ID Task Name Unit Scope Duration Start Finish 2026 2027 2028
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
0 EPC NAG-II (59A): Road Improvement 912 days 09 Oct '24 09 Apr '27
Works in Taluka Seloo, Dist. Wardha
under EPC Mode
1 1 Milestone 0 days 24 Aug '25 24 Aug '25 24 Aug '25
2 2 Milestone 0 days 08 Apr '26 08 Apr '26 08 Apr '26
3 3 Milestone 0 days 23 Nov '26 23 Nov '26 23 Nov '26
4 4 Milestone 0 days 09 Apr '27 09 Apr '27 09 Apr '27
5 5 Pre-Construction Activities 120 days 09 Oct '24 05 Feb '25
6 5.1 Mobilisation of Plants , 60 days 09 Oct '24 07 Dec '24 09 Oct '24 07 Dec '24
Machineries & Installation
7 5.2 Seting Out Data & Surveying 30 days 09 Oct '24 07 Nov '24 09 Oct '24 07 Nov '24
8 5.3 Design & Drawing 90 days 08 Nov '24 05 Feb '25 08 Nov '24 05 Feb '25
9 5.4 NOC & Approval 120 days 09 Oct '24 05 Feb '25 09 Oct '24 05 Feb '25
10 6 Road Works 825 days 01 Dec '24 05 Mar '27
11 6.1 Site Clearance & Dismantling Km 44.255 280 days 01 Dec '24 08 Feb '26 01 Dec '24 08 Feb '26
12 6.2 Earthwork up to top of the Km 44.255 480 days 02 Dec '24 29 Dec '26 02 Dec '24 29 Dec '26
embankment
13 6.3 Subgrade Km 44.255 490 days 04 Dec '24 31 Dec '26 04 Dec '24 31 Dec '26
14 6.4 Earthwork(Shoulder) Km 44.255 680 days 25 Apr '25 05 Mar '27 25 Apr '25 05 Mar '27
15 6.5 Sub-Base Course (GSB) Km 44.255 460 days 14 Feb '25 26 Jan '27 14 Feb '25 26 Jan '27
16 6.6 Dry Lean Concrete (DLC) Km 44.255 690 days 04 Mar '25 22 Jan '27 04 Mar '25 22 Jan '27
17 6.7 Pavement Quality Concrete Km 44.255 690 days 10 Apr '25 28 Feb '27 10 Apr '25 28 Feb '27
18 7 Structure Works 572 days 03 Jan '25 28 Jul '26
19 7.1 Culverts 510 days 03 Feb '25 27 Jun '26
20 7.1.1 Hume Pipe Culvert 1-Row Nos 75 510 days 03 Feb '25 27 Jun '26 03 Feb '25 27 Jun '26
21 7.1.2 Hume Pipe Culvert 2-Row Nos 18 270 days 14 Mar '25 26 Mar '26 14 Mar '25 26 Mar '26
22 7.1.3 Box Culvert Nos 4 120 days 01 Nov '25 28 Feb '26 01 Nov '25 28 Feb '26
23 7.2 Minor Bridges 572 days 03 Jan '25 28 Jul '26
24 7.2.1 Widening & Repair of Minor Nos 6 140 days 03 Jan '25 22 May '25 03 Jan '25 22 May '25
Bridges
25 7.2.2 New/Reconstruction of Nos 7 180 days 02 Dec '25 30 May '26 02 Dec '25 30 May '26
Minor Bridge (Foundation &
Substructure)
26 7.2.3 New/Reconstruction of Nos 7 180 days 02 Jan '26 30 Jun '26 02 Jan '26 30 Jun '26
Minor Bridge (Superstructure)
27 7.2.4 New/Reconstruction of Nos 7 180 days 30 Jan '26 28 Jul '26 30 Jan '26 28 Jul '26
Minor Bridge (Approach)
28 8 Miscallaneous works 693 days 16 May '25 09 Apr '27
29 8.1 Earthen Drain Km 87.15 390 days 13 Oct '25 02 Mar '27 13 Oct '25 02 Mar '27
30 8.2 Covered Drain in Builtup Section Km 1.3 150 days 13 Nov '25 11 Apr '26 13 Nov '25 11 Apr '26
31 8.3 Metal Beam Crash Barrier Rm 3289 37 days 01 Feb '27 10 Mar '27
32 8.4 Retaining Wall/ Toe Wall Rm 440 150 days 02 Dec '25 30 Apr '26 02 Dec '25 30 Apr '26
33 8.5 Major Junction including CD Nos 25 180 days 02 Jan '26 30 Jun '26 02 Jan '26 30 Jun '26
Structure (RCC Pipes)
34 8.6 Utility Pipes in Builtup Section Km 0.65 120 days 10 Mar '26 10 Dec '26 10 Mar '26 10 Dec '26
(Along and across the road)
35 8.7 Approaches to Adjoining Km 43.61 630 days 16 May '25 04 Feb '27 16 May '25 04 Feb '27
agricultrual Field, with 900mm NP4
Pipe Laying
36 8.8 Handing Over Site 30 days 10 Mar '27 09 Apr '27