Project 1

The document outlines a project schedule for 'Project1', detailing various tasks and their durations from 2025 to 2028. Key tasks include mobilization, design approval, civil works, and testing, with durations ranging from 30 to 780 days. The schedule also indicates milestones, inactive tasks, and critical paths associated with the project timeline.

Uploaded by

karri.vasu.gvp
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views4 pages

Project 1

The document outlines a project schedule for 'Project1', detailing various tasks and their durations from 2025 to 2028. Key tasks include mobilization, design approval, civil works, and testing, with durations ranging from 30 to 780 days. The schedule also indicates milestones, inactive tasks, and critical paths associated with the project timeline.

Uploaded by

karri.vasu.gvp
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ID Task Task Name HalfDuration

1, 2025 Half 2, 2025 Half 1, 2026


Mode M J J A S O N D J F M A M J
1 Mobilization & Site Establishment 150 days
2 Detailed Survey, Investigations & 180 days
Geotechnical Studies
3 Design, Engineering & Drawing Approval 600 days
4 Statutory Clearances (Forest, 270 days
Environment, etc.)
5 Land Acquisition & R&R Compliance 180 days
6 Procurement of Long-Lead Equipment 300 days
(Turbines, Generators)
7 Civil Works – Ancillary Structures, Power 690 days
House
8 Major Civil works, WCS 780 days
9 Structural Works (Penstock, Draft Tube, 420 days
Intake, Tail Race)
10 Erection of Electro-Mechanical 450 days
Equipment
11 Construction of Switchyard and 132kV 300 days
Transmission Line
12 Construction of Residential & Office 270 days
Buildings
Task Start-only

Split Finish-only

Milestone External Tasks

Summary External Milestone

Project Summary Deadline

Project: Project1 Inactive Task Path Predecessor Milestone Task


Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task

Inactive Summary Path Predecessor Normal Task

Manual Task Critical

Duration-only Critical Split

Manual Summary Rollup Progress

Manual Summary Manual Progress

Page 1
ID Task Task Name HalfDuration
1, 2025 Half 2, 2025 Half 1, 2026
Mode M J J A S O N D J F M A M J
13 Internal Electrification, Water Supply & 270 days
Sanitation
14 Testing, Commissioning & Trial Operation 90 days

15 Final Documentation, Handing Over & 30 days


Approval Closeouts

Task Start-only

Split Finish-only

Milestone External Tasks

Summary External Milestone

Project Summary Deadline

Project: Project1 Inactive Task Path Predecessor Milestone Task


Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task

Inactive Summary Path Predecessor Normal Task

Manual Task Critical

Duration-only Critical Split

Manual Summary Rollup Progress

Manual Summary Manual Progress

Page 2
Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

Task Start-only

Split Finish-only

Milestone External Tasks

Summary External Milestone

Project Summary Deadline

Project: Project1 Inactive Task Path Predecessor Milestone Task


Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task

Inactive Summary Path Predecessor Normal Task

Manual Task Critical

Duration-only Critical Split

Manual Summary Rollup Progress

Manual Summary Manual Progress

Page 3
Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

Task Start-only

Split Finish-only

Milestone External Tasks

Summary External Milestone

Project Summary Deadline

Project: Project1 Inactive Task Path Predecessor Milestone Task


Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task

Inactive Summary Path Predecessor Normal Task

Manual Task Critical

Duration-only Critical Split

Manual Summary Rollup Progress

Manual Summary Manual Progress

Page 4

You might also like