Approximate TOWN HOUSE - Estimate

The document outlines the budget and detailed cost breakdown for the Town House Taman Melati project, totaling 121,655.66. It includes various construction elements such as framing, roofing, walls, finishes, and sanitary fittings, each with specified quantities and rates. Each section provides a detailed description of the work and associated costs, ensuring a comprehensive overview of the project's financial requirements.

Uploaded by

slidestore.myr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views4 pages

Approximate TOWN HOUSE - Estimate

The document outlines the budget and detailed cost breakdown for the Town House Taman Melati project, totaling 121,655.66. It includes various construction elements such as framing, roofing, walls, finishes, and sanitary fittings, each with specified quantities and rates. Each section provides a detailed description of the work and associated costs, ensuring a comprehensive overview of the project's financial requirements.

Uploaded by

slidestore.myr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

PROJECT : Town House Taman Melati

GFA 25 m2

Description Unit Qty Rate Amount


S/1 Summary

1 work below lowest flr finish 2,500.00

2 frame 6,250.00

3 upper floor 4,500.00

4 roof 13,365.16

5 staircase structure and finishes 13,000.00

6 external wall 11,072.00

7 internal wall & partition 3,648.00

8 windows & doors 8,300.00

9 ironmongery 2,800.00

10 internal wall finishes 7,900.00

11 int floor finishes 4,215.00

12 int ceiling finishes 3,440.00

14 ext. finishes 10,758.00

15 sanitary fittings 7,740.00

16 Sundries 4,150.00

17 Ext Works w Lot Boundry 18,017.50

TOTAL 121,655.66

13
PROJECT : Town House Taman Melati

GFA 25 m2

Description Unit Qty Rate Amount

element no. 1- work below lowest


floor finish
A GFA m2 25 100.00 2,500.00

collection 2,500.00

elemen no. 2 - frame


A GFA m2 25 250.00 6,250.00
collection 6,250.00

element no. 3 - upper flr


A upper floor area m2 30 150.00 4,500.00
collection 4,500.00

element no. 4 - roof


Flat roof
A 150mm thick concrete m2 21 47.00 982.30
B reinforcement kg 401 3.80 1,524.86
C formwork m2 21 35.00 731.50
D Waterproofing system m2 21 35.00 731.50
Pitch Roof
E Pitch roof trusses m2 32 80.00 2,560.00
F Conc roof tiles m2 32 65.00 2,080.00
G G.I Rain gutter m 13 120.00 1,560.00
H Accessories (30%) 624.00
J Thermal insulation m2 32 16.00 512.00
K Aluminium chicken wire mesh m2 32 2.00 64.00
L 100mm dia. Rainwater down pipe (4nos) m 45 35.00 1,575.00
M bend no 4 35.00 140.00
N shoe no 4 35.00 140.00
P debris trap no 4 35.00 140.00

collection 13,365.16

element no. 5 - staircase structure and finishes


A Flight 2 6,500.00 13,000.00
collection 13,000.00

element no. 6 - external wall


A Brickwall m2 256 38.00 9,728.00
B Parapet Wall(1000mm height) m2 13 38.00 494.00
C RC Wall(800mm height) m2 17 50.00 850.00
collection 11,072.00

element no. 8 - internal wall & partition


A Brickwall m2 96 38.00 3,648.00
collection 3,648.00

13
PROJECT : Town House Taman Melati

GFA 25 m2

Description Unit Qty Rate Amount


element no. 7 - windows & doors
A Casement window m2 10 350.00 3,500.00
B Flush door 900 x 2100 no 8 350.00 2,800.00
C PVC Door 750 x 2100 no 4 210.00 840.00
D Main Door 1500 x 2100 no 2 580.00 1,160.00
collection 8,300.00

element no. 9 - ironmongery


A number of door 14 200.00 2,800.00
collection 2,800.00

element no. 10 - internal wall finishes


A skim coating m2 408 7.50 3,060.00
B 20mm screed to rec ceramic m2 40 15.00 600.00
C ceramic wall m2 40 55.00 2,200.00
D paint m2 408 5.00 2,040.00
collection 7,900.00

element no. 11- internal floor finishes


Homogeneous Tiles
A screed to homo. Tiles m2 9 15.00 135.00
B Homogeneous Tiles m2 9 80.00 720.00
Ceramic Tiles
C screed to ceramic Tiles m2 44 15.00 660.00
D Ceramic tiles m2 44 55.00 2,420.00
E Waterproofing system m2 8 35.00 280.00
collection 4,215.00

element no. 12 - internal ceiling finishes


A Skim Coating m2 8 7.50 60.00
B Asbestos ceiling board m2 53 55.00 2,915.00
C Painting to ceiling m2 61 5.00 305.00
D Extra for forming access panel no 2 80.00 160.00
collection 3,440.00

13
PROJECT : Town House Taman Melati

GFA 25 m2

Description Unit Qty Rate Amount


element no. 14 external finishes
Wall
A plaster to wall and column m2 316 16.00 5,056.00
B painting to wall and column m2 316 12.00 3,792.00
Floor
C Cement and sand paving smooth m2 9 15.00 135.00
D Apron m2 0 25.00 -
E Perimeter drain m 15 75.00 1,125.00
Ceiling
F Skim Coating m2 28 7.50 210.00
G Asbestos ceiling board m2 0 55.00 -
H Painting to ceiling m2 28 10.00 280.00
J Extra for forming access panel no 2 80.00 160.00
collection 10,758.00

element no. 15 sanitary fittings


A water closet no 4 650.00 2,600.00
B wash hand basin no 4 380.00 1,520.00
C wash sink no 4 400.00 1,600.00
D soap holder no 4 35.00 140.00
E paper holder no 4 35.00 140.00
F mirror no 4 120.00 480.00
G hose hand bidet no 4 60.00 240.00
H bib tap no 4 30.00 120.00
J basin pillar tap no 4 35.00 140.00
K Shower rose no 4 120.00 480.00
L floor trap no 8 35.00 280.00
collection 7,740.00

element no. 16 Sundries


A Counter top 1000 x 600 no 2 500.00 1,000.00
B MS railing 1200mm height m2 9 350.00 3,150.00
collection 4,150.00

element no. 17 Ext Works w Lot Boundry


A Chamber item 1,500.00
B Turfing m2 5 3.50 17.50
C MS deco fencing m2 17 500.00 8,500.00
D MS gate no 1 8,000.00 8,000.00
collection 18,017.50