Gantt Chart AV Production

The AV-project is scheduled to start on April 7, 2025, and includes various tasks divided into pre-production, production, post-production, and evaluation phases. Each task has assigned members, progress percentages, and specific start and end dates, with most tasks in pre-production already completed. The project timeline extends through June 22, 2025, with key activities including filming, editing, and feedback collection.

Uploaded by

isabelle-hs17023
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views1 page

Gantt Chart AV Production

The AV-project is scheduled to start on April 7, 2025, and includes various tasks divided into pre-production, production, post-production, and evaluation phases. Each task has assigned members, progress percentages, and specific start and end dates, with most tasks in pre-production already completed. The project timeline extends through June 22, 2025, with key activities including filming, editing, and feedback collection.

Uploaded by

isabelle-hs17023
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

AV-project Project start: 4/7/2025

Display week: 4

SIMPLE GANTT CHART


Apr 28, 2025 May 5, 2025 May 12, 2025 May 19, 2025 May 26, 2025 Jun 2, 2025 Jun 9, 2025 Jun 16, 2025
28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
TASK ASSIGNED TO PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Pre production

Interview Tatiana & Isabelle 100% 4/7/25 4/8/25

Summary of information Tatiana 100% 4/8/25 4/10/25

Creat Persona Ariane 100% 4/10/25 4/13/25

Persona Infographic Pouya 100% 4/14/25 4/18/25

Brainstorm All members 100% 5/12/25 5/18/25

Script writing Tatiana 100% 5/15/25 6/1/25

Storyboard & Shot list Pouya 100% 5/22/25 5/29/25

Equipment preparation Pouya 100% 5/30/25 6/1/25

Call Sheet Isabelle 100% 5/20/25 6/1/25

Costume & prop preparation Isabelle 100% 5/23/25 5/29/25

Location permissions Tatiana 100% 5/26/25 5/28/25

Production

Equipment setup Pouya 100% 6/2/25 6/9/25

Rehearsals Cast Members 100% 5/26/25 6/1/25

Filming Pouya 100% 6/2/25 6/12/25

Audio supervision Pouya & Tatiana 100% 5/30/25 6/12/25

Prop & costume managementIsabelle 100% 5/30/25 6/12/25

Shot logging Isabelle 100% 5/30/25 6/12/25

Behind the scene Anh 100% 5/30/25 6/12/25

Post production

Footage selection Pouya 60% 6/9/25 6/15/25

Video editing Pouya 60% 6/9/25 6/15/25

Sound design Tatiana 60% 6/9/25 6/15/25

Color grading Pouya 60% 6/9/25 6/15/25

Voiceover / Subtitles Tatiana 75% 6/4/25 6/15/25

Exporting / Rendering Poya & Tatiana 0% 6/13/25 6/15/25

Evaluation

Feedback collection 6/16/25 6/22/25

Group self-evaluation 6/16/25 6/22/25

Report writing 60% 6/9/25 6/15/25

Budget & time review 60% 6/9/25 6/15/25

Project archiving 6/16/25 6/22/25

Insert new rows ABOVE this one