Cedm02 1 4
Cedm02 1 4
Design Division
Chapter: 1
Page: 1 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
1 MAINLAYING
1.1 GENERAL
Current practice within WSD is for Project Planning Unit to determine the
size and approximate route of a new pipeline. From this information, E/Des
develops the pipeline in detail until tenders are invited for the mainlaying works.
Tender assessment, letting of the contract and contract supervision will be handled
by Construction Division. The work carried out in the design stage includes :-
(a) Selection of the best route and arrangement of land for the pipeline.
(d) Design of thrust blocks, pipe cover, bedding, backfill and special features
such as pipe bridge for mainlaying.
(f) Ensuring that funds are available when the project is gazetted and financial
control of the project whilst in the design stage.
Pipe sizes are normally determined during the planning stage and should be
rounded up to the nearest standard pipe sizes used by WSD.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 2 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(a) In selecting the pipe route, the following points should be considered : -
(i) The shortest possible route between the point of supply and the
point of demand should be used.
(iii) Pipes should not be laid under paved areas unless absolutely
necessary. Under no circumstance should they be laid under a
proposed building site except as a temporary measure.
(iv) The pipeline should be aligned to avoid the necessity for it to pass
over slopes as far as possible. However, where pipes must be laid
in natural or man made slopes, advice must be obtained from GEO
of CEDD. If pipes are to be laid in roads, which traverse a slope,
they should be laid away from the edge of the slope.
(v) Pipes should not be laid nearer than 2m from the trunks of trees.
(vi) Where pipes are to be laid near existing structures the effect of
mainlaying operations on the foundations of the structure should be
analysed and temporary and permanent supports specified as
required.
(vii) The location of streams, culverts and existing services should all
be established in the design stage and pipelines crossing them
should be avoided if possible. Inspection pits should be dug as
described in Section 1.9.2.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 3 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(b) Special care should be taken where a section of pipe intersects a culvert and
in such a situation : -
(ii) the waterway inside the culvert may make it impossible to lay the
pipe inside; and
(iii) the level of the culvert is such that it may be too deep to lay the
pipe beneath it.
(a) Steel is normally used for pipes of DN700 and above. Its main advantages
lie in its high strength/weight ratio and that bends and fittings can be easily
fabricated on site from straight sections of pipe.
(b) If pipes of materials other than steel are being used and there is difficulty in
obtaining bends and fittings or in laying pipes over long spans it is normal
practice to insert steel pipes, bends and fittings to overcome the problem.
The connection between the two different types of pipe material can be
made with a flanged joint or a stepped coupling.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 4 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
1.5.2 DI Pipes
(a) DI pipes are normally used for pipelines of DN150 to DN600 inclusive.
DN80 to DN100 DI pipes may also be used. As DI pipes are usually laid
with flexible joints, anchor blocks must be constructed at bends to prevent
movement at the bends. In confined spaces where it is impossible to build
adequately sized anchor blocks, pipes with rigid joints such as double
flanged DI pipes and fittings or welded steel pipes may be used as they
require relatively smaller thrust blocks.
Unlined galvanised steel pipes are no longer in use for new works because
they are prone to both internal and external corrosion which will lead to
discoloration problems. Use of lined galvanised steel pipes of medium grade (or
lined GI pipes as they are commonly called) should be avoided as far as possible.
They should never be used for salt water. However, the pipes of sizes up to and
including DN100, are particularly useful for laying above ground due to their
strength. They are connected by screwed joints.
(b) Class D UPVC pipes and fittings are used by WSD for buried mains and
services up to and including DN100, using solvent cement joints in
sizes 3/4”, 1” and 12” and preformed sockets with fitted gaskets in the
larger sizes.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 5 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
1.5.5 PE Pipes
(a) As PE pipes have overall advantage over lined GI and DI pipes, it has been
decided to adopt PE pipes for general use and phase out lined GI and DI
pipes for underground pipelines of DN150 and below. The use of larger
diameter PE pipes up to DN 315 (nominal internal bore DN 250) may be
considered.
(d) Reference can be made to “Interim Design Guide for Medium Density
Polyethylene (MDPE) Pipelines for Water Supply Purpose”.
Pipe joints are either flexible or rigid. See Appendix 1.1 for diagrammatic
details of joints.
(a) A flanged joint is an expensive joint and should only be used to connect
pipes to valves or flanged fittings, especially where connections must be
made between pipes of different materials.
(c) Flanged joints should be to BS 4504 (metric) and care should be taken that
the correct pressure rating is stated when indenting pipes and fittings with
flanged joints.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 6 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(a) Welded joints are mainly used on steel pipelines. PE pipes may be site
welded by use of a special welding machine.
(c) Pipes exceeding DN700 should be welded both inside and outside in
accordance with GS.
(b) The ‘O’ ring joint (Tyton) which is used on cast iron, UPVC and DI pipes is
a socket and spigot push-in flexible joint. It can deflect within a range
between 3o to 5o depending on the size of pipe and manufacturers’ design.
Rubber gaskets and joint lubricant are supplied with the pipes.
(c) Bolted Gland Joints (Mechanical) are similar to Tyton joints with the
exception that the gasket is held in position by means of a bolted ring.
They are more expensive than Tyton joints.
(b) VJ couplings provide a flexible joint between two plain ended sections of
pipe in the following circumstances :
(ii) Stepped couplings enable two pipes of the same nominal diameter
but of different materials and external diameters to be joined
together.
(d) Victaulic couplings do not allow angular deflection and are normally used
on exposed pipelines where sections of pipe or plain ended fittings must be
periodically removed. They are a bolted gland type joint and are cheaper
than flexible detachable couplings.
(a) Expansion Joints should be used on welded steel pipelines laid above
ground level. Full details of these joints are given in the Particular
Specification for steel pipes and fittings contained in the Model Tender
Documents.
(b) Where expansion joints are used it is essential that the pipeline is free to
move longitudinally on its supports.
(d) The required number of expansion joints is dependent upon the ambient
temperature at the time of mainlaying but for ordering purposes it should be
assumed that expansion joints are required every 50m on exposed welded
steel pipelines.
1.7 VALVES
(b) All valves or adjacent pipework must be anchored against the thrust induced
when the valves are closed especially for high pressure pipelines.
(a) Gate valves are suitable for isolation duties for either “fully open” or “fully
closed” positions and are unsuitable for :-
(ii) Flow regulation (as even a slightly opened tapered gate permits
uncontrolled leakage around its whole periphery). If left in such a
throttling position chatter and scoring on the downstream side
together with channel erosion of the seats may ensue, hence
thereafter the valve will not be drop-tight.
(b) Gate valves of DN300 and below may be backfilled to just below spindle
level with a small chamber placed around the spindle and a cast iron cover
at ground level. Gate valves exceeding DN300 should be installed in a
valve chamber as described in Section 1.10.
(c) All sectional valves and washout valves should be gate valves as only gate
valves give a positive seal and can be completely opened to allow the
passage of pigging and swabbing devices for pipeline cleaning operations.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 9 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(iv) To reduce cost, sectional valves larger than DN450 should be 75%
of the pipe diameter and connected into the main by tapers.
However, before adoption of this practice, all divisions concerned
should be consulted as to whether there are other overriding
factors.
(iv) Double washout valves should be designed for trunk mains and
primary distribution mains to suit operational needs.
(a) Butterfly valves are lighter, cheaper, smaller and easier to operate than gate
valves. However, as they do not give a positive seal they should not be
used as washout valves and as they obstruct pigging and swabbing
operations they should not be used as sectional valves.
(b) They are used as control valves in treatment works. Remote controlled
motorised butterfly valves are normally installed at the inlets to and outlets
from gravity fed reservoirs as advised by the M&E/Projects Division.
(c) They have friction loss higher than comparable gate valves.
(c) Non-return valves are normally procured and installed by the M&E/Projects
Division.
(a) Air valves are automatic in operation. They are required on all pressure
pipelines, wherever there is a peak or, in some cases, a change to a flatter
gradient after a long rise.
(b) In water supply systems, large orifice air valves are used wherever large
volumes of air must be expelled or admitted rapidly at relatively small
differential pressures when filling and emptying a pipeline. Small orifice
air valves are used for bleeding off the small volumes of air released from
solution whilst the pipeline is in service and under pressure. Double air
valves combining the above features are available.
For current Waterworks practice, only single small orifice air valves and
double orifice air valves are used in water mains.
Single small orifice air valves are installed at local high spots where small
pockets of air may accumulate and at not more than 800m spacing along
straight stretches of a pipeline.
(i) Normally, a double orifice air valve is installed at the highest point
of a pipeline determined relative to the hydraulic gradient existing
on the pipeline (not necessarily the highest point topographically).
Additional double air valves are installed where a pipeline rises
steeply and then changes gradient so as to rise less steeply (i.e. at a
point where a rapid change of grade occurs) and at other high
points along the pipeline where it is obvious that air must emerge
to permit filling of the pipeline.
An isolation valve must be fitted below the air valve to enable the air valve
to be removed for repair. Every air valve should be supplied with an
isolating valve.
Extension pieces below air valves shall be of stainless steel for corrosion
resistance and shall be provided to bring the top of the valve to not more
than 300mm beneath the surface cover.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 12 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(a) Pressure reducing valves are used to protect the water supply systems or
vessels from excessive pressure.
(b) They are designed to relieve excessive pressure in systems when the pre-set
pressure is exceeded.
(c) They are normally of direct action spring type. Lever and weight or dead
weight types are obsolete but may still be found in use. Alternative
designs, such as torsion bar types, have limited application.
(a) It is a level control valve used mainly for controlling the supply of make-up
water (e.g. in cisterns, water tanks etc.). When the pre-set water level is
reached, the valve will be automatically closed to stop the supply of water
into the vessel.
(b) The most effective type is the equilibrium ball float valve which is
commonly used.
The total length of a main can be measured from drawings and adjusted for
slope or inclined gradients. The total number of pipes including specials
can therefore be assessed to a reasonable degree of accuracy.
Truly circular pipes are required for closures and for fabricating specials.
It is normally uneconomical to cut closures from full length pipes. Quarter
length pipes are long enough for the purpose of fabricating most tees and
bends. Closures should be made with half and quarter lengths of plain
pipes and quarter lengths of truly circular pipes.
Tees for fixing air valves should be DN600 in order to make them
interchangeable with manhole tees. However, if the installation of an air
valve is affected due to the lack of cover to the pipeline, a flanged, short
piece of pipe can be site welded to the main to hold the air valve.
(e) Specials
Bends, tees etc. required for steel mainlaying works are termed as specials.
(i) Washouts
Washouts should usually be not less than DN300 if the outlet can cope with
the discharge. For larger pipes with a free outlet, a larger washout is
usually advisable.
Experience has shown that large quantities of debris are often collected at
the dead end main. A washout of the same size as the watermain or
DN300, whichever is the lesser, should be installed at the pipe end to
facilitate the removal of debris. Moreover, an isolation valve in a closed
position should be added before the washout tee branch. For details, refer
to Standard Drawing No. WSD 1.4.
(j) Tapers
(k) Joints
Spherical spigot and socket joints should be supplied for steel pipes of
DN600 and above. For small diameter pipes, flange joints or other
mechanical joints should be supplied.
1.8.2 DI Pipes
(a) The required lengths and quantities of DI pipes and fittings should be
ascertained as described for steel pipes in Sections 1.8.1(a), (b), (c) and (i)
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 15 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
except that all tees should be supplied with socket ends and flange
branches.
(b) Bends
Bends should be supplied as short bends with socket ends for all sizes.
Excessive numbers of 90o bends should be avoided.
(d) Collars
A spigot or socket type flange adaptor should be used for connecting the
downstream side of a valve into the pipeline.
A puddle flange pipe, 1.2m long, flanged at one end, should be used for
connecting the upstream side of larger valves into a pipeline.
The other end of puddle flanged pipe should be either plain or socketted
depending upon the location of the valve, bearing in mind that the open
ends of sockets should face uphill.
(g) Tapers
(a) The required lengths and quantities of lined GI pipes and washouts should
be ascertained as described for steel pipes in Sections 1.8.1(a) and (i).
(b) Fittings, such as bends, bushes, long screws, tees, reducing sockets and
nipples, can be estimated by use of the standard connection details at
Appendix 1.2.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 16 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(a) The required lengths and quantities of UPVC pipes and washouts should be
ascertained as described for steel pipes in Sections 1.8.1(a) and (i).
(b) Fittings, such as bends, caps, elbows, equal/reducing sockets, tees, flange
assembly and valve sockets can be estimated with reference to the standard
connection details at Appendix 1.2.
1.8.5 Valves
Every effort should be made to produce a scheme which will survive the
design life of the pipes for the least capital outlay and optimal operation and
maintenance costs.
If 1:500 contoured survey sheets are available there is no need to survey the
route of a new pipeline, except for locations where the mainlaying work may be
considered as a cause of public concern for reasons such as land resumption being
involved, there being a critical slope nearby, etc. The proposed route should be
plotted on the survey sheet avoiding obstructions and structures. Trees, paved areas,
lawns and gardens should be avoided if possible and it should be ensured that
sufficient working space is available for access and mainlaying operations. E/Des
should then walk along the route of the main to ensure that his proposals are feasible.
If the survey sheet differs from reality the area in question should be surveyed and
the survey sheet corrected.
(a) When the proposed route has been established, inspection pits should be
dug by the WSD Term Contractor at the following locations. If in-situ
testing and sampling are required, E/Des should make a request to GEO
Materials Division for the GEO Term Contractor to carry out the inspection
pit excavation.
(i) At reasonable intervals along the proposed route of the main for
general sub-surface investigation.
(b) Inspection pits should be deeper than the anticipated depth of the main and
in carriageways, samples of the different types of material encountered
should be tested for Atterberg Limits to assess its suitability as backfill
material, if considered necessary.
(c) The following information should be obtained from the inspection pits : -
(d) E/Des should ensure that sufficient inspection pits have been dug to obtain
underground conditions before the alignment is finalised. As a general
guide, one inspection pit should be dug for : -
(e) Non-destructive utility surveys may be conducted to locate lines and levels
of buried utilities. If such surveys are used, then the number of inspection
pits can be suitably reduced.
1.9.3 Gradients
(a) Both gravity and pumping mains must be laid with a minimum gradient of
1:400 to allow air to be released by air valves at high points and water to be
collected at low points where a washout valve should normally be installed
(see Section 1.7.1(e)).
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 19 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(b) If pipes are laid on steep gradients of 1:6 or above, anchor blocks should be
constructed to prevent movement. Typical details of anchor block are
shown on Standard Drawing No. WSD 1.5.
1.9.4 Cover
(a) Under normal conditions pipes should be laid with a minimum of 1m cover
beneath roads and 600mm cover in open areas.
(b) Special cover requirements are stipulated in HyD Technical Circular 3/90
especially for watermains running along kerb zones. Cover requirements
in that circular should be met as far as practicable unless agreed otherwise
by HyD and WSD Region.
(c) Where pipes are being laid in conjunction with new roadworks they should
be laid with a minimum 600mm cover beneath the formation level of the
road to prevent damage by earthmoving equipment.
(e) If the pipes must be laid over existing services and the cover is reduced the
pipe should be protected by a concrete slab and where pipes are laid at more
than 2m deep, E/Des should check that the pipe barrel is strong enough to
withstand the pressure of the surrounding earth. If it is not then concrete
protection should be placed around the pipe.
(f) Any proposal to lay a main on filling exceeding 1.5m must be carefully
considered in regard to the degree of consolidation and the risk of
subsequent movement. Similarly, laying a main with a cover in excess of
2.1m, except where deeper laying for short lengths is necessary to avoid
obstructions, should not be accepted without careful consideration. In
either case, the proposal should be referred to the relevant Region for
approval.
(g) Special attention should be given to the design of large diameter pipelines
with sizes greater than DN1200 for which cover to pipes is a critical
consideration.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 20 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(h) For buried cross-country pipes or pipes laid beneath a footpath in the
country, where vehicles are inaccessible, the minimum cover can be
reduced to 300mm or less, provided the pipes are properly anchored.
(a) Drawings showing the route of the proposed watermain should be circulated
to all the Utility Companies and other relevant Government departments at
an early stage in the design of the pipeline to enable details of their existing
and planned services to be established and avoided where possible.
Inspection pits should be dug and where necessary, non-destructive utility
surveys conducted, particularly in congested areas, to verify the information
received from the Utility Companies.
(c) If necessary a meeting with all concerned parties should be convened in the
design stage to resolve potential difficulties which may arise during
mainlaying operations.
(d) The following specific points should be noted where public utilities may be
affected by the laying of water mains :-
(i) HK Tramways Ltd. does not allow tram tracks to be removed and
new water mains must be tunnelled beneath them.
(iii) With the exception of submarine pipelines new water mains should
be laid up to 300mm away from existing services. Clearances of
submarine pipelines must be individually agreed with the
appropriate authority.
(v) Mainlaying works are normally not allowed within the protection
boundary of Mass Transit Railway unless the plans have first been
forwarded to the MTRC for comment / agreement. Protective
measures may be stipulated by MTRC. For details refer to WB
TC No. 19/2002.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 21 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(a) The choice of bedding, haunching and surround can influence the cost of a
scheme.
(i) A 100mm concrete bed should be used where pipes are laid in a
trench excavated in rock.
(iii) Where pipes cross roads at shallow depths, the pipes should be
surrounded with concrete and/or covered by a steel plate, subject to
the agreement with HyD and Region.
(vi) Where pipes may be subjected to heavy surface loads concrete bed,
haunch or surround should be used.
(vii) Pipes which will not be subjected to heavy loading are normally
backfilled with local material excavated from the pipe trench.
(xi) Material surrounding the pipe should be free from stones or sharp
objects. If the material removed from trench excavation in public
roads is considered incapable of being compacted to a degree
capable of preventing future settlement of the reinstated road
surface, the pipe should be surrounded with a readily compactable
material such as 10mm single-sized stone. Pipes laid in
reclaimed land are normally surrounded by 10mm single-sized
stone.
1.9.7 Backfill
(b) E/Des should base his estimate of the amount of required imported material
on the results of the inspection pits mentioned in Section 1.9.2 and the
required quantities should be covered by items in the Bills of Quantities.
(e) Pulverised fly ash or sand is suitable for use as backfill material in dry
conditions.
(f) Special attention should be given to the design of large diameter pipelines
with sizes greater than DN1200 for which bedding and backfilling is a
critical consideration.
(a) Where buried pipelines join structures, care must be taken to prevent
structural failure of the pipeline if movement or differential settlement
occurs between the pipeline and the structures, and to ensure that the bond
between the pipe and structure is watertight.
(a) Thrust blocks prevent pipes from being moved by forces exerted within the
pipe by the flow of water hitting bends, tapers, and closed or partially closed
valves. The size of a thrust block is dependent upon the deflection of the
flow and the head of water inside the pipe.
(b) Thrust blocks are essential on flexibly joined pipelines where any pipe
movement would open up the joints in the line and cause water leakage.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 24 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(c) Thrust blocks are necessary near valves where a flexible joint is located to
facilitate removal of the valve for maintenance purposes.
(d) Guidelines for provision of thrust blocks for steel pipes with welded joints
are given in WSD Manual of Mainlaying Practice. One of the guidelines
is that for a buried steel pipe of diameter 1200mm and under, which is
subjected to a working pressure of less than 1.0MPa, there is no need to
provide any thrust block for bends smaller than 45o. However, there must
be no loose joint (such as bolted collars or those joints normally used for
valve installations) within 30 m on either side of the bend. In the design of
a steel pipeline, this guideline should be specified by including the
following note on the drawing showing the thrust block schedule :
"Thrust blocks at welded bends less than 45o for a buried steel pipe of
diameter 1200mm and under, which is subjected to a working pressure of
less than 1.0MPa, shall not be required unless there are loose joints within
30 m on either side of the bend or as directed by the Engineer."
(e) Derivation of the criterion in (e) above is based on calculations with the
assumption that the sections of main adjacent to both sides of the bend will
be buried at least by the anchorage length i.e. length required to anchor the
bend by soil friction along the circumference of the pipe. For steel bends
satisfying the above criterion, the availability of anchorage length should be
checked on site in the construction stage to assess the need for thrust blocks.
However, it is envisaged that the assumption on anchorage length may not
always be met on site. Therefore, details of thrust blocks covering a full
range of bends for various diameters of steel pipes required by the Contract
should be included on the drawings.
(f) Thrust blocks should be of grade 20/20 concrete and should as far as
practicable be designed so that flexible joints at the ends of the bend and
blank flanges at the ends of the watermain are left exposed.
(ii) Pipes with rigid joints, e.g. steel pipes with welded and flanged
joints, welded collars etc. take up half of the thrust by continuity
while the other half is taken up by thrust blocks.
(iii) Care must be taken, where loose joints (e.g. flange adaptors,
coupling joints, expansion joints etc.) are used on a steel pipeline
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 25 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
with rigid joints, that no loose joints are located within the
calculated safe length for development of ground anchorage on
both sides of a bend or from the dead end or reducer/taper on the
pipeline. Otherwise, the whole of the thrust must be resisted by
an anchor block in a similar way as for pipes with flexible joints.
(iv) For pipes with flexible joints (e.g. DI pipes with socket and spigot
joints, etc.), all the thrust must be assumed to be taken up by thrust
blocks.
(v) Buried thrust blocks other than those on cross-country mains where
pipe cover is less than 600mm will be designed against working
conditions as follows:-
(vi) The thrust blocks are also to be checked against pressure testing
conditions as follows :-
(h) In general, bearing capacity is not a critical factor in the design of thrust
blocks other than bottom vertical blocks. For ductile iron mains with
nominal diameters between DN80 and DN450 operating at maximum
pressure heads ranging from 60m to 120m, thrust block dimensions are
obtainable from Standard Drawing No. WSD 1.40. The thrust block
dimensions shown on Standard Drawing No. WSD 1.40 have been derived
from calculations performed based on the design assumptions and
requirements stated in this Section.
(i) Further details and worked examples are shown in the Guidance Note on
the Design of Thrust Blocks for Buried Pipelines kept under “Documents
and Drawings” in Design Division Intranet Homepage at
http://intranet.wsd.gov/NWB/des/frontpage.htm.
When water mains are laid in roads, the backfilled trench is to be reinstated
by the mainlaying contractor in accordance with Standard Drawing No. WSD 1.2.
(b) The drastic change in pressure associated with surge may cause bursting at
flanged and push-in type joints of the main. E/Des should obtain advice
from M&E/Projects Division regarding the maximum pressure the main
should sustain under surge condition and the surge suppression equipment
that need to be installed to protect the main and other associated facilities.
(d) Where pipes must cross watercourses and undulating ground it is normal
practice to allow the pipes to span such low areas without any support.
(e) Where flexibly jointed pipelines must span over low areas the sections
which span must have f1anged or welded joints and if necessary a section of
welded steel pipeline may be inserted to achieve a longer span.
(f) Where the pipe bridge may constitute a hazard to public safety, appropriate
measures such as barbed wire or metal spikes must be placed at each end of
the pipe bridge to prevent unauthorised access.
(g) E/Des should consider the following when designing supports for exposed
pipe :
(i) The pier and saddle supports for exposed pipe is assumed to
sustain vertical thrust only. All longitudinal components of the
thrust due to change in direction or diameter of pipeline etc. shall
be resisted by anchor blocks at suitable points of the pipelines.
St = S b + S1
where
St = Maximum stress at saddle
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 28 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(a) Access manholes should be installed every 250m on pipelines larger than
DN600 to permit access for inspection and maintenance at the following
locations in order of priority :
(i) On the upstream side of, and in the same chamber as, sectional
valves of DN600 and above.
(b) These manholes normally consist of a short section of DN600 pipe welded
on the top of the main with a blank flange bolted to the top.
(c) Air valves can be placed on the top of the flanges if appropriate and the
flanges can be removed to ventilate the main during filling and emptying
operations.
(c) For pipelines within flowmeters, straight lengths of at least 15 times and
10 times the pipe diameter, absolutely free of bends or other fittings and
specials, upstream and downstream of the flowmeter respectively are
essential for reasonably accurate measurement. The pipework connected
to the flowmeter shall be accurately aligned and have adequate support to
carry the weight of the flowmeter. A concrete support or metal cradle is
normally required for large flowmeter. E/Des should seek the
M&E/Projects Division's advice on the exact requirement for the particular
project concerned.
(d) There are special requirements for the provision of a chamber for the
turbine type portable insertion flowmeter. During calibration of the main
flowmeter, tip of the stem of the insertion flowmeter is lowered
perpendicularly through a full-bore isolation valve (in open position) and a
stub pipe into the watermain to take measurement. Requirements of the
stub pipe are given in Standard Drawing No. WSD 1.30, details of which
may be modified to suit site conditions subject to agreement with the
M&E/Projects Division. Details of the chamber are shown on Standard
Drawing No. WSD 1.25.
(a) The waste detection meter is somewhat misnamed in that it does not
necessarily record water which is going to waste. It is a recording meter of
special design suitable for installation in a pit underground and it is usually
placed to read flows through a watermain overnight. Any flow through the
water main during the early hours of the morning, say 1 am to 5 am, will be
taken down for comparison with previous records before further
investigation is conducted.
(b) The waste detection requirements are determined by the Leak Detection
Section of the Development (1) Division. E/Des should circulate a set of
layout plans for the proposed mainlaying works to CTO/LD for advice in
accordance with DI No. 828. Any such requirements indicated must be
taken into account.
(c) It is the current requirement within WSD that in all new service reservoirs,
a by-pass shall be incorporated around the first control valve on the
combined outlet main to enable a waste detection meter to be fitted.
(d) Standard details of waste detection meter chambers are shown on Standard
Drawing Nos. WSD 1.32, WSD 1.33 and WSD 7.15.
(a) No trees shall be planted within 3m from the centre line of any existing or
proposed pipes (water or drainage).
(b) Turf, plants and minor flowering shrubs may be accepted over watermains
provided they do not have profuse or penetrating roots.
(c) There shall be no planting within the space of 1.5m around the cover of any
hydrant valve or the covers of WSD's valves, nor within a distance of 1m
from any hydrant outlet.
(d) There shall be free access to all waterworks installations at all times even
when the turf, plants and shrubs are mature.
(e) Where the planting and landscaping are carried out by others, details of site
formation work and of any proposed structures shall be submitted to WSD
for prior approval.
discretion.
When pipelines are to be laid along bridge structures, they should be laid in
troughs or supported on concrete/steel works cantilevered from the side of the bridge
and specially designed for the watermain and provided by HyD. Special allowance
should be made in the design of the pipeline to account for the movement joints of
the bridge structure.
(b) The relative position of the pipe alignment particularly when more than 2
pipes are placed together in parallel should be drawn to scale. The size of
proposed valve chambers should also be plotted to scale on the alignment
plan.
(a) Access manholes are required on all pipelines larger than DN600 and
chambers are required for all types of valve with the exception of gate
valves of DN300 and below which can be backfilled with earth to the base
of the spindle; the spindle is then isolated from the surrounding earth with
precast concrete units or a short section of pipe, and a cast iron cover and
frame placed at ground level. Washout valves should always be located in
chambers to enable a visual inspection to be made of the flow from the main
during emptying operations and to act as a sump if the contents of the pipe
must be pumped to a discharge point away from the main.
(b) Manholes and chambers can be made from precast concrete units or cast in
situ concrete and typical details are shown in the Standard Drawings.
(c) The following points should be taken into consideration during the design
of manholes and chambers :-
(ii) Single air valve chambers are usually housed in precast concrete
units. An isolating stop-cock should be assembled with the single
air valve. To facilitate easy maintenance, the spindle of the
stop-cock should not be at a distance exceeding 450mm below the
top of the cover of the valve chamber.
(iii) The size of the air valve chamber must be big enough for
inspection and maintenance purposes. A clear distance of at least
150mm from the wall, roof, and floor of the valve chamber to the
body of the valve is to be maintained.
(a) Fire hydrants are normally spaced 100m apart but account should be taken
of the location of existing hydrants. Fresh and salt water fire hydrants
should be located alternatively or to suit site condition.
(b) Advice should be sought from FSD regarding the number and location of
new fire hydrants which should be installed in connection with new salt
water and fresh water mainlaying schemes.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 33 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(c) DN150 connections to the new hydrants should be laid from the new main
with a gate valve adjacent to the main.
(d) The Project Planning Unit normally states in the Planning Report who is
responsible for installing the hydrant heads. If the Region is responsible
then the mainlaying contractor should terminate the branch connection with
a blank flange at the location of the hydrant.
(e) For safety reasons, it is not the normal practice to install fire hydrants at
pumping water mains. The nature of the water main should therefore be
pointed out to FSD during the alignment circulation.
(f) It is not the normal practice to install fire hydrants at trunk mains. In
accordance with DI No. 912, prior approval from relevant authorities must
be sought.
(a) Where mains must be laid along slopes advice should be obtained from
GEO as to any precautionary measures which must be taken to prevent the
stability of the slope from being jeopardized by leakage from the main.
GEO usually requires precautions as outlined in Section 9.4.7 of the
Geotechnical Manual for Slopes to be observed.
(b) These measures can include the laying of leakage collection systems
alongside the main to an appropriate point of discharge.
(c) It is a bad practice to bolt pipelines to rock slopes as the bolts must then be
checked at regular intervals to ensure that they remain tight.
(d) The use of flexible/loose joints for water mains close to the crest of slopes
is not advisable because they are vulnerable to ground movement resulting
in leakage.
(e) Where mains are laid up slopes they should be anchored with concrete at
the centre of each pipe to prevent movement and where pipes are laid in
access roads which traverse slopes they should be laid at the side of the road
which leads up the slope.
(f) Where there is a possibility of water leakage into the slope, for example at
the crest, which will affect its stability adversely, the provision of leakage
collection systems should be considered. Reference should be made to
Sections 5.3.2(4) and 9.7 of Geotechnical Manual for Slopes. For laying
of small diameter mains, such as DN80 or below in remote villages, good
engineering judgement should however be exercised as to whether the cost
of the system would render the mainlaying work economically unjustified.
Consultation with GEO at an early design stage can help to reach a
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 34 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(b) Details of proposed roadworks are normally submitted to WSD where they
are circulated around the relevant divisions.
(d) If it is decided that the pipelines should be laid to the future road profiles,
final road levels should be obtained to facilitate the design of the pipeline
profiles. A longitudinal profile or spot levels of the proposed pipeline
must be included in the contract drawings.
(e) In the exceptional case that future road levels cannot be obtained in time,
the approval of AD/NW must be obtained for not including a longitudinal
profile in the contract drawings. Under this circumstance, notes pertaining
to the determination of the pipeline levels must be indicated on the contract
drawings, requiring the Construction Engineer to follow up at the
construction stage. Such a requirement must be clearly spelled out in the
handing over notes from the Design Division to the Construction Division.
(f) Mainlaying normally commences when the formation level for the
roadworks has been reached and if rock is present below formation it is
preferable for the rock trench excavation for the mainlaying works to be
carried out by the roadworks contractor.
(g) Watermains should have a minimum of 600mm cover below the formation
level to protect them from construction traffic.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 35 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(a) Where pipelines must cross heavy-traffic roads, railways, rivers or other
obstructions which prevent digging a trench for laying the pipeline, pipe
jacking techniques may be used to solve the problem.
(b) Pipe jacking propels the pipe directly into the ground. As a result, for
ideal ground conditions, the installation cost and time can be considerably
reduced and the installation work can be carried out safely without the need
of opening up roadways, disturbing traffic, or removing other obstructions.
(c) However there are a number of factors as discussed in the technical paper
on the pipe jacking works undertaken under Contract 12/WSD/86 at
Appendix 1.4. E/Des should consult and liaise closely with the relevant
authorities, consider all other alternatives of mainlaying, and evaluate their
relative merits to the use of pipe jacking.
(b) The principal factors affecting the design of a submarine pipeline may be
summarised as follows :
(i) Its security against the forces of waves, tidal currents, and sea bed
movement, etc.
(iii) Its strength to withstand both the permanent stresses and also the
construction stresses to which it will be subjected.
(c) Submarine pipelines must be buried beneath the sea bed to prevent damage
by ships anchors, the depth of cover being dependent upon the nature of the
sea bed.
(a) Before tenders are invited for submarine pipelines the area of sea bed which
is required for laying the pipeline must be gazetted under the Foreshore and
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 36 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(c) During the design stage the location of all existing services in the sea bed
should be ascertained and advice obtained from the Marine Department and
AFCD regarding fish farms and shipping movements before the route of the
pipe is decided.
(d) Similarly if the pipe is to replace an existing pipeline, the precise location of
the landing points of the existing pipeline must be established by WSD land
surveyors to enable the coordinates of the landing points of the new pipeline
to be correctly established.
(a) To determine the best route for a new submarine pipeline it is essential for a
Marine Geophysical Survey to be carried out of the area of sea bed where
the pipeline is required.
(b) These surveys are normally carried out by the Port Works Division of
CEDD or by a specialist firm.
(a) Steel pipelines are welded together either on a barge or at a landing point
and winched into the required position on the sea bed; this is called the
“Bottom Pull” method and has the advantage of avoiding disruption to
shipping. Steel pipes can also be supported by air bags, floated into
position and then released to sink into the seabed.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 37 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(b) Plastic pipes are not strong enough to be laid by the bottom pull method and
are usually brought to site by barge in lengths of up to 7km wrapped on
drums from where they are ballasted and lowered into a prepared
excavation on the seabed.
(c) Excavation of the seabed can be done by barge mounted grab bucket,
suction dredger or plough.
(d) Where rock is encountered the pipe can be laid on rubber pads on the rock
surface and surrounded by tremie or bagged concrete or by concrete
mattresses.
(a) In the design of an important steel watermain or one of larger than DN1400,
consideration should be given to the necessity of including a cathodic
protection system for the pipeline.
(e) CE/Des must be consulted at the very early stage of design work when it is
considered that a cathodic protection system is required.
(f) The following are useful reference material available in the WSD Library :
(iii) Soil resistivity survey for Pipelines E-F and H-I for Future Increase
of Water Supply from China Stage I.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 38 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(g) There are some local firms equipped to install cathodic protection systems
and capable of carrying out soil resistivity surveys and commissioning tests.
The maximum test pressure for each section of a pipeline should be stated
in the Particular Specification of the Contract, which should be equal to the greater
of the following :-
(a) 1.5 times the maximum working pressure except that, if the maximum
working pressure exceeds 1.5MPa, the testing pressure shall be 1.3 times
the maximum working pressure;
(a) When laying short lengths of water mains for connections or small
extensions where a full hydrostatic pressure test is impracticable.
(b) When laying in areas where reinstatement must be done progressively as the
mainlaying proceeds, e.g. in heavy-traffic roads, rail tracks, access to
factories, etc. but a hydrostatic pressure test might not be possible until the
full length of the water main (or an extensive length) is complete.
The exact location and quantity of tests required shall be determined by the
Construction Engineer on site.
Water for pressure testing of pipeline shall be supplied free of charge to the
mainlaying contractor. Normally, water may be obtained from nearby fire hydrants.
E/Des should check and agree beforehand with the Region on the exact location
where water may be obtained for pressure testing and state this clearly in the contract
document.
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 39 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
1.17.4 Swabbing
(a) Works Area of sufficient size shall be made available for use in waterworks
contracts. The minimum size of Works Area for medium size contracts
having an estimated contract sum of $30M or less shall be 1000m2 and
wherever possible, an additional area to be used as transit pipe storage
compound shall also be provided for mainlaying contracts. The size of
this transit pipe storage compound shall be :-
(b) For large contracts exceeding $30M, larger works areas shall be secured if
space is readily available. A comprehensive assessment of the space
requirement shall be carried out.
(b) There are a number of different lining systems available for rehabilitation of
watermains. They are in general classified as non-structural, semi-
structural and fully-structural lining systems. The choice of replacement
or rehabilitation of a watermain depends on the following criteria:-
(c) A non-structural lining system relies wholly on the strength of the host
watermain. The system is usually in the form of providing a coating (e.g.
cement mortar, epoxy or other material) bonded to the inside wall of the
W Civil Engineering Design Manual - Volume II
Design Division
Chapter: 1
Page: 40 of 40
水務署 Water Supplies Department
Revision: 4
Date: 15/11/2004
(d) A semi-structural lining system relies on the residual strength of the host
watermain. They are further classified into the following categories
depending on their structural strength:-
(i) Category A
A lining is bonded to the host pipe to seal leaks by bridging over
defects (e.g. holes and gaps) in the pipe. The system relies on the
bonding between the lining and the pipe as the lining is thin and
not strong enough to support itself when the pipe is emptied or
subject to negative pressure. The composite structure of lining
and host pipe can withstand full internal pressure while the
external loadings have to borne by the host pipe.
(ii) Category B
Category B is similar to Category A except that the lining is self-
supporting and not required to be bonded to the host pipe.
(iii) Category C
Category C provides a lining which is capable of withstanding the
full internal pressure without reliance on the host pipe. However,
the lining itself cannot withstand the external loadings for the pipe.
(e) A fully-structural lining system does not rely on the strength of the host pipe
and is capable of withstanding the external and internal loads including that
when the pipe is emptied or subject to negative pressures. However, in
view of the lining thickness, the hydraulic performance of the lining system
should be assessed.