Safety of Tower Cranes
Safety of Tower Cranes
Disclaimer
Enquiries
1
Guidelines on Safety of Tower Cranes
Publication No. 1
Guidelines on Safety of Tower Cranes
A. Purpose
This publication sets out the good practices recommended by the Construction Industry
Council (CIC) for enhancing the safety of tower crane operation.
B. Definitions
2
Guidelines on Safety of Tower Cranes
(j) “Specialist Contractor” means any person who enters into a contract with a
Principal Contractor, or a subcontractor of a Principal Contractor to perform the
erection, dismantling and height alteration of tower crane;
(k) “Technically Competent Person of Grade T5” (TCP T5) means a person
possessing academic or professional qualifications or experience of building
works or street works that satisfy the requirements set out in the Code of Practice
for Site Supervision issued by Buildings Department for a particular type of site
supervision or management tasks.
C. Introduction
3. Tower cranes are widely used for conveying of building materials on construction
sites. Given that collapse of tower crane could result in serious threats to the safety of site
personnel and members of the public, organizations and individual responsible for safety of
tower cranes should take appropriate measures to assure their safety.
4. The Factories and Industrial Undertakings Ordinance (“FIUO”), the Factories and
Industrial Undertakings (Lifting Appliances and Lifting Gear) Regulations (“LALGR”) and
the Occupational Safety and Health Ordinance (“OSHO”) impose duties on stake holders
to assure the safety of tower cranes. Furthermore, the Code of Practice on the Safe Use
of Tower Crane has been published by the Commissioner for Labour under Section 7A of
the FIUO providing practical guidance on selection, operation, erection and dismantling,
maintenance, inspection, examination and testing of tower cranes.
5. This publication make recommendations on the measures for further enhancing the
safety of tower cranes based on the good practices suggested by the concerned industry
stakeholders including tower crane owners, specialist contractors and professionals. The
Hong Kong Construction Association and the Construction Industry Council Training
Academy (CICTA) also contributed on technical and administrative aspects.
6. While this publication does not have any legal effects, Labour Department has indicated
that it may take non-compliances of the recommended parctices into account in considering
serving suspension notices under section 10 of the OSHO to the concerned Principal
Contractors or Specialist Contractors. For the avoidance of doubt, notwithstanding such
intention, this publication is issued by CIC for reference by industry stakeholders only and
will not constitute professional advice on tower crane operations or any other issues. The
parties using this publication should therefore seek appropriate advice from their professional
advisers. CIC (including its members and employees) will NOT accept responsibilities for
any consequences resulting from the use of or failure to use this publication.
3
Guidelines on Safety of Tower Cranes
7. The following groups of measures are recommended for enhancing the safety of tower
crane operations –
(a) checking before erection of tower cranes;
(b) improvements of site supervision;
(c) qualification and experience of Specialist Contractors; and
(d) qualification and experience of Competent Persons and workmen.
8. The owner of a tower crane should engage a CME to conduct pre-delivery checking
in accordance with the procedures at Annex A before the tower crane is delivered onto the
site.
9. As stipulated at Annex A, the CME should issue the following documents for the
checking –
(a) Report on Pre-Delivery Verification of Components with sample at Appendix A.1
to Annex A; and
(b) Report on Pre-Delivery Inspection with sample at Appendix A.2 to Annex A.
10. The anchorage of the tower crane should also be certified by a CME using Form 2
prescribed in LALGR before the tower crane may be used.
11. Under clause 4.5 of the Code of Practice for Site Supervision 2005 issued by Buildings
Department, where a tower crane forms part of the temporary works which may have effect
on the permanent structure by way of overstressing or overloading, the Registered Contractor
is required to appoint a person whose qualification and experience are not inferior to a
TCP T5 to certify the plans, design information and/or method statement of the works which
are to be submitted to the Registered Structural Engineer. The person so appointed will also
4
Guidelines on Safety of Tower Cranes
certify the completion of works.
12. In other cases, the Principal Contractor should, before a tower crane is erected, appoint
a TCP T5 to certify the adequacy of the design of the temporary works for supporting and
anchoring the crane paying particular attention to the foundation set-up, wall ties, guy ropes
and sitting structure. The assessment report should be submitted to the Principal Contractor
before concreting of the foundation and supporting structures.
13. Where a derrick crane is used to erect or dismantle a tower crane, the procedures in
paragraphs 8 to 12 above should apply. In particular, where a derrick crane is supported on
the roof, the adequacy of the roof for supporting the derrick crane should be assessed.
14. The Principal Contractor should appoint in writing a supervising engineer with the
following qualifications, experience and competences to control, monitor and supervise
operations on tower cranes –
(a) an engineering degree of relevant discipline;
(b) not less than four years of related working experience;
(c) capability in administering the “Hold Points” on critical parts;
(d) capability in communicating with the Competent Person throughout the operation;
and
(e) capability to conduct a visual inspection on the parts of a tower crane to ensure
that they are in good working order before commencement of any operations.
15. The Principal Contractor should arrange to conduct a risk assessment in good time
before the commencement of any operation on tower cranes to identify the hazards inherent
in the operation and the hazards which could result from adjacent activities. The assessment
should be conducted by a safety professional (e.g. a Registered Safety Officer) and Registered
Professional Engineers with suitable qualification and experience in appropriate disciplines
should be consulted on issues related to structural and mechanical stability. The assessment
5
Guidelines on Safety of Tower Cranes
should be updated immediately before the start of the operations to take into account any
changes in circumstances.
16. The Principal Contractor should formulate measures for avoiding the hazards
identified in risk assessment, or where this is not possible, devise measures for minimizing
their likelihood of occurrence or mitigating their consequences. These measures include –
(a) installation of fall protection system for workers working at height;
(b) suspension of work activities within an exclusion zone around the tower crane
until an operation is completed;
(c) provision of personal protective equipment such as protective gloves, ear
protectors and reflective vests;
(d) sufficient rest breaks;
(e) provision of proper safety training for Competent Person and workmen engaged
in tower crane operations;
(f) provision of adequate lighting between floors; and
(g) employment of qualified workmen and Competent Person.
17. Chinese version of the risk assessment report should be made available on site for
reference by Specialist Contractors engaged in tower crane operations.
18. The Principal Contractor and the Specialist Contractor should jointly prepare a method
statement in Chinese to define the procedures of tower crane operations covering –
(a) all measures for avoiding or mitigating the hazards identified in the risk
assessment;
(b) step-by-step procedures supplemented by diagrammatic illustration;
(c) highlighting of critical hazards and safety precautions by words such as “Danger”,
“Caution” and “Hold Points”;
(d) procedure and instruction on dealing with “Hold Points” of critical parts;
(e) procedures for avoiding hazards to site personnel working adjacent to the tower
crane;
(f) clear statements on the role and tasks of members of the working crew; and
(g) arrangements for effective communication.
19. The guidelines for preparing reports for risk assessment are at Annex B.
6
Guidelines on Safety of Tower Cranes
(iii) Pre-installation checking
20. The Principal Contractor should check the availability of the following documents
before proceeding with the erection of a tower crane or a derrick crane for dismantling a
tower crane –
(a) report on verification of components referred to in paragraph 9(a) above;
(b) report on pre-delivery inspection referred to in paragraph 9(b) above;
(c) report on assessment of supporting structure referred to in paragraph 12 above
where applicable; and
(d) maintenance logbook recording the maintenance and inspection history of the
crane.
21. The Principal Contractor should make the following documents available before
conducting any operation on a tower crane –
(a) report of the risk assessment for the operation including the method statement;
(b) records of the qualification and experience of the supervising engineer and the
Competent Person responsible for the operation; and
(c) all relevant certificates of test and examination of mobile cranes and derrick cranes
used in the operation.
22. Copies of risk assessment report (including the method statement) should be distributed
to the Specialist Contractor who should be advised of the estimated duration of the operation
and the boundaries of the exclusion zone.
23. After the completion of each operation, the Principal Contractor should engage a CME
to conduct a thorough examination and a load test to verify that the tower crane is fit for
use. The use of the tower crane should resume only after satisfactory completion of the
verification process.
7
Guidelines on Safety of Tower Cranes
24. Principal Contractors should only engage competent Specialist Contractors registered
on the specialty of “Erection, dismantling and climbing1” of the Tower Crane trade of
the Voluntary Subcontractor Registration Scheme administered by CIC to execute tower
crane operations. Specialist Contractors should possess relevant experience and sufficient
technical capability and engage Competent Persons and workmen with appropriate skills
and experience.
25. A Specialist Contractor should be able to understand the method statement for tower
crane operations and to explain the details to his working crew including a full explanation
on the risks associated with improper working procedures and those safety hints and
precautions set out in the warning/attention sections of the method statement marked
“Cautions”, “Danger” or “Hold Points”.
26. Specialist Contractors should employ Competent Persons and workmen with
appropriate qualifications, training and experience for performing all operations on tower
cranes taking into account the requirements set out at Annex C.
27. The manufacturer or his local agent should organize familiarization training on tower
cranes for Competent Persons.
I. Summary of Recommendations
28. The improvement measures recommended in the foregoing paragraphs are summarized
at Annex D together with the implementing organizations and timeframe.
1
Code 4.1.1
8
Guidelines on Safety of Tower Cranes
Annex A
Procedures for Pre-Delivery Checking
Purpose
This Annex sets out procedures for pre-erection examination of tower cranes.
Engagement of CME
2. The owner of a tower crane should engage a CME to conduct a pre-erection examination
of the tower crane before its erection on site.
9
Guidelines on Safety of Tower Cranes
Examination by CME
4. The CME should conduct thorough examination of the critical parts of a tower crane
before it is delivered to the construction site making appropriate reference to the information
provided by the owner. A checklist illustrating the possible scope of the examination is at
Appendix A.2. As the checklist is for illustration only and is not meant to be exhaustive,
the CME should verify its applicability and validity by making reference to manufacturer’s
specifications and manual of the specific tower crane and other relevant information.
Non-destructive Tests
5. The non-destructive tests on the critical components including bolts and pins and
welded connections should be conducted by qualified personnel. All bolts and pins (i.e.,
100%) used for connecting main structural parts should be tested. Items with cracks should
be replaced.
6. The CME should prescribe the non-destructive tests to be conducted on welded
connection based on the result of visual inspection of critical parts. For critical parts over 15
years old or of unconfirmed age, the minimum amount of welded connections to be tested
should be 10%. A higher percentage may be specified by the CME where deemed necessary
(e.g. due to a history of cracking).
7. If cracks are detected on any component, then all remaining welded connections on
that component should be tested. Components with cracks should be replaced or repaired in
accordance with the manufacturer’s specifications, and should be examined thoroughly by
the CME.
8. All non-destructive test reports should be forwarded to the CME for review.
10
Guidelines on Safety of Tower Cranes
Appendix A.1
Sample Verification Checklist
Make : ABC
Model : TX100
Year : 2007
( Note : The checklist is by no means exhaustive. Owners should examine its
applicability and validity by making reference to manufacturer’s specifications and
manual of the specific tower crane. )
11
Guidelines on Safety of Tower Cranes
2. Manufacturer Specifications
1 2 3 4 6 7
Standard, K102
Standard, K102
Tower mast sections
Reinforced, K103R
Standard, K102
Reinforced, K101R
Fixing angles/
foundation anchors
12
Guidelines on Safety of Tower Cranes
I have verified that the following main components and critical parts making up the
tower crane conform to the manufacturer’s specifications as follows:
Owner’s Manufacturer’s
Item Main components Qty Main dimensions Year Remarks
identification code
1 Fixing angles / anchors 4 F1, F2, F3, F4 Q200 200mm high 2007 Non- reusable
2 Tower base undercarriage Nil
/ chassis
3 Tower mast sections 1 M1 K103R 1.6m x 1.6m x 5m 2007 Reinforced
high
4 M2, M3, M4, M5 K102 1.6m x 1.6m x 5m 2007 Standard
high
1 M6 K101R 1.6m x 1.6m x 3m 2007 Base section,
high reinforced
4 Slewing ring assembly 1 M1 S300 2007 Reinforced
1 J7 7 5m long 2007
Reg. No.:
13
Guidelines on Safety of Tower Cranes
Appendix A.2
Scope of the Thorough Examination
Report reference :
Report date :
(Note: The checklist shown in this report is by no means exhaustive. CME should examine
its applicability and validity by making reference to manufacturer’s specifications and
manual of the specific tower crane.)
Thoroughly examined by
14
Guidelines on Safety of Tower Cranes
CONTENTS
1. Introduction
3. Visual examination
4. Dimensional examination
6. Summary of findings
15
Guidelines on Safety of Tower Cranes
1. INTRODUCTION
This report presents details of the thorough examination carried out on the critical
parts of the tower crane before they are delivered to a construction site.
Inspection location :
Site address :
Site identification :
Make :
Model :
Jib length :
Serial No. :
Year :
3. VISUAL EXAMINATION
Visual examination was carried out to check and examine the state of the critical parts
listed in Sections 3.1 and 3.2.
(Note: Visible damage includes cracking, deformation, corrosion, wear and abrasion)
16
Guidelines on Safety of Tower Cranes
Critical parts Acceptance criteria Condition acceptable
Yes No Remarks
(a) Fixing angles / foundation anchors No visible damage affecting safety □ □ _________________
(f) Counter-jib
Structural members No visible damage affecting safety □ □ _________________
Welded connections No visible damage affecting safety □ □ _________________
Tie bars No visible damage affecting safety □ □ _________________
Connection pins No visible damage affecting safety □ □ _________________
(g) Jib
Structural members No visible damage affecting safety □ □ _________________
Welded connections No visible damage affecting safety □ □ _________________
Tie bars No visible damage affecting safety □ □ _________________
Connection pins No visible damage affecting safety □ □ _________________
17
Guidelines on Safety of Tower Cranes
3.2 Accessories
(g) Collars
Climbing collars for No visible damage affecting safety □ □ _________________
floor climbing
Climbing ladders for No visible damage affecting safety □ □ _________________
floor climbing
Wall tie collars for telescoping No visible damage affecting safety □ □ _________________
Hydraulic assembly No visible damage affecting safety □ □ _________________
18
Guidelines on Safety of Tower Cranes
4. DIMENSIONAL EXAMINATION
Measurement of the pin and hole diameter for pinned connections was carried out to
check for out-of-tolerance against the manufacturer’s recommendations.
19
Guidelines on Safety of Tower Cranes
The repair and maintenance record prepared by the tower crane owner should include
details of work performed on the following critical parts.
(b) Motors
Hoisting As per manufacturer’s instructions □ □ _________________
Slewing As per manufacturer’s instructions □ □ _________________
Trolley As per manufacturer’s instructions □ □ _________________
Luffing As per manufacturer’s instructions □ □ _________________
(c) Gearboxes
Hoisting As per manufacturer’s instructions □ □ _________________
Slewing As per manufacturer’s instructions □ □ _________________
Trolley As per manufacturer’s instructions □ □ _________________
Luffing As per manufacturer’s instructions □ □ _________________
20
Guidelines on Safety of Tower Cranes
6. SUMMARY OF FINDINGS
□ All critical parts thoroughly examined are in acceptable condition, and are
considered suitable for site installation.
□ The critical parts listed below are not in acceptable condition, and are required
to be replaced or repaired in accordance with the manufacturer’s specifications.
The replaced or repaired parts are required to be further thoroughly examined by
a CME when they become available.
Critical part Details of non-conformance
(a) ___________________________________________
(b) ___________________________________________
(c) ___________________________________________
21
Guidelines on Safety of Tower Cranes
__________________________________________________
__________________________________________________
22
Guidelines on Safety of Tower Cranes
Annex B
Report for Risk Assessment
Purpose
This Annex sets out the guidelines for reporting on risk assessment for tower crane
operations.
Overview
(A) Introduction
4. This section should cover the hazards identified taking into account all relevant matters
including –
(a) preparation work
• deployment of crew for work supervision;
• checks on the suspension points of various accessories (items should be
specified);
• checks on the lifting appliances and lifting gears (items should be specified);
23
Guidelines on Safety of Tower Cranes
6. The method statement should be drawn up in consultation with the Competent Person,
the Registered Safety Officer and other persons concerned and should clearly define the
procedures for every step of the operations. It should be issued to the working crew for
effective compliance with the prescribed procedures.
7. The method statement should include –
(a) details of the construction site and construction works including a site layout
plan;
(b) general safety measures for the works;
(c) pre-construction plan;
(d) operating procedures with key points illustrated by diagrammatic illustrations;
(e) personal protective equipment; and
(f) safety measures for the operation.
24
Guidelines on Safety of Tower Cranes
8. Example of a site layout plan is included at Appendix B.2 while a sample method
statement for dismantling of tower crane is at Appendix B.3.
12. Contractor should enclose a copy of the manufacturer’s manual in the risk assessment
report.
25
Appendix B.1
Basic Operation Procedure Existing and Potential Hazard Public(P) Possible(4) Affected(2) Mitigation Measures Risk
Action
Environment (E) May be Possible(3) Serious(3) P*C Level
Asset(A) Slimly Possible(2) Disastrous(4)
Impossible(1)
(1) Preparation Work:
Item 1.1 Item 1.1 Item 1.1
Formulation of safe working Danger caused by non-specific working W,A 4 3 12 Representative of XX draws up works 9(3x3) QCM/SO
procedure on the addition of mast to procedure (potential danger: Danger triggered hazard analysis, risk control measures and Superintendent
tower crane because of no works statement was prepared or works programme together with QCM, /Chief
works statement being inappropriate) Chief Mechanic, Superintendent and Mechanic
Safety Officer
Item 1.2 Item 1.2 Item 1.2
Staffing arrangement for dedicated Unclear or inadequate definition by monitoring W,A 4 3 12 XX appoints experienced works supervisor 9(3x3)
personnel to monitor the addition of officer triggers danger (potential danger: to monitor all procedures of the addition of
mast to tower crane Danger triggered because monitoring officers mast to tower crane (the supervising officer
are not at site to monitor the addition of chassis is XXX/XXX/XXX)
to mast)
Item 1.3 Item 1.3 Item 1.3
Examination of every hanging There is the danger that an accessory may W,A 4 3 12 Works Supervisor to check all hanging 9(3x3)
point (such as ballasts etc.) (It is fall during the process of hoisting. (Potential points are fit before assigning workers to
necessary to specify which hanging danger: defects of hanging points may lead to carry out proper hoisting.
points are included.) falling.)
Item 1.4 Item 1.4 Item 1.4
Inspect all lifting appliances and Hoisting may lead to the falling of materials. W,A 4 3 12 Works Supervisor to check that lifting 9(3x3)
lifting gears.(It is necessary to (Potential danger: hoisting danger occurs gears and cranes have been issued with
specify which lifting appliances and because lifting gears have not been inspected certificates of inspection and are in good
lifting gears are included.) by public surveyor or they are in poor condition before proceeding to works
conditions.) procedures.
Item 1.5 Item 1.5 Item 1.5
Frequency channel of walkie-talkie Danger occurs during hoisting of material W,A 4 3 12 Works Supervisors are responsible for 9(3x3)
and communication. (potential danger: poor ensuring the proper reception of walkie-
27
the bottom of chassis until they are Item 2.3.3 Item 2.3.3
firm enough and then hammer the 4
Danger of tower crane falling~1 (Potential W,A 4 3 12 Works Supervisor to check shackle is
groups of pins joining the mast until
danger: Inappropriate installation of shackle properly installed before assigning workers
they are firm enough. The
may lead to the fall of tower crane.) to commence the tower crane telescoping
telescoping procedure of tower
procedure.
crane is completed.
Item 2.3.4 Item 2.3.4
Danger of tower crane falling~2 (Potential W,A 4 3 12 Works Supervisor to check the wedges are 9(3x3)
danger: Inappropriate installation of temporary properly installed before assigning workers
support wedges may lead to the fall of tower to commence the tower crane telescoping
crane.) procedure.
(Dismantling of telescopic cage.)
Item 2.4 Item 2.4.1 Item 2.4.1
When the tower crane has climbed Potential danger of fall of person~1 (Potential W,A 4 3 12 Works Supervisor to instruct workers 9(3x3)
to the appropriate height, lower the danger: As workers work on the mast of tower to fix the full body harness firmly with
telescopic cage until it sits firmly on crane there is the danger of fall of person.) fall arrestor before starting the works
the mast, and then hammer out procedure.
the mast.
3. Use wires to secure the telescopic (Potential danger: Inappropriate installation of secure before proceeding.
cage. mono-rail may lead to falling of the mast.)
4. Retrieve the shackle and loosen Works Supervisor to fence off the lower
the hydraulic jack. working area before works procedures
5. Use chain slings to pull out the commence.
telescopic cage along the mono-rail Works Supervisor to check the valid
and hoisthe telescopic cage back to certificates of all lifting devices and to
the ground. (Remark: Other method ensure all lifting devices are in good
of dismantling the telescopic cage condition by visual inspection.
can also be used.)
Works Supervisor to ensure the telescopic
cage has been secured with wires.
Item 2.4.4 Item 2.4.4
Potential danger of falling of hand tools~3 W,A 4 3 12 Works Supervisor to instruct and monitor 9(3x3)
(Potential danger: when tightening bolts, there worker to use hand tool and control rope.
is the danger of hand tools or bolts falling.)
Works Supervisor to fence off the lower
working area before works procedures
commence.
Item 2.4.5 Item 2.4.5
Danger of tower crane falling. (Potential W,A 4 3 12 Works Supervisor to check pins are 9(3x3)
danger: Inappropriate installation of pins may properly installed before assigning workers
lead to falling of the tower crane.) to start the tower crane dismantling
procedure.
Item 2.5 Item 2.5.1 Item 2.5.1
Transport the hydraulic jack and Potential danger of load falling down~2 W,A 4 3 12 Works Supervisor to ensure the hanging
tools etc. back to the ground (Potential danger: Inappropriate hanging points for the hoisting of hydraulic jack and
points for the hoisting of hydraulic jack and telescopic cage are proper before assigning
telescopic cage may lead falling.) workers with rigging certificate and
experience to carry out rigging operation.
Works Supervisor to check the valid
certificates of all lifting devices and to
ensure all lifting devices are in good
condition by visual inspection.
Works Supervisor to instruct and monitor
workers to use skip that have been checked
for bulk handling.
Works Supervisor to fence off the lower
33
Fire breaks out and workers can not get away W,P,E,A 4 3 12 Works Supervisor to inform Chief 9(3x3) Superintendent
and get injured. Mechanic and head of Emergency Action
Team (Superintendent) immediately and to
take action accordingly.
Superintendent to inform first aider to Superintendent
stand-by for rescue. & first aider
Appendix B.3
Sample Method Statement for Dismantling of Tower Crane
Scale: 1:700
36
Guidelines on Safety of Tower Cranes
Sample Layout Plan
Tower crane
Distance ? m
Safe working load ? tonnes
Distance ? m
Safe working load ? tonnes
Unloading area
Longest distance ? m
Safe working load ? tonnes
37
Guidelines on Safety of Tower Cranes
Scale : 1:700
10 m
Platform surface
Basement
7m
Works Procedures:
1. Dismantle 1A to 1F counter-jib ballast with a derrick crane!
38
Guidelines on Safety of Tower Cranes
Sample Tower Crane Dismantling Procedures
Step 2: Dismantle the hook and retrieve the hoisting wire rope
Works Procedures:
39
Guidelines on Safety of Tower Cranes
Scale : 1:700
7.4 m
32.7 m
50T
Hydraulic 21 m
derrick crane
7.8 m 4m Basement
Works procedure :
1. Use 4 chain slings of 2.4 m long and 2 wires to hoist the centre of the jib according to
the manual.
2. Tie the trolley properly with rope and retrieve the cable.
3. Hammer out the square-shaped pins and the steel plate which are connected to
A-frame.
4. Afterwards, hammer out the small pins joining the wedge lock and the slewing ring.
5. Slightly hoist up the jib to a 5 degree angle with the ground level and hammer out the
pins of the oval core within the wedge lock.
6. Use the derrick crane to dismantle the whole jib and lay it on the ground before
continuing with the dismantling process.
40
Guidelines on Safety of Tower Cranes
Important Points Hazard Identification
Distance between the tower crane Fall of person:
and the derrick crane is 7.8 m, the 1. Technicians working at the jib must use “double
safe working load is 12.3 tonnes shackle” safety belts
Fall of object:
Before dismantling the jib, the 1. Enclose the affected area, no access except for
trolley must be tied to the jib with a tower crane dismantling workers
coarse string 2. Hand tools must be tied to the appropriate
position with a rope
Overloading of derrick crane:
Must use a control rope to keep the
1. The derrick crane operator and signaller must
jib within the radius of safe hoisting
ensure the object for hoisting must not exceed
of the derrick crane
the safe working load.
Must use a block to secure the jib
so as to maintain a correct central
position and prevent the release
of too much energy during the
dismantling process
Adequate space must be reserved on
the ground level for placing the jib
of 60 m long
41
Guidelines on Safety of Tower Cranes
Scale : 1:700
10 m
32.7 m
50T
21 m
Hydraulic
derrick crane
Platform surface
7m Basement 4m
Works Procedures:
1. Dismantle the 4G ballast with a derrick crane
42
Guidelines on Safety of Tower Cranes
Sample Tower Crane Dismantling Procedures
Scale : 1:700
11 m
8.8 m
32.7 m
50T 21 m
Hydraulic
derrick crane Control
rope Control
Platform rope
surface
9m Basement 4m
Works Procedures:
1. Use 4 chain slings of 2.4 m long to lift up the centre of the counter jib according to the
manual.
2. Hammer out the small pins joining the wedge lock and the slewing ring.
3. Slightly lift up the counter jib to a 5º angle, hammer out the connecting pins on the
tie bar of the counter jib. Then, hammer out the small pins of the oval core within the
wedge lock.
4. Use the derrick crane to dismantle the whole counter jib and lay it on the ground before
continuing with the dismantling process.
43
Guidelines on Safety of Tower Cranes
44
Guidelines on Safety of Tower Cranes
Sample Tower Crane Dismantling Procedures
Step 6: Dismantle the A-frame + slewing ring + cabin
Scale : 1:700
6.8 m
32.7 m
50T
Hydraulic
derrick crane Platform
surface
Basement 4m
6.6 m
Works Procedures:
1. Use 4 chain slings of suitable length to lift up the A-frame + slewing ring+cabin
according to the instruction manual.
2. Loosen the screws connecting the slewing ring and the mast with a hydraulic block.
3. Use a derrick crane to dismantle the A-frame+slewing ring+cabin and lay them on the
ground.
45
Guidelines on Safety of Tower Cranes
Scale : 1:700
10.2 m
32.7 m
50T
Hydraulic
derrick crane Platform
surface
4m Basement
6.6 m
Works Procedures:
1. Use 4 chain slings of suitable length to lift up one mast.
2. Loosen the screws connecting the masts with a hydraulic block.
3. Use a derrick crane to dismantle the masts and lay them down to the ground one by
one.
46
Guidelines on Safety of Tower Cranes
Sample Tower Crane Dismantling Procedures
Works Procedures:
1. Cut away the outcrop of the concrete footing with oxy-acetylene torch.
2. Use a derrick crane to dismantle the cut-off outcrop down on the ground.
End
47
Guidelines on Safety of Tower Cranes
Appendix B.4
The following persons are appointed as Competent Persons to supervise the dismantling
of tower crane MD-175 at site xxxx of your company until completion of the works. The
Competent Persons have 10 years’ relevant experience and have worked on tower crane of
the same model line.
48
Guidelines on Safety of Tower Cranes
Sample Appointment Letter of Senior/Junior Workmen
The following personnel are appointed as senior/junior workmen for dismantling tower
crane MD-175 at site xxxx of your company until completion of the works.
49
Guidelines on Safety of Tower Cranes
The following personnel will attend the works safety meeting before the start of works.
50
Guidelines on Safety of Tower Cranes
Annex C
Qualification and Experience
of Site Personnel Engaged in Tower Crane Operations
Competent Person
(A) Role
(B) Qualification
• Registered Skilled Worker of the trade “To carry out erection, dismantling,
telescoping/climbing of tower crane, and the hoisting of materials, tools and
equipment related to the aforesaid work” under the Construction Workers
Registration Ordinance (CWRO). (To be implemented in six months after the
trade is available for registration)
(C) Experience
(D) Training
51
Guidelines on Safety of Tower Cranes
(E) Competencies
Senior workman
(A) Qualification
• Registered Skilled Worker of the trade “To carry out erection, dismantling,
telescoping/climbing of tower crane, and the hoisting of materials, tools and
equipment related to the aforesaid work” under CWRO. (To be implemented in
six months after the trade is available for registration)
(B) Experience
(C) Training
52
Guidelines on Safety of Tower Cranes
- Safety Training Course for Construction Workers of Specified Trade (Silver
Card Course) – Construction Materials Rigger (“Rigger Course”); and
- EDTC Course
Junior Workman
(A) Qualification
(B) Training
(C) Supervision
• A junior workman with less than four years of experience should work only under
the direct one-to-one supervision of a senior workman.
53
Guidelines on Safety of Tower Cranes
Annex D
Summary of Recommended Improvement Measures
Section and
subsection Implementation
Improvement Measures Implementing parties
in main timeframe
text
E Checking before Erection of Tower Crane
(i) Pre-delivery checking Tower crane owners Upon issue of
publication
(ii) Checking of anchorage Tower crane owners Upon issue of
Principal Contractors publication
(iii) Checking of supporting Tower crane owners Upon issue of
structure Principal Contractors publication
F Improvement of site supervision
(i) Appointment of Principal Contractors Upon issue of
supervising engineer publication
(ii) Risk assessment and Principal Contractors Already
method statement Specialist Contractors implemented
(iii) Pre-installation checking Principal contractors Upon issue of
publication
(iv) Pre-operation checking Principal contractors Upon issue of
Specialist Contractors publication
(v) Pre-use verification Principal contractors Already
implemented
G Qualification and Principal contractors Upon issue of
experience of specialist Specialist contractors publication
contractors
H Training and experience Principal contractors Already
of competent persons Specialist contractors implemented1
and workmen
1
Except for (i) Registration as Skilled Worker of the trade “To carry out erection, dismantling, telescoping/climbing of tower crane, and the
hoisting of materials, tools and equipment related to the aforesaid work” under the Construction Workers Registration Ordinance (CWRO); and
(ii) Completion of training for Tower Crane Competent Person (Erecting, Dismantling, Telescoping & Climbing). These will be implemented
in six months after the availabilty of the trade for registration and in six months after launching the course respectively
54