Internee Report Draft (New)
Internee Report Draft (New)
5 MVA, Dyn 11
Transformer
Submitted By
Name: Md. Azizul Haque
ID No.: 142-0134-011
Advising Semester: Spring 2017
Installation and Commissioning.” At City Auto Rice and Dal Mills Ltd. Embodies the
results of my own research work, prepared under the supervision of Mr. Ariful Islam,
Technology (ADUST).
We further affirm that the work reported in this internship original and is no part or
whole of the report has been submitted by any other students for the completion of
i
Letter of Permission
ii
Letter of Approval
iii
Letter of Recommendation
iv
iv
Certificate of Approval
B.Sc. Intern entitled:
“33 kv/ 11 kv, 7.5 MVA, Dyn 11 Transformer
Installation and Commissioning.”
Done under my supervision, meets acceptable presentation that is standard and can be
in partial fulfillment of the requirement for the degree of Bachelor of Science (B.Sc.)
Date…………………….. …………………………………
(Ariful Islam)
Assistant Professor
Dept. of EEE, FST
Atish Dipankar University of Science and
Technology, Banani, Dhaka-1213
v
Declaration
I hereby declare that this submission is my own work and to the best of my
knowledge it contains no materials, which are exactly, same, which were previously,
Date: …………….
…………………………….
(Md. Azizul Haque)
B.Sc. Student.
ID: 142-0134-011
Dept. of EEE, FST
vi
ACKNOWLEDGEMENTS
All praises go to Allah, the almighty, for the successful completion of this
internship and fulfillment of author’s dream into reality. However, thanks and
gratitude are also due to the following persons for their continuous support in
I render my heartiest gratitude and sincere respect to Mr. Ariful Islam, Assistant
Professor Faculty in EEE for assigning us such a perfect internship report to work and
practice in real for our inspiration, guidance, valuable suggestion, generous support
I also convey grateful thanks to Mr. Moni Gopal Boshu. Sr.Manager (Electrical) of
Engineering Department.
I would like to thank to office sub stuff & book shatter for providing us relevant
1
Executive Summary
This internship report is originally written based on the power transformer installation
works. Field level experience on erection and commissioning has been integrated
here. This report can also be used as a guide book to power transformer installation.
In my project site final assembly, operation, inspection and maintenance works has
been done based on the information presented in this report. Connections not written
in this report or operation which deviates from the descriptions should not be done
without consulting with the manufacturer. However, this report can help him if
someone wants to work on transformer installation. Here in the internship report book
covers the following topics- Factory Preparation for dispatch, Cautions for
packages and unpacking, Catalogue for various accessories and Drawing requirements
for erection works. Above all, my internship report book plays a role in transformer
installation works.
2
TABLE OF CONTENTS
Page
Dedication i.
Letter of Permission ii.
Letter of Approval iii.
Letter of Recommendation iv.
Certificate of Approval v.
Declaration vi.
ACKNOWLEDGEMENTS 01
Executive Summary 02
TABLE OF CONTENTS 03
3
3.6 Supervised DC System & Grounding works 21
4
4.27 Oil Level 37
4.28 Leakage of Oil 38
4.29 Oil Valves 38
4.30 Gasket Joints 38
4.31 Gas Operated Relay 39
4.32 Dehydrating Breather 40
4.33 Temperature Indicators 41
4.34 Pressure Relief Vent 42
4.35 Pressure Relief Device 42
4.36 Terminal Connections 43
4.37 Auxiliary Wiring 43
4.38 On Load Tap Changer 44
4.39 Radiators 44
4.40 Earth Terminal 44
4.41 Fans 44
4.42 Cooler Control Cubicle 45
4.43 Oil Inspection 46
4.44 Oil Warning 46
4.45 Oil Sampling 46
4.46 Inspection of Sample (BS 5730-1979) 47
4.47 Electrical Strength (BS 5703-1979) 47
4.48 Crackle Test For Moisture (BS 5730-1979) 48
4.49 Acidity (BS 5730-1979) 48
4.50 Sludge (BS 5730-1979) 49
4.51 Flash-Point (Closed) (BS 5730-1979) 49
4.52 Frequency of Testing 50
4.53 Recording The Results 50
4.54 Recommended Action 50
4.55 General 52
4.56 Gasket Joints 52
4.57 Oil Valves 52
4.58 Terminal Connections 52
4.59 Silica Gel Breather 53
5
4.60 Gas Actuated Relay 53
4.61 Temperature Indicators 53
4.62 Thermometer Pocket 53
4.63 Oil Levels 53
4.64 Pressure Relief Vent 54
4.65 Pressure Relief Device 54
4.66 Earthing 54
4.67 Insulation Tests 54
4.68 Voltage Ratio and Continuity Test 55
4.69 Magnetizing Current Tests 55
4.70 Winding Resistance Measurements 55
4.71 Dielectric Fluid Sampling 55
4.72 Temperature Indicators 55
4.73 Gas Operated Relay 56
4.74 Fans 56
4.75 Cooler Control 57
4.76 Alarm and Trip Circuits 57
C. Observed attitudes and gained values
4.77 Attitude and gained values 58
D. The most challenging task performed:
4.78 Factory Preparation for Dispatch 58
4.79 Inspection on Site 59
4.80 Inspection for Exteriors 60
4.81 Transportation from Factory to Site. 61
4.82 Handling on Site 62
4.83 Location and Site Preparation 62
4.84 Inspection and Test Prior to Operation (Commissioning) 64
4.85 Caution When Energizing Transformer. 65
6
5.4 Paint Flanking or Rust Occurrence 69
5.5 Oil Level Discrepancy 69
5.6 Abnormal Noise Level 70
5.7 Foul Odors 70
5.8 Thermometer Reading Discrepancy 71
5.9 Contamination on the Bushing Porcelain 71
5.10 Draining of Insulation Oil 71
5.11 Measurement of Insulation Resistance 71
5.12 Deterioration of Insulating Oil 74
5.13 Standard for the Estimation of Oil Deterioration 75
7
6.22 Grounding 84
2.23 Neutral Point 85
6.24 Safety Ground 85
6.25 Equipment Ground 86
CHAPTER EIGHT
Conclusion 98
REFERENCES 99
APPENDIX 100
8
Chapter One
Overview of the Organization
1.1 History
The date 6th February, 1972 marks the journey of a valiant effort in Gandaria, Dhaka
- one which marked the beginning of the company known as "CITY OIL MILLS" -
the founder Chairman; Mr. Fazlur Rahman started the group from scraps virtually.
The initial period was marked with a lot of hardships due to the post war era when the
country faced economic fallout. Initially the mission of the company was to produce
mustard oil for the local market consumption. The overwhelming demand for the
product propagated and the company soon found its way into the business arena.
For the next 18 years, the company operated within the vicinity of the Dhaka city and
met the demands of the local market. The revenue generated from this soon gave
away for the entrepreneur to evolve the company, which was by now one of the
largest mustard oil producing plants in the country. A vision - to transform the
company to a 21st century conglomerate of the country started. "City Vegetable Oil
Mills" was established at Rupshi, on the outskirts of Dhaka city. This effort evidenced
an accelerated growth of City Group and the company was soon found to open two
more sister concerns by the year 1994 - "Hasan Vegetable Oil Mills Limited" and
Within this period the founder also devised new production units and soon the brand
“TEER" was born, the name itself captivating the hearts and minds of the people.
Appearing in this banner was the flagship product, "TEER SOYABEAN OIL", which
products of City Group soon found its way into the hearts of the people. City Group
9
was by now one of the emerging industries of the country with an ever-expanding
business, which led to 21 sister concerns by the end of the year 2006.
needs of the consumers both home and abroad. Till now City Group is one of the
largest company in the country, and business reaching foreign countries making it one
of the best conglomerates of the country. A year of meticulous work has paid off and
by now CITY GROUP has started its alteration towards an International Standard
over 45 years of experience in the edible oil industry and expanded its wings of
different areas of production. Incorporating Flour, Dal, Feed, Salt, Sugar and Pure
Drinking Water in the product line and integrating vertically; the Group has been in
City Group is dedicated to optimize the quality of the produced consumer items.
Strength lies in the Group's ability to use state-of-the-art technology from Europe and
other countries and imported high grade raw materials which are the finest in the
world. The production facilities are well equipped with top notch machinery from
Singapore, Japan, Switzerland, Germany, USA, Taiwan, Belgium, Thailand, and best
quality raw materials are collected both from overseas and local suppliers. A
vertically integrated concern having more than 15,000 skilled manpower and with a
true depth of market penetration City Group has the physical advantage of all its
mills, factories and establishments being spread over 330 acres of land in the old part
10
of Dhaka i.e. Gandaria; expanding industrial belt at Konapara, Demra, and Rupshi,
The secret of success of City Group lies in fulfillment of all its business
relationship with its customers, employees and all other social groups. All the
members of City Group are actively involved in maintaining the ideals established by
Company founder. Almost four decades of this epic industrial journey can only be
1.3 Production
Started Operation In: 1985, Production Capacity (24 hrs.): 100 M. Tons
Functionality: Supports all the civil construction works of the Group with quality MS
Started Operation In: 1990, Production Capacity (24 hrs.): 100 M. Tons
Functionality: Refines quality Soya Bean Oil from imported CDSO and Super refined
Palm Olean from imported CPO to meet increasing demand of the local market.
Functionality: Supplies all sorts of PP woven bags and Plastic linings to meet in-
house demands
11
05. Hasan Plastic Industries Ltd.
Started Operation In: 1998, Production Capacity (24 hrs.): 40,000 drums
Started Operation In: 1998, Milling Capacity (24 hrs): 200 M. Tons
Functionality: Produces the finest and popular brand of Flour, Atta and Semolina,
“Teer”.
Started Operation In: 1999, Production Capacity (24 hrs.): 20,000 Cartons
Functionality: Meets the Group’s own requirement and also supports printing of
Started Operation In: 1999, Production Capacity (24 hrs): 16,000 Pcs
Functionality: Supports the Group with quality plain & printed tin containers made
from plain tin sheets for marketing its own products i.e. refined oils, vanaspati.
Functionality: City PET Industries Ltd., the FDA approved factory lifts water from a
depth of 600 feet and purifies it using German Ozone technology and Reverse
Osmosis system to process around 1,00,000 liters of truly hygienic natural mineral
12
11. Shampa Oil Mills Ltd.
Functionality: Shampa Oil Mills Limited, was set up as an expansion of the most
Started Operation In: 2001, Production Capacity (24 hrs.): 250 M. Tons
Functionality: Ensures a purified and constant supply of beans, a key food grain, in
Started Operation In: 2002, Production Capacity (24 hrs.): 1,000 M. Tons
Functionality: Farzana Oil Refineries Limited, has got Vanaspati and Canola Oil in
their product range. The raw materials are directly imported from world’s finest
sources and refined with latest technology to ensure that the product reaches the
Acquired In: 2004, Situated At: North Patenga on the bank of the river Karnaphuly in
Chittagong
Functionality: The Terminal has more than 50 tanks, including bonded ones, with a
total storage capacity of about 1.5 Lac Tons of Crude Oil, Bitumen, and Lubricants
etc. Within the compound, there is the VOTT Oil Refineries Ltd. having a refining
Started Operation In: 2004, Production Capacity (24 hrs): 500 M. Tons
Functionality: Ensures a constant quality of full range poultry, fish and cattle feeds.
13
16. Deepa Food Products Ltd.
Functionality: Deepa Food Products Ltd., has got Vanaspati and Canola Oil in their
product range. The raw materials are directly imported from world’s finest sources
Started Operation In: 2005, Production Capacity (24 hrs.): 1000 M. Tons
Functionality: Produces Soya meals and Rapeseed cakes every day. The raw materials
of Latin America and Europe are processed with technologically superior DESMET
BALLESTRA machines to ensure a rich protein source for poultry and fish.
Started Operation In: 2005, Production Capacity (24 hrs): 250 M. Tons
Functionality: Every micro crystal of “Teer Iodized Salt”, produced in City Salt
Started Operation In: 2006, Production Capacity (24 hrs): 1650 M. Tons
Functionality: Produces Teer Refined Sugar, the highly consumed refined sugar in the
market. This large factory refines imported crude sugar in fully automated SU-Tech
machines of Thailand.
Started Operation In: 2007, Production Capacity (24 hrs): 1, 10,000 Pcs
14
Functionality: Supplies all sorts of PP woven bags and Plastic linings to meet in-
house demands.
Started Operation In: 2009, Milling Capacity (24 hrs): 550 M. Tons
the art technology is a valuable addition in City Group’s arsenal in catering to the ever
Pilot Project
the art technology is a valuable addition in City Group’s arsenal in catering to the ever
1.4 Competitors
City Group is one of the leading conglomerates industries in Bangladesh. The main
15
Marketing: More than 2,000 employees are work in this department. They are
making strong and challenging market in country and abroad. They are always study
Sales: Sales is another strong team in City Group. Countrywide they make a network
of sales. They continuously try to grow up the sales volume and relation buildup with
customer.
Finance Department- This department is divided into two parts: 1) Account and 2)
Finance. Both parts are work for making bills, bill collection, bank reconciliation,
Import & Export- Raw materials for production line and foreign parts import
procedure, custom clearance, export, shipping and related all jobs done by them.
Production- This department always engaged for more productivity. City group have
23 plus productive industry. They are control and run production line. Operation and
is actually run by Engineers. They give their services at Line and system maintenance.
They also do all type of maintenances about the distribution and connection.
16
Chapter Two
Plan of Internship Program
Both parts are work for installation, maintenance, repairing and modification works.
This department have more than 55 manpower including engineers, technicians and
helpers. Mechanical have 35 person and electrical have others 20 persons in their
team. Both groups have their own workshop separate for regular works. Electrical
department responsible for two type jobs: 1) Power Line 2) Automation. A technical
GM commending the department and both group have section manager to guide them.
I successfully completed my internship in City Auto Rice and Dal Mills Ltd. From
06th March, 2017 to 05th June, 2017. I have completed 288 hours internship on
DAY
DATE DURATION DAY ACTIVITY
NO
17
03 April 2017 9.00 am to Transformer Erection & Fittings of
05
Monday 5.00 pm Accessories
The production department always helped us. When we went to field for maintenance
These production departments were always engaged in greater production. City group
have 23 plus productive industry. They control and run production line. Operation and
them. I learned about the nature of the machine, operation of the machine and
18
Chapter Three
Training Program
My training program was designed by the authority of City Auto Rice and Dal Mills
Ltd. They trained me according to their schedule. They have associated me with
various tasks at different times and have given me responsibilities. Here I am trying to
I was the first to work with a transformer erection team. While working with them, I
have been watching all the things and acted according to their direction. From them I
was able to learn about the structure and function of the transformer. Physically I
checked all the parts like as Core, Winding, Tank, Fittings & Accessories, Cooling
System, General, Radiators, Conservator, Cooling Fan, Control & Protective Devices,
Winding, WTI, OTI, GAR, Pressure Relief Device, and Magnetic Oil Gauge with
them. I also checked all the parts status. Whenever I got damaged and broken in a
According to the packing list, I was given the responsibility of maintaining the
register book to receive the product properly. The representative of the product
suppliers were handing over the product to me. Then I checked the quality of all the
products. After receiving the products, I told my supervisor to provide the necessary
clearance certificate.
19
3.3 Supervised Transportation and Lifting Work
I used to supervise transformer transportation and lifting works. More than 25 skilled
workers worked with me. All the works like as Transportation from Factory to Site,
Handling on Site, Location and Site Preparation, Safety, Inspection and Test Prior to
After fitting the transformer accessories, I used to cooperate with my team in the
inspection work. There were follow two types of inspection works, one is monthly
condition consist of Oil level, Leakage of Oil, Gas Operated Relay, Silica Gel
Breather, Temperature Indicator checking etc. The Annual Inspection done in de-
energized condition consist of Oil Level, Leakage of Oil, Oil Valves, Gasket Joints,
Vent, Pressure Relief Device, Terminal Connections, Auxiliary Wiring, On Load Tap
Changer, Radiators, Earth Terminal, Fans, Cooler Control Cubicle, Oil Inspection ,
Oil, Oil Warning, Oil Sampling, Inspection of Sample (BS 5730-1979), Electrical
Strength (BS 5703-1979), Crackle Test For Moisture (BS 5730-1979), Acidity (BS
The first thing we noticed before energizing the power of transformer testing was that
Gasket Joints, Oil Valves, Terminal Connections, Silica Gel Breather, Gas Actuated
Vent,, Pressure Relief Device, Earthing. We are also doing Commissioning Test,
20
Insulation Tests, Voltage Ratio and Continuity Test, Magnetizing Current Tests,
Indicators, Gas Operated Relay, Fans, Cooler Control and Alarm and Trip Circuits.
Equipment Ground.
I cooperated with the expert team on the protection relay setting and Release Device
and Relay, Instantaneous Over current Relay, Definite Time Relay, Induction Relay,
Magnetic overload relay, Thermal overload relay, Reverse power relays, Over current
relays with A.C Tripping, Combined overload and earth leakage protection,
I checked all the works according to the approved drawing given to me, as instructed
by my supervisor during the transformer erection. If I had ever seen any kind of
21
Chapter Four
Learning Experiences
A. Knowledge acquired
At my internship I have been able to acquire various types of knowledge about
for me at the same time grate opportunity to learn. Down here I will try to share my
2. Filling of the transformer tank with oil up to the level above coil
6. Fitting of conservator
9. Fitting of bushings
When opening the transformer tank, precaution must be taken to prevent moisture
ingress. If wet air enters into the transformer, it may be cooled by the transformer wall
below its dew point and may be condensed. It may be lowered the dielectric strength
of the transformer. Do not enter the transformer tank until the nitrogen gas has been
entirely dissipated. When working the tank, take care especially not to drop tools or
foreign substances. Worker should not carry anything unnecessary in the tank. Care
should be taken to see that all nuts, bolts and lead connections are properly tightened
and all parts in right places. Also check the internal terminal connections. When the
work in the tank is completed, the inside of the tank should be inspected. Check that it
is clean and right and no foreign substances are left behind. For inside cleaning dry,
Lifting lugs are located on the upper part of the transformer tank for lifting the
transformer. Lifting eyes are provided on the top core channel for removing the core
23
and coil assembly. If the transformer is lifted without the tank cover, the cable must
4.4.1 Installation on the base- When the transformer is skidded, moved on rollers or
jacked up, take care that it does not damage the base or turn over the transformer. The
transformer is also equipped with jacking bosses. Jack should be placed under the
jacking bosses. The transformer should never be lifted or moved when jacking up
radiators or other accessories. When rollers are used, skids must be placed between
4.4.2 Fitting of accessories- Position and direction of the accessories and other parts
should be according to the transformer drawing exactly. Before fitting read the
4.4.3 Fastening with bolts and nuts- Each bolts and should be screwed tight but in
order to avoid stripping of the bolts, pay attention that it is not over tightened. Use
24
Table.2 Suitable torque of the Stainless bolts
Radiators are shipped separately. Blank covers are attached to the opening of radiators
and radiator valves to prevent moisture. Radiator valve is located on each radiator
without lowering the oil of the transformer tank. Each radiator has the oil drain plug
and an air relief plug. So, it is easy to drain the oil individually. The radiator
withstands the same vacuum (full vacuum) and pressure condition as the main tank.
Radiators are so designed and manufactured that any radiator can be placed at any
25
Hoist the radiator from the stored position and pay attention not to damage other
Remove the blank cover and gasket on the radiator valve of the transformer
Clean the gasket groove of the valve. Apply a small amount of adhesive to the
Hoist the radiator by crane car with the side of the flange on which the number is
Pull the radiator by hand, incline it and drain the residual oil inside the radiator.
Match the radiator valve and flange surface of the radiator and clamp them by
nuts.
Clamp the pair of nuts located diagonally one after another in order to clamp
Clamp them tightly until the radiator valve and radiator flange closely match with
each other.
Turn the handle to clock wise direction and set the handle at a vertical position to
open the valve. Turn the handle to anti-clock wise direction and set the handle in
26
4.7 Fitting of Conservator
4.7.1 Conservator- The conservator is shipped separately and filled with nitrogen to
keep out moisture. When mounting the conservator on the transformer, it is necessary
to take care of the proper positioning. Hoist the conservator tank by car crane placing
4.7.2 fitting the protective relay- Install the bushels relay to the conservator before
connecting valve. Remove the blank cover of the flange surface and change gasket for
a new one. Install the relay to the conservator and clamp blots tightly and uniformly.
Be sure to set the relay in the direction indicated on the nameplate fitted to it.
4.7.3 Mounting the conservator on the transformer- When the above operation is
complete, lift the conservator using lifting lugs and mount firmly at the specified
4.8.1 Fittings- The cooling fans are to be attached to the radiator panel. Mounting
brackets for fan should be fastened on main body with proper tightening. Fans to be
mounted with net as per the G.A drawing. The fans have to be installed to the
supports by nuts fastened surely. The fan motors should be placed so that their cable
4.8.2 Cabling- Each fan motor is directly connected to the marshalling box through
four-core armored cable. Proper cable glands (stainless steel) are to be used at entry or
exit point of any boxes. The route of the cable should be as per the specified
drawings. Cable tray or support for running the cable should be provided on the tank
body.
27
4.8.3 Checking- After the completion of wirings, supply the proper power to the fan
motors and make sure that the fans rotate in normal direction and without abnormal
sound.
The oil piping should be in accordance with the diagram of PIPING ROUTE and
PIPING SYSTEM shown in the instruction manual and based on the number tag
a) Removal of blank covers from the separated oil pipes- Oil piping is provided
for connecting the oil circuit of various accessories and some oil piping is transported
separately. Prior to fitting the oil pipes, remove the blank cover from them. Then
remove old gaskets used for the blank covers. In the consequent step, be sure to wipe
off foreign matter with a dry waste. If the painted face is found to be spoiled, repaint
b) Checking the ventilation of oil pipes- When cleaning of oil pipes is finished,
pass either dry air or nitrogen gas through the oil pipe and make sure that there are no
foreign materials.
c) Removal of the blank cover from the oil pipes on the transformer side-
Remove the blank covers and clean the piping faces. Ingress of any foreign material is
strictly prohibited.
d) Assembling- Apply a small amount of adhesive to the gasket and fit the
gasket. Tighten the clamp bolts in diagonal order and evenly until the flange faces
match.
e) The connecting valves are also joined to oil pipes by means of above
procedures.
28
4.10 Gas Actuated Relay
while installing other parts. Care should be taken in unpacking the bushing package to
avoid damage of the porcelain. Before fitting the bushing, clean the porcelain and the
Make connections to both ends of the bushing in such a manner that strain is avoided.
When heavy bus bars are connected to bushings, flexible connections should be used
to prevent damage that might possibly result from expansion and contraction due to
temperature changes. Be sure that all connections are tight enough to prevent local
heat of terminal.
When bushings are installed on the transformer, replace the gasket with a new one.
The flange should be fixed uniformly by nuts in such manner as shown in figure
29
below. Each pair of stud bolt 1-1́, 2-2́ and 3-3́ should be tightened with nuts at same
While working, worker should not use the gloves and tools unless those are tied to the
worker with hempen strings to prevent them being dropped into the transformer tank.
To prevent direct contact of coil and insulator with atmosphere during assembling of
transformer, it is desirable to fill with the insulating oil first up to a level about 25cm
below the tank cover (Fig-1). It is necessary to carry out a dielectric strength test of
Take sample form each drum and check whether the contents have the specified
dielectric strength. If not, filter the entire oil content. Oil filling should be carried out
only after its dielectric strength reaches the specified value. There are two methods for
oil filling. The first method is to fill through the drain valve while discharging
(gradually) the nitrogen gas stored in the tank (Fig-2). The nitrogen gas pressure in
the transformer tank should be kept at a valve between 0.005-0.02Mpa during oil
filling.
The second method is to fill after vacuuming the transformer (Fig-3). This is the
superior method.
When fitting the silica gel breather, do not expose the silica gel charge to the
atmosphere for an undue length of time, otherwise the gel charge will start to absorb
moisture and thus impair its operating property. The breather should be erected as
follows:
30
Remove oil cup by turning in anti-clockwise direction.
Remove breather port blanking paper ring from underside of breather body, thus
exposing ports
Screw breather body in clockwise direction, onto the transformer breather pipe.
Fill the oil cup with transformer oil to BS148, to the level indicated
The instruments are fitted in the marshalling/control cubicle, located on the side. The
instrument bulbs are fitted in their respective pockets found on the tank. Ensure that
horizontal plane will upset the zero of the switch setting scales. Care is needed when
running the capillary, sharp bends should be avoided particularly where it joins the
The capillary should be supported by suitable clips at intervals of 300 to 450 mm and
a suitable length provided so that the bulb may be freely installed or removed.
4.15 Draining the Insulating Oil While Filling With Nitrogen Gas
After all accessories except dehydration breather (this should be installed after the
completing of oil filling) have been installed, drain off the quantity of insulating oil
from the transformer in order to eliminate foreign matter, dust etc. form the oil as well
as any other parts which may absorb. Supply nitrogen gas into the transformer to
displace insulating oil. Do not allow the transformer internal pressure to become
negative. Seating pressure of nitrogen gas should be from 0.005 to 0.02MPa. After
31
draining the total quantity of insulating oil from the transformer, arrange the machine
parts as illustrated in the last page of this clause (OPETARING OF VALVES) and
preferred to fill oil at low humidity. Drums should be opened only at the time
when the oil is needed. Before filling the oil, take sample from the drum and test
The oil filling apparatus should be clean and free from moisture. Care should be
taken to prevent moisture from being introduced into the oil through oil line.
Do not energize the transformer when vacuuming and filling the oil.
Usually the partition wall of tap selector switch compartment cannot withstand at full
vacuum. Before exhausting air from the transformer, connect the equalizing pipe
located between the switch compartment and the transformer tank in order to maintain
Exhaust air from the transformer for more than 12 hours by means of the vacuum
pump and check that degree of vacuum inside the transformer is than 3 mmHg by
32
Connect valve (2) to vacuum pump
Connect valve (5) & OLTC drain valve through vacuum tube.
2) Open (2), (4), (5), (6), (7), (8), (9), (10), (12) & OLTC drain valve.
Exhaust air from both the tank & conservator tank until the degree of vacuum is not
3) After the transformer has been carried out vacuum treatment described above,
maintain vacuum for one hour, then open the oil drain valve (1) and pump
degassed oil into the tank. The insulating oil should be through the oil filter press
4) During oil filling, continue the operating of vacuum pump. When degree of
vacuum becomes more than 3 mmHg, temporarily suspend oil filling and operate
5) When the oil level comes to about 100mm below the oil filter valve (2), stop
vacuum pump and shut (2). Then, continue oil filling under favor of remaining
degree of vacuum.
6) When the indicator of main tank oil level gauge indicates suitable level read from
“oil level-oil temperature pointer” then stop oil filling (shut (1). Oil will go from
main conservator to the OLTC conservator through vacuum tube. After the
closing valve (1), close valve (8) & (9) and remove vacuum tube.
7) Open (7) gradually so that filled oil in OLTC conservator tank is poured into the
8) Close valve (4) and take off the vacuum line, the vacuum gauge etc.
33
9) Attach the dehydrating breather for main tank and close all opening such as oil
10) Oil filling in OLTC: See section 6 of OLTC installations and commissioning
guide available in the motor drive mechanism. As the bottom filter valve of main
tank is connected to the drain valve of OLTC, so during vacuum cycle OLTC
will be vacuum and during oil filling cycle oil will go to OLTC due to vacuum.
4.18.2 Residual gas release and oil level adjustment- Allow more than 8 hours for oil
to permeate into the immersed parts after oil filling. Then release residual gas from
various parts by loosening the air relief plugs until oil escape.
After residual gas is released, carry out oil level adjustment according to ‘the oil level
N.B: During vacuum operation the valve if available at breather pipe end it has to be
shut, otherwise temporally valve has to be fixed for closing the opening.
34
B. Skills learned
inspection and testing. My mentor Mr. Moni Gopal Bosu really helped me to achieve
the skill of the work. I did not know how to do a transformer test before my internship
because it’s not possible without field work. Below I’ll describe how transformer
4.19 Inspection
Monthly inspection can be carried out without any interruption service and by an
taken out of service so that a more comprehensive and through examination can
be made. At the same time, the operation of various protective devices and
4.20 Precautions
35
4.20 Precaution
Personnel engaged on the erection of transformers should remove any loose tools or
personal possessions from their pockets before gaining access to the transformer
interior. Small metal items dropped into the tank would be difficult to remove and
ingress of any foreign material in the interior part is strictly prohibited. Spanners and
similar tools should be secured with strong cord to some external part of txr lid.
To prevent the ingress of dirt, it is essential to clean the area around all drain plugs,
air-release plugs and filter valves thoroughly before draining or commencement of oil
filling. Before breaking a pope work joint or a cover join, ensure that it is clean.
Whenever such a joint is broken, blank it off immediately to prevent the ingress of
dirt or moisture. Before covers are refitted or jointed. A thorough inspection should be
made to ensure that no foreign matter is left inside and all faces are clean and dry.
Compare the oil level in the gauge of the conservator with the cold oil level marking,
on both prismatic gauge and magnetic oil gauge, making appropriate allowance for oil
temperature if the transformer is not cold. If oil level is low, new oil should be added
Look for the sign of oil leakage from welded scams, radiators, flanges, plugs, bosses
and valve outlets. If none are found and oil level is correct, then no further action is
required to be taken. If any oil leakage is found, tighten up flange bolts or screw down
valve in question. Do not top up with new oil until any leakage is cured.
36
4.23 Gas Operated Relay
Check if any gas is trapped in the body of the relay. Any gas present would be visible
Ensure that the silica gel crystals are active (blue). If not, replace with new silica gel
in accordance with the instruments. Ensure that the oil seal cup is full of transformer
oil to the indicated level. For tilling, unscrew the cup by turning it.
Check that the thermometer bulb is properly in position. Ensure that any capillary
tubes are free from any king of interruption for its proper operation. Record reading of
4.26 Transformer
Examine the transformer tank and fittings to ensure that no rust is forming especially
at the welded seams. If so, it should be completely removed with a wire brush or other
means and the metal has to be given a coat of zinc phosphate primer paint, followed
Check the condition of the prismatic oil gauge, if damaged, lower the oil level and fit
a new gauge. Check the condition of the magnetic oil gauge, if damaged, lower the oil
37
level and replace it with new one. Check alarm/trip operation of gauge by lowering
the oil level in the tank. Ensure that the transformer contains oil to the gauge level. If
the oil level is low, top up in accordance with the given instructions.
Look for signs of oil leakage form welded seams, radiators, flanges, plugs, bosses and
valve outlets. If none are found and oil level is correct, then no further action is
needed to be taken. If oil level is low, new oil should be added to bring the oil up to
If any oil leakage is found, tighten up flange bolts or screw down the valve in
question. Do not top up with new oil until any leakage is cured.
Ensure that the drain valves, filter, sampling valves and all air release plugs are fully
closed.
Ensure that the isolating valves between each radiator and the tank, isolating valves
between conservator, turrets and main tank and isolating valves between OLTC
Ensure that all gasket joints are properly tightened. This applies to:
Inspection covers
Conservator cover
Pipe joints
38
Valve flanges
Bushing flanges
After the equipment has been in service for some time, it may be found that the
compression gaskets have shrunk a little and that small oil leaks have been developed
at some of the joints. It is advisable therefore to carry out a general inspection of the
To prevent oil leaks all joints fitted with gaskets must be tightened after the first 6 to
tightened since too much force may break off the stud. Special care must be taken
when tightening the oil seals on molded terminals. The tightening of all covers fitted
with gaskets must be carried out carried out carefully and gradually to avoid undue
stress on bolts or studs and distortion to covers. Nuts or bolts must be tightened a little
After carrying out the tightening described, if the oil lead still persists, the oil should
be lowered below the gasket level and an inspection of the gasket should be carried
Check if any gas is trapped in the body of the relay. Any gas present would be visible
through the windows of the relay and may be siphoned off. Any gas trapped in the
relay may be the indicative of a faulty condition and if gas is seen to be present in the
relay body it should be drawn off through the gas test cock. Check that the pipe into
which the relay is connected is not distorted. The angle of the pipe slope is very
39
important. The slope must be upwards towards the conservator at an angle of between
4.31.1 Trip Element: Test trip element operation by opening the valve on a bottle of
dry air so that air rushes in, impinges on the flap, depresses it and operates the switch.
The approximate minimum air pressure required to operate the switch should be
4.31.2 Alarm Element: Test alarm operation, by slowly admitting dry air from a air
bottle, so that the alarm element gradually falls until the switch operates. The quantity
of air required to operate the switch may be observed on the graduated scale engraved
on inspection windows on each side of the relay and should be noted for the purpose
The trapped gases can be withdrawn from the device by means of the cap fitted in the
cover. Air released to atmosphere through the upped cap which has been collected in
the gas chamber during in order to fulfill the chamber with oil.
Examine the color of the silica gel charge and if the pink showing has reached half
way up the container, it is recommended that the charge should be changes for a fully
active one.
Remove the expanded metal guard retaining nut and the guard.
Slacken the two wing nuts at the top of the breather sufficient to slides out the
silica gel container, retaining the top and bottom sealing gaskets in position.
40
Replace with a reactivated container, ensuring that the top and bottom sealing
Tightened the wing nuts and replace the oil seal bowl filled to the correct level
should be maintained until the whole of the gel has been turned blue. The most
effective method of reactivation is to pass a stream of hot air through the gel
container. Suitable reactivates are available for this purpose from silica gel lit.
Care must be taken to ensure these temperatures are not exceeded, or the moisture
Check that the thermometer bulbs are properly in position. Ensure that all capillary
tubes are free from kinks and all joints for any leakage of operating fluid.
Check that the instruments are mounted in a vertical position, as error, particularly in
the horizontal plane, will upset the zero of the mercury switch setting scales.
Check correct operation of the switches. This can be done by rotating the pointer
checked. Remove the temperature sensitive bulb from its pocket on the tank and
element.
41
The oil should now be warmed through definite intervals to a maximum temperature
of 120ºC and instrument readings have to be checked against the thermometer. The
instrument should be allowed to steady off at each interval to allow for its inherent
4.33.2 Switch adjustment: The mercury switches should be adjusted to operate at the
required valves. Each switch is set by slackening the locking screws on each arm and
moving the left hand setting pointer to the required operating temperature and the
right hand pointer to the resent temperature and retightening both screws should be
done.
The minimum switch differential is obtained by closing the right hand pointer to the
left hand pointer. A built-in stop automatically sets the minimum differential.
When carrying out any adjustment, the mercury switch table should be supported so
The diaphragm may be replaced simply by removing the bolted on lip of the
explosion vent. The diaphragm is clamped between two sealing gaskets at this point.
Check that the valve is closed. Indication of the valve opening is given locally by the
obtrusion of the indicator pin. To reset indicator pin, push the pin flush with the top
cover.
42
4.36 Terminal Connections
Check the integrity of the cable box end clamps and the box fronts should be bolted
up tightly. Check the integrity of the cable end clamps and the clamping screws
should be tightened. Oil leakage problem should be dealt with special attention.
Ensure that all bushings are clean and intact. Check all the lead supports to the
terminals
Check the auxiliary wiring for security of attachment, signs of any damage and
deterioration.
Examine the interior of the cubicle for security of attachment of all fittings and for
ingress of moisture.
Using a 1000 volt Mugger, test the auxiliary wiring between line and earth and
43
4.38 On Load Tap Changer
It is provided from MR Germany. Further information has been provided in the OLTC
section.
4.39 Radiators
Remove all foreign objects from the radiator panels. Hose radiator panels to remove
all dust and dirt which could impede cooling efficiency. Check all welded seams on
Check earth terminal for security of attachment. Ensure a good earth contact.
4.41 Fans
Check the fans for security of attachment and signs of conspicuous damage of
deterioration. The impeller and motor should be inspected to ensure that there is no
buildup of dirt or other matter that could cause overheating of the motor, obstruction
44
The motor bearings should be lubricated with lithium based grease. When carrying
out republication, it is essential that every trace of water and dirt is removed from
around the grease nipple and a clean gun should be used. Only a low pressure should
Motors with lubricators: If lubricators are fitted the fans should be re-lubricated after
16000 hours of running in ambient (up to 50ºC). For each 15ºC above 50ºC the
To re-lubricate the motor should be dismantled and the rotor removed, complete with
bearings. The old grease should be washed out with a good quality solvent. The
bearings should be refilled with grease, leaving the housing empty. If a bearing is
Check the cubicle for damage and security of attachment of tank. Check for damage
Test the operation of the fans by switching the cooler control switch ‘MANUAL’
position.
Test the operation of fans by switching the cooler control switch to the ‘AUTO’
position and adjust the indicating pointer on the winding temperature indicator
(WTI).
Check the operations of the contact at the recommended settings for alarm, trip
and fans by rotating the indicating pointer on the temperature indicators. Also
45
Oil Inspection
4.43 Oil
The oil supplied with the transformer is a pure hydrocarbon mineral oil conforming to
The oil in a transformer operating under normal load conditions, adequately ventilated
and free from moisture, will show little oil deterioration after years of service. If, due
prolonged periods, deterioration of the oil will be accelerated. Routine oil sampling
and testing should be carried out periodically so that from the information obtained it
may be possible to determine whether the oil is suitable for further service.
Excessive and prolonged skin contact with mineral oil should be avoided.
Samples of oil should be drawn from the transformer when the oil is warm. Sampling
cleaning of the drain valve. It is essential that the valve be first thoroughly cleaned
externally and then wiped with clean material reasonably free from fiber (such as thin
Finally, the valve should be flushed by draining off sufficient quantity of oil to ensure
that the sample obtained is representative of the oil at the bottom of the tank.
46
Stopper glass sampling bottles of one liter size are recommended. They must be
absolutely clean and dry and should be rinsed with the first sample drawn. Tests
A limited but amount of information can be obtained from the odor, appearance and
color of the oil. It should be noted for record purposes. Cloudiness in the oil may be
due to suspended moisture or suspended solid matter, such as iron oxide or sludge.
If the oil is dark brown, the presence of dissolved aspartames may be suspected. If the
color is green the presence of copper soaps is indicated and it may be expected that
further deterioration of the oil will be rapid. An acrid acid smell is indicative of
volatile acids which can cause corrosion and which may render the oil unsuitable for
treatment on site. A petrol- like or acetylene odor may indicate a low flash point due
Electrical strength is the max. Voltage which can be applied to an insulating material
without breakdown taking place. If frequent transient sparking occurs, this suggests
the presence of foreign matter e.g. moisture, fibrous material, carbon particles etc. and
the oil should be filtered. The electric strength of a sample of oil in service must never
be allowed to fall below 30kV. If it falls to this value, the oil should be reconditioned.
Ensure that any oil added to the system for the purpose of topping up has an electrical
47
4.48 Crackle Test for Moisture (BS 5730-1979)
The crackle test is simple and useful test for detecting the presence of suspend
moisture in oil.
A metal rod 12.5 mm diameter, heated to a dull redness is lowered to the bottom of
the receptacle and used to stir the oil thoroughly. During this stirring process no
crackle should be detected. Oil does not pass this test should be suitably treated.
The pungent odor of the oil will give an indication of the acidity. Acidity will cause
internal corrosion and if such an odor is present, immediate steps should be taken to
The equipment and solutions required to perform this test may be obtained from
supplier of laboratory apparatus and chemicals but in case of doubt the advice of oil
When the acidity is below 0.5mg. KOH/g no action needs to be taken if the oil is
satisfactory in other respects. When the acidity is above 0.5mg KOH/g the oil should
be re conditioned or discarded.
If the acidity is allowed to exceed 1.0mg KOH/g, there is a considerable risk of sludge
precipitation and corrosion of metal surfaces above oil level by condensed acidic
vapors. It may be possible to retain oil in service with acidity above this value
provided that frequent internal examination of the transformer is made, but this is not
recommended since the oil may reach a state at which it is not possible, economically,
for it to be reconditioned.
Regular filtration checks the development of acidity but is not effective in removing
acid once it has formed. To remove acid the oil may be returned to the oil supplier for
48
reconditioning or new oil may have to be provided but in either case the lower the
acidity at the time of changing the oil, the less the new filling will be affected by acid
breakdown owing to the restriction of cooling also a transformer with sludge deposits
Although there may be no solid deposits visible in oil samples, it is still possible that
sludge may have formed and that the concentration in the oil has not yet reached a
The presence of sludge may then be detected by dilution of the oil with heptanes and
it is recommended that this test be carried out if oil approaches 1.0mg KOH/g.
presence of precipitated sludge it may be necessary, even though the acidity may be
within the prescribed limit to consider applying treatment or changing the oil. When
sludge is allowed to accumulate, the oil circulating ducts become choked which
results in results in higher core and winding temperatures with consequent formation
more sludge.
Flash-point tests should be made if the oil has been subjected to a high temperature
due to an internal fault or shows any sign of unusual odor, but they are not otherwise
necessary.
49
A slow fall of the flash point of oil in a transformer may occur with increasing age
and is not harmful. A fall exceeding 15ºC may indicate unsatisfactory conditions such
matter providing a conducting path between live parts and the frame of the
transformer, in which case the units should be taken out of service for examination.
Oil in transformer tanks should be inspected annually and if practicable, test for
electrical strength and for crackle. The acidity of the oil should be determined in
every two years. In special cases, where severe operating conditions are encountered
or it is known that the oil is deteriorating at an abnormal rate; tests may be desirable at
It is essential to keep records of all tests. The acidity should be plotted on a graph with
time as a base and the records should include relevant operating data such as
Where a test result is outside the recommended limits, a fresh sample should be
rejection of the oil. If the electrical strength is below the limits given then,
50
Where oil is confirmed as failing to meet the limits and the cause is unknown, it is
address given.
thoroughly flushed through with unused oil before refilling and then refill.
In the following charts, fault analysis is confined to the cause of an alarm or trip.
Major faults occurring within the transformer e.g. to the core and windings should be
Gas in Buchholz
51
Check & Test before Energizing
4.55 General
Prior to connecting the transformer to the incoming and auxiliary supply lines, it is
necessary to complete the following tests and checks prior to commissioning the
transformer for normal service. It should be visually checked that all equipment is
mechanically satisfactory and that electrical wiring is in accordance with the relevant
drawings.
Ensure that all gasket joins are tight. It includes transformer tank joint, inspection
covers, cable box covers, conservator cover, pipe joints, valve flanges, Buchholz pipe
*Isolating valves between each radiator and the tank isolating valves between
Ensure that all bushings and palms are clean. Support all leads to the transformer in
terminals.
52
4.59 Silica Gel Breather
Ensure that the silica gel crystals are active (blue). If not, replace with new silica gel
in accordance with the instructions in section available in this manual. Ensure that the
oil seal cup is full of transformer oil to the indicated level. For filling, unscrew the cup
by turning it. Remove the plastic plug inserted in the base of the breather.
Check that the pipe into which the relay is connected is not distorted. The angle of the
pipe slope is very important. The slope must be upwards towards the conservator, at
petcock, any air, which may have collected in the gas chamber, so that the chamber is
full of oil.
Check that the thermometer bulb is properly in position. Also check the switch
manual.
Check the condition of the oil gauge glass. If damaged, lower the oil level and fit a
new one. Check that the conservator contains oil to the gauge level. If the oil level is
53
Check the operation of the magnetic oil level gauge by lowering the oil level
gradually.
Check that the diaphragm is intact. Replace if damaged. For this transformer pressure
Check that the valve is closed. Indication that the valve has opened is given locally by
To reset indicator pin push the pin flush with the top cover.
4.66 Earthing
The transformer tank should be effectively earthed before energizing the transformer.
Two earth pads are fitted to the tank side for this purpose.
Commissioning Test
The following insulation tests should be made using a 5000V Megger and the
readings noted.
HV Windings to Earth
LV Windings to Earth
HV Windings to LV Winding
54
4.68 Voltage Ratio and Continuity Test
Connect a three-phase, 4-wire low voltage supply to the H.V. Terminals; record the
exact values of applied and induced voltages. The transformer rated voltages can now
be calculated from the measured applied and induced voltages and should correspond
Connect a three-phase, 4-wire, low voltage supply to the H.V. terminals, record and
magnetizing current in each line. Compare the result with the factory tests. These
measured values should be kept for future reference should fault finding tests be
necessary.
Check the resistance of all windings using a Kelvin double bridge/ transformer
winding resistance meter. This result should be kept for future references.
Samples of fluid taken from the following positions should be tested in accordance
Samples prior to erection should be taken from tanker or each individual drum
Samples after final erection and filling should be taken from the sampling device.
55
Check and adjust the switch settings.
4.73.1 TRIP ELEMENT: Test trip element operation by opening quickly the valve on
a bottle of dry air so that air rushes in, impinges on the flap, depresses it and operates
the switch. The approximate minimum air pressure required to operate the switch
4.73.2 ALARM ELEMENT: Test alarm operation, by slowly admitting dry air from
an air bottle so that the alarm element gradually falls until the switch operates. The
quantity of air required to operate the switch may be observed on the graduated scale
engraved on inspection windows on each side of the relay and should be noted for the
NOTE: It will be appreciated that unless the transformer has been filled with oil under
vacuum, there will be a quantity of trapped air in the windings and core, which will
gradually be liberated during the first month of service. The rate of evolution is
indicated by the behavior of the trip and alarm contacts, and by the volume of gas
measured by the graduations marked on the gas chamber window. In the event of a
fault, the rate of gas evolution is related to the severity of the fault, and the
composition of the gas collected, related to the nature of the fault. The accumulation
4.74 Fans
Ensure the wiring is in accordance with the wiring diagram inside the terminal box.
56
phase motors require a trial connection to the supply; if the rotation is incorrect it can
be reversed by interchanging any two leads. Starting of the fans may be carried out
immediately the motor has reached full speed, to ensure that it does not exceed the
nameplate current.
No work should be carried out on the fan without first switching off and isolating the
Test operation of the fans by switching the cooler control switch to the ‘MANUAL’
Position. Test operation of the fans by switching the cooler control switch to the
‘AUTO’ Position, and adjust the indicating pointer on the Winding temp. Indicator.
57
C. Observed attitudes and gained values
During the internship time I can able to adopted corporate attitudes and developed my
personality. That was a great opportunity for make a bridge with field technician to
my mentor. They are always help me and finally I gained a corporate values.
The transformer is not dispatch with complete fittings but usually filled with oil. The
tank contains oil to just over the core and windings. Fittings are removed to facilitate
transport. It also indicates (in the G.A. Drawing) the fittings which are removed from
58
The transformer is transported in some sections like the main tank, bushings,
conservator, radiators and other accessories. The dismantled accessories are packed in
crates or boxes. The packing lists are attached with the boxes or crates in water proof
no report is received THREE DAYS after the delivery on site, we can assume that the
NOTE: The acceptance procedure must be carried out after each unloading so that the
59
4.79.2 Check for gas pressure
In order to prevent moisture impregnation, usually the main tank has to be filled with
After removing the protective cover for the pressure gauge mounted on the
transformer tank and opening the connecting valve and the gas pressure has to be
checked. After checking the pressure the valve has to be closed tightly. Positive
indication shows that air/water has not entered in to the tank. If the point reads zero,
air ingress might happen. At that point, the insulation resistance of the windings has to
4.80.1 Check for damage- Checking must be done if the transformer is dropped
4.80.2 Rust- When the painting is damaged or the metal parts are rusted, the rust has
4.80.3 Bolts and Nuts- If the bolts and nuts of covers or valves are found in loose
60
Caution
Before removing a manhole cover, transport plate or other device, vent the
transformer to the atmosphere pressure. Do not enter the transformer until the gas
space has been flushed with dry air or suitable oxygen (not less than 18% oxygen in
traveling speed of the trailer etc. should be regulated according to the conditions of
61
When the transformer is shipped by rail, there is no problem while the train is
running. However attention should be paid to prevent shock during loading and
unloading.
It is undesirable to incline the transformer too sharply. The angle of slope should be
within 10º.
It is better to install a tachometer on the trailer or the train or attach a shock meter to
the transformer itself. To measure the angle of slope of the transformer, use a plumb
bob.
In addition to the main lifting lugs, the tank has subsidiary jacking lugs. Whenever the
tank is lifted, whether empty or not, make sure the cover is bolted in position with the
When jacking or hauling the transformer, use only the jacking lugs and haulage holes
specially provided for this purpose. Never use anything else, such as the valves or
For any reason, if the internal parts of transformer are exposed to atmosphere, it must
be done only in dry conditions and moisture must not be allowed to contaminate the
solid insulation.
Mount the transformer on a level plinth to give an evenly distributed weight. Easy
access is provided all around in order to read or reach the diagram plate, valves, oil
gauge etc.
62
Storage: It is recommended that the transformer has to be put into service
1) The transformer tank is totally filled with dry nitrogen gas when stored for more
than four months from the date of delivery. The transformer tank should be filled with
insulating oil up to a level lower than the tank cover by 25cm. The gas space between
the cover and the oil should be filled with dry nitrogen. The gas pressure must be
checked periodically.
When stored at outdoor totally, cover the tank and accessories with strong water proof
sheets to prevent water ingress. Lay wooden beams under the tank and the boxes.
The tank and accessories should be stored in a dry and clean location free from
63
Safety
After assembling the transformer, check the installation in accordance with the
following.
1) Construction: Make sure that all parts are located in their proper position, and all
2) Connection: Make sure that electrical connections are complete and wring
3) Cooling equipment: Make sure that all radiator valves are open and cooling
control device; cooling fans have been tested for normal operation.
4) Tap changer: Make sure that tap changer operates smoothly and the tap position is
corresponding to the specified voltage. Control device for OLTC is normal condition.
6) Indicators: Check the oil level gauge or thermometers to confirm their calibration.
10) Grounding system: Make sure that the grounding system of the transformer is
complete. (Shine the surface of earthling pads which were painted to prevent rusting
during transportation, remove the paint for good connection of the earthling cable.)
11) Live parts of bushings and lighting arresters: Make sure that phase to phase to
When above inspections are complete, carry out the field test such as insulation
resistance measuring, ration test angular displacement measuring, BCT ration &
64
polarity, Magnetizing current test, % impedance test, Operation test for fan control
cubicle, operational test for OLTC & RTCC panel, Operation of the cooler etc.
When all inspections and test have finished, now the power transformer can be put
It is also necessary to observe the transformer for a few hours after loading.
65
Chapter Five
Problem Identification and Solution
It is very important to know this as an engineer while working in the field. When I
was working with my other guys in the field, we tried to find root cause of the
problems. For this case, my mentor always advised me to follow the ‘Maintenance
Schedule’. It was a very interesting fact that most problems were covered by this
schedule. We used to follow two types of ‘Maintenance Schedule’. One of them was
named (a). Routine Maintenance and Inspection (Frequency Weekly) and the other
was- (b) Periodical Maintenance and Inspection. Both topics are described below with
solutions –
66
As terminal is live part, pay attention (or light black).
not to stand close to the terminal. If giving out offensive
smell.
If abnormal voltage, Investigate the
8. Check voltage, current, load and current and load, condition of
frequency with respective instruments. current and load etc. distribution sys.
are confirmed. etc.
67
oil specimen, carry out oil, (see item
performance test concerning 7 for oil
respective items specified in filtration
BS-148, ASTM UTE C27-101. method).
4. Inspect for local heat Once a year For loose Refer to
damage, corrosion, or connections heat clause 8.7
contamination of terminals, and corrosion of
/ or loosening and corrosion of contamination is
terminals connections. Check contamination is
for contamination on terminal found See clause 8.9
and porcelain. When the
contamination of
terminal and
porcelain is
found.
5.3.1 In case of oil from drain valve or drain plug: In case of looseness of valve of
plug, refasten it. If oil leakage still does not stop, replace calve of plug. Exchange of
5.3.2 In case of oil leakage from gasket: In case of looseness of fastening part, re-
tighten. If oil leakage still does not stop, the gasket has to be replaced.
the oil thorough the drainage valve of plug until the oil level is below the gasket.
oil and grease from gasket fitting surface of valve, clean with wire brush etc. Wash
5.3.3 Disposition of insulating oil: The insulating oil removed during 6.1.2 (1) above
68
5.3.4 Oil-leakage from welded part:
The simplest way to repair a small leaking hole is to calk it carefully with a chisel.
Calking a small leaking hole with putty of paint is temporarily acceptable, but
A hole in cast iron can’t be repaired by welding the cast iron part has to be
replaced.
If a leak does not stop of is found in an important part of the equipment, consult
Where paint flaking or rust occurrence is found, polish with sand paper etc, and
1) If the oil level is above the specified valve-Drain oil thorough the drainage valve or
plug on the lower part of the tank, until the oil level meets the normal position.
2) If the oil level is under the specified valve-add oil thorough the filter valve on the
cover, until the oil level returns to normal position. In the case, check oil leakage
carefully.
Note: depending upon the ambient temperature and temperature rise mentioned on the
name plate the oil level should be in safe region (white region).
69
5.6 Abnormal Noise Level
Whenever there is any abnormality in the noise levels, this can easily be noticed by an
operator used to normal noise and this often leads to discovery of a problems.
Resonance of the case and radiator due to exclusive change in voltage and
Loosening of attachments.
Abnormal notice from static discharge due some ungrounded metal parts or
imperfect earthling
core clamping metal parts, bolts etc. these can be detected from outside of by
listening at the case even when the increased inside level is small.
and 3) Perfect earthling it is suggested to consult with the manufacturing body for the
method of treatment.
5.7.2 Method treatment- After disconnection of transformer form the power supply,
70
5.8 Thermometer Reading Discrepancy
When the transformer is over loaded, decrease the load to 100% and below. Check the
After disconnection of transformer from power supply, wash with water or cloth
soaked with ammonia or carbon tetrachloride, then wash with clear water so as to
insulations in the best possible condition. If it is necessary to drain oil from the
transformer for inspection or repair in the field, bear in mind that exposure of the oil
the atmosphere should be under a clear sky and that exposure time should minimize
within 10 hours if the repair work takes two days it is necessary to refill the
transformer with insulating oil or nitrogen gas to prevent the insulators from
71
Beforehand make sure that the hand pints 0 when the terminals for lead wire are
[NB: Use 5KV Mugger above 6.6kV system and use 1KV Mugger below 6.6 KV
systems.]
72
Maintenance of Insulating Oil
The insulating oil of a transformer, used for insulating between core and winding,
windings and charging parts and also for transferring the heat generated in the core
and windings to the cooling equipment for heat radiation. It is required to have the
following characteristics.
To be well refined and be free from such materials as will corrode metal parts or
cause deterioration.
The manufacturing technique for the transformer and its reliability have been
improved to such extent that inside inspection is almost unnecessary and at present,
deterioration of oil.
73
5.12 Deterioration of Insulating Oil
The insulating oil deterioration gradually as it is used. The causes are absorption of
moisture in the air and foreign materials that the oil. The major cause as oxidation.
The oil is oxidized by contact with air and accelerated by temperature rise of the
Beside the above the oil undergoes such chemical reaction as decomposition and
polymerization to produce matters which do not dissolve in oil and such matter
precipitate on the core and the winding. Those matters are called sludge. The sludge
does not directly affect dielectric strength but the sludge that has been deposited on
the winding prevent cooling by oil and that which is extracted and attaches to the
radiator and tank-wall increases temperature rise of the winding and affects indirectly
dielectric breakdown.
5.12.1 Acid value: The sludge formation is practically nil up to 0.2 degree acid value,
but it increases gradually and a formation can be observed at around 0.4 degree acid
5.12.2 Specific resistance: The specific resistance of the insulating oil is connected
with the insulation of the transformer and greatly influences the insulation resistance
The specific resistance becomes lower with temperature rise of the transformer as in
5.12.3 Dielectric strength: The insulating oil is a main source of insulation for the
transformer and lowering the oil dielectric strength means lowering the dielectric
strength of the transformer itself. Therefore this must be carefully inspected, the
dielectric strength of oil to be 30 KV. For transformer of higher tension, the dielectric
74
insulating oil can have 40-50 KV dielectric strength. The dielectric strength is also
subject to moisture and foreign materials contained in the oil and so more
values will be so large that they will become useless sampling of oil be done with care
The following are the standard for judging the degree of deterioration from the
measured values.
5.13.1 Acid value: Table A shows the recommendable standards for insulating oil
regeneration.
5.13.2 Specific resistance: As shown if Figure 8 the relationship between the acid
value and the specific resistance is such that the measured values are inconvenience.
75
Therefore, the standard are be regarded as mere guides. These are rather useful in
Caution 1 10¹¹-10¹² Ώ cm
5.13.3 Dielectric strength: The dielectric strength of oil has so far been standardized
above 30 kV, however with the change made in the shape of the transformer and the
expansion of use for higher tension the values of the insulating oil should be
resistance as in table 5.
76
Chapter Six
DC System, Protection Relay & Grounding
6.1 DC System
The DC-system consists of a free standing cubicle including Chargers, batteries, and
distribution. Normally the rectifier supplies the load. The battery bank supplies the
load for a limited time if the main supply is interrupted. The DC system shall provide
110V (125V), 24 V DC ± 10% to the consumers in the power plant. The batteries are
typically sized for 5 or 10 hours or: capacity is C10/5 at 1.8V end voltage and 20°C
Installation of the Battery should be done in a clean, cool and dry location. Ideal
temperature of the location shall be 270C for optimum performance and life.
Free space of 1mt should be provided on all sides of the battery for ease in
variations among the cells within the battery? The floor where the battery is to be
located should have the capacity for withstanding the weight of the battery.
6.3 Ventilation
Room size shall be selected so as to maintain the Hydrogen gas concentration within
the safe limits (<1% of room volume).n airtight enclosure However, if the batteries
are subjected to excessive overcharge, Hydrozen and Oxyzen will be vented to the
Mounting channel can be grouted to the floor with the help of the expansion bolts or
suitable foundation bolts. If floor grouting is required, carefully mark the location and
install the floor anchors to match the holes in the mounting frame. If required, use
shims for leveling. Tighten the bolts firmly to anchor the mounting frame.
Use forklift or mobile crane for handling the modules and stacking the system.
For multiple tier assembly place one module at a time on top of the module
already in place.
Properly align the module mounting holes and insert M 10x30 bolts, washers.
78
When all the bolts are in place, check that the assembly is plumb and level then
provided between two adjacent stacks to allow future access for tighting the
Ensure that the charger is turned off before making or breaking electrical
Ensure that all connections are as per General Arrangement drawing and are
firmly tightened with a torque of 10N-m before the charger is switched on.
79
Protection Relays
shown circuit an in fig, it is called a relay. Release devices are used in manually
operated switches and breakers, while relays are used in solenoid-operated breakers.
exceeds the specified value, which results in operation of the relay. Theoretically,
there is no time-lag in operation but in actual practice, there is a time lag of about 240
successive relays of this type is possible with current ratios of 3:1. Their principle
This relay consists of a solenoid and a plunger with adjustable time delay feature in
the form of an oil dash-pot or an air escapement chamber. Such a relay operates after
a specified time irrespective of the magnitude of the fault current selectivity amongst
such relays is obtained, if there is a diff. of 0.5 sec. in the setting of the two successive
80
As back-up protection for other forms of protection, and
Magnetic and thermal overload relays- Magnetic and thermal overload relays are
used to provide protection to motor and other sub circuits against overloads.
In its plunger or plunger or armature in attracted by the magnet coil when current
through it exceed the specified value resulting in operation of the relay. To ensure its
It’s provide the best means of overload protection to motors as the heating
Reverse power relays are sensitive to direction of power flow and are used on ring
mains and feeders operation in parallel the relay operates when the direction of power
reverses. A directional overload relay combines in one relay the functions of overload
81
6.14 Over current relays with A.C Tripping
Over current relays with A.C Tripping The circuit breaker trip coils are usually
arranged to be operated by a separate source of D.C supply but where the provision
and maintenance of a battery and the associated charging equipment are considered
rather uneconomical over current relays with A.C tripping are used. In their case, trip
The arrangement which requires two overload and one earth leakage relay is
commonly used for the protection of motor and distribution feeders in solidly earthed
systems. There is no current through the earth fault relay so long as the circuit is
healthy. In case of an earth fault, there is an imbalance and the residual current result
Definite time current relay are best suited for this application. A minimum difference
of 0.33-0.5 sec is required in the time settings of two adjacent relay. The maximum
time delay which will be on the relay nearest to the supply and must not exceed 2
relays A and B at the sanding end, by directional relay C and D at the receiving end as
shown in fig 11:25 . In the case of a fault between A and C, the power will be feel into
82
the fault from both the ends, relay C will operate first, being instantaneous type.
Ring mains are protected by providing two directional overload relays at each
junction point. Relays of this kind are represented by an arrow and a figure. The
arrow indicates the direction of current which will make the relay operate, and the
Induction type over current relays (IDMTI) are used for the protection of
not provided by these relays are generally set at 125% of the transformer rating,
which helps in riding though the large magnetizing in rush current differential
Modern alternators are designed to withstand all external faults howsoever severe,
until the overload device isolated the fault section. The most dangerous fault that may
occur in an alternator is a ground on the alternator winding itself. In that case, the
machine will be feeding power in its own fault and destroy itself.
to pass over 3-core cables. The output from this current transformer is utilized to
83
energize a current-operate relay as shown in fig 11:28.This arrangement provided
very sensitive earth fault protection and is re-commended for industrial and
6.22 Grounding
devices from any kinds of abnormalities or internal fault in the system which can
main purpose of grounding is to protect the devices from any kinds of internal faults
in the system.
Grounding techniques often use the five senses (sound, touch, smell, taste, and sight)
to immediately connect people with the here and now. For example, listening to loud
music, holding onto a piece of ice, or biting into a lemon are all grounding techniques
that produce sensations that are difficult to ignore, thereby directly and
84
The grounding can be divided into the following three areas with respect to purpose:
NGR is employed in AC distribution networks to limit the fault current which would
flow from the transformer or generator neutral star point in the event of an earth fault
in the systems. It is used when the neutral of supply transformer is accessible and its
own impedance is not enough to limit fault current. The rating of the protection relays
Resistors upto 33 KΩ are offered for fault of short duration like 10 sec., 30 sec., 60
sec., continuous etc. Material of resistor is normally Stainless Steel, FeCrAl, Cast
This is made for protecting personnel from injury. These connections are made to
parts of the system that are usually not energized but may become under abnormal or
fault situations.
85
6.25 Equipment Ground
Grounding is made to ensure a low impedance return path for ground current should
secure that a trip of a faulty circuit is made in a short time. In this power plant we
observed those three types of grounding. The ground grid design was made by
CITEC, using the auto grid program following the IEEE 80-2000 standards.
Design criteria is safe & touch voltage is not a absolute Ohm value
86
Chapter Seven
Drawing Requirements for Erection Works
87
7.2 Single Line Diagram of 33/11KV, 2x7.5MVA Substation
88
7.3 Section on A-A
89
7.4 Section on B-B
90
7.5 Section on C-C & D-D
91
7.6 Layout Plan of Outdoor Equipment
92
7.7 Electrical Layout Plan-A
93
7.8 Electrical Layout Plan-B
94
17.9 33KV Control & Relay Panel For Transformer Feeder
95
7.10 11KV Incoming & Outgoing Panel.
96
7.11 Switchgear Foundation Drawing
97
Chapter Eight
Conclusion
The main objective of this project was the installation, commissioning, maintenance
cooling system and shutdown of transformer. It was very helpful to determine the
know about transformer installation mechanical work. I think at least one mechanical
course should be offered in our university. It will help to make more confidence in
Besides, I have gained a lot of knowledge about switchgear and protective relay as
am hopeful that all the information presented in my internship report will be assisted
98
REFERENCES
1. Power Transformer Installation Guide, Energy Pac, 33 kv/ 11 kv, 7.5 MVA,
Dyn 11 Transformer Installation, 2016. City Auto Rice and Dal Mills Ltd.,
archive.
Fifth Edition: 1990, Second Printing: 1995. 2-B, Nath Market, Nai Sarak,
Delhi-110006.
edition 1989.
5. http://www.google.com/search?q=taansformer/oil&hl
99
APPENDIX
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114