Creation PMS Technip-Copier

The document outlines the construction progress measurement system for the Algiers Refinery Rehabilitation and Adaptation Project, detailing the project scope, purpose, responsibilities, and progress calculation processes. It emphasizes the need for accurate reporting and monitoring of physical work progress to ensure alignment with planned schedules and facilitate contractor payments. Key components include a breakdown of work items, a weighing system for progress evaluation, and the use of specific software for tracking progress.

Uploaded by

Nassilova
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views78 pages

Creation PMS Technip-Copier

The document outlines the construction progress measurement system for the Algiers Refinery Rehabilitation and Adaptation Project, detailing the project scope, purpose, responsibilities, and progress calculation processes. It emphasizes the need for accurate reporting and monitoring of physical work progress to ensure alignment with planned schedules and facilitate contractor payments. Key components include a breakdown of work items, a weighing system for progress evaluation, and the use of specific software for tracking progress.

Uploaded by

Nassilova
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 78

ALGIERS REFINERY

REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 1/78

CONSTRUCTION PROGRESS MEASUREMENT

Azedine DERARDJA
Lemoui Abdelhafid 2012.08.16 10:07:07 Fabien Ruez
2012.08.16 09:51:35
+02'00' 2012.08.16
+01'00' 10:52:11 +01'00'

0 15/Aug/12 Issue for Execution A.LEMOUI A.DERARDJA F.RUEZ

A 14/Jan/11 Issue for Approval R.VAILLEAU D.CACAN C. LOUANCHI


Rev Date STATUS WRITTEN BY CHECKED BY APPROVED BY
DD/MMM/YY (name & visa) (name & visa) (name & visa)

DOCUMENT REVISIONS

Sections changed in last revision are identified by a vertical line in the margin

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 2/78

CONTENTS

CONSTRUCTION PROGRESS MEASUREMENT......................................................................................................1

1. PROJECT SCOPE ...............................................................................................................................................3


1.1 GENERAL OUTLINES ........................................................................................................................................3
1.2 DEFINITIONS / ABBREVIATIONS ........................................................................................................................3
2. PURPOSE ............................................................................................................................................................4

3. REFERENCE DOCUMENTS ...............................................................................................................................4

4. RESPONSIBILITIES ............................................................................................................................................4

5. PROGRESS CALCULATION PROCESS............................................................................................................5


5.1 BASIS OF PROGRESS CALCULATION SYSTEM ...................................................................................................5
5.2 WEIGHING SYSTEM .........................................................................................................................................5
5.3 PHYSICAL PROGRESS SOFTWARE ...................................................................................................................6
5.4 SMC PREPARATION........................................................................................................................................6
5.5 REPORTING PROGRESS...................................................................................................................................6
5.6 APPROVING SYSTEM .......................................................................................................................................7
6. ADDITIONAL REPORTS .....................................................................................................................................7

7. SYSTEM COMPLETION AND TURNOVER PROGRESS ..................................................................................7

8. ATTACHMENTS ..................................................................................................................................................7

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 3/78

1. PROJECT SCOPE
1.1 General outlines
SONATRACH RAFFINERIE D’ALGER, Algiers Refinery Algeria (OWNER) is presently operating a
2.7 MMTPA petroleum refinery at Algiers, Algeria having various units such as Crude Distillation
Unit, Gas Plant, Catalytic Reformer unit and associated auxiliary units including utility & offsite. The
plant is situated at Sidi-Arcine, located east of Algiers Refinery, and is approximately 10 km from
Algiers Airport and 15 km from the Algiers Port. Algiers Refinery was built in 1964 with a capacity of
1.6 MMTPA for processing of Hassi Messaoud crude oil. Capacity of Algiers Refinery was
increased to 2.7MMTPA in the year of 1970.

As part of “Rehabilitation & Adaptation Project” of Algiers Refinery, OWNER intends to revamp
some of the above units and also add a few new units. Engineers India Ltd. (EIL), New Delhi,
INDIA has been retained as PMC by SONATRACH for Rehabilitation & Adaptation Project of
Algiers Refinery. Under the Rehabilitation Project, the crude processing capacity of the Refinery
shall be increased by 35%. The revamp of existing units in the refinery and associated Utilities and
Offsite facilities shall be enhanced / modified under Rehabilitation part.
OWNER has also planned to produce fuels conforming to the Euro-2009 specifications.
Accordingly, OWNER has planned to implement a project under Rehabilitation part to increase the
capacity from the complex including modernization of existing utilities and offsite facilities. Electrical
modernization and Instrument modernization including new DCS and central control room are also
part of Revamp plan.

Under the Adaptation project SONATRACH intends to maximize diesel and minimize fuel oils. For
this matching new Utilities, Offsite facilities and an Effluent Treatment Plant (ETP) with Biological
treatment plant to cater to the requirement of the refinery have been planned. New Residual
Fluidized Catalytic Cracking Unit (RFCCU), Sulfur Block containing Sulfur Recovery unit (SRU),
Amine treatment Unit (ARU), Sour water stripper unit (SWS), Fuel Gas treating unit (FGATU) and a
new MS Block containing Naphtha Hydrotreater unit (NHTU), Light Naphtha Isomerisation Unit
(LNISOM),Continuous Catalytic regeneration Unit(CCRU) have also been planned under the
Adaptation Project.
Under instrumentation modernization work, all existing pneumatic instruments in existing plants,
revamped or otherwise, shall be replaced with electronic instruments with all associated
accessories. A central control room (blast resistant) shall be replaced with a new DCS control
system which will control, monitor the Refinery. Both Rehabilitation and Adaptation area plants,
Utilities and Offsite have been planned along with a number of Satellite rack rooms. Fire and gas
detection and monitoring system of the refinery is also part of Project.
Under electrical modernization work, a new 63 kV grid power reception and distribution terminal
along with a number of new and revamp of substations have been envisaged. This will also include
addition and replacement of existing transformers, switchgears etc. New plant communication, Fire
alarm, telephone systems in plant and few of non plant buildings are also part of the Project.
As part of Fire water system up gradation, a new fire water network along with pump station and
other fire water systems like foam, water monitors have been planned.
1.2 Definitions / Abbreviations
• COMPANY or OWNER: SONATRACH
• EPCC CONTRACTOR: TECHNIP
• SUBCONTRACTOR(S): any party, entity performing site work or causing construction
work to be performed under its own responsibility.
PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 4/78

• SMC means: Site Management & Control System.


• WORK BREAKDOWN STRUCTURE: Means the overall project breakdown structure (To refer
to WBS 9952T-000-PP-0306-0
• Levels 1/2: Control documents produced for the use of Project Management.(Monthly Report
and Executive Summary)
• Level 3/4/5: discipline oriented documents produced to monitor trades activities
• Discipline: Works belonging to one single trade or discipline, identified by a Work Code (e.g:
Concrete works = 17, Steel Structure = 18, Piping = 13)
• Work class : Uniform item within each discipline identified by a sub-work code (e.g: Elevated
concrete: 17210. Light weight fire proofing: 17420)
• Work Item: Identified individual item belonging to a type of work (e.g: Foundation of E-101,
Isometric n° BFW 5760-0-2”-A2A2M-H-AE rev 2)
• Standard Man-hours: Correspond to the in-house TECHNIP statistics as measurement Unit
of construction works to all Work Item classes defined as the performance that a qualified
worker (direct labor) supplied with required tools, on standard environment can produce in one
hour (Referred as SMH)
• Planned Man-hours: correspond to the effective measurement Unit of construction works
common to all Work Item classes, in Site work environment can produce in one hour (referred
as PMH in this procedure). PMH are calculated from relevant SMH multiplied by efficiency
factor determined for all the construction activities in Site conditions. The PMH measurement
system allows proper weighting incidence of different typologies of construction activities and
relevant aggregation bottom/top in accordance with Project WBS, for construction planning
and progress measurement objective.

2. PURPOSE
This procedure covers the overall Progress Measurement System implemented for measuring the
physical work progress during the Construction execution of the PROJECT, including specific
weight factors to be used for a given level.
The reporting progress during the construction execution shall serve two important purposes:
• To position the construction activity with respect to the planned progress at the PROJECT
level and trades activities. This is an essential parameter that assists the CONTRACTOR
assessing its performance and the adequacy of its resources and organization to deliver
the plant with the agreed program.
• To prepare CONTRACTOR monthly payment as defined in the CONTRACT Agreement

3. REFERENCE DOCUMENTS
Construction Execution Plan: 9952T-0000-PP-0801
Progress Measurement Procedure: 9952T-0000-PP-0304 Rev A
Construction Work Breakdown structure: 9952T-0000-PP-0306 Rev 0

4. RESPONSIBILITIES
It is the responsibility of the Site Project Control Manager to ensure that a physical progress
measurement system is in place and is fully implemented so that the reporting is correct and
auditable and that the consolidation of SUBCONTRACTORS reporting rests with the
CONTRACTOR Project Control Manager at Site.

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 5/78

It is the responsibility of each SUBCONTRACTOR to establish, maintain and report against an


auditable and meaningful physical progress system. He is also responsible for reporting progress
information as required by CONTRACTOR in a timely manner. The system shall be integrated into
the CONTRACTOR’s reporting system.
It is the responsibility of each CONTRACTOR Discipline Superintendent to check and approve
inputs and physical progress prepared by SUBCONTRACTORS in their relevant area.
It is the responsibility of the CONTRACTOR Site Project Control Manager to consolidate the overall
construction progress
It is the responsibility of each SUBCONTRACTOR and CONTRACTOR Site Project Control
Manager to analyse the results of the system, to suggest recovery plans based on Actual achieved
progress versus planned progress and expenditure to date.
CONTRACTOR shall accommodate periodic inspections and progress reviews/verifications to be
agreed with COMPANY before issuing the Construction progress report.

5. PROGRESS CALCULATION PROCESS


5.1 Basis of Progress calculation System
The construction progress calculation is based on the construction work breakdown structure
illustrated in the document: 9952T-0000-PP-0306 Rev 0: where the facilities are divided into
different geographical areas or sections having or not different functionalities (Level II). For each of
these plants or sections defined at the Level II trades or disciplines are identified and quantified in
terms of work volumes and direct man-hours required to complete the works (Level III).
Each disciplines or trades are then divided into sub trade activities or type of works (Level IV). The
type of works consists of the combination of the work items (i.e. foundation) of the type of the works
of the concerned discipline or trades.
In the calculation process, the physical progress is evaluated at the work item level that may be, if
required, constituted of several work steps whose completion status can be easily assessed.
Weights assigned to each work item are based on their relevant work volume and productivity
figures to generate the required estimated direct man-hours to construct or fabricate the work item.
The weight of each work step can be either calculated with the same method or selected from the
data provided in Attachment 1.
5.2 Weighing System
The wide range of Project materials to be fabricated, erected, installed at Site are evaluated for
“weight incidence” and progress measurement by transformation of quantity of materials (Bill Of
Quantities, BOQ) of each Work Item into equivalent amount of SMH of work required.
Each Work Item is consequently estimated in PMH and it can be possible to build up to total SMH
of the Project and define the appropriate incidence (percentage) of the Work Item on the whole.
For a fair and fast physical evaluation of each work step completion state (to be done mainly at site
by Contractor/Supervisor/progress Controller), the progress is divided into 5 steps – 0, 25, 50, 75
and 100% that can be easily validated by the persons in charge of progress reporting or
verification.
Having entered the estimated percentage completion (0, 25, 50, 75 or 100% complete) for each of
the work steps, the system compiles the work progress at each level of the defined progress
breakdown structure to eventually produce the Project overall construction progress.

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 6/78

5.3 Physical Progress Software


EPC Contractor software called Easy Plant Site management & Control System SMC will be used
(features and functionalities are illustrated in Attachment 3) for recording, calculation, reporting
and monitoring the physical progress of the works.
5.4 SMC Preparation
Before works commencement, CONTRACTOR will define the progress-reporting breakdown
structure together with the weights of each parameter.
As far as the SMC results will be used for monthly billing of the activity done by
SUBCONTRACTORS (refer to Contracts terms), the SMC breakdown shall match with the
Contracting Plan and Contracts breakdowns. Basically, it should be divided per areas/disciplines.
When the SMC proposed structure and weights are approved by both parties, the SMC will form an
integral part of the Contract documentation and will therefore be binding to all parties.
Reduced to the strict necessity (possibly once, just be, start of mechanical erection when detail
engineering is almost completed) updating the SMC parameters shall be decided as set forth in the
Contract agreement.
5.5 Reporting Progress
The progress will be evaluated by SUBCONTRACTORS on weekly basis or as directed by
CONTRACTOR depending of the works progress.
After evaluation by SUBCONTRACTORS, the progress will be checked by CONTRACTOR.
Agreed progress will be incorporated into the SMC.
The approved weekly progress figures and updated SMC will be issued together with the
construction weekly progress report.
The monthly progress figures shall be approved and consolidated at the cut-off date close to the
25th of each month.
The weekly and monthly progress figures and reports will be distributed to COMPANY, to the
SUBCONTRACTORS, to CONTRACTOR Project Manager and to the Site team as per the Site
document distribution matrix. The following lists the various reports that can be issued:
• Physical progress & manpower table
• Physical progress & manpower table with quantities
• Physical progress bar chart
• Physical progress curve
• Work progress sheet
• Productive manpower histogram & curve
• Work productivity curve
• Work efficiency table
• System progress sheet
• System progress summary (one discipline or all disciplines)
• Unit progress for all systems( one discipline or all disciplines)
ATTACHMENT 3 illustrates some of the functionalities that will be developed for the progress
reporting.

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 7/78

5.6 Approving System


SUBCONTRACTORS proposed progress figures will be cross-checked but reviewed/approved for
the monthly progress close-out. It will be responsibility of the CONTRACTOR Construction Area
Managers/Superintendent(s) or delegate (Supervisor) to approve or comment on the
SUBCONTRACTORS figures and to require clarifications or amendments as necessary.
The progress figures will be reviewed and endorsed by CONTRACTOR Construction Manager.
The progress figures endorsed by CONTRACTOR shall be issued to COMPANY for review and
approval, which shall take place within a period of three days after reports distribution.

6. ADDITIONAL REPORTS
In addition to the progress calculation and reporting, SMC gets the possibility to calculate the
current contractor productivity by comparison with the information incorporated in SMC.The report
displays the work productivity curve for instantaneous and cumulative productivity. The productivity
is calculated based on the following formula for week or month:
Instantaneous (or cumulative) planned hours for week or month/ instantaneous (or cumulative)
planned progress for week or month x instantaneous (or cumulative) actual progress for week or
month/ instantaneous (or cumulative) actual hours for week or month x 100.

7. SYSTEM COMPLETION AND TURNOVER PROGRESS


System Completion and Turnover Progress are addressed in the Handover Philosophy Procedure
9952T-0000-PP-0907.

8. ATTACHMENTS
Attachment 1: Work Classes Definitions and Weights(To referee to Construction work breakdown
procedure 9952T-0000-PP-0306-0 annexure 4.
Attachment 2: Typical Jobsite Breakdown Structure
Attachment 3: SMC Software Functionalities

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 8/78

ATTACHMENT 1:

Work Step Definitions and Weights

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 9/78

Progressive Weight
MEASURE UNIT
WORK CLASS
DISCIPLINE

Step Weight
CODE

DISCIPLINE WORK CLASS DESCRIPTION WORK STEP

13 PIPING
13100 PREFABRICATION
13110 PIPING >= 2 INCH PREFABRICATION
13110 PIPING >= 2 INCH PREFABRICATION (By MATERIAL: CS, SS, AS)
KG
SPOOLING 2 2
MATERIAL RELASED AND CONSERVATION STATUS 3 5
PIPES SECTIONING 20 25
ASSEMBLY AND TACK WELDS 20 45
WELDING 30 75
NDE/PWHT/PAMI EXECUTION AND TRACEABILITY 20 95
SPOOLS IDENTIFICATION AND SHIPPING RELEASE 4 99
FINAL CHECK 1 100

13111 PIPING >= 24 INCH PREFABRICATION


13111 PIPING >= 24 INCH PREFABRICATION (By MATERIAL: CS, SS, AS)
KG
SPOOLING 2 2
MATERIAL RELASED AND CONSERVATION STATUS 3 5
PIPES SECTIONING 20 25
ASSEMBLY AND TACK WELDS 20 45
WELDING 30 75
NDE/PWHT/PAMI EXECUTION AND TRACEABILITY 20 95
SPOOLS IDENTIFICATION AND SHIPPING RELEASE 4 99
FINAL CHECK 1 100

13120 PIPING < 2 INCH PREFABRICATION

13200 ERECTION
13210 PIPING >=2 INCH ON SITE A.E.
13210 PIPING >=2 INCH ON SITE A.E. (By MATERIAL: CS, SS, AS)
KG
DELIVERED MATERIAL READY AT SITE 5 5
ERECTION AND ALIGNMENT 25 30
WELDING 30 60
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 10 70
PIPING SUPPORT DIMENSIONAL CHECK 13 83
PUNCH LIST BEFORE PRESSURE TEST 5 88
PRESSURE TEST 10 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13212 PIPING >=2 INCH ON RACKS AND PIPEWAYS


13212 PIPING >=2 INCH ON RACKS AND PIPEWAYS (By MATERIAL: CS, SS, AS)
KG
PREASSEMBLING 20 20

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 10/78

DELIVERED MATERIAL READY AT SITE 3 23


ERECTION AND ALIGNMENT 24 47
WELDING 22 69
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 7 76
PIPING SUPPORT DIMENSIONAL CHECK 9 85
PUNCH LIST BEFORE PRESSURE TEST 5 90
PRESSURE TEST 8 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13213 PIPING >=2 INCH ON SLEEPERS


13213 PIPING >=2 INCH ON SLEEPERS (By MATERIAL: CS, SS, AS)
KG
PREASSEMBLING 20 20
DELIVERED MATERIAL READY AT SITE 3 23
ERECTION AND ALIGNMENT 24 47
WELDING 22 69
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 7 76
PIPING SUPPORT DIMENSIONAL CHECK 9 85
PUNCH LIST BEFORE PRESSURE TEST 5 90
PRESSURE TEST 8 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13214 PIPING >=24 INCH A.E.


13214 PIPING >=24 INCH A.E. (By MATERIAL: CS, SS, AS)
KG
DELIVERED MATERIAL READY AT SITE 5 5
ERECTION AND ALIGNMENT 25 30
WELDING 30 60
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 10 70
PIPING SUPPORT DIMENSIONAL CHECK 13 83
PUNCH LIST BEFORE PRESSURE TEST 5 88
PRESSURE TEST 10 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13215 PIPING >=24 INCH ON RACKS AND PIPEWAYS


13215 PIPING >=24 INCH ON RACKS AND PIPEWAYS (By MATERIAL: CS, SS, AS)
KG
PREASSEMBLING 20 20
DELIVERED MATERIAL READY AT SITE 3 23
ERECTION AND ALIGNMENT 24 47
WELDING 22 69
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 7 76
PIPING SUPPORT DIMENSIONAL CHECK 9 85
PUNCH LIST BEFORE PRESSURE TEST 5 90
PRESSURE TEST 8 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13216 PIPING >=24 INCH ON SLEEPER


13216 PIPING >=24 INCH ON SLEEPER (By MATERIAL: CS, SS, AS)
KG
PREASSEMBLING 20 20
DELIVERED MATERIAL READY AT SITE 3 23
ERECTION AND ALIGNMENT 24 47

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 11/78

WELDING 22 69
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 7 76
PIPING SUPPORT DIMENSIONAL CHECK 9 85
PUNCH LIST BEFORE PRESSURE TEST 5 90
PRESSURE TEST 8 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13217 PACKAGED PIPING

13221 PIPING UP TO 1 1/2 INCH A.E.


13221 PIPING UP TO 1 1/2 INCH A.E. (By MATERIAL: CS, SS, AS)
KG
PREASSEMBLING, FABRICATION 20 20
DELIVERED MATERIAL READY AT SITE 5 25
ERECTION AND ALIGNMENT (INCL. FABRICATION) 25 50
WELDING 20 70
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 7 77
PIPING SUPPORT DIMENSIONAL CHECK 9 86
PUNCH LIST BEFORE PRESSURE TEST 4 90
PRESSURE TEST 8 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13222 PIPING ON RACKS AND PIPEWAYS UP TO 1 1/2 INCH


13222 PIPING ON RACKS AND PIPEWAYS UP TO 1 1/2 INCH (By MATERIAL: CS, SS, AS)
KG
PREASSEMBLING, FABRICATION 20 20
DELIVERED MATERIAL READY AT SITE 5 25
ERECTION AND ALIGNMENT (INCL. FABRICATION) 25 50
WELDING 20 70
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 7 77
PIPING SUPPORT DIMENSIONAL CHECK 9 86
PUNCH LIST BEFORE PRESSURE TEST 4 90
PRESSURE TEST 8 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13230 STEAM TRACING INSTALLATION


13230 STEAM TRACING INSTALLATION
KG
PREASSEMBLING, FABRICATION 15 15
DELIVERED MATERIAL READY AT SITE 5 20
ERECTION AND ALIGNMENT (INCL. FABRICATION) 30 50
WELDING 20 70
NDE, PWHT, PAMI EXECUTION AND TRACEABILTY 7 77
PIPING SUPPORT DIMENSIONAL CHECK 9 86
PRESSURE TEST 12 98
PUNCH LIST AFTER PRESSURE TEST 1 99
FINAL CHECK 1 100

13240 PIPING SUPPORT ERECTION

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 12/78

13242 CONTROL & SAFETY VALVE ERECTION


13243 CONTROL VALVE ERECTION
KG
DELIVERED MATERIAL READY AT SITE 10 10
DIMENSIONAL CHECK 89 99
FINAL CHECK 1 100

13244 SAFETY VALVE ERECTION


KG
DELIVERED MATERIAL READY AT SITE 10 10
DIMENSIONAL CHECK 89 99
FINAL CHECK 1 100

13245 FIRE HYDRANTS

13332 PRECAST SLEEPERS ERECTION

13600 PIPING REVAMPING


13600 PIPING REVAMPING

13710 TIE INS

13800 SUPPORTS PREFABRICATION


13810 PIPING SUPPORTS PREFABRICATION
13810 PIPING SUPPORTS PREFABRICATION
KG
ASSEMBLY, TACK W. AND DIMENSIONAL CHECK
SECTIONING
WELDING
SHIPMENT RELEASE 99 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 13/78

14 SITE PREPARATION & U/G SYSTEMS


14200 SITE PROTECTION
14211 STEEL NET & PANEL FENCING
14211 STEEL NET & PANEL FENCING
LM
EXCAVATION 5 5
LEAN CONCRETE 5 10
FORMWORKS 10 20
REINFORCEMENT 10 30
CONCRETE POURING 10 40
FORMWORK STRIPPING 5 45
FENCING INSTALLATION 50 95
MISCELLANEA FINISHING WORKS 4 99
FINAL CHECK 1 100

14300 PILING
14320 CAST IN SITU CONCRETE PILES
14321 VIBRATED CAST IN PLACE PILES
LM
FINAL PILE LENGTH 10 10
CASING INSTALLATION (IF ANY) 5 15
REINFORCEMENT CAGE INSTALLATION 45 60
CONCRETING 30 90
CASING RECOVERY (IF ANY) 5 95
FINAL CHECK 5 100

14322 CONTINUOUS FIGHT AUGER PILES


LM
BORING 30 30
TRANSPORT OF EXCAVATED MATERIAL 5 35
POURING 45 80
REINFORCEMENT CAGE INSTALLATION 15 95
INTEGRITY TEST 4 99
FINAL CHECK 1 100

14330 SOIL IMPROVEMENT


14330 SOIL IMPROVEMENT
CUM
BACKFILL WITH GRAVEL 60 60
GENERAL FILL 35 95
FINAL CHECK 5 100

14400 EARTHWORKS
14420 GENERAL EXCAVATION
14420 GENERAL EXCAVATION
CUM
EXCAVATION 60 60
MATERIAL TRANSPORT 35 95
FINAL GRADING 4 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 14/78

14430 GENERAL EMBANKMENT


14430 GENERAL EMBANKMENT
CUM
GROUND PREPARATION 10 10
LAYING MATERIAL/COMPACTION 70 80
FINAL ROLLING 19 99
FINAL CHECK 1 100

14450 SOIL SCRUBBING


14450 SOIL SCRUBBING
SQM
EXCAVATION 60 60
MTERIAL TRANSPORT 35 95
FINAL GRADING 4 99
FINAL CHECK 1 100

14485 EARTH AND SAND TRENCHES


14485 EARTH AND SAND TRENCHES
CUM
EXCAVATION AND DEPTH 50 50
SEND BED/LEAN CONCRETE ELEVATION (IF ANY) 30 80
SAND COVERING (IF ANY) 10 90
BACKFILLING AND COMPACTION (IF ANY) 9 99
FINAL CHECK 1 100

14500 ROADS, YARDS, PAVING


14510 GRAVEL FINISHING
14510 GRAVEL FINISHING
SQM
EXCAVATION AND ELEVATION 10 10
COMPACTED SUBGRADE 40 50
FINAL GRADING 49 99
FINAL CHECK 1 100

14540 ASPHALT ROADS AND YARDS


14540 ASPHALT ROADS AND YARDS
SQM
GROUND PREPARATION 10 10
SUBGRADE COURSE 5 15
SUB BASE COURSE 30 45
BASE COURSE 25 70
BINDER COURSE 15 85
WEAR SURFACE COURSE 10 95
FINISHING WORKS 4 99
FINAL CHECK 1 100

14550 EARTH ROADS AND YARDS


14550 EARTH ROADS AND YARDS
SQM
GROUND PREPARATION 10 10
SUBGRADE COURSE 40 50
SUB BASE COURSE 40 90
FINISHING WORKS 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 15/78

14560 GRAVEL ROADS AND YARDS


14560 GRAVEL ROADS AND YARDS
SQM
EXCAVATION AND FINAL ELEVATION 10 10
COMPACTED SUBGRADE 40 50
FINAL GRADING & FINISHING 49 99
FINAL CHECK 1 100

14600 SITE PREPARATION REVAMPING


14600 SITE PREPARATION REVAMPING

14700 UNDERGROUND PIPING


14710 PIPELINE REROUTING DIA INCH
EXCAVATION 7 7
STRINGING 9 16
FITUP, WELDING & NDT 51 67
COATING OF WELD JOINTS 5 72
BACKFILLING 9 81
HYDROTEST 14 95
TIE-IN AT BOTH ENDS 5 100
14711 TRENCH/BACKFILL. FOR U/G PRESS. PIPE
14711 TRENCH/BACKFILL. FOR U/G PRESS. PIPE
LM
EXCAVATION & DEPTH 20 20
SEND BED/LEAN CONCRETE ELEVATION (IF ANY) 20 40
ANCHOR BLOCKS OPERATIONAL AREA CLEAR (IF AN 20 60
BACKFILLING AND COMPACTION (IF ANY) 20 80
FINAL LAYER AND TEST (IF ANY ) 19 99
FINAL CHECK 1 100

14712 UNDERGROUND CS PRESSURE PIPING


14712 UNDERGROUND CS PRESSURE PIPING
KG
DELIVERED MATERIAL READY AT SITE 5 5
ERECTION AND ALIGNMENT 25 30
WELDING 50 80
NDE, PWHT, PAMI EXECUTION 10 90
HOLIDAY TEST 9 99
FINAL CHECK 1 100

14715 CARBON STEEL SEWERS


14715 CARBON STEEL SEWERS
LM
EXCAVATION 10 10
PIPES JOINING (WELDING) 20 30
PIPES POSITIONING 30 60
PIPES/PITS JOINTS SEALING 10 70
LEAKAGE (GRAVITY TEST) 10 80

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 16/78

RESTORED JOINTS CHECK 10 90


BACKFILLING 9 99
FINAL CHECK 1 100

14716 CARBON STEEL VENTS


14716 CARBON STEEL VENTS
KG
EXCAVATION 10 10
PIPES JOINING (WELDING) 20 30
PIPES POSITIONING 30 60
PIPES/PITS JOINTS SEALING 10 70
LEAKAGE (GRAVITY TEST) 10 80
RESTORED JOINTS CHECK 10 90
BACKFILLING 9 99
FINAL CHECK 1 100

14730 CONCRETE SEWERS


14731 CONCRETE SEWERS
LM
EXCAVATION 10 10
PIPES JOINING (WELDING) 20 30
PIPES POSITIONING 30 60
PIPES/PITS JOINTS SEALING 10 70
LEAKAGE (GRAVITY TEST) 10 80
RESTORED JOINTS CHECK 10 90
BACKFILLING 9 99
FINAL CHECK 1 100

14800 DITCHES AND CROSSINGS


14810 DITCHES

14820 CROSSINGS

14900 DEMOLITIONS
14910 DEMOLITIONS
14910 DEMOLITIONS
U
SAFE CONDITION PRIOR DEMOLITION / DISMANTLING 5 5
DEMOLITION / DISMANTLING 65 70
TRANSPORT TO DISPOSAL AREA 29 99
FINAL CHECK 1 100

14920 DISMANTLING U
SAFE CONDITION PRIOR DEMOLITION / DISMANTLING 5 5
DEMOLITION / DISMANTLING 65 70
TRANSPORT TO DISPOSAL AREA 29 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 17/78

15 INSTRUMENTS AND SYSTEMS


15100 WORKS IN CONTROL ROOM
15100 WORKS IN CONTROL ROOM
151001 INSTALLATION OF CABINETS, BOARD EQUIPMENT AND RACKS
U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 8 10
CONNECTION (EXTERNAL WIRING) 60 80
CHECK 10 90
FINAL INSPECTION 10 99
FINAL CHECK 1 100

151005 INSTALLATION OF CONTROL SYSTEMS


U
INSTALLATION 10 10
CONNECTION (EXTERNAL WIRING) 60 80
CHECK 10 90
FINAL INSPECTION 10 99
FINAL CHECK 1 100

151005F INSTALLATION OF CONTROL SYSTEMS FIELD BUS


U
FINAL INSPECTION 25 99
FINAL CHECK 1 100

151006 INSTALLATION OF F & G EQUIPMENT


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 8 10
INSTALLATION OF INSTRUMENT 70 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

15110 WORKS IN CONTROL ROOM CABLE TRAYS


151002 INSTALLATION OF CABLE TRAYS
LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
PREFABRICATION & INSTALLATION OF SUPPORTS 38 40
INSTALLATION OF CONDUIT 20 60
INSTALLATION OF TRAYS 20 80
GROUNDING 5 85
INSTALLATION OF COVERS 5 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

15120 WORKS IN CONTROL ROOM CABLES & MULTICABLES


151003 INSTALLATION OF CABLES AND MULTICABLES
LM
INSTALLATION 40 60
TEST 20 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 18/78

15130 WORKS IN CONTROL ROOM CABLES CONNECTIONS


151004 CONNECTION OF CABLES AND MULTICABLES AT BOTH ENDS
U
SOURCE POINT CHECK 45 45
DESTINATION POINT CHECK 45 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

15200 INSTRUMENT CABLES JB, LP INSTALLATION


15210 INSTRUMENT CABLES WAYS
152001 INSTALLATION OF FIELD CABLE TRAYS
LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
PREFABRICATION & INSTALLATION OF SUPPORTS 38 40
INSTALLATION OF TRAYS 40 80
GROUNDING 5 85
INSTALLATION OF COVERS 5 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

152002 INSTALLATION OF UNDEGROUND FIELD CONDUITS


LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CONDUIT CONCRETE BASE AND TRENCH INSPECTIO 18 20
CONDUIT INSTALLATION 60 80
CONDUIT INSTALLATION CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

152003 INSTALLATION OF STUBUP


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
STUB UP CONCRETE BASE AND TRENCH INSPECTI 18 20
STUBUP INSTALLATION 60 80
STUBUP INSTALLATION CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

152004 INSTALLATION OF ABOVEGROUND FIELD CONDUITS


LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
PREFABRICATION & INSTALLATION OF SUPPORTS 38 40
INSTALLATION OF CONDUIT 40 80
GROUNDING 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

15220 INSTRUMENT CABLES


152005 INSTALLATION OF UNDERGROUND CABLES AND MULTICABLES
LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 40 60
TEST 20 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 19/78

152006 INSTALLATION OF ABOVEGROUND CABLES AND MULTICABLES


LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 40 60
TEST 20 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

152007 INSTALLATION OF CABLES AND MULTICABLES IN CONDUIT


LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 40 60
TEST 20 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

15230 INSTRUMENT CABLES CONNECTIONS


152008 CONNECTION OF CABLES AND MULTICABLES AT BOTH ENDS
U
SOURCE POINT CHECK 45 45
DESTINATION POINT CHECK 45 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

15240 JUNCTION BOX AND LOC. PANELS INSTALLATION


152009 INSTALLATION OF JUNCTION BOXES
U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 28 30
CONNECTION / WIRING 50 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

152010 INSTALLATION OF LOCAL PANELS


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CONNECTION / WIRING 15 45
INSTALLATION 28 60
CONNECTION 25 85
CHECK 10 95
FINAL INSPECTION 5 99
FINAL CHECK 1 100

15250 FIBER OPTIC


152011 INSTALLATION OF FIBER OPTIC CABLES
LM
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 40 60
TEST 20 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 20/78

152012 INTERMEDIATE SPLICING OF FIBER OPTIC CABLES


U
INSTALLATION 40 40
CHECK 10 50
TEST 45 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

152013 CONNECTION OF FIBER OPTIC CABLES


U
INSTALLATION 40 40
CHECK 10 50
TEST 45 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

152014 TEST OF FIBER OPTIC CABLES


U
CHECK 10 10
TEST 85 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

152015 INSTALLATION OF PATCH PANELS FOR FIBER OPTIC


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 68 70
CONNECTION (INTERNAL WIRING) 10 80
CHECK 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

15300 FIELD INSTRUMENTATION WORKS


15310 FIELD INSTRUMENTATION WORKS
153101 ELECTRONIC FLOW TRANSMITTERS DIFFERENTIAL PRESSURE TYPE INSTALLATION
U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORTS 10 20
SECONDARY CABLE TRAY INSTALLATION 20 40
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 60
INSTALLATION OF INSTRUMENT 25 85
FINAL INSPECTION 3 88
TEST 10 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153102 PNEUMATIC FLOW TRANSMITTERS DIFFERENTIAL PRESSURE TYPE INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
INSTALLATION OF INSTRUMENT 18 38
FINAL INSPECTION 3 49

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 21/78

INSTALLATION 45 94
TEST 7 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153103 PNEUMATIC FLOW LOCAL CONTROL INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
INSTALLATION OF INSTRUMENT 38 58
FINAL INSPECTION 3 69
INSTALLATION 25 94
TEST 7 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153104 FLOW INSTRUMENTS PURGE SYSTEM INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 10 12
INSTALLATION OF INSTRUMENT 68 80
FINAL INSPECTION 3 83
INSTALLATION 10 93
TEST 6 99
FINAL CHECK 1 100

153105 FLOW INSTRUMENTS STEAM TRACING INSTALLATION


U
INSTALLATION 94 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153106 FLOW INSTRUMENTS WINTERIZING BOXES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20
INSTALLATION OF INSTRUMENT 74 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153107 FLOW INSTRUMENTS HEATING BOXES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20
INSTALLATION OF INSTRUMENT 74 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153201 ELECTRONIC LEVEL TRANSMITTERS DISPLACEMENT TYPE INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
SECONDARY CABLE TRAY INSTALLATION 20 36

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 22/78

CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 56


INSTALLATION OF INSTRUMENT 40 96
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153202 PNEUMATIC LEVEL TRANSMITTERS DISPLACEMENT TYPE INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
INSTALLATION OF INSTRUMENT 28 44
INSTALLATION 40 86
TEST 10 96
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153203 LEVEL GAUGES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20
INSTALLATION OF INSTRUMENT 74 94
CHECK 5 99
FINAL CHECK 1 100

153204 ELECTRONIC LEVEL INSTRUMENTS DIFFERENTIAL PRESSURE TYPE INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORTS 10 20
SECONDARY CABLE TRAY INSTALLATION 20 40
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 60
INSTALLATION OF INSTRUMENT 25 85
FINAL INSPECTION 3 88
TEST 10 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153205 PNEUMATIC LEVEL TRANSMITTERS DIFFERENTIAL PRESSURE TYPE INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
INSTALLATION OF INSTRUMENT 38 58
FINAL INSPECTION 3 69
INSTALLATION 25 94
TEST 7 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153206 INSTALLATION OF FLOAT TYPE LEVEL INDICATORS


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
MECHANICAL INSTALLATION 50 52
ELECTRICAL CONNECTION 45 97

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 23/78

FINAL INSPECTION 1 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153207 TANKGAUGING INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
MECHANICAL INSTALLATION 50 52
ELECTRICAL CONNECTION 45 97
FINAL INSPECTION 1 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153208 LEVEL SWITCHES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
SECONDARY CABLE TRAY INSTALLATION 20 36
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 56
INSTALLATION OF INSTRUMENT 40 96
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153209 LEVEL INSTRUMENTS PURGE SYSTEM INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 10 12
INSTALLATION OF INSTRUMENT 10 22
INSTALLATION 60 85
TEST 13 98
FINAL INSPECTION 3 99
FINAL CHECK 1 100

153210 SPECIAL LEVEL INSTRUMENTS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20
SECONDARY CABLE TRAY INSTALLATION 20 40
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 60
INSTALLATION OF INSTRUMENT 34 94
FINAL INSPECTION 3 97
INSPECTION / CHECK POINT 2 99
FINAL CHECK 1 100

153211 LEVEL INSTRUMENTS STEAM TRACING INSTALLATION


U
INSTALLATION 94 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153212 LEVEL INSTRUMENTS WINTERIZING BOXES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 24/78

INSTALLATION OF INSTRUMENT 74 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153213 LEVEL INSTRUMENTS HEATING BOXES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20
INSTALLATION OF INSTRUMENT 74 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153301A ELECTRONIC PRESSURE TRANSMITTERS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORTS 10 20
SECONDARY CABLE TRAY INSTALLATION 20 40
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 60
INSTALLATION OF INSTRUMENT 25 85
TEST 9 97
FINAL INSPECTION 3 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153301B DIRECT PRESSURE SWITCHES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORTS 10 20
SECONDARY CABLE TRAY INSTALLATION 20 40
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 60
INSTALLATION OF INSTRUMENT 25 85
TEST 9 97
FINAL INSPECTION 3 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153302 PNEUMATIC PRESSURE TRANSMITTERS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
INSTALLATION OF INSTRUMENT 38 58
FINAL INSPECTION 3 69
INSTALLATION 25 94
TEST 7 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153303 PNEUMATIC PRESSURE DIRECT LOCAL CONTROL INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
INSTALLATION OF INSTRUMENT 38 58

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 25/78

FINAL INSPECTION 3 69
INSTALLATION 25 94
TEST 7 99
FINAL CHECK 1 100

153304A PNEUMATIC PRESSURE DIRECT LOCAL RECEIVER CONTROL,INDICATOR


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
INSTALLATION OF INSTRUMENT 40 60
FINAL INSPECTION 5 65
INSTALLATION 30 95
TEST 4 99
FINAL CHECK 1 100

153304B PNEUMATIC PRESSURE SWITCH


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
INSTALLATION OF INSTRUMENT 40 60
INSTALLATION 30 95
TEST 2 97
FINAL INSPECTION 5 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153305 LOCAL PRESSURE GAUGES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
INSTALLATION OF INSTRUMENT 80 96
CHECK 3 99
FINAL CHECK 1 100

153306 DRAFT GAUGES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORTS 10 20
INSTALLATION OF INSTRUMENT 65 85
FINAL INSPECTION 3 88
INSTALLATION 10 98
TEST 1 99
FINAL CHECK 1 100

153307 PRESSURE INSTRUMENTS PURGE SYSTEM INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 10 12
INSTALLATION OF INSTRUMENT 68 80
FINAL INSPECTION 3 83

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 26/78

INSTALLATION 15 98
TEST 1 99
FINAL CHECK 1 100

153308 PRESSURE INSTRUMENTS STEAM TRACING INSTALLATION


U
INSTALLATION 94 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153309 PRESSURE INSTRUMENTS WINTERIZING BOXES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20
INSTALLATION OF INSTRUMENT 74 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153310 PRESSURE INSTRUMENTS HEATING BOXES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 18 20
INSTALLATION OF INSTRUMENT 74 94
FINAL INSPECTION 5 99
FINAL CHECK 1 100

153401 THERMOELEMENTS AND THERMOWELLS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 12 14
INSTALLATION OF SUPPORT 3 17
SECONDARY CABLE TRAY INSTALLATION 20 37
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 57
INSTALLATION OF INSTRUMENT 40 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

153402 ELECTRONIC TEMPERATURE TRANSMITTERS / CONVERTERS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
SECONDARY CABLE TRAY INSTALLATION 20 36
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 56
INSTALLATION OF INSTRUMENT 40 96
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153403 PNEUMATIC TEMPERATURE TRANSMITTERS AND CONTROLLERS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 27/78

INSTALLATION OF INSTRUMENT 40 60
INSTALLATION 30 95
TEST 2 97
FINAL INSPECTION 5 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153404 DIRECT TEMPERATURE SWITCHES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
INSTALLATION OF SUPPORTS 10 26
SECONDARY CABLE TRAY INSTALLATION 20 46
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 66
INSTALLATION OF INSTRUMENT 30 96
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153405 THERMOMETERS AND WELLS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
INSTALLATION OF INSTRUMENT 82 98
CHECK 1 99
FINAL CHECK 1 100

153406 TEMPERATURE SYSTEMS INSTALLATION ON TANK


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
INSTALLATION OF INSTRUMENT 80 96
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

15350 FIELD ONLINE INSTRUMENTATION WORKS


153501 ONLINE ELECTRONIC TRANSMITTERS INSTALLATION
U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
SECONDARY CABLE TRAY INSTALLATION 20 36
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 56
INSTALLATION OF INSTRUMENT 30 86
MECHANICAL INSTALLATION 1 90
ELECTRICAL CONNECTION 7 97
FINAL INSPECTION 3 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153502 ONLINE PNEUMATIC TRANSMITTERS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
INSTALLATION OF INSTRUMENT 40 56
MECHANICAL INSTALLATION 1 59

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 28/78

PNEUMATIC CONNECTION 7 66
INSTALLATION 28 95
TEST 2 97
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153503 ONLINE INDICATORS OR TOTALIZERS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
MECHANICAL INSTALLATION 96 98
FINAL INSPECTION 1 99
FINAL CHECK 1 100

153504 ONLINE SPECIAL ELECTRONIC TRANSMITTERS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
SECONDARY CABLE TRAY INSTALLATION 20 36
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 56
INSTALLATION OF INSTRUMENT 30 86
MECHANICAL INSTALLATION 1 90
ELECTRICAL CONNECTION 7 97
FINAL INSPECTION 3 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153505A CONTROL AND ONOFF VALVES (PNEUM) INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSPECTION 10 12
CALIBRATION 10 22
CONNECTION 20 65
FINAL INSPECTION 1 71
INSTALLATION 23 91
CHECK 5 93
TEST 5 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153505B CONTROL AND ONOFF VALVES (MOV) INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSPECTION 10 12
CALIBRATION 10 22
INSTALLATION 33 55
CONNECTION 35 90
CHECK 7 97
FINAL INSPECTION 1 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 29/78

153506 I/P OR P/I CONVERTERS SOLENOID VALVES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CALIBRATION 8 10
INSTALLATION OF SUPPORT 10 20
SECONDARY CABLE TRAY INSTALLATION 20 40
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 60
INSTALLATION OF INSTRUMENT 20 80
TEST 12 97
FINAL INSPECTION 5 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

153507 SELF ACTUATED PRESSURE REDUCING VALVES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 58 60
CONNECTION 5 65
CHECK 34 99
FINAL CHECK 1 100

153508 PUSH BUTTONS,LIMIT SWITCHES AND SELECTORS INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 3 3
CALIBRATION 13 16
INSTALLATION OF SUPPORTS 10 26
SECONDARY CABLE TRAY INSTALLATION 20 46
CABLE INSTAL., WIRING, INSTR. GROUND. & CABLE 20 66
INSTALLATION OF INSTRUMENT 30 96
FINAL INSPECTION 2 98
INSPECTION / CHECK POINT 1 99
FINAL CHECK 1 100

15500R INSTRUMENTATION REVAMPING


15500R INSTRUMENTATION REVAMPING

15600 ANALYZERS INSTALLATION


15600 ANALYZERS INSTALLATION
156001 ONLINE ANALYZER INSTALLATION
U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 10 12
INSTALLATION OF INSTRUMENT 68 80
INSTALLATION 10 93
TEST 5 98
FINAL INSPECTION 3 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 30/78

156002 ANALYZER INSTALLATION IN ANALYZER HOUSE


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 10 12
INSTALLATION OF INSTRUMENT 68 80
INSTALLATION 10 93
TEST 5 98
FINAL INSPECTION 3 99
FINAL CHECK 1 100

156003 PREFABRICATED ANALYZER HOUSES INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTRUMENT HOOK UP INSTALLATION 13 15
CABLES AND WIRING 25 40
JUNCTION BOX / LOCAL PANEL 30 70
INSTALLATION 23 94
TEST 4 98
FINAL INSPECTION 1 99
FINAL CHECK 1 100

156004 ANALYZER EQUIPMENT INSTALLATION


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION OF SUPPORT 20 22
INSTALLATION OF INSTRUMENT 74 96
FINAL INSPECTION 3 99
FINAL CHECK 1 100

15700 TELECOMMUNICATION SYSTEMS INSTALLATION WORKS


15700 TELECOMMUNICATION SYSTEMS INSTALLATION WORKS
157001 TELECOMMUNICATION SYSTEMS INSTALLATION CONTROL ROOM
U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CONNECTION & WIRING 10 87
INSTALLATION 25 99
FINAL CHECK 1 100

157002 TELECOMMUNICATION SYSTEMS INSTALLATION TECHNICAL ROOM


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
CONNECTION & WIRING 10 87
INSTALLATION 25 99
FINAL CHECK 1 100

157003 FIELD INSTALLATION OF COMMUNICATION APPARATUSES


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2
INSTALLATION 5 87
CONNECTION & WIRING 15 99
FINAL CHECK 1 100

157004 INSTALLATION AND CONNECTION OF ANTENNA SYSTEM


U
MATERIAL IDENTIFICATION AND CONSERVATION STA 2 2

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 31/78

CONNECTION & WIRING 20 37


FINAL INSPECTION 2 39
INSTALLATION 20 59
CONNECTION / WIRING 40 99
FINAL CHECK 1 100

15800 INSTRUMENTATION TIE INS


15800 INSTRUMENTATION TIE INS

15900 PACKAGE INSTRUMENTATION TEST


15900 PACKAGE INSTRUMENTATION TEST
159001 DISMOUNTLING, CALIBRATION, TEST AND REINSTALLATION OF SKID MOUNTED INSTRUMENT
U
INSTRUMENT HOOKUP INSTALLATION 35 35
CABLES AND WIRING 25 60
JUNCTION BOX / LOCAL PANEL 35 95
CHECK 3 98
FINAL INSPECTION 1 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 32/78

16 ELECTRICAL INSTALLTION
16100 GROUNDING AND LIGHTNING SYSTEM
16100 GROUNDING AND LIGHTNING SYSTEM
16101 UNDERGROUND GROUNDING CONDUCTOR
LM
CONDUCTOR LAYING 65 65
CONDUCTOR JOINTS AND DERIVATIONS 25 90
TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16102 I/C OF ROD WITH INSPECTION PIT


U
INSTALLATION OF PIT 55 55
INSTALLATION OF ROD 25 80
CONNECTION EXECUTION 10 90
TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16103 I/C OF ROD WITHOUT INSPECTION PIT


U
INSTALLATION OF ROD 80 80
CONNECTION EXECUTION 10 90
TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16104 GROUNDING BAR


U
INSTALLATION OF BAR 40 40
STUB UP AND CONCRETE BASE 30 70
CONNECTION EXECUTION 20 90
TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16105 OVERHEAD CONDUCTOR


LM
LAYING AND FIXING OF ABOVEGROUND CONDUCTO 65 65
CONSUCTOR JOINTS AND DERIVATIONS 25 90
TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16106 EQUIPMENT GROUNDING CONNECTION


U
CONNECTION EXECUTION 90 90
TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16107 GROUNDING PLATE


U
PLATE PREFABRICATION 50 50
PLATE INSTALLATION 40 90

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 33/78

TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16108 LIGHTNING PROTECTION SYSTEM


U
CONDUCTOR LAYING AND FIXING 60 60
CONNECTIONS EXECUTION 20 80
INSTALLATION OF AIR TERMINALS 10 90
TESTS 7 97
FINAL INSPECTION 2 99
FINAL CHECK 1 100

16200 SUBSTATION EQUIPMENT


16210 TRANSFORMERS INSTALLATION
16201 MAIN TRANSFORMERS, LIQUID IMMERSED
U
TRANSPORTATION AND ALIGNMENT 20 20
MECHANICAL INSTALLATION 35 55
ELECTRICAL INSTALLATION 30 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16202 MAIN TRANSFORMERS, CAST RESIN / DRY


U
TRANSPORTATION AND ALIGNMENT 35 35
MECHANICAL INSTALLATION 30 65
ELECTRICAL INSTALLATION 20 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16203 DISTRIBUTION TRANSFORMERS, LIQUID IMMERSED


U
TRANSPORTATION AND ALIGNMENT 20 20
MECHANICAL INSTALLATION 25 45
ELECTRICAL INSTALLATION 40 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16204 DISTRIBUTION TRANSFORMERS, CAST RESIN / DRY


U
TRANSPORTATION AND ALIGNMENT 35 35
MECHANICAL INSTALLATION 30 65
ELECTRICAL INSTALLATION 20 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16220 SUBSTATION EQUIPMENT


16205 REACTORS
U
TRANSPORTATION AND ALIGNMENT 35 35
MECHANICAL INSTALLATION 30 65
ELECTRICAL INSTALLATION 20 85

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 34/78

TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16206 MEDIUM VOLTAGE SWITCHGEARS AND MCCs


U
TRANSPORTATION AND ALIGNMENT 25 25
MECHANICAL INSTALLATION 40 65
ELECTRICAL INSTALLATION 15 80
TESTING 15 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16207 LOW VOLTAGE SWITCHGEARS AND MCCs


U
TRANSPORTATION AND ALIGNMENT 25 25
MECHANICAL INSTALLATION 45 70
ELECTRICAL INSTALLATION 15 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16208 LOW VOLTAGE DISTRIBUTION AND AUXILIARY PANELS


U
FINAL CHECK 1 100
FINAL INSPECTION 4 99
INSTALLATION 85 85
TESTING 10 95

16209 BUS DUCTS


U
PREFABRICATION OF SUPPORTS 15 15
INSTALLATION OF SUPPORTS 20 35
MECHANICAL INSTALLATION 45 80
ELECTRICAL INSTALLATION 10 90
TESTING 5 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16210 CAPACITOR BANKS


U
INSTALLATION 85 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16211 GROUNDING RESISTORS


U
INSTALLATION 85 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 35/78

16212 UPS SYSTEM


U
MECHANICAL INSTALLATION 80 80
ELECTRICAL INSTALLATION 15 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16213 DC CHARGERS
U
MECHANICAL INSTALLATION 70 70
ELECTRICAL INSTALLATION 15 85
TESTING 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16214 BATTERIES
U
RACK AND BATTERIES INSTALLATION 60 60
BATTERY CONNECTION AND FILLING 35 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16215 VARIABLE FREQUENCY DRIVES


U
MECHANICAL INSTALLATION 80 80
ELECTRICAL INSTALLATION 15 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16300 POWER SYSTEM


16310 POWER SYSTEM CABLE WAYS
16301 CABLE TRAYS AND CABLE LADDERS
LM
PREFABRICATION OF SUPPORTS 20 20
INSTALLATION OF SUPPORTS 30 50
INSTALLATION OF TRAYS 39 89
TRAYS GROUNDING 4 93
INSTALLATION OF COVERS 5 98
FINAL INSPECTION 1 99
FINAL CHECK 1 100

16302 UNDERGROUND CONDUITS


LM
ROUTE CHECK AND SUPPORTS INSTALLATION 15 15
CONDUIT PREPARATION AND BENDING 25 40
LAYING OF CONDUIT ANS STUBUP 45 85
INDENTIFICATION OF CONDUIT 10 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16303 ABOVEGROUND CONDUITS


LM
ROUTE CHECK AND SUPPORTS INSTALLATION 25 25
CONDUIT PREPARATION AND BENDING 25 50
LAYING OF CONDUIT 40 90

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 36/78

GROUNDING OF CONDUIT 8 98
FINAL INSPECTION 1 99
FINAL CHECK 1 100

16320 POWER SYSTEM CABLES


16304 CABLES, DIRECTLY BURIED
LM
STUBUP AND CONCRETE BASE 5 5
HANDLING OF CABLE REEL 5 10
LAYING OF CABLES 60 70
INSULATION AND RESISTANCE TEST (BEFORE BACK 5 75
CABLE MARKERS INSTALLATION 10 85
INSULATION AND RESISTANCE TEST (AFTER BACKF 5 90
CABLE WAY MARKERS INSTALLATION 5 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16305 CABLES, IN UNDERGROUND DUCT / CONDUIT


LM
STUBUP, CONCRETE BASE AND DUCT/CONDUIT 5 5
HANDLING OF CABLE REEL 5 10
DUCT/CONDUIT CLEANING 5 15
CABLE PULLING 70 85
INSULATION AND RESISTANCE TEST 5 90
CABLE MARKERS INSTALLATION 5 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16306 INTERCONNECTING CABLES IN CABLE TRAYS / LADDERS


LM
HANDLING OF CABLE REEL 5 5
LAYING OF CABLES 80 85
INSULATION AND RESISTANCE TEST 5 90
CABLE MARKERS INSTALLATION 5 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16330 POWER SYSTEM CABLES CONNECTIONS


16307 CONNECTION OF CABLES
U
GLANDING, CONNECTION AND TESTING 90 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16340 POWER SYSTEM ( PANELS, JUNCTION BOXES)


16308 CONTROL STATIONS
U
PREFABRICATION OF SUPPORTS 25 25
INSTALLATION OF SUPPORTS 30 55
INSTALLATION OF CONTROL STATION 35 90

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 37/78

FINAL INSPECTION 9 99
FINAL CHECK 1 100

16309 WELDING OUTLETS


U
PREFABRICATION AND INSTALLATION OF SUPPORTS 55 55
INSTALLATION OF WELDING OUTLET 35 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16310 INSTLLATION OF CABLE JOINTS


U
INSTALLATION OF JOINT 80 80
JOINT MARKER PLATE INSTALLATION 10 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16311 JUNCTION BOXES


U
PREFABRICATION OF SUPPORTS 25 25
INSTALLATION OF SUPPORTS 30 55
INSTALLATION OF JUNCTION BOX 35 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16312 VARIOUS EQUIPMENT


U
PREFABRICATION AND INSTALLATION OF SUPPORTS 55 55
INSTALLATION OF EQUIPMENT 40 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16313 FIRESTOP BARRIERS


U
INSTALLATION 90 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16400 HIGH VOLTAGE EQUIPMENT


16400 HIGH VOLTAGE EQUIPMENT
16401 AERIAL TRASMISSION LINE / SUBSTATION
U
MECHANICAL INSTALLATION 40 40
ELECTRICAL INSTALLATION 40 80
TESTING 15 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16402 GAS INSULATED LINE/SUBSTATION


U
MECHANICAL INSTALLATION 40 40
ELECTRICAL INSTALLATION 40 80
TESTING 15 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 38/78

16500 ELECTRICAL HEAT TRACING SYSTEM


16500 ELECTRICAL HEAT TRACING SYSTEM
16501 LOCAL DISTRIBUTION PANEL
U
PREFABRICATION OF SUPPORTS 25 25
INSTALLATION OF SUPPORTS 30 55
INSTALLATION OF PANELBOARD 35 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16502 MAIN JUNCTION BOX


U
PREFABRICATION OF SUPPORTS 25 25
INSTALLATION OF SUPPORTS 30 55
ISTALLATION OF JUNCTION BOX 40 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16503 COLD CABLE INSTALLATION


U
INSTALLATION 15 15
CABLE WAY AND WIRING 75 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16504 HEATING CABLE


U
PREINSTALLATION CHECKS 5 5
INSTALLATION OF CABLES 60 65
INSTALLATION AND CONNECTION OF COMPONENTS 25 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16505 CONNECTION OF TEMPERATURE SWITCH


U
INSTALLATION 90 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16550 ELECTRICAL TIE INS

16600 ELECTRICAL REVAMPING


16600 ELECTRICAL REVAMPING

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 39/78

16700 CATHODIC PROTECTION SYSTEM


16700 CATHODIC PROTECTION SYSTEM
16701 TRANSFORMER RECTIFIER
U
ELECTRICAL INSTALLATION 45 85
FINAL CHECK 1 100
FINAL INSPECTION 4 99
MECHANICAL INSTALLATION 30 40
TESTING 10 95
TRANSPORTATION AND ALIGNMENT 10 10

16702 I/C OF ANODES


U
INSTALLATION 90 90
TESTS AND FINAL INSPECTION 9 99
FINAL CHECK 1 100

16703 I/C OF REFERENCE CELLS


U
FINAL CHECK 1 100
INSTALLATION 90 90
TESTS AND FINAL INSPECTION 9 99

16704 I/C OF TEST STATIONS


U
INSTALLATION 90 90
TESTS AND FINAL INSPECTION 9 99
FINAL CHECK 1 100

16705 JUNCTION BOX


U
FINAL CHECK 1 100
INSTALLATION 90 90
TESTS AND FINAL INSPECTION 9 99

16706 CABLES
LM
INSTALLATION 90 90
TESTING 9 99
FINAL CHECK 1 100

16707 CONNECTION OF CABLES


U
CONNECTION 95 95
TESTING 4 99
FINAL CHECK 1 100

16800 LIGHTING SYSTEM


16800 LIGHTING SYSTEM
16801 LOCAL DISTRIBUTION PANEL
U
PREFABRICATION OF SUPPORTS 25 25
INSTALLATION OF SUPPORTS 30 55
INSTALLATION OF PANELBOARD 35 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 40/78

16802 MAIN JUNCTION BOX


U
PREFABRICATION OF SUPPORTS 25 25
INSTALLATION OF SUPPORTS 30 55
INSTALLATION OF JUNCTION BOX 40 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16803 I/C OF LIGHTING FIXTURE, ASSOCIATED JB AND CABLE WAY


U
INSTALLATION OF SUPPORTS 20 20
INSTALLATION OF FIXTURE AND JB 25 45
CABLE WAY AND WIRING 50 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16804 I/C OF STREET LIGHTING POLE


U
MAST INSTALLATION 65 65
LAMP INSTALLATION AND WIRING 25 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16805 I/C OF LIGHTING TOWER


U
MAST AND CROWN INSTALLATION 65 65
LAMP INSTALLATION AND WIRING 25 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

16806 I/C OF RECEPTACLE OUTLET AND CABLE WAY


U
INSTALLATION OF SUPPORTS 20 20
INSTALLATION OF RECEPTACLE 25 45
CABLE WAY AND WIRING 50 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16807 I/C OF LIGHTING LEVEL GAUGE


U
INSTALLATION 30 30
CABLE WAY AND WIRING 65 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16808 I/C OF AIRCRAFT WARNING LIGHTING SYSTEM


U
INSTALLATION OF SUPPORTS 20 20
INSTALLATION OF PANELS AND BEACONS 30 50
CABLE WAY AND WIRING 40 90
FINAL INSPECTION 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 41/78

16900 ROTATING EQUIPMENT


16900 ROTATING EQUIPMENT
16901 ELECTRIC MOTOR
U
ELECTRIC MOTOR AND ACCESSORIES INSTALLATIO 50 50
ELECTRICAL TESTS AND CHECKS 45 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16902 ELECTRIC MOTOR OPERATED VALVE


U
VALVE ACTUATOR INSTALLATION 50 50
ELECTRICAL TESTS AND CHECKS 45 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

16903 DIESEL GENSET


U
EQUIPMENT AND ACCESSORIES INSTALLATION 50 50
ELECTRICAL TESTS AND CHECKS 45 95
FINAL INSPECTION 4 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 42/78

17 CIVIL WORKS
17100 CONCRETE WORKS
17110 FOUNDATIONS
17111 CONCRETE FOUNDATIONS FOR EQUIPMENT/STRUCTURES
CUM
DEEP EXCAVATION 5 5
LEAN CONCRETE LEVEL 5 10
FORMWORKS 22 32
REINFORCEMENT 30 62
EMBEDDED ITEMS 10 72
CASTING 17 89
FORMWORKS STRIPPING 5 94
BACKFILLING 5 99
FINAL CHECK 1 100

17111R FOUNDATIONS REVAMPING


CUM
EXCAVATION 5 5
EXECUTION OF HOLES 9 14
RESIN INJECTION OF HOLES 9 23
LEAN CONCRETE LEVEL 5 28
REINFORCEMENT 28 56
FORMWORK 12 68
EMBEDDED ITEMS 11 79
CASTING 10 89
FORMWORK STRIPPING 5 94
BACKFILLING 5 99
FINAL CHECK 1 100

17113 CONCRETE SMALL FOUNDATIONS


CUM
EXCAVATION 10 10
FORMWORKS 22 32
REINFORCEMENT 23 55
CASTING 30 85
FORMWORKS STRIPPING 9 94
BACKFILLING 5 99
FINAL CHECK 1 100

17116 CONCRETE LARGE MASSIVE FOUNDATIONS


CUM
EXCAVATION 5 5
LEAN CONCRETE 5 10
FORMWORKS 20 30
REINFORCEMENT 28 58
EMBEDDED ITEMS 13 71
CASTING 18 89
FORMWORKS STRIPPING 5 94
BACKFILLING 5 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 43/78

17117 LIGHTING POLES FOUNDATIONS


CUM
EXCAVATION 5 5
LEAN CONCRETE LEVEL 5 10
FORMWORKS 10 20
REINFORCEMENT 20 40
CASTING 10 50
PREFABRICATED LIGHTING POLES FOUNDATIONS 35 85
POSITIONING 10 95
BACKFILLING 4 99
FINAL CHECK 1 100

17114 TANK RINGS / CONCRETE PADS


17114 TANK RINGS / CONCRETE PADS
CUM
EXCAVATION 10 10
LEAN CONCRETE 5 15
RING FOOTING REINFORCEMENT 15 30
RING FOOTING FORMWORKS 15 45
RING FOOTING POURING 15 60
RING PEDESTAL REINFORCEMENT 5 65
RING PEDESTAL FORMWORK & ANCHOR BOLTS 5 70
RING PEDESTAL POURING 5 75
FORMWORKS REMOVAL 15 90
INTERNAL BACKFILLING COMPLETED AND ACCEPTE 9 99
FINAL CHECK 1 100

17115 CAST IN SITU SLEEPERS


17115 CAST IN SITU SLEEPERS
CUM
EXCAVATION 5 5
LEAN CONCRETE LEVEL 5 10
FORMWORKS 25 35
REINFORCEMENT 20 55
EMBEDDED ITEMS 10 65
CASTING 30 95
FORMWORKS STRIPPING 4 99
FINAL CHECK 1 100

17120 CONCRETE ELEVATED STRUCTURES CAST IN SITU


17121 CONCRETE ELEVATED STRUCTURES CAST IN SITU
CUM
FORMWORKS 27 27
REINFORCEMENT 27 54
EMBEDDED ITEMS 15 69
CASTING 20 89
FORMWORKS STRIPPING 10 99
FINAL CHECK 1 100

17130 CONCRETE PAVING / ROADS / YARDS


17131 CONCRETE PAVING
SQM
FORMWORKS, REINFORCEMENT AND JOINTS 60 60
POURING 25 85
FINISHING WORKS 14 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 44/78

17133 FOUNDATIONS ON PAVING


CUM
FORMWORKS 29 29
REINFORCEMENT 30 59
CASTING 40 99
FINAL CHECK 1 100

17141 CABLES CONCRETE TRENCHES


17141 CABLES CONCRETE TRENCHES
CUM
EXCAVATION 10 10
REINFORCED CONCRETE (CAST IN SITU) 10 20
CASTING 45 65
PREFABRICATION OF CONCRETE ELEMENTS 10 75
SAND CABLE COVERING 20 95
CONCRETE COVERS INSTALLATION 4 99
FINAL CHECK 1 100

17142 PITS, MANHOLES AND CATCH BASINS


17142 PITS, MANHOLES AND CATCH BASINS
CUM
EXCAVATION 5 5
CASTING 45 50
PREFABRICATED PITS 20 70
POSITIONING 15 85
ELEMENT TO ELEMENT SEALING 10 95
BACKFILLING 4 99
FINAL CHECK 1 100

17143 DUCT BANKS


17143 DUCT BANKS
CUM
EXCAVATION 20 20
PVC CONDUIT 40 60
RED CONCRETE POURING 39 99
FINAL CHECK 1 100

17144 CONCRETE DITCHES / TRENCHES


17144 CONCRETE DITCHES
CUM
EXCAVATION 10 10
FORMWORKS 15 25
REINFORCEMENT 15 40
CASTING 20 60
FORMWORKS STRIPPING 5 65
PREFABRICATED ELEMENTS 10 75
SAND CABLE COVERING 20 95
CONCRETE COVERS INSTALLATION 4 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 45/78

17146 CONCRETE TRENCHES FOR U/G PIPING


CUM
EXCAVATION 10 10
REINFORCED CONCRETE (CAST IN SITU) 10 20
CASTING 45 65
PREFABRICATION OF CONCRETE ELEMENTS 10 75
SAND CABLE COVERING 20 95
CONCRETE COVERS INSTALLATION 4 99
FINAL CHECK 1 100

17145 PULLING PITS


17145 PULLING PITS
CUM
EXCAVATION 5 5
CASTING 45 50
PREFABRICATED PITS 20 70
POSITIONING 15 85
ELEMENT TO ELEMENT SEALING 10 95
BACKFILLING 4 99
FINAL CHECK 1 100

17149 CONCRETE BOX CULVERTS


17149 CONCRETE BOX CULVERTS
CUM
EXCAVATION 5 5
LEAN CONCRETE LEVEL 5 10
FORMWORKS 22 32
REINFORCEMENT 30 62
EMBEDDED ITEMS 10 72
CASTING 17 89
FORMWORKS STRIPPING 5 94
BACKFILLING 5 99
FINAL CHECK 1 100

17171 COOLING TOWERS AND CONCRETE BASINS


17171 COOLING TOWERS
CUM
EXCAVATION 5 5
LEAN CONCRETE 5 10
FORMWORKS 20 30
REINFORCEMENT 25 55
EMBEDDED ITEMS 5 60
CASTING 20 80
FORMWORKS STRIPPING 10 90
PRECAST ELEMENTS INSTALLATION 9 99
FINAL CHECK 1 100

17172 CONCRETE BASINS


17172 CONCRETE BASINS
CUM
EXCAVATION 10 10
LEAN CONCRETE 5 15
FORMWORKS 20 35
REINFORCEMENT 20 55
WATER STOPS 5 60

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 46/78

CASTING 20 80
FORMWORKS STRIPPING 5 85
PROTECTIVE COATING 5 90
LEAKAGE TEST 5 95
BACKFILLING 4 99
FINAL CHECK 1 100

17173 CONCRETE RETAINING WALLS


17173 CONCRETE RETAINING WALLS
CUM
EXCAVATION 10 10
LEAN CONCRETE 5 15
FORMWORKS 20 35
REINFORCEMENT 20 55
WATER STOPS 5 60
CASTING 20 80
FORMWORKS STRIPPING 5 85
PROTECTIVE COATING 5 90
LEAKAGE TEST 5 95
BACKFILLING 4 99
FINAL CHECK 1 100

17174 CONCRETE DYKES


17174 CONCRETE DYKES
CUM
TO DETAIL IF ANY 100 100

17300 PRECAST CONCRETE


17330 SLEEPERS
17331 SLEEPERS PREFABRICATION
CUM
REINFORCEMENT 25 25
FORMWORKS 20 45
CASTING 34 79
ANCHOR BOLTS 20 99
FINAL CHECK 1 100

17332 PRECAST SLEEPERS ERECTION


CUM
EXCAVATION 5 5
LEAN CONCRETE 10 15
COORDINATES CHECK 60 75
BACKFILLING 24 99
FINAL CHECK 1 100

17400 FIRE PROOFING


17410 DENSE CONCRETE FIRE PROOFING
17411 FIRE PROOFING FOR EQUIPMENT LEGS/CURBS
CUM
WELDED WIRE MESH INSTALLATION 20 20
FORMWORK INSTALLATION 30 50
CONCRETE FIREPROOFING APPLICATION 30 80
FORMWORKS REMOVAL 5 85
FINISHING WORKS 14 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 47/78

17412 FIRE PROOFING FOR EQUIPMENT SKIRTS


CUM
WELDED WIRE MESH INSTALLATION 20 20
FORMWORK INSTALLATION 30 50
CONCRETE FIREPROOFING APPLICATION 30 80
FORMWORKS REMOVAL 5 85
FINISHING WORKS 14 99
FINAL CHECK 1 100

17413 FIRE PROOFING FOR STEEL STRUCTURES


CUM
WELDED WIRE MESH INSTALLATION 20 20
FORMWORK INSTALLATION 30 50
CONCRETE FIREPROOFING APPLICATION 30 80
FORMWORKS REMOVAL 5 85
FINISHING WORKS 14 99
FINAL CHECK 1 100

17420 LIGHT WEIGHT FIRE PROOFING


17421 FIRE PROOFING FOR EQUIPMENT LEGS/CURBS
CUM
CLEANING SURFACE 10 10
REINFORCEMENT MESH 35 45
SPRAYEDCONCRETE APPLICATION 34 79
SUPERFICIAL SMOOTHING 20 99
FINAL CHECK 1 100

17422 FIRE PROOFING FOR EQUIPMENT SKIRTS


CUM
CLEANING SURFACE 10 10
REINFORCEMENT MESH 35 45
SPRAYEDCONCRETE APPLICATION 34 79
SUPERFICIAL SMOOTHING 20 99
FINAL CHECK 1 100

17423 FIRE PROOFING FOR STEEL STRUCTURES (AVIKOTE)


SQM
CLEANING SURFACE 10 10
REINFORCEMENT MESH 35 45
SPRAYEDCONCRETE APPLICATION 34 79
SUPERFICIAL SMOOTHING 20 99
FINAL CHECK 1 100

17500 CIVIL TIE INS


17500 CIVIL TIE INS

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 48/78

17600 SPECIAL COATINGS, GROUTING


17640 GROUTING FOR EQUIPMENT / STEEL STRUCTURES
17640 GROUTING FOR EQUIPMENT / STEEL STRUCTURES
SQM
SURFACE AND SOAKING 20 20
FORMWORKS 20 40
GROUT PREPARATION AND EXPIRING DATE 40 80
GROUTING 19 99
FINAL CHECK 1 100

17900 CIVIL WORK REVAMPING


17900 CIVIL WORK REVAMPING

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 49/78

18 STEEL STRUCTURES
18100 MAIN STRUCTURAL STEEL ERECTION
18111 TRESTLE STRUCTURES
18111 TRESTLE STRUCTURES
KG
ASSEMBLY 20 20
ERECTION 33 53
ALIGNMENT 16 69
ANCHOR BOLTS TIGHTNESS 26 95
CLEANING 4 99
FINAL CHECK 1 100

18112 PROCESS STRUCTURES


18112 PROCESS STRUCTURES
KG
ASSEMBLY 20 20
ERECTION 33 53
ALIGNMENT 16 69
ANCHOR BOLTS TIGHTNESS 26 95
CLEANING 4 99
FINAL CHECK 1 100

18113 PIPE RACKS


18113 PIPE RACKS
KG
ASSEMBLY 20 20
ERECTION 33 53
ALIGNMENT 16 69
ANCHOR BOLTS TIGHTNESS 26 95
CLEANING 4 99
FINAL CHECK 1 100

18113R PIPE RACKS REVAMPING


18113R PIPE RACKS REVAMPING
KG
DISMATLING COMPONENTS 4 4
POSITIONING & WELDING OF SUPPORT 6 10
ASSEMBLY 20 30
ERECTION 30 60
ALIGNMENT 15 75
ANCHOR BOLTS TIGHTNESS 20 95
CLEANING & FINAL ACCEPTANCE 4 99
FINAL CHECK 1 100

18114 STEEL FRAMES ON CONCRETE STRUCTURES


18114 STEEL FRAMES ON CONCRETE STRUCTURES
KG
ASSEMBLY 20 20
ERECTION 33 53
POSITIONING CHECKS 14 67

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 50/78

WELDING AND/OR BOLTING TIGHTNESS 26 93


CLEANING 6 99
FINAL CHECK 1 100

18115 ISOLATED SUPPORTS


18115 ISOLATED SUPPORTS
KG
ASSEMBLY 24 24
ERECTION 24 48
POSITIONING 16 64
BOLTING 30 94
CLEANING & FINAL ACCEPTANCE 5 99
FINAL CHECK 1 100

18200 SECONDARY STRUCTURAL STEEL ERECTION


18211 LADDERS AND HANDRAILS
18211 LADDERS AND HANDRAILS
KG
ASSEMBLY 22 22
ERECTION 36 58
POSITIONING 15 73
BOLTING 22 95
CLEANING 4 99
FINAL CHECK 1 100

18212 GRATINGS
18212 GRATINGS
KG
GRATINGS SELECTION 15 15
GRATINGS ERECTION 55 70
GRATINGS SECURING 25 95
CLEANING 4 99
FINAL CHECK 1 100

18213 CHECKERED PLATES


18213 CHECKERED PLATES
KG
PLATES SELECTION 15 15
PLATES ERECTION 55 70
PLATES SECURING 25 95
CLEANING 4 99
FINAL CHECK 1 100

18214 PLATFORMS AND WALKWAYS ON EQUIPMENT


18214 PLATFORMS AND WALKWAYS ON EQUIPMENT
KG
ASSEMBLY 25 25
ERECTION 33 58
POSITIONING 18 76
BOLTING 18 94
CLEANING 5 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 51/78

18215 EQUIPMENT FRAMES


18215 EQUIPMENT FRAMES
KG
ASSEMBLY 24 24
ERECTION 24 48
POSITIONING 16 64
BOLTING 30 94
CLEANING 5 99
FINAL CHECK 1 100

18217 ISOLATED PLATFORMS/SUPPORTS


18217 ISOLATED PLATFORMS/SUPPORTS
KG
ASSEMBLY 24 24
ERECTION 24 48
POSITIONING 16 64
BOLTING 30 94
CLEANING 5 99
FINAL CHECK 1 100

18300 BUILDINGS AND SHELTERS STRUCTURES


18310 SHELTERS
18310 SHELTERS
KG
ASSEMBLY 19 19
ERECTION 37 56
ALIGNMENT 14 70
ANCHOR BOLTS TIGHTNESS 25 95
CLEANING 4 99
FINAL CHECK 1 100

18320 BUILDINGS
18320 BUILDINGS
KG
ASSEMBLY 19 19
ERECTION 37 56
ALIGNMENT 14 70
ANCHOR BOLTS TIGHTNESS 25 95
CLEANING 4 99
FINAL CHECK 1 100

18400 STEEL STRUCTURES TIE INS


18400 STEEL STRUCTURES TIE INS

18500 STEEL STRUCTURES REVAMPING


18500 STEEL STRUCTURES REVAMPING

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 52/78

18800 CLADDING
18810 SIDING AND ROOFING
18810 SIDING AND ROOFING
SQM
ERECTION 55 55
BOLTING 20 75
CLEANING 24 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 53/78

20 BUILDINGS
20100 CONCRETE AND MASONRY BUILDINGS (By BUILDING)
20110 CONCRETE FOUNDATIONS
20110 CONCRETE FOUNDATIONS
CUM
EXCAVATION 5 5
LEAN CONCRETE LEVEL 5 10
FORMWORKS 23 33
REINFORCEMENT 28 61
EMBEDDED ITEMS 10 71
CASTING 18 89
FORMWORKS STRIPPING 5 94
BACKFILLING 5 99
FINAL CHECK 1 100

20115 CONCRETE STRUCTURE ELEVATIONS


20115 CONCRETE STRUCTURE ELEVATIONS
CUM
FORMWORKS 27 27
REINFORCEMENT 27 54
EMBEDDED ITEMS 15 69
CASTING 20 89
FORMWORKS STRIPPING 10 99
FINAL CHECK 1 100

20400 BUILDINGS Secondary Works (By BUILDING)


20401 CURTAIN AND PARTITION WALLS
20401 CURTAIN AND PARTITION WALLS
SQM
CHECK OF MATERIAL AT SITE BEFORE INSTALLATIO 10 10
WALLS ERECTION 30 40
INTERNAL PLASTERING AND / OR INSULATION LAYE 25 65
INTERNAL PAINTING 25 90
FINISHING WORKS 9 99
FINAL CHECK 1 100

20402 DOORS AND WINDOWS


20402 DOORS AND WINDOWS
U
CHECK OF MATERIAL AT SITE BEFORE INSTALLATIO 10 10
WINDOWS / DOORS INSTALLATION 45 55
ACCESSORIES INSTALLATION AND FINISHING WORKS 44 99
FINAL CHECK 1 100

20403 FLOORING
20403 FLOORING
SQM
CHECK OF MATERIAL AT SITE BEFORE INSTALLATIO 20 20
RAISED FLOOR INSTALLATION 40 60
CONCRETE FLOOR FINISHING 30 90
ACCESSORIES INSTALLATION AND FINAL CLEANING 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 54/78

20404 CEILING
20404 CEILING
SQM
CHECK OF MATERIAL AT SITE BEFORE INSTALLATIO 10 10
PLASTERING OR FALSE CEILING 40 50
PAINTING 30 80
FINISHING WORKS AND CLEANING 19 99
FINAL CHECK 1 100

20406 PLUMBING
20406 PLUMBING
U
WATER NETWORK 60 60
FIXTURES INSTALLATION 30 90
FINISHING WORKS/TESTS 9 99
FINAL CHECK 1 100

20407 CURTAIN WALL EXTERNAL PAINTING


20407 EXTERNAL PLASTERING AND PAINTING
SQM
PLASTERING 50 50
PAINTING 40 90
TOUCHUP 9 99
FINAL CHECK 1 100

20411 HVAC SYSTEM


20411 HVAC SYSTEM
U
DUCTS INSTALLATION 30 30
EQUIPMENT INSTALLATION 20 50
PIPING INSTALLATION 20 70
ELECTRICAL INSTALLATION 15 85
INSTRUMENT INSTALLATION 10 95
FUNCTIONAL TESTS 4 99
FINAL CHECK 1 100

20421 POWER AND LIGHTING


20421 POWER AND LIGHTING
U
CHECK OF MATERIAL AT SITE BEFORE INSTALLATIO 10 10
CABLE PULLING 30 40
LIGHTING FIXTURES INSTALLATION 20 60
OUTLETS & SWITCHES INSTALLATION 20 80
PANEL INSTALLATION 15 95
CHECK & TESTING 4 99
FINAL CHECK 1 100

20430 ELEVATORS
20430 ELEVATORS
U
TEMPLATES SETTING 2 2
BRACKETS INSTALLATION 15 17
GUIDERAILS INSTALLATION 15 32
EXTERNAL LANDING DOOR INSTALLATION 5 37
ELECTRICAL WORKS 20 57

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 55/78

SHAFT MECHANICAL DEVICES INSTALLATION 10 67


MACHINE ROOM ACCESSORY DEVICES INSTALLATIO 15 82
LIFT CAR ASSEMBLY 12 94
HOISTING CABLES INSTALLATION 5 99
FINAL CHECK 1 100

20440 COMMUNICATION/SECURITY SYSTEMS


20440 COMMUNICATION/SECURITY SYSTEMS
U
CHECK OF MATERIAL AT SITE BEFORE INSTALLATIO 10 10
CABLE PULLING 50 60
EQUIPMENT INSTALLATION (COMMUNICATION AND S 30 90
CHECKS AND TESTING 9 99
FINAL CHECK 1 100

20452 FIRE FIGHTING SYSTEM


20452 FIRE FIGHTING SYSTEM
U
MATERIAL AT SITE 5 5
PIPING PREFABRICATION & INSTAL. 35 40
PIPING PAINTING 20 60
SPRINKLER INSTALLATION 20 80
FUNCTIONAL TEST 19 99
FINAL CHECK 1 100

20460 TRANSFORMER YARDS U


CONCRETE FOUNDATIONS 35 35
CONCRETE SLABS AND WALLS 30 65
STEEL STRUCTURES ERECTION 15 80
GALVANISED STEEL MESH FENCE, SHEET ROOFING 14 94
GRAVEL FINISHING & FINAL VISUAL INSPECTION 4 98
FINAL CHECK 2 100

20600R BUILDINGS REVAMPING


20600R BUILDINGS REVAMPING

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 56/78

22 INSULATION
22100 EQUIPMENT INSULATION WORKS
22110 EQUIPMENT HOT INSULATION
22110 EQUIPMENT HOT INSULATION
SQM
JACKETING PREFABRICATION (INCL.STEEL SHEET) 10 10
INSULATING MATERIAL INSTALLATION (INCL. SCAFF 40 50
JACKETING INSTALLATION (INCL.SHEETING) 30 80
MISCELLANEOUS FINISHING WORKS (INCL.SCAFFOL 19 99
FINAL CHECK 1 100

22120 EQUIPMENT COLD INSULATION


22120 EQUIPMENT COLD INSULATION
SQM
PREFABRICATION 20 20
SCAFFOLDING ERECTION 10 30
INSULATING LAYER INSTALLATION 15 45
VAPOR BARRIER 20 65
SHEETING INSTALLATION 20 85
FINAL INSPECTION 5 90
SCAFFOLDING DISMANTLING 9 99
FINAL CHECK 1 100

22200 PIPING INSULATION WORKS


22210 PIPING HOT INSULATION
22210 PIPING HOT INSULATION
SQM
JACKETING PREFABRICATION (INCL STEEL SHEET) 10 10
INSULATING MATERIAL INSTALLATION (INCL. SCAFF 40 50
JACKETING INSTALLATION (INCL. SHEETING) 30 80
MISCELLANEOUS FINISHING WORKS (INCL SCAFFOL 19 99
FINAL CHECK 1 100

22211 PERSONNEL PROTECTION INSULATION (FOR PIPING)


22211 PERSONNEL PROTECTION INSULATION (FOR PIPING)
SQM
JACKETING PREFABRICATION 10 10
INSULATING MATERIAL INSTALLATION 40 50
JACKETING INSTALLATION 30 80
MISCELLANEOUS FINISHING WORK 19 99
FINAL CHECK 1 100

22212 PIPING ACOUSTIC INSULATION


22212 PIPING ACOUSTIC INSULATION
SQM
SCAFFOLDING ERECTION 15 15
INSULATING LAYER INSTALLATION 35 50
SHEETING INSTALLATION 30 80
MISCELLANEOUS FINISHING WORKS 5 85
FINAL INSPECTION 5 90
SCAFFOLDING DISMANTLING 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 57/78

22220 PIPING COLD INSULATION


22220 PIPING COLD INSULATION
SQM
PREFABRICATION 20 20
SCAFFOLDING ERECTION 10 30
INSULATING LAYER INSTALLATION 15 45
VAPOR BARRIER 20 65
SHEETING INSTALLATION 20 85
FINAL INSPECTION 5 90
SCAFFOLDING DISMANTLING 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 58/78

23 PAINTING
23100 STEEL STRUCTURES PAINTING WORKS
23110 STEEL STRUCT. PAINTING IN FIELD
23110 STEEL STRUCT. PAINTING IN FIELD (2 COATS)
SQM
INTERMEDIATE CHECK 35 35
FINAL COATINGS CHECK 35 70
IDENTIFICATION MARKING 15 85
CLEANING & FINAL TOUCHUPS 14 99
FINAL CHECK 1 100

23200 PIPING PAINTING WORKS


23201 PIPING PAINTING
23201 PIPING PAINTING (2+2 COATS)
SQM
SANDBLASING CHECK 22 22
PRIMER CHECK 15 37
INTERMEDIATE CHECK 22 59
FINAL COATINGS CHECK 22 81
IDENTIFICATION MARKING 5 86
CLEANING AND FINAL TOUCHUPS 13 99
FINAL CHECK 1 100

23202 PIPING PAINTING IN SHOP


23202 PIPING PAINTING IN SHOP (2 COATS)
SQM
SANDBLASING CHECK 50 50
PRIMER CHECK 25 75
INTERMEDIATE CHECK 24 99
FINAL CHECK 1 100

23203 PIPING PAINTING IN FIELD


23203 PIPING PAINTING IN FIELD (2 COATS)
SQM
INTERMEDIATE CHECK 35 35
FINAL COATINGS CHECK 35 70
IDENTIFICATION MARKING 15 85
CLEANING AND FINAL TOUCHUPS 14 99
FINAL CHECK 1 100

23210 SUPPORT PAINTING


23211 SUPPORT PAINTING
SQM
SANDBLASING CHECK 50 50
PRIMER CHECK 25 75
INTERMEDIATE CHECK 24 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 59/78

23400 EQUIPMENT PAINTING WORKS


23410 EQUIPMENT PAINTING
23411 EQUIPMENT PAINTING (2 COATS)
SQM
INTERMEDIATE CHECK 35 35
FINAL COATINGS CHECK 35 70
IDENTIFICATION MARKING 15 85
CLEANING & FINAL TOUCHUPS 14 99
FINAL CHECK 1 100

23412 EQUIPMENT PAINTING (FINAL COAT)


SQM
INTERMEDIATE CHECK 35 35
FINAL COATINGS CHECK 35 70
IDENTIFICATION MARKING 15 85
CLEANING & FINAL TOUCHUPS 14 99
FINAL CHECK 1 100

23500 PAINTING REVAMPING


23500 PAINTING REVAMPING

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 60/78

25 STORAGE TANK & SPHERES


25200 STEEL TANKS
25200 STEEL TANKS (By TANK)
25210 FIXED ROOF TANKS
TONS
CHECK LAYOUT AND FITUP OF FLOOR PLATES 6 8
WELDS VISUAL EXAMINATION 8 14
VACUUM BOX TEST OF BASE PLATES JOINTS 4 18
FITUP OF VERTICAL & ORIZONTAL SHELL JOINTS 20 38
WELDS XRAY EXAMINATION 27 65
LAYOUT AND FITUP OF ROOF PLATES 10 75
VACUUM BOX TEST OF ROOF PLATES JOINTS 8 83
FIXED ROOF INSTALLATION FINAL CHECK 8 91
ACCESSORIES INSTALLATION & FINAL CHECK PRIOR 3 94
WATERFILLING AND EQUIPMENT PRESSURE TEST 3 97
SETTLEMENT INSPECTION 2 99
FINAL CHECK 1 100

25220 FLOATING ROOF TANKS


TONS
CHECK LAYOUT AND FITUP OF FLOOR PLATES 8 8
VACUUM BOX TEST OF BASE PLATES JOINTS 10 18
FITUP OF VERTICAL & ORIZONTAL SHELL JOINTS 20 38
WELDS XRAY EXAMINATION 27 65
LAYOUT AND FITUP OF DECK AND PONTOON PLATE 10 75
VACUUM BOX TEST OF DECK SEAMS 7 82
VACUUM BOX TEST FOR PONTOON SEAMS 7 89
FLOATING ROOF INSTALLATION FINAL CHECK 2 91
ACCESSORIES INSTALLATION & FINAL CHECK PRIOR 3 94
WATERFILLING AND EQUIPMENT PRESSURE TEST 3 97
SETTLEMENT INSPECTION 2 99
FINAL CHECK 1 100

25400 SPHERES
25410 SPHERES (By SPHERE)
25410 SPHERES
TONS
ERECTION 30 30
MERIDIAN/VERTICAL WELDS 30 60
EQUATORIAL/CIRCUMFERENT. WELDS 10 70
XRAYS 20 90
CLEANINC, TESTING 10 100

25500 CRYOGENIC TANKS


25510 DOUBLE WALL TANKS (By TANK)
25510 DOUBLE WALL TANKS
TONS
OUTER TANK BOTTOM PLATES 8 8
OUTER TANK SHELL PLATES 25 33
OUTER TANK ROOF PLATES 11 44
INNER TANK BOTTOM PLATES 10 54
INNER TANK SHELL PLATES 22 76
INNER TANK ROOF PLATES 12 88
NOZZELS, SUPPORTS, LADDERS, STAIRS, PLATFOR 6 94
HYDROTEST 5 99
FINAL INSPECTION 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 61/78

25600 SILOS
25610 SILOS
25610 SILOS
TONS
STEEL STRUCTURE ERECTION 15 15
SECONDARY STEEL STRUCTURE ERECTION 5 20
FINISHED WELD VISUAL CHECK (SUPPORTING RING A 5 25
FINISHED WELD VISUAL CHECK (ROOF) 5 30
FINISHED WELD VISUAL CHECK (CYLINDER PART) 15 45
FINISHED WELD VISUAL CHECK (ROOF TO CYLINDER 15 60
FINISHED WELD VISUAL INSPECTION (UPPER SECTIO 15 75
PT(10% OF FILLET WELDS) 7 82
RT(10% OF LONG. & CIRC. JOINTS,100% OF T JOINT 7 89
HYDROSTATIC TEST 5 94
ACCESSORIES INSTALLATION 5 99
FINAL CHECK 1 100

25700 STORAGE TANKS AND SILOS REVAMPING


25700 STORAGE TANKS AND SILOS REVAMPING

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 62/78

68 MECHANICAL ERECTION
68100 HEAVY LIFTS
68110 ITEMS IN ONE PIECE
68110 ITEMS IN ONE PIECE
TONS
EQUI. ERECTION ON FOUNDATION 60 60
ANCHOR BOLTS THIGHTENING BEFORE GROUTING 30 90
INSIDE VISUAL INSPECTION 9 99
FINAL CHECK 1 100

68130 ITEMS IN SEVERAL PIECES

68200 STATIC EQUIPMENT ERECTION


68210 VERTICAL AND HORIZONTAL VESSELS/EXCHANGERS
68210 VERTICAL AND HORIZONTAL VESSELS/EXCHANGERS
TONS
EQUI. ERECTION ON FOUNDATION 60 60
ANCHOR BOLTS THIGHTENING BEFORE GROUTING 30 90
INSIDE VISUAL INSPECTION 9 99
FINAL CHECK 1 100

68300 FIRED EQUIPMENT


68311 PRE-ASSEMBLED FOURNACES

68312 A STEEL STRUCTURES (PRIMARY & SECONDARY)


68312A STEEL STRUCTURES (PRIMARY & SECONDARY) (25% )
TONS
PLATFORMS & LADDERS FOR RADIANT INSTALLATIO 60 60
PLATFORMS AND LADDERS FOR CONVECTION INSTA 30 90
PLATFORMS & LADDERS FOR STACK INSTALLATION 9 99
FINAL CHECK 1 100

68312 B RADIANT PANELS


68312B RADIANT PANELS (15% )
TONS
WALL PANELS POSITIONING, ELEVATION & VERTICAL 40 40
FLOOR PANELS POSITIONING & HORIZONTALITY 25 65
BOLTS TIGHTENING 20 85
ANCHOR BOLTS TIGHTENING 14 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 63/78

68312 C CONVECTION MODULES


68312C CONVECTION MODULES (3% )
TONS
CONVECTION MODULES POSITIONING & PLUMBNESS 50 50
BREECHING SECTION POSITIONING & HORIZONTALIT 20 70
BOLTS TIGHTENING 29 99
FINAL CHECK 1 100

68312 D STACKS & DUCTS


68312D STACKS & DUCTS (12% )
TONS
LOWER SECTION POSITIONING & VERTICALITY 20 20
DAMPER POSITIONING 3 23
INTERMEDIATE AND UPPER SECTION POSITIONING & 25 48
BOLTS TIGHTENING 10 58
HOT FLUE GAS DUCTS FROM STACK TO APH POSIT 7 65
DUCT FROM APH TO F.G. FAN POSITIONING 7 72
FIRST SECTION OF COLD FLUE GAS DUCT INSTALLA 7 79
COLD FLUE GAS DUCTS TO STACK & DUCT FROM F 7 87
AIR DUCTS FROM AIR FANS UP TO APH POSITIONING 7 93
HOT AIR DUCT SYSTEM FROM APH TO BURNERS PO 6 99
FINAL CHECK 1 100

68312 E FURNACES TUBES


68312E FURNACES TUBES (20% )
TONS
RADIANT COILS POSITIONING & VERTICALITY 12 12
RADIANT COILS POSITIONING & HORIZONTALITY 13 25
POSITIONING OF RADIANT COILS SUPPORTS PINS & 5 30
REFRACTORY LINING GAP FILLED WITH CRAMIC FIBE 5 35
BOLTS TIGHTENING 5 40
POSITIONING & SUPPORTING OF PIPES 25 65
WELDING, PWHT & NDT OF PIPES 30 95
COILS/EXTERNAL PIPES HYDROTEST 4 99
FINAL CHECK 1 100

68312 F ACCESSORY (FAN, BURNERS, STEAM DRUM, TLE'S, DESUPERHEATER)


68312F ACCESSORY (FAN, BURNERS, STEAM DRUM, TLES, DESUPERHEATER)(5% )
TONS
ACCESSORIES OF RADIANT, CONVECTION, STACK & 15 15
BURNERS INSTALLATION 35 50
APH & STEAM APH INSTALLATION 15 65
FLUE GAS FAN INSTALLATION 15 80
AIR FANS INSTALLATION 15 95
AIR INTAKE INSTALLATION 4 99
FINAL CHECK 1 100

68312 G FURNACES REFRACTORY


68312G FURNACES REFRACTORY (20% )
SQM
REFRACTORY LINING ON FLOOR RADIANT SECTION 15 15
CASTABLE REFRACTORY INSTALLATION 35 60
REFRACTORY BRICKS INSTALLATION 49 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 64/78

68320 BOILERS
68321 PREASSEMBLED BOILERS
TONS
ERECTION ON FOUNDATION 50 50
LEVELLING, PLUMB ADJUSTMENT, BOLT TIGHTENING 30 80
FINAL INSPECTION 20 100

68322 PARTIALLY PREASSEMBLED BOILERS


TONS
SHELL ASSEMBLY & WELDING/BOLTING 20 20
REFRACTORY PANELS/MATER. ERECT. 15 35
COILS WELDING & ERECTION 20 55
INSTALLATION ON FOUNDATION 10 65
STACK AND FLUE DUCTS WELD./BOLT 15 80
ACCESSORIES & STRUCTURES ERECT. 10 90
XRAY EXAMINATION 8 98
FINAL ALIGNMENT, FINAL INSPECTION 2 100

68330 FLARES
68330 FLARES
TONS
MODULE 1 ERECTION 25 25
MODULE 2 ERECTION 25 50
STAIRS ERECTION 4 54
WINCHS ERECTION 3 57
LIFTING SECTION 2 & BOLTING TO SECTION 1 10 67
LIFTING SECTION 4 & BOLTING TO SECTION 3 AND T 20 87
ACCESSORIES ERECTION 7 94
FINAL VISUAL CHECK 5 99
FINAL CHECK 1 100

68340 STACKS
68340 STACKS
TONS
STACK ERECTION 60 60
ALIGNMENT 20 80
ACCESSORIES 10 90
CHECKS 10 100

68350 REFRACTORY WORKS


68351 CASTABLE REFRACTORY INSTALLATION
TONS
MUFFLE BLOCKS ON FLOOR PANELS INSTALLATION 20 20
FIRST LAYER OF CONCRETE REFRACTORY PLACEM 40 60
SECOND LAYER OF CONCRETE REFRACTORY PLAC 30 90
FINAL VISUAL INSPECTION 9 99
FINAL CHECK 1 100

68352 REFRACTORY BRICKS INSTALLATION


TONS
SURFACE VISUAL INSPECTION 10 10
BRICKS INSTALLATION 80 90
FINAL VISUAL INSPECTION 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 65/78

68390 FLUE GAS STEAM GENERATOR

68500 MACHINERY ERECTION


68520 FANS & BLOWERS
68521 FANS & BLOWERS (BELT DRIVE)
TONS
POSITIONING & PLANT AXES 30 30
ELEVATION AND LEVELING 5 35
ANCHOR BOLTS PRETIGHTENING 5 40
FINAL ANCHOR BOLTS TIGHTENING 10 50
PULLEYS, PARALLELISM & DISTANCE 20 70
IMPELLER CLEARANCE 9 79
CHECK OF ACCESSORIES 20 99
FINAL CHECK 1 100

68527 FANS & BLOWERS (SHAFT DRIVE)


TONS
POSITIONING & PLANT AXES 30 30
ELEVATION AND LEVELING 5 35
ANCHOR BOLTS PRETIGHTENING 5 40
FINAL ANCHOR BOLTS TIGHTENING 10 50
FLANGE PARALLELISM 10 60
FINAL ALIGNMENT 10 70
IMPELLER CLEARANCE 9 79
CHECK OF ACCESSORIES 20 99
FINAL CHECK 1 100

68522 HORIZONTAL/VERTICAL PUMPS AND DRIVE


68523 HORIZONTAL PUMPS AND DRIVE
TONS
POSITIONING AND PLANT AXES 30 30
FINAL ANCHOR BOLTS TIGHTENING 20 50
FLANGE PARALLELISM BEFORE HYDROTEST 15 65
FINAL ALIGNEMENT (FREE AND FLANGED) 15 80
AUXILIARY PIPING INSTALLATION CHECK 19 99
FINAL CHECK 1 100

68528 VERTICAL, IN LINE, DOSING PUMPS AND DRIVE


TONS
POSITIONING AND PLANT AXES 30 30
FINAL ANCHOR BOLTS TIGHTENING 20 50
FLANGE PARALLELISM BEFORE HYDROTEST 15 65
FINAL ALIGNEMENT (FREE AND FLANGED) 15 80
AUXILIARY PIPING INSTALLATION CHECK 19 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 66/78

68524 RECIPROCATING COMPRESSORS AND DRIVE


68524 RECIPROCATING COMPRESSORS AND DRIVE
TONS
CRANK CASE INSTALLATION 20 20
PRELIMINARY CYLINDER INSTALLATION 10 30
CRANK CASE AND CYLINDER POSITIONING & PLANT 10 40
ANCHOR BOLTS PRETIGHTENING 5 45
CLEANING AND INSTALLATION OF CYLINDER SUCTIO 10 55
MOTOR INSTALLATION & POSITIONING 15 70
FINAL ANCHOR BOLTS TIGHTENING 5 75
INSTALLATION OF ACCESSORIES 10 85
FLANGES PARALLELISM 4 89
FINAL ALIGNMENT (FREE & FLANGED) 10 99
FINAL CHECK 1 100

68525 CENTRIFUGAL COMPRESSORS AND DRIVE


68525 CENTRIFUGAL COMPRESSORS AND DRIVE
TONS
COMPRESSOR INSTALLATION 30 30
ELEVATION AND LEVELLING 5 35
DRIVER INSTALLATION 20 55
ANCHOR BOLTS PRETIGHTENING 5 60
FINAL ANCHOR BOLTS TIGHTENING 10 70
INSTALLATION OF ACCESSORIES 15 85
FLANGES PARALLELISM 4 89
FINAL ALIGNMENT (FREE & FLANGED) 10 99
FINAL CHECK 1 100

68526 MIXERS AND AGITATORS


68526 MIXERS AND AGITATORS
TONS
MACHINERY INSTALLATION 20 20
SHAFT VERTICALITY 20 40
BLADE INSTALLATION 20 60
MOTOR INSTALLATION 20 80
ACCESSORIES INSTALLATION & FINAL BOLT TIGHTEN 15 95
ALIGNMENT 4 99
FINAL CHECK 1 100

68600 EQUIPMENT INTERNALS INSTALLATION


68610 TRAYS & INTERNALS INSTALLATION
68611 TRAYS
TONS
TRANSPORT TO JOBSITE 10 10
TRAYS FIRST PORTION INSTALLATION 20 30
TRAYS SECOND PORTION INSTALLATION 20 50
TRAYS THIRD PORTION INSTALLATION 15 65
TRAYS FOURTH PORTION INSTALLATION 15 80
CLEANING 19 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 67/78

68612 DISTRIBUTORS, GRIDS, DEMISTERS, ETC.


TONS
TRANSPORT AT JOBSITE 10 10
INTERNALS INSTALLATION 70 80
CLEANING 19 99
FINAL CHECK 1 100

68620 FILLING MATERIALS ( CATALYST & PACKING )


68620 FILLING MATERIALS ( CATALYST & PACKING )
TONS
TO DETAIL IF ANY 100 100

68700 AIR COOLERS AND COOLING TOWERS


68710 AIR COOLERS ERECTION
68710 AIR COOLERS ERECTION
TONS
MATERIAL IDENTIFICATION/SELECTION 4 4
MAIN FRAME PREASSEMBLY 10 14
PLENUM CHAMBER (AIRHOOD) ERECTION 6 20
BUNDLE INSTALLATION 13 33
LOUVERS, PLATFORMS AND LADDERS INSTALLATION 6 39
WINTERIZATION 6 45
CHECK AND STRUCTURE ERECTION AUTHORIZATIO 2 47
STRUCTURE ERECTION 15 62
FAN/MOTOR INSTALLATION 25 87
FAN/MOTOR ALIGNMENT 12 99
FINAL CHECK 1 100

68720 COOLING TOWERS ERECTION


68720 COOLING TOWERS ERECTION
TONS
LADDERS AND PLATFORM INSTALLATION 10 10
DISPERSION SYS: INSTALLATION 20 30
DISTRIBUTION SYS: PREASSEMBLY AT GROUND 5 35
DISTRIBUTION SYS: INSTALLATION 10 45
DRIFT ELIMINATOR SYS: PREASSEMBLY AT GROUND 5 50
DRIFT ELIMINATOR SYS: INSTALLATION 10 60
MACHINERY INSTALLATION 10 70
FAN: STACK SECTIONS INST. AND FIRST TIGHTENIN 15 85
FAN: STACK VERTICALITY & STACKBLADE GAP CHEC 4 89
FAN: FINAL THIGTENING 5 94
ACCESSORIES INSTALLATION 5 99
FINAL CHECK 1 100

68800 PACKAGE AND MISCELLANEOUS ERECTION


68810 SKID MOUNTED PACKAGES & MISC.
68810 SKID MOUNTED PACKAGES
TONS
SKID INSTALLATION ON FOUNDATION 30 30
ELEVATION & ORIENTATION 15 45
ANCHOR BOLTS TIGHTENING 15 60
DISASSEMBLED PARTS ERECTION 20 80
MACHINERY ALIGNMENT 10 90
EQUIPMENT VERTICALITY 9 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 68/78

68811 MISCELLANEOUS
TONS
SKID INSTALLATION ON FOUNDATION 30 30
ELEVATION & ORIENTATION 15 45
ANCHOR BOLTS TIGHTENING 15 60
DISASSEMBLED PARTS ERECTION 20 80
MACHINERY ALIGNMENT 10 90
EQUIPMENT VERTICALITY 9 99
FINAL CHECK 1 100

68812 ELEVATORS
U
TEMPLATES SETTING 2 2
BRACKETS INSTALLATION 15 17
GUIDERAILS INSTALLATION 15 32
EXTERNAL LANDING DOOR INSTALLATION 5 37
ELECTRICAL WORKS 20 57
SHAFT MECHANICAL DEVICES INSTALLATION 10 67
MACHINE ROOM ACCESSORY DEVICES INSTALLATIO 15 82
LIFT CAR ASSEMBLY 12 94
HOISTING CABLES INSTALLATION 5 99
FINAL CHECK 1 100

68820 BRIDGE CRANE


68820 BRIDGE CRANE
TONS
RAILS PREFIXING 20 20
PREASSEMBLED TRUCKKS AND GRIDER 10 30
BRIDGE CRANE LIFTING AND SETTING 15 45
TROLLEY INSTALLATION 10 55
SECONDARY EQUIPMENT INSTALLATION 10 65
FINAL INSPECTION FOR MECHANICAL WORKS 5 70
CABLES AND FESTOON INSTALLATION 10 80
ELECTRICAL CONNECTIONS 5 85
FINAL INSPECTION OF THE ASSEMBLY 5 90
FINAL TEST 9 99
FINAL CHECK 1 100

68900 MECHANICAL ERECTION REVAMPING


68900 MECHANICAL ERECTION REVAMPING

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 69/78

90 PRECOMMISSIONING
9000 PRECOMMISIONING
1300 P PRECOMMISSIONING PIPING
PRP1 GENERAL
KG
CIRCUIT PREPARATION 10 10
FLUSHING / BLOWING 35 45
SPRING HANGAR SETTING 10 55
REINSTATEMENT 5 60
DRYING 30 90
TIGHTNESS TEST 9 99
FINAL CHECK 1 100

PRP2 DEGREASING
KG
CIRCUIT PREPARATION 5 5
FLUSHING / BLOWING 30 35
SPRING HANGAR SETTING 5 40
DEGREASING 40 80
REINSTATEMENT 5 85
DRYING 10 95
TIGHTNESS TEST 4 99
FINAL CHECK 1 100

PRP3 CHEMICAL CLEANING


KG
CIRCUIT PREPARATION 5 5
FLUSHING / BLOWING 25 30
SPRING HANGAR SETTING 5 35
CHEMICAL CLEANING 45 80
REINSTATEMENT 5 85
DRYING 10 95
TIGHTNESS TEST 4 99
FINAL CHECK 1 100

PRP4 STEAM BLOWING 1


KG
CIRCUIT PREPARATION 5 5
FLUSHING / BLOWING 15 20
SPRING HANGAR SETTING 5 25
CHEMICAL CLEANING 20 45
STEAM BLOWING 35 80
REINSTATEMENT 5 85
DRYING 10 95
TIGHTNESS TEST 4 99
FINAL CHECK 1 100

PRP5 STEAM BLOWING 2


KG
CIRCUIT PREPARATION 5 5
FLUSHING / BLOWING 20 25
SPRING HANGAR SETTING 10 35
STEAM BLOWING 30 65

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 70/78

REINSTATEMENT 15 80
DRYING 10 90
TIGHTNESS TEST 9 99
FINAL CHECK 1 100

1500 P PRECOMMISSIONING INSTRUMENTS


PRI1 FIELD INSTRUMENTS
U
INSTALLATION COMPLETENESS & CORRECTNESS 35 35
PSV CALIBRATION 35 70
FLOW ORIFICE INSTALLATION 29 99
FINAL CHECK 1 100

PRI2 CONTROL PANELS


U
FIRE & GAS DETECTORS SYSTEM 99 99
FINAL CHECK 1 100

PRI3 LOOP CHECK


U
LOOP CHECK EXECUTION 99 99
FINAL CHECK 1 100

1600 P PRECOMMISSIONING ELECTRICAL


PRE1 TRANSFORMERS
U
PREENERGIZATION CHECKS 10 10
ENERGIZATION 60 70
POSTENERGIZATION CHECKS 29 99
FINAL CHECK 1 100

PRE10 VARIABLE FREQUENCY DRIVE


U
VARIABLE FREQUENCY DRIVE FUNCTIONAL TEST 99 99
FINAL CHECK 1 100

PRE11 CATHODIC PROTECTIONGALVANIC ANODE POTENTIAL SURVEY


U
GALVANIC ANODE POTENTIAL SURVEY 99 99
FINAL CHECK 1 100

PRE12 CATHODIC PROTECTIONIMPRESSED CURRENT ANODE POTENTIAL SURVEY


U
IMPRESSED CURRENT ANODE POTENTIAL SURVEY 99 99
FINAL CHECK 1 100

PRE13 ROTATING EQUIPMENTLUBRIFICATION,AIR GAP AND COUPLING ALIGNMENT


U
LUBRICATION 35 35
AIR GAP MEASUREMENT 35 70
COUPLING ALIGNMENT AND ROTOR SUPPORT 29 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 71/78

PRE14 ROTATING EQUIPMENTELECTRIC MOTOR PERFORMANCE TEST


U
PRELIMINARY CHECKS 50 50
FIRST START 49 99
FINAL CHECK 1 100

PRE2 TRANSFORMERS SOAK TEST


U
TRANSFORMER SOAK TEST 99 99
FINAL CHECK 100 100

PRE3A DOUBLE FED SWITCHGEARS


U
PREENERGIZATION CHECKS 5 5
ENERGIZATION BUSBAR A 20 25
POSTENERGIZATION CHECKS BUSBAR A 15 40
ENERGIZATION BUSBAR B 20 60
POSTENERGIZATION CHECKS BUSBAR B 20 80
PHASING CHECK 15 95
OTHER CHECKS 4 99
FINAL CHECK 1 100

PRE3B SINGLE FED SWITCHGEARS


U
PREENERGIZATION CHECKS 25 25
ENERGIZATION BUSBAR A 40 65
POSTENERGIZATION CHECKS BUSBAR A 34 99
FINAL CHECK 1 100

PRE4 MCC / DISTRIBUTION PANELS


U
PREENERGIZATION CHECKS 25 25
ENERGIZATION BUSBAR A 40 65
POSTENERGIZATION CHECKS BUSBAR A 34 99
FINAL CHECK 1 100

PRE5 EMERGENCY DISTRIBUTION


U
PRETRANSFER CHECKS 20 20
SYSTEM TEST 79 99
FINAL CHECK 1 100

PRE6 DIESEL GENSET


U
DIESEL GENSET LOAD BANK TEST 99 99
FINAL CHECK 1 100

PRE7 UPS
U
UPS FUNCTIONAL TEST 99 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 72/78

PRE8 DC SYSTEM
U
DC SYSTEM FUNCTIONAL TEST 99 99
FINAL CHECK 1 100

PRE9A BATTERIES CHARGE


U
BATTERIES CHARGE 99 99
FINAL CHECK 1 100

PRE9B BATTERIES DISCHARGE


U
BATTERIES DISCHARGE 99 99
FINAL CHECK 1 100

6800 P PRECOMMISSIONING MECHANICAL


PRM1 COLUMNS, VESSELS, DRUMS & REACTORS
TONS
FLUSHING / CLEANING 25 25
INTERNALS 40 65
DRYING 20 85
TIGHTNESS TEST 14 99
FINAL CHECK 1 100

PRM10 FILTERS
TONS
CLEANING 40 40
FILTER ELEMENTS CHECK 59 99
FINAL CHECK 1 100

PRM11 FURNACES
TONS
CLEANING & DRYING OF FURNACE COILS 30 30
CHECK REFRACTORY AND REPAIR IF NEEDED 30 60
CHECK BURNER NOZZLES 10 70
CHECK REGISTER & DAMPERS 10 80
CHECK SOOT BLOWERS 10 90
TIGHTNESS TEST 9 99
FINAL CHECK 1 100

PRM12 DIESEL ENGINES


TONS
CLEANING 10 10
OIL FILLING 30 40
FREE ROTATION BY HAND 10 50
ACCESSORIES 49 99
FINAL CHECK 1 100

PRM13 CHEMICAL DOSING SKID


TONS
DOSING TANK CLEANING 15 15
FREE ROTATION BY HAND 15 30
PRECHARGING PULSATION 15 45

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 73/78

STROKE ADJUSTEMENT 15 60
CALIBRATION POT AND PSV INSTALLATION 15 75
FINAL SERVICE TEST (H2O) 10 85
BOXIP 14 99
FINAL CHECK 1 100

PRM14 BRIDGE CRANE


TONS
MECHANICAL CHECKS 20 20
LUBRICATION 50 70
NO LOAD RUN 29 99
FINAL CHECK 1 100

PRM2 AIR FIN EXCHANGERS


TONS
FLUSHING / CLEANING 10 10
TIGHTNESS TEST 10 20
LUBE OIL FILLING 10 30
FREE ROTATION BY HAND 5 35
COUPLING / BELT INSTALLATION 5 40
GUARD AND ACCESSORIES 10 50
LOUVRES OPERABILITY 20 70
BLADES ANGLE CHECK 20 90
SAFETY OPERABILITY 9 99
FINAL CHECK 1 100

PRM3 PUMPS
TONS
CLEANING 15 15
AUXILIARIES CONNECTIONS 10 25
OIL FILLING 15 40
SEAL INSTALLATION 10 50
FREE ROTATION BY HAND 5 55
PUMP DRIVER ALIGNMENT 35 90
COUPLING INSTALLATION 9 99
FINAL CHECK 1 100

PRM4 CENTRIFUGAL COMPRESSORS


TONS
AUXILIARY CIRCUITS FLUSHING 5 5
LUBE / SEAL OIL FLUSHING 10 15
SEAL / BEARING INSTALLATION 5 20
OIL FILLING 5 25
OIL SYSTEM TEST 10 35
FREE ROTATION BY HAND 5 40
COMPRESSOR DRIVER ALIGNMENT 20 60
COUPLING INSTALLATION 5 65
GUARD AND ACCESSORIES 5 70
SUCTION STRAINER INSTALLATION 5 75
NO LOAD RUN 20 95
TIGHTNESS TEST 4 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 74/78

PRM5 RECIPROCATING COMPRESSORS


TONS
AUXILIARY CIRCUITS FLUSHING 10 10
LUBE / SEAL OIL FLUSHING 10 20
SEAL / BEARING INSTALLATION 5 25
OIL FILLING 5 30
OIL SYSTEM TEST 15 45
FREE ROTATION BY HAND 5 50
COUPLING INSTALLATION 5 55
GUARD AND ACCESSORIES 5 60
SUCTION STRAINER INSTALLATION 10 70
NO LOAD RUN 25 95
TIGHTNESS TEST 4 99
FINAL CHECK 1 100

PRM6 FANS AND BLOWERS


TONS
CLEANING 10 10
OIL FILLING 15 25
SEAL INSTALLATION 10 35
FREE ROTATION BY HAND 5 40
DRIVER ALIGNMENT 30 70
COUPLING INSTALLATION 10 80
GUARD AND ACCESSORIES 10 90
SUCTION STRAINER INSTALLATION 9 99
FINAL CHECK 1 100

PRM7 STEAM TURBINES


TONS
AUXILIARY CIRCUITS FLUSHING 10 10
LUBE / SEAL OIL FLUSHING 15 25
BEARING INSTALLATION 15 40
LABYRINTH / PACKING INSTALLATION 5 45
OIL FILLING 5 50
OIL SYSTEM TEST 10 60
FREE ROTATION BY HAND 5 65
DIRECTION OF ROTATION 5 70
COUPLING INSTALLATION 10 80
SUCTION STRAINER INSTALLATION 10 90
GUARD AND ACCESSORIES 9 99
FINAL CHECK 1 100

PRM8 HEAT EXCHANGERS


TONS
FLUSHING / CLEANING 70 70
TIGHTNESS TEST 29 99
FINAL CHECK 1 100

PRM9 EJECTORS
TONS
CLEANING 60 60
CLOSE UP 10 70
TIGHTNESS TEST 29 99
FINAL CHECK 1 100

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 75/78

ATTACHMENT 2:

TYPICAL JOBSITE BREAKDOWN STRUCTURE

The following illustrates the typical breakdown structure to be implemented for the follow-up and
monitoring of the physical progress of the works.

JOBSITE BREAKDOWN
SITE JOBSITE WEIGHTING SYSTEM
JOBSITE
LEVEL
= 100% productive manhours

AREA AREA
AREA A
A AREA
AREA B
B = 100% of site productive
45% 55% manhours

= 100% of area
UNIT
UNIT 11 UNIT
UNIT 22 UNIT
UNIT 33 UNIT
UNIT 44 UNIT
UNIT 55 UNIT
UNIT 66
UNIT productive
42% 28% 30% 25% 48% 27% manhours

CIVIL
CIVIL
DISCIPLINE WORKS
PIPING
PIPING MECHANICAL
MECHANICAL ELECTRICAL
ELECTRICAL INSTRUMENT.
INSTRUMENT. PAINTING
PAINTING = 100% of unit
WORKS
28% 38% 7% 5%
productive
14% 8%
manhours
WORK SMALL
SMALL
FOUNDATIONS
FOUNDATIONS FOUND.
STRUCTURE
STRUCTURE DUCTS
DUCTS PITS
PITS PAVING
PAVING = 100% of discipline
CLASSE FOUND.
35% 0% 9% 15% productive
32% 4%
manhours

ITEM C
C 01
01 C
C 02
02 C
C 03
03 B
B 01
01 B
B 02A
02A B
B 02B
02B = 100% of T. o. W.
20% 25% 12% 12%
productive manhours
15% 16%

ANCHOR
ANCHOR CONCRETE
CONCRETE FINISHING
FINISHING
WORKSTEP EXCAVATION
EXCAVATION FORMWORKS
FORMWORKS REINFORCEMENT
REINFORCEMENT BOLTS
BOLTS POURING
POURING WORKS
WORKS
= 100% of the item
15% 15% 30% 10% 20% 10%

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 76/78

ATTACHMENT 3:

EASY PLANT SMC SOFTWARE FUNCTIONALITIES

The following illustrates SMC functionalities that are possible for the reporting and monitoring of the
construction progress.

As it is shown in the home page, SMC offers several Modules though which it is
Possible to manage the different information and activities, in order to have a complete
view of the status of the Project.

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 77/78

Here below in particular, are shown as example, three different charts about Progress
Management:

SMC Civil Works Overall Manpower Productivity Chart

SMC Civil Works Overall Site Progress Chart

PP 1 - ANG - rev. 2
ALGIERS REFINERY
REHABILITATION AND ADAPTATION PROJECT

CONSTRUCTION PROGRESS MEASUREMENT

Document Class : CLASS 1 Project N° - Unit Doc Type Serial Number Rev. Page

9952T-0000 PP 0807 0 78/78

SMC Detailed Construction Progress by Tag (C3 Level)

PP 1 - ANG - rev. 2