Cec3170 Airport Engg Unit4
Cec3170 Airport Engg Unit4
By:
Dr. Aparna Kanth
• UNIT 1 Highway Material & Construction: Properties of sub-grade & pavement component
material, test on stone aggregates & bituminous materials. Highway Construction: WBM, WMM,
Bituminous & cement concrete pavements.
• UNIT 2 Highway Geometric & Pavement Design: Design of geometric elements of road,
Design factors for flexible and rigid pavements. Group Index and CBR methods for flexible
pavement design. Analysis for wheel load stresses in rigid pavement. Westergaard’s method for
design of rigid pavement.
• UNIT 3 Railway Engineering: Gauges, rail failure and ultrasonic inspection, rail joints & welding
of rails, wear of rails, sleepers, ballast & formation, points & crossings, station & yard, tractive
resistances, hauling capacity of locomotive, modernization of railways.
• UNIT 4 Traffic & Airport Engineering: Traffic studies, intersection design, traffic signs &
signals, selection of site for an airport, airport obstructions, imaginary surfaces, runway
orientation, wind rose diagram, design of runway, basic runway length, corrections of
runway length, airport classification, geometric design, airport capacity, aircraft parking
systems, wind and landing direction indicators.
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
INTERSECTION
• Drivers have to make split second decision at an intersection by considering his route,
intersection geometry, speed and direction of other vehicles etc., else ACCIDENT.
• Overall traffic flow depends on the performance of the intersections. It also affects
the CAPACITY of the road.
• Traffic flow is regulated to only one direction of movement, thus eliminating severe
conflicts between crossing movements.
• All the vehicles entering the rotary are gently forced to reduce the speed and continue to
move at slower speed. Thus, none of the vehicles need to be stopped, unlike in a
signalized intersection.
• Because of lower speed of negotiation and elimination of severe conflicts, accidents and
their severity are much less in rotaries.
• Rotaries are self governing and do not need practically any control by police or traffic
signals.
• They are ideally suited for moderate traffic, especially with irregular geometry, or
intersections with more than three or four approaches.
• All the vehicles are forced to slow down and negotiate the intersection. Therefore,
the cumulative delay will be much higher than channelized intersection.
• Even when there is relatively low traffic, the vehicles are forced to reduce their
speed.
• Rotaries require large area of relatively flat land making them costly at urban areas.
• The vehicles do not usually stop at a rotary. They accelerate and exit the rotary at
relatively high speed.
• Therefore, they are not suitable when there is high pedestrian movements.
• Rotaries are suitable when the traffic entering from all the four approaches are
relatively equal.
• A total volume of about 3000 vehicles per hour can be considered as the upper
limiting case and a volume of 500 vehicles per hour is the lower limit.
• A rotary is very beneficial when the proportion of the right-turn traffic is very high;
typically if it is more than 30 percent.
• Rotaries are suitable when there are more than four approaches or if there is no
separate lanes available for right-turn traffic. Rotaries are ideally suited if the
intersection geometry is complex.
The traffic operations at a rotary are three; diverging, merging and weaving. All the
other conflicts are converted into these three less severe conflicts.
1. Diverging: It is a traffic operation when the vehicles moving in one direction is
separated into different streams according to their destinations.
2. Merging: Merging is the opposite of diverging. Merging is referred to as the
process of joining the traffic coming from different approaches and
going to a common destination into a single stream.
3. Weaving: Weaving is the combined movement of both merging and
diverging movements in the same direction.
3. Exit Radius: The exit radius should be higher than the entry radius and the radius
of the rotary island so that the vehicles will discharge from the rotary at a higher rate.
A general practice is to keep the exit radius as 1.5 to 2 times the entry radius.
However, if pedestrian movement is higher at the exit approach, then the exit radius
could be set as same as that of the entry radius.
4. Island Radius: The radius of the central island is governed by the design speed, and
the radius of the entry curve. The radius of the central island, in practice, is given a
slightly higher radius so that the movement of the traffic already in the rotary will
have priority. The radius of the central island which is about 1.3 times that of the
entry curve is adequate for all practical purposes.
5. Width of Rotary: The entry width and exit width of the rotary is governed by the traffic
entering and leaving the intersection and the width of the approaching road. The width of the
carriageway at entry and exit will be lower than the width of the carriageway at the approaches
to enable reduction of speed. IRC suggests that a two lane road of 7 m width should be kept as
7 m for urban roads and 6.5 m for rural roads. Further, a three lane road of 10.5 m is to be
reduced to 7 m and 7.5 m respectively for urban and rural roads.
The width of the weaving section should be higher than the width at entry and exit. Normally
this will be one lane more than the average entry and exit width. Thus weaving width is given as,
where e1 is the width of the carriageway at the entry and e2 is the carriageway width at exit.
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
DESIGN ELEMENTS OF ROTARY cont…
6. Weaving length: Weaving length determines how smoothly the traffic can merge and
diverge. It is decided based on many factors such as weaving width, proportion of weaving
traffic to the non-weaving traffic etc. This can be best achieved by making the ratio of
weaving length to the weaving width very high. A ratio of 4 is the minimum value
suggested by IRC. Very large weaving length is also dangerous, as it may encourage over-
speeding.
Below Figure shows four types of movements at a weaving section, a and d are the non-
weaving traffic and b and c are the weaving traffic. Therefore,
This capacity formula is valid only if the following conditions are satisfied.
SOLUTION:
SOLUTION:
• Signs Road signs provide local information to drivers. Made from reflective material in
high-contrast colors. Signs may use words and symbols.
➢ Regulatory signs: They declare the accepted legal use of the immediate public roadway.
➢ Warning signs: Allow drivers to be aware of driving hazards like animal crossings or
twisting paths.
➢ Guiding or informational signs: Provide route and amenity information.
➢ Traffic signs: For the traffic control landscape.
• Barriers & Channelizers: Control traffic, warn against hazards, and mitigate accidents.
➢ Traffic delimiters & cones: are often placed temporarily to provide warning around
hazards or work zones.
➢ Highway barriers: help prevent head-on collisions and mark lanes.
➢ Channelizers & road barriers: are more permanent than traffic delimiters or
cones—though some may be removable for multi-access spaces.
• Signs Road signs provide local information to drivers. Made from reflective material in
high-contrast colors. Signs may use words and symbols.
➢ Regulatory signs: They declare the accepted legal use of the immediate public roadway.
➢ Warning signs: Allow drivers to be aware of driving hazards like animal crossings or
twisting paths.
➢ Guiding or informational signs: Provide route and amenity information.
➢ Traffic signs: For the traffic control landscape.
1. The control device should fulfill a need: Each device must have a specific purpose
for the safe and efficient operation of traffic flow.
2. It should command attention from the road users: For commanding attention, proper
visibility should be there. Also the sign should be distinctive and clear.
3. It should convey a clear, simple meaning: Clarity and simplicity of message is
essential for the driver even if he is less educated should properly understand the
meaning in short time.
4. Road users must respect the signs: Respect is commanded only when the drivers are
conditioned to expect that all devices carry meaningful and important messages.
Overuse, misuse and confusing messages of devices tends the drivers to ignore them.
5. The control device should provide adequate time for proper response from the
road users: The sign boards should be placed at a distance such that the driver could
see it and gets sufficient time to respond to the situation. For example, the STOP sign
which is always placed at the stop line of the intersection should be visible for atleast
one safe stopping sight distance away from the stop line.
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
COMMUNICATION TOOLS
A number of mechanisms are used by the traffic engineer to communicate with the
road user.
1. Color: The most commonly used colors are red, green, yellow, black, blue, and
brown .
2. Shape: The categories of shapes normally used are circular, triangular,
rectangular, and diamond shape. Two exceptional shapes used in traffic signs are
octagonal shape for STOP sign and use of inverted triangle for GIVE WAY (YIELD)
sign. Diamond shape signs are not generally used in India
3. Legend: For the easy understanding by the driver, the legend should be short,
simple and specific so that it does not divert the attention of the driver. Symbols are
normally used as legends so that even a person unable to read the language will
be able to understand that.
4. Pattern: Generally solid, double solid and dotted lines are used. Each pattern
conveys different type of meaning.
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
TYPES OF TRAFFIC SIGNS
• The major types of traffic control devices used are- traffic signs, road markings , traffic signals and
parking control.
• Different types of traffic signs are
• Regulatory signs: These signs require the driver to obey the signs for the safety of other road
users.
• Warning sign: These signs are for the safety of oneself who is driving and advice the drivers to
obey these signs
• Informatory signs: These signs provide information to the driver about the facilities available
ahead, and the route and distance to reach the specific destinations
In addition special type of traffic sign namely work zone signs are also available. These type of signs are
used to give warning to the road users when some construction work is going on the road. They are
placed only for short duration and will be removed soon after the work is over and when the road is
brought back to its normal condition.
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
REGULATORY SIGNS
These signs are also called mandatory signs because it is mandatory that the drivers must obey these
signs, else the control agency has the right to take legal action against the driver. These signs have
generally black legend on a white background. They are circular in shape with red borders. They are
classified as:
• Right of way series: They are the STOP sign and GIVE WAY sign.
• Speed series: Number of speed signs may be used to limit the speed of the vehicle on the road.
They include typical speed limit signs, truck speed, minimum speed signs etc.
• Movement series: These include turn signs, alignment signs, exclusion signs, one way signs etc.
• Parking series: They indicate not only parking prohibitions or restrictions, but also indicate
places where parking is permitted, the type of vehicle to be parked, duration for parking etc.
• Pedestrian series: These signs are meant for the safety of pedestrians and include signs
indicating pedestrian only roads, pedestrian crossing sites etc.
• Miscellaneous: It includes ”KEEP OF MEDIAN” sign, signs indicating road closures, signs
restricting vehicles carryingCEC-3170:
hazardous cargo, signs indicating vehicle weight limitations etc.
TRANSPORTATION: Traffic & Airport Engineering
INFORMATORY SIGNS
▪ Informative signs also called guide signs, are provided to assist the drivers to reach their desired
destinations.
▪ These are predominantly meant for the drivers who are unfamiliar to the place. The guide signs
are redundant for the users who are accustomed to the location.
▪ Examples are route markers, destination signs, mile posts, service information, etc.
▪ Route markers are used to identify numbered highways. They are written black letters on
yellow background.
▪ Destination signs are used to indicate the direction to the critical destination points, and to
mark important intersections. Distance in kilometers are sometimes marked to the right side of
the destination. They are, in general, rectangular with the long dimension in the horizontal
direction. They are color coded as white letters with green background.
▪ Mile posts are provided to inform the driver about the progress along a route to reach his
destination. Service guide signs give information to the driver regarding various services such as
food, fuel, medical assistance etc. They are written with white letters on blue background.
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
WARNING SIGNS
▪ Cycle: A signal cycle is one complete rotation through all of the indications provided.
▪ Cycle length: Cycle length is the time in seconds that it takes a signal to complete one
full cycle of indications. It indicates the time interval between the starting of of green for
one approach till the next time the green starts. It is denoted by C.
▪ Interval: Thus it indicates the change from one stage to another. There are two types of
intervals change interval and clearance interval. Change interval is also called the
yellow time indicates the interval between the green and red signal indications for an
approach. Clearance interval is also called all red is included after each yellow interval
indicating a period during which all signal faces show red and is used for clearing off the
vehicles in the intersection
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
DEFINITION & NOTATIONS cont…
▪ Yellow time (Amber time): It is the time after green interval before the signal
turns red. If not given, it is assumed to be 2 sec.
▪ Lost time: It indicates the time during which the intersection is not effectively
utilized for any movement. For example, when the signal for an approach turns
from red to green, the driver of the vehicle which is in the front of the queue, will
take some time to perceive the signal (usually called as reaction time) and some
time will be lost here before he moves.
Multiple movements done at a time is considered as one phase. In one cycle length,
there may be ‘n’ number of phases.
(Left turn traffic is always allowed.)
Cycle length = Time for all phases
The signal design procedure involves six major steps. They include the:
(1) Phase design,
(2) Determination of amber time and clearance time,
(3) Determination of cycle length,
(4) Apportioning of green time,
(5) Pedestrian crossing requirements, and
(6) The performance evaluation of the above design.
The objective is to design phases with minimum conflicts or with less severe conflicts.
There is no precise methodology for the design of phases. This is often guided by the
geometry of the intersection, flow pattern especially the turning movements, the relative
magnitudes of flow. Therefore, a trial and error procedure is often adopted.
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
PHASE DESIGN
To illustrate various phase plan options, consider a four legged intersection with through
traffic and right turns. Left turn is ignored.
The first issue is to decide how many phases are required. It is possible to have two, three,
four or even more number of phases.
(1) Two Phase Signals,
(2) Four Phase Signals CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
TWO-PHASE SIGNALS
• Two phase system is usually adopted if through traffic is significant compared to the
turning movements. For example in figure, non-conflicting through traffic 3 and 4 are
grouped in a single phase and non-conflicting through traffic 1 and 2 are grouped in
the second phase. However, in the first phase flow 7 and 8 offer some conflicts and
are called permitted right turns. Needless to say that such phasing is possible only if
the turning movements are relatively low. On the other hand, if the turning movements
are significant ,then a four phase system is usually adopted.
43
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
FOUR-PHASE SIGNALS
45
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
FOUR-PHASE SIGNALS cont…
46
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
METHODS TO DESIGN SIGNALS
47
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
WEBSTER METHOD
• Sum of ratio of normal flow to saturated flow value for roads A and B:
Y = yA + yB
Where, yA = qA/SA and yB = qB/SB
Saturated flow value (SA and SB) is dependent on road width: (veh/hr/lane)
GB = yB*(Co-L)/Y
48
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
NUMERICAL
49
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
SOLUTION
51
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
INTERVAL DESIGN
• There are two intervals, namely the change interval and clearance interval,
normally provided in a traffic signal. The change interval or yellow time is provided
after green time for movement. The purpose is to warn a driver approaching the
intersection during the end of a green time about the coming of a red signal. They
normally have a value of 3 to 6 seconds. The design consideration is that a driver
approaching the intersection with design speed should be able to stop at the stop line
of the intersection before the start of red time. Institute of transportation engineers
(ITE) has recommended a methodology for computing the appropriate length of
change interval which is as follows:
where y is the length of yellow interval in seconds, t is the reaction time of the driver, v85
is the 85th percentile speed of approaching vehicles in m/s, a is the deceleration rate of
vehicles in m/s2, g is the grade of approach expressed as a decimal. 52
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
INTERVAL DESIGN cont…
85th Percentile Speed (mph) – The 85th percentile speed is the speed at or below which 85
percent of the drivers travel on a road segment. Motorists traveling above the 85th percentile
speed are considered to be exceeding the safe and reasonable speed for road and traffic
conditions.
53
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
CYCLE TIME
• Cycle time is the time taken by a signal to complete one full cycle of iterations.
i.e. one complete rotation through all signal indications. It is denoted by C.
• Vehicles depart from an intersection when the green signal is initiated: As the
signal is initiated, the time interval between two vehicles, referred as headway,
crossing the curb line is noted. The first headway is the time interval between the
initiation of the green signal and the instant vehicle crossing the curb line.
• After few vehicles, the headway will become constant. This constant headway
which characterizes all headways beginning with the fourth or fifth vehicle, is
defined as the saturation headway, and is denoted as h. This is the headway
that can be achieved by a stable moving platoon of vehicles passing through a
green indication. If every vehicles require h seconds of green time, and if the
signal were always green, then s vehicles/per hour would pass the intersection.
54
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
CYCLE TIME cont…
55
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
CYCLE TIME cont…
• These differences for the first few vehicles can be added to get start up lost
time, l1 which is given by,
The green time required to clear N vehicles can be found out as,
where T is the time required to clear N vehicles through signal, l1 is the start-up
lost time, and h is the saturation headway in seconds.
56
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
EFFECTIVE GREEN TIME
• Effective green time is the actual time available for the vehicles to
cross the intersection. It is the sum of actual green time (Gi) plus the
yellow minus the applicable lost times. This lost time is the sum of
start-up lost time (l1) and clearance lost time (l2) denoted as tL. Thus
effective green time can be written as,
57
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
LANE CAPACITY
• The ratio of effective green time to the cycle length (gi/C )is defined as green ratio.
We know that saturation flow rate is the number of vehicles that can be moved in one
lane in one hour assuming the signal to be green always. Then the capacity of a lane
can be computed as,
where ci is the capacity of lane in vehicle per hour, si is the saturation flow rate in
vehicle per hour per lane, C is the cycle time in seconds.
58
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
NUMERICAL
59
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
NUMERICAL
60
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
CRITICAL LANE
During any green signal phase, several lanes on one or more approaches are
permitted to move. One of these will have the most intense traffic. Thus it
requires more time than any other lane moving at the same time. If sufficient
time is allocated for this lane, then all other lanes will also be well
accommodated. There will be one and only one critical lane in each signal
phase. The volume of this critical lane is called critical lane volume.
61
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
DETERMINATION OF CYCLE LENGTH
62
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
DETERMINATION OF CYCLE LENGTH cont…
Let the total number of critical lane volume that can be accommodated per hour is
given by Vc = Tg/h
63
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
DETERMINATION OF CYCLE LENGTH cont…
The above equation is based on the assumption that there will be uniform flow of
traffic in an hour. To account for the variation of volume in an hour, a factor called
peak hour factor, (PHF) which is the ratio of hourly volume to the maximum flow
rate, is introduced. Another ratio called v/c ratio indicating the quality of service is
also included in the equation.
64
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
DETERMINATION OF CYCLE LENGTH cont…
Highway capacity manual (HCM) has given an equation for determining the cycle
length which is a slight modification of the above equation.
Where N is the number of phases, L is the lost time per phase, (V/s)i is the ratio of
volume to saturation flow for phase i, XC is the quality factor called critical V/C
ratio where V is the volume and C is the capacity.
65
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
NUMERICAL
66
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
SOLUTION
67
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
AIRPORT ENGINEERING..
DEFINITION
• Any system that moves people and goods from one place to another falls under the
scope of transportation engineering, which majorly includes:
– Highways and roadways
– Railways
– Waterways
– Airways
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
DEFINITION
There are basically five imaginary surfaces which the FAA (Federal
Aviation Administration) applies to public-use airports for the
purpose of determining obstructions to air navigation.
❑ Conical surface: The conical surface extends outward and upward from
the horizontal surface at a slope of 20:1 for a horizontal distance of 4,000
feet, further defining the airspace around the airport.
❑ Runway Orientation
▪ Crosswind
▪ Wind Coverage
▪ Calm Period
❑ Runway Length
❑This is the period for which the wind intensity remains below 6.4 km/hr
❑This is common to all directions and hence, can be added to wind coverage for
that direction
❑Application of WIND ROSE diagram for finding the orientation of the runway
to achieve wind coverage.
❑Average wind data of 5 to 10 years is used for preparing wind rose diagrams.
The following is the average wind data for 10 years. An airport is to be designed for a single runway. Determine the
maximum wind coverage and the best direction of runway. The permissible cross wind component may be assumed
as suitable for mixed category of aircrafts.
Percentage of Time Total in Percentage of Time Total in
Wind each Wind each
Direction 6.4 – 25 25 – 40 40 – 60 direction 6.4 – 25 25 – 40 40 – 60
Direction direction
km/hr km/hr km/hr percent km/hr km/hr km/hr percent
N 7.4 2.7 0.2 10.3 SSW 6.3 3.2 0.5 10.0
NNE 5.7 2.1 0.3 8.1
SW 3.6 1.8 0.3 5.7
NE 2.4 0.9 0.6 3.9
WSW 1.0 0.5 0.1 1.6
ENE 1.2 0.4 0.2 1.8
W 0.4 0.1 0.0 0.5
E 0.8 0.2 0.0 1.0
WNW 0.2 0.1 0.0 0.3
ESE 0.3 0.1 0.0 0.4
SE 4.3 2.8 0.0 7.1 NW 5.3 1.9 0.0 7.2
SSE 5.5 3.2 0.0 8.7 NNW 4.0 1.3 0.3 5.6
S 9.7 4.6 0.0 14.3 TOTAL 86.5
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
TYPE I WIND ROSE DIAGRAM
➢ Safety requirements
➢ Airport Environment
❑ Normal Landing:
▪ The aircraft should come to a stop within 60 percent of landing distance assuming that the
pilot makes an approach at the proper speed and crosses the threshold of the runway at a
height of 15m.
▪ The runway of full strength is to be provided for the entire landing distance.
▪ Normal Landing: Calculations
Field Length(FL) = Landing distance (LD)
LD = Stopping distance (SD)/0.60
Length of full strength runway (FS) = LD
❑ Normal Take-off:
▪ The take-off distance must be, for a specific weight of aircraft, 115 percent of the actual distance
the aircraft uses to reach a height of 10.5m.
▪ The distance to reach a height of 10.5m should be equal to 115 percent of the lift- off distance.
▪ It requires a clearway at the end of the runway in the direction of take-off. This should not be
less than 150m wide. The upward slope of clearway from the end of the runway shall not
exceed 1.25 percent.
▪ Normal Take-off: Calculations
Field Length (FL) = Full strength runway(FS) + Clearway (CW)
Take-off distance (TOD) = 1.15D10.5m
Clearway (CW) = 0.5[TOD – 1.15(Lift-off distance, LOD)]
Take-off Run (TOR) = TOD – CW
Length of full strength runway (FS) = Take-off run (TOR)
❑ Stopping in Emergency:
▪ For the engine failure case, the take-off distance is the actual distance required to reach a
height of 10.5m with no percentage applied.
▪ It also incidentally recognizes the infrequency of occurrence of the engine failure.
▪ The aircraft accelerates to a speed V1, before finding that the engine has failed and then it
starts decelerating to stop at the end. Therefore, it requires a stopway along with a clearway.
▪ It is required to provide a clearway or a stopway of both in this case.
▪ Stopway is defined as a rectangular paved area at the end of runway in the direction of take-
off.
▪ It is a paved area in which an aircraft can be stopped after an interrupted take-off due to
engine failure.
▪ Its width is at least equal to the width of runway and the thickness of pavement less than that
of the runway, but yet sufficient to take the load of aircraft without failure.
➢ Standard Atmosphere
▪ Temperature at MSL is 15ºC
▪ Pressure at MSL is 760mm of Mercury(Hg)
▪ Air density is 1.225 kg/cu.m
➢ Temperature
▪ Temperature at Mean Sea Level (15ºC)
▪ Airport Reference Temperature (ART)
▪ Standard Temperature at an elevation (STE)
▪ Monthly mean of average daily temperature for the hottest month of the year (Ta)
▪ Monthly mean of the maximum daily temperature for the same month (Tm)
❑ Effect of Temperature
▪ Air density reduces as the elevation increases which in turn reduces the
lift on the wings of the aircraft.
▪ Thus reduces drag on aircraft while landing or requires longer distance
for producing necessary lift for the aircraft to fly.
▪ Increases basic runway length, the increase being 1% for every 1ºC rise
in airport reference temperature above the standard temperature at that
elevation. (as per ICAO, International Civil Aviation Organization)
❑ Altitude:
▪ Affects air density, atmospheric pressure and temperature.
▪ The reduction in air density or atmospheric pressure with height above
MSL affects the drag and lift forces and subsequent requirement of length
of runway.
▪ Requires longer runway length, increase being 7% per 300m altitude
above MSL.
❑ Elevation correction
❑ Temperature correction and
❑ Gradient correction
❑ Elevation correction
▪ Find the required basic field runway length under standard conditions ‘LB’
▪ Calculate elevation correction rate ‘Le’ and apply it to ‘LB’
▪ Add this value to ‘LB’. Lets denote it as ‘LE’.
❑ Temperature Correction
▪ Calculate airport reference temperature (ART)
▪ Calculate standard temperature at the given elevation (ST).
▪ Calculate temperature correction rate ‘Lt’ and apply it to ‘LE’.
▪ Add this value to ‘LE’. Lets denote this corrected length as ‘LT’
❑ Gradient Correction
▪ Calculate effective gradient, if not given.
❑Length of runway
❑Width of runway strip
❑Sight Distance
❑Longitudinal and Effective Gradient
❑Rate of Change of Longitudinal Gradient
❑Transverse Gradient
❑Safety Area
*Codal provisions for runway geometry, are given by International Civil Aviation Organization (ICAO)
CEC-3170: TRANSPORTATION: Traffic & Airport Engineering
AIRPORT CAPACITY
❑ Frontal System
❑ Open Apron system
❑ Finger System
❑ Satellite System