Delegate Pack - Foundation
Delegate Pack - Foundation
Foundation
All rights reserved. No part of this publication may be reproduced or transmitted in any form and by any means (electronic,
photocopying, recording or otherwise) except as permitted in writing by PeopleCert International Ltd. Enquiries for permission
to reproduce, transmit or use for any purpose this material should be directed to the publisher.
Disclaimer
This publication is designed to provide helpful information to the reader. Although every care has been taken by PeopleCert
International Ltd in the preparation of this publication, no representation or warranty (express or implied) is given by PeopleCert
International Ltd as publisher with respect as to the completeness, accuracy, reliability, suitability or availability of the
information contained within it and neither shall PeopleCert International Ltd be responsible or liable for any loss or damage
whatsoever (indicatively but not limited to, special, indirect, consequential) arising or resulting of virtue of information,
instructions or advice contained within this publication.
|PRINCE2 7 Foundation
®
All rights reserved. No part of this publication may be reproduced or transmitted in any form and by any means (electronic,
photocopying, recording or otherwise) except as permitted in writing by PeopleCert International Ltd. Enquiries for permission
to reproduce, transmit or use for any purpose this material should be directed to the publisher.
Disclaimer
This publication is designed to provide helpful information to the reader. Although every care has been taken by PeopleCert
International Ltd in the preparation of this publication, no representation or warranty (express or implied) is given by PeopleCert
International Ltd as publisher with respect as to the completeness, accuracy, reliability, suitability or availability of the
information contained within it and neither shall PeopleCert International Ltd be responsible or liable for any loss or damage
whatsoever (indicatively but not limited to, special, indirect, consequential) arising or resulting of virtue of information,
instructions or advice contained within this publication.
|PRINCE2 7 Foundation
®
Detailed PRINCE2
Book reference Practice Question
Reason for
Name
attending
Job role
Common
challenges
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
People
Organizing
Starting up and initiating a project
Business case
Plans
Quality
Risk
Closing a project
Directing a project
Course review
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Globally recognized
Licensed trainers and PRINCE2: Foundation and
project management People become qualified
consultants Practitioner
method
Legacy of over 25
years, tried and Best Practice PeopleCert
tested
|PRINCE2 7 Foundation
®
Answering
sample test Short
questions quizzes
Working on
case studies
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Introduction
Activity 1
What makes a good
project?
on
time
A good
project
Use your
Learner
Workbook
to note
down your
ideas.
|PRINCE2 7 Foundation
®
delivers
A good
value/ project
benefits
engaged
stakeholders
well
planned meets
meets a need
objectives
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
cross-functional change
PROJECT
uncertainty unique
|PRINCE2 7 Foundation
®
temporary
Topics not included in PRINCE2
specialist detailed
aspects techniques
|PRINCE2 7 Foundation
®
Principles
Common
universal language and Increased
concepts organizational
maturity
flexible Part of an
proven integrated suite
Outcome of methods
focused
|PRINCE2 7 Foundation
®
know how
to start, know how
improve
manage the to
your
steps, and structure
standing
close a a project
within your
project organization
|PRINCE2 7 Foundation
®
The application
of methods,
tools, Controlling Motivating Delegating
techniques, and
competencies
Monitoring
|PRINCE2 7 Foundation
®
Introduce change
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
risk time
scope
quality
sustainability
|PRINCE2 7 Foundation
®
Commercial Sustainability
context
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Portfolio
Programme Programme
Principles
|PRINCE2 7 Foundation
®
Tailor to Principles
Focus on
suit the
products
project
|PRINCE2 7 Foundation
®
Plans
Risks
Issues Progress
Principles
management Managing
Managing Managing
Delivering
product delivery product delivery
Note
• Starting up a project is used by both the directing and managing levels.
• There should be at least two stages, the first of which is the initiation stage.
• Managing a stage boundary is first used at the end of the initiation stage and repeated at the end of each subsequent stage
except the final stage. It is also used to prepare exception plans, which can be done at any time including in the final stage .
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Project plan
Commercial context
e.g. contracts,
relationships
Using the method. Stage plans
For example,
Delivery method assigning roles,
Internal (to project)
|PRINCE2 7 Foundation Figure 2.1 How to apply and tailor PRINCE2 to a project
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Overview of PRINCE2®
project management
Activity 1
Analysing project viability
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Leading
successful
change
People People
central tocentral to
the method
the method
Leading
Communication successful
teams
Current
Target state
state
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Senior
executives
The supplier
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Contractor Union
Public Finance
Industry regulator
Legal team
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Formal
Competing
authority vs
priorities
influence
Multiple
Hierarchical
reporting
tension
lines
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Meeting Co-locating
regularly in a an office-
purposeful based
way Developing project team Supporting virtual
and teams eg:
• Syncing co-
maintaining location days
key • Holding ‘away
relationships days’
• Using virtual
collaboration
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Principles
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
A Securing funding from the business layer for the business case
|PRINCE2 7 Foundation
®
C Because confidence is needed that the project can meet its objectives
and continues to be justified
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
C To define how the business will need to operate in the future to meet
the project objectives
|PRINCE2 7 Foundation
®
A Manage by exception
B Manage by stages
C Focus on products
|PRINCE2 7 Foundation
®
People
Activity 1
Project stakeholders
Look at the potential NowByou
stakeholders in the scenario.
Which stakeholders would you
consider to be influential because
they are at the interface between
the two ecosystems?
Use your
Learner
Workbook to
note down
your ideas.
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
People
Activity 2
Communication
management approach
Develop an outline for the
communication approach the
project team could consider.
Use the list of stakeholders that you
have identified, and the prompts on
the next slide.
|PRINCE2 7 Foundation
®
Responsibilities Standards
What will be and resources and
communicated guidelines
and how this will
be tailored to
stakeholder
groups
Tools and
Frequency techniques
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Plans
Manage by
exception
Risks
All 7 practices
Designed to
should be
support
applied, varied
application
according to
and tailoring
context
Management
approaches define
procedures,
techniques,
standards and
responsibilities
|PRINCE2 7 Foundation
®
PRINCE2
management
products describe
the information that
will be required to
manage the project
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Business
Project
User Supplier
ROLE
The executive represents the business
|PRINCE2 7 Foundation
®
ROLE
Senior user(s) is needed to represent user
|PRINCE2 7 Foundation
®
ROLE
Senior supplier(s) is needed to represent
|PRINCE2 7 Foundation
®
Directing
(project board)
Project
Managing
Figure 6.2 The four organizational layers management
(project manager)
team
Delivering
(team managers)
|PRINCE2 7 Foundation
®
Project management
team roles Senior
user(s)
Executive
Senior
supplier(s)
Project
assurance
Team members
|PRINCE2 7 Foundation
®
Has business, user, Ensures appropriate Reviews the project Has an effective
and supplier governance by roles throughout approach to manage
stakeholder defining the project. communication flows
representation. responsibilities at to and from
each level. stakeholders.
|PRINCE2 7 Foundation
®
Project
assurance
Project
manager
Project
support
Team
Team members
|PRINCE2 7 Foundation
®
Project manager
Senior Senior
Executive
user(s) supplier(s)
Project
assurance
Project
Project
support
Team
manager(s)
benefits
management of a project. time
Has authority to run the project
on behalf of the project board
within agreed project risk quality
tolerances and constraints.
scope sustainability
|PRINCE2 7 Foundation
®
Team manager
Senior Senior
Executive
user(s) supplier(s)
Project
assurance
Project
manager
|PRINCE2 7 Foundation
®
Other roles
Senior Senior
Executive
user(s) supplier(s)
Project
assurance
Project
support
Team
manager(s)
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Manage Transition
Understand Design project Develop project project into
changes to
organizational ecosystem ecosystem organizational
project
ecosystem ecosystem
ecosystem
Adapted from Figure 6.5 PRINCE2 technique for organizational design and development
|PRINCE2 7 Foundation
®
and availability
Define roles,
responsibilities, Manage by
Using lessons to Learn from
experience
and exception
relationships
inform the team
structure and ensure
the right people in the
right roles to deliver
the project
Ensuring those who will use the project
product are on the project management
team to support acceptance and ready
use of the end product.
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
C Manage by stages
|PRINCE2 7 Foundation
®
A Role descriptions
C Product description
D Business case
|PRINCE2 7 Foundation
®
A Project manager
B Project executive
D Project board
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Organizing
Activity 1
Design a project
management team
Use your
Learner
Workbook to
note down
your ideas.
|PRINCE2 7 Foundation
®
The Chief Finance Officer (CFO) of NowByou was appointed 6 The Police Liaison Officer joined NowByou five years ago after
months ago and has been very active with donors and partners to retiring from a successful career with the national police force.
increase the financial standing of the organization. Was previously a He has worked closely with the HR Director on past initiatives
senior executive with a major bank and is keen to bring good and has been establishing a close professional relationship with
portfolio and project management practices to NowByou. the new Director of Campaigns.
Head of Fund-Raising reports to the CFO and previously worked within
Graduate Trainees the HR Director instigated a graduate trainee
an organization with good portfolio, programme and project
programme two years ago. The first four trainees will reach the end
management practices and helped to gain approval for the appointment
of their two-year training programme in two months’ time and have
of the external professional project manager and the establishment of a
all received PRINCE2 training.
Portfolio Office within NowByou. Is PRINCE2 qualified.
The NowByou Director of Campaigns has recently joined Head of Publicity and Social Media he reports to the Director of
NowByou having previously been a senior marketing manager with Campaigns and is responsible for Brand management, press
a commercial manufacturing organization. He has overall release and social media.
responsibilities for all campaigns.
A Portfolio Office Manager, previously a senior administrative officer Marketing Agency Director NowByou have a relationship with a
within NowByou has been appointed to set up the portfolio office and commercial marketing agency, CharityM, who work with the Head
work with the Contracted Project Manager to implement and establish of Publicity and Social Media in developing and placing
the initial project management documentation and processes. advertising on TV and Radio stations.
|PRINCE2 7 Foundation
®
Senior user
Director of Senior supplier
Campaigns Marketing Agency
director
Project manager
Graduate trainee
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
process in PRINCE2
up a
project Managing Managing
a stage a stage Closing
boundary boundary a project
Managing
Managing Managing
Delivering
product delivery product delivery
Note
• Starting up a project is used by both the directing and managing levels.
• There should be at least two stages, the first of which is the initiation stage.
• Managing a stage boundary is first used at the end of the initiation stage and repeated at the end of each subsequent stage
except the final stage. It is also used to prepare exception plans, which can be done at any time including in the final stage .
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Project team
identified and Authorities
appointed exist
Project
Sufficient
approach
information
selected
available
|PRINCE2 7 Foundation
®
Assemble the
project brief
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
of a PRINCE2 project
up a
project Managing Managing
a stage a stage Closing
boundary boundary a project
Managing
Managing Managing
Delivering
product delivery product delivery
Note
• Starting up a project is used by both the directing and managing levels.
• There should be at least two stages, the first of which is the initiation stage.
• Managing a stage boundary is first used at the end of the initiation stage and repeated at the end of each subsequent stage
except the final stage. It is also used to prepare exception plans, which can be done at any time including in the final stage .
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Overview of
a project
initiating a project
Initiate a Project
project authorization
authorization request
Agree tailoring
requirements
Agree the
management
approaches
Prepare the
full business
case
Stage
Managing a
boundary
stage boundary
approaching
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
To define how long it will take for the project to deliver what is
A
required to gain acceptance
To enable control between the project manager and team
B
managers
To review, at a high level, whether the project will add value to an
C
organization
To assess whether a project has been delivered on time and that
D
it has nothing more to contribute
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
A Starting up a project
B Directing a project
C Initiating a project
|PRINCE2 7 Foundation
®
A 1 and 2
B 2 and 3
C 3 and 4
D 1 and 4
|PRINCE2 7 Foundation
®
Starting up a project
Activity 1
Project brief task
Objective: To explain the role of
the project brief.
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Measured
by
Lead
to
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Subsequent Final
Initiation
Pre-project delivery delivery Post-project
stage
stage stage
|PRINCE2 7 Foundation
®
Offset by
associated
risks
Estimated Expected
costs against benefits
How and
when
benefits
can be
measured
|PRINCE2 7 Foundation
®
Sustainability
Project brief management
approach
Benefits
Business case management
approach
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Achievement
of project
Reviews sustainability
performance
targets
Controls
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Output
B. Costs
A. New sales systemby 10% and
are reduced
revenue increased by 10% annually
Outcome D. Sales orders are processed more
B. New sales
quickly andsystem
accurately
Benefit C.A. Some
Costscustomers
are reduced by 10%
perceive and
that therevenue
new
increased
system by 10%
provides annually
poorer customer service
Dis-benefit C. Sales
D. Someorders
customers perceivemore
are processed that the
quickly and accurately
new system provides poorer
|PRINCE2 7 Foundation
® customer service
Copyright 2023 PeopleCert International Ltd.
©
Question 1 | Answer
What is a purpose of the business case practice?
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
A organizations’ strategy
|PRINCE2 7 Foundation
®
A As a benefits tolerance
B As a sustainability tolerance
C As outcomes to be achieved
D As a quality tolerance
|PRINCE2 7 Foundation
®
A Develop
B Check
C Maintain
D Confirm
|PRINCE2 7 Foundation
®
Business case
Activity 1
The business case
Reason
• Discrimination is growing at a
concerning rate
Benefits
• Raising awareness
• Increased brand recognition
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Planning
|
PRINCE2® 7 Foundation
Copyright© 2023 PeopleCert International Ltd.
Plans in PRINCE2
project stage
plan plans
team exception
plans plans
|PRINCE2 7 Foundation
®
Project
plan
Team
plans
Figure 7.1 Relationship between PRINCE2 plans
|PRINCE2 7 Foundation
®
High-level Detailed
Good
design design practice to
avoid work
Site Ground
Project work preparation works Utilities packages
organized spanning
into logical
Substructure
stage
groups of Superstructure boundaries
Public
work Fit-out Mobilised
Mobilized
realm
operations
packages operations
Costs
Time
Manage
constraints at
Quality
each level of
the plan. Scope
Sustainability
Risk
|PRINCE2 7 Foundation
®
Easier to Simplifies
Avoids determine the Reduces the
identification
activities approach, risk of
and
which do not people and neglecting or
sequencing
contribute to resources, overlooking
timelines, risks of work
outputs scope
and issues packages
|PRINCE2 7 Foundation
®
Analysing risks
representation Preparing estimates Repeated for: write product
• Sequence • Project plan • Products/activities
descriptions and
Resource allocations Stage plan
create a product work
organized into
• •
• Team plan flow
• Costs of activities Preparing schedule
packages
diagram
• Risk budget • Closely related
• Change budget Preparing the budget people, resources,
• Cost tolerances activities
Documenting the plan • At least one product
• Plan has various parts • Dependencies –
• Narrative document • Resources
documented
helps explain at high • People
• No overlap
level Figure 7.3 the PRINCE2 planning procedure • Duration
• Cost
• Benefits
|PRINCE2 7 Foundation
®
Mechanical,
Utilities Substructure Superstructure
Electrical, Plumbing
Cleared &
System Fit-out for tenants Tenants ready
Secured site
Tenants secured
|PRINCE2 7 Foundation
®
Work
Plan package
description
Project
product
description
|PRINCE2 7 Foundation
®
Manage
Define roles,
by
Learn from responsibilities,
exception
Sharing planning experience and
relationships
lessons for
future projects
|PRINCE2 7 Foundation
®
A Project plan
B Stage plan
C Team plan
D Exception plan
|PRINCE2 7 Foundation
®
A dependency
B plan
C exception
D scope
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
C Preparing estimates
D Preparing a schedule
|PRINCE2 7 Foundation
®
Plans
Activity 1
Create a product
breakdown structure
Create a draft product breakdown
structure using the information
in the NowByou scenario.
Use your
Learner
Workbook to
note down
your ideas.
|PRINCE2 7 Foundation
®
Revised rail
timetable
Cleared & Operations needs
Substructure Tenants secured assessment
Secured site
Mechanical, Mobilised
External Systems Tenants ready
Electrical, Plumbing operations
product
High-level Marketing
Campaign options Campaign strategy
campaign definition campaign
Donors and
Options’
partners HL Creative concept TV campaign
description
requirements
Options
Brand recognition
assessment Campaign plan Press campaign
HL requirements
workshop
High-level
Campaign visual Social media
requirements
identity guidelines campaign
document
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
B. Requirement
2. The degree to which a set of inherent characteristics of a product, service,
process, person, organization, system, or resource fulfils requirements.
C. User’s quality
expectations 3. A prioritized list of criteria that the project product must meet
before the user will accept it.
D. Acceptance
criteria 4. A description of the quality measures that will be applied by
those performing quality control and the levels that the
finished product must meet.
E. Quality
specifications 5. A need or expectation that is documented in an approved
management product.
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Quality
management
Quality Quality
assurance control
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Assess quality
Implement
issues and Obtain user
quality
raise approval of
management
exceptions if products
approach
necessary
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Quality planning
Project product
description Quality management approach
Product descriptions
Quality specifcations
Quality methods
and tolerances
Quality control
Quality control
Quality register
activities
Product register
Acceptance Product
Quality Quality
Product Product
register management
description register
approach
|PRINCE2 7 Foundation
®
Manage
Define roles,
by
Learn from responsibilities,
exception
experience and
relationships
Aligning quality
controls and
techniques
with stage
boundary
controls
Establishing the quality
tolerances approved by the
project board in the project
|PRINCE2 7 Foundation
®
initiation documentation
Copyright 2023 PeopleCert International Ltd.
©
Review
You should now know:
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
A Quality register
B Quality specifications
C Product register
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
B Accepting products
D Controlling quality
|PRINCE2 7 Foundation
®
Quality
Activity 1
Quality specifications and Use your
Learner
tolerances in NowByou Workbook to
note down
your ideas.
Quality
|PRINCE2 7 Foundation
®
Considerations
your Learner
Learner
Workbook to
Workbook
complete theto
note down
activity
your ideas.
Quality specification Quality tolerance
A description of the quality Permissible deviation in
measures that will be
applied by those quality before escalation is
performing quality control required
and the levels that the
finished product must Consider:
meet.
• Prioritized specifications
Consider:
• User’s quality
expectations
• Business or operational
context
Quality
|PRINCE2 7 Foundation
®
|PRIINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
exposure
budget
likelihood
tolerance
impact
appetite
proximity
|PRINCE2 7 Foundation
®
Identify and
prioritize risks Risk Risk Risk
using risk cause event effect
categories
Threat
|PRINCE2 7 Foundation
®
Very low 9 2 5
Impact
Risk tolerance line
Threat Opportunity
Figure 9.1 Risk matrix
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
bias.
Proximity
|PRINCE2 7 Foundation
®
Communicate
|PRINCE2 7 Foundation
®
1 Maintain the risk register. Ensure that project risks are being
identified, assessed, and controlled throughout the project lifecycle.
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Executive
Senior supplier
Senior user
Business layer
Project manager
Project assurance
|PRINCE2 7 Foundation
®
Ensure
continued Focus on Tailor to suit Manage by
business products the project stages
justification
De-risking the
Define roles,
Learn from responsibilities, Manage by project by having
experience exception
and
relationships
‘stop-go’ decisions
at critical points at
the end of project
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
B Risk register
|PRINCE2 7 Foundation
®
A Risk owner
C Project support
D Project assurance
|PRINCE2 7 Foundation
®
By valuing the need to keep what you have, rather than to get
A
something new
By discounting downside risk, believing that things will go
B
according to plan
|PRINCE2 7 Foundation
®
A Identify
B Assess
C Plan
D Implement
|PRINCE2 7 Foundation
®
Risk
Activity
Identifying and analysing
risks
Identify and analyse three
possible risks for NowByou.
Communicate
|PRINCE2 7 Foundation
®
Probability Impact
(High/Medium/Low) (High/Medium/Low)
|PRINCE2 7 Foundation
®
|PRIINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Managing Managing
Delivering
product delivery product delivery
Note
• Starting up a project is used by both the directing and managing levels.
• There should be at least two stages, the first of which is the initiation stage.
• Managing a stage boundary is first used at the end of the initiation stage and repeated at the end of each subsequent stage
except the final stage. It is also used to prepare exception plans, which can be done at any time including in the final stage .
|PRINCE2 7 Foundation
®
Figure 12.1 The PRINCE2 processes
Copyright 2023 PeopleCert International Ltd.
©
Purpose of controlling a stage process
assign work to be done
|PRINCE2 7 Foundation
®
Overview of
Exception plan
authorized
OR
controlling a
Stage Exception Request for Project board’s
authorized raised advice advice
Managing a Closing a
boundary project
Evaluate Receive
Authorize a work package completed work
work package status package
Managing
|
PRINCE2® 7 Foundation
Copyright© 2023 PeopleCert International Ltd.
product delivery
Controlling a stage activities
The activities of the project
Work
manager in controlling a packages
stage involve:
Issues
Escalate issues and Report highlights
Controlling a risks
stage
and risks
Take corrective action Evaluate stage status
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Notify work
Package Evaluate a
completion
work package
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
product descriptions
approval
Work
package
techniques and procedures
references
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
D 1 and 4
|PRINCE2 7 Foundation
®
Team manager
3 Who authorizes a work package? (1 point)
Project manager
4 Who executes a work package? (1 point)
Team manager
5 What else does this person do? (3 points)
Make notes
in your
Learner
Workbook
|PRINCE2 7 Foundation
®
|PRIINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Assure
project Record
board Provide information
information to help later
to assess stages or
viability projects
|PRINCE2 7 Foundation
®
Business
The project can Provides a means
justification should
be redirected or for implementing
be reconfirmed at
stopped if an exception
the end of each
necessary procedure
stage
|PRINCE2 7 Foundation
®
managing
Exception plan
Exception plan
approval
request
request
OR
Update the
project plan
Prepare next
stage plan Managing a
Figure 18.1 Overview of stage boundary
managing a stage boundary
Stage
Initiating a Controlling a
boundary
|
PRINCE2® 7 Foundation
Copyright© 2023 PeopleCert International Ltd.
project
approaching
stage
Review
You should now know:
• The purpose, objectives and context of the managing a
stage boundary process
• The activities in the managing a stage boundary process.
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Managing a stage
boundary
Activity 1
Create a checklist
Objective: Understand the
management products that are
relevant to this process.
|PRINCE2 7 Foundation
®
|PRIINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Business Off-
opportunity specification
Problem or
concern
|PRINCE2 7 Foundation
®
Often
presented
informally
Categorize by
issue type
Monitor the
external
Apply environment
judgement
Identify
issues early
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Issues
Issue
report
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
A Assessing issues
B Capturing issues
C Deciding on issues
D Implementing changes
|PRINCE2 7 Foundation
®
Issues
Activity
Identifying issues for
NowByou
Objective: To describe types of
issue.
Off-specification
An issue with an immediate and negative
impact / An issue whose timeliness and
impact need to be considered.
|PRINCE2 7 Foundation
®
|PRIINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
control any
establish unacceptable
mechanisms to deviations
monitor and
compare actual
achievements
against those provide a
planned forecast for
the project’s
objectives and
continued
viability
|PRINCE2 7 Foundation
®
Forecast
Exception
A prediction
made by A situation where it can
studying be forecast that there
historical data will be a deviation
and past beyond the
patterns tolerance levels agreed
between the project
manager and the
project board
|PRINCE2 7 Foundation
®
Validate results
Perform specific steps
Identify further actions
Benefits Time
Cost
Risk
Quality
Sustainability Scope
|
PRINCE2® 7 Foundation
Copyright© 2023 PeopleCert International Ltd.
Delegating tolerances
and reporting Business layer
progress Project
plan
Project
tolerances
Project progress
/exceptions
Project
status/
Exception
Reporting
format and
frequency to
report be confirmed
with business
layer
Project board
Highlight Reporting
Stage Stage Stage progress report/ format and
plan tolerances /exceptions Exception frequency to
report be confirmed
with the
project board
Project manager
|PRINCE2 7 Foundation
®
Team manager
Copyright 2023 PeopleCert International Ltd.
©
Types of control
Event-driven controls
Control (decision-making) is an event-based activity.
Time-driven controls
Monitoring and reporting requires a time-
based approach.
|PRINCE2 7 Foundation
®
What needs to be
done differently or
be repeated?
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
PRINCE2 does
Frequency of
not define
reporting
report
should reflect
composition,
required level
format, or
of control
presentation
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Stage-level exceptions
Project manager should produce an issue report and then an
exception report for the project board. The board may then
request an exception plan or take other action.
Project-level exceptions
If project tolerances are forecast to be exceeded the project
board must refer this to the business layer for a decision.
|PRINCE2 7 Foundation
®
Digital
Data analytics systems
Greater supports support work
accuracy decision- across
making multiple
locations
Automation
Solutions must
Digital allows a
fit
technology professional
requirements
has supported focus on
and business
data collection value-adding
maturity
activities
|PRINCE2 7 Foundation
®
Directing a project
2 3 5 4
!
Issue 1
1
Managing product
delivery Figure 11.3 PRINCE2 technique for exception management
|Copyright 72023
PRINCE2®
©
Foundation
PeopleCert International Ltd.
Applying the principles
Know the status of Clarify reporting
each product and requirements and
the project product progress
during delivery management
responsibility
Manage
Define roles,
by
Learn from responsibilities,
exception
experience and
relationships
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
C Highlight report
D Checkpoint report
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Definition Term
A Responsible for setting work package tolerances 6 Project manager
B The result of change normally affecting real-world behaviour and/or circumstances 5 Outcome
C To list all the products required of a plan and the status of those products 9 Product register
D To provide a full and firm foundation for the initiation of the project 10 Project Brief
E The process that controls the link between the project manager and the team manager 3 Managing product delivery
F To report where tolerances have or are forecast to be breached 8 Exception report
G Doing the minimum necessary to decide whether it is worthwhile to initiate the project 1 Starting up a project
H Accountable for the quality of the products delivered 7 Senior supplier
I The measurable improvement resulting from an outcome, perceived as an advantage
2 Benefit
by the investing organization
J A guiding obligation that ensures effective application and tailoring of PRINCE2 to any 4 Principle
project
|PRINCE2 7 Foundation
®
Definition Term
K Maintains information on all the identified threats and opportunities 15 Risk register
L A problem, concern, change request, or off-specification 18 Issue
M Any individual or group that can affect or be affected by the project 20 Stakeholder
N The process that covers the activities of the project board 17 Directing a project
O A diagram showing the sequence of production of products and interdependencies 12 Product flow diagram
P The single point of accountability for the project 14 Project executive
Q People from across the project ecosystem working together to achieve the project’s
19 Collaboration
objectives
R The section of a project that the project manager is managing on behalf of the project
11 Stage
board at any one time.
S to provide a progress and status update of the stage/project at pre-determined intervals 16 Highlight report
T Providing services such as administration, planning support, and guidance on project
13 Project support
tools
|PRINCE2 7 Foundation
®
Progress
Activity 2
Document task
Prepare an explanation of the document(s) you are assigned.
Checkpoint report Highlight report End stage report End project report
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Prepare Prepare
Planned closure Premature closure
Confirm project
acceptance
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Closing a project
Activity
How to prepare for
planned closures
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Provide management Ensure the business layer Ensure plans for realizing
direction and control has a connection to the the post-project benefits are
throughout the project. project. managed and reviewed.
|PRINCE2 7 Foundation
®
Manages by Ensures
exception continued
business
justification
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
A 1 and 2
B 2 and 3
C 3 and 4
D 1 and 4
|PRINCE2 7 Foundation
®
Directing a project
Activity 1
Make notes
|PRINCE2 7 Foundation
®
Directing a project
Activity 2
Project board activities
Project board
?
|PRINCE2 7 Foundation
®
Answers Manages by
exception
business
justification
Authorize
project
Authorize a
closure
stage or
exception
pan
Give ad hoc
direction
|PRINCE2 7 Foundation
®
Principles
|PRINCE2 7 Foundation
®
Plans
Risks
Issues Progress
Principles
|PRINCE2 7 Foundation
®
Managing Managing
Delivering product delivery product delivery
Note
• Starting up a project is used by both the directing and managing levels.
• There should be at least two stages, the first of which is the initiation stage.
• Managing a stage boundary is first used at the end of the initiation stage and repeated at the end of each subsequent stage
except the final stage. It is also used to prepare exception plans, which can be done at any time including in the final stage
.
risk time
scope
quality
sustainability
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Community Previews
White papers
forum
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
|PRINCE2 7 Foundation
®
Thank you!
|PRINCE2 7 Foundation
®