M6A - Insulation Manual
M6A - Insulation Manual
(1) PURPOSE
This manual covers the minimum requirements for material and applications to
be used in the thermal insulation of Company’s vessels, equipment and pipe
works. The aim is also to ensure that the performance and application of the
work is in accordance with the commonly used standards for good workmanship
in the country where the plant is to be constructed. The recommendations and
standards listed in this manual are to be observed carefully.
(2) SCOPE
This manual covers all applications operating between -268 oC and 650oC. This
manual does not incorporate the REFRACTORY insulation of Furnaces,
Reformers or Fired heaters etc..
(3) RESPONSIBILITIES
The Head of Civil Section is responsible to monitor that this manual is adhered
to. The Corrosion Protection Engineer shall be responsible for ensuring that this
manual is followed. The Mechanical Field Engineers are responsible for the
integrity of Insulation. All Project Coordinators are responsible for ensuring that
all Insulation works that may be carried out in lump sum projects etc. are
according to this manual, and shall submit the Fmt-Ci-009, Rev.0,
23/2/06 - Notification of Insulation Request Form for Inspection
(Available Online under controlled documents) to the Corrosion Protection
Engineer at least 24 hours prior to insulation works commencing. Any
deviations from the Company manual shall be approved in writing from the
Head of Civil Section prior to works commencing.
(4) DESCRIPTION
4.1 GENERAL
4.2 COLD INSULATION
4.3 HOT INSULATION
4.4 PERSONNEL PROTECTION
4.5 ACCOUSTIC INSULATION
4.6 MATERIALS
4.7 STORAGE/HANDLING
4.8 COLD INSULATION THICKNESS
4.9 HOT INSULATION THICKNESS
4.10 ACOUSTIC INSULATION THICKNESS
(5) REFERENCE
Section: Civil Page 2 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
(6) DEFINITIONS
(7) LIST OF DRAWINGS
(8) APPENDIX OF DRAWINGS
4.1 GENERAL
The contractor has the following responsibilities in the performance of the work
under the contract:-
To familiarize himself with the type and extent of the work to be provided
under the contract.
To provide a high quality, workmanlike installation and respect Qafco and its
Contract Coordinator’s responsibility for reviewing workmanship and
materials at any stage after the award of the contract.
Products equivalent to the Qafco manual there under shall be accepted after
the physical properties are reported to and approved in writing by the
Company.
The insulation work should not be started until the pressure test of
equipment and pipelines has been completed. All joints (bolted, flanged,
welded, laminated) shall only be insulated after the pressure test. Valves
and flanged joints which were provided with line blinds shall only be
insulated after the leakage test. Pipes without welds may be insulated prior
to the pressure test. For the leakage test of cold-insulated pipelines with
process fluids at operating temperatures, valves and flanges shall be
temporarily insulated (e.g. by means of mineral fiber mats) to prevent the
formation of ice)
Section: Civil Page 3 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
This recommendation applies to the thermal insulation of equipment,
vessels, machinery and pipelines. It contains generally applicable
requirements for insulation materials (type of insulation materials, sheet-
metal, hardware) and the performance of insulation work. This
recommendation will be supplemented by special instructions, if necessary.
Deviations from this recommendation shall be agreed upon in writing.
All surfaces to be insulated shall be clean, dry and free from coarse rust and
scale. Painted surfaces shall be insulated only after the paint has dried
thoroughly.
All piping and equipment within this manual shall be completely insulated
including all hand hole covers, manholes, flanges, fittings and valves etc..
Insulation pipe sections shall be secured with S.S. banding of 25mm over the
pipe covering at about 500 mm centers. All insulation boards shall be
butted tightly together with S.S. Banding of 25mm.
Insulating materials, unless otherwise stated, shall have a PH value of
between 7 and 10 in order that the possibility of corrosion of insulated
equipment or piping is negated. Insulation materials with a leach able
chloride iron content of <6 mg. /kg. Shall be used.
Ceramic Fiber wool blankets shall be used especially for Reformer and
Instrument tubing due to high temperature limits.
Boards shall be used for flat walls. These should be held in place by the use
of insulation pins or suitable approved fixings.
On horizontal pipes subject to foot traffic, the cladding material on the top
quadrant only shall be 2mm thick. (This may be applied in two separate
layers). Particular care and attention shall be exercised in the fabrication,
fitting and sealing of insulation, vapour barriers and cladding around
supports, brackets, nozzles etc. Where possible these shall be insulated to
the same thickness as the piping or equipment, over a length of at least four
times the thickness or 300mm, whichever is the greater.
In the case of Vertical vessels and other equipment, the appropriate type of
metal sheet- Flat or corrugated – (according to Qafco manual) shall be cut to
size and shape, fabricated and assembled to fit to the contour of the vessel
allowing a minimum overlap on longitudinal seams of 75mm and of 100 mm
on circumferential seams.
Roof slope bottom and side ends shall be jointed with the vertical wall
sheets by 1mm thick flat aluminum sheet Flashings. Armaflex or equivalent
materials shall be used to block wall sheet corrugation troughs.
All overlap joints in the cladding shall be sealed with suitable joint sealant as
per Qafco manual.
The Cladding of valves and flanges shall be tapered to allow removal of the
bolts without damage to the insulation. The taper shall be thoroughly sealed
with mastic. At Interruptions in the line, the cladding shall be terminated in
such a manner so as not to impede the withdrawal of stud bolts. In the case of
horizontal pipe run the cladding shall be fitted with end caps of lock form
construction. In case of vertical pipe runs the upper end cap shall be of conical
construction to provide a watershed.
FOR PIPING:
Straight parts, elbows, reducers, tees : by the "Classic Method" or "In-
Situ Method"
Flanged components : by the "Classic Method" or "In-Situ
Method"
Insulation must not be applied to surface that are covered with ice or water.
This is best achieved by restricting the application of cold insulation to plant
shutdown periods. Where it is essential to insulate pipe work, equipment,
fittings on pipe work etc., during maintenance jobs, every effort must be
made to remove ice, either physically or using methanol and drying the
surface as much as possible prior to insulation.
Polyol and Isocyanate mixed and injected materials shall be from the same
manufacturer.
The foam shall be in the form of two components froth foam, produced with
the aid of proprietary ‘insta-foam’ portable pressurized dispenser and
chemical components supplied in the disposable pack form and shall be
introduced through appropriate sited injection holes which have a diameter
of no more than 5.5mm.
In the case of foaming in closed system, at least one opening for filling and
one opening for inspection shall be provided at the uppermost point of the
respective chamber.
Section: Civil Page 7 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
Prior the foaming, the ends of the cladding (e.g. at flanges) shall be sealed
against the foaming pressure (e.g. by means of shaped parts of foam).
After foaming, the openings for filling shall be sealed by means of covers made of sheet metal or
plastics. The opening for inspection shall be sealed by means of self-tapping screws and seal
washers made of plastics as soon as the foam overflows. Extra foam spread on the cladding shall
be cleaned.
Boards, formed slabs and pipe covers shall be laid on clean surface with
closely butted joints. The joints may be glued with joint sealer. Adhesives
shall not adversely affect the foam and coatings.
All insulation boards having been applied in a day shall be covered with the
vapour barrier at least single layer within the same day.
Section: Civil Page 8 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
Vapour seal should be applied over the banding clip area to fully seal and
avoid any damaged.
Final drying shall extend over three days, before the application of any
metal cladding. It is not permitted to use screws as fixings, metal
cladding shall be secured with S.S. banding at the pitch of 150mm.
Valve, Flanged joints, etc., should also be insulated with shells. Cavities and
gaps shall be carefully filled with the same type of foam.
All joints shall than be secured with self-tapping screws only in case “SITU
Method” at
Maximum pitch of 150mm.
METHODS OF APPLICATIONS
All insulation pipe covers / boards shall be butted tightly together with
vapour sealer.
All insulation pipe covers / boards having been applied in a day shall be
covered with the vapour barrier at lest single layer within the same day.
Vapour seal should be applied with gloved hand, trowel or float over the
banding clip area to fully seal any damaged.
Foam Glass shells and slabs shall have small and mainly closed cells. To
avoid cracks caused by internal stresses (e.g. because of changes in
temperature), the size of the shells or slabs shall be selected accordingly.
For single layer applications a staggered joint (>150mm) should be cut from
one half of the insulation, the remaining section should have a bead of joint
sealer fitted to the circumferential and longitudinal joints
Mastic Material shall be emulsion pre-mixed. Two coats shall be applied. The
initial tack coat shall be applied to provide a film thickness of 1mm. A layer
of 10x10 glass cloth Scrim cloth #10 overlapped at least 50mm shall be
used on wet first layer coating of vapour barrier by the application of slight
Section: Civil Page 10 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
pressure working from the centre to the edge, all adjoining edges,
protrusions and terminal points having a 75mm overlap.
The second coat of 1mm thickness vapour barrier to be applied not less than
6-8 hours after the first coat and smoothed to uniform finish to provide a
continuous seal ensuring that the reinforcing membrane is completely
covered.
For the Multi-layer applications the inner layer shall be applied dry and
secured by tape of 25mm wide (glass reinforced polyester self adhesive
tape at 100mm center). Oversized sections or radiuses and beveled lags
shall be fitted with a staggered joint, jointing compound, vapour sealer and
scrim cloth which are to be applied in the same manner for the application
of a single layer (On no account should wood or metal skewers be used that
will penetrate of the insulation as this may cause a cold path.)
Metal Cladding.
Cladding Requirement in “Cryogenic” is optional and shall be decided by
Qafco authorized
Representative according to technical requirements.
Thermal insulation for pipe work, valves etc., operating at high or low
temperatures.
Material should have a high resistance to oil and in standard fire test to
minimized smoke development and water vapour transmission combined
with low thermal conductivity and fire performance.
Material should be self-extinguishing. Should not generate burning
droplets.
METHODS OF APPLICATIONS
Mattress shall be cut to suit the outer diameter of the insulation. Each layer
of mattress on vertical equipment and vertical pipes with diameter of
>1mtr. Shall be additionally secured against sliding off by means of S.S.
banding of 25mm.
When G.I. wire is used to tighten insulation board, knots or twisted ends
shall be bent down into the boards.
Where pipe work is fitted with heat tracing, for better heat transfer, a
thermal shield or a thermal foil shall be placed between the insulation
material and the tracing. The shield or foil shall prevent the insulation
material from penetrating between the tracing and the surface to be
insulated.
In the case of plastic pipes, an aluminum foil may be placed between the
surface to be heated and the tracing cable for better heat distribution. This
foil shall be placed as smooth as possible. The tracing cables as well as the
sensing elements of temperature measuring and control instruments shall
not be damaged and their position not to be changed.
Flanges and valves on hot oil lines are usually left bare in case the insulation
material becomes saturated in the event of a flange leak. This may not be
readily seen and could result in spontaneous combustion. If the un-insulated
valve or flange presents a hazard to plant personnel, a simple box prefabricated
from aluminium cladding with no insulation infill can afford protection.
Metal-to-Metal contact
Ceramic Glass Fibre Blankets shall be used for Reformer pigtails, doglegs,
flexible Instrument tubing & steam tracing lines. Ceramic Re-enforced
Aluminised Glass Fabric Cloth (used internal application where proper water
shed is provided) & Ceramic Re-enforced glass fabric with water proof coating
(used for external application) shall be used as wrapping material for Ceramic
Glass Fibre blankets.
Each layer of insulation board thickness shall not be greater than 50mm.
Hot & Cold Acoustic materials must be replaced with same materials as
existing.
Metal cladding shall be used for the protection of an acoustic system (see
section 4.6). The Sound deadening coating shall have a thickness of
>2mm. (preferably Terophone -112 DB) shall be applied to the internal
portion of cladding and caps. The gross density of the sound-deadening
compound should be approx. 1400 kg/m3. The product of the reducing
factor and the modulus of elasticity (N/cm2) shall be >10 N/cm2 in the
temperature range of 0 to 60oC.
The sound deadening coating shall have a thickness of >2 mm. The
gross density of the sound-deadening compound should be approximate
1400 kg/m3. The sound deadening coating shall be applied to the inside of
claddings and caps. The overlapping areas of the longitudinal and
circumferential seams including the crimps may be left uncoated.
Permanent adhesion between the sound deadening coating and the
cladding must be ensured.
Valves, Flange & Acoustic Covers (Applicable for Hot and Hot
Acoustic Insulation)
4.6 MATERIALS
General
Metal Jacket
The sheeting shall be plain aluminium, semi hard Type AA 3105 H-14 plain,
or corrugated aluminum sheet to DIN-EN 573 / ASTM B-209 or equivalent
standard. The alloying components shall be 0.3 - 0.8% Mn., and 0.2 – 0.8%
Mg.
* 0.8mm thickness of plain sheet for piping & vessels circumference under 450
mm
* 1.0mm thickness of plain sheet for piping & vessels circumference over 450
mm.
* 1.0mm Aluminum Corrugated sheet shall be used for all vertical equipments
circumference
>10,000mm
FASTENING MATERIALS:
Bands:
Bands shall be stainless steel, AISI 304. Application methods of banding are
shown on the attached standard drawings in this manual. Banding shall be
secured as follows :
Stainless Steel banding shall be used on all diameter pipe work, vessel,
Equipment & Exchangers.
Wires:
Wire shall be G.I. The minimum thickness shall be 0.8mm thick.
Section: Civil Page 17 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
Sealing Materials
Netting:
Net for reinforced mineral wool and mastics shall be used as follows :
For mineral wool : Mesh size 20 mm. hexagonal
Diameter of wire : 0.7mm
Self-adhesive aluminium foil tape, 50mm wide for indoor applications. Vapour
barrier coating for outdoor applications according to Cold Insulation applications
(Optional)
Form :
Mineral Wool shall be used solely in mattresses, pipe cover or slab form, the use
of packing materials is prohibited and the mattresses shall not get out of shape
particularly under their own weight.
Characteristics of wool most currently used with application range:
In order to avoid any risk of corrosion its chemical composition shall be checked
in particular:
Alkaline oxide content : 0.3% maximum
Sulphur, in soluble salt form : 0.0% maximum
Sulphur in insoluble salt form : 0.5% maximum
Chlorides iron Contents : <6 mg./kg.
Mineral Wool shall be used solely in mattresses, pipe cover or slab form. The
use of packing materials is prohibited, and the mattresses shall not get out of
shape particularly under their own weight. The following are the characteristics
of wool most currently used with application range :
Thermal Conductivity :
Section: Civil Page 20 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
MT 1000C 1500C 2000C 3000C
W/mk 0.047 0.055 0.067 0.096
Density : 80 Kg/m3 - temperature up to 1500C inclusive
: 100 Kg/ m3 - temperature from 1500C to 3000C inclusive
4.7STORAGE/HANDLING
All insulation materials shall be dry and shall be placed into dry storage
facilities allocated for this purpose. The Insulation Contractor shall
provide site materials facility/ies.
QAFCO – III
Polyurethane ASTM C 591 or better (Units:
mm.)
Temprature
Limits ( 0C )
- 40 or Less
-29 TO -20
-19 TO -10
-39 TO -30
TO 0
0 TO 20
Nominal
Size
(inches)
-9
½ - 3
/4 50 50 40 40 40 40
1 50 50 40 40 40 40
1 1/4 - 11/2
50 50 50 40 40 40
2 - 2 1/2 50 50 50 40 40 40
3 60 60 50 40 40 40
4 60 60 50 40 40 40
6 - 8 80 80 60 50 40 40
10 80 80 60 50 40 40
12 80 80 60 50 40 40
14 80 80 60 50 40 40
16 80 80 60 50 40 40
18 80 80 60 50 40 40
20 80 80 60 50 40 40
24 80 80 80 60 50 40
Above 24” 80 80 80 60 50 40
QAFCO - IV
Temprature
Limits ( 0C )
- 40 or Less
-29 TO -20
-19 TO -10
-39 TO -30
TO 0
0 TO 10
Nominal
Size
(inches)
-9
½ - 3
/4 50 50 40 40 40 40
1 50 50 40 40 40 40
1 /4 - 1 /2
1 1
50 50 50 40 40 40
2 - 2 1/2 50 50 50 40 40 40
3 60 60 50 40 40 40
4 60 60 50 40 40 40
6 - 8 80 80 60 50 40 40
10 80 80 60 50 40 40
12 80 80 60 50 40 40
14 80 80 60 50 40 40
16 80 80 60 50 40 40
18 80 80 60 50 40 40
20 80 80 60 50 40 40
24 80 80 80 60 50 40
Above 24” 80 80 80 60 50 40
QAFCO I & II
(Unit : mm)
Tempratur
From 60 - 150
231 - 300
201 - 400
401 - 600
Nominal
Size
(inches)
½ 30 30 40 50 80
3
/4 30 30 40 50 80
1
30 30 40 50 80
11/2 QAFCO 30
– III
30 40 50 80
2 30 30 40 80 100
3 30 40 50 80 100
4 30 40 50 80 100
6 40 40 80 80 100
8 40 40 80 80 100
10 40 40 80 100 150
12 40 50 80 100 150
14 40 50 80 100 150
Above
14” &
Shell, 40 50 80 100 150
Equip.
Etc.
Section: Civil Page 24 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
QAFCO III
(Unit : mm)
Temprature
Limits ( 0C )
176 - 230
231 - 290
291 - 340
341 - 400
401 - 455
456 - 510
Upto 120
121 – 175
Nominal
Size
(inches)
½ - 3
/4 30 40 50 50 80 80 80 80
1 30 40 50 80 80 80 80 80
1 /4 - 1 /2
1 1
30 40 80 80 80 80 80 80
2 - 2½ 40 50 80 80 80 80 80 80
3 50 80 80 80 80 80 80 100
4 50 80 80 80 80 100 100 100
6 - 8 60 80 80 80 100 100 100 100
10 80 80 80 100 100 100 100 100
12 80 100 100 100 100 100 100 150
14 80 100 100 100 100 100 100 150
16 80 100 100 100 100 100 150 150
18 80 100 100 100 100 150 150 150
20 80 100 100 100 100 150 150 150
24 80 100 100 100 150 150 150 150
Above 24” 80 100 100 100 150 150 150 150
Personal
Protection 30 40 50 50 50 80 100 100
(PP)
Section: Civil Page 25 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
QAFCO – IV
(Unit : mm)
Temprature
Limits ( 0C ) 176 - 230
231 - 290
291 - 340
341 - 400
401 - 455
456 - 510
511 - 600
Upto 120
121 – 175
Nominal
Size
(inches)
½ - 3
/4 30 50 50 50 80 80 80 80 100
1 30 40 50 80 80 80 80 80 100
1 1/4 - 11/2
30 40 80 80 80 80 80 80 100
2 - 2 1/2 50 50 80 80 80 80 80 80 100
3 50 80 80 80 80 80 80 100 100
4 50 80 80 80 100 100 100 100 100
6 - 8 80 80 80 80 100 100 100 100 150
10 80 80 80 100 100 100 100 100 150
12 80 80 100 100 100 100 100 100 150
14 80 80 100 100 100 100 100 150 150
16 80 80 100 100 100 100 150 150 150
18 80 80 100 100 100 150 150 150 150
20 80 80 100 100 100 150 150 150 150
24 80 80 100 100 150 150 150 150 150
Above 24” 80 80 100 100 150 150 150 150 150
Personal
Protection 30 30 30 30 50 80 80 100 150
(PP)
with
with
Equipment to
Steam Tracing.
(Desalination
(Desalination
(Desalination
(Desalination
be insulated
compressors.
Steam Chest
exchangers
condensers
Operating
Ejectors,
Ejectors
Ejectors
Temperatures
Units)
Unit)
holes
(0C)
60 – 150 50 100 60 60 50
151 – 250 -- 100 70 70 50
251 – 350 -- -- 80 80 80
351 – 450 -- -- -- -- 100
451 – 600 -- -- -- -- 130
Section: Civil Page 26 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
NOTE :- Schedule of Acoustic insulation thickness is based on original engineering Specifications of each plant.
QAFCO – III
(Units
: mm.)
Temprature
Limits ( 0C )
176 - 230
231 - 290
291 - 340
341 - 400
401 - 455
456 - 510
Upto 120
121 – 175
Nominal
Size
(inches)
½ - 3
/4 80 80 80 80 100 100 100 100
QAFCO – IV
(Units:
mm.)
Temprature
Limits ( 0C )
176 - 230
231 - 290
291 - 340
341 - 400
401 - 455
456 - 510
511 - 600
Upto 120
121 – 175
Nominal
Size
(inches)
½ - 3
/4 80 80 80 80 100 100 100 100 100
5. REFERENCE
BS En 12241 : 1998.
DIN – EN 573 / ASTM B-209 or Equivalent
AISI 304
ASTM C 518
Section: Civil Page 28 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
ASTM C 591
DIN 52612
ASTM C 177
ASTM C 209
ASTM C 236
ASTM D 1662
ASTM D1667
6. DEFINITIONS
Applications in the temperature range are between -268oC and 650oC termed
“Thermal Insulation”. Thermal Insulation is further split into 3 categories.
All applications below -73.3ºC (-100ºF) are termed “Cryogenic”, and those above
815.6ºC (1500ºF) are termed “Refractory”.
Section: Civil Page 29 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
7. LIST OF DRAWINGS :
COLD INSULATION
S. Drawing Description
No. No.
1 C-1 Application Method Of Banding
2 C-2 Heads Insulation
3 C-3 Insulation For Straight Pipes
4 C-4 ( 1/2 ) Insulation For Flanges Of
Equipment
5 C-4 ( 2/2 ) Insulation For Pipe Flanges
6 C-5 Insulation For Valves & Flanges
7 C-6 Insulation For Tees And Elbows
8 C-7 Insulation For Hangers &
Supports
9 C-8 Insulation Support For Pipes
10 C-9 ( 1/4 ) Insulation for Expansion Joints
( Typical )
11 C-9 ( 2/4 ) Insulation for Expansion Joints
( Typical )
12 C-9 ( 3/4 ) Insulation for Expansion Joints
( Typical )
13 C-9 ( 4/4 ) Insulation for Expansion Joints
( Typical )
14 C-10 Flexible Elastomeric Pipe
Insulation
15 C-11 Elastomeric Sheets
HOT INSULATION
S. Drawing N. Description
No.
1 H-1 Application Method Of Banding
2 H-2 Head Insulation
3 H-3 Expansion Joint For Towers &
Vertical Drums
Section: Civil Page 30 of 27
Approved: Head of Section Date: 2/04/2005
Signature: Replaced: SMt-Ci-004, Rev: 0, 01/03/1996
THERMAL INSULATION MANUAL
4 H-4 Insulation For Piping
5 H-5 (1/2) Insulation For Flanges Of
Equipment
6 H-5 (1/2) Insulation For Pipe Flanges
7 H-6 Insulation For Valves & Flanges
8 H-7 Insulation For Trace Piping
9 H-8 Insulation For Hangers &
Supports
10 H-9 Insulation Support For Pipes
11 H-10 Insulation Of Tanks
12 H-11 Steam Tracing Arrangement
13 H-12 Typical Arrangements For
Cladding
ACOUSTIC INSULATION