MALLARIIII

The evaluation report assesses the proposed road widening project in Barangay Maujao, Bulalacao, Mindoro Oriental, covering a length of 1.738 kilometers. While most requirements were met, the site development plan was not compliant and additional justification is needed for the project. Overall, further information and clarification are required before proceeding with the project.

Uploaded by

Reymart Gaan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views1 page

MALLARIIII

The evaluation report assesses the proposed road widening project in Barangay Maujao, Bulalacao, Mindoro Oriental, covering a length of 1.738 kilometers. While most requirements were met, the site development plan was not compliant and additional justification is needed for the project. Overall, further information and clarification are required before proceeding with the project.

Uploaded by

Reymart Gaan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Evaluation Report on the proposed Road Widening - Secondary Roads - Mindoro

Oriental/Occidental East Coastal Rd - K0195+262 - K0197+000 - Barangay Maujao ,


Bulalacao, Mindoro Oriental, R4B (Pending for total of <span
style='color:green;'>2</span> days) with project type & size: Item 3.4.1 Infrastructure
Projects/Roads and Bridges/Roads, new construction/National Road (1.738 Kilo meter in
Length with no critical slope) of DEPARTMENT OF PUBLIC WORKS AND
HIGHWAYS - SOUTHERN MINDORO DEO - Barangay Maujao, Bulalacao, Mindoro
Oriental, R4B

Requirement Compliant Remarks

Government Issued ID of Engr. Yes acceptable.


ANNIELYN E. PADULLO

Site Development Plan No Please, submit justification of


construction road project that is
not connected to another road and
is under Category D. and If the
total/final length will be more
than 2 Kms, please apply for an
ECC.

- and please coordinate to PEMU


office for the site validation.

Photos of Project Area taken Yes acceptable.


within 15 days from filing

Notarized Accountability Yes acceptable.


Statement of Engr. ANNIELYN
E. PADULLO

Over all Remarks: Requires submission of additional information or further clarification based on the above
results.