9 TT 2023
9 TT 2023
NEW DELHI
Coram:
Shri Jishnu Barua, Chairperson
Shri Ramesh Babu V., Member
Versus
ORDER
The Power Grid Corporation of India Limited (hereinafter referred to as “the
Petitioner”), had filed the instant Petition for the determination of transmission tariff
under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2019 (hereinafter referred to as “the 2019 Tariff Regulations”) for the
period from COD to 31.3.2024 in respect of the following transmission assets under
Asset-I: 400/220 kV 500 MVA ICT IV along with 400kV Bay at Biharsharif
(POWERGRID) Substation and 220 kV Bay at Biharsharif (BSPTCL) Substation
alongwith 220 kV interconnecting line from Biharsharif (BSPTCL) Substation to 220 kV
bushing of ICT installed at Biharsharif (POWERGRID) Substation;
Asset-II: Replacement of 220/132 kV, 1X50 MVA ICT with 220/132 kV 160 MVA ICT
along with suitable modification of bay equipment at Malda Substation;
Asset-III: Reconductoring of 220 kV D/C New Purnea – Purnea Ckt.-I and Ckt.-II
transmission line along with modification of 220 kV bays equipments at New Purnea &
Purnea Substations;
Asset-IV: 400/132 kV, 315 MVA ICT III along with associated bays at Lakhisarai
Substation;
Asset-V: 400/132 kV, 315 MVA ICT III along with associated bays at Banka Substation;
Asset-VI: 420 kV, 1X125 MVAR Bus Reactor along with associated bay at
Susbhasgram Substation;
Asset-VII: Conversion of 63 MVAR fixed line Reactor at New Purnea end of one circuit
of Kishanganj – New Purnea 400 kV D/C line to Switchable Line Reactor (SLR);
Asset-VIII: 400/132 kV, 500 MVA ICT along with associated bays at Maithon
Substation;
Asset-IX: Reconductoring of 400 kV D/C Rangpo – New Siliguri transmission line along
with modification of 400 kV bays equipments at New Siliguri Substations;
“
1) Approve the Transmission Tariff for the tariff block 2019-24 block for the assets
covered under this petition, as per para –8.3 above.
2) Admit the capital cost as claimed in the Petition and approve the Additional
Capitalisation incurred / projected to be incurred.
3) Approve the DOCO for the subject Assets as claimed and allow full tariff as
claimed under instant petition.
4) Approve the initial spares as claimed in the instant petition.
5) Allow the Petitioner to claim the overall security expenses and consequential
IOWC on that security expenses separately.
6) Allow the petitioner to recover the shortfall or refund the excess Annual Fixed
Charges, on account of Return on Equity due to change in applicable Minimum
Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as
amended from time to time) of the respective financial year directly without
making any application before the Commission as provided in Tariff Regulation
2019 as per para 8.3 above for respective block.
7) Approve the reimbursement of expenditure by the beneficiaries towards petition
filing fee, and expenditure on publishing of notices in newspapers in terms of
Regulation 70 (1) Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations, 2019, and other expenditure ( if any) in relation
to the filing of petition.
8) Allow the petitioner to bill and recover Licensee fee and RLDC fees and charges,
separately from the respondents in terms of Regulation 70 (3) and (4) Central
Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations,
2019.
9) Allow the petitioner to bill and adjust impact on Interest on Loan due to change
in Interest rate on account of floating rate of interest applicable during 2019-24
period, if any, from the beneficiaries.
10) Allow the Petitioner to bill and recover GST on Transmission Charges separately
from the respondents, if GST on transmission is levied at any rate in future.
Further, any taxes including GST and duties including cess etc. imposed by any
statutory/Govt./municipal authorities shall be allowed to be recovered from the
beneficiaries.
11) Allow interim tariff in accordance with Regulation 10(3) of Central Electricity
Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 for
purpose of inclusion in the PoC charges.
and pass such other relief as the Commission deems fit and appropriate under the
circumstances of the case and in the interest of justice.”
Background
3. The brief facts of the case are as follows:
the Board of Directors (BoD) of the Petitioner’s Company in its meeting held
₹2207.00 lakh based on the June 2017 price level. The project was scheduled
b. The Petitioner, vide affidavit dated 7.11.2022, has submitted Revised Cost
Transmission Lines:
i. Reconductoring of Rangpo – New Siliguri 400kV D/C line
The existing Twin ACSR Moose line is to be re-conductored with Twin
HTLS conductor
The existing New Purnea (400/220 kV) – Purnea (220/132 kV) 220 kV
D/C line needs to be re-conductored with a Single HTLS conductor
Substation:
(a) Extension at Biharsharif (PG) Sub-station
▪ 400/220 kV, 500 MVA ICT alongwith associated bays
▪ 220 kV ICT bay [along with 220 kV interconnecting line from this bay
to 220 kV bushing of ICT installed at Biharshariff (POWERGRID) Sub-
station
▪ Replacement of 220/132 kV, 1X50 MVA ICT with 220/132 kV, 160
MVA ICT along with suitable modification of bay equipment
▪ 420 kV, 125 MVAR Bus Reactor along with associated bay
be commissioned within 30 months from the date of IA, i.e., by 1.5.2020. The
follows:
4. The Petitioner has submitted the following regarding Assets-II, III, VII, and IX:
a. Asset-II: Replacement of 220/132 kV, 1X50 MVA ICT with 220/132 kV 160
MVA ICT along with suitable modification of bay equipment at Malda
Substation. (COD: 1.10.2019).
of an already existing 50 MVA ICT with the new 160 MVA ICT at the Malda
Sl.
Particulars
No.
400/200/132 kV Malda in ER (also
i Substation
includes suitable bay modification)
50 MVA ICT alongwtih associated bays
ii Original Asset
(220 kV and 132 kV)
iii COD of Original Asset 1.9.1995
Auto Transformer at Malda in Eastern
iv Project of Original Asset
Region
311/TT/2019 (Truing up for period 2014-
v Current Petition no. of Original Project 19 and transmission tariff for period 2019-
24).
30.9.2019
Date of replacement of Original asset (one day prior to COD of replacement; in
Vi
(50 MVA) with new asset (160 MVA) line with relevant provision of the 2019
Tariff Regulations)
vii Date of COD of New 160 MVA ICT 1.10.2019
Sl.
Particulars
No.
i Transmission line 220 kV D/C New Purnea – Purnea
ii Original Asset D/C line of 220 kV New Purnea - Purnea
iii COD of Original Asset 1.11.2003
LILO of 400 kV D/C Bonaigaon- Malda
iv Project of Original Asset line at Purnea and Substation at Purnea
(New) in Eastern Region
207/TT/2020 (Truing up for period 2014-
v Current Petition no. of Original Project 19 and transmission tariff for period 2019-
24).
20.12.2019
Date of replacement of Original
(one day prior to COD of replacement; in
vi conductor and New Siliguri’s bay
line with relevant provision of the 2019
equipment
Tariff Regulations)
vii Date of COD of New Asset 21.12.2019
The Petitioner has further submitted that the de-capitalization as per the
Sl.
Particulars
No.
I Substation 400/200kV New Purnea
Fixed line Reactor at New Purnea for one
ii Original Asset circuit of 400kV D/C New Siliguri – New
Purnea line.
iii COD of Original Asset 1.7.2011
iv Project of Original Asset ERSS-II in Eastern Region
327/TT/2019 (Truing up for period 2014-
V Current Petition no. of Original Project 19 and transmission tariff for period 2019-
24).
Switchable line Reactor at New Purnea
Vi New Asset after Conversion for one ckt. of 400kV D/C Kishanganj –
New Purnea line
5. The Petitioner has further submitted that the de-capitalization as per the provision
of the relevant regulation(s) will be done separately in the original project(s) against
6. The Respondents are distribution licensees and power departments that are
procuring transmission service from the Petitioner, mainly beneficiaries of the Eastern
Region.
7. The Petitioner has served a copy of the petition on the Respondents, and notice
regarding the filing of this Petition has also been published in newspapers in accordance
with Section 64 of the Electricity Act, 2003. None of the Respondents has filed a reply
to the Petition despite notice. No comments or suggestions have been received from
the general public in response to the aforesaid notice published in the newspapers by
the Petitioner.
8. This order is issued considering the submissions made by the Petitioner in the
petition vide affidavit dated 25.5.2022 and Petitioner’s affidavits dated 24.8.2022,
9. The hearing in this matter was held on 16.7.2024, and the order was reserved.
11. The Petitioner has claimed the following Interest on Working Capital (IWC) in
Asset-I
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
O&M Expenses 19.51 20.21 20.92 21.67 22.39
Maintenance Spares 35.11 36.38 37.65 39.01 40.31
Receivables 85.14 97.22 100.10 101.54 101.19
Total Working Capital 139.76 153.81 158.67 162.22 163.89
Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05
Interest on Working Capital 9.57 18.53 19.12 19.55 19.75
Asset-III
(₹ in lakh)
2019-20
(pro-rata
Particulars 2020-21 2021-22 2022-23 2023-24
102
days)
O&M Expenses 0.00 0.00 0.00 0.00 0.00
Maintenance Spares 0.00 0.00 0.00 0.00 0.00
Receivables 2.48 2.97 3.49 3.73 3.71
Total Working Capital 2.48 2.97 3.49 3.73 3.71
Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05
Interest on Working
0.08 0.36 0.42 0.45 0.45
Capital
Asset-IV
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
O&M Expenses 13.42 13.90 14.39 14.91 15.40
Maintenance Spares 24.15 25.02 25.90 26.83 27.73
Receivables 54.75 58.78 62.83 64.98 65.05
Total Working Capital 92.32 97.70 103.12 106.72 108.18
Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05
Interest on Working
2.80 11.77 12.43 12.86 13.04
Capital
Asset-V
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
91 days)
O&M Expenses 13.42 13.90 14.39 14.91 15.40
Maintenance Spares 24.15 25.02 25.90 26.83 27.73
Receivables 64.62 70.07 76.10 79.38 79.28
Total Working Capital 102.19 108.99 116.39 121.12 122.41
Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05
Interest on Working
3.06 13.13 14.02 14.59 14.75
Capital
Asset-VII
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
42 days)
O&M Expenses 2.68 2.77 2.87 2.97 3.08
Maintenance Spares 4.82 4.99 5.17 5.35 5.54
Receivables 5.52 6.17 6.80 7.06 7.20
Total Working Capital 13.02 13.93 14.84 15.38 15.82
Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05
Interest on Working
0.18 1.68 1.79 1.85 1.91
Capital
Asset-VIII
(₹ in lakh)
2020-21
Particulars (pro-rata 2021-22 2022-23 2023-24
244 days)
O&M Expenses 20.17 20.88 21.64 22.35
Maintenance Spares 36.31 37.59 38.94 40.24
Receivables 77.62 81.83 83.78 83.41
Total Working Capital 134.10 140.30 144.36 146.00
Rate of Interest (in %) 11.25 11.25 11.25 11.25
Interest on Working Capital 10.09 15.78 16.24 16.43
Asset-IX
(₹ in lakh)
2020-21
Particulars (pro-rata 2021-22 2022-23 2023-24
1 day)
O&M Expenses 0.07 0.07 0.07 0.07
Maintenance Spares 0.12 0.12 0.12 0.12
Receivables 249.71 259.63 271.66 269.78
Total Working Capital 249.90 259.82 271.85 269.97
Rate of Interest (in %) 11.25 11.25 11.25 11.25
Interest on Working Capital 0.08 29.23 30.58 30.37
Asset-XI
(₹ in lakh)
2021-22
Particulars (pro-rata 41 2022-23 2023-24
days)
O&M Expenses 4.60 4.76 4.93
Maintenance Spares 8.29 8.57 8.88
Receivables 70.94 74.54 79.56
Total Working Capital 83.83 87.87 93.37
Rate of Interest (in %) 10.50 10.50 10.50
Interest on Working Capital 0.99 9.23 9.80
Assets COD
Asset-I
400/220 kV 500 MVA ICT IV along with 400 kV Bay at
Biharsharif (POWERGRID) Sub-station and 220 kV
Bay at Biharsharif (BSPTCL) Substation along with 220 6.9.2019
kV interconnecting line from Biharsharif (BSPTCL)
Sub-station to 220 kV bushing of ICT installed at
Biharsharif (POWERGRID) Sub-station
Asset-II
Replacement of 220/132 kV, 1X50 MVA ICT with 1.10.2019
220/132 kV 160 MVA ICT along with suitable
modification of bay equipment at Malda Substation
Asset-III
Reconductoring of 220 kV D/C New Purnea-Purnea
Ckt.-I and Ckt.-II transmission line along with 21.12.2019
modification of 220 kV bays equipments
at New Purnea & Purnea Sub-stations
Asset-IV
400/132 kV, 315 MVA ICT III along with associated 31.12.2019
bays at Lakhisarai Sub-station
Asset-V 1.1.2020
Provided that the transmission licensee seeking the approval of the date of commercial
operation under this clause shall give prior notice of at least one month, to the generating
company or the other transmission licensee and the long term customers of its
transmission system, as the case may be, regarding the date of commercial operation:
Provided further that the transmission licensee seeking the approval of the date of
commercial operation of the transmission system under this clause shall be required to
submit the following documents along with the petition:
14. The Petitioner has submitted the following documents in support of COD of the
D/C New Purnea-Purnea Ckt.-I and Ckt.-II transmission line along with modification of
220 kV bay equipments at New Purnea and Purnea Substations, and in the case of
Asset-IX, the Petitioner has carried out Re-conductoring of the 400 kV D/C Rangpo-
New Siliguri transmission line along with modification of 400 kV bay equipment at New
Siliguri Substation.
18. We are of the view that in the case of Assets III, the Petitioner has carried out the
stringing of new conductors on existing towers using the same RoW. As per the scope
of work mentioned in the Investment Approval, the petitioner has mentioned the
replacement of terminal end equipment at both the substations, i.e., New Purnea and
Purnea. Based on the auditor certificate and Form-5 , it is noted that the petitioner has
not claimed any expenditure towards terminal end equipments at New Purnea and
Purnea Substations. .
19. In case of Asset-III, the Petitioner has replaced the conductors of Purnea-Purnea
(New) 220 kV D/C line of POWERGRID with HTLS conductor and claimed COD of the
ckt-1 and ckt-2 as 21.12.2019. The details of the existing Purnea-Purnea (New) 220 kV
D/C transmission line and tariff approval details of the same is as follows:
Name of the transmission COD of the transmission Petition No. under which
line asset considered tariff is approved.
220 kV Purnea-Purnea 1.11.2003 Vide order dated 21.09.2021
(New) D/C transmission in Petition No. 207/TT/2020
line has trued-up tariff for 2014-
19 and granted tariff for
2019-24 tariff Period.
20. As per the Petitioner’s submissions, it is observed that for Asset-III, the Petitioner
initially commissioned the 220 kV Purnea-Purnea (New) D/C transmission line in the
year 2003, and re-conductoring work has been completed on 21.12.2019. The existing
years as on 21.12.2019.
21. Regulation 3(73) of the 2019 Tariff Regulations defines useful life in relation to
transmission lines as 35 years. The towers installed in both transmission assets have
not completed their useful life, and only their conductor have been replaced under the
instant Petition are not new transmission assets. Instead, they are re-conductoring and
upgrading the already existing transmission assets, which are expenses in the nature
of additional capitalization in the transmission assets, for which the tariff has already
been approved.
22. The Petitioner is, accordingly, directed to claim the capital cost [under additional
of 220 kV Purnea-Purnea (New) D/C transmission line under the Transmission System,
namely LILO of 400 kV D/C Bonaigaon- Malda Transmission Line at Purnea and Sub-
station at Purnea (New) in Eastern Region in Petition No. 207/TT/2020 at the time of
truing up during 2019-24 tariff period and determination of transmission tariff for 2024-
29 tariff period. Accordingly, we are not inclined to grant a tariff for Asset-III in the instant
petition.
Asset-VII:
23. Similarly, in respect of Asset-VII, i.e., Conversion of 63 MVAR fixed line Reactor
at New Purnea end of one circuit of Kishanganj-New Purnea 400 kV D/C line to
Switchable Line Reactor (SLR), the Petitioner has commissioned the fixed line Reactor
at new Purnea end of one ckt. New Siliguri-New Purnea 400 kV D/C (quad) line on
1.7.2011, and the present scope of the work is only modification of the existing fixed
Reactor, which has completed about only 9 years of useful life as on 19.02.2020. Since
that the expenses incurred towards the fixed line Reactor into switchable line Reactor
claim the capital cost [conversion under additional capital expenditure (ACE)] incurred
Eastern Region Project” while filing true-up of tariff for the 2019-24 and determination
of tariff for the 2024-29 tariff period. Accordingly, we are not inclined to grant a tariff for
Asset-IX:
24. The Petitioner has carried out the stringing of new conductors on existing towers
using the same RoW. In the case of Asset-IX, the Petitioner has carried out the
replacement of the terminal bay equipment with high-rating equipment at the New
Siliguri substation. As per Form-5, it is noted that the petitioner has claimed an amount
of Rs. 934.82 lakhs towards substation equipment. As per the auditor certificate dated
4.08.2021, the petitioner has submitted that an amount of Rs. 1038.59 lakhs has been
25. In case of Asset-IX, the Petitioner initially commissioned the 400 kV D/C Teesta-
V-New Siliguri transmission line, which is part of the Transmission System associated
with Teesta (Stage-V) HEP in the Eastern Region. The Petitioner has made LILO of
the existing 400 kV D/C Teesta-V-New Siliguri transmission line at Rangpo Substation
and claimed the tariff for LILO of the existing 400 kV D/C Teesta-V-New Siliguri
transmission line under Sikkim Part B in Eastern Region. As such, the Asset -IX is partly
covered under the Teesta-V HEP Transmission System in the Eastern Region and
(The Petitioner in the instant tariff petition has claimed a tariff for re-conductoring of the
400 kV D/C Rangpo-New Siliguri (yellow portion of the above-mentioned diagram). It is
noted that the Petitioner in the case of Asset-IX has replaced only conductors of 400 kV
D/C Rangpo-New Siliguri transmission line with HTLS conductors and terminal end
equipments at New Siliguri and claimed COD as 31.3.2021.)
26. Regulation 3(73) of the 2019 Tariff Regulations defines useful life in relation to
transmission lines as 35 years. The towers installed in both transmission assets have
not completed their useful life, and only their conductor and associated bay equipment
have been replaced under the re-conductoring scheme. Regulation 3(73) of the 2019
Tariff Regulations defines the useful life of transmission lines as 35 years. The towers
conductors and associated bay equipment have been replaced under the re-
₹13,332.59 lakhs towards the transmission line and ₹1,038.59 lakhs towards the
substation.
27. We observe that the transmission assets covered in the instant Petition are not
new transmission assets. Instead, they are re-conductoring and upgrading the already
capitalization in the transmission assets, for which the tariff has already been approved.
transmission line, the Petitioner is directed to claim the capital cost [under additional
associated with Teesta (Stage-V) HEP in Eastern Region, while filing true-up of
transmission tariff for 2019-24 and determination of tariff for 2024-29 tariff period.
Accordingly, we are not inclined to grant a tariff for Asset-IX in the instant petition.
29. In view of the above discussions, we are not inclined to grant a tariff for Assets-
Petitioner’s CMD Certificate, the COD approved for the transmission assets is
considered for the purpose of transmission charges of the 2019-24 tariff period as
follows:
Capital Cost
31. Regulation 19 of the 2019 Tariff Regulations provides as follows:
“19. Capital Cost: (1) The Capital cost of the generating station or the transmission
system, as the case may be, as determined by the Commission after prudence check in
accordance with these regulations shall form the basis for determination of tariff for
existing and new projects.
(2) The Capital Cost of a new project shall include the following:
(3) The Capital cost of an existing project shall include the following:
(a) Capital cost admitted by the Commission prior to 1.4.2019 duly trued up by
excluding liability, if any, as on 1.4.2019;
(b) Additional capitalization and de-capitalization for the respective year of tariff
as determined in accordance with these regulations;
(c) Capital expenditure on account of renovation and modernisation as admitted
by this Commission in accordance with these regulations;
(d) Capital expenditure on account of ash disposal and utilization including
handling and transportation facility;
(e) Capital expenditure incurred towards railway infrastructure and its
augmentation for transportation of coal upto the receiving end of generating
station but does not include the transportation cost and any other appurtenant
cost paid to the railway; and
(f) Capital cost incurred or projected to be incurred by a thermal generating
station, on account of implementation of the norms under Perform, Achieve
and Trade (PAT) scheme of Government of India shall be considered by the
Commission subject to sharing of benefits accrued under the PAT scheme
with the beneficiaries.
(4) The capital cost in case of existing or new hydro generating station shall also include:
(a) cost of approved rehabilitation and resettlement (R&R) plan of the project in
conformity with National R&R Policy and R&R package as approved; and
(b) cost of the developer’s 10% contribution towards Rajiv Gandhi Grameen
Vidyutikaran Yojana (RGGVY) and Deendayal Upadhyaya Gram Jyoti Yojana
(5) The following shall be excluded from the capital cost of the existing and new projects:
(a) The assets forming part of the project, but not in use, as declared in the tariff
petition;
(b) De-capitalised Assets after the date of commercial operation on account of
replacement or removal on account of obsolescence or shifting from one
project to another project:
Provided further that unless shifting of an asset from one project to another is
of permanent nature, there shall be no de-capitalization of the concerned
assets.
23.3.2022 for Assets-I, II, III, IV, V, VI, VII, VIII, IX, X, and XI respectively has claimed
capital cost incurred as on COD and Additional Capital Expenditure (ACE) projected to
be incurred in respect of the transmission asset and the same are as follows:
(₹ in lakh)
Apportioned Projected ACE
Expendit Estimated
Approved
Assets ure up to completion
Cost (As per 2019-20 2020-21 2021-22 2022-23 2023-24
COD cost
FR)
Asset-I
3772.19 2224.21 957.30 205.14 136.75 68.38 0.00 3591.78
33. The capital cost claimed vis-à-vis the approved RCE cost is as follows:
Asset-I 3772.19 3602.24 2224.21 957.30 205.14 136.75 68.38 0.00 3591.78
Cost Over-run
34. The Petitioner has submitted that the total apportioned approved cost as per the
FR is ₹35365.89 lakh. The total apportioned cost as per the RCE is ₹34789.00 lakh and
the estimated completion cost is ₹33806.64 lakh. Thus, there is no cost over-run with
35. The Petitioner has further submitted that on an individual asset/ element basis,
completion cost for Asset-I, Asset-II, Asset-VI, Asset-VII, Asset-VIII, and Asset-IX.
However, there is cost overrun in Asset-III, Asset-IV, Asset-V, Asset-X, and Asset-XI on
same aspect.
36. The Petitioner, vide affidavit dated 7.11.2022, has submitted that there is no cost
over-run of the estimated completion cost as compared to the cost approved in the RCE
37. The Petitioner has submitted the details of cost variation with respect to Asset-I,
Asset-XI as follows:
The comparison of RCE cost of ₹34789 lakh is carried out against the approved cost
Sr. Variation
Variation on account of:
No. (₹ in lakh) (In %)
(i) Price Variation
DPR to LOA for approved scope
a 1840 5.13
(on competitive bidding while awarding)
Provision presently kept as per contract price
b 990 2.76
variation clause by Regions.
Sub-Total (PV) 2830 7.89
(ii) Variation in quantities of approved Items 1115 3.11
(iii) Addition of Item 464 1.29
(iv) Compensation for Transmission lines (-) 3182 (-) 8.87
Sub-Total (i to iv) 1227 3.42
(v) Other Reasons (IEDC and IDC)
A IEDC (incl. Contingencies) (-) 1597 (-) 4.45
b IDC (-) 724 (-) 2.02
Sub- Total (IEDC & IDC) (-) 2321 (-) 6.47
Grand Total (-) 1094 (-) 3.05
It may be seen from the above table that there is a variation of (-) ₹1094 lakh (i.e.
There has been an increase in the cost of the project by ₹2830 lakh on this account,
which works out to 7.89% of the approved cost as per details given as follows:
The Petitioner submitted that an amount of ₹1840 lakh has been incurred from the
time of Investment approval of project till award of various contracts (DPR to LOA)
for approved scope based on prices received as per transparent competitive bidding
and further price variation amount of ₹990 lakh is kept in line with contract price
variation clause.
for all packages under this project were awarded only after approval of Competent
Authority as per Detailed Operation Procedure (DoP) to the lowest evaluated and
Further, it may be submitted that a provision of ₹990 lakh towards price variation
clause as per contract is kept in RCE under the head of price variation by Region.
In the subject RCE, quantities of various Substation and transmission line equipment
and civil works have been considered as per actual site requirement and latest
amendments.
With respect to Substation, there has been an addition of circuit breakers, increase
various quantities of civil works like PCC, reinforcement steel, and excavation, etc.
w.r.t. DPR envisaged quantities, and also there is a decrease in quantities of GIS
Bus Duct, etc. resulting in net increase in cost of project by ₹528 lakh.
With respect to transmission line, there has been an addition of hot line stringing
of civil works and also there is a decrease in quantities of hardware fittings and
conductor accessories as per actual site requirement resulting in overall net increase
Further, there is an increase in project cost by ₹457 lakh due to an increase in the
cost of infrastructure works. In the DPR, there was a provision of ₹200 lakh (₹20
lakhs for each Substation) for miscellaneous infrastructure works. In the RCE, an
amount of ₹657 lakh has been provisioned by the site as per actual requirement
Maintenance, T&P-cum-Fitter Room for proper and safe storage, fencing, etc.
There is an increase in project cost by ₹464 lakh due to the addition of cost pertaining
to 80 MVAR, 765 kV 1-phase shunt Reactor at Ranchi (Bero), which has been
Based on the approved DPR cost, there was a provision of ₹3319 lakh under this
head. However, based on the actual expenditure incurred and the balance anticipated
Total IDC and IEDC under the project have decreased by ₹2321 lakh in comparison
to the approved cost, which works out to (-) 6.47% as per the following break-up:
Decrease in IEDC
As per the investment approval, the IEDC, including contingencies for the project, was
estimated at ₹ 4020 lakh on total DCO cost (i.e., IEDC @10.75% & contingency @3%
on total DCO cost), whereas in the RCE, it has been considered as per actual
expenditure, which works out to ₹2423 lakh, resulting in an overall decrease of ₹1597
lakh.
Decrease in IDC
Interest During Construction (IDC) for the project as per the Investment Approval was
estimated as ₹2207 lakh, whereas based on actual funds flow, the IDC for the project
in the RCE works out to ₹1483 lakh. Thus, there is a decrease of ₹724 lakh in IDC.
dated 16.11.2023 has submitted the information with regard to Asset-V and Asset-XI
and stated that there is a cost overrun vis-à-vis their individual FR apportioned costs.
The reasons submitted for variation in the Asset-wise cost are as follows:
39. The Petitioner has submitted that the cost variation was mainly due to actual site
conditions, the awarded rate, and other associated factors which were beyond the
40. Further, the Petitioner has submitted that the Revised Cost Estimate (RCE) for
the subject project has also been submitted vide affidavit dated 7.11.2022, wherein
detailed justification at the project level has also been provided for other transmission
41. We have considered the submissions made by the Petitioner and find that there
compared to the FR cost of ₹35365.89 lakh, the estimated completion cost of ₹33806.64
lakh is lower by ₹1559.25 lakh, including ACE as mentioned above, which is within the
FR apportioned approved cost. Therefore, there is no cost overrun for the project as a
whole.
42. The Petitioner has submitted that the capital cost varied due to variation in the
quantity of approved items like circuit breakers, an increase in the quantities of control,
approved items vs actual items installed, and the reasons for the variation of Substation
items. Therefore, the Petitioner is directed to submit the asset-wise details along with
the variation between the awarded cost and completion cost at the time of true-up with
valid justification at the time of truing up. It is noted that the petitioner has claimed the
capital cost of ₹464 lakh due to the addition of cost pertaining to an 80 MVAR, 765 kV
1-phase shunt Reactor at Ranchi (Bero), which has been supplied as owner-supplied
material (OSM). The petitioner is directed to clarify the reasons for claiming the same
in the instant petition instead of claiming under self-insurance reserves at the time of
truing-up.
43. It is further observed that the cost variation is primarily on account of variation in
estimated prices and final competitive prices. The asset-wise completion cost is within
the FR apportioned approved cost for Asset-I, Asset-II, Asset-VI, Asset-VII, Asset-VIII.,
and Asset-IX. The Petitioner has submitted an RCE vide affidavit dated 7.11.2022 for
Asset-III, Asset-IV, Asset-V, Asset-X, and Asset-XI. Against the total RCE approved
cost of ₹34789.00 lakh, the estimated completed cost of ₹33806.64 lakh is within the
approved cost. Furthermore, there is no cost overrun with respect to any transmission
asset in the instant project as well. Accordingly, the cost variation is allowed. However,
as discussed above, Asset-III, Asset-VII, and Asset-IX have not been considered for
Time overrun
44. As per the IA dated 2.11.2017, the transmission project was scheduled to be
commissioned within 30 months from the date of the IA which works out to be 1.5.2020.
However, the details of the actual commissioning of the transmission assets are as
follows:
Asset-V, and Asset-VI. However, there is a delay in the commissioning of the Asset-VIII
46. The detailed reasons submitted by the Petitioner for time overrun in case of the
Asset-VIII:
Unseasonal Rainfall:
47. The unseasonal and unprecedented rainfall in and around Maithon (under
Dhanbad District of Jharkhand) during the lean rainfall season of March-April-May 2020
48. The Petitioner has further submitted that this period of March-May is also defined
compared to the Long Period Average (LPA) in the Maithon Area (Dhanbad). Cyclonic
activity in the Bay of Bengal and the development of low pressure over areas of
49. The Petitioner has further submitted that most of the works associated with ICT
at Maithon were completed and only testing and commissioning (T&C) related activities
were pending by February 2020. The T&C related activities were planned for the period
March-April 2020, keeping in mind the lean or minimal rainfall pattern in and around
over these months affected the execution of completion of Testing and commissioning
related works and compliances as the heavy rains/thunderstorm conditions not ideal for
51. The Petitioner has further submitted that the Commission, vide its order dated
29.4.2011, had approved the Model Transmission Service Agreement (Model TSA).
52. Clause 14.2.1 of the said Model TSA defines “force majeure” as follows:
exceptional adverse weather conditions which are in excess of the statistical measures
for the last hundred (100) years can be considered as force majeure, and in such cases,
54. The Petitioner has further submitted that in the month of March 2020, the total
rainfall recorded was about 69 mm, which was 247% of normal rainfall. Similarly, the
actual rainfalls during April-May 2020 were also above the normal pattern and were in
excess. The same is also testified by the Yearly Weather Report 2020 for the State of
rainfall in the month of March 2020 in Jharkhand, with 76% excess in the District of
Dhanbad (Maithon) when calculated cumulatively for the period of March-May 2020.
55. The Petitioner has submitted that works related to T&C were affected largely due
to unprecedented rains during the lean rainfall period, due to unseasonal and
uncontrollable on the part of the Petitioner. However, the Petitioner had put in their best
efforts to bring back the project as close as possible to the scheduled timeline, only to
COVID-19:
56. COVID-19 was identified by the WHO as a Global Pandemic and a force majeure
event across all segments/ verticals of the global business/ industry. This situation, by
57. The projects undertaken by the Petitioner were no exception, facing a multitude
of challenges as they navigate through largely uncharted territory with projects and
supply lines experiencing highly unique and mounting risks leading to delays in
Unlock:
The lockdown restricted people from stepping out of their homes across the country. All
Services such as food shops, banks and ATMs, petrol pumps, other essentials, and
their manufacturing were exempted. The Home Ministry stated that anyone who fails to
follow the restrictions can face up to a year in jail. The Government (Centre & State)
had locked down all the cities and restricted the movement from one place to another.
The movement restriction affected the critical supply chain, transportation, worker/
complete halt of ongoing projects. The lockdown imposition was a voluntary step back
of the construction workers, which was also unforeseen and unavoidable. The sites
were either closed or access was largely restricted as a result of measures to contain
the COVID-19 outbreak. The contractors thus were not able to carry out the works as a
result of action by governments to prevent the spread of the outbreak. Specific Covid-
delayed issuance of permits, travel restrictions, and loss time or inefficiencies due to
the need to practice social distancing on the job site are just a few of the issues that had
scheduling consequences. Also, the lack of engineering and technical support and
supply chain disruptions were the major factors impacting the project schedule and
project, faced delays due to the squeezing of supply lines and construction activities.
inefficiencies further pushed back completion dates. The construction could not be
started immediately. The biggest hurdle is that the supply chain has not been fully
restored. Besides, considering the scenario that if anybody gets infected on the
construction site after work has started, the area would be sealed and all related people
will be quarantined for 14-28 days. Construction pace plummeted or came to a grinding
halt. With the halting of various line construction activities, the work was at a standstill
Majeure issues, which led to disruption in the global supply chain and project execution
Further, the Petitioner has submitted that the Ministry of Power (MoP), Government of
India vide letter dated 27.7.2020 had provided an extension of 5 month with respect to
SCOD not prior to 25.3.2020) owing to unforeseen circumstances forced by the Covid-
19 pandemic.
Asset-X:
The detailed reasons submitted by the Petitioner for time overrun in the case of the
transmission Asset-X are more or less similar to those submitted for Asset-VIII.
Therefore, the same is not repeated here for the sake of brevity.
Asset-XI
In response to RoP for the hearing dated 30.10.2023, the Petitioner vide affidavit dated
16.11.2023 has submitted the information with regard to Asset-XI and submitted the
Transportation Constraints
The Petitioner has submitted that 100 MVA ICT could be dispatched from its factory
location (Vadodara) by September 2019 (27.9.2019) for transit towards its eventual
location at Rangpo GIS Station. It is submitted that the ICT was ready for transit by July
2019; however, due to severe rainfall and landslides, the route in hilly areas in Sikkim
was severely affected. Landslides, being a natural calamity, are a force majeure
situation, and time was lost for the repair of the roads and bridges that fell on the route.
Therefore, the dispatch of ICT was held up for this period of 3 months from July to
September 2019. The Petitioner has further submitted that on the way to Rangpo GIS
(and its distributaries) in the mountainous terrain in the State of Sikkim. On one such
bridge, namely the Rangpo Check post (entry) Bridge (ICT reached this check post on
movement of cargo over this bridge, on account of which the 100 MVA ICT could not
be transported beyond this point. The Petitioner has submitted that, as per the orders
of the Rangpo Administration, the incessant rains had taken a severe toll and washed
away additional support pillars and foundations. Thus, load restrictions were introduced
as a safety precaution till the re-strengthening of the same. The Circular of Sikkim
Govt.’s Rangpo Administration has been filed. Further, it is submitted that the route
survey was carried out in 2018 and finalized by December 2018. However, the
information in this circular restricting allowable load passage was passed on by the
overcome this hurdle, owing to time constraints, it was decided to build a temporary
shallow bridge-cum-road over the river-bed to transport the ICT beyond this point.
However, to construct this temporary passage over the river bed, another issue came
up, i.e., high water level/ severe water current due to heavy rains and high hydro
season. Thus, the matter could be taken up at ground level only after high hydro season
had ceased, i.e., in the Winter Season (December 2019). After the
beyond this check post in the last week of December 2019 and eventually reach Rangpo
GIS on 21.1.2020. Thus, considerable time from October 2019 to December 2019, i.e.,
The reasons explained by the Petitioner for the delay in the execution of the Asset-XI
are more-or-less similar to the reasons explained for the delay in the execution of Asset-
VIII. Therefore, the same is not repeated here for the sake of brevity.
The Petitioner has submitted that when it approached the concerned authorities /forums
for availing the requisite shutdowns, the requests were denied for a very long time owing
the existing 400/220/132 Rangpo GIS. Therefore, it was a necessity to obtain multiple
shutdowns for terminal and pre-commissioning works. The following table shows
S.
S/D applied S/D Approved Remarks
No.
(i)Due to High hydro period.
2 3.12.2020 8.12.2020 Not approved Not approved Later provided from 08.12.2020 to
10.12.2020
3 11.12.2020 16.12.2020 Not approved Not approved Later provided from 16.12.2020 to
18.12.2020
Due to the above facts and circumstances, the commissioning of Asset-XI was delayed
for about 348 days. Continuous shutdown on a regular basis was allowed from
19.2.2022.
The Petitioner has submitted that the shutdowns were denied because of various
reasons that include high and peak hydro, monsoon season with heavy rains, and re-
conductoring works of 400kV D/C Rangpo-Siliguri line, which is the Asset-IX of the
instant petition. The Petitioner has further submitted that 400/220/132 KV Rangpo is
one of the most important and critical substations of Eastern region-II. It is the gateway
between all hydel generations of Sikkim to the rest of India. This Station has either direct
Rangnichu, and Chuzachen. Total 5 nos. 400/220 KV 315 MVA (3*105MVA) ICT and
four nos. 220/132KV 100MVA ICTs are present at Rangpo. During peak hydropower
58. In response to RoP for the hearing dated 30.10.2023, the Petitioner vide affidavit
dated 16.11.2023 has submitted the information with regard to the status of the project
59. Further, in response to RoP for the hearing dated 15.12.2023, the Petitioner vide
affidavit dated 10.1.2024 has submitted reasons for delay in the commissioning of
i. Teesta Urja Limited v. PTC India Limited and Ors.: 2020 SCC Online
CERC 145.
ii. Power Grid Corporation of India Limited v. Assam Electricity Grid
Corporation Limited and Ors.: 2018 SCC Online CERC 229.
61. We have considered the submissions made by the Petitioner. We have also gone
through the documentary evidence placed on record by the Petitioner to justify the time
from the date of IA, i.e., 2.11.2017. Accordingly, the SCOD works out to 1.5.2020
against which Asset-I, Asset-II, Asset-IV, Asset-V, Asset-VI, Asset-VIII, Asset-X, and
no delay in the case of Asset-I, Asset-II, Asset-IV, Asset-V, and Asset-VI. However,
there is a time overrun of 91 days, 336 days, and 659 days in respect of Asset-VIII,
62. The Petitioner has submitted that the time overrun in the case of all the
transmission assets is due to COVID-19. The Petitioner has further submitted that in
the case of Asset-VIII and Asset-X, it was due to unseasonal rainfall. Asset-XI got
was delayed due to problems in the transportation of the Asset to Rangpo and
petition and the information filed vide affidavits dated 16.11.2023 and 10.1.2024 in
response to the RoPs for hearing dated 30.10.2023 and 15.12.2023, respectively.
64. With respect to Asset-VIII, Asset-X, and Asset-XI, the Petitioner has submitted
that the Ministry of Power vide letter dated 27.7.2020 has provided an extension of 5
months in respect to SCOD for the inter-State transmission project (under construction
forced by the COVID-19 pandemic. The relevant portion of the letter dated 27.7.2020 is
as follows:
various transmission project sites having been severely affected by the nationwide
and the request of the transmission utilities for extension of SCOD to mitigate the issues
decided that all inter-State transmission projects which were under construction as on
date of lockdown, i.e., 25.3.2020 shall get an extension of 5 months in respect of SCOD
provided the SCOD of these projects was post 25.3.2020. It is also relevant to note that
the transmission licensees whose projects fall under the criteria specified therein and
as such does not require the individual licensee to substantiate/ make out its case for
availing the dispensation provided under the said order. In the present case, the
transmission project of the Petitioner was under construction stage as on the date of
lockdown, i.e., 25.3.2020 and the SCOD of the transmission project was 1.5.2020, i.e.,
post 25.3.2020 and, therefore, the dispensation provided by the MoP vide its letter dated
27.7.2020 is applicable in the instant case. Accordingly, the SCOD of the transmission
66. As per the I.A., the SCOD of the transmission project is 1.5.2020. In terms of the
above letter dated 27.7.2020, the revised SCOD of the transmission project is
considered as 1.10.2020. However, there is a time overrun of 183 days and 506 days
67. With respect to Asset-X, the Petitioner has submitted the reasons for delay as
unprecedented rainfall during the lean season in addition to COVID-19. The Petitioner
has submitted that the time period from October 2019 to March 2020, i.e., about 5
months, is impacted on account of unprecedented rainfall during the lean period. As the
COD of the Asset is revised to 1.10.2020, we examine the reasons given by the
find any reason to examine the time overrun before the revised SCOD. The Petitioner
has not submitted any further reasons for delay after 1.10.2020. It is further noted that
Asset-X is a spare Reactor unit at New Ranchi Sub-station. As per the IA dated
i.e., by 1.5.2020. As per Form-5A, it is noted that the Petitioner had awarded the work
on 13.12.2017 for the supply of a spare Reactor from TBEA. It seems that the
asset. The Petitioner has not submitted when the Reactor reached the site after the
award of the project on 13.12.2017. As per the petitioners' affidavit dated 16.03.2023,
The Petitioner is directed to submit the reasons for the delay from 1.10.2020 to
2.4.2021, and the same will be reviewed at the time of truing-up. The Petitioner further
directed to submit the details of transportation, the details of the Reactor at the time of
truing-up. We are not inclined to condone the total delay of 183 days beyond 1.10.2020,
and the same will be reviewed at the time of truing-up based on the justification for the
68. As per the I.A. dated 2.11.2017, the SCOD of the transmission assets was
1.5.2020. Asset-XI was put into commercial operation on 19.2.2022. Thus, there is a
time overrun of 659 days in the case of Asset-XI. The Petitioner has submitted that the
main reasons for delay are (i) Transportation constraints (July 2019 to September 2019
and October 2019 to December 2019), about 5 months, unprecedented rainfall during
requisite shutdown.
69. As stated above, we have already revised the SCOD of Asset-XI as of 1.10.2020,
and it has been put into commercial operation on 19.2.2022. Thus, the time overrun in
the case of Asset-XI, as per the revised SCOD, is 506 days. Therefore, we examine the
reasons given by the Petitioner for the time overrun beyond the revised SCOD of
1.10.2020, as we do not find any reason to examine the time overrun before the revised
SCOD.
70. The Petitioner has submitted that the project was also affected by the second
wave of COVID-19, as the lockdown was again imposed by the GoI, and several
restrictions were imposed by the State Government on the movement of personnel and
imposed between 1.4.2021 and 30.6.2021 on the movement of men and materials. Due
to the severity of the second COVID-19 wave, all the manufacturing (supply chains) and
71. We have considered the submissions of the Petitioner. The relevant portion of
72. As per the above, it is observed that extension of three months shall be granted
only when SCOD is after 1.4.2021. In the instant case, the revised SCOD of the
in the instant case. It is further observed that the Petitioner had applied for a shutdown
in the month of April, 2020, which means that the Petitioner had completed all erection
works and only testing and commissioning were pending. It is also observed that the
Petitioner submitted application for energisation of 100 MVA ICT, 220/132 kV GIS bay
at PGCIL on 17.12.2020 and the CEA vide letter dated 12th March, 2021 had granted
CEA Energisation Certificate for 100 MVA ICT, the second wave of Covid-19 did not
impact the commissioning of the instant transmission asset. Based on the above
discussion, we are of the view that the Second Wave of COVID-19 did not impact the
73. The petitioner has submitted that the petitioner has sought a shutdown from April
2020 to October 2020, which was denied due to the high hydro period and also due to
reconductoring works of the Rangpo-Siliguri 400 kV D/C line. The shutdown was not
approved, due to which the time period of 180 days was impacted. We have gone
OCC minutes for the denial of shutdown during this period. It is further noted that the
SCOD of the asset is revised to 1.10.2020, so the time overrun sought from April2020
74. The Petitioner has submitted that it had applied for a shutdown from 3.12.2020
to 17.12.2021, on account of getting approval for the shutdown, which caused a delay
of 168 days.
“(2) The “uncontrollable factors” shall include but shall not be limited to the following:
a. Force Majeure events;
b. Change in law; and
c. Land acquisition except where the delay is attributable to the generating company or
the transmission licensee.”
“(25) ‘Force Majeure’ for the purpose of these regulations means the events or
circumstances or combination of events or circumstances including those stated below
which partly or fully prevents the generating company or transmission licensee to
complete the project within the time specified in the Investment Approval, and only if
such events or circumstances are not within the control of the generating company or
transmission licensee and could not have been avoided, had the generating company
or transmission licensee taken reasonable care or complied with prudent utility practices:
(a) Act of God including lightning, drought, fire and explosion, earthquake, volcanic
eruption, landslide, flood, cyclone, typhoon, tornado, geological surprises, or
exceptionally adverse weather conditions which are in excess of the statistical measures
for the last hundred years; or
78. As per the above, it is noted that Regulations 22(1), 3(10), and 3(25) of the 2019
Majeure events, Change in Law, and delays in land acquisition not attributable to the
statutory approvals (unless caused by the developer), which hinder timely project
execution despite reasonable care and adherence to prudent utility practices. We are
of the view that shutdown is a planned activity, and obtaining shutdown approval does
not fall under change in law and Force majeure events. Therefore, we are not inclined
79. The petitioner has submitted that the time period(s) from 3.12.2020 to 8.12.2020
(05 days), 11.12.2020 to 16.12.2020 (06 days), 19.12.2020 to 23.12.2020 (05 days),
24.01.2021 to 26.01.2021 (03 days), 13.06.2021 to 13.07.2021 (30 days) totalling about
gone through the letters issued by ERLDC and based on the request of the petitioner,
ERLDC has granted shutdown approval. Therefore, we are of the view that the delay
on account of shutdown approval by ERLDC has no merit and the same is not
condoned.
80. The Petitioner has submitted minutes of the 174th OCC, 180th OCC, 181st
OCC,184th OCC and 185th OCC. As per the annexure of the various OCC minutes, it
220 kV and 132 kV bay, but when it had finally obtained a shutdown for charging the
ICT, it was not submitted. Therefore, we are not inclined to condone the time period of
Time
Revised Time
Revised Time overrun
Asset SCOD COD Time overrun not
SCOD Overrun condone
Overrun condoned
d
Asset-I 6.9.2019 NIL NIL NA NA
1.10.2019 NIL NIL NA NA
Asset-II
81. As we have already decided above that we are not inclined to grant a tariff for
Asset-III, Asset-VII, and Asset-IX, therefore, we are dealing with Assets-I, II, IV, V, VI,
Petition and has submitted the statement showing IDC claim, discharge of IDC liability
(₹ in lakh)
IDC IDC IDC IDC
IDC as per IDC
discharge discharge discharge discharge
Assets the Auditor Discharged
d during d during d during d during
Certificate up to COD
2019-20 2020-21 2021-22 2022-23
Asset-I 31.91 27.99 1.46 2.46 0.00 0.00
Asset-II 10.67 6.93 3.74 0.00 0.00
Asset-IV 43.17 12.98 2.09 28.10 0.00 0.00
Asset-V 53.28 7.76 45.52 0.00 0.00
Asset-VI 21.16 5.36 0.31 15.49 0.00
Asset-VIII 154.37 143.26 8.56 2.55 0.00
Asset-X 3.74 3.74 0.00 0.00
Asset-XI 157.88 120.66 4.72 32.51
this order, there is a claim for time overrun of 183 and 506 days from the actual COD
for Asset-X and Asset-XI, respectively, and the same has been disallowed.
Accordingly, the IDC on a cash basis up to the COD has been worked out based on the
loan details given in the Statement showing discharge of IDC and Form-9C for the
transmission assets. The IDC claimed and considered as on COD and summary of
discharge of IDC liability up to COD and thereafter, for the purpose of tariff
(₹ in lakh)
IDC
Disallow
ed Due
to
IDC IDC IDC IDC IDC
IDC as per computa
IDC Discharge discharge discharge discharge discharge
Assets Auditor tional
Allowed d upto d during d during d during d during
Certificate error/tim
COD 2019-20 2020-21 2021-22 2022-23
e over-
run not
condone
d
Asset-I 31.91 0.52 31.39 27.46 1.46 2.47 0.00 0.00
84. Further, the Petitioner has claimed IEDC for the transmission assets as per the
Auditor Certificates. The Petitioner has further submitted that the entire amount of IEDC
for the transmission assets has been discharged up to COD. As the time overrun for the
Asset-X and Asset-XI has not been condoned, we disallow the IEDC on a pro rata basis
in these 2 transmission assets. The IEDC claimed, as per the Auditor Certificate, IEDC
Initial Spares
85. Regulation 23(d) of the 2019 Tariff Regulations provides that Initial Spares shall
be capitalised as a percentage of plant and machinery cost up to the cut-off date, subject
(₹ in lakh)
Ceiling limit
Plant and
Initial Spares mentioned as
Assets Particulars machinery
claimed per Regulation
cost
(In %)
Asset-I Sub-station (Brownfield) 3001.92 113.89 6.00
Asset-II Sub-station (Brownfield) 1266.86 72.05 6.00
Asset-IV Sub-station (Brownfield) 2040.94 91.86 6.00
Asset-V Sub-station (Brownfield) 2644.04 91.66 6.00
Asset-VI Sub-station (Brownfield) 927.42 78.34 6.00
Asset-VIII Sub-station (Brownfield) 2372.45 106.42 6.00
Asset-X Sub-station (Brownfield) 1069.24 39.03 6.00
Asset-XI Sub-station (Brownfield) 3435.6 163.52 7.00
follows:
Spares Discharge
Total initial spares in the Auditor certificate (₹ in lakh)
Asset name
COD 2019-20 2020-21 2021-22
TL SS TL SS TL SS TL SS TL SS
Asset-I 0.00 113.89 0.00 83.42 0.00 9.40 0.00 14.32 0.00 6.75
Asset-II 0.00 72.05 0.00 66.91 0.00 5.14 0.00 0.00 0.00 0.00
Asset-IV 0.00 91.86 0.00 76.47 0.00 0.00 0.00 6.54 0.00 8.85
Asset-V 0.00 91.66 0.00 79.06 0.00 0.00 0.00 3.87 0.00 8.73
Asset-VI 0.00 78.34 0.00 75.26 0.00 3.08 0.00 0.00 0.00 0.00
Asset-VIII 0.00 106.42 0.00 98.29 0.00 0.00 0.00 5.69 0.00 2.44
Asset-X 0.00 39.03 0.00 30.55 0.00 0.00 0.00 0.00 0.00 8.48
88. We have considered the submissions of the Petitioner. Based on the information
available on record, the Initial Spares for the transmission asset are allowed as per the
respective percentage of the Plant and Machinery Cost as on the cut-off date. The Initial
Plant and
Machiner
y cost
(excludin
Norms as Initial Initial
g Initial Initial
per 2019 Spares Spares
IDC/IEDC, Spares Spares
Assets Particulars Tariff disallowe Allowed
Land claimed allowable
Regulatio d (₹ in (₹ in lakh)
cost and (₹ in lakh) (₹ in lakh)
ns (In %) lakh)
Cost of
Civil
Works) (₹
in lakh)
D=(A-
A B C B)*C/(100 E=B-D
-C)
Sub-station 3001.92 113.89 6.00 184.34 0.00 113.89
Asset-I
Transmission Line 390.58 0.00 1.00 0.00 0.00 0.00
Asset-II Sub-station 1266.86 72.05 6.00 76.26 0.00 72.05
Asset-IV Sub-station 2040.94 91.86 6.00 124.41 0.00 91.86
Asset-V Sub-station 2644.04 91.66 6.00 162.92 0.00 91.66
89. Accordingly, there are excess Initial Spares claimed for Asset-VI. Therefore, the
Initial Spares have been allowed as per the 2019 Tariff Regulations. The capital cost
(₹ in lakh)
Capital Cost
claimed as Excess IS Capital Cost as
Undischarged IDC
on COD IDC Disallowed IEDC Disallowed Disallowed on COD
Assets as on COD
(Auditor (B) (D) upto COD (G) = (A-B-C-D-
(C)
Certificate) (E) E-F)
(A)
Asset-I 2224.21 0.52 3.93 0.00 0.00 2219.76
Asset-II 733.10 0.13 3.75 0.00 0.00 729.22
Asset-IV 1650.96 1.08 29.56 0.00 0.00 1620.32
Asset-V 2096.24 1.03 44.77 0.00 0.00 2050.44
Asset-VI 776.88 0.59 15.81 0.00 21.06 739.42
Asset-VIII 2275.99 14.30 10.95 0.00 0.00 2250.74
Asset-X 1001.84 1.23 0.00 28.49 0.00 972.12
Asset-XI 3342.52 104.59 53.29 144.27 0.00 3040.37
De-capitalisation:
90. In Form-10B, the Petitioner has submitted the de-capitalisation details in case of
Assets-II, III, VII, and IX. The Petitioner has submitted that the de-capitalisation will be
carried out as per the provisions of the tariff regulations separately in the original
91. We have considered the submissions of the Petitioner. The asset-wise de-
Asset-II:
92. The Commission had trued-up the transmission tariff for the 2014-19 and granted
the tariff for 50 MVA ICT at Malda Substation vide order dated 27.1.2021 in Petition No.
311/TT/2019. The Petitioner has replaced the 50 MVA ICT with a 160 MVA ICT. We
have considered the submissions made by the Petitioner. The Petitioner is directed to
Asset-III:
93. In the case of Asset-III, the Petitioner has proposed to decapitalise only the
conductors and insulators. The Petitioner is directed to decapitalise the same in Petition
No. 207/TT/2020, while filing the true-up of the 2019-24 tariff period. The Petitioner is
further directed to explore how the aforesaid conductors and insulators can be
capitalised at other locations as per need and put to use, or their salvage value needs
Asset-IX:
94. In case of Asset-IX, the Petitioner has submitted that de-capitalisation of the 400
kV Teesta (Stage-V) Siliguri Transmission Line and LILO of 400 kV D/C Teesta V-
Siliguri Line at Rangpo will be carried out separately under Petition No. 465/TT/2020
“24. Additional Capitalisation within the original scope and upto the cut-off date
Provided that in case of any replacement of the assets, the additional capitalization
shall be worked out after adjusting the gross fixed assets and cumulative depreciation
of the assets replaced on account of de-capitalization.
(2) The generating company or the transmission licensee, as the case may be shall
submit the details of works asset wise/work wise included in the original scope of work
along with estimates of expenditure, liabilities recognized to be payable at a future date
and the works deferred for execution.”
96. The Petitioner has claimed that the ACE incurred/ projected to be incurred is
mainly on account of balance/ retention payments, and hence the same is claimed
under Regulations 24(1)(a) and 24(1)(b) of the 2019 Tariff Regulations. The Petitioner
has claimed capital cost as per the cash IDC discharge as on 31.3.2024 as follows:
97. In response, the Petitioner vide affidavit dated 24.8.2022 has submitted that the
element-wise details of ACE claimed and the Liability flow statement in the instant
petition have been submitted vide Form-12 submitted in the Petition. The details of the
(₹ in lakh)
Outsta
Outsta
nding
Year of nding
Part Liabili
Asset Actual Liabilit
Party icul ty as Discharge Additional Liability Recognised
No. Capital y as on
ar on
isation 31.3.20
1.4.20
24
19
201 202 202 202 202 Total 201 202 202 202 202 Total
9- 0- 1- 2- 3- (2019- 9- 0- 1- 2- 3- (2019-
20 21 22 23 24 24) 20 21 22 23 24 24)
TBEA 189. 40.5 27.0 13.5
TL 270.24 270.24 0.00
Energ 2019- 17 4 2 1
Asset-I
y Pvt 20 1097.3 768. 164. 109. 54.8
SS 1097.33 0.00
Ltd 3 13 60 73 7
TBEA
Energ 2019- 150. 170. 250.
Asset-II SS 320.00 320.00 0.00 250.00 0.00
y Pvt 20 00 00 00
Ltd
TBEA
Energ 2019- 120. 215. 180. 60.1
Asset-IV SS 576.06 576.06 0.00
y Pvt 20 23 36 35 2
Ltd
TBEA
Energ 2019- 174. 305. 305. 87.2
Asset-V SS 872.57 872.57 0.00
y Pvt 20 51 40 40 6
Ltd
TBEA
Energ 2019- 53.0 123. 30.0
Asset-VI SS 206.48 206.48 0.00
y Pvt 20 8 40 0
Ltd
TBEA
SS,
Asset- Energ 2020- 202. 200.
BC& 402.58 402.58 0.00
VIII y Pvt 21 58 00
W
Ltd
TBEA
Energ 2021- 187. 51.6 25.8
Asset-X SS 265.28 265.28 0.00
y Pvt 22 52 2 1
Ltd
TBEA
SS,
Energ 2021- 48.5 350. 300.
Asset-XI BC& 698.59 698.59 0.00
y Pvt 22 9 00 00
W
Ltd
98. We have considered the submissions of the Petitioner. The actual / projected
ACE allowed is subject to truing up in respect of the transmission asset, and the same
is as follows:
(₹ in lakh)
Particulars 2019-20 2020-21 2021-22 2022-23
ACE as per Auditor’s certificate 957.30 205.14 136.75 68.38
Add: IDC Discharged 1.46 2.47 0.00 0.00
ACE allowed in the instant order 958.76 207.61 136.75 68.38
Asset-II:
(₹ in lakh)
Particulars 2019-20 2020-21
ACE as per Auditor’s certificate 400.00 170.00
Add: IDC Discharged 0.00 3.75
ACE allowed in the instant order 400.00 173.75
Asset-IV:
(₹ in lakh)
Particulars 2019-20 2020-21 2021-22 2022-23
ACE as per Auditor’s
120.23 215.36 180.35 60.12
certificate
Add: IDC Discharged 2.09 27.47 0.00 0.00
ACE allowed in the
122.32 242.83 180.35 60.12
instant order
Asset-V:
(₹ in lakh)
Particulars 2019-20 2020-21 2021-22 2022-23
ACE as per Auditor’s certificate 174.51 305.40 305.40 87.26
Add: IDC Discharged 0.00 44.77 0.00 0.00
ACE allowed in the instant order 174.51 350.17 305.40 87.26
Asset-VI:
(₹ in lakh)
Particulars 2019-20 2020-21 2021-22
ACE as per Auditor’s certificate 53.08 123.40 30.00
Add: IDC Discharged 0.31 15.50 0.00
Less: Excess IS 3.08 0.00 0.00
ACE allowed in the instant order 50.31 138.90 30.00
Asset-VIII:
(₹ in lakh)
Particulars 2020-21 2021-22
ACE as per Auditor’s certificate 202.58 200.00
Add: IDC Discharged 8.56 2.39
ACE allowed in the instant order 211.14 202.39
Asset-X:
(₹ in lakh)
Particulars 2021-22 2022-23 2023-24
ACE as per Auditor’s certificate 187.85 51.62 25.81
Add: IDC Discharged 0.00 0.00 0.00
ACE allowed in the instant order 187.85 51.62 25.81
99. The capital cost considered for the transmission asset for the 2019-24 tariff
period is as follows:
(₹ in lakh)
Approved ACE 2019-24 Estimated
Capital Cost
Assets Completio
as on COD 2019-20 2020-21 2021-22 2022-23 2023-24
n Cost
Asset-I 2219.76 958.76 207.61 136.75 68.38 0.00 3591.26
Asset-II 729.22 400.00 173.75 0.00 0.00 0.00 1302.97
Asset-IV 1620.32 122.32 242.83 180.35 60.12 0.00 2225.94
Asset-V 2050.44 174.51 350.17 305.40 87.26 0.00 2967.78
Asset-VI 739.42 50.31 138.90 30.00 0.00 0.00 958.63
Asset-VIII 2250.74 211.14 202.39 0.00 0.00 2664.27
Asset-X 972.12 187.85 51.62 25.81 1237.40
Asset-XI 3040.37 101.88 350.00 300.00 3792.26
Debt-Equity ratio
“18. Debt-Equity Ratio: (1) For new projects, the debt-equity ratio of 70:30 as on date
of commercial operation shall be considered. If the equity actually deployed is more than
30% of the capital cost, equity in excess of 30% shall be treated as normative loan:
Provided that:
i. where equity actually deployed is less than 30% of the capital cost, actual
equity shall be considered for determination of tariff:
ii. the equity invested in foreign currency shall be designated in Indian rupees
on the date of each investment:
iii. any grant obtained for the execution of the project shall not be considered
as a part of capital structure for the purpose of debt: equity ratio.
(2) The generating company or the transmission licensee, as the case may be, shall
submit the resolution of the Board of the company or approval of the competent authority
in other cases regarding infusion of funds from internal resources in support of the
utilization made or proposed to be made to meet the capital expenditure of the
generating station or the transmission system including communication system, as the
case may be.
(4) In case of the generating station and the transmission system including
communication system declared under commercial operation prior to 1.4.2019, but
where debt: equity ratio has not been determined by the Commission for determination
of tariff for the period ending 31.3.2019, the Commission shall approve the debt: equity
ratio in accordance with clause (1) of this Regulation.
(6) Any expenditure incurred for the emission control system during the tariff period as
may be admitted by the Commission as additional capital expenditure for determination
of supplementary tariff, shall be serviced in the manner specified in clause (1) of this
Regulation.”
101. The debt-equity considered for the purpose of computation of tariff for the 2019-
Asset-I
ACE Capital Cost
Capital Cost as
during as on In
Funding on COD In % In %
2019-24 31.3.2024 %
(₹ in lakh)
(₹ in lakh) (₹ in lakh)
Debt 1553.83 70.00 960.05 70.00 2513.88 70.00
Equity 665.93 30.00 411.45 30.00 1077.38 30.00
Total 2219.76 100.00 1371.50 100.00 3591.26 100.00
Asset-II
ACE Capital Cost
Capital Cost
during as on
Funding as on COD In % In % In %
2019-24 31.3.2024
(₹ in lakh)
(₹ in lakh) (₹ in lakh)
Debt 510.45 70.00 401.62 70.00 912.07 70.00
Equity 218.77 30.00 172.12 30.00 390.89 30.00
Total 729.22 100.00 573.75 100.00 1302.97 100.00
Asset-V
ACE Capital Cost
Capital Cost as
during as on
Funding on COD In % In % In %
2019-24 31.3.2024
(₹ in lakh)
(₹ in lakh) (₹ in lakh)
Debt 1435.31 70.00 642.14 70.00 2077.45 70.00
Equity 615.13 30.00 275.20 30.00 890.33 30.00
Total 2050.44 100.00 917.34 100.00 2967.78 100.00
Asset-VI
ACE Capital Cost
Capital Cost
during as on
Funding as on COD In % In % In %
2019-24 31.3.2024
(₹ in lakh)
(₹ in lakh) (₹ in lakh)
Debt 517.59 70.00 153.45 70.00 671.04 70.00
Equity 221.83 30.00 65.76 30.00 287.59 30.00
Total 739.42 100.00 219.21 100.00 958.63 100.00
Asset-VIII
ACE Capital Cost
Capital Cost as
during as on
Funding on COD In % In % In %
2019-24 31.3.2024
(₹ in lakh)
(₹ in lakh) (₹ in lakh)
Debt 1575.52 70.00 289.47 70.00 1864.99 70.00
Equity 675.22 30.00 124.06 30.00 799.28 30.00
Total 2250.74 100.00 413.53 100.00 2664.27 100.00
Asset-X
ACE
Capital Cost as Capital Cost as on
during
Funding on COD In % In % 31.3.2024 In %
2019-24
(₹ in lakh) (₹ in lakh)
(₹ in lakh)
Debt 680.48 70.00 185.70 70.00 866.18 70.00
Equity 291.64 30.00 79.58 30.00 371.22 30.00
Total 972.12 100.00 265.28 100.00 1237.40 100.00
Asset-XI
Capital Cost
Capital Cost ACE during
as on
Funding as on COD In % 2019-24 In % In %
31.3.2024
(₹ in lakh) (₹ in lakh)
(₹ in lakh)
Debt 2128.26 70.00 526.32 70.00 2654.58 70.00
Equity 912.11 30.00 225.57 30.00 1137.68 30.00
Total 3040.37 100.00 751.88 100.00 3792.25 100.00
“33. Depreciation: (1) Depreciation shall be computed from the date of commercial
operation of a generating station or unit thereof or a transmission system or element
thereof including communication system. In case of the tariff of all the units of a
generating station or all elements of a transmission system including communication
system for which a single tariff needs to be determined, the depreciation shall be
computed from the effective date of commercial operation of the generating station or
the transmission system taking into consideration the depreciation of individual units:
(2) The value base for the purpose of depreciation shall be the capital cost of the
asset admitted by the Commission. In case of multiple units of a generating station or
multiple elements of a transmission system, weighted average life for the generating
station of the transmission system shall be applied. Depreciation shall be chargeable
from the first year of commercial operation. In case of commercial operation of the
asset for part of the year, depreciation shall be charged on pro rata basis.
(3) The salvage value of the asset shall be considered as 10% and depreciation
shall be allowed up to maximum of 90% of the capital cost of the asset:
Provided that the salvage value for IT equipment and software shall be
considered as NIL and 100% value of the assets shall be considered depreciable;
Provided further that in case of hydro generating stations, the salvage value shall
be as provided in the agreement, if any, signed by the developers with the State
Government for development of the generating station:
Provided also that the capital cost of the assets of the hydro generating station
for the purpose of computation of depreciated value shall correspond to the percentage
of sale of electricity under long-term power purchase agreement at regulated tariff:
(4) Land other than the land held under lease and the land for reservoir in case of
hydro generating station shall not be a depreciable asset and its cost shall be excluded
from the capital cost while computing depreciable value of the asset.
(5) Depreciation shall be calculated annually based on Straight Line Method and at
rates specified in Appendix-I to these regulations for the assets of the generating
station and transmission system:
Provided that the remaining depreciable value as on 31st March of the year
closing after a period of 12 years from the effective date of commercial operation of the
station shall be spread over the balance useful life of the assets.
(6) In case of the existing projects, the balance depreciable value as on 1.4.2019
shall be worked out by deducting the cumulative depreciation as admitted by the
(7) The generating company or the transmission licensee, as the case may be, shall
submit the details of proposed capital expenditure five years before the completion of
useful life of the project along with justification and proposed life extension. The
Commission based on prudence check of such submissions shall approve the
depreciation on capital expenditure.
(9) Where the emission control system is implemented within the original scope of the
generating station and the date of commercial operation of the generating station or
unit thereof and the date of operation of the emission control system are the same,
depreciation of the generating station or unit thereof including the emission control
system shall be computed in accordance with Clauses (1) to (8) of this Regulation.
a) twenty five years, in case the generating station or unit thereof is in operation
for fifteen years or less as on the date of operation of the emission control
system; or
b) balance useful life of the generating station or unit thereof plus fifteen years,
in case the generating station or unit thereof is in operation for more than fifteen
years as on the date of operation of the emission control system; or
c) ten years or a period mutually agreed by the generating company and the
beneficiaries, whichever is higher, in case the generating station or unit thereof
has completed its useful life.”
103. The depreciation has been worked out considering the admitted capital
expenditure as on the COD and thereafter up to 31.3.2024. The Weighted Average Rate
of Depreciation (WAROD) at Annexure has been worked out for the transmission asset
as per the rates of depreciation specified in the 2019 Tariff Regulations. The
Asset-I
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
Depreciation
A Opening Gross Block 2219.76 3178.52 3386.13 3522.88 3591.26
B ACE 958.76 207.61 136.75 68.38 0.00
C Closing Gross Block (A+B) 3178.52 3386.13 3522.88 3591.26 3591.26
Asset-II
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
183 days)
Depreciation
A Opening Gross Block 729.22 1129.22 1302.97 1302.97 1302.97
B ACE 400.00 173.75 0.00 0.00 0.00
C Closing Gross Block (A+B) 1129.22 1302.97 1302.97 1302.97 1302.97
D Average Gross Block (A+C)/2 929.22 1216.09 1302.97 1302.97 1302.97
Weighted average rate of
E 5.28 5.28 5.28 5.28 5.28
Depreciation (WAROD) (In %)
F Balance useful life of the asset 25 25 24 23 22
Lapsed life at the beginning of
G 0 0 1 2 3
the year
Aggregate Depreciable Value (D
H 836.30 1094.49 1172.67 1172.67 1172.67
* 90%)
Depreciation during the year
I 24.53 64.21 68.80 68.80 68.80
(D * E)
Aggregate Cumulative
J Depreciation at the end of the 24.53 88.74 157.54 226.33 295.13
year
Remaining Aggregate
K Depreciable Value at the end of 811.77 1005.74 1015.13 946.34 877.54
the year (H – J)
Asset-IV
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
Depreciation
A Opening Gross Block 1620.32 1742.64 1985.47 2165.82 2225.94
Asset-V
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
91 days)
Depreciation
A Opening Gross Block 2050.44 2224.95 2575.12 2880.52 2967.78
B ACE 174.51 350.17 305.40 87.26 0.00
C Closing Gross Block (A+B) 2224.95 2575.12 2880.52 2967.78 2967.78
D Average Gross Block (A+C)/2 2137.69 2400.03 2727.82 2924.15 2967.78
Weighted average rate of
E 5.73 5.68 5.64 5.61 5.61
Depreciation (WAROD) (In %)
F Balance useful life of the asset 24 24 23 22 21
Lapsed life at the beginning of the
G 0 0 1 2 3
year
Aggregate Depreciable Value (D *
H 1933.75 2169.97 2465.08 2641.78 2681.05
90%)
Depreciation during the year (D *
I 30.44 136.38 153.79 164.16 166.46
E)
Aggregate Cumulative Depreciation
J 30.44 166.82 320.61 484.77 651.23
at the end of the year
Remaining Aggregate Depreciable
K 1903.31 2003.15 2144.47 2157.01 2029.81
Value at the end of the year (H – J)
Asset-VI
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
79 days)
Depreciation
A Opening Gross Block 739.42 789.73 928.63 958.63 958.63
Asset-VIII
(₹ in lakh)
2020-21
Particulars (pro-rata 2021-22 2022-23 2023-24
244 days)
Depreciation
A Opening Gross Block 2250.74 2461.88 2664.27 2664.27
B ACE 211.14 202.39 0.00 0.00
C Closing Gross Block (A+B) 2461.88 2664.27 2664.27 2664.27
D Average Gross Block (A+C)/2 2356.31 2563.08 2664.27 2664.27
Weighted average rate of
E 5.24 5.24 5.24 5.24
Depreciation (WAROD) (In %)
F Balance useful life of the asset 25 25 24 23
Lapsed life at the beginning of the
G 0 0 1 2
year
Aggregate Depreciable Value (D *
H 2120.68 2306.77 2397.84 2397.84
90%)
Depreciation during the year (D *
I 82.61 134.35 139.69 139.69
E)
Aggregate Cumulative Depreciation
J 82.61 216.96 356.66 496.35
at the end of the year
Remaining Aggregate Depreciable
K 2038.07 2089.81 2041.18 1901.49
Value at the end of the year (H – J)
Asset-X
(₹ in lakh)
2021-22
Particulars (pro-rata 364 2022-23 2023-24
days)
Depreciation
A Opening Gross Block 972.12 1159.97 1211.59
B ACE 187.85 51.62 25.81
C Closing Gross Block (A+B) 1159.97 1211.59 1237.40
Asset-XI
(₹ in lakh)
2021-22
Particulars (pro-rata 41 2022-23 2023-24
days)
Depreciation
A Opening Gross Block 3040.37 3142.26 3492.26
B ACE 101.88 350.00 300.00
C Closing Gross Block (A+B) 3142.26 3492.26 3792.26
D Average Gross Block (A+C)/2 3091.31 3317.26 3642.26
Weighted average rate of
E 5.28 5.28 5.28
Depreciation (WAROD) (In %)
F Balance the useful life of the asset 25 25 24
Lapsed life at the beginning of the
G 0 0 1
year
Aggregate Depreciable Value (D *
H 2782.18 2985.53 3278.03
90%)
Depreciation during the year (D *
I 18.33 175.15 192.31
E)
Aggregate Cumulative Depreciation
J 18.33 193.49 385.80
at the end of the year
Remaining Aggregate Depreciable
K 2763.85 2792.05 2892.23
Value at the end of the year (H – J)
“32. Interest on loan capital: (1) The loans arrived at in the manner indicated in
Regulation 18 of these regulations shall be considered as gross normative loan for
calculation of interest on loan.
(5) The rate of interest shall be the weighted average rate of interest calculated on
the basis of the actual loan portfolio after providing appropriate accounting adjustment
for interest capitalized:
Provided that if there is no actual loan for a particular year but normative loan
is still outstanding, the last available weighted average rate of interest shall be
considered;
(5a) The rate of interest on loan for installation of emission control system shall be the
weighted average rate of interest of actual loan portfolio of the emission control system
or in the absence of actual loan portfolio, the weighted average rate of interest of the
generating company as a whole shall be considered.
(6) The interest on loan shall be calculated on the normative average loan of the
year by applying the weighted average rate of interest.
(7) The changes to the terms and conditions of the loans shall be reflected from
the date of such re-financing.”
105. The Weighted Average Rate of IoL (WAROI) has been considered on the basis
of the rate prevailing as on the COD. The Petitioner has prayed that the change in
interest rate due to the floating rate of interest applicable, if any, during the 2019-24
tariff period will be adjusted. Accordingly, the floating rate of interest, if any, shall be
considered at the time of true up. Therefore, the IoL has been allowed in accordance
with Regulation 32 of the 2019 Tariff Regulations for the transmission asset and is as
follows:
Asset-I
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
A Gross Normative Loan 1553.83 2224.96 2370.29 2466.01 2513.88
Asset-II
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
183 days)
A Gross Normative Loan 510.45 790.45 912.07 912.07 912.07
Cumulative Repayments up to the
B 0.00 24.53 88.74 157.54 226.33
Previous Year
C Net Loan-Opening (A-B) 510.45 765.92 823.33 754.54 685.74
D Additions due to ACE 280.00 121.62 0.00 0.00 0.00
E Repayment during the year 24.53 64.21 68.80 68.80 68.80
F Net Loan-Closing (C+D-E) 765.92 823.33 754.54 685.74 616.94
G Average Loan (C+F)/2 638.18 794.63 788.93 720.14 651.34
Weighted Average Rate of Interest
H 7.7176 7.7185 7.7193 7.7193 7.7149
on Loan (In %)
I Interest on Loan (G*H) 24.63 61.33 60.90 55.59 50.25
Asset-IV
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
A Gross Normative Loan 1134.22 1219.84 1389.82 1516.07 1558.15
Cumulative Repayments up to the
B 0.00 22.94 123.98 236.33 355.04
Previous Year
C Net Loan-Opening (A-B) 1134.22 1196.91 1265.84 1279.73 1203.11
D Additions due to ACE 85.62 169.98 126.25 42.08 0.00
E Repayment during the year 22.94 101.04 112.35 118.70 120.29
F Net Loan-Closing (C+D-E) 1196.91 1265.84 1279.73 1203.11 1082.82
G Average Loan (C+F)/2 1165.56 1231.37 1272.79 1241.42 1142.97
Weighted Average Rate of Interest
H 7.4723 7.4711 7.4700 7.4700 7.4676
on Loan (In %)
I Interest on Loan (G*H) 21.89 92.00 95.08 92.73 85.35
Asset-VI
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
79 days)
A Gross Normative Loan 517.59 552.81 650.04 671.04 671.04
Cumulative Repayments up to the
B 0.00 8.71 54.08 103.90 154.52
Previous Year
C Net Loan-Opening (A-B) 517.59 544.09 595.96 567.14 516.52
D Additions due to ACE 35.22 97.23 21.00 0.00 0.00
E Repayment during the year 8.71 45.36 49.82 50.62 50.62
F Net Loan-Closing (C+D-E) 544.09 595.96 567.14 516.52 465.90
G Average Loan (C+F)/2 530.84 570.03 581.55 541.83 491.21
Weighted Average Rate of Interest
H 7.4336 7.4374 7.4410 7.4410 7.4390
on Loan (In %)
I Interest on Loan (G*H) 8.52 42.40 43.27 40.32 36.54
Asset-VIII
(₹ in lakh)
2020-21
Particulars (pro-rata 2021-22 2022-23 2023-24
244 days)
A Gross Normative Loan 1575.52 1723.32 1864.99 1864.99
Cumulative Repayments up to the
B 0.00 82.61 216.96 356.66
Previous Year
C Net Loan-Opening (A-B) 1575.52 1640.71 1648.02 1508.33
D Additions due to ACE 147.80 141.67 0.00 0.00
E Repayment during the year 82.61 134.35 139.69 139.69
F Net Loan-Closing (C+D-E) 1640.71 1648.02 1508.33 1368.64
G Average Loan (C+F)/2 1608.11 1644.36 1578.18 1438.48
Weighted Average Rate of Interest on
H 7.0808 7.0804 7.0804 7.0799
Loan (In %)
Asset-X
(₹ in lakh)
2021-22
Particulars (pro-rata 2022-23 2023-24
364 days)
A Gross Normative Loan 680.48 811.98 848.11
Cumulative Repayments up to the
B 0.00 58.77 124.08
Previous Year
C Net Loan-Opening (A-B) 680.48 753.21 724.03
D Additions due to ACE 131.50 36.13 18.07
E Repayment during the year 58.77 65.31 67.38
F Net Loan-Closing (C+D-E) 753.21 724.03 674.72
G Average Loan (C+F)/2 716.84 738.62 699.38
Weighted Average Rate of Interest on
H 5.9749 5.9749 5.9743
Loan (In %)
I Interest on Loan (G*H) 42.71 44.13 41.78
Asset-XI
(₹ in lakh)
2021-22
Particulars (pro-rata 41 2022-23 2023-24
days)
A Gross Normative Loan 2128.26 2199.58 2444.58
Cumulative Repayments up to the
B 0.00 18.33 193.49
Previous Year
C Net Loan-Opening (A-B) 2128.26 2181.24 2251.09
D Additions due to ACE 71.32 245.00 210.00
E Repayment during the year 18.33 175.15 192.31
F Net Loan-Closing (C+D-E) 2181.24 2251.09 2268.78
G Average Loan (C+F)/2 2154.75 2216.17 2259.94
Weighted Average Rate of Interest on
H 6.3598 6.3575 6.3555
Loan (In %)
I Interest on Loan (G*H) 15.39 140.89 143.63
“30. Return on Equity: (1) Return on equity shall be computed in rupee terms, on the
equity base determined in accordance with Regulation 18 of these regulations.
(2) Return on equity shall be computed at the base rate of 15.50% for thermal
generating station, transmission system including communication system and run-of-
river hydro generating station, and at the base rate of 16.50% for the storage type
hydro generating stations including pumped storage hydro generating stations and run-
“31. Tax on Return on Equity. (1) The base rate of return on equity as allowed by the
Commission under Regulation 30 of these regulations shall be grossed up with the
effective tax rate of the respective financial year. For this purpose, the effective tax rate
shall be considered on the basis of actual tax paid in respect of the financial year in
line with the provisions of the relevant Finance Acts by the concerned generating
company or the transmission licensee, as the case may be. The actual tax paid on
income from other businesses including deferred tax liability (i.e. income from business
other than business of generation or transmission, as the case may be) shall be
excluded for the calculation of effective tax rate.
(2) Rate of return on equity shall be rounded off to three decimal places and shall
be computed as per the formula given below:
Illustration-
(3) The generating company or the transmission licensee, as the case may be, shall
true up the grossed up rate of return on equity at the end of every financial year based
on actual tax paid together with any additional tax demand including interest thereon,
duly adjusted for any refund of tax including interest received from the income tax
authorities pertaining to the tariff period 2019-24 on actual gross income of any
financial year. However, penalty, if any, arising on account of delay in deposit or short
deposit of tax amount shall not be claimed by the generating company or the
transmission licensee, as the case may be. Any under-recovery or over-recovery of
grossed up rate on return on equity after truing up, shall be recovered or refunded to
beneficiaries or the long term customers, as the case may be, on year to year basis.”
107. The Petitioner has submitted that the MAT rate is applicable to the Petitioner's
company. Accordingly, the MAT rate applicable in 2019-20 has been considered for the
purpose of the RoE, which will be trued-up in accordance with Regulation 31(3) of the
2019 Tariff Regulations. The RoE allowed for the transmission asset has been worked
out as follows:
Asset-I
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
A Opening Equity (A) 665.93 953.56 1015.84 1056.87 1077.38
B Additions (B) 287.63 62.28 41.03 20.51 0.00
Asset-II
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
183 days)
A Opening Equity (A) 218.77 338.77 390.89 390.89 390.89
B Additions (B) 120.00 52.12 0.00 0.00 0.00
C Closing Equity (C) = (A+B) 338.77 390.89 390.89 390.89 390.89
D Average Equity (D) = (A+C)/2 278.77 364.83 390.89 390.89 390.89
Return on Equity (Base Rate)
E 15.500 15.500 15.500 15.500 15.500
(In %)
MAT Rate for respective year
F 17.472 17.472 17.472 17.472 17.472
(In %)
Rate of Return on Equity (In
G 18.782 18.782 18.782 18.782 18.782
%)
H Return on Equity(D*G) 26.18 68.52 73.42 73.42 73.42
Asset-IV
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
A Opening Equity (A) 486.10 522.80 595.64 649.75 667.78
B Additions (B) 36.70 72.85 54.11 18.04 0.00
C Closing Equity (C) = (A+B) 522.80 595.64 649.75 667.78 667.78
D Average Equity (D) = (A+C)/2 504.45 559.22 622.70 658.77 667.78
Return on Equity (Base Rate)
E 15.500 15.500 15.500 15.500 15.500
(In %)
MAT Rate for respective year
F 17.472 17.472 17.472 17.472 17.472
(In %)
Rate of Return on Equity (In
G 18.782 18.782 18.782 18.782 18.782
%)
H Return on Equity(D*G) 23.82 105.03 116.95 123.73 125.42
Asset-VI
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
79 days)
A Opening Equity (A) 221.83 236.92 278.59 287.59 287.59
B Additions (B) 15.09 41.67 9.00 0.00 0.00
C Closing Equity (C) = (A+B) 236.92 278.59 287.59 287.59 287.59
D Average Equity (D) = (A+C)/2 229.38 257.76 283.09 287.59 287.59
Return on Equity (Base Rate)
E 15.500 15.500 15.500 15.500 15.500
(In %)
MAT Rate for respective year
F 17.472 17.472 17.472 17.472 17.472
(In %)
Rate of Return on Equity (In
G 18.782 18.782 18.782 18.782 18.782
%)
H Return on Equity(D*G) 9.30 48.41 53.17 54.02 54.02
Asset-VIII
(₹ in lakh)
2020-21
Particulars (pro-rata 2021-22 2022-23 2023-24
244 days)
A Opening Equity (A) 675.22 738.56 799.28 799.28
B Additions (B) 63.34 60.72 0.00 0.00
C Closing Equity (C) = (A+B) 738.56 799.28 799.28 799.28
D Average Equity (D) = (A+C)/2 706.89 768.92 799.28 799.28
Return on Equity (Base Rate)
E 15.500 15.500 15.500 15.500
(In %)
MAT Rate for respective year
F 17.472 17.472 17.472 17.472
(In %)
Rate of Return on Equity (In
G 18.782 18.782 18.782 18.782
%)
H Return on Equity(D*G) 88.75 144.42 150.12 150.12
Asset-XI
(₹ in lakh)
2021-22
Particulars (pro-rata 41 2022-23 2023-24
days)
A Opening Equity (A) 912.11 942.68 1047.68
B Additions (B) 30.57 105.00 90.00
C Closing Equity (C) = (A+B) 942.68 1047.68 1137.68
D Average Equity (D) = (A+C)/2 927.39 995.18 1092.68
Return on Equity (Base Rate)
E 15.500 15.500 15.500
(In %)
MAT Rate for respective year
F 17.472 17.472 17.472
(In %)
Rate of Return on Equity (In
G 18.782 18.782 18.782
%)
H Return on Equity (D*G) 19.57 186.91 205.23
108. The Petitioner has claimed the following O&M expenses for the transmission
Asset-I
Particulars 2019-20
(pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
Transmission Line:
(i) 220 kV Interconnecting Line from PG Sub-station to BSPTCL Sub-station for 500 MVA
ICT-IV
Bays:
(i) Biharsharif: ICT-IV 220 kV Bay Biharsharif (BSPTCL)
(ii) Biharsharif: ICT-IV 400 kV Bay Biharsharif (PG)
(iii) Biharsharif: ICT-IV Biharsharif (PG)
Asset-II
Particulars 2019-
20(pro-rata 2020-21 2021-22 2022-23 2023-24
183 days)
Bays:
(i) Malda: 160 MVA ICT
220 kV Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 0.245 0.254 0.263 0.272 0.282
O&M Expenses claimed (₹
19.60 40.64 42.08 43.52 45.12
in lakh)
Asset-IV
Particulars 2019-
20(pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
Bays:
(i) Lakhisarai: 400 kV Bay for ICT III
(ii) Lakhisarai: 132 kV Bay for ICT III
(iii) Lakhisarai: ICT III
400kV Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 32.15 33.28 34.45 35.66 36.91
O&M Expenses
8.08 33.28 34.45 35.66 36.91
claimed (₹ in lakh)
132 kVBays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 16.08 16.64 17.23 17.83 18.48
O&M Expenses
4.04 16.64 17.23 17.83 18.46
claimed (₹ in lakh)
400 kV ICT Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 0.358 0.371 0.384 0.398 0.411
Asset-V
Particulars 2019-20(pro-
2020-21 2021-22 2022-23 2023-24
rata 91 days)
Bays:
(i) Banka: ICT III
(ii) Banka: 400 kV Bay for ICT III
(iii) Banka: 132 kV Bay for ICT III
400kV Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 32.15 33.28 34.45 35.66 36.91
O&M Expenses
7.99 33.28 34.45 35.66 36.91
claimed (₹ in lakh)
132 kVBays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 16.08 16.64 17.23 17.83 18.48
O&M Expenses
4.04 16.64 17.23 17.83 18.46
claimed (₹ in lakh)
400 kV ICT Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 0.358 0.371 0.384 0.398 0.411
O&M Expenses
28.04 116.87 120.96 125.37 129.47
claimed (₹ in lakh)
Total O&M Expenses
40.03 166.79 172.64 178.66 184.84
claimed (₹ in lakh)
Asset-VI
Particulars 2019-20(pro-
2020-21 2021-22 2022-23 2023-24
rata 79 days)
Bays:
(i) Subhasgram: 125 MVAR BR Bay
Asset-VIII
Particulars 2020-21(pro-rata 244
2021-22 2022-23 2023-24
days)
Bays:
(i) Maithon: 400 kV Bay for ICT Maithon
(ii) Maithon: 220 kV Bay for ICT Maithon
(iii) Maithon: 500 MVA ICT at Maithon
400 kV Bays 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 33.28 34.45 35.66 36.91
O&M Expenses
22.25 34.45 35.66 36.91
claimed (₹ in lakh)
109. The norms specified under Regulation 35(3)(a) of the 2019 Tariff Regulations
provide as follows:
Provided that the O&M expenses for the GIS bays shall be allowed as worked
out by multiplying 0.70 of the O&M expenses of the normative O&M expenses
for bays;
(i) the operation and maintenance expenses for new HVDC bi-pole
schemes commissioned after 1.4.2019 for a particular year shall be allowed pro-
rata on the basis of normative rate of operation and maintenance expenses of
similar HVDC bi-pole scheme for the corresponding year of the tariff period;
(ii) the O&M expenses norms for HVDC bi-pole line shall be considered as
(b) The total allowable operation and maintenance expenses for the transmission
system shall be calculated by multiplying the number of sub-station bays,
transformer capacity of the transformer (in MVA) and km of line length with the
applicable norms for the operation and maintenance expenses per bay, per MVA
and per km respectively.
(c) The Security Expenses and Capital Spares for transmission system shall be
allowed separately after prudence check:
Provided that the transmission licensee shall submit the assessment of the
security requirement and estimated security expenses, the details of year-wise
actual capital spares consumed at the time of truing up with appropriate
justification.
(4) Communication system: The operation and maintenance expenses for the
communication system shall be worked out at 2.0% of the original project cost related
to such communication system. The transmission licensee shall submit the actual
operation and maintenance expenses for truing up.”
110. The O&M Expenses have been worked out for the various elements of the
transmission assets, except Asset-III, Asset-IX, and Asset-X as per the norms specified
Asset-I
Particulars 2019-20
(pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
Transmission Line:
(i) 220 kV Interconnecting Line from PG Sub-station to BSPTCL Sub-station for 500
MVA ICT-IV
Bays:
(i) Biharsharif: ICT-IV 220 kV Bay Biharsharif (BSPTCL)
(ii) Biharsharif: ICT-IV 400 kV Bay Biharsharif (PG)
(iii) Biharsharif: ICT-IV Biharsharif (PG)
TL Length (in km) 0.80 0.80 0.80 0.80 0.80
Asset-II
Particulars 2019-
20(pro-rata 2020-21 2021-22 2022-23 2023-24
183 days)
Bays:
(i) Malda: 160 MVA ICT
220 kV Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 0.245 0.254 0.263 0.272 0.282
O&M Expenses claimed (₹
19.60 40.64 42.08 43.52 45.12
in lakh)
Asset-IV
Particulars 2019-
20(pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
Bays:
(i) Lakhisarai: 400 kV Bay for ICT III
(ii) Lakhisarai: 132 kV Bay for ICT III
(iii) Lakhisarai: ICT III
400kV Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 32.15 33.28 34.45 35.66 36.91
O&M Expenses
8.08 33.28 34.45 35.66 36.91
claimed (₹ in lakh)
132 kVBays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 16.08 16.64 17.23 17.83 18.48
O&M Expenses
4.04 16.64 17.23 17.83 18.46
claimed (₹ in lakh)
400 kV ICT Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 0.358 0.371 0.384 0.398 0.411
O&M Expenses
28.35 116.87 120.96 125.37 129.47
claimed (₹ in lakh)
Asset-V
Particulars 2019-20(pro-
2020-21 2021-22 2022-23 2023-24
rata 91 days)
Bays:
(i) Banka: ICT III
(ii) Banka: 400 kV Bay for ICT III
(iii) Banka: 132 kV Bay for ICT III
400kV Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 32.15 33.28 34.45 35.66 36.91
O&M Expenses
7.99 33.28 34.45 35.66 36.91
claimed (₹ in lakh)
132 kVBays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 16.08 16.64 17.23 17.83 18.48
O&M Expenses
4.04 16.64 17.23 17.83 18.46
claimed (₹ in lakh)
400 kV ICT Bays 1.00 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 0.358 0.371 0.384 0.398 0.411
O&M Expenses
28.04 116.87 120.96 125.37 129.47
claimed (₹ in lakh)
Total O&M Expenses
40.03 166.79 172.64 178.66 184.84
claimed (₹ in lakh)
Asset-VI
Particulars 2019-20(pro-
2020-21 2021-22 2022-23 2023-24
rata 79 days)
Bays:
(i) Subhasgram: 125 MVAR BR Bay
Asset-VIII
Particulars 2020-21(pro-rata 244
2021-22 2022-23 2023-24
days)
Bays:
(i) Maithon: 400 kV Bay for ICT Maithon
(ii) Maithon: 220 kV Bay for ICT Maithon
(iii) Maithon: 500 MVA ICT at Maithon
400 kV Bays 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 33.28 34.45 35.66 36.91
O&M Expenses
22.25 34.45 35.66 36.91
claimed (₹ in lakh)
220 kV Bays 1.00 1.00 1.00 1.00
Norms (₹ lakh/Bay) 23.30 24.12 24.96 25.84
Asset-XI
Asset-XI
Particulars 2021-22(pro-rata 41
2022-23 2023-24
days)
Bays:
(i) Rangpo: 220 kV Bay for ICT
(ii) Rangpo: 132 kV Bay for ICT
(iii) Rangpo: ICT at Rangpo
220 kV ICT Bay 1.00 1.00 1.00
Norms (₹ lakh/Bay) 0.263 0.272 0.282
O&M Expenses claimed (₹ in lakh) 2.95 27.20 28.20
220 kV GIS Bays 1.00 1.00 1.00
Norms (₹ lakh/Bay) 16.884 17.472 18.088
O&M Expenses claimed (₹ in lakh) 1.90 17.47 18.09
400 kV ICT Bays 1.00 1.00 1.00
Norms (₹ lakh/Bay) 12.061 12.841 12.922
O&M Expenses claimed (₹ in lakh) 1.35 12.48 12.92
Total O&M Expenses claimed (₹ in
6.21 57.15 59.21
lakh)
Interest on Working Capital (IWC)
111. Regulation 34(1)(c), Regulation 34(3), Regulation 34(4) and Regulation 3(7) of
“34. Interest on Working Capital: (1) The working capital shall cover:
(i) Cost of limestone or reagent towards stock for 20 days corresponding to the
normative annual plant availability factor;
(ii) Advance payment for 30 days towards cost of reagent for generation
corresponding to the normative annual plant availability factor;
(iii) Receivables equivalent to 45 days of supplementary capacity charge and
supplementary energy charge for sale of electricity calculated on the normative
annual plant availability factor;
(iv) Operation and maintenance expenses in respect of emission control system
for one month;
(v) Maintenance spares @20% of operation and maintenance expenses in
respect of emission control system.
(2) The cost of fuel in cases covered under sub-clauses (a) and (b) of clause (1) of
this Regulation shall be based on the landed fuel cost (taking into account normative
transit and handling losses in terms of Regulation 39 of these regulations) by the
generating station and gross calorific value of the fuel as per actual weighted average
for the third quarter of preceding financial year in case of each financial year for which
tariff is to be determined:
Provided that in case of new generating station, the cost of fuel for the first
financial year shall be considered based on landed fuel cost (taking into account
normative transit and handling losses in terms of Regulation 39 of these regulations)
and gross calorific value of the fuel as per actual weighted average for three months, as
(3) Rate of interest on working capital shall be on normative basis and shall be
considered as the bank rate as on 1.4.2019 or as on 1st April of the year during the tariff
period 2019-24 in which the generating station or a unit thereof or the transmission
system including communication system or element thereof, as the case may be, is
declared under commercial operation, whichever is later:
Provided that in case of truing-up, the rate of interest on working capital shall be
considered at bank rate as on 1st April of each of the financial year during the tariff
period 2019-24.
(4) Interest on working capital shall be payable on normative basis notwithstanding that
the generating company or the transmission licensee has not taken loan for working
capital from any outside agency.”
‘Bank Rate’ means the one year marginal cost of lending rate (MCLR) of the State Bank
of India issued from time to time plus 350 basis points;”
112. The Petitioner has submitted that it has computed IWC for the 2019-24 period,
considering the SBI Base Rate plus 350 basis points as on 1.4.2019. The Petitioner has
113. The IWC is worked out in accordance with Regulation 34 of the 2019 Tariff
Regulations. The Rate of Interest (ROI) considered is 12.05% (SBI 1-year MCLR
applicable as on 1.4.2019 of 8.55% plus 350 basis points) for 2019-20, 11.25% (SBI 1-
year MCLR applicable as on 1.4.2020 of 7.75% plus 350 basis points) for 2020-21,
10.50% (SBI 1-year MCLR applicable as on 1.4.2020 of 7.00% plus 350 basis points)
for 2021-22 and 2022-23 and 12.00% (SBI 1 year MCLR applicable as on 1.4.2023 of
8.50% plus 350 basis points) for 2023-24. The components of the working capital and
Asset-I
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
WC for O&M Expenses
A (O&M Expenses for 1 19.51 20.21 20.92 21.67 22.39
month)
WC for Maintenance
B Spares (15% of O&M 35.11 36.37 37.65 39.01 40.31
Expenses)
Asset-II
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
183 days)
WC for O&M Expenses
A (O&M Expenses for 1 3.27 3.39 3.51 3.63 3.76
month)
WC for Maintenance
B Spares (15% of O&M 5.88 6.10 6.31 6.53 6.77
Expenses)
WC for Receivables
(Equivalent to 45 days
C 23.83 29.48 30.75 30.28 29.81
of annual transmission
charges)
D Total Working Capital 32.98 38.96 40.57 40.43 40.33
E Rate of Interest (In %) 12.05 11.25 10.50 10.50 12.00
Interest on Working
F 1.99 4.38 4.26 4.25 4.84
Capital (D*E)
Asset-IV
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
WC for O&M Expenses
A (O&M Expenses for 1 13.42 13.90 14.39 14.91 15.40
month)
WC for Maintenance
B Spares (15% of O&M 24.15 25.02 25.90 26.83 27.73
Expenses)
WC for Receivables
(Equivalent to 45 days
C 54.74 58.66 62.61 64.75 65.03
of annual transmission
charges)
D Total Working Capital 92.31 97.58 102.89 106.49 108.15
E Rate of Interest (In %) 12.05 11.25 10.50 10.50 12.00
Interest on Working
F 2.80 10.98 10.80 11.18 12.98
Capital (D*E)
Asset-VI
(₹ in lakh)
2019-20
2020- 2021- 2022- 2023-
Particulars (pro-rata
21 22 23 24
79 days)
WC for O&M Expenses (O&M
A 2.68 2.77 2.87 2.97 3.08
Expenses for 1 month)
WC for Maintenance Spares (15% of
B 4.82 4.99 5.17 5.35 5.54
O&M Expenses)
WC for Receivables (Equivalent to 45
C 19.46 21.29 22.68 22.67 22.35
days of annual transmission charges)
D Total Working Capital 26.97 29.06 30.72 30.99 30.96
E Rate of Interest (In %) 12.05 11.25 10.50 10.50 12.00
F Interest on Working Capital (D*E) 0.70 3.27 3.23 3.25 3.72
Asset-VIII
(₹ in lakh)
2020-21
Particulars (pro-rata 2021-22 2022-23 2023-24
244 days)
WC for O&M Expenses (O&M
A 20.17 20.88 21.64 22.35
Expenses for 1 month)
WC for Maintenance Spares
B 36.31 37.59 38.94 40.24
(15% of O&M Expenses)
WC for Receivables
C (Equivalent to 45 days of 77.34 81.43 83.38 83.29
annual transmission charges)
D Total Working Capital 133.83 139.89 143.96 145.88
E Rate of Interest (In %) 11.25 10.50 10.50 12.00
Interest on Working Capital
F 10.06 14.69 15.12 17.51
(D*E)
Asset-XI
(₹ in lakh)
2021-22
Particulars (pro-rata 41 2022-23 2023-24
days)
WC for O&M Expenses (O&M
A 4.60 4.76 4.93
Expenses for 1 month)
WC for Maintenance Spares (15%
B 8.29 8.57 8.88
of O&M Expenses)
WC for Receivables (Equivalent to
C 45 days of annual transmission 66.33 70.14 75.13
charges)
D Total Working Capital 79.22 83.47 88.94
E Rate of Interest (In %) 10.50 10.50 12.00
Interest on Working Capital
F 0.93 8.76 10.67
(D*E)
114. The transmission charges allowed for the transmission assets for the 2019-24
Asset-I
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
208 days)
A Depreciation 80.99 173.31 182.40 187.81 189.62
B Interest on Loan 83.47 169.21 164.66 155.66 142.52
C Return on Equity 86.43 184.95 194.65 200.43 202.35
D O & M Expenses 133.02 242.50 251.00 260.07 268.71
E Interest on Working Capital 9.57 17.28 16.63 17.00 19.66
F Total 393.48 787.25 809.34 820.97 822.86
Asset-IV
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
92 days)
A Depreciation 22.94 101.04 112.35 118.70 120.29
B Interest on Loan 21.89 92.00 95.08 92.73 85.35
C Return on Equity 23.82 105.03 116.95 123.73 125.42
D O & M Expenses 40.47 166.79 172.64 178.86 184.84
E Interest on Working Capital 2.80 10.98 10.80 11.18 12.98
F Total 111.92 475.84 507.82 525.20 528.88
Asset-V
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
91 days)
A Depreciation 30.44 136.38 153.79 164.16 166.46
B Interest on Loan 27.18 116.71 122.94 121.35 111.39
C Return on Equity 29.95 135.23 153.70 164.76 167.22
D O & M Expenses 40.03 166.79 172.64 178.86 184.84
E Interest on Working Capital 3.06 12.25 12.19 12.69 14.69
F Total 130.66 567.36 615.26 641.83 644.61
Asset-VI
(₹ in lakh)
2019-20
Particulars (pro-rata 2020-21 2021-22 2022-23 2023-24
79 days)
A Depreciation 8.71 45.36 49.82 50.62 50.62
B Interest on Loan 8.52 42.40 43.27 40.32 36.54
C Return on Equity 9.30 48.41 53.17 54.02 54.02
D O & M Expenses 6.94 33.28 34.45 35.66 36.91
E Interest on Working Capital 0.70 3.27 3.23 3.25 3.72
F Total 34.17 172.72 183.94 183.87 181.81
Asset-X
(₹ in lakh)
2021-22
Particulars (pro-rata 364 2022-23 2023-24
days)
A Depreciation 58.77 65.31 67.38
B Interest on Loan 42.71 44.13 41.78
C Return on Equity 59.90 66.81 69.00
D O & M Expenses 0.00 0.00 0.00
E Interest on Working Capital 2.12 2.31 2.67
F Total 163.50 178.56 180.83
Asset-XI
(₹ in lakh)
2021-22
Particulars (pro-rata 41 2022-23 2023-24
days)
A Depreciation 18.33 175.15 192.31
B Interest on Loan 15.39 140.89 143.63
C Return on Equity 19.57 186.91 205.23
D O & M Expenses 6.21 57.15 59.21
E Interest on Working Capital 0.93 8.76 10.67
F Total 60.43 568.86 611.05
115. The Petitioner has sought reimbursement of fee paid by it for filing the Petition
116. The Petitioner shall be entitled for reimbursement of the filing fees and
publication expenses in connection with the present Petition, directly from the
Regulations.
117. The Petitioner has sought reimbursement of the licensee fee in accordance with
Regulation 70(4) of the 2019 Tariff Regulations for the 2019-24 tariff period. The
Petitioner shall be entitled to the reimbursement of the licence fee in accordance with
Regulation 70(4) of the 2019 Tariff Regulations for the 2019-24 tariff period. The
Petitioner shall also be entitled to the recovery of RLDC fee and charges in accordance
with Regulations 70(3) of the 2019 Tariff Regulations for the 2019-24 tariff period.
118. The Petitioner has submitted that, if GST is levied at any rate and at any point of
time in the future on charges of transmission of electricity, the same shall be borne and
additionally paid by the Respondent(s) to the Petitioner, and the same shall be charged
and billed separately by the Petitioner. Further additional taxes, if any, are to be paid by
the Petitioner on account of demand from Government/ Statutory authorities, and the
transmission service at present, and we are of the view that the Petitioner’s prayer is
premature.
Security Expenses
120. The Petitioner has submitted that security expenses related to the transmission
assets are not claimed in the instant Petition. It will file a separate Petition to claim the
overall security expenses and the consequential IWC as per Regulation 35(3)(c) of the
projected basis for the 2019-24 tariff period based on actual security expenses incurred
in the FY 2018-19 in Petition No. 260/MP/2020. The Commission vide order dated
3.8.2021 has already disposed of the said Petition. Therefore, the Petitioner’s prayer in
the instant Petition for allowing it to file a separate Petition for claiming the overall
Capital Spares
122. The Petitioner has sought reimbursement of capital spares at the end of the tariff
period. The Petitioner’s claim, if any, shall be dealt with in accordance with the
123. The Petitioner has submitted that Annual Fixed Charges for 2019-24 will be
Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 and will be
shared by the beneficiaries and long term transmission customers in Central Electricity
Regulations, 2010 dated 15.6.2010 and amendment to these Regulations issued vide
124. With effect from 1.11.2020, the sharing of transmission charges is governed by
Losses) Regulations, 2020 (in short, “the 2020 Sharing Regulations‟). Accordingly, the
liabilities of DICs for arrears of transmission charges determined through this order shall
Regulations and shall be recovered from the concerned DICs through Bill 2 under
Regulation 15(2)(b) of the 2020 Sharing Regulations. For the subsequent period, the
125. To summarise:
a. AFC allowed in respect of the following transmission assets for the 2019-24
Asset-I
(₹ in lakh)
2019-20
(pro-rata 208 2020-21 2021-22 2022-23 2023-24
days)
393.48 787.25 809.34 820.97 822.86
Asset-II
(₹ in lakh)
2019-20
(pro-rata 183 2020-21 2021-22 2022-23 2023-24
days)
96.93 239.08 249.46 245.58 242.43
Asset-IV
(₹ in lakh)
2019-20
(pro-rata 92 2020-21 2021-22 2022-23 2023-24
days)
111.92 475.84 507.82 525.20 528.88
Asset-V
(₹ in lakh)
2019-20
(pro-rata 91 2020-21 2021-22 2022-23 2023-24
days)
130.66 567.36 615.26 641.83 644.61
Asset-VI
(₹ in lakh)
2019-20
(pro-rata 79 2020-21 2021-22 2022-23 2023-24
days)
34.17 172.72 183.94 183.87 181.81
Asset-X
(₹ in lakh)
2021-22
2022-23 2023-24
(pro-rata 364 days)
163.50 178.56 180.83
Asset-XI
(₹ in lakh)
2021-22
2022-23 2023-24
(pro-rata 41 days)
60.43 568.86 611.05
127. This order disposes of Petition No. 9/TT/2023 in terms of the above findings and
discussions.
sd/- sd/-
(Ramesh Babu V.) (Jishnu Barua)
Member Chairperson
Page 96 of 104
ANNEXURE-I
Asset-I
Transmission
189.25 40.68 27.02 13.51 0.00 270.46 5.28% 20.90
Line 125.29 395.75 11.61 17.68 19.47 20.54
1101.0 168.7
Sub Station 769.51 166.93 109.73 54.87 0.00 5.28%
2094.47 4 3195.51 130.90 155.63 162.93 167.27 2
189.6
Total 1371.5 142.51 173.31 182.40 187.81
2219.76 958.76 207.61 136.75 68.38 - 3591.26 2
0
Average Gross Block 3282.3 3454.5 3557.0 3591.
2699.14
(₹ in lakh) 3 1 7 26
Weighted Average
5.28
Rate 5.28% 5.28% 5.28% 5.28%
%
of Depreciation
Admitted
Projected ACE Rate of Annual Depreciation as per Regulations
2019-24 Admitted Capital
(₹ in lakh) Deprecia (₹ in lakh)
Capital Cost as
tion as
Cost as on on
per
1.4.2019 31.3.2024
Regulati
Capital (₹ in lakh) 2019- 2020- 2021- 2022- 2023- (₹ in 2020- 2021- 2022- 2023-
Total ons 2019-20
Expenditure 20 21 22 23 24 lakh) 21 22 23 24
Admitted
Projected ACE Rate of Annual Depreciation as per Regulations
2019-24 Admitted Capital
(₹ in lakh) Deprecia (₹ in lakh)
Capital Cost as
tion as
Cost as on on
per
1.4.2019 31.3.2024
Regulati
Capital (₹ in lakh) 2019- 2020- 2021- 2022- 2023- (₹ in 2020- 2021- 2022- 2023-
Total ons 2019-20
Expenditure 20 21 22 23 24 lakh) 21 22 23 24
Admitted
Projected ACE Capital Annual Depreciation as per Regulations
2019-24 Admitted
(₹ in lakh) Cost as Rate of (₹ in lakh)
Capital
on Depreciatio
Cost as on
31.3.202 n as per
1.4.2019
4 Regulations
Capital (₹ in lakh)
Expenditur
2019- 2020- 2021-
Total (₹ in 2019-20 2020-21 2021-22 2022-23 2023-24
20 21 22 lakh)
e
Building Civil Works & Colony 35.44 15.01 0.04 15.05 50.49 3.34% 1.43 1.69 1.69 1.69
Sub Station 2215.30 196.13 202.35 398.47 2613.77 5.28% 122.15 132.67 138.01 138.01
Total 2250.74 211.14 202.39 413.53 2664.27 123.58 134.35 139.69 139.69
Sub Station 945.47 186.83 51.33 25.66 263.82 1209.29 5.28% 54.85 61.14 63.17
IT Equipment (Incl. Software) 26.65 1.02 0.29 0.15 1.46 28.11 15.00% 4.07 4.17 4.20
Total 972.12 187.85 51.62 25.81 265.28 1237.40 58.93 65.31 67.38
Sub Station 3040.37 101.88 350.00 300.00 751.88 3792.26 5.28% 163.22 175.15 192.31
Total 3040.37 101.88 350.00 300.00 751.88 3792.26 163.22 175.15 192.31