TECHNICAL PROPOSAL:
WORK PLAN
Milestone event Milestone date Milestone Nature
Starting the shop drawing upon
Assigning JUN. 15-2025
receiving the down payment
Materials samples supply JUN 18-2025 Start
Materials samples approvals JUN 30-2025 Finish
Mobilization starts JULY. 10-2025 Start
Shop drawing submittal JULY 10-2025 Start
Approved shop drawing JULY 15-2025 Starting the contract period
Starting when having the
Aluminum work manufacturing JULY. 16-2025
downpayment.
Stone & Marble work Starting when having the
JULY. 16-2025
manufacturing downpayment
Starting when having the
Teak woodwork manufacturing JULY. 16-2025
downpayment
Work starts on site JULY 16-2025 Start
Stone & Marble supplying JULY 30-2025 Start.
Manufactured wood supplying AUG 30-2025 Start.
Manufactured Aluminum
SEP 16-2025 Start
supplying
Complete materials supplying JAN 30-2026 Finish
Work finish FEB. 2-2026 Finish
Project finish FEB. 2-2025 Finish
MANUFACTURING LEADTIME:
The most important materials will start manufacturing on July 16, 2025, and complete supply on site
on January 30, 2026.
SHOP DRAWING TIMELINE:
Shop drawings will be submitted on July 10, 2025, and must be completed with approvals on July 15,
2025.
IMPLEMENTATION TIMELINE:
Work on site will start on July 16, 2025, and will be completed on February 2, 2026, Detailed events
will be provided by our timeline we will submit when contracting.
MATERIALS LIST, PROCUREMENT TRACKER, AND MOBILIZATION PLAN NEED NEGOTIATIONS AND
APPROVALS, SO WILL BE AGREED UPON WITH THE PROJECT MANAGER AND CONSULTANT WHEN
CONTRACTING.