0710-Public Private Partnerships.
0710-Public Private Partnerships.
PPPs
PPPs in China
PPP Cycle
Financial Analysis
Performance Management
+VE
Transfer
Construction
period Operation and maintenance period
-VE
Payback period
Concession period
Advantages of PPP
7
Source EGIS
Advantages of PPP
9
Resource-based Privatization/Public
financing Private Partnerships
PPPs and Other Delivery Approaches
13
PSP 私营部门拥有资产,并
政府部门负责投资、经 运营,承担全部风险;
营、并承担全部风险 政府进行规制
PPP项目
Yes No
是 否
存量项目
Brown project
引入资金 引入管理
是
Funding needed 否 是
Management needed
否
是
Rehabitate 否 是
Funding needed否
ROT TOT 期满移交 LOT
是 Transfer or not 否
BOT BOO
2024/7/3
PPP Modalities
Source World bank
PPP Modalities
16 Source World bank
PPP Modalities
Source World bank
17
PPP Modalities Source World bank
18
Where is PPP appropriate?
19
In the UK, fully privatized projects account for approximately 65%, traditional
government investment projects account for about 20%, and projects using various PPP
models account for around 15%.
2024/7/3
21
Phase 3: 2009-2013, Fluctuating Development: Impact of the financial crisis and the
4 trillion yuan stimulus; state-owned enterprises dominated; diversified financing.
Phase 4: 2014-2017, Boom: Intense activity, wide scope, frequent policy issuance,
surge in PPP projects. By the end of 2020, a total of 8,745 PPP projects had been
awarded, with a cumulative capital investment of RMB 14.8 trillion.
2024/7/3
PPP in China
26
10000 100
Phase 5: 2017-Present,
Project number
Regulation: Ministry of Finance Early terminations 80
• In 139 low- and middle-income countries, about 4.5% of PPP projects awarded
between 1984 and 2021 were terminated early (World Bank, 2022).
• Notably, in China, approximately 15.2% of PPP projects awarded between 2014
and 2020 were terminated early (Ministry of Finance of China, 2022).
2024/7/3
PPP in China
27
2024/7/3
Finance-oriented (PPP 1.0)
28
Time Quality
incentivize contracting parties to
Efficiency achieve high efficiency in cost,
time and quality.
VFP
Society Environment
Sustainability-oriented (PPP 3.0):
Sustainability
incorporate social, environmental,
and debt sustainability.
“Public-Public Partnership”
29
In the UK, economic infrastructure projects are mainly provided through privatization,
while social projects are handled through PFI. In China, economic PPP projects have taken
up a significant portion of what would typically be considered social PPP projects.
Transportation Health
Municipal
Transport
Education
Defense
Selection criteria:
Likely Financial Viability and Fiscal Support
Readiness and Risk
Socio Economic Benefits
Regional Development
Sector Network Role Importance in Sector Plan
National Integration and Security
Land Acquisition
Environment/Resettlement
Impact on Export Earnings
Safety
Project Type/Cost
Demand
Stage 2: Due Diligence and
36
Feasibility Studies
Contracting Authority carries out Feasibility Studies.
Government Authority reviews adequacy of study.
Based on (i) if no fiscal support/subsidy needed,
Contracting Authority tenders the project.
Or (ii) if fiscal support needed, Government’s Central PPP
authority assesses request, and socioeconomic justification
and fiscal support and suggests any modification (amount,
type of subsidy etc.).
Government Authority assesses project according to
fiscal space and project risk criteria, agrees on support
and passes a project that meets its criteria back to the
Contracting authority for implementation.
Stage 2: Due Diligence and
37
Feasibility Studies
Stage 2: Due Diligence and
38
Feasibility Studies
Stage 2: Due Diligence and
39
Feasibility Studies
Basis for Lenders in Project Financing
health of project structure
commercial plan
future revenue stream
Financial Model
Financial inputs and outflows
Project risks and uncertainties
Project sensitivities to a given risk
Off-take purchase, revenue failure and cost increase
Financial Viability
Debt-to-Equity Ratio
Higher debt-to-equity ratios mean increased lender exposure to
project risk.
Higher equity results in greater project "ownership" by shareholders
and increases their incentive to ensure project success.
Stage 2: Due Diligence and
40
Feasibility Studies
Self-financing ability indicates what percentage of the
construction cost can be recovered through the net revenues
earned in the operation period, subject to the financing
conditions of the capital market and the equity holders’
requirements of the return to their investments.
NPVR
SFA = ×100%
NFVC
where NPVR is the net present value of the net revenues in the
operation period at the end of the construction period;
and NFVC is the net future value of the construction costs at the
end of the construction period.
Stage 2: Due Diligence and
41
Feasibility Studies
Debt Service Cover Ratio
DSCR measures the cash flowing into the project and
available to meet debt service after deducting operating
expenses against the amount of debt service due in the
same period.
Sales
Revenue
Evaluation criteria
Evaluation criteria will cover (i) compliance of the bids
to the tender specifications, (ii) feasibility of the
proposals, (iii) costs and benefits of the proposals for
the public entity.
Evaluation rules
The first step (validation) of the evaluation consists of
checking compliance of the bids with the technical,
financial and legal specifications of the bidding
documents.
The second step (financial evaluation)
Stage 3: Procurement
53
Technical information
• Design documents and plans for any rehabilitation or development works
included in the contract,
• Description of the site location and access to the site
• Feasibility study,
• International and national standards governing the expected services (works,
maintenance, operation),
• Performance indicators for operation and maintenance with a clear definition
of control and measurement methods, as well as performance requirements,
• Environmental impact assessment study (if any) and a detailed description of
the environmental constraints during all project phases,
• Quality assurance requirements,
• Documents to be provided by each party during the contract,
• Assistance and facilities to be provided by the government and contracting
authority,
Stage 3: Procurement
56
Salvage
Sank
Value
Costs
Sank cost does not affect
cash flow analysis because
Cash
it is an existing fact
out flow
regardless of the
investment decision
t=0 (it is not incremental costs).
Example
t=1
- CF2
t=2 Present value of PV =
cash out flow at t=2 (1 + r ) 2
Present value of
CF10
PV = (1 + r ) 10
Present Value cash in flow at t=10
Net Present Value (NPV) II
66
Present value of
PV0 = - CF0 cash out flow at t=0
Negative value because they
- CF2 Present value of are cash out flow
PV2 = (1 + r) 2
cash out flow at t=2
CF10 Present value of
PV10 = (1 + r) 10 Positive value because they
cash in flow at t=10 are cash in flow
Net of all present value of cash out flow and
all present value of cash in flow is:
NPV = PV0 + PV1 + PV2 + PV3 + + PV42
- CF1 - CF2 CF10
= - CF0 + (1 + r ) 1 + (1 + r ) 2 + + (1 + r )10 + +(1 + r )42
CF42
42
CFt
= tΣ= 0 t
As long as this value is positive, the project will produce
(1 + r) more cash than necessary to repay debt and dividend.
Net Present Value (NPV) III
67
Implication
Positive NPV: the project will generate more cash than the necessary amount to
repay debt to banks and deliver dividend to shareholders, the excess cash solely
to the project’s shareholders.
Zero NPV: the project will generate exactly the necessarily amount of cash to
repay debt to the banks and deliver dividend to shareholders.
Negative NPV: the project cannot generate cash to repay debt to banks and
deliver dividend to shareholders.
Based on: Financial Management, Eugene F. Brigham and Michael C. Ehrhardt, 2008
Internal Rate of Return (IRR)
68
Method
IRR is defined as the discount rate that assumes NPV is equal to zero.
N
CFt
IRR = Σt = 0 (1 + r) t = 0
Implication
IRR is useful when investors assess the project against their hurdle rate, which is a
cost of capital.
IRR > Hurdle Rate: the project will produce more cash than the necessary amount to
repay debt and deliver dividend to shareholders.
IRR = Hurdle Rate: the project will produce the exact amount of cash to compromise
investors’ cost of capital.
Weak points of IRR
It applies the project’s IRR to the reinvestment of cash in flows
When there are more than one change from cash out-flow to cash-in flow, or from cash-
in flow to cash out-flow in the projection, the value of IRR are more than one: calculator
would simply indicate “error”
Modified Internal Rate of Return (MIRR) I
69
Sank
Costs N-t
(1 + r )
Cash 1
(1 + r ) t
out flow
← Cost of capital
Present Value Future Value
42 Future value of all cash in flows
(1 + MIRR) =
Present value of all cash out flows
Modified Internal Rate of Return (MIRR) II
70
Method
MIRR is defined as the discount rate that forces the present value of cash in flows
(CIF) to equal the present value of cash out flows (COF).
N
N
COFt Σt = 0CIFt (1 + r )N - t
Σ
t=0 (1 + r ) t = (1 + MIRR) N
FV of cash in flows
PV of cash out flows =
(1 + MIRR) N
Implication
MIRR is better than IRR because it reinvest the cash-in flow by using the cost of
capital which is more realistic. Thus, MIRR tells more accurate profitability of the
project.
MIRR > Hurdle Rate: the project will produce more cash than the necessary amount to
repay debt and deliver dividend to shareholders.
MIRR is better than IRR because it allows more than one changes in plus and
minus signs in cash flow projection.
Profitability Index (PI)
71
Method
PI is another way of using NPV by dividing PV of future cash flow by initial
investment.
Generally: N
Σt = 1 CFt
PV of future cash flows (1 + r) t
PI = =
Initial investment CF0
For the example cash flow projection: 42
Σ CFt
PV of future cash flows t=4 (1 + r ) t
PI = =
Initial investment 3
Σt = 0 CFt t
Implication (1 + r )
PI tells the relative profitability of the project by indicating the value of the
future cash flows par dollar of initial investment. When PI > 1, the project should
be accepted. When PI = 1, this basically means NPV = 0 and MIRR = Hurdle
Rate.
Comparing two projects with NPV and IRR
72
Project A Project B
$500 $400 $300 $100 $100 $300 $400 $600
t t
-$1000 Cost of capital: 10% -$1000 Cost of capital: 10%
NPV: $78.82 IRR: 14.5%
MIRR: 12.1% PI: 1.08 NPV: $49.18 IRR:
11.8%
NPV MIRR: 11.3% PI:
$400 1.05
Project B
$300 Crossover rate A conflict between NPV and IRR when
$200 (1) Project size differences exist
Project A (2) Timing differences exist
$78.82 $100
$49.18
$0 Take NPV rather than IRR. The logic is
5% 10% 15% r % That NPV selects the project that adds
-$100 7.2% 11.8% 14.5% most to shareholder’s wealth.
Other Important Indicators
73
Debt-to-equity ratio
Outstanding debt
=
Outstanding equity
Issues on Cost of Capita
74
In case of project finance the outstanding debt constantly declines and debt/equity ratio
keeps changing throughout the project life.
CF1 CF2 CFn
NPVP1 = - CF0 + (1 + WACC1) 1+ (1 + WACC2) 2 + + (1 + WACCn) n
[NOPAT: Net Operating Profit After Tax, t: tax rate, KD: debt cost,
D: debt outstanding, Rf: risk free rate, βa: asset beta, Rp: risk premium] Tax shield
Adjustment
Issues on Cost of Capita
75
Both NPVP1 and NPVP2 in the previous slide involve the concept of
CAPM (capital asset pricing model) to get debt, equity and asset beta,
which would not work appropriately in case of project finance for
several reasons:
A country where project is located may not have integrated/efficient market
Data would be not available for market risk premium
An ideal instrument represents the risk free rate would not be available
CAPM may not able to incorporate all risks associated with the project
CAPM does not consider asymmetric down side risks
Required return on debt may different between construction and operating
periods
What if there is single purchaser located in other country?
What to do?
Analysis of Individual Cash Flows
76
Free
FCF used for NPV Cash Year
Flow
(IRR) analysis
(FCF)
Sales
Revenue
Pi = Pi-1 + ∆ I ( fi I ) + ∆ E ( fi E ) + ∆ Q ( Qi )
where, Pi = the toll rate in year i ; ∆ I ( fi I ) = the toll rate adjustment due to the inflation ( fi I ) in
year i and θ = the tolerance of allowed fluctuation in inflation; ∆ E ( fi E ) = the toll rate
adjustment due to the currency exchange rate ( fi E ) in year i ,
Tariff Structure and Adjustment
80
Mechanism
fi E
P δ
i-1 i E + α − 1 [0 ≤ fi E < f rE (1 − α )]
fr
(fi I - θ )
∆ I ( fi I ) = Pi-1 ∆ E ( f i E ) = 0 [f rE ( 1- α ) ≤ fi E < f rE ( 1+ α ) ]
100
− Pi-1δ i fi E - α − 1 [f rE (1+ α ) ≤ f i E < +∞ ]
E
fr
Qi-1
− Pi-1 e − (1 − β ) [0 ≤ Qi-1 < Qie−1(1- β )]
Q
i −1
where, α = the tolerance of allowed fluctuation in currency exchange rate and δ i = the
component rate of base price relating to exchange rate; ∆ Q ( Qi ) = the toll rate adjustment due to
the annual demand ( Qi ) in year i , Qie−1 = the expected annual demand in year i − 1 and β = the
tolerance of allowed fluctuation in annual demand.
PUBLIC PRIVATE PARTNERSHIP:
VALUE FOR MONEY
Value for Money
82
83
Value for money is a process of comparing estimated costs using two
delivery models to determine which is the better value proposition
Risks Retained
• The cost difference between
Risks Retained
Model # 1 and Model # 2 is
Financing
Financing
Costs
the estimated Value for
Costs
Money
• AFP costs: Financing,
Infrastructure Ontario
Base Costs overhead, Project advisors
Base Costs (includes Risk ‘Shadow Bid’ or
Premium)
‘Preferred Bid’ • Key AFP benefit: Risk
transfer
• The savings achieved through
PSC AFP risk transfer more than offset
Base Costs Financing Costs additional AFP costs
Value for Money Test
85
Project management
Performance management
Regulatory framework
Is the failure a
Monthly monitoring meeting persistent long-term Yes
issue?
Payment
Payment made
deduction
Comprehensive KPIs for General PPP
98
Projects
• Cost performance
• Scope of rework
• Safety performance
• Environmental performance
• Productivity
• Pollution occurrence
YEUNG et al. (2007, 2008 and 2009)
Comprehensive KPIs for General PPP
99
Projects
(2) Result-oriented subjective measures:
• Quality performance
• Client's satisfaction
• Customer's satisfaction
• Job satisfaction
• Effective communications
• Employee's attitude
• Reduction of paperwork
Economic viability
(1) Long-term demand for the products/services offered
by the project;
(2) Limited competition from other projects;
(3) Sufficient profitability of the project to attract
investors;
(4) Long-term cash flow that is attractive to lender; and
(5) Long-term availability of suppliers needed for the
normal operation of the project.
Critical Success Factors for PPPs
108
All PPPs are subject to common transaction hazards (Fig. 1), which
could determine the success or failure of PPP projects.
Transaction
hazards
Transaction Governance
Impacts on performance
hazards mechanisms
Resolving uncertainties ex ante, but causing transaction
Cognition
costs and optimism bias
Uncertainty
Resolving uncertainties ex post, but causing opportunistic
Flexibility
behaviors
Insights
Cognition and flexibility complement each other to reduce the hazard
of uncertainty in PPPs but they cannot simply substitute for each other,
due to their respective costs.
Safeguards reduce the hazard of asset specificity, but excessive
safeguards could be harmful to PPPs. Moreover, the credibility of
government is essential for the effectiveness of safeguards.
Transparency and competition complement with each other to reduce
the hazard of information asymmetry in PPPs.
Reputation and trust reduce the hazard of contract incompleteness in
PPPs, but reputation cannot function in the absence of a competitive
procurement process.
Renegotiation and Early Termination
117
Procedures:
Renegotiation and Early Termination
121
Renegotiation
122