Chapter 5
Enterprise Resource Planning
         (ERP) Systems
                                 1
    Learning Objectives
◼   Material Requirements Planning (MRP) Systems
◼   Enterprise Resource Planning (ERP) Systems
◼   Enterprise Resource Planning Process
                                                   2
Evolution of ERP Systems (cf. Chapter 2)
We will focus our discussion on MRP and ERP systems in this chapter.
                                                                       3
    Independent vs. Dependent Demand Items
◼   Independent demand items
     ◼   Items for which demand is influenced by market conditions and is
         not related to the inventory decisions for any other item held in
         stock or produced.
     ◼   These items must be forecasted using various forecasting
         techniques.
     ◼   Examples: wholesale and retail merchandise; maintenance, repair,
         & operating (MRO) supplies; service support inventory, etc.
◼   Dependent demand items
     ◼   Items whose required quantity varies with the production plans for
         other items held in the firm’s inventory.
     ◼   These items are required as components or inputs to a service or
         product.
     ◼   Dependent demand should be calculated, not forecasted.
     ◼   Examples: raw materials and WIP (work-in-process) inventories.
                                                                              4
     Material Requirements Planning (MRP) System
◼   MRP system is a computerized information system developed specifically to
    help manufacturers manage dependent demand inventory and schedule
    replenishment orders.
◼   The key inputs of an MRP system are a bill of materials (BOM) database,
    a master production schedule (MPS), and an inventory record
    database, as shown in the next slide.
◼   Using the above information, the MRP system identifies the actions planners
    must take to stay on schedule, such as releasing new production orders,
    adjusting order quantities, and expediting late orders.
◼   MPS is a part of the material requirements plan that details how many end
    items will be produced within specified periods of time.
◼   An MRP system translates the MPS independent demand into the
    requirements for all subassemblies, components, and raw materials needed
    to produce the required parent items. This process is called an MRP
    explosion because it converts the requirements of various final products
    into a material requirements plan that specifies the replenishment schedules
    of all the subassemblies, components, and raw materials needed to produce
    final products.                                                                5
Material Requirements Plan (MRP) Inputs
                                          6
             A Process View of an Enterprise within a Supply Chain
             (cf. Chapter 1)
Source: Krajewski                                                    7
                      A Process View of a Manufacturer within a Supply
                      Chain
                                                   New
                                                 service/
                                                                                                   Customer
                                                                                                                        External customers
                                                 product
External suppliers
                                                                                                  relationship
                                               development
                                                 process
                                                                           MPS                      process
                                                                           Order
                                                                         fulfillment
                     Supplier                                 Bill of                   Orders               Customer
                                                                          process
                      Orders      Supplier                   materials                 promises               Orders
                                relationship
                                  process                                  MRP
                                               Supplier schedules
    Note: Bill of Materials (BOM) is a record of all the components of an item, the
    parent-component relationships, and the usage quantities derived from engineering
    and process designs.
                                                                                                                                             8
LRP = DRP + MRP (cf. Chapter 4)
                                         Customers
   Distribution centre A            Distribution centre B      Distribution centre C
                                       Plant warehouse
  DRP (independent)
                                           Factory
  MRP (dependent)                      (Final assembly)
       Sub-assembly B                                            Sub-assembly C
                                             Part C
   Part A                  Part B                            Part D             Part E
                                    Raw-material suppliers
                                                                                         9
     The DRP for Plant Warehouse (Recall Chapter 4 Q3)
                                           Week
                        0    1    2    3          4   5   6   7
Distribution Centre A       300               300
Distribution Centre B                 150
Distribution Centre C                         150
Plant Warehouse             300       150     450
MPS Qty                     300       150     450
                                                                  10
The Parent-Component Relationship of Final Assembly
                         Factory
                       Final Assembly
                              (1)
   Sub-assembly B         Part C          Sub-assembly C
         (1)                                    (4)
                           (2)
                                                           11
    Inventory Record
The time-phase information contained in the inventory record
database consists of:
▪   Gross requirements
▪   Scheduled receipts
▪   Projected on-hand inventory
▪   Planned receipts
▪   Planned order releases
                                                               12
    Inventory Record
◼   The inventory record divides the future into time periods called
    time buckets. It shows an item’s lot-size policy, lead time, and
    various time-phased data. The purpose of the inventory record is
    to keep track of inventory levels and component replenishment
    needs.
◼   The gross requirements are the total demand derived from all
    parent production plans.
◼   Scheduled receipts (or open orders) are orders that have been
    placed but not yet completed.
◼   Projected on-hand inventory is an estimate of the amount of
    inventory available each week after gross requirements have been
    satisfied.
◼   Planned receipts – planning for the receipt of new orders will
    keep the projected on-hand balance from dropping below zero.
◼   Planned order releases – indicates when an order for a specified
    quantity for an item is to be issued.
                                                                       13
        Planning Factors
◼   Planning Lead Time
    ◼   It is an estimate of the time between placing an order (either purchased order
        or production or work order) for an item and receiving the item in inventory.
◼   Lot-Sizing Rules
    ◼   It determines the timing and size of order quantities. A lot-sizing rule must be
        assigned to each item before planned receipts and planned order releases can be
        computed. Three lot-sizing rules:
    ◼   Fixed Order Quantity (FOQ) – a rule that maintains the same order quantity
        each time an order is issued (cf. Ch. 2).
    ◼   Periodic Order Quantity (POQ) – a rule that allows different order quantity for
        each order issued but issues the order for predetermined time intervals (cf. Ch. 2).
    ◼   Lot for Lot – A rule under which the lot size ordered covers the gross
        requirements of a single week. It is a special case of POQ rule, under which the
        lot size ordered covers the gross requirements of a single week, i.e. P = 1, and the
        goal is to minimize inventory levels.                                                14
 Inventory Record for Final Assembly
 Item: Final assembly
 Lot size: 200 units
                                          Week
 Lead
 time: 1 week       0     1     2     3          4    5    6    7
Gross
requirements        0    300    0    150     450      0    0    0
Scheduled
receipts            0    0     0      0          0    0    0    0
Projected
on-hand            350   50    50    100         50   50   50   50
inventory
Planned
                                     200     400
receipts
Planned order
                               200   400
releases
                                                                     15
 Inventory Record for Sub-assembly B
 Item: Sub-assembly B
 Lot size: 300 units
                                         Week
 Lead
 time: 1 week      0     1     2     3          4    5    6    7
Gross
requirements       0    0     200   400         0    0    0    0
Scheduled
receipts           0    0      0     0          0    0    0    0
Projected
on-hand            50   50    150   50          50   50   50   50
inventory
Planned
                              300   300
receipts
Planned order
                        300   300
releases
                                                                    16
 Q1. Complete the Inventory Record for Part C.
 Item: Part C
 Lot size: 300 units
                                          Week
 Lead
 time: 1 week          0     1    2   3          4   5   6   7
Gross
requirements
Scheduled
receipts               0    100   0   0          0   0   0   0
Projected
on-hand                50
inventory
Planned
receipts
Planned order
releases
                                                                 17
 Q2. Complete the Inventory Record for Sub-assembly C.
 Item: Sub-assembly C
 Lot size: 500 units
                                      Week
 Lead
 time: 1 week      0    1     2   3          4   5   6   7
Gross
requirements
Scheduled
receipts           0    100   0   0          0   0   0   0
Projected
on-hand           100
inventory
Planned
receipts
Planned order
releases
                                                             18
Material Requirements Plan (MRP) Outputs
                                           19
    Tutorial Exercise 5a
Material Requirements Planning
◼   Answer all the questions
                                 20
    Enterprise Resource Planning (ERP) Systems
◼   An enterprise process is a companywide process that cuts across
    functional areas, business units, geographic regions, product lines,
    suppliers, and customers. ERP systems are large, integrated
    information systems that support many enterprise processes (both core
    and support processes - cf. Ch.1) and data storage needs.
◼   By integrating the firm’s functional areas, ERP systems allow an
    enterprise to view business operations as a whole rather than having to
    try to put together the different information pieces produced by its
    various functions and divisions.
◼   Today, ERP systems are being used by traditional brick-and-mortar
    organizations such as manufacturers, restaurants, hospitals, and hotels,
    as well as by Internet companies that rely extensively on Web
    connectivity to link their customers and suppliers.
◼   ERP revolves around a single comprehensive database that can be
    made available across the entire enterprise. Having a single database
    for all of the firm’s information makes it much easier for managers to
    monitor all of the company’s products at all locations and at all times.
                                                                               21
Enterprise Resource Planning (ERP) Systems
                                    Source: Scalle & Cotteleer
                                                                 22
    ERP Application Modules
◼   The database collects data and feeds them into the various modular
    applications (or suites) of the software system. As new information is
    entered as a transaction in one application, related information is
    automatically updated in the other applications, including the firm’s
    financial and accounting databases, its human resources and payroll
    databases, sales, supplier and customer databases, and so forth.
◼   In this way, the ERP system streamlines the data flows throughout the
    enterprise and supply chain and provides employees with direct access
    to a wealth of real-time operating information scattered across
    different functions in the enterprise.
◼   The manufacturing and supply chain modules specifically deal with
    resource planning. In fact, MRP evolved into manufacturing
    resource planning (MRP II), and then ultimately evolved into ERP.
◼   However, not all applications need to be integrated into an ERP
    system. Module software design divides the ERP system into a set of
    modules that can be used independently or combined with other
    modules, so enterprises purchase only the required modules for
    increased business flexibility.                                          23
     Enterprise Resource Planning Process
1. A business plan is a projected statement of income, costs, profits. It
   usually is accompanied by budgets, a projected balance sheet and cash
   flow statement, showing sources and allocation of funds.
2. This plan provides the framework for developing the sales and
   operations plan (S&OP), a process of balancing supply with demand
   at an aggregate level. Just as it is needed to manage the demand side,
   consensus is needed among the firm’s departments when decisions for
   the supply side are made. Such coordination helps synchronize the flow
   of services, materials, and information through the supply chain to best
   balance supply with customer demand.
3. Based on the sales and operations plan, the next planning level is
   resource planning. For a service provider, it is to determine the firm’s
   workforce schedules and other resource requirements, such as materials,
   facilities, on a more detailed level. For a manufacturer, the master
   production schedule (MPS) specifies the timing and size of production
   quantities for each product and the material requirements planning
   (MRP) process then derives plans for components, purchased materials,
   and workstations.
                                                                              24
       Managerial Inputs from Functional Areas to S&OP
Source: Krajewski
 This diagram lists inputs from each functional area. They must be accounted for to
 make sure that the plan is a good one and also doable.
                                                                                      25
  Aggregation
The sales and operation plan is useful because it focuses on a general
course of action, consistent with company’s strategic goals and objectives,
without getting down in details. In general, enterprises perform
aggregation along 3 dimensions: services or products, workforce, and
time.
                                                                              26
       The Relationship of S&OP and Schedules to Other Plans
Source: Krajewski
                                                               27
    Tutorial Exercise 5b
ERP Systems of McDonald’s
◼   Read the mini case
◼   Answer all the multiple choice questions
                                               28
    Chapter 5 Highlights
◼   MRP is a computerized information system to manage
    dependent demand inventory and schedule orders. It
    translates the master production schedule (MPS) into
    requirements for all subassemblies, components, and
    raw materials through the MRP explosion.
◼   ERP systems are large, integrated information systems
    that support many enterprise processes (both core and
    support processes) and data storage needs.
◼   Enterprise resource planning is the process of balancing
    supply with demand, from the aggregate level (i.e.
    Sales and Operations Planning) down to the short-term
    scheduling level (i.e. resource planning and scheduling).
                                                                29