ID Task Task Name HalfDuration
1, 2025 Half 2, 2025 Half 1, 2026
Mode M J J A S O N D J F M A M J
1 Mobilization & Site Establishment 150 days
2 Detailed Survey, Investigations & 180 days
Geotechnical Studies
3 Design, Engineering & Drawing Approval 600 days
4 Statutory Clearances (Forest, 270 days
Environment, etc.)
5 Land Acquisition & R&R Compliance 180 days
6 Procurement of Long-Lead Equipment 300 days
(Turbines, Generators)
7 Civil Works – Ancillary Structures, Power 690 days
House
8 Major Civil works, WCS 780 days
9 Structural Works (Penstock, Draft Tube, 420 days
Intake, Tail Race)
10 Erection of Electro-Mechanical 450 days
Equipment
11 Construction of Switchyard and 132kV 300 days
Transmission Line
12 Construction of Residential & Office 270 days
Buildings
Task Start-only
Split Finish-only
Milestone External Tasks
Summary External Milestone
Project Summary Deadline
Project: Project1 Inactive Task Path Predecessor Milestone Task
Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task
Inactive Summary Path Predecessor Normal Task
Manual Task Critical
Duration-only Critical Split
Manual Summary Rollup Progress
Manual Summary Manual Progress
Page 1
ID Task Task Name HalfDuration
1, 2025 Half 2, 2025 Half 1, 2026
Mode M J J A S O N D J F M A M J
13 Internal Electrification, Water Supply & 270 days
Sanitation
14 Testing, Commissioning & Trial Operation 90 days
15 Final Documentation, Handing Over & 30 days
Approval Closeouts
Task Start-only
Split Finish-only
Milestone External Tasks
Summary External Milestone
Project Summary Deadline
Project: Project1 Inactive Task Path Predecessor Milestone Task
Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task
Inactive Summary Path Predecessor Normal Task
Manual Task Critical
Duration-only Critical Split
Manual Summary Rollup Progress
Manual Summary Manual Progress
Page 2
Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
Task Start-only
Split Finish-only
Milestone External Tasks
Summary External Milestone
Project Summary Deadline
Project: Project1 Inactive Task Path Predecessor Milestone Task
Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task
Inactive Summary Path Predecessor Normal Task
Manual Task Critical
Duration-only Critical Split
Manual Summary Rollup Progress
Manual Summary Manual Progress
Page 3
Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
Task Start-only
Split Finish-only
Milestone External Tasks
Summary External Milestone
Project Summary Deadline
Project: Project1 Inactive Task Path Predecessor Milestone Task
Date: Mon 26-05-25 Inactive Milestone Path Predecessor Summary Task
Inactive Summary Path Predecessor Normal Task
Manual Task Critical
Duration-only Critical Split
Manual Summary Rollup Progress
Manual Summary Manual Progress
Page 4