Inter-company transmittal
Brunei Shell Petroleum
Project: MPX2 Facility Rejuvenation
Transmittal: MPX-EXT-D-T-AFW-00252
Issue date: 26-03-2021
Transmittal to
Amec Foster Wheeler
For attention of Norziah Dullah
Plaza Sutera Biru, Level 1 & 5,
Lot 73, Jalan Sungai,
Kuala Belait KA 2331
Resp.Eng:
Remarks:
Reference: BSP-1000-D-0452
Condition: -
Documents
Doc. No. of Media Issue Appr.
Document Rev. Title status copies size code code Due before
1000-373-0000-PLN-046 01 WOOD - NUQUEST INSPECTION TEST PLAN IFC 1 A A 15-04-2021
(ITP) FOR PIPING
1000-373-0000-PLN-047 01 WOOD - NUQUEST INSPECTION TEST PLAN IFC 1 A A 15-04-2021
(ITP) FOR STRUCTURAL
1000-373-0000-PLN-048 01 WOOD - NUQUEST INSPECTION TEST PLAN IFC 1 A A 15-04-2021
(ITP) FOR BLASTING AND PAINTING
Legend
Issue code(s) :
A Is correct, no comment added. Move to next review cycle
Status code(s) :
IFC Issued for Comments (IFC)
Approval code(s) :
A Is correct, no comment added. Move to next review cycle
If applicable, please resubmit documents before due date
Please sign a copy of this transmittal and return by mail as acknowledgement of receipt
Raised by: Nur Fatin 'Aqilah Serudin Date signed:
Project document control Signed for receipt:
Brunei Shell Petroleum, Seria KB3534, Negara Brunei Darussalam, (Brunei) Page 1 of 1
Facility Rejuvenation
Transmittal Number: MPX-EXT-D-T-AFW-00252
Responsible Engineer: Raimin Abdul Rahim
MPX-AFW-GEN-QA-5798-0072 01 WOOD - NUQUEST INSPECTION TEST PLAN (ITP) FOR
STRUCTURAL
Section Comments
0 No comment
MPX-AFW-GEN-QA-5798-0073 01 WOOD - NUQUEST INSPECTION TEST PLAN (ITP) FOR
BLASTING AND PAINTING
Section Comments
0 No comment
MPX-AFW-GEN-QA-5798-0074 01 WOOD - NUQUEST INSPECTION TEST PLAN (ITP) FOR
PIPING
Section Comments
0 No comment
Wood Doc No: 1000-373-0000-PLN-046
Contract No:14021000 Revision:R1
Brunei Shell Petroleum Doc No:
MPX-AFW-GEN-QA-5798-0071 Revision: 01
Contract Title
Brunei Shell Petroleum
Facilities Rejuvenation Contract
Document Title
WOOD - NUQUEST
INSPECTION TEST PLAN (ITP) FOR PIPING
01 R1 Issued for Comment TM 05.03.21 RJ 05.03.21 TC 05.03.21
BSP WOOD Origin Chkd Appd Appd
Issue or Revision Description Date Date Date Date
Rev Rev By By By By
BSP / WOOD WOOD CLIENT
PAGE
Page 1 of 7
AMEC FOSTER WHEELER (B) SDN BHD
NuQuest Sdn. Bhd.
CONTRACT TITLE : PROVISION OF ONSHORE ONLY FABRICATION SERVICES
PROJECT NUMBER : BSP-SCR-060
CLIENT : AMEC FOSTER WHEELER (B) SDN BHD
DOCUMENT TITLE : INSPECTION TEST PLAN - PIPING
DOCUMENT NUMBER : ITP - 001
DR MCG SYA
2 03/03/2021 Issued for approval
1 08/07/2020 Issued for Approval
0 13/05/2020 Issue for Review
ISSUED CHK’D APPR’D CHK’D APPR’D DATE
REV DATE DESCRIPTION
NuQuest WOOD PLC
DOC NO. ITP-001
REV. NO. 2
INSPECTION TEST PLAN - Page 2 of 7
PIPING
REVISION OF RECORD
REV. SECTION REVISION OF DESCRIPTION
Deletion of relevant specifications and additions of requirements as per
1 Various
Client
2 All Inclusion of Hold Point “ H” on all NQSB Inspection Activities
NuQuest Sdn Bhd
INSPECTION TEST PLAN – PIPING
CONTRACT TITLE : PROVISION OF ONSHORE ONLY FABRICATION SERVICES Document No.: ITP-001
PROJECT NUMBER : BSP-SCR-060 Revision: 2
CLIENT : AMEC FOSTER WHEELER (B) SDN BHD
CONSTRUCTION QUALITY CONTROL RESPONSIBLE CONTROL VERIFYING INSPECTION PARTY
No. FREQUENCY
ACTIVITY ACTIVITY PARTY DOCUMENT DOCUMENT NQSB WOOD BSP
Ensure approved
WPS, PQR,
Welding Procedure WPS in use/ weather Approved WPS,
1.1 NQSB 100% Mech.Test H W/H/R W/H/R
Qualification Test (PQR) protection/ preheat BSP.12.S.601
Result
temp.
Ensure Weld
prep./Material/Welding
technique/ Record BSP.12.S.601, WPS, PQR,
Welding Procedure
1.2 Parameter/ Final NQSB 100% Approved WPS, ASME Mech.Test H R R
Specification (WPS)
Visual/NDT/Mech test IX/ ANSI B31.3 Result
result as per approved
WPS.
Ensure Joint
prep./Material/Welding
Welder Cert/ I.D
technique/ Visual BSP.12.S.601,
/ Welder
1.3 Welder Qualification Test root/Check NQSB 100% Approved WPS, ASME H W/R W/R
Register/NDT
Parameter/ Final IX/ ANSI B31.3
Report
Visual/NDT/Mech test
result.
Purchase Order,
Identification of
Material Receiving, Delivery order,
dimension, quantity,
inspection & ASTM Material Ref,NQ- Heat no, Material
1.4 condition, type of NQSB 100% H M M
storage(Inclusive of welding 060-OPS-004 receiving
material, grade and
consumable) inspection
size.
report(MRIR)
NOTE:
W = Witness Point R = Review WOOD = Amec Foster Wheeler (B) Sdn Bhd BSP = Brunei Shell Petroleum Company Sdn Bhd
H = Hold Point M = Monitoring NQSB = NuQuest Sdn Bhd
NuQuest Sdn Bhd
INSPECTION TEST PLAN – PIPING
CONTRACT TITLE : PROVISION OF ONSHORE ONLY FABRICATION SERVICES Document No.: ITP-001
PROJECT NUMBER : BSP-SCR-060 Revision: 2
CLIENT : AMEC FOSTER WHEELER (B) SDN BHD
CONSTRUCTION QUALITY CONTROL RESPONSIBLE CONTROL VERIFYING INSPECTION PARTY
No. FREQUENCY
ACTIVITY ACTIVITY PARTY DOCUMENT DOCUMENT NQSB WOOD BSP
Check transfer of
Weld
Cut, preparation & transfer material traceability
AFC Dwg, Material History/Summary
1.5 of material traceability / number prior to cutting NQSB 100% H M M
Handlings procedure Sheet/Working
EQA No./Lot No. and measurement of
AFC Drawing
cut length
Check groove angle,
Fit Up report/
root gap, squareness, Approved WPS, AFC
1.6 Fit-up and alignment check NQSB 100% Working AFC H M M
plumbness and Drawings
drawing
cleanliness of groove
Ensure approved Weld History/
WPS in use/ weather Approved WPS, Summary sheet /
1.7 Welding process NQSB 100% H M M
protection/ preheat BSP.12.S.601 Working AFC
temp. drawing
Ensure that welder Welder
BSP.12.S.601,
assigned to do the job ID/Welder
NQSB 100% Approved WPS, ASME H M M
are qualified and with Qualification
IX/ ANSI B31.3
valid qualification card
NOTE:
W = Witness Point R = Review WOOD = Amec Foster Wheeler (B) Sdn Bhd BSP = Brunei Shell Petroleum Company Sdn Bhd
H = Hold Point M = Monitoring NQSB = NuQuest Sdn Bhd
NuQuest Sdn Bhd
INSPECTION TEST PLAN – PIPING
CONTRACT TITLE : PROVISION OF ONSHORE ONLY FABRICATION SERVICES Document No.: ITP-001
PROJECT NUMBER : BSP-SCR-060 Revision: 2
CLIENT : AMEC FOSTER WHEELER (B) SDN BHD
CONSTRUCTION QUALITY CONTROL RESPONSIBLE CONTROL VERIFYING INSPECTION PARTY
No. FREQUENCY
ACTIVITY ACTIVITY PARTY DOCUMENT DOCUMENT NQSB WOOD BSP
Ensure that welding
machine in use are in
Approved WPS, Equipment
good NQSB Random H M M
BSP.12.S.601 checklist
condition(Amperage,
voltage)
Check root and hot Weld History/
passes of Approved WPS, Summary sheet /
NQSB 100% H M M
welding(where BSP.12.S.601 Working AFC
accessible) drawing
Weld History/
Visual inspection /
AFC Drawing, Summary sheet /
1.8 Welding Completion check I.D / Identify NQSB 100% H M M
BSP.12.S.601 Working AFC
joint for NDT
drawing
Approved NDT
Interpret results and
1.9 NDT NQSB 100% procedures, NDT Report H M M
check for defects.
BSP.12.S.601
NOTE:
W = Witness Point R = Review WOOD = Amec Foster Wheeler (B) Sdn Bhd BSP = Brunei Shell Petroleum Company Sdn Bhd
H = Hold Point M = Monitoring NQSB = NuQuest Sdn Bhd
NuQuest Sdn Bhd
INSPECTION TEST PLAN – PIPING
CONTRACT TITLE : PROVISION OF ONSHORE ONLY FABRICATION SERVICES Document No.: ITP-001
PROJECT NUMBER : BSP-SCR-060 Revision: 2
CLIENT : AMEC FOSTER WHEELER (B) SDN BHD
CONSTRUCTION QUALITY CONTROL RESPONSIBLE CONTROL VERIFYING INSPECTION PARTY
No. FREQUENCY
ACTIVITY ACTIVITY PARTY DOCUMENT DOCUMENT NQSB WOOD BSP
Ensure defective weld Weld History/
Approved WPS,
are repaired Summary sheet /
2.0 Weld Repairs NQSB 100% BSP.12.S.601,NDT H M M
according to approved Working AFC
Procedure
WPS/ re-visual/NDT drawing
Hydro test
Ensure all weldment
Approved Hydro test report,
free from defect and
2.1 Hydro Test NQSB 100% procedure, NQ-060- calibration report H W/R W/R
NDT has been
OPS-004 (Pressure gauge,
completed
chart recorder),
Ensure temperature
monitoring, measuring
and recording
equipment are PWHT report,
calibrated. PWHT
BSP.12.S.601, &
2.2 Post Weld Heat Treatment Ensure equipment NQSB 100% temperature H W W
Approved WPS
setup, thermocouple recording
placement, heating/ chart,NDT report
cooling rate and
soaking time are as
per procedure/ WPS
Post Blasting
Inspection
surface preparation, Blasting painting
Blasting &
2.3 Painting cleanliness, profile NQSB 100% procedure, NQ-060- H M/R M/R
Painting report,
height, weather OPS-002
condition, substrate
temperature
NOTE:
W = Witness Point R = Review WOOD = Amec Foster Wheeler (B) Sdn Bhd BSP = Brunei Shell Petroleum Company Sdn Bhd
H = Hold Point M = Monitoring NQSB = NuQuest Sdn Bhd
NuQuest Sdn Bhd
INSPECTION TEST PLAN – PIPING
CONTRACT TITLE : PROVISION OF ONSHORE ONLY FABRICATION SERVICES Document No.: ITP-001
PROJECT NUMBER : BSP-SCR-060 Revision: 2
CLIENT : AMEC FOSTER WHEELER (B) SDN BHD
CONSTRUCTION QUALITY CONTROL RESPONSIBLE CONTROL VERIFYING INSPECTION PARTY
No. FREQUENCY
ACTIVITY ACTIVITY PARTY DOCUMENT DOCUMENT NQSB WOOD BSP
DFT Inspection
Check thickness of
Blasting painting
DFT,coverage of paint Blasting &
NQSB 100% procedure, NQ-060- H M/R M/R
of the material, Painting report,
OPS-002
surface
appearance/finish
Ensure dimension as
per AFC Drwg.
Final Inspection Check BSP GC ITR,
Fabrication schedule
2.4 (Acceptance of BSP GC cleanliness(free from NQSB 100% Consignment H H H
ITR Checklist
ITR) debris/oil, etc.) note
Install tagging and
packing
NOTE:
W = Witness Point R = Review WOOD = Amec Foster Wheeler (B) Sdn Bhd BSP = Brunei Shell Petroleum Company Sdn Bhd
H = Hold Point M = Monitoring NQSB = NuQuest Sdn Bhd