MWSP III (LAIBAN DAM PROJECT)
27 October 2009
PRESENTATION OUTLINE
 Project Background
 MWSSP III, Laiban Dam, Other Water Sources
 Current Water Situation in Metro Manila
 Demand Supply Gap, Angat Dam, the NEED for Laiban
 The Laiban Dam Project Proposal
 Technical Description  Design Considerations, Facilities  Project Activity Schedule  Implementation Framework  LARP  Environment Assessment  PROJECT COST
MWSP III IDENTIFIED WATER SOURCES
Marikina River Basin Kaliwa Basin Kanan Basin Umiray Basin Laguna Bay Taal Lake Pampanga River Calamba-Sta.Rosa Groundwater Marikina Groundwater
MWSP III PROJECT SELECTION
SOURCE
Kaliwa River (Laiban Dam) Marikina River Kanan River Umiray River (UATP to Angat) Laguna Bay (entire lake) Laguna Bay (eastern portion only) Pampanga River Taal Lake Calamba-Sta. Rosa Groundwater Lower Marikina Groundwater
YIELD (MLD)
1,909 1,280 3,170 777
Remarks
Most economic source (1987) Socially unacceptable (1987) Only after Kaliwa (transbasin) Implemented 1998, to undergo rehab, additional source (190 MLD) Pollution control measures before exploitation for water supply Requires 1.95 m dike in the bay (1992) Pumping cost energy relatively high Not recommended due volcanic hazard For local supply only For local supply only
2,592 1,782 2,592 864 190 130
STUDY ON WATER RESOURCES DEVELOPMENT FOR METRO MANILA (JICA, 2003)
UMIRAY Transbasin ANGAT DAM
Kanan Dam No. 1 Kanan Low Dam Agos Dam
Laiban High Dam
Laiban Low Dam
Kaliwa Low Dam
Water Sources for Metro MANILA Estimated Yields (Capacities)
Scheme Capacity (MLD) Source Combination
1 2 3 4 5 Laiban Dam+Kanan No. 2 Dam Kaliwa Low Dam + Agos Dam Agos Dam Alone Laiban Dam + Agos Kaliwa Low Dam + Kanan No. 2 Dam
Stage 1
1,803 (550)/0 1,500 1,830 (550)/290
Stage 2
3,310 3,000 1,500 1,500 3,310
Total
5,110 3,000 3,000 3,330 3,600
*based on Nippon-Koie/NJS Study, 2003
Stage 1 Cost and Commissioning Dates, Water Sources for Metro MANILA
No Source Combination Stage 1 Cost US $M
804 529 1,071 807 529
Capacity Stage 1 MLD Commissioning Date
1,830 550 1,500 1,830 550 2015 2012 2017 2015 2012
1 2 3 4 5
Laiban Dam+Kanan No. 2 Dam Kaliwa Low Dam + Agos Dam Agos Dam Alone Laiban Dam + Agos Kaliwa Low Dam + Kanan No. 2 Dam
*based on Nippon-Koie/NJS Study, updated to 2005 prices by SKM
The 2005 MWSS Study
 the Laiban Dam + Kanan Dam has until now been recommended to be the priority combination among options already studied due to the higher yield, lowest unit development cost and higher elevation  Considerable works have been done for Laiban Dam
     FS conducted in 1979 DE done in 1980 Construction of diversion tunnel completed in 1984 Plan was reviewed, updated in 1997, 2000, 2007 The original plan from the headworks to the water treatment plant remain unchanged
PROJECT PROFILE  LAIBAN DAM
The Project is a multi-purpose development: it will provide a water supply of 1,950 MLD; it will also provide a 25 MW hydropower plant. It will become the second major source of water supply for Metro Manila, after Angat Dam. A 113-meter high dam will be constructed to utilize the Kaliwa River Basin in Tanay, Rizal. Kaliwa River basin is situated east of Metro Manila and drains a mountainous watershed of about 28,000 hectares on the slope of Sierra Madre Mountains.
MWWS Demand-Supply Projections (2000)
12000 10000 8000
MSW III-3(650)
MLD
KANAN (3200)
6000 4000 2000 0
300 MLD MSW III-2(650) UATP (800) MSW III-1(650)
1990
1995
2000
2005
2010
2015
2020
2025
2030
MWSP III, Agos River Pre-FS, 2000
Year
2035
MWSS
 Covers the NCR (17 towns and cities); cities); 5 in Rizal and 6 in Cavite  Total Service Area of 1,940 sq km
 1,400-MWCI 400 540-MWSI 540-
 Population in the Service Area, 14 Million  Served Population of about 9 Million     Angat River Umiray Sum-ag SumGroundwater 3,200 MLD 800 MLD 190 MLD 90 MLD
UMIRAY RIVER
ANGAT RESERVOIR
9 CMS 70 CMS
IPO DAM
46 CMS NIA
4,000 MLD (UMIRAY, 4,480 ANGAT, IPO) 900 MLD CAPACITY
LA MESA TREATMENT PLANT NO. 1
MWSS Existing Water Supply System
3 Tunnels
LA MESA TREATMENT PLANT NO. 2
)
5 Aqueducts
BIGTI SETTLING BASIN
1,500 MLDLA MESA RESERVOIR CAPACITY
BAGBAG RESERVOIR
BALARA TREATMENT PLANT NO. 2
380 MLD, La Mesa
BALARA TREATMENT PLANT NO. 1
1,130 MLD SAN JUAN CAPACITY RESERVOIR
TO DISTRIBUTION SYSTEM
470 MLD CAPACITY
TO DISTRIBUTION SYSTEM
Inflow from Umiray Angat Transbasin Tunnel
ANGAT DAM releases thru main turbines releases thru auxiliary turbines
ANGAT DAM SPILLWAY DIKE
BUSTOS DAM (NIA) 28,000-30,000 has
di re ct io n
IPO DAM 3 tunnels BICTI STILLING BASIN
6 aqueducts
IPO DAM
La Mesa Treatment Plants 1 & 2
LA MESA DAM Balara Treatment Plants 1 & 2
of
flo
MWSS DEMAND-SUPPLY SITUATION DEMAND9,000 8,000
Projected Demand (MLD)
7,000
Latest Water Demand Update
6,000
JICA STUDY, 2001 MWSS Projections
5,000 4,000 3,000 2,000 1990 1995 2000 2005 2010 Year 2015 2020 2025 2030
SumSum-ag River Source
Umiray Transbasin Angat Dam + GW sources
MWSS FRANCHISE AREA TOTAL POPULATION*
2008 2010 2015 2020 2025 14.578 Million 14.894 Million 15.937 Million 16.962 Million 18.001 Million
Service (sq.km) MWSI (West) MWCI (East) TOTAL
1MWSS
MWSS Demand Variations
1.80 1.60 1.40 1.20
ADD Ratio
1.00 0.80 0.60 0.40 0.20 0.00
00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 00
Time
* Based on NSO projections
Population
Water Production (MLD) 20071 NRW 1,513.04 354.16 1,867.20 Total 2,293.37 1,377.97 3,671.34
Served (M) Billed Volume 8.1 5.3 13.4 780.33 1,023.81 1,804.14
540 1,400 1,940
service Quarterly Service Performance Information (QSPI). Figures based on plant production and do not reflect conveyance losses through Angat, Ipo and eventually to the WTPs.
Angat Dam Spillway Main Dike
PAST WORKS RELATED TO THE ANGAT HYDRO PLANT SAFETY
NPCs Report, 1988 The JICA Study, 1989 EDCOPs/T&TIs Dam Safety Review, 2001 MWSS Engineering and Geological Report on Angat MWSS Dam and Dike Safety Evaluation, 2002 (NZ assisted) PHIVOLCS/USGS Joint Study, 2000
Ipo Dam
Based on the USBRs SEED Criteria, both the Angat Dam and Main Dike are rated CONDITIONALLY POOR*
* A potentially dam safety deficiency is recognized for unusual loading conditions, which may realistically occur during the expected life of the structure. CONDITIONALLY POOR may also structure. be used when uncertainties exist as to critical analysis parameters, which identify a potential dam safety deficiency; further investigations and studies are necessary. deficiency; necessary.
ORIGINAL PROJECT DESIGN (1983)
 Headworks
 LAIBAN Dam (113 meters; MaxWL=270 m; MinWL=237 m: Max Q = 4,885 CMS, Bottom Outlet, Elev 187, 300 CMS)  Twin multi-level intakes; one-intake for Kanan  3.2 dia, 7.8 km tunnel, concrete-lined  3.2 dia.,4.0 km tunnel, steel pipeline  2.7 m dia., 1.8 km steel-lined tunnel (with surge shaft and adit leading to powerplant
 Hydropower Station (30 MW)
 With by-pass to Pantay Creek to Laguna Lake (Morong)
 Treatment works
 3 phase development (800 MLD), 2 CWRs 50 ML
ORIGINAL PROJECT DESIGN (1983) -contd
 Distribution System
 Waterways from Pantay Treatment Plant to Cogeo Reservoir (3.2 m dia x 1.2 km pressure pipeline, 3.6 m dia x 6.9 km of concrete-lined tunnel)  Service reservoirs at Cogeo, Phase 1-120 ML, and 60 ML at Capitol  Pressure control station at Mayamot  Pumping station at La Mesa, 160 MLD for higher north  44 km of 2,000 to 2,600 mm dia trunk mains from Cogeo to south and La Mesa pumping station   158 km pipelines, 300 to 1,500 mm dia, and secondary distribution including 583,000 service connections  all phases
2006 Estimated Project Cost (MWSS Study) Project Components
Headworks (dams, tunnels etc.) Treatment Plant Distribution System Environmental & Watershed Management Resettlement Right-of-way Indirect Costs (Engg., Taxes, Contingencies, etc) IDC and front-end fee TOTAL
Cost (Php M)
13,060.00 3,254.00 9,951.00 90.00 7,417.00 2,651.00 64.00 5,560.00 47,928.00
MWSS Total Expenditures To Date for LAIBAN DAM Description Before MWSS Privatization: (FS, Detailed Engg., Diversion tunnels, partial land acquisition, and other pre-construction activities) After MWSS Privatization: a) (Review/Updating of documents including preliminary resettlement planning), year 2001 -------------------------------------------------- 36.00M b) Technical review & assess tender docs for construction, year 2006-2007 ---------- 24.00M c) Further geological investigation at damsite (on-going) -------------------------------------5.00M TOTAL Amt
(Php M)
690.00
65.00
755.00
LAIBAN DAM  Technical Considerations
 Dam Design  compliant to ICOLD standards, also referred to USBR and US Corps of Engrs
 Philippine Fault (Infanta segment; Digdig & Bondoc Peninsula)  West Valley Fault (Marikina Fault)  Slopes of the dam is at 1.5:1, just like that of Angat Main Dam  Concrete Faced Rock-filled Dam (CFRD)  Dam designed to withstand extreme events (PMF, MCE)
LAIBAN DAM  Technical Considerations
 Tunnels and Waterways Design
 Tunnels (3 segments, 14.65 km, Tunnels 1 and 2 follow original alignments)  Pipeline (or Tunnel ??) expected to cross the West Valley Fault  Geology dictates whether conventional drill and blast or use of TBM would be practicable in specific tunnel sections; also the need for lining.  Tunneling activity is in the critical path
Case 1 M = 8.0 R = 20 km PGA = 0.41 g PGAR = 0.25 g
Case 2 M = 8.2 R = 20 km PGA = 0.43 g PGAR = 0.26 g
Source: JICA Study, 2003
LAIBAN DAM  Technical Considerations
(Reservoir Area  Limestone Formation)
 Based on the results of the geologic mapping, majority of the limestone bodies investigated within the reservoir area may not have major impact/s on the designated reservoir water level of 270 masl except the one located along the bank of Lenatin River which is about 1 km upstream of the proposed dam site. - Geotechnical Investigation for Laiban Dam Project (Laiban Dam Limestone Project, April 2008)  Considering the size of the dams catchment area, it is very unlikely that the water that is lost will find itself exiting into another drainage basin. It is possible that the water flows back into the river farther downstream. - EDCOP/BERGS Geological Report, November 2008
LAIBAN DAM PROJECT  Facilities
 Dam and Headworks
        113 meter high dam, CFRD Twin Intakes (Laiban + Kanan) Reservoir and Watershed Access Roads 22.5 CMS (1,950 MLD) flow Operating levels (max. 270 m; min. 235 m) PMF, 3,702 CMS Seismic consideration, 0.4 g PGA
LAIBAN DAM PROJECT  Facilities
 Raw Water Conveyance
 Tunnel 1, 7.8 km total
 3.2 m dia concrete-lined section, 7.5 km  2.7 m dia steel-lined section, 300 meters
 Pipeline 1, 4.0 km, 3.2 m dia.  Tunnel 2, 1.8 km, 2.7 m dia., steel-lined
 With headrace and surge tank
 Pantay Hydropower Plant
 25 MW Capacity, 2 x 12.5 MW Francis Turbines (by-pass provided)
LAIBAN DAM PROJECT  Facilities
 Water Treatment Plant
 Conventional Treatment facility  2,400 MLD capacity
 Treated Water Conveyance Facilities
 Pipeline No. 2, 5 km, 3.2 m dia.  Tunnel No. 3, 5 km, 3.6 m dia.
 Storage Facilities, Pump Station, Pressure Control Station
    Antipolo Reservor, 20 ML Taytay Reservoir, 120 ML Antipolo Pumping Station, 110 MLD capacity Taytay Pressure Control Station
LAIBAN DAM PROJECT  Facilities
 Trunk Mains, River Crossings and Off-take Points
 Trunk Main from Taytay to Pasig, along Ortigas Extension to Dr. Sixto Antonio Drive, 11.8 km, 2.2m dia  1 river crossing, Marikina River  Trunk Main from Taytay to SLEX, through C-5/C-6 alignments, 14.5 km, 3.2 m dia  4 river crossings  Marikina River, Antipolo, Pasig, Taguig  4 Measurement Points
PROJECT FACILTIES
LAIBAN DAM PROJECT
PANTAY POWER HOUSE 25 MW Francis Turbines PANTAY WTP 2400 MLD Cap. ANTIPOLO 20 MLD RESERVOIR & 111 MLD cap. PUMPING STATION TAYTAY120 MLD RESERVOIR
P
HEP
metering point
TAYTAY PRESSURE CONTROL STATION INTAKE STRUCTURES
PASIG
SLEX metering points
LAIBAN DAM PROJECT  PROJECT COST
 Project Costs to be updated to reflect:
    Current materials, labor and equipment costs Contractual arrangements (EPC) CPIs Available, verified and validated quantities  especially for major work items
 Derived and/or updated unit costs are to be compared with existing, valid and actual construction costs in various on-going jobs in the Philippines as well as in similar, overseas projects
LAIBAN DAM PROJECT PROJECT COST COMPONENTS
CONSTRUCTION (DIRECT) COST LARP ENVIRONMENTAL INDIRECT COST (engineering, supervision, management & administration, contingencies) TAXES AND DUTIES
LAIBAN DAM PROJECT Comparative Features & Costs
Past Works Original, 1983, Electrowatt, Renardet Electrowatt,Renardet, 1997 GHD, Renardet, ISSI, PERTCONSUL, 2000 Daruma, Norconsult 2007 Total Cost P 10.5 B (USD 400 M) P 21.93 B (USD 828 M) P 31.91 B (USD 747 M) P 47.55 B (USD 951 M) LARP 257 families (P 990 M) 3,000 families (P 3,304 M) +3,000 families (P 4,502 M) 4,413 families (P 15,170 M) Design Q 22 CMS (1,900 MLD) 22 CMS (1,900 MLD) 22 CMS (1,900 MLD) 21 CMS (1,814 MLD) Power 30 MW (1 unit) 30 MW (2-15 MW) 30 MW (2-15 MW) 25 MW (2-12.5 MW)
LAIBAN DAM PROJECT  SCHEDULE
PHASE 1 Proposal Preparation
project update proposal preparation
PHASE 2 Contract Negotiation
proposal evaluation negotiation competitive challenge award of project
PHASE 3 Planning & Organizing
organization of JV, project company government approvals/permits off-take agreement financial closure tendering
PHASE 4 Construction
LARP, ROW, entry permits EPC mobilization construction activities commissioning
PHASE 5 Operations
post construction operational and occupancy permits operations  treated bulk water supply; power supply
LAIBAN DAM PROJECT  Implementation Framework
 Project to be implemented through the Corporate Joint Venture scheme, EO 423, 30 April 2005, in accordance with NEDA Guidelines on JV Agreements  The Proponent  JV Agreement between The Proponent and MWSS  The JV Partners (Proponent and MWSS) shall organize a Project Company   90% of the equity shares to be subscribed by the Proponent, remaining  10% by MWSS
LAIBAN DAM PROJECT -LARP
 An instrument to mitigate adverse impacts caused by dislocation, loss of houses, assets, livelihood and social disintegration  LARP addresses of both IP and non-IP families  Further validation shall be done during the final technical design phase of the project in order to cover all issues that will be raised by affected persons (APs) and affected families (AFs)  Important underlying principle  the quality of life offered by LARP with the project should be equal or better than without the project
LAIBAN DAM PROJECT -LARP
Objective
To ensure just compensation and peaceful and effective resettlement of the households/families to be affected by the project. These include: 1. AFs whose land and properties will be directly submerged by the dam; 2. AFs who will be at risk with the operation of the dam; 3. AFs who will be affected by the construction of other facilities of the project like pipes and water treatment plant (WTP) and 4. AFs in San Ysiro who will be affected by the relocation of families from Tanay, General Nakar and Antipolo.
AF = affected families
KALIWA WATERSHED (28,000 has.)
DARAITAN
MADILAY-DILAY
AREA OF WATERSHED = 28,000 HAS
DAM
KALIWA RIVER
Diversion Tunnel
FLOW
MAMUYAO
LIMUTAN RIVER
LENATIN RIVER
LAIBAN STO.NIO
KUYAMBAY SAN ANDRES
TINUKAN STA. INES
CAYABU
INTAKE
PROJECT IMPACT
BGY. STA. INES AF=474
FLOODING OF 7 BGYS. IN TANAY AND 0NE IN GEN. NAKAR
BGY. LIMUTAN AF=390
BGY. MAMUYAO AF=323
BGY. STO. NINO AF=318 BGY. TINUKAN AF=290 BGY. CAYABU AF=175 BGY. LAIBAN AF=720
BGY. SAN ANDRES AF=423
BGY. DARAITAN 591
Source: DENR
Parcel 1
Proposed Resettlement Site in San Ysiro, Antipolo City as proclaimed under Proclamation No. 2480 Issued on Jan 26, 1986 Area (hectares) MWSS Property 1,507
Parcel 4
MWSS Titled Property Lot 1 = 232 hectares Lot 2 = 1,275 hectares Total = 1,507 hectares
Parcel 2
Parcel 1 Parcel 2 Parcel 3 Parcel 4 Total
887 360 379 1,291 4,424
Parcel 3
LAIBAN DAM PROJECT  Affected Barangays, Impacts and Mitigation Measures
Affected Barangays (i) Tanay, Rizal       Laiban San Andres Cayabu Sto. Nino Tinucan Mamuyao Type of Impact/Recommended Action  Proposed Dam Site  To be submerged/for relocation  To be submerged/for relocation  To be submerged/for relocation  To be submerged/for relocation  To be submerged/for relocation  To be submerged/for relocation  will not be submerged  To be indirectly affected, will have access problem  will not be submerged  Risk area incase of flooding and dam break, originally proposed for relocation Proposed Measures to avoid/minimize impacts
Sta. Inez
Will not be included for relocation Will not be included for relocation
Provide access to San Ysiro, the relocation site Installation of early warning mechanism and monitoring system to monitor status of dam during inclement weather
Daraitan
LAIBAN DAM PROJECT  Affected Barangays, Impacts and Mitigation Measures
Proposed Measures to avoid/minimize impacts
Affected Barangays (i) Gen. Nakar, Quezon
Type of Impact/Recommended Action
Lumutan
 within the Kaliwa Watershed  will not be submerged, but will be indirectly affected Lack of access to resources/market)  Existing road link is only through Brgy. Sta. Inez  No existing road network to Gen. Nakar ( proposed for relocation)
Will not be included for relocation
Improve existing access to Sta Inez and then access to San Ysiro, the relocation site
LAIBAN DAM PROJECT  Affected Barangays, Impacts and Mitigation Measures
(i) Antipolo, Rizal Proposed Water Treatment Plant (WTP ) Site of the treatment plant, families to be displaced ( proposed to be relocated ) Displacement of current settlers, loss of access to farm production and losses on structures, and crops/trees, if movement is done on current land use and properties and assets
 Barangay Pantay
 San Ysiro
Minimal movement of existing structures/properties Identify sites that are not occupied by current settlers within the 4,440 hectares to be used for resettlement and facilities to be established based on the physical development plan that will be prepared.
Project Affected Families (updated)
LAIBAN DAM PROJECT  LARP
Proposed Resettlement Package and Compensation
 OPTION 1  Outright compensation for APs/AFs  OPTION 2  Resettlement Assistance of:
    30 sq meter house, single detached 240 sq meter home lot 5,000 sq meter farm lot Compensation for lots, structures, fruit and permanent trees  Other assistance packages on livelihood, employment, capacity building
LAIBAN DAM PROJECT LARP Budget Components
 Land Acquisition Cost/Compensation
 Farm & home lots, structures, permanent trees, fruit trees
 Resettlement Cost (San Ysiro)
 Development cost, housing units, community facilities, etc.
 Other Costs & Contingencies
 Training, services
LAIBAN DAM PROJECT - EIA
DENR Requirements
 ECC Amendment  Environmental Performance Report and Management Plan  Environmental Impact Statement
- Environmental Compliance Certificate
ECC issued by NEPC  August 18, 1986
Condition 1 2 3 4 5 6 7 8 9 Particulars Implementation of biological controls against malaria and other insect related diseases in the project area Implementation of epidemiological monitoring plan Establishment of micro-seismic monitoring centers microImplementation of submitted resettlement plan and commitments Provision of assistance to displaced minorities in terms of livelihood opportunities Conformance with Alternative 3 relative to sludge disposal Formulation and establishment of contingency plans and warning system Implementation of measures to minimize soil erosion of the quarried areas and riverbanks Mitigating measures on air, water and noise pollution.
LAIBAN DAM PROJECT  Environmental
 Conduct of EIS  Site Scoping, Public Consultations, Public Hearing
 Land use, flora & fauna, reservoir & watershed, geology & hydrogeology, hydrology, air, noise, etc.
 Environmental Impact Sampling & Study  ECC Application & DENR Review  EIS Consultancy Cost (other related studies, etc.)
QUESTIONS . . . CLARIFICATIONS . . . DETAILS . . . . .