كهربا 2 Batool Nofal

The document consists of a series of questions and answers related to excavation, foundations, electrical civil works, quantity estimation, steel and reinforcement, safety, manholes, concrete testing, general civil works in power projects, and codes and tools. Each section contains multiple-choice questions that cover essential concepts and practices in civil engineering and construction. The document serves as a knowledge assessment tool for professionals in the field.

Uploaded by

abedm0933
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views8 pages

كهربا 2 Batool Nofal

The document consists of a series of questions and answers related to excavation, foundations, electrical civil works, quantity estimation, steel and reinforcement, safety, manholes, concrete testing, general civil works in power projects, and codes and tools. Each section contains multiple-choice questions that cover essential concepts and practices in civil engineering and construction. The document serves as a knowledge assessment tool for professionals in the field.

Uploaded by

abedm0933
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Section 1: Excavation & Earthworks

1. What is the maximum safe slope for excavation in sandy soil?


o A. 1:1 ( )
o B. 2:1
o C. 1:2
o D. 1:0.5
2. How do you calculate the volume of a rectangular excavation?
o A. Area × Perimeter
o B. Width × Depth × 2
o C. Length × Width × Depth ( )
o D. Height × Length × 2
3. What is benching in excavation?
o A. Installing steel mesh
o B. Creating horizontal steps ( )
o C. Mixing concrete
o D. Piling method
4. When is shoring required?
o A. In wide areas only
o B. When soil is hard
o C. When depth exceeds safe limits ( )
o D. During surface cleaning
5. What document provides soil classification for excavation?
o A. Design drawing
o B. Geotechnical report ( )
o C. Electrical layout
o D. Project schedule

Section 2: Foundations & Concrete

6. What is the typical concrete mix ratio for footing (by volume)?
o A. 1:3:6
o B. 1:2:4 ( )
o C. 1:1.5:3
o D. 1:4:8
7. What is the purpose of lean concrete?
o A. Reinforcement
o B. Waterproofing
o C. Provide clean base ( )
o D. To increase slope
8. What is the minimum concrete cover in footings?
o A. 10 mm
o B. 25 mm
o C. 40 mm
o D. 50 mm ( )

ENG BATOOL NOFAL 0790538777


9. What is blinding concrete?
o A. Concrete for beams
o B. Surface finishing
o C. Concrete layer under footing ( )
o D. Temporary slab
10. How is concrete volume of a pedestal calculated?

• A. Base Area × Height ( )


• B. Diameter × Length
• C. Perimeter × Depth
• D. Width × Thickness × 2

Section 3: Electrical Civil Works

11. What is a duct bank?

• A. Water drainage
• B. Concrete encased cable ducts ( )
• C. Manhole
• D. Electrical pole

12. What is the minimum slope for cable trenches?

• A. 1%
• B. 0.5% ( )
• C. 3%
• D. Flat

13. What is the typical concrete grade for duct bank encasement?

• A. C10
• B. C20
• C. C25 ( )
• D. C40

14. What ensures the position of ducts in trench?

• A. Steel bars
• B. Mortar
• C. Duct spacers ( )
• D. Bricks

15. What is a thrust block used for?

• A. Prevent duct collapse

ENG BATOOL NOFAL 0790538777


• B. Resist pipe movement ( )
• C. Support manholes
• D. Anchor cable trays

Section 4: Quantity Estimation

16. What is the formula for volume of a trapezoidal footing?

• A. Area × Height
• B. (A1 + A2)/2 × Depth ( )
• C. Length × Width × 2
• D. L × W ÷ 2

17. What is BOQ?

• A. Blueprint of Quantities
• B. Building Organization Quote
• C. Bill of Quantities ( )
• D. Basic Offer Quote

18. What is the unit for excavation in BOQ?

• A. Square meter
• B. Cubic meter ( )
• C. Linear meter
• D. Ton

19. How to calculate concrete for rectangular footing?

• A. Perimeter × Height
• B. L × B × D ( )
• C. L × B × 2
• D. Area × Volume

20. What is the standard concrete waste factor?

• A. 1%
• B. 2%
• C. 3%
• D. 5% ( )

Section 5: Steel & Reinforcement

ENG BATOOL NOFAL 0790538777


21. What is BBS?

• A. British Building Standard


• B. Bar Bending Schedule ( )
• C. Bulk Brick Schedule
• D. Beam Base Specification

22. What is lap length in tension zone?

• A. 10 × dia
• B. 40 × dia
• C. 50 × dia ( )
• D. 30 × dia

23. What is the minimum cover for reinforcement in columns?

• A. 15 mm
• B. 25 mm
• C. 40 mm ( )
• D. 60 mm

24. How is steel quantity calculated?

• A. Number × Dia × Length × Density ( )


• B. Dia + Length × 2
• C. Dia × 2
• D. None

25. Why are dowels used in footing?

• A. For aesthetics
• B. For vertical connection ( )
• C. For waterproofing
• D. To reduce weight

Section 6: Safety & Site Work

26. What PPE is mandatory near electrical works?

• A. Leather jacket
• B. Safety helmet & gloves ( )
• C. Raincoat
• D. Sports shoes

27. What is a safe distance from overhead HT lines?

ENG BATOOL NOFAL 0790538777


• A. 1 meter
• B. 3 meters ( )
• C. 0.5 meter
• D. No restriction

28. What is the color code for electrical ducts?

• A. Yellow
• B. Red ( )
• C. Green
• D. White

29. When should formwork be stripped for vertical surfaces?

• A. 2 hours
• B. 12 hours
• C. 24 hours ( )
• D. 48 hours

30. How do you prevent collapse in deep excavation?

• A. Use heavy machinery


• B. Install warning signs
• C. Provide shoring/bracing ( )
• D. Pour water

Section 7: Manholes & Underground Works

31. What is a standard inner dimension of electrical manhole?

• A. 0.5×0.5m
• B. 1.2×1.2m ( )
• C. 2×2m
• D. 3×3m

32. What is used to test soil compaction?

• A. Soil probe
• B. Compaction meter
• C. Nuclear densometer ( )
• D. Soil gauge

33. What is the sequence of trench backfill?

ENG BATOOL NOFAL 0790538777


• A. Top to bottom
• B. Center first
• C. Bottom to top in layers ( )
• D. No sequence

34. What is the purpose of cable markers?

• A. Decoration
• B. To identify cable route ( )
• C. Reduce cost
• D. Light up trench

35. What is "as-built drawing"?

• A. Original plan
• B. Modified construction drawing ( )
• C. Electrical layout
• D. Demolition plan

Section 8: Concrete Testing

36. What is slump test used for?

• A. Check cement content


• B. Check workability ( )
• C. Check steel
• D. Check durability

37. What is the curing period of concrete?

• A. 1 day
• B. 3 days
• C. 7 days
• D. 7 to 14 days ( )

38. What causes honeycombing in concrete?

• A. Over-curing
• B. Improper compaction ( )
• C. Fast mixing
• D. Use of steel

39. What is segregation in concrete?

• A. Color change

ENG BATOOL NOFAL 0790538777


• B. Breaking of concrete
• C. Separation of materials ( )
• D. Bending of rods

40. What tool is used for concrete compaction?

• A. Plate compactor
• B. Poker vibrator ( )
• C. Trowel
• D. Hammer

Section 9: General Civil Works in Power Projects

41. What is the main civil task in substation construction?

• A. Generator testing
• B. Foundation & yard work ( )
• C. Transformer wiring
• D. Cable pulling

42. Tower foundation type depends on:

• A. Paint type
• B. Tower height
• C. Soil condition ( )
• D. Voltage only

43. What is an earth pit?

• A. Water storage
• B. Drain pit
• C. Electrical grounding point ( )
• D. Manhole

44. What is used to measure rebar spacing?

• A. Dial gauge
• B. Measuring tape ( )
• C. Vernier scale
• D. Screw gauge

45. Where are cable trenches located?

ENG BATOOL NOFAL 0790538777


• A. Above slab
• B. In foundations
• C. Below ground ( )
• D. On ceiling

Section 10: Codes & Tools

46. What code is commonly used for concrete works?

• A. IEEE
• B. ASTM
• C. ACI ( )
• D. ISO

47. Which software is used for quantity take-off?

• A. AutoCAD
• B. Primavera
• C. Excel
• D. PlanSwift ( )

48. What is the standard unit for steel bars in BOQ?

• A. Kg ( )
• B. Meter
• C. Ton
• D. Number

49. What is the importance of cover blocks?

• A. To decorate concrete
• B. Hold rebar in place ( )
• C. Increase load
• D. Reduce cost

50. What is the full form of PPE?

• A. Professional Project Engineer


• B. Personal Protection Equipment ( )
• C. Project Planning Equipment
• D. Power Project Estimate