Water Tank

The document is a cost estimate for the construction of a toilet facility at Om Sidhartha Gumba in Harion Municipality, detailing various civil works and their associated costs. It includes a breakdown of materials and labor for tasks such as excavation, brickwork, plastering, and plumbing. The total estimated cost of the project is 353,177.72, with contributions from both the municipality and the user's community.

Uploaded by

Harish Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views3 pages

Water Tank

The document is a cost estimate for the construction of a toilet facility at Om Sidhartha Gumba in Harion Municipality, detailing various civil works and their associated costs. It includes a breakdown of materials and labor for tasks such as excavation, brickwork, plastering, and plumbing. The total estimated cost of the project is 353,177.72, with contributions from both the municipality and the user's community.

Uploaded by

Harish Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Harion Municipality

Office Of The Excutive Municipal Harion, Sarlahi


Cost Estimate
Name of work :Om Sidhartha Gumba Sauchalaya FY 2075/076
Name of place : Harion municipality, ward-06 Date:-
Item Length Breadth Height
S.N
No Description of item No (meter) (meter) (meter) Quantity Unit Rate Amount Remarks.
CIVIL WORKS
Clearing the site of all the unuseful materials
1 1.0 1 - - - 1.00 L.S. 650.00 650.00
from site after completing the works.

2 E/W in excavation
toilet
longwall 2 4.60 0.60 0.90 4.97
shortwall 2 1.09 0.60 0.90 1.18
partition wall 2 1.09 0.30 0.30 0.20
septic tank 1 3.50 2.30 2.40 19.32
2.0 Total E/W = 25.67 M3 346.08 8883.88
3 Brick Soling
toilet
longwall 2 4.60 0.60 5.52
shortwall 2 1.09 0.60 1.31
partition wall 2 1.09 0.30 0.65
septic tank 1 3.50 2.30 8.05
3.0 Total Brick soling work = 15.53 M2 500.96 7779.84

4 1:2:4 P.C.C.
toilet
longwall 2 4.60 0.60 0.08 0.41
shortwall 2 1.09 0.60 0.08 0.10
partition wall 2 1.09 0.30 0.08 0.05
septic tank 1 3.50 2.30 0.08 0.60
4.0 Total 1:2:4 P.C.C. work = 1.16 M3 13371.90 15511.41

5 Brick Masonary Work in 1:6 C/S Mortar


toilet
longwall 2 4.60 0.60 0.30 1.66
2 4.60 0.45 0.30 1.24
2 4.60 0.30 0.25 0.69
2 4.60 0.23 2.70 5.71
shortwall 2 1.09 0.60 0.30 0.39
2 1.09 0.45 0.30 0.29
2 1.09 0.30 0.25 0.16
2 1.09 0.23 2.70 1.35
partition wall 2 1.09 0.30 0.30 0.20
2 1.09 0.13 2.70 0.74
septic tank
longwall 2 3.50 0.13 2.40 2.10
shortwall 2 2.30 0.13 2.40 1.38
5 Total Brick Work= 15.91 M3 10813.94 172049.73
6 1:1.5:3 P.C.C. for R.C.C. work -
toilet slab 1 4.10 2.90 0.10 1.19
septic tank cover 1 3.50 2.30 0.08 0.60
6.0 Total P.C.C. for R.C.C. work = 1.79 M3 13371.90 23935.71

7 Steel reinforcement for R.C.C. work


7.0 Total R.C.C. Work 1% of P.C.C. of R.C.C= 140.52 kg 96.30 13532.61

8 Form work
toilet slab 1 4.10 - 2.90 11.89
side of slab 2 4.10 - 0.10 0.82
2 2.90 - 0.10 0.58
septic tank cover 1 3.50 - 2.30 8.05
side of septic tank 2 3.50 0.08 0.53
2 2.30 0.08 0.35
8.0 Total Form Work= 22.22 M2 293.48 6521.23

9 12.5mm Cement plaster (1:4) on wall


toilet
inside wall 4 1.09 - 2.70 11.77
2 3.89 - 2.70 21.01
outside wall 2 4.60 - 2.70 24.84
2 1.55 - 2.70 8.37
ceiling 1 5.20 - 2.15 11.18
floor 1 3.89 1.09 4.24
septic tank
inside wall 2 2.69 - 9.00 48.42
2 1.84 - 9.00 33.12
cover 1 3.15 - 2.30 7.25
floor 1 2.69 - 1.84 4.95
deduction
ventilation 3 0.30 0.30 -0.27
D 3 0.75 1.80 -4.05
9.0 total plaster= 170.83 M2 264.54 45191.17
`
10 Punning work
toilet
floor 1 3.89 1.09 4.24
septic tank
inside wall 2 2.69 - 9.00 48.42
2 1.84 - 9.00 33.12
floor 1 2.69 - 1.84 4.95
10.0 Total Punning 90.73 M2 234.55 21280.99
11 Two coat distemer paint
toilet
inside wall 4 1.09 - 2.70 11.77
2 3.89 - 2.70 21.01
outside wall 2 4.60 - 2.70 24.84
2 1.55 - 2.70 8.37
ceiling 1 5.20 - 2.15 11.18
11.0 Total Paint = 77.17 M2 116.83 9015.81
12 Chaukath Works
door 2 4.80 0.08 0.08 0.06
2 0.60 0.08 0.08 0.01
12.0 Total = 0.06 M2 177912.00 11528.70

13
0.50 mm Colour C.G.I. sheet door covering.
2 0.75 1.95 2.93
13.0 Total Paint = 2.93 M2 1125.13 3296.64

14 14.0 580 mm orissa pan with low level cistern 3 2.00 No. 3000.00 6000.00
3/4'' dia PPR pipe,Gate Valve and necessary
15 15.0 1
fittings. 1.00 Job 8000.00 8000.00
water tank 5000 litre 2 5000.00 litre
Total 353177.72
Amount contributed by Municipality 300000.00
Amount contributed by User's community 53177.72

पेश गर् जाच गर्ने सहि: प्ाहाण गर्ने सहि : स्वनकण गर्ने सहि: