97
13,451.86
330915.71
Item : 701(1) Tile Works (Ground
No./Description Floor)
Unit of : sq.m.
Measurement
Output per hour :
Quantity : 1457.6
4
Sub-total for B P
C. Total P
(A+B)
D. Output/day
480.00
Sub-total for E
F. Direct Cost (C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s 2016
H. Contractor's Profit 8% per D.O 197 s
2016 (CP)
I. Value Added Tax 5% per D.O 197 s
2016 (VAT)
J. Total Unit Cost
DETAILED UNIT PRICE
PROJECT NAME CBC DORMITORY
ANALYSIS
Amount
0.00
0.00
151,200.00
Amount
₱194,700.00
₱10,205,000.00
₱20,700.00
₱7,440.00
₱5,915.00
₱207,390.00
₱68,400.00
10709545.00
10,860,745.00
1086074.5
868,859.60
543,037.25
13358716.35
TILE WORKS
AREA 40 CM 60 CM 30X60 30 CM CEME SAND ADHESI
28 176.4 CM NT 12.6 0.7 VE
4.666667
6.44 40.572 2.898 0.161 1.073333
1457.636 4081.381 655.9362 36.4409 242.9393
55.82002 156.2961 25.11901 1.395501 9.303337
9.530001 53.36801 4.288501 0.23825 1.588334
1557.4 216.97 4237.6 53.36 0 700.84 38.935 259.57
3 2 8 8 2 7 1
GROU
T 2.52
0.5796
87.45816
3.349201
0.6671
94.574
1
Item : 701(2) Tile Works (Second
No./Description Floor)
Unit of : sq.m.
Measurement
Output per hour :
Quantity : 1495.6
5
Sub-total for B P
C. Total P
(A+B)
D. Output/day
480.00
Sub-total for E
F. Direct Cost (C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s 2016
H. Contractor's Profit 8% per D.O 197 s
2016 (CP)
I. Value Added Tax 5% per D.O 197 s
2016 (VAT)
J. Total Unit Cost
DETAILED UNIT PRICE
PROJECT NAME CBC DORMITORY
ANALYSIS
Amount
0.00
0.00
162,000.00
Amount
₱194,700.00
₱10,230,000.00
₱21,600.00
₱7,500.00
₱5,915.00
₱208,940.00
₱68,400.00
10737055.00
10,899,055.00
1089905.5
871,924.40
544,952.75
13405837.65
TILE WORKS
AREA 40 CM 60 CM 30X60 30 CM CEME SAND ADHESI
34.569 217.7847 CM NT
15.55605 0.864225 VE5.7615
6.44 40.572 2.898 0.161 1.073333
1461.074 4091.008 657.4834 36.52685 243.5124
55.82002 156.2961 25.11901 1.395501 9.303337
9.530001 53.36801 4.288501 0.23825 1.588334
1567.4 258.35 4247. 53.36 0 705.34 39.185 261.23
3 7 3 8 5 8 9
GROU
3T.11121
0.5796
87.66445
3.349201
0.6671
95.371
6
Item : 701(3) Tile Works (Third
No./Description Floor)
Unit of : sq.m.
Measurement
Output per hour :
Quantity : 1495.6
5
Sub-total for B P
C. Total P
(A+B)
D. Output/day
480.00
Sub-total for E
F. Direct Cost (C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s 2016
H. Contractor's Profit 8% per D.O 197 s
2016 (CP)
I. Value Added Tax 5% per D.O 197 s
2016 (VAT)
J. Total Unit Cost
DETAILED UNIT PRICE
PROJECT NAME CBC DORMITORY
ANALYSIS
Amount
0.00
0.00
162,000.00
Amount
₱265,100.00
₱10,297,500.00
₱21,960.00
₱7,560.00
₱5,980.00
₱210,800.00
₱70,200.00
10879100.00
11,041,100.00
1104110
883,288.00
552,055.00
13580553.00
TILE WORKS
AREA 40 CM 60 CM 30X60 30 CM CEME SAND ADHESI
38.125 240.1875 CM NT
17.15625 0.953125 VE
6.354167
6.44 40.572 2.898 0.161 1.073333
1471.029 4118.882 661.9632 36.77573 245.1716
55.82002 156.2961 25.11901 1.395501 9.303337
9.530001 53.36801 4.288501 0.23825 1.588334
1580.9 280.7 4275.1 53.36 0 711.42 39.523 263.49
4 6 8 8 5 6 1
GROU
3T.43125
0.5796
88.26176
3.349201
0.6671
96.288
9
Item : 801(1) Ceiling (Ground
No./Description Floor)
Unit of : sq.m.
Measurement
Output per hour :
Quantity : 1309.7
2
Sub-total for B P
C. Total P
(A+B)
D. Output/day
480.00
Sub-total for E
F. Direct Cost (C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s 2016
H. Contractor's Profit 8% per D.O 197 s
2016 (CP)
I. Value Added Tax 5% per D.O 197 s
2016 (VAT)
J. Total Unit Cost
DETAILED UNIT PRICE
PROJECT NAME CBC DORMITORY
ANALYSIS
Amount
0.00
0.00
152,400.00
Amount
₱432,715.00
₱256,700.00
₱51,340.00
₱166,440.00
₱23,600.00
₱136,500.00
1067295.00
1,219,695.00
121969.5
97,575.60
60,984.75
1500224.85
CEILING WORKS
T
AREA CHANN FURRI WALL CLIP BOAR LIND
EL
1309.716 779.5929 NG
2338.779 ANGLE
2566.179 D
5457.15 454.7625 RIVE
94288.49
Sub-total for B P
C. Total P
(A+B)
D. Output/day
480.00
Sub-total for E
F. Direct Cost (C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s 2016
H. Contractor's Profit 8% per D.O 197 s
2016 (CP)
I. Value Added Tax 5% per D.O 197 s
2016 (VAT)
J. Total Unit Cost
Amount
0.00
0.00
165,100.00
Amount
₱362,415.00
₱232,600.00
₱91,420.00
₱139,065.00
₱23,200.00
₱114,275.00
962975.00
1,128,075.00
112807.5
90,246.00
56,403.75
1387532.25
CEILING WORKS
T
AREA CHANN FURRI WALL CLIP BOAR LIND
EL
1096.934 652.9371 NG
1958.811 ANGLE
2325.164 4570.56 D380.88 RIVE
84774.59
Sub-total for A P
Name and Capacity No. of No. of Days Daily Rate
Equip
B Equipment, (2014 ACEL Rates) .
Sub-total for B P
C. Total P
(A+B)
D. Output/day
480.00
Sub-total for E
F. Direct Cost (C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s 2016
H. Contractor's Profit 8% per D.O 197 s
2016 (CP)
I. Value Added Tax 5% per D.O 197 s
2016 (VAT)
J. Total Unit Cost
Amount
0.00
0.00
165,100.00
Amount
₱455,100.00
₱274,500.00
₱114,780.00
₱174,835.00
₱21,800.00
₱143,500.00
1184515.00
1,349,615.00
134961.5
107,969.20
67,480.75
1660026.45
CEILING WORKS
T
AREA CHANN FURRI WALL CLIP BOAR LIND
EL
1377.152 819.7334 NG
2459.2 ANGLE D
2744.013 5738.134 478.1778 RIVE
100651.5
Sub-total for B
C. Total (A+B)
480.00
D. Output/day
Sub-total for E
F. Direct Cost (C+E)
G. Overhead, Contingencies and Miscellaneous Contractor's Profit (CP)
Value Added Tax (VAT) Total Unit Cost 10% per D.O 197 s 201
H. 8% per D.O 197 s 2016
I. 5% per D.O 197 s 2016
J.
te Amount
0 43200
0 32400
0 18900
94,500.00
P Amount
te
0.00
P 0.00
P 94,500.00
st Amount
00.00 ₱173,600.00
00.00 ₱76,000.00
50.00 ₱23,800.00
00.00 ₱140,600.00
00.00 ₱9,600.00
423600.00
518,100.00
51810
6 41,448.00
25,905.00
637263.00
Item No./Description : 1001 (1) Paintworks (Ground
Floor) Unit of Measurement : sq.m.
Output per hour :
Quantity : 1,480.185
Sub-total P
for B
C. P
D. Output/da
480.00
y
22400
33600
19600
75,600.00
Amount
4,800.00
0.00
4,800.00
80,400.00
Amount
₱203,250.00
₱51,375.00
₱87,000.00
₱58,500.00
₱11,400.00
411525.00
491,925.00
49192.5
39,354.00
24,596.25
605067.75
Item No./Description : 1001 (2) Paintworks (Second
Floor) Unit of Measurement : sq.m.
Output per hour :
Quantity : 1645.24
Sub-total P
for B
C. P
D. Output/da
480.00
y
Sub-total
for E
F. Direct DETAILED UNIT PRICE
Cost ANALYSIS
PROJECT NAME CBC DORMITORY
(C+E)
10%
G. Overhead, Contingencies and Miscellaneous per D.O 197 s
H. 2016
Contractor 8% per D.O 197 s 2016
's Profit
(CP)
I. Value 5% per D.O 197 s 2016
Added
Tax (VAT)
J. Total
Unit
Cost
Amount
24000
36000
21000
81,000.00
Amount
4,800.00
0.00
4,800.00
85,800.00
Amount
₱224,930.00
₱56,855.00
₱96,280.00
₱64,740.00
₱12,920.00
455725.00
541,525.00
54152.5
43,322.00
27,076.25
666075.75
Item No./Description : 1001 (3) Paintworks (Third
Floor) Unit of Measurement : sq.m.
Output per hour :
Quantity : 1576.24
Sub-total P
for B
C. P
D. Output/da
480.00
y
24000
36000
21000
81,000.00
Amount
4,800.00
0.00
4,800.00
85,800.00
Amount
₱214,090.00
₱54,115.00
₱91,640.00
₱61,620.00
₱12,160.00
433625.00
519,425.00
51942.5
41,554.00
25,971.25
638892.75
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME CBC DORMITORY
Sub-total for B
C. Total (A+B)
480.00
D. Output/day
Sub-total for E
F. Direct Cost (C+E)
G. Overhead, Contingencies and Miscellaneous
10% per D.O 197 s 201
H. Contractor's Profit (CP) 8% per D.O 197 s 2016
I. Value Added Tax (VAT) 5% per D.O 197 s 2016
J. Total Unit Cost
0 25600
0 76800
0 33600
136,000.00
P Amount
te
0.00
P 0.00
P 136,000.00
st Amount
0.00 ₱1,080.00
0.00 ₱3,040.00
0.00 ₱6,240.00
7.00 ₱10,275.00
0.00 ₱20,700.00
99.00 ₱41,998.00
9.00 ₱5,890.00
.00 ₱1,470.00
60.00 ₱81,880.00
50.00 ₱25,250.00
40.00 ₱15,520.00
10.00 ₱117,990.00
4.00 ₱15,466.00
1.00 ₱2,510.00
1.00 ₱4,016.00
353325.00
489,325.00
48932.5
6
39,146.00
24,466.25
601869.75
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME CBC DORMITORY
Sub-total for A
Name and Capacity No. of No. of Days Daily Ra
Equip.
BEquipment, (2014 ACEL Rates)
a. Excavators218.0027,032.0
b. Payloader218.0013,864.0
c. Compactor36.0013,865.0
d. Bulldozer218.0013,864.0
e. Dumptruck518.0011,360.0
f. Circle Saw Bar cutter314.00400
Sub-total for B
C. Total (A+B)
480.00
D. Output/day
Sub-total for E
F. Direct Cost (C+E)
G. Overhead, Contingencies and Miscellaneous
10% per D.O 197 s 201
H. Contractor's Profit (CP) 8% per D.O 197 s 2016
I. Value Added Tax (VAT) 5% per D.O 197 s 2016
J. Total Unit Cost
te Amount
0 60800
0 136800
0 93100
P 290,700.00
te Amount
0 973,152.00
0 166,368.00
0 249,570.00
0 499,104.00
0 1,022,400.00
.00 16,800.00
0.00
P 2,927,394.00
P 3,218,094.00
st Amount
₱15,750.00
0.00
₱16,500.00
00.00
₱74,000.00
00.00
₱62,000.00
00.00
₱108,000.00
5.00
₱887,500.00
8.00
₱83,276.00
54.6
49 36.4
63 28
53.2
3831280.00
7,049,374.00
6 704937.4
563,949.92
352,468.70
8670730.02